Upload
lytu
View
222
Download
5
Embed Size (px)
Citation preview
Seite 1Milica Vukadinovic, GIZ DKTI programme
Implemented by:
Local subsidies / RDA Zlatibor / Center for Development Leskovac
DKTI - Development of a Sustainable Bioenergy Market in Serbia
GIZ DKTI Programme
Development of feasible biogas projects
21.04.2016
Seite 2
Structure of the presentation
Milica Vukadinovic, GIZ DKTI programme
1. About the GIZ DKTI Programme in Serbia
2. Framework conditions for biogas project
development
3. Investments in agricultural biogas facilities in Serbia
4. Viable biogas concept from the DKTI perspective
21.04.2016
Implemented by:
Seite 3
Facts about the GIZ DKTI programme
Milica Vukadinovic, GIZ DKTI programme
Objective: To strengthen capacities and create an enabling
environment for sustainable use of bioenergy in Serbia
Funded by: German Federal Ministry for Economic Cooperation and
Development (BMZ) under the German Climate Technology
Initiative (DKTI)
Duration: March 2013 – December 2017
Political partners: Ministry of Agriculture and Environmental Protection &
Ministry of Mining and Energy
21.04.2016
Implemented by:
Seite 4Milica Vukadinovic, GIZ DKTI programme21.04.2016
Structure of the programme:
Efficient use of
firewood in HHPolicy advice Project
development
Biomass
supply
KfW - FA: Advise to
investments in
district heating
companies
GIZ - TA: Support to the
creation of a
sustainable
supply of
biomass
GIZ: Support to
harmonization
of laws and
regulations to
EU standards
Support to
policy definition
and strategy
implementation
GIZ:Promotion of
efficient stoves
and ovens /
firewood drying
Advise to
implement
efficiency- and
emission
standards
GIZ:Advise to the
implementation
of cost efficient
and innovative
bioenergy
projects
Technology and
knowlege
transfer
Cross-cutting theme: sustainability
BioRES
GIZ:Support to the
creation of
regional
Biomass Trade
and Logistic
centres
Support
development of
local biomass
supply chains
Implemented by:
Seite 5
Project development component
Milica Vukadinovic, GIZ DKTI programme
Capacity building: awareness raising, financial and technical
know-how, operation of bioenergy facilities
Identification of projects and potential investors: bioenergy
heating systems in public buildings, biogas facilities, facilities for
generation of industrial process heat
Technical assistance:
plant design and project concepts, elaboration of bankable
(pre-)feasibility studies, project documentation, etc.
access to finance and investment subsidies
development of biomass supply chain
21.04.2016
Implemented by:
Seite 6
Project development component
Milica Vukadinovic, GIZ DKTI programme
Technical support for enhancement of efficiency of processes
related to procurement procedure, permits and licensing for
bioenergy projects
Best-practice dissemination
Dialogue-platform for Serbian and international companies and
institutional stakeholders to exchange project ideas, information
and experiences
21.04.2016
Implemented by:
Seite 7Milica Vukadinovic, GIZ DKTI programme21.04.2016
Thematic areas
Straw
combustion for
process heat
Fuel switch in
public buildings
Biogas project
development
Awareness raising
Capacity building
Technology partnership / Multiplication of best practices
Identification of projects / Acceptance
Concept development / pre-feasibility
Feasibility assessment / Investment structuring / A2F
Implementation
Implemented by:
Seite 8
Structure of the presentation
Milica Vukadinovic, GIZ DKTI programme
1. About the GIZ DKTI Programme in Serbia
2. Framework conditions for biogas project
development
3. Investments in agricultural biogas facilities in Serbia
4. Viable biogas concept from the DKTI perspective
21.04.2016
Implemented by:
Seite 9
139 159 186 274 370 450617
8501.050
1.3001.600
1.7502.050
2.680
3.5003.711
3.891
5.181
6.268
7.766
8.213
8.5638.726
8.928
650
1.100
1.2711.377
1.893
2.291
3.097
3.352
3.637
3.905
4.177
0
500
1.000
1.500
2.000
2.500
3.000
3.500
4.000
4.500
0
1.000
2.000
3.000
4.000
5.000
6.000
7.000
8.000
9.000
10.000
Ins
talle
d e
lec
tric
ca
pa
cit
y
Nu
mb
er
of
bio
ga
s p
lan
ts
Years
Number of biogas plants in Germany
Installed electric capacity in Megawatt [MW]
© Fachverband Biogas e.V. / German Biogas Association
Number of biogas plants in Germany and installed capacity
Milica Vukadinovic, GIZ DKTI programme21.04.2016
EEG 2004
EEG 2009
EEG 2012
EEG 2014
Seite 10
139 159 186 274 370 450617
8501.050
1.3001.600
1.7502.050
2.680
3.5003.711
3.891
5.181
6.268
7.766
8.213
8.5638.726
8.928
650
1.100
1.2711.377
1.893
2.291
3.097
3.352
3.637
3.905
4.177
0
500
1.000
1.500
2.000
2.500
3.000
3.500
4.000
4.500
0
1.000
2.000
3.000
4.000
5.000
6.000
7.000
8.000
9.000
10.000
Ins
talle
d e
lec
tric
ca
pa
cit
y
Nu
mb
er
of
bio
ga
s p
lan
ts
Years
Number of biogas plants in Germany
Installed electric capacity in Megawatt [MW]
© Fachverband Biogas e.V. / German Biogas Association
Number of biogas plants in Germany and installed capacity
Milica Vukadinovic, GIZ DKTI programme21.04.2016
EEG 2004
EEG 2009
EEG 2012
EEG 2014
Bonus for
energy crops
Bonus for
using heat...
