Upload
others
View
0
Download
0
Embed Size (px)
Citation preview
52E18NW9492 2.5474 ECHO BAY010
GEOPHYSICAL REPORT
ELECTROMAGNETIC ft MAGNETIC SURVEYS
SHOAL LAKE PROJECT - ONTARIO
GRIDS 5A, 5B, 6E S 7C
RECEIVEDl 5 1983
MINING LANDS SECTION
A.P. Pryslak April, 1983
A. Introduction
This report deals with results of geophysical surveys conducted over 4 grids situated in the Shoal Lake area of Northwestern Ontario. Two grids are situated in Glass Township, north of Clytie Bay of Shoal Lake. These surveys are part of a follow-up program to an INPUT survey completed by Questor Surveys Limited in the fall of 1981 and are base-metal targets. Grids 6E and 7C are part of a regional exploration program for Cameron Island type gold mineralization.
Access to the properties situated around Shoal Lake is via the Rush Bay Road which connects Clytie Bay of Shoal Lake with the Trans-Canada Highway.
B. Regional Geology
The metavolcanic-metasedimentary sequence forms part of the Wabigoon Subprovince, Superior Province of Archean Age. The O.G.S. Compilation Map 2443 - Kenora - Fort Frances Sheet illustrates the major lithological units for the Shoal Lake area. Detailed geological mapping by Davies gives further information on the geology of the Shoal Lake area.
C. Linecutting
Grids were established over the target areas in January and February, 1983. Lines were spaced at 400-foot intervals and stations were picketed at 100-foot intervals along the lines.
D. Geophysical Surveys
All grids were surveyed using Apex Parametrics Max-Min II units at a frequency of 444 Hz with 400-foot coil separation. Readings were taken at 100-foot station intervals, except in areas of anomalous readings where this was reduced to 50-foot intervals.
21...
- 2 -
The magnetic survey utilized the Geometrics G-816 unit, serial No.450. Again, readings were at 100-foot intervals, except for areas of anomalous activity where it was reduced to 50-foot stations. All grids were surveyed by the magnetometer.
The VLF-EM survey was carried out over grid 7C. The instrument used for the survey was a Geonics EM 16 unit utilizing the Culter, Maine station.
E. Property 5 - Grid A
(i) Geology - Davies 1 mapping shows that the grid area is
underlain by a sequence of felsic and mafic metavolcanics intruded by minor gabbro sills.
(ii) H.L.E.M. Survey Results - A strong long-trending conductor lies to the north of the Base Line between lines 12+OOE and 48+OOE. The central and east portions of this feature display widths of 75 to 175 feet or it may also be interpreted as two separate but narrow conductors. The conductors are correlative with a weak positive magnetic anomaly. The amplitude of the magnetic response varies from several tens of gammas to approximately 600 gammas on line 20+OOE. This conductor was tested by Selco a number of years ago and was identified as graphic tuff-sediments with minor pyrrhotite, pyrite and sphalerite.
Two short conductors lie approximately 1000-feet to the north of the long conductor. The conductivity is variable along the strike length of both features. The most easterly conductor, which lie south of a small lake, is correlative with a weak magnetic anomaly in the magnetude of 200 gammas. This conductor would appear to lie along the contact of felsic pyroclastics and mafic metavolcanic flows.
- 3 -
The easterly conductor has no apparent correlation with anomalous magnetic responses and is likely due to graphitic tuffs or sediments.
(iii) Magnetometer Survey Results - A narrow positive magnetic anomaly extends from co-ordinate 14N - 40E to 12N - 52E. Elsewhere, the magnetic susceptabilities are low and subtely reflect the trend of lithological units. Several isolated high peaks may reflect errors in reading.
(iv) Recommendations - Minor base-metal mineralization is known to occur in the area just outside the grid. Davies' mapping shows that outcrops over the grid area are abundant. Therefore, it is recommended that the grid be mapped and that particular attention be paid to locating the source of the conductors. Testing of conductors by diamond drilling would be dependant upon results of these geological investigations.
F. Property 5 - Grid B
(i) Geology - Davies 1 mapping shows that the north part of the grid is underlain by felsic pyroclastics and that the south part is comprised of mafic metavolcanic flows.
(ii) H.L.E.M. Survey Results - Two conductors have been identified by the survey. The conductivity of both features varies from weak to moderate along the strike. The north conductor is strongest at the west while the south conductor has its strongest response at the east end.
Both conductors have moderate magnetic signature but this is also variable along the strike of the conductors.
. 4 -
(ill) Magnetometer Survey Results - Moderate positive magnetic anomalies are elongated in an east-west direction and display stratigraphic trends. The variation in magnetic response within the mafic volcanic sequence probably is due to minor differences in flow units.
(iv) Recommendations - The conductors should be prospected during the summer months to find their possible source. If these are not located, testing by diamond drilling is recommended.
G. Property 6 - Grid E
(i) Geology - Davies 1 mapping shows this area to be underlain by the lower tholeiitic volcanic sequence. The south part of the grid is occupied by rocks of the upper calc-alkaline felsic volcanics, with the contact being under the lake and approximately parallel to the shore in the west part of the grid. The southeast part of the grid is underlain by intrusive rocks of the Canoe Lake Stock.
(ii) H.L.E.M. Survey Results - A total of six conductors were identified by the survey and 3 were subsequently tested by diamond drilling. All conductors are comprised of chert- pyrrhotite units intraformational to mafic volcanic flows. Conductor No.l - Co-ordinate 14N, 4+OOE to 12N, 20+OOE.
Weak to moderate conductor with a weak flanking magnetic anomaly. Tested by diamond drilling on L8E, 12N.
Conductor No.2 - Co-ordinate 2N, 4+OOE to IN, 28+OOE.
A strong magnetic response flanks the conductor to the south. This is correlative with a mafic- ultramafic flow versus more normal basalts situated north of the conductor which have a low magnetic signature.
- 5 -
Conductor No.4 - Co-ordinate 7N, 48+OOE, to ION, 68+OOE. This conductor was tested by diamond drilling on L52E and is due to chert-pyrrhotite.
Conductor No.5 - Co-ordinate 85, 60+OOE.This strong, single line feature is situated near the contact of the volcanics and the Canoe Lake Stock. It was tested by diamond drilling and is due to an intraformational unit of chert-pyrrhotite.
Conductor No.6 - Co-ordinate 2S, 0+00.This weak conductor with high quadrature response is likely due to minor chert-sulphide bands associated with the transition zone between the
tholeiitic volcanics and the calc-alkaline volcanics. This transition zone was tested by drilling on line 8+OOE and intersected such mineral ization.
(iii) Magnetometer Survey Results - Positive magnetic features are
related either to chert-pyrrhotite zones or magnetite-bearing ultramafic units. The areas of magnetic response are occupied either by normal basalt flows in the north part of the grid or by the calc-alkaline sequence in the south part.
(iv) Recommendations - Conductor No.2 is situated in an area of topographic high and is likely to be exposed in outcrop. This should be checked and sampled for gold mineralization.
H. Property 7 - Grid C
(i) Geology - This grid lies east of Clytie Bay and north of Bag Bay of Shoal Lake. Davies 1 mapping shows that the east end of the grid is underlain by intrusive rocks of the Canoe Lake Stock. Mafic volcanics, gabbro and ultramafic rocks
occupy the central part of the grid and felsic pyroclastics are exposed along the protrusion of the shoreline. , ,
- 6 -
The above volcanic sequence is interpreted to be stratigraphically equivalent to the sequence in the vicinity of Cameron Island.
The Crown Point mine is located within the Canoe Lake granodiorite. Gold mineralization here is associated with quartz veins. :
In 1968, Olympia Mines carried out diamond drilling on a sulphide zone situated east of the base line in the central part of the property.
(ii) H.L.E.M. Survey Results - Three strong bedrock conductors have been identified by this survey. These fall within the mafic- ultramafic volcanic sequence. Drilling by Olympia Mines identified one of the conductors as due to chert-pyrrhotite with minor nickel and copper values. It is uncertain if the drilling tested only one or both of the two parallel conductors situated east of the base line. The third conductor, lying between the base line and the shore line is likely similar in nature to that encountered by the drilling.
A weak conductor situated at the east end of the grid between lines 261N and 269N appears to conform with the contact of the volcanic sequence and the Canoe Lake Stock.
A weak, single line response occurs at co-ordinate 65E, 245N. The quadrature response is greater than the in-phase, suggesting a lake bottom sediment response.
(iii) Magnetometer Survey Results - A zone of positive magnetic response, approximately 600-feet wide, extends from the area north of the base line on 237+OON to the area south of the base line on 281+OON. This magnetic feature identifies a sequence of ultramafic flows and pyrrhotite-bearing cherts and basalts.
- 7 -
The area of Tow magnetic response along the west portion of the grid correlates with felsic metavolcanics and the low magnetic response to the east of the positive magnetic anomaly correlates with the granodiorite of the Canoe Lake Stock.
(iv) VLF-EM Survey Results - Numerous conductors have been identified by this survey. The VLF survey shows that the two HLEM conductors situated east of the base line are in fact separate conductors and not a single broad feature. Some of the features coincide with shore line or areas of topographic lows. Geological mapping is required to see if some of the features are due to structures within the bedrock.
(v) Recommendations - Geological mapping is recommended prior to any testing for gold mineralization by diamond drilling.
S2E18NW9492 2.5474 ECHO BAY 900
1983 10 052.5474
Mr. Wade MathewMining RecorderMinistry of Natural Resources808 Robertson StreetBox 5160Kenora, OntarioP9N 3X9
Dear Sir:
RE: Geophysical (Electromagnetic and Magnetometer) Survey on mining claims K 533164 et al 1n the Areas of Shoal Lake, Echo Bay and Boys Township.
The Geophysical (Electromagnetic and Magnetometer) survey assessment work credits as listed with my Notice of Intent dated September 7, 1983 have been approved as of the above date.
