3/4, Third Floor, Civil Secretariat, Jammu/ G-15, Civil Secretariat, Srinagar www.jkcmmonitoring.nic.in, email: [email protected]
Ph#0191-2520430 (Jmu)/ 0194-2485570 (Sgr)
1
GOVERNMENT OF JAMMU & KASHMIR
Chief Minister’s Monitoring Cell www.jkcmmonitoring.nic.in
Physical verification report of the project namely
“INDUSTRIAL ESTATE GHATTI”
District Kathua
By
Deputy Director,
CM’s Monitoring Cell.
3/4, Third Floor, Civil Secretariat, Jammu/ G-15, Civil Secretariat, Srinagar www.jkcmmonitoring.nic.in, email: [email protected]
Ph#0191-2520430 (Jmu)/ 0194-2485570 (Sgr)
2
Name of Project: Industrial Estate at Ghatti, Kathua
Implementing Deptt. : Industries & Commerce Department
Executing Agency: J&K SIDCO Ltd.
Funding Agency : GoI
Month of Start: September, 2009
Month of Completion: September, 2013 (targeted)
Financial Progress
The Project has been approved by the State Cabinet vide decision No.88/6/2009 dated: 13-06-2009 for an amount of Rs 81.15 crores
which includes Rs 22.925 crores for acquisition of land and Rs 58.23 crores as development cost.
Particulars Amount in Crores
Approved Development Cost 58.23
Funds Released 14.19 (24% of approved cost)
Expenditure Incurred 14.19
The funding/ expenditure details with regard to land acquisition, for which an amount of Rs 22.925 crores has been earmarked in the
project, were not available with the J&K SIDCO Ltd. The Manager of J&K SIDCO and the Engineers posted with the Corporation who accompanied
during the field visit informed that, as far as proceedings of land
acquisition is concerned, they were only aware of the physical status because the financial side is being dealt with directly by the Director,
Industries & Commerce, Jammu and the Deputy Commissioner, Kathua.
Physical Progress
S.No Items Physical Status
1 Land to be acquired= 3502 Kanals
82% land acquired (Land acquired = 2886 Kanals)
2 Environment Clearance
Granted by the Ministry of Environment & Forest in the meeting held in August, 2013
and by the National Wild Life Board in the meeting held in July, 2013.
3 Site Development-Survey investigation &
site development
Preliminary survey completed Soil & water investigation partly completed
Site development partly completed
4 Industrial
Infrastructure – Roads
Road measuring 3.30 kms completed
3/4, Third Floor, Civil Secretariat, Jammu/ G-15, Civil Secretariat, Srinagar www.jkcmmonitoring.nic.in, email: [email protected]
Ph#0191-2520430 (Jmu)/ 0194-2485570 (Sgr)
3
A Road network within
Industrial Complex
i 100 feet wide road with
divider & carriage way width of 15 m
33% upto premix status
(1.30 km out of 3.97 km)
ii 60 feet wide road with carriage width of 7.5 m
15% upto premix status (1.00 km out of 6.65 km)
iii 40 feet wide road with carriage way of 5.50 m
28% upto WBM status (0.90 km out of 3.19 km)
iv 25 feet wide road on both sides of divider under HT line and
carriage way of 3.65 m on either side
16% upto WBM status (0.30 km out of 1.85 km)
B Widening of road from NH to entry point with
carriage width of 7.50 m
100% upto premix status (Approved length = 3.30 km)
C Rotary 33% (1 out of 3 completed)
5 Drainage System
A Construction of drains
i Const. Of main drain 19% (2600 m out of 13860 m completed)
ii Const. Of surface drain (type-I)
35% (4400 m out of 12610 m completed)
iii Const. Of surface drain (type-II)
15% (1600 m out of 10780 m completed)
B Construction of culverts
i 2 m span RCC culverts 2 nos. completed
ii 1.40 m span RCC
culverts
26 nos. Completed
iii 0.90 m span RCC
culverts
18 nos. Completed
iv 0.60 m span RCC
culverts
12 nos. Completed
v Const. Of RCC Box
culvert
1 no. completed
vi Const. Of RCC bridge
over canal
1 no. Targeted, but work not taken up yet
6 Protection works
i Boundary fencing of Park, Housing Colony,
Pump House
700 m out of 2700 m completed
ii Retaining walls 2.50 m high
300 m targeted, but work not yet taken up yet
iii Flood Channel 10% (120 m out of 1210 m completed)
7 Water distribution system
i Drilling of Tube Wells 1 out of 5 completed
3/4, Third Floor, Civil Secretariat, Jammu/ G-15, Civil Secretariat, Srinagar www.jkcmmonitoring.nic.in, email: [email protected]
Ph#0191-2520430 (Jmu)/ 0194-2485570 (Sgr)
4
ii OHT of 1 lac gallons with
sump tank of 1 lac gallon
1 out of 6 completed
iii Providing and laying of
100 mm dia. G.I. Mains/ Distribution
3%
(440 m out of 15600 m completed)
iv Provision for submersible pump booster, chain
pulley, portable welding set. Etc.