450 new
plants p.a.
New
requirements
on efficiency
and ecology
340 new
plants p.a.
Bonus for emission
reduction
Bonus for manure
1000 new plants p.a.
Bonus for
energy crops
Bonus for
using heat...
200 new
plants in
2015
Seite 11
Feed-in Tariffs for Biomass and Biogas in Serbia
(based on proposal for 2016)
Milica Vukadinovic, GIZ DKTI programme21.04.2016
Type of Electrical Generation Feed-in Tariff
Biomass power plant up to 1 MWel 13,26 €Ct./kWh
Biomass power plant 1 - 10 MWel 13,82-0,56 x Pel €Ct./kWh
Biomass power plant 10 MWel 8,22 €Ct/kWh
Biogas power plant up to 2 MWel 18,333 – 1,111 x Pel €Ct./kWh
Biogas power plant 2 - 5 MWel 16,852 – 0,370 x Pel €Ct./kWh
Biogas power plant over 5 MWel 15 €Ct/kWhSource: http://www.mre.gov.rs/doc/javne%20rasprave/28.09/Objedinjeno%20Uredba%20o%20podsticajnim%20merama%202015%20098%2014a.pdf
Annual increasing rate = inflation rate of EURO zone
Duration of power purchase agreement (PPA)= 12 years
Implemented by:
Seite 12
Biogas potential from manure in Serbia
Milica Vukadinovic, GIZ DKTI programme21.04.2016
Type of Biomass
Theoretica
l potential
in PJ in
Serbia
Electrical
efficiency in %
Potential electrical
energy in GWh/a
Potential electrical
capacity in MW
Manure (cattle, pig and
poultry)e3.4 34 322.2 45
Velvet Farm plant, Curug, Serbia - Photo: GIZ 2014
Source: DBFZ Study 2015
Solid cattle manure, Serbia - Photo: GIZ 2014
Liquid cattle manure, Serbia - Photo: GIZ 2014Liquid pig manure, Serbia - Photo: GIZ 2014
Implemented by:
Seite 13
Project proposal medium-sized farm
50 kWel biogas plant in Serbia
Milica Vukadinovic, GIZ DKTI programme
Initial values:
Following scenarios are evaluated:
1. Digestion of available liquid pig manure for electricity generation of
50 kWel
2. Digestion of available liquid and solid cattle manure for electricity
generation of 50 kWel
100 % of electricity generated will be sold under current feed-in-tariffs,
30% of heat generated will be used for internal heating purposes
21.04.2016
Institute for Animal Husbandry, Serbia - Photo: GIZ 2015
Implemented by:
Seite 14
Project proposal 50 kWel biogas plant in Serbia:
Manure input – required quantity and quality
Milica Vukadinovic, GIZ DKTI programme21.04.2016
Cattle Farm in Serbia, Photo: GIZ 2015
Substrates DMS oDMS
t/a m³/d % FM % DMS % m³/year l/kg oDMS m³/year
Liquid Pork manure 31,928 87 2.0% 75% 60% 120,687 420.0 201,145
total 31,928 87 120,687 201,145
Production of CH4Fresh Material
Biogas production of substrates
Production of biogas
or
Pig farm of around 4.000 animal units (fatteners) or cattle farm
around 500 animal units can provide needed amount for the
proposed plant size
Analysis of organic dry matter content and real quantity values
necessary for each individual farm and project
Biogas production of substratesSubstrates Fresh Material DMS oDMS COD Production of CH4 Production of biogas
t/a m³/d % FM % DMS mg/l % m³/year l/kg oDMS m³/year
Liquid cattle manure 10,142 28 7.0% 75% 53% 95,458.15 337.0 179,433
Solid cattle manure 730 2 18.0% 80% 60% 25,229 400.0 42,048
total 10,872 30 8% 0 120,687 221,481
Implemented by:
Seite 15
Output 50 kWel biogas plant
Milica Vukadinovic, GIZ DKTI programme21.04.2016
Production of CH4 120,687 m³/a
Caloric Value CH4 9.968 kWh/m³
Losses 5.0%
