81
Full Business Case The Modernisation and Re-design of Primary and Community Health and Social Care in Mid Argyll Version 22 28 April 2003

Full Business Case The Modernisation and Re-design of

  • Upload
    others

  • View
    2

  • Download
    0

Embed Size (px)

Citation preview

Full Business Case

The Modernisation and Re-design of Primary and Community Health and Social Care in Mid Argyll

Version 22

28 April 2003

Contents

Contents Page No

1 Executive Summary 1

2 Strategic Context 8

3 The Outline Business Case 20

4 The Preferred Solution 22

5 The Public Sector Comparator 27

6 The PPP/PFI Procurement Process 30

7 The Appraisal Process 36

8 Summary of Contract Structure 52

9 Accounting Treatment 55

10 Project Management Arrangements 55

11 Benefits Assessment and Benefits Realisation Plan 58

12 Risk Management Strategy 62

13 Post Project Evaluation Plan 70

14 Information Management and Technology Strategy 71

15 Equipment 74

16 Personnel Issues 76

17 Conclusion 78

18 Specific Statements 78

19 Financial Appendices

Page 1 of 78

1 Executive Summary

1.1 Background & objectives of the project

1.2 The Modernisation and Redesign of Primary and Community Health and

Social Care Services in Mid Argyll is a project that is responding to local

health and social needs. It proposes plans for service change that will enable

appropriate and sustainable health and social care service to be provided for

the local community of Mid Argyll for the next 30 years and beyond.

1.3 The purpose of the project is to enable and facilitate fundamental change in the

way in which health and social care is delivered to the people of Mid Argyll.

The underlying aim is to redesign services from a patient‟s point of view.

Health and social care services will be shaped around the needs of patients and

clients through the development of partnerships and co-operation between

patients, their carers and families and NHS staff; between the local health and

social care services; between the public sector, voluntary organisations and

private providers to ensure a patient-centred service. Overall, the project aims

to substantially increase services and the amount of care that is delivered

locally. The project will establish this new service model and develop

facilities that can support it effectively.

1.4 The objectives for the project were identified as follows:

To enable the Trust to provide a modern service that integrates primary

care, community health and hospital services and social services.

To focus services on health maintenance and ill health prevention.

To provide accessible services.

To maximise clinical effectiveness through developing new and innovative

models of service delivery and new ways of working that put the patient at

the centre of the service.

To improve the quality of the service available to the local population by

providing modern purpose built facilities.

To enable the Trust to provide an efficient and effective service.

To provide flexibility for future change.

To provide a facility that is acceptable to patients, staff and public.

To provide a contemporary and modern facility, which will support Health

and Social Care services over at least the next 30 years.

1.5 The redesign of services described above and the improvements in service

effectiveness and quality that arise from this redesign simply cannot be

Page 2 of 78

delivered unless the project proceeds. The very poor condition and functional

suitability of the existing Mid Argyll Hospital, which is over 100 years old,

provides a serious constraint on both the continuing provision of existing

services and even more so on the development of improved and new services.

1.6 The Preferred Option

1.7 The preferred option for delivering the new service model is the development

of a single new facility on the site of the existing Mid Argyll Hospital that will

replace:

The existing 100 years old Mid Argyll Hospital and peripheral

PAMs departments i.e. X-Ray, Physiotherapy, Speech and

Language Therapy and Community Dental all of which are in very

poor physical condition.

The Duncuan Care of the Elderly Unit (located approximately 200

metres from the Mid Argyll Hospital

Part of an existing Elderly Dementia Ward in the Argyll & Bute

Hospital. Although this is a relatively small part of the Argyll &

Bute Hospital, it an essential element in the overall strategy for the

closure of this Hospital and the disposal of this large site for which

substantial sale proceeds are expected.

Primary Care – GP and Dental Surgeries in Lochgilphead

1.8 The preferred route for procuring the new facilities is through the

Government‟s Private Public Partnerships/Private Finance Initiative

(PPP/PFI). This approach has been tested against the conventional public

sector procurement route and found to offer better value for money and will

enable significant risks associated with the delivery of the project to be borne

by the private sector partner.

1.9 The Trust followed the European Procurement Regulations Negotiated

Procedure to select a private sector partner who will design, construct, equip,

operate (hard facilities management services) and finance the project. The

partner will comprise a consortium whose members are shown in the table

overleaf.

Page 3 of 78

1.10 Since being identified as the preferred partner the Consortium has worked with

the Trust to develop this FBC and a detailed planning and design solution that

meets the project brief. Throughout this process the consortium has

demonstrated the following strengths and qualities:

Financial and commercial soundness.

Extensive experience of healthcare PFI.

Specific experience of the PFI development of Community

Hospital services.

Understanding of and empathy with the service aspirations of

NHS Argyll and Clyde in relation to this project.

1.11 The design solution developed in collaboration between the Trust and

Canmore Partnership represents an innovative approach to integrating and co-

locating a range of primary care and supporting community hospital based

health and social care services. It will provide the full functional content

specified and meet all key operational policies set out in the project brief. It

will achieve this by exploiting the topography of the site to create a low rise

building that will cluster services in logical groupings and minimise patient

and visitor movement within the building. The scheme provides

approximately 7,000 sq.m of accommodation on two floors.

1.12 The Trust and the Consortium have maintained a close working relationship

with the Argyll and Bute Council as the statutory planning and highways

authority. A formal application for planning consent was submitted on 24

December 2002. Sub sequentially approval of the scheme was delegated to a

sub-group comprising a local planning officer and two local councillor

members of the Planning Committee. The Trust and the Consortium have

worked with the sub-group over the last three months to clarify all the

planning requirements for the scheme. Only two minor issues of access

Consortium Member

Consortium promoter/Bid Coordinator Canmore Partnership

Builder/Contractor Balfour Beatty

Funder/Senior Debt Bank of Ireland plc

Financial Adviser Canmore/Operis Group

Legal Adviser Dundas and Wilson

Architect HLM

Quantity Surveyor Capita Cost Management

M&E Services Engineers DSSR/FES

Structural Engineers Oscar Faber

Facilities Manager Parsons Brinckerhoff

Healthcare/Medical Planner WS Atkins

Equipment Specialist MPM Capita/UME

Page 4 of 78

remain outstanding and the Trust and the Consortium are confident that these

will be resolved shortly and will have no detrimental affect on financial close.

