8
FUTURE OFFSHORE FOUNDATIONS Cost-effectively delivering foundations for use in deeper water with bigger turbines 13-14 November 2012 www.futurewindfoundations.com Swissôtel Bremen, Germany With wind farms moving into new water depths with challenging soil conditions & bigger turbines, big questions are being raised about foundations needs & which solutions are going to be the most applicable whilst bringing down costs. Take 2 days out of the office to gain key insights into: How monopile designs can be adjusted to make them suitable for new projects Where & when jackets, gravity-base foundations or tripods will be most suitable Industrialising the manufacture, logistics & installation of all solutions to bring down the cost of energy How to best inspect & maintain new & existing foundations once installed to ensure they last the full lifetime of the project PLUS! Hear the latest from innovative demo projects Windfloat & Twisted Jackets DON’T MISS! Post-Forum Master Class On 15 November Building robust logistics strategies for foundations from the manufacture plant to the project site to reduce installation timelines & cost Kasper Roed Jensen, Team Lead Offshore Structural & Civil Engineering, Vattenfall Marc Seidel, Leading Expert Offshore Engineering, Repower Systems SE João Goncalo Maciel, Technology Development Director, EDP Inovação & Project Director, Windfloat James Lowe, Engineering Manager, Mainstream Renewable Power Isaac Tavares, Project Manager, Centrica & RES Offshore Julian Garnsey, Head of Offshore Civil Engineering, RWE Innogy Phil de Villiers, Offshore Wind Accelerator Manager, The Carbon Trust Thomas Arensbach, Head of Offshore Projects UK, Siemens Wind Power Kai Irschik, Turbine Engineering, Head of Loads Department, AREVA Wind GmbH Per Sparrevik, Expert Adviser - Discipline Leader Subsea Technology, Norwegian Geotechnical Institute (NGI) Danny Bonnett, Lead Structural Engineer, RES Offshore Bernard van Hemert, Technical Project Manager, Typhoon Offshore Book Before 27 September & Save up to £450! PLUS! Substations Focus Day On 15 November Assess methods for installation, engineering & maintenance of offshore substations for future projects Sponsored By:

Future Offshore Foundations Web

  • Upload
    gm330

  • View
    1.040

  • Download
    3

Embed Size (px)

Citation preview

Page 1: Future Offshore Foundations Web

FUTUREOFFSHOREFOUNDATIONS Cost-effectively delivering foundations foruse in deeper water with bigger turbines

13-14 November 2012

www.futurewindfoundations.com

Swissôtel Bremen, Germany

With wind farms moving into new water depths with challenging soilconditions & bigger turbines, big questions are being raised about foundationsneeds & which solutions are going to be the most applicable whilst bringingdown costs. Take 2 days out of the office to gain key insights into:

• How monopile designs can be adjusted to make them suitable for new projects

• Where & when jackets, gravity-base foundations or tripods will be most suitable

• Industrialising the manufacture, logistics & installation of all solutions to bring down thecost of energy

• How to best inspect & maintain new & existing foundations once installed to ensurethey last the full lifetime of the project

PLUS! Hear the latest from innovative demo projects Windfloat & Twisted Jackets

DON’T MISS! Post-Forum Master Class On 15 November Building robust logistics strategies for foundations from the manufactureplant to the project site to reduce installation timelines & cost

Kasper Roed Jensen, Team Lead Offshore Structural & Civil Engineering,

Vattenfall

Marc Seidel,Leading Expert Offshore Engineering, Repower Systems SE

João Goncalo Maciel, TechnologyDevelopment Director, EDP Inovação & Project Director, Windfloat

James Lowe, Engineering Manager, Mainstream RenewablePower

Isaac Tavares, Project Manager, Centrica & RES Offshore

Julian Garnsey,Head of Offshore Civil Engineering, RWE Innogy

Phil de Villiers,Offshore Wind Accelerator Manager, The Carbon Trust

Thomas Arensbach,Head of Offshore Projects UK, Siemens Wind Power

Kai Irschik, Turbine Engineering, Head of Loads Department, AREVA Wind GmbH

Per Sparrevik,Expert Adviser - Discipline Leader SubseaTechnology, Norwegian GeotechnicalInstitute (NGI)

Danny Bonnett, Lead Structural Engineer, RES Offshore

Bernard van Hemert, Technical Project Manager, Typhoon Offshore

Book Before 27 September &

Save up to £450!

PLUS!

