18
Geomechanical evaluation of caving macro-block options at Chuquicamata Underground Project in Chile using three-dimensional numerical modelling E. Hormazabal Principal Engineer, SRK Consulting, Engineers and Scientists Apoquindo 4001, 7 th Floor Las Condes, Santiago, Chile [email protected] F. Villegas VCP-CODELCO, National Copper Corporation of Chile El Teniente Division Millán 440, Rancagua, Chile [email protected] F. Rovira Project Engineer, SRK Consulting, Engineers and Scientists Apoquindo 4001, 7 th Floor Las Condes, Santiago, Chile [email protected] C. Carranza-Torres Associate Professor of Geotechnical Engineering University of Minnesota, Duluth Campus 1303 Ordean Court, Duluth, MN 55812, USA [email protected] Abstract The Chuquicamata Underground Project in theAtacama Desert in northern Chile is one of the largest planned mining projects in the world to use the method of block caving with macro-blocks option, to mine out copper ore. VCP-CODELCO (Vice-President Office of the National Copper Corporation of Chile) is currently completing a pre-feasibility engineering evaluation of this project, which considers the construction and operation of at least two macro-block mining units to be managed independently from each other. A geo-mechanical study has been carried out to evaluate various options related to pillar sizes and mining sequences for the macro-blocks caving configurations considered for the project. As part of this study, complex three-dimensional continuum models have been developed and applied to evaluate the influence of the above mentioned variables (and existing geological features such as the presence of a major fault and different lithological units) on the mechanical response of the underground openings —particularly, in regard to stress concentration developing in critical areas of the excavations such as macro-blocks pillars and rib-pillars. This paper describes general aspects of the Chuquicamata Underground Project, focalizing mainly on the three-dimensional geo-mechanical analysis carried out to evaluate the feasibility of the project.

Geomechanical evaluation of caving macro-block options at ... · [email protected] F. Rovira Project Engineer, SRK Consulting, Engineers and Scientists Apoquindo 4001, 7th Floor

  • Upload
    others

  • View
    2

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Geomechanical evaluation of caving macro-block options at ... · fvillegas@codelco.cl F. Rovira Project Engineer, SRK Consulting, Engineers and Scientists Apoquindo 4001, 7th Floor

Geomechanical evaluation of caving macro-block options at ChuquicamataUnderground Project in Chile using three-dimensional numerical modelling

E. HormazabalPrincipal Engineer, SRK Consulting, Engineers and ScientistsApoquindo 4001, 7th FloorLas Condes, Santiago, [email protected]

F. VillegasVCP-CODELCO, National Copper Corporation of ChileEl Teniente DivisionMillán 440, Rancagua, [email protected]

F. RoviraProject Engineer, SRK Consulting, Engineers and ScientistsApoquindo 4001, 7th FloorLas Condes, Santiago, [email protected]

C. Carranza-TorresAssociate Professor of Geotechnical EngineeringUniversity of Minnesota, Duluth Campus1303 Ordean Court, Duluth, MN 55812, [email protected]

Abstract

The Chuquicamata Underground Project in the Atacama Desert in northern Chile is one of the largestplanned mining projects in the world to use the method of block caving with macro-blocks option, tomine out copper ore. VCP-CODELCO (Vice-President Office of the National Copper Corporationof Chile) is currently completing a pre-feasibility engineering evaluation of this project, whichconsiders the construction and operation of at least two macro-block mining units to be managedindependently from each other. A geo-mechanical study has been carried out to evaluate variousoptions related to pillar sizes and mining sequences for the macro-blocks caving configurationsconsidered for the project. As part of this study, complex three-dimensional continuum models havebeen developed and applied to evaluate the influence of the above mentioned variables (and existinggeological features such as the presence of a major fault and different lithological units) on themechanical response of the underground openings —particularly, in regard to stress concentrationdeveloping in critical areas of the excavations such as macro-blocks pillars and rib-pillars. Thispaper describes general aspects of the Chuquicamata Underground Project, focalizing mainly onthe three-dimensional geo-mechanical analysis carried out to evaluate the feasibility of the project.

