Upload
others
View
5
Download
0
Embed Size (px)
Citation preview
This document contains information that is proprietary to Gopalpur Ports Ltd. and BMT, which is to be held in
confidence. No disclosure or other use of this information is permitted without the express authorization of
Gopalpur Ports Ltd. or BMT.
Gopalpur Ports Limited
Pre- feasibility Study for
development of liquid jetties
at Gopalpur Port
Final Report
October 2018
BMT Consultants (India) Private Limited
310 Sarthik Square, S.G. Highway, Ahmedabad – 380 054
Tel: +91 (79) 40028708 Fax: +91 (79) 40028710
Pre- feasibility Study
Final Report
prepared for
Gopalpur Ports Ltd.
Prepared under the management of:
Name: Anvi Maniar
Position: Senior Manager
Reviewed and approved by:
Name: Tarun Kaw
Position: Director
Reference: BMT/1395/PFR/Final Report/Issue 1
Date: 26.10.2018
Gopalpur Ports Ltd. Development of Liquid Jetties at Gopalpur Port Pre- feasibility Study
Final Report
BMT Consultants India Page i
Executive Summary
Introduction
Gopalpur Port is located in Ganjam district of Odisha and is being developed by Gopalpur
Ports Limited (GPL) under Build Own Operate Transfer (BOOT) model. The phase- wise
development plan of the port includes setting up the infrastructure for imports of LNG and
LPG, alongwith a no. of other liquids. The liquid cargo mix includes Liquified Natural Gas
(LNG), Liquified Petroleum Gas (LPG), Petroleum and other liquids (POL), edible/vegetable
oil and chemicals including ammonia.
GPL intends to establish the feasibility of setting up the required facilities for handling liquids
at Gopalpur Port. In this context, GPL have appointed BMT Consultants (India) Pvt. Ltd.
(BMT) to prepare a Pre- feasibility Report (PFR) for the development of liquid jetties at
Gopalpur Port. The assignment aims to undertake assessment of the feasibility of
developing and operating liquid terminal, which includes handling of LNG, LPG, POL,
edible oil, chemicals etc. along with identification of locations for developing the
infrastructure and preliminary level terminal configuration.
Existing infrastructure
At present, the port has an existing berth and two breakwaters. Construction of two
additional berths is ongoing at the port adjacent to the existing berth. These berths will be
used to handle dry bulk and general cargo. Currently partial operations are ongoing and
the area behind the existing berth is used as the back-up yard. Development of the back-
up yard, railway sidings, yard and road network are proposed on the landside area behind
the berths under the current phase of development. Generally, the land side area at
Gopalpur Port, is uneven and undulating with sparse vegetation. There is no other
habitation at site.
Traffic and terminal configuration
The liquid cargo mix to be handled at Gopalpur includes LNG, LPG, POL, edible/vegetable
oil and chemicals including ammonia are envisaged to be imported. The forecasted
throughput ranges from 0.1 Mtpa of other liquids in the first two years and reaching upto a
total volume of 13 Mtpa (10 Mtpa LNG and 3 Mtpa LPG, other liquids) in 2028.
For the development of the liquid terminals at Gopalpur Port, the terminal processes for (i)
LNG and (ii) LPG and other liquids were studied. Based on the analysis of the various LNG
terminal concepts and taking into cognizance the advantages offered by the Floating
Storage Regasification Unit (FSRU) as compared to the other options, it has been selected
as the preferred alternative for the current stage of the project. This option has relatively
low capital cost and provides significant commercial flexibility compared to the other
configurations described. As per the operational considerations, upto 3.5 Mtpa can be
handled using a single FSRU. Accordingly, it is proposed that the FSRU based facility will
be developed for the current phase and subsequently the terminal will be converted to a
conventional LNG terminal to handle higher volumes.
Gopalpur Ports Ltd. Development of Liquid Jetties at Gopalpur Port Pre- feasibility Study
Final Report
BMT Consultants India Page ii
Functional requirements
The vessel size analysis for LPG and other liquids suggests that the ships calling at
Goplapur Port will be relatively smaller tankers in the range of 30,000 DWT. For LNG
carriers, considering the global trends and current industry standards, in the initial phase,
design LNGC size is considered as 138,000 m3, with the maximum vessel size being
considered as 173,000 m3. In the future, the terminal can be planned to handle upto Q-Max
size vessels i.e. 267,000 m3. Based on the assessment of functional requirements, the
principal harbour dimensions are fixed as per the table below. These parameters will govern
the jetty design, storage capacity and harbour design.
Table 1: Functional requirements
Current phase (facility with FSRU) Future phase (conventional LNG facility)
Inner channel depth (m wrt CD) 13.0 13.2
Outer channel depth (m wrt CD) 15.3 15.6
Channel width (m) 230 270
Turning circle dia. (m) 560 610
Depth in harbour (m wrt CD) 13.0 13.2
The berth requirement is determined based on the number and size of vessels as well as
the type of cargo to be handled. Considering the safety aspects and need for cargo
segregation, it is proposed that separate jetties will be provided for (i) LNG (ii) LPG and
other liquids. Based on the jetty occupancy assessment, it is proposed that two liquid jetties
be developed; one dedicated jetty for LNG operations and the other liquid jetty for LPG and
the other liquids.
The land side requirements for the cargoes is assessed basis the land required for storage
at the port as well as associated evacuation facilities. The area requirement of LNG terminal
with FSRU is 5-10 ha, and upon developing the conventional onshore LNG facility, with
storage, process side facilities and other ancillary infrastructure alongwith evacuation
related facilities, around 40 ha area will be required. Given the total area requirement for
LPG and liquids, the land area needed for developing the liquid terminal is in a range of 15-
20 ha.
The NG will be evacuated primarily by means of pipeline. To make LNG available to
customers not linked to the gas pipeline network, it will be supplied by cryogenic trucks.
The other liquids like POL, edible oil, chemicals etc. will be evacuated mainly by means of
pipeline. The liquid cargo will be evacuated from the port and delivered to the destination
via road and railway modes as well.
Site selection
For selection of the most suitable locations for developing marine and landside facilities,
the key aspects under consideration are feasibility of developing multiple jetties in the
harbour, safety considerations, segregation requirements, cost economics and operational
requirements as well as constraints alongwith environmental considerations.
Gopalpur Ports Ltd. Development of Liquid Jetties at Gopalpur Port Pre- feasibility Study
Final Report
BMT Consultants India Page iii
The available waterfront for development of additional jetties includes the following:
(i) Stretch in continuation with dry/ general cargo berths already developed
(ii) Along the south breakwater
(iii) Along the intermediate breakwater
Since the site selection for LNG facility necessitates taking into cognizance the safety
aspects, the identification of location for LNG jetty is carried out first, followed by selection
of location for the other liquids jetty. Having studied each of the three alternative options
with regards to understanding their salient features towards assessing their suitability as
the preferred location for developing the LNG facility and also keeping in view the port
expansion plans, the location along the outer arm of the south breakwater emerges as the
most suitable alternative. It is also considered that the dry bulk berths will be developed as
planned by GPL, along the inner arm of south breakwater. Accordingly, as per the analysis
of the available sites, the location along the intermediate breakwater is found to be
favourable for developing the jetty for LPG and other liquids. The locations for the jetties
will require to be finalised following a Quantitative Risk Assessment (QRA) study.
Figure 1: Locations of liquid terminals (marine and landside facilities)
The portion of the landside area behind the bulk and general cargo berths is earmarked as
the back up area for the current dry bulk terminal development. Hence, the land parcels
available for liquid terminal back up area development are those located to the east and
west of the dry bulk back up yard. Based on area availability, pipeline connectivity,
operational convenience and safety as well as expandability, the location, size and
arrangement of the back up yard for both the liquid jetties, based on the phase wise
Gopalpur Ports Ltd. Development of Liquid Jetties at Gopalpur Port Pre- feasibility Study
Final Report
BMT Consultants India Page iv
requirements are assessed. Considering the location of the LNG jetty, the most suitable
location for developing the back up area taking into account the area availability and
pipeline routing is the location to the west of the coal stockyards. Taking into cognizance
the location of the liquid handling jetty areas at two locations (i) area to the north of the
railway corridor (ii) area between the railway corridor and the warehouse will be utilised for
developing the landside facilities for liquids are proposed to be developed as the terminals
for liquids. The suitability of these locations will be reviewed and finalised following further
studies at a later stage.
Major utilities include power, water (potable water, service water, firewater) and diesel oil
for the proposed port expansion. The requirements are assessed, and the sources of
supply are also identified. To improve the overall environmental sustainability of the port by
means of resource optimization and recycling, it is proposed that the waste water will be
adequately treated for reuse for alternative purposes.
For the proposed expansion bulk raw materials will be required for the construction phase
but will not be needed during the operational phase. It is proposed to commence the
construction within 6-8 months after obtaining all approvals. The expansion project is
estimated to cost approx. INR 1,300 Crore. The expansion project will be financially and
economically beneficial since it is expected to promote employment opportunities during
the construction and operational phases of the expansion alongwith additional indirect
employment and improvement in infrastructure in the vicinity. There are no resettlement
issues envisaged resulting from this expansion project.
Gopalpur Ports Ltd. Development of Liquid Jetties at Gopalpur Port Pre- feasibility Study
Final Report
BMT Consultants India Page v
Contents
1 Introduction ....................................................................................... 16
1.1 Background .................................................................................................... 16
1.2 Project proponents ......................................................................................... 16
1.2.1 Shapoorji Pallonji Group ................................................................... 16
1.2.2 Orissa Stevedores Ltd. ..................................................................... 16
1.3 Scope of work ................................................................................................ 17
1.3.1 Exclusion ........................................................................................... 17
1.4 Purpose of report ........................................................................................... 17
1.5 Data consulted ............................................................................................... 18
1.6 Meetings and site visits .................................................................................. 18
1.7 Format of report ............................................................................................. 18
2 Project Description and Site Analysis ............................................ 20
2.1 Site location .................................................................................................... 20
2.2 Port boundary................................................................................................. 20
2.3 Port development and phasing ...................................................................... 21
2.4 Existing infrastructure .................................................................................... 22
2.4.1 Marine side........................................................................................ 22
2.4.2 Landside ............................................................................................ 23
2.5 Connectivity .................................................................................................... 23
2.5.1 Road .................................................................................................. 23
2.5.2 Rail .................................................................................................... 23
2.6 Landside characteristics ................................................................................ 23
2.6.1 Topography ....................................................................................... 23
2.6.2 Existing land use and ownership ...................................................... 23
2.7 Soil conditions ................................................................................................ 24
2.7.1 Land side ........................................................................................... 24
2.7.2 Marine side........................................................................................ 24
2.8 Climate ........................................................................................................... 24
2.9 Meteorological and oceanographic conditions ............................................... 25
2.9.1 Temperature...................................................................................... 25
2.9.2 Rainfall .............................................................................................. 25
2.9.3 Relative humidity ............................................................................... 25
2.9.4 Wind .................................................................................................. 25
2.9.5 Cyclones ........................................................................................... 26
2.9.6 Tides ................................................................................................. 26
2.9.7 Currents ............................................................................................ 27
2.9.8 Waves ............................................................................................... 27
2.10 Seismic conditions ......................................................................................... 28
2.11 Raw material requirements ............................................................................ 28
2.12 Resource optimization and recycling ............................................................. 28
2.13 Employment generation ................................................................................. 28
3 Traffic Forecast ................................................................................. 29
Gopalpur Ports Ltd. Development of Liquid Jetties at Gopalpur Port Pre- feasibility Study
Final Report
BMT Consultants India Page vi
4 Terminal Concepts ............................................................................ 30
4.1 LNG ................................................................................................................ 30
4.1.1 LNG process overview ...................................................................... 30
4.1.2 Regasification- terminal concepts ..................................................... 33
4.1.3 Terminal with Floating Storage and Regasification Unit
(FSRU)/Floating Storage Unit (FSU) ................................................ 34
4.1.4 Recommendation .............................................................................. 41
4.2 Other liquids ................................................................................................... 42
5 Operating Considerations and Functional requirements .............. 43
5.1 Traffic forecast summary ............................................................................... 43
5.2 Ship size analysis........................................................................................... 43
5.2.1 LNG ................................................................................................... 43
5.2.2 Other liquids ...................................................................................... 45
5.3 Principal harbour dimensions ......................................................................... 47
5.3.1 Approach channel ............................................................................. 47
5.3.2 Harbour and turning circle ................................................................. 47
5.3.3 Minimum stopping distance .............................................................. 48
5.4 Jetty requirements ......................................................................................... 48
5.4.1 LNG ................................................................................................... 49
5.4.2 Other liquids ...................................................................................... 52
5.5 Approach trestle ............................................................................................. 53
5.6 Land side requirements ................................................................................. 54
5.6.1 Storage .............................................................................................. 54
5.7 Evacuation ..................................................................................................... 55
6 Alternative Locations ....................................................................... 56
6.1 Feasibility of multiple jetties in the harbour .................................................... 56
6.1.1 Existing harbour layout and conditions ............................................. 56
6.1.2 Key planninng parameters ................................................................ 58
6.1.3 Principal guiding considerations for site selection ............................ 58
6.1.4 Assessment of potential jetty locations ............................................. 61
6.2 Landside development ................................................................................... 67
6.2.1 Key considerations for back up area selection ................................. 67
6.2.2 Assessment of back up area locations ............................................. 68
7 Proposed Infrastructure ................................................................... 74
7.1 Project site and surroundings ........................................................................ 74
7.2 Utilities ............................................................................................................ 75
7.2.1 Power requirement ............................................................................ 75
7.2.2 Water requirement ............................................................................ 75
7.3 Wastes and management .............................................................................. 75
7.3.1 Liquid wastes .................................................................................... 75
7.3.2 Solid wastes ...................................................................................... 76
7.3.3 Oily wastes ........................................................................................ 76
7.3.4 Wastes generated at FSRU .............................................................. 77
Gopalpur Ports Ltd. Development of Liquid Jetties at Gopalpur Port Pre- feasibility Study
Final Report
BMT Consultants India Page vii
7.4 Storm water drainage ..................................................................................... 77
7.5 Oil Spill Contingency Plan .............................................................................. 77
7.6 Disaster Management Plan ............................................................................ 78
7.6.1 Green belt ......................................................................................... 79
8 Rehabilitation and Resettlement ..................................................... 81
9 Project Schedule and Cost Estimates ............................................. 82
10 Financial and Social Benefits .......................................................... 83
Gopalpur Ports Ltd. Development of Liquid Jetties at Gopalpur Port Pre- feasibility Study
Final Report
BMT Consultants India Page viii
Tables
Table 3-1: Traffic forecast for Gopalpur Port (Mtpa) ................................................. 29
Table 4-1: Comparison of LNG terminal concepts ................................................... 39
Table 5-1: Design vessel size- FSRU ....................................................................... 45
Table 5-2: Design vessel size - LNGC...................................................................... 45
Table 5-3: Typical bulk liquid ship sizes ................................................................... 46
Table 5-4: Design vessel size for LPG and other liquids .......................................... 46
Table 5-5: Approach channel dimensions ................................................................ 47
Table 5-6: Turning circle dimensions ........................................................................ 48
Table 5-7: Jetty occupancy for FSRU based LNG facility ........................................ 51
Table 5-8: Jetty occupancy for conventional LNG facility (future) ............................ 52
Table 5-9: Jetty occupancy for LPG and other liquids .............................................. 53
Table 6-1: Downtime at locations within Gopalpur harbour ...................................... 59
Table 6-2: Land use area break up for LNG terminal ............................................... 69
Table 6-3: Land use area break up for LPG and other liquids’ terminal ................... 72
Figures
Figure 2-1: Location of Gopalpur Port........................................................................ 20
Figure 2-2: Project site layout .................................................................................... 21
Figure 2-3: Wind climate rose diargram ..................................................................... 26
Figure 2-4: Wave climate rose diagram ..................................................................... 27
Figure 4-1: LNG value chain ...................................................................................... 30
Figure 4-2: Typical LNG regasification process flow diagram ................................... 32
Figure 4-3: Conventional LNG terminal ..................................................................... 33
Figure 4-4: Typical LNG regasification process flow diagram on an FSRU .............. 35
Figure 4-5: Stand alone jetty ...................................................................................... 36
Gopalpur Ports Ltd. Development of Liquid Jetties at Gopalpur Port Pre- feasibility Study
Final Report
BMT Consultants India Page ix
Figure 4-6: Conventional jetty for side-by-side mooring ............................................ 37
Figure 4-7: Liquid cargo operations ........................................................................... 42
Figure 5-1: Liquid jetty- general arrangement (typ.) .................................................. 49
Figure 6-1: Existing harbour of Gopalpur Port ........................................................... 56
Figure 6-2: Proposed layout of ongoing development at Gopalpur Port ................... 57
Figure 6-3: Wave extraction points ............................................................................ 59
Figure 6-4: Alternative locations for LNG jetty ........................................................... 62
Figure 6-5: Jetty location for LPG and other liquids ................................................... 65
Figure 6-6: Proposed liquid jetty locations at Gopalpur Port ..................................... 66
Figure 6-7: LNG back up yard facility ......................................................................... 70
Figure 6-8: Area availability for development of LPG/other liquid terminal ................ 71
Figure 6-9: LPG and other liquids back up yard facility ............................................. 73
Figure 7-1: Seismic map of India ............................................................................... 78
Figure 7-2: Cyclone and wind zones in India ............................................................ 79
Annexure
Annexure A: Drawings .................................................................................................. 84
Gopalpur Ports Ltd. Development of Liquid Jetties at Gopalpur Port Pre- feasibility Study
Final Report
BMT Consultants India Page x
List of Drawings
Drawing no. Drawing title
BMT-1395-GPL-PFR-DWG-001 EXISTING LAYOUT- GOPALPUR PORT
BMT-1395-GPL-PFR-DWG-002 ALTERNATIVE LOCATIONS FOR LNG JETTY IN GOPALPUR PORT HARBOUR
BMT-1395-GPL-PFR-DWG-003 JETTY LOCATIONS FOR LNG AND OTHER LIQUIDS AT GOPALPUR PORT
BMT-1395-GPL-PFR-DWG-004 LNG TERMINAL (JETTY AND BACK UP YARD) LOCATION AT GOPALPUR PORT
BMT-1395-GPL-PFR-DWG-005 LNG AND LPG/ OTHER LIQUIDS TERMINALS LOCATIONS AT GOPALPUR PORT
Gopalpur Ports Ltd. Development of Liquid Jetties at Gopalpur Port Pre- feasibility Study
Final Report
BMT Consultants India Page xi
SYMBOLS AND ABBREVIATIONS
Symbols and abbreviations used are generally in accordance with the following list.
