Geotechnical Consultants

Embed Size (px)

Citation preview

  • 7/27/2019 Geotechnical Consultants

    1/34

    This electronic communication and its contents may containconfidential information which is the exclusive property ofGeotechnical Consultants, Inc. The recipient(s) assumes allliability arising from any alteration, misuse or unauthorizeddistribution. If you have received this information in error,please notify the sender immediately.

    614.895.140Fax: 614.895.117www.gci2000.co

    720 Greencrest DrivWesterville, Ohio 43081-490

    Westerville, Ohio Youngstown, Oh

  • 7/27/2019 Geotechnical Consultants

    2/34

    SUBSURFACE EXPLORATION

    AND PRELIMINARY

    GEOTECHNICAL ENGINEERING REPORT

    PROPOSED

    FAIRFIELD COUNTY JUSTICE CENTER-MSMJ SITE

    342 WEST WHEELING STREET

    LANCASTER, OHIO

    Prepared by:

    Geotechnical Consultants, Inc.

    Prepared for:

    The Fairfield County Commissioners

    Wachtel & McAnally Architects/Planners

    GCI Project No. 11-G-16121

    June 10, 2011

    Main Offic720 Greencrest Driv

    Westerville, Ohio 43081-490614.895.140

    Fax: 614.895.117www.gci2000.co

    Branch Offices

    Youngstown 8433 South Ave. Bldg. 1, Suite 1 Youngstown, OH 44514 (330) 965-1400 Fax (330) 965-14

  • 7/27/2019 Geotechnical Consultants

    3/34

  • 7/27/2019 Geotechnical Consultants

    4/34

    TABLE OF CONTENTS

    INTRODUCTION......................................................................................................................................................1

    SITE HISTORY AND PROJECT DESCRIPTION..................................................................................................2

    SUBSURFACE CONDITIONS ................................................................................................................................3

    LABORATORY.........................................................................................................................................................5

    ANALYSIS AND CONCLUSIONS.........................................................................................................................5

    GEOTECHNICAL EVALUATION

    BUILDING SUPPORT

    SEISMIC FACTOR

    EXCAVATIONS AND GROUNDWATER

    PAVEMENTS

    GENERAL SITE PREPARATION AND EARTHWORK

    CONSTRUCTION MATERIALS ENGINEERNG AND TESTING ...................................................................11

    FINAL ......................................................................................................................................................................12

    APPENDIX FOLLOWING PAGE NUMBER.......................................................................................................12

    General Notes for Soil Classification

    General Site Location Map (DeLorme. Street Atlas USA 2011)

    USGS Topographic Map 1992 Lancaster, Ohio Quadrangle2009 Aerial Photograph Fairfield County Auditor

    Sanborn Fire Insurance Map (May, 1893)

    Boring Location Plan

    Table 1: Summary of Encountered Subsurface Conditions

    Test Boring Logs

    Table 2: Laboratory Test Results

    ODNR Water Well Logs (2)

  • 7/27/2019 Geotechnical Consultants

    5/34

    1

    INTRODUCTION

    As requested and authorized by Mr. Kent Staker of Wachtel & McAnally Architects/Planners, Inc on

    behalf of the Fairfield County Commissioners, Geotechnical Consultants, Inc. (GCI) has performed a

    subsurface exploration for a proposed Fairfield County Justice Center building at 342 West Wheeling

    Street in Lancaster, Ohio. Prior to drilling, the client provided us with a Scheme E site plan, dated

    6/5/2010, that showed the proposed and existing building footprints and six requested boring locations.

    Our study consisted of six standard penetration test borings performed at or near the suggested locations

    within the proposed structure footprint and limited laboratory testing. A sketch showing the

    approximate boring locations and copies of the boring logs are included in the appendix of this report.

    Test hole locations were established from existing site landmarks and general site features. Topographic

    information was not shown on the plan provided, and GCI did not survey the ground surface elevations

    at the boring locations.

    The intent of this study is to evaluate subsoil conditions and offer preliminary design recommendations

    relative to foundations, pavements, and earthwork. This report is issued prior to the receipt of final

    foundation and grading plans. We would suggest that this office review these plans to provide

    additional recommendations.

    This preliminary report has been prepared for the exclusive use of the Fairfield County Commissioners,

    Wachtel & McAnally Architects/Planners and their consultants for specific application to the proposed

    Fairfield County Justice Center to be located at 342 West Wheeling Street in Lancaster, Ohio in

    accordance with generally accepted soil and foundation engineering practices. No warranty, expressed

    or implied, is made.