Work not taken up yet
8 Landscaping
i Green Belt (target is 48.38 kanals) Work of developing Nursery for plants taken
up
ii Premises for Housing
Colony
(target is 75 kanals)
Work not taken up yet
9 Administrative
Buildings
i Administrative Block Completed
ii Guest House Work not yet taken up
iii Pump House Building 20% (1 out of 5 completed)
iv Storage Shed Building Completed
10 Housing Facility (Residential Flats)
i Const. Of Staff Qtrs (A-type) 2 bed room sets
(Target is 12 nos.) Work not taken up yet
ii Const. Of Staff Qtrs (B-type) 1 bed room sets
(Target is 12) Work not taken up yet
11 Commercial Building
i Shopping Complex including Tuck Shops
Work not taken up yet
ii Restaurants/ Dhabas Work not taken up yet
iii Hotel and Multiplex etc. Work not taken up yet
12 Mega Signboard Completed
13 Electrical Works
i Electrification of Buildings/ Sheds/ Pump
House
Admn. Block, Store Shed & one pump house completed
ii Road lighting 17%
(3.26 km out of 19.63 km completed)
iii Creation of 100 KVA sub-
station
28%
(4 nos. Out of 14 nos. Completed)
iv Shifting of 63 KVA sub-
station along with HT Line
100%
(Targeted 3.26 km completed)
v Extension of 11 KVA 7% (1.30 km out of 19.63 km completed)
vi Sub-station for Pump houses
20% (1 out of 5 completed)
3/4, Third Floor, Civil Secretariat, Jammu/ G-15, Civil Secretariat, Srinagar www.jkcmmonitoring.nic.in, email: [email protected]
Ph#0191-2520430 (Jmu)/ 0194-2485570 (Sgr)
5
Backdrop of Project
A number of initiatives are being taken by the government for
creating a favourable atmosphere for industrial investment in the state. Taking another step in this direction, the state cabinet had in June 2009
approved a project for development of an Industrial Estate at Ghatti in district Kathua.
An area of about 3500 kanals, at a distance of 3.30 kms from the
NH-1A at Ghatti, was identified for acquisition and its development as an Industrial Estate. Industries and Commerce Department entrusted the
task of developing the estate to the J&K SIDCO Ltd.
Some funds were provided during 2009-10, 2010-11 & 2011-12
under the project, but only 80% of land has been acquired and some of the essential works approved under the project taken up at site. The
pace of execution remained sluggish due to stoppage of funding in subsequent years and un-certainty of getting necessary clearances from
concerned quarters.
However, during the current year, i.e. 2013, in a meeting held in the month of July, the National Wild Life Board has granted its clearance
and in another meeting held in the month of August, the Project has also been cleared by the Ministry of Environment & Forest, GoI subject to the
fulfilment of certain conditions.
The official orders with regard to clearances granted are awaited,
but it was intimated by the Manager, J&K SIDCO that the conditions laid down by the Central authorities would escalate the project cost. The
Jasrota Fort cum Wildlife sanctuary lies adjacent to the industrial estate site across the local river and compensation running into crores is being
demanded by the Wildlife authorities. Besides, additional green patches have to be developed in the Estate. Moreover, in order to keep the
pollution levels in the vicinity of the area under control, clearance has been granted only for setting up of industries falling in the green and
orange categories and not to the industries of red category.
