Upload
others
View
3
Download
0
Embed Size (px)
Citation preview
Use or disclosure of data contained on this page is subject to the restriction(s) on the title page of this document.GSFC SE Seminar: September 13, 2016 1
Goddard Space Flight Center
Systems Engineering Seminar
ISIM Element Environmental Testing
and Verification – Running the
Gauntlet
Julie Van Campen
JWST/ISIM Lead Systems Engineer
September 13, 2016
For Public Release
Use or disclosure of data contained on this page is subject to the restriction(s) on the title page of this document.GSFC SE Seminar: September 13, 2016 2
JWST Architecture
James Webb Space Telescope System
Launch Segment Observatory Segment Ground Segment
Optical Telescope Element (OTE)
Spacecraft Element (SE)
Launch Vehicle
Payload Adapter
Launch Site Services
Science and Operations Center (SOC)
Common Systems
Institutional Systems
Spacecraft Bus
Sunshield
Ariane Launcher
Deep Space NetworkSpace Telescope Science Institute
Provided by NASA/GSFC
Provided by NGAS
Provided by STScI
Provided by ESA
Integrated Science Instrument Module (ISIM)
FGSNIRSpec
Provided by CSA
JWST Observatory
MIRINIRCam
Mission Systems Engineering
OTIS – Integrated OTE & ISIM
Use or disclosure of data contained on this page is subject to the restriction(s) on the title page of this document.GSFC SE Seminar: September 13, 2016 3
JWST Observatory Segment Partitions
Observatory Segment
Segment Element Subsystem
Observatory Segment
Optical Telescope
Element
Primary Mirror Subsystem
Secondary Mirror Subsystem
Aft Optics Subsystem
OTE Electronics Subsystem
Thermal Management
Subsystem
Deployment Tower
Subsystem
Wavefront Sensing & Control
Subsystem
Integrated Science
Instrument Module Near-Infrared Camera
Near-Infrared Spectrograph
Mid-Infrared Instrument
Fine Guidance Sensor/ NIRISS
ISIM Structure Subsystem
Thermal Control Subsystem
ISIM Command & Data Handling
Electronics
ISIM Remote Services Unit
ISIM Flight Software
ISIM Electronics Compartment
ISIM Harness
MIRI Shield
Operations Scripts Subsystem
ISIM Harness Radiator
Spacecraft
Element
Sunshield Subsystem
Structure and Mechanisms
Subsystem
Thermal Control Subsystem
Electrical Power Subsystem
Propulsion Subsystem
Attitude Control Subsystem
Command and Data Handling
Subsystem
Communications Subsystem
Flight Software
Electrical Harness
MIRI Cooling System
Use or disclosure of data contained on this page is subject to the restriction(s) on the title page of this document.GSFC SE Seminar: September 13, 2016 4
Observatory I&T
Optical Telescope Element
NG Team
JPL
ESA
U of Az
LEGEND
ESA/EC
CSA
GSFC
STScI
Observatory Systems EngineeringObservatory Performance & Programmatics
Mission Systems Engineering
Mission Project Management
ISIM Enclosure
MIRI
Optics System
Detector Subsystem
Instrument Control Electronics
Cooling System
Management, Systems Engineering
Instrument FSW
NIRCam
Optics Assy.
Detector Sub-system
Instrument Control Electronics
Wavefront Sensing Elements
Instrument FSW
NIRSpec
Optics Assy.
Microshutter Subsystem & FSW
Detector Subsystem & FSW
Instrument Control Electronics
Instrument FSW
Spacecraft
S/C Bus
Sunshield
Observatory FSW FGS/TF
Structure
I&T
ISIM Management, Systems, & Science
OTE Simulator
IECIRSU FSW Thermal
Harness
ICDH
Optics Assy.
Instrument Control Electronics
Instrument FSW
Detector Subsystem
JWST Observatory Segment Partners Roles
Harness Radiator
OSS MIRI Shield
Use or disclosure of data contained on this page is subject to the restriction(s) on the title page of this document.GSFC SE Seminar: September 13, 2016 5
Integrated Science Instrument Module
■ The ISIM system consists of:
– Five sensor systems
● MIRI, NIRCam, NIRSpec, NIRISS, FGS
– Nine instrument support systems:
● Optical metering structure system
● Electrical Harness System
● Harness Radiator System
● ISIM Electronics Compartment (IEC)
● Cryogenic Thermal Control System
● Command and Data Handling System
(ICDH)
● ISIM Remote Services Unit (IRSU)
● Flight Software System
● Operations Scripts System
ISIM is one of three elements that together make up the JWST space vehicle
• Approximately 1.4 metric tons, ~20% of JWST by mass
Use or disclosure of data contained on this page is subject to the restriction(s) on the title page of this document.GSFC SE Seminar: September 13, 2016 6
ISIM Element
Hierarchy
Element Sub-Element Subsystem
GSFC provided EIDP
Non-GSFC provided EIDP
GSFC & Non-GSFC provided EIDPs
Region 1
TTHR
Region 2
Region 3
Region 3
ISIM Element
ISIM Structure
MIRI Shield
FGS
NIRCam
ISIM Harnesses
IHR Structure
IEC Structure
IEC ElectronicsBoxes
ICDH Electronics BoxesFlt-01 & Flt-03
NIRSpec
MIRI
ISIM Thermal Control Subsystem (TCS)
ISIM Electronics Compartment (IEC)
ISIM FlightSoftware (IFSW)
ISIM Command & Data Handling (ICDH)
ISIM Prime
ISIM HarnessRadiator (IHR)
Use or disclosure of data contained on this page is subject to the restriction(s) on the title page of this document.GSFC SE Seminar: September 13, 2016 7
■ ISIM Hardware
– ISIM Prime, IEC, and HR are delivered to OTIS for integration
– ICDH Delivered to the Spacecraft (Northrop Grumman)
ISIM Element at Delivery to OTIS
ISIM PrimeRegion 1
(GSE Stand)
ISIM Electronics CompartmentRegion 2
Harness Radiator(Thermal Trans Region)
(GSE Stand)
(GSE Stand)
Use or disclosure of data contained on this page is subject to the restriction(s) on the title page of this document.GSFC SE Seminar: September 13, 2016 8
ICDH Overview – Region 3/Spacecraft
Single Board Computer (SBC)
• Hosts ISIM Flight Software
Focal Plane Array Processors (FPAP)
• Simultaneous Science Data
Processing
Backplane (not shown)
Chassis
• Provides mechanical housing
and some radiation shielding
for assemblies
Power Distribution Unit (PDU)
Bus Interface Card (BIC)
• NIRCam, NIRSpec, MIRI FPEs,
SSR & FPAP SpaceWire
Interfaces
• Science Data Storage
Formatting
Housekeeping (HKI) Card
• S/C and ICE 1553B Interfaces
• ICDH Temperature and Voltage
Monitoring
Use or disclosure of data contained on this page is subject to the restriction(s) on the title page of this document.GSFC SE Seminar: September 13, 2016 9
ISIM Structure – Qualification Tests
Optical Stability - Cryoset Test
2010
Cryogenic Strength Test - Cryoproof Test
2011
Modal Survey
2011
Use or disclosure of data contained on this page is subject to the restriction(s) on the title page of this document.GSFC SE Seminar: September 13, 2016 10
ISIM Harness Test Flow
Milliohm Testing
Hi-Pot Testing
Thermal Cycle testing
Hi-Pot Testing
CleaningBakeoutDelivery to
ISIM I&T
FIS Integration
200-Series
30
0-Series
X-RayDC Bonding
TestVisual
Inspection
DimensionalInspection
DC Resistance
Test
Insulation Resistance
Test
Dielectric Withstandin
g Voltage Test
Shield Resistance
Test
Thermal Shock
Visual Inspection
DCResistance
Test
Insulation Resistance
Test
Dielectric Withstandin
g Voltage Test
Focal Plane Electronics Thermal Transition Region
Harnesses
Incoming Quality
Assurance Inspection
AssemblyMilliohm Testing
Hi-Pot Testing
Final Quality Assurance Inspection
IRSU to Region 1 Thermal Transition Harnesses and IEC
Internal
Fabrication
Final Quality Assurance Inspection
(4 cycles to 27K)
Testing Performed at Goddard
(Level 300A)
Cleaning Bakeout400-Series
Hi-Pot Testing
Assembly
All Other Thermal Transition Region
Harnesses
300/200-Series
400-Series
Thermal Cycle testing
(4 cycles to
Use or disclosure of data contained on this page is subject to the restriction(s) on the title page of this document.GSFC SE Seminar: September 13, 2016 11
IRSU Testing at Box Level
Physical Verification
Functional Verification
Test
FunctionalVerification
Tests
FunctionalVerification
Tests
EMI/EMC Testing per the
ISIM plan
FunctionalVerification
Tests
Conformal Coating
Preliminary Mechanical/
ElectricalIntegration
FunctionalVerification
Tests
FinalMechanical/
ElectricalIntegration
FunctionalVerification
Tests
IRSU Box Test Flow
VibrationTesting –
ProtoflightLevels
Thermal Vac -4 Cycles -
ProtoflightLevels
Board Test FlowPCU, ITCE, MSC
Thermal Cycles (PCU & MSC)
Box ModMech/ElecIntegration
FunctionalVerification
Tests
WorkmanshipVibe
1 Cycle TVACFunctionalVerification
Tests
Completion ofBurn-In
For200 hours
ISIM
Test
Flow
Delivery to ISIM
CV1RR
Use or disclosure of data contained on this page is subject to the restriction(s) on the title page of this document.GSFC SE Seminar: September 13, 2016 12
IEC Integration & TEST Plan
Use or disclosure of data contained on this page is subject to the restriction(s) on the title page of this document.GSFC SE Seminar: September 13, 2016 13
MIRI Shield in Facility 238 / Doghouse in
TV/TB Test
1
Use or disclosure of data contained on this page is subject to the restriction(s) on the title page of this document.GSFC SE Seminar: September 13, 2016 14
ISIM Prime
ISIM utilizes aluminum heat straps for coupling to
its radiators
The ISIM Heat Strap System was designed, fabricated, and qualified by Space Dynamics Laboratory.
