Geometric Standards

  • Upload
    -

  • View
    219

  • Download
    0

Embed Size (px)

Citation preview

  • 8/2/2019 Geometric Standards

    1/28

    SECTION 3

    GEOMETRIC STANDARDS

    Section

    3

  • 8/2/2019 Geometric Standards

    2/28

    Rural Roads - Design ManualSection 3 Geometric StandardsRepublic of YemenMinistry of Public Works and Highways

    SECTION 3

    GEOMETRIC STANDARDS

    TABLE OF CONTENTS

    Page

    3.1 Introduction .........................................................................................1

    3.2 Sight Distance.......................................................................................13.2.1 Stopping Sight Distance .........................................................1

    3.2.2 Intermediate Site Distance.......................................................3

    3.3 Superelevation......................................................................................3

    3.4 Horizontal Alignment.............................................................................73.4.1 Circular Curves ..................................................................7

    3.4.2 Transition Curves ................................................................8

    3.4.3 Improving Horizontal Alignment ............................................. 10

    3.4.4 Geometric Controls ............................................................ 10

    3.4.5 Widening on Curves ........................................................... 11

    3.5 Vertical Alignment...............................................................................

    123.5.1 Elements of Vertical Alignment...............................................

    13

    3.5.2 Crest Curves ................................................................... 14

    3.5.3 Sag Curves ..................................................................... 17

    3.5.4 Gradient ........................................................................ 17

    3.5.5 Climbing Lanes ................................................................ 18

    3.6 Cross Section ......................................................................................193.6.1 Rationale for Determining Road Widths ...................................... 19

    3.6.2 Carriageways and Shoulders..................................................

    203.6.3 Cross Slope .................................................................... 23

    3.6.4 Passing Places ................................................................. 24

  • 8/2/2019 Geometric Standards

    3/28

    Rural Roads - Design ManualSection 3 Geometric StandardsRepublic of YemenMinistry of Public Works and Highways

    SECTION 3

    GEOMETRIC STANDARDS

    3.1 INTRODUCTION

    As mentioned in Section 2, the geometric features for most of the rural

    roads in Yemen are governed by the natural terrain characteristics.

    However, this does not exclude the fact that the geometric design should be

    consistent with the traffic volume, composition of traffic and design speed.

    This Section provides a summary of the geometric design data and containssufficient information for the majority of roadway design problems. A

    Policy on Geometric Design for Highways and Streets by the American

    Association of State Highways and Transportation Officials (AASHTO) is

    a reference in which the basic theory behind geometric design data is fully

    explained. Also, Guidelines for Geometric Design of Very Low-Volume

    Roads (ADT400) by AASHTO, and TRRL Road Note No. 6 A guide

    to Geometric Design can be consulted.

    Several design standards from projects previously undertaken in Yemen

    have been reviewed. The Consultants have taken into consideration the

    technical aspect combined with the specific requirements of this project in

    developing a new set of geometric standards. The review covers the sight

    distance, horizontal and vertical alignment and cross sectional elements as

    related to traffic volumes and design speeds.

    3.2 SIGHT DISTANCE

    Sight distance is the length of roadway ahead visible to the driver.

    Ability to see ahead is of utmost importance in the safe and efficient

    operation of a roadway. If safety is to be built into the roadways, the

    designer must provide sight distance of sufficient length in which drivers

    can control their vehicles so as to avoid striking an unexpected obstacle on

    the traveled way.

    Two sight distances are considered in design of bi-directional carriageway

    for rural intermediate and village access roads: Stopping Sight Distance

    and Intermediate Sight Distance.

  • 8/2/2019 Geometric Standards

    4/28

    Rural Roads - Design ManualSection 3 Geometric StandardsRepublic of YemenMinistry of Public Works and Highways

    Stopping sight distance is generally determined as the sum of two

    distances:

    (1) Reaction Distance, the distance traveled by the vehicle from the

    instant the driver sights an object necessitating a stop to the instant

    the driver actually applies the brakes. This distance depends on the

    reaction time of the driver which varies according to the alertness of

    the driver. AASHTO Policy on Geometric Design for Highways

    and Streets uses a brake reaction time of 2.5s, while AASHTO

    Guidelines for Geometric Design of Low-Volume Local Roads

    (ADT 400) recommends a reaction time of 2s for rural roads.

    (2) Braking Distance, the distance required to stop the vehicle from

    the instant the brakes are applied. This distance is a function of the

    longitudinal friction factor, and thus deceleration of the vehicle.

    The stopping sight distance in the AASHTO Policy is given by the

    following formula which has two components corresponding to the two

    distances mentioned above:

    aV039.0Vt278.0S

    2

    +=

    where,

    S = stopping sight distance, m

    t = brake reaction time, s

    V = design speed, kph

    a = driver deceleration, m/s2

    Table 3.1 shows a comparison between minimum sight distance standards

    for AASHTO and TRL, for very low volume roads.

    Table 3.1 Comparison of Minimum Stopping Sight Distance Standards

    Minimum Stopping Sight Distance (m)

    AASHTO(1)

    TRL Road Note 6(2)Design

    Speed KphADT < 250 ADT 250 400 fL Smin

    20 15 15 __ __

    30 25 30 0.6 2540 35 40 0.55 35

    50 45 55 0.50 50

    60 60 70 0.47 65

    70 75 90 0.43 85

    80 95 110

    85__

    0.40 120

  • 8/2/2019 Geometric Standards

    5/28

    Rural Roads - Design ManualSection 3 Geometric StandardsRepublic of YemenMinistry of Public Works and Highways

    As discussed in Section 3.5.2, sight distance plays a key role in determining

    the minimum lengths of crest vertical curves. Stopping sight distance is

    measured from the drivers eyes (eye height, h1) to an object height (h2).