  • 7/27/2019 Geotechnical Consultants

    6/34

    2

    SITE HISTORY AND PROJECT DESCRIPTION

    The site is comprised of two irregular-shaped parcels totaling about 2.5 acres in size. The property is

    bordered by retail buildings and Lincoln Avenue (US Route 22) to the south, the tree-lined Hocking

    River in its current alignment to the west, West Wheeling Street to the north, and a gas station to the

    northeast. South Memorial Drive (U.S. Route 33) forms the east side boundary. The roadway was

    constructed over the abandoned Ohio Canal at some time between 1893 and 1899; it was known as

    Front Street at that time. A foundry and a glass plant were once located east and southeast of the site on

    the east side of Route 33. A general site location map is appended to this report.

    Review of historic (1889 through 1929) Sanborn maps of the area indicates the site has seen prior

    development in the form of several buildings used for a slaughter house from at least 1889 to 1919. The

    1929 map shows a foundry on the parcel. The Hocking River once crossed through the site, entering the

    property from the north and then curving to the west; it appears on Sanborn maps dated 1899 and

    earlier and is designated as the old channel (see attached copy of the 1893 map). We do not know

    when the river was straightened and realigned to the west end of the site. At some point, fill was placed

    on the site possibly in connection with the channel rerouting or as a means of dealing with spoils from

    the on-site or adjacent foundries and glass plant. Review of the 1992 Lancaster, Ohio USGS

    topographic quadrangle (see attached copy) shows grades ranging from elevation 833 feet near the east

    site boundary to below elevation 820 feet to the west by the Hocking River. It also shows a building to

    the east of the existing jail that no longer is present on the site; presumably the existing concrete

    pavement in this area is the old floor slab, which could account for the significant spalling we observed

    as it would have consisted of non-air-entrained concrete.

    According to the Fairfield County Auditor record, a supermarket was constructed in the northwest

    portion of the site in 1955. In 1994, this structure was converted to the current minimum security

    county jail facility. The client indicated that they believe the existing structure is supported on shallow

  • 7/27/2019 Geotechnical Consultants

    7/34

    3

    strip footings and has been subject to some minor settlement that has not impaired its functionality.

    Conversation with a deputy at the site indicated that the west building wall and adjacent slab were

    jacked up about 1 to 2 inches through use of grout injections about two years ago, but he repeated that

    functionality was not impaired prior to that repair. There is concrete pavement at the north end of the

    site, with asphalt pavement covering the rest of the parcel (see cover photograph). We visually judged

    the pavements to be in fair to poor condition.

    The project consists of constructing a one-story, slab-on-grade prison building with a mezzanine in the

    central portion of the property. The exterior walls will be 8-inch thick reinforced concrete masonry

    block with a 4-inch veneer, and the slab will be an 8-inch precast with a 2-inch topping. The structural

    engineer (Mr. Ray Blinn of Eeman & Blinn, Inc.) provided the following building load information:

    exterior wall loads will vary from 5.48 to 6.38 kips per lineal foot in the two-story portion and be about

    3.03 kips per foot for one-story walls; column loads in the two-story portion will vary from 78 to 89

    kips and range from 20 to 30 kips in the one-story area. He estimated about 80% of the loads will be

    dead loads. A grading plan was not available at the writing of this report, but we anticipate minor grade

    changes (i.e., 2 feet or less of cuts and fills) will be required to achieve a level building pad and regrade

    pavement areas. We understand that at least some of the existing building will likely be demolished as

    part of the project.

    SUBSURFACE CONDITIONS

    GCI mobilized a truck-mounted drill rig (CME-45 with an automatic sampling hammer) to the site on

    March 2, 2011 and drilled six standard penetration test borings at or near the requested locations to

    obtain a generalized profile of existing subsurface conditions. Borings B-1 through B-6 were drilled

    within the proposed building footprint to depths of either 25 or 30 feet. Specific boring information can

    be obtained from the boring logs in the appendix. We summarize our boring findings below and in the

    attached Summary of Encountered Subsurface Conditions table.

