Upload
dana-rotaru
View
218
Download
0
Embed Size (px)
Citation preview
7/29/2019 FullPaper Simpozion Rotaru Elena Daniela FINAL ENGLEZA 2003
http://slidepdf.com/reader/full/fullpaper-simpozion-rotaru-elena-daniela-final-engleza-2003 1/7
THE IMPROVEMENT OF REDIU RIVERBED, UPSTREAM OF THE
TARGU FRUMOS CITY, IASI COUNTY
Elena Daniela ROTARU
University of Agronomic Sciences and Veterinary Medicine of Bucharest, 59 Mărăşti Blvd,
District 1, 011464, Bucharest, Romania, Phone: +4021.318.25.64, Fax: + 4021.318.25.67,
Email: [email protected],
Advisor Professor Augustina TRONAC
University of Agronomic Sciences and Veterinary Medicine of Bucharest, 59 Mărăşti Blvd,
District 1, 011464, Bucharest, Romania, Phone: +4021.318.25.64, Fax: + 4021.318.25.67,Email: [email protected]
Corresponding author email: elenadaniela.rotaru@gmail.
Abstract
The estabilshment’s goal is to to provide flood defense and to protect the objectives from the south side of
Targu Frumos. In this article I approach the issues of the optimal choice for an ideal projection. This thing
was possible by interpreting two solutions, using multi-criteria analysis.
Also I analyse the aspect of the environmental impact during the execution of the work, as well as during
the exploatation.
After calculations, the second way of projection is considered to be the optimal, thus solving the flooding
problem from the south area of the city.
Key words: defence, flood, riverbed, environment.
THE ESTABILSHMENT’S GOAL
The estabilshment’s goal is to to provide flood
defense and to protect the objectives from the
south side of Targu Frumos. houses,greenhouses, land, rail, by increasing the
transport capacity of the river for transit Rediuflood flows.
NATURAL CONDITIONS,
CURRENT SITUATION AND
PROPOSED SOLUTION
2.1 The River flows from the hill Breazu,
flowing through the valley The, along the road
Rediu that connects Iasi city The Thecommune. The River is affluent of River
Bahluiet and is part of a complex scheme of arrangement river basin Bahlui (river basin
Prut), whose main purpose is the protectionagainstOfloodsOof OcityOIasi.
The river has a total length of 14 km and a river basin confluent zone of 42 km.
Current situation is as follows:
Fig. 1. Current situation
The current situation is as follows:Dam accumulation shows a gap of about 80 m
located between the bottom and left side drain.Also there is subsidence of fillings about 70
cm. Bottom emptying (monk + box) are
destroyedOinO proportionOof O90%.
The branch surface (overflow + channel + sink)are destroyed 50%
7/29/2019 FullPaper Simpozion Rotaru Elena Daniela FINAL ENGLEZA 2003
http://slidepdf.com/reader/full/fullpaper-simpozion-rotaru-elena-daniela-final-engleza-2003 2/7
On the left bank is Pascani railroad - Podu
Iloaiei. Currently, the storage basin is anextensive in progress social project that
includes a stadium and a natural park with playgrounds for children.
As a result of the accumulation of non-
permanent shutdown in recent years have madeworks unsilting and calibration of bed
downstream of the dam, achieving a channel
width of approximately 10m based on providing sufficient transmission capacity for a
transit ensuring flow of 10%. Works werecarried out and unsilting downstream of the
confluence with the River Bahlueţ. (Consitrans,
2009 )
Fig.2 Current situation
Taking into account this accumulation is
considered rehabilitation works, includingunsilting basin involves high costs, low
efficiency.Therefore, the proposed work area fitting Rediu
riverbed in Tg. Frumos to defend against
flooding will be work-damming recalibration of
bed to make possible the safe transit of largewater Oflows.Considering the equipment assets, works to be
performed will be included in Class IV of
importance, according to STAS 4273/83, for the flow calculation is according to STAS
4068/88 Q5% = 49mc / sThe arrangement works Rediu stream
The situation of the stream Rediu aranjament
looksOasOfollows:- earth-dam upstream (L = 3000ml) is
uncalibratedO bed,Oundeveloped.- earth-dam downstream, to bridge DN28 (L =
350ml): bed was enlarged with a base width of
about 10 m, and the resulting material was
systematized on the left bank, in the form of dikes with slopes of 1: 1 ÷ 1: 1.5 and canopy
cover width of about 3 m, poorly compacted.-DN28-bridge downstream to the confluence
with the Bahlui river (L = 200ml), the bed has
reduced transport capacity. On the left side is adefense dyke a little high, beyond the waters.
