Upload
others
View
15
Download
0
Embed Size (px)
Citation preview
www.consultjtc.com
GEOTECHNICAL INVESTIGATION REPORT
PROPOSED COMMUNICATIONS TOWER Beech Hill Road
Durham, New Hampshire 03824
Prepared for:
Town of Durham 8 Newmarket Road
Durham, New Hampshire 03824
Prepared by:
John Turner Consulting, Inc. 19 Dover Street
Dover, New Hampshire 03820
JTC Project No. 18-15-089
November 19, 2018
____________________ Rachel Cannon Senior Project Manager 19 Dover Street Dover, NH 03820 [email protected] Ph: (603) 799-1868
Thomas A. McIntosh III, PE Senior Geotechnical Engineer 19 Dover Street Dover, NH 03820 [email protected] Ph: (508) 446-6180
Judson Zachar, PE Director of Geotechnical Engineering 19 Dover Street Dover, NH 03820 [email protected] Ph: (508) 320-4668
www.consultjtc.com
November 19, 2018 Town of Durham 8 Newmarket Road Durham, New Hampshire 03824 Attn: April Talon
RE: Geotechnical Investigation Report Proposed Communications Tower Beech Hill Road Durham, New Hampshire
Dear Ms. Talon:
In accordance with our proposal and your authorization to proceed, John Turner Consulting, Inc. (JTC) has performed a geotechnical investigation for the above captioned project. Presented herein and attached are the results of the site subsurface investigation, and our recommendations regarding the design and construction of the foundation, and other geotechnical related concerns or issues.
We appreciate the opportunity to assist you on this venture and we look forward to working with you on this project through its completion. Please do not hesitate to contact us if you have any questions or require additional information.
Sincerely, JOHN TURNER CONSULTING, INC.
Rachel Cannon Senior Project Manager 19 Dover Street Dover, NH 03820 [email protected] Ph: (603) 799-1868
Proposed Communication Tower Beech Hill Road, Durham, New Hampshire
Geotechnical Investigation Report Page 2 of 12
www.consultjtc.com
Table of Contents
1.0 INTRODUCTION ................................................................................................................................................ 3 2.0 PROJECT INFORMATION ................................................................................................................................... 3
2.1 Site Description ............................................................................................................................................ 3 2.2 Regional Geologic Setting ............................................................................................................................ 3 2.3 Proposed Development ............................................................................................................................... 4
3.0 GEOTECHNICAL EXPLORATIONS ....................................................................................................................... 4 4.0 GEOTECHNICAL LABORATORY TESTING ........................................................................................................... 4 5.0 SUBSURFACE CONDITIONS ............................................................................................................................... 5
5.1 Soils .............................................................................................................................................................. 5 5.1.1 Forest Mat & Subsoil................................................................................................................................ 5 5.1.2 Till ............................................................................................................................................................ 5
5.2 Bedrock ........................................................................................................................................................ 5 5.3 Groundwater ................................................................................................................................................ 5
6.0 GEOTECHNICAL ANALYSIS & RECOMMENDATIONS ......................................................................................... 6 6.1 Site Preparation and Grading ....................................................................................................................... 6 6.2 Communications Tower ............................................................................................................................... 7 6.3 Equipment Shelters and/or Tanks and Telecommunications Equipment .................................................... 8 6.4 General Foundation Preparation Requirements .......................................................................................... 9 6.5 Seismic Considerations .............................................................................................................................. 10 6.6 Wind Loading ............................................................................................................................................. 10 6.7 Re-Use of Site Soils ..................................................................................................................................... 10 6.8 Construction Monitoring and Quality Control Testing ............................................................................... 10 6.9 Additional Considerations .......................................................................................................................... 11
7.0 CLOSING .......................................................................................................................................................... 12 APPENDIX A: Limitations APPENDIX B: Recommended Soil Gradation & Compaction Specifications APPENDIX C: Site Plan & Test Boring Location Plan APPENDIX D: Test Boring Logs & Key to Symbols and Descriptions APPENDIX E: Geotechnical Laboratory Testing Results APPENDIX F: Site Photographs Page
Proposed Communication Tower Beech Hill Road, Durham, New Hampshire
Geotechnical Investigation Report Page 3 of 12
www.consultjtc.com
1.0 INTRODUCTION
John Turner Consulting, Inc. (JTC) is pleased to present this Geotechnical Investigation Report for the proposed Communications Tower to be located at Beech Hill Road in Durham, New Hampshire. JTC conducted geotechnical explorations, laboratory testing, and engineering evaluations in general accordance with our proposed scope of services submitted to Durham Public Works on August 23, 2018.
The purpose of the geotechnical investigation was to obtain information on the subsurface conditions at the site and to provide geotechnical engineering recommendations to support the planning, design, and construction of the proposed development. Geotechnical explorations and laboratory testing services were performed in October of 2018.
This report summarizes available project information, presents the geotechnical exploration and laboratory testing programs, describes the subsurface conditions encountered, and provides geotechnical engineering recommendations to support the planning, design, and construction of the proposed Telecommunications Facility. The contents of this report are subject to the attached Limitations.
2.0 PROJECT INFORMATION
The following subsections provide general descriptions of the site, the regional geologic setting, and the proposed development.
2.1 Site Description
The site is located near the northwest corner of the Town of Durham near the an existing water storage tank approximately one half mile northwest of the end of pavement of Beech Hill Road. The subject property is accessible by a dirt access road from the end of Beech Hill Road. Presently, the site is at the apex of a steeply sloped and heavily-wooded terrain. The terrain descends dramatically to the south from approximately EL. 276 ft. to EL. 115 ft. towards Route 4 over a distance of approximately 1,400 feet. The Madbury town line and high tension, electric transmission lines are located approximately 200 feet to the north of the site. Refer to the attached existing site plan entitled, “Lot Line Revision and Water Line & Access Easement Plan” prepared by Doucet Survey of Newmarket, NH dated 08 December 2018 for further information.
2.2 Regional Geologic Setting
JTC’s review of the “Surficial geologic map of the Dover West quadrangle, Strafford County, New Hampshire” (Koteff, Carl, Goldsmith, Richard, and Gephart, G.D., 1989) indicates the site soils are likely to consist of non-sorted mixture ranging from clay-size particles to large boulders but dominantly silt to pebble sizes. Locally includes small irregular masses of sorted and stratified sand and gravel.
Proposed Communication Tower Beech Hill Road, Durham, New Hampshire
Geotechnical Investigation Report Page 4 of 12
www.consultjtc.com
2.3 Proposed Development
JTC understands that the proposed development involves the construction of a 150 ft tall telecommunication tower and an equipment shelter. We understand that design details are still being developed, but that the intent is to support the tower and equipment shelter on conventional, cast-in-place, concrete spread footings which are anticipated to be 15 ft x 15 ft (225 s.f.) and 10 ft x 18 ft (180 s.f.) respectively. Site-specific structural loading was not available at the time of this report.