Please Inform the recorded holder of these mining claims and so Indicate on your records.
Yours very truly,
E.F. AndersonDirectorLand Management Branch
Whitney Block, Room 6610 Queen's Park Toronto, Ontario M7A 1W3 Phone:(416)965-1380
D. K1nv1g:mc
Encl.
cc: Selco Ine55 University AvenueSuite 1700Toronto, Ontario M5J 2H7
cc: T. Pryslak534 Berry StreetWinnipeg, Manitoba R3H OR9
cc: Resident Geologist Kenora, Ontario
/rr\ Ministry of Technical Assess Ivy] Natural VyJ Resources Work CreditsOntario ^^
mCnt . J" f 2.5474
[Date Mining Recorder's Report off 1983 09 06 work NO. 29-83
Recorded Holder
SELCO INCTownship or Area
ECHO BAY AND BOYS TOWNSHIPS
Type of survey and number of Assessment days credit per claim
Geophysical
Electromagnetic days
40 Magnetometer days
Induced polarization days
Section 7 7 ( 19) See "Mining Claims Assessed" column
fipnlngir.al days
Geochemical . days
Man days D Airborne CD
Special provision H Ground f*l
FX! Credits have been reduced because of partial
coverage of claims.
l l Credits have been reduced because of corrections
to work dates and figures of applicant.
Mining Claims Assessed
K 564171 to 76 inclusive 564178 589131 to 33 inclusive 589145 to 47 inclusive 589152 to 54 inclusive 589161 590008-09
Special credits under section 77 ( 16) for the following mining claims
20 DAYS MAGNETOMETER
K 564170 590010
No credits have been allowed for the following mining claims
1 _ l not sufficiently covered by the survey 1 _ 1 Insufficient technical data filed
The Mining Recorder may reduce the above credits if necessary in order that the total number of approved assessment days recorded on each claim does not exceed the maximum allowed as follows: Geophysical 80; Geological 40; Geochemical 40; Section 77(19) 60:
828 (83/6)
/1.ZN f/mistryof Technical Assess IVy] Natural vyv Resources Work CreditsOntario ^^
ment F" e 2.5474
Date Mining Recorder's Report of1983 09 06 workfjo. 29-83
Recorded HolderSELCO INC
Township or AreaECHO BAY AND BOYS TOWNSHIPS
Type of survey and number of Assessment days credit per claim
Geophysical 20
MflgnetnmRtnr days
Induced polarization days
Other days
Section 77 (19) See "Mining Claims Assessed" column
Geological . days
Genr.hpmioal days
Man days C3 Airborne f~l
Special provision Lx Ground 03
L~3 Credits have been reduced because of partial
coverage of claims.
d Credits have been reduced because of corrections
to work dates and figures of applicant.
Mining Claims Assessed
K 564171 to 76 inclusive 564178 589131 to 33 inclusive 589145 to 47 inclusive 589152 589154 589161 590008-9
Special credits under section 77 (16) for the following mining claims
10 DAYS ELECTROMAGNETIC
K 564170 589153 590010
No credits have been allowed for the following mining claims
LJ not sufficiently covered by the survey 1 1 Insufficient technical data filed
*
The Mining Recorder may reduce the above credits if necessary in order that the total number of approved assessment days recorded on each claim does not exceed the maximum allowed as follows: Geophysical 80; Geological 40; Geochemical 40; Section 77(19) 60:
828 (83/6)
Ministry ofNaturalResources
ario
1983 09 07
Your file: 29-83
Our file: 2.5474
Mr. Wade MathewMining RecorderMinistry of Natural Resources808 Robertson StreetBox 5160Kenora, OntarioP9N 3X9
Dear Sir:
Enclosed are two copies of a Notice of Intent with statements
listing a reduced rate of assessment work credits to be allowed
for a technical survey. Please forward one copy to the recorded
holder of the claims and retain the other. In approximately
fifteen days from the above date, a final letter of approval of
these credits will be sent to you. On receipt of the approval
letter, you may then change the work entries on the claim record
sheets.
For further information, if required, please contact
Mr. F.W. Matthews at 416/965-1380.
Yours very truly,
/Anderson r*ector
Land Management Branch
Whitney Block, Room 6450Queen's ParkToronto, OntarioM7A 1W3Phone: 416/965-1316
D. Kinvig:mc
Ends:
cc: Selco Inc55 Univeristy Avenue Suite 1700 Toronto, Ontario M5J 2H7
cc: Mr. G.H. FergusonMining X Lands Commissioner
845 Toronto, Ontario
cc: T. Pryslak534 Berry Street Winnipeg, Manitoba R3H OR9
Ministry ofNaturalResources
Ontario
Notice of Intent
for Technical Reports
1983 09 06
2.5474/29-83
An examination of your survey report indicates that the requirements of The Ontario Mining Act have not been fully met to warrant maximum assessment work credits. This notice is merely a warning that you will not be allowed the number of assessment work days credits that you expected and also that in approximately 15 days from the above date, the mining recorder will be authorized to change the entries on his record sheets to agree with the enclosed statement. Please note that until such time as the recorder actually changes the entry on the record sheet, the status of the claim remains unchanged.
If you are of the opinion that these changes by the mining recorder will jeopardize your claims, you may during the next fifteen days apply to the Mining and Lands Commissioner for an extension of time. Abstracts should be sent with your application.
If the reduced rate of credits does not jeopardize the status of the claims then you need not seek relief from the Mining and Lands Commissioner and this Notice of Intent may be disregarded.
If your survey was submitted and assessed under the "Special Provision-Performance and Coverage" method and you are of the opinion that a re-appraisal under the "Man-days" method would result in the approval of a greater number of days credit per claim, you may, within the said fifteen day period, submit assessment work breakdowns listing the employees names, addresses and the dates and hours they worked. The new work breakdowns should be submitted direct to the Lands Management Branch, Toronto. The report will be re-assessed and a new statement of credits based on actual days worked will be issued.
846 (82/5)
Ministry ofNaturalResources
Ontario
Report of Work(Geophysical, Geological, Geochemical and Expenditures)
SHOAL - P6
ftrThe Mining Act
Instructions: Please type or print. If number of mining claims traversed
exceeds space on this form, attach a list. Note: Only days credits calculated in the
"Expenditures" section may be entered in the "Expend. Days Cr." columns.
Do not use shaded areas below.Type of Survfly(i)
GeophysicalClaim Holder(t)
Selco Inc.Address
55 University Ave., SuiteSurvey Company
Selco Inc.Name and Address of Author (of Geo-Technical report)
T. Pryslak - 534 Berry St.,
] Township or Area
Shoal Lake M2339Prospector's Licence No.
T190
1700, Toronto. Ontario M5J 2H7l Date of Survey (from Si t o) Total Miles of line Cut
17, 01, 83 08 02 83 i c m 1- lp ,| Day | Mo. | Yr. Day 1 Mo. j Yr. ^ "l" 1 6S
Winnipeg, Manitoba R3H OR9Credits Requested per Each Claim in Columns at right Mining Claims Traversed (List in numerical sequence)Special Provisions
For first survey:
Enter 40 days. (This includes line cutting)
For each additional survey: using the same grid:
Enter 20 days (for each)
Man Days
Complete reverse side and enter total (s) here
Airborne Credits
Note: Special provisions credits do not apply to Airborne Surveys.
Geophysical
- Electromagnetic
- Magnetometer
- Radiometric
- Other
Geological
Geochemical
Geophysical
- Electromagnetic
- Magnetometer
- Radiometric
- Other
Geological
Geochemical
Electromagnetic
Magnetometer
Radiometric
Days per Claim
20
40
Days per Claim
Days perClaim
Expenditures (excludes power stripping)Type of Work Performed
Performed on Claim(s)
Calc ulatton of Expenditure Days Credits
Total Expenditures
S * 15
C
~
Total )ays Credits
Instructions Total Days Credits may be apportioned at the claim holder's choice. Enter number of days credits per claim selected in columns at right.
,Dat
ftfc. 17-8-^52^Ptjterj^TV-
ITAgent (Signature! ,(J
Mining ClaimPrefix Number
K 564170
564171
564172
564173
564174
564175
564176
: 564178
590008
. 590009
590110
1
f
Expend. Days Cr.
i
' J
For Office Use Only*~Dtai Uays Cr. Date Recorded . Recorded ^\ 1 /A **
VS^.^I/D^^it f ffi OTTnSpproveoT^WBLuiU**
^
Mining ClaimPfflix. | Number
R crcM/t
fM1NIN
[CSIraAM
Ji8
rIAK i y 1983
^ K*-L/ f j'
*
r t/1" /I J\^yw
KENOR MiNlNG OlV
1 IK lin jjl II Vi/*-* W la U \i
Q 2 1 li
^^^^^^^^^^**Mi^a^ha^
Expend. Days Cr.
L0-' Iff
rrzr-
A
p n^ ia M ||
83 pwiji&giS]
Total number of mining claims covered by this J J report of work.
Mmjta^^c^ber f ^
Sgi^ScTO-i^ __ Tvl^ft^JJVf **p -....^^^^^^1^^
Certification Verifying Report of Work "y~ l i '
t hereby certify that 1 have a personal or witnessed same during and/or after
end intimate knowledge of the facts set forth in the Report of Work annexed hereto, having performed the work its completion and the annexed report is true.
Name and Postal Addrest of Pereon Certifying
A. Pryslak - 534 Berry St., Winnipeg, Manitoba R3H OR9 J ^^lfflfl.Date Certified
Feb. 10, 1983Certified bvXSigWtu/e) " M
1362 (81/9)
Ministryof Report of Work
Re'so'urces (Geophysical, Geological, QntarjO Geochemical and Expenditures)
9 S hoal - P5 Grid 'A' The Mining ActType of Survey(s)
GeophysicalClaim Holder(s)
Selco Inc.