    AASHTO policy uses h1 = 1080 mm and h2 = 150mm or h2 = 600mm if the

    object is a vehicle. With the increased use of SUVs, the average eye height

    has increased, so that h1 could be assumed to be 1.4m and h2 15cm. This

    sight distance criterion should be checked for all classes of roads irrelevant

    of the number of lanes, traffic volume or pavement type. Measures to be

    taken to correct any deficiency include removal of obstacles, excavation of

    side slopes or trimming of sharp crest curves.

    3.2.2 Intermediate Site Distance

    The Intermediate sight distance is the distance needed for two drivers

    traveling with design speed to stop before colliding. This criterion is valid

    in the case of one-lane roads. For village access roads having a traffic load

    of less than 50 vehicles/day the intermediate sight distance can be neglected

    if the lane is widened up to at least 4.5m.

    Table 3.2 shows the proposed minimum normal and relaxed standards forsight distances related to design speeds for RAP roads.

    Table 3.2: Minimum Standards for Sight Distances Related to Design SpeedsMinimum Sight Distance, m

    Stopping Intermediate

    Rural Intermediate Village Access

    Design

    Speed,

    KPHNormal Relaxed Normal Relaxed

    Rural

    Intermediate

    Village

    Access

    20 20 15 15 15 50 30

    30 35 30 30 25 80 5040 50 40 40 35 110 70

    50 65 55 - 45 150 -

    60 85 70 - 200 -

    80 130 110 - 300 -

    100 160 155 - 380 -

    120 230 540

    Sight distance could also be related to type of terrain if the design speed for

    each terrain is specified. It must however be recognized that in each terrain,owing to local topographical changes, higher or lower speeds than

    recommended may apply.

    Sight distances are also affected by vertical grade and obstacles along the

    side of the roadway on horizontal alignment.

  • 8/2/2019 Geometric Standards

    6/28

    Rural Roads - Design ManualSection 3 Geometric StandardsRepublic of YemenMinistry of Public Works and Highways

    Superelevation may be defined as the rotation of the roadway cross section

    in such a manner as to overcome the centrifugal force that acts on a motor

    vehicle traversing a curve. On a superelevated carriageway, the centrifugal

    force is resisted by:

    1. The weight component of the vehicle parallel to the superelevated

    surface and

    2. The side friction between the tires and the pavement.

    It is impossible to balance centrifugal force by superelevation alone,

    because for any given curve radius, a certain superelevation rate is exactly

    correct for only one operating speed around the curve. At all other speeds,there will be a side thrust outward or inward relative to the center of the

    curve, which must be offset by side friction.

    The general formula to calculate superelevation for various curve radii is

    the following:

    e+f = V2

    / 127R

    where,

    e = Superelevation rate, in meter per meter width of road.

    f = side friction factor or coefficient of side friction between vehicle tires

    and road pavement.

    R = radius of curve, in meters.

    V = design speed in kph.

    The value of f shall be obtained from an expression which recognizes that

    the value of the side friction varies with the speed of travel, the loss in therubber tread and the natural condition of road surface. The acceptable value

    borne out by practice on similar roads is given by:

    f = 0.19 0.0006V

    where V is the same value above.

    Superelevation should not be so excessive as to cause a stationary vehicle

    to slide down the cross slope, regardless of the nature and condition of theroad surface. Superelevation rate shall not be less than the rate of crown

    slope (Table 3.3), i.e. camber or crossfall.

    Table 3.3: Horizontal Curve Design Data Maximum Superelevation

    Superelevation %

  • 8/2/2019 Geometric Standards

    7/28

    Rural Roads - Design ManualSection 3 Geometric StandardsRepublic of YemenMinistry of Public Works and Highways

    Superelevation slopes on curves shall extend the full width of the

    shoulders, except that the shoulder slope on the low side shall not be less

    than the minimum shoulder slope used on tangents.

    For 2-lane roadways, different superelevation slopes for each half of the

    road shall not be used; superelevation shall remain a plane for the full width

    of roadbed, except on transitions.

    The axis of rotation for superelevation is usually the centerline of the road.

    However, in special cases such as desert roads where curves are preceded

    by relatively long tangents, the plane of the superelevation may be rotated

    about the inside edge of pavement to improve perception of the curve. Inlevel country, drainage pockets caused by superelevation may be avoided

    by changing the axis of rotation from the centerline to the inside edge of the

    pavement.

    Superelevation transition is the general term denoting the length of

    highway needed to accomplish the change in cross slope from a normal

    crown section to the fully superelevated section, or vice versa. To meet the

    requirements of comfort and safety the superelevation run-off should beeffected uniformly over a length adequate for the likely travel speed. The

    superelevation transition can be divided into two sections defined as

    follows:

    - Tangent Run-off or Run-out: This is the distance in which the level

    of the edge of pavement is raised to a horizontal plane with the

    centerline grade through the axis of rotation.

