Metropolitan Sanitation Management Investment Project
Monthly Report No. 14 – December 2019 (Pekanbaru)
TABLE OF CONTENTS
A. GENERAL PROJECT INFORMATION .......................................................................................................... 1
MSMIP ....................................................................................................................................................... 1 1.
PISC MSMIP ............................................................................................................................................... 1 2.
MSMIP PEKANBARU CITY ............................................................................................................................... 1 3.
3.1 Scope of Work MSMIP Pekanbaru City ............................................................................................. 1
3.2 Current Contract Details ................................................................................................................... 2
3.3 Structural Organization of Supervision Team ................................................................................... 2
B. PROGRESS ACTIVITY ................................................................................................................................ 5
CONSTRUCTION .............................................................................................................................................. 5 1.
1.1 General Progress Activity .................................................................................................................. 5
1.2 Construction Activity and Fund Absorption for the Current Period ................................................... 5
1.3 Plan of Construction Activity ........................................................................................................... 17
SUPERVISION ............................................................................................................................................... 17 2.
2.1 Supervision Activity ......................................................................................................................... 17
2.2 Key Experts Progress Activity .......................................................................................................... 18
2.3 Supervision Plan Activity for the Upcoming Period ......................................................................... 20
C. MAJOR ISSUES AND PROPOSED REMEDIAL ACTIONS ................................................................................. 21
1. TABLE OF PARTICULAR ISSUES AND PROPOSED REMEDIAL ..................................................................................... 21
POTENTIAL ISSUES AND PROPOSED REMEDIAL ACTIONS ....................................................................................... 22 3.
D: ATTACHMENT ............................................................................................................................................ 23
ATTACHMENT D1: MINUTES OF MEETING ....................................................................................................... 24
ATTACHMENT D2: DOCUMENTATION OF SUPERVISION ............................................................................................. 42
ATTACHMENT D3: TIMESHEETS ........................................................................................................................... 47
Metropolitan Sanitation Management Investment Project
Monthly Report No. 14 – December 2019 (Pekanbaru) 1
A. GENERAL PROJECT INFORMATION
MSMIP 1.
The Metropolitan Sanitation Management Investment Project (MSMIP) will provide improved urban
wastewater services in three major cities in Indonesia; Makassar, Pekanbaru and Jambi. The project
will provide first time off-site sewerage and wastewater treatment facilities for the Central Business
District of these cities.
The MSMIP responds to the needs of these urban communities, including low income households,
by developing new systems, improving governance and building local institutional capacity including
community-based and government owned wastewater service providers.
PISC MSMIP 2.
The Project Implementation Supervision Consultant (PISC) will provide detailed sub-project
construction supervision of the sewerage and wastewater treatment plants planned for Makassar,
Pekanbaru and Jambi complete with the social, environmental and safety related aspects.
Furthermore, the PISC will provide support to the Central Project Management Unit (CPMU),
Provincial Project Implementation Units and Local Project Management Units (LPMU).
MSMIP Pekanbaru City 3.
3.1 Scope of Work MSMIP Pekanbaru City
The scope of the work for the MSMIP includes the site supervision and other services as described in
the terms of reference included in the contract.
The construction contract packages are shown below.
Wastewater Sewer System North – Package NC
Waste Water Treatment Plant (WWTP) – Package B1 - IPAL
Wastewater Sewer System South – Package SC1
Wastewater Sewer System South – Package SC2
For the Contract NC, the Probity Audit is completed. Revised draft bidding document submitted to
CPMU 11 March 2019. NOL for final bidding document was issued on 12 April 2019. RPB and decree
of Pokja was approved. IFB was advertised 29 April 2019. The Prebid meeting was completed on 07
May 2019. Deadline for bid submission was extended until 17 June 2019 (original deadline is 29 May
2019). Four proposals were evaluated by Pokja. Bid Evaluation Report (BER) was submitted to ADB
on 02 August 2019. NOL to the BER received on 16 August 2019. It has since been decided that the
project be re-tendered.
For the Contract B1 - IPAL; A final draft of the bidding document was sent to CPMU on 27 March
2019 and CPMU submitted the document to ADB on 29 March 2019. Conditional Approval to the
Final Bidding Document from ADB was received on 29 April 2019. The bidding document has been
revised accordingly. The Probity Audit was carried out between 13-30 June 2019. Strategic issues
related to the bidding process discussed on 15 July 2019. It was agreed to use single-stage: two
Metropolitan Sanitation Management Investment Project
Monthly Report No. 14 – December 2019 (Pekanbaru) 2
envelope bidding procedure for this Contract. Responses to audit results have been accommodated.
This was submitted to PPK on 29 July 2019. The revised SBD was sent to CPMU on 23 August 2019
and forwarded to ADB on 26 August 2019. ADB conditional NOL received on 26 September 2019. The
revised bidding document was submitted to ADB on 01 October 2019. It is currently in the process of
the approval of the Directorate General. It is currently anticipated that mobilization /construction on
site will commence in April 2020. The construction duration has been reduced from 30 months to 26
months therefore substantial completion is anticipated in May 2022.
