NO PROJECT TITLE DESCRIPTIONS VALUE (RM) OWNER / CLIENT YEAR
1 EPCC OF NGDS TO NIBONG TEBAL FL1 DL1, NIBONG TEBAL, PENANG
ENGINEERING, PROCUREMENT, CONSTRUCTION
AND COMMISSIONING OF NPS 12 STEEL PIPE LINE
CONSTRUCTION OF ODORIZER BUILDING AND
ODORIZER SYSTEM - 32 KM
4,800,000.00
MASMIRIN CORPORATION
SDN BHD / GAS MALAYSIA
SDN BHD
2004/2005
2 EPCC OF NGDS TO PRAI FL DL STAGE 1/03, PRAI IND. AREA, PENANG
ENGINEERING, PROCUREMENT, CONSTRUCTION
AND COMMISSIONING OF NPS 12 STEEL PIPES -
8KM
3,200,000.00
MASMIRIN CORPORATION
SDN BHD / GAS MALAYSIA
SDN BHD
2005
3 EPCC OF NGDS TO PRAI FL DL (LOOPING) STAGE 1/03, PRAI IND. AREA, PENANG
ENGINEERING, PROCUREMENT, CONSTRUCTION
AND COMMISSIONING OF NPS 8 STEEL PIPES -
4.5KM
2,800,000.00
MASMIRIN CORPORATION
SDN BHD / GAS MALAYSIA
SDN BHD
2005
4EPCC OF THE NGDS TO TAMAN MAKMUR FL STAGE 1/08, KULIM, KEDAH DARUL
AMAN
ENGINEERING, PROCUREMENT, CONSTRUCTION
AND COMMISSIONING OF NPS 8 STEEL PIPES - 4KM1,200,000.00 GAS MALAYSIA BERHAD 2009
5EPCC OF THE NGDS TO SUNGAI PETANI FL STAGE 1/09, SUNGAI PETANI, KEDAH
DARUL AMAN
ENGINEERING, PROCUREMENT, CONSTRUCTION
AND COMMISSIONING OF NPS 8 STEEL PIPES -
0.4KM
145,000.00 GAS MALAYSIA BERHAD 2009
6EPCC OF THE NGDS TO KUNDANG FL STAGE 1/10, KUNDANG INDUSTRIAL AREA,
RAWANG, SELANGOR DARUL EHSAN
ENGINEERING, PROCUREMENT, CONSTRUCTION
AND COMMISSIONING OF NPS 6 STEEL PIPES -
0.7KM
418,455.00 GAS MALAYSIA BERHAD 2009
7 EPCC OF GPRW AT PUTRA INTERCHANGE, PUTRAJAYA
ENGINEERING, PROCUREMENT, CONSTRUCTION
AND COMMISSIONING OF NPS 16 STEEL PIPES -
720M
1,111,000.00 GAS MALAYSIA BERHAD 2009
8
EPCC OF GPRW AT CADANGAN MEMBINA JLN PINTAS DARI SENGKANG (J104) KE
FELDA INAS BANDAR TENGGARA, JALAN JOHOR BAHRU-AIR HITAM, KULAI, JOHOR
DARUL TAKZIM
ENGINEERING, PROCUREMENT, CONSTRUCTION
AND COMMISSIONING OF NPS 8, NPS 4 STEEL PIPES
- 230M
600,000.00 GAS MALAYSIA BERHAD Aug 2009 to Jan 2010
9 EPCC OF THE NGDS TO TEBRAU FL STAGE 1/10, TEBRAU, JOHOR DARUL TAKZIM
ENGINEERING, PROCUREMENT, CONSTRUCTION
AND COMMISSIONING OF NPS 6, NPS 4 STEEL PIPES
- 226M
695,000.00 GAS MALAYSIA BERHADDec 2009 to June
2010
NO PROJECT TITLE DESCRIPTIONS VALUE (RM) OWNER / CLIENT YEAR
10EPCC OF THE NGDS TO PANDAMAR FL STAGE 1/10, PANDAMAR, KLANG, SELANGOR
DARUL EHSAN
ENGINEERING, PROCUREMENT, CONSTRUCTION
AND COMMISSIONING OF NPS 6, NPS 4 STEEL PIPES
- 1416M
595,000.00 GAS MALAYSIA BERHAD Dec 2009 to Oct 2010
11EPCC OF THE NGDS TO GAMBANG FL STAGE 1/10, GAMBANG, PAHANG DARUL
MAKMUR
ENGINEERING, PROCUREMENT, CONSTRUCTION
AND COMMISSIONING OF NPS 8, NPS 6, NPS 4
STEEL PIPES - 2292M
865,500.00 GAS MALAYSIA BERHAD 2010
12THE EPCC OF NGDS TO STX PRECISION SDN BHD IN NIBONG TEBAL, PULAU PINANG
INCLUSIVE OF THE STATION CIVIL WORK
ENGINEERING, PROCUREMENT, CONSTRUCTION
AND COMMISSIONING OF 63MM PE SERVICE LINE. -
600M
88,000.00 GAS MALAYSIA BERHADMarch 2010 to June
2010
13 EPCC OF THE NGDS TO PRAI DL STAGE 1/10, PRAI, PULAU PINANG
ENGINEERING, PROCUREMENT, CONSTRUCTION
AND COMMISSIONING OF 125MM AND 63MM PE
PIPES. - 500M
202,610.00 GAS MALAYSIA BERHADApril 2010 to August
2010
14EPCC AND COMMISSIONING OF THE NGDS TO CHENG FL STAGE 1/10, CHENG
INDUSTRIAL AREA, MELAKA
ENGINEERING, PROCUREMENT, CONSTRUCTION
AND COMMISSIONING OF NPS 4 STEEL PIPES -
200M
83,000.00 GAS MALAYSIA BERHADApril 2010 to July
2010
15EPCC OF THE NGDS TO KAMUNTING FL STAGE 3/10, KAMUNTING, PERAK DARUL
RIDZUAN
ENGINEERING, PROCUREMENT, CONSTRUCTION
AND COMMISSIONING OF NPS 6 & NPS 4 STEEL
PIPES - 300M
169,873.00 GAS MALAYSIA BERHADJune 2010 to October
2010
16EPCC OF NGDS TO LATEXX, PLANT 1 IN KAMUNTING, PERAK DARUL RIDZUAN
INCLUSIVE OF STATION CIVIL WORKS
ENGINEERING, PROCUREMENT, CONSTRUCTION
AND COMMISSIONING OF NPS 4 STEEL SERVICE
LINE - 600M
94,923.00 GAS MALAYSIA BERHADApril 2010 to July
2010
17EPCC OF THE NGDS TO SHAH ALAM DL STAGE 1/10, SHAH ALAM, SELANGOR DARUL
EHSAN
ENGINEERING, PROCUREMENT, CONSTRUCTION
AND COMMISSIONING OF PE 125MM - 25M281,500.00 GAS MALAYSIA BERHAD 2010
18EPCC OF THE NGDS TO GEBENG FL STAGE 1/10, GEBENG INDUSTRIAL AREA, PAHANG
DARUL MAKMUR
ENGINEERING, PROCUREMENT, CONSTRUCTION
AND COMMISSIONING OF NPS 6 AND NPS 4 STEEL
SERVICE LINE - 2904M
1,085,000.00 GAS MALAYSIA BERHADJune 2010 to March
2011
NO PROJECT TITLE DESCRIPTIONS VALUE (RM) OWNER / CLIENT YEAR
19EPCC OF THE NGDS TO SHAH ALAM FL DL STAGE 1/10, SHAH ALAM, SELANGOR DARUL
EHSAN
ENGINEERING, PROCUREMENT, CONSTRUCTION
AND COMMISSIONING OF NPS 6 AND NPS 4 STEEL
SERVICE LINE - 540M
445,000.00 GAS MALAYSIA BERHADJune 2010 to Oct
2011
20EPCC OF THE NGDS TO NORTH PORT DL STAGE 1/10, NORTH PORT, SELANGOR DARUL
EHSAN
ENGINEERING, PROCUREMENT, CONSTRUCTION
AND COMMISSIONING OF PE 125MM, PE 90MM
AND PE 63MM - 300M
195,000.00 GAS MALAYSIA BERHAD 2010
21 EPCC OF THE NGDS TO PUTRAJAYA FL STAGE 1/10, PRECINCT 18, PUTRAJAYA
ENGINEERING, PROCUREMENT, CONSTRUCTION
AND COMMISSIONING OF NPS 4 STEEL SERVICE
LINE - 60M
59,500.00 GAS MALAYSIA BERHAD 2010
22EPCC OF THE NGDS TO SERI KEMBANGAN FL STAGE 2/10, SERI KEMBANGAN,
SELANGOR DARUL EHSAN
ENGINEERING, PROCUREMENT, CONSTRUCTION
AND COMMISSIONING OF NPS 6 AND NPS 4 STEEL
PIPES - 3800M
1,038,364.25 GAS MALAYSIA BERHADAugust 2010 to
February 2011
23 EPCC OF THE NGDS TO NIBONG TEBAL FL STAGE 1/10, NIBONG TEBAL, PULAU PINANG
ENGINEERING, PROCUREMENT, CONSTRUCTION
AND COMMISSIONING OF NPS 6 AND NPS 4 STEEL
PIPES - 800M
130,280.00 GAS MALAYSIA BERHADSeptember 2010 to
January 2011
24EPCC OF THE GPRW AT KERJA-KERJA MENGGANTIKAN JAMBATAN DI LALUAN A125,
JALAN AYER TAWAR-SIMPANG LIMA, DAERAH MANJUNG, PERAK DARUL RIDZUAN
ENGINEERING, PROCUREMENT, CONSTRUCTION
AND COMMISSIONING OF NPS 12 STEEL PIPES
WITH 2 NOS HOT TAPPING STOPPLE OF 12" X 12" -
200M
454,410.00 GAS MALAYSIA BERHAD 2010
25EPCC OF THE NGDS TO KUALA KETIL FL STAGE 1/10, KUALA KETIL, KEDAH DARUL
AMAN
ENGINEERING, PROCUREMENT, CONSTRUCTION
AND COMMISSIONING OF NPS 6 AND NPS 4 STEEL
PIPES - 1100M
495,000.00 GAS MALAYSIA BERHAD Dec 2010
26GENTING PURA KENCANA, BATU PAHAT PROPOSED STREET LIGHTING INSTALLATION
FOR PHASE 1A AND PHASE 1BCIVIL AND FIBER PULLING 381,820.00
KOMASI
COMMUNICATIONS SDN
BHD / GPROPERTY
CONSTRUCTION SDN. BHD.
2010
27GENTING INDAHPURA, KULAI PROPOSED STREET LIGHTING INSTALLATION FOR 82
UNIT SEMI-DETACHED HOUSE, PACKAGE 3A AT ZONE 33CIVIL AND FIBER PULLING 106,070.00
KOMASI
COMMUNICATIONS SDN
BHD / GPROPERTY
CONSTRUCTION SDN. BHD.