Page 2: Geomechanical evaluation of caving macro-block options at ... · fvillegas@codelco.cl F. Rovira Project Engineer, SRK Consulting, Engineers and Scientists Apoquindo 4001, 7th Floor

Introduction

The Chuquicamata Underground Project in theAtacama Desert in northern Chile is one of the largestplanned underground caving mining operations in the world —see Figure 1. The mining projectcontemplates using the method of block caving with macro-blocks caving option to mine out copperore [1,2,3,4]. VCP-CODELCO (Vice-President Office of the National Copper Corporation of Chile)is finishing a pre-feasibility engineering evaluation of the project, which considers the constructionand operation of at least two macro-block mining units to be operated independently from each other.A critical aspect of designing a caving operation such as the one at Chuquicamata Underground iscontrolling the stress concentrations developed in key areas of the excavations, such as abutments inpillars and rib-pillars. This paper describes general characteristics of the three-dimensional elasto-plastic models developed for Chuquicamata Underground Project with the purpose of validatingvarious macro-block design alternatives considered for the project.

Geological and geotechnical units for Chuquicamata Underground Project

The Chuquicamata porphyry copper ore is a prismatic body that dips vertically towards the west (seeFigure 2). The mineralization at the site is controlled by the West Fault which forms the hangingwallof the copper deposit —the West Fault is a major regional fault with an almost North-South trend,4 to 6 m in thickness and leading to a 150 to 200 m wide shear (or breccia) zone on its westernside. The predominant rock types at Chuquicamata Underground are granodiorites and porphyriesin contact with the West Fault. This shear zone has poor to very poor geo-mechanical quality. Onthe eastern side of the West fault a massive quartz-sericitic rock body occurs; beyond this body,porphyries with different types of alteration are present. The main rock mass types at ChuquicamataUnderground project are shown in Figure 2. A simplified set of geotechnical units considered in thisstudy is shown in Figure 3.

The geotechnical characterization of the Chuquicamata Underground site has been carried out basedon geological-geotechnical borehole logging and surface mapping information [5]. The qualityof the rock mass has been rated using the Rock Mass Rating (RMRL) system by Laubscher [6]and GSI by Hoek et al. [7]. The rock mass geo-mechanical properties for the geotechnical unitshave been evaluated using the Hoek-Brown rock mass failure system [8] as implemented in thesoftware ROCLAB (available from wwww.rocscience.com) and also using results of laboratorytesting (unconfined and triaxial compression tests of intact rock provided by VCP-CODELCO).Calibrations of rock mass properties have been also conducted in exploration drifts [5]. Table 1summarizes mean geotechnical properties parameters for the various rock mass units considered inthe three-dimensional models.

Page 3: Geomechanical evaluation of caving macro-block options at ... · fvillegas@codelco.cl F. Rovira Project Engineer, SRK Consulting, Engineers and Scientists Apoquindo 4001, 7th Floor

200 km

Calama (ChuquicamataUnderground Project)

Antofagasta

Tocopilla

Figure 1. Chuquicamata Underground Project location in relation to Antofagasta andCalama cities in northern Chile.

Page 4: Geomechanical evaluation of caving macro-block options at ... · fvillegas@codelco.cl F. Rovira Project Engineer, SRK Consulting, Engineers and Scientists Apoquindo 4001, 7th Floor

The pre-mining in situ stress field was provided byVCP-CODELCO [2] and is given by the followingprincipal stress components:

σv = 0.026 × h [MPa] (1)

σEW = 0.033 × σv + 9.7 [MPa] (2)

σNS = 0.033 × σv + 10.0 [MPa] (3)

Table 1. Summary of geotechnical properties for the various geotechnical unitsconsidered in the three-dimensional elasto-plastic models —mean values of

properties are indicated.