The straps create a thermal path between the sensors and the radiator panels that provide their passive cryogenic cooling
Use or disclosure of data contained on this page is subject to the restriction(s) on the title page of this document.GSFC SE Seminar: September 13, 2016 15
MIRI Integration – Delivered September 2012
Use or disclosure of data contained on this page is subject to the restriction(s) on the title page of this document.GSFC SE Seminar: September 13, 2016 16
MIRI Shield Integration
Use or disclosure of data contained on this page is subject to the restriction(s) on the title page of this document.GSFC SE Seminar: September 13, 2016 17
FGS Integration – Delivered December 2012
Use or disclosure of data contained on this page is subject to the restriction(s) on the title page of this document.GSFC SE Seminar: September 13, 2016 18
ISIM ElementSystem Func
ISIM Prime Integration
ISIM ElementCV1-RR
IEC
HR
IECIntegrate NC and NS boxes
IECSI Testing in FIESTA Area
IECInterface
Metrology
HRIntegrate NC
and NS harnesses
HRIntegrate
FGS and MIRI harnesses
ISIM PrimeIntegration/Mass Props
M MMISIM Element System Func /
MetrologyM
■ Prior to the ISIM level Pre-Environmental Review (PER), integration and risk reduction tests were performed
– Accommodated staggered SI delivery
– FGS + MIRI in first wave
– NIRCam and NIRSpec in second wave
ISIM Integration and Risk Reduction Tests
ISIM ElementPER
IECIntegrate
FGS & MIRI boxes
IECSI Testing in FIESTA Area
Use or disclosure of data contained on this page is subject to the restriction(s) on the title page of this document.GSFC SE Seminar: September 13, 2016 19
ISIM Electrical Tests Flow
Use or disclosure of data contained on this page is subject to the restriction(s) on the title page of this document.GSFC SE Seminar: September 13, 2016 20
Achieved CV1 RR Timeline
Maximum Gradient
Primary Mirror (OSIM)This max gradient will be
managed in test to be Ts>140
Start
MIRI CC
FGS
80>Tf>60
FGS/NIRISS
Dark Count Images (OSS)
OSIM
Stability
Criteria Met
SI Stability
Criteria Met
Track MATF/IATF Targets / ADM
Ln2 OSIM
Shroud
CPT Part 1
(include JPL Regression)
TB 1-H-0-0
OSIM Final
Checkout
OSIM+SI
Checkout
Trim Htr & Heat
Strap Conductance
(TB 1-H-1-0 )
Initial
Optical
Baseline
CPT Part 2
FGS-NIRISS
Performance
Characterization
FGS-Guider
Performance
Characterization
Begin Warm
Up
Track MATF/IATF Targets / ADM
SES Re-
Pressurize
System
FunctionalWarm SI Only
Warm Environment
Warm He Shrd
Release N2
Pwr
ASIC/Det
Pwr OFF
Switch to
SWTS SSR
Cooler EMC
Safety Check
Vacuum Conditions
LO
CK
ED
OP
EN
CL
OS
E
@1
85K
OP
EN
CPT1
Cycle
O/C
CL
OS
E
OP
EN
CL
OS
E
OP
EN
@1
35K
8/29/2013 11/9/2013
9/1
9/8 9/15 9/22 9/29 10/6 10/13 10/20 10/27 11/3
Pwr MIRI Detector Htrs
(MIRI
Use or disclosure of data contained on this page is subject to the restriction(s) on the title page of this document.GSFC SE Seminar: September 13, 2016 21
Top Level Goals of CV1-RR Very Well Satisfied
Will march through the objectives, as presented at the CV1-RR Test Design Review:
• The fundamental purpose of ISIM CV1-RR was, through this early exercise of the ISIM CV test hardware and procedures, to maximize the likelihood that the subsequent ISIM verification tests, CV2 and CV3, will run effectively and efficiently (i.e., as the name of the test implies, to reduce the risk that they won’t)
• Hence, in broad terms, the primary objectives of CV1-RR were:
– To demonstrate that the test configuration, which includes large amounts of new GSE, is able to support the test requirements of the ISIM verification program (identify any necessary fixes to hardware before CV2) − highly successful; despite issues with He shroud and spacecraft simulators, we could have run a successful verification test
– By dry-running critical test procedures, to learn how to most efficiently formulate and execute them and to analyze the results (identify any necessary improvements to procedures before CV2) − also successful and extremely productive; learned a huge amount about test scripts, data flow, optical test procedures that will enable us to improve the execution of CV2 and CV3
Use or disclosure of data contained on this page is subject to the restriction(s) on the title page of this document.GSFC SE Seminar: September 13, 2016 22
Thermal IsolationStructural Kinematic or Semi-
Kinematic (flexure) Interface
Structural Non-Compliant
Joint (bolted/pinned)
Legend
Actively Heated
Actively Cooled
Actively Heated & Cooled
Thermal Strap (Flex)
A
20K He Shroud Floor A
He Shroud Sides
20K
He Shroud Roof
Primary Support
Integration Frame (SIF)
ITP
Similar to GIS
MATF
20K
# KNominal Test
Temperature (K)
ISIM Element
IATF &
MCA
STMS
Panels
G10
Standoffs
IEC
HR
45K
35K
IEC N2
Panel
(203-1)
IEC He
Shroud
HR
Support
Stand
45K – 56K
MCA
EB
170K
35K
Cold
Plate
During Test: Load Path via Ti
Blade Flexures to Upper GESHA
During Set up: Load Path via ITP
Lift Points to Support Frame (SIF)
To He Shroud Floor20K
Flt KM
20K
Flt Heat
Straps
180K
20K273K
40K-70K
20K
ISIM Element Cryo-Vacuum Test
ConfigurationStructural Support & Temperature Control
# He Zone #
10
9
1 32
8
Framework
67
20K
MIRI SI
6K
Flt Harness (ICP-A to ICP-2)
Q-Meters
Passive, or cntrl via Thermal
Strap to cold/hot source
HR DSR
10
CooldownControl
Cold
Plate
4
5Cooling
Lines
Invar
Frame
Flt KM
Seperable
10
10
Flight Hardware
20K
ITP KM I/F
OSIM Thermal Baffle
IEC Flexures
Zero-Q Htrs
MCA Thermal Strap
Zone 7 Order
Q-meters: FGS, MIRI, NIRSpec, NIRCam,
STMS Panels
Zone 10 Order
MCA CP, HR DSR, SIF
SES PV
Wall
SES LN2/He
Shrouds
Port 8
CC MGSE
Cooled
Shield
60K
ISIM CV Test Configuration – He Zones
Use or disclosure of data contained on this page is subject to the restriction(s) on the title page of this document.GSFC SE Seminar: September 13, 2016 23
NIRSpec Arrival in the SSDIF, September 2013
Use or disclosure of data contained on this page is subject to the restriction(s) on the title page of this document.GSFC SE Seminar: September 13, 2016 24
NIRCam Delivery and Detector Replacement
■ Flight NIRCam delivered to ISIM I&T September 18, 2013
■ New NIRCam flight detectors installed November 19 2013…10 months early!
Use or disclosure of data contained on this page is subject to the restriction(s) on the title page of this document.GSFC SE Seminar: September 13, 2016 25
NIRCam Integration to ISIM
Use or disclosure of data contained on this page is subject to the restriction(s) on the title page of this document.GSFC SE Seminar: September 13, 2016 26
IEC Mechanical & Electrical Integration
Use or disclosure of data contained on this page is subject to the restriction(s) on the title page of this document.GSFC SE Seminar: September 13, 2016 27
Thermal Transition Harness Integration
Use or disclosure of data contained on this page is subject to the restriction(s) on the title page of this document.GSFC SE Seminar: September 13, 2016 28
ISIM Overview – ISIM SubElements
ISIM Prime
ISIM Harness Radiator
ISIM Electronics
Compartment
Use or disclosure of data contained on this page is subject to the restriction(s) on the title page of this document.GSFC SE Seminar: September 13, 2016 29
JWST Overview - ISIM Element
ISIM Prime ISIM Harness Radiator ISIM Electronics Compartment
ISIM Prime is the term used to describe the assembly of the ISIM Structure, the SIs, the MIRI Cooler and all subsystems that integrate to the ISIM Structure.
It is meant to encompass all hardware that mounts to the telescope via the ISIM Structure KMs.
The term does not appear in requirements documents but was coined to describe an actual piece of assembled hardware that gets delivered as an entity. ISIM Prime is not just the ISIM Structure, nor is it ISIM Element (Prime + HR + IEC + ICDH), nor is it the R1 hardware.
Use or disclosure of data contained on this page is subject to the restriction(s) on the title page of this document.GSFC SE Seminar: September 13, 2016 30
ISIM Prime Mass Properties
Objective of Test
Level of Test
Known Deviations from Flight Configuration
• Provide information used to calculate the mass of ISIM Prime.
• Provide information used to calculate the CG of ISIM Prime.
• n/a
• Flight ISIM Structure Kinematic mounts cannot be part of the measurement
• GSE HSA is on ISIM Prime for the measurement• 4x Non-Flight CFMPs (Corner Fitting Metrology Plates) are
still integrated on various -V3 corner fittings• 15x Non-flight metrology nests are still integrated to ISIM
Prime for this measurement• 15x Non-flight metrology retention bands are integrated to
non-flight metrology nests on ISIM Prime• 4x Non-flight metrology nests are integrated FGS• 4x Non-flight metrology retention bands are integrated to
non-flight metrology nests are integrated FGS• Some protective padding was on ISIM Prime for this
operation• 4x Non-flight lift-blocks & shackles were integrated to ISIM
Prime (they are needed to enable the lift itself)• Non-flight ICP-A blanket is integrated to ISIM Prime (this
represents a flight blanket that the OTE team is going use so it isn’t part of ISIM Prime mass)
• Traveling ground was hanging from ISIM Prime• Traveling purge was hanging from ISIM Prime• RTG saddle connection (cable ties currently used vs machined
pieces to be used on flight)• No MIRI cooler line AFTER the line field joint at cooler line
location 4.