2010
NO PROJECT TITLE DESCRIPTIONS VALUE (RM) OWNER / CLIENT YEAR
28 INFRA-DIGI AT PARIT RAJA INDUSTRIAL PARK, BATU PAHAT CIVIL AND FIBER PULLING 2,116,161.80
KOMASI
COMMUNICATIONS SDN
BHD / TIME DOTCOM
BERHAD
2010
29 PROPOSED OSP CIVIL TO DIGI CABIN AT BANDAR PUTRA, SEGAMAT JOHOR CIVIL AND FIBER PULLING 1,67,059.45
KOMASI
COMMUNICATIONS SDN
BHD / TIME DOTCOM
BERHAD
2010
30 FIBER PULLING TO DIGI AT SEGAMAT, JOHOR CIVIL AND FIBER PULLING 151,786.02
KOMASI
COMMUNICATIONS SDN
BHD / TIME DOTCOM
BERHAD
2010
31 INFRA & FIBER PULL -(DIGI MSC PRO KEPONG IND PARK) CIVIL AND FIBER PULLING 491,298.19
KOMASI
COMMUNICATIONS SDN
BHD / TIME DOTCOM
BERHAD
2010
32 INFRA & FIBER - DIGI CABIN AT MIMALAND TO MH AT UIA GOMBAK (1 ROUTE) CIVIL AND FIBER PULLING 581,327.20
KOMASI
COMMUNICATIONS SDN
BHD / TIME DOTCOM
BERHAD
2010
33 INFRA-PROPOSED OSP CIVIL TO DIGI CABIN AT GEMERAH, SEGAMAT, JOHOR CIVIL AND FIBER PULLING 131,729.24
KOMASI
COMMUNICATIONS SDN
BHD / TIME DOTCOM
BERHAD
2010
34 FIBER PULLING (IB 48C)- DIGI PROJECT AT MIMALAND (ROUTE 2) CIVIL AND FIBER PULLING 1,072,413.02
KOMASI
COMMUNICATIONS SDN
BHD / TIME DOTCOM
BERHAD
2010
35
ELECTRIFIED DOUBLE TRACK PROJECT -SEREMBAN TO GEMAS PACKAGE
1–CONSTRUCTION AND COMPLETION OF FIBER OPTIC CABLES RELOCATION WORK
(ENGINEERING SERVICES) SECTION 7 (CH482.410-CH486.070 & CH488.450-CH490.300
)
CIVIL AND FIBER PULLING 209,960.00
KOMASI
COMMUNICATIONS SDN
BHD / FIBERAIL SDN BHD
2010
36
ELECTRIFIED DOUBLE TRACK PROJECT -SEREMBAN TO GEMAS PACKAGE
2–CONSTRUCTION AND COMPLETION OF FIBER OPTIC CABLES RELOCATION WORK
(ENGINEERING SERVICES) SECTION 2A (CH500.775-CH504.141 & CH505.150-
CH506.990)
CIVIL AND FIBER PULLING 210,478.10
KOMASI
COMMUNICATIONS SDN
BHD / FIBERAIL SDN BHD
2010
NO PROJECT TITLE DESCRIPTIONS VALUE (RM) OWNER / CLIENT YEAR
37
ELECTRIFIED DOUBLE TRACK PROJECT -SEREMBAN TO GEMAS PACKAGE 2
–HORIZONTAL DIRECT DRILLING (HDD) INSTALLATION WORKS SECTION 2A
(CH500.775-CH504.141 & CH505.150-CH506.990)
CIVIL AND FIBER PULLING 513,916.00
KOMASI
COMMUNICATIONS SDN
BHD / FIBERAIL SDN BHD
2010
38PERLAKSANAAN PROJEK RANGKAIAN TEMPATAN TELEKOM MALAYSIA BERHAD
SECARA JADUAL KADAR HARGACIVIL AND FIBER PULLING 10,000,000.00
KOMASI
COMMUNICATIONS SDN
BHD / TM BERHAD
2010
39
SUPPLY & INSTALL OF 7 WAY 100MM DIA HDPE DUCTING BY HDD METHOD AND
TELEPHONE MANHOLE AND DUCTING FOR CADANGAN PEMBANGUNAN KAMPUS
BARU UNIVERSITI KUALA LUMPUR (UNIKL) CAWANGAN JOHOR DI PASIR GUDANG,
JOHOR
CIVIL AND FIBER PULLING 245,310.00
KOMASI
COMMUNICATIONS SDN
BHD / TRC SDN. BHD.
2010
40PERLAKSANAAN PROJEK RANGKAIAN TEMPATAN TELEKOM MALAYSIA BERHAD
SECARA JADUAL KADAR HARGACIVIL AND FIBER PULLING 5,000,000.00
KOMASI
COMMUNICATIONS SDN
BHD / TM BERHAD
2010
41RELOCATION OF FIBER OPTIC CABLE AT SEREMBAN – TABOH NANING BETWEEN
KP119.000 – KP 121.000CIVIL AND FIBER PULLING 205,089.72
KOMASI
COMMUNICATIONS SDN
BHD / FIBERAIL SDN BHD
2010
42ELECTRIFIED DOUBLE TRACK PROJECT - SEREMBAN TO GEMAS PACKAGE 1
–HORIZONTAL DIRECT DRILLING (HDD) INSTALLATION WORKS–ADDITIONAL NO 7ELECTRIFIED DOUBLE TRACK 244,140.40
KOMASI
COMMUNICATIONS SDN
BHD / FIBERAIL SDN BHD
2010
43PROPOSED STREET LISTING INSTALLATION FOR 82 UNITS SEMI-DETACHED HOUSES,
PACKAGE 3A AT ZONE 33.STREET LISTING INSTALLATION 106,070.00
KOMASI
COMMUNICATIONS SDN
BHD / GPROPERTY
CONSTRUCTION SDN. BHD.
2010
44PROPOSED ELECTRICAL LV INFRASTRUCTURE WORKS AT ZONE 33A PACKAGE 3A FOR
SEMI-DETACHED HOUSESELECTRICAL LV INFRASTRUCTURE WORKS 219,912.00
KOMASI
COMMUNICATIONS SDN
BHD / GPROPERTY
CONSTRUCTION SDN. BHD.
2010
45 PROPOSED STREET LIGHTING INSTALLATION FOR PHASE 1A AND PHASE 1B STREET LIGHTING INSTALLATION 38,180.00
KOMASI
COMMUNICATIONS SDN
BHD / ALD CONSTRUCTION
2010
NO PROJECT TITLE DESCRIPTIONS VALUE (RM) OWNER / CLIENT YEAR
46
DIVING SERVICES TO CONDUCT UNDERWATER INSPECTION OF ANODES AND PIPELINE
AT WEST MOORING DOLPHIN, JIMAH POWER PLANT, PORT DICKSON, NEGERI
SEMBILAN DARUL KHUSUS
MARINE & SALVAGE WORKS 177,000.00
MACH 3 ENGINEERING
CONSULTANTS SDN
BHD/EXCALIBER
RESOURCES SDN BHD
March 2011
47TO REPAIR ANODES FEEDER CABLE AT JIMAH POWER PLANT PORT DICKSON, NEGERI
SEMBILAN DARUL KHUSUSMARINE & SALVAGE WORKS 160,000.00
MACH 3 ENGINEERING
CONSULTANTS SDN
BHD/EXCALIBER
RESOURCES SDN BHD
March 2011
48 TO PROVIDE MANPOWER (DIVERS) AT TURKMENISTAN CABLE LAYING PROJECT MARINE & SALVAGE WORKS 550,000.00
IFACTORS SDN
BHD/EXCALIBER
RESOURCES SDN BHD
April 2011 to May
2011
49
TO CONDUCT UNDERWATER SURVEY, HACKING, REPAIR RE-BAR, INSTALL FOAM
WORK AND GROUTING AT INNER JETTY SHELL BAGAN LUAR, BUTTERWORTH,
PENANG
MARINE & SALVAGE WORKS 160,000.00
RNC TECHNOLOGY (M) SDN
BHD/EXCALIBER
RESOURCES SDN BHD
May 2011
50TO REPAIR ANODES FEEDER CABLE AT JIMAH POWER PLANT PORT DICKSON, NEGERI
SEMBILAN DARUL KHUSUSMARINE & SALVAGE WORKS 230,000.00
MACH 3 ENGINEERING
CONSULTANTS SDN
BHD/EXCALIBER
RESOURCES SDN BHD
August 2011
51 EPCC OF THE NGDS TO SITIAWAN, FL STAGE 1/11, SITIAWAN, PERAK DARUL RIDZUAN
ENGINEERING, PROCUREMENT, CONSTRUCTION
AND COMMISSIONING OF NPS 8, NPS 6 AND NPS 4
STEEL PIPES
249,400.00 GAS MALAYSIA BERHAD 2011
52EPCC OF THE NGDS TO MERU FL STAGE 1/11, MERU, KLANG, SELANGOR DARUL
EHSAN
ENGINEERING, PROCUREMENT, CONSTRUCTION
AND COMMISSIONING OF NPS 6 AND NPS 4 STEEL
PIPES
530,000.00 GAS MALAYSIA BERHAD 2011
53
SUPPLY MATERIALS, MANPOWERS WITH NECESSARY HANDLING TOOLS &
EQUIPMENT FOR INSTALLATION, TESTING AND COMMISSIONING OF NATURAL GAS
PIPELINE WORK FOR BAHRU STAINLESS PROJECT, TANJUNG LANGSAT, JOHOR
PIPELINE TESTING AND COMMISSIONING 1,070,000.00TRACTOR-LINE INDUSTRIES
SDN BHD2011
54 EPCC OF THE NGDS TO SENAWANG FL STAGE 1/10, SENAWANG, NEGERI SEMBILANENGINEERING, PROCUREMENT, CONSTRUCTION
AND COMMISSIONING OF NPS 4 STEEL PIPES -24M 175,000.00 GAS MALAYSIA BERHAD 2011
55EPCC OF THE NGDS TO AYER HITAM FL STAGE 1/11, AYER HITAM, JOHOR DARUL
TAKZIM
ENGINEERING, PROCUREMENT, CONSTRUCTION
AND COMMISSIONING OF NPS 4 STEEL PIPES -
144M
235,000.00 GAS MALAYSIA BERHAD 2011
NO PROJECT TITLE DESCRIPTIONS VALUE (RM) OWNER / CLIENT YEAR
56 HERCULES PROJECT: FTK MAN CIVIL & FIBER INFRASTRUCTURE AT SACC SHAH ALAM CIVIL AND FIBER PULLING 2,875,146.74
KOMASI
COMMUNICATIONS SDN
BHD / TIME DOTCOM
BERHAD
2011
57
SUPPLY AND ENGINEERING WORKS FOR MAXIS PROJECT ~ RAILWAY CROSSING AT
ALOR SETAR, KUBANG SEMANG, MAMBANG DIAWAN, TANJUNG MALIM, KUALA
KUBU BARU, KEPONG CENTRAL AND KAJANG
CIVIL AND FIBER PULLING 748,102.30
KOMASI
COMMUNICATIONS SDN
BHD / FIBERAIL SDN BHD
2011
58 RELOCATION FOR NETWORK JALAN MUTIARA RINI – GELANG PATAH CIVIL AND FIBER PULLING 213,000.00
KOMASI
COMMUNICATIONS SDN
BHD / CELCOM (M) BERHAD
2011
59
THE SUPPLY AND PROVISION OF UNDERGROUND INFRASTRUCTURE, 48 CORES
OPTICAL FIBRE CABLE AND ACCESSORIES FROM TNBD SEREMBAN TO KILAT FOR
TELEKOM MALAYSIA REQUIREMENT
CIVIL AND FIBER PULLING 433,645.50
KOMASI
COMMUNICATIONS SDN
BHD / FIBRECOMM
NETWORK (M) SDN BHD
2011
60 MAXIS NGBB PROJECT SAUJANA VILLA- CIVIL WORK CIVIL AND FIBER PULLING 280,341.87
KOMASI
COMMUNICATIONS SDN
BHD / HUAWEI
TECHNOLOGIES (M) SDN
BHD
2011
61 MAXIS NGBB PROJECT HP DESIGN (JY33) CIVIL AND FIBER PULLING 130,328.04
KOMASI
COMMUNICATIONS SDN
BHD / HUAWEI
TECHNOLOGIES (M) SDN
BHD
2011
62 CIVIL WORK (HDD) (DSH2 FDC1)CIVIL AND HORIZONTAL DIRECTIONAL DRILLING
(HDD)324,296.95
KOMASI
COMMUNICATIONS SDN
BHD / HUAWEI
TECHNOLOGIES (M) SDN
BHD
2011
63 MAXIS NGBB PROJECT DAMANSARA HEIGHT WSEM FDC6 - MICROTRENCHING CIVIL AND FIBER PULLING 208,981.34
KOMASI
COMMUNICATIONS SDN
BHD / HUAWEI
TECHNOLOGIES (M) SDN
BHD
2011