1 Proper names and organisations – India
BMT CI ............. BMT Consultants India
DAE ................. Department of Atomic Energy
GoI ................... Government of India
GoO ................. Government of Odisha
GPL .................. Gopalpur Ports Limited
IMD .................. Indian Meteorological Department
IREL ................. Indian Rare Earths Limited
MoEFCC .......... Ministry of Environment, Forest and Climate Change
OSCOM ........... Orissa Sands Complex
OSPCB ............ Odisha State Pollution control Board
SOUTHCO ....... Southern Electricity Supply Company of Odisha Ltd.
TSSEZ ............. Tata Steel Special Economic Zone Limited
2 Proper names and organisations – Other
BA .................... British Admiralty
ECMWF ........... European Centre for Medium- Range Weather Forecasts
NCEP ............... National Centres for Environmental Prediction
NIO .................. National Institute of Oceanogaphy
PIANC .............. Permanent International Association of Navigation Congresses
UKMO .............. United Kingdom Meteorological Office
3 Other abbreviations
approx .............. approximately
BOOT ............... Build Own Operate Transfer
Gopalpur Ports Ltd. Development of Liquid Jetties at Gopalpur Port Pre- feasibility Study
Final Report
BMT Consultants India Page xii
dia .................... diameter
max .................. maximum
min ................... minimum
No .................... number
avg ................... average
BOG ................. Boil-off Gas
CA .................... Concession Agreement
CD .................... Chart Datum
CNG ................. compressed natural gas
DPR ................. Detailed Project Report
ENE ................. east northeast
ESE .................. east southeast
FEED ............... Front- End Engineering Design
FSRU ............... Floating Storage and Regasification Unit
FSU .................. Floating Storage Unit
HAT ..................Highest Astronomical Tide
HAZID .............. Hazard Identification study
HAZOP ............ Hazard and Operability study
Hs .................... Significant Wave Height
HP .................... High Pressure
LoA .................. Length overall (of a ship)
LAT .................. Lowest Astronomical Tide
LNG ................. Liquefied Natural Gas
LNGC ............... Liquefied Natural Gas Carrier
LPG .................. Liquefied Petroleum Gas
M ...................... “mega” or one million (106)
MHWS ............. Mean High Water Spring tides
MSL ................. Mean Sea Level
Gopalpur Ports Ltd. Development of Liquid Jetties at Gopalpur Port Pre- feasibility Study
Final Report
BMT Consultants India Page xiii
MLWS .............. Mean Low Water Spring tides
NE .................... northeast
NG ................... Natural Gas
NNE ................. north northeast
NNW ................ north northwest
NW ................... northwest
OSD ................. oil spill dispersants
PFR .................. Pre- feasibility Report
PNG ................. Piped Natural Gas
POL .................. Petroleum and other liquids
PRF .................. port reception facility
QRA ................. Quantitative Risk Assessment
SSE .................. south southeast
SSW ................. south southwest
STP .................. Sewage Treatment Plant
ToR .................. Terms of Reference
UKC ................. Under Keel Clearance
wrt .................... with respect to
WE ................... wave extraction
WNW ............... west northwest
WSW ................ west southwest
4 Units of measurement
Length, area and volume
ha ..................... hectare(s)
kL ..................... kilo litre
km.................... kilometre(s)
km2 ................... square kilometre(s)
Gopalpur Ports Ltd. Development of Liquid Jetties at Gopalpur Port Pre- feasibility Study
Final Report
BMT Consultants India Page xiv
m...................... metre(s)
mm................... millimetre(s)
mm2 .................. square millimetre(s)
m2 ..................... square metre(s)
m3 ..................... cubic metre(s)
n. mile.............. nautical mile(s)
Time and time derived units
hr ...................... hour(s)
min ................... minute(s)
sec ................... second(s)
knot .................. nautical mile per hour
m/s ................... metre per second
tpd .................... tonnes per day
tph .................... tonnes per hour
yr ...................... year
Mass, force and derived units
displacement .... the total mass of the vessel and its contents. (This is equal to the volume
of water displaced by the vessel multiplied by the density of the water.)
DWT ................. dead weight tonne, the total mass of cargo, stores, fuels, crew and
reserves with which a vessel is laden when submerged to the summer
loading line. (Although this represents the load carrying capacity of the
vessel it is not an exact measure of the cargo load).
g ....................... gram = kg x 10-3
kg ..................... kilogram(s)
kPa ................... kilo pascal
Mt ..................... million tonnes = t x 106
t ........................ tonne = kg x 103
Other units
°C ..................... degrees Celsius (temperature)
Gopalpur Ports Ltd. Development of Liquid Jetties at Gopalpur Port Pre- feasibility Study
Final Report
BMT Consultants India Page xv
MLD ................. Millions Litres per day
MMSCFD ......... Million Metric Standard Cubic Feet per Day
MMSCMD ........ Million Metric Standard Cubic Meters per Day
Mtpa ................. million tonnes per annum
Gopalpur Ports Ltd. Development of Liquid Jetties at Gopalpur Port Pre- feasibility Study
Final Report
BMT Consultants India Page 16
1 Introduction
1.1 Background
Gopalpur Port is located at latitude 19°18’8” N, longitude 84°5’56” E in the Bay of Bengal,
approx. 15 km South of the Rushikulya River estuary in Ganjam district of Odisha. Gopalpur
Port is being developed by Gopalpur Ports Limited (GPL). Gopalpur Ports Ltd. (GPL) is a
consortium between Shapoorji Pallonji Group (SP Group) and Orissa Stevedores Ltd
(OSL). The project is being executed under Build Own Operate Transfer (BOOT) model.
The phase- wise development plan of the port includes handling of containers and also
setting up the infrastructure for imports of LNG and LPG, alongwith a no. of other liquids,
since ports on the eastern coast have a very good potential to handle liquid cargo, including
LNG. The liquid cargo mix includes Liquified Natural Gas (LNG), Liquified Petroleum Gas
(LPG), Petroleum and other liquids (POL), edible/vegetable oil and chemicals including
ammonia.
GPL intends to establish the feasibility of setting up the required facilities for handling liquids
at Gopalpur Port. In this context, GPL have appointed BMT Consultants (India) Pvt. Ltd.
(BMT) to prepare a Pre- feasibility Report (PFR) for the development of liquid jetties at
Gopalpur Port.
1.2 Project proponents
1.2.1 Shapoorji Pallonji Group
Shapoorji Pallonji Group (SP Group) has a majority stake in the GPL consortium. SP Group,
from a general contracting company is now a diversified business conglomerate. SP Group
offers complete solutions in various businesses i.e., Engineering and Construction,
Infrastructure, Real Estate, Energy, Water & Financial Services. With a turnover of more
than ~USD 4 billion, SP Group serves clients in more than 50 countries. The Group has a
60,000 strong workforce, comprising of about 40 nationalities.
1.2.2 Orissa Stevedores Ltd.
Orissa Stevedores Ltd. (OSL) has been offering services in stevedoring and cargo handling
over the last 35 years and handles more than 35 Mtpa of cargo with a workforce of 7000
employees. Its core competencies include project cargo handling, custom house agency,
steamer agency, mining, exports, ship owning & management. OSL has prominent
presence at almost all the major ports on the east coast of India. They offer services like
stevedoring, project cargo handling, C & F activities, container handling and freight
forwarding etc. The group is also involved in various other businesses like aviation,
automobile dealerships, education, hospitality, real estate, and healthcare.
(Source: Gopalpur port website)
Gopalpur Ports Ltd. Development of Liquid Jetties at Gopalpur Port Pre- feasibility Study
Final Report
BMT Consultants India Page 17
1.3 Scope of work
The assignment aims to undertake assessment of the feasibility of developing and
operating liquid terminal, which includes handling of LNG, LPG, POL, edible oil, chemicals
etc. along with identification of locations for developing the infrastructure and preliminary
level terminal configuration.
The scope of services for this assignment include the following:
• Assessment of marine requirements for the given cargoes and traffic; which includes:
- Assessment of number of jetties required
- Establishing the location of the jetties within the existing harbour
- Assessment of feasibility of having multiple jetties inside the harbour
- Establishing the design vessel size
- Establishing dredging requirements, if any
• Assessment of the terminal configuration
• Assessment of landside requirements; covering broad assessment of area required for
storage/regasification/handling of liquid cargoes and its location
• Broad assessment of the pipeline route from jetty to the storage area/boundary of the
port for transfer to third-party agencies having their tankage outside the port limits
• Broad-based cost estimation for development of the facility
1.3.1 Exclusion
The following is excluded from BMT’s scope:
• Traffic study
• Any risk assessment such as Quantitative Risk Assessment (QRA)
• Numerical model studies
• Specifications of Floating Storage and Regasification Unit (FSRU)/ Floating Storage
Unit (FSU)/on-land terminal equipment
• Layout for landside facilities/tankages
• Any other studies
1.4 Purpose of report
This document constitutes the Final Report for establishing the feasibility of setting up
infrastructure for handling liquids at Goplapur Port. It includes the study and evaluation of
possible suitable locations for developing the liquid jetty/ies and the supporting back up
infrastructure, and on its basis, proposing a feasible development scheme.
Gopalpur Ports Ltd. Development of Liquid Jetties at Gopalpur Port Pre- feasibility Study
Final Report
BMT Consultants India Page 18
The developer of the port wishes to avail the statutory clearance for handling of liquid
cargoes at Gopalpur Port. The purpose of this report is to support this process. The report
once approved by GPL, will be submitted for approval from statutory authorities.
As stipulated in the ToR, the Final Report is the second deliverable.
1.5 Data consulted
The data reviewed and consulted for preparation of this report includes the data made
available to us by GPL and other studies carried out previously by BMT.
1.6 Meetings and site visits
A telephonic call was held between BMT personnel Mr. Darpan Jethi and Mr. Selvaraj
Narayanan and Mr. Kartik Deuskar from GPL on June 11, 2018 to kickstart the project. The
discussion mainly included scope of work, exclusions alongwith definition of the way
forward to get an overall clarity on the requirements of the project.
An interim presentation was made by the BMT team at the client office in Mumbai on August
2, 2018 to discuss the progress on the project and avail necessary clarifications from GPL
required for preparation for the Draft report.
A meeting was held between the teams of BMT and GPL at the client office in Mumbai to
discuss the findings of the Draft Report and to resolve queries towards finalisation of the
report.
BMT personnel met Mr. Selvaraj Narayanan from GPL on August 28, 2018 to discuss the
Final Report and for necessary clarifications towards conclusion of the assignment.
1.7 Format of report
The format of report is arranged as follows:
Chapter 1: Introduction
The introduction chapter sets the background for the project and the current report.
Chapter 2: Project Description and Site Analysis
This chapter discusses about the location and other general physical and meteorological
characteristics of the port site. It also includes the existing and proposed development at
the port.
Chapter 3: Traffic Forecast
The type and volume of cargoes expected at the terminal is summarized in this chapter,
including the forecasted volumes for a horizon period of 10 years.
Chapter 4: Terminal Concepts
This chapter discusses the components and processes of an LNG terminal and explores
the various available alternatives for the regasification process. It also compares the
Gopalpur Ports Ltd. Development of Liquid Jetties at Gopalpur Port Pre- feasibility Study
Final Report
BMT Consultants India Page 19
alternatives, followed by selection of the most suitable scheme for Gopalpur LNG terminal.
The chapter also describes the terminal processes for the other liquids.
Chapter 5: Operating Considerations and Functional Requirements
Operational and functional requirements of the proposed terminal are assessed in this
chapter. It includes the derivation of key dimensions and requirements of various
components such as the jetty, storage and other marine and landside infrastructure.
Chapter 6: Alternative Locations
Different alternatives locations are identified, examined and compared in terms of their
characteristics to arrive at the most suitable location for the liquid jetty/ies.
Recommendation on preferred location/s for the marine and landside components is given
basis the comparative analysis.
Chapter 7: Proposed Infrastructure
This chapter discusses the requirement and sources of utilities and waste management
pertaining to development of the liquid handling infrastructure as well as a brief overview
of the disaster management plan for the port.
Chapter 8: Rehabilitation and Resettlement
This chapter addresses the aspect of rehabilitation and resettlement considering the
proposed development.
Chapter 9: Project Schedule and Cost Estimates
The timeline for commencement of construction and project costing are included in this
chapter.
Chapter 10: Financial and Social Benefits
This chapter discusses the potential financial and social benefits envisaged as a result of
the development of this liquid handling facility at Gopalpur.
Gopalpur Ports Ltd. Development of Liquid Jetties at Gopalpur Port Pre- feasibility Study
Final Report
BMT Consultants India Page 20
2 Project Description and Site Analysis
2.1 Site location
Gopalpur Port is located on the East coast of India, at latitude 19°18’8” N, longitude
84°57’56” E in the Bay of Bengal, approx. 15 km South of the Rushikulya River estuary in
Ganjam district of Odisha.
Figure 2-1: Location of Gopalpur Port
2.2 Port boundary
The port boundary stretches along 4 km stretch along the coastline. The area within the
port boundary and around the port are devoid of any heritage site, vegetation and natural
habitation like forests, mangrove and/or any endangered plant/animal species. A portion of
the project land is situated on demined land which was mined by Indian Rare Earths Ltd.
(IREL) previously and handed back to the Government of Odisha (GoO). GoO then leased
the demined land to GPL. Figure 2-2 indicates the project boundary layout. It is further
discussed in detail in Chapter 6.
Gopalpur Ports Ltd. Development of Liquid Jetties at Gopalpur Port Pre- feasibility Study
Final Report
BMT Consultants India Page 21
Figure 2-2: Project site layout
The port is located in a non-urbanized area adjoining villages, agricultural tracks, grazing
sites and non-productive lands. Hence, the economy of the region is mainly agro-based
with majority of people engaged in agriculture which is supported by irrigation canals, with
fishing being the other important occupation in the region.
