111
Use or disclosure of data contained on this page is subject to the restriction(s) on the title page of this document. GSFC SE Seminar: September 13, 2016 1 Goddard Space Flight Center Systems Engineering Seminar ISIM Element Environmental Testing and Verification Running the Gauntlet Julie Van Campen JWST/ISIM Lead Systems Engineer September 13, 2016 For Public Release

Goddard Space Flight Center ISIM Element Environmental ... · ISIM utilizes aluminum heat straps for coupling to its radiators The ISIM Heat Strap System was designed, fabricated,

  • Upload
    others

  • View
    3

  • Download
    0

Embed Size (px)

Citation preview

  • Use or disclosure of data contained on this page is subject to the restriction(s) on the title page of this document.GSFC SE Seminar: September 13, 2016 1

    Goddard Space Flight Center

    Systems Engineering Seminar

    ISIM Element Environmental Testing

    and Verification – Running the

    Gauntlet

    Julie Van Campen

    JWST/ISIM Lead Systems Engineer

    September 13, 2016

    For Public Release

  • Use or disclosure of data contained on this page is subject to the restriction(s) on the title page of this document.GSFC SE Seminar: September 13, 2016 2

    JWST Architecture

    James Webb Space Telescope System

    Launch Segment Observatory Segment Ground Segment

    Optical Telescope Element (OTE)

    Spacecraft Element (SE)

    Launch Vehicle

    Payload Adapter

    Launch Site Services

    Science and Operations Center (SOC)

    Common Systems

    Institutional Systems

    Spacecraft Bus

    Sunshield

    Ariane Launcher

    Deep Space NetworkSpace Telescope Science Institute

    Provided by NASA/GSFC

    Provided by NGAS

    Provided by STScI

    Provided by ESA

    Integrated Science Instrument Module (ISIM)

    FGSNIRSpec

    Provided by CSA

    JWST Observatory

    MIRINIRCam

    Mission Systems Engineering

    OTIS – Integrated OTE & ISIM

  • Use or disclosure of data contained on this page is subject to the restriction(s) on the title page of this document.GSFC SE Seminar: September 13, 2016 3

    JWST Observatory Segment Partitions

    Observatory Segment

    Segment Element Subsystem

    Observatory Segment

    Optical Telescope

    Element

    Primary Mirror Subsystem

    Secondary Mirror Subsystem

    Aft Optics Subsystem

    OTE Electronics Subsystem

    Thermal Management

    Subsystem

    Deployment Tower

    Subsystem

    Wavefront Sensing & Control

    Subsystem

    Integrated Science

    Instrument Module Near-Infrared Camera

    Near-Infrared Spectrograph

    Mid-Infrared Instrument

    Fine Guidance Sensor/ NIRISS

    ISIM Structure Subsystem

    Thermal Control Subsystem

    ISIM Command & Data Handling

    Electronics

    ISIM Remote Services Unit

    ISIM Flight Software

    ISIM Electronics Compartment

    ISIM Harness

    MIRI Shield

    Operations Scripts Subsystem

    ISIM Harness Radiator

    Spacecraft

    Element

    Sunshield Subsystem

    Structure and Mechanisms

    Subsystem

    Thermal Control Subsystem

    Electrical Power Subsystem

    Propulsion Subsystem

    Attitude Control Subsystem

    Command and Data Handling

    Subsystem

    Communications Subsystem

    Flight Software

    Electrical Harness

    MIRI Cooling System

  • Use or disclosure of data contained on this page is subject to the restriction(s) on the title page of this document.GSFC SE Seminar: September 13, 2016 4

    Observatory I&T

    Optical Telescope Element

    NG Team

    JPL

    ESA

    U of Az

    LEGEND

    ESA/EC

    CSA

    GSFC

    STScI

    Observatory Systems EngineeringObservatory Performance & Programmatics

    Mission Systems Engineering

    Mission Project Management

    ISIM Enclosure

    MIRI

    Optics System

    Detector Subsystem

    Instrument Control Electronics

    Cooling System

    Management, Systems Engineering

    Instrument FSW

    NIRCam

    Optics Assy.

    Detector Sub-system

    Instrument Control Electronics

    Wavefront Sensing Elements

    Instrument FSW

    NIRSpec

    Optics Assy.

    Microshutter Subsystem & FSW

    Detector Subsystem & FSW

    Instrument Control Electronics

    Instrument FSW

    Spacecraft

    S/C Bus

    Sunshield

    Observatory FSW FGS/TF

    Structure

    I&T

    ISIM Management, Systems, & Science

    OTE Simulator

    IECIRSU FSW Thermal

    Harness

    ICDH

    Optics Assy.

    Instrument Control Electronics

    Instrument FSW

    Detector Subsystem

    JWST Observatory Segment Partners Roles

    Harness Radiator

    OSS MIRI Shield

  • Use or disclosure of data contained on this page is subject to the restriction(s) on the title page of this document.GSFC SE Seminar: September 13, 2016 5

    Integrated Science Instrument Module

    ■ The ISIM system consists of:

    – Five sensor systems

    ● MIRI, NIRCam, NIRSpec, NIRISS, FGS

    – Nine instrument support systems:

    ● Optical metering structure system

    ● Electrical Harness System

    ● Harness Radiator System

    ● ISIM Electronics Compartment (IEC)

    ● Cryogenic Thermal Control System

    ● Command and Data Handling System

    (ICDH)

    ● ISIM Remote Services Unit (IRSU)

    ● Flight Software System

    ● Operations Scripts System

    ISIM is one of three elements that together make up the JWST space vehicle

    • Approximately 1.4 metric tons, ~20% of JWST by mass

  • Use or disclosure of data contained on this page is subject to the restriction(s) on the title page of this document.GSFC SE Seminar: September 13, 2016 6

    ISIM Element

    Hierarchy

    Element Sub-Element Subsystem

    GSFC provided EIDP

    Non-GSFC provided EIDP

    GSFC & Non-GSFC provided EIDPs

    Region 1

    TTHR

    Region 2

    Region 3

    Region 3

    ISIM Element

    ISIM Structure

    MIRI Shield

    FGS

    NIRCam

    ISIM Harnesses

    IHR Structure

    IEC Structure

    IEC ElectronicsBoxes

    ICDH Electronics BoxesFlt-01 & Flt-03

    NIRSpec

    MIRI

    ISIM Thermal Control Subsystem (TCS)

    ISIM Electronics Compartment (IEC)

    ISIM FlightSoftware (IFSW)

    ISIM Command & Data Handling (ICDH)

    ISIM Prime

    ISIM HarnessRadiator (IHR)

  • Use or disclosure of data contained on this page is subject to the restriction(s) on the title page of this document.GSFC SE Seminar: September 13, 2016 7

    ■ ISIM Hardware

    – ISIM Prime, IEC, and HR are delivered to OTIS for integration

    – ICDH Delivered to the Spacecraft (Northrop Grumman)

    ISIM Element at Delivery to OTIS

    ISIM PrimeRegion 1

    (GSE Stand)

    ISIM Electronics CompartmentRegion 2

    Harness Radiator(Thermal Trans Region)

    (GSE Stand)

    (GSE Stand)

  • Use or disclosure of data contained on this page is subject to the restriction(s) on the title page of this document.GSFC SE Seminar: September 13, 2016 8

    ICDH Overview – Region 3/Spacecraft

    Single Board Computer (SBC)

    • Hosts ISIM Flight Software

    Focal Plane Array Processors (FPAP)

    • Simultaneous Science Data

    Processing

    Backplane (not shown)

    Chassis

    • Provides mechanical housing

    and some radiation shielding

    for assemblies

    Power Distribution Unit (PDU)

    Bus Interface Card (BIC)

    • NIRCam, NIRSpec, MIRI FPEs,

    SSR & FPAP SpaceWire

    Interfaces

    • Science Data Storage

    Formatting

    Housekeeping (HKI) Card

    • S/C and ICE 1553B Interfaces

    • ICDH Temperature and Voltage

    Monitoring

  • Use or disclosure of data contained on this page is subject to the restriction(s) on the title page of this document.GSFC SE Seminar: September 13, 2016 9

    ISIM Structure – Qualification Tests

    Optical Stability - Cryoset Test

    2010

    Cryogenic Strength Test - Cryoproof Test

    2011

    Modal Survey

    2011

  • Use or disclosure of data contained on this page is subject to the restriction(s) on the title page of this document.GSFC SE Seminar: September 13, 2016 10

    ISIM Harness Test Flow

    Milliohm Testing

    Hi-Pot Testing

    Thermal Cycle testing

    Hi-Pot Testing

    CleaningBakeoutDelivery to

    ISIM I&T

    FIS Integration

    200-Series

    30

    0-Series

    X-RayDC Bonding

    TestVisual

    Inspection

    DimensionalInspection

    DC Resistance

    Test

    Insulation Resistance

    Test

    Dielectric Withstandin

    g Voltage Test

    Shield Resistance

    Test

    Thermal Shock

    Visual Inspection

    DCResistance

    Test

    Insulation Resistance

    Test

    Dielectric Withstandin

    g Voltage Test

    Focal Plane Electronics Thermal Transition Region

    Harnesses

    Incoming Quality

    Assurance Inspection

    AssemblyMilliohm Testing

    Hi-Pot Testing

    Final Quality Assurance Inspection

    IRSU to Region 1 Thermal Transition Harnesses and IEC

    Internal

    Fabrication

    Final Quality Assurance Inspection

    (4 cycles to 27K)

    Testing Performed at Goddard

    (Level 300A)

    Cleaning Bakeout400-Series

    Hi-Pot Testing

    Assembly

    All Other Thermal Transition Region

    Harnesses

    300/200-Series

    400-Series

    Thermal Cycle testing

    (4 cycles to

  • Use or disclosure of data contained on this page is subject to the restriction(s) on the title page of this document.GSFC SE Seminar: September 13, 2016 11

    IRSU Testing at Box Level

    Physical Verification

    Functional Verification

    Test

    FunctionalVerification

    Tests

    FunctionalVerification

    Tests

    EMI/EMC Testing per the

    ISIM plan

    FunctionalVerification

    Tests

    Conformal Coating

    Preliminary Mechanical/

    ElectricalIntegration

    FunctionalVerification

    Tests

    FinalMechanical/

    ElectricalIntegration

    FunctionalVerification

    Tests

    IRSU Box Test Flow

    VibrationTesting –

    ProtoflightLevels

    Thermal Vac -4 Cycles -

    ProtoflightLevels

    Board Test FlowPCU, ITCE, MSC

    Thermal Cycles (PCU & MSC)

    Box ModMech/ElecIntegration

    FunctionalVerification

    Tests

    WorkmanshipVibe

    1 Cycle TVACFunctionalVerification

    Tests

    Completion ofBurn-In

    For200 hours

    ISIM

    Test

    Flow

    Delivery to ISIM

    CV1RR

  • Use or disclosure of data contained on this page is subject to the restriction(s) on the title page of this document.GSFC SE Seminar: September 13, 2016 12

    IEC Integration & TEST Plan

  • Use or disclosure of data contained on this page is subject to the restriction(s) on the title page of this document.GSFC SE Seminar: September 13, 2016 13

    MIRI Shield in Facility 238 / Doghouse in

    TV/TB Test

    1

  • Use or disclosure of data contained on this page is subject to the restriction(s) on the title page of this document.GSFC SE Seminar: September 13, 2016 14

    ISIM Prime

    ISIM utilizes aluminum heat straps for coupling to

    its radiators

    The ISIM Heat Strap System was designed, fabricated, and qualified by Space Dynamics Laboratory.