  • 7/27/2019 Geotechnical Consultants

    8/34

    4

    Surface Cover

    The borings were drilled in existing pavement areas. Northern borings B-1 and B-2 encountered a rigid

    section consisting of 3 to 4 inches of concrete over 3 inches of stone base. The remaining borings found

    1 to 3.5 inches of asphalt cast directly on granular fill rather than stone base.

    Existing Fill

    The six borings encountered existing fill below the pavement section, extending to depths ranging from

    9 feet to 17.5 feet below existing grade at the boring locations. The fill consisted primarily of dark

    brown/black foundry sand (which we would classify as a non-plastic silty fine to medium sand - SM)

    with varying but generally minor amounts of slag, glass, and brick. Occasional zones of slightly plastic

    silty, clayey sand (SC-SM) or low plasticity clayey sand (SC) were encountered within the fill.

    Standard penetration N-values recorded in the fill ranged from 0 to 13 blows per foot (bpf), commonly

    from 2 to 8 bpf indicating the fill was loose to very loose in cohesionless density.

    Natural Soils

    We found natural cohesive soils, varying from non-organic to organic and from moderate to high

    plasticity, immediately below the fill in the five of the six boring locations (east boring B-3 encountered

    more granular natural soils below the deep fill cover at 17.5 feet below the surface). The cohesive soils

    were alluvial deposits associated with the former Hocking River channel. In southeast boring B-4, we

    encountered a non-organic, low to moderate plasticity brown lean clay (CL) that was medium stiff. The

    other four borings (B-1, B-2, B-5 and B-6) drilled in the north and west portions of the site found

    heavily stained lean to fat clays (CL to CH/OL to OH) with varying amounts of organics and shells that

    were very soft (0 to 2 blows per foot commonly recorded).

    The alluvial clays were underlain by a saturated granular formation that was encountered at depths

    ranging from 12.5 feet (B-4) to 24.5 feet (B-5) below existing grade at the boring locations. These

    deposits varied from slightly plastic silty, clayey sand with gravel (SC-SM) to non-plastic silty sand

    with gravel/poorly graded sand with silt and gravel (SM/SP-SM). Trace shells were noted at the top of

    the granular formation in B-1 and B-6. Standard penetration testing showed the sands to be loose to

    medium dense. With the exception of B-3, the borings terminated within sand at depths of 25 or 30 feet.

    East boring B-3 encountered a gray glacial till formation below the upper silty clayey sand with gravel

    formation at a depth of 26 feet below the surface. Till is a primarily cohesive material comprised of

    varying amounts of sand and gravel cemented in a lean clay matrix that generally exhibits low to moderate

    plasticity. We visually classified the soil as gray sandy lean clay with gravel (CL) under the Unified

    Classification System. Occasional thin layers of silty sand with gravel (SM) were noted within the

    otherwise cohesive formation. The gray till was very stiff in cohesive consistency. We terminated B-3 in

    the gray till at a depth of 30 feet below the surface.

    Bedrock

    Bedrock was not encountered in the borings performed (maximum drilled depth of 30 feet). The USDA

    Soil Survey of Fairfield County maps the site as being in an area with bedrock consisting of sandstonewith interbedded shale. We estimate the depth to top of bedrock to be in excess of 100 feet, based on

    review of logs for water wells in the site vicinity that are registered with ODNR (see attached copies of

    two of those logs).

    Groundwater and Soil Moisture Conditions

    We encountered water seepage in the six borings at the time of drilling. In B-2, the groundwater was

    found within the upper portion of the fill at a depth of 3 feet below the surface; the water level dropped

    to 8 feet by the completion of drilling. Seepage was encountered within the lower portions of the fill

    mass in borings B-1, B-3, and B-6 at depths of 7.5 to 9.5 feet below the surface; by the completion of

  • 7/27/2019 Geotechnical Consultants

    9/34

    5

    drilling, the water levels were recorded at depths of 9.5 to 10 feet below grade in these three boreholes.

    In B-5, groundwater was observed at a depth of 12.5 feet below the surface in the upper portion of the

    natural dark gray organic clay layer; the water level remained constant at the encountered depth in that

    borehole at completion. B-4 found seepage within the underlying natural sand formation at a depth of

    17.5 feet, with the level rising about a foot in the borehole by the end of drilling.

    We generally characterize the retrieved fill samples as moist, with some very moist to wet zones where

    seepage was encountered within the fill. The natural stained clays and underlying sand deposits were

    typically described as wet.

