geng1300040h.pdf

Embed Size (px)

Citation preview

  • 8/11/2019 geng1300040h.pdf

    1/12

    Proceedings of the Institution of Civil Engineers

    http://dx.doi.org/10.1680/geng.13.00040

    Paper 1300040

    Received 01/04/2013 Accepted 12/11/2013

    Keywords: excavation/geotechnical engineering/temporary works

    ICE Publishing: All rights reserved

    Geotechnical Engineering

    A soil-nailed excavation for the Brisbane

    Airport Link project, Australia

    Bridges and Gudgin

    A soil-nailed excavation for theBrisbane Airport Link project,Australiaj1 Chris Bridges MSc, PhD, CEng, FICE, MHKIE, RPEQ

    Senior Principal, Coffey Geotechnics Pty Ltd, Brisbane, Australiaj2 James Gudgin MEng, CEng, MICE, RPEQ

    Senior Geotechnical Engineer, Coffey Geotechnics Pty Ltd, Brisbane,Australia

    j1 j2

    The Airport Link project in Brisbane, Australia, involved 15 km of tunnelling including 5.7 km of twin road tunnels,

    busway tunnels and connecting ramps. The Kedron area is the location of a number of entry and exit ramps which

    join the tunnel. The construction site consisted of a number of tunnels crossing each other and formed using a

    number of techniques. Access was required to a maximum of 18 m below ground level to allow for the construction

    of a pile-supported capping slab, which would act as a roof slab for a mined tunnel passing east to west. This paper

    presents details of the design and construction of the soil-nailed walls which provided support to three sides of this

    excavation. The excavation also provided access for commencement of a mined tunnel using canopy tubes headingeastward through one of the soil-nailed walls. The project constraints meant that the solution required close

    coordination between the contractor and the designers of the temporary and permanent works. The excavation was

    constructed successfully and has now been decommissioned. Design risks were managed throughout construction

    through continuous on-site observation and a comprehensive monitoring programme.

    Notationc9 characteristic effective cohesion

    E elastic modulus

    H height of soil-nailed wall

    K constant

    K0 earth pressure coefficientqu unconfined compressive strength

    Su undrained shear strength

    b bulk unit weight

    Poisson ratio

    9v effective vertical stress at centre of length of soil nail

    beyond calculated failure surface

    ave average ultimate bond stress

    9 characteristic effective friction angle

    1. IntroductionThe Brisbane Airport Link project was a complex A$4.2 billion

    road tunnel project, which has provided over 7 km of, mostly

    underground, new road. It was delivered using the publicprivate

    partnership (PPP) model by the special project vehicle (SPV)

    Brisconnections for the Queensland government. The works

    were designed and constructed by a ThiessJohn Holland joint

    venture (TJH) and completed in July 2012. The project required

    15 km of tunnelling owing to the twin boring technique adopted

    and a total of 25 new bridges for interchanges. The project links

    Brisbane airport with the central business district (CBD), with

    access portals at several densely populated suburbs.

    The project was constructed within and beneath busy urban andsuburban areas, just north of the Brisbane CBD. At the tunnel

    portals, cut-and-cover techniques were utilised to transition from

    the mined tunnels onto the surface roads. It was in these areas

    where the biggest interface with the public and Brisbanes busy

    road network occurred.

    This paper presents a case study of a temporary excavation that

    enabled construction of a mined tunnel in the Kedron area of the

    project. The near-vertical excavation was up to 18 m deep and

    was formed using soil nails.

    2. Project brief

    The Kedron Park Hotel tunnel (KPHT) site is located within the

    suburb of Kedron, approximately 8 km from Brisbane CBD and

    10 km from Brisbane airport. The construction site was within

    the complex Kedron portal area of the Airport Link project,

    where the southbound and westbound tunnels cross over.

    1

  • 8/11/2019 geng1300040h.pdf

    2/12

    The project requirement was to allow construction of the westboundexit ramp from the southbound tunnel. The ground conditions were

    such that traditional tunnelling methods were not considered to be

    viable; therefore, a cut-and-cover solution was preferred. Figure 1

    shows the complex interaction of the tunnels in this area; of

    particular relevance to this paper is the interaction between the exit

    ramp from the main southbound tunnel (10) and the entry ramp

    onto the main southbound tunnel which underlies it (11).

    3. Site conditions

    3.1 Geotechnical conditions

    This particular area of Brisbane has complex geological conditions.

    The excavation extended primarily through a relatively thick

    sequence of deeply laterised, Late Triassic aged, Aspley/Tingalpa

    formation which can be found within the top few metres of the

    current ground surface. Its lithology is typically recorded as a grey/

    brown stiff to hard silty clay/gravelly clay, with standard penetra-

    tion test (SPT)Nvalues ranging from the low 30s to refusal.