2.3 Port development and phasing
According to the Detailed Project Report (DPR) by RITES, the project has been divided
into 4 phases; based on the projected traffic. Phase 1 and Phase 2 are maintained as
stipulated in the Concession Agreement (CA) signed in 2003; which are as follows:
Phase 1: development of the port to such an extent that the port is able to operate as a fair
weather lighterage port. Phase 1 (fair weather lighterage port) commenced operations in
January 2007.
Phase 2: expansion and development of the port to such an extent that the port is able to
operate as an all-weather deep-water direct berthing port. Phase 2 included the following
facilities:
• 1,730 m long south breakwater
• 360 m long intermediate breakwater
• 11 nos. of groynes
• 1,900 m long channel, dredged to -11 m CD to -12.5 m CD
Gopalpur Ports Ltd. Development of Liquid Jetties at Gopalpur Port Pre- feasibility Study
Final Report
BMT Consultants India Page 22
• 150 m long multipurpose berth with berth pockets dredged to -10 m CD
• Motorable road along the berth, south breakwater and stockyards
• 1,200 m railway siding renovated
• Development of 10 acres of stockyard behind the berth, including site grading
• Construction of buildings
These facilities were damaged in the Phailin cyclone in October 2013; while the DPR was
being prepared by RITES. RITES then defined Phase 3 and Phase 4 as follows:
Phase 3 includes construction of:
• 2,070 m of south breakwater
• 380 m of intermediate breakwater
• 11 nos. of groynes
• 1,900 m x 200 m approach channel dredged to -13.50 m CD
• 550 m dia turning circle dredged to a depth of -13.50 m CD
• 2 nos. of dry bulk berths and 1 no. of multipurpose berth having a total quay length of
535 m; with berth pockets dredged to -13.50 m CD
• Development of stockyard
• Development of roads, railways and utilities
Phase 4 includes:
• Total 2,170 m south breakwater
• Total 380 m of intermediate breakwater
• Total 300 m of multipurpose berth and 500 m of bulk cargo berth; with berth pockets
dredged upto -15 m CD
• Development of stockyard
• Development of roads, railways, buildings and other utilities
2.4 Existing infrastructure
2.4.1 Marine side
The marine facilities at the port include an existing berth and two breakwaters. The berth is
aligned to the shoreline; and it is a 300 m long and 30 m wide berth, which is currently
undergoing refurbishment. Partial operations are ongoing on the available portion of the
berth. Construction of two additional berths of lengths 300 m and 200 m and of width 28 m
each, is ongoing at the port adjacent to the existing berth. These three berths will be used
to handle dry bulk and general cargo.
Gopalpur Ports Ltd. Development of Liquid Jetties at Gopalpur Port Pre- feasibility Study
Final Report
BMT Consultants India Page 23
The existing south breakwater starts from a little south of the existing berth. An intermediate
breakwater is constructed perpendicular to the shoreline at about 850 m NE from the
existing berth. Works for extension of breakwaters is currently ongoing.
2.4.2 Landside
Currently partial operations are ongoing and the area behind the existing berth is used as
the back-up yard. A road runs parallel to the berth which gives access to the berth and the
storage area. A port office and signal centre are present on the landside, alongwith
temporary site offices for various agencies involved in the current phase development and
labour sheds.
Development of the back-up yard, railway sidings and yard and road network are proposed
on the landside area behind the berths under the current phase of development. The works
are in the ground filling and levelling stage at present.
2.5 Connectivity
2.5.1 Road
The Gopalpur Port is located 7 km from the National Highway 5 (NH 5), which runs till
Chatrapur. NH 217, which originates from the road connecting Gopalpur Port to Raipur in
Chhattisgarh, runs adjacent to the port entry. The road has been widened to 7.5 m. In
addition, there is also a road with wide right of way connecting the port via IREL gate and
their colony.
2.5.2 Rail
The railway trunk line from Chennai to Howrah runs upto a distance of 6 km from the port.
An existing siding from Chatrapur railway station to IREL plant abuts the port area. Rail
linkage to the port can be provided through this siding with a provision for doubling up as
and when required.
2.6 Landside characteristics
2.6.1 Topography
The topography of the area along the shore is highly undulated, with a no. of sand heaps
and indentations. The land is generally sloping towards the sea. Topography survey results
show that the terrain of the port site has contours mainly ranging from 2 m to 15 m. The
area towards the land side boundary of the survey area have ground elevation as high as
24 m. Low lying patches filled of water as well as green areas having vegetation are
observed over the area, as well.
2.6.2 Existing land use and ownership
Along the shoreline, there is an existing berth built by GPL on which cargo is handled. The
land immediately behind the berth is used as a storage area for the cargo. The port
boundary is adjacent to the plant of IREL on the land side. Filling and levelling operations
Gopalpur Ports Ltd. Development of Liquid Jetties at Gopalpur Port Pre- feasibility Study
Final Report
BMT Consultants India Page 24
are ongoing in the back up area. There is an existing Penna cement plot towards south of
the back up yard near the base of the south breakwater.
Small green patches consisting of bushes are scattered in the surrounding area. Most of
the remaining land near the port area is barren. There is no other habitation at the port site.
It is understood that the majority of the land being considered for development of the liquid
handling facilities is under GPL ownership. Some land parcels are at present owned by
other parties (such as IREL), but the acquisition process for this land is underway and
expected to be completed soon.
2.7 Soil conditions
2.7.1 Land side
The subsoil stratification and the field test results conducted in the boreholes on the land
side indicate that the soils at site, predominantly, consist of sands, sometimes interspersed
with clay binding at lower depths.
The general sequence of geological strata along the surveyed area is as follows:
• Loose to medium dense sand
• Dense to very dense sand, with silty sand at places
• Again a layer of medium dense sand
• Weak Khondalite and moderately strong Khondalite
The bedrock generally dips gently as we move from land side towards the sea.
2.7.2 Marine side
The borehole information in general shows the following geological sequence over the
entire area:
• The top layer primarily comprises of loose to medium dense sand interspersed with
dense sand
• This is followed by dense clayey sand and silty sand
• A layer of weak Khondalite is observed under it, followed by moderately strong to strong
Khondalite
• Presence of hard clay is observed towards the eastern side
(Source: Geotechnical investigation survey report by Ideal Geoservices Pvt. Ltd., 2017)
2.8 Climate
The climate of the region is characterised by two seasonal monsoons viz. northeast (NE)
and southwest (SW). NE monsoon occurs between December and March and is
characterised by predominant north-easterly winds. During this period, the risk of a tropical
Gopalpur Ports Ltd. Development of Liquid Jetties at Gopalpur Port Pre- feasibility Study
Final Report
BMT Consultants India Page 25
storm or cyclone is higher than in most months. SW monsoon extends from June upto
September and is characterised by occurrence of rain, with predominantly south-westerly
winds.
2.9 Meteorological and oceanographic conditions
2.9.1 Temperature
Maximum temperature varies from 29°C and 35°C with the highest temperature occurring
in June. Minimum temperature varies between 15°C and 24°C, with the lowest occurring in
December/January.
2.9.2 Rainfall
The average annual rainfall is 1,439 mm. The average number of rainy days is 67 per year.
June to October are the wettest months of the year with an average rainfall in excess of
185 mm per month, with a maximum of 296 mm in July. December to April are dry months
with average rainfall below 20 mm per month.
2.9.3 Relative humidity
Relative humidity is fairly high and uniform round the year. The mean relative humidity
varies between 74% and 84%.
2.9.4 Wind
The most prominent offshore wind direction is parallel to the coast in the south to SW
direction during southwest monsoon period; with the highest occurrence from SW. Winds
from NE direction are also present in northeast monsoon period. The magnitudes of wind
are mostly lower than 9 m/s.
Following figure gives the wind rose diagram for the port location:
Gopalpur Ports Ltd. Development of Liquid Jetties at Gopalpur Port Pre- feasibility Study
Final Report
BMT Consultants India Page 26
Figure 2-3: Wind climate rose diargram
(Source: ECMWF, 1995-2014)
2.9.5 Cyclones
East coast is prone to cyclonic storms around the year but mostly these occur prior to SW
monsoon i.e. in May and after southwest monsoon i.e. in October and November. Around
18 depressions are formed annually in the Bay of Bengal out of which 6 turn out to be
cyclonic storms on an average.
(Data source: DPR prepared by RITES, 2014)
2.9.6 Tides
The tidal levels at Gopalpur are given in the following table:
Tide Level (wrt CD)
High Astronomical Tide (HAT) + 2.20 m
Mean High Water Spring (MHWS) +1.70 m
Mean High Water Neap (MHWN) + 1.30 m
Mean Sea Level (MSL) + 1.10 m
Mean Low Water Neap (MLWN) + 0.90 m
Mean Low Water Spring (MLWS) + 0.70 m
Lowest Astronomical Tide (LAT) + 0.00 m
(Data source: Mathematical modelling report by BMT, 2018)
Gopalpur Ports Ltd. Development of Liquid Jetties at Gopalpur Port Pre- feasibility Study
Final Report
BMT Consultants India Page 27
2.9.7 Currents
The current at project site flows parallel to the coast, unidirectional towards NE except
during the neap tidal days, during which they reverse towards SW. The current
measurements show that the currents are less influenced by tidal phases.
The data on currents was collected in 1994 by NIO Goa. The long shore current speed
observed was relatively high about 1.2 m/s during June to August and it was about 0.5 m/s
during rest of the year.
(Data source: RITES Report 2014)
2.9.8 Waves
The offshore waves near the port location are primarily form the SSE, south and SSW
directions. The predominant wave periods vary from 6 to 10 sec, and the maximum
significant wave height occurring offshore is below 5 m.
Results of near shore wave transformation study show that the ambient maximum
significant wave height is 4.8 m at 20 m CD water depth. 70.1% waves at the location are
encountered form SSE direction. 97.5% of the times wave height are below 1.5 m; and 65%
of the time the wave periods vary between 6 to 12 sec. Highest waves are corresponding
to a wave period of 8 to 10 sec.
Following figure shows the rose plot of wave height for the wave climate at the port:
Figure 2-4: Wave climate rose diagram
(Source: Wave climate and tranquillity study report by BMT, 2017)
Gopalpur Ports Ltd. Development of Liquid Jetties at Gopalpur Port Pre- feasibility Study
Final Report
BMT Consultants India Page 28
2.10 Seismic conditions
The proposed project falls under Zone II as per the seismic map of India shown in IS: 1893
(Part 1) – 2002.
2.11 Raw material requirements
The proposed expansion of the Port envisages handling of liquid cargo in addition to
ongoing bulk and break bulk cargo operations. Hence, the proposed expansion will not
need any bulk raw materials during the operational phase. However, raw materials such as
cement, steel, sand gravel etc. will be required for the construction of marine structures and
land-based facilities, during the construction phase. These materials will be sourced from
the local suppliers.
2.12 Resource optimization and recycling
To improve the overall environmental sustainability of the port by means of resource
optimization and recycling, it is proposed that the waste water will be adequately treated
for reuse for alternative purposes and not be discharged into the sea. The sewage from the
liquid handling infrastructure will be collected by a drainage network in a sewage collection
sump near the sewage treatment plant (STP) to be developed at the facility. The treated
water will be collected in treated water sump near the STP after tertiary treatment for
reusing the STP recycled water for purposes such as gardening, dust suppression etc. The
run off during dust suppression by water sprinkling into sea is prohibited by passing it
through an oil-water separator, primary treatment (settling) and subsequently treated at
STP.
2.13 Employment generation
The potential level of employment generation resulting from the proposed liquid terminal
development at Gopalpur Port is envisaged to be for manpower of approx. 1000 persons
during the construction phase and 200 persons during the operational phase. Local
manpower will be preferred during construction phase.
Gopalpur Ports Ltd. Development of Liquid Jetties at Gopalpur Port Pre- feasibility Study
Final Report
BMT Consultants India Page 29
3 Traffic Forecast
The liquid cargo mix constituting the potential throughput to be handled at Gopalpur
includes LNG, LPG, POL, edible/vegetable oil and chemicals including ammonia. At this
stage, it is envisaged that all the liquid cargo will constitute import volumes. The cargo-
wise traffic forecast for liquid cargo is summarized below:
Table 3-1: Traffic forecast for Gopalpur Port (Mtpa)
Cargo 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028
LNG - - 2.5 3.0 4.0 5.0 6.0 7.5 8.5 10.0
LPG - - 0.15 0.2 0.3 0.45 0.5 0.65 0.75 1.0
Liquids 0.05 0.1 0.2 0.3 0.5 0.7 1.2 1.5 1.8 2.0
Total 0.05 0.1 2.85 3.5 4.8 6.15 7.7 9.65 11.05 13.0
FY21 FY22 FY23 FY24 FY25 FY26 FY27 FY28
Gopalpur Ports Ltd. Development of Liquid Jetties at Gopalpur Port Pre- feasibility Study
Final Report
BMT Consultants India Page 30
4 Terminal Concepts
4.1 LNG
4.1.1 LNG process overview
4.1.1.1 Value chain
The LNG value chain consists of different independent segments. Each of the segments
has specific industrial processes and requirements. Following figure gives a graphical
representation of the LNG value chain:
Figure 4-1: LNG value chain
The segments of the value chain are explained below in brief:
• Exploration and extraction
Under the first process, geological structures are analysed, and tests are carried out to
identify areas where there is a high possibility of discovering gas. If the gas is available,
it goes into extraction wherein raw gas is sourced from gas fields or underground
reservoirs or coal bed methane.
• Production and liquefaction
Production involves treatment of gas where various solid, liquid and gaseous
contaminants are removed. It is then converted from gaseous to liquid form by cooling
it to -162º C at which the gas is reduced to 1/600th of its volume and gets converted to
liquid state; thus making it economical for transportation and storage.
Gopalpur Ports Ltd. Development of Liquid Jetties at Gopalpur Port Pre- feasibility Study
Final Report
BMT Consultants India Page 31
• Shipping
This includes transport of the LNG from place of origin to place of consumption. LNG
is shipped at -163º C in LNG Carriers (LNGC) having specially designed cryogenic
tankers at maximum transport pressure of 25 kPa. The size of the LNGCs range from
15,000 m3 to 267,000 m3.
• Regasification
At the receiving terminal, the LNG is offloaded and is transferred from ships to
cryogenic storage tanks. LNG is then vaporized by gradually warming it, to retrieve
natural gas (NG) for send-out.
• Distribution
The NG is distributed to various range of end users via either pipelines under required
pressure and send-out capacity (piped natural gas or PNG) or by trucks /tankers
(compressed natural gas or CNG) for domestic, commercial and industrial use.
4.1.1.2 Import terminal components
The LNG receiving terminal is near the end of LNG supply/ value chain. An LNG import
terminal receives, stores and vaporizes LNG into NG for further distribution to the
consumption point. The LNG is unloaded from LNGCs using unloading system, stored in
either onshore or floating storage tanks, vaporized in either onshore or floating
regasification plant with process equipment and then delivered through distribution
pipelines or trucks/ tankers. The LNG terminal is to be designed to deliver gas at specified
rate and pressure into the distribution pipeline.
An LNG import terminal broadly comprises the following components:
• LNG unloading system including jetty and unloading arms
• LNG storage tanks
• LNG vaporisers
• In-tank and external LNG pumps
• Vapour handling system
• Supporting utilities, piping, valves, control systems, and safety systems required for the
terminal’s safe operation
• Infrastructure (roads, fencing and buildings)
• Flare stack
• Facilities for truck loading and power generation (optional/additional)
4.1.1.3 Process
The LNG process comprises of three major, relatively independent, processes:
• Unloading LNG from ship to storage
Gopalpur Ports Ltd. Development of Liquid Jetties at Gopalpur Port Pre- feasibility Study
Final Report
BMT Consultants India Page 32
• LNG regasification and despatch
• Boil-off gas (BOG) management
Following figure shows the schematic flow diagram of LNG process:
Figure 4-2: Typical LNG regasification process flow diagram
Subsequent to berthing of the LNGC, the hard LNG transfer lines as well as vapour return
line are connected to the LNGC and the unloading process is initiated. The unloading arms
or flexible hoses mounted on the unloading platform are attached to the manifold of the
LNGC and LNG is transferred to onshore storage tanks or to an FSU using ship pumps.