Substations Focus Day On 15 NovemberAssess methods forinstallation, engineering &maintenance of offshoresubstations for future projects

Sponsored By:

Page 2: Future Offshore Foundations Web

08.30 Registration & Morning Coffee

09.10 Chair’s Opening Remarks Marc Seidel, Leading Expert Offshore Engineering,

REpower

09.15 How Can Monopile Designs BeAdjusted For Use In Deeper Water &With Bigger Turbines?

Kasper Roed Jensen, Team Lead Offshore Structural & CivilEngineering, Vattenfall

• How will designs be adapted for use in water of 40m+? - how wide would the pile diameter need to be? - could these monopiles ever cope with increased loads

from deeper water & large 6MW+ turbines & how? • Cost modelling for using monopiles on sites currently

pencilled in as jackets - could mixing foundation types on sites where

monopiles are not right for the whole project bringcosts down & how would that work practically?

• Which solutions for grouted connections are the mosteffective & economically sound & why?

- what new solutions will be needed as loads increase?

09.45 Met Mast Dynamic Response Focus:Integrated Analysis & ComponentAnalysis For Current & Future Projects

Danny Bonnett, Lead Structural Engineer, RES Offshore

• Serviceability criteria - assessing the compromise between good quality data

& an economic structure • How do you determine foundation stiffness requirements? - platform deflection, tip deflection & rotational stiffness • Analysis of lattice towers for fatigue - appropriate S-N curves • Water depth limitations for monopile structures - is it really about effective depth? • Assessment of fatigue damage of in-service structures • What are the alternatives to a permanent structure?

10.15 Morning Refreshments & Networking Break

10.45 Exploring Industry Research Projects ForDesign Of Piled Steel Sub-Structures

Julian Garnsey, Head of Offshore Civil Engineering,RWE Innogy

Isaac Tavares, Project Manager, Centrica

Alastair Muir Wood, Geotechnical Engineer, DONG Energy

Hear about the latest research initiatives aimed at providingnew data & design guidance to allow improved designmethodology & life extension for offshore wind turbinefoundations. In combination these projects will bringsignificant economic savings & benefits to both existing &future wind turbine foundations.

Gain insight into two ambitious industry initiatives: • SLIC - a project to provide improved fatigue design

methods for offshore wind turbine substructures • PISA - a project to strengthen understanding of soil-

structure interaction to allow improved pile design methods

11.25 Are Suction Cans A SuitableFoundation For Germany?

Ernest Diepstraten, General Manager, Cathie Associates SA/NV

• Experience gained using suctions cans thus far outside ofGerman waters

- recent experience in Germany • Implications on design of suction cans following DIN • Assessing the sequence for a successful integrated

design • Do’s and don’ts - recommendations for future projects

11.55 Critically Evaluating The Use OfJackets To Ensure They Are The RightChoice For Your Projects

• When does it make sense to move to jackets? • Why are different jacket designs being chosen? - what are the reasons against using 4-legged

structures? • How will jackets cope with the loading effects associated

with wind that aren’t present in oil & gas? • Grouted connections - what did we learn from monopile & TP failures? - how can we avoid similar issues for grouted

connections on jacket foundations? • Assessing the cost structure of jacket foundations

To join this session please contact Heather on [email protected] or +44 (0)20 8267 4785

12.35 Networking Lunch

13.35 Innovative ‘Twisted Jacket’ DemoProject Update

James Lowe, Engineering Manager, Mainstream Renewable Power

Gain an update from the Twisted Jacket demo projectcurrently being run by Mainstream Renewable Power to findout:

• Has the prototype performed to its design criteria in termsof how the structure would cope with the loads?

• Did the installation take place as expected? • What challenges have been faced so far • Will any design changes be made as a result of the

demonstration & why? • What are the cost projections for large 6MW+ turbines?

Cost-effectively delivering foundationsfor use in deeper water with bigger turbinesDay 1 Tuesday, 13 November

Book Now! Visit www.futurewindfoundations.com

Page 3: Future Offshore Foundations Web

14.20 Exploring The Case Of The Tripod AsA Proven Foundation Concept &Assessing Its Operational Benefits

Kai Irschik, Turbine Engineering, Head of Loads Department, AREVA Wind GmbH

• The standard tripod as a proven technology - what are the benefits of a tripod design compared to

other solutions? • Operational experience from Alpha Ventus - what makes the tripod a robust & easy design? - lessons learned - accessibility - inspection - maintenance - scour • What alternative tripod versions have been investigated &

where do they fit better than the original design?