3.0 GEOTECHNICAL EXPLORATIONS
JTC subcontracted Soil Exploration Corp (SoilEx) to perform two (2) geotechnical test borings. designated as B-1 and B-2 via a tire-mounted CME-75 ATV drill rig. JTC directed the drilling, testing, and sampling activities and logged the subsurface conditions encountered at each boring location.
The exploration locations were selected in relation to the existing site features and proposed development, and under the constraints of drill rig access and utility conflicts. Subsequently, the relative location of each exploration was established via measurements from existing site features and scaling the dimensions onto the provided plan(s). The attached Test Boring Location Plan depicts the approximate exploration locations.
The test borings were advanced to depths of 32 feet below the ground surface (bgs) utilizing 4¼-inch inside-diameter continuous-flight hollow-stem-augers (HSAs). As the borings were advanced, standard penetration tests (SPTs) were conducted at regular intervals and soil samples were obtained via 2-inch outside-diameter split-spoon samplers driven by an automatic 140-pound hammer. SPTs were performed in general accordance with ASTM D1586, Standard Test Method for Penetration Test and Split-Barrel Sampling of Soils. The test borings were backfilled with soil cuttings upon completion of drilling. Soil samples were sealed in moisture-tight containers and returned to JTC’s office for further review, classification, and/or geotechnical laboratory testing. Detailed records of the drilling, testing, and sampling performed; and the soil, bedrock, and groundwater conditions observed at each test boring location are provided on the attached Test Boring Logs.
4.0 GEOTECHNICAL LABORATORY TESTING
JTC selected representative soil samples for geotechnical laboratory testing at our in-house laboratory. The following tests were performed:
• 4 Moisture contents; • 4 Particle-size analyses; • 1 Atterberg Limits
Proposed Communication Tower Beech Hill Road, Durham, New Hampshire
Geotechnical Investigation Report Page 5 of 12
www.consultjtc.com
Geotechnical laboratory testing was performed in general accordance with ASTM procedures. Test results are provided on the attached Geotechnical Laboratory Testing Reports.
5.0 SUBSURFACE CONDITIONS
The following subsections describe the site soil, bedrock, and groundwater conditions encountered, based on results of the geotechnical explorations and laboratory testing. Detailed descriptions of the conditions observed at each test boring are provided on the attached Test Boring Logs.
5.1 Soils
The overburden soils encountered at the test boring locations appear to be consistent with those described by the published geologic data. The primary soil strata are briefly described in the paragraphs below.
5.1.1 Forest Mat & Subsoil
Forest Mat and Subsoil materials were encountered at the ground surface at both boring locations. The Forest Mat and Subsoil were generally described as loose, silty fine Sand (SM) with organics. The Forest Mat and Subsoil is approximately 2 feet thick.
5.1.2 Till
Native granular soils interpreted as Till were encountered beneath the Forest Mat & Suboil layers and consisted of olive brown, silty sand (SM), silty gravel with sand (GM), silty sand (SM), with gravel and poorly graded medium-coarse sand (SP). The till deposits were considered medium dense to very dense based on SPT N-Values ranging from 24 to 50 blows per foot.
5.2 Bedrock
Practical refusal to further penetration of the augers and/or split-spoon sampler was not encountered at the test boring locations. Bedrock is not expected to impact excavation based on the results of this investigation.
5.3 Groundwater
Groundwater and/or wet soils were not encountered at all test boring locations. Short-term (i.e., during drilling, upon completion of drilling, and/or a few hours after drilling) water levels observed in test borings performed in silty soils should be considered approximate.
JTC estimates that this investigation occurred during a period of seasonally normal to high ground water. Site groundwater levels should be expected to fluctuate seasonally and in response to precipitation events, construction activity, site use, and adjacent site use.
Proposed Communication Tower Beech Hill Road, Durham, New Hampshire
Geotechnical Investigation Report Page 6 of 12
www.consultjtc.com
6.0 GEOTECHNICAL ANALYSIS & RECOMMENDATIONS
The evaluation of the site and the proposed development was based on the subsurface conditions encountered at the exploration locations, results of geotechnical laboratory testing, provided site plans/grading, and provided structural loading conditions, as described herein.
6.1 Site Preparation and Grading
Site preparation and grading should be performed in accordance with the following procedures:
• A geotechnical engineer should directly observe site preparation and grading activities; • The site soils contain substantial proportions of fine sand, silt, and/or clay, and may
degrade and/or become unworkable when subjected to construction traffic or other disturbance during wet conditions. As such, site preparations, grading, and earthworks should be performed during a dry season if possible. The Contractor shall be aware of these conditions and must take precautions to minimize subgrade disturbance. Such precautions may include diverting storm run-off away from construction areas, reducing traffic in sensitive areas, minimizing the extent of exposed subgrade if inclement weather is forecast, backfilling excavations and footings as soon as practicable, grading (and compacting) exposed subgrades to promote surface water run-off, and maintaining an effective dewatering program, as necessary. Over-excavation to remove degraded or unworkable subgrade soils should be anticipated and budgeted (cost and schedule);
• Any existing subsurface utilities and underground structures, including any private septic tank, leach field, and associated piping, should be completely removed from the footprint of the proposed building, and replaced/backfilled with properly placed and compacted Structural Fill. Any existing subsurface utilities in proposed pavement areas should be removed and/or appropriately abandoned in place (e.g., pressure grouting), as approved by the on-site geotechnical engineer;
• The site should be cleared and stripped of any existing trees/vegetation not designated to remain; Topsoil, Rootmat, Forest Mat; loamy/organic-laden Subsoil; and any otherwise unsuitable materials;
o The geotechnical explorations indicated a 2.0-foot thick layer of Forest Mat/Subsoil.
• Existing Fill and/or any otherwise unsuitable materials should be completely removed from the proposed building footprint, plus about 5 feet laterally;
o Additional Existing/Undocumented Fill materials should be expected proximate to any former building(s), foundations, and/or subsurface utilities.
• In cut areas, the final foot of excavation should be performed using a smooth-edged cutting bucket (no teeth) to minimize subgrade disturbance;
• Following clearing, stripping, removal of any Existing Fill/Undocumented Fill/unsuitable soil, and/or cutting to subgrade, the top 6 inches of exposed subgrade soils should be
Proposed Communication Tower Beech Hill Road, Durham, New Hampshire
Geotechnical Investigation Report Page 7 of 12
www.consultjtc.com
scarified and then proof-rolled using a large smooth-drum roller with successive passes aligned perpendicularly. However, proof-rolling should not be performed if/when the exposed subgrade soils are wet (i.e., due to presence of groundwater, stormwater, perched water, etc.) because this may result in soil pumping and instability. Therefore, the proof-rolling efforts, including the number of passes and whether to employ static or vibratory methods, should be directed by the on-site geotechnical engineer (static methods should be anticipated based on the results of the test borings);
o Any loose, soft, wet, and/or otherwise unsuitable soils (typically evidenced by rutting, pumping, and/or deflection of the subgrade) should be over-excavated to expose suitable soils, or other remedial measures should be taken, as approved by the on-site geotechnical engineer;
o Any over-excavations should be backfilled with properly placed and compacted;
• Structural Fill should be used for subgrade fill within the equipment compound. The placement of Structural Fill materials to achieve design subgrades in the building pad should not begin until the exposed subgrade soils have been directly observed and approved by the on-site geotechnical engineer;
• Common Fill is acceptable for subgrade fill in parking and driveway areas. The placement of Common Fill materials to achieve design subgrades in pavement areas should not begin until the exposed subgrade soils have been directly observed and approved by the on-site geotechnical engineer; and
• Structural Fill and Common Fill materials and placement and compaction requirements are provided in the attached Tables.