    Underlying the soil strength material, and just below the base of

    the excavation, the extremely weathered to slightly weathered

    formation is characterised by very low- to low-strength inter-

    bedded sandstone and siltstones, with occasional weathered clay

    seams. The Aspley/Tingalpa formation overlays the Late Triassic

    aged Brisbane Tuff formation. The highly weathered BrisbaneTuff generally has been recorded as having low to medium

    strength increasing to high/very high strength as the effects of

    weathering decrease. Distinctly weathered and altered tuffs have

    variable strength and can be gritty and friable, due to the highquartz content of the rock.

    Key geological risks identified included the possibility of sand

    lenses within the upper residual soils, clay seams within the

    Aspley and Tingalpa formations and the possibility of weak ash

    zones within the tuff. These could lead to planes of weakness or

    instability and groundwater flow paths.

    Based on the boreholes undertaken within the vicinity of the

    excavation, the anticipated ground conditions were

    j up to 5 m of stiff clay, residual soil, overlying

    j up to 15 m of hard clay, residual soil, overlying

    j extremely weathered to highly weathered siltstone, expected

    to be encountered at the base of the excavation.

    The depth to the weathered siltstone varied across the excavation,

    being shallower to the west, expected to outcrop in the walls, and

    deeper to the east.

    Groundwater levels were taken from standpipe readings, which

    were commenced prior to award of the project. These showed a

    fairly consistent depth to the groundwater table of around 10 m

    below ground level.

    3.2 Site constraints

    The site was located within a densely populated urban environ-

    ment, adjacent to Brisbanes key north south arterial road. There

    1. Kedron Park Hotel2. Car park3. Moreton Bay fig tree4. Church hall5. Church6. Lutwyche Road7. Construction loading8. Deep excavations9. Tunnel through wall10. Eastwest tunnel

    (exit ramp mainsouthbound tunnel)

    11. Northsouth tunnel(entry ramp mainsouthbound tunnel)

    8

    82

    3

    7 9

    4

    11

    65

    10

    Figure 1.Location of the Kedron site and key constraints

    2

    Geotechnical Engineering A soil-nailed excavation for the Brisbane

    Airport Link project, Australia

    Bridges and Gudgin

  • 8/11/2019 geng1300040h.pdf

    3/12

    were a number of key constraints (Figures 1and2), given below,which follow the numbering on Figure 1.

    (a) The Kedron Park Hotel and car park (1 and 2) is a large

    building to the north of the excavation; it is a pub housed in a

    historic building of local significance.

    (b) A mature Moreton Bay fig tree (3), which was protected and

    could not be disturbed, is adjacent to the north wall.

    (c) A church hall (4) and church (5) are adjacent to the south

    wall.

    (d) A major arterial road (Lutwyche Road) lies to the west of the

    excavation (6).

    (e) Deep excavations (8) surround the site to the north, west and

    beneath.

    (f) A mined tunnel (10) was to be constructed from east

    to west immediately at the base of the excavation, with

    the tunnel also cutting through the east wall of the

    excavation (9).

    (g) A tunnel (11) runs north to south going underneath the east

    west tunnel was to be constructed simultaneously with the

    excavation and mined tunnel.

    As the design and construction process continued, a number of

    additional issues arose with regard to construction loading and

    processes

    j proposed blasting of the mined tunnel underneath thestructure

    j tower crane immediately behind the wall (1 m offset)

    j other construction loads at minimal distance behind the wall

    owing to the constrained site.

    4. Design

    4.1 Design options and concepts

    The original design concept was to construct a cut-and-cover

    tunnel at this location with contiguous piled external walls and

    using top-down construction to form temporary and permanent

    propping. The total excavation was to be 30 m deep with the

    tunnel roof constructed at 20 m below ground level. The contrac-

    tor explored alternative solutions, particularly focusing on soil

    nailing due to perceived cost and programme benefits.

    The concept design focused on initially reviewing the feasibility of

    a soil-nailed excavation for the full depth of 30 m. Owing to site

    constraints and constructability concerns, the excavation would

    need to have near-vertical walls (.858), with absolute vertical

    walls at the south-east corner, near the church hall, and at least part

    of the east face where the westbound tunnel would penetrate the

    wall. Stability analyses were undertaken to determine a proposed

    nailing pattern for preparation of a costbenefit assessment.

    N

    Hotel

    Inclinometer5

    Piled wallsupportedexcavation

    (cut-and-cover)Soil-nailed excavation

    Tunneladvancethrough

    wall

    Proposedmin

    edtunnel

    Churchhall

    Church

    Tower cranepile supported

    Inclinometer3

    Proposedmined

    tunnelunder A

    Majorarterialroad

    Figure 2.Site layout

    3

    Geotechnical Engineering A soil-nailed excavation for the Brisbane

    Airport Link project, Australia

    Bridges and Gudgin

  • 8/11/2019 geng1300040h.pdf

    4/12

    The adopted solution consisted of a soil-nailed excavation to thetunnel roof at approximately 20 m below current ground level

    (design by the temporary works designer), below which a

    temporary anchored, piled retention system would be installed

    (design by the permanent works designer). This was developed in

    response to concerns from the tunnelling team regarding the out-

    of-balance forces that would be exerted on the northsouth

    tunnel, which passed less than 5 m below the base of the full

    excavation. The 1.2 m dia. piles, spaced at 1.3 m centres, would

    be propped by a temporary arched capping slab and two or three

    rows of ground anchors. The maximum soil-nailed excavation

    depth was now 18 m in order to reach a platform level for

    installation of the piles. The pile-supported excavation extended

    an additional 10 m below the soil-nail wall, allowing for con-

    struction of the elliptical tunnelling (Figure 3).

