33
www.consultjtc.com GEOTECHNICAL INVESTIGATION REPORT PROPOSED COMMUNICATIONS TOWER Beech Hill Road Durham, New Hampshire 03824 Prepared for: Town of Durham 8 Newmarket Road Durham, New Hampshire 03824 Prepared by: John Turner Consulting, Inc. 19 Dover Street Dover, New Hampshire 03820 JTC Project No. 18-15-089 November 19, 2018 ____________________ Rachel Cannon Senior Project Manager 19 Dover Street Dover, NH 03820 [email protected] Ph: (603) 799-1868 Thomas A. McIntosh III, PE Senior Geotechnical Engineer 19 Dover Street Dover, NH 03820 [email protected] Ph: (508) 446-6180 Judson Zachar, PE Director of Geotechnical Engineering 19 Dover Street Dover, NH 03820 [email protected] Ph: (508) 320-4668

GEOTECHNICAL INVESTIGATION REPORT · 2020-02-04 · Geotechnical Investigation Report Page . 5. of . 12. . Geotechnical laboratory testing was performed in general accordance with

  • Upload
    others

  • View
    15

  • Download
    0

Embed Size (px)

Citation preview

Page 1: GEOTECHNICAL INVESTIGATION REPORT · 2020-02-04 · Geotechnical Investigation Report Page . 5. of . 12. . Geotechnical laboratory testing was performed in general accordance with

www.consultjtc.com

GEOTECHNICAL INVESTIGATION REPORT

PROPOSED COMMUNICATIONS TOWER Beech Hill Road

Durham, New Hampshire 03824

Prepared for:

Town of Durham 8 Newmarket Road

Durham, New Hampshire 03824

Prepared by:

John Turner Consulting, Inc. 19 Dover Street

Dover, New Hampshire 03820

JTC Project No. 18-15-089

November 19, 2018

____________________ Rachel Cannon Senior Project Manager 19 Dover Street Dover, NH 03820 [email protected] Ph: (603) 799-1868

Thomas A. McIntosh III, PE Senior Geotechnical Engineer 19 Dover Street Dover, NH 03820 [email protected] Ph: (508) 446-6180

Judson Zachar, PE Director of Geotechnical Engineering 19 Dover Street Dover, NH 03820 [email protected] Ph: (508) 320-4668

Page 2: GEOTECHNICAL INVESTIGATION REPORT · 2020-02-04 · Geotechnical Investigation Report Page . 5. of . 12. . Geotechnical laboratory testing was performed in general accordance with

www.consultjtc.com

November 19, 2018 Town of Durham 8 Newmarket Road Durham, New Hampshire 03824 Attn: April Talon

RE: Geotechnical Investigation Report Proposed Communications Tower Beech Hill Road Durham, New Hampshire

Dear Ms. Talon:

In accordance with our proposal and your authorization to proceed, John Turner Consulting, Inc. (JTC) has performed a geotechnical investigation for the above captioned project. Presented herein and attached are the results of the site subsurface investigation, and our recommendations regarding the design and construction of the foundation, and other geotechnical related concerns or issues.

We appreciate the opportunity to assist you on this venture and we look forward to working with you on this project through its completion. Please do not hesitate to contact us if you have any questions or require additional information.

Sincerely, JOHN TURNER CONSULTING, INC.

Rachel Cannon Senior Project Manager 19 Dover Street Dover, NH 03820 [email protected] Ph: (603) 799-1868

Page 3: GEOTECHNICAL INVESTIGATION REPORT · 2020-02-04 · Geotechnical Investigation Report Page . 5. of . 12. . Geotechnical laboratory testing was performed in general accordance with

Proposed Communication Tower Beech Hill Road, Durham, New Hampshire

Geotechnical Investigation Report Page 2 of 12

www.consultjtc.com

Table of Contents

1.0 INTRODUCTION ................................................................................................................................................ 3 2.0 PROJECT INFORMATION ................................................................................................................................... 3

2.1 Site Description ............................................................................................................................................ 3 2.2 Regional Geologic Setting ............................................................................................................................ 3 2.3 Proposed Development ............................................................................................................................... 4

3.0 GEOTECHNICAL EXPLORATIONS ....................................................................................................................... 4 4.0 GEOTECHNICAL LABORATORY TESTING ........................................................................................................... 4 5.0 SUBSURFACE CONDITIONS ............................................................................................................................... 5

5.1 Soils .............................................................................................................................................................. 5 5.1.1 Forest Mat & Subsoil................................................................................................................................ 5 5.1.2 Till ............................................................................................................................................................ 5

5.2 Bedrock ........................................................................................................................................................ 5 5.3 Groundwater ................................................................................................................................................ 5

6.0 GEOTECHNICAL ANALYSIS & RECOMMENDATIONS ......................................................................................... 6 6.1 Site Preparation and Grading ....................................................................................................................... 6 6.2 Communications Tower ............................................................................................................................... 7 6.3 Equipment Shelters and/or Tanks and Telecommunications Equipment .................................................... 8 6.4 General Foundation Preparation Requirements .......................................................................................... 9 6.5 Seismic Considerations .............................................................................................................................. 10 6.6 Wind Loading ............................................................................................................................................. 10 6.7 Re-Use of Site Soils ..................................................................................................................................... 10 6.8 Construction Monitoring and Quality Control Testing ............................................................................... 10 6.9 Additional Considerations .......................................................................................................................... 11

7.0 CLOSING .......................................................................................................................................................... 12 APPENDIX A: Limitations APPENDIX B: Recommended Soil Gradation & Compaction Specifications APPENDIX C: Site Plan & Test Boring Location Plan APPENDIX D: Test Boring Logs & Key to Symbols and Descriptions APPENDIX E: Geotechnical Laboratory Testing Results APPENDIX F: Site Photographs Page

Page 4: GEOTECHNICAL INVESTIGATION REPORT · 2020-02-04 · Geotechnical Investigation Report Page . 5. of . 12. . Geotechnical laboratory testing was performed in general accordance with

Proposed Communication Tower Beech Hill Road, Durham, New Hampshire

Geotechnical Investigation Report Page 3 of 12

www.consultjtc.com

1.0 INTRODUCTION

John Turner Consulting, Inc. (JTC) is pleased to present this Geotechnical Investigation Report for the proposed Communications Tower to be located at Beech Hill Road in Durham, New Hampshire. JTC conducted geotechnical explorations, laboratory testing, and engineering evaluations in general accordance with our proposed scope of services submitted to Durham Public Works on August 23, 2018.

The purpose of the geotechnical investigation was to obtain information on the subsurface conditions at the site and to provide geotechnical engineering recommendations to support the planning, design, and construction of the proposed development. Geotechnical explorations and laboratory testing services were performed in October of 2018.

This report summarizes available project information, presents the geotechnical exploration and laboratory testing programs, describes the subsurface conditions encountered, and provides geotechnical engineering recommendations to support the planning, design, and construction of the proposed Telecommunications Facility. The contents of this report are subject to the attached Limitations.

2.0 PROJECT INFORMATION

The following subsections provide general descriptions of the site, the regional geologic setting, and the proposed development.

2.1 Site Description

The site is located near the northwest corner of the Town of Durham near the an existing water storage tank approximately one half mile northwest of the end of pavement of Beech Hill Road. The subject property is accessible by a dirt access road from the end of Beech Hill Road. Presently, the site is at the apex of a steeply sloped and heavily-wooded terrain. The terrain descends dramatically to the south from approximately EL. 276 ft. to EL. 115 ft. towards Route 4 over a distance of approximately 1,400 feet. The Madbury town line and high tension, electric transmission lines are located approximately 200 feet to the north of the site. Refer to the attached existing site plan entitled, “Lot Line Revision and Water Line & Access Easement Plan” prepared by Doucet Survey of Newmarket, NH dated 08 December 2018 for further information.