It is likely that the development works which have suffered during the last couple of years will pick up pace from now onwards provided
adequate funding is arranged.
Field Observations
During the field visit a sign board of the Industrial Estate Ghatti
was found erected at the entry of the approach road to the estate from NH-1A. The approach road was initially a single lane road providing
connectivity to a few villages situated ahead of the site of Industrial Estate Ghatti. Now this approach road has been widened with carriage
way of 7.50 meters for a length of 3.30 km up to pre-mix level but, the
3/4, Third Floor, Civil Secretariat, Jammu/ G-15, Civil Secretariat, Srinagar www.jkcmmonitoring.nic.in, email: [email protected]
Ph#0191-2520430 (Jmu)/ 0194-2485570 (Sgr)
6
road surface is not smooth. The Executive Engineer, SIDCO informed
that a final quote of macadam has yet to be laid and only after that the surface would become smooth. The 11 KVA electric lines were found
extended all along the length of the approach road and street lighting has also been provided at certain points.
After reaching the site of the Industrial Estate, some of the
buildings, roads, drains, electric system, water supply system that has been constructed/ developed by SIDCO was inspected. The buildings that
have been constructed include an administrative block, store shed cum office and a pump house. All the three buildings have been fenced.
Besides, the tube well installed in the Pump House, within its premises
an OHT of one lac gallons and a sump tank of one lac gallons have also been constructed.
The Administrative Block is a double storey structure comprising of
office rooms on the ground floor and a few rooms on the first floor, a couple of which are being used as guest rooms for the officials for their
night stay. Vitrified tiles have been laid on the floors in the administrative block and offices/ rooms have been well furnished and
properly maintained.
Between the fencing of the administrative block and the store shed cum office, a nursery is being developed for raising plantation within the
industrial estate. While inspecting the store shed, a few bags of cement were found stacked there.
A rotary has been constructed around the foundation of a HT electric tower in front of the fence of the administrative block. A stretch
of the 100 feet wide main road leading from the rotary has been constructed in such a manner that the HT wires align with the divider of
this main road and plants have been planted on the divider. The layout of roads has prevented carrying out the herculean task of shifting HT tower
or HT wires from the site and has helped in proper utilization of space.
Some of the main drains which have been constructed were in good condition but weeds had grown in a few smaller drains due to poor
maintenance. A couple of culverts and some portion of 60 feet wide and 40 feet wide roads were also inspected. Protection works were found
executed along a non-perennial storm drain flowing through the site. A bridge has been constructed over the drain adjacent to the old bridge to
make it double lane road.
Overall, the quality of works executed in the Industrial Estate is
satisfactory.
3/4, Third Floor, Civil Secretariat, Jammu/ G-15, Civil Secretariat, Srinagar www.jkcmmonitoring.nic.in, email: [email protected]
Ph#0191-2520430 (Jmu)/ 0194-2485570 (Sgr)
7
Problem Areas/ Suggestions
1) Delay in acquisition of land:
Land measuring 3502 kanals and 14 marlas has to be acquired in
four villages for development of the Industrial Estate. The village-wise
land acquisition status is given below:-
Village Land Acquired Not Acquired
Kalana 1457 k 100% acquired &
possession taken
over in Dec 2007
Nanan 853 k 19 M 716 K and 07 M
acquired &
possession taken
over by SIDCO in
July 2009
Fresh acquisition
proceedings for acquiring
remaining 137 k 12 M
initiated and matter is
pending with Revenue
authorities in DC’s Office
Kathua
Pandhrar 712 k 17 M 100% acquired &
possession taken
over in Oct 2009
Mearth 478 k 18 M Compensation is being
paid to land owners for the
last 4 years by DC’s Office,
Kathua & possession not
handed over to SIDCO yet
From the above table it is evident that the project has been
approved by the State Cabinet more than 4 years back and the land
acquisition proceedings have not been completed by the Revenue
authorities of district Kathua till date. The Deputy Commissioner, Kathua
needs to intervene in the matter and ensure that compensation is
disbursed to the land owners and land acquired and handed over to
SIDCO without further delay.
