23
GOHFN WOLF ATTORNEYS AT LAW JULIE D. KOHLER Please Reply To: Bridgeport Writer's Direct Dial: (203)337-4157 E-Mail: [email protected] November 12, 2014 Attorney Melanie Bachman Acting Executive Director Connecticut Siting Council Ten Franklin Square New Britain, CT 06501 Re: Notice of Exempt Modification Northeast Utilities (CL&P)/T-Mobile co -location Site ID CT11085C 1 Country Club Road, Woodbridge CT Dear Attorney Bachman: This office represents T -Mobile Northeast LLC ("T -Mobile") and has been retained to file exempt modification filings with the Connecticut Siting Council on its behalf. In this case, Northeast Utilities/Connecticut Light and Power ("CL&P") owns the existing transmissions tower (structure # 240926) and related facility at 1 Country Club Road Woodbridge Connecticut (latitude 41.318007/longitude -73.008775). T -Mobile intends to add three (3) antennas with and related equipment at this existing telecommunications facility in Woodbridge ("Woodbridge Facility"). Please accept this letter as notification, pursuant to R.C.S.A. §16-50j-73, of construction which constitutes an exempt modification pursuant to R.C.S.A. § 16 -50j -72(b)(2). In accordance with R. C.S.A. § 16-50j-73, a copy of this letter is being sent to the Woodbridge First Selectman Ellen Scalettar and the property owner, Northeast Utilities/CL&P. Please also see the letter of authorization from Northeast Utilities attached hereto as Exhibit A. The existing Woodbridge Facility consists of a 160.5 foot transmission tower. T - Mobile plans to add three (3) antennas on pipe mounts at a centerline of 148 feet. T - Mobile will remove three (3) TMAs (tower mounted amplifiers) from its array at the 158 foot centerline, and install a cabinet and three (3) RRUs (remote radio units) on a proposed H-frame. Finally, T -Mobile will install coax cable and reuse existing coax cable. (See the plans revised to August 8, 2014 attached hereto as Exhibit B). The existing Woodbridge Facility is structurally capable of supporting T -Mobile's proposed modifications, as indicated in the structural analysis dated September 29, 2014, and attached hereto as Exhibit C. T -Mobile last sought to modify this facility in EM-T -MOBILE -167-100909. I I IS BROAD STREET 158 DBaR Htt[, Averrua 32O POST ROAD WHST 6S~ ORANGE CENTER ROAD P.O. Box 1821 DANBURY, GT O6HIO WESTPORT, CT 06880 ORANGE, CT OC~~~ BRIDGEPORT, CI' 06601-1821 'I~r,: (203) 7922771 TEL: (203) 222-1034 Tom.:-(203) 298-4066 '[~L: (203) 368-0211 Fax: (203) 791-8149 Fpx: (203) 227-1373 Fax: (203) 298-4068 Fnx: (203) 3949901

GOHFN WOLF - Connecticut

  • Upload
    others

  • View
    2

  • Download
    0

Embed Size (px)

Citation preview

GOHFNWOLFATTORNEYS AT LAW

JULIE D. KOHLER

Please Reply To: BridgeportWriter's Direct Dial: (203) 337-4157E-Mail: [email protected]

November 12, 2014

Attorney Melanie BachmanActing Executive DirectorConnecticut Siting CouncilTen Franklin SquareNew Britain, CT 06501

Re: Notice of Exempt ModificationNortheast Utilities (CL&P)/T-Mobile co-locationSite ID CT11085C1 Country Club Road, Woodbridge CT

Dear Attorney Bachman:

This office represents T-Mobile Northeast LLC ("T-Mobile") and has beenretained to file exempt modification filings with the Connecticut Siting Council on itsbehalf.

In this case, Northeast Utilities/Connecticut Light and Power ("CL&P") owns theexisting transmissions tower (structure # 240926) and related facility at 1 Country ClubRoad Woodbridge Connecticut (latitude 41.318007/longitude -73.008775). T-Mobileintends to add three (3) antennas with and related equipment at this existingtelecommunications facility in Woodbridge ("Woodbridge Facility"). Please accept thisletter as notification, pursuant to R.C.S.A. §16-50j-73, of construction which constitutesan exempt modification pursuant to R.C.S.A. § 16-50j-72(b)(2). In accordance with R.C.S.A. § 16-50j-73, a copy of this letter is being sent to the Woodbridge First SelectmanEllen Scalettar and the property owner, Northeast Utilities/CL&P. Please also see theletter of authorization from Northeast Utilities attached hereto as Exhibit A.

