ID Task
Mode
Task Name Duration Start Finish Predecessors Resource Names
1 Phase #1 7 days Thu 28/11/13 Fri 6/12/13
2 Staff management/allocation 3 days Thu 28/11/13 Mon 2/12/13
3 Project/Safety Briefing 3 days Tue 3/12/13 Thu 5/12/13 2
4 Implement evacuation plan 1 day Fri 6/12/13 Fri 6/12/13 3
5 Preparing site 10 days Mon 9/12/13 Fri 20/12/13 1
6 Allocate dump site 1.5 days Mon 9/12/13 Tue 10/12/13 Admin[200%]
7 Allocate material drop off zone 1.5 days Mon 9/12/13 Tue 10/12/13 Admin[200%]
8 Install temporary office 10 days Mon 9/12/13 Fri 20/12/13 Labour[600%],Truck,Crane,Truck driver,Crane operator
9 Install lunch room 5 days Mon 9/12/13 Fri 13/12/13 Crane,Truck,Labour[600%],Crane operator,Truck driver
10 Install storage room 5 days Mon 9/12/13 Fri 13/12/13 Crane,Crane operator,Labour[600%],Truck,Truck driver
11 Handling delivery 3 days Mon 16/12/13Wed 18/12/1310
12 Delivery of piles 3 days Mon 16/12/13Wed 18/12/13 Truck,Crane,Labour[400%],Crane operator,Truck driver
13 Delivery of prefabricated reinforcement cage3 days Mon 16/12/13Wed 18/12/13 Crane,Crane operator,Labour[400%],Truck,Truck driver
14 Stage 1 106 daysMon 23/12/13Mon 19/05/14
15 Demolition and Construction Phase 1 (Grid A-C)24 days Mon 23/12/13Thu 23/01/14 5
16 Remove existing fender system 10 days Mon 23/12/13Fri 3/01/14 Labour[200%],Crane,Crane operator
17 Remove existing deck 5 days Mon 6/01/14 Fri 10/01/14 16 Labour[400%],Crane,Crane operator
18 -clear area 1 day Mon 6/01/14 Mon 6/01/14
19 -install fences/handrails 3 days Mon 6/01/14 Wed 8/01/14
20 -cut deck 2 days Thu 9/01/14 Fri 10/01/14 19
21 -dispose deck 2 days Thu 9/01/14 Fri 10/01/14 19
22 Remove existing piles 2 days Mon 13/01/14Tue 14/01/14 17 Labour[400%],Piling rig[200%],Piling rig operator[200%]
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
W T F S S M T W T F S
24 Nov '13 1 Dec '13
Critical
Critical Split
Critical Progress
Task
Split
Task Progress
Manual Task
Start-only
Finish-only
Duration-only
Baseline
Baseline Split
Baseline Milestone
Milestone
Summary Progress
Summary
Manual Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Deadline
fc
Page 1
ID Task
Mode
Task Name Duration Start Finish Predecessors Resource Names
23 -vibrate and pull piles 2 days Mon 13/01/14Tue 14/01/14
24 -dispose piles 2 days Mon 13/01/14Tue 14/01/14
25 Drive new piles 3 days Wed 15/01/14Fri 17/01/14 22 Site Supervisor,Piling rig operator,Welder,Surveyor,Piling rig
26 -pitch 3 days Wed 15/01/14Fri 17/01/14
27 -adjust position 3 days Wed 15/01/14Fri 17/01/14
28 -soft start vibration 3 days Wed 15/01/14Fri 17/01/14
29 -hammer 3 days Wed 15/01/14Fri 17/01/14
30 -prepare pile head 3 days Wed 15/01/14Fri 17/01/14
31 Install concrete muffs 4 days Mon 20/01/14Thu 23/01/14 25 Crawler crane,Crawler crane operator,Labour[200%]
32 -bolt equal angles 2 days Mon 20/01/14Tue 21/01/14 30
33 -place concrete muffs on equal angles2 days Wed 22/01/14Thu 23/01/14 32
34 Demolition and Construction Phase 2 (Grid C-E)14 days Mon 13/01/14Thu 30/01/14
52 Demolition and Construction Phase 3 (Grid E-G)14 days Mon 20/01/14Thu 6/02/14
70 Demolition and Construction Phase 4 (Grid G-I)14 days Mon 27/01/14Thu 13/02/14
88 Demolition and Construction Phase 5 (Grid I-K)14 days Mon 3/02/14 Thu 20/02/14
