7/24/2019 Geothermal Design - Ground Loop Design GLD2010 Software
1/50
GLD2010 -Loopfield & Piping Workshop Week 2 - Slide 1.1 - 1
22 2010 2010
: B: B
GLD2010 -Loopfield & Piping Workshop Week 2 - Slide 1.1 - 2
!! 2: 2:
The objective of this workshop is to provide the geothermal designer with an in-
depth look at designing practical and purgeable piping system designs
using the industry leading Ground Loop Design GLD2010 Software Suite.
You are encouraged to interact with your instructor. We are seeking to provide
the geothermal professional with the tools and familiarity that he/she needs
to optimize a wide range of GSHP systems.
By extending the user's mastery of the GLD program, it is possible to eliminate
the design and field guesswork that has often been used to connect
loopfields to the load systems. Designers will quickly discover that thedrudgery of hand calculations can be eliminated and replaced by a much
more accurate and practical tool that designs piping systems which can beeffectively purged and can be built with pipe sizes and types that are
appropriate to your operations.
7/24/2019 Geothermal Design - Ground Loop Design GLD2010 Software
2/50
GLD2010 -Loopfield & Piping Workshop Week 2 - Slide 1.1 - 3
A?
? ?
B
B : &
& : &
2010
GLD2010 -Loopfield & Piping Workshop Week 2 - Slide 1.1 - 4
What is the CFD Module?
The computational fluid dynamics (CFD) module enables designersto easily design, build, simulate and optimize the piping systems
that comprise the foundation of ground heat exchanger systems.
Why does one want to optimize a piping system?To ensure that the system can be purged and to ensure that the
system provides effective heat transfer with minimal circulationpump costs.
Cant I do this by hand?Not really. Modeling reverse return systems is very complex and
impossible to do with any accuracy by hand or even with aspreadsheet. Plus, it takes hours to make modifications and redo
calculations. With the CFD Module, it takes a few seconds.
7/24/2019 Geothermal Design - Ground Loop Design GLD2010 Software
3/50
GLD2010 -Loopfield & Piping Workshop Week 2 - Slide 1.1 - 5
What can the CFD Module model do?The CFD module can model piping systems that consist of a wide
possible range of connected components including :Manifolds/Vaults, Supply and Return Runouts, Supply and Return
Headers, single and double u-bends, the fittings that connect thesystems together and circulation pumps.
How does it do this?Utilizing a new, patent-pending visual interface for viewing and
creating a design via a drag and drop methodology, the CFDmodule can automatically design optimal flow-balanced (direct and
reverse return) systems while providing designers with the flexibilitythey need for standard and non-standard systems.
GLD2010 -Loopfield & Piping Workshop Week 2 - Slide 1.1 - 6
What results do I get out of the Module?Outputs include flow rates, fluid velocities, Reynold's numbers,
pressure drop, fluid volume and the like for every single point in adynamic geothermal piping system.
7/24/2019 Geothermal Design - Ground Loop Design GLD2010 Software
4/50
GLD2010 -Loopfield & Piping Workshop Week 2 - Slide 1.1 - 7
A A
A? A?
?
B
B : &
& : &
2010
GLD2010 -Loopfield & Piping Workshop Week 2 - Slide 1.1 - 8
A? A?
7/24/2019 Geothermal Design - Ground Loop Design GLD2010 Software
5/50
GLD2010 -Loopfield & Piping Workshop Week 2 - Slide 1.1 - 9
A? A?
GLD2010 - Loopfield & Piping Workshop Week 2 - Slide 1.1 -10
We want to design geothermal heat exchangers that are easily purged
and perform well.
We want a system that is easily purged so that we can get all the air
bubbles out and ensure stable performance.
We want a system that performs well so that the circulation pumps donot consume unnecessary energy.
/100
< 5
5 7
7 10
1015
> 15
A? A?
7/24/2019 Geothermal Design - Ground Loop Design GLD2010 Software
6/50
GLD2010 - Loopfield & Piping Workshop Week 2 - Slide 1.1 -11
A sample system:
22,000kWh cooling5,000 kWh heating
Well Designed piping system:12 x 2 borefield10 ft. hd @ 45gpm~ 0.5 hp pump with 85% efficiency = 3,504 kWhPump penalty = 11%
Poorly Designed System:12 x 2 borefield34 ft. hd @ 45 gpm
~ 1 hp pump with 85% efficiency = 7,884 kWhPump penalty = 22%
A? A?