    After installation of the piles, an arched roof would bridge

    between the piles of the north and south walls. A tunnel would

    then be mined beneath the arch and a permanent lining installed

    between the piled walls.

    The adoption of this temporary works scheme led to major

    changes in the permanent works over the original tender design.

    A smooth interface between the two design teams was, therefore,

    crucial and a series of meetings were held between the two teams

    of designers and the contractor to develop the design (temporaryand permanent) for this section of the works. These meetings

    were also important in overcoming the concern of some indivi-duals in the construction team with respect to the height and

    inclination of the soil-nail wall. This was due to the lack of

    experience of soil nailing within the construction team and the

    perception that significant deformations would result.

    4.2 Detailed design

    The Australian standard on earth retaining structures (AS 4678-

    2002 (Standards Australia, 2002)) includes the design of soil-

    nailed walls as an informative appendix only. The complexity of

    this wall as well as its height, however, specifically moves it

    outside the limitations of this standard. Various international

    guides and standards were available at the time of design,

    including BS 8006:1995 (BSI, 1995), Ciria C637 (Phear et al.,

    2005), Geoguide 7 (GEO, 2008) and Geotechnical Engineering

    Circular No. 7 (Lazarte et al., 2003). The authors had previous

    knowledge of Ciria C637 and this guide was adopted. The design

    also had to comply with the various project specifications and the

    project deed, which incorporated client-specific requirements that

    fell outside the specifications.

    Ciria C637 uses the limit state design methodology of Eurocode

    7 (BSI, 2004), where partial factors are applied to the soil

    strengths and to the actions affecting the wall. The partial factors

    used were as detailed in Table 8.2 of Ciria C637 and arereproduced inTable 1.

    Construction sequence:

    1.

    2.

    3.

    4.

    5.

    Top heading of southboundtunnel constructed.Soil-nailed excavationcompleted.Bored piles installed and roofslab formed.Pilot tunnel of westboundtunnel constructed withground anchors installed asexcavation proceeded. Southboundtunnel completed.

    Westbound tunnel completed.

    Church hall

    15mlongsoil

    nailsExcavation

    backfilled oncompletion ofmined tunnel

    roof

    Temporaryexcavation level

    Mined tunnel(westbound)

    2

    3

    4

    5

    3 3

    4

    1

    4

    Southboundmined tunnel

    Permanentstructure

    Medium-strengthsiltstone

    Very low-strengthsiltstone

    Extremelyweatheredsiltstone

    Residual soilvery stiff tohard clay

    Residual soilstiff clay

    Figure 3.Construction sequence (section A)

    4

    Geotechnical Engineering A soil-nailed excavation for the Brisbane

    Airport Link project, Australia

    Bridges and Gudgin

  • 8/11/2019 geng1300040h.pdf

    5/12

    A summary of the geotechnical parameters adopted in the

    analyses is presented in Table 2. The geotechnical parameters

    were derived from the available site investigation data, including

    limited laboratory testing. These parameters were agreed by the

    teams designing the temporary and permanent works.

    The design was carried out using limit state design and a limit

    equilibrium method of analysis. Two software packages were

    utilised for design work, namely

    j

    Slope/W, limit equilibrium slope stability analysis programdeveloped by Geostudio

    j Snailz, soil reinforcement program developed by Roadway

    Geotechnical Engineering, California Department of

    Transportation.

    Snailz was primarily used to determine the soil nail length required

    based on the design nail spacing, borehole diameter, soil properties

    and facing strength. This analysis was then checked using Slope/W.

    The two programs assess soil nails differently, with Snailz allowing

    for different bond stresses for each soil type and including the

    effect of the soil nail head in the analysis. Slope/W, however, allows

    for a different bond stress for each nail and a more complex

    geometry can be analysed. On this project Snailz generally gave

    higher factors of safety than Slope/W, most likely owing to Snailz

    considering the contribution of the nail head in the analyses. A

    typical section analysed is shown inFigure 4.