Geotechnical γ σci mi GSI σt E ν c φ

unit [kN/m3] [MPa] [−] [−] [MPa] [GPa] [−] [kPa] [deg]

RQS (Q<S) 25.9 15 25.0 70 0.06 9.38 0.20 2665 35RQS (Q>S) 26.7 89 10.5 70 0.88 22.57 0.20 4700 41RQS (Q=S) 26.6 52 11.9 70 0.46 13.48 0.20 3670 38BEF (West fault zone) 25.1 37 17.0 35 0.02 1.06 0.28 1910 29ZCI (Intense shear zone) 23.0 20 17.0 35 0.01 0.82 0.28 1435 25Broken material 20.0 − − − − 1.03 0.29 200 38

Notation: γ is the bulk unit weight of the rock mass; σci is the unconfined compression strength of intact rock; mi

is the Hoek-Brown parameter; GSI is the Geological Strength Index; σt is the uniaxial tensile strength of the intactrock; E the rock mass Young’s Modulus; ν is the Poisson’s ratio; c is the equivalent rock mass cohesion; φ is theequivalent rock mass internal friction angle —parameters E, ν, c and φ have been computed with software ROCLAB.

Page 5: Geomechanical evaluation of caving macro-block options at ... · fvillegas@codelco.cl F. Rovira Project Engineer, SRK Consulting, Engineers and Scientists Apoquindo 4001, 7th Floor

MB1

MB2

Figure 2. Geotechnical units considered for the Chuquicamata Underground Project.Red lines indicate the various macro-blocks units considered in the project (outline of

excavations are for production level 1,841 m). Black lines indicate the twomacro-blocks units analyzed as part of the study (macro-block unit MB1 and

macro-block unit MB2).

Page 6: Geomechanical evaluation of caving macro-block options at ... · fvillegas@codelco.cl F. Rovira Project Engineer, SRK Consulting, Engineers and Scientists Apoquindo 4001, 7th Floor

MB1

ZCI

FW

RQS (Q=S)

RQS (Q<S)

RQS (Q>S)

PES

Production Level

Layout (1841)

GEOTECHNICAL UNITS

ZCI

FW

RQS (Q=S)

RQS (Q<S)

RQS (Q>S)

PES

Production Level

Layout (1841)

GEOTECHNICAL UNITS

MB2

MB1

Figure 3. Layout of geotechnical units (at production level) and layout ofunderground caving infrastructure for the two macro-blocks units considered in this

study (production level 1,841 m).

Page 7: Geomechanical evaluation of caving macro-block options at ... · fvillegas@codelco.cl F. Rovira Project Engineer, SRK Consulting, Engineers and Scientists Apoquindo 4001, 7th Floor

aa

Caving Option #1

Caving Option #3

Caving Option #2

Caving Option #4

MB1 MB1MB2 MB2

50

15 20 15

72

72

72

72

36

32

20

21

70

54

370 72

72

54

13

14

year 11

years 8 and 9

year 10

year 9

year 8

year 7

year 7

year 6

year 6

year 5

year 5

year 4

year 3

years 3 and 4 years 1 and 2

MB1 MB1MB2 MB2

year 11

year 10

years 8 and 9

year 9

year 8

year 7

year 6

year 5year 3

year 4

year 6

year 5

year 7

60

30 1515

UCL

PLyears 3 and 4 years 1 and 2

72

72

72

72

36

32

20

370

21

70

54

72

72

54

13

14

years 3 and 4 years 1 and 2

50

20 1515

year 11

year 10

year 9

year 8

year 7

year 6

year 5year 3

year 4

year 5

year 6

year 7

years 8 and 9 72

72

72

72

36

32

20

UCL

PL

year 11

year 10

year 9

year 8

year 7

year 6

year 5

years 8 and 9

year 7

year 6

year 5

year 4

year 3

years 3 and 4 years 1 and 2

60

3015 15

21

70

54

72

72

54

13

14

72

72

72

72

36

32

20

Figure 4. Caving options #1 through #4 analyzed with three-dimensionalelasto-plastic models.