The existing Woodbridge Facility consists of a 160.5 foot transmission tower. T-Mobile plans to add three (3) antennas on pipe mounts at a centerline of 148 feet. T-Mobile will remove three (3) TMAs (tower mounted amplifiers) from its array at the 158foot centerline, and install a cabinet and three (3) RRUs (remote radio units) on aproposed H-frame. Finally, T-Mobile will install coax cable and reuse existing coaxcable. (See the plans revised to August 8, 2014 attached hereto as Exhibit B). Theexisting Woodbridge Facility is structurally capable of supporting T-Mobile's proposedmodifications, as indicated in the structural analysis dated September 29, 2014, andattached hereto as Exhibit C.

T-Mobile last sought to modify this facility in EM-T-MOBILE-167-100909.

I I IS BROAD STREET 158 DBaR Htt[, Averrua 32O POST ROAD WHST 6S~ ORANGE CENTER ROAD

P.O. Box 1821 DANBURY, GT O6HIO WESTPORT, CT 06880 ORANGE, CT OC~~~

BRIDGEPORT, CI' 06601-1821 'I~r,: (203) 7922771 TEL: (203) 222-1034 Tom.:-(203) 298-4066'[~L: (203) 368-0211 Fax: (203) 791-8149 Fpx: (203) 227-1373 Fax: (203) 298-4068Fnx: (203) 3949901

GOH~NWOLF

November 12, 2014~~~:~ CT11085CT tiNNE I'S AT LAN

Page 2

The planned modifications to the Woodbridge Facility fall squarely within thoseactivities explicitly provided for in R.C.S.A. § 16-50j-72(b)(2).

1 . The proposed modification will not increase the height of the tower. T-Mobile's existing antennas are at 158 feet; proposed additional antennas will beinstalled below those antennas at a centerline of 148 feet. The enclosed tower drawingconfirms that the proposed modification will not increase the height of the tower.

2 . The proposed modifications will not require an extension on the siteboundaries or lease area, as depicted on Sheet 2 of Exhibit B. T-Mobile's equipmentwill be located entirely within the existing compound area.

3 . The proposed modification to the Facility will not increase the noise levelsat the existing facility by six decibels or more.

4 . The operation of the replacement antennas and equipment will notincrease the total radio frequency (RF) power density, measured at the base of thetower, to a level at or above the applicable standard. According to a Radio FrequencyEmissions Analysis Report prepared by EBI Consulting dated November 12, 2014, T-Mobile's operations would add 5.77% of the FCC Standard. Therefore, the calculated"worst case" power density for the planned combined operation at the site including allof the proposed antennas would be 5.77% of the FCC Standard as calculated for amixed frequency site as evidenced by the engineering exhibit attached hereto as

Exhibit D.

For the foregoing reasons, T-Mobile respectfully submits that the replacementantennas and equipment at the Woodbridge Facility constitutes an exempt modificationunder R.C.S.A. § 16-50j-72(b)(2). Upon acknowledgement of this exempt modification,T-Mobile shall commence construction approximately sixty days from the receipt of theCouncil's decision.

Sincerely,

(~,~.~ ___J ,Julie D. Kohler

cc: Woodbridge First Selectman Ellen ScalettarNortheast UtilitiesSheldon Freincle, NSS

~- Northeast~//I1~~~ Utilities System

Mr. Mark RichardT-Mobile35 Griffin Rd.Bloomfield, CT 06002

56 Prospect Street, Hanford, CT 06103

Northeast Utilities Service CompanyP.O. Bog 270Hartford, CT 06141-0270(203)665-5000

October 30, 2014

RE: T-Mobile Antenna Site, CT-17 085C, 1 Country Club Rd, Woodbridge CT, structure 24092.

Dear Mr. Richard:

Based on our reviews of the site drawings, the structural analysis provided by CentekEngineering and, and the foundation analyses performed by Centek Engineering, we havereviewed for acceptance this modification

Since there are no outstanding structural or site related issues to resolve at this time,construction at these locations may begin as soon as scheduling allows. You may contact Mr.O'Brien (860-665-6987); once the lease issues are secured you may then contact Mr. JohnLandry directly (860-665-5425) to begin the construction arrangements

S' re ,

obert GrayTransmission Line Engineering

Ref: 14025.013 - CT11085C Structural Analysis RevO 14-09-29.pdfCT11085C-L700-CD-V2. pdf

_ ` a f

~~, ~ ,~ s ~~~E ~~•. ~ ~ ~ ~ '§.

..~'~ - ~~ds,;~; _ . -

1 ry= ~ ~~

i ~ .;. :t' L~ _~

~~[~`~'il~l.[~

a .e.~~ ~ ~ ' ~ __ A

~, ~ l

~ ~ r _ _ J ~

'7, i,~~ ••~ -_ y — —°i~~ if ~.~ Jc ~ - ~~~

1~ 1~~ .~`i_

_ ..

