GLAST LAT Project DOE/NASA Status Review, March 30 & 31, 2004
4.1.7 DAQ & FSW V5 1
GLAST Large Area Telescope:GLAST Large Area Telescope:
Gunther HallerSLACLAT Chief Electronics EngineerDAQ & Flight Software Systems Manager
[email protected](650) 926-4257
GammaGamma--ray Large ray Large Area Space Area Space TelescopeTelescope W.B.S 4.1.7 Electronics, Data W.B.S 4.1.7 Electronics, Data
Acquisition & Flight Software Acquisition & Flight Software
GLAST LAT Project DOE/NASA Status Review, March 30 & 31, 2004
4.1.7 DAQ & FSW V5 2
ContentsContents
• Technical Status• Roadmap to Flight Hardware/Software• Schedule• Cost and Budget• Summary
GLAST LAT Project DOE/NASA Status Review, March 30 & 31, 2004
4.1.7 DAQ & FSW V5 3
LAT Electronics Hardware and Flight SoftwareLAT Electronics Hardware and Flight Software
3 Event-Processor Units (EPU) (2 + 1 spare)
– Event processing CPU– LAT Communication Board– SIB
Spacecraft Interface Units (SIU)*
– Storage Interface Board (SIB): Spacecraft interface, control & telemetry
– LAT control CPU– LAT Communication
Board (LCB): LAT command and data interface
16 Tower Electronics Modules & Supplies
* Primary & Secondary Units shown in one chassis
Power-Distribution Unit (PDU)*– Spacecraft interface,
power– LAT power distribution– LAT health monitoring
Global-Trigger/ACD-EM/Signal-Distribution Unit*
TKR
CAL
FSW is an integral part of the data acquisition (DAQ) subsystem and is managed, budgeted, and scheduled as part of the DAQ subsystem
TKR Front-End Electronics (MCM)ACD Front-End Electronics (FREE)CAL Front-End Electronics (AFEE)
GLAST LAT Project DOE/NASA Status Review, March 30 & 31, 2004
4.1.7 DAQ & FSW V5 4
LAT ElectronicsLAT Electronics
• TKR: Tracker• CAL: Calorimeter• ACD: Anti-Coincidence Detector• TEM: Tower Electronics Module• EPU: Event Processor Unit• SIU: Spacecraft Interface Unit• GAS Unit: Global Trigger-ACD-
Signal Distribution Unit– CRU: Command/Response Unit– EBM: Event Builder Module– GEM: Global trigger Electronics
Module– AEM: ACD Electronics Module
• Flight Software running on RAD750 processors in SIU and EPU cPCI crates
GLAST LAT Project DOE/NASA Status Review, March 30 & 31, 2004
4.1.7 DAQ & FSW V5 5
ComponentsComponents
• Power Distribution Unit (PDU)• GASU
– GASU DAQ board with GASU ASICs & power-supply board• Tower Electronics Module (TEM) incl. TEM ASIC’s• Tower Power Supply (TPS)• Spacecraft Interface Unit (SIU) /Event-Processor Unit (EPU)
– Includes 4 custom boards• Heater Control Unit• Harness• Software• Front-End Simulator• Test-bed/EGSE (Electrical Ground Support Equipment)
GLAST LAT Project DOE/NASA Status Review, March 30 & 31, 2004
4.1.7 DAQ & FSW V5 6
PDU & GASU & GASUPDU & GASU & GASU--ASICASIC
• Power Distribution Unit– Switches power to TEM’s, GASU, EPU crates– Digitizes temperatures to be used for thermal
control • GASU
– Global trigger, event builder, command-response unit, ACD control/monitoring/data-readout
• GASU Power Supply– Supplies power to GASU and ACD from 28V
• Accomplishments– Designed/fabricated/assembled full enclosures
(primary and redundant) with flight-like components.– Functionality tested incl. FSW
• More detailed tests in progress– Being incorporated in DAQ/FSW test-bed– Qualification model with modifications incorporated
in layout• GASU DAQ ASIC (GLTC2)
– Full production fabricated/packaged– Screening has started at SLAC
GLAST LAT Project DOE/NASA Status Review, March 30 & 31, 2004
4.1.7 DAQ & FSW V5 7
TEM & TEM TEM & TEM ASICASIC’’ss & TPS& TPS
• Tower Electronics Module (TEM)– Control/readout/monitoring of
TKR and CAL sub-system• Tower Power Supply (TPS)
– Supply power to TEM/CAL/TKR from 28V