Such an area is frequently flooded homes.
A.RecalibratingOtheO bedThe technical solution adopted for this work
takes into account the morphologicalcharacteristics of Rediu riverbed and
geotechnical characteristics of the materials
from the riverbed banks. It is proposedrecalibration bed, ensuring a riverbed width of
10m based on 1:2 slopes. Material extractedfrom the the bed will be used for filling in the
body of defense dykes.
Fig. no. 1 Dyke section
B.Dams defense. Are proposed defence dykes
and for the existing ones, to bring thecoresponding share for the class IV, plus a
guard importance of 0.3-0.5 m.
Defense dams are proposed and existing dams
bring appropriate share class IV, plus a guardimportance of 0.3-0.5 m This will ensure thetransit flow to the probability of exceeding the
5% according to class designed.
Considering that: right slope is steep andtherefore extends and expands the area on the
left bank; There is an ongoing project to bypass belt town on the right bank of the stream;
During periods of high water, by overcoming
the right bank, floods cause damageon aunproductive land; Considered justified
realization a defence dam on the left bank .The dam will be done in extending bank will
7/29/2019 FullPaper Simpozion Rotaru Elena Daniela FINAL ENGLEZA 2003
http://slidepdf.com/reader/full/fullpaper-simpozion-rotaru-elena-daniela-final-engleza-2003 3/7
take the canopy cover width of 3.5 m, and
slopes of 1:2 slopes.
To protect the dyke from the bank erosion,
preventing gullyng, the wet parament will be protected with a erosion mat set at the foot of
slope in a spur plainconcrete with dimension
0.4x0.8m.The parameter from the dam site will be
covered with a layer 20 cm thick topsoil to begrassed.
For the filling of the dam body will use
material from the riverbed and in additionrecalibration of the old dam front.
Fig. no. 2 Cross section of the recalibrated bed
UndercrossingFor pluvial water discharges inside dammed,
the project includes execution of 3
undercrossing by dyke defence body They willtake over the channel waters collected from the
dyke upstream slope protection and river willdownload in Rediu river. Undercrossings will
be placed into sections with low allowances to
ensure gravity flow gutters.Undercrossings will be equip with planar gates
upstream and downstream with inverted flapwhich is closed under the effect of water
pressure increase in the river.
PROPOSED WORKS ARE:Variant 1
Lenght dyke = 1040 ml. The defence dyke is
closed downstream (near confluence) in therailway ambankement and upstream in higher
terrance on a left bank, defending just thestadium and the park area ( project in
execution)Recalibration work will be done on a bed
lengthOof O850Oml.
Effect is thus removed from the flood an areaof approximately 9ha.
VARIANT 2Lenght dyke = 1650 ml. The defence dyke is
closed downstream (near confluence) in the
railway ambankement and upstream in existingdischarge channel defending the the stadium
and the park area ( project in execution) and an
additional area with an area of approximately11ha.
In this area it is possible to develop the city incomplete safety in terms of flooding.
Work will be done on a recalibration of bed
length 1600ml. Effect is thus removed from theflood a total area of approx. 20ha.
(Consitrans, 2009)
BACKGROUND BY CALCULATION
A.HydraulicOcalculations
For the rest of the Rediu riverbed whith for we propose recalibration I realized curve
remuneration calculation used 20 sectors (P1 -
P17 and intersections with to DN 280 DN 28)
for flows with insurance 5%, 2% and 1% twovariants: natural and regime arrangedcorresponding the current situation and the
situation that will occur after the execution of
the work.Has been developed calculation of study river
sector to determine control flow and todetermine appropriate levels of water flow
calculation and spectrum free surface velocity
curve. Hydraulic calculations are suportedsurveyings in this proiect.
