  • 8/20/2019 General Safeguards

    1/2

    P1179-HES-D-REP-0003

    Rev.0

    Solstad Offshore Asia Pacific Pte. Ltd.

    2016 – 2019 WHP and Pipeline Construction and Installation Campaign

    Page 21 of 74

     

    'GENERAL' EFFECTIVE EXISTING SAFEGUARDS 'LIFTING' EFFECTIVE EXISTING SAFEGUARDS

    G1 Familiar with and follow approved procedures L1 Follow the Chevron colour coding standard

    G2 Ensure clear communications between all parties L2 Use certified portable lifting equipment

    G3 Use trained and qualified personnel, and minimise number of SSE's L3 Ensure weights are known prior to lifting

    G4 Use certified compliant equipment L4 Use tag lines, ensuring they are the correct quantity, location and length

    G5 Confirm compliance with Chevron's banned equipment guidelines L5 Follow correct manual handling techniques

    G6 Inspect tools prior to use to ensure they are in good condition and functioning L6 Certified Crane operators

    G7 Ensure all tool / equipment safety devices are functioning and have not been disabled L7 All relevant parties to agree that conditions are suitable for the lift

    G8 Ensure preventive maintenance system are in place for all tool / equipment L8 Use qualified and experienced lifting personnel

    G9 Perform and adhere to PTW/Risk Assessment/SOC-BBS Card/STOP /Toolbox talk/Isolation (rigging supervisors, banksmen, crane operators, etc)

    G10 Ensure safe access and egress L9 Banksman to wear a hi-viz vest (visual indication)

    G11 Ensure adequate lighting, ventilation, shade and similar L10 Verify supplied certified rigging is as per design drawings

    G12 Access to adequate re-hydration & electrolytes, especially when working outside L11 Maintain both visual and radio comms at all times for manriding lifts

    G13 Wear appropriate PPE L12 Use barricades and restrict access during lifting operations to essential personnel only

    G14 Monitor weather and other ambient conditions

    G15 Monitor weather forecasts and Chevron in-field weather radar

    G16 Use IIF and PBED (Check 6) techniques

    G17 Use correct manual handling techniques

    G18 Use good housekeeping practices 'PPE REQUIREMENT' EFFECTIVE EXISTING SAFEGUARDS

    G19 Use T-Card System

    G20 Deploy life rings while working above water P1 General

    G21 Ensure OVID in place for all vessels Helmet with chinstrap, safety glasses, gloves, safety boots and 100% cotton or flame retardant coverall

    G22 Follow Management of Change for any deviations P2 Rigging / Lifting

    G23 Smoking only in the approved area P1 plus mechanical handling rated gloves

    G24 Buddy work system and management of workman shift P3 Welding

    G25 Use of Stop Work Authority (SWA) P1 plus double eye protection (safety glasses + welding shield), welding gloves, appropriate respiratory protection

    G26 Use barricades to restrict unauthorised access P4 Grinding/Flammable Gas Cutting / Descaling and Chipping

    G27 Control Tower and Pipe Line Tunnel are authorized access areas P1 plus double eye protection (face shield + safety goggles), ear protection and leather gloves) - Welder specific Hard Hats - Integrated face shield clips

    G28 Human Factor Training is provided to personnel (see HSE training plan) P5 Working at height

    P1 plus Safety Harness, Work Vest or Lifejacket (when working overside)

    'MARINE REQUIREMENT' EFFECTIVE EXISTING SAFEGUARDS P6 Working nearby the water, open area or on the barge

    M1 Follow Preventive Maintenance System (PMS) P1 plus Work Vest or Lifejacket

    M2 Follow vessel operation manual P7 Working in high noise area

    M3 Chevron Marine Operations Manual P1 plus Ear Protection

    M4 Approved Anchor Patterns

    M5 Mooring Function Test

    M6 AHT SOP - Barge / Tug Operations Manual

    M7 FRC and FRC Team on standby where required

    M8 All items seafastened where required.

  • 8/20/2019 General Safeguards

    2/2

    P1179-HES-D-REP-0003

    Rev.0

    Solstad Offshore Asia Pacific Pte. Ltd.

    2016 – 2019 WHP and Pipeline Construction and Installation Campaign

    Page 22 of 74

     

    'HOT WORK' EFFECTIVE EXISTING SAFEGUARDS

    H1 If hot work in confined space then LEL must = 0%

    H2 Only Solstad Chief and 2nd Officers are the nominated gas testers onboard

    H3 Flash back arrestors fitted to regulators and handsets in all gas cutting/welding equipment

    H4 Fire watch in place to remain 30 mins after work has been completed

    H5 Calibrated welding / cutting machines

    H6 Fire blankets and fire extinguishers in use at the work site

    H7 Welding hose management

    H8 Gas leak tests conducted as part of shift equipment pre-checks