GLD2010 - Loopfield & Piping Workshop Week 2 - Slide 1.1 -12
To achieve the goal of designing an easy-to-purge and high performance system we needto look at and understand these parameters in our designs:
FlowRate (gpm) Velocity(ft/s) Reynolds Numbers PressureDrop (ft. head)
A? A?
7/24/2019 Geothermal Design - Ground Loop Design GLD2010 Software
7/50
GLD2010 - Loopfield & Piping Workshop Week 2 - Slide 1.1 -13
?
B B
A?
B : &
& : &
2010
GLD2010 - Loopfield & Piping Workshop Week 2 - Slide 1.1 -14
We use the following equations:
1) Darcy-Weisbach (calculates pressure drop from friction factor, pipeparameters, fluid density and fluid velocity)
2) Reynolds Number (calculates Reynolds Number from density, velocity, pipeparameters and viscosity)
3) A range of equivalent resistance calculations for determining pressuredrops across network nodes.
4) The Hazen-Williams equation is not used (due to very limited applicability)
B B
7/24/2019 Geothermal Design - Ground Loop Design GLD2010 Software
8/50
GLD2010 - Loopfield & Piping Workshop Week 2 - Slide 1.1 -15
?
A?
B
B : &
& : &
2010
GLD2010 - Loopfield & Piping Workshop Week 2 - Slide 1.1 -16
: :
7/24/2019 Geothermal Design - Ground Loop Design GLD2010 Software
9/50
GLD2010 - Loopfield & Piping Workshop Week 2 - Slide 1.1 -17
: :
GLD2010 - Loopfield & Piping Workshop Week 2 - Slide 1.1 -18
: :
7/24/2019 Geothermal Design - Ground Loop Design GLD2010 Software
10/50
GLD2010 - Loopfield & Piping Workshop Week 2 - Slide 1.1 -19
: :
GLD2010 - Loopfield & Piping Workshop Week 2 - Slide 1.1 -20
?
A?
B
B : &
& : &
2010
7/24/2019 Geothermal Design - Ground Loop Design GLD2010 Software
11/50
GLD2010 - Loopfield & Piping Workshop Week 2 - Slide 1.1 -21
Standardized Nomenclature is critical to clear communication.
GLD2010 - Loopfield & Piping Workshop Week 2 - Slide 1.1 -22
U-Tube: An assembly of two lengths of HDPE pipe connected on one end with a molded, purpose built U-bend.
GHX: Refers to a ground heat exchanger, and may include vertical, horizontal trenching, horizontal boring,pond or lake heat exchanger buried in the ground or submerged in a body of water.
7/24/2019 Geothermal Design - Ground Loop Design GLD2010 Software
12/50
GLD2010 - Loopfield & Piping Workshop Week 2 - Slide 1.1 -23
GHX Circuits: HDPE pipe buried in the ground i n horizontal or vertical orientation designed to transfer energyto and from the ground. Typically a number of GHX Circuits are fusion welded to a GHX Header that is in turnfusion welded to a Supply-Return Runout. Heat transfer fluid is circulated through the assembly to a building.
GHX Header: Connection points between Supply-Return Runout piping and GHX Circuits. GHX Headers areburied in the ground adjacent to the GHX Field and are comprised of an assembly of fusion welded fittingsand pipe. Fittings and pipe are manufactured using HDPE resin and are connected using heat fusion (butt
fusion, socket fusion or electro-fusion). Most GHX Headers are Reducing Headers
GLD2010 - Loopfield & Piping Workshop Week 2 - Slide 1.1 -24
GHX Module Supply-Return Runout : Supply-Return Runout refers to the high-density polyethylene (HDPE)piping installed to connect the GHX Circuit piping to the Pump House header. The Supply-Return Runout has
both a supply pipe and a return pipe.
7/24/2019 Geothermal Design - Ground Loop Design GLD2010 Software
13/50
GLD2010 - Loopfield & Piping Workshop Week 2 - Slide 1.1 -25
GHX Module: Completed assembly of GHX components, i ncluding GHX Supply and Return Runouts, GHXheader and GHX Circuits.
GLD2010 - Loopfield & Piping Workshop Week 2 - Slide 1.1 -26
GHX Field: Assembly of all GHX Modules connected to a single building or group of buildings via GHXManifold(s)/Vault(s).
7/24/2019 Geothermal Design - Ground Loop Design GLD2010 Software
14/50
GLD2010 - Loopfield & Piping Workshop Week 2 - Slide 1.1 -27
B B
?
B : & B : &
A?