Uf ~ ' ~~ !~.,~ ~~~~ ~, ~ ~~ ,

~~~~- s ~.~,~~

~~ ~

`~ ~- '~ '~~' ~ ~ ~ ~ SITE LOCATION

r~ _ ~,

~~i~ ~ (E) GOLF CART PATH ~I ~` ~ u

w -~ -

..~, ~ ~ -

~.; ~ , ~ ,S

~t~~

~,— S 7

CONFIGURATION

OVERALL SITE PLAN 1

~o~ UN.T.s. LE-1

SUBMITTALS LEASE EXHIBITLE REV A os.o~.~a

NORTHEAST SITE SOLUTIONSSITE NUMBER: 54 MAIN STREET, UNIT 3

LE REV A 08.08.14 TLANTIS CT11085C STURBRIDGE, MA 01566~ (508) 434-5237

GROUP SITE NAME: FOR

1340 Centre Street WOODBRIDGE/ WC X58/ RACEBSuite 212

T-MOBILE NORTHEAST, LLC

Newton, MA 02459 SITE ADDRESS:

g OOMF ELD, CST 060 2HOffice: 617-965-0789

1 COUNTRY CLUB RD, OFFICE: (860) 692-7100- ......................-- ---.. WOODBRIDGE, CT 06524

Fax: 617-213-5056 FAX: (860) 692-7159

DRAWN BY: FG CHECKED BY:SM PAGE1 OF4

14, ~,

(E) 160' -6" HIGH TENSION POWERTRANSMISSION TOWER ST24092B

(E) BRUSH `~(E) GSM!UMTS QUAD POLE ANTENNA 2 jON (E) PIPE MOUNT ~~ ~

j (TYP. 1/SECTOR. TOTAL OF 3)~ ELEV : 158't (AGL)

~~ (P) COMMSCOPE DUAL POLE ANTENNA'~J~~ ~~('-~JJJ~~~ ~(E) TRANSFORMER ON (P) PIPE MOUNT

~ ~ i~ (TYP. t/SECTOR, TOTAL OF 3)

~-, 3 1 / (P) (3) RRUs ON (P) H-FRAME ELEV : 148't (AGL)

LEASE AREA 20'X2D' ~ ,L~ ~- ;~' ~ i ~

--..

J I

(E) S' HIGH i ~ j GAMS ~ N~TN 280'STOCKADE~i i /FENCE

~~i Vii" ipN

O ~O (E) HIGH TENSION POW RO ~(J TRANSMISSION TOWE

- --------- ST24092A O Oi ~ --------- O O

(E) TELCO i i O ODEMARC i i

i i 4i ~~ ~ ii i /

------------20, - --- -------' ~ m/ ' f 9

~, I ~~a(P) C6) 7/8" COAX CABLES / / / ~~2yy(E) (12) 7/8" COAX CABLES s

FOR EQUIPMENT (E) UNDERGROUND -~ ~ QCOAX CABLE

CONFIGURATION DUCTBANK TREtdCH jSEE PAGE 3 ~

j

~(E) ACCESS (E) 8' HIGH STOCKADEDRIVEWAY FENCE

LE-4

ALL EQUIPMENT LOCATIONS ARE APPROXIMATE AND ARESUBJECT TO APPROVAL BY LESSEE/LICENSEE'SSTRUCTURAL & RF ENGINEERS. LOCATIONS OF POWER &TELEPHONE FACILITIES ARE SUBJECT TO APPROVAL BYUTILIN COMPANIES.

SITE PLAN 1N.T.s. LE-2

CONFIGURATION

SUBMITTALS LEASE EXHIBITLE REV A aa.a~.ia

NORTHEAST SITE SOLUTIONSSITE NUMBER: 54 MAIN STREET, UNIT 3

LE REV A 08.08.14 TLANTIS CT11085C STURBRIDGE, MA 01566

GROUP SITE NAME: (508) 434-5237

FOR

_____ 1340 Centre Street WOODBRIDGE/ WC X58/ RACEB T-MOBILE NORTHEAST, LLCSuite 212

Newton, MA 02459 SITE ADDRESS: 35 GRIFFIN ROAD SOUTH

1 COUNTRY CLUB RD, BLOOMFIELD, CTosoo2Office: 617-965-0789

WOODBRIDGE, CT 06524 OFFICE: (860) 692-7100

Fax: 617-213-5056 FAX: (860) 692-7159

DRAWN BY: FG CHECKED BY:SM PAGE 20F 4

LEASE AREA 20'X20'

- r --~-------------- -------------------------- ----i

(E) TRANSFORMER

i (P) (3) RRUs ON (P) H-FRAMEii

i

(E) UMTS 6102 GABINET

(E) 6'-0"X10'-0" CONCRETE PAD

M~

(E) RBS 3t06 CA6►NET

(E) 4'-0"X6'-0" CONCRETE PAD

_ L_

i

TO INTERCEPT

~ (E)i100 AMP EREAKER PANEL~Ot~ H-FRAME

i~~ i

i~. i

iii

(P~' 2416 CABINET ON H-FRAMEii

i

iii

1~~

ii~ (E)UNDERGROUND~ ~ COAX CABLEj DUCTBANKTRENCH

iv... .............i

~ i

L

iii

ii

~g'~ ~ (P) (6) 7/8" COAX CABLES(E) (12) 7/8" COAX CABLES

i

20~

CONFIGURATION

EQUIPMENT LAYOUT ~ 704 B UN.r.s. LE-3

SUBMITTALS LEASE EXHIBIT NORTHEAST SITE SOLUTIONSLE REV A 08.07.14 SITE NUMBER: 54 MAIN STREET, UNIT 3LE REV A 08.08.14 TLANTI S CT11085C STURBRIDGE, MA 01566

GROUP SITE NAME: (508) 434-5237

FOfl

'T 1340 Centre Street WOODBRIDGE/ WC X58/ RACEBSuite 212

T-MOBILE NORTHEAST, LLC

Newton, MA 02459 SITE A~DREss: 35 GRIFFIN ROAD SOUTH

1 COUNTRY CLUB RD, BLOOMFIELD, CTo6002Office: 617-965-0789

WOODBRIDGE, CT 06524 OFFICE: (860) 692-7100

Fax: 617-213-5056 FAX: (860) 692-7159

DRAWN BY; FG CHECKED BY:SM PAGE30F4

(E) GSM/UMTS QUADPOLE ANTENNA ON(E) PIPE MOUNT(1"YP. 1 /SECTOR, TOTAL OF 3)ELEV :158'± (AGL)

(P) COMMSCOPE DUALPOLE ANTENNA ON(P) PIPE MOUNT(TYP. 1/SECTOR, TOTAL OF 3)ELEV :148'± (AGL)

—(E) HIGH TENSION—TOWER

TRANSMISSION TOWER

ST24092B

_ TQP OF (E) TOWERELEV._ 160'-6" ± (AGL)

RAD CENTER OF(E) T-MOBILE ANTENNAS__

ELEV._ 158'± (AGL) ~

RAD CENTER OF~) T-MOBILE ANTENNAS

ELEV.= 146'± (AGL)

(P) (fi) 7/8" COAX CABLES(E) (Y 2) 7/8" COAX CABLESROUTED OUTSIDE TOWER

(P) 2416 CABINET ON H-FRAME

(P) (3) RRUs ON H-FRAME

(E) 6102 CABINET —ON CONCRETE PAD

(E) RBS 3106 CABINETON GONCRETE PAD

(E) GPS

(E) 8' HIGHSTOCKA~EFENCE

8' HIGH STOC4<A~EFENCE

CONFIGURATION

SOUTH ELEVATION 1 ~O4SCALE: N.T.S.

LE-4

SUBMITTALS LEASE EXHIBIT NORTHEAST SITE SOLUTIONSLE REV A 08.07.14

