GE Energy Storage
LM6000 Hybrid EGTTM
GE Hybrid Solutions for today’s grid
Joe HeinzmannGE Energy StorageHybrid Initiative Product LeaderNext Gen San Francisco
2GE Title or job number
2/16/2017
3GE Title or job number
2/16/2017
The Grid is a busy place3
4GE Title or job number
2/16/2017
Curtailed Renewables
Peak Load
Maximize Baseload
Spinning Reserve
Fast Ramping
Frequency Regulation
Baseload0
-10
10
20
30
40
Reduce Emissions
Summer day under 50% renewable conditions
ES provides instantaneous local capacity, & cont inuous ancillary services with no fuel consumption or emissions.
Energy Storage is a flexible asset that provides unprecedented flexibility in grid
optimization.Baseload causes excess solar to be curtailed
Short duration peaks after sunset
Respond to sunset dynamics
Real-time frequency control
Dynamic response to events (clouds)
Enables high capacity factor baseload
From peak capacity and ancillary services12:00 18:0006:0000:00 24:00
Sys
tem
Dem
and
(MW
)
© 2016 General Electric Company - All rights reserved
5GE Title or job number
2/16/2017
Curtailed Renewables
Peak Load
Maximize Baseload
Spinning Reserve
Fast Ramping
Frequency Regulation
Reduce Emissions
ES provides instantaneous local capacity, & cont inuous ancillary services with no local fuel consumption or emissions.
Additional clean energy into system
Reduction in conventional “peakers”
Enables dynamic capacity
Provides 100% of FR with no emissions or constraints
Provides 100% of SR with no emissions or constraints
Enables high capacity factor of baseload generation
From peak capacity and ancillary services
January February March April May June July August September October NovemberDecember
© 2016 General Electric Company - All rights reserved
Addresses target pain points- with minimal siting issues
Grid-connected storage provides value throughout the elect ricity value chain
6
• Emissions/costs• Variable peaks• Low asset utilization
• Flexible generation• Improve power quality• Bolster reserve margin
• Power quality issues• System reliability• Capacity constraints
• Renewable integration• Peak management• Asset upgrade deferral
• Demand charge/High Peak• High retail rates• Power outage
• Peak shifting• Ancillary services• Self-use
Pain Points:
Benefits:
Dist ribut ion Load SitedGeneration
© 2016 General Electric Company - All rights reserved
Rapidly declining Battery and System costs
100
1,000
10,000
100,000
1,000,000
'96 '97 '98 '99 '00 '01 '02 '03 '04 '05 '06 '07 '08 '09 '10 '11 '12 '13 '14 '15 '16 '17 '18 '19 '20 '21 '22 '23 '24 '25
$700/kWh
$250/MWh
$150/MWh
$50/MWh
$6/watt
$1/watt
$3/watt
$65/MWh
$450/kWh
$350/kWh
Ann
ual M
W in
stal
led
(log
scal
e)
Wind
Solar PVEnergy Storage
$55/MWhCCGT + ST
LCOE
LCOECapEx
CapEx
$2,000/kWh
7
$300/kWh
From 2010 to 2020 marks a 40X improvement in overall ES viability
Sources: EIA, IEA, NREL, GWEC, EPIA, BNEF, Lux, Navigant, HIS CERA, GE AnSolar : PV panel cost
© 2016 General Electric Company - All rights reserved
© 2016, General Electric Company. Proprietary information. All rights reserved.
8
Anatomy of a Energy Storage System
Dispatch communication and Controls
AC Front End
Interconnect
AC Collector
Inverters
Isolation Transformers
DC Enclosure
Batteries
Fire Suppression
Climate Control
8
© 2016, General Electric Company. Proprietary information. All rights reserved.
9
Scalable Solutions
1 MVA / 6 MWh
1 MVA / 4 MWh
1 MVA / 2 MWh
0.5 MVA / 1 MWh
© 2016, General Electric Company. Proprietary information. All rights reserved.
10
GE MW Class ES PlatformCustom solutions from standard, proven building blocks
Standard pre-fab enclosure + additional safety features
Battery EnclosureGE’s Mark VIe Control System has more than 16 million hours of combined operation
Controls
>3.5 million GE Prolectransformers installed
Transformer
>25,000 GE Renewables Inverters installed across Wind, Solar, and ES
InverterProven Li-Ion chemistryTier 1 Suppliers with full GE Supplier Qualification
DC Block
© 2016 General Electric Company - All rights reserved
© 2016, General Electric Company. Proprietary information. All rights reserved.