6.2 Communications Tower
Based on the subsurface conditions encountered at the exploration locations and our current understanding relative to the proposed development, the monopole foundation can be designed and constructed as a single conventional spread footing. The designed capacity and reinforcement should be based on the Soil Properties table below.
Table 1: Soil Properties.
GLACIAL SAND DEPOSIT
Moist Unit Weight (γm) Saturated Unit Weight (γsat)
125pcf
63 pcf
Allowable Bearing Pressure 3 tsf
Friction Angle (ϕ) 34°
Proposed Communication Tower Beech Hill Road, Durham, New Hampshire
Geotechnical Investigation Report Page 8 of 12
www.consultjtc.com
• Assuming the footing is in direct contact with the soil, lateral loading and overturning
moments can be resisted by the passive lateral earth pressures and sliding friction in the natural granular soils.
• Base lateral loads induced by wind loading can be resisted by passive earth pressures assumed to act on the full width and depth of the footing. The passive earth pressures can be computed based on a triangular distribution with an equivalent fluid pressure of 200 pounds per cubic foot which includes a safety factor of 1.5. All backfill around the footing must be placed in thin lifts and compacted to assure adequate passive resistance at the footing.
• For combined loading from dead loads and transient live loads such as seismic and wind loading, the maximum allowable contact pressure can be increased by one-third. Footing dimensions must be selected so that the resultant of the soil contact pressure falls within the middle-third, or kern distance, of the footing ensuring compressive stresses at the bottom of the footing under dead load and maximum wind load.
• The bottom of the footing must be placed a minimum of four feet below finished exterior grade in order to ensure adequate frost protection. At this depth, the footing will bear directly on the medium dense to very dense natural TILL strata. All loosened material should be removed, and if necessary, the subgrade should be lightly proof-compacted using a vibratory plate compactor.
• The Forest Mat/Subsoil materials are not suitable for load bearing. These materials should be completely removed from the footprint of the tower foundation, plus at least 5 feet laterally, as described in Section 6.1
• Global stability analysis is recommended on foundations located at slopes. All foundations shall be placed in accordance with IBC section 1808.7 Foundations on or Adjacent to Slopes. The lateral soil modulus parameter shall have appropriated reductions relative to the slope geometry and effective lateral resistance area.
• Foundation subgrade preparation shall be in accordance with section 6.4 below. The foundation must be inspected by a geotechnical engineer or representative as required by the applicable codes and assure compliance with the project specifications and the appropriated recommendations.
6.3 Equipment Shelters and/or Tanks and Telecommunications Equipment
Design recommendations for the cast-in-place concrete equipment pads are provided as follows:
Passive Earth Pressure (Kp)
Coefficient of Friction (sliding)
Equivalent Fluid Pressure
3.5
0.35 IBC
200 psf/ft IBC
Proposed Communication Tower Beech Hill Road, Durham, New Hampshire
Geotechnical Investigation Report Page 9 of 12
www.consultjtc.com
• A modulus of vertical subgrade reaction, kvi, of 200 pounds per cubic inch (pci) should be available for structural design of equipment pads/floor slabs-on-grade, provided that the subgrade, Structural Fill, and the Clean Granular Fill are prepared as recommended in Subsections 6.1, 6.2, and 6.3;
• The cast-in-place, concrete equipment pad subbase should be underlain by a minimum 6-inch thick layer of Crushed Stone atop Mirafi 600X Geotech Fabric, or equivalent, to provide a capillary break and a stable working surface;
• In accordance with the New Hampshire State Building Code; all foundations must be placed a minimum of 4 ft below existing grade.
6.4 General Foundation Preparation Requirements
During construction, we expect that much of the development area will be excavated or disturbed during site preparation and grading (Subsection 6.1), excavations for foundations (Subsection 6.2), and/or excavations for new underground utilities. It is imperative that the subgrade beneath the concrete pad be reinstated with properly placed and compacted Structural Fill be prepared as recommended herein.
• Excavations for foundations must extend into undisturbed native Glacial Deposits and/or Structural Fill built-up from properly prepared native soils, as described herein;
o If Undocumented Fill, loose, soft, wet, frozen, or otherwise unsuitable soils/materials are encountered at the foundation subgrade, over-excavations should remove all Fill and/or unsuitable soils within the footing zone of influence, which is defined as then area extending laterally 1 foot from edges of the footing and then outward and downward at a 1H:1.5V (horizontal to vertical) splay of bearing until a suitable native subgrade soil is encountered; and
o Any over-excavations should be backfilled with properly placed and compacted Structural Fill as approved by the on-site geotechnical engineer.
• The exterior sides of equipment pads, footings, or piers should be backfilled with non-frost-susceptible fill in order to mitigate potential adverse effects of frost. Backfill for equipment pads, footings, or piers should consist of well-graded, free-draining, granular soil conforming to the requirements of Clean Granular Fill for equipment pads and Structural Fill for footings, as described in the attached Specifications.
• Backfill for equipment pads, footings and piers must be placed in uniform horizontal lifts having a maximum loose lift thickness of 8 inches and compacted to 95 percent of its modified proctor maximum dry density (MPMDD; per ASTM D1557). Thinner lifts may be required in order to achieve the required compaction criteria;
• The subgrade should be level and free of standing water and debris. If shallow and/or perched groundwater is encountered, it must be removed in advance of excavation and continuously maintained at least 2 feet below the bottom of excavation and subsequent construction grade until the backfilling is complete;
Proposed Communication Tower Beech Hill Road, Durham, New Hampshire
Geotechnical Investigation Report Page 10 of 12
www.consultjtc.com
• A geotechnical engineer licensed by the State of New Hampshire or his representative should directly observe the foundation subgrade preparation activities and the subgrade soils prior to the placement foundation materials.
6.5 Seismic Considerations
Earthquake loadings must be considered under the requirements of the current edition of the New Hampshire Building Code (NH-Code) which refers to the 2009 edition of the International Building Code (IBC). IBC Table 1613.5.2 is used to establish the site class based on the average soil properties and soil profile. Site class is then used to determine the site coefficient and mapped spectral response for a given structure. Based on the conditions encountered at the test boring locations, the site is classified as:
Site Class D: Stiff Soil Profile.