SITE NUMBER: 54 MAIN STREET, UNIT 3LEREVA 08.08.74 TLANTIS CT11085C STURBRIDGE, MA 01566

GROUP SITE NAME: (508) 4345237

FOR1340 Centre Street WOODBRIDGE/ WC X58/ RACEB T-MOBILE NORTHEAST, LLC

Suite 212 sireno~REss: 35 GRIFFIN ROAD SOUTH

Newton, MA 02459 1 COUNTRY CLUB RD, BLOOMFIELD, Crosoo2

Office: 617-965-0789 WOODBRIDGE, CT 06524 OFFICE: (aso) ss2-~ioo

Fax: 617-213-5056 FAX: (860) fi92-7159

DRAWN BY: FG CHECKED BY:SM PAGE40F4

C-NT=Ke►,~~r,e~r~n g

Centered an Solutions "

S t r u c t u r a l A n a l y s i s o fC L& P P o l e

T-Mobile: CT1 1085C

CL&P Structure No. 24092

760.5' Electric Transmission Pole

Country Club Road,Woodbridge, CT

CENTEK Project No. 74025.013

Date: September 29, 2014

~~tig1A 414fIdP~i~~d

~' ~.a-~— fi+.

~ G = ~.~

~`~' ~.. 3 ~' ~

- ~r ~~ ~~~~r ~~~~dtl 6d~ S ''

Prepared for:T-Mobile USA

35 Griffin RoadBloomfield, CT 06002

63-2 North Branford Road, Branford, CT 06405 203.488.0580 Fax 203.488.8587 www.CentekEng.com

CENTEK Engineering, lnc.Structural Analysis — 160.5-ft CL&P Pole # 24092T-Mobile Antenna Upgrade — CT11085CWoodbridge, CTSeptember 29, 2014

Table of Contents

SECTION 1 - REPORT

■ INTRODUCTION

■ PRIMARY ASSUMPTIONS USED IN THE ANALYSIS

■ ANALYS I S

• DESIGN BASIS

• RESULTS

■ CONCLUSION

SECTION 2 - CONDITIONS &SOFTWARE

■ STANDARD ENGINEERING CONDITIONS

■ GENERAL DESCRIPTION OF STRUCTURAL ANALYSIS PROGRAMS

• PLS POLE

SECTION 3 - DESIGN CRITERIA

■ CRITERIA FOR DESIGN OF PCS FACILITIES ON OR EXTENDING ABOVEMETAL ELECTRIC TRANSMISSON TOWERS

• NU DESIGN CRITERIA TABLE

■ PCS SHAPE FACTOR CRITERIA

■ WIRE LOADS SHEET

SECTION 4 - DRAWINGS

■ EL-1 TOWER ELEVATION AND FEEDLINE PLAN

SECTION 5 - NESC/NU LOAD CALCULATIONS

■ ANTENNA LOADS

■ COAX CABLE LOAD ON CL&P POLE

SECTION 6 - PLS POLE ANALYSIS

• PLS REPORT

■ ANCHOR BOLT ANALYSIS

■ FOUNDATION ANALYSIS

SECTION 7 - REFERENCE MATERIAL

■ RF DATA SHEET

■ EQUIPMENT CUT SHEETS

TABLE OF CONTENTS TOC-1

CENTEK Engineering, Inc.Structural Analysis — 760.5-ft CL&P Pole # 24092T-Mobile Antenna Upgrade — CT11085CWoodbridge, CTSeptember 29, 2014

Introduction

The purpose of this report is to analyze the existing 160.5' CL&P pole located at Country Club Rd.,Woodbridge, CT for the proposed antenna and equipment upgrade by T-Mobile.

The proposed loads consist of the following:

■ T-MOBILE (Existing to be removed

Antennas: Six (6) TMA's flush mounted to the CL&P pole with a RAD center elevation of158-ft above tower base plate.

■ T-MOBILE (Existing to remain

Antennas: Three (3) RFS APX16DWV-16DWVS-E-A20 panel antennas flush mounted to theCL&P pole with a RAD center elevation of 158-ft above tower base plate.Coax Cables: Twelve (12) 1-5/8" Q~ coax cables mounted to the exterior of the CL&P pole asindicated in Section 4 of this report.

■ T-MOBILE (Proposed):

Antennas: Three (3) Andrew LNX-6515DS panel antennas flush mounted to theexisting CL&P utility pole with a RAD center elevations of 148 -ft above tower baseplate.Coax Cables: Six (6) 1-5/8" Q1 coax cables mounted to the outside of the CL&P pole asindicated in Section 4 of this report.

Primary assum,otions used in the analysis

■ ASCE Manual No. 72, "Design of Steel Transmission Pole Structures Second Edition",defines allowable steel stresses for evaluation of the CL&P utility pole.

■ All utility pole members are adequately protected to prevent corrosion of steel members.■ All proposed antenna mounts are modeled as listed above.■ No residual stresses exist due to incorrect pole erection.■ All bolts are appropriately tightened providing the necessary connection continuity.■ All welds conform to the requirements of AWS D1.1.■ All utility pole members were properly designed, detailed, fabricated, and installed and have

been properly maintained since erection.■ Any deviation from the analyzed loading will require a new analysis for verification of

structural adequacy.

REPORT SECTION 1-1

CENTEK Engineering, Inc.Structural Analysis — 160.5-ft CL&P Pole # 24092T-Mobile Antenna Upgrade — CT11085CWoodbridge, CTSeptember 29, 2014

Desian Basis

Our analysis was performed in accordance with ASCE Manual No. 72 — "Design of Steel TransmissionPole Structures Second Edition", NESC C2-2007 and Northeast Utilities Design Criteria.