B
& : &
2010
GLD2010 - Loopfield & Piping Workshop Week 2 - Slide 1.1 -28
B : () B : ()
Note: Direct Return (DR) systems uncommon but useful for illustrative purposes
7/24/2019 Geothermal Design - Ground Loop Design GLD2010 Software
15/50
GLD2010 - Loopfield & Piping Workshop Week 2 - Slide 1.1 -29
B : () B : ()
GLD2010 - Loopfield & Piping Workshop Week 2 - Slide 1.1 -30
B : () B : ()
7/24/2019 Geothermal Design - Ground Loop Design GLD2010 Software
16/50
GLD2010 - Loopfield & Piping Workshop Week 2 - Slide 1.1 -31
B : () B : ()
GLD2010 - Loopfield & Piping Workshop Week 2 - Slide 1.1 -32
B : () B : ()
7/24/2019 Geothermal Design - Ground Loop Design GLD2010 Software
17/50
GLD2010 - Loopfield & Piping Workshop Week 2 - Slide 1.1 -33
B : () B : ()
GLD2010 - Loopfield & Piping Workshop Week 2 - Slide 1.1 -34
B : () B : ()
This RR GHX Module is know as the horseshoe. It can offer lower pressure
drops compared to standard RR GHX Modules (i.e. 8.3 vs 10.3 ft head) . Doyou know why?
7/24/2019 Geothermal Design - Ground Loop Design GLD2010 Software
18/50
GLD2010 - Loopfield & Piping Workshop Week 2 - Slide 1.1 -35
BB : :
GLD2010 - Loopfield & Piping Workshop Week 2 - Slide 1.1 -36
BB : :
7/24/2019 Geothermal Design - Ground Loop Design GLD2010 Software
19/50
GLD2010 - Loopfield & Piping Workshop Week 2 - Slide 1.1 -37
& &
?
& : & & : &
A?
B
B : &
2010
GLD2010 - Loopfield & Piping Workshop Week 2 - Slide 1.1 -38
: :
You want to have a piping system that you can purge with available purge pumps.
A 2 ft/sec fluid velocity throughout entire system is required to purge air effectively.
Systems are purged with water and all calculations must be done with water.
7/24/2019 Geothermal Design - Ground Loop Design GLD2010 Software
20/50
GLD2010 - Loopfield & Piping Workshop Week 2 - Slide 1.1 -39
: : You want to have a piping system that you can purge with available purge pumps.
A 2 ft/sec fluid velocity throughout entire system is required to purge air effectively.
Systems are purged with water and all calculations must be done with water.
GLD2010 - Loopfield & Piping Workshop Week 2 - Slide 1.1 -40
: :
You want to have a piping system that you can purge with available purge pumps.
A 2 ft/sec fluid velocity throughout entire system is required to purge air effectively.
Systems are purged with water and all calculations must be done with water.
48.27 GPM and 18.4 ft. hd:
7/24/2019 Geothermal Design - Ground Loop Design GLD2010 Software
21/50
GLD2010 - Loopfield & Piping Workshop Week 2 - Slide 1.1 -41
: : 48.27 GPM and 18.4 ft. hd:
Clearly, we need a higher flow rate to purge the GHX Header Sections on this GHX Module.
GLD2010 - Loopfield & Piping Workshop Week 2 - Slide 1.1 -42
: :
Based on this configuration, to achieve 2 ft/s flow rates across the headering system requires:
158 GPM and 331 ft. hd
This clearly is unreasonable and justifies the use of a reducing headering system
7/24/2019 Geothermal Design - Ground Loop Design GLD2010 Software
22/50
GLD2010 - Loopfield & Piping Workshop Week 2 - Slide 1.1 -43
: : Reducing headering systems will enable purging velocities throughout a system while maintainingreasonable flow rates and pressure drops.
GLD2010 - Loopfield & Piping Workshop Week 2 - Slide 1.1 -44
: :
Reducing headering systems enable purging velocities throughout a system while maintaining reasonable
flow rates and pressure drops.
51.75 GPM and 46.7 ft. hd
7/24/2019 Geothermal Design - Ground Loop Design GLD2010 Software
23/50
GLD2010 - Loopfield & Piping Workshop Week 2 - Slide 1.1 -45
: : Other Reducing Header Options:
(/)
1
(/)
2
(/)
2/2 5.60 / 2/2 5.79 / 2/2 8.63
1 2/2 4.79 / 2/2 4.96 / 2/2 7.41
2 2/2 4.03 / 2/2 4.18 / 2/2 6.25
3 2/2 3.30 / 2/2 3.43 / 2/2 5.14
4 2/2 2.60 / 2/2 2.71 / 2/2 4.07
5 1 /1 2.98 / 2/2 2.00 / 2/2 3.03
6 1 /1 2.55 / 1 /1 2.68 / 2/2 2.00
7 1/1 2.00 / 1/1 2.10 / 1/1 3.21
51.75 53.5 79.8
46.7 . 49.1 . 99 .