Page 8: Geomechanical evaluation of caving macro-block options at ... · fvillegas@codelco.cl F. Rovira Project Engineer, SRK Consulting, Engineers and Scientists Apoquindo 4001, 7th Floor

MB1 MB1MB2 MB2

Caving Option #5 Caving Option #6

year 11

year 10

year 9

year 8

year 7

year 6

year 5

years 8 and 9

year 7

year 6

year 5

year 4

year 3

50

15 1520

years 3 and 4 years 3 and 4years 1 and 2 years 1 and 2

370

21

70

54

72

72

54

13

14

72

72

72

72

36

32

20

UCL

PL

21

70

72

72

72

54

13

72

72

72

72

36

32

20

60

3015 15

year 11

year 10

year 9

year 8

year 7

year 6

year 5year 3

year 4

year 5

year 6

year 7

years 8 and 9

Figure 5. Caving options #5 and #6 analyzed with the three-dimensionalelasto-plastic models.

Page 9: Geomechanical evaluation of caving macro-block options at ... · fvillegas@codelco.cl F. Rovira Project Engineer, SRK Consulting, Engineers and Scientists Apoquindo 4001, 7th Floor

Numerical Modelling

The main objective of the numerical modelling work done for this project has been to quantify thestress concentration at various critical areas of the planned caving infrastructure (galleries, drifts,pillars, rib-pillars, etc.). The following are the most relevant assumptions made in the models:

Drifts and galleries for extraction and undercutting levels have been considered with a square cross-section of 4 m by 4 m; undercutting height of 14 m and undercutting advance of 25 m have beenassumed; the crown pillar has 16 meters in height; the caving scheme follows the scheme used at‘El Teniente’ mine with a production grid of 15 × 16 meters; block caving method with macro-block variant and conventional caving sequencing has been considered; the West fault has beenincorporated with a uniform thickness of 10 meters.

Six different caving options have been considered in the study. These options, referred to as cavingoptions #1 through caving options #6, do have the following characteristics:

• Caving option #1: a pillar of width 20 m is left at the undercutting level between macro-blocksMB1 and MB2.

• Caving option #2: a pillar of width 30 m is left at the undercutting level between macro-blocksMB1 and MB2.

• Caving option #3: this caving option is similar to the caving option 1, except that the pillarat the undercutting level next to macro-block MB1 is removed before preparation of macro-block MB2 takes place.

• Caving option #4: the option is similar to the caving option 2, except that the pillar at theundercutting level next to macro-block MB1 is removed before preparation of macro-blockMB2 takes place.

• Caving option #5: the option is similar to the caving option 1, except that the pillar at theundercutting level next to macro-block MB2 is removed during extraction of the macro-blockMB1.

• Caving option #6: the option is similar to the caving option 2, except that the pillar at theundercutting level next to macro-block MB2 is removed during extraction of the macro-blockMB1.

Figures 4 and 5 show the different caving options considered in the study. The figures also indicatethe mining sequence (i.e., evolution of caving regions in time) provided by VCP-Codelco [7].

The numerical models for this project have been generated using the code FLAC3D (available fromwww.itasca.com). The models incorporate detailed geometrical features of the caving infrastructure,as well as different lithological units at the site —see, for example, Figures 6 through 9. Numericalalgorithms developed to incorporate the various geo-mechanical features in the numerical models(such as initialization of ground stresses, caving sequencing, etc.) follow current geo-mechanicalmodelling practice —see for example [9].