2.2 Regional Geologic Setting

JTC’s review of the “Surficial geologic map of the Dover West quadrangle, Strafford County, New Hampshire” (Koteff, Carl, Goldsmith, Richard, and Gephart, G.D., 1989) indicates the site soils are likely to consist of non-sorted mixture ranging from clay-size particles to large boulders but dominantly silt to pebble sizes. Locally includes small irregular masses of sorted and stratified sand and gravel.

Page 5: GEOTECHNICAL INVESTIGATION REPORT · 2020-02-04 · Geotechnical Investigation Report Page . 5. of . 12. . Geotechnical laboratory testing was performed in general accordance with

Proposed Communication Tower Beech Hill Road, Durham, New Hampshire

Geotechnical Investigation Report Page 4 of 12

www.consultjtc.com

2.3 Proposed Development

JTC understands that the proposed development involves the construction of a 150 ft tall telecommunication tower and an equipment shelter. We understand that design details are still being developed, but that the intent is to support the tower and equipment shelter on conventional, cast-in-place, concrete spread footings which are anticipated to be 15 ft x 15 ft (225 s.f.) and 10 ft x 18 ft (180 s.f.) respectively. Site-specific structural loading was not available at the time of this report.

3.0 GEOTECHNICAL EXPLORATIONS

JTC subcontracted Soil Exploration Corp (SoilEx) to perform two (2) geotechnical test borings. designated as B-1 and B-2 via a tire-mounted CME-75 ATV drill rig. JTC directed the drilling, testing, and sampling activities and logged the subsurface conditions encountered at each boring location.

The exploration locations were selected in relation to the existing site features and proposed development, and under the constraints of drill rig access and utility conflicts. Subsequently, the relative location of each exploration was established via measurements from existing site features and scaling the dimensions onto the provided plan(s). The attached Test Boring Location Plan depicts the approximate exploration locations.

The test borings were advanced to depths of 32 feet below the ground surface (bgs) utilizing 4¼-inch inside-diameter continuous-flight hollow-stem-augers (HSAs). As the borings were advanced, standard penetration tests (SPTs) were conducted at regular intervals and soil samples were obtained via 2-inch outside-diameter split-spoon samplers driven by an automatic 140-pound hammer. SPTs were performed in general accordance with ASTM D1586, Standard Test Method for Penetration Test and Split-Barrel Sampling of Soils. The test borings were backfilled with soil cuttings upon completion of drilling. Soil samples were sealed in moisture-tight containers and returned to JTC’s office for further review, classification, and/or geotechnical laboratory testing. Detailed records of the drilling, testing, and sampling performed; and the soil, bedrock, and groundwater conditions observed at each test boring location are provided on the attached Test Boring Logs.

4.0 GEOTECHNICAL LABORATORY TESTING

JTC selected representative soil samples for geotechnical laboratory testing at our in-house laboratory. The following tests were performed:

• 4 Moisture contents; • 4 Particle-size analyses; • 1 Atterberg Limits

Page 6: GEOTECHNICAL INVESTIGATION REPORT · 2020-02-04 · Geotechnical Investigation Report Page . 5. of . 12. . Geotechnical laboratory testing was performed in general accordance with

Proposed Communication Tower Beech Hill Road, Durham, New Hampshire

Geotechnical Investigation Report Page 5 of 12

www.consultjtc.com

Geotechnical laboratory testing was performed in general accordance with ASTM procedures. Test results are provided on the attached Geotechnical Laboratory Testing Reports.

5.0 SUBSURFACE CONDITIONS

The following subsections describe the site soil, bedrock, and groundwater conditions encountered, based on results of the geotechnical explorations and laboratory testing. Detailed descriptions of the conditions observed at each test boring are provided on the attached Test Boring Logs.

5.1 Soils

The overburden soils encountered at the test boring locations appear to be consistent with those described by the published geologic data. The primary soil strata are briefly described in the paragraphs below.

5.1.1 Forest Mat & Subsoil

Forest Mat and Subsoil materials were encountered at the ground surface at both boring locations. The Forest Mat and Subsoil were generally described as loose, silty fine Sand (SM) with organics. The Forest Mat and Subsoil is approximately 2 feet thick.

5.1.2 Till

Native granular soils interpreted as Till were encountered beneath the Forest Mat & Suboil layers and consisted of olive brown, silty sand (SM), silty gravel with sand (GM), silty sand (SM), with gravel and poorly graded medium-coarse sand (SP). The till deposits were considered medium dense to very dense based on SPT N-Values ranging from 24 to 50 blows per foot.

5.2 Bedrock

Practical refusal to further penetration of the augers and/or split-spoon sampler was not encountered at the test boring locations. Bedrock is not expected to impact excavation based on the results of this investigation.

5.3 Groundwater

Groundwater and/or wet soils were not encountered at all test boring locations. Short-term (i.e., during drilling, upon completion of drilling, and/or a few hours after drilling) water levels observed in test borings performed in silty soils should be considered approximate.

JTC estimates that this investigation occurred during a period of seasonally normal to high ground water. Site groundwater levels should be expected to fluctuate seasonally and in response to precipitation events, construction activity, site use, and adjacent site use.

Page 7: GEOTECHNICAL INVESTIGATION REPORT · 2020-02-04 · Geotechnical Investigation Report Page . 5. of . 12. . Geotechnical laboratory testing was performed in general accordance with

Proposed Communication Tower Beech Hill Road, Durham, New Hampshire

Geotechnical Investigation Report Page 6 of 12

www.consultjtc.com

6.0 GEOTECHNICAL ANALYSIS & RECOMMENDATIONS

The evaluation of the site and the proposed development was based on the subsurface conditions encountered at the exploration locations, results of geotechnical laboratory testing, provided site plans/grading, and provided structural loading conditions, as described herein.

6.1 Site Preparation and Grading

Site preparation and grading should be performed in accordance with the following procedures:

• A geotechnical engineer should directly observe site preparation and grading activities; • The site soils contain substantial proportions of fine sand, silt, and/or clay, and may

degrade and/or become unworkable when subjected to construction traffic or other disturbance during wet conditions. As such, site preparations, grading, and earthworks should be performed during a dry season if possible. The Contractor shall be aware of these conditions and must take precautions to minimize subgrade disturbance. Such precautions may include diverting storm run-off away from construction areas, reducing traffic in sensitive areas, minimizing the extent of exposed subgrade if inclement weather is forecast, backfilling excavations and footings as soon as practicable, grading (and compacting) exposed subgrades to promote surface water run-off, and maintaining an effective dewatering program, as necessary. Over-excavation to remove degraded or unworkable subgrade soils should be anticipated and budgeted (cost and schedule);

• Any existing subsurface utilities and underground structures, including any private septic tank, leach field, and associated piping, should be completely removed from the footprint of the proposed building, and replaced/backfilled with properly placed and compacted Structural Fill. Any existing subsurface utilities in proposed pavement areas should be removed and/or appropriately abandoned in place (e.g., pressure grouting), as approved by the on-site geotechnical engineer;

• The site should be cleared and stripped of any existing trees/vegetation not designated to remain; Topsoil, Rootmat, Forest Mat; loamy/organic-laden Subsoil; and any otherwise unsuitable materials;

o The geotechnical explorations indicated a 2.0-foot thick layer of Forest Mat/Subsoil.

• Existing Fill and/or any otherwise unsuitable materials should be completely removed from the proposed building footprint, plus about 5 feet laterally;

o Additional Existing/Undocumented Fill materials should be expected proximate to any former building(s), foundations, and/or subsurface utilities.