Instructions: Please type or print. ^ f P ^ — I f number of mining claims traversed
exceeds space on this form, attach a list. Note: Only days credits calculated in the
"Expenditures" section may be entered in the "Expend. Days Cr." columns.
^ Do not use shaded areas below.Township or Area
M1949Prospector's Licence No.
T190Address
55 University Ave., Suite 1700 , Toronto, Ontario M5J 2H7Survey Company Date of Sur
Selco Inc. .Day | Mo
vey (from 81 to) Total Miles of line CutFeb. '83 Q c m lc
1 Yr. Day | Mo. | Yr. S . 0 m 1 S .Neme and Addrest of Author (of Geo Technical report) --
T. Pryslak - 534 Berry Street, Winnipeg, Manitoba R3H OR9
Credits Requested per Each Claim in Columns at rightSpecial Provisions
For first survey:
Enter 40 days. (This includes line cutting)
For each additional survey: using the same grid:
Enter 20 days (for each)
Man Days
Complete reverse side and enter total (s) here
Airborne Credits
Note: Special provisions
credits do not apply to Airborne Surveys.
Geophysical
- Electromagnetic
- Magnetometer
- Radiometric
- Other
Geological
Geochemical
Geophysical
- Electromagnetic
- Magnetometer
- Radiometric
- Other
Geological
Geochemical
Electromagnetic
Magnetometer
Radiometric
Days per Claim
20
40
Days perClaim
Days per Claim
Expenditures (excludes power stripping)Type of Work Performed
Performed on Claim(s)
Calculation of Expenditure Days Credits
Total ExpendituresTotal
Days Credits
SInstructions
Total Days Credits may be apportioned at the claim holder's choice. Enter number of days credits per claim selected in columns et right.
Date nt(Signature)
Certification Verifying Report of Work
Mining Claims Traversed (List in numerical sequence)Mining Claim
Prefix
K
Number
589131
589132
589133
589145 '
589146
589147
589152
589153
589154
589161
,C, -ff ,
\*;
4
Expend. Days Cr.
(—— *7*
P^
. s:WA *
^
5797 A 7
\j
y
Mining ClaimPrefix | Number
|
AMImil
AM7i8i9
Expend. Days Cr.
EECElViP^t-K 1 5 19
UNO LANDS
KENORAMINING DIV.
i y b n/ EMAR 2 5 198;
10jllil8ili2i3i^
i
B
&ECUC
PMiS'tf
Total number of mining claims covered by this report of work. J Q
N
l hereby certify that l have a personal and intimate knowledge of the facts set forth in the Report of Work annexed hereto, having performed the work or witnessed same during and/or after its completion and the annexed report is true.
Name and Postal AddresS of Person Certifying
- T. Pryslak - 534 Berry Street, Winnipeg. Manitoba R3H OR9Date Certified
March 14, 1983Certified bv^Sigrurtu/e)
1362 ( 81/9)
Ministryot
ReSlcesOntario
Report of Work(Geophysical, Geological, Geochemical and Expenditures)
Shoal - P5 Grid 'B 1 The Mining A
Instructions: Please type or print,— I f number of mining claims traversed
exceeds space on this form, attach a list. Only days credits calculated in the "Expenditures" section may be entered in the "Expend. Days Cr." columns.
Do not use shaded areas below.
ote: -
Type of SurveyU)
GeophysicalTownship or Area
M1949Claim Holdar(t)
Selco Inc,Prospector's Licence No.
T190Address
Survey Company55 University Ave., Suite 1700, Toronto, Ontario M5J 2H7
Date of Survey (frornfli.to) . rt -Feb. 83Selco Inc. Day Mo. l Yr. Day l Mo. | Yr.
Total Miles of line Cut
4 mis.Name and Address of Author (of Geo Technical report)
T. Pryslak - 534 Berry Street, Winnipeg, Manitoba R3H OR9Credits Requested per Each Claim in Columns at rightSpecial Provisions
For first survey:
Enter 40 days. (This includes line cutting)
For each additional survey: using the tame grid:
Enter 20 days (for each)
Man Days
Complete reverse side and enter total (s) here
Airborne Credits
Note: Special provisions credits do not apply to Airborne Surveys.
Geophysical
- Electromagnetic
- Magnetometer
- Radiometric
- Other
Geological
Geochemical
Geophysical
- Electromagnetic
- Magnetometer
- Radiometric
- Other
Geological
Geochemical
Electromagnetic
Magnetometer
Radiometric
Days per Claim
20
40
Days per Claim
Days per Claim
Mining Claims Traversed (List in numerical sequence)
Expenditures (excludes power stripping)Type of Work Performed
Performed on ClaimU)
Calculation of Expenditure Days Credits
Total ExpendituresTotal
Days Credits
InstructionsTotal Days Credits may be apportioned at the claim holder's choke. Enter number of days credits per claim selected in columns at right.
Mining ClaimPrefix Number
623794
623795
589134
589155
Expend. Days Cr.
Mining ClaimPrefix Number
M1NIN3 LANDS SECTION
Expend, l Dayt Cr.
Total number of mining claims covered by this report of work.
Date Approved as Recorded
Certification Verifying Report of Workl hereby certify that l have a personal and intimate knowledge of the facts set forth in the Report of Work annexed hereto, having performed the work or witnessed same during and/or after its completion and the annexed report is true.
Name and Postal Address of Person Certifying
T. Pryslak - 534 Berry Street, Winnipeg , Manitoba R3H OR9Date Certified
March 14, 1983Certified
1362 ( 81/9)
Ministry ofNaturalResources
Ontario
Report of Work(Geophysical, Geological, Geochemical and Expenditures)
Shoal P7 Grid 'C' The Mining Act
•l? 9- X""9*~ P lease type or print. *^ f ~ 0 —S— I f number of mining claims traversed
exceeds space on this form, attach a l ist.— Only days credits calculated in the
"Expenditures" section may be entered in the "Expend. Days Cr." columns.
— Do not use shaded areas below.Type of Survey(t)
GeophysicalClaim Holder(t)
Selco Inc.
Township or Area
M2339Prospector's Licence No.
T190Add ran
Survey Company55 University Avenue, Suite 1700, Toronto, Ontario M5J 2H7
Date of Survey (from 61 to)Feb. '83
Day l Mo. | Yr. Day | Mo. | Yr.
Total Miles of line Cut
12 mis.Selco Inc.Name and Address of Author (of Geo-Technical report)
T. Pryslak - 534 Berry Street. Winnipeg. Manitoba R3H OR9Credits Requested per Each Claim in Columns at right Mining Claims Traversed (List in numerical sequence)Special Provisions
For first survey:Enter 40 days. (This includes line cutting)
For each additional survey: using the same grid:
Enter 20 days (for each)
Man Days
Complete reverse side and enter total(s) here
Airborne Credits
Note: Special provisions credits do not apply to Airborne Surveys.
GeophysicalHLEM and VLF
- Electromagnetic
- Magnetometer
- Radiometric
- Other
Geological
Geochemical
Geophysical
- Electromagnetic
- Magnetometer
- Radiometric
- Other
Geological
Geochemical
Electromagnetic
Magnetometer
Radiometric
Days perClaim
4040
Days perClaim
Days per Claim
Expenditures (excludes power stripping)Type of Work Performed
Performed on Claim(s)
Calc ulation of Expenditure Days Credits
Total Expenditures
S - 15C
Total )ays Credits
Instructions Total Days Credits may be apportioned at the claim holder's choice. Enter number of days credits per claim selected
Date, l . ~ ~ RStHcvirVvB^ ^
jupea H
^S c *n^
^AgernjSignature)
S*\
Certification Verifying Report of Workhereby certify that 1 have a personal
or witnessed same during and/or after
Mining ClaimPrefix
KNumber
533164533165533166533167533168533169623402623659623660623791623792623793
Expend. Days Cr.
L
tt? t i H
A
r-
i*M
[i5
For Office Use OnlyTotal Days Cr. Data BenafdBa1 ——— , ——————Recorded
^0/nw-**/*3 -
l Date Approved a* R^Qrcfe' —— ZT&Stf?±S XL.
Mining ClaimPrefix
REi\\
HNING
*- KEMtf
1 /-
MAr?
2^A
Number
CftVt'K 1 5 1983
Expend. Dayi Cr.
3—
LANDS SECTION
"^ o -v "r — — .,''\'G D iV. '
^ "bZ t) m :j L hi-l'?^rftg|"^~- i * m ,ii j
Total number of mining claims covered by this . report of work. i c.
Minj/rp*
iiffifna
eVder ———
^aaUcs^lector , f'
Kt^fhV-/4-K '———— ————————————— f———— ——————— J ———
and intimate knowledge of the facts set 'forth in the Report of Work annexed hereto, having performed the work its completion and the annexed report is true.
Name and Postal Address of Person Certifying
nipeg Manitoba P3H QP^Tbate" Certified
1 March 14, 1983Certified byjaigna/C/e) S
136? (81/9)
Ministryof GeotechnicalSSrces "-p""
Ontario Approval
File
Mining Lands Comments 7
CE "To: Geophysics
Comments
roved f~l Wish to see again with corrections
To: Geology - Expenditures
Comments
[) Approved |~] Wish to see again with correctionsSignature
To: Geochemistry
Comments
l l Approved l Wish to see again with correctionsDate Signature
l ]TO: Mining Lands Section, Room 6462, Whitney Block. (Tel: 5-1380)
1593 (81/10)
inc. 55 University Avenue Suite 1700Toronto Ontario M5J 2H7 Telephone: (416) 361 0794Telex: 06 22537 Cable: Selcoex Toronto
April 21, 1983
Ministry of Natural Resources Mining Lands Section Room 6450, Whitney Block Queen's Park Toronto, Ontario
li-
R EC EI ViLand Management'C1RCU! ATECOMMITS PLEASE : :' : PY nv ~"
APR 221983A'-iDERSON
i 'iO."ITON
Dear Sir,
RE: SHOAL PROJECT - PROPERTY 6 - M.2339
Further to my letter (April 13, 1983) in which I enclosed the Report and drawings for this group of claims; I have now received the final drawings SO 3580 and SO 3580B, please find copies enclosed.