64 MAXIS NGBB PROJECT DAMANSARA HEIGHT WSEM FDC6 - MICROTRENCHING CIVIL AND FIBER PULLING 216,343.13
KOMASI
COMMUNICATIONS SDN
BHD / HUAWEI
TECHNOLOGIES (M) SDN
BHD
2011
NO PROJECT TITLE DESCRIPTIONS VALUE (RM) OWNER / CLIENT YEAR
65 CIVIL WORK (BANGSAR PERMAI) CIVIL WORK 213,441.86
KOMASI
COMMUNICATIONS SDN
BHD / HUAWEI
TECHNOLOGIES (M) SDN
BHD
2011
66 MAXIS NGBB PROJECT DAMANSARA HEIGHT WSEM FDC9 (DSH1 FDC9) CIVIL AND FIBER PULLING 303,446.00
KOMASI
COMMUNICATIONS SDN
BHD / HUAWEI
TECHNOLOGIES (M) SDN
BHD
2011
67SUPPLY, INSTALL, COMMUNICATION OF CIVIL INFRASTRUCTURE AND FIBRE OPTIC
CABLE WORKS FOR EASTERN AND SOUTHERN REGIONSCIVIL AND FIBER PULLING 440,205.00
KOMASI
COMMUNICATIONS SDN
BHD / CELCOM (M) BERHAD
2011
68SUPPLY AND ENGINEERING WORKS FOR LINE MAXIS TP TANAH MERAH, PASIR MAS,
MENTAKAB, WAKAF BARU, GUA MUSANG AND KUALA KRAICIVIL AND FIBER PULLING 526,961.00
KOMASI
COMMUNICATIONS SDN
BHD / FIBERAIL SDN BHD
2011
69 ENGINEERING WORKS FROM MAXIS TOWER TO ML409 AYER TAWAR , PERAK CIVIL AND FIBER PULLING 950,758.39
KOMASI
COMMUNICATIONS SDN
BHD / FIBERAIL SDN BHD
2011
70 EPCC OF THE NGDS TO PLENTONG FL STAGE 1/11, PLENTONG, JOHOR DARUL TAKZIMENGINEERING, PROCUREMENT, CONSTRUCTION
AND COMMISSIONING OF NPS 4 STEEL PIPES - 60M225,000.00 GAS MALAYSIA BERHAD
March 2011 to Sept
2012
71EPCC OF THE NGDS TO BANTING FL STAGE 1/11, BANTING,OLAK LEMPIT, BANTING,
SELANGOR
ENGINEERING, PROCUREMENT, CONSTRUCTION
AND COMMISSIONING OF NPS 8, NPS 6 AND NPS 4
STEEL PIPES - 1512M
4,745,000.00 GAS MALAYSIA BERHADJune 2011 to April
2012
72EPCC OF THE NGDS TO PADANG TERAP FL STAGE 1/11 & 2/11, PADANG TERAP,
KEDAH DARUL AMAN
ENGINEERING, PROCUREMENT, CONSTRUCTION
AND COMMISSIONING OF NPS 8 STEEL PIPES AND
CONSTRUCTION OF ODORIZER BUILDING AND
ODORIZER SYSTEM - 17000M
6,887,783.00 GAS MALAYSIA BERHAD 2011 to 2012
73TO INSTALL CP ANODES (410 UNIT) BY UNDERWATER WELDING METHOD AT LOADING
JETTY TG. BIN POWER PLANT, KUKUP, PONTIAN, JOHOR DARUL TAKZIMMARINE & SALVAGE WORKS 350,000.00
SBN INDUSTRIES SDN
BHD/EXCALIBER
RESOURCES SDN BHD
March 2012 to April
2012
NO PROJECT TITLE DESCRIPTIONS VALUE (RM) OWNER / CLIENT YEAR
74DIVING SERVICES FOR DECOMMISIONING WORK OF PCSB AT SM-4 AND SM-V
PLATFORM, LABUAN FTMARINE & SALVAGE WORKS 980,000.00
IEV ENGINEERING SDN
BHD/EXCALIBER
RESOURCES SDN BHD
April 2012 to May
2012
75 DIVING SERVICES AT FERRY TERMINAL, PRAI, PENANG MARINE & SALVAGE WORKS 215,000.00DSTS SDN BHD/EXCALIBER
RESOURCES SDN BHD
September 2012 to
October 2012
76UNDERWATER INSPECTION AND REPAIR (WELDING & JACKETING) OF JETTY PILES AT
KARAMUNTING BULK OIL TERMINAL, SANDAKAN, SABAHMARINE & SALVAGE WORKS 320,000.00
RNC TECHNOLOGY (M) SDN
BHD/EXCALIBER
RESOURCES SDN BHD
November 2012 to
December 2012
77 EPCC OF THE NGDS TO KAPAR FL STAGE 1/12, (REINFORCEMENT), KAPAR, SELANGORENGINEERING, PROCUREMENT, CONSTRUCTION
AND COMMISSIONING OF NPS 8 STEEL PIPES - 36M990,060.00 GAS MALAYSIA BERHAD 2012
78 EPCC OF THE NGDS TO NILAI FL STAGE 1/12, NILAI, NEGERI SEMBILAN DARUL KHUSUS
ENGINEERING, PROCUREMENT, CONSTRUCTION
AND COMMISSIONING OF NPS 6 AND NPS 4 STEEL
PIPES - 240M
284,795.00 GAS MALAYSIA BERHAD 2012
79 MENSA : KELANA BREM TOWER 1 (KEB1B)ENGINEERING, PROCUREMENT, CONSTRUCTION &
COMMISSIONING22,000.00 TIME DOT COM BERHAD 2012
80 MENSA : KELANA BREM 2 (KEBTB)ENGINEERING, PROCUREMENT, CONSTRUCTION &
COMMISSIONING22,000.00 TIME DOT COM BERHAD 2012
81 HTK CARINA COVERAGE (GPON): DAMANSARA UPTOWN 3 (DUPBB)ENGINEERING, PROCUREMENT, CONSTRUCTION &
COMMISSIONING22,000.00 TIME DOT COM BERHAD 2012
82SO-12F FIBER PULLING FROM TDC M/H W-18-01-03 TO CKHBW RISER LEVEL 5 (UOB
KL)
ENGINEERING, PROCUREMENT, CONSTRUCTION &
COMMISSIONING3,942.20 TIME DOT COM BERHAD 2012
83 SO-48F FIBER PULLING FROM BMPTW (MDF) TO CKHBW RISER LEVEL 5 (MUAMALAT)ENGINEERING, PROCUREMENT, CONSTRUCTION &
COMMISSIONING19,398.26 TIME DOT COM BERHAD 2012
84 MENSA : FTK FOR MENSA WISMA GOOD YEARENGINEERING, PROCUREMENT, CONSTRUCTION &
COMMISSIONING22,000.00 TIME DOT COM BERHAD 2012
NO PROJECT TITLE DESCRIPTIONS VALUE (RM) OWNER / CLIENT YEAR
85SO : 48 FIBER PULLING & SPLICING FROM BANK RAKYAT SERVER ROOM TO MANHOLE
W-12-00-01CIVIL AND FIBER PULLING 9,795.71 TIME DOT COM BERHAD 2012
86 CARINA : FTK FOR DAMANSARA UPTOWN 1ENGINEERING, PROCUREMENT, CONSTRUCTION &
COMMISSIONING22,000.00 TIME DOT COM BERHAD 2012
87 CARINA : FTK FOR DAMANSARA UPTOWN 2ENGINEERING, PROCUREMENT, CONSTRUCTION &
COMMISSIONING22,000.00 TIME DOT COM BERHAD 2012
88FTK - CARINA COVERAGE (GPON) : FIBER PULLING AT DAMANSARA UPTOWN 5
(DAUPB)
ENGINEERING, PROCUREMENT, CONSTRUCTION &
COMMISSIONING22,000.00 TIME DOT COM BERHAD 2012
89 FTK WORK - JALAN DAMANSARA - JALAN 19/13ENGINEERING, PROCUREMENT, CONSTRUCTION &
COMMISSIONING84,126.18 TIME DOT COM BERHAD 2012
90 REPAIR DUCT - S/O BGN BANK RAKYAT ENGINEERING, PROCUREMENT, CONSTRUCTION &
COMMISSIONING11,000.00 TIME DOT COM BERHAD 2012
91 FIBER PULLING 48F FROM ROCHE TO MH B19-00-06ENGINEERING, PROCUREMENT, CONSTRUCTION &
COMMISSIONING4,229.06 TIME DOT COM BERHAD 2012
92 COVERAGE : OVERTIME CHARGERS AND CABLE TRAY FOR UPTOWN 5ENGINEERING, PROCUREMENT, CONSTRUCTION &
COMMISSIONING25,185.56 TIME DOT COM BERHAD 2012
93 NETWORK UPGRADE : VIRGO - FIBER 48F FOR ROYAL DOMAIN (RDSPW)ENGINEERING, PROCUREMENT, CONSTRUCTION &
COMMISSIONING19,165.06 TIME DOT COM BERHAD 2012
NO PROJECT TITLE DESCRIPTIONS VALUE (RM) OWNER / CLIENT YEAR
94NETWORK UPGRADE : VIRGO FIBER PULLING AND TERMINATION 48F FOR MONT
KIARA DAMAI (MKDCW)
ENGINEERING, PROCUREMENT, CONSTRUCTION &
COMMISSIONING6,287.96 TIME DOT COM BERHAD 2012
95NETWORK UPGRADE : VIRGO FIBER PULLING AND TERMINATION 48F FOR MONT
KIARA ASTANA, CROWN(MKCTW) & TIARA (MKTTW)
ENGINEERING, PROCUREMENT, CONSTRUCTION &
COMMISSIONING8,594.84 TIME DOT COM BERHAD 2012
96NETWORK UPGRADE : VIRGO FIBER PULLING AND TERMINATION 48F FOR MONT
KIARA AMAN (MKACW)
ENGINEERING, PROCUREMENT, CONSTRUCTION &
COMMISSIONING6,287.96 TIME DOT COM BERHAD 2012
97 TRANSFORMER ADSL TO GPON : VISTA COM B. - PULLING AND TERMINATIONENGINEERING, PROCUREMENT, CONSTRUCTION &
COMMISSIONING27,531.38 TIME DOT COM BERHAD 2012
98SUPPLY AND ENGINEERING WORKS FOR SITES SG PETANI (TWSW), PADANG SERAI
(PSERFH), JERANTUT (JERA) AND LAHAT (JTSK)
ENGINEERING, PROCUREMENT, CONSTRUCTION &
COMMISSIONING448,155.93
KOMASI
COMMUNICATIONS SDN
BHD / FIBERAIL SDN BHD
2012
99RELOCATION OF UTILITIES TELEKOM & TNB WORKS (PROJECT MEMBINA JALAN
LINGKARAN TENGAH SEREMBAN, NEGERI SEMBILAN - FASA 2B
ENGINEERING, PROCUREMENT, CONSTRUCTION &
COMMISSIONING689,440.00
KOMASI
COMMUNICATIONS SDN
BHD / KONSORTIUM
TEMOKIN VILLA JELAS JV
SDN BHD
2012
100
(OSP) 48F FIBER PULLING FROM KLANG PROTECH TO RINGCUT EXTS TIME MANHOLE
(B-50-01-83) (96C MAN GLMRB- I-CITY) & SO-(OSP)48F FIBER PULLING FROM KLANG
PROTECH INTAN MELLINIUM MDF ROOM
CIVIL AND FIBER PULLING 371,406.88
KOMASI
COMMUNICATIONS SDN
BHD / TIME DOTCOM
BERHAD
2012
101ELECTRIFIED DOUBLE TRACK PROJECT BETWEEN SEREMBAN TO GEMAS PACK 1-
SEREMBAN TO TABOH NANING. (CH464.00-CH466.275)ELECTRIFIED DOUBLE TRACK 117,678.80
KOMASI
COMMUNICATIONS SDN
BHD / FIBERAIL SDN BHD
2012
102MICRO TRENCHING AND 12C ABF FIBER OPTIC WORKS FROM HP TOWER TO MENARA
SHELL, BUKIT DAMANSARA.CIVIL AND FIBER PULLING 161,878.84
KOMASI
COMMUNICATIONS SDN
BHD / FIBERAIL SDN BHD
2012
NO PROJECT TITLE DESCRIPTIONS VALUE (RM) OWNER / CLIENT YEAR
103
THE SUPPLY AND PROVISION OF ENGINEERING SERVICES FOR CIVIL INFRASTRUCTURE,
OPTICAL FIBRE CABLE AND ACCESSORIES FROM STULANG DARAT TO MENARA
CYBERPOT.