• In cut areas, the final foot of excavation should be performed using a smooth-edged cutting bucket (no teeth) to minimize subgrade disturbance;

• Following clearing, stripping, removal of any Existing Fill/Undocumented Fill/unsuitable soil, and/or cutting to subgrade, the top 6 inches of exposed subgrade soils should be

Page 8: GEOTECHNICAL INVESTIGATION REPORT · 2020-02-04 · Geotechnical Investigation Report Page . 5. of . 12. . Geotechnical laboratory testing was performed in general accordance with

Proposed Communication Tower Beech Hill Road, Durham, New Hampshire

Geotechnical Investigation Report Page 7 of 12

www.consultjtc.com

scarified and then proof-rolled using a large smooth-drum roller with successive passes aligned perpendicularly. However, proof-rolling should not be performed if/when the exposed subgrade soils are wet (i.e., due to presence of groundwater, stormwater, perched water, etc.) because this may result in soil pumping and instability. Therefore, the proof-rolling efforts, including the number of passes and whether to employ static or vibratory methods, should be directed by the on-site geotechnical engineer (static methods should be anticipated based on the results of the test borings);

o Any loose, soft, wet, and/or otherwise unsuitable soils (typically evidenced by rutting, pumping, and/or deflection of the subgrade) should be over-excavated to expose suitable soils, or other remedial measures should be taken, as approved by the on-site geotechnical engineer;

o Any over-excavations should be backfilled with properly placed and compacted;

• Structural Fill should be used for subgrade fill within the equipment compound. The placement of Structural Fill materials to achieve design subgrades in the building pad should not begin until the exposed subgrade soils have been directly observed and approved by the on-site geotechnical engineer;

• Common Fill is acceptable for subgrade fill in parking and driveway areas. The placement of Common Fill materials to achieve design subgrades in pavement areas should not begin until the exposed subgrade soils have been directly observed and approved by the on-site geotechnical engineer; and

• Structural Fill and Common Fill materials and placement and compaction requirements are provided in the attached Tables.

6.2 Communications Tower

Based on the subsurface conditions encountered at the exploration locations and our current understanding relative to the proposed development, the monopole foundation can be designed and constructed as a single conventional spread footing. The designed capacity and reinforcement should be based on the Soil Properties table below.

Table 1: Soil Properties.

GLACIAL SAND DEPOSIT

Moist Unit Weight (γm) Saturated Unit Weight (γsat)

125pcf

63 pcf

Allowable Bearing Pressure 3 tsf

Friction Angle (ϕ) 34°

Page 9: GEOTECHNICAL INVESTIGATION REPORT · 2020-02-04 · Geotechnical Investigation Report Page . 5. of . 12. . Geotechnical laboratory testing was performed in general accordance with

Proposed Communication Tower Beech Hill Road, Durham, New Hampshire

Geotechnical Investigation Report Page 8 of 12

www.consultjtc.com

• Assuming the footing is in direct contact with the soil, lateral loading and overturning

moments can be resisted by the passive lateral earth pressures and sliding friction in the natural granular soils.

• Base lateral loads induced by wind loading can be resisted by passive earth pressures assumed to act on the full width and depth of the footing. The passive earth pressures can be computed based on a triangular distribution with an equivalent fluid pressure of 200 pounds per cubic foot which includes a safety factor of 1.5. All backfill around the footing must be placed in thin lifts and compacted to assure adequate passive resistance at the footing.

• For combined loading from dead loads and transient live loads such as seismic and wind loading, the maximum allowable contact pressure can be increased by one-third. Footing dimensions must be selected so that the resultant of the soil contact pressure falls within the middle-third, or kern distance, of the footing ensuring compressive stresses at the bottom of the footing under dead load and maximum wind load.

• The bottom of the footing must be placed a minimum of four feet below finished exterior grade in order to ensure adequate frost protection. At this depth, the footing will bear directly on the medium dense to very dense natural TILL strata. All loosened material should be removed, and if necessary, the subgrade should be lightly proof-compacted using a vibratory plate compactor.

• The Forest Mat/Subsoil materials are not suitable for load bearing. These materials should be completely removed from the footprint of the tower foundation, plus at least 5 feet laterally, as described in Section 6.1

• Global stability analysis is recommended on foundations located at slopes. All foundations shall be placed in accordance with IBC section 1808.7 Foundations on or Adjacent to Slopes. The lateral soil modulus parameter shall have appropriated reductions relative to the slope geometry and effective lateral resistance area.

• Foundation subgrade preparation shall be in accordance with section 6.4 below. The foundation must be inspected by a geotechnical engineer or representative as required by the applicable codes and assure compliance with the project specifications and the appropriated recommendations.

6.3 Equipment Shelters and/or Tanks and Telecommunications Equipment

Design recommendations for the cast-in-place concrete equipment pads are provided as follows:

Passive Earth Pressure (Kp)

Coefficient of Friction (sliding)

Equivalent Fluid Pressure

3.5

0.35 IBC

200 psf/ft IBC

Page 10: GEOTECHNICAL INVESTIGATION REPORT · 2020-02-04 · Geotechnical Investigation Report Page . 5. of . 12. . Geotechnical laboratory testing was performed in general accordance with

Proposed Communication Tower Beech Hill Road, Durham, New Hampshire

Geotechnical Investigation Report Page 9 of 12

www.consultjtc.com

• A modulus of vertical subgrade reaction, kvi, of 200 pounds per cubic inch (pci) should be available for structural design of equipment pads/floor slabs-on-grade, provided that the subgrade, Structural Fill, and the Clean Granular Fill are prepared as recommended in Subsections 6.1, 6.2, and 6.3;

• The cast-in-place, concrete equipment pad subbase should be underlain by a minimum 6-inch thick layer of Crushed Stone atop Mirafi 600X Geotech Fabric, or equivalent, to provide a capillary break and a stable working surface;

• In accordance with the New Hampshire State Building Code; all foundations must be placed a minimum of 4 ft below existing grade.

6.4 General Foundation Preparation Requirements

During construction, we expect that much of the development area will be excavated or disturbed during site preparation and grading (Subsection 6.1), excavations for foundations (Subsection 6.2), and/or excavations for new underground utilities. It is imperative that the subgrade beneath the concrete pad be reinstated with properly placed and compacted Structural Fill be prepared as recommended herein.

• Excavations for foundations must extend into undisturbed native Glacial Deposits and/or Structural Fill built-up from properly prepared native soils, as described herein;

o If Undocumented Fill, loose, soft, wet, frozen, or otherwise unsuitable soils/materials are encountered at the foundation subgrade, over-excavations should remove all Fill and/or unsuitable soils within the footing zone of influence, which is defined as then area extending laterally 1 foot from edges of the footing and then outward and downward at a 1H:1.5V (horizontal to vertical) splay of bearing until a suitable native subgrade soil is encountered; and

o Any over-excavations should be backfilled with properly placed and compacted Structural Fill as approved by the on-site geotechnical engineer.

• The exterior sides of equipment pads, footings, or piers should be backfilled with non-frost-susceptible fill in order to mitigate potential adverse effects of frost. Backfill for equipment pads, footings, or piers should consist of well-graded, free-draining, granular soil conforming to the requirements of Clean Granular Fill for equipment pads and Structural Fill for footings, as described in the attached Specifications.

• Backfill for equipment pads, footings and piers must be placed in uniform horizontal lifts having a maximum loose lift thickness of 8 inches and compacted to 95 percent of its modified proctor maximum dry density (MPMDD; per ASTM D1557). Thinner lifts may be required in order to achieve the required compaction criteria;

• The subgrade should be level and free of standing water and debris. If shallow and/or perched groundwater is encountered, it must be removed in advance of excavation and continuously maintained at least 2 feet below the bottom of excavation and subsequent construction grade until the backfilling is complete;

Page 11: GEOTECHNICAL INVESTIGATION REPORT · 2020-02-04 · Geotechnical Investigation Report Page . 5. of . 12. . Geotechnical laboratory testing was performed in general accordance with

Proposed Communication Tower Beech Hill Road, Durham, New Hampshire

Geotechnical Investigation Report Page 10 of 12

www.consultjtc.com

• A geotechnical engineer licensed by the State of New Hampshire or his representative should directly observe the foundation subgrade preparation activities and the subgrade soils prior to the placement foundation materials.