GLD2010 - Loopfield & Piping Workshop Week 2 - Slide 1.1 -46
: :
Flow Balance and Reynolds Numbers
Flow balance is very important to ensure that all of the GHX circuits transfer an equal # of BTUS to and fromthe ground. Unbalanced systems perform poorly.
This DR system has GHX Circuit flow rates that decrease from 3.88 gpm to 2.95 gpm, a nearly 21%
imbalance, across the entire GHX Module.
Note: Propylene Glycol with freeze protection down to 20F, 27 gpm, 17.5 ft hd.
7/24/2019 Geothermal Design - Ground Loop Design GLD2010 Software
24/50
GLD2010 - Loopfield & Piping Workshop Week 2 - Slide 1.1 -47
: : Balanced Flow and Reynolds Numbers
Reynolds indicate flow type (turbulent, laminar, etc). Turbulent flow is optimal for efficient heat transfer.
This direct return system has GHX circuit flow Reynolds numbers that drop as the distance from thesupply-return runout to GHX circuit increases. In this example, the Reynolds numbers drop from3,845 to 2,944: again, a ~20% drop.
What about compact headering systems?Do reverse return systems perform better?
GLD2010 - Loopfield & Piping Workshop Week 2 - Slide 1.1 -48
: :
You want to have a piping system that you can purge with available purge pumps.
A 2 ft/sec fluid velocity throughout entire system is required to purge air effectively.
Systems are purged with water and all calculations must be done with water.
7/24/2019 Geothermal Design - Ground Loop Design GLD2010 Software
25/50
GLD2010 - Loopfield & Piping Workshop Week 2 - Slide 1.1 -49
: : You want to have a piping system that you can purge with available purge pumps.
A 2 ft/sec fluid velocity throughout entire system is required to purge air effectively.
Systems are purged with water and all calculations must be done with water.
GLD2010 - Loopfield & Piping Workshop Week 2 - Slide 1.1 -50
: :
You want to have a piping system that you can purge with available purge pumps.
A 2 ft/sec fluid velocity throughout entire system is required to purge air effectively.
Systems are purged with water and all calculations must be done with water.
45.32 GPM and 6.6 ft. hd :
The GHX circuits are being purged but the headering is not.
7/24/2019 Geothermal Design - Ground Loop Design GLD2010 Software
26/50
GLD2010 - Loopfield & Piping Workshop Week 2 - Slide 1.1 -51
: : Based on this configuration, to achieve 2 ft/s flow rates across the headering system requires:
146 GPM and 345 ft. hd.
This clearly is unreasonable and justifies the use of a reducing headering system .
GLD2010 - Loopfield & Piping Workshop Week 2 - Slide 1.1 -52
: :
Reducing headering systems enable purging velocities throughout a system while maintainingreasonable flow rates and pressure drops.
7/24/2019 Geothermal Design - Ground Loop Design GLD2010 Software
27/50
GLD2010 - Loopfield & Piping Workshop Week 2 - Slide 1.1 -53
: : Reducing headering systems enable purging velocities throughout a system while maintainingreasonable flow rates and pressure drops.
46.7 GPM and 46.2 ft. hd.
GLD2010 - Loopfield & Piping Workshop Week 2 - Slide 1.1 -54
: :
Other Reducing Header Options:
(/)
1
(/)
2
(/)
2/2 5.05 /5.05 2/2 2.34/2.34 2/2 2.69/2.69
1 2/1 4.44/2.00 2/1 2.06/2.00 2/1 2.37/2.29
2 2/1 3.81/2.54 2/1 3.84/2.56 2/2 2.03/2.93
3 2/1 3.17/2.94 2/2 3.20/2.96 2/2 3.67/2.18
4 2/2 2.53/2.53 2/2 2.55/2.55 2/2 2.92/2.92
5 1 /2 2.94/3.17 2/2 2.96/3.20 2/2 2.18/3.67
6 1 /2 2.54/3.81 1 /2 2.56/3.84 2/2 2.93/2.037 1/2 2.00/4.44 1/2 2.00/2.06 1/2 2.29/2.37
46.7 49.5 71.9
37.6 . . 42.5 . 84 . .
7/24/2019 Geothermal Design - Ground Loop Design GLD2010 Software
28/50
GLD2010 - Loopfield & Piping Workshop Week 2 - Slide 1.1 -55
: : Flow Balance and Reynolds Numbers
Flow balance is important to ensure that all of the GHX circuits exchange an equal # of BTUS with the
ground. Unbalanced systems perform poorly.