2) Slow Funding:
The detail of year-wise funding against development cost of Rs
5822.87 lacs and the expenditure incurred by SIDCO on the project is
given below:-
3/4, Third Floor, Civil Secretariat, Jammu/ G-15, Civil Secretariat, Srinagar www.jkcmmonitoring.nic.in, email: [email protected]
Ph#0191-2520430 (Jmu)/ 0194-2485570 (Sgr)
8
(Rs in Lacs)
Year Funds
released
Expenditure
incurred
Un-spent
balance
2009-10 600.00 236.70 363.30
2010-11 400.00 756.48 6.82
2011-12 418.67 425.38 0.11
2012-13 0.00 0.00 0.11
2013-14 0.00 0.00 0.11
Total 1418.67 1418.56 0.11
Only Rs 1418.67 lacs have been released against the development
cost of Rs 5822.87 lacs which works out to about 24%. The Government Order of administrative approval to the project inter alia envisages that
the expenditure on development of the Industrial Estate shall be incurred out of 40% of premium received by the Corporation on account of land
allotted to the prospective allottees/ Plan funds by debit to the appropriate head.
Unless the infrastructure, such as roads, lanes, drains, water
supply, electric supply, etc necessary in the industrial estate are developed to a certain level it is unlikely that any industrialist would be
willing to set up a unit at Ghatti. Therefore, sufficient Plan funds have to be provided by the Industries & Commerce Department so that J&K
SIDCO Ltd. can re-commence the halted works immediately and develop the minimum infrastructure necessary for allotment of land in the estate
and generation of income which could then be utilized for completion of
the left over works.
Physical Verification Conducted by :
Madan Gopal Sharma, Deputy Director Planning,
Monitoring Cell, Chief Minister’s Secretariat.
Officer of Executing
Agency who accompanied the
inspecting officer:
Sh. Vikram.K.Gupta, General Manager,
SIDCO Sh. Tara Chand Thakur, Executive Engineer
(Electrical) Sh. O.P.Sharma, Manager Estate
Sh. D.K.Khanna, Executive Engineer (Civil)
Date of conduct of
physical inspection: 22-10-2013
3/4, Third Floor, Civil Secretariat, Jammu/ G-15, Civil Secretariat, Srinagar www.jkcmmonitoring.nic.in, email: [email protected]
Ph#0191-2520430 (Jmu)/ 0194-2485570 (Sgr)
9
Administrative Block
Store Shed cum office
3/4, Third Floor, Civil Secretariat, Jammu/ G-15, Civil Secretariat, Srinagar www.jkcmmonitoring.nic.in, email: [email protected]
Ph#0191-2520430 (Jmu)/ 0194-2485570 (Sgr)
10
Road
Rotary
3/4, Third Floor, Civil Secretariat, Jammu/ G-15, Civil Secretariat, Srinagar www.jkcmmonitoring.nic.in, email: [email protected]
Ph#0191-2520430 (Jmu)/ 0194-2485570 (Sgr)
11
Cross Drain
Drain
3/4, Third Floor, Civil Secretariat, Jammu/ G-15, Civil Secretariat, Srinagar www.jkcmmonitoring.nic.in, email: [email protected]
Ph#0191-2520430 (Jmu)/ 0194-2485570 (Sgr)
12
Over Head Tank
Tube Well
3/4, Third Floor, Civil Secretariat, Jammu/ G-15, Civil Secretariat, Srinagar www.jkcmmonitoring.nic.in, email: [email protected]
Ph#0191-2520430 (Jmu)/ 0194-2485570 (Sgr)
13
Electric Generator
Electric Transformer
3/4, Third Floor, Civil Secretariat, Jammu/ G-15, Civil Secretariat, Srinagar www.jkcmmonitoring.nic.in, email: [email protected]
Ph#0191-2520430 (Jmu)/ 0194-2485570 (Sgr)
14
Nursery
Plantation