Energy Potential 1,142,857 kWh/a
Energy Potential Capacity 143 kW
Energetic Use
Energy potential 1,142,857 kWh/a 0 kWh/a
Caloric Capacity 143 kW 0 kW
Electrical Capacity 50 kW 0 kW
Electrical Efficiency 35% 0%
Thermal Eficiency 40% 0%
Thermal Capacity 57 kW 0 kW
Overall capacity 143 kW 0 kW
Full operation time 8000 hours/a 0 hours/a
Electricity Generation 400,000 kWh/a 0 kWh/a
Heat Generation 457,143 kWh/a 0 kWh/a
Energetic Demand 1,142,857 kWh/a 1,142,857 kWh/a
Calorific Value Natural Gas 8.5 kWh/m³
Sustitution of Natural Gas 134,454 m³ / year
CHP Steam Production (24/7)
Energy Use
Source: Own Calculations GIZ, 2015
Photo: GIZ Serbia 2015
30-40 % of generated heat shall be used for biogas process (own consumption)
Implemented by:
Seite 16
Estimated investment costs (CAPEX) for model-case
Milica Vukadinovic, GIZ DKTI programme21.04.2016
Investment CostsDescription Quantity Cost per Unit Total Cost Life-Time Depreciation
1 Ground preparation 1.00 10,000.00 10,000.00€ 15.00 666.67€
2 Foundations and canals 1.00 10,000.00 10,000.00€ 15.00 666.67€
3
Installation of Digesters incl Heating
system, Protection and Insulation 1.00 70,000.00 70,000.00€ 15.00 4,666.67€
4 Buildings and Infrastructure 1.00 10,000.00 10,000.00€ 15.00 666.67€
5 Storage Tank open 1.00 50,000.00 50,000.00€ 15.00 3,333.33€
6 Installation of equipment 1.00 50,000.00 50,000.00€ 15.00 3,333.33€
200,000.00€
Planning and Engineering1 Project Concept and Permission 1.00 10,000.00 10,000.00€ 15.00 666.67€
2 Design and Feasibility Studie 1.00 10,000.00 10,000.00€ 15.00 666.67€
3 Site supervision 1.00 10,000.00 10,000.00€ 15.00 666.67€
4 30,000.00€
Equipment and Components1 Pumping systems 1 7,500.00 7,500.00€ 15.00 500.00€
2 Tube system Substrate 1 10,000.00 10,000.00€ 15.00 666.67€
3 Agitation systems 4 5,000.00 20,000.00€ 15.00 1,333.33€
4 Gas membrane 1 15,000.00 15,000.00€ 15.00 1,000.00€
5 Biogas flare 1 5,000.00 5,000.00€ 15.00 333.33€
6 Gas treatment 1 10,000.00 10,000.00€ 15.00 666.67€
7 Gas pipelines 1 5,000.00 5,000.00€ 15.00 333.33€
8 Measuring and Control 1 5,000.00 5,000.00€ 15.00 333.33€
9 CHP and Transformer Station 1 60,000.00 60,000.00€ 15.00 4,000.00€
10 Electrical Integration 1 20,000.00 20,000.00€ 15.00 1,333.33€
157,500.00€
Other
1 Miscelleanous 5% 387,500.00€ 19,375.00€ 15.00 1,291.67€
2 Insurance and Bank Guarantees 2.5% 387,500.00€ 9,687.50€ 15.00 645.83€
5 29,062.50€
416,562.50€ 27,770.83€
Civil Works
8.331 €/kW overall
estimated
investment cost
Photo: Fachverband Biogas 2015
Implemented by:
Seite 17
Cash Flow: 50 kW Biogas Manure Plant, FiT= 18Ct/kWh
Milica Vukadinovic, GIZ DKTI programme21.04.2016
Source: Own Calculations GIZ, 2015
Indicators 10 years 15 years
NPV (5%) 74,718.89€ 244,638.95€
IRR 15.04% 21.30%
Concept0 1 11 12 13 14 15
Total (15
years)
Heat Use 3,291.43 5,015.29 5,115.60 5,217.91 5,322.27 5,428.71 70,327.20
Electricity Feed-In 57,600.00 87,767.60 89,522.95 91,313.41 93,139.68 95,002.47 1,230,726.02
Reduction of CO²-Emission 0.00 0.00 0.00 0.00 0.00 0.00 0.00
TOTAL INCOMES 60,891.43 92,782.89 94,638.55 96,531.32 98,461.94 100,431.18 1,301,053.22
Raw Material 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Maintenance Biogas plant 4,278.75 6,519.72 6,650.11 6,783.11 6,918.77 7,057.15 91,423.07