CIVIL AND FIBER PULLING 372,000.00
KOMASI
COMMUNICATIONS SDN
BHD / FIBRECOMM
NETWORK (M) SDN BHD
2012
104THE CIVIL WORK AND INSTALLATION FIBRE OPTIC CABLE FROM FIBRECOMM-MAXIS
R5 TO TM PUTRAJAYA VIA TM DUCTINGCIVIL AND FIBER PULLING 389,037.20
KOMASI
COMMUNICATIONS SDN
BHD / FIBRECOMM
NETWORK (M) SDN BHD
2012
105NEW CIVIL INFRASTRUCTURE OPTICAL FIBRE CABLE AND ACCESSORIES SEMANTAN
(LEVEL 7) –FCN HP TOWER CABIN (ROOFTOP) USING MICRO TRENCHING METHODCIVIL AND FIBER PULLING 369,518.00
KOMASI
COMMUNICATIONS SDN
BHD / FIBRECOMM
NETWORK (M) SDN BHD
2012
106PROPOSED CIVIL, HORIZONTAL DIRECTIONAL DRILLING AND MICRO TRENCHING
WORKS FROM NTT CYBERJAYA TO PATIMAS TO MENARA AIK HUA
CIVIL, HORIZONTAL DIRECTIONAL DRILLING AND
MICRO TRENCHING WORKS3,139,120.30
KOMASI
COMMUNICATIONS SDN
BHD / NTT MSC SDN BHD
2012
107 MENSA PROJECT : FTK MAN CIVIL & FIBER INFRASTRUCTURE AT KELANA JAYA CIVIL AND FIBER PULLING 1,547,393.21
KOMASI
COMMUNICATIONS SDN
BHD / TIME DOTCOM
BERHAD
2012
- SUPPLY & INSTALL 2 WAY GI PIPE FOR ROAD CROSSING
- SUPPLY & INSTALL 100MM CORRUGATED DUCT
- INSTALL 19 CORE P/S/P CABLE
- INSTALL 2 CORE P/S/P CABLE
- INSTALL CABLE PIT DETECTOR PIT
- INSTALL POLES, ASPECTS AND TRAFFIC LIGHT CONTROLLER
- SUPPLY & INSTALL DETECTOR LOOP SENSOR
- SUPPLY & INSTALL TRAFFIC LIGHT CONTROLLER PLINTH
108 SUPPLY & INSTALLATION TRAFFIC LIGHT SYSTEM 850,000.00
ITRAMAS TECHNOLOGY
SDN BHD / WCT (TRAFFIC
SIGNAL SYSTEM FOR
MEDINI, BANDAR
ISKANDAR, JOHOR) /
INTEGRATED DYNASTY (M)
SDN BHD
2012
NO PROJECT TITLE DESCRIPTIONS VALUE (RM) OWNER / CLIENT YEAR
- SUPPLY & INSTALL 100MM CORRUGATED DUCT
- INSTALL 19 CORE P/S/P CABLE
- INSTALL 2 CORE P/S/P CABLE
- INSTALL / REPAIR CABLE PIT
- SUPPLY & INSTALL DETECTOR LOOP SENSOR
- INSTALL TRAFFIC LIGHT POLE, ASPECTS C/W TERMINATION
110 TRAFFIC LIGHT JUNCTION WORK AT NEGERI SEMBILAN (GEMAS AND GEMENCHEH) SUPPLY & INSTALLATION TRAFFIC LIGHT SYSTEM 90,800.00
TYCO FIRE, SECURITY &
SERVICES MALAYSIA SDN
BHD / INTEGRATED
DYNASTY (M) SDN BHD
2013
111EPCC OF THE NGDS TO PULAU INDAH, FL STAGE 2/12 KLANG, SELANGOR DARUL
EHSAN
ENGINEERING, PROCUREMENT, CONSTRUCTION
AND COMMISSIONING OF NPS 8, NPS 6 AND NPS 4
STEEL PIPES - 200M
250,000.00 GAS MALAYSIA BERHAD 2013
112EPCC OF THE NGDS TO BUKIT RAMBAI, FL STAGE 1/12 BUKIT RAMBAI INDUSTRIAL
AREA IV, MELAKA
ENGINEERING, PROCUREMENT, CONSTRUCTION
AND COMMISSIONING OF NPS 6 AND NPS 4 STEEL
PIPES - 700M
489,000.00 GAS MALAYSIA BERHAD 2013
113
RELOCATION OF GAS PIPELINE WORKS RELATED TO THE CONSTRUCTION AND
COMPLETION OF VIADUCT GUIDEWAY AND OTHER ASSOCIATED WORKS FROM
DATARAN SUNWAY STATION TO SECTION 17
ENGINEERING, PROCUREMENT, CONSTRUCTION
AND COMMISSIONING OF NPS 8 STEEL PIPES
RELOCATION WITH 6 NOS OF HOT TAPPING
STOPPLES OF 8" X 8" - 3200M
4,200,000.00
MUDAJAYA CORPORATION
BERHAD / MRT
CORPORATION BHD
2013
114EPCC OF THE NGDS TO KAPAR MERU FL STAGE 1/12, KAPAR & MERU, KLANG,
SELANGOR DARUL EHSAN
ENGINEERING, PROCUREMENT, CONSTRUCTION
AND COMMISSIONING OF NPS 4 STEEL PIPES - 66M382,350.00 GAS MALAYSIA BERHAD July 2012 to Jan 2013
115TO CONDUCT DIVING INSPECTION AT JETTY PILES QUAY 2 & 3 MMHE PASIR GUDANG,
JOHORMARINE & SALVAGE WORKS 270,000.00
RNC TECHNOLOGY (M) SDN
BHD/EXCALIBER
RESOURCES SDN BHD
May 2013
116 TO INSTALL ANODES AT TANJUNG LANGSAT JETTY, JOHOR DARUL TAKZIM MARINE & SALVAGE WORKS 325,000.00
SBN INDUSTRIES SDN
BHD/EXCALIBER
RESOURCES SDN BHD
June 2013
109 SUPPLY & INSTALLATION TRAFFIC LIGHT SYSTEM 356,500.00
ITRAMAS TECHNOLOGY
SDN BHD / WCT (TRAFFIC
SIGNAL SYSTEM FOR
MEDINI, BANDAR
ISKANDAR, JOHOR) /
INTEGRATED DYNASTY (M)
SDN BHD
2013
NO PROJECT TITLE DESCRIPTIONS VALUE (RM) OWNER / CLIENT YEAR
117EPCC OF THE NGDS TO SENAI FL STAGE 1/13, SENAI INDUSTRIAL AREA, JOHOR DARUL
TAKZIM
ENGINEERING, PROCUREMENT, CONSTRUCTION
AND COMMISSIONING OF NPS 4 STEEL PIPES -
600M
199,998.00 GAS MALAYSIA BERHAD 2013
118EPCC OF THE NGDS TO KULAI FL STAGE 1/12, JALAN AIR HITAM, KULAIJAYA, JOHOR
DARUL TAKZIM
ENGINEERING, PROCUREMENT, CONSTRUCTION
AND COMMISSIONING OF NPS 4 STEEL PIPES -
120M
256,265.00 GAS MALAYSIA BERHAD 2013
119 EPCC OF THE NGDS TO CHUPING FL STAGE 1/12, CHUPING,PERLIS INDERA KAYANGAN
ENGINEERING, PROCUREMENT, CONSTRUCTION
AND COMMISSIONING OF NPS 8, NPS 6, AND NPS 4
STEEL PIPES - 9864M
2,335,700.00 GAS MALAYSIA BERHAD 2013
120EPCC OF THE NGDS TO TANJUNG LANGSAT FL STAGE 3/12, TANJUNG LANGSAT,
JOHOR DARUL TAKZIM
ENGINEERING, PROCUREMENT, CONSTRUCTION
AND COMMISSIONING OF NPS 8, AND NPS 4 STEEL
PIPES - 900M
435,000.00 GAS MALAYSIA BERHAD 2013
121EPCC OF THE NGDS TO SEPANG FL STAGE 1/13 (REINFORCEMENT), SALAK TINGGI,
SEPANG, SELANGOR DARUL EHSAN
ENGINEERING, PROCUREMENT, CONSTRUCTION
AND COMMISSIONING OF NPS 8 STEEL PIPES -
3198M
3,603,188.00 GAS MALAYSIA BERHAD 2013
122PROJEK MENAIKTARAF LEBUHRAYA JOHOR BAHRU- PASIR GUDANG DARI 4 LORONG
KE 6 LORONG, JOHOR (THE''PROJECT")ROAD MAINTENANCE WORKS 555,647.80
KOMASI
COMMUNICATIONS SDN
BHD / IDX MULTI
RESOURCES SDN BHD
2013
123
THE SUPPLY AND THE PROVISION OF ENGINEERING SERVICES OF OPTICAL FIBRE
CALBLE INFRASTRUCTURE AND INSTALLATION FOR JOHOR FIBRE ROLL-OUT MENARA
ANSAR TO DANGA BAY (8.5 KM)
CIVIL AND FIBER PULLING 2,245,568.50
KOMASI
COMMUNICATIONS SDN
BHD / PUNCAK SEMANGAT
SDN BHD
2013
124
THE ROAD NAMELY UTILITY MAPPING , HDD, MILLING & PAVING & PIER CABLE
BRIDGE FOR TNB'S CABLE LAYING FROM 33KV PMU TTJ TO TNB SSU AT ON SEMI-SITE
1
CIVIL AND FIBER PULLING 2,820,635.00
KOMASI
COMMUNICATIONS SDN
BHD / SCG INDUSTRIES
MALAYSIA SDN BHD
2013
125 PSND10948: NWK: CIVIL & FIBER FOR MUADZAM SHAH (MAXIS) CIVIL AND FIBER PULLING 499,905.30
KOMASI
COMMUNICATIONS SDN
BHD / TIME DOTCOM
BERHAD
2013
NO PROJECT TITLE DESCRIPTIONS VALUE (RM) OWNER / CLIENT YEAR
126 PSND10936: NWK: CIVIL & FIBER FOR DIGI SOUTH OF RAUB (AS) CIVIL AND FIBER PULLING 1,463,299.63
KOMASI
COMMUNICATIONS SDN
BHD / TIME DOTCOM
BERHAD
2013
127 PSND10949: NWK: CIVIL & FIBER FOR DIGI DONG , PAHANG CIVIL AND FIBER PULLING 1,914,462.41
KOMASI
COMMUNICATIONS SDN
BHD / TIME DOTCOM
BERHAD
2013
128SUPPLY AND ENGINEERING WORKS FROM TH PROPERTIES DATA CENTRE TO EXISTING
MANHOLE (ROUTE 1 AND ROUTE 2) AT BANDAR ENSTEKCIVIL WORKS 564,304.21
KOMASI
COMMUNICATIONS SDN
BHD / FIBERAIL SDN BHD
2013
129UNDERWATER INSPECTION TO JETTY STRUCTURE AT FELDA SAHABAT, LAHAD DATU,
SABAHMARINE & SALVAGE WORKS 185,000.00
3R SYSTEMS SDN
BHD/EXCALIBER
RESOURCES SDN BHD
March 2014
130 UNDERWATER INSPECTION AT BOUSTEAD NAVAL DOCK YARD, LUMUT, PERAK MARINE & SALVAGE WORKS 155,000.00
RNC TECHNOLOGY (M) SDN
BHD/EXCALIBER
RESOURCES SDN BHD
March 2014 to April
2014
131REHABILITATION OF CATHODIC PROTECTION AT KPC, KUANTAN, PAHANG DARUL
MAKMURMARINE & SALVAGE WORKS 510,000.00
SBN INDUSTRIES (M) SDN
BHD/EXCALIBER
RESOURCES SDN BHD
March 2014 to May
2014
132 INSTALL ANODES (WELDING) AT KBOT JETTY PILES, SANDAKAN, SABAH MARINE & SALVAGE WORKS 280,000.00
SBN INDUSTRIES (M) SDN
BHD/EXCALIBER
RESOURCES SDN BHD
June 2014 to July
2014
133 DIVING SERVICES FOR DEWATERING AT CENDOR MOPU (OFFSHORE) MARINE & SALVAGE WORKS 1,250,000.00
CENDOR MOPU PRODUCER
LTD/EXCALIBER RESOURCES
SDN BHD
October 2014