Yours very truly,
SELCO INC.
J.E. RackleyClaims Control Co-ordinator
JER:rt Encl.
1983 04 21 2.5474
Mining RecorderMinistry of Natural Resources808 Robertson StreetBox 5160Kenora, OntarioP9N 3X9
Dear Sir:
We have received reports and maps for a Geophysical (Electromagnetic and Magnetometer) survey submitted under Special Provisions (credit for Performance and Coverage) on Mining Claims K 533164 et al 1n the Areas of Shoal Lake, Echo Bay and Boys Township.
This material will be examined and assessed and a statement of assessment work credits will be Issued.
Yours very truly,
E.F. AndersonDirectorLand Management Branch
Whitney Block, Room 6450Queen's ParkToronto, OntarioM7A 1W3Phone: 416/965-1360
A. Barr:se
cc: Selco Incorporated Toronto, OntarioAttention: Ms. J.E. Rackley.
IRC 55 University Avenue Suite 1700Toronto Ontario M6J 2H7 Telephone: (416) 361 0794Telex: 06 22537 Cable: Selcoex Toronto
April 13, 1983
Ministry of Natural Resources Mining Lands Section Room 6450, Whitney Block Queen's Park Toronto, Ontario
Dear Sir,
RE: SHOAL PROJECT - PROPERTY 6 - M.2339
Further to our Report of Work (Feb. 16, 1983) please find enclosed the following:-
CONTENT
{in duplicate) Geophysical Report Technical Data Sheets Drawings No. SO 3580 (B)
RECEIVED,^K l 5 1983
MINING LANDS SECTION
I apologize for submitting preliminary drawings, our field operations were working under a tight time-frame and I am expecting the finished drawings to be available within 2 weeks.
Yours very truly,
SELCO INC.
J.E. RackleyClaims Control Co-ordinator
JERcrt End.
• pMfe^M* ^ ^^^V 55 University Avenue Suite 1700• l if ^^^/^^^ Toronto Ontario M5J2H7 Telephone:(416)361 0794
Telex: 06 22537 Cable: Selcoex Toronto
April 13, 1983
Ministry of Natural Resources Kt^C* Mining Lands SectionRoom 6450, Whitney Block M l 5 1983Queen's ParkToronto, Ontario MINING LANDS SECTION
Dear Sir,
RE: SHOAL PROJECT - PROPERTIES 5 8. 7 - M.1949. 2339
Further to our Report of Work (March 21, 1983) please find enclosed the following:-
CONTENT
(in duplicate) Geophysical ReportsTechnical Data Sheets Drawings No. SO 3547, 3547B, 3547C
SO 3548, 3548B SO 3550, 3550B
Yours very truly,
SELCO INC.
x*—^ —* - ""^^ C'~~-~x-;" *t-"' ' x*"^ ,
J.E. RackleyClaims Control Co-ordinator
JER:rtEncl.
Ontario
Ministry of Natural Resources
GEOPHYSICAL - GEOLOGICAL - GEOCHEMICAL TECHNICAL DATA STATEMENT
SHOAL - P5GRID 'A' 1
TO BE ATTACHED AS AN APPENDIX TO TECHNICAL REPORTFACTS SHOWN HERE NEED NOT BE REPEATED IN REPORT
TECHNICAL REPORT MUST CONTAIN INTERPRETATION, CONCLUSIONS ETC.
"Z.o aV)
SE(Ko
Type of Survey(s).
Township or Area.
Claim Holder(s)^
GeophysicalM.1949Selco Inc. - 55 University Ave..Suite 1700. Toronto, Ontario M5J 2H7 Selco Inc._______^_^_^^_^^^_Survey Company
Author of Report A.P. Pryslak
Address of Author 534 Berry St.. Winnipeg. Man. R3H OR9
Covering Dates of Survey
Total Miles of Line Cut
Feb. '83 - Mar. '83(linecutting to office)
6.5 miles
SPECIAL PROVISIONS CREDITS REQUESTED
ENTER 40 days (includes line cutting) for first survey.
ENTER 20 days for each additional survey using same grid.
Geophysical
Electromagnetic.
DAYS per claim
Radiometric
-Other
Geological.
Geochemical.
AIRBORNE CREDITS (Special provision credits do not apply to airborne surveys)
Magnetometer. .Electromagnetic. . Radiometric(enter days per claim)
^G:or Agent
-?
Res. Geol.. .Qualifications.
Previous Surveys File No. Type Date Claim Holder
MINING CLAIMS TRAVERSED List numerically
K'(prefix)'
...L....,
.saam.........(number)
.589X32........
• ••••••••* *v\ •••••••••••••••t* * VA4 A 4k An ********t***
............J8L.................J5MU7..i
iRICEIVED
TOTAL CLAIMS. 10
837 (5/79)
GEOPHYSICAL TECHNICAL DATA
GROUND SURVEYS — If more than one survey, specify data for each type of survey
Number of Stations —0^83 _____ Mag*530 Station interval 50' (same at 100')
Profile scale _____ l " :2QK,
Number of Readings EMS383
Line spacing _______ 100J
Mag"530
Contour interval Every 100 Gammas to 500 Gammas
Instrument
Every 500 Gammas thereafter
Geometrics G816
Accuracy — Scale constant.
Diurnal correction method.
gammaBase Station
Base Station check-in interval (hours)——————^^^————....—————^—..—..^-—.——Base Station location and value Intersection at Base Lines and Cross Lines
ELECTROMAGNETIC Coil configurationfVijl separation
1
Accuracy .
Method:Frpqnrnry 444
Horizontal
1+
H7
25m and 250mn w
CH Fixed transmitter CD Shoot back Hln line
(specify V.L. F. station)
CD Parallel line
Parameters mpasnred
Instrument
In-phase and quadrature components of secondary field as a percentage of primary field.
Scale constant
Corrections made.
o Base station value and location ___.^——.-
Elevation accuracy—-
<
OiQu.
Instrument
Method D Time Domain
Parameters - On time
- Off time ___
D Frequency Domain
Frequency —————
Range ————————
Delay time __________—_————___~
Integration time _______.^ ......____.-—
Power ——,
Electrode array __—___-
Electrode spacing _. — .-
Type of electrode __- ^.
SELF POTENTIAL
Instrument^—-———^-——^^———-^——————-...--—-...-...——..—.—.—^—— Range.Survey Method ———--——————---———-——-^———————^^—-^-—-—.—..——.
Corrections made.
RADIOMETRIC
Instrument ———Values measured
Energy windows (levels)——^——————^—-——.—-.—^-—-———..—^—^—^—-—....——Height of instrument______________________________Background Count, Size of detector-——-—-—^———-^—-^^-^^—^-——..—^^^—.^—-.—.-—-——————.-——Overburden ——————-———^^^^—^——————.-—^—^———-...——.———.———.—^^^..—.
(type, depth — include outcrop map)
OTHERS (SEISMIC, DRILL WELL LOGGING ETC.)
Type of survey—.-——.-———-——————-————————Instrument _______ .——.. ___.— .—————————Accuracy______.—..-....—————.—-——————-.-——Parameters measured.......____...__,.
Additional information (for understanding results).
AIRBORNE SURVEYS
Type of survey(s)—. .--
Instrument(s) ——.--. ..—(specify for each type of survey)
Accuracy__..-.-..... ............- .._....^.... ..(specify for each type of survey)
Aircraft used. ....... ....... _ .......^...—————————
Sensor altitude._^-.... .^.-..-. ^ .....-.-^. . ^—^-^^———^^-^.
Navigation and flight path recovery method—.- ._....,^,^.———^——
Aircraft altitude_-. ..... ............ . ___.. -.-..__.__________ t.inp Sparing
Miles flown over toial are.i..... .... . .... _.. ^ .__________Over claims only.
GEOCHEMICAL SURVEY - PROCEDURE RECORD
Numbers of claims from which samples taken.
Total Number of Samples. Type of Sample.
(Nature of Material)
Average Sample Weight——————— Method of Collection________
Soil Horizon Sampled- Horizon Development- Sample Depth————— Terrain—————————
Drainage Development———————————— Estimated Range of Overburden Thickness.
ANALYTICAL METHODSValues expressed in: per cent D
p.p. m. CDp. p. b. D
Cu, Pb,
Others—
Zn, Ni, Co, Ag, Mo, As,-{circle)
Field Analysis (.Extraction Method. Analytical Method- Reagents Used——
Field Laboratory AnalysisNo. --———-———
SAMPLE PREPARATION(Includes drying, screening, crushing, ashing)
Mesh size of fraction used for analysis———..
Extraction Method. Analytical Method . Reagents Used——..
Commercial Laboratory (. Name of Laboratory_ Extraction Method__ Analytical Method —— Reagents Used ————
.tests)
.tests)
.tests)
GeneraL General.
Ontario
Ministry of Natural Resources
GEOPHYSICAL - GEOLOGICAL - GEOCHEMICAL TECHNICAL DATA STATEMENT
File SHOAL - P5
GRID 'B 1
TO BE ATTACHED AS AN APPENDIX TO TECHNICAL REPORTFACTS SHOWN HERE NEED NOT BE REPEATED IN REPORT
TECHNICAL REPORT MUST CONTAIN INTERPRETATION, CONCLUSIONS ETC.
lOCd M
Type of Survey(s).
Township or Area.
Claim Holder(s)—
GeophysicalM. 1949Selco Inc. - 55 University Ave.Suite 1700, Toronto, Ontario M5J 2H7
Survey Company. Author of Report.