    - Superelevation Run-off: This is directly proportional to the total

    Superelevation, which is the product of the lane width and the

    superelevation rate.

    Length of run-off on this basis is directly proportional to the total

    superelevation, which is the product of the lane width and the

    superelevation rate. Section 3.4.2 below shows how to calculate the

    superelevation run-off distance using the rate of pavement rotation method.

    Figure 3.1 shows typical details for superelevation runoff.

  • 8/2/2019 Geometric Standards

    8/28

    Rural Roads - Design Manual

    Section 3 Geometric StandardsRepublic of YemenMinistry of Public Works and Highways

    DOCS-0974-04 3-6

    Figure 3.1 Typical Details for Superelevation Runoff

    Inside Edge of

    Roadway (P.G.L)

    Outside Edge of

    Roadway

    1 / 4 LA

    or 10m Max

    Tangent Run out Length of Superelevation Runoff

    Length of Application (as shown on the profile)

    Total Length of Application

    1 / 4 LA

    or 10m Max

    or 10m Maxor 10m Max

    Inside Edge of

    Roadway (P.G.L)

    Outside Edge of

    Roadway1 / 4 LA

    or 10m Max 1 / 4 LA

    or 10m Max

    Total Length of Application

    Outside Edge ofRoadway

    Superelevation Application Details LA

    +e

    +eo

    -eo

    -e

    +e

    +eo

    -eo

    -e

    B

    B/2e

    B/2e

    B/2e2

    B/2e2

    B/2e

    B/2e

    +e

    -eo

    -e

    +e

    +eo

    -e

    P G L C/L

    B/2e2

    B/2e2

    Sign Convention for CrossfallMethod of Attaining Superlevation of

    Pavement Revolved about

    Centerlines of Roadways

    e

    e

    Inside Edge of

    Roadway (P.G.L)

    Outside Edge of

    Roadway

    1 / 4 LA

    or 10m Max

    Tangent Run out Length of Superelevation Runoff

    Length of Application (as shown on the profile)

    Total Length of Application

    1 / 4 LA

    or 10m Max

    or 10m Maxor 10m Max

    Inside Edge of

    Roadway (P.G.L)

    Outside Edge of

    Roadway1 / 4 LA

    or 10m Max 1 / 4 LA

    or 10m Max

    Total Length of Application

    Outside Edge ofRoadway

    Superelevation Application Details LA

    +e

    +eo

    -eo

    -e

    +e

    +eo

    -eo

    -e

    B

    B/2e

    B/2e

    B/2e2

    B/2e2

    B/2e

    B/2e

    +e

    -eo

    -e

    +e

    +eo

    -e

    P G L C/L

    B/2e2

    B/2e2

    Sign Convention for CrossfallMethod of Attaining Superlevation of

    Pavement Revolved about

    Centerlines of Roadways

    e

    e

  • 8/2/2019 Geometric Standards

    9/28

    Rural Roads - Design ManualSection 3 Geometric StandardsRepublic of YemenMinistry of Public Works and Highways

    3.4 HORIZONTAL ALIGNMENT

    3.4.1 Circular Curves

    The natural terrain, as mentioned earlier, governs the horizontal alignments.

    The roads that are located on escarpments are therefore characterized by the

    multitude of hairpin curves that necessitate a back and forth maneuver in

    order to make the turn. For these roads, no minimum curvature can be

    specified, as speeds will drop to zero during the maneuver.

    For the remaining cases, the minimum radii will have to correspond to the

    design speeds as per the recommendations listed in Table 3.4, determinedusing the superelevation equation defined above:

    R =f)(e127

    V2

    +

    Table 3.4: Horizontal Curve Design Data Minimum Radii (m)

    Rural Intermediate Roads

    Escarpment

    Design

    Speed

    kph

    fmaxFlat/Rolling

    emax = 8%

    Mountainous

    emax = 6% emax =4% emax =6%

    VillageAccess

    Roads

    emax = 6%

    20 0.18 - 15(1)

    15(1)

    15(1)

    15

    30 0.17 - 30 35 30 30

    40 0.17 50 55 60 55 55

    50 0.16 80 90 100 90 90

    60 0.15 125 135 150 135 135

    80 0.14 230 250 -

    100 0.12 395 435 -

    120__

    600 - -

    (1) Not applicable for hairpin curves. Minimum radii to be 12-15m in mountainous and

    escarpment areas. For hairpin curves a compound curve 15-10-15 may be used instead of

    15m or 20m simple curve radius.

    The minimum radius is a limiting value for a given design speed

    determined from the maximum rate of superelevation and the maximum

    side friction factor. Use of sharper curvature for that design speed would

    call for superelevation beyond the limit considered practical or for

    operation with tire friction beyond safe limits, or both

  • 8/2/2019 Geometric Standards

    10/28

    Rural Roads - Design ManualSection 3 Geometric StandardsRepublic of YemenMinistry of Public Works and Highways

    Design Speed, Kph 30 40 50 60 70 85 100 120

    Side Friction Factor 0.33 0.30 0.25 0.23 0.20 0.18 0.15 0.15

    The values for horizontal curve design shown in Table 3.4 should be used

    for rural roads when practical. In constrained situations relaxed values

    based on reduced design speed shown in Table (3.5) may be used.

    In cases where the existing curve has a radius less than those listed, and

    widening entails land acquisition, high excavations or high fills, signs shall

    be posted to reduce the speed to correspond to the adopted radius.