Although the material constitute models in the numerical model do not present a rheological behavior,the models account for a ‘time’component associated with the excavation sequencing. For example,each of the caving options described earlier on (see Figures 4 and 5) is comprised of 21 phases of

Page 10: Geomechanical evaluation of caving macro-block options at ... · fvillegas@codelco.cl F. Rovira Project Engineer, SRK Consulting, Engineers and Scientists Apoquindo 4001, 7th Floor

excavation and each of these phases of excavation is assumed to occur during a period of 11 years—i.e., the ‘year’ time unit indicated in Figures 4 and 5 relate to each excavation unit indicated in thesame figure.

West faultCaved material

at year 3

MB1

Undercutting

MB2

half-drawbells

closeddrawbells

opendrawbells

production level

under-cutting level

32 m

50 m

16 m

Figure 6. View of the three-dimensional numerical model for caving option #5, foryear 3. The stage shown considers extraction of approximately 32 m of ore columnfor macro-block unit MB1; undercutting of 50 m, and opening of 9 drawbells formacro-block unit MB2. Represented in red is the broken material; represented in

yellow are the excavations; represented in white are the galleries and drifts (beforeexcavation); represented in green is the West Fault (rock mass has been hidden on

purpose for clarity in the presentation).

Page 11: Geomechanical evaluation of caving macro-block options at ... · fvillegas@codelco.cl F. Rovira Project Engineer, SRK Consulting, Engineers and Scientists Apoquindo 4001, 7th Floor

Interpretation of results

The following is a summary of results obtained from the numerical study carried out for Chuquica-mata Underground Project, as reported in detail in [4]:

1. In general, the abutment stress reaches 75 to 85 MPa for caving option #1 and #2, while theabutment stress for others options are lower than 50 MPa —see Figure 7.

2. The abutment stresses are localized in the geotechnical unit RQS (Q > S) while accumulateddeformations are localized in the geotechnical units RQS (Q < S) and RQS (Q = S), foroptions #1 and #2, respectively —see Figure 8.

3. Low-level stresses (corresponding to unloading or deconfinement) are observed 10 m belowthe extraction level for options #3, #4, #5 and #6. For options #1 and #2, the zone of low-levelstresses gets reduced significantly —see Figure 9.

4. Figure 10 shows the stress path for a point located 10 m above the extraction level floor inthe macro-block pillar. For caving options #1 and #2, the peak strength of the rock mass isexceeded at year 3 (undercutting of MB2), while for options #3 and #4, the peak strength ofthe rock mass is exceeded at year 2 (undercutting of MB1). For options #5 and #6, stressdeconfinement and tensile stress development can be observed at year 3 —see Figure 9.

5. Figure 11 shows the stress path for a point located 2 m above the extraction level floor inthe macro-block pillar. For options #1, #2, #3 and #4, the peak strength of the rock massis not exceeded at any year. For options #5 and #6, stress deconfinement and tensile stressdevelopment can be observed at year 3 —see Figure 9.

Page 12: Geomechanical evaluation of caving macro-block options at ... · fvillegas@codelco.cl F. Rovira Project Engineer, SRK Consulting, Engineers and Scientists Apoquindo 4001, 7th Floor

MB2

MB2

MB2

MB2

MB2

MB2

MB1

MB1

MB1

MB1

MB1

MB1

Contoursof MajorPrincipal Stress[in MPa]

-80-70-60-50-40-30-20-10

Caving Option #1 (year 3)

Caving Option #3 (year 3)

Caving Option #5 (year 3)

Caving Option #2 (year 3)

Caving Option #4 (year 3)

Caving Option #6 (year 3)

Stress-concentration Stress-concentration

Figure 7. Comparison of different caving options in terms of major (i.e., most‘compressive’) principal stresses. Note abutment stress concentrations developing in

macro-block pillar for caving options #1 and #2.