Plans, Procedures, and WOAs
• ISIM Prime Mass Properties Test Plan, JWST-PLAN-020889
• ISIM handling WOA, JWST-WOA-005903
Test Facility / View of Test
• NASA GSFC B29 SSDIF
Use or disclosure of data contained on this page is subject to the restriction(s) on the title page of this document.GSFC SE Seminar: September 13, 2016 31
Harness Radiator and IEC Integrated to the SIF
Use or disclosure of data contained on this page is subject to the restriction(s) on the title page of this document.GSFC SE Seminar: September 13, 2016 32
ISIM Element and SIF Build Up
Use or disclosure of data contained on this page is subject to the restriction(s) on the title page of this document.GSFC SE Seminar: September 13, 2016 33
ISIM Integrated Functional and Performance
Test Flow
ISIM System Functional Test (SFT) in Air
ISIM System Functional Test (SFT) in Vacuum: Pre-Test
SSDIFAmbient Temp. / Ambient Pressure
SES
ISIM System Abbreviated Functional Continuity (AFC) Test
ISIM Comprehensive Performance Test (CPT) Part 1
ISIM Comprehensive Performance Test (CPT) Part 2
ISIM System Functional Test (SFT) in Vacuum: Post-Test
Ambient Temp. / Ambient Pressure Ambient Temp. / Vacuum
Cryo Temp. / Vacuum Cryo Temp. / Vacuum
Ambient Temp. / Vacuum
Ambient Temp. / Ambient Pressure
ISIM System Abbreviated Functional Continuity (AFC) Test - Practice Run
Use or disclosure of data contained on this page is subject to the restriction(s) on the title page of this document.GSFC SE Seminar: September 13, 2016 34
Signal Continuity / Component Operability
FPE Configurations – excluding FGS/NIRISS
Use or disclosure of data contained on this page is subject to the restriction(s) on the title page of this document.GSFC SE Seminar: September 13, 2016 35
Signal Continuity / Component Operability
FPE/ICE Configurations – FGS/NIRISS
Use or disclosure of data contained on this page is subject to the restriction(s) on the title page of this document.GSFC SE Seminar: September 13, 2016 36
ISIM Element Just Prior to Move to the SES
Use or disclosure of data contained on this page is subject to the restriction(s) on the title page of this document.GSFC SE Seminar: September 13, 2016 37
ISIM Element Being Lowered in the SES
Use or disclosure of data contained on this page is subject to the restriction(s) on the title page of this document.GSFC SE Seminar: September 13, 2016 38
ISIM Element in SES
Use or disclosure of data contained on this page is subject to the restriction(s) on the title page of this document.GSFC SE Seminar: September 13, 2016 39
ISIM Element in SES Just Prior to Pump Down
August 2013
Use or disclosure of data contained on this page is subject to the restriction(s) on the title page of this document.GSFC SE Seminar: September 13, 2016 40
ISIM Cryo-Vacuum Test Configuration
Vacuum Shell (9m diam x 13m tall)
GHe Shroud, 20K
IEC (inside, 293K)ISIM (inside, 43K)
SES Integration Fixture with sTMS
N2 Shroud
Vibration Isolators (not used)
OSIM (inside cryopanels, 100K)
GHe Shroud
OTE Simulator (OSIM)
Cryocooler GSE
Use or disclosure of data contained on this page is subject to the restriction(s) on the title page of this document.GSFC SE Seminar: September 13, 2016 41
OSIM Into the SES for Cryo Calibration
Use or disclosure of data contained on this page is subject to the restriction(s) on the title page of this document.GSFC SE Seminar: September 13, 2016 42
OSIM in the SES
Use or disclosure of data contained on this page is subject to the restriction(s) on the title page of this document.GSFC SE Seminar: September 13, 2016 45
Detector Degradation – The issue
■ In January 2011 NIRCam reported that
their 5µm cutoff detector arrays had
degraded over a two year period.
■ Degradation was a significant increase in
hot pixels (high dark current).
■ Nature of degraded pixels is an “RC”
response with a high residual dark
current.
■ All JWST flight 5µm cutoff detectors and
at least two flight 2.5µm cutoff detector
appear to be degrading.
Use or disclosure of data contained on this page is subject to the restriction(s) on the title page of this document.GSFC SE Seminar: September 13, 2016 46
■ Ideally, the hardware within the three components would not be changed from the start of CV2 through the conclusion of CV3 and only the three components would be mated and demated for various tests.
■ Reality is that some hardware will need to be changed after CV2 and beforemechanical environmental, EMI/EMC, and cryo-vac performance testing
■ At the PER, we presented:
– What are we going to do?
– What are the risks?
– How are the risks mitigated?
■ CV3 - This test will verified the ISIM System in its final configuration after environmental exposure and provided the post-environmental performance verification test
■ All hardware changes between CV2 and CV3 were fully verified
ISIM Element I&T Flow
Use or disclosure of data contained on this page is subject to the restriction(s) on the title page of this document.GSFC SE Seminar: September 13, 2016 47
ISIM Element Environmental Testing
ISIM PrimeVibe test
[Prime Vibe Fix.]
ISIM ElementAFC/SFT 5
Cryo-Vac Test #3 SFT 6[ITP]
Delivery ISIM Element (ISIM
Prime, HR, ICDH and IEC) to OTIS
HRRetrofit KMs / Mass Props
SIF (Base Frame)
IEC (ISIM
Electronics Compartment)
ISIM Harness Radiator
IECRework boxes /
Other work
M
EICIT / IVT (IEC with
Reworked boxes and
HR with Harnesses)
[FIESTA]
ISIM PrimeSI Integration
[S-ITP]
ISIM PrimeRegion 1 HW
changes[S-ITP] KM
ISIM ElementEMI/EMC
[S-ITP]
ISIM ElementAcoustics
- IRSU Powered -[S-ITP]
ISIM ElementAFC [ITP]
M
M M
On Vibe fixture
ISIM PrimeGravity Sag
[HCC fixture]
M
M
SI Rework(rework and some func testing with
reworked eboxes)
FGS / NS Testing
ISIM ElementCryo-Vac Test #2
SIF (Base Frame)
IEC (ISIM
Electronics Compartment)
ISIM Harness Radiator
ISIM ElementAFC
SFT3 / Metrology[S-ITP]
IECMass
Properties
IECVibe Test
- IRSU Powered
HRVibe Test
EICITOn SIF @IEC / HR
Connections
M
IECJackpostrework /
Other work
CompleteConfiguration Change
for CV3Break at ICP 3 and A
M
IVT
NC FPA IVTNS MCE IVTNS FPE IVT
NC FPAAFT
NC ICP 2
MCE IVT
MSS Acceptance
Test
ISIM ElementAFC / SFT4
[S-ITP]
M
HRAcoustics
Test
Use or disclosure of data contained on this page is subject to the restriction(s) on the title page of this document.GSFC SE Seminar: September 13, 2016 48
ISIM CV2 Design
Activity verifies requirement(s) requiring the comparison of
pre- and post-environmental tests
Activity provides data used to close previous PRs and PFRsActivity provides basic health and safety reducing the risk of finding a problem that could have a large impact if not
found until the next test phase
Activity provides continued Model Validation data for system and subsystem items
Activity verifies requirement(s) and leads to a
subsystem’s final verification
Activity verifies requirement(s) and is time critical to obtain a
performance or functional assessment to reduce risk of finding an issue late/CV3.
Higher Priority
Activity verifies requirement(s) and is straightforward to perform in CV2, AND does not need to be repeated in CV3 - doing it now
takes it off the table
Activity provides data for calibration of science data; if not obtained in CV2, becomes High priority for CV3.
Lower Priority
Minimum Test for ISIM CV2:
All other objectives are prioritized:
Use or disclosure of data contained on this page is subject to the restriction(s) on the title page of this document.GSFC SE Seminar: September 13, 2016 49
ISIM Cryo-Vacuum Test 2 Timeline
ISIM Cryovacuum Test #2 Timeline (4/17/2014)
Ther
mal
Pro
file
Test
Det
ails
an
d T
imel
ine
Phase
1 6
Test Start
CooldownDecisionAbbreviated
Continuity
System Functional (Vac)
SES Pumpdown
Outgassing Cert
Cooldown End
ISIM Structure160>Ts>140 Range
CCH Active
MIRI Detector Heaters Active
MIRI SI>60 Range
IEC EB Cycle - Test1 Cycle over Operating Range
9
CPT Part 1
5.7OSIM Checkout
4
OSIM+SI Checkout (& Focusing)
Achieve TB 1-C-0-0
2.5
Optical Baseline
2.5
NIRSpec Performance
9.7
NIRCam Performance
Achieve TB 1-H-0-0
Raise SI boundary Temps to Hot operational conditions.