106 Demolition and Construction Phase 6 (Grid K-M)14 days Mon 10/02/14Thu 27/02/14
124 Demolition and Construction Phase 7 (Grid M-O)14 days Mon 17/02/14Thu 6/03/14
142 Demolition and Construction Phase 8 (Grid O-Q)14 days Mon 24/02/14Thu 13/03/14
160 Demolition and Construction Phase 9 (Grid Q-S)14 days Mon 3/03/14 Thu 20/03/14
178 Demolition and Construction Phase 10 (Grid S-U)14 days Mon 10/03/14Thu 27/03/14
196 Demolition and Construction Phase 11 (Grid V-X)14 days Mon 17/03/14Thu 3/04/14
214 Demolition and Construction Phase 11 (Grid X-Z)14 days Mon 24/03/14Thu 10/04/14
W T F S S M T W T F S
24 Nov '13 1 Dec '13
Critical
Critical Split
Critical Progress
Task
Split
Task Progress
Manual Task
Start-only
Finish-only
Duration-only
Baseline
Baseline Split
Baseline Milestone
Milestone
Summary Progress
Summary
Manual Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Deadline
fc
Page 2
ID Task
Mode
Task Name Duration Start Finish Predecessors Resource Names
232 Demolition and Construction Phase 12 (Grid Z-A2)14 days Mon 31/03/14Thu 17/04/14
250 Demolition and Construction Phase 13 (Grid A2-A4)14 days Mon 7/04/14 Thu 24/04/14
268 Demolition and Construction Phase 14 (Grid A4-A6)14 days Mon 14/04/14Thu 1/05/14
286 Demolition and Construction Phase 15 (Grid A6-A9)21 days Mon 21/04/14Mon 19/05/14
304 Stage 2 40 days Tue 20/05/14 Mon 14/07/14
305 Demolition and Deck & Beam Construction Phase 1 (Grid A-C)16 days Tue 20/05/14 Tue 10/06/14 286
306 Remove the remaining existing deck in between new piles4 days Tue 20/05/14 Fri 23/05/14 Labour[400%],Crane,Crane operator
307 -clear area 1 day Tue 20/05/14 Tue 20/05/14
308 -install fences/handrails 1 day Tue 20/05/14 Tue 20/05/14
309 -cut deck 3 days Wed 21/05/14Fri 23/05/14 308
310 -dispose deck 3 days Wed 21/05/14Fri 23/05/14 308
311 Remove existing piles 3 days Mon 26/05/14Wed 28/05/14306 Labour[400%],Piling rig[200%],Piling rig operator[200%]
312 -vibrate and pull piles 3 days Mon 26/05/14Wed 28/05/14
313 -dispose piles 3 days Mon 26/05/14Wed 28/05/14
314 Place precast concrete plank 3 days Thu 29/05/14 Mon 2/06/14 311 Crawler crane,Crawler crane operator,Labour[400%]
315 Place pile reinforcement cages 3 days Tue 3/06/14 Thu 5/06/14 314 Labour[400%],Crawler crane,Crawler crane operator
316 Place beam reinforcement cages3 days Fri 6/06/14 Tue 10/06/14 315 Truck,Truck driver,Crawler crane operator,Crawler crane,Labour[400%]
317 Place top of slab reinforcement 2 days Fri 6/06/14 Mon 9/06/14 315 Truck,Truck driver,Crawler crane,Crawler crane operator,Labour[400%]
318 Demolition and Deck & Beam Construction Phase 2 (Grid C-E)16 days Mon 26/05/14Mon 16/06/14
331 Demolition and Deck & Beam Construction Phase 3 (Grid E-G)16 days Fri 30/05/14 Fri 20/06/14
344 Demolition and Deck & Beam Construction Phase 4 (Grid G-I)16 days Thu 5/06/14 Thu 26/06/14
357 Demolition and Deck & Beam Construction Phase 5 (Grid I-K)16 days Wed 11/06/14Wed 2/07/14
W T F S S M T W T F S
24 Nov '13 1 Dec '13
Critical
Critical Split
Critical Progress
Task
Split
Task Progress
Manual Task
Start-only
Finish-only
Duration-only
Baseline
Baseline Split
Baseline Milestone
Milestone
Summary Progress
Summary
Manual Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Deadline
fc
Page 3
ID Task
Mode
Task Name Duration Start Finish Predecessors Resource Names