• Accomplishments– 16 sets of engineering models
were fabricated and assembled– Being tested and incorporated in
DAQ/FSW test-bed– Out for RFP for flight
fab/assembly, 1st article is used for qualification
• TEM ASIC’s (GTCC1 & GCCC1)– Full production was
fabricated/packaged– Have started screening at SLAC– Qualification will start at GSFC
next month
PICTURE
GLAST LAT Project DOE/NASA Status Review, March 30 & 31, 2004
4.1.7 DAQ & FSW V5 8
SIU/EPU (1)SIU/EPU (1)
• Modules– Custom Enclosure (cPCI crate)
• Holds modules– Custom cCPI Backplane (CBP)
• Interconnects modules– British AeroSpace 750 PPC processor board
• CPU– Custom LAT Communication Board (LCB)
• Control/event interface from cPCI processor to LAT – Custom Storage Interface Board (SIB)
• MIL1553 interface to spacecraft, EEPROM storage in crates– Custom Crate Power Supply (CPS)
• Supply power to PCI modules from 28V• Accomplishments
– Designed/fabricated/assembled fully functioning engineering modules with flight-like components
– Integrated in crate with BAE 750 processor– Tests in progress using flight software– Being integrated in DAQ/FSW test-bed– Some layout modifications in progress for qualification board fabrication
GLAST LAT Project DOE/NASA Status Review, March 30 & 31, 2004
4.1.7 DAQ & FSW V5 9
SIU/EPU (2)SIU/EPU (2)
Enclosure Backplane
Power-Supply CPU
SIB
LCB
GLAST LAT Project DOE/NASA Status Review, March 30 & 31, 2004
4.1.7 DAQ & FSW V5 10
Harness & Heater Control Unit & FES & EGSEHarness & Heater Control Unit & FES & EGSE
• Point-to-Point Cables (“Harness”)– Designed & ordered complete set of
cables for test-bed– Ready to integrate when available– Preparing package for RFP for flight
order• Heater Control Unit
– Designed/fabricated/assembled first-version engineering module
– Ready to test• Front-End Simulator
– Emulates CAL/TKR/ACD sub-systems for use on DAQ/FSW test-bed
– Designed/fabricated/assembled/tested front-end simulator board prototype
– Testing in progress, being integrated on test-bed
– Fabricated/assembled 34 copies
GLAST LAT Project DOE/NASA Status Review, March 30 & 31, 2004
4.1.7 DAQ & FSW V5 11
Flight SoftwareFlight Software• Incremental FSW builds coincide with the hardware builds as follows:
– Engineering Model 1 • Run single tower, single CPU
– Used for EGSE test-stands for hardware development (built, tested, done)
– Used for LAT single-tower engineering unit by I&T group (built, tested, done)
– Engineering Model 2 • Multiple towers, GASU, single CPU
– Used for EGSE test-stands for hardware development (in progress)– Used as test-bed for hardware and software development & test (in
progress)– ISIS (Instrument Spacecraft Interface Simulator) Build & Release
– To be delivered to the Spacecraft vendor (Formal Release)– Full LAT Build & Release
• Complete set of 16 towers, GASU, full set of CPU’s– Used as test-bed for hardware and software development & test– To be delivered to I&T for full-LAT testing (Formal Release)
GLAST LAT Project DOE/NASA Status Review, March 30 & 31, 2004
4.1.7 DAQ & FSW V5 12
LAT FSW ArchitectureLAT FSW Architecture
1553 Rx service
Spacecraft Interface Unit
Q
Q
Q
Q
Q
Q
Masters
1553 Tx service LCB Tx service
SC Att./Time
Watchdog
File/Object
HSK
Instr. Phys.
LCB Rx service
Other Tasks
Q
Q
Q
Slaves
SC Att./Time
File/Object
HSK
1 PPSInterrupt
GBM Interrupt
Event Processing Unit(s)
QLCB Tx service
LCBRx
Q
Other Tasks
Q
Q
Q
Slaves
SC Att./Time
File/Object
HSK
MSGtask
Q Instr. Phys.Q
Event Builder (EB) output side. The EB is an element of the GASU.To EPU(s)To SSR
Event Builder (EB) input side. The EB is an element of the GASU.Command/Response Unit (CRU). The CRU is an element of the GASU.