Selco Inc.A. P. Pryslak
Address of Author. 534 Berry St.. Winnioea. Man. R3H OR9
Covering Dates of Survey.
Total Miles of Line Cut—
Feb. '83 - Mar. '83(linecutting to office)
4 miles
SPECIAL PROVISIONS CREDITS REQUESTED
ENTER 40 days (includes line cutting) for first survey.
ENTER 20 days for each additional survey using same grid.
~ , . . GeophysicalDAYS
per claim
?0
40
-Other.Geological.
AIRBORNE CREDITS (Special provision credits do not apply to airborne lurveyi)
Magnetometer. .Electromagnetic. . Radiometric(enter days per claim)
HATR, ftfrf. V4 -SAuthor of Reporter Agent
Res. Geol. . Qualifications J- ' -3 l f vPrevious Surveys
File No. Type Date Claim Holder
MINING CLAIMS TRAVERSED List numerically
.....K....,'(prefix)'
K
.6.2.3794........(number)
623795
K 589134
i
K tt
AVR 1 5 1983
..M1N1NJG..LAMD5..SJ;.CHQN.
TOTAL CLAIMS.
837 (5/79)
GEOPHYSICAL TECHNICAL DATA
GROUND SURVEYS — If more than one survey, specify data for each type of survey
Number of Stations EM S 2Q7 Mag=257___________Number of Readings EM*2Q7 Mag-257
Station interval____50' (some at 100').———————.Line spacing.
Profile scale_______l": 202———————\———-———^^-^—————Contour interval Every 1QQ Gammas to 5QQ Gamma s—————-——
Every 500 Gammas thereafter
Instrument_____Geometrics G816———————————......——Accuracy — Scale constant -— 1 Diurnal correction method Ra g pBase Station check-in interval (hours).^^.———^^ Base Station location and value intersection
Instrument Apex Max-Min II
XECTROMAGNETKCoil configurationTojl separation
Accuracy,Method: Frequency ™ ^
Horizontal125m and 250m+
CD Fixed transmitter d Shoot back Sp In line Hz
(specify V.L.F. station)
ED Parallel line
Parameters measured In-phase and quadrature components of secondary fieldas a percentage of primary field.
Instrument ——.^—^——-—^-^———-———^——-—-————————————-—-—-—————^—Scale constant.Corrections made.
^
o Base station value and location
Elevation accuracy.
7tOM4
5Ni-Hrt^ Oo* Qb] OQ ZHH
grtt-H
rt
Method D Time Domain CD Frequency DomainParameters - On time Frequency .
Off time Range. ..— TVlay time
— Integration time
Power . .... . .... . .. . —————————————
Electrode array —————————————————————————————————————————————————— - — — ——— —— —Electrode spacing — - ———————————————————————————————————————————— - ————————————Tvoe of electrode .. ....., ———————————————————————————————————————————
SELF POTENTIAL
Instrument___________________________________________ Range.Survey Method ————-———————————————————^^——————.———.——-——
Corrections made.
RADIOMETRIC
Instrument.Values measured .
Energy windows (levels) -——.—————.^———.—————.—....—...^^-^^————.—.——Height of instrument____________________________Background Count. Size of detector————————————-^^^—^—^^———.....——.—-^—.^^——..—..—Overburden —————————————-—————..—.—--..-—————...——^-—.—...———
(type, depth — include outcrop map)
OTHERS (SEISMIC, DRILL WELL LOGGING ETC.)
Type of survey———————————————————————Instrument ————^—^——^-—————^——————
Accuracy————————————————————————————Parameters measured.
Additional information (for understanding results).
AIRBORNE SURVEYS Type of survey(s) ————
Instrument(s) ——————(specify for each type of survey)
Accuracy———————————————(specify for each type of survey)
Aircraft used^—^^————————-——.—.——^——^^^^^-——
Sensor altitude-Navigation and flight path recovery method.
Aircraft altitude_________________________________Line Sparing Miles flown over total area__________________________Over claims only.
GEOCHEMICAL SURVEY - PROCEDURE RECORD
Numbers of claims from which samples taken.
Total Number of Samples. Type of Sample.
(Nature of Material)
Average Sample Weight———————— Method of Collection————————
Soil Horizon Sampled. Horizon Development. Sample Depth_____ Terrain—————————
Drainage Development———————————— Estimated Range of Overburden Thickness.
ANALYTICAL METHODS Values expressed in: per cent D
aD
per cent p. p. m. p. p. b.
Cu, Pb,
Others_
Zn, Ni, Co, Ag, Mo, As.-(circle)
Field Analysis (.Extraction Method. Analytical Method- Reagents Used——
Field Laboratory AnalysisNo. ———————-——
SAMPLE PREPARATION(Includes drying, screening, crushing, ashing)
Mesh size of fraction used for analysis ————
Extraction Method. Analytical Method - Reagents Used ——
Commercial Laboratory (. Name of Laboratory—. Extraction Method—— Analytical Method ——.Reagents Used .—--—-
.tests)
.tests)
-tests)
Genera General.
Sgwsb O
Ontario
Ministry of Natural Resources
GEOPHYSICAL - GEOLOGICAL - GEOCHEMICAL TECHNICAL DATA STATEMENT
SHOAL - P7 GRID 'C 1
TO BE ATTACHED AS AN APPENDIX TO TECHNICAL REPORTFACTS SHOWN HERE NEED NOT BE REPEATED IN REPORT
TECHNICAL REPORT MUST CONTAIN INTERPRETATION, CONCLUSIONS ETC.
Type of Survey(s) Geophysical
Township or Area M.2339—-——..^^-——————..——ClaimHoirier(s) Selco I nc - " 5 5 University Ave..
Suite 1700, Toronto, Ontario M5J 2H7Survey Company SelCQ Inc.
Author of Report A.P. PryslakAddress of Ai.thnr 534 Berry St.. Winnipeg. Man. R3H OR9 Covering Dates of Survey__E^b.' 83 - Mar.' 83
Total Miles of Line Cut —————(linecutting to office)
12 miles
SPECIAL PROVISIONS CREDITS REQUESTED
ENTER 40 days (includes line cutting) for first survey.
ENTER 20 days for each additional survey using same grid.
Geophysical
—Electromagnetic.—Magnetometer——Radiometric——
—Other————-—
DAYS per claim
40
Geological.Geochemical.
AIRBORNE CREDITS (Special provision credit! do not apply to airborne surveys)
Magnetometer. .Electromagnetic Radiometric(enter days per claim)
DATE:.Author of Report or Agent
Res. Geol.. Qualifications C. -
Previous Surveys File No. Type Date Claim Holder
MINING CLAIMS TRAVERSED List numerically
K 533164(prefix)
K(number)
533165
K
K
533166
533167
..If..
K
533168 t
533169,
K
K
623402
623659
K
K
.6.23660..
623791
.L K
..6..?.?.?.?.?.. 623793
AHK l 5 1988
TOTAL CLAIMS. 12
837 (5/79)
GEOPHYSICAL TECHNICAL DATA
GROUND SURVEYS — If more than one survey, specify data for each type of survey f
Number of Stations-jE^—Jte^S___________Number of Readings EM*530 Mag'683
Station interval 5 0 ' ( S0m6 a t 1 00 ')_______________Line .paring 400'_______________________1 " - 902. Profile scale_____^ '* u*________________________________________________________
Contour inte^i ^^y 1 00 Gammas to 500 GammasEvery 500 Gammas thereafter
Instrument ——Geometrics G816——————————{j' Accuracy - Scale constant ± I 9ammaZO
Diurnal correction method Base Station
Base Station check-in interval (hours)-^-————————.^—.——.^^——.—.....—.———.Base Station location and value Intersection at Base Lines and Cross Lines
Instrument Apex Max-Mi n II_______Coil configuration Horizontal_______Coil separation 125m and 250m————
* 0.535 -. Accuracy ——————~——————————————?J Method: d Fixed transmitter d Shoot back 10In line d Parallel line
- Frequency 444 Hz______________(specify V.L.F. station)
, In-phase and quadrature components of secondary fieldParameters measured i-.L.,-.--^...!....^ , ,f . .. :..,^.. *4-iJ______________-—^—^asaperuenLdyt UTprimary — ~—--
Instrument ————————————————————————————Scale constant __Corrections made.
^
O Base station value and location
Elevation accuracy.
Instrument ____Z Method d Time Domain d Frequency DomainQP Parameters — On time ___________________________ Frequency.< N3 H3 ^
i/:or
— Off time ___________________________ Range.— Delay time ——-—-..—-————^—-—————-——.^-^— Integration time —,.^—————————————————
Q tf Power.W3 ' Electrode arrayZ E lectrode spacing
Type of electrode
SELF POTENTIAL
Instrument________________________________________. Range.Survey Method .^—^——-—.-—.^^-—————...————.-—™—————.——-..—.——..——
Corrections made.
RADIOMETRICInstrument.Values measured .
Energy windows (levels)———^^-^^—^-——————--———-————..———-.——-.—.Height of instrument______________________________Background Count.Size of detector^-—————-——^^^—-..—.———-————-..—————^—.—^—.^^—^—
Overburden ——-——---—-—--^—-——--—.^—-^-—^-——-—————-^—.——.—.—..——(type, depth — include outcrop map)
OTHERS (SEISMIC, DRILL WELL LOGGING ETC.) Type of survey————^-^^——^—.—^^—————.
Instrument ——————————————————————————— Accuracy____________________________Parameters measured.
Additional information (for understanding results).
AIRBORNE SURVEYS
Type of survey(s) ————
Instrument(s) ——————(specify for each type of survey)
Accuracy-—————^——^—-————(specify for each type of survey)
Aircraft used——^——————————————-——^———™.—..——
Sensor altitude-Navigation and flight path recovery method.
Aircraft altitude_______________________________Line Spacing—— Miles flown over total area__________________________Over claims only.