    Table (3.5) Horizontal Curve Design Data Minimum Radii (m)

    for Reduced Design Speed

    Rural Intermediate Roads

    Flat / Rolling Mountainous Escarpment

    Village

    Access

    Roads

    Design

    Speed

    kph

    Reduced

    Design

    Speed

    kph

    fmax

    emax = 8%

    emax = 6% emax = 4% emax = 6% emax = 6%

    20 20 0.180__

    15(1)

    15(1)

    15(1)

    15

    30 25 0.170__

    20 25 20 20

    40 30 0.170 30 30 35 30 30

    50 40 0.170 50 55 60 55 55

    60 50 0.160 80 90 100 90 90

    80 65 0.145 150 160 __ __ __

    100 85 0.135 265 290 __ __ __

    120 100 0.125 385 __ __ __ __

    (1) Not applicable to hairpin curves. Minimum radii shall be 12-15m. in mountainous and escarpment areas. Forhairpin curves, a compound curve of 15-10-15m may be used instead of a 15m or 20m simple curve.

    Note: The above data are for constrained situations based on reductions in design speed up to 15 kph. These areapplicable to roads with ADT 250-400 vpd with limited heavy vehicle traffic (see AASHTO Guidelines for

    Geometric Design of Very Low-Volume Local Roads (ADT400)).

    3.4.2 Transition Curves

    Transition curves are not normally used in Yemen. This section, explains

    how to design them if they are required.

    T iti b i t d b t t t d i l t

  • 8/2/2019 Geometric Standards

    11/28

    Rural Roads - Design ManualSection 3 Geometric StandardsRepublic of YemenMinistry of Public Works and Highways

    Several methods exist for the calculation of transition curves and may be

    used in most situations. The rate of pavement rotation method has been

    adopted here. The rate of pavement rotation is defined as the change in

    crossfall divided by the time taken to travel along the length of transition atthe design speed. The length of transition curve is derived from the

    formula:

    3.6n

    V.eLs =

    where Ls = Length of transition curve (meters)

    e = Superelevation of the curve (meters per meter)

    V = Design speed (km/h)N = Rate of pavement rotation (meters per meter per second)

    The same values of rate of change of pavement rotation should be used to

    calculate the minimum length (Lc) over which adverse camber should be

    removed on a tangent section prior to the transition:

    3.6n

    V.eL nc =

    where Lc = Length of section over which adverse camber is removed

    (meters)

    en = Normal crossfall of the pavement (meters per meter).

    The length of transition curve (Ls) is used to apply the superelevation, with

    the adverse camber removed on the preceding section of tangent (Lc). The

    change from normal cross-section to full superelevation at the start of thecircular curve is achieved over the superelevation run-off distance which is

    the sum of Ls and Lc.

    The resulting combination of horizontal alignment design and

    superelevation for different design speeds is presented in Table 3.5 below:

    Table 3.6: Horizontal Curve Design Data

    Minimum Superelevation Transition LengthSuperelevation Transition Length, m

    Rural Intermediate RoadsDesign Speed,

    KphFlat/Rolling Mountains Escarpment

    Village Access

    20 - - 18 27

    30 29 19 29

  • 8/2/2019 Geometric Standards

    12/28

    Rural Roads - Design ManualSection 3 Geometric StandardsRepublic of YemenMinistry of Public Works and Highways

    3.4.3 Improving Horizontal Alignment

    The major criteria for considering improvements to the horizontal

    alignment are the following:

    1. Safety

    2. Grade profile

    3. Type of Roadway

    4. Design speed

    5. Topography

    6. Cost (Construction, Maintenance, Operation)

    Of these considerations, safety comes first. Therefore, the stopping sight

    distance shall be adequate at all points of the roadway.

    The grade profile shall be considered next in mountainous and escarpment

    section. Critical grades are commonly encountered on existing roads

    located in these sections. The possible improvement of these grades by

    adjusting the horizontal alignment should be investigated in the cases

    where such an adjustment does not entail major earthworks orencroachment into private property.

    The road types that are considered in this Manual are the rural intermediate

    roads and the village access roads. The standards for the horizontal

    alignment will vary for each of these two road types.

    The design speed in turn controls sight distance and hence safety.

    Topography controls both curve radius and design speed to a large extent.

    The economics of construction, maintenance and operation must be

    balanced carefully against other factors in order to produce the safety

    alignment consistent with the level of design.

    3.4.4 Geometric Controls

    The general geometric controls of horizontal alignments that could be

    looked at in considering improvements for the rural intermediate roads arethe following:

    Location of curves: Alignment shall be as direct as possible but consistent

    with topography. A flowing alignment consistent with the contours is

    aesthetically more pleasing than one with long tangents. Natural slopes and

  • 8/2/2019 Geometric Standards

    13/28

    Rural Roads - Design ManualSection 3 Geometric StandardsRepublic of YemenMinistry of Public Works and Highways

    Curve Length and Central Angle: Winding alignment composed of short

    curves shall be avoided since it results in erratic operation. In general, the

    length of curve should be at least 100 m long for a central angle of 5

    degrees. The minimum length shall be increased 30m for each 1 degreedecrease in the central angle. Sight distance or other safety considerations

    shall not be sacrificed thereby. In general, the central angle of each curve

    shall be as small as physical conditions permit, in order to achieve the

    shortest possible route.