    The characteristc bond or skin friction (ave) was initially

    estimated usingEquation 1based on equation 8.4 of Ciria report

    C637

    Parameter Design approach 1,combination 1 (DA1-1)

    Design approach 1,combination 2 (DA1-2)

    Actions (A), multiply action by partial factor given below

    Permanent unfavourable 1.35 1.0

    Permanent favourable 1.00 1.0

    Variable unfavourable 1.50 1.3

    Variable favourable zero zero

    Materials (M), divide material strength by partial factor given below

    tan9 1.0 1.25

    c9 1.0 1.25

    Su 1.0 1.40

    qu 1.0 1.40

    Bulk density 1.0 1.00

    Resistance (R)

    Overall stability 1.0 1.0

    Bearing capacity 1.0 1.0

    Sliding 1.0 1.0

    Table 1.Partial factors used in analyses

    Geological unit Description b: kN/m3 c9: kPa 9: degrees E: MPa ave: kPa K0

    Residual soil Stiff clay 21 5 25 40 75 0.3 0.6

    Residual soil Hard clay 21 5 28 80 125 0.3 0.6

    Siltstone Very low low

    strength

    22 22.5 30 90 125 0.3 1.0

    Note:b, bulk unit weight;c9, effective cohesion;9, effective friction angle;E, elastic modulus;ave, average ultimate bond stress; , Poisson

    ratio;K0, earth pressure coefficient.

    Table 2.Characteristic material properties used in analyses

    5

    Geotechnical Engineering A soil-nailed excavation for the Brisbane

    Airport Link project, Australia

    Bridges and Gudgin

  • 8/11/2019 geng1300040h.pdf

    6/12

    tave (K9vtan 9 c9) (kPa)1:

    where,9v is the effective vertical stress at the centre of the lengthof a soil nail beyond the calculated failure surface (kPa), 9 is

    the effective friction angle (degrees), c9 is the effective cohesion

    (kPa) andKis a constant taken as 1.

    The results of the assessment of the characteristic bond were

    compared to typical values of bond stress typically experienced

    for this material in South-East Queensland and appropriate values

    of characteristic bond were adopted for each material. This was

    confirmed during the design phase by the execution of an

    ultimate load test.

    In order to determine the maximum working loads on each rowof soil nails, analysis of each stage of construction of the soil-

    nailed walls was carried out using a global factor of safety

    approach (unfactored soil parameters) within Snailz, whereas

    overall stability was checked using partial factors.

    The two-dimensional finite-element analysis software, Plaxis, was

    used to predict ground movements, particularly in the vicinity of

    the church hall and church at the crest of the south wall. The

    construction sequence considered in the Plaxis modelling consid-

    ered the construction of the temporary and permanent works.

    Models were generated by both the temporary works and

    permanent works design teams and compared and agreed before

    construction began. The construction sequence adopted was as

    follows (Figure 3).

    (a) Construct southbound top heading.

    (b) Staged soil nail excavation to the base of excavation.

    (c) Install contiguous piles from base of excavation.

    (d) Construct roof slab.

    (e) Construct westbound pilot tunnel.

    (f) Excavate and complete southbound tunnel.

    (g) Finish westbound tunnel.

    In the Plaxis analysis, characteristic values were adopted and the

    predicted and actual ground movements (measured by inclin-

    ometers) at two sections on achieving final excavation level are

    given inFigure 5.

    As a requirement of the project deed, a minimum surcharge of

    20 kPa had to be adopted in all significant temporary works

    designs. In addition, specific surcharges from construction plant

    including mobile cranes and concrete trucks at the crest of thewalls also had to be considered. Proposed equipment was

    discussed with the construction team during the early stages of

    design development.

    Soil nails of 32 mm dia. with a steel grade of 500 MPa were

    nominated. These were installed in 150 mm dia. holes at an angle

    of 108 below the horizontal in 40 MPa grout. The nail lengths

    varied from 10 m to 15 m due to the change in excavation height,

    varying load conditions around the excavation and improving

    ground conditions with depth.

    The soil nails were installed with a vertical spacing of 1 .2 m and

    a horizontal spacing of 1.5 m centre to centre (Figure 4). The soil

    nail heads consisted of a 200 mm3 200 mm 3 20 mm thick

    plate placed on top of the shotcrete surface and held in place by a

    nut. The shotcrete was nominally 100 mm thick with a minimum

    strength of 40 MPa at 28 days and had a single layer of mesh

    Base of soilnailed wall

    Very lowlow-strength siltstone

    Soil nails:Top row 05 m below crestSpacing 12 m V: 15 m HTen 15 m nailsFour 12 m nailsInclination 10 below horizontal

    Sub-horizontal drains:Top row 5 m longBottom row 10 m longSpacing 5 m HInclination 10 above horizontal

    Residual soil hard clay

    Residual soil stiff clay

    GWL (RL12)

    RL 222

    RL 5

    Figure 4.Typical section

    6

    Geotechnical Engineering A soil-nailed excavation for the Brisbane

    Airport Link project, Australia

    Bridges and Gudgin

  • 8/11/2019 geng1300040h.pdf

    7/12

    (SL82) placed centrally throughout, with an additional layer of

    mesh (1 m2) at the soil nail heads.

    The structure was nominated as being required for 2 years;

    however, the project deed stipulated a design life of 5 years forthe tensile elements. Given the short duration, durability was

    considered through sacrificial thicknesses of steel elements.

    Sheathing of the soil nails, as required for permanent soil nails,

    was not undertaken.