The CL&P pole structure, considering existing and future conductor and shield wire loading, with theproposed T-Mobile equipment was analyzed as follows:

■ UTILITY POLE ANALYSIS

The purpose of this analysis is to determine the adequacy of the existing utility pole tosupport the proposed antenna loads. The loading and design requirements were analyzed inaccordance with the NU Design Criteria Table, NESC C2-2007 —Construction Grade B, andASCE Manual No. 72.

Load cases considered:

Load Case 1: NESC Heavy WindWind Pressure ..................................... 4.0 psfRadial Ice Thickness ............................. 0.5"Vertical Overload Capacity Factor ............. 1.50Wind Overload Capacity Factor ................ 2.50Wire Tension Overload Capacity Factor...... 1.65

Load Case 2: NESC Extreme WindWind Speed ....................................... 110 mph ~'~Radial Ice Thickness ............................. 0"

Load Case 3: NESC Extreme Ice w/WindWind Pressure ..................................... 6.4 psfRadial Ice Thickness ............................. 0.75"Vertical Overload Capacity Factor ............. 1.0Wind Overload Capacity Factor ................ 1.0

Note 1: NESC C2-2007, Sectima25, Rule 250C: Extreme T~Vind Loading,1.25 z Gust Response Factor (ivied speed: 3-second gust)

■ UTILITY POLE

This analysis finds that the subject utility pole is adequate to support the proposed antennamast and related appurtenances. The pole stresses meet the requirements set forth by theASCE Manual No. 72, "Design of Steel Transmission Pole Structures Second Edition", for theapplied NESC Heavy and Hi-Wind load cases. The detailed analysis results are provided inSection 9 of this report. The analysis results are summarized as follows:

A maximum usage of 70.79% occurs in the utility pole under the NESC Heavy loading condition

POLE SECTION:

The utility pole was found to be within allowable limits.

Tower Section Elevation Stress Ratio

Result(% of capacity)

Tube Number 8 0.00' -18.50' (AGL) 70.79% PASS

REPORT SECTION 1-2

CENTEK Engineering, lnc.Structural Analysis — 760.5-ft CL&P Pole # 24092T-Mobile Antenna Upgrade — CT11085CWoodbridge, CTSeptember 29, 2014

BASE PLATE'

The base plate was found to be within allowable limits from the PLS output based on 24 bendi nes.

Tower Component Design Limit Stress Ratio

Result(percentage of capacity)

Base Plate Bending 43.84% PASS

■ FOUNDATION AND ANCHORS

The existing foundation consists of a 10-ft QS x 47.0-ft long reinforced concrete caisson. The baseof the tower is connected to the foundation by means of (44) 2.25"QJ, ASTM A615-75 anchor boltsembedded approximately 8.5-ft into the concrete foundation structure. Foundation informationwas obtained from NUSCO drawing # 01229-60001 sheet 3 of 14.

BASE REACTIONS:

From PLS-Pole analysis of CL&P pole based on NESC/NU prescribed loads.

Load Case Shear A~cial Moment

NESC Heavy Wind 137.65 kips 107.01 kips 13125.16 ft-kipsNESC Extreme Wind 88.11 kips 67.62 kips 8446.51 ft-kips

NESC Extreme Ice w/Wind 93.46 kips 79.63 kips 8898.74 ft-kipsNote 1 — 10%increase applied to tower base reactions per OTRM 051

ANCHOR BOLTS:The anchor bolts were found to be within allowable limits.

Tower Component Design Limit Stress Ratio

Result(/o of capacity)

Anchor Bolts Tension 68.56% PASS

FOUNDATION:

The foundation was found to be within allowable limits.

Foundation Design Limit Proposed ResultLoading

Reinforced Concrete Moment Capacity 71.4% PASSCaisson Lateral Deflection 1.32 in. PASS

(1) Lateral deflection limited to L/100 per OTRM 059 Rev 4 dated 2/01/10. (L/100 = 18.5'12/100=5.64-in)

REPORT SECTION 1-3

CENTEK Engineering, hoc.Structural Analysis — 160.5-ft CL&P Pole # 24092T-Mobile Antenna Upgrade — CT11085CWoodbridge, CTSeptember 29, 2014

Conclusion

This analysis shows that the subject tower is adequate to support the proposed modified antennaconfiguration.

The analysis is based, in part, on the information provided to this office by Northeast Utilities and T-Mobile. If the existing conditions are different than the information in this report, Centek Engineering, Inc.must be contacted for resolution of any potential issues.

Please feel free to call with any questions or cor~r~r~~n~s ~'',

Respectfully Submitted byr ~;`~,~~- ,~,~~n~{`;n''~,

~Y ~ ~~"7i.

