Greta Energy Investment Projects in South Federal District Of Russian Federation. Belilovsky V. Ermolenko G. Tshomaria V. Kompanietz E. Popel O. Dunaev K. Kaledina A. German-Russian seminar for nontraditional and renewable sources of energy. Berlin 12-13.11.08. Nikomarova A. - PowerPoint PPT Presentation

Citation preview

Page 1: German-Russian seminar for nontraditional and renewable sources of energy. Berlin 12-13.11.08

German-Russian seminar for nontraditional and renewable sources of energy. Berlin 12-13.11.08

Popel O.Dunaev K.Kaledina A.

Belilovsky V.Ermolenko G.Tshomaria V.Kompanietz E.Kompanietz E.

Greta Energy Investment Projects in South Federal District Of Russian Federation

Nikomarova A.

Page 2: German-Russian seminar for nontraditional and renewable sources of energy. Berlin 12-13.11.08

Small HPPs of Uruch and Hazni-Don rivers in Kabardino-Balkariya

Feasibility of the Project

Page 3: German-Russian seminar for nontraditional and renewable sources of energy. Berlin 12-13.11.08

Project DescriptionProject Description

The project foresees construction of:

• 2 HPPs cascade at Uruch river

• 4 HPPs cascade at Hazni-Don river

With total installed capacity 45 MW

Page 4: German-Russian seminar for nontraditional and renewable sources of energy. Berlin 12-13.11.08

Goal of the projectGoal of the project

To increase power generating capacities of Kabardino-Balkariya Republic with minimization of negative environmental impact

Year 2008:

Deficit of generating capacities 85%

Deficit of power 74%

Page 5: German-Russian seminar for nontraditional and renewable sources of energy. Berlin 12-13.11.08

Project Participants

Investor:

Engineering, planning, main equipment producer&supplier

JSC «Greta Energy RU»

JSC «INSET»

Page 6: German-Russian seminar for nontraditional and renewable sources of energy. Berlin 12-13.11.08
Page 7: German-Russian seminar for nontraditional and renewable sources of energy. Berlin 12-13.11.08
Page 8: German-Russian seminar for nontraditional and renewable sources of energy. Berlin 12-13.11.08
Page 9: German-Russian seminar for nontraditional and renewable sources of energy. Berlin 12-13.11.08
Page 10: German-Russian seminar for nontraditional and renewable sources of energy. Berlin 12-13.11.08

Main Equipment

Parameters

Name of HPP

Turbines Number of

unitsLife time,

years

«Uruchskya-1» ГА8М2 (propeller) 4 40

«Uruchskya-2» ГА9М (Francis turbine) 6 40

«Hadzidon-1» ГА10 (Pelton turbine) 2 40

«Hadzidon-2» ГА10 (Pelton turbine) 3 40

«Hadzidon-3» ГА10 (Pelton turbine) 4 40

«Hadzidon-4» ГА10М (Pelton turbine)ГА10 (Pelton turbine)

21

40

Page 11: German-Russian seminar for nontraditional and renewable sources of energy. Berlin 12-13.11.08

Main parameters of SHPPs at Uruch river

№п/п

Parameter Units Total

Including HPP

SHPP-1 SHPP-2

1 Calculated capacity MW 20,8 11,06 9,74

2Guaranteed capacity

MW 3,2 1,0 2,2

3 Installed capacity MW 22,1 12,5 9,6

4 Calculated flow m3/s 55,0 40,0 15,0

5 Calculated head m 35,0÷81,06 35,0 81,06

6 Hours of operationThousand

hours- 3,15 5,50

7Average annual production

Mln. kWh 88,4 34,83 53,57

Page 12: German-Russian seminar for nontraditional and renewable sources of energy. Berlin 12-13.11.08