Liquefaction refers to the loss of strength in saturated cohesionless soils due to the buildup of pore water pressures during cyclic or seismic loading. Based on the conditions encountered at the test boring locations, the site is NOT considered to be susceptible to liquefaction.
6.6 Wind Loading
The terrain and relatively open site indicate an Exposure C condition. Reference pressures for determining wind loading should be based either on Section 1609 Table 1604.11 of The International Building Code or the provisions contained in TIA/EIA 222-G-09 Structural Standard for Antenna Supporting Structures and Antennas, whichever is higher.
6.7 Re-Use of Site Soils
The Forest Mat, Subsoil, & Till materials encountered at the exploration locations are not suitable for re-use as Structural Fill, Clean Granular Fill, or Common Fill. These soils may be re-used in areas to be landscaped, subject to conformance with the project specifications.
6.8 Construction Monitoring and Quality Control Testing
A qualified engineer or representative should be retained to review the site and subgrade operations, as required by the New Hampshire State Building Code (NH-Code). Similarly, quality control testing, including in-place field density and moisture tests, should be performed to confirm that the specified compaction is achieved. It is recommended that JTC be retained to provide earthwork construction monitoring and quality control testing services.
Quality control testing recommendations are provided as follows:
• During site grading and foundation subgrade preparation, 3 field density tests should be performed for every 5,000 square feet (per lift) of Structural Fill placement, at a minimum.
Proposed Communication Tower Beech Hill Road, Durham, New Hampshire
Geotechnical Investigation Report Page 11 of 12
www.consultjtc.com
At least 3 tests should be performed on each lift of material even if the lift is less than 5,000 square feet;
• During backfilling of utility trenches, at least 1 test should be conducted on Structural Fill per 50 linear feet (per lift) of trench; and
• During site grading and pavement subgrade preparation, 3 field density tests should be performed for every 5,000 square feet (per lift) of Common Fill, at a minimum. At least 3 tests should be performed on each lift even if the lift is less than 5,000 square feet.
6.9 Additional Considerations
Additional design recommendations are provided as follows:
• Exterior concrete sidewalks shall be underlain by at least 12 inches of Clean Granular Fill. The thickness of the Clean Granular Fill shall be increased to no less than 18 inches for exterior concrete slabs located adjacent to exterior doorways and ramps to provide additional frost protection at building entry/exit points;
• The exterior ground surface adjacent to the equipment compound should be sloped away from the building to provide for positive drainage. Similarly, the final surface materials adjacent to the building should be relatively impermeable to reduce the volume of precipitation infiltrating into the subsurface proximate to building foundations. Such impermeable materials include cement concrete, bituminous concrete, and/or vegetated silty/clayey topsoil; and
• Permanent fill or cut slopes should have a maximum slope of 2.5H:1V (horizontal to vertical) or flatter for dry conditions. Permanent fill or cut slopes should be no steeper than 3H:1V for wet/submerged conditions (e.g., stormwater basin) unless a properly designed surface slope stabilization system (e.g. rip rap, geosynthetics) is provided.
Additional construction considerations/recommendations are provided as follows:
• Safe temporary excavation and/or fill slopes are the responsibility of the Contractor. Excavations should be conducted in accordance with local, state, and federal (OSHA) requirements, at a minimum. If an excavation cannot be properly sloped or benched due to space limitations, adjacent structures, and/or seepage, the Contractor should install an engineered shoring system to support the temporary excavation;
• Subgrade conditions will be influenced by excavation methods, precipitation, stormwater management, groundwater control(s), and/or construction activities. Most of the site soils are poorly-drained, moisture-sensitive, and considered susceptible to disturbance when exposed to wet conditions and construction activities. As such, the Contractor shall be aware of these conditions and must take precautions to minimize subgrade disturbance. Such precautions may include diverting storm run-off away from construction areas, reducing traffic in sensitive areas, minimizing the extent of exposed subgrade if inclement weather is forecast, backfilling excavations and footings as soon as
Proposed Communication Tower Beech Hill Road, Durham, New Hampshire
Geotechnical Investigation Report Page 12 of 12
www.consultjtc.com
practicable, and maintaining an effective dewatering program, as necessary; • Proper groundwater control and stormwater management are necessary to maintain site
stability. Groundwater should be removed in advance and continuously maintained at least 2 feet below the working construction grade until earthworks and/or backfilling are complete;
• If groundwater seepage and/or wet soils due to shallow groundwater are observed, a ¾-inch minus crushed stone base should be placed atop the exposed subgrade soils. The stone should be immediately placed atop the undisturbed subgrade and then tamped with a plate compactor until exhibiting stable conditions. The stone shall be protected, as required, with a geotextile filter fabric such as Mirafi 600X or equal. The purpose of the stone base is to protect the wet subgrade, facilitate dewatering, and provide a dry/stable base upon which to progress construction; and
• All slopes should be protected from erosion during (and after) construction.
7.0 CLOSING
We trust the contents of this report are responsive to your needs at this time. Should you have any questions or require additional assistance, please do not hesitate to contact our office.
www.consultjtc.com
APPENDIX A: LIMITATIONS
Explorations
1. The analyses and recommendations presented in this report are based in part upon the data obtained from widely-spaced subsurface explorations. Subsurface conditions between exploration locations may vary from those encountered at the exploration locations. The nature and extent of variations between explorations may not become evident until construction. If variations appear, it will be necessary to re-evaluate the recommendations of this report.
2. The generalized soil profile described in the text is intended to convey trends in subsurface conditions. The boundaries between strata are approximate and idealized and have been developed by interpretation of widely-spaced explorations and samples; actual strata transitions are probably more gradual. For specific information, refer to the individual test pit and/or boring logs.
3. Water level readings have been made in the test pits and/or test borings under conditions stated on the logs. These data have been reviewed and interpretations have been made in the text of this report. However, it must be noted that fluctuations in the level of the groundwater may occur due to variations in rainfall, temperature, and other factors differing from the time the measurements were made.
Review
4. It is recommended that John Turner Consulting, Inc. be given the opportunity to review final design drawings and specifications to evaluate the appropriate implementation of the geotechnical engineering recommendations provided herein.
5. In the event that any changes in the nature, design, or location of the proposed areas are planned, the conclusions and recommendations contained in this report shall not be considered valid unless the changes are reviewed, and conclusions of the report modified or verified in writing by John Turner Consulting, Inc.
Construction
6. It is recommended that John Turner Consulting, Inc. be retained to provide geotechnical engineering services during the installation phases of the work. This is to observe compliance with the design concepts, specifications, and recommendations and to allow design changes in the event that subsurface conditions differ from those anticipated prior to the start of construction.