This RR system has GHX circuit fl ow rates that range from 3.31 gpm to 3.41 gpm, a less than 5% imbalanceacross the entire GHX Module. Note: Propylene Glycol with freeze protection down to 20F, 27 gpm, 20.2 ft hd.
GLD2010 - Loopfield & Piping Workshop Week 2 - Slide 1.1 -56
: :
Balanced Flow and Reynolds Numbers
Reynolds indicate flow type (turbulent, laminar, etc). Turbulent flow is optimal for efficient heat transfer.
This RR system has GHX circuit fl ow Reynolds Numbers drop from 3,404 to 3,305, a 5% drop.
7/24/2019 Geothermal Design - Ground Loop Design GLD2010 Software
29/50
GLD2010 - Loopfield & Piping Workshop Week 2 - Slide 1.1 -57
: : Design:
Direct Return Systems are mirror images on the supply and return lines
Reverse Return Systems are palindromes on the supply and return lines
Performance:
Reverse return systems provide more balanced flow, more balanced heat transfer and are thereforesuperior. For this reason they are considered to be the gold standard design methodology.
GLD2010 - Loopfield & Piping Workshop Week 2 - Slide 1.1 -58
: :
7/24/2019 Geothermal Design - Ground Loop Design GLD2010 Software
30/50
GLD2010 - Loopfield & Piping Workshop Week 2 - Slide 1.1 -59
?
A?
B
B : &
& : &
2010
GLD2010 - Loopfield & Piping Workshop Week 2 - Slide 1.1 -60
1) GHX Circuit Lengths
2) Number of Circuits in a GHX Module
3) Pressure Drop Maximums4) Supply Return Pipe Size Selection
7/24/2019 Geothermal Design - Ground Loop Design GLD2010 Software
31/50
GLD2010 - Loopfield & Piping Workshop Week 2 - Slide 1.1 -61
: : GHX Circuit Length and Pipe Si ze Selection: Pressure Drop Considerations
Conclusion: Choose the right pipe size for the circuit length
3/4 500 14.6
1 500 4.8
1 1/4 500 1.4
1 1/2 500 0.6
3/4 500 15.1
1 500 5.0
1 1/4 500 1.8
1 1/2 500 1.0
GLD2010 - Loopfield & Piping Workshop Week 2 - Slide 1.1 -62
: :
GHX Circuit Length and Pipe Size Selection
General Guideline:
200
250
300 1
350 11
400 1
500 + 1
7/24/2019 Geothermal Design - Ground Loop Design GLD2010 Software
32/50
GLD2010 - Loopfield & Piping Workshop Week 2 - Slide 1.1 -63
(B) : (B) : GHX Circuit Length: Circuits of Different Length in a Single DR GHX Module
Conclusion: DR Module imbalance exacerbated by 7%. Therefore dont do it unless
GLD2010 - Loopfield & Piping Workshop Week 2 - Slide 1.1 -64
(B) : (B) :
GHX Circuit Length: Circuits of Different Length in a Single DR GHX Module
Partially mitigate problem by having two GHX circuits in series (two bores per circuit for example)
7/24/2019 Geothermal Design - Ground Loop Design GLD2010 Software
33/50
GLD2010 - Loopfield & Piping Workshop Week 2 - Slide 1.1 -65
(B) : (B) : GHX Circuit Length: Circuits of Different Length in a Single DR GHX Module
Partially mitigate problem by having two GHX circuits in series (two bores per circuit for example)
GLD2010 - Loopfield & Piping Workshop Week 2 - Slide 1.1 -66
(B) : (B) :
Reducing Circuit Designs: An interesting experiment
Circuits of different and reducing depths in a single DR module can lead to more balanced flow
7/24/2019 Geothermal Design - Ground Loop Design GLD2010 Software
34/50
GLD2010 - Loopfield & Piping Workshop Week 2 - Slide 1.1 -67
(B) : (B) : GHX Circuit Length: Circuits of Different Length in a Single RR GHX Module
Conclusion: RR Systems are integrated systems that are systemically very sensitive to changes.Therefore, all GHX circuits should be the same length.