    The straps create a thermal path between the sensors and the radiator panels that provide their passive cryogenic cooling

  • Use or disclosure of data contained on this page is subject to the restriction(s) on the title page of this document.GSFC SE Seminar: September 13, 2016 15

    MIRI Integration – Delivered September 2012

  • Use or disclosure of data contained on this page is subject to the restriction(s) on the title page of this document.GSFC SE Seminar: September 13, 2016 16

    MIRI Shield Integration

  • Use or disclosure of data contained on this page is subject to the restriction(s) on the title page of this document.GSFC SE Seminar: September 13, 2016 17

    FGS Integration – Delivered December 2012

  • Use or disclosure of data contained on this page is subject to the restriction(s) on the title page of this document.GSFC SE Seminar: September 13, 2016 18

    ISIM ElementSystem Func

    ISIM Prime Integration

    ISIM ElementCV1-RR

    IEC

    HR

    IECIntegrate NC and NS boxes

    IECSI Testing in FIESTA Area

    IECInterface

    Metrology

    HRIntegrate NC

    and NS harnesses

    HRIntegrate

    FGS and MIRI harnesses

    ISIM PrimeIntegration/Mass Props

    M MMISIM Element System Func /

    MetrologyM

    ■ Prior to the ISIM level Pre-Environmental Review (PER), integration and risk reduction tests were performed

    – Accommodated staggered SI delivery

    – FGS + MIRI in first wave

    – NIRCam and NIRSpec in second wave

    ISIM Integration and Risk Reduction Tests

    ISIM ElementPER

    IECIntegrate

    FGS & MIRI boxes

    IECSI Testing in FIESTA Area

  • Use or disclosure of data contained on this page is subject to the restriction(s) on the title page of this document.GSFC SE Seminar: September 13, 2016 19

    ISIM Electrical Tests Flow

  • Use or disclosure of data contained on this page is subject to the restriction(s) on the title page of this document.GSFC SE Seminar: September 13, 2016 20

    Achieved CV1 RR Timeline

    Maximum Gradient

    Primary Mirror (OSIM)This max gradient will be

    managed in test to be Ts>140

    Start

    MIRI CC

    FGS

    80>Tf>60

    FGS/NIRISS

    Dark Count Images (OSS)

    OSIM

    Stability

    Criteria Met

    SI Stability

    Criteria Met

    Track MATF/IATF Targets / ADM

    Ln2 OSIM

    Shroud

    CPT Part 1

    (include JPL Regression)

    TB 1-H-0-0

    OSIM Final

    Checkout

    OSIM+SI

    Checkout

    Trim Htr & Heat

    Strap Conductance

    (TB 1-H-1-0 )

    Initial

    Optical

    Baseline

    CPT Part 2

    FGS-NIRISS

    Performance

    Characterization

    FGS-Guider

    Performance

    Characterization

    Begin Warm

    Up

    Track MATF/IATF Targets / ADM

    SES Re-

    Pressurize

    System

    FunctionalWarm SI Only

    Warm Environment

    Warm He Shrd

    Release N2

    Pwr

    ASIC/Det

    Pwr OFF

    Switch to

    SWTS SSR

    Cooler EMC

    Safety Check

    Vacuum Conditions

    LO

    CK

    ED

    OP

    EN

    CL

    OS

    E

    @1

    85K

    OP

    EN

    CPT1

    Cycle

    O/C

    CL

    OS

    E

    OP

    EN

    CL

    OS

    E

    OP

    EN

    @1

    35K

    8/29/2013 11/9/2013

    9/1

    9/8 9/15 9/22 9/29 10/6 10/13 10/20 10/27 11/3

    Pwr MIRI Detector Htrs

    (MIRI

  • Use or disclosure of data contained on this page is subject to the restriction(s) on the title page of this document.GSFC SE Seminar: September 13, 2016 21

    Top Level Goals of CV1-RR Very Well Satisfied

    Will march through the objectives, as presented at the CV1-RR Test Design Review:

    • The fundamental purpose of ISIM CV1-RR was, through this early exercise of the ISIM CV test hardware and procedures, to maximize the likelihood that the subsequent ISIM verification tests, CV2 and CV3, will run effectively and efficiently (i.e., as the name of the test implies, to reduce the risk that they won’t)

    • Hence, in broad terms, the primary objectives of CV1-RR were:

    – To demonstrate that the test configuration, which includes large amounts of new GSE, is able to support the test requirements of the ISIM verification program (identify any necessary fixes to hardware before CV2) − highly successful; despite issues with He shroud and spacecraft simulators, we could have run a successful verification test

    – By dry-running critical test procedures, to learn how to most efficiently formulate and execute them and to analyze the results (identify any necessary improvements to procedures before CV2) − also successful and extremely productive; learned a huge amount about test scripts, data flow, optical test procedures that will enable us to improve the execution of CV2 and CV3

  • Use or disclosure of data contained on this page is subject to the restriction(s) on the title page of this document.GSFC SE Seminar: September 13, 2016 22

    Thermal IsolationStructural Kinematic or Semi-

    Kinematic (flexure) Interface

    Structural Non-Compliant

    Joint (bolted/pinned)

    Legend

    Actively Heated

    Actively Cooled

    Actively Heated & Cooled

    Thermal Strap (Flex)

    A

    20K He Shroud Floor A

    He Shroud Sides

    20K

    He Shroud Roof

    Primary Support

    Integration Frame (SIF)

    ITP

    Similar to GIS

    MATF

    20K

    # KNominal Test

    Temperature (K)

    ISIM Element

    IATF &

    MCA

    STMS

    Panels

    G10

    Standoffs

    IEC

    HR

    45K

    35K

    IEC N2

    Panel

    (203-1)

    IEC He

    Shroud

    HR

    Support

    Stand

    45K – 56K

    MCA

    EB

    170K

    35K

    Cold

    Plate

    During Test: Load Path via Ti

    Blade Flexures to Upper GESHA

    During Set up: Load Path via ITP

    Lift Points to Support Frame (SIF)

    To He Shroud Floor20K

    Flt KM

    20K

    Flt Heat

    Straps

    180K

    20K273K

    40K-70K

    20K

    ISIM Element Cryo-Vacuum Test

    ConfigurationStructural Support & Temperature Control

    # He Zone #

    10

    9

    1 32

    8

    Framework

    67

    20K

    MIRI SI

    6K

    Flt Harness (ICP-A to ICP-2)

    Q-Meters

    Passive, or cntrl via Thermal

    Strap to cold/hot source

    HR DSR

    10

    CooldownControl

    Cold

    Plate

    4

    5Cooling

    Lines

    Invar

    Frame

    Flt KM

    Seperable

    10

    10

    Flight Hardware

    20K

    ITP KM I/F

    OSIM Thermal Baffle

    IEC Flexures

    Zero-Q Htrs

    MCA Thermal Strap

    Zone 7 Order

    Q-meters: FGS, MIRI, NIRSpec, NIRCam,

    STMS Panels

    Zone 10 Order

    MCA CP, HR DSR, SIF

    SES PV

    Wall

    SES LN2/He

    Shrouds

    Port 8

    CC MGSE

    Cooled

    Shield

    60K

    ISIM CV Test Configuration – He Zones

  • Use or disclosure of data contained on this page is subject to the restriction(s) on the title page of this document.GSFC SE Seminar: September 13, 2016 23

    NIRSpec Arrival in the SSDIF, September 2013

  • Use or disclosure of data contained on this page is subject to the restriction(s) on the title page of this document.GSFC SE Seminar: September 13, 2016 24

    NIRCam Delivery and Detector Replacement

    ■ Flight NIRCam delivered to ISIM I&T September 18, 2013

    ■ New NIRCam flight detectors installed November 19 2013…10 months early!

  • Use or disclosure of data contained on this page is subject to the restriction(s) on the title page of this document.GSFC SE Seminar: September 13, 2016 25

    NIRCam Integration to ISIM

  • Use or disclosure of data contained on this page is subject to the restriction(s) on the title page of this document.GSFC SE Seminar: September 13, 2016 26

    IEC Mechanical & Electrical Integration

  • Use or disclosure of data contained on this page is subject to the restriction(s) on the title page of this document.GSFC SE Seminar: September 13, 2016 27

    Thermal Transition Harness Integration

  • Use or disclosure of data contained on this page is subject to the restriction(s) on the title page of this document.GSFC SE Seminar: September 13, 2016 28

    ISIM Overview – ISIM SubElements

    ISIM Prime

    ISIM Harness Radiator

    ISIM Electronics

    Compartment

  • Use or disclosure of data contained on this page is subject to the restriction(s) on the title page of this document.GSFC SE Seminar: September 13, 2016 29

    JWST Overview - ISIM Element

    ISIM Prime ISIM Harness Radiator ISIM Electronics Compartment

    ISIM Prime is the term used to describe the assembly of the ISIM Structure, the SIs, the MIRI Cooler and all subsystems that integrate to the ISIM Structure.

    It is meant to encompass all hardware that mounts to the telescope via the ISIM Structure KMs.

    The term does not appear in requirements documents but was coined to describe an actual piece of assembled hardware that gets delivered as an entity. ISIM Prime is not just the ISIM Structure, nor is it ISIM Element (Prime + HR + IEC + ICDH), nor is it the R1 hardware.

  • Use or disclosure of data contained on this page is subject to the restriction(s) on the title page of this document.GSFC SE Seminar: September 13, 2016 30

    ISIM Prime Mass Properties

    Objective of Test

    Level of Test

    Known Deviations from Flight Configuration

    • Provide information used to calculate the mass of ISIM Prime.

    • Provide information used to calculate the CG of ISIM Prime.

    • n/a

    • Flight ISIM Structure Kinematic mounts cannot be part of the measurement

    • GSE HSA is on ISIM Prime for the measurement• 4x Non-Flight CFMPs (Corner Fitting Metrology Plates) are

    still integrated on various -V3 corner fittings• 15x Non-flight metrology nests are still integrated to ISIM

    Prime for this measurement• 15x Non-flight metrology retention bands are integrated to

    non-flight metrology nests on ISIM Prime• 4x Non-flight metrology nests are integrated FGS• 4x Non-flight metrology retention bands are integrated to

    non-flight metrology nests are integrated FGS• Some protective padding was on ISIM Prime for this

    operation• 4x Non-flight lift-blocks & shackles were integrated to ISIM

    Prime (they are needed to enable the lift itself)• Non-flight ICP-A blanket is integrated to ISIM Prime (this

    represents a flight blanket that the OTE team is going use so it isn’t part of ISIM Prime mass)

    • Traveling ground was hanging from ISIM Prime• Traveling purge was hanging from ISIM Prime• RTG saddle connection (cable ties currently used vs machined

    pieces to be used on flight)• No MIRI cooler line AFTER the line field joint at cooler line

    location 4.