It should be noted that if there is a delay to the NC Contract completion by re-tendering, commission
of the IPAL Treatment Works will be impacted as the pipeline would be finished after the treatment
facility is ready to accept flow.
Currently there are two Contracts awarded and under construction, Contract SC1 and Contract SC2.
The Contractor for Contract SC1 is Wijaya Karya – Karaga, KSO. (Wika).
The Contractor for Contract SC2 is Hutama Karya – Rosa Lisca, KSO. (HK Rosa).
The report below deals with the details and progress of Contract SC1 and Contract SC2.
3.2 Current Contract Details
Contract SC1 Contract SC2
Contract Award Date 01 November 2018 01 November 2018
Commencement Date 09 November 2018 09 November 2018
Accepted Contract Amount Rp. 203,756,600,000 Rp. 141,457,750,000
Contract Period 780 days 780 days
Approved Extension of Time None None
Current Contract Completion Date 27 December 2020 27 December 2020
Down Payment 13.60 % 13.60 %
Monthly Certificate (MC) - Total to Date 41.23% 45.02%
Planned Progress 45.02 % 44.95 %
Progress to Date 30.52 % 33.14 %
3.3 Structural Organization of Supervision Team
The structural organizational structure of the Project Implementation Supervision Consultant team
in Pekanbaru is shown in the organogram on the next page.
Metropolitan Sanitation Management Investment Project
Monthly Report No. 14 – December 2019 (Pekanbaru) 3
Figure 1
Metropolitan Sanitation Management Investment Project
Monthly Report No. 14 – December 2019 (Pekanbaru) 4
The status of the staff mobilization for the Pekanbaru team is given in the table below:
Position Name Mobilization
Date
Demobilization
Date
PR / Sanitation Marketing Specialist Johan Kadhafi 28-Aug-18
Office Manager Titisari Hermani 06-Sep-18
Guard - 1 M. F. Padli 25-Sep-18
Bilingual Secretary Helen Ahyar 26-Sep-18
Accounting Specialist Dea Arsitasari 01-Oct-18
Office Boy Aldi Norman 05-Oct-18
Guard - 2 M Faisal 05-Oct-18
Engineering Support 1 / Drafting Ary Iqbal 30-Oct-18
Field Supervisor 1 Widya Wannenda Reza 30-Oct-18
Field Supervisor 2 Abdul Gafar 30-Oct-18
Field Supervisor 3 Meidinel 30-Oct-18
Field Supervisor 4 Busra Effendi 30-Oct-18
Field Supervisor 5 Harmen Gusnadi 27-Jun-19
Structural Engineer Rusman Sihotang 12-Nov-18
Health and Safety Coordinator Wisik Adi Purnomo 12-Nov-18
Quantity Surveyor 1 Kristiadi 15-Jan-19
Surveyor Support Novial Azhar 28-Jan-19 29-Nov-19
Sewerage Engineer - 1 Syahrul 29-Jan-19
City Team Leader Robert Moran 02-May-19
Sewerage Engineer - 2 Yan Haryadi 08-Jul-19
Metropolitan Sanitation Management Investment Project
Monthly Report No. 14 – December 2019 (Pekanbaru) 5
B. PROGRESS ACTIVITY
Construction 1.
1.1 General Progress Activity
Contracts for the construction of packages SC1 and SC2 were issued on 01 November 2018. The
Commencement Date for both Contracts was 09 November 2018. The Contract Duration for both
Contracts is 780 days. Physical construction on site commenced on Contract SC1 on 25 March 2019.
Physical construction on site on Contract SC2 commenced on 26 March 2019.
Both Contractors have continued with ‘Open Cut’ pipe installation activities since construction
commenced. In addition, both Contractors have installed steel sheet piles at the starting pit and
arriving pit locations for jacking and boring work. Jacking and Boring work has begun. Jacking
operations on the SC1 Contract have been slow due to difficulties with the entry of ground water
and the Contractor continues to drain the excavation site. The SC2 Contractor also had difficulty
dealing with high ground water due to the elevation of the pipeline that would be deeper installed.
Currently, both Contractors perform their work faster than scheduled in terms of pipe installation
using the Open-Cut method, but both Contractors are very behind schedule in terms of tunneling /
pipe jacking and boring work as well as manhole construction activities and reinstatements of the
road pavement works both rigid pavement (Concrete) and flexible pavement work (Asphalt).
The initial asphalting of the former pipeline excavation work of both packages was poor in their
quality and both Contractors were informed that the asphalt pavement repair work was to date
unacceptable. Both Contractors have been instructed to improve the asphalt pavement work.
Coordination with the various utility organizations continues in relation to the proposed works.
Further details regarding progress of the works are set out below.