Page 13: Geomechanical evaluation of caving macro-block options at ... · fvillegas@codelco.cl F. Rovira Project Engineer, SRK Consulting, Engineers and Scientists Apoquindo 4001, 7th Floor

Contoursof AccumulatedShear Strain[no units]

-0.0010.00000.00250.00500.00750.01000.01250.0150

-80-70-60-50-40-30-20-10

Contoursof MajorPrincipal Stress[MPa]

RQS (Q=S)

RQS (Q<S)

RQS (Q>S)

ZCI

FAULT

ModelGeotechnicalUnits

a)

b)

c)

MB2

MB2

MB2

MB2

MB2

MB2

MB1

MB1

MB1

MB1

MB1

MB1

Caving Option #1 (year 3)

Caving Option #1 (year 3)

Caving Option #1 (year 3)

Caving Option #2 (year 3)

Caving Option #2 (year 3)

Caving Option #2 (year 3)

Figure 8. Representation of results in the model sliced by a horizontal plane located atthe roof of the under-cutting level for caving options #1 and #2. Represented are: a)geotechnical units; b) abutment stresses for geotechnical unit RQS (Q>S) of goodquality; c) shear strain increment for geotechnical unit RQS (Q<S) of poor quality.

Page 14: Geomechanical evaluation of caving macro-block options at ... · fvillegas@codelco.cl F. Rovira Project Engineer, SRK Consulting, Engineers and Scientists Apoquindo 4001, 7th Floor

MB2

MB2

MB2

MB2

MB2

MB2

MB1

MB1

MB1

MB1

MB1

MB1

Caving Option #1 (year 5)

Caving Option #3 (year 4)

Caving Option #5 (year 4)

Caving Option #2 (year 5)

Caving Option #4 (year 4)

Caving Option #6 (year 4)

Contoursof MinorPrincipal Stress[MPa]

-25.0-22.5-20.0-17.5-15.0-12.5-10.0-7.5

Unloading Unloading

UnloadingUnloading

Figure 9. Comparison of different caving options in terms of minor (i.e., most‘tensile’) principal stresses. Note the concentration of low stresses (i.e., unloading)

developing below the extraction level in caving options #3, #4, #5 and #6.

Page 15: Geomechanical evaluation of caving macro-block options at ... · fvillegas@codelco.cl F. Rovira Project Engineer, SRK Consulting, Engineers and Scientists Apoquindo 4001, 7th Floor

Caving Option #1 Caving Option #2 Caving Option #3

Caving Option #4 Caving Option #5 Caving Option #6

-2 0 2 4 6 8 10 12 14 16 18 20 22

σ 1(M

Pa

)

15

79

13

1721

-2 0 2 4 6 8 10 12 14 16 18 20 22

σ 1(M

Pa

)

15

79

13

1721

-2 0 2 4 6 8 10 12 14 16 18 20 22

σ 1(M

Pa

)

15

7

913

1721

-2

-2

0

0

2

2

4

4

6

6

8

8

10

10

12

12

14

14

16

16

18

18

20

20

22

22

0

5

10

15

20

25

30

35

40

45

50

55

60

65

70

75

80

σ 1(M

Pa

)

15

7

9

13

1721

-2

-2

0

0

2

2

4

4

6

6

8

8

10

10

12

12

14

14

16

16

18

18

20

20

22

22

0

5

10

15

20

25

30

35

40

45

50

55

60

65

70

75

80

σ 1(M

Pa

)

15

79

13

17

21

15

79

13

17

21

σ3 [MPa] σ3 [MPa] σ3 [MPa]

σ3 [MPa] σ3 [MPa] σ3 [MPa]