11
GE Energy Storage Grid Projects
GE Energy Storage Grid Projects
4 MW / 18 MWh Behind the Meterat large Indust rial
(5x) 50 kW / 100 kWh T&D Network Support
1 MW / 2 MWhWind Integrat ion
(3x) 200 kW / 400 kWhIntegrated Wind Turbine
(2x) 10 kW / 20 kWh Behind the Meter
1 MW / 2 MWh T&D Network
Support
1 MW / 2 MWh RenewableIntegrat ion
37 MVA / 20 MWh Grid Stability
Imperial Irrigation District
0.5 MW / 1 MWh Behind the Meter at indust rial plant
~ 80 MW / ~75 MWh of Grid projects Installed or in Process
7MW / 7MWh Grid StabilityOntario IESO
2MW / 8MWhSolar Integrat ion
Commissioned
Recent order or being built
3MW / 6 MWh PV/Storage Micro grid
MAECI Solar
200kW/1MWhT&D Network Support
Major Ut ilit y
1 MW / 2 MWh Behind the Meter
© 2016 General Electric Company - All rights reserved
MOU or Negotiation
(2x) 10 MW / 5 MWh EGT
300 MW / 300 MWhFFR
Arenko
~ 370 MW / ~375 MWh of Grid projects total
© 2016 General Electric Company - All rights reserved
GE Power
POWERING EVERYONE
Issues facing Generation Fleets• Integration of variable generation
• Flat load growth – But faster ramps and higher peaks
• Multiple starts per day
• Dispatch to min loads
• Increased need for spinning reserve
• Contingency Reserve/Inertia requirements
• Avoiding Stranded Assets
• Reducing emissions
© 2016, General Electric Company. Proprietary information. All rights reserved.
13
GE Introduces the
LM6000 Hybrid EGT™
• Pmin of Zero
• 50 MWs Immediate Responsive Contingency
• Primary Frequency Response - NERC BAL-003
• 50MW Flexible Response without start time
• -8 to +5 MVAR Voltage support
• Black Start Capability
Greenhouse Gas Free Attributes
Reduced GHG/Lower Heat rate operation• 50 MWs Peaking Energy for Local
Contingency
• 25 MWs of High Speed Frequency Regulation
• Self Managed BESS SOC
ProvidesReduced Costs and Higher Asset Revenue
• Optimized System Dispatch
• Lower System Fuel Use
• Lower System GHG Emissions
• Increased LM6000 revenue
• Lower LM6000 Life Cycle Costs
Enables
© 2016, General Electric Company. Proprietary information. All rights reserved.
1414
Reduced system energy costs
© 2016, General Electric Company. Proprietary information. All rights reserved.
15
Hybrid EGT Benefits
© 2016, General Electric Company. Proprietary information. All rights reserved.
16
Hybrid EGT Operation
16
© 2016, General Electric Company. Proprietary information. All rights reserved.
17
GE LM6000 Hybrid EGT™LM6000 MarkVIe Integrated Control System
• OpFlex Control Upgrade - Mark VI/e & Woodward compatible
– 5 min Fast start - Seamless restart
– Fast Synchronization
– Improved NOx Controls at ultra low output
10MW GE Packaged Energy Storage System • GE BESS Mark Vie BESS smart Dispatch controls
• 10MW Battery with an Integrated Enclosure with HVAC & Fire Suppression System
• GE Brilliance Inverters with GE Prolec Transformers
• GE Collector Switchgear and Auxilliary Power MCC
Fully integrated & performance backed by GE10MW GE Packaged ES System
LM6k Gas Turbine Package
© 2016, General Electric Company. Proprietary information. All rights reserved.
18
10MW GE Packaged Energy Storage System Proven building blocks
18
Standard pre-fab enclosure + additional safety featuresBattery Enclosure
GE’s Mark VIe Control System has more than 16 million hours of combined operation
Controls
>3.5 million GE Prolectransformers installed
Transformer
>25,000 GE Renewables Inverters installed across Wind, Solar, and ES
InverterProven Li-Ion chemistryTier 1 Suppliers with full GE Supplier Qualification
DC Block
© 2016 General Electric Company - All rights reserved
70’
© 2016, General Electric Company. Proprietary information. All rights reserved.
19
Detailed Layout
~40’
~140’
© 2016, General Electric Company. Proprietary information. All rights reserved.
20
EGT Very High Level Single Line Drawing & Controls
GRID
GSU
52G 52B
GT BESS BESS Aux
Power
GT Aux
Power
GE Hybrid Supervisory Controls
© 2016, General Electric Company. Proprietary information. All rights reserved.
2121
© 2016, General Electric Company. Proprietary information. All rights reserved.
22
Typical Project Schedule
© 2016, General Electric Company. Proprietary information. All rights reserved.
23
GE Hybrid LM6000 Comparison
Direct Project Value ExistingLM6000
10MW 4 hr BESS Only
LM6000 EGT Upgrade
Contingency reserve value no emissions 0 10MWs 50MWInstant On
RA Value 50 MWs 10MWs 50MWsMax Power 50 MWs 10MWs 50MWsMin Power >0 -10MWs -10MWsSpinning reserve value no emissions 0 10MWs 50MWsEnergy capacity Unlimited Very Limited UnlimitedHigh speed Frequency regulation 0 10 MWs 10-25MWsGrid Energy Neutrality
Black Start with no emissions ?
Utilize Existing Interconnect N/A
Utilize Existing Substation & GSU N/A
Utilize existing Communications and Backhaul N/A
Utilize existing Land N/A
Speed to Install N/A Slower FastCost 0 $$ $
Joe HeinzmannGE Energy StorageHybrid Initiative Commercialization [email protected]