Use of Report
7. This report has been prepared for the exclusive use of The Town of Durham for specific application to the project located at Beech Hill Road in Durham, New Hampshire. All considerations are based on the available information and is in accordance with generally accepted soil and foundation engineering practices. No other warranty, expressed or implied, is made.
8. This report has been prepared for this project by John Turner Consulting, Inc. This report was completed for preliminary design purposes and may be limited in its scope to complete an accurate bid. Contractors wishing a copy of the report may secure it with the understanding that its scope is limited to preliminary geotechnical design considerations.
www.consultjtc.com
APPENDIX B: RECOMMENDED SOIL GRADATION & COMPACTION SPECIFICATIONS
TABLE 1: Structural Fill
SIEVE SIZE PERCENT PASSING BY WEIGHT
5-inch 100
¾-inch 60 - 100
No. 4 20 - 80
No. 200 0 - 10
NOTES: 1. For use as structural load support below foundations and within the building pad. Structural Fill placed beneath building
foundations should include the Footing Zone of Influence which is defined as that area extending laterally one foot from the edge of the footing then outward and downward at a 1:1.5 (H:V) splay.
2. ¾-inch crushed stone may be used in wet conditions. 3. Structural Fill should be free of construction and demolition debris, frozen soil, organic soil, peat, stumps, brush, trash,
and refuse; 4. Structural Fill should not be placed on soft, saturated, or frozen subgrade soils; 5. Structural Fill should be placed in lifts not exceeding 12 inches for heavy vibratory rollers and 8 inches for vibratory
plate compactors. 6. Place and compact within ± 3% of optimum moisture content. 7. Compact to at least 95% relative compaction per ASTM D1557. 8. The adequacy of the compaction efforts should be verified by field density testing.
www.consultjtc.com
TABLE 2: Clean Granular Fill
Clean SIEVE SIZE PERCENT PASSING BY WEIGHT
3-inch 100
¾-inch 60 – 90
No. 4 20 – 70
No. 200 2 – 8
NOTES: 1. Should consist of crushed stone beneath the concrete pad, as approved by on-site geotechnical engineer. 2. For minimum 6-inch base below the cast-in-place concrete equipment pads. 3. For minimum 12-inch base for exterior concrete slabs exposed to frost. 4. For minimum 18-inch base at exterior ramps, aprons, and loading bays adjacent to entrances/exit ways. 5. For use as footing and foundation wall backfill. 6. For use as backfill behind unbalanced foundation/retaining walls. 7. Place in lifts not exceeding 12 inches for heavy vibratory rollers and 8 inches for vibratory plate compactors. 8. Place and compact within ± 3% of optimum moisture content. 9. Compact to at least 95% relative compaction per ASTM D1557. 10. Compact to at least 95% relative compaction per ASTM D1557 when placed as foundation wall backfill in conjunction
with a bond break. 11. The adequacy of the compaction efforts should be verified by field density testing.
TABLE 3: Common Fill
SIEVE SIZE PERCENT PASSING BY WEIGHT
6-inch 100
¾-inch 60 – 100
No. 4 20 – 85
No. 200 0 – 25 NOTES:
1. For use as common/subgrade fill in parking areas and roadway embankments. 2. For use as foundation wall backfill if used in conjunction with a bond break and sized/screened to 3-inch minus. 3. Place in lifts not exceeding 12 inches. 4. Maximum stone size should not exceed ½ the actual lift thickness. 5. Compact to at least 92% relative compaction per ASTM D1557 when placed as subgrade fill in parking areas or roadway
embankments. 6. Compact to at least 95% relative compaction per ASTM D1557 when placed as foundation wall backfill in conjunction
with a bond break. 7. The adequacy of the compaction efforts should be verified by field density testing.
www.consultjtc.com
APPENDIX C: SITE PLAN & TEST BORING LOCATION PLAN
LOT LINE REVISION &
WATER LINE & ACCESS
EASEMENT PLAN
FOR
TOWN OF DURHAM
OVER LAND OF
CUTTER BEECH HILL, LLC
TAX MAP 9, LOT 12
BEECH HILL ROAD
DURHAM, NEW HAMPSHIRE
BYDESCRIPTIONDATENO.
DRAWN BY:
CHECKED BY:
JOB NO.: SHEET
DRAWING NO.:
DATE:
OF
W.J.D.
5345
DECEMBER 8, 2017
5345A
1 1
P.J.S.
Serving Your Professional Surveying & Mapping Needs
102 Kent Place, Newmarket, NH 03857 (603) 659-6560
2 Commerce Drive (Suite 202) Bedford, NH 03110 (603) 614-4060
10 Storer Street (Riverview Suite) Kennebunk, ME (207) 502-7005
http://www.doucetsurvey.com
0
SCALE: 1 INCH = 60 FT.
60 12060
LOCATION MAP (n.t.s.)
LOCATION MAP (n.t.s.)
”
Notes:
1. Test borings were performed on October 22 & 25, 2018 under the direction of JTC. 2. Test boring locations should be considered approximate. 3. Refer to the Test Boring Logs for the subsurface conditions encountered at each boring location. 4. Basemap source: December 8, 2017 “Lot Line Revision & Water Line & Access Easement Plan” prepared by
Doucet Survey Inc. 5. Not to scale.
Town of Durham
8 Market Road Durham, New Hampshire 03824
Beech Hill Communication Tower
Beech Hill Road Durham, New Hampshire
TEST BORING LOCATION PLAN
B-1
B-2
N
www.consultjtc.com
APPENDIX D: TEST BORING LOGS & KEY TO SYMBOLS AND DESCRIPTIONS
0
2.5
5
7.5
10
12.5
15
17.5
Dark brown, silty sand (SM); loose; moist: FOREST MAT- contains frequent organics
0.5Olive brown, silty fine to medium sand (SM); loose; moist:
SUBSOIL- contains occasional organics
2Olive brown, silty sand (SM); dense; moist: GLACIAL TILL
- contains mottles
- becomes medium dense
SS01
SS02
SS03
SS04
SS05
1232
4102522
2029109
4121210
8111422
39.6
49.1
PROJECT: Proposed Telecommunications Tower PROJECT NO.: 18-15-089
CLIENT: Town of Durham, New Hampshire
PROJECT LOCATION: Beech Hill Road, Durham, New Hampshire
LOCATION: See Test Boring Location Plan ELEVATION:
LOG OF BORINGNo. B-1
DRILLER: Soil Exploration Corp LOGGED BY: RC
DRILLING METHOD: 4.25" ID HSA DATE: 10/22&25/2018
DEPTH TO - WATER> INITIAL: NA AFTER 24 HOURS:
Test boring was backfilled with soil cuttings upon completion.
De
pth
(fe
et)
Description
Gra
ph
ic
Ele
vatio
n (
feet)
Sa
mp
leN
o.