    Tangents or Straights Affording Passing Opportunities: An 800m tangent

    is considered adequate for the purpose of providing passing opportunities

    on 2-lane roadways. Passing tangents shall be provided as frequently aspossible in keeping with the terrain. Shorter radii ensuring greater length of

    intervening tangent shall be preferred to sweeping curves of large radii

    which reduce the length of intervening tangents. However, sharp curves at

    the end of passing tangents and especially long tangents shall not be used.

    Compound Curves: These shall be avoided in general. On a compound

    curve the shorter radius shall be least 2/3 of the longer radius. The total arc

    length of a compound curve shall not be less than 100m.

    Curvature on Fills: Other than flat curvature should be avoided on high,

    long fills. In the absence of cut slopes, shrubs, trees, etc., above the

    roadway, it is difficult for drivers to perceive the extent of curvature and

    adjust their operation to the conditions.

    These design controls should be checked for the existing roads under

    consideration. Design solutions should be developed within the specific

    budget constraint associated with every road.

    3.4.5 Widening on Curves

    Pavement widening is needed on certain open curves because:

    a. A large vehicle or truck occupies a greater width, requiring allowance

    for the swept path of the vehicle as it follows a curved path, and

    b. The drivers have some difficulty in steering their vehicles to hold tothe center of the lane and to allow them to maneuver when

    approaching other vehicles.

    The required amount of widening is dependent on the characteristics of the

    vehicles using the road, the radius and length of the curve, and lateral

  • 8/2/2019 Geometric Standards

    14/28

    Rural Roads - Design ManualSection 3 Geometric StandardsRepublic of YemenMinistry of Public Works and Highways

    applied on the inside edge of pavement only, and preferably attained over

    superelevation runoff length. Widening values are given in Table 3.5.

    Figure 3.2 shows how carriageway widening on curves is graduallyattained from the inside of the curve.

    Table 3.7: Horizontal Curve Design Data

    Widening on Curves for all Road Types

    Pavement Widths, mRadius

    4.0-4.9 5.0-5.9 6.0-6.9 7.0

  • 8/2/2019 Geometric Standards

    15/28

    Rural Roads - Design ManualSection 3 Geometric StandardsRepublic of YemenMinistry of Public Works and Highways

    curvature design standards for such alignments are to be reduced to the

    minimum in order to avoid land acquisition.

    The major criteria for considering improvements to the vertical alignmentare the following:

    1. The grade line is a reference line by which the elevation of the

    pavement and other features of the highway are established. Though

    controlled mainly by the topography, other factors such as horizontal

    alignment, safety, sight distance, speed, construction costs and the

    performance of heavy vehicles on a grade should be considered.

    2. All portions of the grade line shall meet sight distance requirements for

    the design speed classification of the road.

    3. In level terrain, the elevation of the grade line is often controlled by

    drainage considerations. In rolling terrain a reasonably undulating

    grade line is desirable from the standpoint of operation and

    construction economy.

    4. Two vertical curves in the same direction separated by a short section

    of tangent grade shall in general be avoided, particularly in valley

    curves.

    5. It is desirable to reduce the grades at intersections. Turns are

    negotiated with reduced mechanical wear and fuel consumption, and

    increased safety.

    6. The standards listed in Tables 3.6 and 3.7 should be met in terms of

    maximum gradient and minimum K-values.

    7. In order to avoid drainage problems in flat and level grades on

    uncurbed pavements, the pavement has to be adequately crowned to

    drain the surface laterally.

    3.5.1 Elements of Vertical Alignment

    The two main components of vertical alignment are:

    i. Vertical curvature, which is governed by sight distance and comfort

    criteria, and

  • 8/2/2019 Geometric Standards

    16/28

    Rural Roads - Design ManualSection 3 Geometric StandardsRepublic of YemenMinistry of Public Works and Highways

    2

    L

    x

    200

    L.Gy

    =

    where y = vertical distance from the tangent to the curve (meters)

    x = horizontal distance from the start of the vertical curve

    (meters)

    G = algebraic difference in gradients (%)

    L = length of vertical curve (meters)

    3.5.2 Crest Curves

    The provision of ample sight distance for the road design speed represent

    the main control for safe operation on crest curves.

    The minimum lengths of crest curves are designed to provide sufficient

    sight distance during daylight conditions. Conditions normally do not allow

    full overtaking sight distance and the design should aim to reduce the

    length of crest curves to provide minimum stopping sight distance in order

    to allow for increasing overtaking opportunities on the gradients on eitherside of the curve.

    Two conditions exist when considering minimum sight distance criteria on

    vertical curves. The first is where sight distance is less than the length of

    the vertical curve, and the second is where sight distance extends beyond

    the vertical curve. Consideration of the properties of the parabola results in

    the following relationships for minimum curve length to achieve the

    required sight distances:

    For S < L:

    ( )221

    2

    200

    .

    hh

    SGLm

    +=

    For S > L:( )

    G

    hhSLm

    2

    212002+

    =

    Where Lm = minimum length of vertical crest curve (meters)

    S = required sight distance (meters)

    G = algebraic difference in gradients (%)

    h1 = driver eye height (meters)

    h bj t h i ht ( t )

  • 8/2/2019 Geometric Standards

    17/28

    Rural Roads - Design ManualSection 3 Geometric StandardsRepublic of YemenMinistry of Public Works and Highways

    Tables 3.8 and 3.11 show the two vertical alignment design parameters for

    various terrain types: minimum vertical curvature in terms of K-values, and

    maximum gradient.