GEOCHEMICAL SURVEY - PROCEDURE RECORD
Numbers of claims from which samples taken.
Total Number of Samples. Type of Sample.
(Nature of Material)
Average Sample Weight——————— Method of Collection—————-^.^
Soil Horizon Sampled. Horizon Development. Sample Depth————— Terrain___:—————.
Drainage Development———————————— Estimated Range of Overburden Thickness.
ANALYTICAL METHODS Values expressed in: per cent
p.p. m. p. p. b.
D D D
Cu, Pb,
Others—
Zn, Ni, Co, Ag, Mo, As.-(circle)
Field Analysis (-Extraction Method. Analytical Method- Reagents Used ——
Field Laboratory AnalysisNo. ,——————^^^.
SAMPLE PREPARATION(Includes drying, screening, crushing, ashing)
Mesh size of fraction used for analysis————
Extraction Method. Analytical Method - Reagents Used --—.
Commercial Laboratory (- Name of Laboratory— Extraction Method^— Analytical Method —— Reagents Used .————
.tests)
.tests)
.tests)
General____.. General.
GEOPHYSICAL TECHNICAL DATA
''M S'.'RV!.,Y'- i 1 i-. -' .'i utir ;;nrvcy, J'V'.'cify ''-it:i IIM -ruh type of survey
Number of Stations VLFS 58Q____________________Number of Readings VI F=5Rn
Station interval 50' and 100'_________________Line sparing 400 '—————
Profile scale_____1";2QX^—-—^——^.—^^^.^^^^^^^^^^^^^Contour interval.
Instrument ——...———^.—.c iAccuracy — Scale constant.
Diurnal correction method.
' Base Station check-in interval (hours).
Base Station location and value —..-..-.
Instrument Ggom'cs EM16Coil configuration N/A
Coil separation ___N/AAccuracy IP 1";5n 0/ QR l"
Method: d Fixed transmitter D Shoot back Q In line d! Parallel line17.8 KHz Cutler NAAFrequency———-—-—-——^——^——————-—————————-——————-——^———————-——^^^————.
(specify V.L.F. station)Parameters measured I n "Phase a nd quad-phase components of vertical magnetic —————-
field as a percentage of horizontal primary field.
Instrument ——————————————————————————.——————————————————————————————————
Scale constant
Corrections made.
Base station value and location .
Elevation accuracy.
Instrument ———————————————————————————————————————————————— Method D Time Domain D Frequency Domain
Parameters - On time ___________________________ Frequency —————
— Off time ___________________________ Range ————————
— Delay time _________________________:——
— Integration time —————.^—-r.———-—^-——————^
Power _____________—————————————————————————————————————
Electrode array —
Electrode spacing .
Type of electrode
Ontario
Ministry of Natural Resources
GEOPHYSICAL - GEOLOGICAL - GEOCHEMICAL TECHNICAL DATA STATEMENT
GRID 'E'
TO BE ATTACHED AS AN APPENDIX TO TECHNICAL REPORTFACTS SHOWN HERE NEED NOT BE REPEATED IN REPORT
TECHNICAL REPORT MUST CONTAIN INTERPRETATION, CONCLUSIONS ETC.
OFFICE USE ONLY
Type of Sur Township o Claim Hold
Survey Corr
Author of F
Address of
Covering Di
Total Miles
SPECIAL
vpy( s) Geophysicalr Area M. 1949
sr( s) Selco Inc. - 55 University Ave.,Suite
ipany Se! CO
teporr A. P.
1700, Toronto, Ontario M5J 2H7Inc.
PryslakAnthnr 534 Berry St., Winnioea. Man. R3H OR9ites nf Survey
of Line Cut
PROVISIONSCREDITS REQUESTED
ENTER 40 days (includes line cutting) for first survey.ENTER 20 days for each additional survey using same grid.
AIRBORNI Magnetome
HATR. HJ
Res. Geol.
Feb. '83 - Aor.'83(linecutting to office)
8.5 miles
DAYSf~, . . . per claim Geophysical
— Magnpt"T"'tpr 40
-DtWr
r.,^m;™i. CREDITS (Special provision credit! do not apply to airborne turveyi)
ter Rlprtrnmpgnptir , , RaHjnrnptrir(enter dayi per claim)
}r\A -&S Sir.NATITRF.- r A ^- *"""*"? -c; ""-*"^
Previous SurveysFile No.
^ -Author of Report or Agent
Qualifications ^ ^ ^
Type Date Claim Holder
MINING CLAIMS TRAVERSED List numerically
K 564170(prefix) (number)
K 564171
K 564172
K 564173
K 564174
,,,....,..,..K....,............564175..............
.........,,,...JL............,..5MU.fL........... k: 564178K 59QQQ8
K 5.9.QQQ9
;""""""RICIIWD""'-"-"APR 1 5 1983
TOTAL CT AIMS H
i
j ta
837 (5/79)
GEOPHYSICAL TECHNICAL DATA
GROUND SURVEYS — If more than one survey, specify data for each type of survey
Number of Stations EMS479 Ma9=519___________Number of Readings EfM79 Ma 3=5]Q Station interval 100' (some at 50')—————————Line spacing____400'_________
Profile scale______1":20X—————————,————————^-^^.—^.^-^,^-^---Contour interval Every 100 Gammas -1000 to +1000———.——^^^—^———-^———
Every 1000 Gammas thereafter
Instrument Geometrics G816————————.——.——-——————^—————————Si * ih Accuracy - Scale constant ~ l gamma____^_____________________^_^_^^.^__Z Diurnal correction method Base Station___________________________m—^————
lo
N X
Base Station check-in interval (hours)—^———^^^—..—.-..————.-™-—————Base Station location and value Intersection at Base Lines and Cross Lines
ECTROMAGNETIC
Instrument
Coil configuration Coil separationArrnrary
Method: Freciuencv 444
Horizontal125m and 250m
i 0.5*
d Fixed transmitter d Shoot back Hz
0In line d Parallel line
J (specify V.L.F. station) W
Parameters measured In-phasp and ciuadr3tyir'^ components of secondaryas a percentage of primary field.
Instrument ^————^^—.^.^—^—^^—^^-^——^^—————^—^——^^—^^^^Scale constant —.
Corrections made.
Base station value and location
Elevation accuracy.
Instrument ™————————,——————————————————————————————————— Method D Time Domain d Frequency Domain
- On time ___________________________ Frequency —^....^.- Off time ___________________________ Range ————————
time.——————————————————————————— Integration time
Power.Q u:Electrode array.Electrode spacing
: of electrode
SELF POTENTIAL
Instrument_________________________________________ Range.Survey Method-—-——————————-————————————^—^-—.—^-—-—————
Corrections made.
RADIOMETRICInstrument.Values measured.Energy windows (levels)————————^^—————-^—^——^^^^^^^^^^——-—— Height of instrument______________________________Background Count. Size of detector————-^^^——-.—-——————-——-————-————-——.————.—
Overburden .^-—-——————.———^^.^-^^^-—^—^—————————.^^-^^.^^—^—^(type, depth - include outcrop map)
OTHERS (SEISMIC, DRILL WELL LOGGING ETC.) Type of survey-—^—^^—-—————————————^—
Instrument ___________________________
Accuracy———————————————————————————Parameters measured.
Additional information (for understanding results).
AIRBORNE SURVEYS
Type of survey(s)————
Instrument(s) ——————(specify for each type of survey)
Accuracy—————^^—^———————.(specify for each type of survey)
Aircraft used ^———^^—————^^^^^^..-.—^..--..^-^^^^—^^..
Sensor altitude.Navigation and flight path recovery method.
Aircraft altitude_________________________________Line Spacing—— Miles flown over total area________________________Over claims only.
GEOCHEMICAL SURVEY - PROCEDURE RECORD
Numbers of claims from which samples taken.
Total Number of Samples. Type of Sample.
(Nature of Material)
Average Sample Weight——————— Method of Collection________
Soil Horizon Sampled. Horizon Development. Sample Depth———— Terrain—————————
Drainage Development——————————— Estimated Range of Overburden Thickness.
ANALYTICAL METHODS Values expressed in: per cent
p. p. m. p. p. b.
D CD D
Cu, Pb,
Others—
Zn, Ni, Co, Ag, Mo, As,-(circle)
Field Analysis (.Extraction Method. Analytical Method- Reagents Used——
Field Laboratory AnalysisNo. ————————-
SAMPLE PREPARATION(Includes drying, screening, crushing, ashing)
Mesh size of fraction used for analysis ———-
Extraction Method. Analytical Method . Reagents Used——.
Commercial Laboratory (- Name of Laboratory.— Extraction Method—— Analytical Method —— Reagents Used -————
.tests)
.tests)
.tests)
GeneraL General.
LL i/E.
JZ X /Csr ( t/ x
j22. x5 ^ ooio
l//
'33
x 6-
i/ (X4-C
v/ l/ i/t---' t/
i/ /. -7 3. xi/
v//75
5m r-//uL
t
T"/" /Ac,
0/2C.
NOTES
400 surface rights reservation along the shores of all lakes and rivers.
Flooding Rights reserved to 1064 mean sea l evel.
Islands in Shoal Lake and inlets thereto do not form part of Glass Township
52E10NW9492 2.5474 ECHO BAY
O-950 00'
ECHO BAY and BOYS TP M.194994045'00"
49" 77 30 n
C\J
LJ
O
en
xCD
LU OxCO
ozCO
490 3000 J
D. 2384*9111 .489112 ;s9 lo32l
7I07S47 -078- 710786
.589741 1589742 1589 74 3
- - --J IT J. . — fc MCA3I
490 37'30"
37'
36
35
33
32'
31
ro roCJ
COT?OO
O)
•*—
X4-
O
O)
O-J
XGO
LJ-J
95000' 59 58' 57' 56 55 54' 53' 52' 51'
MONUMENT BAY (Lake of the Woods)
50'
M.2682
49' 47 46 94f
L 490 30'00'
45'00"
495 944
LEGEND
HIGHWAY AND ROUTE No.