From SIU From EPU(s) Event Assembly
SolidState
Recorder
Spacecraft
1553
LAT Instrument
Command/Response
Data to SSR
Physics data from LAT
Slave to master
Master to slave
Telemetry (LAT to SC)
Telecommand (SC to LAT)
Legend
Discretes(to SIU PIDs)
To SIU
QQ TCS
Q WatchdogQ Watchdog
MSGtask
1 PPSInterrupt
* For details: FSW link on LAT main web-page
GLAST LAT Project DOE/NASA Status Review, March 30 & 31, 2004
4.1.7 DAQ & FSW V5 13
FSW Engineering Model 1FSW Engineering Model 1
TEM
Full set CAL front-end electronics
VME CPU with software
Full set TKR front-end electronics
• Accomplishments– Designed/tested/delivered
EM1 SW built– Software to run full tower
• Configuration of tracker, calorimeter, TEM
• Solicited Housekeeping• Event Delivery
– Also major progress in primary boot code of RAD750
* The test-stand shown does not have physics detectors
GLAST LAT Project DOE/NASA Status Review, March 30 & 31, 2004
4.1.7 DAQ & FSW V5 14
DataData--Taking with EM1Taking with EM1
• From EM1 testing as performed by I&T in the SLAC clean room– Includes physics detectors– Displays courtesy of the I&T
group and LATTE
GLAST LAT Project DOE/NASA Status Review, March 30 & 31, 2004
4.1.7 DAQ & FSW V5 15
Electrical Ground Support EquipmentElectrical Ground Support Equipment
• EGSE test-stand copies for ACD, CAL, TKR, DAQ HW & SW effort (60 total)
• Accomplishments– Ordered and received
• VME crates & single-board computers• VME SLAC custom transition board• Custom PCI Mezzanine Card (PMC) LCB’s• Connectors for cables• TEM & TEM PS boards and enclosures (for
TKR/CAL/DAQ setups)• GASU board and enclosure (for ACD/DAQ setups)• 28V-power supplies
– Have started testing and shipping of new test-stands
GLAST LAT Project DOE/NASA Status Review, March 30 & 31, 2004
4.1.7 DAQ & FSW V5 16
FSW/DAQ TestFSW/DAQ Test--BedBed
• Includes full set of DAQ modules/harness plus front-end simulator boards to emulate CAL/TKR/ACD front-end system
• Accomplishments– Produced DAQ modules for testbed– Started to integrate modules– Ready to start using FSW on the testbed mid/end April
GLAST LAT Project DOE/NASA Status Review, March 30 & 31, 2004
4.1.7 DAQ & FSW V5 17
Roadmap to Flight HardwareRoadmap to Flight Hardware
• Fabrication of printed circuit boards– 2 vendors selected
• Fabrication of enclosures– 1 Vendor selected
• Assembly of boards and modules– 2 vendors evaluated/qualified
• Harness– 2 vendors selected
GLAST LAT Project DOE/NASA Status Review, March 30 & 31, 2004
4.1.7 DAQ & FSW V5 18
Modules for Qualification Test and Flight DeliveryModules for Qualification Test and Flight Delivery
Jun-21May-21Apr-30Mar-30HarnessNov-1Sept-1May-26Apr-27EPU/SIUOct-27Aug-31Jun-23May-24GASUOct-14Aug-16May-10Apr-9PDU
Aug-2*Jun-25Apr-17Mar-17TEM & TEM-PS
End Testing
Start Qual ProgramStart Fab/Assembly
Drawing Release
Qualification Unit
Aug-20Aug-10Jul-13Aug-13HarnessJan-16Nov-16Sep-1Aug-1EPU/SIUJan-19Nov-19Aug-27Jul-27GASUJan-1Nov-18Aug-16Jul-16PDUAug-30Jul-16May-21Apr-17TEM & TEM-PS
I&T Delivery
Start FLT Accept. Program
Start Fab/Assembly
Drawing Release
Flight Unit
* TEM proto-flight is used for first 2 towers
GLAST LAT Project DOE/NASA Status Review, March 30 & 31, 2004
4.1.7 DAQ & FSW V5 19
Roadmap to Flight SoftwareRoadmap to Flight Software
• Functions added for EM2– GASU/PDU configuration– Streaming housekeeping– Inter-task communication– Primary/secondary boot of RAD750– MIL 1553 communication– Telecommand / telemetry– Software watchdog
• Functions added for Flight Unit – Event-filtering/compression– Event monitoring– Charge injection calibration– Diagnostics– Thermal control– Full command and telemetry
support– Time services– Gamma-Ray-Burst (GRB)