15.00 Assessing The Validity Of ConcreteGravity-Base Foundations At Large-Scale Project Level

Petter J. Karal, Chief Executive Officer, Seatower

• Understanding the full costs of gravity-base foundations - in what circumstances can they be as or more

competitive to other types of foundations? • What are the restrictions to using gravity-base? • What are the expectations around manufacturing volumes

& timelines? • Effective seabed preparation - understanding the necessary considerations at the site

to ensure it is flat enough • What are the long-term issues over the lifetime? • What are the differences between the different types of

gravity-base foundations? • Timescales & methods for installation - what is the financial impact of not needing heavy lift

equipment at the installation site? • What are the weather requirements regarding weather

windows & wave conditions for installation of gravityfoundations?

- how does this affect the projects in terms of cost & risk?

15.40 Refreshments & Networking Break

16.10 Innovative Floating Foundations: The Windfloat Case Study

João Goncalo Maciel, Technology Development Director,EDP Inovação & Project Director Windfloat

• Main design considerations of the Windfloat - how is Windfloat behaving compared to on paper? • How does the structure behave once in the water? - how is the turbine performing? • Understanding the interaction between the turbine & the

foundation structure • Operations & maintenance needs • Cost analysis

16.55 Close Of Day 1 & Networking Drinks Reception

08.30 Delegate Sign-In & Morning Coffee

09.10 Chair’s Opening Remarks Thomas Arensbach, Head of Offshore Projects UK,

Siemens Wind Power

09.15 Update To Determine The CurrentStatus Of The Winning FoundationsDesigns From The Offshore WindAccelerator (OWA)

Phil de Villiers, Offshore Wind Accelerator Manager, The Carbon Trust

The results of the OWA competition were announced inSeptember 2011, but where are we now? Gain an updatefrom The Carbon Trust around:

• How close are the different winners to commercialisationof their designs?

• Which have received certification? • How far has each concept progressed through lab &

field tests? • Where specifically do the designers see them being

applicable? • How cost-effective is each design compared with others? • Are there planned demo site installations & when will they be? • What are the projected manufacturing & installation costs?

09.50 Foundation Choice Case Study:Exploring The Decision-MakingProcess For The Gemini Project

Bernard van Hemert, Technical Project Manager, Typhoon Offshore

• Summary of site conditions for the project • Our search for the most optimal foundation type for our

4MW turbines from three-legged jacket to four-leggedjacket to monopile

• Exploring how installation limitations affected our choice touse monopiles

- costs, installation vessels, etc. • How did we design the monopiles without having all the

detailed geotechnical information? - cyclic approach - preliminary results • Overcoming the challenge of grouted connection vs.

flanged connection - CAPEX & OPEX - risks in certification - risks during installation - risks during lifetime operation

10.30 Refreshments & Networking Break

Day 2 Wednesday, 14 November

Book Now! Call +44 (0)20 8267 4011

Page 4: Future Offshore Foundations Web

11.05 Assessing Fabrication Processes ToEnsure Delivery Of The Numbers OfFoundations Needed For Near-FutureProjects

• How much will fabrication of the different concepts cost? • What needs to be adapted in the fabrication process for

each concept for serial production - which concept is easiest to fabricate on such a scale? - is there scope for automation of production to bring

down costs? - timescales • Is the suggestion of 100 jackets per year realistic? • Quality control in manufacturing - what guidelines or standards should be in place to

increase reliability?

11.45 Building Robust Logistics Plans To EnsureLarge Volumes Of Foundations Can BeMoved Smoothly From Fabrication SitesTo The Installation Sites

Martin Huss, Managing Director, A2SEA • What are the transport needs for moving the different types

of foundations from the manufacturing plant to theinstallation site?

- getting foundations to the port - moving from the shore to the project site • With huge volumes of foundations, how will ports cope? - what facilities will be needed at the quayside? - storage options - when would you need to have a feed-in port?

12.25 Networking Lunch

13.25 Turbine & Foundation InstallationStrategy: Full Structure Installation Vs.Split Structure Installation

Mark Reinders, Technical Project Manager, Siemens Wind Power

• Fictive project case study describing overall projectinstallation & commissioning methodologies & timeline

• Comparison of the cash flow for full structure installation vs.split structure installation

- when is revenue generated? - what are the effects of timing of investments? • Suggestions for future development from a turbine

manufacturers point of view - what types of vessels do Siemens Wind Power see the

need for? - what should future foundation installation strategies look

like?

14.05 Vessels Focus: Assessing WhichVessels Will Be Available, What TheirCapabilities & Costs Are

Paal Strømstad, Project Manager, Ingenium Ventus • What will the vessel needs be for new foundations? - finding vessels & cranes that can carry the weight of

foundations for larger turbines

- what are the limitations of the cranes? - how will vessel designs need to be bespoke to each

different kind of jacket, monopile or gravity-basefoundation?