    Plans, Procedures, and WOAs

    • ISIM Prime Mass Properties Test Plan, JWST-PLAN-020889

    • ISIM handling WOA, JWST-WOA-005903

    Test Facility / View of Test

    • NASA GSFC B29 SSDIF

  • Use or disclosure of data contained on this page is subject to the restriction(s) on the title page of this document.GSFC SE Seminar: September 13, 2016 31

    Harness Radiator and IEC Integrated to the SIF

  • Use or disclosure of data contained on this page is subject to the restriction(s) on the title page of this document.GSFC SE Seminar: September 13, 2016 32

    ISIM Element and SIF Build Up

  • Use or disclosure of data contained on this page is subject to the restriction(s) on the title page of this document.GSFC SE Seminar: September 13, 2016 33

    ISIM Integrated Functional and Performance

    Test Flow

    ISIM System Functional Test (SFT) in Air

    ISIM System Functional Test (SFT) in Vacuum: Pre-Test

    SSDIFAmbient Temp. / Ambient Pressure

    SES

    ISIM System Abbreviated Functional Continuity (AFC) Test

    ISIM Comprehensive Performance Test (CPT) Part 1

    ISIM Comprehensive Performance Test (CPT) Part 2

    ISIM System Functional Test (SFT) in Vacuum: Post-Test

    Ambient Temp. / Ambient Pressure Ambient Temp. / Vacuum

    Cryo Temp. / Vacuum Cryo Temp. / Vacuum

    Ambient Temp. / Vacuum

    Ambient Temp. / Ambient Pressure

    ISIM System Abbreviated Functional Continuity (AFC) Test - Practice Run

  • Use or disclosure of data contained on this page is subject to the restriction(s) on the title page of this document.GSFC SE Seminar: September 13, 2016 34

    Signal Continuity / Component Operability

    FPE Configurations – excluding FGS/NIRISS

  • Use or disclosure of data contained on this page is subject to the restriction(s) on the title page of this document.GSFC SE Seminar: September 13, 2016 35

    Signal Continuity / Component Operability

    FPE/ICE Configurations – FGS/NIRISS

  • Use or disclosure of data contained on this page is subject to the restriction(s) on the title page of this document.GSFC SE Seminar: September 13, 2016 36

    ISIM Element Just Prior to Move to the SES

  • Use or disclosure of data contained on this page is subject to the restriction(s) on the title page of this document.GSFC SE Seminar: September 13, 2016 37

    ISIM Element Being Lowered in the SES

  • Use or disclosure of data contained on this page is subject to the restriction(s) on the title page of this document.GSFC SE Seminar: September 13, 2016 38

    ISIM Element in SES

  • Use or disclosure of data contained on this page is subject to the restriction(s) on the title page of this document.GSFC SE Seminar: September 13, 2016 39

    ISIM Element in SES Just Prior to Pump Down

    August 2013

  • Use or disclosure of data contained on this page is subject to the restriction(s) on the title page of this document.GSFC SE Seminar: September 13, 2016 40

    ISIM Cryo-Vacuum Test Configuration

    Vacuum Shell (9m diam x 13m tall)

    GHe Shroud, 20K

    IEC (inside, 293K)ISIM (inside, 43K)

    SES Integration Fixture with sTMS

    N2 Shroud

    Vibration Isolators (not used)

    OSIM (inside cryopanels, 100K)

    GHe Shroud

    OTE Simulator (OSIM)

    Cryocooler GSE

  • Use or disclosure of data contained on this page is subject to the restriction(s) on the title page of this document.GSFC SE Seminar: September 13, 2016 41

    OSIM Into the SES for Cryo Calibration

  • Use or disclosure of data contained on this page is subject to the restriction(s) on the title page of this document.GSFC SE Seminar: September 13, 2016 42

    OSIM in the SES

  • Use or disclosure of data contained on this page is subject to the restriction(s) on the title page of this document.GSFC SE Seminar: September 13, 2016 45

    Detector Degradation – The issue

    ■ In January 2011 NIRCam reported that

    their 5µm cutoff detector arrays had

    degraded over a two year period.

    ■ Degradation was a significant increase in

    hot pixels (high dark current).

    ■ Nature of degraded pixels is an “RC”

    response with a high residual dark

    current.

    ■ All JWST flight 5µm cutoff detectors and

    at least two flight 2.5µm cutoff detector

    appear to be degrading.

  • Use or disclosure of data contained on this page is subject to the restriction(s) on the title page of this document.GSFC SE Seminar: September 13, 2016 46

    ■ Ideally, the hardware within the three components would not be changed from the start of CV2 through the conclusion of CV3 and only the three components would be mated and demated for various tests.

    ■ Reality is that some hardware will need to be changed after CV2 and beforemechanical environmental, EMI/EMC, and cryo-vac performance testing

    ■ At the PER, we presented:

    – What are we going to do?

    – What are the risks?

    – How are the risks mitigated?

    ■ CV3 - This test will verified the ISIM System in its final configuration after environmental exposure and provided the post-environmental performance verification test

    ■ All hardware changes between CV2 and CV3 were fully verified

    ISIM Element I&T Flow

  • Use or disclosure of data contained on this page is subject to the restriction(s) on the title page of this document.GSFC SE Seminar: September 13, 2016 47

    ISIM Element Environmental Testing

    ISIM PrimeVibe test

    [Prime Vibe Fix.]

    ISIM ElementAFC/SFT 5

    Cryo-Vac Test #3 SFT 6[ITP]

    Delivery ISIM Element (ISIM

    Prime, HR, ICDH and IEC) to OTIS

    HRRetrofit KMs / Mass Props

    SIF (Base Frame)

    IEC (ISIM

    Electronics Compartment)

    ISIM Harness Radiator

    IECRework boxes /

    Other work

    M

    EICIT / IVT (IEC with

    Reworked boxes and

    HR with Harnesses)

    [FIESTA]

    ISIM PrimeSI Integration

    [S-ITP]

    ISIM PrimeRegion 1 HW

    changes[S-ITP] KM

    ISIM ElementEMI/EMC

    [S-ITP]

    ISIM ElementAcoustics

    - IRSU Powered -[S-ITP]

    ISIM ElementAFC [ITP]

    M

    M M

    On Vibe fixture

    ISIM PrimeGravity Sag

    [HCC fixture]

    M

    M

    SI Rework(rework and some func testing with

    reworked eboxes)

    FGS / NS Testing

    ISIM ElementCryo-Vac Test #2

    SIF (Base Frame)

    IEC (ISIM

    Electronics Compartment)

    ISIM Harness Radiator

    ISIM ElementAFC

    SFT3 / Metrology[S-ITP]

    IECMass

    Properties

    IECVibe Test

    - IRSU Powered

    HRVibe Test

    EICITOn SIF @IEC / HR

    Connections

    M

    IECJackpostrework /

    Other work

    CompleteConfiguration Change

    for CV3Break at ICP 3 and A

    M

    IVT

    NC FPA IVTNS MCE IVTNS FPE IVT

    NC FPAAFT

    NC ICP 2

    MCE IVT

    MSS Acceptance

    Test

    ISIM ElementAFC / SFT4

    [S-ITP]

    M

    HRAcoustics

    Test

  • Use or disclosure of data contained on this page is subject to the restriction(s) on the title page of this document.GSFC SE Seminar: September 13, 2016 48

    ISIM CV2 Design

    Activity verifies requirement(s) requiring the comparison of

    pre- and post-environmental tests

    Activity provides data used to close previous PRs and PFRsActivity provides basic health and safety reducing the risk of finding a problem that could have a large impact if not

    found until the next test phase

    Activity provides continued Model Validation data for system and subsystem items

    Activity verifies requirement(s) and leads to a

    subsystem’s final verification

    Activity verifies requirement(s) and is time critical to obtain a

    performance or functional assessment to reduce risk of finding an issue late/CV3.

    Higher Priority

    Activity verifies requirement(s) and is straightforward to perform in CV2, AND does not need to be repeated in CV3 - doing it now

    takes it off the table

    Activity provides data for calibration of science data; if not obtained in CV2, becomes High priority for CV3.

    Lower Priority

    Minimum Test for ISIM CV2:

    All other objectives are prioritized:

  • Use or disclosure of data contained on this page is subject to the restriction(s) on the title page of this document.GSFC SE Seminar: September 13, 2016 49

    ISIM Cryo-Vacuum Test 2 Timeline

    ISIM Cryovacuum Test #2 Timeline (4/17/2014)

    Ther

    mal

    Pro

    file

    Test

    Det

    ails

    an

    d T

    imel

    ine

    Phase

    1 6

    Test Start

    CooldownDecisionAbbreviated

    Continuity

    System Functional (Vac)

    SES Pumpdown

    Outgassing Cert

    Cooldown End

    ISIM Structure160>Ts>140 Range

    CCH Active

    MIRI Detector Heaters Active

    MIRI SI>60 Range

    IEC EB Cycle - Test1 Cycle over Operating Range

    9

    CPT Part 1

    5.7OSIM Checkout

    4

    OSIM+SI Checkout (& Focusing)

    Achieve TB 1-C-0-0

    2.5

    Optical Baseline

    2.5

    NIRSpec Performance

    9.7

    NIRCam Performance

    Achieve TB 1-H-0-0

    Raise SI boundary Temps to Hot operational conditions.

    4

    CPT Part 2

    3.1

    Power ON Trim

    Htrs

    Achieve TB 1-C-1-0

    2

    OSS SI Operations

    Test EndNIRISS

    Performance

    1.9

    Guider Performance

    1.5

    MIRI Performance

    11

    Warm Up Decision

    Warm Up

    2

    System FunctionalPost-Test (Vac)

    SES Re-Press

    12

    OSS Day in the Life

    OSIM Ambient Checks

    1

    NIRCam ASIC Tuning

    1 1 1

    Take Darks

    Evaluate

    Initial Flux Evaluation

    HR Q to OTE Test

    1

    NIRSpec ShortDetection

    Optical Baseline

    2.6

    NIRCamAlignment

    Close MIRI CCC

    OSS FGS Guiding

    Checkout

    1.5

    EM SSR Test 1.5

    EM SSR Test

    7D 14 D 21 D 28 D 35 D 42 D 49 D 56 D 63 D 70 D 77 D 84 D 91 D 98 D 105 D 112 D

    4

    MIRI CC Heat Load (Initial)

    2

    CCH Fail-OverTest

    Power ON Trim Htrs

    Achieve TB 1-H-1-0

    MSA Heaters Active

    2.5

    Co-BoresightOptical Test

    Nspec=140KNspec=280K

    Nspec Stable

    MIRI Stable

    FGSStable

    NCamStable

    SI Stability Points

    1

    2.5

    5.6

    4

    (5) (1) (5)

    0

    20

    40

    60

    80

    100

    120

    140

    160

    180

    200

    220

    240

    260

    280

    300

    0 5 10 15 20 25 30 35 40 45 50 55 60 65 70 75 80 85 90 95 100 105 110

    Tem

    pera

    ture

    (K)

    Time (Days)