6.5 Seismic Considerations

Earthquake loadings must be considered under the requirements of the current edition of the New Hampshire Building Code (NH-Code) which refers to the 2009 edition of the International Building Code (IBC). IBC Table 1613.5.2 is used to establish the site class based on the average soil properties and soil profile. Site class is then used to determine the site coefficient and mapped spectral response for a given structure. Based on the conditions encountered at the test boring locations, the site is classified as:

Site Class D: Stiff Soil Profile.

Liquefaction refers to the loss of strength in saturated cohesionless soils due to the buildup of pore water pressures during cyclic or seismic loading. Based on the conditions encountered at the test boring locations, the site is NOT considered to be susceptible to liquefaction.

6.6 Wind Loading

The terrain and relatively open site indicate an Exposure C condition. Reference pressures for determining wind loading should be based either on Section 1609 Table 1604.11 of The International Building Code or the provisions contained in TIA/EIA 222-G-09 Structural Standard for Antenna Supporting Structures and Antennas, whichever is higher.

6.7 Re-Use of Site Soils

The Forest Mat, Subsoil, & Till materials encountered at the exploration locations are not suitable for re-use as Structural Fill, Clean Granular Fill, or Common Fill. These soils may be re-used in areas to be landscaped, subject to conformance with the project specifications.

6.8 Construction Monitoring and Quality Control Testing

A qualified engineer or representative should be retained to review the site and subgrade operations, as required by the New Hampshire State Building Code (NH-Code). Similarly, quality control testing, including in-place field density and moisture tests, should be performed to confirm that the specified compaction is achieved. It is recommended that JTC be retained to provide earthwork construction monitoring and quality control testing services.

Quality control testing recommendations are provided as follows:

• During site grading and foundation subgrade preparation, 3 field density tests should be performed for every 5,000 square feet (per lift) of Structural Fill placement, at a minimum.

Page 12: GEOTECHNICAL INVESTIGATION REPORT · 2020-02-04 · Geotechnical Investigation Report Page . 5. of . 12. . Geotechnical laboratory testing was performed in general accordance with

Proposed Communication Tower Beech Hill Road, Durham, New Hampshire

Geotechnical Investigation Report Page 11 of 12

www.consultjtc.com

At least 3 tests should be performed on each lift of material even if the lift is less than 5,000 square feet;

• During backfilling of utility trenches, at least 1 test should be conducted on Structural Fill per 50 linear feet (per lift) of trench; and

• During site grading and pavement subgrade preparation, 3 field density tests should be performed for every 5,000 square feet (per lift) of Common Fill, at a minimum. At least 3 tests should be performed on each lift even if the lift is less than 5,000 square feet.

6.9 Additional Considerations

Additional design recommendations are provided as follows:

• Exterior concrete sidewalks shall be underlain by at least 12 inches of Clean Granular Fill. The thickness of the Clean Granular Fill shall be increased to no less than 18 inches for exterior concrete slabs located adjacent to exterior doorways and ramps to provide additional frost protection at building entry/exit points;

• The exterior ground surface adjacent to the equipment compound should be sloped away from the building to provide for positive drainage. Similarly, the final surface materials adjacent to the building should be relatively impermeable to reduce the volume of precipitation infiltrating into the subsurface proximate to building foundations. Such impermeable materials include cement concrete, bituminous concrete, and/or vegetated silty/clayey topsoil; and

• Permanent fill or cut slopes should have a maximum slope of 2.5H:1V (horizontal to vertical) or flatter for dry conditions. Permanent fill or cut slopes should be no steeper than 3H:1V for wet/submerged conditions (e.g., stormwater basin) unless a properly designed surface slope stabilization system (e.g. rip rap, geosynthetics) is provided.

Additional construction considerations/recommendations are provided as follows:

• Safe temporary excavation and/or fill slopes are the responsibility of the Contractor. Excavations should be conducted in accordance with local, state, and federal (OSHA) requirements, at a minimum. If an excavation cannot be properly sloped or benched due to space limitations, adjacent structures, and/or seepage, the Contractor should install an engineered shoring system to support the temporary excavation;

• Subgrade conditions will be influenced by excavation methods, precipitation, stormwater management, groundwater control(s), and/or construction activities. Most of the site soils are poorly-drained, moisture-sensitive, and considered susceptible to disturbance when exposed to wet conditions and construction activities. As such, the Contractor shall be aware of these conditions and must take precautions to minimize subgrade disturbance. Such precautions may include diverting storm run-off away from construction areas, reducing traffic in sensitive areas, minimizing the extent of exposed subgrade if inclement weather is forecast, backfilling excavations and footings as soon as

Page 13: GEOTECHNICAL INVESTIGATION REPORT · 2020-02-04 · Geotechnical Investigation Report Page . 5. of . 12. . Geotechnical laboratory testing was performed in general accordance with

Proposed Communication Tower Beech Hill Road, Durham, New Hampshire

Geotechnical Investigation Report Page 12 of 12

www.consultjtc.com

practicable, and maintaining an effective dewatering program, as necessary; • Proper groundwater control and stormwater management are necessary to maintain site

stability. Groundwater should be removed in advance and continuously maintained at least 2 feet below the working construction grade until earthworks and/or backfilling are complete;

• If groundwater seepage and/or wet soils due to shallow groundwater are observed, a ¾-inch minus crushed stone base should be placed atop the exposed subgrade soils. The stone should be immediately placed atop the undisturbed subgrade and then tamped with a plate compactor until exhibiting stable conditions. The stone shall be protected, as required, with a geotextile filter fabric such as Mirafi 600X or equal. The purpose of the stone base is to protect the wet subgrade, facilitate dewatering, and provide a dry/stable base upon which to progress construction; and

• All slopes should be protected from erosion during (and after) construction.

7.0 CLOSING

We trust the contents of this report are responsive to your needs at this time. Should you have any questions or require additional assistance, please do not hesitate to contact our office.

Page 14: GEOTECHNICAL INVESTIGATION REPORT · 2020-02-04 · Geotechnical Investigation Report Page . 5. of . 12. . Geotechnical laboratory testing was performed in general accordance with

www.consultjtc.com

APPENDIX A: LIMITATIONS

Explorations

1. The analyses and recommendations presented in this report are based in part upon the data obtained from widely-spaced subsurface explorations. Subsurface conditions between exploration locations may vary from those encountered at the exploration locations. The nature and extent of variations between explorations may not become evident until construction. If variations appear, it will be necessary to re-evaluate the recommendations of this report.

2. The generalized soil profile described in the text is intended to convey trends in subsurface conditions. The boundaries between strata are approximate and idealized and have been developed by interpretation of widely-spaced explorations and samples; actual strata transitions are probably more gradual. For specific information, refer to the individual test pit and/or boring logs.

3. Water level readings have been made in the test pits and/or test borings under conditions stated on the logs. These data have been reviewed and interpretations have been made in the text of this report. However, it must be noted that fluctuations in the level of the groundwater may occur due to variations in rainfall, temperature, and other factors differing from the time the measurements were made.

Review

4. It is recommended that John Turner Consulting, Inc. be given the opportunity to review final design drawings and specifications to evaluate the appropriate implementation of the geotechnical engineering recommendations provided herein.

5. In the event that any changes in the nature, design, or location of the proposed areas are planned, the conclusions and recommendations contained in this report shall not be considered valid unless the changes are reviewed, and conclusions of the report modified or verified in writing by John Turner Consulting, Inc.

Construction

6. It is recommended that John Turner Consulting, Inc. be retained to provide geotechnical engineering services during the installation phases of the work. This is to observe compliance with the design concepts, specifications, and recommendations and to allow design changes in the event that subsurface conditions differ from those anticipated prior to the start of construction.