~~~y~el ~3 ~~~ ~. ~ ~ No. 29,)36 ,~'ti ~UTimothy J. Lynn, PE ~~ ̀ ~~~ra sF~~' ~~ ti .̀Structural Engineer ''.,. ̀ ~S °`°"°~ ~'' ~`

:~ ~~~jiVd~.L, ~~ ,,~<.

~~r;~laaYilSt~~~,{4,

REPORT SECTION 1-4

E61 Consulting~ environmental ~ engineering ~ due diligence

RADIO FREQUENCY EMISSIONS ANALYSIS REPORTEVALUATION OF HUMAN EXPOSURE POTENTIAL

TO NON-IONIZING EMISSIONS

T-Mobile Existing Facility

Site ID: CT11058E

Woodbridge / WC X58 / RACEB1 Country Club Road

Woodbridge, CT 06524

November 12, 2014

EBI Project Number: 62145328

Site Compliance Summary

Compliance Status: COMPLIANT

Site total MPE% ofFCC general public rj~]]allowable limit:

21 B Street 'Burlington, MA 01803 Tel: (781) 273.2500 Fax: (781) 273.3311

ELI C n l i-_ :~ environmental ~ engineering ~ due diligence

November 12, 2014

T-Mobile USAAttu: Jason Overbey, RF Manager35 Griffin Road SouthBloomfield, CT 06002

Emissions Analysis for Site: CT11058E —Woodbridge / WC X58 / RACEB

EBI Consulting was directed to analyze the proposed T-Mobile facility located at 1 Country Club Road,

Woodbridge, CT, for the purpose of determining whether the emissions from the Proposed T-Mobile

Antenna Installation located on this property are within specified federal limits.