LNGC pumps usually have an unloading rate of 5,000 m3 to 12,000 m3/ hr depending on
the vessel size; such that they can unload the vessel within 15-18 hours from the time of
connection. Some of the vapour generated in the storage tank during unloading operations
is returned to the ship, in order to maintain positive pressure.
LNG is stored in cryogenic state at low pressure in storage tanks. Due to leakage of
surrounding heat into the storage tanks, some amount of LNG boils off and increases the
pressure of the tank; thus causing undue stress to the tank walls leading to breach of
containment. The BOG is therefore evacuated from the storage tanks and passed through
BOG compressor (used to increase the pressure of boil-off gas) and recondenser where
LNG is injected to re-liquefy the boil-off gas. The amount of vapour that can be
recondensed depends on the amount of send-out required. If there is not enough LNG
send-out to absorb the boil-off vapour, then the vapour must be compressed to pipeline
pressure, or flared or vented.
From the storage tanks, the submerged pumps provided in the tank pump out the LNG to
the recondenser from where high pressure (HP) LNG pump boosts the pressure and send
it to the vaporizer. The regasification process comprises of multiple vaporizers which
operate in parallel to gradually increase the temperature and covert LNG (liquid form) into
NG (gaseous form). This NG is then metered and despatched to the onshore NG pipeline
via HP pipelines and the pressure is achieved through multi- staged high send- out pumps.
Gopalpur Ports Ltd. Development of Liquid Jetties at Gopalpur Port Pre- feasibility Study
Final Report
BMT Consultants India Page 33
The above process can be carried out on an onshore terminal or floating terminal i.e. FSRU
or its variants. The different terminal concepts are explained in the subsequent sections.
4.1.2 Regasification- terminal concepts
4.1.2.1 Conventional LNG terminal
Most LNG import terminals operating all over the world are conventional onshore
regasification LNG import terminals. The conventional terminal consists of a marine facility
for offloading LNG from a standard LNGC to an onshore regasification unit. However,
conventional onshore terminals are relatively expensive to build and also a typical
regasification plant with two storage tanks would require about 4-5 years of construction
time.
The time for construction of the onshore regasification and especially the storage tanks is
considerably longer than the marine works. The marine facility for a typical conventional
LNG terminal consists of a loading platform and breasting and mooring dolphins. The ship-
to-shore transfer of LNG is carried out through loading arms on the loading platform
connected to the manifold of the standard LNGC.
The key features of a conventional LNG terminal are:
• The jetty is generally constructed in water depths less than 25.0 m and with operating
wave heights less than 2.0 m
• Reduced costs compared to FSRU/FSU berthing since loads are reduced
• Common jetty type, built extensively throughout the world
• Higher cargo handling possible as compared to FSRU/FSU type terminals
Figure 4-3: Conventional LNG terminal
Onshore
regasification
and storage
LNG
Carrier
Gopalpur Ports Ltd. Development of Liquid Jetties at Gopalpur Port Pre- feasibility Study
Final Report
BMT Consultants India Page 34
(Image source: Kochi LNG terminal, Shapoorji Pallonji database)
From the carrier, the fluid will be transported through offshore and onshore pipeline
arrangement to conventional LNG tank terminal. The offshore part of pipeline is typically
laid along a trestle and the onshore part either buried and/or above ground with structural
support arrangement.
To achieve an earlier start of operations, the deployment of a temporary FSRU or FSU may
be a viable option.
4.1.3 Terminal with Floating Storage and Regasification Unit (FSRU)/Floating
Storage Unit (FSU)
Floating storage and regasification units (FSRUs) were developed driven by the need for a
fast delivery LNG storage and regasification solution. FSRU projects have a short delivery
time in comparison with land-based terminals, which is the main advantage, whereas, the
land-based terminals are built for long-term operations.
The concept of FSRU is becoming very popular amongst potential LNG import terminals
being planned and built. FSRU consists of a modified/new build LNG vessel with a
regasification unit retrofitted on to it. Existing LNG ships can be converted to FSRUs by
making necessary changes to accommodate unloading arms, regasification system and
utilizing the storage tank on the ship as the storage medium.
Subsequently, the concept of FSU has also been developed in which the regasification unit
is located onshore and LNGC can be used as a storage facility to save time and cost on
the construction of onshore LNG storage tanks. However, in the case of FSU the onshore
regasification equipment is required to be installed and completed for operations.
The regasification process on an FSRU is similar to onshore regasification and only differs
in terms of size and capacities. The process equipment is arranged in a more compact
manner on-board an FSRU. The standard LNG vessel carrying LNG can be moored parallel
or adjacent to a permanently moored FSRU or an FSU. The mooring arrangement can be
Gopalpur Ports Ltd. Development of Liquid Jetties at Gopalpur Port Pre- feasibility Study
Final Report
BMT Consultants India Page 35
a standalone mooring facility or side by side mooring for transfer of LNG from carrier to the
FSRU/FSU. The liquefied gas is regasified on the on-board regasification unit (or onshore
regasification unit in case of an FSU) and transferred via high pressure pipelines to the end
users.
Figure 4-4: Typical LNG regasification process flow diagram on an FSRU
An FSRU/FSU can be moored on a permanent basis at the terminal until the onshore
facilities are complete for operations. This may be assumed to be around 3-4 years
depending on the commissioning of the onshore facilities and the throughput to be handled
at the facility.
A barge mounted regasification unit is similar to an FSU option with the regasification
carried out on a custom built non-propelled regasification barge instead of onshore.
4.1.3.1 FSRU/FSU mooring options
FSRU vessels can be classified either as ships or offshore installations depending upon
the design they incorporate. FSRU is typically positioned in near-shore water depth of 15
to 30 m. The FSRU can be connected to the onshore transfer point via a high pressure
sub-sea gas pipeline. The various mooring options of an FSRU/FSU can be classified as
follows:
1. FSRU/FSU and LNGC moored standalone/twin jetty
2. Single jetty side-by-side mooring: FSRU/FSU and LNGC moored side-by-side
3. Two separate jetties for LNGC and FSRU/FSU each
For FSRU, the regasified LNG is to be transported so the connection to the shore is by high
pressure gas pipeline. In case of an FSU based option, the regasification is based onshore
and the connection will require a cryogenic pipeline.
Cryogenic BOG
Compressor
M
BOG Recondenser
LP LNG Pumps
HP LNG Pumps
LNG Surge Drum
LNG Separator
FAV Option
S&T Option
WG System
WG System
WG System
LNGC / FSU / Jetty
Sampling & Metering Station
Natural Gas
Sendout
HP BOG Compressor
Option
Truck Loading Station Option
LNG
Recondenser Option
BOG Compressor Suction Drum
Gopalpur Ports Ltd. Development of Liquid Jetties at Gopalpur Port Pre- feasibility Study
Final Report
BMT Consultants India Page 36
This therefore rules out the offshore mooring options as, in general, subsea LNG pipelines
are not yet developed and/or are very expensive and the practical maximum distance of
transporting LNG by pipeline is 5 km without intermediate pumping and vapour recovery
system.
1. FSRU/FSU and LNGC moored – standalone/twin jetty
The conventional FSRU and LNGC are moored on a twin berthing facility independently on
either side of the loading platform. The LNG is transferred from LNGC to FSRU through
unloading and loading arms respectively. The gas from the FSRU is sent out onshore via
high pressure gas pipelines. For an FSU option this would mean a cryogenic connection to
the shore.
• The jetty is generally constructed in water depths less than 25.0 m and with operating
wave heights less than 2.0 m
• Cost of standalone jetty is higher compared to side-by-side mooring
• Facilitates smooth operating conditions and has minimum downtime
Figure 4-5: Stand alone jetty
2. Single jetty side-by-side mooring
The facility is a typical berthing facility consisting of a loading platform, berthing dolphins
and mooring dolphins. The FSRU is moored to the jetty similar to an LNGC at a
conventional LNG terminal. The LNGC moored directly to the FSRU, is protected by
fenders between the hulls. The LNGC transfers LNG to the FSRU through loading arms on
the FSRU, which is regasified on the FSRU and gas send-out is through pipelines either
subsea or over a trestle. For an FSU option this would mean storage of LNG and a
cryogenic pipeline connection to the shore.
Gopalpur Ports Ltd. Development of Liquid Jetties at Gopalpur Port Pre- feasibility Study
Final Report
BMT Consultants India Page 37
• It is generally constructed in water depths less than 25.0 m and are designed to operate
with wave heights less than 2.0 m
• Considered to be of acceptable cost
• Smooth operation with minimum downtime provided in sheltered environment
An alternative arrangement for the jetty is a set of mono-pile/ multi-pile dolphins (mooring
and berthing) to provide stability to the FSRU. A flexible gas transfer pipeline connects to
a smaller gas transfer platform which in turn connects to the send-out pipeline. This option
is generally not suitable for FSU based terminals as subsea cryogenic pipelines are
considered non-viable until date.
• This arrangement is generally constructed in water depths less than 25.0 m and are
designed to operate with wave heights less than 2.0 m
• Considered to be cost efficient
• Smooth operation with minimum downtime
The jetty can be placed on the lee side of the breakwater which facilitates smooth unloading
operations without downtime due to sheltered environment. The facility is possible for both
side-by-side and stand-alone/ twin jetty mooring.
Figure 4-6: Conventional jetty for side-by-side mooring
3. Two separate jetties for LNGC and FSRU each
The concept consists of mooring an FSRU and an LNGC to two separate jetties. The LNG
from the carrier is transferred via unloading arms on one jetty, through the cryogenic
pipelines and loaded onto the FSRU moored on another jetty via loading arms. The gas
send-out from the FSRU is via high pressure gas pipeline. For an FSU option this would
mean storage of LNG and a cryogenic pipeline connection to the shore.
Gopalpur Ports Ltd. Development of Liquid Jetties at Gopalpur Port Pre- feasibility Study
Final Report
BMT Consultants India Page 38
• It is generally constructed in water depths less than 25.0 m and are designed to operate
with wave heights less than 2.0 m.
• No ship-to-ship offloading limitations as compared to side-by-side mooring hence
facilitating smooth operations. However, cost is higher due to construction of two
separate jetties and installation of cryogenic pipelines.
4.1.3.2 Comparative analysis of terminal concepts
The following table shows the comprehensive analysis carried out by studying and
comparing each concept as per the list of parameters for the selection of a suitable terminal
type for the development of an LNG terminal within the port.
Gopalpur Ports Ltd. Development of Liquid Jetties at Gopalpur Port Pre- feasibility Study
Final Report
BMT Consultants India Page 39
Table 4-1: Comparison of LNG terminal concepts
Terminal concept Conventional jetty with
onshore regasification
FSU with onshore
regasification FSRU
Comparative parameters
Land requirement - Large area required. - Land required is lesser as compared to
conventional terminal.
- Lowest requirement along all alternatives.
Time for commissioning - Longest construction time, hence longer
duration for commissioning.
- Shorter time to commission as compared to
conventional terminal.
- Regasification process can be modularized
and built simultaneously in a separate
location.
- Dependent on FSRU existing fleet or lead-
time for repurposed/new build.
- Lowest construction time along all
alternatives.
- Shorter time to commission as compared to
conventional terminal.
- Extensive planning not required for FSRU
as compared to a conventional onshore
regasification terminal.
Regasification
process and capacity
- Suitable for high throughput.
- Long term flexibility.
- Variety of regasification/ vaporization
options available.
- Continuous gas send-out.
- Less capacity as compared to onshore
terminal.
- Variety of regasification/vaporization
options available.
- Possibility to combine with small LNG tanks
onshore to increase send-out reliability
during cyclones.
- Less capacity as compared to onshore
terminal.
- Limited vaporization options.
LNGC mooring and fluid
transfer
- Conventional LNG terminal, no issues
foreseen.
- Ship-to-ship offloading is required, which is
widely acceptable and practised in the LNG
industry now.
- Ship-to-ship offloading requires additional
procedures, could limit supply options.
Gopalpur Ports Ltd. Development of Liquid Jetties at Gopalpur Port Pre- feasibility Study
Final Report
BMT Consultants India Page 40
Capital expenditure - Expensive - Savings on construction of storage tanks,
therefore lower capex than a
conventional terminal.
- FSU can be moved from one point of
demand to serve another.
- Higher capex compared to FSU +
onshore regasification as it is not easily
scalable.
- FSRU can be moved from one point of
demand to serve another.
Feasibility within the port - It is possible to develop this option,
provided that land is available.
- This option is highly preferable as it is
easily scalable.
- Regasification process can be
modularized leading to faster turnaround
time.
- Feasible.
Gopalpur Ports Ltd. Development of Liquid Jetties at Gopalpur Port Pre- feasibility Study
Final Report
BMT Consultants India Page 41
4.1.4 Recommendation
Based on the analysis of the various LNG terminal concepts and taking into cognizance the
advantages offered by the FSRU as compared to the other options, it has been selected
as the preferred alternative for the current stage of the project. This option has relatively
low capital cost and provides significant commercial flexibility compared to the other
configurations described. The key advantages of this alternative are as follows:
• Lowest land and time requirement
Conversion of a vessel to FSRU requires significantly lesser time than the construction
of onshore tanks for storage. In addition, there is no requirement of land for this
alternative. Hence, the project gestation period is lowered significantly, and revenue
generation can commence earlier than that possible if a conventional type of LNG
terminal is being developed. These factors help make FSRU an attractive alternative
since this results in time and cost reduction as well.
• Lowest capital cost
The alternative of retrofitting of older vessels coming off long-term charter for utilisation
as FSRU is a favourable option, considering that this works out to be the most
economical storage solution. Construction of onshore storage (tanks) is considerably
costlier than an FSRU. This alternative also helps save the costs associated with land
requirement. Since the market is highly cost sensitive, it is necessary to ensure lower
capital expenditure in development of the terminal. Hence, the option of FSRU is the
most attractive considering that this will incur the lowest capex amongst all the options.
• Scalability
This alternative offers scalability in operations, thus allowing GPL to enhance the
capacity of the facility in the future with increased demand, with a view to meeting the
rising market demands. It also helps justify the initial investment to customers.
• Modularization
Modularization is an additional advantage offered by choosing the FSRU configuration,
which ensures lower turnaround time, also resulting in reduced time and costs. To keep
the gas price attractive and not burden the customers with initial high capex, the option
of expanding the terminal in sync with the demand growth in phases is deemed a
favourable alternative.
It is to be noted that between FSRU based and onshore LNG terminals, these are more a
complement to each other, since the terminal concepts are very different, and the choice
of terminal is to be made on basis of the project requirements and constraints. The value
that FSRUs bring to the LNG value chain are different from that of the land-based terminals.
As per the current trends, operational considerations and trade practices, upto 3.5 Mtpa
can be handled using a single FSRU. For throughput exceeding 3.5 Mt, it can be handled
using either 2 nos. FSRU or by converting the facility to a conventional LNG terminal with
onshore regasification and storage.
Gopalpur Ports Ltd. Development of Liquid Jetties at Gopalpur Port Pre- feasibility Study
Final Report
BMT Consultants India Page 42
Accordingly, it is proposed that the FSRU based facility will be developed for the current
phase i.e. to handle upto 3.5 Mtpa, following which, the terminal will be converted to a
conventional LNG terminal to handle the increased volumes.
4.2 Other liquids
The other liquids to be handled at Gopalpur consist of LPG, edible oil, POL, chemicals like
ammonia etc. Since there are no stringent requirements with regards to the safety aspects
in handling and operations (unlike LNG), all these liquid cargoes can be handled on the
same berth and terminal.
The movement of LPG and other liquid bulk cargo, from the vessel will be undertaken by
means of pipelines connected to the shore- based storage tanks. Pumping equipment is
available on the smaller size vessels.
For liquid cargo, the discharge from the ship’s tanks will be via the cargo piping system to
the ship’s manifold usually situated amid ships, on either starboard or port side. From there,
by means of shore- based unloading arms, liquid cargo will be transferred to the shore
manifold and then distributed to shore-based tanks. The loading arm hose must be flanged
oil tight to the ship’s manifold so that oils spills can be avoided.