detection/alert – SC repointing request
• EM2 Flight Software design was reviewed by NASA/DOE committee 2/26/04– Assessment was very positive– Started to implement EM2 designs
GLAST LAT Project DOE/NASA Status Review, March 30 & 31, 2004
4.1.7 DAQ & FSW V5 20
Software Key Milestones for I&T/ISISSoftware Key Milestones for I&T/ISIS
• June 04– I&T requires software to control/readout multi-tower (i.e. GASU) configuration (EM2)
• July 04– Instrument Spacecraft Interface Simulator (ISIS) to Spectrum Astro
• August 04– Demo to LAT system engineering on fully instrumented test-bed
• December 04– I&T requires tested software to control/readout full LAT– FU SW build to I&T
• December 04– FU build finish and transition to formal test– FU Formal test complete Feb 05
• February 05– I&T requires FU software release to operate/test (whole LAT is integrated)– Start of system testing
• May 05– End of system test
• July 05– Ship LAT to NRL for environmental test
• Functional demonstrations every month to show progress
GLAST LAT Project DOE/NASA Status Review, March 30 & 31, 2004
4.1.7 DAQ & FSW V5 21
Open Issues, Technical Risks and MitigationsOpen Issues, Technical Risks and Mitigations
• FSW– BAE RAD750 flight processor might be different than BAE
engineering module in respect to operation• Scheduled to receive first flight processor in May
– Software needs to be shown to work on integrated instrument
• Tests and demonstrations are planned on integrated test-bed
• HW– Couple of components still need to be TID radiation tested
(DAQ ASIC’s, National transceiver)• Radiation tests planned for April/May
– Overall inter-system timing in respect to trigger needs to be shown to work
• Test planned on test-bed once complete
GLAST LAT Project DOE/NASA Status Review, March 30 & 31, 2004
4.1.7 DAQ & FSW V5 22
Critical Path for TEM DAQ Electronics to Tower ACritical Path for TEM DAQ Electronics to Tower A
Completion Dates (baseline variance)
Critical Path in Red
Finish Test TEM DAQ Board 6/18/04 (-39)
TEM DAQ Enclosure 6/1/04 (-39)
Start of Test TEM DAQ Assembly 6/25/04 (-39)
Tower A DAQ Electronics Delivered 8/2/04 (-39)
TEM PS Assembly 5/10/04 (-36)
End Acceptance Test 8/2/04 (-39)
Acceptance Test 7/2/04 (-36)
Design Cables Fab/Assemble Cables
4/30/04 (-42)
Acceptance Test 7/9/04 (-42)
Start FabTEM DAQ Board 4/17/04 (-39)
GLAST LAT Project DOE/NASA Status Review, March 30 & 31, 2004
4.1.7 DAQ & FSW V5 23
Approved Approved Cost Changes Since Cost Changes Since RebaselineRebaseline
(k$)
4.1.7 Baseline, November 03 $18,733Changes:• Additional FSW Manpower $ 747*• Additional EGSE $ 457• SIU Cost Variance Reduction $ 258• Stanford Benefits Rate Increase $ 155Total Change $ 1,6174.1.7 Baseline, February 04 $20,350
Approved Changes in March 04• ISIS Upgrade $ 94*
*Corresponding NASA funding increase
GLAST LAT Project DOE/NASA Status Review, March 30 & 31, 2004
4.1.7 DAQ & FSW V5 24
Schedule/BudgetSchedule/Budget
• Total budget: $20,350• Work Scheduled up to date: $11,472• Work Performed: $11,912• Actuals: $11,352• Schedule Variance $440k or 2.1% of total budget (ahead of
schedule)– Some flight components were delivered earlier than
expected• Cost Variance: $560k or 2.7% of total budget (under budget)
– Latency of invoicing/payment for components received
GLAST LAT Project DOE/NASA Status Review, March 30 & 31, 2004
4.1.7 DAQ & FSW V5 25
SummarySummary
• Technical:– No technical issues which would risk sub-system
• Schedule– Hardware is on track to provide flight hardware in time– Software schedule is aggressive but feasible
• Cost– No additional cost increases beyond what was discussed
are identified– Remaining budget should be sufficient to deliver sub-
system