0 10 20

0 10 20

0 10 20

0 10 20

0 10 20

0 10 20

σ 1(M

Pa

40

80

0

20

60

40

80

0

20

60

40

80

0

20

60

40

80

0

20

60

40

80

0

20

60

40

80

0

20

60

2 m

10 m

Extraction of 100% of MB1 and MB2.1121

Extraction of 284m column of MB1 and 126 m column of MB2.0717

Third undercutting of MB2.0313

Extraction of 32m column of MB1. Layout MB2 construction .0309

Third undercutting for MB1.0207

Drawbells opening for MB1 and first undercutting for MB1.0205

Construction of Undercutting drifts for MB1.0101

DESCRIPTIONYEARPHASE

Extraction of 100% of MB1 and MB2.1121

Extraction of 284m column of MB1 and 126 m column of MB2.0717

Third undercutting of MB2.0313

Extraction of 32m column of MB1. Layout MB2 construction .0309

Third undercutting for MB1.0207

Drawbells opening for MB1 and first undercutting for MB1.0205

Construction of Undercutting drifts for MB1.0101

Figure 10. Stress paths for various points at 10 m above the extraction-level-floor inthe macro-block pillar (the Hoek-Brown shear failure envelope is indicated in red).

For caving options #1 and #2, the peak strength of the rock mass is exceeded at year 3(undercutting of MB2); for caving options #3 and #4, the peak strength of the rock

mass is exceeded at year 2 (undercutting of MB1); for caving option #5 and #6,concentration of low stresses (i.e., relaxation stresses) can be observed at year 3

(undercutting of MB2).

Page 16: Geomechanical evaluation of caving macro-block options at ... · fvillegas@codelco.cl F. Rovira Project Engineer, SRK Consulting, Engineers and Scientists Apoquindo 4001, 7th Floor

Caving Option #1 Caving Option #2 Caving Option #3

Caving Option #4 Caving Option #5 Caving Option #6

-2 0 2 4 6 8 10 12 14 16 18 20 22

σ 1(M

Pa

)

-2 0 2 4 6 8 10 12 14 16 18 20 22

σ 1(M

Pa

)

-2 0 2 4 6 8 10 12 14 16 18 20 22

σ 1(M

Pa

)

-2

-2

0

0

2

2

4

4

6

6

8

8

10

10

12

12

14

14

16

16

18

18

20

20

22

22

0

5

10

15

20

25

30

35

40

45

50

55

60

65

70

75

80

σ 1(M

Pa

)-2

-2

0

0

2

2

4

4

6

6

8

8

10

10

12

12

14

14

16

16

18

18

20

20

22

22

0

5

10

15

20

25

30

35

40

45

50

55

60

65

70

75

80

σ 1(M

Pa

)

σ3 [MPa] σ3 [MPa] σ3 [MPa]

σ3 [MPa] σ3 [MPa] σ3 [MPa]

0 10 20

0 10 20

0 10 20

0 10 20

0 10 20

0 10 20

σ 1(M

Pa

40

80

0

20

60

40

80

0

20

60

40

80

0

20

60

40

80

0

20

60

40

80

0

20

60

40

80

0

20

60

1

5

79

13

1721

1

5

79

13

1721

1

5

79

13

1721

15

79

13

1721

1

5

7913

1721

15

79

13

1721

Extraction of 100% of MB1 and MB2.1121

Extraction of 284m column of MB1 and 126 m column of MB2.0717

Third undercutting of MB2.0313

Extraction of 32m column of MB1. Layout MB2 construction .0309

Third undercutting for MB1.0207

Drawbells opening for MB1 and first undercutting for MB1.0205

Construction of Undercutting drifts for MB1.0101

DESCRIPTIONYEARPHASE

Extraction of 100% of MB1 and MB2.1121

Extraction of 284m column of MB1 and 126 m column of MB2.0717

Third undercutting of MB2.0313

Extraction of 32m column of MB1. Layout MB2 construction .0309

Third undercutting for MB1.0207

Drawbells opening for MB1 and first undercutting for MB1.0205

Construction of Undercutting drifts for MB1.0101

2 m

10 m

Figure 11. Stress paths for various points at 2 m above the extraction-level-floor in themacro-block pillar (the Hoek-Brown shear failure envelope is indicated in red). Forcaving options #1, #2, #3 and #4, the peak strength of the rock mass is not exceededin any year; for caving options #5 and #6, tensile and relaxation can be observed at

year 3 (undercutting of macro-block MB2).