1.13 Since appointment as Preferred Bidder, the Canmore planning and design team

have worked with the Trust‟s Project Team and Departmental User Groups to

develop the preferred design solution. As a result of this extensive work

programme the FBC is based on 1:200 scale drawings and detailed room data

sheets including 1:50 scale room layouts for all key rooms which have been

approved and “signed off” by the Trust.

1.14 Value for money

1.15 Comparison between the Canmore PFI option and the Public Sector

Comparator is shown in the tables below where the Net Present Cost (NPC)

and Equivalent Annual Charge (EAC) are shown for both the 33 year term of

the proposed contract and the 60 year economic life of the building.

Figure 7-11 - NPC analysis

33 year analysis 60 year analysis

Net Present Cost PFI PSC PFI PSC

£’000 £’000 £’000 £’000

NPC of project cashflows 20,185 18,829 21,199 19,499

NPC of retained risk 3,965 5,911 4,805 6,751

Risk-adjusted NPV of project 24,150 24,740 26,004 26,250

Figure 7-12 - EAC analysis

33 year analysis 60 year analysis

Net Present Cost PFI PSC PFI PSC

£’000 £’000 £’000 £’000

EAC of project cashflows 1,325 1,236 1,235 1,136

EAC of retained risk 269 400 280 394

Risk-adjusted EAC of project 1,594 1,636 1,515 1,530

1.16 The analysis shows that the PFI option asset offers both the lowest NPC and

the lowest EAC, and therefore best value for money, over both the contract

period and the economic life of the building.

1.17 The preferred solution (the PFI solution) demonstrates better value for money

than the PSC because, whilst the individual cost elements of the PFI solution

are not significantly cheaper than the Public Sector Comparator equivalents,

the overall quantum and timing of costs, taking into account the significant

amount of risk assumed by the private sector, delivers a better overall package

than a publicly funded route.

Page 5 of 78

1.18 Affordability

1.19 Since the submission of the OBC a number of changes to the scheme have

occurred including:

Additional accommodation to enable the number of GPs to increase

from 6 to 10 and the number of GP trainees from 2 to 3.

Additional treatment rooms to allow for the extension of nurse

practitioner roles.

Additional accommodation for the Scottish Ambulance service to

enable the relocation of Para-medical teams adjacent to the A&E

Department and to enable the garage/workshop to move to more

suitable accommodation more closely linked to the main service

base.

An increase in the size of physio gymnasium to support its use for

progressive rehabilitation and assistance with self care.

Decontamination/Sterilising rooms for dental surgery and podiatry

to comply with emergent SEHD guidance on the decontamination

of surgical instruments.

Minor adjustments to departmental areas as a result of development

of the operational policies post OBC

1.20 These changes have added 1373 square metres of departmental area to the

schedule of accommodation on which the PSC was based. The PSC has been

updated to take account of the changes in the scheme including the additional

capital and revenue costs arising from these changes. It should be noted that

additional costs arising from the additional accommodation for SAS, Social

Services and GPs will be offset by increased rental charges for these parties.

1.21 Further non-service led changes to the PSC have also occurred since

submission of the OBC:

Change of tender price inflation projection from the OBC business

case level (MIPS 325) to current forecast for the start on site period

(MIPS 383). Hence, this will set the PSC costs at a comparable

level with the PPP/PFI cost level.

Update of the Planning Contingency to accurately reflect the risk

profile of the project that has now been established as a result of

developing the FBC.

1.22 The table overleaf shows the overall costs associated with the preferred PPP/PFI

Option and compares it in overall cost terms with the updated PSC and the original

OBC revenue profile. It is important to note that the Trust did not incorporate the

impact of residual interest under land and buildings guidance as part of the original

cost envelope for the project. This incorporates the impact on both core services and

services within the scope of the PFI deal as described in 7.5.

Page 6 of 78

Figure 7-6 – Overall FBC Affordability

Revenue Profile

Capital

Charges /

Unitary

Charge

Capital

Charges

Savings from

Demolitions

Service

Costs

External

Income

Additional

Revenue

OBC (as approved) 1,044 595 (250) 1,389

Updated PSC to MIPS 383 (ref Fig 7-2) 1,717 (106) 631 (441) 1,801

Preferred PPP/PFI Option 1,689 (106) 528 (441) 1,670

The Unitary Charge already includes provision for Hard FM; to avoid double counting the Hard FM costs included in the PSC have

been netted off against service costs (i.e £631k - £103k per the PSC) for the PFI option.

1.23 The conclusions reached from the affordability analysis are that the scheme is

broadly affordable when comparing Canmore‟s tariff against the updated PSC

resource envelope (exclusive of the impact of residual interest). There is some

further scope for improving the affordability position in the likely event that

the agreed senior debt interest rate at financial close is lower than the modelled

rate of 5.3% which included a 0.5% buffer.

1.24 The PPP/PFI Contract

1.25 This project has been progressed primarily using the Standard Form Contract

documentation issued by the NHS Executive as last updated in October 2000

and recommended for use by the Scottish Executive Health Department in

Scottish PFI/PPP projects.

1.26 The duration of the Project Agreement will be divided into two phases:

Construction phase

Operational phase

1.27 The construction phase will last two years during which the a Special Purpose

Company “Project Co”, set up to deliver the project, will build the facility,

procure and install all Group 2 & 3 equipment, fully commission and test the

buildings and equipment to ensure that they are fit for purpose can be brought

into full operational use by the Trust.

1.28 The operational phase will last thirty years and during this period “Project Co”

will make the buildings and equipment available to the Trust for occupation

and use. The “Project Co” will also provide building and engineering

maintenance services (hard facilities management) during this phase but not

soft facilities management services nor equipment maintenance, repair and

replacement which will be provided by the Trust. The Trust will pay a single

unitary payment monthly in arrears from the date of commencement of this

service. The payment will be adjusted to take account of the availability of all

or part of the building and the performance of the Consortium in delivering the

service.

Page 7 of 78

1.29 Timetable to financial close and delivery of the service

1.30 The timetable from approval of the Final Business Case through financial

close to service commencement is set out overleaf:

NHS Argyll and Clyde Board Approval of FBC 12 May 2003

SEHD Approval of the FBC 14 May 2003

Financial Close 28 May 2003

Complete Construction 31 May 2005

Service Commencement 1 July 2005

1.31 Public/Staff Engagement

1.32 Since the Outline Business Case was approved the Trust has continued to fully

engage staff and the local community in the project. In parallel with the

development of the FBC and the procurement of the private sector partner the

Trust has been implementing its Project Public/Staff Engagement Plan. This

has enabled and facilitated extensive public/staff participation in the planning

and design of the facilities, the decision making on service delivery models

and the selection of a private sector partner. The project now enjoys a very

high public profile throughout Mid Argyll.

Page 8 of 78

2 Strategic Context

2.1 NHS Argyll and Clyde is responsible for maintaining and improving the health

of the people who live in Argyll and Clyde which is an area of approximately

2,880 square miles. This area includes the towns of Paisley, Greenock,

Dumbarton and Helensburgh that are located on the edge of the Clyde

conurbation and rural towns such as Oban, Dunoon, Campbeltown, Rothesay

and Lochgilphead. It also covers remote and island areas featuring up to 24

inhabited islands.

2.2 The main role of NHS Argyll and Clyde is to assess health needs, commission

health services to meet these needs, promote healthy living and plan future

health services for the people who live in this area.

2.3 Lomond and Argyll Primary Care NHS Trust is responsible for the

development and delivery of local hospital services and primary care,

community and mental health services. It works in partnership with a number

of agencies including Argyll and Bute Council and West Dunbartonshire

Council.

2.4 The Modernisation and Redesign of Primary and Community Health and

Social Care Services in Mid Argyll is a project that is responding to local

health and social needs. It proposes plans for service change that will enable

appropriate and sustainable health and social care service to be provided for

the local community of Mid Argyll.

2.5 The objectives for the project were identified as follows:

To enable the Trust to provide a modern service that integrates primary

care, community health and hospital services and social services.

To focus services on health maintenance and ill health prevention.

To provide accessible services.

To maximise clinical effectiveness.

To improve the quality of the service available to the local population by

providing modern purpose built facilities.

To enable the Trust to provide an efficient and effective service.

To provide flexibility for future change.

To provide a facility that is acceptable to patients, staff and public.

To provide a contemporary and modern facility, which will support Health

and Social Care, services over at least the next 30 years.

Page 9 of 78

To achieve these objectives by fundamental redesign of service delivery to

take account of the patient/user‟s viewpoint at all times, and to develop

flexibility in the use of the facility and ways of working.

2.6 A number of factors identified in national and local strategies and plans and

analysis of health care need influenced the proposals in the Outline Business

Case for this project. These factors indicated how the need for health and

social care is changing and the opportunities that are emerging to provide

services in different and better ways. They strongly supported the role of

community hospitals as focal points for the provision of modern health and

social care in remote communities and the need for modern premises to enable

this. These factors remain valid at Full Business Case stage and are restated in

the following.

Our National Health – A plan for action, a plan for change

The key themes of the National Health Plan that are most relevant to the

radical service changes that will be enabled by this project include:

Modernising services.

Locally appropriate services – improving access.

Community and public participation in service design and

provision.

Seamless care – tailor-made care pathways.

Integrated services – partnership with Local Authorities and

other organisations.

Unified NHS – National standards.

Staff Partnership – involvement and support to provide new

flexible and effective ways of working.

Addressing the priorities of heart disease, cancer and poor

mental health.

Improved care for the elderly and younger people.

The White Paper “Working together for a Healthier Scotland”

The Outline Business Case evidenced the significant contribution that local

healthcare services can make to the aspirations of the White Paper “Working

together for a Healthier Scotland”. It demonstrated the need to redesign local

services to provide an extended range of healthcare service, integrated with

housing and social services, general dentistry and other Primary Care Services.

It also demonstrated the key role that the Trust‟s Community Hospitals at

Lochgilphead, Campbeltown, Islay, Mull, Bute and Dunoon can play in

supporting this new service by facilitating integrated working and by

providing practical locations for the development of local “intermediate care”.

The development of such hospitals will enable NHS Argyll and Clyde to

exploit the strategic opportunities offered by:

Technological advances in teleradiology, video conferencing and

information and communications technology generally to benefit the

Page 10 of 78

people that use its services and reduce the professional isolation of its

staff. Community hospitals will therefore become the core facility to

support development of telemedicine services.

Evidence of how extended primary health care teams with nurses,

allied health professionals and social care professionals working

together can provide accessible, integrated and clinically effective

services.

The White Paper “Designed to Care”

The Outline Business Case highlighted how the proposal would fit with the

aims of the Government‟s White Paper “Designed to Care” particularly in

relation to:

Joint investment planning and commissioning of services.

The need to make better use of the resources including staff

skills and time.

To drive efficiency through a rigorous approach to

performance.

Equitable services availability and accessibility.

Goodness of fit between major capital investment decisions and

Health Improvement Programmes.

Ensuring that quality is the driving force for decision making.

The project is also consistent with the following National Plans and Strategies:

“Caring for Scotland” a strategy for Nursing and Midwifery.

Primary Care Modernisation Group “Making the

Connections - Developing Best Practice into common

Practice,

RARARI report “ Solutions for the provision of Health

Care in the Remote and Rural areas of Scotland in the 21st

Century”,

Temple Report “Future Practice – A Review of the Scottish

Medical Work Force”.

Local Health Plan

In this plan, NHS Argyll and Clyde acknowledged the need to replace the

Community Hospital facilities in Mid Argyll and to include the project under

the national priority of Reshaping Hospital Services. The Health

Improvement Programme stated that “the proposed redevelopment of Mid

Argyll Hospital, Lochgilphead, offers the potential to significantly improve

Page 11 of 78

and reshape services in the area and, subject to the revenue and resource

transfer consequences being affordable the Board would wish to support the

final business case submission”. The Mid Argyll project was the top priority

in the capital programme for two years prior to submission of the OBC.

The Trust’s Implementation Plan

Lomond and Argyll Primary Care NHS Trust‟s Implementation Plan

1999/2003 stressed the need and prioritised as number one the replacement of

Mid Argyll Community Hospital facilities and commits to the submission of

the Trust‟s Full Business Case for approval by the Board in March 2003.

Argyll and Bute LHCC Plan 2000

The Argyll and Bute LHCC plan identified the development of Care of the

Elderly services as its top clinical priority, focusing on:

Support and develop Community based services.

Increase rehabilitation services, such as OT, physiotherapy.

Review of clinical leadership.

Response to SHAS findings.

The Plan also set a target for the replacement of the 103-year-old Mid Argyll

hospital by 2003.

Mid Argyll Community Hospital Review

A review of Mid Argyll Hospital was commissioned in 1999 to assess the

appropriateness of facilities, skills, case mix advice, transfer criteria, use of

protocols and advice on a model of care development. Professor Lewis Ritchie

conducted this review and whilst he identified general clinical and equipment

developments, he confirmed that the range of service provided was appropriate

but a “replacement Mid Argyll Community Hospital development with

associated on-site services should be pursued as soon as funding allows.”

The Scottish Health Advisory Service

The SHAS report “Service for Older People in Lomond and Argyll” March

2000 (and in 1996) identified that the existing Care of the Elderly

accommodation (Duncuan Ward) is an isolated building not appropriate for

rehabilitation or continuing care. The accommodation comprises a mixture of

multi bedded bays and two single rooms with a lack of patient storage or

personal space, there are no separate OT or Physiotherapy facilities these

being provided at other buildings on the hospital site.

The Trust’s Mental Health Strategy

NHS Argyll and Clyde‟s key objectives in this service are to deliver the

strategic direction for mental health services established in the Mental Health

Page 12 of 78

Framework and Argyll and Clyde Health Board‟s response “Climbing the

Framework – a Way to Go”. This Strategy envisages the replacement of the

Argyll and Bute Hospital with a smaller facility that will meet the functional

needs of the service in the 21st Century. This re-provision envisages a

redistribution of beds for the confused elderly in order to provide satellite

residential facilities associated with Community Hospitals. The Strategy also

envisages the integration (including physical) of mental health services with

Primary Care, Social and Local Authority services.

The Trust’s Property Strategy

Prior to the submission of the Outline Business Case, Lomond and Argyll

Primary Care NHS Trust completed a rigorous appraisal of its entire property

portfolio and from this it has developed a comprehensive Property Strategy

that aims to progressively improve the condition and performance of its estate

and to improve its effectiveness and efficiency in supporting service delivery.

The existing Mid Argyll Hospital was identified as a poor performer in terms

of physical condition, energy performance, functional suitability, space

utilisation and compliance with fire and statutory standards. The expenditure

required to bring this poor performance back to a satisfactory level was

estimated to be in excess of £2.5 million (as at 2000). However, the Property

Strategy recognised that even this level of expenditure would not fully address

issues of functional suitability and therefore proposed the replacement of the

Hospital as the only practical way forward.

A recent (2003) review of the condition of the existing Mid Argyll Hospital

facilities has identified that if the procurement of the proposed new facilities

are delayed beyond 2005 then it is inevitable that expenditure will be required

to maintain the existing buildings in operational use. A broad estimate of the

minimum requirement is shown in the table below.

Expenditure Category Capital

expenditure

£ million

Backlog maintenance 2.50

Compliance with Disability

Discrimination Act

0.50

Upgrading/refurbishment to bring

environmental quality to an acceptable

level

1.00

Additional temporary accommodation 1.00

Total: 5.00

2.7 Key assumptions underlying the analysis of the strategic contect

2.8 The key assumptions underlying the analysis of the strategic context were:

Page 13 of 78

It will increasingly be possible to provide services safely and effectively

closer to peoples‟ homes and this will benefit people who use the services

by improving access.

Interagency collaboration, multidisciplinary working and service

integration are vital to the effective provision of services for many groups

in the population.

Transport services in rural communities cannot realistically improve to

the point where access to services in distant population centres becomes

convenient.

Medical, information and communications technology will continue to

improve and create opportunities for improving local access especially to

diagnostic services.

Peoples‟ expectations about the services that they receive and where and

when they receive them will continue to increase and meeting these

expectations will remain a social policy priority.

Nurses, Allied Health Professionals and Social Care Professional will

continue to develop their roles in providing care in the context of

extended primary care teams.

Improvement of service through the design of programmed packages of

care for older people and children will remain national priorities. This

will also apply to the improvement of services for people with a range of

diseases that cause premature death or reduce peoples‟ functioning or

quality of life (e.g. CHD, cancer).

The demand for locally based services will increase and this will mean

using facilities and staff in an imaginative way to expand capacity to

meet this demand.

Significant and sustained improvements in health and well being are

achieved through supported self care and services and facilities are

needed to motivate people to look after themselves and to help them to

do this.

2.9 Since the Outline Business Case was approved these assumptions have either

remained valid or become strengthened by changes such as the issue of further

government policy in the form of National Service Frameworks or increasing

evidence of the feasibility and safety of providing access to a range of services

in local community hospital settings.

2.10 This statement is evidenced by the recently published White Paper

Partnerships for Care. This paper confirmed many of the themes on which

the assumptions underpinning the case for change in this FBC are based.

These include:

The high priority attached to improvement of peoples‟ health and

improvement of community services.

A re-emphasis of the attributes of a whole systems approach to the

provision of services. These include empowered self care, redesigned

care pathways and the breaking down of barriers and tackling weakness

Page 14 of 78

at the interfaces between primary and secondary care and health and

social care organisations and professions.

The need to design sustainable and flexible services and facilities that

can absorb rising expectations and demand, especially to meet needs for

increased programmed care for chronic disease.

The opportunities offered by technological and medical advances to

improve both the process and outcome of care. Investment to take

advantages of this opportunity will be geared to the reform agenda. It

will be expected to enable service redesign, improved care and shifting

care closer to home.

Increasing expectations that service design will be driven by best

evidence and patients‟ needs and will mean new ways of working to

achieve these ends.

2.11 Outline Business Case approval gave many staff encouragement to pursue the

underlying aim of the OBC - to fundamentally redesign the way health care

has been delivered locally. A lot of work has been done by many staff groups

to plan future service delivery from the patient/user‟s perspective. This will

be achieved by removing traditional boundaries between health and social care

professions, developing new ways of working, building on clinical/care

networks that already exist, using new technology to support the process, and

using patient/user input and feedback imaginatively. Flexible use of space in

the new facility will be a key feature of the fundamental changes that are

planned to facilitate the “one stop shop” approach to service delivery, and to

achieve best use of resources.

2.12 Sustainability of services in general, including remote and rural areas, has

become even more of a concern since the OBC was approved. The proposals

in this FBC will encourage sustainability by removing boundaries between

primary and secondary care, medical and nursing care, and health and social

care, allowing the full potential of clinical/care networks to be realised. This

will allow staff to maintain and develop patient/user services while sharing

workload (including out of hours) and reducing professional isolation. Service

development and education of students and staff have been shown to improve

sustainability of potentially fragile services, by encouraging recruitment and

retention.

2.13 An important development since the Outline Business Case approval has been

the need to find space in the new facility for a Resource Centre comprising a

suite of four meeting rooms (which can be joined together by removing

partition walls) and a multidisciplinary library. The space for this facility has

been found by adopting flexible use of all consulting, treatment and clinical

office space, with no departmental or staff designation, and this flexibility on

the part of all staff has allowed this development without any increase in the

size of the building. The Resource Centre will be available to all staff and

patient groups, and will allow a full range of health promotion activities,

professional and student educational activities and meetings. It will make this

Page 15 of 78

building a teaching and learning facility for patients, students of all disciplines,

and all staff.

2.14 Since the Outline Business Case was approved the Trust has continued to fully

engage the public in the project. In parallel with the development of the FBC

and the procurement of the private sector partner the Trust has been

implementing a Public/Staff Engagement Plan. This has enabled and

facilitated public/staff participation in the planning and design of the facilities,

the decision making on service delivery models and the selection of a private

sector partner. The project now enjoys a very high profile throughout Mid

Argyll.

2.15 Present levels of service activity

2.16 Lomond and Argyll Primary Care NHS Trust serves a population of circa

140,000 that is unevenly spread across large towns such as Dumbarton,

Alexandria and Helensburgh that are located on the edge of the Clyde

conurbation, rural towns such as Oban, Dunoon, Campbeltown, Rothesay and

Lochgilphead and remote and island areas featuring up to 24 inhabited islands.

2.17 The Trust‟s current activities include Primary Care Services comprising

General Practice, Community Dentistry, Community Services and Community

Hospitals throughout Lomond and Argyll. The Trust is also responsible for

Mental Health Services and for the development and implementation of Joint

Local Mental Health Strategies with Argyll and Bute Council and West

Dunbartonshire Council.

2.18 The Mid Argyll Hospital inpatient activity for the period 1992/1993 to forecast

2002/2003 is shown in the tables below.

2.19 GP Acute

Inpatient Activity ; April 1992 to March 2002 ; GP Acute

Mid Argyll Hospital 92/93 93/94 94/95 95/96 96/97 97/98 98/99 99/00 00/01 01/02 Forecast 02/03*

Bed Complement 15 15 15 15 15 15 15 15 15 15 15

Avg. Staffed Beds 15 15 15 15 15 15 15 15 15 15 15

Avg. Occupied Beds 10 9 9 10 9 10 11 10 9 10 9

Inpatient Discharges 335 374 377 433 411 493.0 581.0 561.0 506 438 467

Occupied Bed Days 3551 3441 3431 3767 3247 3552 3816 3454 3285 3559 3175

% Occupancy 65 63 62.6 68.3 59.5 64.9 69.7 62.9 61.4 65.7 57.3

Avg. LOS 10.6 9.2 9.1 8.7 7.9 7.2 6.6 6.2 6.7 8.4 6.1

Turnover Interval 5.7 5.4 5.4 4 5.4 3.9 4.2 3.6 4.2 4.2 5.1

2.20 The table shows significant improvement trend in activity performance over

the last ten years in terms of average length of stay and turnover interval.

Page 16 of 78

2.21 This performance is reflected in the bed occupancy figures of the ward, which

suggest that on average ten of the beds are normally occupied. This average

masks the variability in daily bed usage as a frequency analysis of this

covering the period April 1999 – September 2000 shows that there were 52

occasions when 12 or more beds were in use. Furthermore, the pattern of this

covered both the winter and summer, which directly correlates with the busy

Argyll tourist industry and winter pressure peaks.

2.22 The reason why there has been a fall in inpatient activity in 2000 – 2002

directly relates to the impact of the Foot and Mouth Disease crisis on the

Tourism industry in Argyll. Activity has recovered for 2003/03.

2.23 It is also noted that a significant proportion of the Mid Argyll‟s catchment

population from Tarbert and Inveraray who require medical inpatient services

by pass the Mid Argyll Hospital and proceed directly to DGHs in Oban (37

miles) or Alexandria (65 miles).

2.24 A CSA Information Services Division analysis of inpatient admission codes

identified that between 100 and 150 patients could receive their care in their

local Community Hospital if the bed complement was increased with an

enhanced medical and nursing staff establishment. This is a national and local

priority, which the Trust and the LHCC wish to see developed.

2.25 The Trust and the locality have modelled the impact of these additional

patients on the acute bed complement. Taking into account planned

performance improvements regarding throughput and lengths of stay this

increase in activity can be met within the existing 15 GP acute bed

complement.

2.26 Elderly Assessment

Inpatient Activity; April 1992 to Forecast March 2003 Elderly Assessment

Mid Argyll Hospital

92/93 93/94 94/95 95/96 96/97 97/98 98/99 99/00 00/01 01/02 Forecast 02/03*

Bed Complement 6 6 6 6 6 6.0 6.0 6.0 6 6 6

Avg. Staffed Beds 6 7 7 8 7 7.0 7.0 7.0 6 6 6

Avg. Occupied Beds

4 6 6 8 6 6.0 6.0 6.0 5 4 4

Inpatient Discharges

41 63 92 92 73 60 59.0 44.0 60 46 31

Occupied Bed Days

1636 2161 2153 2935 2270 2313 2227 2041 1825 1250 1405

% Occupancy 75 89 85.6 97.2 88.9 92.5 92.3 92.6 77.5 57.1 63.9

Throughput 13.5 9.5 13.3 11.1 10.4 10.0 9.8 7.3

Avg. LOS 39.9 34.3 23.4 31.9 31.1 38.6 37.7 46.4 30.1 27.2 45.8

Turnover Interval 6.8 4.1 3.9 0.9 3.9 3.1 3.2 3.7 8.7 20.4 25.9

2.27 Elderly Assessment activity over the last two years has been affected by the

work conducted in the locality to speed assessment and prevention admission

to the hospital. The recruitment of a Consultant in Elderly Medicine by the

Page 17 of 78

Acute Trust together with a new Clinical Nurse Manager in Elderly for the

Duncuan Unit has helped protect assessment beds from continuing care

occupancy. It is expected that this development will continue to impact on

assessment beds used in the new hospital.

2.28 Elderly Long Stay

Inpatient Activity; April 1992 to Forecast March 2003 Elderly Long Stay

Mid Argyll Hospital

92/93 93/94 94/95 95/96 96/97 97/98 98/99 99/00 00/01 01/02 Forecast 02/03*

Bed Complement 24 24 24 24 24 24.0 24.0 24.0 24 24 24

Avg. Staffed Beds 24 23 23 22 23 23 23 23 24 24 24

Avg. Occupied Beds

23 19 16 18 20 21.0 21.0 20.0 20 22 19

Inpatient Discharges

19 15 11 16 12 13 22.0 44.0 9 9 7

Occupied Bed Days

8425 6927 5750 6640 7140 7606 7581 7413 7300 8052 6863

% Occupancy 96 82 68.2 83.5 84.9 90.0 88.8 84.5 86.1 91.9 78.3

Throughput 0.8 0.6 0.5 0.7 0.5 0.6 1.0 2.2

Avg. LOS 443.4 461.8 523 415 595 585.1 344.6 168.5 825.2 894.7 1029.4

Turnover Interval 0 103.6 244 82.3 105.6 64.9 43.4 30.9 133.1 20.4 285.2

2.29 The table for the Elderly Long Stay Services shows that until 99/2000 there

had been a significant reduction in length of stay and improvement in turnover

interval. However, a period of nearly two years without consultant input and

nurse specialist support coupled with the absence of a nursing home in Mid

Argyll has had an adverse effect on performance. In addition 2002/03 has

seen a phased reduction in bed numbers to prepare for the temporary decanting

of the elderly to temporary accommodation at the end of March 2003.

2.30 One of the factors responsible for increasing demand on long stay beds has

been the steadily declining number of nursing home and residential home beds

available in the area.

2.31 The service recognises however, that the type and range of care it currently

offers does not meet modern requirements for this patient group. The recent

SHAS report on Elderly Care services within Lomond and Argyll Primary

Care NHS Trust identified the absence of adequate facilities to support the

service.

2.32 The service recognises that modern Elderly Care services requires not only

appropriate accommodation but new models of integrated service provision

tailored to meet individual patient/client needs supporting the principle of

maintaining elderly patients independence within their own homes. This will

require changes in the existing resource utilisation (a reduction of 6 Elderly

Care beds) and reinvestment in Rehabilitation, Nursing and Social Care

services. This process has already commenced via the integrated interagency

Winter Plan arrangements, which has seen investment in additional

rehabilitation, social services and nursing services.

Page 18 of 78

2.33 NHS Argyll and Clyde recently completed a balance of care study (December

2002) which proposes a 51 continuing care bed reduction across Argyll and

Bute with patients transferring to more appropriate care settings. This

reduction calculated on a Health Board population basis, equates to a 5.4 bed

reduction in Mid Argyll. The Mid Argyll locality in anticipation of the new

hospital building commencing has during 2002/03 commenced the reduction

in long stay beds and so by April will have achieved this target. In practical

terms the bed numbers will reduce even further during the construction period

to 20 beds as the alternative accommodation identified can only house 20

beds.

2.34 The service has identified a possible transfer of elderly care activity to the GP

Acute ward due to the reduction in elderly beds. The service will however,

monitor the impact of this linked to it community infrastructure developments.

2.35 The Interagency Winter Plan addresses winter pressures by preventing

admission and reducing delayed discharges. The closure of 6 beds has allowed

the identification of £148,000 to support the development of community

services to support this. However, this resource release is at marginal cost and

further service development and investment will be required to obtain the

benefits identified within the project.

2.36 Outpatients and Accident and Emergency Services

2.37 The table below shows an increase in activity for Accident and Emergency

and Outpatient services at Mid Argyll Hospital over the period. The last two

years show fluctuations in activity in AHP‟s and Outpatients due to service

cessation as a result of recruitment and retention of staff difficulties and

reductions in outreach service linked to junior doctor hours changes in

Orthopaedics, ENT and Dermatology.

Year 95/96 96/97 97/98 98/99 99/00 00/01 01/02 Forecast

02/03

A&E 3,289 3,589 3,306 3,372 3,440 3727 3659 3639

New Outpatients 3,383 3,781 3,343 3,410 3,478 3040 3006 3902

AHP Outpatients 14129 16604 15546 15857 16174 17044 15624 14127

Total: 20,801 23,974 22,195 22,639 23,092 23,811 22,289 21,668

2.38 Argyll and Bute has the highest mortality rate for vehicle accidents in

Scotland. Argyll and Clyde Health Board‟s Annual Report of the Director of

Public Health 2000 identified a Standardised Mortality Ratio (SMR) of 109 for

Argyll and Bute compared with range of 64 to 84 in the other four Argyll &

Clyde Council areas. Lochgilphead‟s location at the centre of Argyll and the

Junction of road networks results in a higher incidence of accidents and

fatalities. Fatal road crashes and numerous injuries are dealt with by the

emergency services and Medical and Nursing staff at the Mid Argyll Hospital.

The small medical and nursing establishment are committed to the

continuation of this life saving service.

Page 19 of 78

2.39 It is expected that more and more follow up activity will be conducted at Mid

Argyll using the developing skills and resources of the primary care team, with

where appropriate, use of Telemedicine Technology.

2.40 The Outpatient service will provide increasing work up services locally as part

of developing Managed Clinical Networks and standardisation of care

protocols. This will help reduce the number of journeys patients have to make

to specialist services in the centre, reducing their inconvenience and distress. It

will also reduce the “patient pin cushion” effect of duplicating diagnostic tests

at secondary and tertiary centres, which not only benefits patients but frees up

capacity and better utilises scarce resources. It is expected that this initiative

will also branch over into Day Case activity as appropriate.

2.41 Midwifery Services

2.42 Currently Midwifery services in Mid Argyll are provided centrally from Mid

Argyll Hospital, Lochgilphead. The annual caseload is 100 pregnant ladies

with a local delivery rate of 22 in 1999.

2.43 The Trust has conducted surveys of women‟s expectations from the service

and these have consistently identified the following requirements:

Continuity of care from midwives who are practised and up to date.

Midwives to give complete and unbiased information about all

aspects of the maternity event.

Midwives to be flexible in outlook.

Unless complications arise, that midwives should be the main

provider of ante natal, intra partum and post natal care.

2.44 The main areas of Mid Argyll are divided into three in terms of maternity

services:

Lochgilphead and Ardrishaig

Inveraray

Tarbert

2.45 All three areas have the same midwifery provision in terms of antenatal and

postnatal care.

2.46 In the main, the “specialist” services for Lochgilphead, Ardrishaig and

Inveraray are provided by the Vale of Leven Hospital, Alexandria (80+ miles

from Lochgilphead). The Tarbert area has historically had specialist input

from the Southern General Hospital, Glasgow (100+ miles away).

2.47 Unmet Demand for Services

2.48 There is some evidence that the limited range and scale of services currently

provided by the Mid Argyll Hospital results in people travelling further afield

to access services. For instance, people living in the southern part of the area,

such as Tarbert, will travel to Oban to access some services. If the services and

Page 20 of 78

facilities proposed in this business case were available, then it is likely that

these people would prefer to travel less distance and access the services in

Lochgilphead.

3 The Outline Business Case

3.1 The Outline Business Case defined the purpose of the project as enabling and

facilitating fundamental change in the way in which health and social care is

delivered to the people of Mid Argyll. The underlying aim is to redesign

services from a patient‟s point of view. Health and social care services will be

shaped around the needs of patients and clients through the development of

partnerships and co-operation between patients, their carers and families and

NHS staff; between the local health and social care services; between the

public sector, voluntary organisations and private providers to ensure a

patient-centred service. Overall, the project aims to substantially increase

services and the delivery of care locally.

3.2 The Trust developed a long list of options for addressing the gaps between the

service needed and the current service. These were as follows:

• Closure of Mid Argyll Hospital.

• Do nothing.

• Do minimum – address the backlog of maintenance on the existing

Mid Argyll Hospital and the Duncuan Care of the Elderly Unit.

• Upgrade and extend the existing Mid Argyll Hospital and the Duncuan

Care of the Elderly Unit and provide a 12 bed Elderly Dementia Unit.

• Provide a modern, purpose built facility to accommodate a range of

Primary Care, Community Health and Social Care Services for Mid

Argyll in Lochgilphead.

3.3 A broad assessment of the options on the long list was undertaken to

determine:

• How well they would meet the service need.

• The service benefits that could be expected.

• The technical feasibility.

• The expected capital and revenue cost.

3.4 A number of options were rejected for the following reasons:

• The option to close Mid Argyll Hospital was rejected, as it would very

significantly reduce accessibility to services for the population of Mid

Page 21 of 78

Argyll and seriously undermine the viability of this rural community. It

would have meant unacceptable travel distances and times to the nearest

alternative available services.

• The “Do nothing” option was rejected on the grounds that it would fail

to address the very significant issues in relation to the current gap between

the modern service needed supported by new ways of working and current

provision. Additionally, the already unacceptable physical condition and

functional suitability of the existing facilities would continue to deteriorate

and this will effectively result in the need to close the Hospital in the

longer term.

• The option of extending and upgrading the existing Mid Argyll

Hospital and the Duncuan Unit were carefully considered in terms of

technical feasibility, financial impact and service fit. It was shown to be

technically feasible. However, it was likely to mean serious compromises

in terms of the building layout and functional suitability for modern

healthcare service delivery, because the existing buildings cannot easily be

adapted to meet the new requirements without significant structural and

building services changes. The cost of such changes, added to very high

backlog maintenance expenditure required on both of these buildings

would mean an overall capital cost almost equivalent to a new building

cost. It would have meant a high capital cost that would achieve few of

the benefits of a new building. Hence, this option would provide poor

value for money in comparison to the “new build” option.

3.5 It was clear from the appraisal of options that there were two broad options for

the Trust to consider:

Option 1: “Do minimum”. Despite the “Do minimum” approach, this

option would involve substantial expenditure on backlog maintenance

and future life cycle building and engineering replacement costs to

ensure that the existing buildings could remain operational. In addition

to retaining the existing Mid Argyll Hospital, this option would entail

the retention of a number of other buildings in the Lochgilphead area

including the existing GP and GPD surgeries and social services

building. This option would inevitably be broadly similar in terms of

model of service provision to that which currently exists.

Option 2: Provide a modern, purpose built facility to accommodate

a range of Primary Care, Community Health and Social Care Services

for Mid Argyll. This option would facilitate and enable the

development of new models of service provision, allowing the

integration of primary and community health and social care services.

3.6 An extensive search for suitable sites for the location of the new facilities

proposed in Option 2 was conducted and led to the identification of six

potential sites in and around Lochgilphead. Technical and feasibility studies

of these sites led to a number of them being rejected and a shortlist of three as

follows:

Page 22 of 78

Option 2A – the existing Mid Argyll Hospital site

Option 2B – Whitegates site

Option 2C – Baddens site.

3.7 The shortlisted options were the subject of an option appraisal exercise carried

out by the Trust in accordance with the Scottish Capital Investment Manual.

This examined the non-financial benefits and full life (capital and revenue)

costs of each option. A summary of the results of this are shown in the table

below.

Option

No Description “Weighted Benefit

Score”

Full life costs (NPC)

£millions

1 Do minimum 388 33.82

2A Existing Mid Argyll Hospital site 687 53.33

2B Whitegates site 786 53.66

2C Baddens site 672 55.89

3.8 The table shows that the “Weighted Benefit Score” for the three variations of

Option No 2 were all substantially greater than Option No 1: Do Minimum.

This confirmed that Option 2, irrespective of the site chosen would be capable

of delivering substantial benefits compared to the existing situation and

therefore that the project is worthwhile.

3.9 Whilst “Whitegates” site had the highest benefits score there little to choose

between the variations of Option No 2 in terms of non-financial benefits.

Similarly, the choice of site for Option 2 does not greatly influence the overall

lifecycle costs of this option.

3.10 During the course of developing the OBC, the “Whitegates” site was sold and

was no longer available to the Trust. Therefore, the Project Team made the

decision to select the “Existing Mid Argyll” site as the preferred site for the

inclusion in the OBC.

3.11 The review of the OBC has shown that the fundamental decisions made at that

time remain robust at this FBC stage of the project.

