1 Barber Tracker Planning & Mechanical Preparation June 2009 Tracker Planning & Mechanical Preparation An outline of (known) outstanding work to be carried out to integrate the trackers into the MICE experiment Alignment of the Tracker into the Solenoid bore Fitting of the Hall probes Replacement of known ‘BAD’ light guides Trial assembly of the blackout tent in the available space Assembly of the fibre support trellis Gas system Helium Window

G.Barber Tracker Planning & Mechanical Preparation June 2009 1 Tracker Planning & Mechanical Preparation An outline of (known) outstanding work to be carried

Embed Size (px)

Citation preview

1G.Barber Tracker Planning & Mechanical Preparation June 2009

Tracker Planning & Mechanical Preparation

An outline of (known) outstanding work to be carried out to integrate the trackers into the MICE experiment

• Alignment of the Tracker into the Solenoid bore

• Fitting of the Hall probes

• Replacement of known ‘BAD’ light guides

• Trial assembly of the blackout tent in the available space

• Assembly of the fibre support trellis

• Gas system

• Helium Window

2G.Barber Tracker Planning & Mechanical Preparation June 2009

Tracker Alignment into Mice

An outline into the procedure for aligning the fibre trackers into the Spectrometer Solenoids in the Mice experiment

3G.Barber Tracker Planning & Mechanical Preparation June 2009

Carbon Fibre Stations

The carbon fibre stations are key to the alignment, they have

all been machined on a CNC. The planes were added using

this machined accuracy therefore we know the mean

axis of the tracker with relation to points on these stations

4G.Barber Tracker Planning & Mechanical Preparation June 2009

Tracker Support Feet

The tracker is supported at 4 points in the bore of the solenoid, these 4 points are adjustable using eccentric cams to give the required position.

Support Points

Adjustable Cam Mounts

5G.Barber Tracker Planning & Mechanical Preparation June 2009

X & Y Alignment Tool

Knowing that the stations are accurately machined means we can use this to set the position of the tracker inside the bore of the solenoid. To do this we make a replica of the bottom half of the station, this includes the mounting positions. It has a Ø2mm hole at the known centre of the stations which can be surveyed. The alignment tool has similar adjustable cams to allow the Ø2mm hole (centre of station) to be positioned on the beam line axis. This is done at both support positions along the solenoid bore as the bore concentricity is not guaranteed. Once this is done and because the tool is an exact copy of the station profile a measurement can be taken of the distance between the cam edge that the tool sits on and the profile. This measurement is duplicated on the actual station and when pushed into the solenoid to the correct position the tracker will be on axis.

Cams sit on Bore Wall

3rd Steady

Measurement to Replicate

Adjustment

Ø2mm Hole(Center of Station)

6G.Barber Tracker Planning & Mechanical Preparation June 2009

Phi and Z Alignment

The phi and Z alignment relies on a hemispherical bracket on the tracker being pulled into a Vee block that is mounted and fixed from the patch panel. This block needs to be aligned then doweled, Z is just a straight measurement but phi will need to be surveyed. To do this a bar with Ø2mm hole is held in the Vee block as the diagram shows.

The alignment bar ispulled into the Vee

Hemisphere Bracket pulled into Vee to

locate tracker

This end of the bracketis fixed and doweled

to the patch panelafter alignment

Ø2mm Hole

7G.Barber Tracker Planning & Mechanical Preparation June 2009

Fitting of the Hall Probes

There are a series of hall probes installed into the bore of the solenoid. The positions are yet to be defined but at least two are on the bore, fitted to collars and the remainder are fitted to brackets attached to the tracker space frame.

Hall Probe support plate (G10)

W Section to strengthen bond to space frame

Collar to attach the Hall Probes into the bore of the solenoid.These are removable to allow the tracker to be withdrawn

The connections to the outside world are via a connector block that fits into the 26th position in the patch panel.

8G.Barber Tracker Planning & Mechanical Preparation June 2009

Replacement of the ‘BAD’ Waveguides

Perhaps ‘BAD’ is to strong a word but during the assembly for the cosmic ray testing it was noticed that 2 of the internal waveguides were damaged. Both were on the same assembly and as we have a spare waveguide it should be a simple matter to replace it.The bad channels are Station 15-connector C28-Fibres 21 & 22

9G.Barber Tracker Planning & Mechanical Preparation June 2009

Trial Assembly of the Blackout Tent

As the layout in the hall has evolved it is apparent that the existing tent (6M x 3M with a 1.5M x 1.5M entrance porch) will not be a comfortable fit. What I am proposing is to erect the tent in situ during a suitable time slot. This will enable us to make any modifications needed. We may need to include and seal cut-outs for trunking, racks etc and emergency routes will need to be considered.

2.5

M

10G.Barber Tracker Planning & Mechanical Preparation June 2009

Assembly of the Fibre Support Trellis

Due to the unpredictable ‘lay’ of the external waveguides and changes to the height of the cassettes, the trellis that supports the waveguides is likely to need modifying to suit. As it is constructed from Minitec section (big boys Meccano) this is easy to do. The protection covers will be fabricated from mesh so this again can be manufactured in situ.

11G.Barber Tracker Planning & Mechanical Preparation June 2009

Helium Gas System

There is a need to lower the Xo in the tracker volume and so the air will be replaced with helium. As the volume will not be gas tight due to the nature of the connectors it will be necessary to bubble the helium at a low rate. At this rate it would take a while to purge the air from the system so we use a two setting system. Using standard air valve that are linked mechanically we can purge at a much higher flow rate and then switch to the run flow rate. The mechanical link ensures that both input and output switch at the same time.

12G.Barber Tracker Planning & Mechanical Preparation June 2009

Helium Gas Window

The helium window is not yet fully designed, and will need to be FEA ’d as it is a pressure window. It is to be fitted to a set of holes that are the same as the holes that seal the patch panel at the opposite end. It appears that these holes have not been drilled at Wang and will need to be drilled in situ by hand. This can be done using a template that is clamped in place.

13G.Barber Tracker Planning & Mechanical Preparation June 2009

Conclusions

There are still a number of things to do, many of them can be done only after the cosmic ray tests are completed or when the solenoid arrives. It is therefore important to prepare as much as possible, for example mods that may be required to the blackout tent. This may be carried out during a period when the area is less busy.