All information used in this report was analyzed as a percentage of current M~imum Permissible

Exposure (% MPE) as listed in the FCC OET Bulletin 65 Edition 97-Oland ANSUIEEE Std C95.1. The

FCC regulates Maacimum Permissible Exposure in units of microwatts per square centimeter (µW/cm2).

The number of µW/cm2 calculated at each sample point is called the power density. The exposure limit

for power density varies depending upon the frequencies being utilized. Wireless Carriers and Paging

Services use different frequency bands each with different exposure lunits, therefore it is necessary to

report results and limits in terms of percent MPE rather than power density.

All results were compared to the FCC (Federal Communications Commission) radio frequency exposure

rules, 47 CFR 1.1307(b)(1) — (b)(3), to determine compliance with the Maximum Permissible Exposure

(MPE) limits for General Population/LTncontrolled environments as defined below.

General nonulation/uncontrolled exposure limits apply to situations in which the general public maybe

exposed or in which persons who are exposed as a consequence of their employment may not be made

fully awaxe of the potential for exposure or cannot exercise control over their exposure. Therefore,

members of the general public would always be considered under this category when exposure is not

employment related, for example, in the case of a telecommunications tower that exposes persons in a

nearby residential area.

Public exposure to radio frequencies is regulated and enforced in units of microwatts per square

centimeter (µW/cmz). The general population exposure limit for the 700 MHz Band is 467 µW/cmZ, and

the general population exposure limit for the PCS and AWS bands is 1000 µW/cm2. Because each carrier

will be using different frequency bands, and each frequency band has different exposure limits, it is

necessary to report percent of MPE rather than power density.

21 B Street 'Burlington, MA 018Q3 ~ Tel: (781) 273.2500 Fax: (781) 273.3311

E61 Consulting~ environmental ~ engineering ~ due diligence

OccupationaUcontrolled exposure limits apply to situations in which persons are exposed as a

consequence of their employment and in which those persons who are exposed have been made fully

aware ofthe potential for exposure and can exercise control over their exposure. Occupational/controlled

exposure limits also apply where exposure is of a transient nature as a result of incidental passage through

a location where exposure levels maybe above general population/uncontrolled limits (see below), as

long as the exposed person has been made fully aware of the potential for exposure and can exercise

control over his ar her exposure by leaving the area or by some other appropriate means.

Additional details can be found in FCC OET 65.

CALCULATIONS

Calculations were done for the proposed T-Mobile Wireless antenna facility located at 1 Country Club

Road, Woodbridge, CT, using the equipment information listed below. All calculations were performed

per the specifications under FCC OET 65. Since T-Mobile is proposing highly focused directional panel

antennas, which project most of the emitted energy out toward the horizon, all calculations were

performed assuming a lobe representing the maacimum gain of the antenna per the antenna manufactures

supplied specifications, minus 10 dB, was focused at the base of the tower. For this report the sample

point is the top of a 6 foot person standing at the base of the tower.

For all calculations, all equipment was calculated using the following assumptions:

1) 2 GSM channels (PCS Band - 1900 MHz) were considered for each sector of the proposed

installation. These Channels have a transmit power of 30 Watts per Channel

2) 2 UMTS channels (AWS Band — 2100 MHz) were considered for each sector of the proposed

installation. These Channels have a transmit power of 30 Watts per Channel.

3) 2 LTE channels (AWS Band — 2100 MHz) were considered for each sector of the proposed

installation. These Channels have a transmit power of 60 Watts per Channel.

4) 1 LTE channel (700 MHz Band) was considered for each sector of the proposed installation.

This channel has a transmit power of 30 Watts..

5) All radios at the proposed installation were considered to be running at full power and were

uncombined in their RF transmissions paths per carrier prescribed configuration. Per FCC

OET Bulletin No. 65 -Edition 97-01 recommendations to achieve the maximum anticipated

value at each sample point, all power levels emitting from the proposed antenna installation

are increased by a factor of 2.56 to account for possible in-phase reflections from the

surrounding environment. This is rarely the case, and if so, is never continuous.

21 B Street 'Burlington, MA 01803 Tel: (781) 273.2500 Fax: (781) 273.3311

ia environmental ~ engineering ~ due diligence

6) For the following calculations the sample point was the top of a six foot person standing at

the base of the tower. The maximum gain of the antenna per the antenna manufactures

supplied specifications minus 10 dB was used in this direction. This value is a very

conservative estimate as gain reductions for these particular antennas are typically much

higher in this direction.