370 Demolition and Deck & Beam Construction Phase 6 (Grid K-M)16 days Tue 17/06/14 Tue 8/07/14
383 Demolition and Deck & Beam Construction Phase 7 (Grid M-O)16 days Mon 23/06/14Mon 14/07/14
384 Remove the remaining existing deck in between new piles4 days Mon 23/06/14Thu 26/06/14 371 Labour[400%],Crane,Crane operator
385 -clear area 1 day Mon 23/06/14Mon 23/06/14
386 -install fences/handrails 1 day Mon 23/06/14Mon 23/06/14
387 -cut deck 3 days Tue 24/06/14 Thu 26/06/14 386
388 -dispose deck 3 days Tue 24/06/14 Thu 26/06/14 386
389 Remove existing piles 3 days Fri 27/06/14 Tue 1/07/14 384 Labour[400%],Piling rig[200%],Piling rig operator[200%]
390 -vibrate and pull piles 3 days Fri 27/06/14 Tue 1/07/14
391 -dispose piles 3 days Fri 27/06/14 Tue 1/07/14
392 Place precast concrete plank 3 days Wed 2/07/14 Fri 4/07/14 389 Crawler crane,Crawler crane operator,Labour[400%]
393 Place pile reinforcement cages 3 days Mon 7/07/14 Wed 9/07/14 392 Labour[400%],Crawler crane,Crawler crane operator
394 Place beam reinforcement cages3 days Thu 10/07/14 Mon 14/07/14393 Truck,Truck driver,Crawler crane operator,Crawler crane,Labour[400%]
395 Place top of slab reinforcement 2 days Thu 10/07/14 Fri 11/07/14 393 Truck,Truck driver,Crawler crane,Crawler crane operator,Labour[400%]
W T F S S M T W T F S
24 Nov '13 1 Dec '13
Critical
Critical Split
Critical Progress
Task
Split
Task Progress
Manual Task
Start-only
Finish-only
Duration-only
Baseline
Baseline Split
Baseline Milestone
Milestone
Summary Progress
Summary
Manual Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Deadline
fc
Page 4
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T
1 Dec '13 8 Dec '13 15 Dec '13 22 Dec '13 29 Dec '13 5 Jan '14 12 Jan '14 19 Jan '14
Critical
Critical Split
Critical Progress
Task
Split
Task Progress
Manual Task
Start-only
Finish-only
Duration-only
Baseline
Baseline Split
Baseline Milestone
Milestone
Summary Progress
Summary
Manual Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Deadline
fc
Page 5
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T
1 Dec '13 8 Dec '13 15 Dec '13 22 Dec '13 29 Dec '13 5 Jan '14 12 Jan '14 19 Jan '14
Critical
Critical Split
Critical Progress
Task
Split
Task Progress
Manual Task
Start-only
Finish-only
Duration-only
Baseline
Baseline Split
Baseline Milestone
Milestone
Summary Progress
Summary
Manual Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Deadline
fc
Page 6
S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T
1 Dec '13 8 Dec '13 15 Dec '13 22 Dec '13 29 Dec '13 5 Jan '14 12 Jan '14 19 Jan '14
Critical
Critical Split
Critical Progress
Task
Split
Task Progress
Manual Task
Start-only
Finish-only
Duration-only
Baseline
Baseline Split
Baseline Milestone
Milestone
Summary Progress
Summary
Manual Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Deadline
fc
Page 7
S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T
1 Dec '13 8 Dec '13 15 Dec '13 22 Dec '13 29 Dec '13 5 Jan '14 12 Jan '14 19 Jan '14
Critical
Critical Split
Critical Progress
Task
Split
Task Progress
Manual Task
Start-only
Finish-only
Duration-only
Baseline
Baseline Split
Baseline Milestone
Milestone
Summary Progress
Summary
Manual Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Deadline
fc
Page 8