1.2 Construction Activity and Fund Absorption for the Current Period
The works carried out by the SC1 and SC2 Contractors during this period were the continued
installation of 150mm and 200mm PVC pipes throughout the respective work zones. In general
terms Open-Cut excavation works are proceeding on schedule on both projects. Installation of Steel
Sheet Piles is ongoing on the starting and arriving pits but slightly behind schedule for both projects.
The SC1 Contractor continues to dewater the excavation and grout inject around the jacking pipes.
The SC1 Contractor was to have mobilized two additional tunneling crews on 21 October 2019
however this did not materialize until very late in November 2019 so effectively provided no
progress for the month of November 2019 so that it couldnt give progress to December 2019 and is
one of the key reasons that the SC1 Contractor is behind schedule. The SC2 Contractor is behind in
Jacking tunneling and behind in manhole construction works too. The mobilization of the Jacking
equipment was scheduled for October 2019 but works are still to commence on site. Consequently,
for both Contractors, physical progres are behind the planned progress. Further details of the
construction activities for both Contracts are set out below.
Metropolitan Sanitation Management Investment Project
Monthly Report No. 14 - December 2019 (Pekanbaru) 6
1.2.1. Construction activities carried out:
A. Activities carried out by SC1 Package, Wijaya Karya - Karaga, KSO. to date are as follows:
A.1. Progress Achieved this Month
NO Works Detail Percentage
(%)
Actual Percentage (%)
Last Month
This Month
Total to
Date
I GENERAL COST
1 Mobilisation and demobilisation for tools, machines and personnel.
1.03 0.87 0.87
2 Measuring and Benchmarking pipeline 0.46 0.41 0.41
3 Building the Office Site 0.39 0.39 0.39
4 Traffic Management 1.77 1.58 1.58
5 Test Pits 0.07 0.06 0.06
6 Soil Investigation
0.07 0.07
0.07
7 Securing the Existing Utility 0.37 0.31 0.31
8 Stock Yard and workers housing 0.36 0.36 0.36
9 Pre-commissioning and Commissioning 0.23 0.06 0.04 0.10
II PROCUREMENT WORK
1. Procurement of PVC Pipe
1 Procurement of PVC Pipe S.10 dia. 150 mm 2.32 1.73
1.73
2 Procurement of PVC Pipe S.10 dia. 200 mm 1.02 0.72 0.72
3 Procurement of PVC Pipe S.10 dia. 250 mm 0.39 0.33 0.33
4 Procurement of PVC Pipe S.10 dia. 300 mm 0.42 0.31 0.31
5 Procurement of PVC Pipe S.10 dia. 400 mm 0.29 0.21 0.21
2. Procurement of Reinforcement Concrete Pipe
Metropolitan Sanitation Management Investment Project
Monthly Report No. 14 - December 2019 (Pekanbaru) 7
NO Works Detail Percentage
(%)
Actual Percentage (%)
Last Month
This Month
Total to
Date
1 Procurement of RCP dia. 450 mm 0.35 0.24
0.24
2 Procurement of RCP dia. 600 mm 1.75 1.28
1.28
III PIPE INSTALLATION
A PIPE INSTALLATION OPEN TRENCH METHOD
1. PVC dia. 150 mm 24.35 10.45 1.08 11.53
2. PVC dia. 200 mm 3,47 0.49
0.49
3. PVC dia. 250 mm 1.75 1.28 1.28
B PIPE INSTALLATION BORING METHOD
1. PVC dia. 150 mm 10.35 1.73 0.20 1.94
2. PVC dia. 200 mm 17.85 1.70 0.04 1.74
3. PVC dia. 250 mm 7.05 1.85 0.54 2.38
4. PVC dia. 300 mm 5.76 0.10
0.10
5. PVC dia. 400 mm 2.11 0.04
0.04
C PIPE INSTALLATION JACKING METHOD
1. RCP dia. 450 mm 2.58 0.04
0.04
1. RCP dia. 600 mm 11.74 2.35 0.58 2.93
D
PROCUREMENT AND INSTALLATION DROP MAINTENANCE HOLE
0.31
E PROCUREMENT AND INSTALLATION CLEAN OUT 0.35
F PROPERTY (HOUSE CONECTION) 3.09 0.36 0.03 0.37
Total 2.58 0.04
0.04
Metropolitan Sanitation Management Investment Project
Monthly Report No. 14 - December 2019 (Pekanbaru) 8
Table 2
Metropolitan Sanitation Management Investment Project
Monthly Report No. 14 - December 2019 (Pekanbaru) 9
Figure 3
Metropolitan Sanitation Management Investment Project
Monthly Report No. 14 - December 2019 (Pekanbaru) 10
The Contractors construction progress to the end of December 2019 is 30.52% (Revised schedule)
which is -14.50 % lower than the planned progress of 45.02 %.
Upon review by the PISC, it was apparent that the Contractors tunneling works are now
approximately 12 weeks behind schedule. The Contractor proposed to mobilize two additional
boring crews in September 2019 however this did not materialize due to the unavailability of
equipment until late in December 2019. The Contractor has lost almost two months of proposed
productivity from these two crews. The Contractor is only slightly behind in relation to the Open-Cut
pipelaying operations. The Contractor has substantially completed 62.40% the house connections in
his Contract.
The Contractor submitted a revised program on 19 July 2019 which has mitigated the issues and
provides a new S-Curve without compromising the Completion Date of 27 December 2019. Upon
review and after consultation with PPK, this revised program was ‘Approved with Comments’ for
monitoring purposes. The figures above are based on the revised schedule and the PISC continues to
monitor progress of the works against this schedule. The PISC has been reviewing progress rates of
the works carried out to date and a meeting was held with the Contractor on 14 October 2019 to
review the Contractors Progress and the Contractors Program with a view to ensuring that the
schedule is not compromised.
Following the meeting on 14 October 2019, the PISC wrote to the Contractor on 15 October 2019
and requested the submission of a new Revised Program. The Contractor has developed a new
program based on Addendum 1 and his ‘Action Plan’ discussed on 14 October 2019 and this was
submitted on 25 October 2019. The PISC was cautiously optimistic this schedule is achievable
provided that the Contractor mobilizes the resource mentioned in their ‘Action Plan’. After
consultation with PPK the plan was ‘Accepted with Comments’ effective from 01 November 2019.
The Contractor is now currently behind planned progress by approximately -14.50% against the new
program however. The Contractor failed to mobilize the necessary resources promised. The delays
are associated with the boring tunneling works. The PISC wrote to the Contractor on 14 November
2019 and requested the submission of an ‘Action Plan’ to address these issues. The PISC reminded
the Contractor of the requirements of the Conditions of Contract where a ‘Show Cause’ meeting will
be required if progress falls behind by more than 10%. The PISC will write to PPK in relation to this
matter in early January 2019 as has been agreed.
A.2 Fund Absorption
The Contractor has submitted fourteen Monthly Certificates for the months of November 2018 to
December 2019 which have been processed and approved. The absorption of funds that have been
carried out by the Contractor to date is based on the fourteen Monthly Certificates approved to
date. The fund absorption can be show in the following graph.
Metropolitan Sanitation Management Investment Project
Monthly Report No. 14 - December 2019 (Pekanbaru) 11
Figure 4
363,908,194 222,164,944
2,770,813,997 3,766,133,735 2,611,954,838 3,662,390,668 4,170,572,100 3,565,938,323
9,494,139,512 9,673,524,087 10,272,931,669
17,420,875,432 15,505,060,783
505,271,943
869,180,137 1,091,345,081
3,862,159,078 7,628,292,813
10,240,247,651
13,902,638,319
18,073,210,419
21,639,148,742
31,133,288,254
40,806,812,341
51,079,744,010
68,500,619,442
84,005,680,225
-
5,000,000,000
10,000,000,000
15,000,000,000
20,000,000,000
25,000,000,000
30,000,000,000
35,000,000,000
40,000,000,000
45,000,000,000
50,000,000,000
55,000,000,000
60,000,000,000
65,000,000,000
70,000,000,000
75,000,000,000
80,000,000,000
85,000,000,000
90,000,000,000
Nov-18 Dec-18 Jan-19 Feb-19 Mar-19 Apr-19 May-19 Jun-19 Jul-19 Aug-19 Sep-19 Oct-19 Nov-19 Dec-19
1 2 3 4 5 6 7 8 9 10 11 12 13 14
Fund Absorption Chart on SC1 Contract
MC Absorption Commulative of Absorption
Metropolitan Sanitation Management Investment Project
Monthly Report No. 14 - December 2019 (Pekanbaru) 12
The disbursement / absorption of funds that have been carried out up to December 2019 (14th
month) is in the amount of Rp. 84.005.680.225 or 41.23% of the Contract value. It should be noted
that the December 2019 evaluation was based on a forecast to the end of the financial year.
Unfortunately, however neither of the two Contractor achieved the desired progress during
December 2019 so progress is now behind the interim payments made to both Contractors.
B. Activities carried out by SC2 Package, Hutama Karya - Rosa Lisca, KSO. are as follows:
B.1. Progress Achieved this month
NO Works Detail Percentage
(%)
Percentage (%)
Last Month
This Month
Total to
Date
I GENERAL COST
1 Mobilisation and demobilisation for tools,
machines and personnel. 0.23 0.09 0.02 0.12
2 Measuring and Benchmarking pipeline 1.35 0.68 0.05 0.73
3 Building the Office Site 0.94 0.94 - 0.94
4 Traffic Management 1.62 1.33 0.01 1.34
5 Test Pit 0.04 0.02 - 0.02
6 Soil Investigation 0.50 0.50 - 0.50
7 Securing the Existing Utility 0.26 0.12 0.01 0.13
8 Stock Yard and workers housing 1.60 1.60 - 1.60
9 Pre-commissioning and Commissioning 0.04 - - -
II PROCUREMENT WORK
1. Procurement of PVC Pipe
1 Procurement of PVC Pipe S.10 dia. 150 mm 2.66 1.94 0.06 2.00
2 Procurement of PVC Pipe S.10 dia. 200 mm 0.77 0.52
0.52
3 Procurement of PVC Pipe S.10 dia. 250 mm
4 Procurement of PVC Pipe S.10 dia. 400 mm 1.81 0.67 - 0.67
Metropolitan Sanitation Management Investment Project
Monthly Report No. 14 - December 2019 (Pekanbaru) 13
NO Works Detail Percentage
(%)
Percentage (%)
Last Month
This Month
Total to
Date
2. Procurement of Reinforcement Concrete Pipe
1 Procurement of RCP dia. 600 mm 4.60 1.46 0.36 1.46
2 Procurement of RCP dia. 800 mm 0.36 0.21 0.01 0.22
III PIPE INSTALLATION
A PIPE INSTALLATION OPEN TRENCH METHOD
1. PVC dia. 150 mm 34.75 16.40 1.44 17.84
2. PVC dia. 200 mm 3.88 2.05 0.05 2.10
3. PVC dia. 250 mm
B PIPE INSTALLATION BORING METHOD
1. PVC dia. 150 mm 4.53 0.08 - 0.08
2. PVC dia. 200 mm 7.92 1.85 0.18 2.04
3. PVC dia. 250 mm
4. PVC dia. 400 mm 5.48 0.09 - 0.09
C PIPE INSTALLATION JACKING METHOD
1. RCP dia. 600 mm 25.52 0.61 0.12 0.73
1. RCP dia. 800 mm 1.70 - - -
D PROCUREMENT AND INSTALLATION DROP MAINTANANCE HOLE
0.20 - - -
E PROCUREMENT AND INSTALLATION CLEAN OUT 0.23 - - -
Total 100.00 100.00 31.17 1.97
Tabel 5
Metropolitan Sanitation Management Investment Project
Monthly Report No. 14 - December 2019 (Pekanbaru) 14
Figure 6
Metropolitan Sanitation Management Investment Project
Monthly Report No. 14 - December 2019 (Pekanbaru) 15
Following the meeting on 14 October 2019, the PISC wrote to the Contractor on 15 October 2019
and requested the submission of a new Revised Programme. The Contractor had stated that a
revised programme would be submitted on 18 October 2019 however this was not submitted until
26 October 2019 but was rejected. The Contractor resubmitted a Revised S-Curve on 08 November
2019. The PISC was cautiously optimistic that the ‘Action Plan’ is achievable to recover progress
provided that the Contractor mobilizes the resources necessary to achieve the outputs described.
The PISC recommended approval of the revised S-Curve on 14 November 2019 and it has been used
to monitor progress since 18 November 2019.
The Contractors construction progress for to the end of December 2019 is 33,14%, which is -11.81%
lower than the planned progress of 44.95%. The Contractor is slightly behind in most departments
with the exception of the manhole and shaft construction with some delays noted in the tunneling
works due to ground water issues. We estimate that the Contractor is approximately 12 weeks
behind in Jacking and Boring operations as the Contractor has failed to mobilize the Jacking
equipment as promised. The PISC reminded the Contractor of the requirements of the Conditions of
Contract where a ‘Show Cause’ meeting will be required if progress falls behind by more than 10%.
The PISC will write to PPK in relation to this matter in early January 2019 as has been agreed.
B.2. Fund Absorption
The Contractor has submitted fourteen Monthly Certificates for the months of November 2018 to
December 2019. The Absorption of funds that have been carried out by the Contractor to date are
based on the fourteen Monthly Certificates approved to date. The fund absorption can be show in
the following graph.
Metropolitan Sanitation Management Investment Project
Monthly Report No. 14 - December 2019 (Pekanbaru) 16
Figure 7
[VALUE]
5,063,192,910
2,655,529,737 1,698,637,221 2,053,632,440
240,439,339 1,540,413,219
4,235,390,226
656,097,997
6,013,032,376
3,018,512,418
11,045,487,764 10,654,866,646
14,129,093,790
5,739,132,918
8,394,662,655
10,093,299,876
12,146,932,316 12,387,371,655 13,927,784,874
18,163,175,100 18,819,273,097
24,832,305,473
27,850,817,891
38,896,305,655
49,551,172,301
63,680,266,091
-
5,000,000,000
10,000,000,000
15,000,000,000
20,000,000,000
25,000,000,000
30,000,000,000
35,000,000,000
40,000,000,000
45,000,000,000
50,000,000,000
55,000,000,000
60,000,000,000
65,000,000,000
70,000,000,000
Nov-18 Des-18 Jan-19 Feb-19 Mar-19 Apr-19 Mei-19 Jun-19 Jul-19 Agu-19 Sep-19 Okt-19 Nov-19 Des-19
1 2 3 4 5 6 7 11 12 13 14 15 16 17
Fund Absorption Chart on SC2 Contract
MC Absorption Commulative of Absorption
Metropolitan Sanitation Management Investment Project
Monthly Report No. 14 - December 2019 (Pekanbaru) 17
The disbursement / absorption of funds that have been carried out up to December 2019 (14th
month) is in the amount of Rp. 49.551.172.302,- or 45.02% of the Contract Value.