7) The antennas used in this modeling are the RFS APXI6DWV-16DWVS-E-A20 for 1900

MHz (PCS) and 2100 MHz (AWS) channels and the Commscope LNX-6515DS-VTM for

700 MHz channels. This is based on feedback from the carrier with regards to anticipated

antenna selection. The RFS APXI6DWV-16DWVS-E-A20 has a maximum gain of 16.3

dBd at its main lobe. The Commscope LNX-6515DS-VTM has a m~imum gain of 14.6

dSd at its main lobe. The maximum gain of the antenna per the antenna manufactures

supplied specifications, minus 10 dB, was used for all calculations. This value is a very

conservative estimate as gain reductions for these particular antennas are Typically much

higher in this direction.

8) The antenna mounting height centerlines of the proposed antennas are 158 feet & 148 feet

above ground level (AGL).

9) Emissions values for additional carriers were taken from the Connecticut Siting Council

active database. Values in this database are provided by the individual carriers themselves.

All calculations were done with respect to uncontrolled /general public threshold limits.

21 B Street 'Burlington, MA 01803 ~ Tel: (781) 273.2500 ~ Fax: (781) 273.3311

EBI C su~~~o~~oi environmental ~ engineering ~ due diligence

T-Mobile Site Inventory and Power Data

Sector: A Sector: B Sector: CAntenna #: 1 Antenna #: 1 Antenna #: 1

RFS APXI6DVW- RFS APXI6DWV- RFS APXI6DWV-Make /Model:

16DVJVS-E-A20 Make /Model:

16DVWS-E-A20 Make /Model:

16DVWS-E-A20Gain: 163 dBd Geis 16.3 dBd Gain: 16.3 dBd

Hei ht AGL): 158 Hei ht AGL : 158 Hei ht AGL : l58

Frequency Bands 1900 MIIz(PCS) /

Frequenc_y Bands 1900 MIIz(PCS) /

Frequency Bands 1900 MIIz(PCS)

2100 MIIz AWS 2100 MIIz AWS 2100 MFIz AWS)Channel Count 6 Channel Co~mt 6 # PCS Charnels: 6

Total TX Power. 240 Total T'X Power. 240 # AWS Channels: 240ERP 3,833.82 ERP V~: 3,833.82 ERP ( 3,833.82

Antenna Al MPE% 1.59 AntennaBl MPE% 1:59 Anteima Cl MPE% 1.59

Antenna #: 2 Antenna #: 2 Antenna #: 2Commscope LNX- Commscope LNX- Commscope LNX-

Make /Model: 6515DS-VTM

Make /Model: 6515DS-VTM

Make /Model: 6515DS-VT'M

Crain: 14.6 dBd Crain_ 14.6 dBd Crain. 14.6 dBdAei t (AGL : 148 Hei ht (AGL): 148 Hei ht (AGL : 148

Fre enc Bands 700 Mhz Fre uenc Bands 700 Mhz Fre uenc Bands 700 MhzChannel Count 1 Channel Count 1 Channel Count 1

Total TX Power. 30 Total TX Power: 30 Total TX Power: 30FRp 445.37 ERP 445.37 ERP 445.37

Antenna A2 MPE% 0.33 Antenna B2 MPE% 0.33 Antenna C2 MPE% 0.33

Site Com osite MPE%Carrier MPE%

T-Mobile 5.77

No Additional Carriers Listedin the CSC MPE Database

Site Total MPE %: 5.77

T-Mobile Sector 1 Total: 1.92T-Mobile Sector 2 Total: 1.92T-Mobile Sector 3 Total: 1.92

Site Total: 5.77

21 B Street 'Burlington, MA 01803 Tel: (781) 273.2500 Fax: (781) 273.3311

ELI I i__ __ environmental ~ engineering ~ due diligence

SllIlllriRl'3'

All calculations performed for this analysis yielded results that were within the allowable lunits for

general public exposure to RF Emissions.

The anticipated maximum composite contributions from the T-Mobile faciliTy as well as the site

composite emissions value with regards to compliance with FCC's allowable limits for general public

exposure to RF Emissions are shown here:

T-Mobile Sector Power Densi Value (%Sector l: 1.92Sector 2: 1.92Sector 3 : 1.92

T-Mobile Total:. 5.77

Site Total: 5.77

Site Com liance Status: COMPLIANT

The anticipated composite MPE value for this site assuming all carriers present is 5.77% of the allowable

FCC established general public limit sampled at the ground level. This is based upon values listed in the

Connecticut Siting Council database for existing carrier emissions.

FCC guidelines state that if a site is found to be out of compliance (over allowable thresholds), that

carriers over a 5% contribution to the composite value will require measures to bring the site into

compliance. For this facility, the composite values calculated were well within the allowable 100%

threshold standard per the federal government.

/i ~~ ~~~h/~ ///

Scott Heffernan

RF Engineering Director

EBI Consulting

21 B Street

Burlington, MA 01803'

21 B Street 'Burlington, MA 01803 Tel: (781) 273.2500 Fax: (781) 273.3311