Use of Report

7. This report has been prepared for the exclusive use of The Town of Durham for specific application to the project located at Beech Hill Road in Durham, New Hampshire. All considerations are based on the available information and is in accordance with generally accepted soil and foundation engineering practices. No other warranty, expressed or implied, is made.

8. This report has been prepared for this project by John Turner Consulting, Inc. This report was completed for preliminary design purposes and may be limited in its scope to complete an accurate bid. Contractors wishing a copy of the report may secure it with the understanding that its scope is limited to preliminary geotechnical design considerations.

Page 15: GEOTECHNICAL INVESTIGATION REPORT · 2020-02-04 · Geotechnical Investigation Report Page . 5. of . 12. . Geotechnical laboratory testing was performed in general accordance with

www.consultjtc.com

APPENDIX B: RECOMMENDED SOIL GRADATION & COMPACTION SPECIFICATIONS

TABLE 1: Structural Fill

SIEVE SIZE PERCENT PASSING BY WEIGHT

5-inch 100

¾-inch 60 - 100

No. 4 20 - 80

No. 200 0 - 10

NOTES: 1. For use as structural load support below foundations and within the building pad. Structural Fill placed beneath building

foundations should include the Footing Zone of Influence which is defined as that area extending laterally one foot from the edge of the footing then outward and downward at a 1:1.5 (H:V) splay.

2. ¾-inch crushed stone may be used in wet conditions. 3. Structural Fill should be free of construction and demolition debris, frozen soil, organic soil, peat, stumps, brush, trash,

and refuse; 4. Structural Fill should not be placed on soft, saturated, or frozen subgrade soils; 5. Structural Fill should be placed in lifts not exceeding 12 inches for heavy vibratory rollers and 8 inches for vibratory

plate compactors. 6. Place and compact within ± 3% of optimum moisture content. 7. Compact to at least 95% relative compaction per ASTM D1557. 8. The adequacy of the compaction efforts should be verified by field density testing.

Page 16: GEOTECHNICAL INVESTIGATION REPORT · 2020-02-04 · Geotechnical Investigation Report Page . 5. of . 12. . Geotechnical laboratory testing was performed in general accordance with

www.consultjtc.com

TABLE 2: Clean Granular Fill

Clean SIEVE SIZE PERCENT PASSING BY WEIGHT

3-inch 100

¾-inch 60 – 90

No. 4 20 – 70

No. 200 2 – 8

NOTES: 1. Should consist of crushed stone beneath the concrete pad, as approved by on-site geotechnical engineer. 2. For minimum 6-inch base below the cast-in-place concrete equipment pads. 3. For minimum 12-inch base for exterior concrete slabs exposed to frost. 4. For minimum 18-inch base at exterior ramps, aprons, and loading bays adjacent to entrances/exit ways. 5. For use as footing and foundation wall backfill. 6. For use as backfill behind unbalanced foundation/retaining walls. 7. Place in lifts not exceeding 12 inches for heavy vibratory rollers and 8 inches for vibratory plate compactors. 8. Place and compact within ± 3% of optimum moisture content. 9. Compact to at least 95% relative compaction per ASTM D1557. 10. Compact to at least 95% relative compaction per ASTM D1557 when placed as foundation wall backfill in conjunction

with a bond break. 11. The adequacy of the compaction efforts should be verified by field density testing.

TABLE 3: Common Fill

SIEVE SIZE PERCENT PASSING BY WEIGHT

6-inch 100

¾-inch 60 – 100

No. 4 20 – 85

No. 200 0 – 25 NOTES:

1. For use as common/subgrade fill in parking areas and roadway embankments. 2. For use as foundation wall backfill if used in conjunction with a bond break and sized/screened to 3-inch minus. 3. Place in lifts not exceeding 12 inches. 4. Maximum stone size should not exceed ½ the actual lift thickness. 5. Compact to at least 92% relative compaction per ASTM D1557 when placed as subgrade fill in parking areas or roadway

embankments. 6. Compact to at least 95% relative compaction per ASTM D1557 when placed as foundation wall backfill in conjunction

with a bond break. 7. The adequacy of the compaction efforts should be verified by field density testing.

Page 17: GEOTECHNICAL INVESTIGATION REPORT · 2020-02-04 · Geotechnical Investigation Report Page . 5. of . 12. . Geotechnical laboratory testing was performed in general accordance with

www.consultjtc.com

APPENDIX C: SITE PLAN & TEST BORING LOCATION PLAN

Page 18: GEOTECHNICAL INVESTIGATION REPORT · 2020-02-04 · Geotechnical Investigation Report Page . 5. of . 12. . Geotechnical laboratory testing was performed in general accordance with

LOT LINE REVISION &

WATER LINE & ACCESS

EASEMENT PLAN

FOR

TOWN OF DURHAM

OVER LAND OF

CUTTER BEECH HILL, LLC

TAX MAP 9, LOT 12

BEECH HILL ROAD

DURHAM, NEW HAMPSHIRE

BYDESCRIPTIONDATENO.

DRAWN BY:

CHECKED BY:

JOB NO.: SHEET

DRAWING NO.:

DATE:

OF

W.J.D.

5345

DECEMBER 8, 2017

5345A

1 1

P.J.S.

Serving Your Professional Surveying & Mapping Needs

102 Kent Place, Newmarket, NH 03857 (603) 659-6560

2 Commerce Drive (Suite 202) Bedford, NH 03110 (603) 614-4060

10 Storer Street (Riverview Suite) Kennebunk, ME (207) 502-7005

http://www.doucetsurvey.com

0

SCALE: 1 INCH = 60 FT.

60 12060

LOCATION MAP (n.t.s.)

LOCATION MAP (n.t.s.)

Page 19: GEOTECHNICAL INVESTIGATION REPORT · 2020-02-04 · Geotechnical Investigation Report Page . 5. of . 12. . Geotechnical laboratory testing was performed in general accordance with

Notes:

1. Test borings were performed on October 22 & 25, 2018 under the direction of JTC. 2. Test boring locations should be considered approximate. 3. Refer to the Test Boring Logs for the subsurface conditions encountered at each boring location. 4. Basemap source: December 8, 2017 “Lot Line Revision & Water Line & Access Easement Plan” prepared by

Doucet Survey Inc. 5. Not to scale.

Town of Durham

8 Market Road Durham, New Hampshire 03824

Beech Hill Communication Tower

Beech Hill Road Durham, New Hampshire

TEST BORING LOCATION PLAN

B-1

B-2

N

Page 20: GEOTECHNICAL INVESTIGATION REPORT · 2020-02-04 · Geotechnical Investigation Report Page . 5. of . 12. . Geotechnical laboratory testing was performed in general accordance with

www.consultjtc.com

APPENDIX D: TEST BORING LOGS & KEY TO SYMBOLS AND DESCRIPTIONS

Page 21: GEOTECHNICAL INVESTIGATION REPORT · 2020-02-04 · Geotechnical Investigation Report Page . 5. of . 12. . Geotechnical laboratory testing was performed in general accordance with

0

2.5

5

7.5

10

12.5

15

17.5

Dark brown, silty sand (SM); loose; moist: FOREST MAT- contains frequent organics

0.5Olive brown, silty fine to medium sand (SM); loose; moist:

SUBSOIL- contains occasional organics

2Olive brown, silty sand (SM); dense; moist: GLACIAL TILL

- contains mottles

- becomes medium dense

SS01

SS02

SS03

SS04

SS05

1232

4102522

2029109

4121210

8111422

39.6

49.1

PROJECT: Proposed Telecommunications Tower PROJECT NO.: 18-15-089

CLIENT: Town of Durham, New Hampshire

PROJECT LOCATION: Beech Hill Road, Durham, New Hampshire

LOCATION: See Test Boring Location Plan ELEVATION:

LOG OF BORINGNo. B-1

DRILLER: Soil Exploration Corp LOGGED BY: RC

DRILLING METHOD: 4.25" ID HSA DATE: 10/22&25/2018

DEPTH TO - WATER> INITIAL: NA AFTER 24 HOURS:

Test boring was backfilled with soil cuttings upon completion.