    The detailed design took account of the site constraints as

    detailed in Section 3.2. The location of the Moreton Bay fig tree

    immediately at the crest of the north wall, for example, meant

    that the upper row of soil nails beneath the tree could not be

    installed. The project arborist recommended that the cut face was

    protected by plastic sheeting beneath the shotcrete so that the soil

    adjacent to the tree would not dry out. The shotcrete was,therefore, thickened and heavily reinforced over this zone with

    the next row of soil nails designed to take the additional load.

    The location of the tower crane led to the position of the soil

    nails being amended to avoid the supporting piles. Similarly, the

    soil nails were also located to avoid the inclinometers behind the

    wall facing.

    The interaction between the wall and the proposed tower crane

    was considered in detail. This included finite-element modelling

    to assess the soilstructure interaction within the system. It was

    critical to design the tower crane foundation within the rotation

    tolerance of the crane. The relative movement of the soil-nailed

    wall and the tower crane piles led to additional down-drag, or

    negative skin friction, in the foundation. As a result, design loads

    in the piles were estimated to be greater than that from the static

    load of the crane itself.

    The most significant effect on the design, however, was the

    location of the future tunnel portal on the eastern face of the

    excavation (Figure 6). Here, the steel nails were replaced by

    glass-reinforced plastic (GRP) nails to enable the bars to be

    ripped up during tunnelling. The GRP nails were 40 mm dia.installed in 150 mm grout holes. Unlike steel bars, which can

    behave plastically and creep after their tensile capacity has

    been reached, the GRP nails require greater deformation to

    achieve their ultimate capacity, after which they fail in a brittle

    manner. The GRP nails adopted had a break load capacity of

    860 kN.

    Given that the excavation was to remain in place for 24 months,

    0

    5

    10

    15

    20

    5 0 5 10 15 20 25 30 35 40 45 50 55

    Horizontal displacement: mm

    Actual

    Predicted0

    5

    10

    15

    20

    5 0 5 10 15 20 25 30 35 40 45 50

    Reducedlevel:m

    AHD

    Reducedlevel:m

    AHD

    Horizontal displacement: mm

    Actual

    Predicted0

    2

    4

    6

    8

    10

    12

    14

    16

    18

    20

    0 50 100

    Reducedlevel:m

    AHD

    Base depth(RL 68)

    Base depth(RL 68)

    SPT : blowsN

    Residual soil stiff clay

    Inclinometer 5

    Base depth(RL 68)

    Residual soil hard clay

    Moderatelyweathered siltstone

    Moderatelyweathered

    siltstone

    Residualsoil stiffclay

    Residualsoil hardclay

    Inclinometer 3

    Figure 5.Comparison of predicted against actual lateral wall

    movement

    Figure 6.East wall during construction showing canopy tubes

    set out

    7

    Geotechnical Engineering A soil-nailed excavation for the Brisbane

    Airport Link project, Australia

    Bridges and Gudgin

  • 8/11/2019 geng1300040h.pdf

    8/12

    the design called for specific drainage measures to be installed.This included 150 mm wide geocomposite strip drains which

    were installed between the soil nails and beneath the shotcrete at

    a 2.5 m horizontal spacing. In addition, the ground investigation

    had identified the possibility of a perched water table within the

    upper stiff clay layer. Two rows of sub-horizontal drains were,

    therefore, installed: one at the bottom of the stiff clay layer and

    another at the bottom of the excavation. Both rows of sub-

    horizontal drains were placed at a 5 m horizontal spacing.

    The project team was concerned about the impact of ground

    movements on the church hall and church. Although the excava-

    tion would generate some ground movement, additional move-

    ments were anticipated owing to the two tunnels beneath the

    excavation, as well as the general dewatering of the area due to

    nearby cavern construction. A monitoring programme for the

    church and church hall was implemented in addition to the

    monitoring already in place around the excavation. This included

    multiple targets and settlement plates, and staged trigger levels

    based on the status of construction.

    5. ConstructionSoil-nailed wall construction is a top-down technique which

    requires a staged approach to construction. The following

    construction sequence was nominated.

    (a) Excavate to 0.5 m below the upper row of soil nails.

    (b) Drill, install and grout first row of nails.

    (c) Place strip drains and mesh on excavated face and shotcrete.

    (d) Attach head plate and nut.

    (e) Excavate to 0.5 m below the next row of soil nails.

    (f) Repeat steps (b) to (e).

    (g) Repeat to bottom of excavation, ensuring that horizontal

    drains are installed as the excavation proceeds.

    The construction was complicated by the need initially to

    maintain an access ramp from the south wall and into the

    excavation for as long as possible, until full access could beprovided from the cut-and-cover tunnel to the west of the

    excavation to service the works. This meant that the nails on the

    south wall could not be installed until a majority of the nails on

    the north and east walls were complete. Figure 7 shows the

    varying excavation depths across the structure while the access

    ramp was in operation. This required close coordination between

    the site and design team to ensure that an adequate width of ramp

    was left in place to provide stability to the wall.