4
CPT Part 2
3.1
Power ON Trim
Htrs
Achieve TB 1-C-1-0
2
OSS SI Operations
Test EndNIRISS
Performance
1.9
Guider Performance
1.5
MIRI Performance
11
Warm Up Decision
Warm Up
2
System FunctionalPost-Test (Vac)
SES Re-Press
12
OSS Day in the Life
OSIM Ambient Checks
1
NIRCam ASIC Tuning
1 1 1
Take Darks
Evaluate
Initial Flux Evaluation
HR Q to OTE Test
1
NIRSpec ShortDetection
Optical Baseline
2.6
NIRCamAlignment
Close MIRI CCC
OSS FGS Guiding
Checkout
1.5
EM SSR Test 1.5
EM SSR Test
7D 14 D 21 D 28 D 35 D 42 D 49 D 56 D 63 D 70 D 77 D 84 D 91 D 98 D 105 D 112 D
4
MIRI CC Heat Load (Initial)
2
CCH Fail-OverTest
Power ON Trim Htrs
Achieve TB 1-H-1-0
MSA Heaters Active
2.5
Co-BoresightOptical Test
Nspec=140KNspec=280K
Nspec Stable
MIRI Stable
FGSStable
NCamStable
SI Stability Points
1
2.5
5.6
4
(5) (1) (5)
0
20
40
60
80
100
120
140
160
180
200
220
240
260
280
300
0 5 10 15 20 25 30 35 40 45 50 55 60 65 70 75 80 85 90 95 100 105 110
Tem
pera
ture
(K)
Time (Days)
ISIM Structure Average FGS Bench NIRCam OA
NIRCam POM NIRSPEC OA NIRSPEC FPA/ASIC
NIRSpec POM MIRI Bench MIRI 18K Stage
MIRI POM Qmeter Max Helium Shroud
ITP SIF Average IEC Max
PM Average OSIM Shroud PM Gradient
ISIM Gradient MIRI Shield Structure Average Facility Shroud
0
20
40
60
80
100
120
140
160
180
200
220
240
260
280
300
0 5 10 15 20 25 30 35 40 45 50 55 60 65 70 75 80 85 90 95 100 105 110
Te
mp
era
ture
(K
)
Time (Days)
ISIM Structure Average FGS Bench NIRCam OA
NIRCam POM NIRSPEC OA NIRSPEC FPA/ASIC
NIRSpec POM MIRI Bench MIRI 18K Stage
MIRI POM Qmeter Max Helium Shroud
ITP SIF Average IEC Max
PM Average OSIM Shroud PM Gradient
ISIM Gradient MIRI Shield Structure Average Facility Shroud
(1)
6
MIRI CC Leak Detection w/ RGA
2
MIRI Cold Detector
FGS Guiding on OSIM Sources while moving
SI mechanisms
FGS Guiding on Bad Pixel
G1
Tra
ck
G2
Tra
ck
G1
Fin
e G
uid
e
G2
Fin
e G
uid
e
NIRCam Darks
8
Guider/NIRISSASIC Tuning
2
Fault Mgmt
OSIM ADMMeasurements
2
MIRI CC Heat Load (Follow-On)
Co-BoresightSet-Up
Power OFF
FGS & NS
Achieve TB 0-C-0-0[FGS-NS)
Power ON
FGS & NS
Power OFFNC
Achieve TB 0-C-0-0[NC)
Power ONNC
ADM & MCA flux
OSIM (Frame)=102K
Power OFF
Trim Htrs
Power OFF
Trim Htrs
Pupil Shear ReviewR1-OSIM Sweep
ReviewR2-SI Focus Mech
Review
R3-OSIM multi-field focus
Review
FinalPerformance
Use or disclosure of data contained on this page is subject to the restriction(s) on the title page of this document.GSFC SE Seminar: September 13, 2016 50
ISIM Cryo-Vacuum Test 2 Procedure List
NumbProcedure
(Current Rev)Procedure Name Baseline Plan Notes
1 JWST-PROC-022529 ISIM Element Cryo-Vacuum Test #2 Note (1) [was 016116]
2 JWST-PROC-016387 JWST ISIM Long System Functional Test (Air) Note (1) [was 016393]
3 JWST-PROC-016353 ISIM Long System Functional Test in Vacuum (Pre-Test) Note (1) [was 016394]
4 JWST-PROC-016358 ISIM Long System Functional Test in Vacuum (Post-Test) Note (1) [was 021887]
5 JWST-PROC-016395 ISIM Comprehensive Performance Test Part 1 Revise/release existing Revise to RevA
6 JWST-PROC-016497 ISIM Comprehensive Performance Test Part 2 Revise/release existing Revise to RevA
7 JWST-PROC-016249JWST ISIM System Abbreviated Functional Continuity (AFC) Test
Procedure Revise/release existing Revise to RevC
8 JWST-PROC-016302 OSIM Final Checkout Test Procedure Revise/release existing Revise to RevA
9 JWST-PROC-016304 OSIM Initial Flux Evaluation Procedure New procedure
10 JWST-PROC-016305 JWST CV2 OSIM & SI Checkout Test Procedure Note (1) [was 016313]
11 JWST-PROC-016307 NIRCam Optical Alignment Test Procedure ISIM Cryo-Vacuum Test 2 New procedure
12 JWST-PROC-016344 JWST SIDECAR ASIC and SCA Tuning Procedure Note (1) [was 016314]
13 JWST-PROC-016346 NIRSpec MCA Short Detection Test Procedure New procedure
14JWST-PROC-023678 FGS-NIRISS Performance Characterization Test Procedure, ISIM Cryo-
Vacuum Test 2
Note (1)
[was 016434]
15 JWST-PROC-016360 MIRI Cryo-Cooler Heat Load Verification Test in CV2 New procedure
16 JWST-PROC-016306 ISIM Optical Baseline Procedure Note (1) [was 016434]
17 JWST-PROC-016308 NIRCam Performance Characterization Test Procedure New procedure [was 016433]
18 JWST-PROC-016318 NIRSpec Performance Characterization Test Procedure New procedure
19JWST-PROC-016309 MIRI Performance Characterization Test Procedure, ISIM Cryo-
Vacuum Test 2
Note (1)
[was 016447]
20JWST-PROC-023679 FGS-Guider Performance Characterization Test Procedure, ISIM Cryo-
Vacuum Test 2
Note (1)
[was 016435]
21 JWST-PROC-016335 JWST ISIM Co-Boresight Test Procedure New procedure
22 JWST-PROC-021687 MIRI Cryo-Cooler MIRI Detector Lower Temperature Test Procedure New procedure M. Ressler/JPL
A. Glasse / EC
23 JWST-PROC-016340 Warm Dark Cryo-2 Test Procedure Note (1) [was 016315]
24JWST-PROC-016341 GS&O/OSS SI Characterization Test Procedure Note (1)
[was 016317]
25JWST-PROC-016343 Cryo-2 Day in the Life Procedure Note (1)
[was 016273]
26 JWST-PROC-016361 OSS FGS Guiding Checkout New procedure
27 JWST-PROC-TBD JWST ISIM Ambient Fault Management Test Note (1) [was 016494]
Use or disclosure of data contained on this page is subject to the restriction(s) on the title page of this document.GSFC SE Seminar: September 13, 2016 5151
CV2 Planned vs Actual Test Flow:
CV2 Planned
CV2 Actual
Use or disclosure of data contained on this page is subject to the restriction(s) on the title page of this document.GSFC SE Seminar: September 13, 2016 52
■ SCRAMBLED INTEGRATION
52
Parallel observations – Data Scramble
REGULAR INTEGRATION
Use or disclosure of data contained on this page is subject to the restriction(s) on the title page of this document.GSFC SE Seminar: September 13, 2016 5353
Data Scrambling Context
FGS
MIRI
NIS
NRC
NRS
IRSU ICDH HW SSR
ISIM FSW
UserCommands
SSR Mgr
SSR Sorter
FITS Writer
FPE Data Acq
Real-Time Ground System
CECIL Scripts
R-T Log
What the FSW Eng wants to
seeOSS
What the FSW Eng actually
sees
What the SI Eng/Scientist
sees
Visit Files
SSR Image Dump Files• Header/Data/Footer• Many SCAs interleaved
64-PixelFPE packets
Use or disclosure of data contained on this page is subject to the restriction(s) on the title page of this document.GSFC SE Seminar: September 13, 2016 54
CV2 Test Summary
■ CV2 started on June 16, 2014 with Abbreviated Functional Continuity
Test
■ Facility issues (power and chilled water) and the SuROM anomaly
(during CPT Part 1 Test) early in the test flow triggered a re-
arrangement of the CV2 timeline
– The higher priority tests from each of the SI Performance
Characterization Test Procedures were moved earlier in the flow,
before the CPT Part 2 Test.
– The lower priority tests (science calibrations) were left to the end of
the cold operating temperature plateau.
■ All tests at the cold operating temperature were completed by 9/14.
The transition to the hot operating temperature started on 9/15 and the
Co-Boresight Test was performed.
Use or disclosure of data contained on this page is subject to the restriction(s) on the title page of this document.GSFC SE Seminar: September 13, 2016 55
■ Best focus with analysis uncertainty estimates for all SI’s
■ First cut at (OSIM + SI) WFE and first cut back-out of SI-only WFE for the MIMF field points, plus ISIM_1 (NIRSpec
fixed slit)
■ Uncertainties: variation in WFE determined by each analyst (all SI’s) and comparison to the variation at the end of
CV1RR for MIRI, FGS and NIRISS
■ First cut at (OSIM + SI) WFE and first cut back-out of SI-only WFE over the full fields of NIRCam and MIRI
– Uncertainties: variation in WFE determined by each analyst (for NIRCam) and comparison to the variation at
the end of CV1RR for MIRI
■ CV-environment pupil shear for each SI and comparison to results from CV1RR where available
– First cut at on-orbit pupil shear for each SI
■ CV-environment FOV/boresight for each SI and comparison to results from CV1RR where available
– First cut at on-orbit FOV/boresight for each SI (PFR on NIRCam LW B)
■ Check of Co-boresight data quality
– (We will only have time to confirm that the data quantity and quality is sufficient to perform the analysis relevant
to co-boresight requirements)
■ ISIM Balance #3 (TB 1H10) is with SI’s ON, trim heaters ON
– Fraction of heat at SI that gets to radiator end;
– Strap end-to-end thermal conductance
■ ISIM Balance #4 (TB 1H00) is with SI’s ON, trim heaters OFF, to determine:
– Fraction of heat at SI that gets to radiator end;
– Strap end-to-end thermal conductance
■ PFR Investigations complete
■ Data quality and completeness and is sufficient for any “Problems” that required additional data
■ Summary of departure from expectation
Warm-Up Decision Point Success
Criteria
All required testing was accomplished in CV2 before warm-up
Co
llect
ed a
ll n
eed
ed d
ata
Use or disclosure of data contained on this page is subject to the restriction(s) on the title page of this document.GSFC SE Seminar: September 13, 2016 56
ISIM Element Environmental Testing
ISIM PrimeVibe test
[Prime Vibe Fix.]
ISIM ElementAFC/SFT 5
Cryo-Vac Test #3 SFT 6[ITP]
Delivery ISIM Element (ISIM
Prime, HR, ICDH and IEC) to OTIS
HRRetrofit KMs / Mass Props
SIF (Base Frame)
IEC (ISIM
Electronics Compartment)
ISIM Harness Radiator
IECRework boxes /
Other work
M
EICIT / IVT (IEC with
Reworked boxes and
HR with Harnesses)
[FIESTA]
ISIM PrimeSI Integration
[S-ITP]
ISIM PrimeRegion 1 HW
changes[S-ITP] KM
ISIM ElementEMI/EMC
[S-ITP]
ISIM ElementAcoustics
- IRSU Powered -[S-ITP]
ISIM ElementAFC [ITP]
M
M M
On Vibe fixture
ISIM PrimeGravity Sag
[HCC fixture]
M
M
SI Rework(rework and some func testing with
reworked eboxes)
FGS / NS Testing
ISIM ElementCryo-Vac Test #2
SIF (Base Frame)
IEC (ISIM
Electronics Compartment)
ISIM Harness Radiator
ISIM ElementAFC
SFT3 / Metrology[S-ITP]
IECMass
Properties
IECVibe Test
- IRSU Powered
HRVibe Test
EICITOn SIF @IEC / HR
Connections
M
IECJackpostrework /
Other work
CompleteConfiguration Change
for CV3Break at ICP 3 and A
M
IVT
NC FPA IVTNS MCE IVTNS FPE IVT
NC FPAAFT
NC ICP 2
MCE IVT
MSS Acceptance
Test
ISIM ElementAFC / SFT4
[S-ITP]
M
HRAcoustics
Test
Use or disclosure of data contained on this page is subject to the restriction(s) on the title page of this document.GSFC SE Seminar: September 13, 2016 57
ISIM Prime Gravity Sag Test
Objective of Test
Level of Test
Known Deviations from Flight Configuration
• Measure distortions (information) of the ISIM Structure and exterior targets on the SIs with ISIM Prime in a +V1 and –V1 orientation.