    Table 3.8 shows the minimum K-values for the following conditions using

    the equations above:

    1. Stopping sight distance measured from eye height h1 of 1.080m to a

    stopped vehicle, i.e. object height h2 = 0.6m. K-values are for

    ADT

  • 8/2/2019 Geometric Standards

    18/28

    Rural Roads - Design ManualSection 3 Geometric StandardsRepublic of YemenMinistry of Public Works and Highways

    Table 3.8 Minimum Vertical Curvature Values

    for Very-Low Volume Roads

    (1) K-values are for higher risk locations for ADT 100-250 vpd and all locations for

    250-400 vpd. K-values are for H1 = 1080 mm and h2 = 600 mm representing a stoppedvehicle.

    (2) K-values are based on stopping sight distance measured from eye height of 1.05m and

    an object height of 0.2m.

    Table 3.9: Vertical Alignment Design Data Minimum K-Value for Curves

    K- Value

    Rural Intermediate Roads

    Flat/Rolling Mountainous Escarpment

    Village Access

    Roads

    Design

    Speed

    KphCrest Sag Crest Sag Crest Sag Crest Sag

    20 - - - 1 2 1 2

    30 - - 3 4 3 4 3 4

    40 18 20 5 8 5 8 5 8

    50 28 35 9 11 9 11 - -

    60 55 55 14 15 14 15 - -

    80 85 75 18 20 - - - -

    100 160 105 22 22 - - - -

    120 250 - - - - - - -

    AASHTO ADT

  • 8/2/2019 Geometric Standards

    19/28

    Rural Roads - Design ManualSection 3 Geometric StandardsRepublic of YemenMinistry of Public Works and Highways

    access roads. No-passing signs should be erected where the available sight

    distance does not allow overtaking.

    3.5.3 Sag Curves

    It has been assumed that adequate sight distance will be available on sag

    curves in daylight. However, at night, visibility is limited by the distance

    illuminated by the headlamp beams, and minimum sag curve length for this

    condition is given as:

    For S < L:

    ( )

    tan.200

    .

    1

    2

    Sh

    SGLm

    +=

    For S > L:( )

    G

    ShLm

    tan.200 1 +=

    Where h1 = headlight height (meters)

    = angle of upward divergence of headlight beam (degrees)

    Appropriate values for h1 and are 0.6 meters and 1.0 degrees respectively.The use of these equations can lead to requirements for unrealistically long

    vertical curves as, especially at higher speeds, sight distances may be in

    excess of the effective range of the headlamp beam, particularly when low

    meeting beams are used. Thus, the only likely situation when the above

    equations should be considered for use is on the approaches to fords and

    drifts and other similar locations where flowing or standing water may be

    present on the road surface. Most of these structures occur on low speed

    road where headlamp illumination is more likely to reach the full sightdistances.

    It is recommended that, for most situations, sag curves are designed using

    the driver comfort criterion of vertical acceleration (Table 3.10). The

    K-values used are given in Table 3.8.

    Table 3.10: Minimum Levels of Acceptable Vertical Acceleration

    Design Speed km/h 120 100 85 70 60 50 40 30

    Vertical acceleration

    (Proportion of g in m/sec2)

    0.05 0.06 0.07 0.08 0.08 0.09 0.10 0.10

    3.5.4 Gradient

  • 8/2/2019 Geometric Standards

    20/28

    Rural Roads - Design ManualSection 3 Geometric StandardsRepublic of YemenMinistry of Public Works and Highways

    For very low levels of traffic flow with only a few four-wheel drive

    vehicles, the maximum traversable gradient is in excess of 20 per cent.

    Small commercial vehicles can usually negotiate a 19 per cent gradient,

    whilst two-wheel drive trucks can successfully tackle gradients of 15-16per cent except when heavily laden.

    Gradients of 10 per cent or over will usually need to be paved to enable

    sufficient traction to be achieved, as well as for pavement maintenance

    reasons.

    As traffic flows increase, the economic disbenefits of more severe

    gradients, measured as increased vehicle operating and travel time costs,are more likely to result in economic justification for reducing the severity

    and/or length of a gradient. On the higher design classes of road, the lower

    maximum recommended gradients reflect the economics, as well as the

    need to avoid the build up of local congestion. However, separate economic

    assessment of alternatives to long or severe gradients should be undertaken

    where possible or necessary.

    Table 3.11: Vertical Alignment Data Maximum Gradient

    Gradient, %

    Rural Intermediate RoadsDesign Speed

    KphFlat/Rolling Mountainous Escarpment

    Village Access

    20 - 14(1) 15(2) 15(3)

    30 - 11 11 11

    40 8 10 10 10

    50 7 9 9 -

    60 6 8 8 -

    80 5 7 - -

    100 5 5 - -

    120 5 - - -

    (1) Maximum gradient for new roads. For existing alignments may be relaxed to18%.

    (2) For Hairpin bends, the maximum gradient should not exceed 6% at centerline of

    curve + 15m from each approach. For existing roads, it can be relaxed to 10%.(3) May be relaxed for existing roads for sections where changes in alignment are

    not cost-effective.