• Dealing with bottlenecks in available jack-up vessels - how will project CAPEX be affected? • Installing foundations from floating vessels - which concepts will floating vessels work for? - which floating vessels can cope with installing

foundations in harsher conditions such as those on theNorth Sea?

14.45 Is Underwater Noise A 'ShowStopper'? Noise Mitigation, Trends ForPile Installation & What It Means ForThe Industry

Nils Raab, Sales Manager – Wind, MENCK • Assessing why noise is such an issue - the impact of regulation & the environment on offshore

wind installation • The Resonance Chamber - understanding how noise emission varies in different

foundation types - improving noise calculation & simulation for better

designs & installation methods • Exploring the latest underwater noise reduction methods

15.25 Refreshments & Networking Break

15.55 Protecting Against Corrosion AcrossThe Different Foundation Concepts

Isaac Tavares, Project Manager, RES Offshore • External corrosion protection - what must designers consider to ensure protection is

not damaged by vessels being used later in the project? • Dealing with internal corrosion of monopiles - what methods are available to repair corrosion on

existing monopiles that wasn’t anticipated? - using corrosion & inhibitors to avoid internal corrosion

on future monopiles

16.05 Understanding The Long-TermBehaviour Of Foundations Used For25m+ Water Depth To Effectively PlanInspection & Maintenance

Per Sparrevik, Expert Adviser - Discipline Leader SubseaTechnology, Norwegian Geotechnical Institute (NGI)

• Once each of the concepts is in the water whatparticularly needs to be monitored?

- fatigue - how soil is performing against what was predicted - corrosion • Inspection techniques - what tools are available & work best - what are the extra costs involved? • What are the latest ideas regarding repair of foundations? • Establishing how higher loads from bigger turbines will

affect the life-time performance of different foundations

16.45 Chair’s Closing Remarks & Close Of Forum

Cost-effectively delivering foundationsfor use in deeper water with bigger turbinesDay 2 Wednesday, 14 November

Book Now! Visit www.futurewindfoundations.com

Page 5: Future Offshore Foundations Web

Led by: Keith Miller, Chairman, FoundOcean

09.00-12.30 (Registration begins at 08.30)

As future rounds of offshore projects increase the numbers offoundations & other components needed for projects, efficientorganisation of the logistics from the assembly hubs to the sitebecomes essential to avoid delays & save money. Join WindpowerMonthly for this in-depth morning master class to gain practical &strategic tools on how to put together your logistics programmes.

During this highly interactive peer-to-peer experienceexchange the following will be addressed:

Fabrication logistics• Finding the right locations for assembly hubs - facilities needed• space• proximity to shore• Avoiding the need to transfer foundations between various vehiclesto get them to the load out site

Storage• as projects get bigger how can you ensure you have enoughspace for foundation storage?

- how should you most affectively lay foundations in the load-outarea to aid transfer to installation vessels?

• are there currently ports that can store hundreds of structures?• will there be enough room for future vessels to moor?

Transport to site• How much can of the foundation assembly can be done onshore? - how will this affect moving foundations from the storage areas to

the vessel deck?• impacts on installation timeframes• Vessel requirements & availability - how much deck space do you need?• efficient packing - load capacities - how will vessel be developed to guarantee the kind of flexibility

needed to increase the efficiency of installation?

Building Robust Logistics For Installing Foundations ForFuture Offshore Wind Projects

Separately Bookable Master Class

Thursday, 15 November 2012

Book Now! Call +44 (0)20 8267 4011

AWARD-WINNING WINDPOWER MONTHLY EVENTS!

We are proud to have been listed as “Highly Commended” for the Best Energy Conference 2012 award, and shortlisted for the Best New ConferenceLaunch award. This year’s Conference Awards is the first time Windpower Monthly Events have entered and we are delighted to have received suchrecognition from the industry for the quality of our events.

Here are some upcoming events you may be interested in:

Offshore Operations & Maintenance9-10 October 2012, London, UKwww.offshoremaintenanceforum.com

Wind LATAM - Brazil26-28 November 2012, Sao Paolo, Brazilwww.windlatam.com

WindLift Onshore & Offshore27-28 November 2012, London, UKwww.windliftevent.com

Wind Connect 23 January 2013, London, UKwww.windconnectevent.com

Wind Resource Assessment 201327-28 March 2013, London, UKwww.windresourceassessmentforum.com

Vessels & Access 2013May 2013, London, UKwww.offshorevesselsforum.com

Page 6: Future Offshore Foundations Web

Due to popular demand Windpower Monthly will be hosting anOffshore Substations Focus Day on 15 November.

The day will explore key issues regarding substation design,installation and maintenance affecting projects in deeper water andwith large numbers of turbines.