1.3 Plan of Construction Activity
Construction activities planned for the coming month are as follows:
A. SC1 Contract
• Installation of Open Trench PVC Pipe on Jl. Kusuma, Jl. Nanas, Jl. Teladan, Jl. Panda, Jl. Kuda
Laut and Gang. Nurul Iman 2.
• Jakcing (Starting and Arriving) pit construction work on MH 18, MH.17 and Pipe Jacking work
from MH 19A to MH 20 and from MH.19A to MH 19.
• Continue the installation of Manhole in MH.21, MH.20 and MH.19. Gang Rahmat 4 points,
Gang Nurul Iman 3 points and Gang Keluarga 7 points.
• Continue boring work by opening the Pit at MH AB 6, MH AB 7, MH AB 8, MH Ab 9 and MH
Ab 10 on Jl. Ababil and continue the boring work in MH BLS 2A - MH AB 2 on Jl. Belibis, MH
AB 2 - MH AB 3 and MH AB 4 - MH AB 3 on Jl. Ababil, MH KS 2 - MH KS 3, MH KS 2 - MH KS
2A on Jl. Kasuari (Continued) and MH TG 5 - MH TG 6 on Jl. Tiung.
• Asphalt road repair / restoration work Jl. Merak, Jl. Kakatua, Jl. Murai, Jl. Gelatik and Jl.
Selindit.
B. SC2 Contract
• Open Trench Work: Gang Mesjid (continued), Jl. Gajah 2, Jl. Ahmad Yani 2, Gang Sekuntum,
Gang Falam, Gang Aster 2, Gang Muamalah (continued).
• Boring Works: Opening pit on Jl. Ahmad Yani MHAY2a, MHAY2, MHAY4A, Boring on Jalan
Ahmad Yani MHAY2a to JS-2, MHAY2a to MHAY2.
• Jacking Works: Jacking MH23 to JS-2, Jacking MH23 to MH24, Opening Starting pit MH25,
Opening Ariving Pit MH26, Jacking MH25 To MH24.
• Man Hole: Jl. Nusa Indah 2 points, Gang Singa 3 points, Jl. Kamboja 8 points, Jl. Dahlia 7
points, Jl. Bunga Harum 6 points, Jl. Bunga Kertas 7 Points.
• Restoration / repair of Concrete and Asphalt Roads: Jl. Rusa (Asphalt), Jl. Nusa Indah
(Asphalt), Gang Pelita (Concrete), Gang Adha (Concrete), Gang Damai (Concrete) and Gang
Aster (Concrete).
Supervision 2.
2.1 Supervision Activity
Supervision activities during the period include:
• Conducting Progress Meetings in site office of the SC1 and SC2 Contractors.
• Continued supervision of the SC1 and SC2 Contractors works.
• Conducting socialization with the residents who have a direct impact due to the
implementation of work.
Metropolitan Sanitation Management Investment Project
Monthly Report No. 14 - December 2019 (Pekanbaru) 18
• Reviewing Shop Drawings submitted by both Contractors.
• Coordination with the PPK, the Field Directors as well as the various Stakeholders.
• Coordination with both Contractors and the PPK as well as relevant agencies related to the
MSMIP activities in Pekanbaru City, including Public Work city Office, Transportation Agency,
Traffic Police about traffic management at the location of activities and to the utility owners.
• Monitoring progress of the SC1 and SC2 Contractors.
• It should be noted that there was a Public Holiday on 25 December 2019.
Details of the Progress Meetings held this period can be seen in the table below and the various
minutes are provided in appendix D1.
2.2 Key Experts Progress Activity
The timesheets of all the key and non-key staff is included in Attachment D3.
The key experts progress activity is summarized in the table below;
Key Expert Name Progress Activity
City Office Leader Robert
Moran
Coordinating for all matters related to MSMIP project
activities.
Coordinating with the PPK and Institutions.
Reviewing progress and documentation prepared by
the PISC team.
Reviewing Contractors Programmes.
Chairing Bi-Weekly Meetings.
Preparing Addendum 2.
Sewerage Engineer 1 Pak
Syahrul
Conducting an inspection of the location of the pipe installation construction activities.
Checking the Contractor's work application letter prior to the execution of work commencing for tools, materials, labor, work methods and schedule details.
Monitoring the schedule for implementing contractor work.
Attending meetings with Contractors and Directors.
Coordinating with Field Supervision for field problems.