    Full-time observation of the works was undertaken by a represen-

    tative of the temporary works designer owing to the high level of

    risk associated with this excavation. Their responsibilities in-

    cluded

    j mapping of the excavation to confirm that the geotechnical

    conditions were consistent with design

    j nomination of test nails and observation of nail testing

    j raising non-conformance reports as necessary

    j responding to requests for information from the

    construction team

    j providing design direction to allow construction to proceed

    without undue delay

    j reviewing the daily monitoring results.

    Acceptance testing to assess workmanship was specified on

    production nails at a rate of six tests per 100 nails in accordance

    with Queensland Department of Transport and Main Roads

    standard MRTS03 (TMR, 2010), with the test nails nominated by

    the designer. This required the nails to be subjected to loads of

    1.5 times the working load for three cycles with a maximum

    deflection of the soil nail not exceeding 0.1% of its length.

    Ultimate load testing to confirm design parameters was also

    specified and six tests on short bond lengths were undertaken at

    different levels within the excavation. It was decided that theultimate load tests were to be carried out within the excavation

    rather than in the excavation face, which enabled the nails to be

    exhumed and examined after testing as a measure of construc-

    tion quality control. Figure 8 is a photograph showing one of

    the exhumed nails. The exhumed soil nails showed that the

    grout column around the nail remained intact after failure, with

    some nails showing a clean break in the grout at the end of the

    nail. This indicated that the soil nail and grout failed as one

    element as it was pulled out of the excavated face. All testing

    was carried out in accordance with the recommendations of

    Ciria C637.

    All the soil nails passed the acceptance tests; however, there were

    issues with poor-quality centralisers being used, which collapsed

    under the weight of the steel bars. This product was quickly

    replaced with one of acceptable quality. The ultimate load tests

    confirmed the design parameters used with calculated ultimate

    Figure 7.Access ramp into excavation

    8

    Geotechnical Engineering A soil-nailed excavation for the Brisbane

    Airport Link project, Australia

    Bridges and Gudgin

  • 8/11/2019 geng1300040h.pdf

    9/12

    bond stresses up to 250 kPa in the hard residual clay. Some tests

    were cut short as failure had not occurred when the load had

    reached 80% of the ultimate tensile capacity of the nail, beyond

    which it was not safe to continue the test.

    On completion of the excavation, the permanent works began

    with piles being installed along the toes of the north and southwalls and part of the east wall. In addition, 114 mm dia.

    canopy tubes, 12 m to 15 m long, were installed in the east

    wall in preparation for the mined tunnel. Once the piles were

    installed, fill was placed inside the excavation in order to

    provide a form for the tunnels arched roof. The reinforced

    concrete roof arch was cast (Figures 9 and 10). The tunnel was

    then mined and permanent lining was placed beneath the arch.

    Upon completion of tunnelling, the excavation was backfilled

    with flowable fill.

    During construction the issue of rock blasting within the tunnels

    during mining was raised. An independent specialist assessed the

    effect of blasting on the soil nailing and concluded that there

    would be no effect. The design team reviewed this assessment

    and reanalysed selected wall sections in Snailz using unfactored

    parameters and a horizontal coeffiecient of acceleration of 0.2,

    while targeting a factor of safety of greater than 1.

    6. PerformanceWall movements were monitored by reflector survey prisms

    which were fixed to the shotcrete wall at two levels as the

    excavation proceeded. In addition, lateral movements were also

    monitored by inclinometers which were located around the

    excavation, along with ground settlement monitoring markers to

    measure vertical deformations. Trigger levels were established for

    all monitoring points and the results of all monitoring were

    distributed around the design and construction teams. The wall-

    monitoring system, with the exception of the reflector survey

    prisms, was unchanged from that planned for the original piled

    wall.

    Two monitored sections of the excavation are presented in Figure

    Figure 8.Exhumed nail following ultimate load testing

    Figure 9.Reinforcement for arch capping slab

    Figure 10.Aerial photograph during arch construction

    9

    Geotechnical Engineering A soil-nailed excavation for the Brisbane

    Airport Link project, Australia

    Bridges and Gudgin

  • 8/11/2019 geng1300040h.pdf

    10/12

    5, which shows the predicted and actual lateral ground movementat completion of the full depth of excavation. The encountered

    ground conditions at inclinometer 3 comprised approximately

    4 m of stiff residual clay over 8 m of hard residual clay, overlying

    moderately weathered siltstone. At this location the measured

    lateral ground movements towards the excavation reached 31 mm

    at completion of the excavation, against a predicted movement of

    40 mm. The prisms were installed as the excavation proceeded

    and could only measure deflections from the time of installation.

    They would not, therefore, show the total movements of the wall,

    but would be indicative of the deformations that were occurring

    and could be checked against the inclinometers, which were

    approximately 2 m back from the wall face. At completion of the

    excavation the prisms at this section had moved 28 mm at 18 .2 m

    AHD (Australian height datum) and 12 mm at 13.4 m AHD, 2 m

    and 6.8 m below the wall crest, respectively. The upper prism

    compared well to the inclinometer data, but the lower prism

    showed much less movement, which may be indicative of the

    delay in placing the prism after excavation.