Blo
wC
ou
nts
% <
#2
00 TEST RESULTS
10 20 30 40 50Penetration -
Water Content -
Plastic Limit Liquid Limit
Figure
Th
is i
nfo
rma
tio
n p
ert
ain
s o
nly
to
th
is b
ori
ng
an
d s
ho
uld
no
t b
e i
nte
rpre
ted
as
be
ing
in
dic
ati
ve
of
the
sit
e.
PAGE 1 of 2
20
22.5
25
27.5
30
32.5
35
- becomes dense
- becomes very dense
Boring terminated at 32 ft.
SS06
SS07
SS08
11162025
13172443
18242650
43.6
PROJECT: Proposed Telecommunications Tower PROJECT NO.: 18-15-089
CLIENT: Town of Durham, New Hampshire
PROJECT LOCATION: Beech Hill Road, Durham, New Hampshire
LOCATION: See Test Boring Location Plan ELEVATION:
LOG OF BORINGNo. B-1
DRILLER: Soil Exploration Corp LOGGED BY: RC
DRILLING METHOD: 4.25" ID HSA DATE: 10/22&25/2018
DEPTH TO - WATER> INITIAL: NA AFTER 24 HOURS:
Test boring was backfilled with soil cuttings upon completion.
De
pth
(fe
et)
Description
Gra
ph
ic
Ele
vatio
n (
feet)
Sa
mp
leN
o.
Blo
wC
ou
nts
% <
#2
00 TEST RESULTS
10 20 30 40 50Penetration -
Water Content -
Plastic Limit Liquid Limit
Figure
Th
is i
nfo
rma
tio
n p
ert
ain
s o
nly
to
th
is b
ori
ng
an
d s
ho
uld
no
t b
e i
nte
rpre
ted
as
be
ing
in
dic
ati
ve
of
the
sit
e.
PAGE 2 of 2
0
2.5
5
7.5
10
12.5
15
17.5
Dark brown, silty sand (SM); medium dense; moist: FORESTMAT
- contains frequent organics0.5
Olive brown, silty fine to medium sand (SM); medium dense;moist: SUBSOIL
- contains occasional organics2
Olive brown, silty sand (SM); medium dense; moist: GLACIALTILL
- contains mottles
- becomes dense
SS01
SS02
SS03
SS04
SS05
15586
12121616
12141010
15272119
14141839
45.9
PROJECT: Proposed Telecommunications Tower PROJECT NO.: 18-15-089
CLIENT: Town of Durham, New Hampshire
PROJECT LOCATION: Beech Hill Road, Durham, New Hampshire
LOCATION: See Test Boring Location Plan ELEVATION:
LOG OF BORINGNo. B-2
DRILLER: Soil Exploration Corp LOGGED BY: RC
DRILLING METHOD: 4.25" ID HSA DATE: 10/25/2018
DEPTH TO - WATER> INITIAL: NA AFTER 24 HOURS:
Test boring was backfilled with soil cuttings upon completion.
De
pth
(fe
et)
Description
Gra
ph
ic
Ele
vatio
n (
feet)
Sa
mp
leN
o.
Blo
wC
ou
nts
% <
#2
00 TEST RESULTS
10 20 30 40 50Penetration -
Water Content -
Plastic Limit Liquid Limit
Figure
Th
is i
nfo
rma
tio
n p
ert
ain
s o
nly
to
th
is b
ori
ng
an
d s
ho
uld
no
t b
e i
nte
rpre
ted
as
be
ing
in
dic
ati
ve
of
the
sit
e.
PAGE 1 of 2
20
22.5
25
27.5
30
32.5
35
Boring terminated at 32 ft.
SS06
SS07
SS08
10132525
16192023
20232342
PROJECT: Proposed Telecommunications Tower PROJECT NO.: 18-15-089
CLIENT: Town of Durham, New Hampshire
PROJECT LOCATION: Beech Hill Road, Durham, New Hampshire
LOCATION: See Test Boring Location Plan ELEVATION:
LOG OF BORINGNo. B-2
DRILLER: Soil Exploration Corp LOGGED BY: RC
DRILLING METHOD: 4.25" ID HSA DATE: 10/25/2018
DEPTH TO - WATER> INITIAL: NA AFTER 24 HOURS:
Test boring was backfilled with soil cuttings upon completion.
De
pth
(fe
et)
Description
Gra
ph
ic
Ele
vatio
n (
feet)
Sa
mp
leN
o.
Blo
wC
ou
nts
% <
#2
00 TEST RESULTS
10 20 30 40 50Penetration -
Water Content -
Plastic Limit Liquid Limit
Figure
Th
is i
nfo
rma
tio
n p
ert
ain
s o
nly
to
th
is b
ori
ng
an
d s
ho
uld
no
t b
e i
nte
rpre
ted
as
be
ing
in
dic
ati
ve
of
the
sit
e.
PAGE 2 of 2
MO
RE
TH
AN
1/2
OF
CO
AR
SE
FR
AC
TIO
N <
No.
4S
IEV
E S
IZE
GM
GC
GR
AV
ELS
MA
JOR
DIV
ISIO
NS
Inor
gani
c cl
ays
of h
igh
plas
ticity
, fat
cla
ys
GW
Wel
l-gra
ded
sand
or
grav
elly
san
ds, l
ittle
or
no f
ines
Poo
rly g
rade
d sa
nds
or g
rave
lly s
ands
, litt
le o
r no
fin
es
SIL
TS
& C
LAY
S
Org
anic
cla
ys o
f m
ediu
m to
hig
h pl
astic
ity, o
rgan
ic s
ilty
clay
s, o
rgan
ic s
ilts
Inor
gani
c si
lts, m
icac
eous
or
diat
omac
eous
fin
e sa
ndy
orsi
lty s
oils
, ela
stic
silt
s
GR
AV
ELS
WIT
HO
VE
R 1
5%F
INE
S
SY
MB
OLS
Silt
y gr
avel
s, g
rave
l-san
d m
ixtu
res
CLE
AN
SA
ND
SW
ITH
LE
SS
TH
AN
5%
FIN
ES
SA
ND
S W
ITH
OV
ER
15%
FIN
ES
CH
Cla
yey
grav
els,
gra
vel-s
and-
clay
mix
ture
s
TY
PIC
AL
NA
ME
S
SP
SC
ML
CL
OL
SW
CLE
AN
GR
AV
ELS
WIT
HLE
SS
TH
AN
5%
FIN
ES
Inor
gani
c si
lts a
nd v
ery
fine
sand
s, r
ock
flour
, silt
y or
clay
ey f
ine
sand
s or
cla
yey
silts
with
slig
ht p
last
icity
LIQ
UID
LIM
IT G
RE
AT
ER
TH
AN
50%
SIL
TS
& C
LAY
S
GP
OH
FINE-GRAINED SOILSOVER 50% < No.200 SIEVE SIZE
PT
Pea
t and
oth
er h
ighl
y or
gani
c so
ils
LIQ
UID
LIM
IT 5
0% O
R L
ES
S
SA
ND
S
COARSE-GRAINED SOILSOVER 50% > No.200 SIEVE SIZE
MH
SM
Wel
l-gra
ded
grav
els
or g
rave
l-san
d m
ixtu
res,
littl
e or
no
fines
Poo
rly g
rade
d gr
avel
s or
gra
vel-s
and
mix
ture
s, li
ttle
or n
ofin
es
Org
anic
silt
s an
d or
gani
c si
lty c
lays
of
low
pla
stic
ity
Inor
gani
c cl
ays
of lo
w to
med
ium
pla
stic
ity, g
rave
lly c
lays
,sa
ndy
clay
s, s
ilty
clay
s, le
an c
lays
Silt
y sa
nd, s
and-
silt
mix
ture
s
MO
RE
TH
AN
1/2
OF
CO
AR
SE
FR
AC
TIO
N >
No.