GLD2010 - Loopfield & Piping Workshop Week 2 - Slide 1.1 -68
: :
The number of GHX Circuits on a GHX Module: Flow Balancing Considerations
8 GHX circuits per GHX module: 15-25% imbalance 20 GHX circuits per GHX module: 40-60% imbalance
24 GHX circuits per GHX module: 50-80% imbalanceConclusion: Dont use a large number of GHX Circuits on a DR GHX Module
7/24/2019 Geothermal Design - Ground Loop Design GLD2010 Software
35/50
GLD2010 - Loopfield & Piping Workshop Week 2 - Slide 1.1 -69
: : The number of GHX Circuits on a GHX Module: Flow Balancing Consideration
80 gpm
Conclusion: RR systems of all sizes are inherently balanced GHX modules. The maximum number of GHXcircuits normally will be determined by supply-return runout size limits and pressure drop concerns for
purging and operations.
GLD2010 - Loopfield & Piping Workshop Week 2 - Slide 1.1 -70
: :
If pressure drop in a GHX Module is greater than around 30 ft. hd under normal operation, the designer should:
A) Reduce the number of GHX circuits in the GHX Module
B) Increase the pipe size for the supply/return runoutC) Consider using a geothermal vault to reduce the length of the Supply-Return Runout
D) Increase the GHX circuit pipe diameter
Lets explore these designsoptions via this example:
7/24/2019 Geothermal Design - Ground Loop Design GLD2010 Software
36/50
GLD2010 - Loopfield & Piping Workshop Week 2 - Slide 1.1 -71
: : Reduce the number of GHX circuits in the GHX Module:
First look at 16 GHX Circuits per GHX Module (Propylene Glycol, 20F freeze protection)Pressure drop is 56 ft. hd = too high
Reduce the number of circuits to 11 per GHX module
GLD2010 - Loopfield & Piping Workshop Week 2 - Slide 1.1 -72
: :
Reduce the number of GHX circuits in the GHX Module:
With 11GHX Circuits per GHX Module (Propylene Glycol, 20F freeze protection)Pressure drop is 30.7 ft. hd = ok
Aim for 28 GHX Modules with 11 GHX Circuits and 1 GHX Module with 12 GHX Circuits for 320 Circuits
7/24/2019 Geothermal Design - Ground Loop Design GLD2010 Software
37/50
GLD2010 - Loopfield & Piping Workshop Week 2 - Slide 1.1 -73
: : If pressure drop in a GHX Module is greater than around 30 ft. hd under normal operation, the designer should:
A) Reduce the number of GHX circuits in the GHX ModuleB) Increase the pipe size for the supply/return runout
C) Consider using a geothermal vault to reduce the length of the Supply-Return RunoutD) Increase the GHX circuit pipe diameter
Lets explore these designsoptions via this example:
GLD2010 - Loopfield & Piping Workshop Week 2 - Slide 1.1 -74
: :
Increase the pipe size for the supply return runout
First look at 16 GHX Circuits per GHX Module with 2 Supply-Return Runouts
Pressure drop is 56 ft. hd = too high
7/24/2019 Geothermal Design - Ground Loop Design GLD2010 Software
38/50
GLD2010 - Loopfield & Piping Workshop Week 2 - Slide 1.1 -75
: : Increase the pipe size of the supply return runout to 3
With 16GHX Circuits per GHX Module with 3 runouts: Pressure drop is 15.8 ft. hd = ok
Aim for 20 GHX Modules with 16 GHX Circuits for a total of 320 Circuits
GLD2010 - Loopfield & Piping Workshop Week 2 - Slide 1.1 -76
: :
If pressure drop in a GHX Module is greater than around 30 ft. hd under normal operation, the designer should:
A) Reduce the number of GHX circuits in the GHX Module
B) Increase the pipe size for the supply/return runoutC) Consider using a geothermal vault to reduce the length of the Supply-Return Runout
D) Increase the GHX circuit pipe diameter
Lets explore these designsoptions via this example:
7/24/2019 Geothermal Design - Ground Loop Design GLD2010 Software
39/50
GLD2010 - Loopfield & Piping Workshop Week 2 - Slide 1.1 -77
: : Assume the GHX Modules are 700ft/1000ft from the building
First look at 16 GHX Circuits per GHX Module with 3 RunoutsPressure drop is 35.2 ft. hd = high
Consider using a vault because going up to 4 Supply Return runouts can be difficult
GLD2010 - Loopfield & Piping Workshop Week 2 - Slide 1.1 -78
: :
Use a vault that connects to a building via 500 ft 4 pipe
With 16GHX Circuits per GHX Module with 3 runouts
Pressure drop is 20.3 ft. hd = ok
Aim for 20 16 Circuit GHX Modules coming off of the vault
7/24/2019 Geothermal Design - Ground Loop Design GLD2010 Software
40/50
GLD2010 - Loopfield & Piping Workshop Week 2 - Slide 1.1 -79
: : Use a vault that connects to a building via 500 ft 4 pipe
GLD2010 - Loopfield & Piping Workshop Week 2 - Slide 1.1 -80
: :