10.00-16.00 (Registration begins at 09.30)

By attending just one day you will find out about:• Design considerations for substations in deeper water and forlarger projects

– exploring the latest standards• Economically installing topsides with much higher weights thanpreviously known

– what vessels and lifting tools are available? – how long will they take to install? – what will be the cost of installation? – self installing vs. traditional installation techniques – foundation needs

• How big substations are going to need to be to cater for newHVDC equipment

• Should new substations be taken out on vessels or floated out tothe site?

• Best-practice corrosion protection• What considerations need to be made for fire protection andsuppression?

Who should attend?This event is a must-attend for civil & structural engineers working onsubstation design, installation and maintenance.

The agenda for this focus day is still in development so keep an eyeon www.offshorewindsubstations.com for updates.

Companies we are inviting to speak include DONG Energy,Centrica, RWE, DNV & RES Offshore.

Offshore Substation Design,Installation & Maintenance

Separately Bookable Focus Day

Feedback From past attendees

“Very good event, well organised and attended.”Technical Director, Submarine Technology Ltd “

This event allowed/forced like-minded individualsacross race, gender and generation to openly sharein a small group setting through short sound bitetopics. Great job! People were here until the veryend, what a compliment! Your entire team wasengaging, kind, supportive and competent.”Senior Vice President EHS, PCG Wind“

Great opportunity fornetworking, and keeping upwith innovations.”International Project Management,Availon Inc

“This conference was very informativeand a great place to network.”National Co-ordinator, Elevator Industry Work Fund

Cost-effectively delivering foundationsfor use in deeper water with bigger turbines

Sponsored By:

Thursday, 15 November 2012

Book Now! Visit www.futurewindfoundations.com

Media Partners:

Page 7: Future Offshore Foundations Web

6

7

8

9

10

23

4

1

5

Reserved*

*Correct at time of printing

Available*contact [email protected]

INDUSTRY BREAKDOWN

WHo WIll You meet?

WHo sHould attend?

SENIOR LEVEL ATTENDEES 22%22%10%14%11%7%5%1%

Engineer

Manager

Director

C-Level

Consultant

Finance/Investment

Project Manager

Academic/Other

23%16%13%11%

10%9%5%3%

OEM

Engineer

Consultant

Finance/Investment

Developer

Other

Govt

Utilitiy

Directors, Heads, Managers of:

� Foundations/Structures

�Civil Engineering

� Structural Engineering

� Installation

�O&M

� Technical/Technology

� Project

� Site

� Procurement

� Business Development

Book Now! Call +44 (0)20 8267 4011

Get Involved

Page 8: Future Offshore Foundations Web

FEATURING SPEAKERS FROM:

3 WAYS TO BOOK1. Online: www.futurewindfoundations.com

2. Email: [email protected]

3. Call: +44 (0)20 8267 4011

Book Before 27 September & Save Up To £450!

Brochure code: WEB

Book before 27 Sept

Book before26 Oct

Book after 26 Oct

Two-Day Forum Only£1300 £1400 £1500

Saving Saving Saving£200 £100 –

Two-Day Forum + Logistics Master Class

£1549 £1649 £1749

Saving Saving Saving£450 £350 £250

Two-Day Forum + Substations Focus Day

£1749 £1849 £1949

Saving Saving Saving£200 £100 –

Substations Focus Day Only£549 £599 £649

Saving Saving Saving£100 £50 –

Additional options Details*

Logistics Master Class Only £449

Speaker Notes £199 (No VAT)

Further Information For DelegatesEmail [email protected]

*All rates will have VAT @ 19% added ** vs booking items seperately at standard prices

Conference Code: 17181111587

www.futurewindfoundations.com

Foundations for Future Offshore Windis produced by Haymarket Conferences

FUTUREOFFSHOREFOUNDATIONS Cost-effectively delivering foundations foruse in deeper water with bigger turbinesA Two-Day Forum Plus Half-Day Master Class/Focus Day: 13-15 November 2012, Bremen, Germany

Sponsorship, Exhibition & Business Development OpportunitiesDon’t miss out on this great opportunity to increase your exposure amongstdecision-makers looking into foundations solutions & enjoy face-to-face timewith potential customers; contact Heather Smith on +44 (0) 20 8267 4785 oremail [email protected] today.

Let Us Manage Your Event For YouHaymarket Events organises a variety of event formats on behalf of third-parties, includingassociations, not-for-profit organisations, the public sector and corporate clients. We work to theclient’s objectives to produce dynamic events that deliver exceptional results. For more information,please contact Barney Roe on +44 (0)20 8267 4063 or email [email protected] Terms & Conditions available online at time of booking