De

pth

(fe

et)

Description

Gra

ph

ic

Ele

vatio

n (

feet)

Sa

mp

leN

o.

Blo

wC

ou

nts

% <

#2

00 TEST RESULTS

10 20 30 40 50Penetration -

Water Content -

Plastic Limit Liquid Limit

Figure

Th

is i

nfo

rma

tio

n p

ert

ain

s o

nly

to

th

is b

ori

ng

an

d s

ho

uld

no

t b

e i

nte

rpre

ted

as

be

ing

in

dic

ati

ve

of

the

sit

e.

PAGE 1 of 2

Page 22: GEOTECHNICAL INVESTIGATION REPORT · 2020-02-04 · Geotechnical Investigation Report Page . 5. of . 12. . Geotechnical laboratory testing was performed in general accordance with

20

22.5

25

27.5

30

32.5

35

- becomes dense

- becomes very dense

Boring terminated at 32 ft.

SS06

SS07

SS08

11162025

13172443

18242650

43.6

PROJECT: Proposed Telecommunications Tower PROJECT NO.: 18-15-089

CLIENT: Town of Durham, New Hampshire

PROJECT LOCATION: Beech Hill Road, Durham, New Hampshire

LOCATION: See Test Boring Location Plan ELEVATION:

LOG OF BORINGNo. B-1

DRILLER: Soil Exploration Corp LOGGED BY: RC

DRILLING METHOD: 4.25" ID HSA DATE: 10/22&25/2018

DEPTH TO - WATER> INITIAL: NA AFTER 24 HOURS:

Test boring was backfilled with soil cuttings upon completion.

De

pth

(fe

et)

Description

Gra

ph

ic

Ele

vatio

n (

feet)

Sa

mp

leN

o.

Blo

wC

ou

nts

% <

#2

00 TEST RESULTS

10 20 30 40 50Penetration -

Water Content -

Plastic Limit Liquid Limit

Figure

Th

is i

nfo

rma

tio

n p

ert

ain

s o

nly

to

th

is b

ori

ng

an

d s

ho

uld

no

t b

e i

nte

rpre

ted

as

be

ing

in

dic

ati

ve

of

the

sit

e.

PAGE 2 of 2

Page 23: GEOTECHNICAL INVESTIGATION REPORT · 2020-02-04 · Geotechnical Investigation Report Page . 5. of . 12. . Geotechnical laboratory testing was performed in general accordance with

0

2.5

5

7.5

10

12.5

15

17.5

Dark brown, silty sand (SM); medium dense; moist: FORESTMAT

- contains frequent organics0.5

Olive brown, silty fine to medium sand (SM); medium dense;moist: SUBSOIL

- contains occasional organics2

Olive brown, silty sand (SM); medium dense; moist: GLACIALTILL

- contains mottles

- becomes dense

SS01

SS02

SS03

SS04

SS05

15586

12121616

12141010

15272119

14141839

45.9

PROJECT: Proposed Telecommunications Tower PROJECT NO.: 18-15-089

CLIENT: Town of Durham, New Hampshire

PROJECT LOCATION: Beech Hill Road, Durham, New Hampshire

LOCATION: See Test Boring Location Plan ELEVATION:

LOG OF BORINGNo. B-2

DRILLER: Soil Exploration Corp LOGGED BY: RC

DRILLING METHOD: 4.25" ID HSA DATE: 10/25/2018

DEPTH TO - WATER> INITIAL: NA AFTER 24 HOURS:

Test boring was backfilled with soil cuttings upon completion.

De

pth

(fe

et)

Description

Gra

ph

ic

Ele

vatio

n (

feet)

Sa

mp

leN

o.

Blo

wC

ou

nts

% <

#2

00 TEST RESULTS

10 20 30 40 50Penetration -

Water Content -

Plastic Limit Liquid Limit

Figure

Th

is i

nfo

rma

tio

n p

ert

ain

s o

nly

to

th

is b

ori

ng

an

d s

ho

uld

no

t b

e i

nte

rpre

ted

as

be

ing

in

dic

ati

ve

of

the

sit

e.

PAGE 1 of 2

Page 24: GEOTECHNICAL INVESTIGATION REPORT · 2020-02-04 · Geotechnical Investigation Report Page . 5. of . 12. . Geotechnical laboratory testing was performed in general accordance with

20

22.5

25

27.5

30

32.5

35

Boring terminated at 32 ft.

SS06

SS07

SS08

10132525

16192023

20232342

PROJECT: Proposed Telecommunications Tower PROJECT NO.: 18-15-089

CLIENT: Town of Durham, New Hampshire

PROJECT LOCATION: Beech Hill Road, Durham, New Hampshire

LOCATION: See Test Boring Location Plan ELEVATION:

LOG OF BORINGNo. B-2

DRILLER: Soil Exploration Corp LOGGED BY: RC

DRILLING METHOD: 4.25" ID HSA DATE: 10/25/2018

DEPTH TO - WATER> INITIAL: NA AFTER 24 HOURS:

Test boring was backfilled with soil cuttings upon completion.

De

pth

(fe

et)

Description

Gra

ph

ic

Ele

vatio

n (

feet)

Sa

mp

leN

o.

Blo

wC

ou

nts

% <

#2

00 TEST RESULTS

10 20 30 40 50Penetration -

Water Content -

Plastic Limit Liquid Limit

Figure

Th

is i

nfo

rma

tio

n p

ert

ain

s o

nly

to

th

is b

ori

ng

an

d s

ho

uld

no

t b

e i

nte

rpre

ted

as

be

ing

in

dic

ati

ve

of

the

sit

e.

PAGE 2 of 2

Page 25: GEOTECHNICAL INVESTIGATION REPORT · 2020-02-04 · Geotechnical Investigation Report Page . 5. of . 12. . Geotechnical laboratory testing was performed in general accordance with

MO

RE

TH

AN

1/2

OF

CO

AR

SE

FR

AC

TIO

N <

No.

4S

IEV

E S

IZE

GM

GC

GR

AV

ELS

MA

JOR

DIV

ISIO

NS

Inor

gani

c cl

ays

of h

igh

plas

ticity

, fat

cla

ys

GW

Wel

l-gra

ded

sand

or

grav

elly

san

ds, l

ittle

or

no f

ines

Poo

rly g

rade

d sa

nds

or g

rave

lly s

ands

, litt

le o

r no

fin

es

SIL

TS

& C

LAY

S

Org

anic

cla

ys o

f m

ediu

m to

hig

h pl

astic

ity, o

rgan

ic s

ilty

clay

s, o

rgan

ic s

ilts

Inor

gani

c si

lts, m

icac

eous

or

diat

omac

eous

fin

e sa

ndy

orsi

lty s

oils

, ela

stic

silt

s

GR

AV

ELS

WIT

HO

VE

R 1

5%F

INE

S

SY

MB

OLS

Silt

y gr

avel

s, g

rave

l-san

d m

ixtu

res

CLE

AN

SA

ND

SW

ITH

LE

SS

TH

AN

5%

FIN

ES

SA

ND

S W

ITH

OV

ER

15%

FIN

ES

CH

Cla

yey

grav

els,

gra

vel-s

and-

clay

mix

ture

s

TY

PIC

AL

NA

ME

S

SP

SC

ML

CL

OL

SW

CLE

AN

GR

AV

ELS

WIT

HLE

SS

TH

AN

5%

FIN

ES

Inor

gani

c si

lts a

nd v

ery

fine

sand

s, r

ock

flour

, silt

y or

clay

ey f

ine

sand

s or

cla

yey

silts

with

slig

ht p

last

icity

LIQ

UID

LIM

IT G

RE

AT

ER

TH

AN

50%

SIL

TS

& C

LAY

S

GP

OH

FINE-GRAINED SOILSOVER 50% < No.200 SIEVE SIZE

PT

Pea

t and

oth

er h

ighl

y or

gani

c so

ils

LIQ

UID

LIM

IT 5

0% O

R L

ES

S

SA

ND

S

COARSE-GRAINED SOILSOVER 50% > No.200 SIEVE SIZE

MH

SM

Wel

l-gra

ded

grav

els

or g

rave

l-san

d m

ixtu

res,

littl

e or

no

fines

Poo

rly g

rade

d gr

avel

s or

gra

vel-s

and

mix

ture

s, li

ttle

or n

ofin

es

Org

anic

silt

s an

d or

gani

c si

lty c

lays

of

low

pla

stic

ity

Inor

gani

c cl

ays

of lo

w to

med

ium

pla

stic

ity, g

rave

lly c

lays

,sa

ndy

clay

s, s

ilty

clay

s, le

an c

lays

Silt

y sa

nd, s

and-

silt

mix

ture

s

MO

RE

TH

AN

1/2

OF

CO

AR

SE

FR

AC

TIO

N >

No.