OTHER ROADS
TRAILS
SURVEYED LINES:TOWNSHIPS, BASE LINES, ETC. LOTS,MINING CLAIMS, PARCELS.ETC.
UNSURVEYED LINES! LOT LINES PARCEL BOUNDARY MINING CLAIMS ETC.
RAILWAY AND RIGHT OF WAYUTILITY LINES NON-PERENNIAL STREAM FLOODING OR FLOODING RIGHTS SUBDIVISION ORIGINAL SHORELINE MARSH OR MUSKEGMINES
DISPOSITION OF CROWN LANDS
TYPE OF DOCUMENT
PATENT, SURFACE S MINING RIGHTS
SURFACE RIGHTS ONLY
MINING RIGHTS ONLY
LEASE, SURFACE SMINING RIGHTS
SURFACE RIGHTS ONLY
MINING RIGHTS ONLY
LICENCE OF OCCUPATION
CROWN LAND SALE
OROER-IN-COUNCIL
RESERVATION
CANCELLED .
SAND S GRAVEL
SYMBOL
V
m HHT c.s ocCO 0 O
SCALE : l INCH - 40 CHAINSO 500 IOOO B 000
FEET
METRESO 200 4OO 600 800 l KM.
ACRES HECTARES
AREA
SHOAL.IATE OF ISSUE
K'Ero
AKE
MINING DIVISION
KENORA
ONTARIO
MINISTRY OF NATURAL RESOURCESSURVEYS AND MAPPING BRANCH
DATE 10th. SEPTEMBER/73
NATIONAL TOPOGRAPHIC SERIES
52E 10
PLAN No.
M 2339l V l — L— \J \J*J
22500N
22900N
233-
OON
23700N
241-
OON
245-
OON
24900N
2 53-0 ON
257-OON
261-
OON
265-
OON
26900N
273-
OON
277-
OON
281-
OON
285-
OON
28900N
60-OOE -
65-OOE -
70-O
OE -
r
205
-194
" -239
-246
- -l 19
-81
\- -258
-252
- -241
-235
-227
-223
7500E -
80-O
OE
85-OOE -
90-O
OE -
9&OOE
100-OOE -
l O 5-
0 O E -
L- -107
-97
*-
-113
225-OON
2290
0N23
300N
237-
OON
2 41
-0 ON
2 4 5-
0 ON
2490
0N253-OON
257-OON
261-
OON
265-OON
269-OON
273-OON
277-
OON
281-
OON
285-
OON
28&OON
- 6
0-DO
E
- 6500E
- 7
0-OO
E
75-O
OE
8000E
BASELINE
AZ.
30"
- 8
5-OOE
MAGN
ETOM
ETER
IN
STRU
MENT
TY
PE:
GEOM
ETRI
CS
G-S
ISR
eadi
ngs
in G
amm
as:
Bas
e:
60,
000
Pro
file:
Co
nto
ur
Inte
rval
: E
very
100
0 ga
mm
as f
rom
-5
00
0 g
amm
as t
o-l S
OO
gam
mas
Eve
ry 1
00 g
amm
as f
rom
-l
500 g
amm
as t
o 50
0 ga
mm
as
Eve
ry 5
00 g
amm
as
to
50
00
gam
mas
E
very
l O
OP
gam
mas
th
ere
after
__
- 9
000E
OTH
ER
IN
FO
RM
AT
ION
SE
E
DRW
G.
Nfi.
S0.3
547B
SO. 3
547
C
TYP
E
H.L
.E.M
., LO
CA
TIO
N
PLA
N,
CLA
IMS
V.L.
F.
- 9
5-O
OE
\
- 10
CKJO
E
O L
40
0
FEE
T
- 10
500E
EX
PLO
RA
TIO
N
SHO
AL
LAK
E
PRO
JEC
T
PRO
PER
TY
7.
GR
ID '
C1- O
PTI
ON
MAG
. S
UR
VE
Y
DR
AW
N 6
Y
L-
TR
AC
ED
BY
SD
.
DA
TE
OA
TF
Mar
ch
H83
N.T
.S.
PL
AN
S0
.35
47
52E
1QN
W94
92 2
.54
74
EC
HO
BA
Y
65-O
OE -
7000E -
75-O
OE -
80-O
OE
85-OOE
90-O
OE -
95-O
OE -
100-
OOE -
22500N
229-
OON
233-
OON
237-
OON
241-
OON \
245
-OON
281-
OON
285-OON
289-
OON
Shoal
\ Lake
PROPERTY 7
Shoa
l Lo k e
GRID 'C
FAIR
SE
RV
ICE
O
PTI
ON
LOC
ATI
ON
PL
AN
CLA
IM
MA
P M
.2339-O
NT
Sca
le
1=1/
4 m
i.
- 6
5'O
OE
70-O
OE
- 7
5-O
OE
80-O
OE
- 8
5-O
OE
- 9
000E
- 9
5-O
OE
- 1
00-O
OE
BA
SE
LIN
E
AZ.
30
0
ELE
CTR
OM
AG
NE
T/C
IN
STR
UM
EN
T TY
PE
t A
pex
MA
X-M
IN
E
HORI
ZONT
AL
LOO
P (P
erce
nt o
f Pr
imor
y Fi
eld)
Fr
eque
ncy:
44
4 Hz
. Ca
ble
Leng
th:
400
ft.
In Ph
ase:
*—
* —
—L
Oi
-2
Out
of P
hase
Q
uadr
atur
eCo
nduc
tor
Wid
th;
Prof
ile
Scal
e:
l"
20 *A
OTH
ER
IN
FO
RM
AT
ION
SEE
DRW
G.
N4
S0.
3547
SO
. 354
7C
TY
PE
MA
G.
V.L
.F.
O L
40
0_
lFE
ET
52E^
e^w^
4^^
2.54
74 E
CHO
BAY
225-
OON
229-
OO
N 23
3-O
ON
237-
OO
N 24
1-O
ON
245D
ON
24
9-O
ON
253-
OO
N 25
7-OO
N 26
1-OO
N 26
5-Q
ON
2690
0N
273O
ON
27
7-O
ON
281-
OON
285-
OO
N 28
9-OO
N
^^^
^
^^
J 1 in
c.E
XP
LOR
ATI
ON
SH
OA
L LA
KE
PR
OJE
CT
PR
OP
ER
TY
7,
H.L
E.
GR
ID '
C'- O
PTIO
NM
. SU
RVE
Y
DR
AW
N B
Y
DA
TE
L.
C.
Fe
b.
1^*
3
TRAC
ED B
Y D
ATE
ba-f
epl*
* S
-J.
Mar
ch
W W
N.T
.S.
-
PLA
N
S0.
3547
B
22
0
225-OON
22MON
233-
OON
237-
OON
241-
OON
245-
OON
60-O
OE -
65-OOE -
s o
S l
S 1
6 2
6 2
4 3
l P
70-OOE -
75-OOE -
800QE -
85-O
OE -
9000E -
95-OOE
//
24900N
253-
OON
257-
OON
261-OO
N26
5-OO
N26
9-OO
N27
3-OO
N277-OON
281-
OON
285-
OON
28&OON
1 r i i \^^^^
^^"™—
\ \ \
* ** * V l i \
1
t i 1 1 f i
l' 1
" " "
" ' ?
/" 1 x
7 "^
. , i ^ ^
^
4
1 1"t
^ 3 2 i
1 t T 3 0
- -T -12
- -i
: -5
^ ;
1 ,
i i
* !
l
'l 4
* t
.-
O
*
-:
-4 - t
-•-
.. r
. .
; O
- ^ ;
-i ;
-12
. -? -52
-3C
-^E
' -3
0
-4C
-42
1 -i
f
12 12
* *
.*
S^ X y
"••.
* - *
o
, 1
/'
. . f
' ^^-
'"
*
*s i / /
x
1 \ 1 1•.^
\ \1 - 1 : '
" 4 1 1 2 \ •\6 \ 16 2G 27
- 35 ie
* -.
- -i - 1
c
\J ^x*'.
\. ^ \" : t s
7 m m
L^- f
*
. . i
-4 -5 -i
. -4
/
100-
OOE -
105-
OOE -
3 -l
3 -l
3 CI
6 -10
4 O
2 l l
16\
O
O \2 \
27
-,\
is^- -4
;3
12
:3
::
- 4
; 2
-e
24
-14
19
65-O
OE
- 7
0-OO
E
- 7500E
80-OOE BASELINE
AZ. 30
0
- 8
5-O
OE
ELEC
TRO
MAG
NETI
C .N
STH
UM
ENT
TYPE
* V.
L.F.
Inst
rum
ent'
GE
ON
ICS
E
M.
16St
atio
n^C
UT
LER
IPPr
ofile
Sc
ale-
Q
p |"
:20
0XoFi
ltere
d Di
p An
gles
(F
rase
r)
Cont
our
Inte
rval
--
- 9
0-OO
E
SEE
DRW
G.
Nfi
SO.3
547
SO. 3
547
B
TY
PE
MA
G.
H.L
.E.M
, LO
CA
TIO
N
PLA
N,
CLA
IMS
- 9
5-OO
E
\
- 10
0-ooE
o L400
FEET
- 10
5-OOE
SH
OA
L LA
KE
PR
OJE
CT
PRO
PER
TY 7
, G
RID
'c'- O
PTIO
N
225-
OO
N 22
9-O
ON
233-
OO
N 23
700N
24
1-O
ON
245-
OO
N 24
9-O
ON
253-
OO
N 25
7-O
ON
261-
OO
N 26
5'O
ON
26
MO
N
273^
0N
2770
0N
281-
OO
N 28
5-O
ON
2890
0N
^RA
WN
BY
LG
T R
AC
ED
8Y
DcH
-apl
ol-
5-73
,
V.L
.F.