    Note that groundwater levels and moisture conditions can vary with changes in season and precipitation. It

    is likely that the underlying sand formation is hydraulically connected to the adjacent Hocking River.

    LABORATORY TESTING

    We determined the natural moisture content of the first split spoon sample of natural soils obtained in

    each boring (from depths of 13.5 to 15 in five of the borings, from 18.5-20 in B-3). East/southeast

    borings B-3 and B-4 samples were found to have natural moisture contents of 13.5% and 7.7%,

    respectively, at the time of drilling. The other four samples consisted of stained clays that had much

    higher moisture contents, ranging from 31.9% in B-2 to 57.5% in B-1. We subjected the two samples

    with the highest moisture content, B-1 and B-5, to loss-on-ignition testing. Results indicated respective

    organic contents of 9.2% and 4.3%. From a geotechnical view point, we consider organic contents of

    above 4% to 5% to be significant.

    ANALYSIS AND CONCLUSIONS

    GEOTECHNICAL EVALUATION

    The borings encountered deep deposits of loose fill over the entire building pad. Soft, organic Hocking

    River channel deposits underlie the north and west portions of the proposed footprint, but may not be

    present in the southeast part. These subsoil conditions will have a significant impact on foundation and

    floor slab options, and pavement design to a lesser extent due to both total and differential settlement

    concerns. We discuss these issues and other concerns below.

  • 7/27/2019 Geotechnical Consultants

    10/34

    6

    The existing structure in the northwest corner of the site was built in 1955. It reportedly was constructed

    using conventional shallow spread footings and slab-on-grade and has undergone some settlement but of

    low enough magnitude (1 to 2 inches) to not impair its functionality. The proposed new justice center

    building will be located southeast of the existing building and over the old Hocking River channel. Our

    borings showed the existing fill in this area to consist primarily of a silty fine to medium sand in loose to

    very loose condition that will settle under applied new fill and building loads. Additionally, four of our

    borings encountered very soft natural alluvial clays with varying amounts of organics and shells. These old

    channel deposits combined with the loose fills pose a significant differential settlement potential for the

    proposed construction. Additionally, the proposed structural loads of the new jail will be about double

    those of the existing facility (and therefore will induce a larger magnitude of settlement), and the new

    building will have reinforced concrete masonry walls, which typically are not flexible enough to accept

    large movements without cracking. Based on our borings and despite the reported good

    performance of the adjacent existing structure, we feel the site fills and soft clays are not suitable for

    support of shallow foundations or conventional slab-on-grade for the proposed construction.

    To mitigate settlement concerns, we recommend that the structure be supported on deep foundations that

    extend through the existing fill and soft, natural alluvial clay deposits to bear in the underlying non-

    organic, medium dense to dense sand and gravel or stiff glacial till soils. Based on the soil profile and

    anticipating that groundwater may typically be encountered at depths of 8 to 10 feet below the surface, we

    suggest using auger-cast piles for the deep foundations. Auger-cast piles are efficient in deep sand and

    gravel deposits as they gain capacity primarily due to skin friction, and groundwater does not interfere with

    their installation. Slab support would remain a concern, unless the slab is also supported on these

    elements. If this option is selected, we recommend that additional final phase borings be performed to

    finalize design recommendations. Final phase borings should extend to deeper depths on the order of 60

    feet to 70 feet to gather sufficient information to analyze auger-cast piles.

  • 7/27/2019 Geotechnical Consultants

    11/34

    7

    Another possible option would be to modify/strengthen the site soils using stone columns such as

    Geopiers. Geopiers are closely spaced rammed stone columns which, when properly designed and

    installed, will improve soil bearing conditions enough to allow the use of conventional spread footings and

    slab-on-grade. In our opinion, soil bearing capacities on the order of 4.000 psf to 5,000 psf would be

    feasible for the site when properly fortified with stone columns. We recommend that these elements

    extend through the fill and soft natural clays to bear in the sand formation. Geopiers are a proprietary

    system which would be designed by Geopier, Inc.

    Caissons (drilled piers) could be considered for the deep foundation element, but they would require casing

    to prevent cave-in of the loose granular fill soils and careful groundwater control. Groundwater will be

    encountered near the fill/natural soil interface, which will necessitate the use of casing within the natural as

    well as the fill site soils. We also anticipated the need to use a tremie during concrete placement. Caissons

    are a less preferred option due to the concern of their being subject to excessive post-construction

    downdrag forces and the potential for bearing soils to heave during construction.