4S

IEV

E S

IZE

Cla

yey

sand

s, s

and-

clay

mix

ture

s

HIG

HLY

OR

GA

NIC

SO

ILS

RA

NG

E O

F G

RA

IN S

IZE

S

CO

BB

LES

coar

sefin

e

12"

to 3

"

3" to

No.

43"

to 3

/4"

3/4"

to N

o. 4

No.

4 to

No.

10

No.

10

to N

o. 4

0N

o. 4

0 to

No.

200

Bel

ow N

o. 2

00

305

to 7

6.2

76.2

to 4

.75

BO

ULD

ER

S

Gra

in S

ize

in M

illim

eter

s

76.2

to 1

9.1

19.1

to 4

.75

4.75

to 0

.075

SA

ND

4.75

to 2

.00

2.00

to 0

.425

0.42

5 to

0.0

75

CLA

SS

IFIC

AT

ION

coar

sem

ediu

mfin

e

U.S

. Sta

ndar

dS

ieve

Siz

e

Abo

ve 1

2"

SIL

T &

CLA

Y

GR

AV

EL

No.

4 to

No.

200

Abo

ve 3

05

Bel

ow 0

.075

REFE

RENCE: U

NIF

IED

SO

IL C

LA

SS

IFIC

AT

ION

SY

ST

EM

- A

ST

M D

2488

-93

Gra

vel,

Sand

, and

Silt

(n

onpl

astic

)

N-V

alue

0 - 4

Ve

ry L

oose

Rel

ativ

e D

ensi

ty

5 - 1

0 Lo

ose

11-3

0M

ediu

m D

ense

31 -

50

Den

se51

+

Very

Den

se

Silt

(pla

stic

) and

Cla

y

N-V

alue

0 - 2

0

- 25

0

Very

Sof

t

SuC

onsi

sten

cy

3 - 4

2

51 -

500

Sof

t

5 - 8

5

01 -

1000

M

ediu

m S

tiff

9 - 1

5 1

001

- 200

0 S

tiff

16 -

30 2

001

- 400

0 V

ery

Stiff

31 +

4

001+

Har

d

Stan

dard

Pen

etra

tion

Test

ing

(SPT

) N60

bas

ed o

n bl

ows

per 1

2 in

ches

.W

R =

Wei

ght o

f Rod

s; W

H =

Wei

ght o

f Ham

mer

REL

ATI

VE

DEN

SITY

/CO

NSI

STEN

CY

KE

Y T

O S

YM

BO

LS

AN

D D

ESC

RIP

TIO

NS

Stan

dard

Spl

it Sp

oon

Sam

ple

Shel

by T

ube

Soni

c or

Vi

bro-

Cor

e Sa

mpl

e

Auge

r Cut

tings

3" S

plit

Spoo

n Sa

mpl

eD

ynam

ic C

one

Pene

trom

eter

Bulk

/Gra

b Sa

mpl

e

Wat

er T

able

(a

fter 2

4 ho

urs)

Roc

k C

ore

Vane

She

ar

Geo

prob

e Sa

mpl

e

Wat

er T

able

(a

t tim

e of

dril

ling)

TY

PIC

AL

SY

MB

OL

S

Parti

ng:

Seam

:

Laye

r:St

ratu

m:

Pock

et:

Lens

:O

ccas

iona

l:Fr

eque

nt

0.5

in. t

o 1/

16 in

.

12 in

. to

0.5

in.

>12

in.

Smal

l erra

tic d

epos

it Le

ntic

ular

dep

osit

One

or l

ess

per f

oot o

f thi

ckne

ss

Mor

e th

an o

ne p

er fo

ot o

f thi

ckne

ss

>1/

16 in

.

Term

Des

crip

tion

SOIL

MO

ISTU

RE

MO

DIF

IER

STe

rm

D

escr

iptio

n

PER

CEN

T O

R P

OR

TIO

NS

OF

SOIL

Dam

p bu

t no

visi

ble

wat

er

Abse

nce

of m

oist

ure;

dus

ty, d

ry to

touc

h

Moi

st

Dry Wet

Visi

ble

free

wat

er

The

desc

ripto

r "da

mp"

sho

uld

not b

e us

ed (u

se "m

oist

").

The

desc

ripto

r "sa

tura

ted"

sho

uld

not b

e us

ed (u

se "w

et")

.

Rec

esse

d C

over

Se

t in

Con

cret

eTo

p of

Wel

l,R

eces

sed

Pipe

Cov

ered

Ris

er

Cap

ped

Ris

er w

/ Lo

ckin

g C

over

Pipe

Ris

er

Con

cret

e Se

al

Gra

vel B

ackf

ill

Asso

rted

Cut

tings

Bent

onite

Slu

rry

Bent

onite

Pel

lets

Silic

a Sa

nd,

blan

k PV

CSl

otte

d Pi

pe w

/ Sa

ndEn

dcap

on

Pipe

Pa

cked

in S

and

Silic

a Sa

nd, N

o Pi

pe (E

nd P

lug)

WEL

L SY

MB

OLS

Varv

edAl

tern

atin

g se

ams

or la

yers

of s

ilt a

nd/o

r cla

yan

d so

met

imes

f. s

and

skurtzer
Line
Page 26: GEOTECHNICAL INVESTIGATION REPORT · 2020-02-04 · Geotechnical Investigation Report Page . 5. of . 12. . Geotechnical laboratory testing was performed in general accordance with

www.consultjtc.com

APPENDIX E: GEOTECHNICAL LABORATORY TESTING RESULTS

Page 27: GEOTECHNICAL INVESTIGATION REPORT · 2020-02-04 · Geotechnical Investigation Report Page . 5. of . 12. . Geotechnical laboratory testing was performed in general accordance with

Particle Size Distribution ReportP

ER

CE

NT

FIN

ER

0

10

20

30

40

50

60

70

80

90

100

GRAIN SIZE - mm.

0.0010.010.1110100

% CobblesCoarse

% Gravel

Fine Coarse Medium

% Sand

Fine Silt

% Fines

Clay

0.0 0.0 10.2 6.4 14.0 29.8 39.6

6 in

.

3 in

.

2 in

.

in.

1 in

.

¾ in

.

½ in

.

3/8

in.

#4

#1

0

#2

0

#3

0

#4

0

#6

0

#1

00

#1

40

#2

00

TEST RESULTS

Opening Percent Spec.* Pass?