SU
RV
EY
DA
TE F
tb.
[*?B
5
DA
TE M
arc
h 1
*583
NT
. s.
PLA
N
SO. 3
547
C
52E10NW9492 2.5474 ECHO BAY
230
10-OON -
SOON -
BflSE LINE -
5-OOS -
10-OOS -
52E1eNI9492 2 .5474 ECHO BAT240
O 400E 8-OOE 12-OOE 16-OOE 20-OOE 2400E
O 4-0 O E 8-OOE 12-OOE 16-OOE 20-OOE 2400E
- 1000N
- 5-OON
DflSE LINE AZ.90 0
- 5-OOS
- 10-OOS
MAGNETOMETER INSTRUMENTTYPE: G EOMETRICS csie
. r 35*Readings in Gammas: L -51S) Bose: 60,000 gammasProfile:Contour Interval: Every l OOgammas from-lOOOto-t-500 gammas
Every SQOgammas thereafter.
OTHER INFORMATIONSEE DRWG. NO
SO-3548 BTYPE
H.L.E.M., LOG.PLAN,CLAIMS
OL
200 400 J
FEET
i EXPLORATION
SHOAL LAKE PROJECT
PROPERTY 5 —GRID 'B'
MAG. SURVEYDRAWN BY
L.C-
TRACED SYPlot J.G.
DATEFeb. I383
DATE1/larc.K 1365
N.T.S. PLAN
S0.3548
o 4-0 O E 8-0 O E 12-OOE 16-OOE 20-OOE 2400E
10-OON -
5-OON -
BflSE LINE
5-0OS -
10-OOS -
O 4-OOE 800E 12-OOE 16-OOE 20-OOE 24-OOE
- 10-OON
- 5-OON
BflSE LINE
- 5-OOS
- 10-OOS
52E10NW9492 2.5474 ECHO BAY 25©
-N-
LOCATION PLAN
CLAIM MAP M.I945,ONTScale : l"' 1/4 mile
ELECTROMAGNETIC INSTRUMENT
TYPE: APEX MAX- WIN E
HORIZONTAL LOOP ( Percent of Primary Field)Frequency: 4 44 HzCable Length: 400ftIn Phase: e— e — r ' 2[, Out of Phose
QuadratureConductor Width: Profile Scole: l" 20 0Xo
OTHER INFORMATIONSEE DRWG. N2SO. 3548
TYPEMAG.
O 100 200
FEET
i EXPLORATION
SHOAL LAKE PROJECTi -JPROPERTY 5 —GRID B
H.L.E.M. SURVEYDRAWN BY
L.C
TRACED 9YDaia Plot
DATE
DATE1383
NT. S. PLAN
S0.3548B
o
25-OON -
20-OON -
1500N -
10-O
ON -
5-OON -
BflS
E LINE
500S -
1000S -
15-O
OS -
20-OOS -
O
52E19NW9492 2.5474
ECHO SAY
260
l&OOE
20-0
0 E
24-O
OE2&OOE
32-OOE
3&OOE
40-OOE
44-OOE
4&OOE
52-OOE
5&OOE
4-0 O
E&OOE
12-O
OE
BASE LI
NE AZ.640
-153
4-OO
E8-OOE
12-OOE
l&OOE
20-O
OE24
-OOE
2800E
32-O
OE3&OOE
4000E
44-O
OE4&OOE
- 2
5-OO
N
- 2
0-OO
N
- 1500N
- SOON
MAGN
ETOM
ETER
IN
STRU
MENT
TY
PE: G
EOME
TRIC
S GS
IGR
eadi
ngs
in G
amm
as:
[' "7
Ba
se:
60
,00
0 g
amm
as
Pro
file:
Con
tour
Inte
rval:
Eve
ry l
OO
gom
mas
fro
m-1
30
0 t
o -f-
BOO
gam
mas
Eve
ry 5
00 g
amm
as
ther
eafte
r
OT
HE
R
INF
OR
MA
TIO
NS
EE
D
RW
G.
NOS
0.3
550B
TY
PE
H.L
.E.M
., LO
G. P
LA
N,
CLA
IMS
O L
200
400
_l
FE
ET
EX
PLO
RA
TIO
N
SH
OA
L LA
KE
P
RO
JEC
T
PR
OP
ER
TY
5
—G
RID
MA
G.
SU
RV
EY
DR
AW
N B
YL
C
TRA
CE
D B
YD
ata
P
lot-
J-
G
DA
TE
Fab
DAT
EM
arc
h
N.T
.S.
PL
AN
S0
.35
50
l&OOE
2 OOP E
24-OOE
2&OO
E32-OOE
3&OO
E4000E
44-O
OE48
-OOE
52-0
O E
56-n
OE
O4-
0 O E
800E
12-OOE
2500N -
20-O
ON -
15-O
ON -
10-O
ON -
5-0O
N/ -
BflSE
LINE -
5-OOS -
10OOS -
15-O
OS -
O4-
OOE
8-OO
E12-OOE
16-OOE
2000E
24-O
OE28-OOE
32-O
OE36-OOE
4000E
44-OOE
4&OOE
PROPERTY 5
BASE LINE AZ.640
LO
CA
TIO
N
PLA
N
CLA
IM
MAP
M
.I94
9-O
NT
. S
cale
! l";
1/4
mile
- 2
500N
- 2
&OO
N
- 1
500N
-
1000
N
- &
OO
N
ELE
CTR
OM
AG
NE
TIC
IN
STR
UM
EN
T TY
PE
: A
PE
X
MA
X-M
IN I
I
HO
RIZ
ON
TAL
LOO
P (P
erce
nt
of P
rimar
y Fi
eld)
Fr
eque
ncy:
4
44
Hz
Cobl
e Le
ngth
: 400ft
.In
Ph
ase:
e—
— e
——
Cond
ucto
r W
idth
;
Prof
ile
Scal
e:
l" 20
07o
L-Z
ft
IO
D
Out
of P
hase
Q
uadr
atur
e
OT
HE
R
INF
OR
MA
TIO
NSEE DRWG. NO
SO. 35 50
TYPE
MAG.
O200
l400
FEET
52E
1M
H9492
2.5
47
4
ECH
O
BA
YS
70
lE
XP
LOR
ATI
ON
SHO
AL
LAK
E
PR
OJE
CT
PR
OP
ER
TY
5 —
GR
ID '
A'
H.L
.E.M
. SU
RVE
Y
DR
AW
N B
YL
.C,
TR
AC
ED
BY
Plo
t J.
G.
DA
TE F
ab
.
DA
TE M
arch
13
83
N.T
.S.
PL
AN
S0.
3550
B
085
AV
9
ssoo
"'- '"^s^
SS
/
.***-
'- J"*-
. **!-~"
?'.
K
x
X
\v;ftV
ft*
fttf
MAG
NET
OM
ETER
IN
STR
UM
EN
T TY
PE
'. G
eom
etr
ics
G.8
I6R
eadi
ngs
in G
amm
as:
[ ,7G
S Ba
se:
60,0
00 g
amm
as
Pro
file:
Con
tour
Int
erva
l: E
very
lO
Oga
mm
as f
rom
-IOO
O t
ot
1000
gam
mas
Ev
ery
lOO
Oga
mm
as
ther
eafte
r
OTH
ER
IN
FO
RM
AT
ION
SEE
DR
WG
. N
2S
O-3
580
B
TY
PE
H.L.
E.M
., LO
G. P
LAN
,CLA
IMS
O2
00
400
FE
ET
EX
PLO
RA
TIO
N
SH
OA
L LA
KE
P
RO
JEC
TP
RO
PE
RTY
6
-GR
ID '
E'
MA
G.
SU
RV
EY
DR
AW
N B
Y L.C
.
TR
AC
ED
BY P
lot
DA
TE
Fab
. I3
Q3
DA
TE
383
NT
. S.
PLA
N SO
-358
0
S2E1BNW9492 2.5474 ECHO BAY
290
frRiD
'E'
PR
OP
ER
TY
TL 1
0*00
Mw 0
0*00
M
Tl
10+0
05
CL
AIM
BO
UN
DA
RY
O
N ^^O
RE
L.IM
E.
SO
.3S
SO
-MA
G
SELC
O M
ININ
GIN
STRt
lMEI
Er
Cofld
bclo
r
o
J6N
Cond
ucto
r W
idt h
: Pr
ofile
Sc
ale:
\"-
- 20
07o
//e 11
div
er
Bay
K .5
64
17
4
590008
CLA
IM
BO
UN
DA
RY
ON
SH
OR
E L
INE
590010
PR
OP
ER
TY
6
GR
ID
E
* H
elld
ive
r B
ay
LOC
AT
ION
P
LAN
CLA
IM
MA
P
M.3
339-O
NT
Sca
le
l : 1
/4 m
ile
ELEC
TRO
MA
GN
ETIC
IN
STR
UM
EN
T TY
PE
: A
PEX
MA
X- M
INE
HORI
ZONT
AL
LOO
P (P
erce
nt o
f Pr
imar
y Fi
eW)
Freq
uenc
y :
4 4 4
H z
Cobt
e Le
ngth
: 40
0ft
\ OT
HE
R
INF
OR
MA
TIO
NSEE DRWG. NO
SO-3
580
TYPE
MAG.
O200
400
FEET
52E10NW9492 3.5474 ECHO BAY
310
EX
PLO
RA
TIO
N
SH
OA
L LA
KE
P
RO
JEC
T
PR
OP
ER
TY
6-G
RID
E
H.L
.E.M
. SU
RVE
YD
RA
WN
BY L
.C
TR
AC
ED
BY P
lot
DA
TE
Fab.
DA
TE
Ap
ril
1383
NT
.S.
PL
AN S0.3
580B