134CONDITION ASSESSMENT AND ENGINEERING WORKS AT BOUSTEAD NAVAL
DOCKYARD, LUMUT, PERAKMARINE & SALVAGE WORKS 220,000.00
RNC TECHNOLOGY (M) SDN
BHD/EXCALIBER
RESOURCES SDN BHD
Nov 2014 to Dec
2014
NO PROJECT TITLE DESCRIPTIONS VALUE (RM) OWNER / CLIENT YEAR
135 EPCC OF THE NGDS TO LUMUT FL STAGE 1/13, SITIAWAN, PERAK DARUL RIDZUAN
ENGINEERING, PROCUREMENT, CONSTRUCTION
AND COMMISSIONING OF NPS 6 AND NPS 4 STEEL
PIPES - 456M
330,000.00 GAS MALAYSIA BERHAD 2014
136EPCC OF THE NGDS TO KULAI FL STAGE 1/13, KAWASAN PERINDUSTRIAN I-PARK,
KULAIJAYA, JOHOR BAHRU, JOHOR DARUL TAKZIM
ENGINEERING, PROCUREMENT, CONSTRUCTION
AND COMMISSIONING OF NPS 6 AND NPS 4 STEEL
PIPES - 2388M
1,238,000.00GAS MALAYSIA BERHAD 2014
137
CADANGAN PEMBANGUNAN KILANG BERKEMBAR 3 ½ TINGKAT JENIS A (6 UNIT),
JENIS B (10 UNIT) DAN KILANG SESEBUAH 3 1/2 TINGKAT (1 UNIT) DI ATAS LOT PT
1260 (HSD) 176557, JALAN PUCHONG, MUKIM PETALING, DAERAH PETALING,
SELANGOR DARUL EHSAN UNTUK TETUAN BROADWAY MERGER SDN BHD
SUB-CONTRACT OF GAS PIPE PROTECTION AND
MDPE PIPE RELOCATION - 150M
200,000.00 BROADWAY MERGER SDN
BHD2014
138EPCC OF THE NGDS TO MAK MANDIN & PRAI FL DL STAGE 1/14, MAK MANDIN &
PRAI, PULAU PINANG
ENGINEERING, PROCUREMENT, CONSTRUCTION
AND COMMISSIONING OF NPS 8, NPS 6 AND NPS 4
STEEL PIPES - 1380M
1,298,000.00GAS MALAYSIA BERHAD 2014
139EPCC OF THE NGDS TO TANJUNG LANGSAT FL STAGE 2/14, TANJUNG LANGSAT,
JOHOR DARUL TAKZIM
ENGINEERING, PROCUREMENT, CONSTRUCTION
AND COMMISSIONING OF NPS 8, NPS 6 AND NPS 4
STEEL PIPES - 984M
530,000.00GAS MALAYSIA BERHAD 2014
140EPCC OF THE NGDS TO TANJUNG LANGSAT FL STAGE 3/14, TANJUNG LANGSAT,
JOHOR DARUL TAKZIM
ENGINEERING, PROCUREMENT, CONSTRUCTION
AND COMMISSIONING OF NPS 6 AND NPS 4 STEEL
PIPES - 822M
850,000.00GAS MALAYSIA BERHAD 2014
141MENAIKTARAF JALAN MUAR - TANGKAK-SEGAMAT JOHOR (FASA 1: SEGAMAT -
TANGKAK) PAKEJ 2ROAD MAINTENANCE WORKS 4,847,006.50
KOMASI
COMMUNICATIONS SDN
BHD / BINA MEKAR SDN
BHD
2014
142FULL TURNKEY OF CIVIL AND FIBER INFRASTRUCTURE OF CELCOM PROJECT - PHASE 2 :
CELCOM SKUDAI TAMAN UNIVERSITICIVIL AND FIBER PULLING 234,000.00
KOMASI
COMMUNICATIONS SDN
BHD / TIME DOTCOM
BERHAD
2014
143
MASS RAPID TRANSIT LEMBAH KLANG: JAJARAN SUNGAI BULOH KAJANG PACKAGE V8
: CONSTRUCTION AND COMPLETION OF VIADUCT GUIDEWAY AND OTHER WORKS
FROM TAMAN MESRA KAJANG STATION RELOCATION OF EXISTING DIGI & MAXIS
SERVICES
ENGINEERING, PROCUREMENT, CONSTRUCTION &
COMMISSIONING FOR CIVIL AND FIBER PULLING237,123.88
KOMASI
COMMUNICATIONS SDN
BHD / FIBERAIL SDN BHD
2014
144SUPPLY AND ES FOR NEW CIVIL INFRASTRUCTURE, OPTICAL FIBRE CABLE AND
ACCESSORIES FOR 48 CORES FROM CABIN PMU SKUDAI TO TAMAN SRI SKUDAICIVIL AND FIBER PULLING 216,608.80
KOMASI
COMMUNICATIONS SDN
BHD / FIBRECOMM
NETWORK (M) SDN BHD
2014
NO PROJECT TITLE DESCRIPTIONS VALUE (RM) OWNER / CLIENT YEAR
145 CABLE MIGRATION WORKS TO JB SENTRAL CABLE MIGRATION WORKS 278,970.52
KOMASI
COMMUNICATIONS SDN
BHD /FIBERAIL SDN BHD
2014
146 BUTTERFLY PROJECT AIR HITAM SKUDAI LINKENGINEERING, PROCUREMENT, CONSTRUCTION &
COMMISSIONING468,538.00
KOMASI
COMMUNICATIONS SDN
BHD / TIME DOTCOM
BERHAD
2014
147 HDD WORKS FOR SITE "JPELFH01" KTMB CROSSING JOHOR BAHRU HORIZONTAL DIRECTIONAL DRILLING WORKS 123,860.97
KOMASI
COMMUNICATIONS SDN
BHD /FIBERAIL SDN BHD
2014
148RELOCATION OF MICRO TRENCHING WORKS FROM MH NO 3 (ISTANA HOTEL)TO
EXISTING MANHOLE AT MAJU EXPRESSWAY (BULATAN KG PANDAN)CIVIL AND FIBER PULLING 916,280.52
KOMASI
COMMUNICATIONS SDN
BHD /FIBERAIL SDN BHD
2014
149CIVIL AND PULLING WORK FOR MALAYSIA MARINE HEAVY ENGINEERING
(MMHE)(THE 'WORK)CIVIL AND FIBER PULLING 234,115.00
KOMASI
COMMUNICATIONS SDN
BHD / TIME DOTCOM
BERHAD
2014
150 TRAFFIC LIGHT JUNCTION WORK AT MEDINI JUNCTION, BANDAR ISKANDAR, JOHOR SUPPLY & INSTALLATION TRAFFIC LIGHT SYSTEM 61,000.00
TYCO FIRE, SECURITY &
SERVICES MALAYSIA SDN
BHD / INTEGRATED
DYNASTY (M) SDN BHD
2014
151 TRAFFIC LIGHT JUNCTION WORK AT TAMAN SELASIH, KULIM SUPPLY & INSTALLATION TRAFFIC LIGHT SYSTEM 75,000.00
TYCO FIRE, SECURITY &
SERVICES MALAYSIA SDN
BHD / INTEGRATED
DYNASTY (M) SDN BHD
2014
152 TRAFFIC LIGHT JUNCTION WORK AT LABU, NEGERI SEMBILAN SUPPLY & INSTALLATION TRAFFIC LIGHT SYSTEM 43,000.00
TYCO FIRE, SECURITY &
SERVICES MALAYSIA SDN
BHD / INTEGRATED
DYNASTY (M) SDN BHD
2014
NO PROJECT TITLE DESCRIPTIONS VALUE (RM) OWNER / CLIENT YEAR
153 TRAFFIC LIGHT JUNCTION WORK AT TANJUNG TOKONG, PENANG SUPPLY & INSTALLATION TRAFFIC LIGHT SYSTEM 95,000.00
TYCO FIRE, SECURITY &
SERVICES MALAYSIA SDN
BHD / E & O / INTEGRATED
DYNASTY (M) SDN BHD
2014
154 TO RELOCATE TRAFFIC SIGNAL SYSTEM AT CENTRAL MARKET SUPPLY & INSTALLATION TRAFFIC LIGHT SYSTEM 57,000.00
TYCO FIRE, SECURITY &
SERVICES MALAYSIA SDN
BHD / E & O / INTEGRATED
DYNASTY (M) SDN BHD
2014
155 PMU 132KV TASEK GELUGOR SWITCHING STATION
2 X 13KV AIS OHL FEEDER BAYS, 2X 132KV UGC
FEEDER BAYS, 1X132 BUS COUPLER BAY, NEW
TRANSMISSION RTU, CONTROL & RELAY PANEL,
LVAC, GENSET, EARTHING SYSTEMS AND ALL
OTHER ASSOCIATE ANCILLARY EQUIPMENT, NEW
132KV BUILDING, ACCESS ROAD AND ASSOCIATED
CIVIL WORK , ALL RELATED TESTING
&COMMISIONING WORKS BY OEM'S TESTER
505,520.00 TRANSPRO SDN BHD 2014
156 TRAFFIC LIGHT JUNCTION WORK AT JELUTONG EXPRESSWAY, PENANG SUPPLY & INSTALLATION TRAFFIC LIGHT SYSTEM 125,000.00
TYCO FIRE, SECURITY &
SERVICES MALAYSIA SDN
BHD / IJM / INTEGRATED
DYNASTY (M) SDN BHD
2014
157EPCC OF THE NGDS TO BUKIT KEMUNING DL STAGE 1/13 (LOOPING) BUKIT
KEMUNING, SHAH ALAM, SELANGOR DARUL EHSAN
ENGINEERING, PROCUREMENT, CONSTRUCTION
AND COMMISSIONING OF PE 125 MM, PE PIPES -
750M
517,337.50 GAS MALAYSIA BERHAD Aug 2013 to Jan 2014
158EPCC OF THE NGDS TO SEPANG FL STAGE 3/13, TANJUNG INDUSTRIAL PARK, SEPANG,
SELANGOR DARUL EHSAN
ENGINEERING, PROCUREMENT, CONSTRUCTION
AND COMMISSIONING OF NPS 16, NPS 8 AND NPS
6 STEEL PIPES - 9260M
6,494,600.00 GAS MALAYSIA BERHADDec 2013 to Nov
2014
159TO SUPPLY APC SOLUTIONS FOR JPKN NEW BUILDING DATA CENTER IN KK AND DRC
IN TAWAU
TO SUPPLY APC SOLUTIONS FOR JPKN NEW
BUILDING DATA CENTER IN KK AND DRC IN TAWAU6,000,000.00 SRI KOMPUTER SDN BHD July 2014 to Jan 2015
160SUPPLY MANPOWER AND DIVING EQUIPMENT FOR SALVAGE WORK (KD PERANTAU)
AT LUMUT PERAKMARINE & SALVAGE WORKS 1,600,000.00
BOUSTEAD NAVAL
DOCKYARD/EXCALIBER
RESOURCES SDN BHD
Dec 2014 to Jan 2015
161PRESERVATION SERVICES FOR TREATMENT OF WATER DAMAGED MACHINERY OF
PARTIALLY SUNKEN KD PERANTAU.
CARRY OUT PRESERVATION OF MACHINERY AND
EQUIPMENT DAMAGE PREVENTION AND
CLEANING AFTER SALVAGE OF KD PERANTAU.
3,100,000.00BOUSTEAD NAVAL
SHIPYARD SDN BHDDec 2014 Feb 2015
NO PROJECT TITLE DESCRIPTIONS VALUE (RM) OWNER / CLIENT YEAR
162 SALVAGE OPERATION KD PERANTAUTO CONTINUE AND TAKE OVER SALVAGE
OPERATION1,594,232.50
BOUSTEAD NAVAL
SHIPYARD SDN BHDJan-15
163 EXTENSION - SALVAGE OPERATION KD PERANTAUEXTENSION OF SALVAGE OPERATION KD
PERANTAU (UPRIGHT AND REAFLOAT)2,441,886.00
BOUSTEAD NAVAL
SHIPYARD SDN BHDJan-15
164 NAVAL ARCHITECTURE - SALVAGE KD PERANTAU
TO PROVIDE ENGANGE SERVICE OF NAVAL
ARCHITECT TO CONDUCT DOCKING ANALYSIS AND
SHIP STABILITY ANALYSIS OF KD PERANTAU AND TO
PROVIDE FULL ANALYSIS REPORT.