Date Location Topic
04 December 2019 HK– Rosalisca’s Site Office, KSO Bi-Weekly Progress Meeting SC2
04 December 2019 Wika – Karaga’s Site Office, KSO Bi-Weekly Progress Meeting SC1
19 December 2019 HK– Rosalisca’s Site Office, KSO Bi-Weekly Progress Meeting SC2
19 December 2019 Wika – Karaga’s Site Office, KSO Bi-Weekly Progress Meeting SC1
Metropolitan Sanitation Management Investment Project
Monthly Report No. 14 - December 2019 (Pekanbaru) 19
Key Expert Name Progress Activity
Sewerage Engineer 2 Yan
Haryadi
Monitoring the schedule for implementing the
Contractors work.
Providing support to the City Office Leader.
Attending meetings with Contractors and Directors and
preparing Presentation Slides.
Providing comments on Contractors letters and
submissions.
Evaluating the performance of Contractors work.
Reviewing NC Contract requirements.
Structural Engineer Rusman
Sihotang
Conducting supervision in the field for SC-1 and SC-2 locations, including quality / working methods, materials used, methods of installing shoring / plaster for security of excavation.
Evaluating the performance of Contractors every week.
Attending the Bi-Weekly Progress Meeting.
Checking pipes and components of MH (Material on Site) in SC1 and SC2.
Coordinating with SC-1 and SC-2 Contractors.
H&S Engineer Wisik Adi
Purnomo
Checked HSE performance on site (SC1 & SC2), especially in use of PPE.
Attending Bi-Weekly Progress Meetings.
Preparation of Minutes of Meeting for the Bi-Weekly Progress Meeting for both Contractors SC-1 & SC-2.
Together with socialization team, did socialization to the community at SC-1 & SC-2 locations as implementation of Environmental Management Efforts.
Public Relations/
Sanitation Marketing
Specialist
Johan
Kadhafi
Sozialication for public affected physical activity in
various streets.
Organize the Media Social for the Publication IPAL
Pekanbaru in FB, IG and Youtube.
Reguler liaison and general assistance to the PPK,
Bappeda, Land Agency, Public Work Agency of
Pekanbaru City.
Metropolitan Sanitation Management Investment Project
Monthly Report No. 14 - December 2019 (Pekanbaru) 20
Key Expert Name Progress Activity
Quantity Surveyor Pak
Kristiadi
Checking Daily Reports on SC1 and SC2.
Checking the Weekly Reports of SC.1 and SC.2.
Checking Monthly Reports for SC.1 and SC.2.
Checking Contractors Progress calculations.
Checking the ground excavation field and pipe
installation of the SC1 and SC2 pipes.
Assisting in the preparation of Addendum 2.
2.3 Supervision Plan Activity for the Upcoming Period
The following supervision work is planned for the upcoming period;
• Prepare for a ‘Show Cause’ Meeting for SC1 and SC2 Contractors.
• Supervise all Contractor activities in the field.
• Continuing inspection the Contractors Shop Drawings for longitudinal and transverse pieces.
• Continuing to coordinate with the Contractor to make detailed schedules as completeness of
the Contractor's work requests.
• Prepare standard monitoring schedule detail as a control for the Contractor's work progress
and compare it with the targets in the S Curve.
• Coordinate with the field supervisor to be able to monitor the Contractor's work.
• Continuing to identify 1000 priority connections and additional SR plans at the wastewater
service location, to continuously update prospective customer data.
• Prepare and attend Progress meetings with Contractors, PPK and PISC.
• Review material requests and material tests submitted by SC1 and SC2.
• Overseeing stockyard activities for the arrival of materials and equipment / tools.
• Continuing a photo survey of current road conditions that will be affected by construction.
• Review Contract Drawing for Sc1 and SC2.
• Review and evaluate Contractor work plans for SC1 and SC-2.
• Sozialization for public affected physical activity.
• Continue regular liaison and general assistance to the PPK, Bappeda, Land Agency, Public
Work Agency of Pekanbaru City.
Metropolitan Sanitation Management Investment Project
Monthly Report No. 14 - December 2019 (Pekanbaru) 21
C. MAJOR ISSUES AND PROPOSED REMEDIAL ACTIONS
1. Table of Particular Issues and Proposed Remedial
A table of issues and proposed remedial actions is given below;
Item Issue Proposed Remedial Action
1
Utilities that are in the ground and that are
above ground (air cables) are causing difficulties
with positioning and subsequent excavation and
construction of the manholes and pits as well as
restricting space for maneuvering heavy
equipment.
Continue close coordination with
utility owners based on a case by case.
2 Local socialization issues.
Socialization will be per RT and RW
and directly with the community along
the route of the pipelines.
3 Locations of House Inlets (HI) for future
connections.
Continue to prepare HI for future
connections, where HI can serve
several housing units in the service
area.
Metropolitan Sanitation Management Investment Project
Monthly Report No. 14 - December 2019 (Pekanbaru) 22
Potential Issues and Proposed Remedial Actions 3.
A table of Issues and proposed remedial action is given below;
Item Issue Proposed Remedial Action
1 Time overruns
The Contractors will be monitored for the production and
submission of compliant programmes. Actual progress will be
monitored against the programme and deficiencies/ remedial
measures proposed.