    ISIM Structure Average FGS Bench NIRCam OA

    NIRCam POM NIRSPEC OA NIRSPEC FPA/ASIC

    NIRSpec POM MIRI Bench MIRI 18K Stage

    MIRI POM Qmeter Max Helium Shroud

    ITP SIF Average IEC Max

    PM Average OSIM Shroud PM Gradient

    ISIM Gradient MIRI Shield Structure Average Facility Shroud

    0

    20

    40

    60

    80

    100

    120

    140

    160

    180

    200

    220

    240

    260

    280

    300

    0 5 10 15 20 25 30 35 40 45 50 55 60 65 70 75 80 85 90 95 100 105 110

    Te

    mp

    era

    ture

    (K

    )

    Time (Days)

    ISIM Structure Average FGS Bench NIRCam OA

    NIRCam POM NIRSPEC OA NIRSPEC FPA/ASIC

    NIRSpec POM MIRI Bench MIRI 18K Stage

    MIRI POM Qmeter Max Helium Shroud

    ITP SIF Average IEC Max

    PM Average OSIM Shroud PM Gradient

    ISIM Gradient MIRI Shield Structure Average Facility Shroud

    (1)

    6

    MIRI CC Leak Detection w/ RGA

    2

    MIRI Cold Detector

    FGS Guiding on OSIM Sources while moving

    SI mechanisms

    FGS Guiding on Bad Pixel

    G1

    Tra

    ck

    G2

    Tra

    ck

    G1

    Fin

    e G

    uid

    e

    G2

    Fin

    e G

    uid

    e

    NIRCam Darks

    8

    Guider/NIRISSASIC Tuning

    2

    Fault Mgmt

    OSIM ADMMeasurements

    2

    MIRI CC Heat Load (Follow-On)

    Co-BoresightSet-Up

    Power OFF

    FGS & NS

    Achieve TB 0-C-0-0[FGS-NS)

    Power ON

    FGS & NS

    Power OFFNC

    Achieve TB 0-C-0-0[NC)

    Power ONNC

    ADM & MCA flux

    OSIM (Frame)=102K

    Power OFF

    Trim Htrs

    Power OFF

    Trim Htrs

    Pupil Shear ReviewR1-OSIM Sweep

    ReviewR2-SI Focus Mech

    Review

    R3-OSIM multi-field focus

    Review

    FinalPerformance

  • Use or disclosure of data contained on this page is subject to the restriction(s) on the title page of this document.GSFC SE Seminar: September 13, 2016 50

    ISIM Cryo-Vacuum Test 2 Procedure List

    NumbProcedure

    (Current Rev)Procedure Name Baseline Plan Notes

    1 JWST-PROC-022529 ISIM Element Cryo-Vacuum Test #2 Note (1) [was 016116]

    2 JWST-PROC-016387 JWST ISIM Long System Functional Test (Air) Note (1) [was 016393]

    3 JWST-PROC-016353 ISIM Long System Functional Test in Vacuum (Pre-Test) Note (1) [was 016394]

    4 JWST-PROC-016358 ISIM Long System Functional Test in Vacuum (Post-Test) Note (1) [was 021887]

    5 JWST-PROC-016395 ISIM Comprehensive Performance Test Part 1 Revise/release existing Revise to RevA

    6 JWST-PROC-016497 ISIM Comprehensive Performance Test Part 2 Revise/release existing Revise to RevA

    7 JWST-PROC-016249JWST ISIM System Abbreviated Functional Continuity (AFC) Test

    Procedure Revise/release existing Revise to RevC

    8 JWST-PROC-016302 OSIM Final Checkout Test Procedure Revise/release existing Revise to RevA

    9 JWST-PROC-016304 OSIM Initial Flux Evaluation Procedure New procedure

    10 JWST-PROC-016305 JWST CV2 OSIM & SI Checkout Test Procedure Note (1) [was 016313]

    11 JWST-PROC-016307 NIRCam Optical Alignment Test Procedure ISIM Cryo-Vacuum Test 2 New procedure

    12 JWST-PROC-016344 JWST SIDECAR ASIC and SCA Tuning Procedure Note (1) [was 016314]

    13 JWST-PROC-016346 NIRSpec MCA Short Detection Test Procedure New procedure

    14JWST-PROC-023678 FGS-NIRISS Performance Characterization Test Procedure, ISIM Cryo-

    Vacuum Test 2

    Note (1)

    [was 016434]

    15 JWST-PROC-016360 MIRI Cryo-Cooler Heat Load Verification Test in CV2 New procedure

    16 JWST-PROC-016306 ISIM Optical Baseline Procedure Note (1) [was 016434]

    17 JWST-PROC-016308 NIRCam Performance Characterization Test Procedure New procedure [was 016433]

    18 JWST-PROC-016318 NIRSpec Performance Characterization Test Procedure New procedure

    19JWST-PROC-016309 MIRI Performance Characterization Test Procedure, ISIM Cryo-

    Vacuum Test 2

    Note (1)

    [was 016447]

    20JWST-PROC-023679 FGS-Guider Performance Characterization Test Procedure, ISIM Cryo-

    Vacuum Test 2

    Note (1)

    [was 016435]

    21 JWST-PROC-016335 JWST ISIM Co-Boresight Test Procedure New procedure

    22 JWST-PROC-021687 MIRI Cryo-Cooler MIRI Detector Lower Temperature Test Procedure New procedure M. Ressler/JPL

    A. Glasse / EC

    23 JWST-PROC-016340 Warm Dark Cryo-2 Test Procedure Note (1) [was 016315]

    24JWST-PROC-016341 GS&O/OSS SI Characterization Test Procedure Note (1)

    [was 016317]

    25JWST-PROC-016343 Cryo-2 Day in the Life Procedure Note (1)

    [was 016273]

    26 JWST-PROC-016361 OSS FGS Guiding Checkout New procedure

    27 JWST-PROC-TBD JWST ISIM Ambient Fault Management Test Note (1) [was 016494]

  • Use or disclosure of data contained on this page is subject to the restriction(s) on the title page of this document.GSFC SE Seminar: September 13, 2016 5151

    CV2 Planned vs Actual Test Flow:

    CV2 Planned

    CV2 Actual

  • Use or disclosure of data contained on this page is subject to the restriction(s) on the title page of this document.GSFC SE Seminar: September 13, 2016 52

    ■ SCRAMBLED INTEGRATION

    52

    Parallel observations – Data Scramble

    REGULAR INTEGRATION

  • Use or disclosure of data contained on this page is subject to the restriction(s) on the title page of this document.GSFC SE Seminar: September 13, 2016 5353

    Data Scrambling Context

    FGS

    MIRI

    NIS

    NRC

    NRS

    IRSU ICDH HW SSR

    ISIM FSW

    UserCommands

    SSR Mgr

    SSR Sorter

    FITS Writer

    FPE Data Acq

    Real-Time Ground System

    CECIL Scripts

    R-T Log

    What the FSW Eng wants to

    seeOSS

    What the FSW Eng actually

    sees

    What the SI Eng/Scientist

    sees

    Visit Files

    SSR Image Dump Files• Header/Data/Footer• Many SCAs interleaved

    64-PixelFPE packets

  • Use or disclosure of data contained on this page is subject to the restriction(s) on the title page of this document.GSFC SE Seminar: September 13, 2016 54

    CV2 Test Summary

    ■ CV2 started on June 16, 2014 with Abbreviated Functional Continuity

    Test

    ■ Facility issues (power and chilled water) and the SuROM anomaly

    (during CPT Part 1 Test) early in the test flow triggered a re-

    arrangement of the CV2 timeline

    – The higher priority tests from each of the SI Performance

    Characterization Test Procedures were moved earlier in the flow,

    before the CPT Part 2 Test.

    – The lower priority tests (science calibrations) were left to the end of

    the cold operating temperature plateau.

    ■ All tests at the cold operating temperature were completed by 9/14.

    The transition to the hot operating temperature started on 9/15 and the

    Co-Boresight Test was performed.

  • Use or disclosure of data contained on this page is subject to the restriction(s) on the title page of this document.GSFC SE Seminar: September 13, 2016 55

    ■ Best focus with analysis uncertainty estimates for all SI’s

    ■ First cut at (OSIM + SI) WFE and first cut back-out of SI-only WFE for the MIMF field points, plus ISIM_1 (NIRSpec

    fixed slit)

    ■ Uncertainties: variation in WFE determined by each analyst (all SI’s) and comparison to the variation at the end of

    CV1RR for MIRI, FGS and NIRISS

    ■ First cut at (OSIM + SI) WFE and first cut back-out of SI-only WFE over the full fields of NIRCam and MIRI

    – Uncertainties: variation in WFE determined by each analyst (for NIRCam) and comparison to the variation at

    the end of CV1RR for MIRI

    ■ CV-environment pupil shear for each SI and comparison to results from CV1RR where available

    – First cut at on-orbit pupil shear for each SI

    ■ CV-environment FOV/boresight for each SI and comparison to results from CV1RR where available

    – First cut at on-orbit FOV/boresight for each SI (PFR on NIRCam LW B)

    ■ Check of Co-boresight data quality

    – (We will only have time to confirm that the data quantity and quality is sufficient to perform the analysis relevant

    to co-boresight requirements)

    ■ ISIM Balance #3 (TB 1H10) is with SI’s ON, trim heaters ON

    – Fraction of heat at SI that gets to radiator end;

    – Strap end-to-end thermal conductance

    ■ ISIM Balance #4 (TB 1H00) is with SI’s ON, trim heaters OFF, to determine:

    – Fraction of heat at SI that gets to radiator end;

    – Strap end-to-end thermal conductance

    ■ PFR Investigations complete

    ■ Data quality and completeness and is sufficient for any “Problems” that required additional data

    ■ Summary of departure from expectation

    Warm-Up Decision Point Success

    Criteria

    All required testing was accomplished in CV2 before warm-up

    Co

    llect

    ed a

    ll n

    eed

    ed d

    ata

  • Use or disclosure of data contained on this page is subject to the restriction(s) on the title page of this document.GSFC SE Seminar: September 13, 2016 56

    ISIM Element Environmental Testing

    ISIM PrimeVibe test

    [Prime Vibe Fix.]