92,400.00BOUSTEAD NAVAL
SHIPYARD SDN BHDJan-15
165REPAIR, REHABILITATION AND REVIVAL OF SHIP LIFT PLATFORM AT TLDM LUMUT FOR
BOUSTEAD NAVAL SHIPYARD, LUMUT, PERAK D.RMARINE & SALVAGE WORKS 215,000.00
RNC TECHNOLOGY (M) SDN
BHD/EXCALIBER
RESOURCES SDN BHD
Mar 2015 to June
2015
166 TO SUPPLY APC SOLUTIONS FOR MATRADE BUILDING DATA CENTER UPGRADING JOBTO SUPPLY APC SOLUTIONS FOR MATRADE
BUILDING DATA CENTER UPGRADING JOB1,800,000.00 BIT GROUP SDN BHD
Mar 2015 to Sept
2015
167 UNDERWATER SALVAGE OF TUG BOAT AT PENANG PORT CONSORTIUM PENANG MARINE & SALVAGE WORKS 250,000.00EXCALIBER RESOURCES SDN
BHD
Nov 2015 to Dec
2015
168 UNDERWATER SALVAGE OF TUG BOAT AT PENANG PORT CONSORTIUM PENANG MARINE & SALVAGE WORKS 250,000.00EXCALIBER RESOURCES SDN
BHD
Nov 2015 to Dec
2015
169 EPCC OF THE NGDS TO TEBRAU FL STAGE 1/14, TEBRAU, JOHOR DARUL TAKZIM
ENGINEERING, PROCUREMENT, CONSTRUCTION
AND COMMISSIONING OF NPS 6 AND NPS 4 STEEL
PIPES -1296M
1,213,852.00 GAS MALAYSIA BERHAD 2015
170EPCC OF THE NGDS TO WEST PORT FL STAGE 2/14, WEST PORT, KLANG, SELANGOR
DARUL EHSAN
ENGINEERING, PROCUREMENT, CONSTRUCTION
AND COMMISSIONING OF NPS 4 STEEL PIPES -48M218,000.00 GAS MALAYSIA BERHAD 2015
171EPCC OF THE NGDS TO BANTING FL STAGE 1/14, OLAK LEMPIT INDUSTRIAL AREA,
BANTING, SELANGOR DARUL EHSAN
ENGINEERING, PROCUREMENT, CONSTRUCTION
AND COMMISSIONING OF NPS 8, NPS 6 AND NPS 4
STEEL PIPES
2,460,080.00GAS MALAYSIA BERHAD 2015
172EPCC OF THE NGDS TO MERU FL STAGE 3/15, MERU, KLANG, SELANGOR DARUL
EHSAN
ENGINEERING, PROCUREMENT, CONSTRUCTION
AND COMMISSIONING OF NPS 4 STEEL PIPES176,278.00 GAS MALAYSIA BERHAD 2015
NO PROJECT TITLE DESCRIPTIONS VALUE (RM) OWNER / CLIENT YEAR
173
MSVT-TUKAR KABEL VOLTAN TINGGI 22KV PILC UNTUK TUJUAN PENUKARAN PILC
SEDIA ADA SEPANJANG 2KM KAWASAN PASIR GUDANG INDUSTRI FASA 8 (KERJA -
KERJA MERENTANG 1 LITAR KABEL 240MMP XLPE 22KV IC BARU ANTARA PE TIONG
NAM KE PCOC DAN BYPASS PE KOMERSIAL MINERAL BAGI MENGGANTIKAN KABEL
LAMA) -KERJA HDD
CIVIL AND FIBER PULLING 197,067.00
KOMASI
COMMUNICATIONS SDN
BHD / TENAGA NASIONAL
BERHAD
2015
174
MSVT-MERENTANG KABEL VOLTAN TINGGI 11KV XLPE UNTUK TUJUAN RE-
CONFIGURE SISTEM SEDIADA KAWASAN JOHOR JAYA FASA 10 (MSVT NEW INJECTION
MERENTANG 1 LITAR KABEL VOLTAN TINGGI 1C 240MMP 22KV DARI PMU TEBRAU KE
TEMPAT CADANGAN POTONG & SAMBUNG KE S/S GIANT SEPANJANG 1746M) (KERJA
KONTRAK HDD)
CIVIL AND FIBER PULLING 249,294.40
KOMASI
COMMUNICATIONS SDN
BHD / TENAGA NASIONAL
BERHAD
2015
175RECTIFICATION WORK FOR INTERMARK CABLE AT JUNCTION OF JALAN AMPANG -
JALAN TUN RAZAKCIVIL AND FIBER PULLING 102,591.31
KOMASI
COMMUNICATIONS SDN
BHD / FIBERAIL SDN BHD
2015
176
MSVT- TUKAR KABEL VOLTAN TINGGI 11KV UNTUK TUJUAN RE-CONFIGURE SISTEM
SEDIADA DI KAWASAN JOHOR JAYA FASA 8 (MSVT NEW INJECTION 3C 240MMP 11KV
PE TMN MOLEK NO 3 KE PE TMN MOLEK NO 14 SEPANJANG 1229 METER ) (KERJA
KONTRAK HDD)
CIVIL AND FIBER PULLING 103,000.00
KOMASI
COMMUNICATIONS SDN
BHD / TENAGA NASIONAL
BERHAD
2015
177CONTRACT FOR NETWORK DEVELOPMENT PROJECT VIA SCHEDULE OF RATE (JKH) FOR
TELEKOM MALAYSIA BERHAD ™CIVIL AND FIBER PULLING 34,773,000.00
KOMASI
COMMUNICATIONS SDN
BHD / TM BERHAD
2015
178
THE SUPPLY, DELIVERY, INSTALLATION, TESTING AND COMMISSIONING OF THE
TELEPHONE INFRASTRUCTURE WORKS FOR TOTAL 80 UNITS OF MIXED RESIDENTIAL
UNITS ( STAGE 1-39 UNITS & STAGE 2-41 UNITS) DI ATAS SEBAHAGIAN LOT PTD
104940, INDAHPURA ZONE 33B, MUKIM KULAI, DAERAH KULAIJAYA, NEGERI JOHOR
DARUL TAKZIM
ENGINEERING, PROCUREMENT, CONSTRUCTION &
COMMISSIONING418,730.00
KOMASI
COMMUNICATIONS SDN
BHD / GPROPERTY
CONSTRUCTION SDN BHD
2015
179
THE SUPPLY, DELIVERY , INSTALLATION , TESTING & COMMISSIONING OF TELEPHONE
INFRASTRUCTURE WORKS FOR PROPOSED DEVELOPMENT AT PHASE 1 FOR ECO
BUSINESS PARK 1 ON PART OF LOT PTD 117036, 117040 & 117041, MUKIM TEBRAU ,
DAERAH JOHOR BHARU, JOHOR
ENGINEERING, PROCUREMENT, CONSTRUCTION &
COMMISSIONING819,705.00
KOMASI
COMMUNICATIONS SDN
BHD / ECO BUSINESS PARK
1 DEVELOPMENT SDN BHD
2015
180 TRAFFIC LIGHT JUNCTION WORK AT NILAI, NEGERI SEMBILAN SUPPLY & INSTALLATION TRAFFIC LIGHT SYSTEM 145,000.00
TYCO FIRE, SECURITY &
SERVICES MALAYSIA SDN
BHD / IJM / INTEGRATED
DYNASTY (M) SDN BHD
2015
NO PROJECT TITLE DESCRIPTIONS VALUE (RM) OWNER / CLIENT YEAR
181 TRAFFIC LIGHT JUNCTION WORK AT LUKUT, NEGERI SEMBILAN SUPPLY & INSTALLATION TRAFFIC LIGHT SYSTEM 30,000.00
TYCO FIRE, SECURITY &
SERVICES MALAYSIA SDN
BHD / INTEGRATED
DYNASTY (M) SDN BHD
2015
182 TRAFFIC LIGHT JUNCTION WORK AT KEPONG SUPPLY & INSTALLATION TRAFFIC LIGHT SYSTEM 95,000.00
TYCO FIRE, SECURITY &
SERVICES MALAYSIA SDN
BHD / INTEGRATED
DYNASTY (M) SDN BHD
2015
183 LOI FOR P&D : COVERAGE: WISMA UOA DAMANSARA 2 CIVIL AND FIBER PULLING 1,060.00 TIME DOT COM BERHAD 07.07.2015 to
07.07.2015
184SERVICE ORDER : FIBER PULLING WORK TO MDF ROOM MENARA PNB JALAN TUN
RAZAK, KL CIVIL AND FIBER PULLING 2,333.56 TIME DOT COM BERHAD
13.08.2015 to
13.08.2015
185 THE ASCENT @ PARADIGM MALL PETALING JAYA, SELANGOR DARUL EHSAN CIVIL AND FIBER PULLING 1,537.78 TIME DOT COM BERHAD 09.09.2015 TO
09.09.2015
186 RAISE UP MANHOLE – MENARA PNB CIVIL AND FIBER PULLING 1,060.00 TIME DOT COM BERHAD 28.10.2015 TO
28.10.2015
187 LOI FOR P&D : NTT CYBERJAYA CIVIL AND FIBER PULLING 1,060.00 TIME DOT COM BERHAD 2015
188 FIBER PULLING FOR NTT CYBERJAYA CIVIL AND FIBER PULLING 4,348.21 TIME DOT COM BERHAD 15.09.2015 TO
28.09.2015
189EPCC OF THE NGDS TO LIPAT KAJANG FL STAGE 2/13 AND STAGE 3/13, LIPAT KAJANG
INDUSTRIAL AREA, MUKIM JASIN, MELAKA
ENGINEERING, PROCUREMENT, CONSTRUCTION
AND COMMISSIONING OF NPS 12, NPS 8 AND NPS
6 STEEL PIPES -29262M
9,988,772.00 GAS MALAYSIA BERHAD 2015
NO PROJECT TITLE DESCRIPTIONS VALUE (RM) OWNER / CLIENT YEAR
190 EPCC OF THE NGDS TO KL FL STAGE 1/15, JALAN PEEL, KUALA LUMPUR
ENGINEERING, PROCUREMENT, CONSTRUCTION
AND COMMISSIONING OF NPS 8, NPS 6 AND NPS 4
STEEL PIPES -1056M
2,731,471.60 GAS MALAYSIA BERHAD 2015
191EPCC OF GPRW AT JALAN GUDANG, JOHOR PORT INDUSTRIAL AREA, PASIR GUDANG,
JOHOR DARUL TAKZIM
ENGINEERING, PROCUREMENT, CONSTRUCTION
AND COMMISSIONING OF NPS 6 STEEL PIPES -
204M
494,998.80 GAS MALAYSIA BERHAD 2015
192 EPCC OF THE NGDS TO KULAI FL STAGE 1/15, KULAIJAYA, JOHOR DARUL TAKZIM
ENGINEERING, PROCUREMENT, CONSTRUCTION
AND COMMISSIONING OF NPS 6 AND NPS 4 STEEL
PIPES -1506M
868,924.40 GAS MALAYSIA BERHAD 2016
193COVERAGE : PROPOSED CIVIL & FIBER PULLING 48 FROM BANGSAR HEIGHT TOWER
TO TIME EXISTING M/H CIVIL AND FIBER PULLING 26,624.18 TIME DOT COM BERHAD 2016
194COVERAGE : PROPOSED CIVIL & FIBER PULLING FROM PURI AYU CONDO TO TIME
EXISTING M/H CIVIL AND FIBER PULLING 49,425.24 TIME DOT COM BERHAD 2016
195EPCC OF NGDS TO PEGOH FL STAGE 2/15, HICOM INDUSTRIAL PARK PEGOH, ALOR
GAJAH, MELAKA (HONDA MALAYSIA SDN BHD)
ENGINEERING, PROCUREMENT, CONSTRUCTION
AND COMMISSIONING OF NPS 4 & NPS 61,898,000.00 GAS MALAYSIA BERHAD 2016
196TO DESIGN AND BUILD TRAFFIC LIGHT SIGNALLING JUNCTION AT MACHANG BUBUK,
PENANGSUPPLY & INSTALLATION TRAFFIC LIGHT SYSTEM 212,265.00
TF LAND SDN BHD /
INTEGRATED DYNASTY (M)
SDN BHD
2016
197 TO RELOCATE EXISTING TRAFFIC LIGHTS JUNCTION @ MEDINI, JOHOR SUPPLY & INSTALLATION TRAFFIC LIGHT SYSTEM 109,230.00
NURI MERDU SDN BHD /
INTEGRATED DYNASTY (M)
SDN BHD
2016
198 SALVAGE WORKS AT PENANG PORT SDN BHD MARINE & SALVAGE WORKS 670,000.00EXCALIBER RESOURCES SDN
BHD
Feb 2016 to March
2016
199PROPOSED CONTAINER TERMINAL ASSOCIATED INFRASTRUCTURE WORKS AT POIC,
LAHAD DATU, SABAHMARINE & SALVAGE WORKS 250,000.00
SCORR TECHNOLOGY SDN
BHD/EXCALIBER
RESOURCES SDN BHD
March 2016 to May
2016
NO PROJECT TITLE DESCRIPTIONS VALUE (RM) OWNER / CLIENT YEAR
200 COVERAGE : CIVIL AND FIBER PULLING AT BUKIT PANDAN 1 CIVIL AND FIBER PULLING 25,440.00 TIME DOT COM BERHAD 2016
201SUASANA BUKIT CEYLON - CIVIL (60MTR) AND PULLING (200MTR) FOR SUASANA
BUKIT CEYLON AT PERSIARAN RAJA CHULAN, KUALA LUMPURCIVIL AND FIBER PULLING 19,480.40 TIME DOT COM BERHAD 2016
202SO DRIVEN (DIGI) : OVERHEAD INFRA (2000M) AND FIBER PULLING (2300M) FOR DIGI
DONG RESILIENCY TOWN AREACIVIL AND FIBER PULLING 46,662.37 TIME DOT COM BERHAD 2016