Main parameters of SHPPs at Hazni-Don river

№п/п

Parameter Units Total

Including SHPP

SHPP-1 SHPP-2

1 Calculated capacity MW 22,33 5,17 5,26

2 Guaranteed capacity MW 5,28 1,38 1,38

3 Installed capacity MW 22,9 5,4 5,4

4 Calculated flow m3/s 11,72 2,16 2,16

5 Calculated head m 1086 311,5 310

6 Hours of operationThousand

hours- 3,30 3,28

7Average annual production

Mln. kWh 86,82 17,04 17,26

Page 13: German-Russian seminar for nontraditional and renewable sources of energy. Berlin 12-13.11.08

Main parameters of SHPPs at Hazni-Don river

№п/п

Parameter Units Total

Including SHPP

SHPP-3 SHPP-4

1 Calculated capacity MW 22,33 6,75 5,15

2 Guaranteed capacity MW 5,28 1,41 1,11

3 Installed capacity MW 22,9 7,0 5,10

4 Calculated flow m3/s 11,72 3,30 4,10

5 Calculated head m 1086 310,5 154

6 Hours of operationThousand

hours- 4,35 4,50

7Average annual production

Mln. kWh 86,82 29,34 23,18

Page 14: German-Russian seminar for nontraditional and renewable sources of energy. Berlin 12-13.11.08

Preliminary project economical profile

SHPP

Indicators

SHPP cascade of Uruch river

SHPP cascade of Hazni-Don river

Total investment, mln. rub 948 930

Specific investments, mln. Rub./1MW 42,9 40,6

Tariff for power, rub./kWh 2,76 2,76

Power purchase income, mln. rub 242,76 238,43

Page 15: German-Russian seminar for nontraditional and renewable sources of energy. Berlin 12-13.11.08

Economical effectiveness indicators Value

Total investment, billion rub1,878

NPV, billion rub 2,769

IRR, %19,68

Discounted payback time, years6,7

Preliminary project economical

profile

Page 16: German-Russian seminar for nontraditional and renewable sources of energy. Berlin 12-13.11.08

Белиловский В. А.Ермоленко Г. В.Каледина А. С.Цхомария В. Н.

Page 17: German-Russian seminar for nontraditional and renewable sources of energy. Berlin 12-13.11.08

Permanent constant price increase for energy resources in Russia, strengthening of environmental requirements, as well as an increasing risk of power grid shutdowns and emergencies makes domestic experts and agricultural enterprises select modern processing and recycling technologies of cattle breeding and poultry farm waste.

Page 18: German-Russian seminar for nontraditional and renewable sources of energy. Berlin 12-13.11.08

The following problems can be solved by anaerobic digestion of biodegradable waste:

Implementation of environmental protecting measures to reduce toxic emissions into air, water and soil;

Increasing farm profits by using biogas for heat and power production, as well as offering to the market organic fertilizers with stable properties (absence of smell or repeated rotting), moreover 1 litre of which equals to 100 kg of manure used as fertilizers;

Improvement of reliability and safety in energy supply of cattle breeding and poultry farms by using its own renewable energy sources;

Improvement of soils fertility and fodder area crops by using fertilizers, as a source of biogenic elements and humus.

Page 19: German-Russian seminar for nontraditional and renewable sources of energy. Berlin 12-13.11.08

The technology of anaerobic methane digestion with regard to circulation of organics allows to create a system with closed cycle: crop raising - fodder and foodstuffs - waste - anaerobic digestion – crop raising. In this scheme agricultural sector is provided with fertilizers and fodders, and industrial sector (in case of methane recycling) with raw material and energy. This approach contributes to Kyoto Protocol and leads to the reduction of: pollutions, greenhouse gases emission and consumption of nonrenewable resources.

Page 20: German-Russian seminar for nontraditional and renewable sources of energy. Berlin 12-13.11.08

According to the statistics of German Biogas Association there are 2200 agricultural biogas plants currently in operation in Europe .