    ISIM ElementAFC/SFT 5

    Cryo-Vac Test #3 SFT 6[ITP]

    Delivery ISIM Element (ISIM

    Prime, HR, ICDH and IEC) to OTIS

    HRRetrofit KMs / Mass Props

    SIF (Base Frame)

    IEC (ISIM

    Electronics Compartment)

    ISIM Harness Radiator

    IECRework boxes /

    Other work

    M

    EICIT / IVT (IEC with

    Reworked boxes and

    HR with Harnesses)

    [FIESTA]

    ISIM PrimeSI Integration

    [S-ITP]

    ISIM PrimeRegion 1 HW

    changes[S-ITP] KM

    ISIM ElementEMI/EMC

    [S-ITP]

    ISIM ElementAcoustics

    - IRSU Powered -[S-ITP]

    ISIM ElementAFC [ITP]

    M

    M M

    On Vibe fixture

    ISIM PrimeGravity Sag

    [HCC fixture]

    M

    M

    SI Rework(rework and some func testing with

    reworked eboxes)

    FGS / NS Testing

    ISIM ElementCryo-Vac Test #2

    SIF (Base Frame)

    IEC (ISIM

    Electronics Compartment)

    ISIM Harness Radiator

    ISIM ElementAFC

    SFT3 / Metrology[S-ITP]

    IECMass

    Properties

    IECVibe Test

    - IRSU Powered

    HRVibe Test

    EICITOn SIF @IEC / HR

    Connections

    M

    IECJackpostrework /

    Other work

    CompleteConfiguration Change

    for CV3Break at ICP 3 and A

    M

    IVT

    NC FPA IVTNS MCE IVTNS FPE IVT

    NC FPAAFT

    NC ICP 2

    MCE IVT

    MSS Acceptance

    Test

    ISIM ElementAFC / SFT4

    [S-ITP]

    M

    HRAcoustics

    Test

  • Use or disclosure of data contained on this page is subject to the restriction(s) on the title page of this document.GSFC SE Seminar: September 13, 2016 57

    ISIM Prime Gravity Sag Test

    Objective of Test

    Level of Test

    Known Deviations from Flight Configuration

    • Measure distortions (information) of the ISIM Structure and exterior targets on the SIs with ISIM Prime in a +V1 and –V1 orientation.

    • The measurements taken during the test are used to validate the analytical gravity sag modeling (because we can't measure anything internal during the gravity test)

    • Use the analytical modeling to do on-orbit predictions based on ground testing

    • n/a

    • Flight MIRI Shield will not be present (so that MIRI metrology targets can be seen)

    • GSE HSA may still be integrated to ISIM Prime as opposed to the flight HSA

    • GSE metrology targets are installed for this operation

    • MIRI Cooler Line supports are not flight• MIRI Cooler Line will be replaced with one that

    comes with the flight HSA• RTG saddle connection (cable ties vs machined

    piece) • Non-bonded OTIS accel mounts not on• Flight ICP-A Micrometeoroid shields will not be

    present

    Plans, Procedures, and WOAs

    • ISIM Prime Gravity Release Test Plan, JWST-PLAN-021021

    • ISIM Prime Metrology Procedure, JWST-PROC-018065

    Test Facility / View of Test

    • NASA GSFC, Building 29 SSDIF

  • Use or disclosure of data contained on this page is subject to the restriction(s) on the title page of this document.GSFC SE Seminar: September 13, 2016 58

    ISIM Gravity Sag Test

  • Use or disclosure of data contained on this page is subject to the restriction(s) on the title page of this document.GSFC SE Seminar: September 13, 2016 59

    ■ Detector Subsystem changeout

    ■ MSA FM2 + MCE repair

    ■ OA cover replacement

    NIRSpec Major HW Changes after CV#2

    MSA FM2 OA coverFPA, ASICs and harness

    NIRSpec with closed OA cover January 28th 2015

  • Use or disclosure of data contained on this page is subject to the restriction(s) on the title page of this document.GSFC SE Seminar: September 13, 2016 60

    Successful FGS “Halftime Show” at GSFC

    ■ Detector Subsystem change out

    ■ Motor Replacement

    ■ Grism replacement

    ■ Harness rework

    ■ FPGA Change

  • Use or disclosure of data contained on this page is subject to the restriction(s) on the title page of this document.GSFC SE Seminar: September 13, 2016 61

    ■ Three changed SCAs due to vibe issues

    ■ All FPA masks were replaced

    ■ FPE boxes each had a board replaced due to a capacitor failure that

    could propagate and take down an entire FPE box

    NIRCam Post CV2 Changes

  • Use or disclosure of data contained on this page is subject to the restriction(s) on the title page of this document.GSFC SE Seminar: September 13, 2016 62

    ISIM Env. Testing

    CV3CV1RR CV2

    MIRI Focal Plane Harnesses

    PFR-135• Loss of MIRI Imager exposures Replace Imager flight harness

    with Imager spare

    4 PFR-163• Unusable MIRI Imager exposures Replace Imager flight harness

    with LW spare

    5

    MIRI Focal Plane Electronics

    Known Issues at FPS delivery to OA• Corrupted detector frames• Temp sensor idiosyncrasies

    PFR-124• FPE ground path

    anomaly

    FPE Retrofit

    PFR-164 • Command Failure• Temp Sensor Anomaly• FPM Anneal Errors

    Open Work• FPE Repair

    recommended by PFR-164 ARB

    6 6 6 7 7

    MIRI Timeline of Hardware Changes

    Planned Work(presented at PER)

    New Work(response to PR/PFR)

    Legend

    MIRI Optical Module

    Replace MIRI OM Top MLI

    Remove OM strain gauge connectors

    1 2PR JWST-WOA-006409-005• Restrain accelerometer

    harness

    3

    20

    11

    20

    12

    20

    13

    20

    14

    20

    15

    20

    16

    20

    17

    Integration and Testing

    OBA delivered to ISIMFPS delivered to OA

    PER PSR

  • Use or disclosure of data contained on this page is subject to the restriction(s) on the title page of this document.GSFC SE Seminar: September 13, 2016 63

    ISIM Heat strap issue is the ISIM critical path

    ■ NIRCam heat strap performance during CV-2 was in spec but out of family WRT the other instruments– This anomaly prompted a check of the strap joint fastener torques – Lose bolts were found– Subsequent examination revealed lose bolts throughout the heat strap

    system● Since lose fasteners were found everywhere, they may not explain

    the anomalous NIRCam strap performance■ Several separate issues are raised by the above observations:

    1. Loss of mechanical preload due to design flaws / failed components

    2. Loss of mechanical preload due to long term material creep3. Loss of thermal conductivity due to workmanship issues at strap to

    end-block interface

  • Use or disclosure of data contained on this page is subject to the restriction(s) on the title page of this document.GSFC SE Seminar: September 13, 2016 64

    MIRI optics assembly and flight HSA

    Heat strap work paces installation of the MIRI thermal shield

  • Use or disclosure of data contained on this page is subject to the restriction(s) on the title page of this document.GSFC SE Seminar: September 13, 2016 65

    ■ L2 Environment– Defined in JWST Environmental

    Specification, EV1-0074● Initial definition early in JWST program indicated

    relatively benign environment● Newer model, L2 - Charged Particle

    Environment (L2-CPE), Model Released in 2004 shows significantly higher electron fluxes at high energies than the previous LRAD model

    ■ Concern– Lots of charged particles at L2– Exposed dielectrics can collect particles and

    build up large potentials (charging a capacitor)

    – When potential reaches the dielectric breakdown voltage of the material, potentially damaging discharges can occur

    – ~1/3 of all spacecraft failures and anomalies due to the space environment result from plasma-induced charging

    – Primary concern are the Region 2-1 harnesses

    Space Charging

    AmbientIons &Electrons

    SputteredIons

    EnergeticIons Magnetospheric

    ElectronsBackscatteredElectrons

    SecondaryElectrons

    UV Sunlight

    Photo-emittedElectrons

  • Use or disclosure of data contained on this page is subject to the restriction(s) on the title page of this document.GSFC SE Seminar: September 13, 2016 66

    Space Charging

    Insure all harnesses can withstand the induced current from such a discharge

    Added black Kapton XC tape to Microshutter and MIRI FPHs

    All harnesses have black Kapton Jackets

    Finite resistance between jacket and shell offers bleed path for surface charge

    Micrometeoroid Protection

    MSS Shielding Added:

    MIRI FPE harness between harness radiator and diagonal BSF beam

    MIRI FPE harness between diagonal BSF beam and ICP-A

    MIRI FPE harness inboard from ICP-A, i.e., interior to the ISIM enclosure (also a new request from me)

    NIRSpec FPE harness between the harness radiator and BSF diagonal beam or inboard from ICP-A

    Harnesses also shielded by blanketing between ICP-2 and the HR

    All harnesses meet the POS requirements of ISIM-1557.

    JWST-RPT-029291, “ISIM Harness Meteoroid-Environment Probability of Success”

    Space Charging and Micrometeoroid Risk

  • Use or disclosure of data contained on this page is subject to the restriction(s) on the title page of this document.GSFC SE Seminar: September 13, 2016 67

    ISIM Prime Successfully reintegrated after

    changes

    ISIM Prime: April 2015

  • Use or disclosure of data contained on this page is subject to the restriction(s) on the title page of this document.GSFC SE Seminar: September 13, 2016 68

    ISIM Integration and NIRSpec Team

  • Use or disclosure of data contained on this page is subject to the restriction(s) on the title page of this document.GSFC SE Seminar: September 13, 2016 69

    ISIM Element Environmental Testing

    ISIM PrimeVibe test

    [Prime Vibe Fix.]

    ISIM ElementAFC/SFT 5

    Cryo-Vac Test #3 SFT 6[ITP]

    Delivery ISIM Element (ISIM

    Prime, HR, ICDH and IEC) to OTIS

    HRRetrofit KMs / Mass Props

    SIF (Base Frame)

    IEC (ISIM

    Electronics Compartment)

    ISIM Harness Radiator

    IECRework boxes /

    Other work

    M

    EICIT / IVT (IEC with

    Reworked boxes and

    HR with Harnesses)

    [FIESTA]

    ISIM PrimeSI Integration

    [S-ITP]

    ISIM PrimeRegion 1 HW

    changes[S-ITP] KM

    ISIM ElementEMI/EMC

    [S-ITP]

    ISIM ElementAcoustics

    - IRSU Powered -[S-ITP]

    ISIM ElementAFC [ITP]

    M

    M M

    On Vibe fixture

    ISIM PrimeGravity Sag

    [HCC fixture]

    M

    M

    SI Rework(rework and some func testing with

    reworked eboxes)

    FGS / NS Testing

    ISIM ElementCryo-Vac Test #2

    SIF (Base Frame)

    IEC (ISIM

    Electronics Compartment)

    ISIM Harness Radiator

    ISIM ElementAFC

    SFT3 / Metrology[S-ITP]

    IECMass

    Properties

    IECVibe Test

    - IRSU Powered

    HRVibe Test

    EICITOn SIF @IEC / HR

    Connections

    M

    IECJackpostrework /

    Other work

    CompleteConfiguration Change

    for CV3Break at ICP 3 and A

    M

    IVT

    NC FPA IVTNS MCE IVTNS FPE IVT

    NC FPAAFT

    NC ICP 2

    MCE IVT

    MSS Acceptance

    Test

    ISIM ElementAFC / SFT4

    [S-ITP]

    M

    HRAcoustics

    Test

  • Use or disclosure of data contained on this page is subject to the restriction(s) on the title page of this document.GSFC SE Seminar: September 13, 2016 70

    Goddard ISIM Metrology Survey

    Laser Radar(MV260)

    Laser TrackerLeica LT840

    ISIM

    Stations Used:• 9 Laser Radar (LR)

    stations

    • 4 Laser Tracker (LT) stations

    Duration of all measurements ~10 days

    ~23,000 LR points measured (enhanced metrology mode)

    ~200 LT points (spatial trigger mode)

  • Use or disclosure of data contained on this page is subject to the restriction(s) on the title page of this document.GSFC SE Seminar: September 13, 2016 71

    +V2

    +V3

    MIRIPOM

    NIRISS(TF)

    POM

    MATF1 MATF2

    MATF3 MATF4

    MATF5

    IATF1 IATF2

    IATF3

    IATF4

    L1 L2

    L2L1

    L1 L2

    L1

    L2

    mc

    rc

    mc

    rc

    mc

    rc

    rcFM3+ƟV2

    FM3-ƟV2

    FM3+ƟV3

    FM3-ƟV3

    View Looking UpFrom OSIM

    IATF & MCAADM Targets

    MCAPDI

    rc1rc2

    & Screen

    rc3

    L1L2 mc

    Si Flux Mon

    InSb Flux Mon

    FGS 2 (B)POM

    NIRSpecPOMNIRCam

    BPOM

    FGS 1 (A)POM

    NIRCamA

    POM

    JWST PV-046839

    CV2 ISIM, MATF, IATF Test Configuration

  • Use or disclosure of data contained on this page is subject to the restriction(s) on the title page of this document.GSFC SE Seminar: September 13, 2016 72

    Science Instrument pupil alignment reference

    (PAR)

    PARs are used at ambient to trend pupil changes, not calculate absolute pupil alignment

    MIRI

    Guider

    NIRSpec

    NIRISS

    V3

    V2

  • Use or disclosure of data contained on this page is subject to the restriction(s) on the title page of this document.GSFC SE Seminar: September 13, 2016 75

    STOP Models

    Thermal ModelModel Format : Thermal Desktop

    Structural ModelModel Format: NASTRAN

    NIRCam Short

    Wavelength Channel

    MIRI Imager

    Mode

    NIRSpec Camera

    Imaging Mode

    Fine Guider

    Channel A

    Optical ModelsModel Format: Code V, LOM*

    OSIM

    *LOM – Linear Optical Model developed

    in-house by GSFC optical analysis team.

  • Use or disclosure of data contained on this page is subject to the restriction(s) on the title page of this document.GSFC SE Seminar: September 13, 2016 76

    STOP Analysis Process

    Integrated

    Thermal Model

    Thermal

    Analysis

    Temperatures

    (thermal)

    Integrated

    Structural

    Model

    Structural

    Analysis

    Displacements

    of Tracking

    Nodes

    Instrument

    Optical Model

    Optical

    Analysis

    Optical

    Performance

    (WFE, Focus,

    Pupil Shear,

    LOS)

    Thermal Desktop Thermal Desktop

    NASTRAN NASTRAN

    Map Temps to

    Structure FEM

    Temperatures

    (structural)

    Perturbations

    (optical)

    Generate

    Perturbations

    for Optical

    Model

    Discipline

    Model

    Analysis/

    Process

    Intermediate

    Results

    Final Results

    Th

    erm

    al

    Str

    uctu

    ral

    Op

    tica

    l

    Ideas/TMG,

    Python

    EXCEL

    Code V, Linear Optical

    Model (LOM),

    Spreadsheet Math Models

    Code V, Linear Optical

    Model (LOM),

    Spreadsheet Math Models

  • Use or disclosure of data contained on this page is subject to the restriction(s) on the title page of this document.GSFC SE Seminar: September 13, 2016 77

    Load Cases and Analysis Objectives

    Note: Table lists primary load cases ran. Additional load cases were ran for studies and benchmarking.

  • Use or disclosure of data contained on this page is subject to the restriction(s) on the title page of this document.GSFC SE Seminar: September 13, 2016 78

    ISIM Element Environmental Testing

    ISIM PrimeVibe test

    [Prime Vibe Fix.]

    ISIM ElementAFC/SFT 5

    Cryo-Vac Test #3 SFT 6[ITP]

    Delivery ISIM Element (ISIM

    Prime, HR, ICDH and IEC) to OTIS

    HRRetrofit KMs / Mass Props

    SIF (Base Frame)

    IEC (ISIM

    Electronics Compartment)

    ISIM Harness Radiator

    IECRework boxes /

    Other work

    M

    EICIT / IVT (IEC with

    Reworked boxes and

    HR with Harnesses)

    [FIESTA]

    ISIM PrimeSI Integration

    [S-ITP]

    ISIM PrimeRegion 1 HW

    changes[S-ITP] KM

    ISIM ElementEMI/EMC

    [S-ITP]

    ISIM ElementAcoustics

    - IRSU Powered -[S-ITP]

    ISIM ElementAFC [ITP]

    M

    M M

    On Vibe fixture

    ISIM PrimeGravity Sag

    [HCC fixture]

    M

    M

    SI Rework(rework and some func testing with

    reworked eboxes)

    FGS / NS Testing

    ISIM ElementCryo-Vac Test #2

    SIF (Base Frame)

    IEC (ISIM

    Electronics Compartment)

    ISIM Harness Radiator

    ISIM ElementAFC

    SFT3 / Metrology[S-ITP]

    IECMass

    Properties

    IECVibe Test

    - IRSU Powered

    HRVibe Test

    EICITOn SIF @IEC / HR

    Connections

    M

    IECJackpostrework /

    Other work

    CompleteConfiguration Change

    for CV3Break at ICP 3 and A

    M

    IVT

    NC FPA IVTNS MCE IVTNS FPE IVT

    NC FPAAFT

    NC ICP 2

    MCE IVT

    MSS Acceptance

    Test

    ISIM ElementAFC / SFT4

    [S-ITP]

    M

    HRAcoustics

    Test

  • Use or disclosure of data contained on this page is subject to the restriction(s) on the title page of this document.GSFC SE Seminar: September 13, 2016 79

    IEC Mass Properties

    Objective of Test

    Level of Test

    Known Deviations from Flight Configuration

    • Provide a measured mass of the IEC• Provide information used to calculate the final

    delivered mass and CG of the IEC

    • n/a

    • FLIGHT DITCE box is not present for this measurement.

    • The flight lock NEA are not present for this test.• The flight on-orbit flexures are not present for this

    test• Flight baffles may not be present depending on

    timing of measurement (if tied to vibe test handling, the will be present)

    • Note that the Towel bar harness supports should be present for this test but have not been delivered yet

    Plans, Procedures, and WOAs

    • ISIM IEC Mass Properties Test Plan

    Test Facility / View of Test

    • NASA GSFC, Building 29, SSDIF

  • Use or disclosure of data contained on this page is subject to the restriction(s) on the title page of this document.GSFC SE Seminar: September 13, 2016 80

    IEC Vibration Test

    Objective of Test

    Level of Test

    Known Deviations from Flight Configuration

    • Verify minimum workmanship standards have been met by subjecting the IEC to the low frequency structural dynamic spectrum of the launch environment

    • Provide data for FEM verification

    • Protoflight (5-100 Hz)

    • FLIGHT DITCE box is not present for this test• Mass sim is used

    • The flight lock NEA are not present for this test• The flight on-orbit flexures are not present for this

    test• No flight harnesses are connected to EXTERIOR of

    IEC (HR end or OTE end)• We may need to use a harness sim on ICP-2

    end to load towel bar and connector (harness with no pins)

    Plans, Procedures, and WOAs

    • ISIM Element Level IEC Vibe Test Plan• Facility test procedure based on plan

    Test Facility / View of Test

    • NASA GSFC, Building 7, Rm 028

  • Use or disclosure of data contained on this page is subject to the restriction(s) on the title page of this document.GSFC SE Seminar: September 13, 2016 81

    Harness Radiator Mass Properties

    Objective of Test

    Level of Test

    Known Deviations from Flight Configuration

    • Provide a measured mass of the IEC• Provide information used to calculate the final

    delivered mass and CG of the IEC

    • n/a

    • The HR can NOT be picked up and weighed as an assembly because it is required to be assembled to a flight or GSE frame – otherwise, the HR doesn’t exist as an assembly.

    • At the ISIM level, the GSE frame is so heavy (made of invar for CTE reasons) that it swamps the mass of the HR and would make a measurement unreliable.

    • Measurements• During the HR kinematic mount retrofit – set for

    post CV2 – the HR team will measure as many individual components or subassemblies as possible and we will compare that to the CAD estimates/predictions.

    • We will use that info to make a CAD prediction for the full HR mass, CG, and MOI and we will use a monte carlo analysis using the measurement tolerances to put a bounding box on the mass and CG.

    Plans, Procedures, and WOAs

    • ISIM Harness Radiator KM Retrofit WOA

    Test Facility / View of Test

    • NASA GSFC, B29 SSDIF

  • Use or disclosure of data contained on this page is subject to the restriction(s) on the title page of this document.GSFC SE Seminar: September 13, 2016 82

    Harness Radiator Vibe Test

    Objective of Test

    Level of Test

    Known Deviations from Flight Configuration

    • Strength test• Verify minimum workmanship standards have been met

    by subjecting the HR to the low frequency structural dynamic spectrum of the launch environment

    • Provide data for FEM verification

    • Protoflight (5-100 Hz)

    • Flight harnesses are replaced by mass simulators• Added the flight harnesses to this test configuration

    based on feedback at the PER.• Required unique GSE to deal with free

    connector ends.

    Plans, Procedures, and WOAs

    • ISIM Harness Radiator Vibe Test Plan• Facility test procedure based on plan

    Test Facility / View of Test

    • NASA GSFC, Building 7, Rm 028 (MB-C 220 #1 Shaker)

  • Use or disclosure of data contained on this page is subject to the restriction(s) on the title page of this document.GSFC SE Seminar: September 13, 2016 83

    Harness Radiator Acoustics Test

    Objective of Test

    Level of Test

    Known Deviations from Flight Configuration

    • Verify the ability to survive the launch acoustic environment and to demonstrate acceptable workmanship

    • Protoflight

    • Flight harnesses are replaced by mass simulators• Added the flight harnesses to this test configuration

    based on feedback at the PER.• Required unique GSE to deal with free

    connector ends.

    Plans, Procedures, and WOAs

    • ISIM Harness Radiator Acoustics Test Plan• Facility test procedure based on plan

    Test Facility / View of Test

    • NASA GSFC, Building 10

  • Use or disclosure of data contained on this page is subject to the restriction(s) on the title page of this document.GSFC SE Seminar: September 13, 2016 84

    ISIM Element Environmental Testing

    ISIM PrimeVibe test

    [Prime Vibe Fix.]