203 CIVIL AND FIBER PULLING AT MAXIS KUANTAN CIVIL AND FIBER PULLING 163,800.00 TIME DOT COM BERHAD 2016
204 SO : FIBER INFRA WORKS AT CELCOM SITE - JALAN KIA PENG, KUALA LUMPUR CIVIL AND FIBER PULLING 38,941.78 TIME DOT COM BERHAD 2016
205 SO : CIVIL AND FIBER PULLING AT SUCCESS ELECTRONIC CIVIL AND FIBER PULLING 17,713.46 TIME DOT COM BERHAD 2016
206 SO : CIVIL AND FIBER FOR VISI CENDERAWASIH @ PTTC IPOH, PERAK CIVIL AND FIBER PULLING 33,541.49 TIME DOT COM BERHAD 2016
207FTK FOR PROPOSED NEW INFRASTRUCTURE OF CIVIL AND FIBER PULLING FROM
JALAN TAMAN BUKIT MALURI TO KIARA 5CIVIL AND FIBER PULLING 209,880.00 TIME DOT COM BERHAD 2017
208PROPOSED FIBER INFRASTRUCTURE WORK AT SOUTHVIEW SERVICES APARTMENT
BANGSAR, KUALA LUMPURCIVIL AND FIBER PULLING 77,829.52 TIME DOT COM BERHAD 2017
209SO : PROPOSED NEW FIBER INFRA TO GRAND WEIL HOTEL, JALAN SULTAN IDRIS,
IPOH, PERAKCIVIL AND FIBER PULLING 105,292.10 TIME DOT COM BERHAD 2017
NO PROJECT TITLE DESCRIPTIONS VALUE (RM) OWNER / CLIENT YEAR
210 PMU 132KV BUKIT TENGAH REHAB (STAGE 3 ), PULAU PINANG INSTALLATION OF 132KV SUBSTATION INCLUDING
CABLING, TESTING & COMMISIONING 1,100,000.00
PEMBINAAN TERAS MAJU
SDN BHD 2017
2112W CIVIL AND 48F PULLING WORK FOR MAISSON ARA DAMANSARA TO EXISTING
TIME M/HOLECIVIL AND FIBER PULLING 176,893.85 TIME DOT COM BERHAD 2017
212
PROJEK MASS RAPID TRANSIT LEMBAH KELANG JAJARAN SUNGAI BULOH - KAJANG
PACKAGE V3 : CONSTRUCTION AND COMPLETION OF VIADUCT GUIDEWAY AND
OTHER ASSOCIATED WORKS FROM DATARAN SUNWAY STATION TO SECTION 17
SUPPLY & INSTALLATION TRAFFIC LIGHT SYSTEM 1,283,310.20MUDAJAYA CORPORATION
BERHAD2017
213EPCC OF NGDS TO PULAU INDAH FL STAGE 1/16, SELANGOR HALAL HUB, PULAU
INDAH, SELANGOR DARUL EHSAN (LONGSON FOOD PRODUCTS SDN BHD)
ENGINEERING, PROCUREMENT, CONSTRUCTION
AND COMMISSIONING OF NPS 8 AND NPS 4 STEEL
PIPES - 324M
485,290.00 GAS MALAYSIA BERHAD 2017
214
EPCC OF NGDS TO SENDAYAN FL STAGE 2/16, SENDAYAN TECH VALLEY, SEREMBAN 2,
NEGERI SEMBILAN DARUL KHUSUS (VIO STAR INTERNATIONAL (M) SDN BHD AND
DAIHATSU ENGINE MANUFACTURING SDN BHD)
ENGINEERING, PROCUREMENT, CONSTRUCTION
AND COMMISSIONING OF NPS 6 AND NPS 4 STEEL
PIPES -1290M
662,700.00 GAS MALAYSIA BERHAD 2017
215EPCC OF THE NGDS TO TANJUNG LANGSAT FL STAGE 3/16, TANJUNG LANGSAT,
JOHOR DARUL TAKZIM (KIRAN GLOBAL ALKALI SDN BHD)
ENGINEERING, PROCUREMENT, CONSTRUCTION
AND COMMISSIONING OF NPS 8, NPS 6 AND NPS 4
STEEL PIPES -1688M
692,700.00 GAS MALAYSIA BERHAD 2017
216EPCC OF THE NGDS TO TANJUNG LANGSAT FL STAGE 4/16, TANJUNG LANGSAT,
JOHOR DARUL TAKZIM (POLYNT COMPOSITE MALAYSIA SDN BHD)
ENGINEERING, PROCUREMENT, CONSTRUCTION
AND COMMISSIONING OF NPS 8 AND NPS 4 STEEL
PIPES -264M
228,600.00 GAS MALAYSIA BERHAD 2017
217EPCC OF THE NGDS TO TANJUNG LANGSAT FL STAGE 5/16, TANJUNG LANGSAT,
JOHOR DARUL TAKZIM (NORMAN PROCESS OILS MALAYSIA PLANT SDN BHD)
ENGINEERING, PROCUREMENT, CONSTRUCTION
AND COMMISSIONING OF NPS 4 STEEL PIPES -60M223,900.00 GAS MALAYSIA BERHAD 2017
218
PROJEK MASS RAPID TRANSIT LALUAN 2: SUNGAI BULOH-SERDANG-PUTRAJAYA (SSP)
UNDERGROUND WORKS PACKAGE: DESIGN, CONSTRUCTION AND COMPLETION OF
TUNNELS, STATION AND ASSOCIATED STRUCTURES FROM JALAN IPOH NORTH ESCAPE
SHAFT TO DESA WATERPARK SOUTH PORTAL
END CAPPING WORK AT PETRONAS KG. BARU 58,000.00MMC GAMUDA KVMRT (T)
SDN BHD2017
219EPCC OF THE NGDS TO KAPAR FL STAGE 5/16, KAPAR, KLANG, SELANGOR DARUL
EHSAN (SUNWAY VCP SDN BHD)
ENGINEERING, PROCUREMENT, CONSTRUCTION
AND COMMISSIONING OF NPS 4 STEEL PIPES -48M289,000.00 GAS MALAYSIA BERHAD 2017
220EPCC OF THE NGDS TO MERU FL STAGE 2/16, KLANG, SELANGOR DARUL EHSAN
(IDEAL QUALITY SDN BHD)
ENGINEERING, PROCUREMENT, CONSTRUCTION
AND COMMISSIONING OF NPS 4 STEEL PIPES -36M250,000.00 GAS MALAYSIA BERHAD 2017
NO PROJECT TITLE DESCRIPTIONS VALUE (RM) OWNER / CLIENT YEAR
221EPCC OF THE NGDS TO PASIR GUDANG FL STAGE 3/16, PASIR GUDANG, JOHOR DARUL
TAKZIM (ALMER MALAYSIA SDN BHD)
ENGINEERING, PROCUREMENT, CONSTRUCTION
AND COMMISSIONING OF NPS 4 STEEL PIPES -60M298,000.00 GAS MALAYSIA BERHAD 2017
222EPCC OF THE NGDS TO YONG PENG FL STAGE 1/17, YONG PENG, JOHOR DARUL
TAKZIM (TEO SENG FEEDMILLS SDN BHD)
ENGINEERING, PROCUREMENT, CONSTRUCTION
AND COMMISSIONING OF NPS 4 STEEL PIPES -84M268,000.00 GAS MALAYSIA BERHAD 2017
223FULL TURNKEY FOR PROPOSED NEW INFRASTRUCTURE OF CIVIL AND FIBER PULLING
FROM JALAN TAMAN BUKIT MALURI TO KIARA 5CIVIL AND FIBER PULLING 2,099,880.00 TIME DOT COM BERHAD 2017
224FULL TURNKEY TO BUILD CIVIL AND FIBER INFRASTRUCTURE WORK AT SRI
KEMBANGANCIVIL AND FIBER PULLING 495,180.00 TIME DOT COM BERHAD 2017
225FULL TURNKEY TO BUILD CIVIL AND FIBER INFRASTRUCTURE WORK FOR DESA PARK
CITY MAN PROJECTCIVIL AND FIBER PULLING 282,108.92 TIME DOT COM BERHAD 2017
226 COVERAGE: AS-BUILD : FIBER AND CIVIL INFRASTRUCTURE WORK FOR KIPARK MAN CIVIL AND FIBER PULLING 171,592.80 TIME DOT COM BERHAD 2017
227SO DRIVEN (DIGI): OVERHEAD INFRA AND FIBER PULLING FOR DIGI DONG RESILIENCY
TOWN AREACIVIL AND FIBER PULLING 56,474.02 TIME DOT COM BERHAD 2017
228SERVICE ORDER: PROPOSED FIBER INFRASTRUCTURE FOR TNB PMU PROJECT RAUB
SITE-PERMANENT SOLUTIONCIVIL AND FIBER PULLING 98,985.61 TIME DOT COM BERHAD 2017
229SERVICE ORDER: PROPOSED FIBER INFRASTRUCTURE WORK AT TNB PMU BENTONG,
PAHANGCIVIL AND FIBER PULLING 54,504.59 TIME DOT COM BERHAD 2017
230EPCC OF NGDS TO BUKIT RAJA FL STAGE 1/16, BUKIT RAJA PRIME INDUSTRIAL PARK
KLANG.
ENGINEERING, PROCUREMENT, CONSTRUCTION
AND COMMISSIONING OF NPS 4 STEEL PIPES -36M240,000.00 GAS MALAYSIA BERHAD 2017
231EPCC OF NGDS TO SITIAWAN FL STAGE 1/16, KAMPUNG ACHEH INDUSTRIAL ESTATE,
SITIAWAN, PERAK.
ENGINEERING, PROCUREMENT, CONSTRUCTION
AND COMMISSIONING OF NPS 8 - 192M, NPS 6 -
408M AND NPS 4 - 48M STEEL PIPES
428,000.00 GAS MALAYSIA BERHAD 2017
NO PROJECT TITLE DESCRIPTIONS VALUE (RM) OWNER / CLIENT YEAR
232EPCC OF NGDS TO GEBENG FL STAGE 2/17 GEBENG INDUSTRIAL AREA, KUANTAN,
PAHANG DARUL MAKMUR.
ENGINEERING, PROCUREMENT, CONSTRUCTION
AND COMMISSIONING OF NPS 12 - 300M, NPS 8 -
2,688M AND NPS 6 - 12M STEEL PIPES
1,830,000.00 GAS MALAYSIA BERHAD 2017
233 KERJA- KERJA PMU 132/33KV BERANANG ICT (2x90MVA) SELANGOR TO SUPPLY, DELIVER, INSTALL, TEST AND
COMMISIONNING 201,135.00
PEMBINAAN TERASMAJU
SDN BHD 2017
234 KERJA- KERJA PMU 132/33KV NEW TELUK INTAN PERAK TO SUPPLY, DELIVER, INSTALL, TEST AND
COMMISIONNING 420,555.00
PEMBINAAN TERASMAJU
SDN BHD 2017
235SUPPLY AND DELIVERY OF SHUNT CAPACITOR BANK DAMPING REACTOR TO ASSET
MAINTENANCE DEPARTMENT, TNB TRANSMISSIO AS STRATEGIC SPARES
SUPPLY OF THREE (3) UNITS OF 132kV 30MVAR
SHUNT CAPACITOR BANK DAMPING REACTOR
(0.5%) , THREE UNITS OF 132kV 30MVAR SHUNT
CAPACITOR BANK DAMPING REACTOR (6.0%),
THREE (3) UNITS OF 132kV 60 MVAR SHUNT
CAPACITOR BANK DAMPING REACTOR (0.5%),
THREE (3) UNITS OF 132kV 60MVAR SHUNT
CAPACITOR DAMPING REACTOR (6.0%) TO ASSET
MAINTENANCE DEPARTMENT, TNB TRANSMISSION
AS STRATEGIC SPARES
1,220,000.00 TRANSPRO SDN BHD 2017
236SUPPLY OF 275kV SURGE ARRESTER FOR ASSET MAINTENANCE, TRANSMISSION
DIVISION, TNB
SUPPLY AND DELIVERY OF 90 UNITS 275kV SURGE
ARRESTER 910,000.00 TRANSPRO SDN BHD 2017
237 EPCC OF NGDS TO KAMUNTING FL STAGE 2/17, TAIPING, PERAK DARUL RIDZUAN
ENGINEERING, PROCUREMENT, CONSTRUCTION
AND COMMISSIONING OF NPS 8 - 240M, NPS 6 -
24M STEEL PIPES
347,000.00 GAS MALAYSIA BERHAD 2018
238EPCC OF NGDS TO PULAU INDAH FL STAGE 3/17, PULAUN INDAH INDUSTRIAL PARK
(PHASE 2A), KLANG, SELANGOR DARUL EHSAN.
ENGINEERING, PROCUREMENT, CONSTRUCTION
AND COMMISSIONING OF NPS 8 - 228M, NPS 4 -
24M STEEL PIPES
286,000.00 GAS MALAYSIA BERHAD 2018
239 KERJA- KERJA PMU 132/33KV BATU RAKIT EXTENSION (1x45MVA)TO SUPPLY, DELIVER, INSTALL, TEST AND
COMMISIONNING 182,850.00
PEMBINAAN TERASMAJU
SDN BHD 2018
240EPCC OF NGDS TO SENAWANG FL STAGE 1/17, SENAWANG INDUSTRIAL AREA,
SENAWANG, NEGERI SEMBILAN DARUL KHUSUS.
ENGINEERING, PROCUREMENT, CONSTRUCTION
AND COMMISSIONING OF NPS 4 - 24M STEEL PIPES239,000.00 GAS MALAYSIA BERHAD 2018
241EPCC OF NGDS TO BUKIT RAJA FL STAGE 1/17, BUKIT RAJA PRIME INDUSTRIAL PARK,
BUKIT RAJA, SELANGOR DARUL EHSAN.
