General Infrastructures Services Department

LIU-SPS external beam dump-

Internal Review

Civil Engineering Aspect for Option B (LSS4)30/7/2014

Martin Manfredi

GS-SE-FAS

30/7/2014 J. Osborne, M. Manfredi, GS-SE-FAS 1

Page 2: General Infrastructures Services Department LIU-SPS external beam dump - Internal Review Civil Engineering Aspect for Option B (LSS4) 30/7/2014 Martin

General Infrastructures Services Department

TAG41

TAG42

TT40

TJ8

TT41

SPS ring

TI8

MagnetMQID.80500

DUMPLINE AREA FO

RESEEN

TAG41

Neutrino access gallery (CNGS)

Proton Beam Line

SUMMARY:

• Path foreseen to reach DUMP AREA (TI8): ~300m

• Different Options developed Feasibility study

• Cost estimate and planning for CE work

• Conclusion

30/7/2014 J. Osborne, M. Manfredi, GS-SE-FAS 2

LIU-SPS external beam dump // Extraction from LSS4

Page 3: General Infrastructures Services Department LIU-SPS external beam dump - Internal Review Civil Engineering Aspect for Option B (LSS4) 30/7/2014 Martin

General Infrastructures Services Department

~ 140 m

Tunnel TAG41 slope: 2.29%

Section view

Plan view

ECA4

~ 3.10 m

~ 2.

50 m

A

A

A

A

Section A-A

Actual space available for transport:1.56m (W); 2.05m (H)

30/7/2014 J. Osborne, M. Manfredi, GS-SE-FAS 3

PATH FORESEEN // Access from Shafts PAM4 TI8 Dump Area

Page 4: General Infrastructures Services Department LIU-SPS external beam dump - Internal Review Civil Engineering Aspect for Option B (LSS4) 30/7/2014 Martin

General Infrastructures Services Department

TAG41 Tunnel TAG42 slope: 7.26%Section view

~ 120 mTT41

TT41

TAG41

TI8

Plan view

B

B

B

B

C

C

C

C

Section B-BSection C-C

TT41TT41~ 3.40 m

~ 2.

70 m

~ 2.

15 m

TAG42

30/7/2014 J. Osborne, M. Manfredi, GS-SE-FAS 4

PATH FORESEEN // Access from Shafts PAM4 TI8 Dump Area

Page 5: General Infrastructures Services Department LIU-SPS external beam dump - Internal Review Civil Engineering Aspect for Option B (LSS4) 30/7/2014 Martin

General Infrastructures Services Department

Tunnel TAG42

Magnet: MQID.80500

Tunnel TT41

Tunnel TI8 slope: 0.4%TJ8

Plan view

~ 30 m

~ 12 m

DD

Section D-D

~ 6.00 m

~ 2.

15 m TT41TT41

New Tunnel foreseen which allows a straight

connection between

TAG42 --> TI8

30/7/2014 J. Osborne, M. Manfredi, GS-SE-FAS 5

PATH FORESEEN // Access from Shafts PAM4 TI8 Dump Area

Page 6: General Infrastructures Services Department LIU-SPS external beam dump - Internal Review Civil Engineering Aspect for Option B (LSS4) 30/7/2014 Martin

General Infrastructures Services Department

Existing TI8 tunnel

Existing TT41 tunnel

TI8 beam line

Dump line Plan view

• Extraction Point before MQID.80500• 7MBSG + 7 MBNH, 12.16m of final drift up to absorber, 93.65m total length

TI8 enlargementDUMP

Option B1, DUMP LINE characteristics:

Magnet: MQID.80500

30/7/2014 J. Osborne, M. Manfredi, GS-SE-FAS 6

EXTERNAL DUMP DESIGNED // Option B1 (single enlargement)

Section F-FCrane 5Ton?Ventilation

Unit

F

F

Option B1, CE conditions:• TI8 enlargement before the first MBNH• At least 4.80m of distance kept from the existing TT41 tunnel (4.92m calculated)• Single cross section, allow easy construction works and equipments

installation/maintenance• CONC+IRON+CONC used as shielding around the absorber (50+100+50)

Option B1, Enlargement size: 68.5m long – 10.5m wide

Page 7: General Infrastructures Services Department LIU-SPS external beam dump - Internal Review Civil Engineering Aspect for Option B (LSS4) 30/7/2014 Martin

General Infrastructures Services Department

Existing TI8 tunnel

Existing TT41 tunnelPlan view

TI8 enlargementDUMP

Magnet: MQID.80500

30/7/2014 J. Osborne, M. Manfredi, GS-SE-FAS 7

EXTERNAL DUMP DESIGNED // Option B2 (single enlargement)

Section F-FCrane 5Ton?Ventilation

Unit

F

F

Option B2, Enlargement size: 73.5m long – 10.5m wide

• Extraction Point before MQID.80500• 7MBSG + 7 MBNH, 17.16m of final drift up to absorber, 98.65m total length

Option B2, DUMP LINE characteristics:

• TI8 enlargement before the first MBNH• At least 4.80m of distance kept from the existing TT41 tunnel (4.92m calculated)• Single cross section, allow easy construction works and equipments

installation/maintenance• CONC+IRON+CONC used as shielding around the absorber (50+100+50)

