sample gantt chart for road construction (rural)
Citation preview
ID Task Name Duration Start Finish
1 Site Mobilization 47 days Tue 9/15/15 Sat 10/31/15
2 Access Road Construction61 days Sun 11/1/15 Thu 12/31/15
3 Construction of Weir/Intake
305 days Sun 11/1/15 Wed 8/31/16
4 Construction of Desilting Tank
152 days Fri 1/1/16 Tue 5/31/16
5 Construction of Headrace Civil Works
335 days Sun 11/1/15 Fri 9/30/16
6 Construction of Surge Tank
153 days Sun 5/1/16 Fri 9/30/16
7 Construction of Penstock Civil Works
304 days Mon 2/1/16 Wed 11/30/16
8 Construction of Power House
304 days Wed 6/1/16 Fri 3/31/17
9 Construction of Tailrace 243 days Sat 10/1/16 Wed 5/31/17
10 Construction of Switch Yard
304 days Sat 10/1/16 Mon 7/31/17
8/16 9/20 10/25 11/29 1/3 2/7 3/13 4/17
July 1 September 11 November 21 February 1 April 11
Page 1
4/17 5/22 6/26 7/31 9/4 10/9 11/13 12/18 1/22 2/26 4/2 5/7 6/11 7/16 8/20
April 11 June 21 September 1 November 11 January 21 April 1 June 11
Page 2