4S
IEV
E S
IZE
Cla
yey
sand
s, s
and-
clay
mix
ture
s
HIG
HLY
OR
GA
NIC
SO
ILS
RA
NG
E O
F G
RA
IN S
IZE
S
CO
BB
LES
coar
sefin
e
12"
to 3
"
3" to
No.
43"
to 3
/4"
3/4"
to N
o. 4
No.
4 to
No.
10
No.
10
to N
o. 4
0N
o. 4
0 to
No.
200
Bel
ow N
o. 2
00
305
to 7
6.2
76.2
to 4
.75
BO
ULD
ER
S
Gra
in S
ize
in M
illim
eter
s
76.2
to 1
9.1
19.1
to 4
.75
4.75
to 0
.075
SA
ND
4.75
to 2
.00
2.00
to 0
.425
0.42
5 to
0.0
75
CLA
SS
IFIC
AT
ION
coar
sem
ediu
mfin
e
U.S
. Sta
ndar
dS
ieve
Siz
e
Abo
ve 1
2"
SIL
T &
CLA
Y
GR
AV
EL
No.
4 to
No.
200
Abo
ve 3
05
Bel
ow 0
.075
REFE
RENCE: U
NIF
IED
SO
IL C
LA
SS
IFIC
AT
ION
SY
ST
EM
- A
ST
M D
2488
-93
Gra
vel,
Sand
, and
Silt
(n
onpl
astic
)
N-V
alue
0 - 4
Ve
ry L
oose
Rel
ativ
e D
ensi
ty
5 - 1
0 Lo
ose
11-3
0M
ediu
m D
ense
31 -
50
Den
se51
+
Very
Den
se
Silt
(pla
stic
) and
Cla
y
N-V
alue
0 - 2
0
- 25
0
Very
Sof
t
SuC
onsi
sten
cy
3 - 4
2
51 -
500
Sof
t
5 - 8
5
01 -
1000
M
ediu
m S
tiff
9 - 1
5 1
001
- 200
0 S
tiff
16 -
30 2
001
- 400
0 V
ery
Stiff
31 +
4
001+
Har
d
Stan
dard
Pen
etra
tion
Test
ing
(SPT
) N60
bas
ed o
n bl
ows
per 1
2 in
ches
.W
R =
Wei
ght o
f Rod
s; W
H =
Wei
ght o
f Ham
mer
REL
ATI
VE
DEN
SITY
/CO
NSI
STEN
CY
KE
Y T
O S
YM
BO
LS
AN
D D
ESC
RIP
TIO
NS
Stan
dard
Spl
it Sp
oon
Sam
ple
Shel
by T
ube
Soni
c or
Vi
bro-
Cor
e Sa
mpl
e
Auge
r Cut
tings
3" S
plit
Spoo
n Sa
mpl
eD
ynam
ic C
one
Pene
trom
eter
Bulk
/Gra
b Sa
mpl
e
Wat
er T
able
(a
fter 2
4 ho
urs)
Roc
k C
ore
Vane
She
ar
Geo
prob
e Sa
mpl
e
Wat
er T
able
(a
t tim
e of
dril
ling)
TY
PIC
AL
SY
MB
OL
S
Parti
ng:
Seam
:
Laye
r:St
ratu
m:
Pock
et:
Lens
:O
ccas
iona
l:Fr
eque
nt
0.5
in. t
o 1/
16 in
.
12 in
. to
0.5
in.
>12
in.
Smal
l erra
tic d
epos
it Le
ntic
ular
dep
osit
One
or l
ess
per f
oot o
f thi
ckne
ss
Mor
e th
an o
ne p
er fo
ot o
f thi
ckne
ss
>1/
16 in
.
Term
Des
crip
tion
SOIL
MO
ISTU
RE
MO
DIF
IER
STe
rm
D
escr
iptio
n
PER
CEN
T O
R P
OR
TIO
NS
OF
SOIL
Dam
p bu
t no
visi
ble
wat
er
Abse
nce
of m
oist
ure;
dus
ty, d
ry to
touc
h
Moi
st
Dry Wet
Visi
ble
free
wat
er
The
desc
ripto
r "da
mp"
sho
uld
not b
e us
ed (u
se "m
oist
").
The
desc
ripto
r "sa
tura
ted"
sho
uld
not b
e us
ed (u
se "w
et")
.
Rec
esse
d C
over
Se
t in
Con
cret
eTo
p of
Wel
l,R
eces
sed
Pipe
Cov
ered
Ris
er
Cap
ped
Ris
er w
/ Lo
ckin
g C
over
Pipe
Ris
er
Con
cret
e Se
al
Gra
vel B
ackf
ill
Asso
rted
Cut
tings
Bent
onite
Slu
rry
Bent
onite
Pel
lets
Silic
a Sa
nd,
blan
k PV
CSl
otte
d Pi
pe w
/ Sa
ndEn
dcap
on
Pipe
Pa
cked
in S
and
Silic
a Sa
nd, N
o Pi
pe (E
nd P
lug)
WEL
L SY
MB
OLS
Varv
edAl
tern
atin
g se
ams
or la
yers
of s
ilt a
nd/o
r cla
yan
d so
met
imes
f. s
and
www.consultjtc.com
APPENDIX E: GEOTECHNICAL LABORATORY TESTING RESULTS
Particle Size Distribution ReportP
ER
CE
NT
FIN
ER
0
10
20
30
40
50
60
70
80
90
100
GRAIN SIZE - mm.
0.0010.010.1110100
% CobblesCoarse
% Gravel
Fine Coarse Medium
% Sand
Fine Silt
% Fines
Clay
0.0 0.0 10.2 6.4 14.0 29.8 39.6
6 in
.
3 in
.
2 in
.
1½
in.
1 in
.
¾ in
.
½ in
.
3/8
in.
#4
#1
0
#2
0
#3
0
#4
0
#6
0
#1
00
#1
40
#2
00
TEST RESULTS
Opening Percent Spec.* Pass?
