3
Gorgon Project Barrow Island LNG Plant SUPPLIERS FRONT SHEET (FOR A4/A3 DOCUMENTS ONLY) Purchase Order No. 78500051 Package Description DESIGN AND CONSTRUCTION OF LNG JETTY & MARINE STRUCTURES Suppliers Name SAIPEM - LEIGHTON CONSORTIUM Suppliers Reference No. F10178-SAI-140-PIP-DWG / 3-IFC SUPPLIERS DOCUMENT NO. Suppliers Rev Suppliers Rev Date Suppliers Name and Signature Prepared Checked Approved - A 08-OCT-10 E. BARRE JR PERROT D. FRONTINI JC. DUFAU 01 02-DEC-10 E. BARRE JR PERROT D. FRONTINI JC. DUFAU 02 26-JUL-11 E. BARRE JR PERROT D. FRONTINI JC. DUFAU REVIEW SHALL NOT BE ASSUMED TO INDICATE EITHER RESPONSIBILITY OR LIABILITY FOR ACCURACY AND COMPLETENESS OF THIS DOCUMENT OR TO ALTER ANY CONTRACTUAL TERMS AND CONDITIONS GORGON PROJECT – BARROW ISLAND LNG PLANT Document Title: 1. AC - ACCEPTED. WORK MAY PROCEED PIPING ARRANGEMENT DRAWINGS BOOK - JETTY PAR - SAYB 2. ACC – ACCEPTED WITH COMMENTS. PROCEED WITH WORK. INCORPORATE COMMENTS AND RESUBMIT Equipment/Tag No’s. 3. NAC - NOT ACCEPTED. WORK MAY NOT PROCEED. REVISE AND RESUBMIT 4. NR – NOT REVIEWED. FOR INFORMATION ONLY Name ....................................... ........................................... ...... This document supersede /is superseded by: G1-VE- PROJECT DOCUMENT NO. Signature .................................. ............................................. ... Disc Code Unit No. SDRL PO No. Sequence No. Rev Date ....................................... ........................................... ........ G1-VE- X - 7000 - B01 00051 0036 02

G1-VE-X-7000-B01000510036_02-003

Embed Size (px)

DESCRIPTION

kn

Citation preview

Page 1: G1-VE-X-7000-B01000510036_02-003

Gorgon ProjectBarrow Island LNG Plant

SUPPLIERS FRONT SHEET(FOR A4/A3 DOCUMENTS ONLY)

Purchase Order No. 78500051

Package Description DESIGN AND CONSTRUCTION OF LNG JETTY & MARINE STRUCTURES

Suppliers Name SAIPEM - LEIGHTON CONSORTIUM

Suppliers Reference No. F10178-SAI-140-PIP-DWG / 3-IFC

SUPPLIERS DOCUMENT NO. SuppliersRev

SuppliersRev Date

Suppliers Name and Signature

Prepared Checked Approved

- A 08-OCT-10 E. BARRE JR PERROTD. FRONTINIJC. DUFAU

01 02-DEC-10 E. BARRE JR PERROTD. FRONTINIJC. DUFAU

02 26-JUL-11 E. BARRE JR PERROTD. FRONTINIJC. DUFAU

REVIEW SHALL NOT BE ASSUMED TO INDICATE EITHER RESPONSIBILITY OR LIABILITY FOR ACCURACY AND COMPLETENESS OF THIS DOCUMENT OR TO ALTER ANY CONTRACTUAL TERMS AND

CONDITIONS

GORGON PROJECT – BARROW ISLAND LNG PLANTDocument Title:

1. AC - ACCEPTED. WORK MAY PROCEED PIPING ARRANGEMENT DRAWINGS BOOK - JETTY PAR - SAYB

2. ACC – ACCEPTED WITH COMMENTS. PROCEED WITH WORK. INCORPORATE COMMENTS AND RESUBMIT

Equipment/Tag No’s.

3. NAC - NOT ACCEPTED. WORK MAY NOT PROCEED. REVISE AND RESUBMIT

4. NR – NOT REVIEWED. FOR INFORMATION ONLY

Name ........................................................................................

This document supersede /is superseded by: G1-VE-

PROJECT DOCUMENT NO.

Signature ..................................................................................

Disc Code

Unit No. SDRL PO No. Sequence No. Rev

Date ..........................................................................................

G1-VE- X - 7000 - B01 00051 0036 02

Page 2: G1-VE-X-7000-B01000510036_02-003

GORGON PROJECT - BARROW ISLAND LNG PLANTDESIGN AND CONSTRUCTION OF LNG JETTY & MARINE STRUCTURES

PIPING ARRANGEMENT DRAWINGS BOOK - JETTY PAR – SAYBRev. : 02

Page : 2/4Réf. G1-VE X 7000 B01 00051 0036

Disc Unit No. SDR PO No. Sequential

REVISION RECORDING

Date Rev. Status Description of Revision

08-OCT-10 A IDC IDC-INTERNAL DISCIPLINE CHECK

02-DEC-10 01 IFC IFC-ISSUED FOR CONSTRUCTION

26-JUL-11 02 IFCIFC-ISSUED FOR CONSTRUCTION