According to the type of cargo and the envisaged parcel sizes, tanks of different sizes as
per the cargo storage requirement will be constructed. The terminal will also house the
evacuation related facilities i.e. truck loading, rail loading and pipeline connectivity.
Figure 4-7: Liquid cargo operations
Liquid cargo shipment in tanker
Unloaded at berth using unloading arms
Transferred to tank farm via pipeline
Stored in liquid tank farm
Evacuation to deliver to customers
Loaded into tankers
for evacuation via
road
Loaded into tank
cars for
evacuation via rail
Loaded into tank
cars for
evacuation via rail
Gopalpur Ports Ltd. Development of Liquid Jetties at Gopalpur Port Pre- feasibility Study
Final Report
BMT Consultants India Page 43
5 Operating Considerations and Functional
requirements
This chapter examines in detail the major operating considerations to be taken into
cognizance while planning the liquid terminal. The functional requirements are also
assessed on the basis of the requirements of the facility to develop the marine and landside
infrastructure layout and to formulate the scheme of operation for this facility.
5.1 Traffic forecast summary
The cargo mix and the forecasted traffic throughput are as discussed in Chapter 3. The
pre- feasibility study takes into consideration throughput starting from 0.1 Mtpa of other
liquids in the first two years and reaching upto a total volume of 13 Mtpa (10 Mtpa LNG and
3 Mtpa LPG, other liquids) in 2028.
5.2 Ship size analysis
Design vessel sizes are governed mainly by the availability of vessels worldwide and
considering the global fleet, throughput, water depth and marine facilities and the aspect of
ensuring scalability in case of future expansions. Liquid cargoes are handled in tankers.
The market demands high service levels in terms of timely and safe movement of high-
value, sensitive and sometimes hazardous and aggressive liquid cargoes. This section
arrives at the design vessel size for the FSRU, LNGC as well as the other liquids.
It is envisaged that the LNG terminal at Gopalpur will commence operations with an FSRU
permanently moored at the jetty to which the vessels will be moored on the side, followed
by conversion of the facility to a conventional onshore type LNG facility in the future, upon
increase in the throughput. In such a scenario, the jetty has to be designed considering the
size of FSRU vessel as well as the LNGC which may call at the port in the future.
For LPG and the other liquids, the design vessel size is assessed on the basis of the
historical ship sizes, prevalent global shipping practices based on the value/type of cargo
as well as the typical parcel size requirements of the buyers.
5.2.1 LNG
5.2.1.1 Global LNGC and FSRU fleet
Considering the size of LNG on order or under construction across various global
shipyards, the current “standard” size for LNGC is approximately 160,000 m3, up from
135,000 m3 during 1990s. To understand the changing dynamic of the “standard” LNG ship
size with respect to time, we have differentiated the ships with respect to their vintage and
storage capacities as below:
Vintage categories
• Older vintage (hull delivery up to year 2007)
• Newer vintage (hull delivery from 2008 onwards)
Gopalpur Ports Ltd. Development of Liquid Jetties at Gopalpur Port Pre- feasibility Study
Final Report
BMT Consultants India Page 44
• Under construction (hull delivery from 2013 onwards)
Storage capacity categories
• Very small (< 50,000 m3)
• Small (between 50,000 m3 and 120,000 m3)
• Medium (between 120,000 m3 and 160,000 m3)
• Large (between 160,000 m3 and 180,000 m3)
• Very large (> 180,000 m3)
5.2.1.2 Sizing
• Repurposed FSRU
Based on the above section, we conclude that for a retrofitted FSRU, the candidate ship
coming from the LNG fleet would be of older vintage and therefore typically would be of
medium capacity. Accordingly, the ships of capacity ranging from 125,000 m3 – 145,000 m3
are within the optimal range of vessels for the retrofitted FSRU.
• New-built FSRU
We understand that all the new-built FSRU vessels and under-construction FSRU vessels
are large ships. Given the significant number of 170,000 m3 ships under construction, a
standard capacity of up to 175,000 m3 is to be considered for the new-built FSRU storage
capacity.
• LNG carrier (LNGC)
The choice of LNGC is constrained by the storage capacity of FSRU as they must have
smaller or similar storage capacities than the FSRU. Accordingly, the design vessel size is
finalised.
5.2.1.3 Selection of FSRU
The type of vessel to be selected for the purpose of utilisation as FSRU depends on a no.
of factors. In addition to the consideration of the global fleet availability, forecasted
throughput and storage requirements while selecting the FSRU vessel, a major factor
determining the final choice is also capital cost of the FSRU and its economics.
FSRU conversion for older tonnage that is coming off long-term charter is a favourable
option. Ships that are 25 years or older, typically about 138,000 m3 capacity, are the
approximate size of vessels that are repurposed to FSRUs. Moss or membrane
containment vessels can be retrofitted into FSRU. Typically, moss containment is favoured
because moss tanks are better than membrane tanks at withstanding sloshing loads as
well as considering the availability of space in moss containment for locating the
regasification equipment. FSRUs having tank capacities of 125,000 to 150,000 m3 are
mostly in use.
Gopalpur Ports Ltd. Development of Liquid Jetties at Gopalpur Port Pre- feasibility Study
Final Report
BMT Consultants India Page 45
It is, therefore, proposed that a previously used (20-25 years old) vessel of 138,000 m3
capacity be deployed by GPL for the LNG facility at Gopalpur. The decision of deploying a
previously used vessel of 138,000 m3 in place of choosing a larger vessel of recent make
for the purpose of FSRU is primarily based on the strategy of storage cost optimization.
As explained above, the FSRU proposed to be deployed at the terminal will be of size
138,000 m3 considering the criteria of selection as discussed.
Table 5-1: Design vessel size- FSRU
FSRU dimensions
Size range (m3) 125,000 – 150,000
Capacity (m3) Up to 150,000
LoA (m) 290
Beam (m) 43.4- 48.9
Draught (m) 11.0-11.5
The average capacity of the FSRU for planning the facility is considered as 138,000 m3.
5.2.1.4 LNG carrier (LNGC)
The nature of the commodity i.e. cargo characteristics and its parcel size determine the
ship size to be used on a particular service. In addition, the global shipping trend is also a
major determinant of the design LNGC size.
With respect to economies of scale, the bigger the size of the LNGC is, the higher is the
convenience in operations and the profitability. Also, with the increasing throughput over
the years, the design vessel size of LNGC calling at the port will also get larger. Accordingly,
in the initial phase, design LNGC size is considered as 138,000 m3, but the infrastructure
is to be designed to serve requirements in the future as well. Accordingly, vessel of size
173,000 m3 is considered as the maximum vessel size to be served at the terminal at
present. In the future, the terminal can be planned to handle upto Q-Max size vessels.
Table 5-2: Design vessel size - LNGC
LNGC dimensions Current phase Future phase
Size (m3) Upto 173,000 Upto Q-Max i.e. 267,000
Capacity (m3) 138,000 220,000
LoA (m) 290 345
Beam (m) 45.8 54
Draught (m) 11.8 12.0
5.2.2 Other liquids
Ocean-going POL, oil and chemical tankers generally range from 5,000 DWT to 40,000
DWT in size and are considerably smaller than the tankers used for moving voluminous
Gopalpur Ports Ltd. Development of Liquid Jetties at Gopalpur Port Pre- feasibility Study
Final Report
BMT Consultants India Page 46
cargo like crude oils. This is partly due to their specialized nature and stringent conditions
for storage and shipping and also because economies of scale are less important than in
the trades dealing with large volumes. It is also applicable to LPG tankers to be taken into
consideration for the study.
Product tankers normally have a series of separate cargo tanks that are either coated with
specialized coatings such as phenolic epoxy or zinc paint or made from stainless steel.
Many carriers can transport multiple cargoes as they have several separate cargo tanks.
The carrier design and tank material are determined by the chemical composition of the
cargo that needs to be transported.
Typical bulk liquid carriers have dimensions as summarised in the table below:
Table 5-3: Typical bulk liquid ship sizes
Carrying capacity (DWT) LoA (m) Beam (m) Min. draught (m)
10,000 127 20.8 7.9
20,000 158 25.8 9.6
30,000 180 29.2 10.9
40,000 211 32.3 12.6
The design vessel size for LPG and other liquids is assessed as below:
Table 5-4: Design vessel size for LPG and other liquids
Design vessel size parameters LPG Other liquids
Capacity (DWT) 30,000 20,000
LoA (m) 180 158
Beam (m) 29.2 25.8
Draught (m) 10.9 9.6
The above vessel details will govern the jetty design, storage capacity, harbour design
including channel and turning circle dimensions as well as harbour traffic control. In the
case of LNG, depending on the throughput, it is possible that in the future the operations
may be carried out without the FSRU i.e., by direct berthing of vessels and larger sized
vessels will be calling at the facility at this stage. Hence taking into consideration the trend
of increase in average and maximum ship sizes, the layout will be optimised to berth ships
of sizes discussed in this section.
In the case of other liquids, given the shipping trends and the parcel sizes, major variations
in the design vessel size is not envisaged.
Gopalpur Ports Ltd. Development of Liquid Jetties at Gopalpur Port Pre- feasibility Study
Final Report
BMT Consultants India Page 47
5.3 Principal harbour dimensions
5.3.1 Approach channel
“Approach Channels – A Guide for Design”, PIANC, Report no. 121-2014 provides
guidance for the determination of the underkeel clearance (UKC) requirements for safe
navigation.
As per standard requirements, the UKC shall be considered at 30% of the draught for the
channel subjected to the wave action and 10% of the vessel draught for the calm protected
water. The channel width is assessed by considering 5 times the beam of the vessel for a
two-lane navigation.
Considering the dimensions of the different design vessels as per cargoes (refer Table 5-2
and Table 5-4), the navigational requirements will be governed by the LNGC size as it is
the largest. Accordingly, the required navigation channel dimensions are assessed as
follows:
Table 5-5: Approach channel dimensions
Approach channel dimensions Current phase (facility with FSRU) Future phase (conventional LNG facility)
Channel depth
LNGC size (m3) 173,000 267,000
Vessel draught (m) 11.8 12
Inner channel depth (m wrt CD) 13.0 13.2
Outer channel depth (m wrt
CD)
15.3 15.6
Channel width
Vessel beam (m) 45.8 54
Channel width (m) 230 270
Hence, the depth of -15.5 m proposed in the current phase and -18.5 m in the future phase
in the navigation channel will be sufficient for navigation of design vessel size.
The existing channel width of 200 m is sufficient for single way navigation. Considering that
the vessel movement in the inner channel and harbour will be assisted by tugs, it is not
deemed necessary to increase the channel width for navigation of the liquid tankers.
However, in the future, depending on traffic to be handled at the port and should there be
requirement of two-way navigation, widening of the channel will have to be examined at
that stage.
5.3.2 Harbour and turning circle
PIANC and IS: 4651 (Part V) recommend that where vessels turn by free interplay of the
propeller and assisted by tugs, the minimum diameter of the turning circle should be 1.7 to
2.0 times (1.70 for protected locations and 2.0 for exposed locations) the length of the
Gopalpur Ports Ltd. Development of Liquid Jetties at Gopalpur Port Pre- feasibility Study
Final Report
BMT Consultants India Page 48
largest vessel to be turned. These ships would be assisted with tugs in manoeuvring in the
approach channel, in the harbour basin and to and from the jetty.
The water depth in the harbour basin and in the front of and alongside the jetty should
generally be sufficient for safe manoeuvring. The water depth should be based on the
maximum loaded draught of the largest design vessel. For sheltered areas the estimated
minimum UKC required would be 10% of the ship’s draught.
Table 5-6: Turning circle dimensions
For 173,000 m3 LNGC For Q-Max LNGC
Vessel LoA (m) 290 345
Turning circle dia. (m) 560 610
Vessel draught (m) 11.8 12
Depth in harbour (m wrt CD) 13.0 13.2
Accordingly, the turning circle of 600 m at present will suffice considering the navigation
requirements. The available depth in the harbour is adequate as per the requirements
assessed.
5.3.3 Minimum stopping distance
As per standard industry norms, a minimum stopping distance requirement is in the range
of 3 to 5 ship lengths between the main breakwater roundhead and the start of the turning
basin. This implies a requirement of 1000 m for the design ships, which is in line with the
available distance in the existing harbour. Accordingly, the distance available to steady the
ship and fasten the tugs to vessel before entering the port is in the range of 3 to 3.5 for the
design vessel sizes.
5.4 Jetty requirements
The main components of the liquid jetty are:
• unloading platform
• approach trestle
• breasting dolphins
• mooring dolphins
• catwalks
A jetty with dolphin type berthing facility supported by piles is the most common and suitable
structural system for liquid handling facilities. A central unloading platform with breasting
dolphins provides safety and the mooring dolphins provide adequate anchorage and
stability for achieving operational conditions. The trestle structure will support the liquid
carrying pipeline, utilities including fire-fighting water supply and a roadway. Typical liquid
jetty is as shown in Figure 5-1.
Gopalpur Ports Ltd. Development of Liquid Jetties at Gopalpur Port Pre- feasibility Study
Final Report
BMT Consultants India Page 49
Figure 5-1: Liquid jetty- general arrangement (typ.)
Jetty requirements are calculated on the basis of operational considerations, cargo
volumes and the no. of ship calls. The arrival of vessels at jetty is usually a stochastic
process. The number of jetties required will depend on the jetty occupancy. Jetty
occupancy is expressed as a percentage of the number of hours a jetty is occupied by
vessel(s) to the total no. of berth hours available in a year. Therefore, in order to calculate
the number of jetties required, it is essential to know if the ships arrive randomly or if there
are significant peaks in the arrival pattern. High jetty occupancy factors can seem attractive
because this yields the highest jetty utilisation, but it also has a significant impact on waiting
time and congestion issues.
The assessment of jetty occupancy takes into consideration the following:
• Effective working duration
While calculating the required no. of jetties, it is considered that cargo handling and ship
servicing will be carried out 24 hrs a day in multiple shifts.
Annually, 350 days are considered for the calculation of jetty occupancy, taking into
consideration incremental weather downtime, equipment breakdown etc.
• Additional service requirements
The turn-around time at the port includes the time required for actual unloading/loading
operations and time for peripheral activities. Apart from the actual time for
loading/unloading cargo, additional time is required for berthing and de-berthing of ships,
obtaining customs clearance, surveys, positioning and hook up of equipment, waiting for
pilots and clearance for navigation. An average duration of 6 hours per vessel is allowed
for these activities.
• Cargo handling rate
The unloading time is determined by the effective cargo handling rates. The details of
handling rates are explained in the subsequent sections.
5.4.1 LNG
The jetty occupancy assessment for LNG is carried out for the current phase i.e. for the
FSRU based facility as well as the future phase i.e. the conventional onshore type of LNG
facility.
Approach
trestle
Unloading
platform
Breasting
dolphins
Mooring
dolphins
Gopalpur Ports Ltd. Development of Liquid Jetties at Gopalpur Port Pre- feasibility Study
Final Report
BMT Consultants India Page 50
5.4.1.1 FSRU based LNG facility
Effectively, the jetty occupancy is being assessed on the basis of the total time taken by
the cargo to be transferred (i) from the LNGC to the FSRU (ii) FSRU to onshore
regasification unit (iii) regasification and send-out. Since there is no onshore storage to be
provided, it is considered that that after offloading the LNG from LNGC to FSRU, the
regasification and cargo transfer from FSRU to onshore unit and send-out will be
undertaken as a continuous process. Effectively, the LNG facility is under utilization and
hence occupied for the whole duration until the entire process of (i) LNGC to FSRU transfer
of LNG (ii) regasification at FSRU and send-out is complete.
In essence, the governing factors for determining duration of occupancy of the facility are
(i) rate of unloading from LNGC to FSRU (ii) send-out rate. Since there is no onshore
storage to be provided, it is considered that that after offloading the LNG from LNGC to
FSRU, the cargo transfer from FSRU to onshore regasification unit and further
regasification and send-out will be undertaken as a continuous process. Considering that
the rate of transfer of cargo from FSRU to onshore unit is greater than the send-out rate,
the calculation is carried out using the gas send-out rate.
As per prevailing industry trends and operational practices, the unloading time is
determined by the effective cargo handling rates. As per standard FSRU configurations
available in the industry for the proposed size of vessel, handling rate of 7,500 m3/hr from
the LNGC to FSRU is proposed. For the send-out of regasified cargo, 4 send-out units with
a total regasification capacity of 600 MMSCFD are considered.