    At inclinometer 5, the ground conditions comprised approxi-

    mately 4 m of stiff residual clay over 10 m of hard residual clay,

    overlying moderately weathered siltstone. At this location the

    measured ground movements towards the excavation at the

    inclinometer reached 15 mm at completion of the excavation

    against a predicted movement of 50 mm. The prism on thissection showed movements of 16 mm at 17.3 m AHD (1.6 m

    below the wall crest) and appears to be in agreement with the

    inclinometer. The ground surface movements were approximately

    11 mm at 2 m behind the wall crest, reducing to 6 mm at 8 m

    from the wall face and 0 mm at 13 m.

    The ground movements at the church hall and church were less

    than 10 mm at the completion of the excavation and no signs of

    damage or distress were noted. Similarly, at the hotel measured

    ground movements were less than 5 mm and again no damage

    was noted.

    The ground conditions encountered were generally consistent

    with the design model. It is considered that the inclinometers

    measured less movement than predicted as the surcharges consid-

    ered in the analyses were never fully achieved on site. In addition,

    the determination of deformations in Plaxis relies upon soil shear

    strength and soil stiffness parameters. As no direct measurement

    of stiffness was undertaken during the investigation and testing

    programme, the stiffness was derived from a conservative estima-

    tion based on undrained shear strength using empirical calcula-

    tions and local experience. This adoption of conservative values,

    which was due to the concern of impact on adjacent structures,

    may have led to an underestimation of soil stiffness and, hence,

    less movement than anticipated. This effect is noted more in the

    results of inclinometer 5, which has the greater soil thickness.

    The greater movement at inclinometer 3 can, to some degree, be

    explained by the presence of a laydown area at the crest of wall,

    which would have added a surcharge throughout the constructionperiod on this section of the wall. In addition, the wall at

    inclinometer 3 was higher than that at inclinometer 5.

    The following is a general summary of the wall behaviour.

    j Horizontal wall movements were approximately 0.2% of the

    wall height.

    j Vertical wall movements were between 70% and 100% of the

    horizontal movements.

    j The measured wall movements were consistent with case

    histories (Figure 11).

    j The inclinometers identified lateral movement at the residual

    claysiltstone boundary.

    j Measured wall movements were less than those estimated by

    Plaxis.

    j There was no visual evidence of significant wall movement.

    j There was no identifiable damage to the church and church

    hall.

    7. Summary and conclusionThe authors believe that this is one of the deepest soil-nailed

    excavations to date in Australia. During the design stage, there-

    fore, there was concern by the main contractor regarding the

    feasibility of the soil-nailed solution. The reasons for this concern

    were many and included

    j lack of experience of the construction and verification teams

    and general lack of Australian experience with soil nailing

    j the large depth of excavation

    j a perception of greater ground deformation resulting from the

    use of soil nails

    j proximity of adjacent structures

    j complicated construction sequence involving two tunnels to

    be constructed beneath the final excavation.

    The temporary works designers were able to demonstrate to key

    personnel within the construction and verification teams thefeasibility of the solution, and early involvement of the temporary

    works design team with both the contractor and permanent works

    design team enabled a smooth interface between the two compo-

    nents of the work. The agreement of the design approach and

    parameters to be used in design was particularly important and

    allowed for alignment of the permanent and temporary analytical

    models. This led to an agreed set of monitoring trigger levels for

    each monitoring point around the excavation.

    The temporary works team remained fully involved with the

    construction team throughout the excavation and installation of

    the soil nails, including having full-time representation on site.

    This was crucial as the authors have seen many occurrences of

    over-excavation and subsequent wall movement during soil-nailed

    wall construction, due to contractors inexperience. This also

    ensured that quality issues such as the use of inappropriate

    centralisers were identified and corrected quickly. The contrac-

    10

    Geotechnical Engineering A soil-nailed excavation for the Brisbane

    Airport Link project, Australia

    Bridges and Gudgin

  • 8/11/2019 geng1300040h.pdf

    11/12

    tors respect for the risks involved with this element of the works

    was the key to its success.

    Locating the instrumentation within a metre of the wall facerequired the use of an experienced survey team, which enabled

    the soil nails to be placed such that they did not impact on the

    inclinometers or crane piled foundations. The results of the

    monitoring indicate that the movement of the wall was within

    those typically expected (Figure 11).

    Ultimately, over 1500 soil nails, steel and GRP were installed in

    this excavation. Ground movements were less than anticipated,

    with no damage occurring to adjacent structures, and the soil-

    nailing option reduced the programme time by 3 months, com-

    pared with the original piled wall scheme.

    AcknowledgementsThe authors would like to acknowledge the Thiess and John

    Holland joint venture for their support in the preparation of this

    paper.

    REFERENCES

    Bruce DA and Jewell RA (1986) Soil nailing: application and

    practice Part 1.Ground Engineering19(8): 10 15.