• The measurements taken during the test are used to validate the analytical gravity sag modeling (because we can't measure anything internal during the gravity test)
• Use the analytical modeling to do on-orbit predictions based on ground testing
• n/a
• Flight MIRI Shield will not be present (so that MIRI metrology targets can be seen)
• GSE HSA may still be integrated to ISIM Prime as opposed to the flight HSA
• GSE metrology targets are installed for this operation
• MIRI Cooler Line supports are not flight• MIRI Cooler Line will be replaced with one that
comes with the flight HSA• RTG saddle connection (cable ties vs machined
piece) • Non-bonded OTIS accel mounts not on• Flight ICP-A Micrometeoroid shields will not be
present
Plans, Procedures, and WOAs
• ISIM Prime Gravity Release Test Plan, JWST-PLAN-021021
• ISIM Prime Metrology Procedure, JWST-PROC-018065
Test Facility / View of Test
• NASA GSFC, Building 29 SSDIF
Use or disclosure of data contained on this page is subject to the restriction(s) on the title page of this document.GSFC SE Seminar: September 13, 2016 58
ISIM Gravity Sag Test
Use or disclosure of data contained on this page is subject to the restriction(s) on the title page of this document.GSFC SE Seminar: September 13, 2016 59
■ Detector Subsystem changeout
■ MSA FM2 + MCE repair
■ OA cover replacement
NIRSpec Major HW Changes after CV#2
MSA FM2 OA coverFPA, ASICs and harness
NIRSpec with closed OA cover January 28th 2015
Use or disclosure of data contained on this page is subject to the restriction(s) on the title page of this document.GSFC SE Seminar: September 13, 2016 60
Successful FGS “Halftime Show” at GSFC
■ Detector Subsystem change out
■ Motor Replacement
■ Grism replacement
■ Harness rework
■ FPGA Change
Use or disclosure of data contained on this page is subject to the restriction(s) on the title page of this document.GSFC SE Seminar: September 13, 2016 61
■ Three changed SCAs due to vibe issues
■ All FPA masks were replaced
■ FPE boxes each had a board replaced due to a capacitor failure that
could propagate and take down an entire FPE box
NIRCam Post CV2 Changes
Use or disclosure of data contained on this page is subject to the restriction(s) on the title page of this document.GSFC SE Seminar: September 13, 2016 62
ISIM Env. Testing
CV3CV1RR CV2
MIRI Focal Plane Harnesses
PFR-135• Loss of MIRI Imager exposures Replace Imager flight harness
with Imager spare
4 PFR-163• Unusable MIRI Imager exposures Replace Imager flight harness
with LW spare
5
MIRI Focal Plane Electronics
Known Issues at FPS delivery to OA• Corrupted detector frames• Temp sensor idiosyncrasies
PFR-124• FPE ground path
anomaly
FPE Retrofit
PFR-164 • Command Failure• Temp Sensor Anomaly• FPM Anneal Errors
Open Work• FPE Repair
recommended by PFR-164 ARB
6 6 6 7 7
MIRI Timeline of Hardware Changes
Planned Work(presented at PER)
New Work(response to PR/PFR)
Legend
MIRI Optical Module
Replace MIRI OM Top MLI
Remove OM strain gauge connectors
1 2PR JWST-WOA-006409-005• Restrain accelerometer
harness
3
20
11
20
12
20
13
20
14
20
15
20
16
20
17
Integration and Testing
OBA delivered to ISIMFPS delivered to OA
PER PSR
Use or disclosure of data contained on this page is subject to the restriction(s) on the title page of this document.GSFC SE Seminar: September 13, 2016 63
ISIM Heat strap issue is the ISIM critical path
■ NIRCam heat strap performance during CV-2 was in spec but out of family WRT the other instruments– This anomaly prompted a check of the strap joint fastener torques – Lose bolts were found– Subsequent examination revealed lose bolts throughout the heat strap
system● Since lose fasteners were found everywhere, they may not explain
the anomalous NIRCam strap performance■ Several separate issues are raised by the above observations:
1. Loss of mechanical preload due to design flaws / failed components
2. Loss of mechanical preload due to long term material creep3. Loss of thermal conductivity due to workmanship issues at strap to
end-block interface
Use or disclosure of data contained on this page is subject to the restriction(s) on the title page of this document.GSFC SE Seminar: September 13, 2016 64
MIRI optics assembly and flight HSA
Heat strap work paces installation of the MIRI thermal shield
Use or disclosure of data contained on this page is subject to the restriction(s) on the title page of this document.GSFC SE Seminar: September 13, 2016 65
■ L2 Environment– Defined in JWST Environmental
Specification, EV1-0074● Initial definition early in JWST program indicated
relatively benign environment● Newer model, L2 - Charged Particle
Environment (L2-CPE), Model Released in 2004 shows significantly higher electron fluxes at high energies than the previous LRAD model
■ Concern– Lots of charged particles at L2– Exposed dielectrics can collect particles and
build up large potentials (charging a capacitor)
– When potential reaches the dielectric breakdown voltage of the material, potentially damaging discharges can occur
– ~1/3 of all spacecraft failures and anomalies due to the space environment result from plasma-induced charging
– Primary concern are the Region 2-1 harnesses
Space Charging
AmbientIons &Electrons
SputteredIons
EnergeticIons Magnetospheric
ElectronsBackscatteredElectrons
SecondaryElectrons
UV Sunlight
Photo-emittedElectrons
Use or disclosure of data contained on this page is subject to the restriction(s) on the title page of this document.GSFC SE Seminar: September 13, 2016 66
Space Charging
Insure all harnesses can withstand the induced current from such a discharge
Added black Kapton XC tape to Microshutter and MIRI FPHs
All harnesses have black Kapton Jackets
Finite resistance between jacket and shell offers bleed path for surface charge
Micrometeoroid Protection
MSS Shielding Added:
MIRI FPE harness between harness radiator and diagonal BSF beam
MIRI FPE harness between diagonal BSF beam and ICP-A
MIRI FPE harness inboard from ICP-A, i.e., interior to the ISIM enclosure (also a new request from me)
NIRSpec FPE harness between the harness radiator and BSF diagonal beam or inboard from ICP-A
Harnesses also shielded by blanketing between ICP-2 and the HR
All harnesses meet the POS requirements of ISIM-1557.
JWST-RPT-029291, “ISIM Harness Meteoroid-Environment Probability of Success”
Space Charging and Micrometeoroid Risk
Use or disclosure of data contained on this page is subject to the restriction(s) on the title page of this document.GSFC SE Seminar: September 13, 2016 67
ISIM Prime Successfully reintegrated after
changes
ISIM Prime: April 2015
Use or disclosure of data contained on this page is subject to the restriction(s) on the title page of this document.GSFC SE Seminar: September 13, 2016 68
ISIM Integration and NIRSpec Team
Use or disclosure of data contained on this page is subject to the restriction(s) on the title page of this document.GSFC SE Seminar: September 13, 2016 69
ISIM Element Environmental Testing
ISIM PrimeVibe test
[Prime Vibe Fix.]
ISIM ElementAFC/SFT 5
Cryo-Vac Test #3 SFT 6[ITP]
Delivery ISIM Element (ISIM
Prime, HR, ICDH and IEC) to OTIS
HRRetrofit KMs / Mass Props
SIF (Base Frame)
IEC (ISIM
Electronics Compartment)
ISIM Harness Radiator
IECRework boxes /
Other work
M
EICIT / IVT (IEC with
Reworked boxes and
HR with Harnesses)
[FIESTA]
ISIM PrimeSI Integration
[S-ITP]
ISIM PrimeRegion 1 HW
changes[S-ITP] KM
ISIM ElementEMI/EMC
[S-ITP]
ISIM ElementAcoustics
- IRSU Powered -[S-ITP]
ISIM ElementAFC [ITP]
M
M M
On Vibe fixture
ISIM PrimeGravity Sag
[HCC fixture]
M
M
SI Rework(rework and some func testing with
reworked eboxes)
FGS / NS Testing
ISIM ElementCryo-Vac Test #2
SIF (Base Frame)
IEC (ISIM
Electronics Compartment)
ISIM Harness Radiator
ISIM ElementAFC
SFT3 / Metrology[S-ITP]
IECMass
Properties
IECVibe Test
- IRSU Powered
HRVibe Test
EICITOn SIF @IEC / HR
Connections
M
IECJackpostrework /
Other work
CompleteConfiguration Change
for CV3Break at ICP 3 and A
M
IVT
NC FPA IVTNS MCE IVTNS FPE IVT
NC FPAAFT
NC ICP 2
MCE IVT
MSS Acceptance
Test
ISIM ElementAFC / SFT4
[S-ITP]
M
HRAcoustics
Test
Use or disclosure of data contained on this page is subject to the restriction(s) on the title page of this document.GSFC SE Seminar: September 13, 2016 70
Goddard ISIM Metrology Survey
Laser Radar(MV260)
Laser TrackerLeica LT840
ISIM
Stations Used:• 9 Laser Radar (LR)
stations
• 4 Laser Tracker (LT) stations
Duration of all measurements ~10 days
~23,000 LR points measured (enhanced metrology mode)
~200 LT points (spatial trigger mode)
Use or disclosure of data contained on this page is subject to the restriction(s) on the title page of this document.GSFC SE Seminar: September 13, 2016 71
+V2
+V3
MIRIPOM
NIRISS(TF)
POM
MATF1 MATF2
MATF3 MATF4
MATF5
IATF1 IATF2
IATF3
IATF4
L1 L2
L2L1
L1 L2
L1
L2
mc
rc
mc
rc
mc
rc
rcFM3+ƟV2
FM3-ƟV2
FM3+ƟV3
FM3-ƟV3
View Looking UpFrom OSIM
IATF & MCAADM Targets
MCAPDI
rc1rc2
& Screen
rc3
L1L2 mc
Si Flux Mon
InSb Flux Mon
FGS 2 (B)POM
NIRSpecPOMNIRCam
BPOM
FGS 1 (A)POM
NIRCamA
POM
JWST PV-046839
CV2 ISIM, MATF, IATF Test Configuration
Use or disclosure of data contained on this page is subject to the restriction(s) on the title page of this document.GSFC SE Seminar: September 13, 2016 72
Science Instrument pupil alignment reference
(PAR)
PARs are used at ambient to trend pupil changes, not calculate absolute pupil alignment
MIRI
Guider
NIRSpec
NIRISS
V3
V2
Use or disclosure of data contained on this page is subject to the restriction(s) on the title page of this document.GSFC SE Seminar: September 13, 2016 75
STOP Models
Thermal ModelModel Format : Thermal Desktop
Structural ModelModel Format: NASTRAN
NIRCam Short
Wavelength Channel
MIRI Imager
Mode
NIRSpec Camera
Imaging Mode
Fine Guider
Channel A
Optical ModelsModel Format: Code V, LOM*
OSIM
*LOM – Linear Optical Model developed
in-house by GSFC optical analysis team.