Hydraulic calculations were performed withHEC-RAS computer program. This program
determines the water level applying uniform
motion energy equation by iterative procedurecalled the standard step method from a cross
sectionOtoOanother.Hydraulic calculation was performed assuming
both natural regime, thus establishing flood
flow curve by providing 5%, as well asarranged under unsilting considering the
riverbed and dikes designed. Given the currentconfiguration of the riverbed and valley and
earthworks required compensation of fitting
was accepted hypothesis that in some sections,water flooding the lands bordering the right
bank than on a small area, but without reachingthe road and houses. (Rotaru E.D., 2011)
B.StabilityOcalculations
For the cross section defence dike on the Rediuriver , I realized stability calculations with the
GeoSlope Studio program analysing methods:
Spencer, Fellenius, Jambu, Morgenstern-Priceand I chose values resulting Morgenstern-Price
method are the lowest. (GeoStudio, 2007)
7/29/2019 FullPaper Simpozion Rotaru Elena Daniela FINAL ENGLEZA 2003
http://slidepdf.com/reader/full/fullpaper-simpozion-rotaru-elena-daniela-final-engleza-2003 4/7
7/29/2019 FullPaper Simpozion Rotaru Elena Daniela FINAL ENGLEZA 2003
http://slidepdf.com/reader/full/fullpaper-simpozion-rotaru-elena-daniela-final-engleza-2003 5/7
microclimate, vegetation, wildlife, and
landscape.In principle the regularization works and flood
defense have a positive impact ontheenvironment.
Regarding the negative impact on the
environment, the most influence occurs duringexecutionOof Oworks.
During exploitation the negative environmentalimpact of work decreases and tends to a normal
situation that increases positive weight to
negative influences. The proposed works do notgenerate waste and require no materials leading
to environmental pollution.The project analyzes constructive solutions
which harmoniously frames with the landscape,
being used mostly natural materials.
Defense embankments slopes unprotected bydefensive works will be grassed. Uponcompletion of the work, the contractor will
dismantle buildings and facilities for the
organization of their site.On this occasion the arrangements will be
needed to playback the previous use of the landon which objects were site organization.
It will remove all their effects and potential
sources of pollution of land (production bases,repair shops and maintenance equipment, fuel
depots).On the occasion of the dissolution of the site,
the Contractor shall also ensure site cleaning
from the land requirement site organization.(Consitrans, 2009)
MULTICRITERIA ANALYSIS
Multicriteria analysis method allows comparingmultiple versions of a project solutions, based
on criteria relevant and representative to that project.
The purpose of the method consists in selecting
and recommending alternative which compliesas possible rigorous and complete
requirements.For multi-criteria analysis for the optimal
choice of regularization workscan be consider
the following criteria and sub-criteria:a) C1 - economic criteria:
- C1.1 - cost of investment and operation and
maintenance costs updated for a period of 20years;
- C1.2 - the cost of damage caused by erosion,
collapse of banks, flooding (affecting
households, land, crops etc.).- C1.3 - related costs: lower revenues from
tourism, sport, recreation b) C2 - Social criteria:
- C2.1 - aesthetic landscape;
- C2.2 - Protection of riparian waters;- C2.3 - recreation, tourism, sport,
- C2.4-impaired population in the area(restricted, circulation, stress, including the
execution of works);
- C2.4 - quality of water used by riparianc) C3 - ecological criteria:
- C3.1 - overall impact index due to spatialsolutions, IGSA;
- C3.2 - index overall impact due to
constructive solutions, IGSC;
- C3.3 - degree of impairment of ecosystems,namely preservation, conservation,transformation, destruction;
d) C4 - compliance criteria restrictions:
- C4.1 - compliance with urban river basin andriver basin management plan;
- C4.2 - approved areas "accepted" as the floodwaters;
- C4.3 - affecting protected areas
- C4.4 - public services affecting water supply,sewage, landfills.
Criteria and sub-criteria chosen are those for which the expected spatial differences between
variants considered.