Size Finer (Percent) (X=Fail)
Material Description
Atterberg Limits (ASTM D 4318)
Classification
Coefficients
Date Received: Date Tested:
Tested By:
Checked By:
Title:
Date Sampled:Location: B-1(S-1)Sample Number: G18-129 Depth: 0'-2'
Client:
Project:
Project No: Figure
Silty sand
1/23/8#4#10#20#40#50
#100#200
100.097.089.883.476.569.464.451.239.6
SM
4.8735 2.5219 0.23560.1407
In-Situ Moisture: 17.5%
10-26-18 10-29-18
Ted Moody
Jeff Young
Lab Manager
10-22-18
Town of Durham, NH
Communications Tower - Beech Hill Rd, Durham, NH
18-15-089
PL= LL= PI=
USCS (D 2487)= AASHTO (M 145)=
D90= D85= D60=D50= D30= D15=D10= Cu= Cc=
Remarks
* (no specification provided)
001
Particle Size Distribution ReportP
ER
CE
NT
FIN
ER
0
10
20
30
40
50
60
70
80
90
100
GRAIN SIZE - mm.
0.0010.010.1110100
% CobblesCoarse
% Gravel
Fine Coarse Medium
% Sand
Fine Silt
% Fines
Clay
0.0 0.0 6.9 3.5 12.2 28.3 49.1
6 in
.
3 in
.
2 in
.
1½
in.
1 in
.
¾ in
.
½ in
.
3/8
in.
#4
#1
0
#2
0
#3
0
#4
0
#6
0
#1
00
#1
40
#2
00
TEST RESULTS
Opening Percent Spec.* Pass?
Size Finer (Percent) (X=Fail)
Material Description
Atterberg Limits (ASTM D 4318)
Classification
Coefficients
Date Received: Date Tested:
Tested By:
Checked By:
Title:
Date Sampled:Location: B-1(S-3)Sample Number: G18-130 Depth: 5'-7'
Client:
Project:
Project No: Figure
Silty sand
3/41/23/8#4#10#20#40#50
#100#200
100.096.996.993.189.683.977.472.660.149.1
SM
2.1899 0.9717 0.14920.0794
In-Situ Moisture: 12.1%
10-26-18 10-29-18
Ted Moody
Jeff Young
Lab Manager
10-22-18
Town of Durham, NH
Communications Tower - Beech Hill Rd, Durham, NH
18-15-089
PL= LL= PI=
USCS (D 2487)= AASHTO (M 145)=
D90= D85= D60=D50= D30= D15=D10= Cu= Cc=
Remarks
* (no specification provided)
002
Particle Size Distribution ReportP
ER
CE
NT
FIN
ER
0
10
20
30
40
50
60
70
80
90
100
GRAIN SIZE - mm.
0.0010.010.1110100
% CobblesCoarse
% Gravel
Fine Coarse Medium
% Sand
Fine Silt
% Fines
Clay
0.0 0.0 8.4 5.3 14.4 28.3 43.6
6 in
.
3 in
.
2 in
.
1½
in.
1 in
.
¾ in
.
½ in
.
3/8
in.
#4
#1
0
#2
0
#3
0
#4
0
#6
0
#1
00
#1
40
#2
00
TEST RESULTS
Opening Percent Spec.* Pass?
Size Finer (Percent) (X=Fail)
Material Description
Atterberg Limits (ASTM D 4318)
Classification
Coefficients
Date Received: Date Tested:
Tested By:
Checked By:
Title:
Date Sampled:Location: B-1(S-7)Sample Number: G18-131 Depth: 25'-27'
Client:
Project:
Project No: Figure
Silty sand
3/41/23/8#4#10#20#40#50
#100#200
100.095.094.291.686.379.671.966.453.643.6
SM
3.5554 1.6706 0.21300.1199
In-Situ Moisture: 9.6%
10-26-18 10-29-18
Ted Moody
Jeff Young
Lab Manager
10-22-18
Town of Durham, NH
Communications Tower - Beech Hill Rd, Durham, NH
18-15-089
PL= LL= PI=
USCS (D 2487)= AASHTO (M 145)=
D90= D85= D60=D50= D30= D15=D10= Cu= Cc=
Remarks
* (no specification provided)
003
Particle Size Distribution ReportP
ER
CE
NT
FIN
ER
0
10
20
30
40
50
60
70
80
90
100
GRAIN SIZE - mm.
0.0010.010.1110100
% CobblesCoarse
% Gravel
Fine Coarse Medium
% Sand
Fine Silt
% Fines
Clay
0.0 0.0 11.0 5.1 12.2 25.8 45.9
6 in
.
3 in
.
2 in
.
1½
in.
1 in
.
¾ in
.
½ in
.
3/8
in.
#4
#1
0
#2
0
#3
0
#4
0
#6
0
#1
00
#1
40
#2
00
TEST RESULTS
Opening Percent Spec.* Pass?
Size Finer (Percent) (X=Fail)
Material Description
Atterberg Limits (ASTM D 4318)
Classification
Coefficients
Date Received: Date Tested:
Tested By:
Checked By:
Title:
Date Sampled:Location: B-2(S-4)Sample Number: G18-132 Depth: 10'-12'
Client:
Project:
Project No: Figure
Silty sand
3/41/23/8#4#10#20#40#50
#100#200
100.095.793.089.083.978.271.767.155.845.9
SM
5.8427 2.3953 0.19360.1016
In-Situ Moisture: 11.2%
10-26-18 10-29-18
Ted Moody
Jeff Young
Lab Manager
10-22-18
Town of Durham, NH
Communications Tower - Beech Hill Rd, Durham, NH
18-15-089
PL= LL= PI=
USCS (D 2487)= AASHTO (M 145)=
D90= D85= D60=D50= D30= D15=D10= Cu= Cc=
Remarks
* (no specification provided)
004
CLIENT:
DATE:
Date Received:
Lab Technician:
REMARKS:
B-1(S-3) 5'-7'
October 31, 2018
10-22-18 & 10-25-18
Rachel CannonSampled By:
Date Sampled:
Summary of Atterberg Limits
Boring # Sample DepthMoisture
Content
USCS
Classification
Liquidity
IndexLiquid Limit Plastic Limit
Plasticity
Index
ASTM D4318
Town of Durham, NH
10/25/2018
Ted Moody Reviewed By: Jeff Young
Communications Tower
Beach Hill Rd.
Durham, NH
18-15-089-001CREPORT #:
PROJECT:
ML12.10% 22 NP - -
_________________________________________________________________________________________________
19 Dover Street | Dover, NH 03820 | Phone: (603) 749-1841 | www.consultjtc.com
www.consultjtc.com
APPENDIX F: SITE PHOTOGRAPHS PAGE
www.consultjtc.com
BEECH HILL COMMUNICATION TOWER BEECH HILL ROAD DURHAM NEW HAMPSHIRE
Site, To West
Set up on B-1, To South
Drilling activities, Typical
Sample collection, Typical
Set up on B-2, To North
Sample of Glacial Till, Typical
SITE PHOTOGRAPHS