Page 17: Geomechanical evaluation of caving macro-block options at ... · fvillegas@codelco.cl F. Rovira Project Engineer, SRK Consulting, Engineers and Scientists Apoquindo 4001, 7th Floor

Final comments

This paper has presented a general description of a geo-mechanical stress analysis carried for theChuquicamata Underground project in Chile. Based on geological and geotechnical characterizationof the site, and by application of three-dimensional elasto-plastic numerical models the stability ofthe macro-block pillars in the proposed caving operations has been assessed.

The results obtained from the analyses suggest that caving option # 6 (one of the six options con-sidered in this study) leads to smaller stress concentration for abutment stresses; the results alsosuggest that for this option stress deconfinement and tensile stress development could potentiallytrigger rock mass instabilities. [It should be mentioned, nevertheless, that in this engineering designstage, no support has been considered for the underground caving infrastructure; thus stability ofgalleries and drifts could potentially and easily achieved by incorporation of support in areas of theinfrastructure that would require so.]

The numerical models developed for this project do not simulate the actual propagation of caving(rather they account for a front of ‘broken’ material that advances in time, as dictated by the givensequencing of excavation). In a next feasibility stage, it is recommended that caving propagationis better taken into account, e.g., by simulating evolution of the front using or softening/strengthreduction schemes.

Acknowledgements

The authors would like to thank CODELCO (National Copper Corporation of Chile), and in partic-ular, Mr. Sergio Fuentes Project Manager and Sergio Olavarria, Project Director of ChuquicamataUnderground Project, for granting permission to publish this paper.

References

1. CODELCO, “Geología y Recursos Minerales para la Ingeniería Conceptual del ProyectoChuquicamata Subterráneo”, Subgerencia de Geología. Dirección de Geología de Desarrollo.División Codelco Norte. CODELCO, Chile, 2007.

2. CODELCO–VCP, “Estudio de Prefactibilidad Proyecto Chuquicamata Subterráneo APIN07DM43”, VCP, CODELCO, Chile, 2009.

3. SRK Consulting Ltda., “Trabajos Geomecanicos Complementarios del Proyecto Chuquica-mata Subterráneo”, Technical report MSC-ICO-SRK-2000-GTE-INF-002-Rev P. SRK Con-sulting Ltda. Santiago, Chile, 2009.

4. SRK Consulting Ltda., “Evaluación Geomecánica de la Malla de Extracción Proyecto MinaChuquicamata Subterráneo”, Technical report MSC-ICO-SRK- 2000-GTE-INF-001-Rev P.Santiago, Chile, 2008.

5. A. Karzulovic, “Revisión Caracterización Geológico Geotécnico Proyecto Mina Chuquica-mata Subterránea”, PMCHS MSC-ICO-AKL-2000-GEM-INF-001-REV P. A. karzulovic &Asoc. Ltda., Chile, 2007.

6. D. H. Laubscher, “A Geomechanics Classification System for the Rating of Rock Mass inMine Design”, J. S. Afr. Inst. Metall., vol 90(10), 1990.

7. E. Hoek, “Strength of rock and rock masses”, ISRM News Journal, 2(2), pp. 4-16 1, 1994.

Page 18: Geomechanical evaluation of caving macro-block options at ... · fvillegas@codelco.cl F. Rovira Project Engineer, SRK Consulting, Engineers and Scientists Apoquindo 4001, 7th Floor

8. E. Hoek, C. Carranza-Torres and B. Corkum, “Hoek-Brown Failure Criterion 2002 Edition”,5th NorthAmerican Rock Mechanics Symposium and 17th TunnelingAssociation of Canada.Editors: R. Hammah, W. Bawden, J. Curran and M. Telesnicki, University of Toronto Press:Toronto, Vol 1, 2002, 267-273, 2002.

9. HCItasca–SRK, “Complementary Geotechnical Studies for Conceptual Design of an Under-ground Mine at Chuquicamata”, HCItasca–SRK, Vancouver, Canada, 2006.