PISC will help quickly to deal with problems that occur in the field,
both technical and non-technical issues. PISC will continue to
monitor progress of both Contractors.
2 Cost overruns
The PISC will monitor the committed costs by continuous updating
of the forecast cost to complete. This will enable the early
identification and resolution of any variances.
3 Quality concerns
Close monitoring will be required of the following:
Approval of the sources of all materials.
Review and approval of methodology.
Inspection and testing of the Works.
4 Health and Safety
concerns
Safe systems of work will be developed, monitored and controlled in
conjunction with the Client and Contractor.
5 Socialization to
Citizen
Preparation and coordination with residents in the locations that will
be carried out by MSMIP activities will continue.
6 Clean Construction Control must be carried out every day in the field to ensure that field
conditions remain neat, clean and safe for the community.
Metropolitan Sanitation Management Investment Project
Monthly Report No. 14 - December 2019 (Pekanbaru) 23
D: ATTACHMENT
Metropolitan Sanitation Management Investment Project
Monthly Report No. 14 - December 2019 (Pekanbaru) 24
ATTACHMENT D1: MINUTES OF MEETING
TWO FORMAL MEETING WAS HELD ON THIS MONTH
Metropolitan Sanitation Management Investment Project
Monthly Report No. 14 - December 2019 (Pekanbaru) 25
Metropolitan Sanitation Management Investment Project
Monthly Report No. 14 - December 2019 (Pekanbaru) 26
Metropolitan Sanitation Management Investment Project
Monthly Report No. 14 - December 2019 (Pekanbaru) 27
Metropolitan Sanitation Management Investment Project
Monthly Report No. 14 - December 2019 (Pekanbaru) 28
Metropolitan Sanitation Management Investment Project
Monthly Report No. 14 - December 2019 (Pekanbaru) 29
Metropolitan Sanitation Management Investment Project
Monthly Report No. 14 - December 2019 (Pekanbaru) 30
Metropolitan Sanitation Management Investment Project
Monthly Report No. 14 - December 2019 (Pekanbaru) 31
Metropolitan Sanitation Management Investment Project
Monthly Report No. 14 - December 2019 (Pekanbaru) 32
Metropolitan Sanitation Management Investment Project
Monthly Report No. 14 - December 2019 (Pekanbaru) 33
Metropolitan Sanitation Management Investment Project
Monthly Report No. 14 - December 2019 (Pekanbaru) 34
Metropolitan Sanitation Management Investment Project
Monthly Report No. 14 - December 2019 (Pekanbaru) 35
Metropolitan Sanitation Management Investment Project
Monthly Report No. 14 - December 2019 (Pekanbaru) 36
Metropolitan Sanitation Management Investment Project
Monthly Report No. 14 - December 2019 (Pekanbaru) 37
Metropolitan Sanitation Management Investment Project
Monthly Report No. 14 - December 2019 (Pekanbaru) 38
Metropolitan Sanitation Management Investment Project
Monthly Report No. 14 - December 2019 (Pekanbaru) 39
Metropolitan Sanitation Management Investment Project
Monthly Report No. 14 - December 2019 (Pekanbaru) 40
Metropolitan Sanitation Management Investment Project
Monthly Report No. 14 - December 2019 (Pekanbaru) 41
Metropolitan Sanitation Management Investment Project
Monthly Report No. 14 - December 2019 (Pekanbaru) 42
ATTACHMENT D2: DOCUMENTATION OF SUPERVISION
1. SC1 DAN SC2 WORK PROGRAMME
2. MATERIAL APPROVAL REQUESTS
Metropolitan Sanitation Management Investment Project
Monthly Report No. 14 - December 2019 (Pekanbaru) 43
1. PROGRAM KERJA SC1 DAN SC2
Metropolitan Sanitation Management Investment Project
Monthly Report No. 14 - December 2019 (Pekanbaru) 44
SC1: Wijaya Karya – Karaga, KSO.
Metropolitan Sanitation Management Investment Project
Monthly Report No. 14 - December 2019 (Pekanbaru) 45
SC2: Hutama Karya – Rosalisca, KSO.
Metropolitan Sanitation Management Investment Project
Monthly Report No. 14 – December 2019 (Pekanbaru) 46
2. MATERIAL APPROVAL REQUESTS
No Material Approval Request was Approved in This Month.
Metropolitan Sanitation Management Investment Project
Monthly Report No. 14 – December 2019 (Pekanbaru) 47
ATTACHMENT D3: TIMESHEETS
Three timesheets are attached
Metropolitan Sanitation Management Investment Project
Monthly Report No. 14 – December 2019 (Pekanbaru) 48
Timesheet for International Key Expert
Metropolitan Sanitation Management Investment Project
Monthly Report No. 14 – December 2019 (Pekanbaru) 49
Timesheet for National Key Expert
Metropolitan Sanitation Management Investment Project
Monthly Report No. 14 – December 2019 (Pekanbaru) 50
Timesheet for Non – Key Person