If pressure drop in a GHX Module is greater than around 30 ft. hd under normal operation, the designer should:
A) Reduce the number of GHX circuits in the GHX Module
B) Increase the pipe size for the supply/return runoutC) Consider using a geothermal vault to reduce the length of the Supply-Return Runout
D) Increase the GHX circuit pipe diameter
Lets explore these designsoptions via this example:
7/24/2019 Geothermal Design - Ground Loop Design GLD2010 Software
41/50
GLD2010 - Loopfield & Piping Workshop Week 2 - Slide 1.1 -81
: : Increase the GHX circuit pipe diameter
GLD2010 - Loopfield & Piping Workshop Week 2 - Slide 1.1 -82
: :
In summary, if the pressure drop in a GHX Module is greater than around 30 ft. hd under normaloperation, the design should:
A)Reduce the number of GHX circuits in the GHX Module
B)Increase the pipe size for the supply/return runout
C)Consider using a geothermal vault to reduce the length of the Supply-Return Runout
D)Consider increasing the GHX circuit pipe diameter
7/24/2019 Geothermal Design - Ground Loop Design GLD2010 Software
42/50
GLD2010 - Loopfield & Piping Workshop Week 2 - Slide 1.1 -83
: : Supply Return Runout Pipe Size Selection: Head Loss and Flow Rates
Remember to not spec anything greater than 4 on the supply/return pipe size because anything biggeris very difficult to install in the field. Even 4 are hard to handle and require butt fusion.
Selection of a Supply Return Runout pipe size is based on:
The number of GHX circuits on the headering system: more GHX circuits = larger diameter runoutsPurging flow rate and pressure drop goals (remember you need to optimize for purging first! )The performance of the loopfield (flow rates, velocities, circulation pump costs, etc)
GLD2010 - Loopfield & Piping Workshop Week 2 - Slide 1.1 -84
: :
Two Inch vs Three Inch Supply Return Runouts
200 ft Supply/Return runouts14 GHX Circuits
50 ft Supply/Return runouts14 GHX Circuits
Conclusion: Larger diameter pipe = smaller purge pumps and lower cost performance
2 / 3 /
31.3 . 10.3 .
13.1 . . 4.2 .
# 5,700 5,700
2 / 3 /
13.3 . 9.4 .
5.9 . . 3.9 .
# 5,800 5,900
7/24/2019 Geothermal Design - Ground Loop Design GLD2010 Software
43/50
GLD2010 - Loopfield & Piping Workshop Week 2 - Slide 1.1 -85
: :
GLD2010 - Loopfield & Piping Workshop Week 2 - Slide 1.1 -86
: :
2 / 3 /
0.75 814 1420
1.00 610 1015
1.25 46 610
7/24/2019 Geothermal Design - Ground Loop Design GLD2010 Software
44/50
GLD2010 - Loopfield & Piping Workshop Week 2 - Slide 1.1 -87
2010 2010
?
2010 2010
A?
B
B : &
& : &
GLD2010 - Loopfield & Piping Workshop Week 2 - Slide 1.1 -88
Basics:
Two Key Components: the GHX Circuit and the Pipe Pair
7/24/2019 Geothermal Design - Ground Loop Design GLD2010 Software
45/50
GLD2010 - Loopfield & Piping Workshop Week 2 - Slide 1.1 -89
The GHX CircuitThe GHX Circuit
An individual GHX Circuit consists of the following fivesubcomponents:
Af - Fitting for attachment to parent header pipe (optional)A - Supply side pipeAfu - End fitting that connects Pipe A and Pipe A' (optional)A' - Return side pipe (usually length A = length A')A'f - Fitting for attachment to child header pipe (optional)
Definable features for each subcomponent: Fitting type (socket tee branch, butt tee branch, etc.) Fitting pipe size Fitting equivalent length Fitting name Fitting volume Pipe size, type, inner & outer diameter Pipe length, Extra pipe length Pipe name, volume
GLD2010 - Loopfield & Piping Workshop Week 2 - Slide 1.1 -90
The Pipe PairThe Pipe Pair
An individual Pipe Pair consists of the following four subcomponents:
Af - Supply side fitting (generally before the supply side pipe)A - Supply side pipeA' - Return side pipeA'f - Return side fitting (generally after the return side pipe)
Definable features for each subcomponent: Fitting type (socket tee branch, butt tee branch, etc.) Fitting pipe size Fitting equivalent length Fitting name Fitting volume Pipe size, type, inner & outer diameter
Pipe length, Extra pipe length Pipe name, volume
7/24/2019 Geothermal Design - Ground Loop Design GLD2010 Software
46/50
GLD2010 - Loopfield & Piping Workshop Week 2 - Slide 1.1 -91
Snapping The Components Together to Form a System
GLD2010 - Loopfield & Piping Workshop Week 2 - Slide 1.1 -92
Manual Design Methods Automatic Design Methods Headering Design Adding Circulation Pumps System Performance Review
7/24/2019 Geothermal Design - Ground Loop Design GLD2010 Software
47/50
GLD2010 - Loopfield & Piping Workshop Week 2 - Slide 1.1 -93
2010 2010
?