TI8 beam line

Dump line

Option B2, CE conditions:

Page 8: General Infrastructures Services Department LIU-SPS external beam dump - Internal Review Civil Engineering Aspect for Option B (LSS4) 30/7/2014 Martin

General Infrastructures Services Department

Existing TI8 tunnel

Existing TT41 tunnelPlan view

TI8 enlargementDUMP

Magnet: MQID.80500

30/7/2014 J. Osborne, M. Manfredi, GS-SE-FAS 8

EXTERNAL DUMP DESIGNED // Option B3 (single enlargement)

Section F-FCrane 5Ton?Ventilation

Unit

F

F

Option B3, Enlargement size: 91.0m long – 10.5m wide

• Extraction Point before MQID.80500• 7MBSG + 3 MBNH, 62.57m of final drift up to absorber, 144.06m total length

Option B3, DUMP LINE characteristics:

Option B3, CE conditions:• TI8 enlargement before the first MBNH• At least 4.80m of distance kept from the existing TT41 tunnel (4.92m calculated)• Single cross section, allow easy construction works and equipment

installation/maintenance• CONC+IRON+CONC used as shielding around the absorber (50+100+50)

TI8 beam line

Dump line

Page 9: General Infrastructures Services Department LIU-SPS external beam dump - Internal Review Civil Engineering Aspect for Option B (LSS4) 30/7/2014 Martin

General Infrastructures Services Department

Existing TI8 tunnel

Existing TT41 tunnelPlan view

TI8 enlargement DUMP

Magnet: MQID.80600

30/7/2014 J. Osborne, M. Manfredi, GS-SE-FAS 9

EXTERNAL DUMP DESIGNED // Option B4 (single enlargement)

Section F-FCrane 5Ton?Ventilation

Unit

F

F

Option B4, Enlargement size: 83.6m long – 12.5m wide

• Extraction Point before MQID.80600• 7MBSG + 7 MBNH, 26.26m of final drift up to absorber, 107.76m total length

Option B4, DUMP LINE characteristics:

Option B4, CE conditions:• TI8 enlargement before the first MBNH• At least 4.80m of distance kept from the existing TT41 tunnel (8.38m calculated)• Single cross section, allow easy construction works and equipments

installation/maintenance• Only CONC used as shielding around the absorber (300cm)

TI8 beam line

Dump line

Page 10: General Infrastructures Services Department LIU-SPS external beam dump - Internal Review Civil Engineering Aspect for Option B (LSS4) 30/7/2014 Martin

General Infrastructures Services Department

New Tunnel TAG42 TI8

TI8 Enlargement

(+10%) Contingency for unknown/missing items

(+12%) Consultancy fees

ESTIMATE ACCURACY +/- 50%

OPTIONS OVERVIEW AND CE COST ESTIMATE

B2 B3 B4

73.5 x 10.5 91.5 x 10.5 83.6 x 12.5 (m)

30/7/2014 J. Osborne, M. Manfredi, GS-SE-FAS 10

Enlargement Size (L x W)

MQID.80500 MQID.80500 MQID.80600 -Extraction Point

Final Drift Length / Total Length 17.16 / 98.65 62.57 / 144.06 26.26 / 107.76 (m)

MBNH foreseen 7 3 7

Type of shielding (*) C+I+C C+I+C C

0.50 0.50 0.50 (MCHF)

Cost Estimate for Civil Engineering work (**): B2 B3 B4

6.80 8.40 9.80 (MCHF)

7.30 8.90 10.30 (MCHF)

0.73 0.89 1.03 (MCHF)

0.88 1.07 1.24 (MCHF)

8.91 10.86 12.57 (MCHF)TOTAL:

Options Overview:

(n°)

-

C+I+CCONCRETE: 50 (cm)IRON: 100 (cm)CONCRETE: 50 (cm) 200 (cm)

C CONCRETE: 300 (cm)

(*) shielding thickness

(**) NOT INCLUDED: GS-SE Resources, Demolition existing TI8 tunnel, Instrumentation for ground stability monitoring, Special works, Services (ventilation, electricity, etc)

Page 11: General Infrastructures Services Department LIU-SPS external beam dump - Internal Review Civil Engineering Aspect for Option B (LSS4) 30/7/2014 Martin

General Infrastructures Services Department

OPTIONS OVERVIEW AND PLANNING

30/7/2014 J. Osborne, M. Manfredi, GS-SE-FAS 11

Options Overview:• Extraction Point before MQID80500

• Extraction Point before MQID80600 DUMP LINE shifted 30m downstream

Feasible using shielding blocks with CONC+IRON+CONC //Option B2,B3 //

Feasible using shielding blocks with ONLY CONC (two enlargement at least are needed more cost foreseen, )

NOT Feasible using shielding blocks with ONLY CONC (and a single enlargement)

Feasible using shielding blocks with ONLY CONC (and a single enlargement) //Option B4//

20 months20 months

Planning and Resources:

(*) The resources given in this table are over and above the existing resources currently in GS-SE Group