The assessment of jetty utilisation to examine the feasibility of handling the target LNG
throughput using an FSRU is as shown below. It is undertaken for combinations with
different sizes of LNGCs vis a-vis the FSRU of proposed capacity to understand the most
optimal scenario.
Gopalpur Ports Ltd. Development of Liquid Jetties at Gopalpur Port Pre- feasibility Study
Final Report
BMT Consultants India Page 51
Table 5-7: Jetty occupancy for FSRU based LNG facility
LNG jetty occupancy assessment
Vessel particulars
Annual Throughput (t) 35,00,000 35,00,000
Annual Throughput (m3) 77,00,000 77,77,000
LNGC Vessel size (m3) 1,38,000 1,95,000
FSRU size (m3) 1,38,000 1,38,000
Number of LNGC calls per annum 56 40
Unloading and regasification
Unloading arm working hr 24 24
Capacity of unloading arms (m3/hr) 7,500 7,500
Handling rate per day (m3/day/jetty) 1,80,000 1,80,000
Avg. send-out rate of NG (MMSCFD) from regas 600 600
Avg. send-out rate of LNG (m3/day) from regas 31,980 31,980
Total handling duration
Additional berthing/ unberthing/ waiting time (day) 0.33 0.42
LNG unloading from LNGC to FSRU/vessel (day) 0.77 1.08
Balance FSRU capacity (m3) (difference of capacities of LNGC and FSRU) - 57,000
Regas, send-out duration of LNG from FSRU/vessel (day) 4.32 6.10
Total duration of LNG transfer from LNGGC to FSRU to send-out/vessel (day) 5.42 7.60
Jetty occupancy percentage
Assumed available berth days per annum 350 350
No. of jetties 1 1
Total vessel days 302 303
Jetty occupancy 86% 87%
As seen from the above table, the jetty occupancy is slightly higher than the standard
operating limit of 85% for LNG terminals. However, there is a possibility of optimising the
process or increasing the regasification/send-out rate to ensure more efficient operations.
The alternative of deploying a larger FSRU with higher capacities can also be explored, but
the cost economics would have to be evaluated.
Thus, it is inferred from the above assessment that as explained in §4.1.3, upto 3.5 Mtpa
can be handled using a single FSRU (i.e. a single jetty).
5.4.1.2 Conventional onshore based LNG facility
As explained in §4.1.3, at a stage when the throughput exceeds 3.5 Mt, the facility will be
converted to a conventional LNG terminal with onshore regasification and storage for
handling the cargo. In this phase, vessels of size upto Q-Max are envisaged to be handled
at the port. The unloading rate at the LNG jetty is considered as 12,500 m3/hr.
Gopalpur Ports Ltd. Development of Liquid Jetties at Gopalpur Port Pre- feasibility Study
Final Report
BMT Consultants India Page 52
Table 5-8: Jetty occupancy for conventional LNG facility (future)
Assessment of jetty occupancy
Annual Throughput (t) 10,000,000
Annual Throughput (m3) 22,000,000
Average Vessel Size (m3) 225,000
Average Parcel Size (m3) 180,000
Number of ships per annum 122
Operational hr/ day 24
Handling Rate per day (m3/hr) 12,500
Handling time per shipment (hrs) 14.40
Berthing/ unberthing/ waiting time (hrs) 8.00
Total days per ship (hrs) 22.40
Total days per ship (days) 0.93
Berth days per annum 114
No. of berths provided 1
Available working days at port (annual) 350
Berth occupancy rate 33%
The assessment of jetty occupancy indicates that 1 no. jetty will also be sufficient for 10
Mtpa, considering a conventional onshore LNG terminal. In this scenario, it will also be
possible to handle greater volumes efficiently at the LNG terminal with the available marine
infrastructure.
5.4.2 Other liquids
As explained previously, LPG and other liquids like POL, edible oil, chemicals etc. can be
handled on the same jetty. For the projected annual throughput of LPG and other liquids,
the jetty occupancy is calculated to establish the jetty requirements, as shown in Table 5-9.
Gopalpur Ports Ltd. Development of Liquid Jetties at Gopalpur Port Pre- feasibility Study
Final Report
BMT Consultants India Page 53
Table 5-9: Jetty occupancy for LPG and other liquids
Description LPG Other liquids
Annual throughput (t) 10,00,000 20,00,000
Average parcel size (t) 26,000 15,000
Number of ships per annum 38 133
Working time per day (hr) 24 24
Handling rate (tpd) 24,000 15,000
Handling time per shipment (days) 1.1 1.0
Other time (days) 0.25 0.25
Total time per ship (days) 1.33 1.25
No. of days of operation for handling one vessel 51 167
Number of berths 1
Number of days in a year 350
Berth occupancy (%) 62%
As per the assessment shown above, the operating capacity of a single berth works out to
3 Mtpa. This scenario considers utilisation of unloading pumps installed at the berth.
At the time of commencement of liquid bulk operations at Gopalpur, smaller vessels with
lower parcel sizes are envisaged to call at the port. At this stage, the cargo can be handled
at the general cargo berth (currently under construction) using ship gears. It is assessed
that upto 1.7 Mtpa can be effectively handled, considering an output of 10,000 t/day.
Thus, based on the above assessment, it is proposed that two liquid jetties be developed;
one dedicated jetty for LNG operations and the other liquid jetty for LPG and the other
liquids.
5.5 Approach trestle
The jetties will be connected to the landfall point by means of an approach trestle. The
approach trestle is to be designed to accommodate:
• Access road for movement of fire trucks and ambulances (in case of emergency and
mobile crane (in travelling mode only).
• Walkway for movement of personnel, primarily for service and maintenance of the pipes
and utilities.
• Pipe rack and utility corridor
• Lighting
• Safety equipment
Gopalpur Ports Ltd. Development of Liquid Jetties at Gopalpur Port Pre- feasibility Study
Final Report
BMT Consultants India Page 54
5.6 Land side requirements
The land side requirements for the cargoes is assessed basis the land required for storage
at the port as well as associated evacuation facilities.
5.6.1 Storage
The assessment of total storage requirement is undertaken by analysing the commodity
wise area requirements in relation to the forecasted volumes. Storage area requirements
are sensitive to a wide array of parameters, principally:
• Projected annual throughput volumes
• Average dwell time
• Cargo types and segregation/safety requirements
• Area for internal circulation and access
5.6.1.1 LNG
At present, it is proposed to deploy an FSRU for the LNG operation and it will be utilised
for storage of the cargo. The construction of an onshore storage facility is not envisaged to
be required given the forecasted throughput at present and the existing project
requirements. A small buffer storage provision is proposed at the truck loading terminal to
support the truck loading operations. Accordingly, the area requirement in this phase is
approx. 5-10 ha.
Following ramp up of LNG volumes at the terminal (>3.5 Mt), the terminal will be converted
to a conventional onshore LNG facility, with storage, process side facilities and other
ancillary infrastructure alongwith evacuation related facilities will be provided onshore. At
this stage, an area of approx. 40 ha will be required for the LNG facility.
5.6.1.2 Other liquids
• LPG
Considering an annual throughput of 1 Mtpa, it is assumed that storage for one parcel
load i.e. 30,000 t is to be provided. Accordingly, it is proposed that 3 clusters of tanks
with total 10,000 kL capacity of each cluster will be constructed.
• Other liquids
The total annual throughput of other liquids is 2 Mtpa.
Accordingly, it is proposed that tanks of sizes ranging from 500 kL to 5,000 kL
depending on the type of cargo and the parcel size of each type of commodity to be
stored at the liquid terminal. Larger tanks upto 15,000 kL may be considered in the
future depending on parcel sizes and storage requirements.
Given the total area requirement for LPG and liquids, the land area needed for developing
the liquid terminal is in a range of 15-20 ha.
Gopalpur Ports Ltd. Development of Liquid Jetties at Gopalpur Port Pre- feasibility Study
Final Report
BMT Consultants India Page 55
It is also important to ensure that the safety aspects for the cargoes to be handled also be
taken into cognizance while locating and planning the back up area.
5.7 Evacuation
5.7.1.1 LNG
The NG will be evacuated primarily by means of pipeline. The LNG facility will be connected
to the gas grid by means of tie- in pipeline, via which, the gas will be evacuated and
transported to the customers.
To make LNG available to customers who are not linked to the gas pipeline network, LNG
will be supplied by cryogenic trucks (upto 25 t capacity). Though the demand for LNG from
industrial zones is substantial, they are scattered and still not connected. Hence, for such
customers, road transportation will fulfil the requirement. Low fixed costs and short
distances make road tankers more preferable. Moreover, road tankers offer high flexibility
and durability. With road tanker deliveries, LNG is not regasified at the terminal but at the
end user locations. Approx. 20 truck loading bays are proposed to be provided for
evacuation of LNG. These will be built in phases as per the throughput requirements.
5.7.1.2 Other liquids
The other liquids like POL, edible oil, chemicals etc. will be evacuated mainly by means of
pipeline. The pipeline will be connected from the liquid storage at Goplapur upto the users’
facilities. For customers who cannot be served by means of the pipeline, the liquid cargo
will be evacuated from the port and delivered to the destination via both road and railway
modes as well. Tankers will be used for evacuation by road and tank cars for evacuation
through rail.
Gopalpur Ports Ltd. Development of Liquid Jetties at Gopalpur Port Pre- feasibility Study
Final Report
BMT Consultants India Page 56
6 Alternative Locations
6.1 Feasibility of multiple jetties in the harbour
6.1.1 Existing harbour layout and conditions
The assignment calls for exploring various locations in the harbour of Gopalpur Port to
develop liquid jetties for handling the estimated liquid cargo throughput. The port
infrastructure being developed at Gopalpur is meant for handling of dry bulk and general
cargo. The operational safety, convenience and control aspects as well as the cost of
investment and operations assume paramount importance when evaluating the options.
The existing harbour layout of Gopalpur Port is as shown in Figure 6-1.
Figure 6-1: Existing harbour of Gopalpur Port
The existing landside and marine infrastructure at the port as well as the infrastructure
under development currently is described in §2.3. Following completion of the current
phase of development, the infrastructure in the Gopalpur Port harbour and on the landside
will be as shown below in Figure 6-2 (refer corresponding drawing no. BMT-1395-GPL-
PFR-DWG-001).
Gopalpur Ports Ltd. Development of Liquid Jetties at Gopalpur Port Pre- feasibility Study
Final Report
BMT Consultants India Page 57
Figure 6-2: Proposed layout of ongoing development at Gopalpur Port
Gopalpur Ports Ltd. Development of Liquid Jetties at Gopalpur Port Pre- feasibility Study
Final Report
BMT Consultants India Page 58
As seen from the above figure, the available waterfront for development of additional jetties
includes the following:
(i) Stretch in continuation with dry/general cargo berths already developed
(ii) Along the south breakwater
(iii) Along the intermediate breakwater
It is to be noted that as part of the future developments at the port, it is proposed that
development of 2 nos. bulk berths may be considered, along the inner arm of the southern
breakwater. Hence, this needs to be taken into consideration while studying the possible
locations for the liquid jetties, with regards to waterfront availability and operational safety.
Thus, it is inferred from the above discussion that it will be feasible to develop multiple
jetties in the harbour, considering the availability of waterfront.
Based on our understanding of the requirements of liquid terminal, we propose to identify
and examine alternative site locations based on the parameters explained in §6.1.2.
6.1.2 Key planninng parameters
For the alternative locations as stated above, the facility planning philosophy is based on
the following parameters:
• Separate berths for handling LNG and LPG/other liquids
• Commencement of LNG facility as FSRU based terminal and conversion to a
conventional LNG terminal in future
• Handling of liquids on existing general cargo berth using ship gears in initial stages and
gradually shifting operations to the dedicated liquid berth fitted with unloading arms
• Conveyance of cargo between jetty and back up area through pipelines
• Storage provision in the back up area considering parcel size required to be stored and
necessary cargo segregation
• Cost economics and safety in handling
• Berths are considered to be operational 7 days a week over 330 working days per year
(considering the cyclone prone location of Gopalpur Port), allowing 35 non- operational
days for maintenance and unforeseen reasons. Further, the berths will operate round-
the-clock i.e. 3 shifts of 8 hours each resulting in 24 hr/day working.
6.1.3 Principal guiding considerations for site selection
Key considerations guiding the process of studying the available options towards
identification of suitable sites for locating the jetties are as follows:
6.1.3.1 Tranquillity in the harbour
Given the nature of liquid cargo proposed to be handled at the port, it is of utmost necessity
to ensure that the location of the berth is at a tranquil location for safe operations. The
maximum allowable wave height being considered for assessment of tranquillity in the
various locations in the Gopalpur harbour is 1.0 m.
Gopalpur Ports Ltd. Development of Liquid Jetties at Gopalpur Port Pre- feasibility Study
Final Report
BMT Consultants India Page 59
The tranquillity at various locations in the Gopalpur Port harbour has been examined on
the basis of results of numerical model study1 carried out. An excerpt of the study i.e. results
of the downtime analysis at various locations are as shown below.
Figure 6-3: Wave extraction points
Results of the downtime analysis for the wave extraction (WE) points shown above is given
in the table below.
Table 6-1: Downtime at locations within Gopalpur harbour
Location Downtime (%) Downtime (hr/yr)
WE2 0.3 25.0
WE3 0.08 7.0
WE4 0.04 3.5
WE5 0.01 1.0
WE7 0 0.0
WE8 0 0.0
WE9 0 0.0
WE10 0.08 7.0
1 Wave climate and tranquillity study at Gopalpur Port by BMT Consultants (India) Pvt. Ltd., November 2017
Gopalpur Ports Ltd. Development of Liquid Jetties at Gopalpur Port Pre- feasibility Study
Final Report
BMT Consultants India Page 60
WE11 0 0.0
WE12 0.04 3.5
WE13 0.01 1.0
WE14 0 0.0
WE15 0 0.0
WE16 0 0.0
WE18 0.02 2.0
The results of the study indicate that all the potential locations in the harbour that are to be
examined for selection of location have negligible downtime and are thus, adequately
tranquil as required for the liquid handling operations.
6.1.3.2 Availability of depth/dredging requirements
Based on the assessment of functional requirements in §5.3, the proposed depth of -15.6
m CD in the harbour and channel in the current phase of development will be sufficient for
the vessels envisaged to be handled at the liquid terminal. GPL already has an Environment
and CRZ Clearance to handle bulk cargo with an approved depth of -15 m CD. However,
it is proposed that Capesize vessels will be handled for bulk cargo for which a depth of -18
m CD will be required at the berths, the channel and the turning basin, hence needing
additional dredging. This issue will be further examined and included in the EIA in detail.
It is important to note that a 25-30 m distance will be required to be maintained between
the dredge line and breakwater toe to ensure that the stability of the breakwater is not
affected. However, detailed studies will be required at a later stage to determine the exact
distance to be maintained from the dredge line for safety of the breakwater.
6.1.3.3 Safety zone
This parameter is specific to the LNG jetty, but it also affects location of other facilities in
its vicinity. An exclusive safety zone with at least 250 m radius at the time an LNG ship is
berthed at the jetty is to be maintained and the LNG jetty needs to be located accordingly.
The accurate safety distance to be maintained will have to be ascertained by carrying out
a QRA study. This radius where no other structure/operation allowed is measured from
centre of the manifold. Considering that the FSRU will be permanently moored at the LNG
jetty, it will be necessary to maintain this zone of safety all the time i.e. 24 x 7 without any
structure/operations in this area.
It is also necessary to check the proximity of the LNG jetty to existing approach channel
and turning basins to ensure there are no navigation risks.
6.1.3.4 Separation distance
The separation distance is also a particular requirement of the LNG jetty and is to be
considered for selecting the location of the jetty. A clear 500 m separation distance from
the centre of the manifold of LNG jetty to the centre of any other jetty structure is required
to be maintained to ensure safe operations.