Electricity Consumption 960.00 1,462.79 1,492.05 1,521.89 1,552.33 1,583.37 20,512.10
Operation Staff 2,920.00 4,449.33 4,538.32 4,629.08 4,721.66 4,816.10 62,390.97
Telekommunication 300.00 365.70 373.01 380.47 388.08 395.84 5,188.03
Biological Support 2,500.00 3,047.49 3,108.44 3,170.60 3,234.02 3,298.70 43,233.54
Fees and dues 1,000.00 1,218.99 1,243.37 1,268.24 1,293.61 1,319.48 17,293.42
Administration and Overhead 608.91 927.83 946.39 965.31 984.62 1,004.31 13,010.53
Insurance 1,041.41 1,041.41 1,041.41 1,041.41 1,041.41 1,041.41 15,621.09
Miscelleanous 1,217.83 1,855.66 1,892.77 1,930.63 1,969.24 2,008.62 26,021.06
Maintenance CHP 4,800.00 7,313.97 7,460.25 7,609.45 7,761.64 7,916.87 102,560.50
TOTAL Operation Costs 19,626.90 28,202.88 28,746.11 29,300.20 29,865.38 30,441.86 397,254.32
EBITDA 41,264.53 64,580.01 65,892.44 67,231.12 68,596.57 69,989.33 903,798.90
Interest costs 11,455.47 0.00 0.00 0.00 0.00 0.00 67,597.75
EBTDA 29,809.06 64,580.01 65,892.44 67,231.12 68,596.57 69,989.33 836,201.15
Taxes 0 0 0 0 0 0 0.00
NET SURPLUS 29,809.06 64,580.01 65,892.44 67,231.12 68,596.57 69,989.33 836,201.15
Investment Costs -416,562.50 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Working Capital 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Debt Financing 229,109.38 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Repayment 18,215.24 0.00 0.00 0.00 0.00 0.00 229,109.38
Grant 62,484.38 0.00 0.00 0.00 0.00 0.00 0.00 0.00
0.00
CASH FLOW -124,968.75 11,593.82 64,580.01 65,892.44 67,231.12 68,596.57 69,989.33 482,123.03
OVERVIEW CASH-FLOW in Euro
≈ +15 %
increase in FiT
≈ +45 %
increase in
profitability!!
Implemented by:
Seite 18
Technical and financial aspects to consider
Milica Vukadinovic, GIZ DKTI programme
Modification of existing manure tanks for conversion into a biogas
digester possible by installing heat insulation, agitation system, gas
storage, heating pipes and concrete protection
Low dry matter content may require specific biogas technology or
additional solid organic substrates
Availability of slurry and manure all over the year
Additional external heat demand for further income growth
Grant availability and requirements – IPARD funds for example
21.04.2016
Implemented by:
Seite 19
Agricultural biogas plant example
Milica Vukadinovic, GIZ DKTI programme21.04.2016
City halls, schools, hospitals, swimming pools, grennhouses etc.
Source: ‘Biogas – an introduction’, FNR, 2009
Implemented by:
Seite 20
Regional and national benefits
Milica Vukadinovic, GIZ DKTI programme21.04.2016
Implemented by:
New jobs in various sectors: agriculture, crafts and trades, machine
and component suppliers, biogas operators etc.
Additional taxes to the municipality
Production of high-quality fertilizer for farms
Generation of electricity and heat from renewable energy sources
Security of supply
Climate protection
Seite 21Milica Vukadinovic, GIZ DKTI programme21.04.2016
Thank you for your attention!
Milica Vukadinovic, GIZ-DKTI Component Leader Project Development
Deutsche Gesellschaft für
Internationale Zusammenarbeit
(GIZ) GmbH
Development of a Sustainable
Bioenergy Market in Serbia
Bože Jankovića 39
11000 Belgrade
Serbia
T +381 11 3912 507
Please visit us on: www.bioenergy-serbia.rs
Implemented by: