ID Task Name Duration Start Finish 1 Site Mobilization 47 days Tue 9/15/15 Sat 10/31/15 2 Access Road Constructio 61 days Sun 11/1/15 Thu 12/31/15 3 Construction of Weir/Intake 305 days Sun 11/1/15 Wed 8/31/16 4 Construction of Desilting Tank 152 days Fri 1/1/16 Tue 5/31/16 5 Construction of Headrace Civil Works 335 days Sun 11/1/15 Fri 9/30/16 6 Construction of Surge Tank 153 days Sun 5/1/16 Fri 9/30/16 7 Construction of Penstock Civil Works 304 days Mon 2/1/16 Wed 11/30/16 8 Construction of Power House 304 days Wed 6/1/16 Fri 3/31/17 9 Construction of Tailrace 243 days Sat 10/1/16 Wed 5/31/17 10 Construction of Switch Yard 304 days Sat 10/1/16 Mon 7/31/17 8/16 9/20 10/25 11/29 1/3 2/7 3/13 4/17 September 11 November 21 February 1 April 11 Page 1

gantt chart sample

Embed Size (px)

DESCRIPTION

sample gantt chart for road construction (rural)

Citation preview

Page 1: gantt chart sample

ID Task Name Duration Start Finish

1 Site Mobilization 47 days Tue 9/15/15 Sat 10/31/15

2 Access Road Construction61 days Sun 11/1/15 Thu 12/31/15

3 Construction of Weir/Intake

305 days Sun 11/1/15 Wed 8/31/16

4 Construction of Desilting Tank

152 days Fri 1/1/16 Tue 5/31/16

5 Construction of Headrace Civil Works

335 days Sun 11/1/15 Fri 9/30/16

6 Construction of Surge Tank

153 days Sun 5/1/16 Fri 9/30/16

7 Construction of Penstock Civil Works

304 days Mon 2/1/16 Wed 11/30/16

8 Construction of Power House

304 days Wed 6/1/16 Fri 3/31/17

9 Construction of Tailrace 243 days Sat 10/1/16 Wed 5/31/17

10 Construction of Switch Yard

304 days Sat 10/1/16 Mon 7/31/17

8/16 9/20 10/25 11/29 1/3 2/7 3/13 4/17

July 1 September 11 November 21 February 1 April 11

Page 1

Page 2: gantt chart sample

4/17 5/22 6/26 7/31 9/4 10/9 11/13 12/18 1/22 2/26 4/2 5/7 6/11 7/16 8/20

April 11 June 21 September 1 November 11 January 21 April 1 June 11

Page 2