    Bruce DA and Jewell RA (1987) Soil nailing: application and

    practice Part 2.Ground Engineering20(1): 21 33.

    BSI (1995) BS 8006:1995: Code of practice for strengthened/

    reinforced soils and other fills. BSI, London, UK.

    BSI (2004) BS EN 1997-1:2004: Eurocode 7: Geotechnical design

    Part 1: General rules. BSI, London, UK.

    Clough GW and ORourke TD (1990) Construction induced

    movements of in situ walls. Proceedings of the Conference on

    the Design and Performance of Earth Retaining Structures,

    Connell University, Ithaca, NY, USA, pp. 439470.

    Durgunoglu HT, Keskin HB, Kulac HF, Ikiz S and Karadayilar T

    (2007a) Performance of soil nailed walls based on casestudies. Proceedings of the XIV European Conference on Soil

    Mechanics and Geotechnical Engineering, Madrid, Spain, pp.

    559564.

    Durgunoglu HT, Keskin HB, Kulac HF, Ikiz S and Karadayilar T

    (2007b) Performance of very deep temporary soil nailed

    walls in Istanbul. Proceedings of the TC17 Ground

    Improvement Workshop, XIV Conference of the International

    Society for Soil Mechanics and Geotechnical Engineering,

    Madrid, Spain.

    GEO (2008)Guide to Soil Nail Design and Construction.

    (Geoguide 7). Government of the Hong Kong Special

    Admininstrative Region, Hong Kong.Ho CL, Ludwig HP, Fragaszy RJ and Chapman KR (1989) Field

    performance of a soil nail system in loess.Proceedings of

    Foundation Engineering: Current Principles and Practices,

    Evanston, IL, USA, pp. 12811292.

    Lazarte CA, Elias V, Espinoza D and Sabatini PJ (2003)

    Geotechnical Engineering Circular No. 7: Soil Nail Walls.

    Federal Highway Administration, US Department of

    Transportation, Washington, DC, USA.

    Phear A, Dew C, Ozsoy B et al. (2005)Soil Nailing Best

    Practice Guidance. Ciria, London, UK, Ciria C637.

    Shen CK, Bang S, Romstad KM, Kulchin L and Denatale JS (1981)

    Field measurements of an earth support system. Proceedings

    of the American Society of Civil Engineers Journal of the

    Geotechnical Engineering Division 107(12): 16251642.

    Standards Australia (2002) AS4678-2002: Australian standard

    Earth-retaining structures. Standards Australia, Sydney,

    Australia.

    0

    0020

    0040

    0060

    0080

    0100

    0120

    0140

    0 5 10 15 20 25 30 35

    Lateralwallmovement,

    :m

    h

    Wall height, : mH

    Bruce and Jewell (1986, 1987)

    Durgunoglu (2007a, 2007b)et al.

    Clough and ORourke (1990)

    Thompson and Miller (1990)

    Stocker and Riedinger (1990)

    Ho (1989)et al.

    Shen (1981)et al.

    Airport link project

    h/ 05%H

    h/H 04%

    h/H 02%

    h/H 01%

    Figure 11.Lateral wall movement plotted against wall height (comparison with case histories (seeBruce and Jewell, 1986;Clough and

    ORourke, 1990;Durgunogluet al., 2007a,2007b;Ho et al., 1989;Shenet al., 1981;Stocker and Riedinger, 1990;Thompson and

    Miller, 1990)

    11

    Geotechnical Engineering A soil-nailed excavation for the Brisbane

    Airport Link project, Australia

    Bridges and Gudgin

  • 8/11/2019 geng1300040h.pdf

    12/12

    Stocker MF and Riedinger G (1990) Bearing behaviour of nailedretaining structures. Proceedings of a Conference on the

    Design and Performance of Earth Retaining Structures,

    Cornell University, Ithaca, NY, USA, pp. 612628.

    Thompson SR and Miller IR (1990) Design, construction and

    performance of a soil nailed wall in Seattle, Washington.

    Proceedings of a Conference on the Design andPerformance of Earth Retaining Structures, Cornell

    University, Ithaca, NY, USA, pp. 629643.

    TMR (2010)Drainage, Retaining Structures and Protective

    Treatments. Queensland Government, Brisbane, Australia,

    MRTS03.

    WHAT DO YOU THINK?

    To discuss this paper, please email up to 500 words to the

    editor at [email protected]. Your contribution will be

    forwarded to the author(s) for a reply and, if considered

    appropriate by the editorial panel, will be published as a

    discussion in a future issue of the journal.

    Proceedingsjournals rely entirely on contributions sent in

    by civil engineering professionals, academics and students.

    Papers should be 20005000 words long (briefing papersshould be 10002000 words long), with adequate illustra-

    tions and references. You can submit your paper online via

    www.icevirtuallibrary.com/content/journals, where you

    will also find detailed author guidelines.

    Geotechnical Engineering A soil-nailed excavation for the Brisbane

    Airport Link project, Australia

    Bridges and Gudgin