Gopalpur Ports Ltd. Development of Liquid Jetties at Gopalpur Port Pre- feasibility Study
Final Report
BMT Consultants India Page 61
6.1.3.5 Accessibility to land and connectivity to back up areas
It is necessary to ensure that the jetty location is in proximity to its back up area, considering
that the cargo conveyance from jetty to storage will be through pipeline and this will have
implications on costs and operational convenience. It is also necessary that the location to
be developed be accessible from land, with road connectivity for movement of vehicles,
personnel and also to ensure availability of construction material as well as the utilities like
power, water, waste water etc.
6.1.3.6 Environmental considerations
Since all the locations under consideration are situated in the same harbour, all the sites
are similar with respect to environmental considerations. None of the sites are envisaged
to have any varying or additional environmental impacts that need to be taken into
cognizance at the site selection stage.
6.1.4 Assessment of potential jetty locations
In line with the above considerations, the following options are being examined for selecting
the most suitable locations for the jetties. Since the site selection for LNG facility
necessitates taking into cognizance the safety aspects, the identification of location for LNG
jetty is carried out first, followed by selection of location for the other liquids jetty.
6.1.4.1 LNG
The alternative locations for developing the LNG jetty are as shown in Figure 6-4.
Considering the requirement of a safety zone of 250 m radius from the manifold, the
alternative locations are-
• Location A: Outer arm of south breakwater
• Location B: Intermediate breakwater
• Location C: Inner arm of south breakwater
Gopalpur Ports Ltd. Development of Liquid Jetties at Gopalpur Port Pre- feasibility Study
Final Report
BMT Consultants India Page 62
Figure 6-4: Alternative locations for LNG jetty
Gopalpur Ports Ltd. Development of Liquid Jetties at Gopalpur Port Pre- feasibility Study
Final Report
BMT Consultants India Page 63
A broad based examination of the characteristics of each site location is undertaken and
discussed below.
Location A
Location A refers to the option along the outer arm of south breakwater. This location is
being studied, considering the future development of bulk berths along inner arm of south
breakwater. The annual downtime at locations along this length is in the range of 0.04-
0.08%, hence, is negligible. This location is also accessible by land, as the road/ utilities
can run from the landfall point along the breakwater length, upto the jetty.
With reference to Figure 6-4, it is important to note that the approach channel or turning
circle may possibly coincide with the 250 m radius safety zone required to be maintained
for the LNG jetty. In this case, there would be restrictions to movement/ manoeuvring of the
other incoming/ outgoing vessels when passing through this overlapping area. Hence, it is
necessary to ensure that the location of the jetty is selected such that it fulfils the
requirements of the safety zone as well as the separation distance from other infrastructure,
especially the proposed berths on the inner arm of the breakwater.
Since this location is farthest from the existing landside development and berth line at the
port (>1000 m), there are no potential issues such as operational conflicts or safety
concerns with respect to the existing infrastructure. Also, it will be possible to undertake
dredging at this location to match the proposed harbour depth of -15.5 m, hence, availability
of depth will also be fulfilled.
This location appears to be a favourable location for constructing the LNG jetty, and will be
compared with respect to the other options to finalise the most suitable location.
Location B
This option is proposed along the intermediate breakwater. This location is not expected to
be exposed to any wave disturbance, given the negligible downtime envisaged along this
zone. Since it is situated very close to the landfall point, accessibility by land and
construction of road/ utilities upto the jetty will be very convenient, as well as of least length
and cost, of all the options. Dredging at the location will ensure availability of required
depths for vessel handling.
With respect to the safety zone and separation distance, there may be possible conflicts if
the LNG jetty is proposed at this location. The waterfront along which the existing berths
are located, as well as the landside infrastructure, are in close vicinity (~500 m) to this
location. While the portion of the berth line coinciding with the safety zone for this location
is not developed till date, it is proposed that the existing berths will be extended in the near
future, upon ramp up in the cargo volumes. If the LNG jetty is constructed along the
intermediate breakwater, the extension of the general cargo berth will not be feasible,
considering the safety aspects. Also, the turning circle coincides with the safety zone if the
LNG jetty is along the intermediate breakwater, and this would result in restrictions to vessel
movement in the harbour.
Gopalpur Ports Ltd. Development of Liquid Jetties at Gopalpur Port Pre- feasibility Study
Final Report
BMT Consultants India Page 64
Also, since the landside area of the terminal and gate complex and terminal landside is in
close proximity to this location, there may be safety related issues considering the frequent
personnel and vehicular movements as well as the landside operational activities.
Based on the above discussions, the concept of developing the LNG jetty at this location
seems to have significant safety related issues. It is, therefore, not considered as a
favourable alternative for the LNG jetty.
Location C
The third alternative location under study for the LNG jetty in the Gopalpur harbour is along
the inner arm of the south breakwater. This alternative is being assessed for suitability
considering that this facility be developed at the given location instead of the dry bulk berths
proposed by GPL in the future.
The annual downtime at locations along this length is 0, hence this location is highly
advantageous in terms of availability of tranquillity. This location is also accessible by land,
as the road/ utilities can run from the landfall point along the breakwater length, upto the
jetty.
It is possible to locate the LNG jetty along this length such that the approach channel or
turning circle do not coincide with the 250 m radius safety zone required for the LNG jetty.
Locating the jetty at this site would also fulfil the requirement of the separation distance
from other infrastructure. However, if this location is chosen for development of the LNG
jetty, it would lead to restrictions to the future expansion of the marine infrastructure within
the harbour. While this alternative is mostly promising as a potential location for the LNG
jetty, it is not the most optimal solution, especially taking into account future plans and
scope of expansion in this harbour.
Having studied each of the three alternative options with regards to understanding their
salient features towards assessing their suitability as the preferred location for developing
the LNG facility, and also keeping in view the long term expansion plans of Gopalpur Port,
the location along the outer arm of the south breakwater emerges as the most suitable
alternative. QRA is required to be undertaken in the detailed feasibility stage to further
assess the suitability and finalise this location for development of the LNG jetty.
6.1.4.2 LPG and other liquids
The LNG jetty location is proposed along the outer arm of south breakwater (refer §6.1.4.1).
It is as shown in Figure 6-5.
Gopalpur Ports Ltd. Development of Liquid Jetties at Gopalpur Port Pre- feasibility Study
Final Report
BMT Consultants India Page 65
Figure 6-5: Jetty location for LPG and other liquids
Gopalpur Ports Ltd. Development of Liquid Jetties at Gopalpur Port Pre- feasibility Study
Final Report
BMT Consultants India Page 66
While there are general guidelines with respect to operational safety in handling of LPG
and certain hazardous/ explosive liquid chemicals, there are no specific requirements
(unlike LNG) to be considered while selecting a location for the jetty.
As explained in the previous section, the annual downtime at his location is negligible, thus
offering tranquillity for operations. The location is also accessible by land, and development
of road and utilities upto this location will be of short length and low cost. Since there are
no particular safety and separation related parameters to be followed for choosing a
location for this jetty, the proximity of terminal land side area and gate complex as well as
the turning circle on the marine side do not cause any safety related conflicts or operational/
navigational restrictions. Also, it will be possible to undertake dredging at this location to
match the proposed harbour depth of -15.5 m, hence, availability of depth will also be
fulfilled.
As per the above analysis, this location appears to be a favourable for constructing the jetty
for LPG and other liquids. It will be finalised following the QRA study.
6.1.4.3 Recommendation
Following an analysis of the site characteristics of potential locations within the harbour at
Gopalpur Port for the liquid jetties and their suitability with respect to the requirements of
the proposed infrastructure, it is proposed that the LNG jetty will be developed along the
outer arm of the south breakwater and the LPG and other liquid’s jetty will be developed
along the intermediate breakwater (refer Figure 6-6) and drawing no. BMT-1395-GPL-PFR-
DWG-003).
Figure 6-6: Proposed liquid jetty locations at Gopalpur Port
Gopalpur Ports Ltd. Development of Liquid Jetties at Gopalpur Port Pre- feasibility Study
Final Report
BMT Consultants India Page 67
6.2 Landside development
As per the current phase of development at Gopalpur Port, marine and landside
infrastructure are proposed as part of this phase and are under construction at present.
Accordingly, the land parcels available and suitable for back up area development are to
be identified and planned as per the requirements of the liquid handling facility.
As seen in Figure 6-7, the portion of the landside area behind the bulk and general cargo
berths, extending upto the railway corridor is earmarked as part of the back up area for the
current dry bulk terminal development. Hence, the land parcels available for liquid terminal
back up area development are those located to the east and west of the dry bulk back up
yard. This section identifies and defines the location, size and arrangement of the back up
yard for both the liquid jetties, based on the phase wise requirements. The facilities required
for cargo evacuation (including pipeline route) are also discussed.
6.2.1 Key considerations for back up area selection
• Area availability
On the basis of the requirements of the back up facility for each cargo, the area required
has been assessed as per the phases. While selecting a suitable land parcel to be
earmarked for development of the back up yard for a particular cargo, it will be necessary
to check the availability of adequate area (as per current and future development plans).
It is also important to check that the type of facility being set up at the location is not
conflicting with any existing land use/activities in the immediate vicinity.
• Pipeline connectivity- length, terrain, interfaces
An important criterion to be examined is the pipeline connectivity between the (i) jetty and
the storage facility in the back up yard and (ii) storage facility towards evacuation. It is also
essential to identify the pipeline route running between the jetty and landside facility, to
ensure it is an optimal alternative
The corridor availability for development of pipeline along the favoured route is to be
checked. In addition, it is preferred to develop a pipeline that has an alignment with lesser
bends, lower length, running along similar terrain throughout the corridor distance and
fewer interfaces which may interfere with the pipeline alignment owing to the land use at
the location.
• Operational convenience and safety
Given that the types of cargoes to be handled at the terminal will be hazardous, prone to
explosion etc., it is of utmost necessity that the aspects of operational convenience, control
and safety be taken into cognizance while planning the landside as well as the marine
infrastructure for this terminal.
• Expandability
Considering the cargo forecast and having identified the way forward for development of
the terminal in the coming years, it will be important to ensure that the scope of
Gopalpur Ports Ltd. Development of Liquid Jetties at Gopalpur Port Pre- feasibility Study
Final Report
BMT Consultants India Page 68
Considering the cargo forecast and having identified the way forward for development of
the terminal in the coming years, it will be important to ensure that the scope of
expandability be checked when selecting the back up locations and planning for the
development of the facility.
6.2.2 Assessment of back up area locations
6.2.2.1 LNG
The landside requirements for the LNG back up yard have been assessed in §5.6.1.1. No
storage or process facilities are to be provided in this phase. The area will have to be
developed to house offices, supporting buildings for the facility and evacuation related
infrastructure. Accordingly, in the current phase of FSRU based LNG terminal, an area of
5-10 ha will be required.
In the future phase when the LNG terminal is converted from FSRU based facility to a
conventional type of LNG terminal with onshore facilities, the back up area will house the
process side facilities, storage tanks and the evacuation facilities i.e. truck loading bays,
pipelines infrastructure etc. The area requirement in this phase is in the range of 40 ha.
Considering the location of the LNG jetty, the most suitable location for developing the back
up area taking into account the area availability and pipeline routing is the location to the
west of the coal stockyards and the Penna Cements facility (refer Figure 6-7). Also, given
the location of this area, it will be possible to ensure the safety aspects with respect to
surrounding land use and activities are also taken care of. Considering the distance of this
area from the other facilities at the port, it will be possible to locate the tank farms such that
the safety related criteria of the blast radius, heat radiation effects and other necessary
parameters are adequately fulfilled.
40 ha area, as per the functional requirements for development of an onshore conventional
type of LNG terminal, is available at this location. It is to be noted that the ground level will
have to be raised to +8.5 m CD. Considering that a portion of the back up yard will be
developed on the area formed by the beach build up, wave runoff will be suitably managed.
The pipeline from the jetty will run along the breakwater and reach the back up yard, with
almost no interfaces. The approx. length of this pipeline will be ~3 km.
Also, it will be possible to plan and align the back up area such that the arrangement of
various facilities within the yard alongwith routing of pipeline for evacuation can be planned
as required. Appropriate area will also be allocated for green belt development. In the
future, tanks will be provided for storage of cargo. The LNG cargo is proposed to be
evacuated through pipeline as well as trucks, as explained in §5.6.1.1. Truck loading zone
with loading bays and waiting/parking will be provided. The pipeline routing will be planned
so as to transport the cargo upto the end users’ facilities. The alignment of pipeline for
users outside the GPL boundary/to offload to the grid from the storage area will be along
the port road (refer Figure 6-7).
It is also envisaged that in the future, the users based in Tata Steel Special Economic Zone
Ltd. (TSSEZ) will be potential LNG customers. At this stage, it is proposed that a direct
pipeline will be provided from the back up yard to the customers. The alignment is as shown
in Figure 6-7 (reference drawing no. BMT-1395-GPL-PFR-DWG-005).
Gopalpur Ports Ltd. Development of Liquid Jetties at Gopalpur Port Pre- feasibility Study
Final Report
BMT Consultants India Page 69
The location is recommended based on the findings of the pre- feasibility study. The exact
location will have to be finalised after the QRA study in the Front-End Engineering Design
(FEED) stage. Further detailing regarding the suitability of arrangement of facilities within
the back up yard will be confirmed after the Hazard Identification (HAZID) and Hazard and
Operability (HAZOP) studies have been carried out, at a later stage.
The area wise break up of the various zones in the LNG terminal to be developed on the
landside is as follows:
Table 6-2: Land use area break up for LNG terminal
Sr. No. Land use Area in ha
1 Storage and allied facilities 16
2 Truck loading facilities, pump house 7.0
3 Green belt 5
4 Other facilities 12.5
Total 40.5
Gopalpur Ports Ltd. Development of Liquid Jetties at Gopalpur Port Pre- feasibility Study
Final Report
BMT Consultants India Page 70
Figure 6-7: LNG back up yard facility
Gopalpur Ports Ltd. Development of Liquid Jetties at Gopalpur Port Pre- feasibility Study
Final Report
BMT Consultants India Page 71
6.2.2.2 LPG and other liquids
As discussed previously, at the stage of commencement of operations, small volumes of
other liquids are envisaged which can be handled through ship gears at the general cargo
berth. Further on, the liquid jetty along the intermediate breakwater will be developed to
handle increased volumes.
Accordingly, considering the location of the liquid handling jetty (on the eastern side of the
facility), the land parcel available such that it is accessible from the jetty, is the area situated
in the northeastern portion of the terminal. Taking into account the land availability to the
north of the railway corridor, this area is also considered suitable as the back up area for
liquid handling. Accordingly, areas at two locations (i) area to the north of the railway
corridor (ii) area between the railway corridor and the warehouse will be utilised for
developing the landside facilities for liquids (refer Figure 6-8).
Figure 6-8: Area availability for development of LPG/other liquid terminal
Gopalpur Ports Ltd. Development of Liquid Jetties at Gopalpur Port Pre- feasibility Study
Final Report
BMT Consultants India Page 72
The back up areas will house the storage tanks and the evacuation facilities i.e. the truck
loading zone, pipeline connecting to the end users/ grid as well pipeline running upto the
railway for evacuation through tank cars. As per the assessment of area requirement
discussed in §5.6.1.2, an area of 15-20 ha will be required for the back up facility for LPG
and other liquids. The back up yard to the north of the railway corridor i.e. area 1 has an
area of 11 ha and the back up area 2 (to the north of the warehouse) has an area of 9.5
ha. As per the requirements, the back up yards are being proposed so as to develop
separate facilities for LPG and the other liquids, considering the different cargo
characteristics and safety aspects. The land parcel on the northern side of the back up area
2 is available for expansion of the liquid terminal in the future. Appropriate area will also be
allocated for green belt development in both the terminal areas.
In the initial phase, when the liquid tankers are being handled at the existing general cargo
berth, a pipeline will be developed from that berth upto the back up area for cargo
conveyance. Thereafter, upon development of the dedicated liquid berth, the pipeline will
be augmented so that it connects from the jetty at the intermediate breakwater upto the
storage tanks in both, back up areas 1 and 2 (refer Figure 6-9). The length of the pipeline
from the jetty to the back up area 1 will be approx. 1.5 km and upto back up area 2 will be
in the range of 0.7 km. Pipeline connectivity to end users’ properties will be provided as per
the requirements from these storage yards. Suitable design and provision will be made for
underground pipe corridor at the junctions where the pipeline crosses the railway line and/
or railway loading areas.