Use or disclosure of data contained on this page is subject to the restriction(s) on the title page of this document.GSFC SE Seminar: September 13, 2016 76
STOP Analysis Process
Integrated
Thermal Model
Thermal
Analysis
Temperatures
(thermal)
Integrated
Structural
Model
Structural
Analysis
Displacements
of Tracking
Nodes
Instrument
Optical Model
Optical
Analysis
Optical
Performance
(WFE, Focus,
Pupil Shear,
LOS)
Thermal Desktop Thermal Desktop
NASTRAN NASTRAN
Map Temps to
Structure FEM
Temperatures
(structural)
Perturbations
(optical)
Generate
Perturbations
for Optical
Model
Discipline
Model
Analysis/
Process
Intermediate
Results
Final Results
Th
erm
al
Str
uctu
ral
Op
tica
l
Ideas/TMG,
Python
EXCEL
Code V, Linear Optical
Model (LOM),
Spreadsheet Math Models
Code V, Linear Optical
Model (LOM),
Spreadsheet Math Models
Use or disclosure of data contained on this page is subject to the restriction(s) on the title page of this document.GSFC SE Seminar: September 13, 2016 77
Load Cases and Analysis Objectives
Note: Table lists primary load cases ran. Additional load cases were ran for studies and benchmarking.
Use or disclosure of data contained on this page is subject to the restriction(s) on the title page of this document.GSFC SE Seminar: September 13, 2016 78
ISIM Element Environmental Testing
ISIM PrimeVibe test
[Prime Vibe Fix.]
ISIM ElementAFC/SFT 5
Cryo-Vac Test #3 SFT 6[ITP]
Delivery ISIM Element (ISIM
Prime, HR, ICDH and IEC) to OTIS
HRRetrofit KMs / Mass Props
SIF (Base Frame)
IEC (ISIM
Electronics Compartment)
ISIM Harness Radiator
IECRework boxes /
Other work
M
EICIT / IVT (IEC with
Reworked boxes and
HR with Harnesses)
[FIESTA]
ISIM PrimeSI Integration
[S-ITP]
ISIM PrimeRegion 1 HW
changes[S-ITP] KM
ISIM ElementEMI/EMC
[S-ITP]
ISIM ElementAcoustics
- IRSU Powered -[S-ITP]
ISIM ElementAFC [ITP]
M
M M
On Vibe fixture
ISIM PrimeGravity Sag
[HCC fixture]
M
M
SI Rework(rework and some func testing with
reworked eboxes)
FGS / NS Testing
ISIM ElementCryo-Vac Test #2
SIF (Base Frame)
IEC (ISIM
Electronics Compartment)
ISIM Harness Radiator
ISIM ElementAFC
SFT3 / Metrology[S-ITP]
IECMass
Properties
IECVibe Test
- IRSU Powered
HRVibe Test
EICITOn SIF @IEC / HR
Connections
M
IECJackpostrework /
Other work
CompleteConfiguration Change
for CV3Break at ICP 3 and A
M
IVT
NC FPA IVTNS MCE IVTNS FPE IVT
NC FPAAFT
NC ICP 2
MCE IVT
MSS Acceptance
Test
ISIM ElementAFC / SFT4
[S-ITP]
M
HRAcoustics
Test
Use or disclosure of data contained on this page is subject to the restriction(s) on the title page of this document.GSFC SE Seminar: September 13, 2016 79
IEC Mass Properties
Objective of Test
Level of Test
Known Deviations from Flight Configuration
• Provide a measured mass of the IEC• Provide information used to calculate the final
delivered mass and CG of the IEC
• n/a
• FLIGHT DITCE box is not present for this measurement.
• The flight lock NEA are not present for this test.• The flight on-orbit flexures are not present for this
test• Flight baffles may not be present depending on
timing of measurement (if tied to vibe test handling, the will be present)
• Note that the Towel bar harness supports should be present for this test but have not been delivered yet
Plans, Procedures, and WOAs
• ISIM IEC Mass Properties Test Plan
Test Facility / View of Test
• NASA GSFC, Building 29, SSDIF
Use or disclosure of data contained on this page is subject to the restriction(s) on the title page of this document.GSFC SE Seminar: September 13, 2016 80
IEC Vibration Test
Objective of Test
Level of Test
Known Deviations from Flight Configuration
• Verify minimum workmanship standards have been met by subjecting the IEC to the low frequency structural dynamic spectrum of the launch environment
• Provide data for FEM verification
• Protoflight (5-100 Hz)
• FLIGHT DITCE box is not present for this test• Mass sim is used
• The flight lock NEA are not present for this test• The flight on-orbit flexures are not present for this
test• No flight harnesses are connected to EXTERIOR of
IEC (HR end or OTE end)• We may need to use a harness sim on ICP-2
end to load towel bar and connector (harness with no pins)
Plans, Procedures, and WOAs
• ISIM Element Level IEC Vibe Test Plan• Facility test procedure based on plan
Test Facility / View of Test
• NASA GSFC, Building 7, Rm 028
Use or disclosure of data contained on this page is subject to the restriction(s) on the title page of this document.GSFC SE Seminar: September 13, 2016 81
Harness Radiator Mass Properties
Objective of Test
Level of Test
Known Deviations from Flight Configuration
• Provide a measured mass of the IEC• Provide information used to calculate the final
delivered mass and CG of the IEC
• n/a
• The HR can NOT be picked up and weighed as an assembly because it is required to be assembled to a flight or GSE frame – otherwise, the HR doesn’t exist as an assembly.
• At the ISIM level, the GSE frame is so heavy (made of invar for CTE reasons) that it swamps the mass of the HR and would make a measurement unreliable.
• Measurements• During the HR kinematic mount retrofit – set for
post CV2 – the HR team will measure as many individual components or subassemblies as possible and we will compare that to the CAD estimates/predictions.
• We will use that info to make a CAD prediction for the full HR mass, CG, and MOI and we will use a monte carlo analysis using the measurement tolerances to put a bounding box on the mass and CG.
Plans, Procedures, and WOAs
• ISIM Harness Radiator KM Retrofit WOA
Test Facility / View of Test
• NASA GSFC, B29 SSDIF
Use or disclosure of data contained on this page is subject to the restriction(s) on the title page of this document.GSFC SE Seminar: September 13, 2016 82
Harness Radiator Vibe Test
Objective of Test
Level of Test
Known Deviations from Flight Configuration
• Strength test• Verify minimum workmanship standards have been met
by subjecting the HR to the low frequency structural dynamic spectrum of the launch environment
• Provide data for FEM verification
• Protoflight (5-100 Hz)
• Flight harnesses are replaced by mass simulators• Added the flight harnesses to this test configuration
based on feedback at the PER.• Required unique GSE to deal with free
connector ends.
Plans, Procedures, and WOAs
• ISIM Harness Radiator Vibe Test Plan• Facility test procedure based on plan
Test Facility / View of Test
• NASA GSFC, Building 7, Rm 028 (MB-C 220 #1 Shaker)
Use or disclosure of data contained on this page is subject to the restriction(s) on the title page of this document.GSFC SE Seminar: September 13, 2016 83
Harness Radiator Acoustics Test
Objective of Test
Level of Test
Known Deviations from Flight Configuration
• Verify the ability to survive the launch acoustic environment and to demonstrate acceptable workmanship
• Protoflight
• Flight harnesses are replaced by mass simulators• Added the flight harnesses to this test configuration
based on feedback at the PER.• Required unique GSE to deal with free
connector ends.
Plans, Procedures, and WOAs
• ISIM Harness Radiator Acoustics Test Plan• Facility test procedure based on plan
Test Facility / View of Test
• NASA GSFC, Building 10
Use or disclosure of data contained on this page is subject to the restriction(s) on the title page of this document.GSFC SE Seminar: September 13, 2016 84
ISIM Element Environmental Testing
ISIM PrimeVibe test
[Prime Vibe Fix.]