    Settlement in pavement areas remains a concern regardless of which foundation system is selected,

    although a flexible pavement system would be much more forgiving when compared to building

    elements. This is evidenced by the performance of the existing pavement. The need for periodic

    maintenance as movements occur should be anticipated. We do recommend that existing asphalt be

    stripped in proposed pavement areas, and the exposed subgrade carefully proofrolled to delineate

    soft/loose soils requiring stabilization prior to placement of new fill or pavement sections. Unless

    properly milled, stripped asphalt will not be suitable for re-use as fill. If milled, asphalt fill should not

    be placed within the proposed building pads.

    We understand that the existing building may be partially or totally demolished as part of the project.

    Additionally, the existing concrete pavement east of the present jail may in fact be an old building slab

  • 7/27/2019 Geotechnical Consultants

    12/34

  • 7/27/2019 Geotechnical Consultants

    13/34

    9

    SEISMIC FACTOR

    The borings at the site revealed a generalized profile consisting of loose fill overlying very soft to

    medium stiff natural clay deposits overlying medium dense sand and gravel. In accordance with the

    Ohio Building Code, we would estimate the site as a Site Class E soft soil profile.

    EXCAVATIONS AND GROUNDWATER

    Bedrock was not encountered in the borings (up to 30-foot drilled depths) and is not anticipated to

    impact slab-on-grade, foundation, and utility excavations within the drilled boring depths. The site fill

    and natural soils can be excavated using conventional hydraulic equipment. The site fills are loose to

    very loose, and will need to be braced or appropriately sloped to maintain sidewall stability. All

    excavations must be in accordance with federal, state, and local guidelines (i.e., OSHA

    requirements).

    Groundwater was initially encountered in the six borings at depths ranging from 3 to 17.5 feet below the

    surface and was measured at depths of 8 to 16.5 feet at the completion of drilling operations. As such,

    we anticipate that groundwater will be encountered during installation of the recommended deep

    foundation elements, probably near the fill/natural soil interface. Significant flows are likely as we

    believe the underlying sand and gravel formation is hydraulically connected to the adjacent Hocking

    River. If water is encountered in shallow utility excavations within the existing fills, we recommend the

    trench be dewatered to allow for backfilling in dry conditions; portable sump pumps and working mats of

    crushed stone may be able to handle these more minor groundwater flows.

    PAVEMENTS

    The site contains loose fill deposits, as well as soft/organic natural soils in some areas of the property;

    these soils will settle and may cause premature pavement breakup/drainage problems to some degree.

    As such, we do not recommend installation of rigid sections as the concrete may crack excessively

  • 7/27/2019 Geotechnical Consultants

    14/34

    10

    should movements occur. Provided the site is properly prepared, it is our opinion that a flexible

    pavement system can be used for site development, with the expectation of periodic maintenance being

    required. We recommend that existing asphalt be stripped from proposed pavement areas. Subgrades

    should be carefully proofrolled to identify soft/loose soils. These areas should be stabilized prior to

    additional fil placement or new pavement construction. Particular attention should be paid to areas

    where the existing pavement experienced distress. Installation of a biaxial geogrid directly below the

    base course aggregate would mitigate the effects of differential settlements by helping the pavement

    section to float intact over the fill deposits, and their use should be considered in design.

    Design of a site-specific pavement design is beyond the scope of this preliminary study; this would

    require laboratory testing and we would need design traffic information. For this type of project, GCI

    would normally recommend a typical minimum pavement section of 3 inches of asphalt over 8 inches of

    aggregate base in light-duty automobile parking areas. Heavy-duty areas subject to occasional truck

    traffic would consist of a minimum of 4 inches of asphalt over 10 inches of base aggregate.

    Providing adequate sub-base drainage is important to future pavement performance. Finger drains

    connecting to weep-holes in all inlets, proper grading of pavement sub-grades and surfaces to shed run-

    off, and under-drains in any pavement swales are suggested sub-base drainage methods and should be

    used by the site civil engineer.

    GENERAL SITE PREPARATION AND EARTHWORK

    As a general approach to site preparation, we recommend the following:1. Where the existing structure is to be demolished, completely remove below-grade structural

    elements, including foundations, slabs, and walls. Similarly, within the proposed building pad

    limits plus 10 feet beyond the walls, remove the existing concrete pavement and any old below-

    grade structural elements from the former building. Properly backfill the resulting excavation.