    ISIM ElementAFC/SFT 5

    Cryo-Vac Test #3 SFT 6[ITP]

    Delivery ISIM Element (ISIM

    Prime, HR, ICDH and IEC) to OTIS

    HRRetrofit KMs / Mass Props

    SIF (Base Frame)

    IEC (ISIM

    Electronics Compartment)

    ISIM Harness Radiator

    IECRework boxes /

    Other work

    M

    EICIT / IVT (IEC with

    Reworked boxes and

    HR with Harnesses)

    [FIESTA]

    ISIM PrimeSI Integration

    [S-ITP]

    ISIM PrimeRegion 1 HW

    changes[S-ITP] KM

    ISIM ElementEMI/EMC

    [S-ITP]

    ISIM ElementAcoustics

    - IRSU Powered -[S-ITP]

    ISIM ElementAFC [ITP]

    M

    M M

    On Vibe fixture

    ISIM PrimeGravity Sag

    [HCC fixture]

    M

    M

    SI Rework(rework and some func testing with

    reworked eboxes)

    FGS / NS Testing

    ISIM ElementCryo-Vac Test #2

    SIF (Base Frame)

    IEC (ISIM

    Electronics Compartment)

    ISIM Harness Radiator

    ISIM ElementAFC

    SFT3 / Metrology[S-ITP]

    IECMass

    Properties

    IECVibe Test

    - IRSU Powered

    HRVibe Test

    EICITOn SIF @IEC / HR

    Connections

    M

    IECJackpostrework /

    Other work

    CompleteConfiguration Change

    for CV3Break at ICP 3 and A

    M

    IVT

    NC FPA IVTNS MCE IVTNS FPE IVT

    NC FPAAFT

    NC ICP 2

    MCE IVT

    MSS Acceptance

    Test

    ISIM ElementAFC / SFT4

    [S-ITP]

    M

    HRAcoustics

    Test

  • Use or disclosure of data contained on this page is subject to the restriction(s) on the title page of this document.GSFC SE Seminar: September 13, 2016 85

    ISIM Prime Vibe Test

    Objective of Test

    Level of Test

    Known Deviations from Flight Configuration

    • Verify minimum workmanship standards have been met by subjecting the ISIM Prime to the low frequency structural dynamic spectrum of the launch environment

    • Provide data for FEM verification

    • Protoflight (5 - 100 Hz)

    • Flight and GSE purge lines are tied off to ISIM Structure because there is no purge panel (part of STMS for CV testing and part of OTE for flight) available during this test

    • 2x non-flight CFMPs (corner fitting metrology plates) will be in integrated at the time of this test

    • Flight cooler line ends at cooler line location 4. A GSE line will be added from cooler line location 4a through 1 to properly load line supports 1, 2, 3, and 4a.

    • ICP-A : Harnesses are attached on ISIM side but no harnesses are attached to the HR side

    • MIRI and NS FPE harness supports (located between ICP-A and HR) will not have harnesses attached because these harnesses are not present unless ISIM Element (not just Prime) is assembled.

    • Harnesses that go to T-ICP-1 (on OTE) will be tied off to FGS ICP-A since the OTE is not present.

    Plans, Procedures, and WOAs

    • ISIM Prime Vibe Test Plan, JWST-PLAN-020896 • Facility test procedure based on plan

    Test Facility / View of Test

    • NASA GSFC, Building 7, 028 (MB-C 220 #1 Shaker)

  • Use or disclosure of data contained on this page is subject to the restriction(s) on the title page of this document.GSFC SE Seminar: September 13, 2016 86

    ISIM Element Acoustics Test

    Objective of Test

    Level of Test

    Known Deviations from Flight Configuration

    • Verify the ability to survive the launch acoustic environment and to demonstrate acceptable workmanship

    • Protoflight (note Risk under review on next slide)

    • The ISIM Prime has 4x Non-Flight CFMPs (Corner Fitting Metrology Plates) are still integrated on various -V3 corner fittings

    • The IEC DITCE box is not present for this test.• The IEC V2 vents are not present for this test.• The IEC flight baffles (4x) are not present for this test.• The IEC inner and outer conformal shields are not

    present for this test.• The IEC flight lock NEA are not present for this test.• The IEC flight on-orbit flexures are not present for this

    test• The ISIM Prime, HR and IEC are mounted to the SIF as

    opposed to the composite Backplane.• The IEC mounts to the SIF (SES Integration Fixture) are

    GSE mounts, not flight launch locks• A GSE purge panel is used to support purge lines (on

    STMS Frame)• Flight cooler line on ISIM Prime ends at cooler line

    location 4. A GSE line will be added from cooler line location 4a through 1 to properly load line supports 1, 2, 3, and 4a.

    Plans, Procedures, and WOAs

    • ISIM Element Acoustics Test Plan, JWST-PLAN-021019

    Test Facility / View of Test

    • NASA GSFC, Building 10 Acoustics Chamber

  • Use or disclosure of data contained on this page is subject to the restriction(s) on the title page of this document.GSFC SE Seminar: September 13, 2016 87

    ISIM Element Acoustic Control vs. Spec

    -1.03 dB -1.19 dB

    Reference Spec Frequency Range

    +1.41 dB

    +1.03 dB

    Very good control

    achieved with

    essentially two 1/3

    octave bands

    outside 1 dB tolerance goal

  • Use or disclosure of data contained on this page is subject to the restriction(s) on the title page of this document.GSFC SE Seminar: September 13, 2016 88

    NIRSpec Microshutter Black “dots” are failed-closed/plugged shutters.

    Minor increase failed closed shutters observed after ISIM Protoflight level Acoustics

    MSA Performance and Trending

  • Use or disclosure of data contained on this page is subject to the restriction(s) on the title page of this document.GSFC SE Seminar: September 13, 2016 89

    Protoflight Acoustic Test Levels for OTIS

    ■ Will control chamber to +/- 1 dB to meet AE's minimum spec level (purple

    bar level) and uniformity requirements

    – Demonstrated tolerance and uniformity during Tent Frame Dry Run Test

    115

    120

    125

    130

    135

    140

    145

    31.5 63 125 250 500 1000 2000

    So

    un

    d P

    ressu

    re L

    evel

    (dB

    )

    Octave Band Center Frequency (Hz)

    Proposed Minimum Protoflight SPL DCI 1/6 PF 85%FF

    ISIM actual

    SCE PF

    OTIS PF

    PF waiver

    Fill Factor adjustmentMid bands waiver request

  • Use or disclosure of data contained on this page is subject to the restriction(s) on the title page of this document.GSFC SE Seminar: September 13, 2016 90

    ■ OTIS tent configuration: notably more attenuation @ high frequencies critical to MSA’s

    – Geometry and material choice included and demonstrated improvement

    – Microphone quantity, type, placement not equivalent, but minor uncertainty

    compared to insertion loss improvement over original contamination bag from

    ISIM vibe test

    – No appreciable change in attenuation within specified octave bands (31.5 - 2 kHz)

    Insertion Loss Improvement Help MSA’s (OTIS)

    0

    5

    10

    15

    20

    25

    250 500 1000 2000 4000 8000 16000 32000

    Insert

    ion

    Lo

    ss (

    dB

    )

    Frequency (Hz)

    Insertion Loss: OTIS vs ISIM

    OTIS Tent, Run 22

    ISIM Bag, Small frame, Run 44

    >8dB

    above

    16 kHz

    No benefit at mid-high frequencies

  • Use or disclosure of data contained on this page is subject to the restriction(s) on the title page of this document.GSFC SE Seminar: September 13, 2016 91

    ISIM Element EMI/ EMC Test

    Objective of Test

    Level of Test

    Known Deviations from Flight Configuration

    • Radiated Emissions Testing• Radiated Susceptibility Testing• Conducted Emission (limited)

    • Charts with test details follows

    • The ISIM Prime has 4x Non-Flight CFMPs (Corner Fitting Metrology Plates) are still integrated on various -V3 corner fittings

    • The IEC DITCE box is not present for this test.• The IEC V2 vents are not present for this test.• The IEC flight baffles (4x) are not present for this test.• The IEC inner and outer conformal shields are not

    present for this test.• The IEC flight lock NEA are not present for this test.• The IEC flight on-orbit flexures are not present for this

    test• The ISIM Prime, HR and IEC are mounted to the SIF as

    opposed to the composite Backplane.• The IEC mounts to the SIF (SES Integration Fixture) are

    GSE mounts, not flight launch locks• A GSE purge panel is used to support purge lines (on

    STMS Frame)• Flight cooler line on ISIM Prime ends at cooler line

    location 4. A GSE line will be added from cooler line location 4a through 1 to properly load line supports 1, 2, 3, and 4a.

    Plans, Procedures, and WOAs

    • JWST/ ISIM EMI/ EMC Control Plan• JWST/ ISIM EMI EMC Test Procedure

    Test Facility / View of Test

    • NASA GSFC, Building 7, N115 (Anechoic Chamber)

  • Use or disclosure of data contained on this page is subject to the restriction(s) on the title page of this document.GSFC SE Seminar: September 13, 2016 92

    ISIM Level EMI/EMC Tests

    ■ Test plan defined in ISIM EMC Control Plan, JWST-PLAN-004633,

    section 3.3 – All Successfully Executed!

    – Conducted tests (power subsystem compatibility)

    – Radiated tests (communications subsystem compatibility)

    – Self-compatibility/crosstalk

    MIRI FPE

    OTE ACS

    RWA

    (x6)

    Propulsion (Bi-Prop)

    SCATs (x4)

    MRE-1 DTMs

    (x8)

    Region 1 Region 2(IEC)

    Region 3

    Legends:

    ISIM 1553B-I

    Spacewire Discrete-pt to pt

    Region 1-(within SI/OA) Region 2-(within IEC) Region 3-(within Spacecraft Bus)

    Primary Mirror

    Secondary Mirror

    Tertiary Mirror

    photons Primary Power

    FSSE (x2)

    NIRCam FPE 1&2

    NIRSpec ICE

    MIRI FPE

    WDE (x6)

    CTP

    (x2)

    NIRSpec

    ASICs/FPA

    Mech.

    FGS

    NIRCam

    Mech.

    MSA

    Sunshield

    Li Ion

    Battery

    CSSA

    (x4)

    VDE

    (x2)

    IRU (2)

    ADU

    (x2)

    Sunshield

    Acts (x8)

    RS422

    Cold

    Junction

    Box (x2)

    SSR

    S/C-ISIM1553B-SI

    SAR

    (x2)S/A

    (5 panels)

    S/C 1553B-S

    TAU

    Motor Switching

    Relays: 4-pole

    Analog/

    BilevelJT

    Compressor

    Coolant Lines

    FGS G2 FPE/ICE

    Radiator Heat

    Switches

    Contn Ctrl Htrs

    Cryo Temp

    Sensors

    G1 ASICs/

    FPA/Mech.G2 ASICs/

    FPA/Mech.

    TF ASICs/

    FPA/Mech.

    ASICs/FPA 1

    MIRIColdheads

    Mech.