    Note: The length of the maximum gradient in this case should not exceed 200m for new

    roads otherwise the speed should be dropped below 20kph. Sections with agradient greater than 10% should be considered for paving. For existing roads

    the length of the maximum gradient may be relaxed to 300m.

  • 8/2/2019 Geometric Standards

    21/28

    Rural Roads - Design ManualSection 3 Geometric StandardsRepublic of YemenMinistry of Public Works and Highways

    journey times and reduced vehicle operating costs. Benefits will increase

    with increases in gradient, length of gradient, traffic flow, the proportion of

    trucks, and in overtaking opportunities. The effect of a climbing lane in

    breaking up queues of vehicles held up by a slow moving truck willcontinue for some distance along the road.

    Experience has shown that climbing lanes are unlikely to be justified other

    than on a small proportion of roads with heavy flows.

    As climbing lanes will be used largely by trucks and buses, they must be a

    minimum of 3.0 meters in width. They must be clearly marked and, where

    possible, should end on level or downhill sections where speed differencesbetween different classes of vehicles are lowest to allow safe and efficient

    merging manoeuvres.

    3.6 CROSS SECTION

    3.6.1 Rationale for Determining Road Widths

    The cross section of a roadway is made up of:

    Number and width of lanes Shoulder width Cross slopes Pavement type Side slopes Drainage Right-of-way width

    Lane and shoulder widths are be determined according to the traffic

    volume, traffic composition and vehicle speed, and characteristics of the

    terrain. The cross section may need to vary over a particular route because

    the controlling factors are changing. The basic requirements are, however,

    that changes in the cross section shall not be made unnecessarily, that the

    cross section standards shall be uniform within each subsection of the route

    and any changes of the cross section shall be effected gradually and

    logically over a transition length.

    In certain cases, however, it may be necessary to accept isolated reductions

    in cross section standards, for example when an existing narrow bridge or

    other structure has to be retained In such cases a proper application of

  • 8/2/2019 Geometric Standards

    22/28

    Rural Roads - Design ManualSection 3 Geometric StandardsRepublic of YemenMinistry of Public Works and Highways

    Road class D: Village Access Roads with low volume of traffic (1000vpd): a running surface width of 6 7m allows vehicles in opposing

    directions to pass safely without the need to slow down or move laterally in

    their lanes.

    Economic considerations call for minimization of road width in order to

    reduce construction and maintenance costs, whilst being sufficient to carry

    the traffic flows efficiently and safely.

    Table 3.12 shows the recommended values for carriageway, shoulder and

    formation widths for various classes of roads.

    Figure 3.1 shows typical road cross section with dimension ranges.

    3.6.2 Carriageways and Shoulders

    As the maximum width of a vehicle is 2.5m, the lane width should be 3.0

    3.5 m. For the higher classes of roads a lane width of 3.5m is prescribed.For low volume traffic of mostly light vehicles on rural local access roads,

    a lane width of 2.75m and even 2.50m may be acceptable. For roads with

    substantial commercial traffic, the paved width should exceed the lane

    width in order to reduce the cost of shoulder maintenance and lessen the

    wheel load concentration at the pavement edges.

    One of the constraints in designing the cross sections, is to ensure that the

    works are limited to the existing right-of-way. This limits the need forexpropriation. The cross section along the rural intermediate roads and the

    village access roads will follow the existing platform width, varying

    generally between 3m and 7m with variable shoulders on both sides. Figure

    3.1 shows the typical cross sections along with the number of lanes varying

    between one and two lanes per section.

  • 8/2/2019 Geometric Standards

    23/28

    Rural Roads - Design Manual

    Section 3 Geometric StandardsRepublic of YemenMinistry of Public Works and Highways

    DOCS-0974-04 3-21

    Table 3.12 Summary of Standards for Various Cross Section Elements

    Cross Slopes (% )

    Road Function

    Approx

    Range of

    Traffic Flow

    (ADT)

    No. of LanesLane width

    (m)

    C/W width

    (m)

    Shoulder width

    (m) Pavement Shoulders Formation

    Rural Intermediate(Governorate)

    400-3000 2 3.0-3.5 6-7 0.0-1.5 2.0% 2-3% 2-3%

    Tertiary(District)

    100-1000 2 2.5-3.0 5-6 0.0-1.0 2.0% 2-3% 2-3%

    Feeder(Village Access)

  • 8/2/2019 Geometric Standards

    24/28

    Rural Roads - Design Manual

    Section 3 Geometric StandardsRepublic of YemenMinistry of Public Works and Highways

    DOCS-0974-04 3-22

    ROAD MARKING

    2-3%

    2-3% 2-3%

    2-3%

    2%2%

    FORMATION WIDTH

    6 - 8

    1 LANE1 LANE

    2.5 3.5 2.5 3.5 0.5 1.50.5 1.5

    CARRIAGEWAY

    GRAVELSHOULDER

    GRAVELSHOULDER

    C

    L

    Min0.5

    1.0

    ALL DIMENSIONS ARE IN METERS

    Crossfall

    Figure 3.3 Typical Cross Section Terminology and Dimensions

    Slope normally

    1V:2H for depthof 2m, or inaccordance with

    type of soil and

    depth

    Slopeaccording to

    type of soil and

    depth of Cut.

    For existing

    alignments a

    slope of 1:10may be used

    Drainage ditch

    usually V-shaped.