ISIM ElementAFC/SFT 5
Cryo-Vac Test #3 SFT 6[ITP]
Delivery ISIM Element (ISIM
Prime, HR, ICDH and IEC) to OTIS
HRRetrofit KMs / Mass Props
SIF (Base Frame)
IEC (ISIM
Electronics Compartment)
ISIM Harness Radiator
IECRework boxes /
Other work
M
EICIT / IVT (IEC with
Reworked boxes and
HR with Harnesses)
[FIESTA]
ISIM PrimeSI Integration
[S-ITP]
ISIM PrimeRegion 1 HW
changes[S-ITP] KM
ISIM ElementEMI/EMC
[S-ITP]
ISIM ElementAcoustics
- IRSU Powered -[S-ITP]
ISIM ElementAFC [ITP]
M
M M
On Vibe fixture
ISIM PrimeGravity Sag
[HCC fixture]
M
M
SI Rework(rework and some func testing with
reworked eboxes)
FGS / NS Testing
ISIM ElementCryo-Vac Test #2
SIF (Base Frame)
IEC (ISIM
Electronics Compartment)
ISIM Harness Radiator
ISIM ElementAFC
SFT3 / Metrology[S-ITP]
IECMass
Properties
IECVibe Test
- IRSU Powered
HRVibe Test
EICITOn SIF @IEC / HR
Connections
M
IECJackpostrework /
Other work
CompleteConfiguration Change
for CV3Break at ICP 3 and A
M
IVT
NC FPA IVTNS MCE IVTNS FPE IVT
NC FPAAFT
NC ICP 2
MCE IVT
MSS Acceptance
Test
ISIM ElementAFC / SFT4
[S-ITP]
M
HRAcoustics
Test
Use or disclosure of data contained on this page is subject to the restriction(s) on the title page of this document.GSFC SE Seminar: September 13, 2016 85
ISIM Prime Vibe Test
Objective of Test
Level of Test
Known Deviations from Flight Configuration
• Verify minimum workmanship standards have been met by subjecting the ISIM Prime to the low frequency structural dynamic spectrum of the launch environment
• Provide data for FEM verification
• Protoflight (5 - 100 Hz)
• Flight and GSE purge lines are tied off to ISIM Structure because there is no purge panel (part of STMS for CV testing and part of OTE for flight) available during this test
• 2x non-flight CFMPs (corner fitting metrology plates) will be in integrated at the time of this test
• Flight cooler line ends at cooler line location 4. A GSE line will be added from cooler line location 4a through 1 to properly load line supports 1, 2, 3, and 4a.
• ICP-A : Harnesses are attached on ISIM side but no harnesses are attached to the HR side
• MIRI and NS FPE harness supports (located between ICP-A and HR) will not have harnesses attached because these harnesses are not present unless ISIM Element (not just Prime) is assembled.
• Harnesses that go to T-ICP-1 (on OTE) will be tied off to FGS ICP-A since the OTE is not present.
Plans, Procedures, and WOAs
• ISIM Prime Vibe Test Plan, JWST-PLAN-020896 • Facility test procedure based on plan
Test Facility / View of Test
• NASA GSFC, Building 7, 028 (MB-C 220 #1 Shaker)
Use or disclosure of data contained on this page is subject to the restriction(s) on the title page of this document.GSFC SE Seminar: September 13, 2016 86
ISIM Element Acoustics Test
Objective of Test
Level of Test
Known Deviations from Flight Configuration
• Verify the ability to survive the launch acoustic environment and to demonstrate acceptable workmanship
• Protoflight (note Risk under review on next slide)
• The ISIM Prime has 4x Non-Flight CFMPs (Corner Fitting Metrology Plates) are still integrated on various -V3 corner fittings
• The IEC DITCE box is not present for this test.• The IEC V2 vents are not present for this test.• The IEC flight baffles (4x) are not present for this test.• The IEC inner and outer conformal shields are not
present for this test.• The IEC flight lock NEA are not present for this test.• The IEC flight on-orbit flexures are not present for this
test• The ISIM Prime, HR and IEC are mounted to the SIF as
opposed to the composite Backplane.• The IEC mounts to the SIF (SES Integration Fixture) are
GSE mounts, not flight launch locks• A GSE purge panel is used to support purge lines (on
STMS Frame)• Flight cooler line on ISIM Prime ends at cooler line
location 4. A GSE line will be added from cooler line location 4a through 1 to properly load line supports 1, 2, 3, and 4a.
Plans, Procedures, and WOAs
• ISIM Element Acoustics Test Plan, JWST-PLAN-021019
Test Facility / View of Test
• NASA GSFC, Building 10 Acoustics Chamber
Use or disclosure of data contained on this page is subject to the restriction(s) on the title page of this document.GSFC SE Seminar: September 13, 2016 87
ISIM Element Acoustic Control vs. Spec
-1.03 dB -1.19 dB
Reference Spec Frequency Range
+1.41 dB
+1.03 dB
Very good control
achieved with
essentially two 1/3
octave bands
outside 1 dB tolerance goal
Use or disclosure of data contained on this page is subject to the restriction(s) on the title page of this document.GSFC SE Seminar: September 13, 2016 88
NIRSpec Microshutter Black “dots” are failed-closed/plugged shutters.
Minor increase failed closed shutters observed after ISIM Protoflight level Acoustics
MSA Performance and Trending
Use or disclosure of data contained on this page is subject to the restriction(s) on the title page of this document.GSFC SE Seminar: September 13, 2016 89
Protoflight Acoustic Test Levels for OTIS
■ Will control chamber to +/- 1 dB to meet AE's minimum spec level (purple
bar level) and uniformity requirements
– Demonstrated tolerance and uniformity during Tent Frame Dry Run Test
115
120
125
130
135
140
145
31.5 63 125 250 500 1000 2000
So
un
d P
ressu
re L
evel
(dB
)
Octave Band Center Frequency (Hz)
Proposed Minimum Protoflight SPL DCI 1/6 PF 85%FF
ISIM actual
SCE PF
OTIS PF
PF waiver
Fill Factor adjustmentMid bands waiver request
Use or disclosure of data contained on this page is subject to the restriction(s) on the title page of this document.GSFC SE Seminar: September 13, 2016 90
■ OTIS tent configuration: notably more attenuation @ high frequencies critical to MSA’s
– Geometry and material choice included and demonstrated improvement
– Microphone quantity, type, placement not equivalent, but minor uncertainty
compared to insertion loss improvement over original contamination bag from
ISIM vibe test
– No appreciable change in attenuation within specified octave bands (31.5 - 2 kHz)
Insertion Loss Improvement Help MSA’s (OTIS)
0
5
10
15
20
25
250 500 1000 2000 4000 8000 16000 32000
Insert
ion
Lo
ss (
dB
)
Frequency (Hz)
Insertion Loss: OTIS vs ISIM
OTIS Tent, Run 22
ISIM Bag, Small frame, Run 44
>8dB
above
16 kHz
No benefit at mid-high frequencies
Use or disclosure of data contained on this page is subject to the restriction(s) on the title page of this document.GSFC SE Seminar: September 13, 2016 91
ISIM Element EMI/ EMC Test
Objective of Test
Level of Test
Known Deviations from Flight Configuration
• Radiated Emissions Testing• Radiated Susceptibility Testing• Conducted Emission (limited)
• Charts with test details follows
• The ISIM Prime has 4x Non-Flight CFMPs (Corner Fitting Metrology Plates) are still integrated on various -V3 corner fittings
• The IEC DITCE box is not present for this test.• The IEC V2 vents are not present for this test.• The IEC flight baffles (4x) are not present for this test.• The IEC inner and outer conformal shields are not
present for this test.• The IEC flight lock NEA are not present for this test.• The IEC flight on-orbit flexures are not present for this
test• The ISIM Prime, HR and IEC are mounted to the SIF as
opposed to the composite Backplane.• The IEC mounts to the SIF (SES Integration Fixture) are
GSE mounts, not flight launch locks• A GSE purge panel is used to support purge lines (on
STMS Frame)• Flight cooler line on ISIM Prime ends at cooler line
location 4. A GSE line will be added from cooler line location 4a through 1 to properly load line supports 1, 2, 3, and 4a.
Plans, Procedures, and WOAs
• JWST/ ISIM EMI/ EMC Control Plan• JWST/ ISIM EMI EMC Test Procedure
Test Facility / View of Test
• NASA GSFC, Building 7, N115 (Anechoic Chamber)
Use or disclosure of data contained on this page is subject to the restriction(s) on the title page of this document.GSFC SE Seminar: September 13, 2016 92
ISIM Level EMI/EMC Tests
■ Test plan defined in ISIM EMC Control Plan, JWST-PLAN-004633,
section 3.3 – All Successfully Executed!
– Conducted tests (power subsystem compatibility)
– Radiated tests (communications subsystem compatibility)
– Self-compatibility/crosstalk
MIRI FPE
OTE ACS
RWA
(x6)
Propulsion (Bi-Prop)
SCATs (x4)
MRE-1 DTMs
(x8)
Region 1 Region 2(IEC)
Region 3
Legends:
ISIM 1553B-I
Spacewire Discrete-pt to pt
Region 1-(within SI/OA) Region 2-(within IEC) Region 3-(within Spacecraft Bus)
Primary Mirror
Secondary Mirror
Tertiary Mirror
photons Primary Power
FSSE (x2)
NIRCam FPE 1&2
NIRSpec ICE
MIRI FPE
WDE (x6)
CTP
(x2)
NIRSpec
ASICs/FPA
Mech.
FGS
NIRCam
Mech.
MSA
Sunshield
Li Ion
Battery
CSSA
(x4)
VDE
(x2)
IRU (2)
ADU
(x2)
Sunshield
Acts (x8)
RS422
Cold
Junction
Box (x2)
SSR
S/C-ISIM1553B-SI
SAR
(x2)S/A
(5 panels)
S/C 1553B-S
TAU
Motor Switching
Relays: 4-pole
Analog/
BilevelJT
Compressor
Coolant Lines
FGS G2 FPE/ICE
Radiator Heat
Switches
Contn Ctrl Htrs
Cryo Temp
Sensors
G1 ASICs/
FPA/Mech.G2 ASICs/
FPA/Mech.
TF ASICs/
FPA/Mech.
ASICs/FPA 1
MIRIColdheads
Mech.