    Concrete rubble may be incorporated in structural fills if first broken into pieces no larger than 4

    inches in maximum dimension and thoroughly mixed with site soils to avoid creation of voids.

  • 7/27/2019 Geotechnical Consultants

    15/34

    11

    If properly crushed to meet gradation requirements, the concrete may be used as new pavement

    base material or underslab gravel.

    2. Existing utilities that cross the proposed building footprint should be rerouted, the old line(s)removed, and the excavation properly backfilled. The ends of abandoned pipes outside the

    building footprint should be properly capped.

    3. Remove existing asphalt. Asphalt may not be re-used as structural fill unless properly milled.We do not recommend asphalt be incorporated in any building pad fills.

    4. Strip surface vegetation and topsoil, if present within proposed building or pavement areas.Topsoil may not be re-used as structural fill.

    5. Thoroughly proofroll the stripped subgrades in pavement areas prior to filling or finish gradingto identify unstable areas. Particular attention should be paid to areas where the existing

    pavements experienced distress. Stabilize as needed. Unstable subgrades below structural slabs

    do not need to be stabilized. GCI should be contacted to observe proofrolling procedures.

    6. Place and compact new fill in loose lifts (8 inches thick or less) to at least 98% optimumStandard Proctor dry density (ASTM D-698). Lift thickness should be reduced to 6 inches in

    confined areas where compactive effort is reduced. Cohesive site soils will be best compacted

    with a sheepsfoot roller, while cohesionless soils will be best compacted with a vibratory,

    smooth drum roller. The moisture content of the fill soils should be controlled to within 3% of

    optimum moisture content. Depending on the time of year of earthwork, moisture adjustment of

    the fill may be required to achieve compaction. Off site borrow should be reviewed by GCI

    prior to use.

    7. Excavate through the prepared building pad for foundations. Additional borings are neededto design the recommended extended foundation system.

    8. Slab and pavement subgrades should be compacted to a flat, smooth, stable surface with a flatdrum compactor prior to placement of aggregate base. Subgrade preparation during wet

    weather may require the use of an engineered fabric or geogrid.

    CONSTRUCTION MATERIALS ENGINEERING AND TESTING

    GCI provides full service construction materials engineering and testing services. For project continuity

    throughout construction, we recommend that GCI be retained to observe, test, and document:

    earthwork procedures (stripping, fill placement, compaction, utility trench backfill, etc.) foundation and slab preparation (proof-rolling, excavations, undercuts, etc.), concrete placement (footings, structural concrete, slabs) and compressive strength testing, and structural steel (welds, bolts, etc.).

    The purpose of this work is to assess that the intent of our recommendations is being followed and to make

    timely changes to our recommendations (as needed) in the event site conditions vary from those

  • 7/27/2019 Geotechnical Consultants

    16/34

    12

    encountered in our borings. Please contact our field department to initiate these services.

    FINAL

    This report is preliminary and not sufficient for final design of the recommended extended foundation

    system. Additional deeper borings will need to be performed.

    We recommend that GCI be provided the opportunity for general review of the final foundation and

    grading plans and project specifications in order to verify that recommendations contained in this report

    have been properly interpreted and implemented. In the event that any changes in the nature of the

    development are planned, conclusions and recommendations contained in this report shall not be

    considered valid unless changes are reviewed and conclusions of this report are modified or verified in

    writing. The recommendations contained in this report are the opinion of Geotechnical Consultants,

    Inc. based on the subsurface conditions found in the borings and available development information.

    The site has seen prior development and was located within the floodplain of the Hocking River prior to

    its realignment and the subsequent placement of substantial amounts of fill across the property. As such,

    the nature and extent of variations between borings may not become evident until construction. If

    variations then appear evident, it will be necessary to re-evaluate the recommendations of this report.

    This report is prepared for design purposes only and is not considered sufficient to prepare an accurate

    bid document.

    GCI appreciates the opportunity to work with you on this project and we hope to continue service for

    the project through construction. If you have any questions or the need for additional services, please

    call.