For multi-criteria analysis of the optimal choicefor the regularization of Rediu stream, it
considers the following criteria and sub-criteria:
a) C1 - economic criteria:
- C1.1 - cost of investment and operation andmaintenance costs updated for a period of 20
years;- C1.2 - the cost of damage caused by erosion,
collapse of banks, flooding (affecting
households, land, crops etc.) For a period of 20years;
b) C2 - Social criteria:- C2.1 - aesthetic landscape;
- C2.2 - areas removed from the effect of
flooding;c) C3 - ecological criteria:
- C3.3 - degree of impairment of ecosystems,
namely preservation, conservation,transformation, destruction;
d) C4 - compliance criteria restrictions:
7/29/2019 FullPaper Simpozion Rotaru Elena Daniela FINAL ENGLEZA 2003
http://slidepdf.com/reader/full/fullpaper-simpozion-rotaru-elena-daniela-final-engleza-2003 6/7
- C4.1 - compliance with urban river basin and
river basin management plan. Taking into account three types of calculation:
VARIANT 1Long dam defense = 1040ml.
unsilting and reshaping riverbed wors L = 850
ml. Effect is thus removed from the flood anarea about 9ha.
VARIANT 2Long dam defense = 1650ml. unsilting and
reshaping riverbed wors L = 1600ml. Effect is
thus removed from the flood a total area of approx. 20ha.
VARIANT 3 = option 0 - no work.The results of the 3 different scores obtained
are presented in the following table:
According to the above table, suitable for
multi-criteria analysis (by weight criteria) thevariant that has obtained the highest weighted
scoreOisOversionO2.
Variant 3 (variant "zero" - no investment) cannot be taken into account because, although
ecologically is the most advantageouseconomic and social factors are severely
affected. So by floods that occur, if they do not
perform anyplanning work on the streamRediu, a number of households are directly
affected.
7/29/2019 FullPaper Simpozion Rotaru Elena Daniela FINAL ENGLEZA 2003
http://slidepdf.com/reader/full/fullpaper-simpozion-rotaru-elena-daniela-final-engleza-2003 7/7
The damages justifies realization of regularization works and flood protection.
Option 2 is the most advantageous socially andenvironmentally.
From the economic perspective, the investmentneeded to carry out the works in version 2 is
higher than in option 1, but the increase is not
directly proportional to the surface removedfrom the flood effect. (At a 30% increase of the
investment, the protected area is increased with100%). This means that from a social
perspective, the city will have secured an area
of land (owned by municipality) that canexpand public building objectives.
Variant 2, although ecologically, has somedisadvantages, especially in the execution of
works riverbed, thus directly affecting the
ecosystem of the area, is recommended for implementation.
Analysis method multicriteria decision clearlyshows that exclusive consideration of the
investment cost criterion is disadvantageous to
all general and local requirements and interests.It follows from the above that the project in
Variant 2 most responsive requirements
imposed by multi-criteria analysis and has theleast impact on the environment.
(Rotaru E.D., 2011)
CONCLUSIONS
Fitting Rediu riverbed upstream of Tg.
Beautiful, Iasi county for defense against floodsin the south of the objectives of Tg. Beautiful
by increasing the transport capacity of the river for transit Rediu flood flows, after studying
design alternatives, we chose as the best option
variant 2 involving defense breakwater length =1650ml.
The defense dam closes, downstream, and
upstream of the railway embankment in theexisting discharge channel, defending the park
and stadium but also an additional area with asurface of approx. 11 hectares. In this area it is
possible to develop the city in complete safety
from the point of view of the defense against
flooding. Work will be done on a recalibrationof bed length 1600ml. Effect is removed fromthe flood a total area of approx. 20 ha.
The proposed works will be carried out with
minimum employment of private land. Riparianresidents on whose property is to run defense
works are directly interested in their achievement, being the first to suffer when
floods.
REFERENCES
Consitrans , 2009. Feasibility Study – The improvementof Rediu riverbed, upstream of the , Targu frumos city,
Iasi County, p 3-28.
Daniela Elena Rotaru, Project license - The improvementof Rediu riverbed, upstream of the , Targu frumos city,
Iasi County, p 46-70.
Chen G.K, Zhu D.Y. , Fee C.F., Qian O.H., 2007. Conciscalculation algorithm safety factor using the method
Morgenstern price - Canadian Geotechnical JournalGeoStudio, 2007. Product details Slope / W software for
calculating the safety factor for soil and rocks.