            *(Austria 119, Belgium 100, Czech Rep. 10, Denmark 40, France 5, Germany 1900, Greece 67, Irland 13, Italy 67, Lithuania 4, Netherlands 15, Poland 15, Portugal 100, Sweden 6, Swizerland 69, UK 60)

Page 21: German-Russian seminar for nontraditional and renewable sources of energy. Berlin 12-13.11.08

Distribution of total amount of agricultural sector organic waste among the federal districts of Russia (mln. Tons/%)

Page 22: German-Russian seminar for nontraditional and renewable sources of energy. Berlin 12-13.11.08

The largest share of organic agricultural waste (225 mln t. 36 %) is produced in the Southern Federal District. That’s why Krasnodarskiy Krai is the region of our interests. In the table below one can see data on waste productivity of Yeysk farms.

Farms Waste productivity, tons/dayООО "СПЭ" 71,1ЗАО "Заводское" 27,6АФ "Кухаревская" 44СХП "Советское" 112,9ООО "Кубань-СВ" 43ООО "Камышеватский" 27,2ЗАО "Ясенские зори" 57,8ЗАО "Воронцовское" 44,8АФ "Александровская" 10,3ООО "Агро-Вита" 59,4АФ "Приморская" 13,9ЗАО "Родина" 127,1

Page 23: German-Russian seminar for nontraditional and renewable sources of energy. Berlin 12-13.11.08

«GRETA ENERGY RU» and Yeysk administration are discussing feasibility of biogas plants construction using the waste of the above mentioned farms. For example we examined one of these farms – JSC “Rodina”.

Page 24: German-Russian seminar for nontraditional and renewable sources of energy. Berlin 12-13.11.08

The construction of bioenergy power plant and organic fertilizers production line using manure and agricultural

waste as raw material

The aim of the project is to construct biogas plant for JSC “Rodina” farm (Krasnodarkiy krai, Yeysk) operating on the base of recycling biomass and cattle breeding waste.

The project of constructing biogas plant goes along with «Russian Energy Strategy up to 2020» which defines the development of renewable energy as a priority direction.

Page 25: German-Russian seminar for nontraditional and renewable sources of energy. Berlin 12-13.11.08

The goals of the project and ways of achieving them.

Goals Ways of achieving

Improvement of reliability and safety of farms’ power supply

Construction on the territory of the farm, bioenergy plant, working on biogas, produced from the manure of the farm;Receiving additional heat from the heat exchangers of the fermented manure in methane tanks

Improvement of environmental protection

For atmosphere – prevention of biogas (methane) emissions and as well as reduction of natural gas used in heat production; For soil – prevention of contaminated manure and other biowaste emissions; For water – prevention of biogenic elements emissions into rain, soil, spring- flood and other water

Page 26: German-Russian seminar for nontraditional and renewable sources of energy. Berlin 12-13.11.08

Goals Ways of achieving

Improvement of economic effectiveness

Receiving additional profits due to:reduction of electric power purchase from utilities; reduction of natural gas purchase; reduction of mineral fertilizers purchase; Sales of bio fertilizers excess, obtained as a result of waste recycling; decrease of expenditures due to harmful emissions reduction.

Page 27: German-Russian seminar for nontraditional and renewable sources of energy. Berlin 12-13.11.08
Page 28: German-Russian seminar for nontraditional and renewable sources of energy. Berlin 12-13.11.08

Data used for calculation:average annual livestock of animals – 3486 headsdaily quantity of manure – 127,1 tons/dayhumidity of manure – 85% (mechanical harvesting)yield of biogas with 1 kg a. g. m. from 0,25 - 0,35 м3 of

biogas (60% СН4 and 40% СО2 )humidity of silo - 75%yield of biogas from 1 kg a. g. m. of silo from 0,4- 0,6 м3

biogas (60% СН4 and 40% СО2)Efficiency of conversion of biogas energy into heat– 85%Efficiency of conversion of biogas energy into power- 30% Price of electric power - 2 rub. 32 k. of KWt.hPrice of fertilizers - 1000 rbl. / ton 1 liter of such fertilizers, obtained as a result of manure

recycling, equals to 100 kg of manure, used as fertilizers

Page 29: German-Russian seminar for nontraditional and renewable sources of energy. Berlin 12-13.11.08

the yield of biogas calculation

ParamentValue

UnitsMin MaxThe required volume of bioreactor 2097 cubic meters

Biogas The volume of produced biogas 4766 6673 cubic meters/day

Organic fertilizers The volume of produced organic fertilizers per day 120 tons/day The volume of produced organic fertilizers per year 43883 tons/yr