  • 7/27/2019 Geotechnical Consultants

    17/34

    APPENDIX

  • 7/27/2019 Geotechnical Consultants

    18/34

    GENERAL NOTES FOR SOIL SAMPLING AND CLASSIFICATIONS

    BORINGS, SAMPLING AND GROUNDWATER OBSERVATIONS:"#$%%$&' (&) *(+,%$&' -.#. /0&)1/2.) $& (//0#)(&/. -$23 ,#0/.)1#.* '.&.#(%%4 #./0'&$5.) (&) (//.,2.) (* *2(&)(#) +.230)* 06.7,%0#(2$0& 06 *18*1#6(/. /0&)$2$0&*9 :3. 80#$&'* -.#. )#$%%.) 1*$&' ( 2#1/;9? 20 ?9@ 6..29 :3. *2#(2$6$/(2$0& %$&.* 0& 23. %0'*#.,#.*.&2 23. (,,#07$+(2. 801&)(#4 8.2-..& *0$% 24,.* (2 23(2 *,./$6$/ %0/(2$0& (&) 23. 2#(&*$2$0& +(4 8. '#()1(%9

    A(2.# %.=.%* -.#. +.(*1#.) (2 )#$%% %0/(2$0&* 1&).# /0&)$2$0&* *2(2.) 0& 23. %0'*9 :3$* )(2( 3(* 8..& #.=$.-.) (&) $&2.#,#.2(2$0&*+(). $& 23. 2.72 06 23. #.,0#29 B%1/21(2$0&* $& 23. %.=.% 06 23. '#01&)-(2.# +(4 0//1# )1. 20 023.# 6(/20#* 23(& 230*. ,#.*.&2 (2 23.2$+. 23. +.(*1#.+.&2* -.#. +().9

    :3. C2(&)(#) D.&.2#(2$0& :.*2 EFC:GH $&/3.*12$%$5$&' ( >M@ ,01&) 3(++.# 6#.. 6(%%$&' N@ $&/3.*9 :3. &1+8.# 06 8%0-* #.O1$#.) 20 )#$=. 23. *(+,%.# .(/3 I $&/3.* 06,.&.2#(2$0& (#. #./0#).)9 :3. *1++(2$0& 06 23. 8%0-* #.O1$#.) 20 )#$=. 23. *(+,%.# 60# 23. 6$&(% >K $&/3.* 06 ,.&.2#(2$0& $* 2.#+.)23. C2(&)(#) D.&.2#(2$0& P.*$*2(&/. EQJ9 C0$% ).&*$24R/0&*$*2.&/4 $& 2.#+* 06 23. Q

  • 7/27/2019 Geotechnical Consultants

    19/34

    GENERAL NOTES FOR SOIL SAMPLING AND CLASSIFICATIONS

    PARTICLE SIZE DEFINITION CONSTITUENT MODIFIERS

    f01%).#*S g>KZ_088%.*S NZ 20 >KZ :#(/. T.** 23(& ?Xc#(=.%S _0(#*.S NRMZ 20 NZ B.- ?@X

    B$&.S Q09 M ENR>IZJ 20 NRMZ T$22%. >?@ EK9@++J 20 Q09 M EM9`?++J C0+. N@@ EK9@++J G0*2%4 ?@@@XB$&. Q09 K@@ E@9@`M++J 20 Q09 M@ E@9MK?++J

    C$%2 h _%(4 i@9@`M++j /%(**$6$/(2$0& 8(*.) 0& 0=.#(%% ,%(*2$/$24j $& '.&.#(%/%(4 ,(#2$/%.* i@9@@?++9

    ASTM/UNIFIED SOIL CLASSIFICATION AND SYMBOL CHART

    _LFPCaMM`>

  • 7/27/2019 Geotechnical Consultants

    20/34

  • 7/27/2019 Geotechnical Consultants

    21/34

  • 7/27/2019 Geotechnical Consultants

    22/34

  • 7/27/2019 Geotechnical Consultants

    23/34

  • 7/27/2019 Geotechnical Consultants

    24/34

  • 7/27/2019 Geotechnical Consultants

    25/34

  • 7/27/2019 Geotechnical Consultants

    26/34

  • 7/27/2019 Geotechnical Consultants

    27/34

  • 7/27/2019 Geotechnical Consultants

    28/34

  • 7/27/2019 Geotechnical Consultants

    29/34

  • 7/27/2019 Geotechnical Consultants

    30/34

  • 7/27/2019 Geotechnical Consultants

    31/34

  • 7/27/2019 Geotechnical Consultants

    32/34

  • 7/27/2019 Geotechnical Consultants

    33/34

  • 7/27/2019 Geotechnical Consultants

    34/34