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F
19 Jan '14 26 Jan '14 2 Feb '14 9 Feb '14 16 Feb '14 23 Feb '14 2 Mar '14
Critical
Critical Split
Critical Progress
Task
Split
Task Progress
Manual Task
Start-only
Finish-only
Duration-only
Baseline
Baseline Split
Baseline Milestone
Milestone
Summary Progress
Summary
Manual Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Deadline
fc
Page 9
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F
19 Jan '14 26 Jan '14 2 Feb '14 9 Feb '14 16 Feb '14 23 Feb '14 2 Mar '14
Critical
Critical Split
Critical Progress
Task
Split
Task Progress
Manual Task
Start-only
Finish-only
Duration-only
Baseline
Baseline Split
Baseline Milestone
Milestone
Summary Progress
Summary
Manual Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Deadline
fc
Page 10
0%
0%
0%
0%
T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F
19 Jan '14 26 Jan '14 2 Feb '14 9 Feb '14 16 Feb '14 23 Feb '14 2 Mar '14
Critical
Critical Split
Critical Progress
Task
Split
Task Progress
Manual Task
Start-only
Finish-only
Duration-only
Baseline
Baseline Split
Baseline Milestone
Milestone
Summary Progress
Summary
Manual Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Deadline
fc
Page 11
T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F
19 Jan '14 26 Jan '14 2 Feb '14 9 Feb '14 16 Feb '14 23 Feb '14 2 Mar '14
Critical
Critical Split
Critical Progress
Task
Split
Task Progress
Manual Task
Start-only
Finish-only
Duration-only
Baseline
Baseline Split
Baseline Milestone
Milestone
Summary Progress
Summary
Manual Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Deadline
fc
Page 12
0%
0%
F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M
2 Mar '14 9 Mar '14 16 Mar '14 23 Mar '14 30 Mar '14 6 Apr '14 13 Apr '14 20 Apr '14
Critical
Critical Split
Critical Progress
Task
Split
Task Progress
Manual Task
Start-only
Finish-only
Duration-only
Baseline
Baseline Split
Baseline Milestone
Milestone
Summary Progress
Summary
Manual Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Deadline
fc
Page 13
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M
2 Mar '14 9 Mar '14 16 Mar '14 23 Mar '14 30 Mar '14 6 Apr '14 13 Apr '14 20 Apr '14
Critical
Critical Split
Critical Progress
Task
Split
Task Progress
Manual Task
Start-only
Finish-only
Duration-only
Baseline
Baseline Split
Baseline Milestone
Milestone
Summary Progress
Summary
Manual Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Deadline
fc
Page 14
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M
2 Mar '14 9 Mar '14 16 Mar '14 23 Mar '14 30 Mar '14 6 Apr '14 13 Apr '14 20 Apr '14
Critical
Critical Split
Critical Progress
Task
Split
Task Progress
Manual Task
Start-only
Finish-only
Duration-only
Baseline
Baseline Split
Baseline Milestone
Milestone
Summary Progress
Summary
Manual Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Deadline
fc
Page 15
F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M
2 Mar '14 9 Mar '14 16 Mar '14 23 Mar '14 30 Mar '14 6 Apr '14 13 Apr '14 20 Apr '14
Critical
Critical Split
Critical Progress
Task
Split
Task Progress
Manual Task
Start-only
Finish-only
Duration-only
Baseline
Baseline Split
Baseline Milestone
Milestone
Summary Progress
Summary
Manual Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Deadline
fc
Page 16
0%