Organic fertilizers moisture content 90,0% % Power production

Per hour 343 480 kWh/hPer day 8240 11536 kWh/dayPer year 3007 4210 MWh/yr

Heat productionPer hour 0,839 1,174 Gcal/hPer day 20 28 Gcal/dayPer year 7346 10285 Gcal/yr

Motor fuel equivalent

Daily output of motor fuel equivalent 2860 4003 liter/day Annual output of motor fuel equivalent 1043809 1461332 liter/year

natural gas equivalentDaily output of natural gas equivalent 2860 4003 cubic meters/dayAnnual output of natural equivalent 1043809 1461332 cubic meters/yr

1.The energy characteristics of bioreactor utilizing manure.

Page 30: German-Russian seminar for nontraditional and renewable sources of energy. Berlin 12-13.11.08

ParametrValue

UnitsMin Max

The needed volume of bioreactor 3240 cubic meters

Biogas

The volume of produced biogas 8576 12388cubic

meters/day

Organic fertilizers

The volume of produced organic fertilizers per day 156 tons/day

The volume of produced organic fertilizers per year 57049 tons/yr

Organic fertilizers moisture 90,0% %

Power production

Per hour 618 892 kW/h

Per day 14828 21417 kW/day

Per year 5412 7817 MW/yr

Heat production

Per hour 1,5 2,1 Gcal/h

Per day 36 52 Gcal/day

Per year 13219 19094 Gcal/yr

Motor fuel equivalent

Daily output of motor fuel equivalent 5145 7433 liter/day

Annual output of motor fuel equivalent 1878199 2712917 liter/year

natural gas equivalent

Daily output of natural gas equivalent 5145 7433cubic

meters/day

Annual output of natural equivalent 1878199 2712917 cubic meters/yr

2. The energy characteristics of bioreactor utilizind manure + 30% silo.

Page 31: German-Russian seminar for nontraditional and renewable sources of energy. Berlin 12-13.11.08

biogas plant price calculationParameter thousand rbl

Price of technological equipment, 28712

Price of design and technological documentation (working design)

2316

Construction and installation, putting into operation, technological supervision, staff training

11652

Total price of biogas system 42680

Price of cogeneration installation 37000

Total 79680

Page 32: German-Russian seminar for nontraditional and renewable sources of energy. Berlin 12-13.11.08

Preliminary economic estimatePrice of biogas installation, thousand rbl. 80000

Annual operational expenditures for newly introduced installation

Wages of 5 service staff workers (85 thousand rbl per person of the annual wage fund), thousand rbl.

425

Annual maintanace expenditures - 1% of total equipment price , thousand rbl

800

Basic repair expenditures - 2,6% of total price, thousand rbl 2080

Total expenditures 3305

Annual expenditures reduction

Utilized raw materials Manure Manure+30% silo

Reduction of heat charges, thousand rbl. 6976 12556

Value of sold fertilizers (50% of produced fertilizers), thousand rbl. 21942 28525

Total 28918 41081

Annual economic effect, thousand rbl. 25613 37776

Payback period, year 3 2

Page 33: German-Russian seminar for nontraditional and renewable sources of energy. Berlin 12-13.11.08

Project financing

The construction of biogas plant will be lead by «GRETA ENERY RU». Once the construction is complete, the plant will be leased to the corresponding farm.

The financing scheme: Loans – 90 % - 72000 thousand rbl. Budgetary financing – 0 % - 0 thousand rbl. Shareholders' equity – 10 % - 8000 thousand

rbl.

Page 34: German-Russian seminar for nontraditional and renewable sources of energy. Berlin 12-13.11.08

Resume

Annual economic effect from biogas plant - 25613 thousand rbl. (in case of animal manure recycling only), payback period - 3 years.