A?
B
B : &
& : &
2010
GLD2010 - Loopfield & Piping Workshop Week 2 - Slide 1.1 -94
1:1:
1) Use the wizard to build a GHX Module
- Reverse Return
- 10 Circuits
- 15 ft Circuit Separation
- 325 ft one way Circuit Length
- 1 in SDR 11 Circuit Pipe Size
- 2 in SDR 11 Header Pipe Size
- 200 ft Supply-Return Runout Length
- 2 in SDR 11 Supply-Return Runout Pipe Size
7/24/2019 Geothermal Design - Ground Loop Design GLD2010 Software
48/50
GLD2010 - Loopfield & Piping Workshop Week 2 - Slide 1.1 -95
2:2:
Using the GHX Module that you built in the previous exercise:
1) Display the pipe size, pipe length and pipe type for the entire system
2) Switch to purge mode and then select the results you wish to see in purge mode
3) Auto Adjust the Purging Flow Rate so that 2 ft/s is achieved in the GHX circuits
4) Manually adjust the purging flow rate so that 2 ft/s is achieved in the entiresystem (including the headering pairs)
5) Auto Size the Headers so that 2 ft/s is achieved in the headering pairs whileminimizing flow rates
GLD2010 - Loopfield & Piping Workshop Week 2 - Slide 1.1 -96
3:3:
Using the GHX Module that you optimized in the previous exercise:
1) Determine the flow rate and head loss requirements for the purge pump(write this number down for later use!)
2) Switch to PEAK LOAD mode
3) Select the results you wish to see for operational simulations
4) Enter a Peak Load Flow Rate
5) Select propylene glycol with freeze protection to 20F
6) Determine the Reynolds numbers7) Determine the Head Loss for the GHX Module under operational conditions
(write this number down for later use!)
7/24/2019 Geothermal Design - Ground Loop Design GLD2010 Software
49/50
GLD2010 - Loopfield & Piping Workshop Week 2 - Slide 1.1 -97
4:4:
1) Use the wizard to build a GHX Module
- Reverse Return
- 10 Circuits
- 15 ft Circuit Separation
- 325 ft one way Circuit Length
- 1 in SDR 11 Circuit Pipe Size
- 3 in SDR 11 Header Pipe Size
- 200 ft Supply-Return Runout Length
- 3 in SDR 11 Supply-Return Runout Pipe Size
GLD2010 - Loopfield & Piping Workshop Week 2 - Slide 1.1 -98
5:5:
Using the GHX Module that you built in the previous exercise:
1) Display the pipe size, pipe length and pipe type for the entire system
2) Switch to purge mode and then select the results you wish to see in purge mode
3) Auto Adjust the Purging Flow Rate so that 2 ft/s is achieved in the GHX circuits
4) Manually adjust the purging flow rate so that 2 ft/s is achieved in the entire
system (including the headering pairs)
5) Auto Size the Headers so that 2 ft/s is achieved in the headering pairs whileminimizing flow rates
7/24/2019 Geothermal Design - Ground Loop Design GLD2010 Software
50/50
GLD2010 - Loopfield & Piping Workshop Week 2 - Slide 1.1 -99
6:6:
Using the GHX Module that you optimized in the previous exercise:
1) Determine the flow rate and head loss requirements for the purge pump(compare this result from the system you designed before with 2 in headers)
2) Switch to PEAK LOAD mode
3) Select the results you wish to see for operational simulations
4) Enter a Peak Load Flow Rate
5) Select propylene glycol with freeze protection to 20F
6) Determine the Reynolds numbers
7) Determine the Head Loss for the GHX Module under operational conditions
(compare this result from the system you designed before with 2 in headers)
Q & AQ & A
Thank you for using GLD Software and for learning how to use it correctly! Pleasetry to use some of what you have learned prior to the next session
, :
..
! !