FPA
ASICs/FPA 2
FGS G1 FPE/ICE
NIRCam ICE
MIRI ICE
FGS TF
FPE/ICE/TCE
CCE-PT
(x2)
CCE-JT
(x2)
ICDH
(x2)
NIRSPEC MCE
IRSU (x2)
NIRSpec FPE
STA (x3)
BAGA
2 axis
Mechanical I/F
DITCE (x2)
FSM Acts
LVDS
PCU
DEU
(x2)
CMU
19
Hexapod
(6 DOF)
CMU
1..18
Hexapod
(7 DOF)
(X18)
CMU
20
Tower
Acts (x2)
FSS (x2)
CCU
ISIM -
Cryocooler
Region 3
Te
mp
Mo
nito
r/R
eso
lve
rs
CMU
20,21
CMU
21Deployment
Acts (x2)
Latch
Acts (x2)
SMSS
Wings
Latch
Acts (x18)
Deployment
Acts (x4)
C&DH
Spacecraft - Region 3
RSA
PT
Compressor
RS485
COMM
TWTA
(x2) SW
SW
(x2)SW
6 d
B
Sp
litte
r
Dip
lexe
rD
iple
xe
r
Gim
ba
l
Asse
mb
ly
Dip
lexe
r
Hyb
rid
Co
up
ler
Hyb
rid
Co
up
ler
Hyb
rid
C
ou
ple
r
Ka
-Ba
nd
Filt
erISO
SC Switch (P/R)MGA Switch
TWTA Switch
BP
F
S-Band
Transponder
(x2)
MGA
S-band
LHCP
HGA
Ka-band
RHCP
SC Omni
S-band
LHCP
OTE Omni
S-band
LHCP
Ka-Band
Modulator
(x2)
Region 3
SPG
EPS
SMS
Cryocooler Region 3 EGSE
SPACECRAFT SIMULATOR
ICDH in S/C bus
ISIM
Flight ICDH outside chamber for EMI;Outside chamber for cryo-vac
FGS NIRISS
Flight DITCE (OTE e-box in IEC) not powered during test
Unit Under Test
Use or disclosure of data contained on this page is subject to the restriction(s) on the title page of this document.GSFC SE Seminar: September 13, 2016 93
ISIM EMI Test Team
Use or disclosure of data contained on this page is subject to the restriction(s) on the title page of this document.GSFC SE Seminar: September 13, 2016 94
ISIM Element Environmental Testing
ISIM PrimeVibe test
[Prime Vibe Fix.]
ISIM ElementAFC/SFT 5
Cryo-Vac Test #3 SFT 6[ITP]
Delivery ISIM Element (ISIM
Prime, HR, ICDH and IEC) to OTIS
HRRetrofit KMs / Mass Props
SIF (Base Frame)
IEC (ISIM
Electronics Compartment)
ISIM Harness Radiator
IECRework boxes /
Other work
M
EICIT / IVT (IEC with
Reworked boxes and
HR with Harnesses)
[FIESTA]
ISIM PrimeSI Integration
[S-ITP]
ISIM PrimeRegion 1 HW
changes[S-ITP] KM
ISIM ElementEMI/EMC
[S-ITP]
ISIM ElementAcoustics
- IRSU Powered -[S-ITP]
ISIM ElementAFC [ITP]
M
M M
On Vibe fixture
ISIM PrimeGravity Sag
[HCC fixture]
M
M
SI Rework(rework and some func testing with
reworked eboxes)
FGS / NS Testing
ISIM ElementCryo-Vac Test #2
SIF (Base Frame)
IEC (ISIM
Electronics Compartment)
ISIM Harness Radiator
ISIM ElementAFC
SFT3 / Metrology[S-ITP]
IECMass
Properties
IECVibe Test
- IRSU Powered
HRVibe Test
EICITOn SIF @IEC / HR
Connections
M
IECJackpostrework /
Other work
CompleteConfiguration Change
for CV3Break at ICP 3 and A
M
IVT
NC FPA IVTNS MCE IVTNS FPE IVT
NC FPAAFT
NC ICP 2
MCE IVT
MSS Acceptance
Test
ISIM ElementAFC / SFT4
[S-ITP]
M
HRAcoustics
Test
Use or disclosure of data contained on this page is subject to the restriction(s) on the title page of this document.GSFC SE Seminar: September 13, 2016 95
ISIM CV3 Design/Timeline Decisions
Activity provides data used to close previous PRs and PFRs
Activity verifies requirement(s) requiring the comparison of
pre- and post-environmental tests
Activity provides basic health and safety reducing the risk of finding a problem that could have a large impact if not
found until the next test phase
operational planning / observing mode previews
Activity verifies requirement(s) reduce risk of finding an issue at OTIS level tests.
Activity provides data for calibration of on-orbit science data.
Activity provides continued Model Validation data for system and subsystem items
Highest Priority for ISIM CV3:
All other objectives are prioritized based on the consequence of deletion:
Risk
ISIM level or subsystem’s final verification
Risk
Use or disclosure of data contained on this page is subject to the restriction(s) on the title page of this document.GSFC SE Seminar: September 13, 2016 96
ISIM Cryo-vacuum Test #3 As Run Timeline 4/4/2016
Thermal Control
Thermal Balance Points
Key Decision Points
Test
s /
Task
s
Phase
Phase
Phase
Phase
Test Start Cooldown
End
11/10
1 6
CooldownDecision
AbbreviatedContinuity
System Functional +Fault Mgmt (Vac)
SES Pumpdown
Outgassing Cert
CCH Contamination Region
MIRI Detector Heaters Active
MIRI
Use or disclosure of data contained on this page is subject to the restriction(s) on the title page of this document.GSFC SE Seminar: September 13, 2016 97
Path from Requirements to Data Collection
1. Verification Matrix
2. Optical Performance Verification Plan4. Initial Optical Baseline Test Procedure
5. OTP Tracking Spreadsheet 3. CV Test Procedure
Use or disclosure of data contained on this page is subject to the restriction(s) on the title page of this document.GSFC SE Seminar: September 13, 2016 98
■ Offsets generated via Structural, Thermal, Optical Performance (STOP)
modeling
■ Offsets implemented for focus for NIRCam, NIRSpec, Guider, and
NIRISS (and pupil shear for NIRCam)
■ Reference: ISIM CV2 & CV3 STOP: Ground to On-Orbit Gravity and
Thermal Cases, JWST-PRES-027671, R. Gracey
Final Alignment Offset Using SI Mechanisms for
Best Performance On-Orbit
R. Gracey
Use or disclosure of data contained on this page is subject to the restriction(s) on the title page of this document.GSFC SE Seminar: September 13, 2016 99
Sample NIRCam CV3 Results
Learned how long we need to wait after powering on!
ASIC tuning led to good noise behavior.
Mod B DHS alignment –wheel zero points repeated well from CV2.
Linearity data will provide the pipeline correction.
Use or disclosure of data contained on this page is subject to the restriction(s) on the title page of this document.GSFC SE Seminar: September 13, 2016 100
Ghost with the NIRISS SOSS Mode
Use or disclosure of data contained on this page is subject to the restriction(s) on the title page of this document.GSFC SE Seminar: September 13, 2016 101
Harness Thermal Loads into ISIM in CV3
ColdBalance
WarmBalance
Use or disclosure of data contained on this page is subject to the restriction(s) on the title page of this document.GSFC SE Seminar: September 13, 2016 102
■ The CV3 test has run phenomenally well. We will have run for 110 days from start of AFC
(Ambient Functional Checkout) before chamber pump-down to door opening post test –
almost on track with original 104 days prediction
■ Completed all planned activities as well as additional requests at cold operational
temperatures and started the warm up to ambient on Thursday, January 28th
– 214 PRs written to date (compared to 407 in CV2) – 133 of them are ready for closure
– Nearly all software/ops related, no hardware related issues other than the known MIRI
FPE
– ZERO PFRs!
■ Opened the chamber door Saturday, the 13th of February 2016
■ Only one significant event during the test….
ISIM CV3 Summary
1
• Fantastic support from the ISIM test team, Code 549 facilities team and Code 200 facilities team….
THANK YOU ALL!
Use or disclosure of data contained on this page is subject to the restriction(s) on the title page of this document.GSFC SE Seminar: September 13, 2016 103
The Blizzard of 2016
1
Use or disclosure of data contained on this page is subject to the restriction(s) on the title page of this document.GSFC SE Seminar: September 13, 2016 104
1
http://www.theatlantic.com/science/archiv
e/2016/02/snowed-in-at-nasa/433959/
Use or disclosure of data contained on this page is subject to the restriction(s) on the title page of this document.GSFC SE Seminar: September 13, 2016 105
MIRI FPE Design Problem & Solution
SPW-B Haywire to reroute clock through Long Stub
B-Side clock outTo backplane
SPW Slice2 of 2, in Side B Slot FPGA Tx
SPW Slice2 of 2, in Side B Slot
B-Side clock outTo backplane
Current Design
With Haywire
Signal Path
Lift Tx pins
Haywire
Long 5” Stub
Haywire Incorporating Stub
FPGA Tx
Use or disclosure of data contained on this page is subject to the restriction(s) on the title page of this document.GSFC SE Seminar: September 13, 2016 106
FPE Repair and Test Plan
FPE removed from IEC
ETAS SignOff
ISIM PSR
3/8
3/10/16
3d
3/7
3/7/16
1d
3/23/16
IEC EICIT
5/5
5/6/16
2d
Integrate FPE into IEC
5/3
5/4/16
2d
Repair FPE
3/17
3/23/16
4.5d
Receipt Inspect/Test
3/10
3/17/16
5.5d
Remove and ship FPE to JPL
3/8
3/9/16
2d
FPE Test
3/24
3/28/16
3d
FPE receipt inspect/test
5/2
5/2/16
1d
PSR2
5/9
5/9/16
1d
Prep for PSR2
4/25
5/6/16
10d
Pack and ship to
Goddard
4/22
4/22/16
1d
Hold PSR1
4/21
4/21/16
1d
Prep for PSR1
4/20
4/20/16
1d
SIDU Test
4/18
4/19/16
2d
Cold Detector Test
4/8
4/15/16
6dFPE Thermal
Cycles (TCs) with Testing Over Full
Temp Range
4/4
4/7/16
4d
Work Instruction Prep
2/29
3/16/16
13d
TRR
3/22/16
3/3/16
JWST Risk B oard, Project decision
2/29 5d
ARB: Propose solution(s)
2/1
2/26/16
20dComplete PFR-164 related tests
in CV-3
1/11
1/22/16
9d
Root Cause Investig.- test
repair plan
1/11
1/29/16
14d
ISIM Milestones
Investigation/Decision Points
Rework Activities
MIRI FPE PFR 58524 DRAFT PATH FORWARD SCHEDULE
FPE Vibe
3/29
3/30/16
2d
TVAC Test
3/30
4/1/16
3d
SMT Assembly
4/6/16
4/12/16
5d
SPW Spare Build
Board Fab
3/2/16
4/5/16
25d
Thermal Plate Fab
3/2
3/15/16
10d
Hand Assembly
4/13
4/19/16
5d
Safe to Mate
4/20
4/26/1