Size Finer (Percent) (X=Fail)

Material Description

Atterberg Limits (ASTM D 4318)

Classification

Coefficients

Date Received: Date Tested:

Tested By:

Checked By:

Title:

Date Sampled:Location: B-1(S-1)Sample Number: G18-129 Depth: 0'-2'

Client:

Project:

Project No: Figure

Silty sand

1/23/8#4#10#20#40#50

#100#200

100.097.089.883.476.569.464.451.239.6

SM

4.8735 2.5219 0.23560.1407

In-Situ Moisture: 17.5%

10-26-18 10-29-18

Ted Moody

Jeff Young

Lab Manager

10-22-18

Town of Durham, NH

Communications Tower - Beech Hill Rd, Durham, NH

18-15-089

PL= LL= PI=

USCS (D 2487)= AASHTO (M 145)=

D90= D85= D60=D50= D30= D15=D10= Cu= Cc=

Remarks

* (no specification provided)

001

Page 28: GEOTECHNICAL INVESTIGATION REPORT · 2020-02-04 · Geotechnical Investigation Report Page . 5. of . 12. . Geotechnical laboratory testing was performed in general accordance with

Particle Size Distribution ReportP

ER

CE

NT

FIN

ER

0

10

20

30

40

50

60

70

80

90

100

GRAIN SIZE - mm.

0.0010.010.1110100

% CobblesCoarse

% Gravel

Fine Coarse Medium

% Sand

Fine Silt

% Fines

Clay

0.0 0.0 6.9 3.5 12.2 28.3 49.1

6 in

.

3 in

.

2 in

.

in.

1 in

.

¾ in

.

½ in

.

3/8

in.

#4

#1

0

#2

0

#3

0

#4

0

#6

0

#1

00

#1

40

#2

00

TEST RESULTS

Opening Percent Spec.* Pass?

Size Finer (Percent) (X=Fail)

Material Description

Atterberg Limits (ASTM D 4318)

Classification

Coefficients

Date Received: Date Tested:

Tested By:

Checked By:

Title:

Date Sampled:Location: B-1(S-3)Sample Number: G18-130 Depth: 5'-7'

Client:

Project:

Project No: Figure

Silty sand

3/41/23/8#4#10#20#40#50

#100#200

100.096.996.993.189.683.977.472.660.149.1

SM

2.1899 0.9717 0.14920.0794

In-Situ Moisture: 12.1%

10-26-18 10-29-18

Ted Moody

Jeff Young

Lab Manager

10-22-18

Town of Durham, NH

Communications Tower - Beech Hill Rd, Durham, NH

18-15-089

PL= LL= PI=

USCS (D 2487)= AASHTO (M 145)=

D90= D85= D60=D50= D30= D15=D10= Cu= Cc=

Remarks

* (no specification provided)

002

Page 29: GEOTECHNICAL INVESTIGATION REPORT · 2020-02-04 · Geotechnical Investigation Report Page . 5. of . 12. . Geotechnical laboratory testing was performed in general accordance with

Particle Size Distribution ReportP

ER

CE

NT

FIN

ER

0

10

20

30

40

50

60

70

80

90

100

GRAIN SIZE - mm.

0.0010.010.1110100

% CobblesCoarse

% Gravel

Fine Coarse Medium

% Sand

Fine Silt

% Fines

Clay

0.0 0.0 8.4 5.3 14.4 28.3 43.6

6 in

.

3 in

.

2 in

.

in.

1 in

.

¾ in

.

½ in

.

3/8

in.

#4

#1

0

#2

0

#3

0

#4

0

#6

0

#1

00

#1

40

#2

00

TEST RESULTS

Opening Percent Spec.* Pass?

Size Finer (Percent) (X=Fail)

Material Description

Atterberg Limits (ASTM D 4318)

Classification

Coefficients

Date Received: Date Tested:

Tested By:

Checked By:

Title:

Date Sampled:Location: B-1(S-7)Sample Number: G18-131 Depth: 25'-27'

Client:

Project:

Project No: Figure

Silty sand

3/41/23/8#4#10#20#40#50

#100#200

100.095.094.291.686.379.671.966.453.643.6

SM

3.5554 1.6706 0.21300.1199

In-Situ Moisture: 9.6%

10-26-18 10-29-18

Ted Moody

Jeff Young

Lab Manager

10-22-18

Town of Durham, NH

Communications Tower - Beech Hill Rd, Durham, NH

18-15-089

PL= LL= PI=

USCS (D 2487)= AASHTO (M 145)=

D90= D85= D60=D50= D30= D15=D10= Cu= Cc=

Remarks

* (no specification provided)

003

Page 30: GEOTECHNICAL INVESTIGATION REPORT · 2020-02-04 · Geotechnical Investigation Report Page . 5. of . 12. . Geotechnical laboratory testing was performed in general accordance with

Particle Size Distribution ReportP

ER

CE

NT

FIN

ER

0

10

20

30

40

50

60

70

80

90

100

GRAIN SIZE - mm.

0.0010.010.1110100

% CobblesCoarse

% Gravel

Fine Coarse Medium

% Sand

Fine Silt

% Fines

Clay

0.0 0.0 11.0 5.1 12.2 25.8 45.9

6 in

.

3 in

.

2 in

.

in.

1 in

.

¾ in

.

½ in

.

3/8

in.

#4

#1

0

#2

0

#3

0

#4

0

#6

0

#1

00

#1

40

#2

00

TEST RESULTS

Opening Percent Spec.* Pass?

Size Finer (Percent) (X=Fail)

Material Description

Atterberg Limits (ASTM D 4318)

Classification

Coefficients

Date Received: Date Tested:

Tested By:

Checked By:

Title:

Date Sampled:Location: B-2(S-4)Sample Number: G18-132 Depth: 10'-12'

Client:

Project:

Project No: Figure

Silty sand

3/41/23/8#4#10#20#40#50

#100#200

100.095.793.089.083.978.271.767.155.845.9

SM

5.8427 2.3953 0.19360.1016

In-Situ Moisture: 11.2%

10-26-18 10-29-18

Ted Moody

Jeff Young

Lab Manager

10-22-18

Town of Durham, NH

Communications Tower - Beech Hill Rd, Durham, NH

18-15-089

PL= LL= PI=

USCS (D 2487)= AASHTO (M 145)=

D90= D85= D60=D50= D30= D15=D10= Cu= Cc=

Remarks

* (no specification provided)

004

Page 31: GEOTECHNICAL INVESTIGATION REPORT · 2020-02-04 · Geotechnical Investigation Report Page . 5. of . 12. . Geotechnical laboratory testing was performed in general accordance with

CLIENT:

DATE:

Date Received:

Lab Technician:

REMARKS:

B-1(S-3) 5'-7'

October 31, 2018

10-22-18 & 10-25-18

Rachel CannonSampled By:

Date Sampled:

Summary of Atterberg Limits

Boring # Sample DepthMoisture

Content

USCS

Classification

Liquidity

IndexLiquid Limit Plastic Limit

Plasticity

Index

ASTM D4318

Town of Durham, NH

10/25/2018

Ted Moody Reviewed By: Jeff Young

Communications Tower

Beach Hill Rd.

Durham, NH

18-15-089-001CREPORT #:

PROJECT:

ML12.10% 22 NP - -

_________________________________________________________________________________________________

19 Dover Street | Dover, NH 03820 | Phone: (603) 749-1841 | www.consultjtc.com

Page 32: GEOTECHNICAL INVESTIGATION REPORT · 2020-02-04 · Geotechnical Investigation Report Page . 5. of . 12. . Geotechnical laboratory testing was performed in general accordance with

www.consultjtc.com

APPENDIX F: SITE PHOTOGRAPHS PAGE

Page 33: GEOTECHNICAL INVESTIGATION REPORT · 2020-02-04 · Geotechnical Investigation Report Page . 5. of . 12. . Geotechnical laboratory testing was performed in general accordance with

www.consultjtc.com

BEECH HILL COMMUNICATION TOWER BEECH HILL ROAD DURHAM NEW HAMPSHIRE

Site, To West

Set up on B-1, To South

Drilling activities, Typical

Sample collection, Typical

Set up on B-2, To North

Sample of Glacial Till, Typical

SITE PHOTOGRAPHS