    FPA

    ASICs/FPA 2

    FGS G1 FPE/ICE

    NIRCam ICE

    MIRI ICE

    FGS TF

    FPE/ICE/TCE

    CCE-PT

    (x2)

    CCE-JT

    (x2)

    ICDH

    (x2)

    NIRSPEC MCE

    IRSU (x2)

    NIRSpec FPE

    STA (x3)

    BAGA

    2 axis

    Mechanical I/F

    DITCE (x2)

    FSM Acts

    LVDS

    PCU

    DEU

    (x2)

    CMU

    19

    Hexapod

    (6 DOF)

    CMU

    1..18

    Hexapod

    (7 DOF)

    (X18)

    CMU

    20

    Tower

    Acts (x2)

    FSS (x2)

    CCU

    ISIM -

    Cryocooler

    Region 3

    Te

    mp

    Mo

    nito

    r/R

    eso

    lve

    rs

    CMU

    20,21

    CMU

    21Deployment

    Acts (x2)

    Latch

    Acts (x2)

    SMSS

    Wings

    Latch

    Acts (x18)

    Deployment

    Acts (x4)

    C&DH

    Spacecraft - Region 3

    RSA

    PT

    Compressor

    RS485

    COMM

    TWTA

    (x2) SW

    SW

    (x2)SW

    6 d

    B

    Sp

    litte

    r

    Dip

    lexe

    rD

    iple

    xe

    r

    Gim

    ba

    l

    Asse

    mb

    ly

    Dip

    lexe

    r

    Hyb

    rid

    Co

    up

    ler

    Hyb

    rid

    Co

    up

    ler

    Hyb

    rid

    C

    ou

    ple

    r

    Ka

    -Ba

    nd

    Filt

    erISO

    SC Switch (P/R)MGA Switch

    TWTA Switch

    BP

    F

    S-Band

    Transponder

    (x2)

    MGA

    S-band

    LHCP

    HGA

    Ka-band

    RHCP

    SC Omni

    S-band

    LHCP

    OTE Omni

    S-band

    LHCP

    Ka-Band

    Modulator

    (x2)

    Region 3

    SPG

    EPS

    SMS

    Cryocooler Region 3 EGSE

    SPACECRAFT SIMULATOR

    ICDH in S/C bus

    ISIM

    Flight ICDH outside chamber for EMI;Outside chamber for cryo-vac

    FGS NIRISS

    Flight DITCE (OTE e-box in IEC) not powered during test

    Unit Under Test

  • Use or disclosure of data contained on this page is subject to the restriction(s) on the title page of this document.GSFC SE Seminar: September 13, 2016 93

    ISIM EMI Test Team

  • Use or disclosure of data contained on this page is subject to the restriction(s) on the title page of this document.GSFC SE Seminar: September 13, 2016 94

    ISIM Element Environmental Testing

    ISIM PrimeVibe test

    [Prime Vibe Fix.]

    ISIM ElementAFC/SFT 5

    Cryo-Vac Test #3 SFT 6[ITP]

    Delivery ISIM Element (ISIM

    Prime, HR, ICDH and IEC) to OTIS

    HRRetrofit KMs / Mass Props

    SIF (Base Frame)

    IEC (ISIM

    Electronics Compartment)

    ISIM Harness Radiator

    IECRework boxes /

    Other work

    M

    EICIT / IVT (IEC with

    Reworked boxes and

    HR with Harnesses)

    [FIESTA]

    ISIM PrimeSI Integration

    [S-ITP]

    ISIM PrimeRegion 1 HW

    changes[S-ITP] KM

    ISIM ElementEMI/EMC

    [S-ITP]

    ISIM ElementAcoustics

    - IRSU Powered -[S-ITP]

    ISIM ElementAFC [ITP]

    M

    M M

    On Vibe fixture

    ISIM PrimeGravity Sag

    [HCC fixture]

    M

    M

    SI Rework(rework and some func testing with

    reworked eboxes)

    FGS / NS Testing

    ISIM ElementCryo-Vac Test #2

    SIF (Base Frame)

    IEC (ISIM

    Electronics Compartment)

    ISIM Harness Radiator

    ISIM ElementAFC

    SFT3 / Metrology[S-ITP]

    IECMass

    Properties

    IECVibe Test

    - IRSU Powered

    HRVibe Test

    EICITOn SIF @IEC / HR

    Connections

    M

    IECJackpostrework /

    Other work

    CompleteConfiguration Change

    for CV3Break at ICP 3 and A

    M

    IVT

    NC FPA IVTNS MCE IVTNS FPE IVT

    NC FPAAFT

    NC ICP 2

    MCE IVT

    MSS Acceptance

    Test

    ISIM ElementAFC / SFT4

    [S-ITP]

    M

    HRAcoustics

    Test

  • Use or disclosure of data contained on this page is subject to the restriction(s) on the title page of this document.GSFC SE Seminar: September 13, 2016 95

    ISIM CV3 Design/Timeline Decisions

    Activity provides data used to close previous PRs and PFRs

    Activity verifies requirement(s) requiring the comparison of

    pre- and post-environmental tests

    Activity provides basic health and safety reducing the risk of finding a problem that could have a large impact if not

    found until the next test phase

    operational planning / observing mode previews

    Activity verifies requirement(s) reduce risk of finding an issue at OTIS level tests.

    Activity provides data for calibration of on-orbit science data.

    Activity provides continued Model Validation data for system and subsystem items

    Highest Priority for ISIM CV3:

    All other objectives are prioritized based on the consequence of deletion:

    Risk

    ISIM level or subsystem’s final verification

    Risk

  • Use or disclosure of data contained on this page is subject to the restriction(s) on the title page of this document.GSFC SE Seminar: September 13, 2016 96

    ISIM Cryo-vacuum Test #3 As Run Timeline 4/4/2016

    Thermal Control

    Thermal Balance Points

    Key Decision Points

    Test

    s /

    Task

    s

    Phase

    Phase

    Phase

    Phase

    Test Start Cooldown

    End

    11/10

    1 6

    CooldownDecision

    AbbreviatedContinuity

    System Functional +Fault Mgmt (Vac)

    SES Pumpdown

    Outgassing Cert

    CCH Contamination Region

    MIRI Detector Heaters Active

    MIRI

  • Use or disclosure of data contained on this page is subject to the restriction(s) on the title page of this document.GSFC SE Seminar: September 13, 2016 97

    Path from Requirements to Data Collection

    1. Verification Matrix

    2. Optical Performance Verification Plan4. Initial Optical Baseline Test Procedure

    5. OTP Tracking Spreadsheet 3. CV Test Procedure

  • Use or disclosure of data contained on this page is subject to the restriction(s) on the title page of this document.GSFC SE Seminar: September 13, 2016 98

    ■ Offsets generated via Structural, Thermal, Optical Performance (STOP)

    modeling

    ■ Offsets implemented for focus for NIRCam, NIRSpec, Guider, and

    NIRISS (and pupil shear for NIRCam)

    ■ Reference: ISIM CV2 & CV3 STOP: Ground to On-Orbit Gravity and

    Thermal Cases, JWST-PRES-027671, R. Gracey

    Final Alignment Offset Using SI Mechanisms for

    Best Performance On-Orbit

    R. Gracey

  • Use or disclosure of data contained on this page is subject to the restriction(s) on the title page of this document.GSFC SE Seminar: September 13, 2016 99

    Sample NIRCam CV3 Results

    Learned how long we need to wait after powering on!

    ASIC tuning led to good noise behavior.

    Mod B DHS alignment –wheel zero points repeated well from CV2.

    Linearity data will provide the pipeline correction.

  • Use or disclosure of data contained on this page is subject to the restriction(s) on the title page of this document.GSFC SE Seminar: September 13, 2016 100

    Ghost with the NIRISS SOSS Mode

  • Use or disclosure of data contained on this page is subject to the restriction(s) on the title page of this document.GSFC SE Seminar: September 13, 2016 101

    Harness Thermal Loads into ISIM in CV3

    ColdBalance

    WarmBalance

  • Use or disclosure of data contained on this page is subject to the restriction(s) on the title page of this document.GSFC SE Seminar: September 13, 2016 102

    ■ The CV3 test has run phenomenally well. We will have run for 110 days from start of AFC

    (Ambient Functional Checkout) before chamber pump-down to door opening post test –

    almost on track with original 104 days prediction

    ■ Completed all planned activities as well as additional requests at cold operational

    temperatures and started the warm up to ambient on Thursday, January 28th

    – 214 PRs written to date (compared to 407 in CV2) – 133 of them are ready for closure

    – Nearly all software/ops related, no hardware related issues other than the known MIRI

    FPE

    – ZERO PFRs!

    ■ Opened the chamber door Saturday, the 13th of February 2016

    ■ Only one significant event during the test….

    ISIM CV3 Summary

    1

    • Fantastic support from the ISIM test team, Code 549 facilities team and Code 200 facilities team….

    THANK YOU ALL!

  • Use or disclosure of data contained on this page is subject to the restriction(s) on the title page of this document.GSFC SE Seminar: September 13, 2016 103

    The Blizzard of 2016

    1

  • Use or disclosure of data contained on this page is subject to the restriction(s) on the title page of this document.GSFC SE Seminar: September 13, 2016 104

    1

    http://www.theatlantic.com/science/archiv

    e/2016/02/snowed-in-at-nasa/433959/

  • Use or disclosure of data contained on this page is subject to the restriction(s) on the title page of this document.GSFC SE Seminar: September 13, 2016 105

    MIRI FPE Design Problem & Solution

    SPW-B Haywire to reroute clock through Long Stub

    B-Side clock outTo backplane

    SPW Slice2 of 2, in Side B Slot FPGA Tx

    SPW Slice2 of 2, in Side B Slot

    B-Side clock outTo backplane

    Current Design

    With Haywire

    Signal Path

    Lift Tx pins

    Haywire

    Long 5” Stub

    Haywire Incorporating Stub

    FPGA Tx

  • Use or disclosure of data contained on this page is subject to the restriction(s) on the title page of this document.GSFC SE Seminar: September 13, 2016 106

    FPE Repair and Test Plan

    FPE removed from IEC

    ETAS SignOff

    ISIM PSR

    3/8

    3/10/16

    3d

    3/7

    3/7/16

    1d

    3/23/16

    IEC EICIT

    5/5

    5/6/16

    2d

    Integrate FPE into IEC

    5/3

    5/4/16

    2d

    Repair FPE

    3/17

    3/23/16

    4.5d

    Receipt Inspect/Test

    3/10

    3/17/16

    5.5d

    Remove and ship FPE to JPL

    3/8

    3/9/16

    2d

    FPE Test

    3/24

    3/28/16

    3d

    FPE receipt inspect/test

    5/2

    5/2/16

    1d

    PSR2

    5/9

    5/9/16

    1d

    Prep for PSR2

    4/25

    5/6/16

    10d

    Pack and ship to

    Goddard

    4/22

    4/22/16

    1d

    Hold PSR1

    4/21

    4/21/16

    1d

    Prep for PSR1

    4/20

    4/20/16

    1d

    SIDU Test

    4/18

    4/19/16

    2d

    Cold Detector Test

    4/8

    4/15/16

    6dFPE Thermal

    Cycles (TCs) with Testing Over Full

    Temp Range

    4/4

    4/7/16

    4d

    Work Instruction Prep

    2/29

    3/16/16

    13d

    TRR

    3/22/16

    3/3/16

    JWST Risk B oard, Project decision

    2/29 5d

    ARB: Propose solution(s)

    2/1

    2/26/16

    20dComplete PFR-164 related tests

    in CV-3

    1/11

    1/22/16

    9d

    Root Cause Investig.- test

    repair plan

    1/11

    1/29/16

    14d

    ISIM Milestones

    Investigation/Decision Points

    Rework Activities

    MIRI FPE PFR 58524 DRAFT PATH FORWARD SCHEDULE

    FPE Vibe

    3/29

    3/30/16

    2d

    TVAC Test

    3/30

    4/1/16

    3d

    SMT Assembly

    4/6/16

    4/12/16

    5d

    SPW Spare Build

    Board Fab

    3/2/16

    4/5/16

    25d

    Thermal Plate Fab

    3/2

    3/15/16

    10d

    Hand Assembly

    4/13

    4/19/16

    5d

    Safe to Mate

    4/20

    4/26/1