ENGINEERING, PROCUREMENT, CONSTRUCTION
AND COMMISSIONING OF NPS 6 - 504M,NPS 4 -
36M STEEL PIPES
319,500.00 GAS MALAYSIA BERHAD 2018
242CIVIL AND PULLING FOR UMOBILE HUTAN MELINTANG (MELI), TAMAN DESA
MELINTANG BARU FASA LI, PERAKCIVIL AND FIBER PULLING 29,518.08 TIME DOT COM BERHAD 2018
243 CIVIL AND PULLING FOR UMOBILEPULAU JUAR, PERAK CIVIL AND FIBER PULLING 13,713.82 TIME DOT COM BERHAD 2018
NO PROJECT TITLE DESCRIPTIONS VALUE (RM) OWNER / CLIENT YEAR
244 CIVIL AND PULLING FOR UMOBILE SLIM RIVER EXIT (PBNS) CIVIL AND FIBER PULLING 170,053.25 TIME DOT COM BERHAD 2018
245 CIVIL AND PULLING FOR UMOBILE KOTA SETIA (KTST)) CIVIL AND FIBER PULLING 81,911.31 TIME DOT COM BERHAD 2018
246 CIVIL AND PULLING FOR UMOBILE KEM PLKN SUNGKAI (KPSK) SUNGKAI, PERAK. CIVIL AND FIBER PULLING 33,829.74 TIME DOT COM BERHAD 2018
247FIBER PULLING (550M) FOR ATELIER CONSTRUCTION SDN BHD AT SHELL STATION,
HENTIAN RTC GOPENG MUKIM SIMPANG PULAI, PERAKCIVIL AND FIBER PULLING 13,148.17 TIME DOT COM BERHAD 2019
248FIBER PULLING (260M) FOR ATELIER CONSTRUCTION SDN BHD AT SHELL STATION,
HENTIAN ALOR PONGSU PERAK.CIVIL AND FIBER PULLING 10,277.17 TIME DOT COM BERHAD 2019
249(BBB 90964) CADANGAN MSVT BAGI MENGATASI ISU FEEDER PANJANG & NTL
ELEMENT PADA PMU SSWW (F05) SEBANYAK 0.6mw (PMU SSW 11kV, TNB BANGI)
TO LAY 2 WAY AND 3 WAY 160MM HDPE PN10 BY
HDD METHOD 700,000.00 MUTU NUSANTARA / TNB 2019
250
INSTALLATION, TESTING AND COMMISIONING OF 33KV ALUMINIUM XLPE SINGLE
CORE UNDERGROUND CABLES, UNDERGROUND AND ACCESSORIES FROM PMU KOTA
DAMANSARA TO PPU TROPICANA 2 FOR TNB DISTRIBUTION SELANGOR
TO SUPPLY HDD MACHINE, PILOTING, REAMING
AND PULLING 4 WAY HDPE 6" AND WAY 4"1,200,000.00 MUTU NUSANTARA / TNB 2019
251
KERJA-KERJA MEMBAIKPULIH, MENGUJI DAN MEMULATUGAS PENGECAS MODEL 110
TPR 50 BUATAN SAFT NIFE DI PENCAWANG MASUK UTAMA BATU GAJAH (BGJH)
275kV DIBAWAH JAGAAN UNIT PERLINDUNGAN DAN AUTOMASI JABATAN
SENGARAAN GRID UTARA (SUBZONE - IPOH)
REFURBISH CHARGER 55,000.00TENAGA NASIONAL
BERHAD2019
252PEMBEKALAN PERALATAN PENCAWANG DI PMU 75/132KV NATIONAL UNIVERSITY
(NUNI) DAN PMU 275KV SERDANG (SRDG)MATERIAL SUPPLY 128,220.00
TENAGA NASIONAL
BERHAD2019
253
KERJA-KERJA MEMBAIKPULIH, MENGUJI DAN MEMULATUGAS PENGECAS BATERI
BANK DI PENCAWANG MASUK UTAMA BINTANG (BTNG) 132kV DIBAWAH JAGAAN
UNIT PERLINDUNGAN DAN AUTOMASI JABATAN SENGARAAN GRID UTARA (SUBZONE
- IPOH)
REFURBISH DC CHARGER 48,000.00TENAGA NASIONAL
BERHAD2019
254 KERJA- KERJA PMU 132/33KV BERANANG ICT (2x90MVA) SELANGOR TO SUPPLY, DELIVER, INSTALL, TEST AND
COMMISIONNING 201,135.00
PEMBINAAN TERASMAJU
SDN BHD 2019
255MENAIKTARAF LALUAN FT60 DARI DAMAR LAUT KE CHANGKAT JERING (PAKAEJ 2A),
PERAK CIVIL AND FIBER PULLING 220,682.37 TUMPUAN BINA SDN BHD 2019
256DISTRIBUTION CABLE (D/SIDE) FROM FXC OUTDOOR CABINET TO OUTDOOR
PEDESTAL TROPICANA AMAN CHERIA, SLEANGOR.CIVIL AND FIBER PULLING 148,000.00 TIME DOT COM BERHAD 2019
NO PROJECT TITLE DESCRIPTIONS VALUE (RM) OWNER / CLIENT YEAR
257MENAIKTARAF LALUAN FT60 DARI DAMAR LAUT KE CHANGKAT JERING (PAKEJ 1:
CH0-CH10400)CIVIL AND FIBER PULLING 340,579.97 MEGA SASA SDN BHD ON GOING
258
MEREKA BENTUK DAN MEMBANGUN INFRASTRUKTUR PUSAT DATA SERTA
MEMBEKAL, MEMASANG, MENGUJI, MENTAULIAH DAN MENYELENGGARA
PERALATAN INFRASTRUKTUR PUSAT DATA DI BANGUNAN BUSINESS CENTRE II,
KULIM HI-TECH PARK, KEDAH
MEREKA BENTUK DAN MEMBANGUN
INFRASTRUKTUR PUSAT DATA44,838,000.00
UNIT PERMODENAN
TADBIRAN DAN
PERANCANGAN
PENGURUSAN MALAYSIA
(MAMPU)
ONGOING
(MAINTENANCE UP
TO 2020
259EPCC OF NGDS TO BESTARI JAYA FL STAGE 1/17 (REINFORCEMENT), BESTARI JAYA,
SELANGOR DARUL EHSAN
ENGINEERING, PROCUREMENT, CONSTRUCTION
AND COMMISSIONING OF NPS 16 - 8,400M, NPS 8 -
240M STEEL PIPES
4,470,000.00 GAS MALAYSIA BERHAD ON GOING
260EPCC OF NGDS TO KLUANG FL STAGE 2/17 (REINFORCEMENT), KLUANG, JOHOR
DARUL TAKZIM
ENGINEERING, PROCUREMENT, CONSTRUCTION
AND COMMISSIONING OF NPS 12 - 15,480M, NPS
8 - 24M, NPS 6 - 60M STEEL PIPES
8,298,000.00 GAS MALAYSIA BERHAD ON GOING
261FULL TURNKEY FOR UNDERGROUND CIVIL & FIBRE INFRASTRUCTURE WORK FROM
BUKIT KERAYONG TO SIMPANG ASSAM JAWA CIVIL AND FIBER PULLING 2,330,000.00 TIME DOT COM BERHAD ON GOING
262FULLY TURNKEY FOR NEW CIVIL & FIBER INFRASTRUCTURE FOR RAWANG MAN PH3
AND PANGSAURI SERI CEMPAKA (USP CLAWBACK PROJECT 2017)CIVIL AND FIBER PULLING 1,052,000.00 TIME DOT COM BERHAD
AWARDED,
ENGINEERING STAGE
263PROJECT MASS RAPID TRANSIT LALUAN 2: SUNGAI BULOH-SERDANG-PUTRAJAYA
(SPP) REINSTATEMENT OF GAS PIPELINES FOR KAMPUNG BARU NORTH STATION REINSTATEMENT OF GAS PIPELINES 1,898,000.00
MMC GAMUDA KVMRT (T)
SDN BHD
AWARDED,
ENGINEERING STAGE
264
NEW FIBER PULLING AT PLUS HIGHWAY (AYER KEROH TO SEREMBAN)
1. AYER KEROH - PEDAS LINGGI (MULTIPLE LOCATIONS)
2.PEDAS LINGGI - SENAWANG (END TO END)
FIBER PULLING 245,000.00 TIME DOT COM BERHAD ON GOING
265
ENGINEERING, PROCUREMENT, CONSTRUCTION AND COMMISSIONING OF
NATURAL GAS DISTRIBUTION SYSTEM TO BANDAR SULTAN SULAIMAN FL STAGE
1/20, BANDAR SULTAN SULAIMAN INDUSTRIAL AREA, KLANG SELANGOR DARUL
EHSAN
ENGINEERING, PROCUREMENT, CONSTRUCTION
AND COMMISSIONING OF NPS 6 STEEL PIPES -
396M AND NPS 4 STEEL PIPES - 24M
297,500.00 GAS MALAYSIA BERHAD AWARDED,
ENGINEERING STAGE
266EPCC OF NGDS TO NILAI DL STAGE 1/20, NILAI INDUSTRIAL AREA, NILAI, NEGERI
SEMBILAN DARUL KHUSUS
ENGINEERING, PROCUREMENT, CONSTRUCTION
AND COMMISSIONING OF NPS 4 STEEL PIPES -80M
PE 63MM
137,500.00 GAS MALAYSIA BERHAD AWARDED,
ENGINEERING STAGE
267EPCC OF NGDS TO TONGKANG PECHAH FL STAGE 1/20, TONGKANG PECHAH
INDUSTRIAL ESTATE JOHOR DARUL TAKZIM
ENGINEERING, PROCUREMENT, CONSTRUCTION
AND COMMISSIONING OF NPS 4 STEEL PIPES -12M
AND NPS 6 STEEL PIPES 228M
277,500.00 GAS MALAYSIA BERHAD AWARDED,
ENGINEERING STAGE
268EPCC OF NGDS TO TANGJUNG LANGSAT FL STAGE 2/20, TANJUNG LANGSAT
INDUSTRIAL COMPLEX, JOHOR DARUL TAKZIM
ENGINEERING, PROCUREMENT, CONSTRUCTION
AND COMMISSIONING OF NPS 4 STEEL PIPES 84M137,000.00 GAS MALAYSIA BERHAD
AWARDED, PENDING
LETTER OF AWARD
269 MANAGE SERVICES (IT OUTSOURCING) IT OUTSOURCING FOR TOUCH 'N GO SDN BHD 2,247,000.00 TOUCH 'N GO SDN BHD
SHORTLISTED,
PENDING BOARD
COMMITTEE FOR
AWARD
NO PROJECT TITLE DESCRIPTIONS VALUE (RM) OWNER / CLIENT YEAR
270MEREKABENTUK, MEMBANGUN, MEMBEKAL, MEMASANG, MENGKONFIGURASI,
MENGUJI DAN MENTAULIAH PUSAT DATA BERSEPADU KEMENTERIAN PERTAHANANICT AND MAINTENANCE FOR MINDEF 37,800,000.00
KEMENTERIAN
PERTAHANAN MALAYSIA
SHORTLISTED,
PENDING BOARD
COMMITTEE FOR
AWARD
271
MEREKA BENTUK , MEMBEKAL, MENGHANTAR, MEMASANG, MENGKONFIGURASI,
MENGUJI DAN MENTAULIAH PUSAT DATA MELIBATKAN SISTEM RANGKAIAN SERTA
KESELAMATAN, PERALATAN DAN PERISIAN TEKNOLOGI MAKLUMAT DAN
KOMUNIKASI (ICT) SERTA KHIDMAT SOKONGAN BAGI PENGGANTIAN PERALATAN
ICT DAN PUSAT PEMULIHAN BENCANA (DRC) APLIKASI KRITIKAL AGENSI
ICT FOR MAMPU CLOUD 41,300,000.13
UNIT PERMODENAN
TADBIRAN DAN
PERANCANGAN
PENGURUSAN MALAYSIA
(MAMPU)
SHORTLISTED,
PENDING BOARD
COMMITTEE FOR
AWARD
272
DESIGN, SUPPLY, INSTALL, TESTING, COMMISSIONING AND IMPLEMENTATION OF
AIRPORT
COLLABORATIVE DECISION MAKING (A-CDM) INCLUDING COMPREHENSIVE
MAINTENANCE FOR
MALAYSIA AIRPORTS (SEPANG) SDN. BHD.
DESIGN, SUPPLY, INSTALL, TESTING,
COMMISSIONING,
IMPLEMENTATION AND MAINTENANCE
20,600,000.00MALAYSIA AIRPORTS
(SEPANG) SDN BHD
SHORTLISTED,
PENDING BOARD
COMMITTEE FOR
AWARD
273CONTRACT FOR THE SUPPLY AND DELIVERY OF 3 LAYER PE COATED (3 LPE) STEEL
LINE PIPE TO GMB
SUPPLY AND DELIVERY OF 3 LAYER PE COATED (3
LPE) STEEL LINE PIPE TO GMB42,000,000.00 GAS MALAYSIA BERHAD
PRE- QUALIFICATION
STAGE
274CONTRCT FOR ENTENDED UNINTERRUPTABLE POWER SUPPLY (UPS) AND
IMPLEMENTATION OF SMART RACK SOLUTION FOR GAS MALAYSIA EXTENDED UPS AND SUPPLY SMART RACK 1,229,430.40 GAS MALAYSIA BERHAD TENDERING STAGE
275EPCC OF NGDS TO ENSTEK FL STAGE 1/20, TECHPARK 2 @ ENSTEK, NEGERI
SEMBILAN DARUL KHUSUS
ENGINEERING, PROCUREMENT, CONSTRUCTION
AND COMMISSIONING OF NPS 4 STEEL PIPES -
132M AND NPS 6 STEEL PIPES- 324M
406,440.00 GAS MALAYSIA BERHAD TENDERING STAGE
276EPCC OF NGDS TO PASIR GUDANG FL STAGE 1/20, PASIR GUDANG INDUSTRIAL
AREA, PASIR GUDANG JOHOR DARUL TAKZIM
ENGINEERING, PROCUREMENT, CONSTRUCTION
AND COMMISSIONING OF NPS 4 STEEL PIPES -12M 296,000.00 GAS MALAYSIA BERHAD TENDERING STAGE