Adding 30% silo will change the annual economic effect to 37776 thousand rbl., payback period - 2 years.

Page 35: German-Russian seminar for nontraditional and renewable sources of energy. Berlin 12-13.11.08

ResumeBiogas plant will produce both heat and

power to partially cover the needs of JSC “Rodina” (greenhouses, biolaboratory, administrative buildings). Moreover biogas plant will effectively recycle biowaste – manure (127, 1 ton a day and produce environmentally friendly and highly effective fertilizers as a by-product (1 litre of which equals to 100 kg of manure used as fertilizers).

Important results of the project are saving of traditional fuel and reduction of greenhouse gases emissions into atmosphere.

Page 36: German-Russian seminar for nontraditional and renewable sources of energy. Berlin 12-13.11.08

Yeisk Wind Farm 50 MWt in Yeisk Wind Farm 50 MWt in Krasnodar regionKrasnodar region

Page 37: German-Russian seminar for nontraditional and renewable sources of energy. Berlin 12-13.11.08

Project descriptionProject descriptionConstruction of 50 MW wind power plant in Yeisk

municipality of Krasnodar Krai (25 wind generators with unit capacity 2 MW)

Project GoalsProject Goals- Environmental friendly power supply of recreation zone;

- Improvement of power supply reliability at the dead end of HV line.

Page 38: German-Russian seminar for nontraditional and renewable sources of energy. Berlin 12-13.11.08

Location of Yeisk wind farmLocation of Yeisk wind farm

В Э СВ Э С

50 МВт50 МВт

Site coordinates:

46.7 degrees of north latitude

38,3 degrees of east longitude

Page 39: German-Russian seminar for nontraditional and renewable sources of energy. Berlin 12-13.11.08

70 м

THE WIND MONITORING THE WIND MONITORING MAST AT THE YEISK SITEMAST AT THE YEISK SITE

- - Height of mastHeight of mast – 70 – 70 mm

- - Measurement of speeds and wind Measurement of speeds and wind directions at heightsdirections at heights 40, 50, 60 и 40, 50, 60 и 70 70 mm

- - Measurement of air temperature Measurement of air temperature

- - The independent power supply The independent power supply from solar modulesfrom solar modules

-- GSM data transmission GSM data transmission

Page 40: German-Russian seminar for nontraditional and renewable sources of energy. Berlin 12-13.11.08

Preliminary results of wind monitoring have Preliminary results of wind monitoring have shown higher than reference data wind shown higher than reference data wind potential at the site. potential at the site.

Preliminary calculated annual electricity Preliminary calculated annual electricity production - production - 170 170 mlnmln. . kWhkWh

Prefeasibility study resultsPrefeasibility study results

Page 41: German-Russian seminar for nontraditional and renewable sources of energy. Berlin 12-13.11.08

Economical effectiveness indicators Value

Total investment, billion rub 2,470

NPV, billion rub 3,114

IRR, % 20,1

Discounted payback time, years 7,6

Project economical profile

(at tariffs - 1 1.5-.5-11..88 rub rub.. /kWh/kWh ))

Page 42: German-Russian seminar for nontraditional and renewable sources of energy. Berlin 12-13.11.08

Krasnopolyanskaya HPP-2 at Mzimta river, Sochi

Page 43: German-Russian seminar for nontraditional and renewable sources of energy. Berlin 12-13.11.08

Project descriptionProject description

Construction of HPP with installed capacity 30 MW at river Mzimta in Sochi

Aim of the project

• Guaranteed power supply of Winter Olympic Games complex;

Page 44: German-Russian seminar for nontraditional and renewable sources of energy. Berlin 12-13.11.08

Economical effectiveness indicators Value

Total investment, billion rub 2,771

NPV, billion rub 631

IRR, % 27,1

Discounted payback time, years 12,8

Project economical profile (at tariffs - 1 1.8-3.0rub.8-3.0rub.. /kWh/kWh ) )