M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T
20 Apr '14 27 Apr '14 4 May '14 11 May '14 18 May '14 25 May '14 1 Jun '14
Critical
Critical Split
Critical Progress
Task
Split
Task Progress
Manual Task
Start-only
Finish-only
Duration-only
Baseline
Baseline Split
Baseline Milestone
Milestone
Summary Progress
Summary
Manual Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Deadline
fc
Page 17
0%
0%
0%
0%
0%
0%
M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T
20 Apr '14 27 Apr '14 4 May '14 11 May '14 18 May '14 25 May '14 1 Jun '14
Critical
Critical Split
Critical Progress
Task
Split
Task Progress
Manual Task
Start-only
Finish-only
Duration-only
Baseline
Baseline Split
Baseline Milestone
Milestone
Summary Progress
Summary
Manual Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Deadline
fc
Page 18
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T
20 Apr '14 27 Apr '14 4 May '14 11 May '14 18 May '14 25 May '14 1 Jun '14
Critical
Critical Split
Critical Progress
Task
Split
Task Progress
Manual Task
Start-only
Finish-only
Duration-only
Baseline
Baseline Split
Baseline Milestone
Milestone
Summary Progress
Summary
Manual Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Deadline
fc
Page 19
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T
20 Apr '14 27 Apr '14 4 May '14 11 May '14 18 May '14 25 May '14 1 Jun '14
Critical
Critical Split
Critical Progress
Task
Split
Task Progress
Manual Task
Start-only
Finish-only
Duration-only
Baseline
Baseline Split
Baseline Milestone
Milestone
Summary Progress
Summary
Manual Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Deadline
fc
Page 20
0%
T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S
1 Jun '14 8 Jun '14 15 Jun '14 22 Jun '14 29 Jun '14 6 Jul '14 13 Jul '14 20 Jul '14
Critical
Critical Split
Critical Progress
Task
Split
Task Progress
Manual Task
Start-only
Finish-only
Duration-only
Baseline
Baseline Split
Baseline Milestone
Milestone
Summary Progress
Summary
Manual Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Deadline
fc
Page 21
T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S
1 Jun '14 8 Jun '14 15 Jun '14 22 Jun '14 29 Jun '14 6 Jul '14 13 Jul '14 20 Jul '14
Critical
Critical Split
Critical Progress
Task
Split
Task Progress
Manual Task
Start-only
Finish-only
Duration-only
Baseline
Baseline Split
Baseline Milestone
Milestone
Summary Progress
Summary
Manual Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Deadline
fc
Page 22
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S
1 Jun '14 8 Jun '14 15 Jun '14 22 Jun '14 29 Jun '14 6 Jul '14 13 Jul '14 20 Jul '14
Critical
Critical Split
Critical Progress
Task
Split
Task Progress
Manual Task
Start-only
Finish-only
Duration-only
Baseline
Baseline Split
Baseline Milestone
Milestone
Summary Progress
Summary
Manual Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Deadline
fc
Page 23
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S
1 Jun '14 8 Jun '14 15 Jun '14 22 Jun '14 29 Jun '14 6 Jul '14 13 Jul '14 20 Jul '14
Critical
Critical Split
Critical Progress
Task
Split
Task Progress
Manual Task
Start-only
Finish-only
Duration-only
Baseline
Baseline Split
Baseline Milestone
Milestone
Summary Progress
Summary
Manual Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Deadline
fc
Page 24