The area wise break up of the various zones in the liquid terminal to be developed on the
landside is as follows:
Table 6-3: Land use area break up for LPG and other liquids’ terminal
Sr. No. Land use Area in ha
1 Storage and allied facilities 8
2 Truck loading facilities, pump house 2.5
3 Green belt 2
4 Other facilities 7.5
Total 20
Gopalpur Ports Ltd. Development of Liquid Jetties at Gopalpur Port Pre- feasibility Study
Final Report
BMT Consultants India Page 73
Figure 6-9: LPG and other liquids back up yard facility
Gopalpur Ports Ltd. Development of Liquid Jetties at Gopalpur Port Pre- feasibility Study
Final Report
BMT Consultants India Page 74
7 Proposed Infrastructure
The proposed project is the expansion phase of GPL aimed at diversifying the cargo spread
by creating facilities to handle liquids including LNG, LPG, POL, edible oil, chemicals etc.
The details of proposed facilities are described in Chapter 5.
7.1 Project site and surroundings
Gopalpur Port is located near the village Arjeepalli in the Ganjam District of Odisha midway
between the Gopalpur town and Rushikulya estuary (Figure 2-1). The land area of 393
acres (160 ha) is in possession of GPL and and have been assured of an additional 353.7
Ha for port expansion by the Govt. of Odisha as per the terms of GPL’s Concession
Agreement with the Govt of Odisha. This includes an additional area of 119 acres (48 ha),
which is in the process of being transferred to GPL from the GoO. This land area in
possession of GPL is a narrow coastal strip along the Bay of Bengal with a maximum width
of 800 m. Further 615 acres (250 ha) is earmarked for GPL and will be transferred as per
the conditions of the CA. Additional accreted area of 140 acres (56.5 ha) will also be
available with GPL. Accordingly, GPL will have under possession a total area of about
1,267 acres i.e. 512.75 ha. The Orissa Sands Complex (OSCOM), a unit of IREL, which is
under the administrative control of Department of Atomic Energy (DAE), Government of
India (GoI), adjoins the south-western boundary of GPL. TSSEZ is located about 2 km to
the north-west of the Port.
The OSCOM is involved in beach sand mining and mineral separation activity producing
ilmenite and other associated minerals. The sand after extraction of the heavy minerals is
used for re-filling the mined voids. Hence, the area at Gopalpur Port, where once sand was
mined, is uneven and undulating with sparse vegetation except for salt tolerant shrubs and
creepers. Trees like casurina, cashew nut, palm, coconut etc. grow towards the landward
periphery and inland.
The port is located in a non-urbanized area adjoining villages, agricultural tracks, grazing
sites and non-productive lands. Hence, the economy of the region is mainly agro-based
with majority of people engaged in agriculture which is supported by irrigation canals.
Rotation of crops is a common practice in the District. The important crops grown in the
area are rice, ragi, jower, bajra, maize, arhar, mung, biri, groundnut, jute, cotton, sugarcane
etc. Fishing is also an important occupation after agriculture in the region with freshwater
fishing mainly concentrated in the in the Rushikulya River and nearby dams while marine
catches are generally from nearshore coastal zone using small fishing vessels.
As per Census data, there are 60 villages within 10 km of the GPL with a total population
of about 74,000 and literacy rate of 46%. Most villages have access to primary schools and
primary medical facilities. Dug wells and hand pumps are major sources of potable water
though some villages are provided water through tankers.
The port is connected to the NH 5 via a 7 km road and to Howrah Chennai railway line
through a siding of OSCOM. Nearest airport is at Bhubaneshwar which is 150 km from
GPL.
Gopalpur Ports Ltd. Development of Liquid Jetties at Gopalpur Port Pre- feasibility Study
Final Report
BMT Consultants India Page 75
7.2 Utilities
Major utilities include power, water (potable water, service water, firewater) and diesel oil
for the proposed port expansion.
7.2.1 Power requirement
The present average power consumption of the Port is about 11 KV/1000 KVA which is
mainly met from 132 KV main at Chhatrapur grid substation of the Southern Electricity
Supply Company of Odisha (SOUTHCO) Ltd. The port has its own substation with two
33/11 KV transformers.
The power for proposed expansion is estimated at 33 KV and will also be met through the
SOUTHCO grid. It is also proposed to install diesel generator of adequate capacity to meet
emergency power requirements after the expansion.
7.2.2 Water requirement
The water requirement is envisaged to increase incrementally as the proposed expansion
is underway, with the ultimate requirement at the end of the expansion estimated at 1.4
million lit/day (MLD). Initially this requirement will be met through local supplies as is done
at present. Also, there are some industries in the vicinity that are examining the alternative
of a desalination plant, and GPL is under discussion with these industries for sourcing water
from their plant to serve the augmented water requirement of the port in the future.
7.3 Wastes and management
The major wastes at ports during day to day operations include those generated at the
land-based facilities and those produced by ships at berths. These wastes can be liquid,
solid and hazardous.
7.3.1 Liquid wastes
7.3.1.1 Domestic wastewater
Domestic wastewater is the major contributor to liquid wastes at ports. At present, domestic
wastewater at the port is treated in septic tank – soak pit arrangement. Due to low traffic of
ships at the port this arrangement of sewage disposal is quite adequate. With the proposed
expansion the traffic of ships would increase, however, the workers which constitute the
major component, are unlikely to increase substantially since liquids will be unloaded
through pipelines and transferred to storage tanks. However, as more land is made
available to GPL by the GoO and port operations increase, provision will be made for a
sewage treatment plant (STP) and treated wastewater will be used for gardening and other
secondary uses such as dust suppression, floor washing etc.
The amount of sewage generated on a ship depends on the number of persons on board
and the type of system used. This volume is estimated to be in 0.04-0.45 m3/day per person
out of which 0.01-0.06 m3 is probably black water and the balance grey or galley water. As
per Annex-IV of MARPOL 73/78 which came into force from September 2008, it is
mandatory for ships to treat and disinfect sewage, store it in the holding tanks and release
Gopalpur Ports Ltd. Development of Liquid Jetties at Gopalpur Port Pre- feasibility Study
Final Report
BMT Consultants India Page 76
it at a distance of more than 3 nm from the nearest land, while, sewage if untreated can be
released only beyond 12 nautical miles. In view of this it will be ensured that the ocean
going ships visiting the port have sewage storing tanks on board and that sewage is not
released in the port waters.
7.3.1.2 Floor washing and other miscellaneous wastes
Small volume of wastewater will be generated from floor washings and other miscellaneous
uses. This wastewater after allowing settling will be mixed with water used for dust
suppression etc.
7.3.2 Solid wastes
The solid waste generated at ports includes food waste from canteen, paper, plastic
discards, cardboard boxes, empty drums, construction debris etc. This waste is segregated
into biodegradable and non-biodegradable wastes and stored in separate containers. The
stored waste is handed over to vendors approved by the Odisha State Pollution control
Board (OSPCB) for disposal/recycling as per pre-decided schedule following the Solid
Waste Management Rules, 2016.
The same system of solid waste collection, segregation and disposal will be adopted for
shore-based solid waste generation for the Port expansion.
Solid waste generated by ships includes food waste, domestic waste, plastics, incinerator
ash, paper, card board etc. The food waste which generally varies between 0.001 and
0.002 m3/person/day for cargo ships is permitted to be disposed at sea (but not in port
waters) after being comminuted, shredded or passed through grinder or collected in bins
and delivered to Port Reception Facility (PRF) as per Annexure-V of MARPOL 73/78.
Annexure-V of MARPOL 73/78 prohibits disposal of other solid wastes such as plastics,
incineration ash, paper etc to sea and is to be stored on board and delivered to PRF.
7.3.3 Oily wastes
Shore-based facilities at the port generate small volume (940 lit/yr) of oily waste such as
spent oil, oily sludge, tank bottoms, oily rags etc. This waste is stored in covered containers
and given to OSPCB approved recyclers as per the Hazardous and Other Wastes
(Management and Transboundary Movement) Rules, 2016. The same system will continue
in future as well.
Ships on the contrary generate large volume of oily wastes such as the following:
• Bilge, a mixture of liquids such as water oil, sludge and chemicals collected in the bilge
of a ship. The bilge volume varies depending on the type and size of the ship but is
roughly 0.3 m3/day.
• Oily residual waste resulting from fuel consumption generated at a rate of 0.0-0.03 m3/t
of fuel (marine gas oil; heavy fuel oil).
• Oil tank washings popularly termed as slops, are generated when oil cargo tanks are
cleaned with water and hence contain oil, water and dispersants. They are generally
stored in settling tanks. Annexure-I of MARPOL 73/78 allows release of water
Gopalpur Ports Ltd. Development of Liquid Jetties at Gopalpur Port Pre- feasibility Study
Final Report
BMT Consultants India Page 77
separated from oil to sea provided oil content of water is less than 15 ppm and some
other conditions are met. However, this effluent cannot be released in the port area.
Thus, the oily waste generated on board the ships cannot be released to the sea and hence
is to be stored on board and evacuated to PRF. GPL does not have PRF at present. Hence,
ships will have to discharge wastes such as oil, plastics, incineration ash, paper etc to next
port of call where such facilities are available. However, there is arrangement at the port to
receive such wastes in an emergency situation.
7.3.4 Wastes generated at FSRU
FSRU will be at berth on long-term basis and will generate wastes like any normal ship.
The sewage generated on board will be treated in on-board sewage treatment facility and
the effluent meeting the OSPCB will be released to the sea. Food waste and other solid
waste will be segregated and there will be arrangement to evacuate this waste on daily
basis or as required. Similarly, the oily waste also will be unloaded in closed containers and
given to authorized vendors.
In addition, FSRU will be using seawater for onboard gasification of LNG. The return
seawater with temperature lower than that of ambient seawater will be released back to the
sea. This effluent will meet the General Standards for Discharge of Environmental
Pollutants Part – A: Effluents (Marine Coastal Areas) as per the Environment Protection
Act, 1986.
Accordingly, considering that the system on the FSRU is of open loop type, the volume of
seawater required to vaporize LNG will be approx. 15,000 m3/hr and equivalent volume will
be released to the sea at a temperature that is about 7°C below that of the ambient
seawater (cold water effluent). Seawater intake and effluent release are integral to the
design and construction of FSRU and is directly withdrawn/released from the ship’s hull.
7.4 Storm water drainage
Storm water drainage will be planned along roads with suitable catch drains. Surface runoff
will be discharged into the proposed roadside drains (on both sides of the road) and
subsequently channelled to retention ponds for each sub-catchment prior discharging into
the existing natural drain connecting the sea. Closed concrete rectangular drain system will
be considered for the roadside drain for ease of maintenance and more effective use of
land as it serves as a pedestrian footpath.
7.5 Oil Spill Contingency Plan
The port has an Oil Spill Contingency Plan as required under the National Oil Spill Disaster
Contingency Plan and is in the process of augmenting oil spill combating equipment to
meet Tier-I response. The present inventory includes fence boom, oil skimmer, Oil Spill
Dispersants (OSD), absorbent sheets, absorbent booms, portable OSD applicator, shovels,
scrapers, buckets, rakes, rope, line, whistles, first aid material, chemical suit, chemical
resistant nitrile gloves, gumboots, helmet with eye cover etc.
The port has tugs, mooring launches and storage barge to assist in oil spill combating
should an oil spill occur.
Gopalpur Ports Ltd. Development of Liquid Jetties at Gopalpur Port Pre- feasibility Study
Final Report
BMT Consultants India Page 78
The present Oil Spill Contingency Plan will be suitably amended to include the port
expansion to handle liquids and additional equipment will be procured as recommended in
the revised Plan.
7.6 Disaster Management Plan
Based on the seismic map of India illustrated in Figure 7-1 the Ganjam District falls in the
Low Risk Zone and hence the probability of occurrence of earthquake is very low.
Figure 7-1: Seismic map of India
However, the region is highly prone to cyclones. The wind and cyclone map of India (Figure
7-2) categorizes the coastal belt of Odisha under Very High Damage Risk Zone.
Cyclonic storms from Bay of Bengal hitting the Odisha coast is common and some of them
have crossed the coast between Gopalpur and Puri causing widespread devastation. A
very severe cyclone – Phailin crossed the Gopalpur coast on October 12, 2013 resulting in
catastrophic destruction including the infrastructure of the Gopalpur Port. The south
breakwater was considerably damaged and the large armour stones were displaced into
the channel and the manoeuvring area. The support infrastructure like electricity, water
supply, roads, shore line and banks suffered unprecedented devastation.
Gopalpur Ports Ltd. Development of Liquid Jetties at Gopalpur Port Pre- feasibility Study
Final Report
BMT Consultants India Page 79
Figure 7-2: Cyclone and wind zones in India
Coastal strip of the Ganjam District was also influenced by the Tsunami of December 2004
through the Gopalpur Port is not vulnerable to flooding. To respond to such natural
calamities and man-made accidents, GPL has a well-structured Disaster Management
Plan. The Plan is divided in 3 main parts and relevant sub-sections as follows:
• Part-I: General- it includes introduction; vulnerability assessment and risk analysis;
preventive measures, mainstreaming DM concerns into development plans/
programmes/projects; preparedness measures; response; partnership with other stake
holders; financial arrangements.
• Part-II: Disaster specific action plan deals with cyclone; tsunami; oil spill disaster;
berths, breakwater collapse etc; collision between vessels resulting in fire/ explosion/
sinking of vessel; explosion on board vessel at berth.
• Part-III: Cross-cutting issues cover review and updation of plans; coordination and
implementation.
In view of the change in the cargo mix, particularly due to the proposal to handle LNG, LPG,
POL and hazardous chemicals, these Plans will be modified as required.
7.6.1 Green belt
An area of about 7 ha out of 60.5 ha (for development of liquid terminal back up areas)
available with GPL will be developed as green belt. The plan for green belt development
will be made and included in the EIA. Trees will be planted lining the connecting road and
around vehicle parking areas, terminal building and in other available sites. Selection of the
plant species will be based on their adaptability to the existing geographical conditions and
the vegetation composition of the region. As far as possible native plant species will be
Gopalpur Ports Ltd. Development of Liquid Jetties at Gopalpur Port Pre- feasibility Study
Final Report
BMT Consultants India Page 80
selected, which have good ornamental value and are fast growing with excellent canopy
cover.
Gopalpur Ports Ltd. Development of Liquid Jetties at Gopalpur Port Pre- feasibility Study
Final Report
BMT Consultants India Page 81
8 Rehabilitation and Resettlement
The land in possession of GPL under the CA with the GoO is a narrow coastal strip free
from human settlements. The land is unproductive waste land unfit for agriculture. Hence,
there are no rehabilitation and resettlement issues.
Gopalpur Ports Ltd. Development of Liquid Jetties at Gopalpur Port Pre- feasibility Study
Final Report
BMT Consultants India Page 82
9 Project Schedule and Cost Estimates
The proposed project envisages expansion of the port to handle liquid cargo. It is proposed
to commence the construction within 6-8 months after obtaining all approvals,
environmental and statutory clearances, whichever is later. The expansion project
consisting of development of the LNG based FSRU terminal and the facility for LPG and
other liquids is estimated to cost about INR 1,300 Crore. Details of project schedule will be
included in the EIA.
Gopalpur Ports Ltd. Development of Liquid Jetties at Gopalpur Port Pre- feasibility Study
Final Report
BMT Consultants India Page 83
10 Financial and Social Benefits
The coastal strip of the Ganjam District is economically underdeveloped with agriculture
and fishing as the major occupation in coastal villages. The proposed port expansion is
expected to promote employment opportunities during the construction and operational
phases of the expansion. During construction the labour will be sourced from nearby
villages and during operation there will be requirement of engaging contractual services for
a variety of unskilled jobs such as solid waste segregation and lifting, sanitation, gardening
and other ancillary services.
Many industries from TSSEZ located about 2 km from the port and other industries in the
region will use the port facilities for their import and export cargo. This will also generate
considerable additional indirect employment and improvement in infrastructure such as
roads, shops and medical facilities.
Gopalpur Ports Ltd. Development of Liquid Jetties at Gopalpur Port Pre- feasibility Study
Final Report
BMT Consultants India Page 84
Annexure A: Drawings