    Other shapes may

    also be used.

    Surfacing

    Base

    Subgrade

    l d lbli f

  • 8/2/2019 Geometric Standards

    25/28

    Rural Roads - Design ManualSection 3 Geometric StandardsRepublic of YemenMinistry of Public Works and Highways

    The shoulder widths depend upon the availability of Right-of-Way, type of

    terrain and the type of the road base (bound or unbound). These are

    observed to fall in the range of 0 to 2 meters. No paving is generally needed

    for shoulders except in locations where water is likely to penetrate at theedge of the pavement which is an area particularly vulnerable to structural

    damage. Shoulders should also be paved if the level of traffic flow

    approaches the upper limit for a particular design class. In such cases a

    surface dressing or other seal may be applied.

    For 2-lane paved roads with carriageway width greater than 5 meters, full

    shoulders may be omitted in mountainous and escarpment type terrain

    where the costs of achieving desired cross sections are very high. In thiscase the minimum paved width shall be 5.5 meters and side drains and edge

    barriers should be given special considerations.

    For single lane roads the carriageway width shall be 3.0m. Shoulders

    widths may be 0-1.5m depending on traffic volume, mix and terrain.

    Two lane roads should be delineated by continuous lines at least 10cm wide

    situated on the shoulder immediately adjacent to the running surface.

    Centerline markings are also recommended on roads of at least 5m width.

    3.6.3 Cross Slope

    Cross slope (crossfall) is needed on all roads to assist in the draining of

    water into side drains. However it should not be so great as to be hazardous

    by making steering difficult.

    The normal cross slopes are a function of the type of pavement. Forbituminous pavements, the normal cross slope is generally taken as 2.0%.

    The normal crossfall should be designed as shown in Figure 3.1.

    In the case of rural roads the shoulders are generally not paved. Their

    normal cross fall should be 2 - 3% to ensure faster drainage rate. In case the

    carriageway is superelevated the shoulder should follow the same

    Superelevation rate. The cross slopes of the formation shall be 2-3%. For

    unpaved roads, a cross slope of 3% shall be used.

    Applying steeper crossfalls to the formation not only improve drainage

    performance of various pavement layers, but also provide a slightly greater

    thickness of base material at the edge of the pavement where the bearing

    capacity is the smallest due to the least confinement, and thus where the

    R l R d D i M lR bli f Y

  • 8/2/2019 Geometric Standards

    26/28

    Rural Roads - Design ManualSection 3 Geometric StandardsRepublic of YemenMinistry of Public Works and Highways

    the excavation of ditches on tracks through steep sidelong ground. In such

    cases drainage details should be provided. Figure 3.4 shows this concept

    with is advantages and disadvantages. Drainage channel shape and slope of

    cutting are determined according to soil and terrain types.

    Side Slopes

    V1 V2Sound Rock Weathered Rock Sity Sand H

  • 8/2/2019 Geometric Standards

    27/28

    Rural Roads - Design ManualSection 3 Geometric StandardsRepublic of YemenMinistry of Public Works and Highways

    places and the potential difficulty of reversing. In general, passing places

    should be constructed at the most economic locations as determined by

    terrain and ground condition, such as at transitions from cut to fill, rather

    than at precise intervals.

    The length of individual passing places will vary with local conditions and

    the sizes of vehicles in common use but, generally, a length of 20 meters

    including tapers will cater for most commercial vehicles on roads of this

    type.

    A clear distinction should be drawn between, passing places and lay-bys.

    Lay-bys may be provided for specific purposes, such as parking or busstops, and allow vehicles to stop safety without impeding through traffic

  • 8/2/2019 Geometric Standards

    28/28

    Rural Roads - Design Manual

    Section 3 Geometric StandardsRepublic of YemenMinistry of Public Works and Highways

    DOCS-0974-04 3-26

    Cross-Section with Cross-fall to Valley Side Cross-Section with Cross-fall to Mountain Side

    Advantages Disadvantages Advantages Disadvantages

    - no side drains required, resulting insubstantial reduction in earthworks.

    - less cross-drainage structures required

    - evenly spread surface water runoff along

    road edge reduces erosion problems.

    - potentially dangerous for vehicles slidingwhen surface slippery

    - careful maintenance of surface required toensure water drains evenly over shoulders

    - when gradient exceeds 8 percent, cross-fall must be changed to mountain side.

    - safer for vehicles in wet and slipperyconditions

    - wider formation improves sight distance

    - critical outside edge of road less prone to

    damage- controlled surface drainage outlets

    - more earthworks because of the increasedwidth to accommodate drainage.

    - higher back slopes requiring protection.

    - frequent cross-drainage structures required

    - more expensive

    Source: WB Technical Paper 496.

    Figure 3.5 Alternative Cross Sections in Mountainous Terrain

    Shoulder

    50 - 100

    C

    L

    Carriageway200-250

    Catch water drains whererequired; masonry linedchannel and/or polythenesheet to avoid water from

    seeping into slope material

    Drain60 - 80

    3% -5%

    In situ soil oroptional gravel

    Bio-engineering

    slope protection onslopes below and

    above road

    Side drain: in weakmaterial to be

    masonry linedNote: cut and fill to balance, avoidspoil as much as possible

    Construction steps: to allow for carefulexcavation with minimal disturbance ofnatural slope and regular, well compactedfill layers on stable ground