4 The Preferred Solution

4.1 As part of the process of developing this FBC the Trust continued the

development of the preferred option of developing new facilities on the

existing Mid Argyll Hospital site. In parallel with this work the Trust

successfully identified a private sector partner to design, construct, finance and

operate the proposed new facilities in accordance with the Government‟s

Private Public Partnerships/Private Finance Initiative (PPP/PFI). The preferred

solution for procuring the project is now through the PPP/PFI procurement

Page 23 of 78

route using a consortium led by Canmore Partnership. The composition of the

consortium members is set in the table below.

Consortium Member

Consortium promoter/Bid Coordinator Canmore Partnership

Builder/Contractor Balfour Beatty

Funder/Senior Debt Bank of Ireland plc

Financial Adviser Operis Group

Legal Adviser Dundas and Wilson

Architect HLM

Quantity Surveyor Capita Cost Management

M&E Services Engineers DSSR/FES

Structural Engineers Oscar Faber

Facilities Manager Parsons Brinckerhoff

Healthcare/Medical Planner WS Atkins

Other MPM Capita/UME

4.2 Since being identified as the preferred partner the Consortium has worked with

the Trust to develop this FBC and throughout this process the consortium has

demonstrated the following strengths and qualities:

Financial and commercial soundness.

Extensive experience of healthcare PFI.

Specific experience of the PFI development of Community

Hospital services.

Understanding of and empathy with the service aspirations of

NHS Argyll and Clyde in relation to this project.

4.3 The design solution developed in collaboration between the Trust and

Canmore Partnership represents an innovative approach to integrating and co-

locating a range of primary care and supporting community hospital based

health and social care services. It will provide the full functional content

specified and meet all key operational policies set out in the project brief. It

will achieve this by exploiting the topography of the site to create a low rise

building that will cluster services in logical groupings and minimise patient

and visitor movement within the building.

4.4 Externally the solution will provide landscaping that will complement the

natural features of the surrounding area. This will sustain the high quality of

the external environment to the benefit of staff, patients and the visiting

public. It will also provide car parking that will be situated to give convenient

level access to the designated entrances to the proposed building. The solution

will also create car parking provision for people with disabilities that will

minimise travel distances and ensure level access to the proposed building.

All patient and public accesses to the building will be from traffic routes that

do not carry goods traffic.

Page 24 of 78

4.5 The accommodation will be provided over one full floor at ground level and

one half floor at lower ground level. Each floor will have direct external

access. At each level there will be separate access for patients and goods and

at ground floor level separate entrances for Accident and Emergency (A&E)

patients and other patients and the general public are proposed. There will be

separate A&E entrances for emergency and non-emergency patients. There

will also be separate entrances for goods inwards and goods outwards

movements. The principal patient and visiting public entrances will be

situated on the elevation that will face the main car park and front on to the

main access road for pedestrians, car drivers, ambulances and public service

vehicles.

4.6 The design promises to give patients and the visiting public convenient and

weather protected access to a building with an external appearance that is as

welcoming and as domestic in character as the building materials dictated by

the local climate will permit. The welcoming and domestic features will

continue to be apparent on entering the building due to an interior design that

fosters a sense of familiarity.

4.7 On entering the building through the main entrance patients and the visiting

public will enter an area that will:

Be on a primary care scale.

Give immediate access to all primary care departments including

those providing nurse and allied health professional led services

and social care.

Give immediate access to a range of support facilities, such as a

children‟s‟ play area and a cafeteria.

4.8 There will be easy access from this area to the departments providing in

patient and more specialist care. Vertical and horizontal circulation routes are

to be arranged to ensure that there is minimal conflict between access routes

for goods and other non-patient traffic and those for patients.

4.9 Departmental designs and adjacencies have incorporated a number of aspects

of modern practice, including:

The provision of non-designated generic consulting spaces for

use by general medical practitioners, visiting consultants and

other professionals.

Non-cellular space for clinical administration, research and

teaching and meetings.

The provision of space that is capable of flexible use to cope with

variations in demand for work streams such as inpatient

Page 25 of 78

admission and day hospital based therapy and emergency and

elective ambulatory care.

Integration of reception and patient administration functions for a

range of clinical health and social care services.

4.10 On entering the appropriate A&E entrance patients will have immediate access

to the A&E department and easy and discrete access to the obstetric delivery

area. Staff working in A&E treatment rooms will have immediate access to

the staff and facilities of key related functions such as generic nurse treatment

areas and radiology.

4.11 Patients and the visiting public needing access to the lower ground floor will

have direct access at that level and via either stairs or lift from the ground floor

main entrance. These routes will provide access to an area accommodating

functions that combine to offer an integrated service for older people,

including those with a mental health problem. These functions will provide an

integrated response that will meet the complex needs of older people whether

for focused intermediate care or for longer term support.

4.12 The design solution also satisfies the need for safety, security and dignity in a

number of important ways including:

Discrete and lockable facilities for the collection and disposal of

clinical waste.

Enclosed provision for the decontamination of instruments used

in dental and podiatry procedures.

Encouragement of safe wandering by older patients.

Discrete and separate routes for the removal of cadavers from

A&E and inpatient areas.

Access to all parts of the proposed building for fire appliances

and level evacuation routes from all departments in the event of a

fire or other emergency.

Provision of very high levels of en-suite single bed room

accommodation in all inpatient areas.

Provision of sound attenuation at the main reception counter to

ensure privacy for patients and/or visitors when in conversation

with reception staff.

4.13 The Trust and the Consortium have maintained a close working relationship

with the Argyll and Bute Council as the statutory planning and highways

authority. A formal application for planning consent was submitted on 24

December 2002. Sub sequentially approval of the scheme was delegated to a

sub-group comprising a local planning officer and two local councillor

Page 26 of 78

members of the Planning Committee. The Trust and the Consortium have

worked with the sub-group over the last three months to clarify all the

planning requirements for the scheme. Only two minor issues of access

remain outstanding and the Trust and the Consortium are confident that these

will be resolved shortly and will have no detrimental affect on financial close.

4.14 Since appointment as Preferred Bidder, the Canmore planning and design team

have worked with the Trust‟s Project Team and Departmental User Groups to

develop the preferred design solution. As a result of this extensive work

programme the FBC is based on 1:200 scale drawings and detailed room data

sheets including 1:50 scale room layouts for all key rooms which have been

approved and “signed off” by the Trust.

4.15 The timetable from approval of the Final Business Case through financial

close to service commencement is set out below:

NHS Argyll and Clyde Board Approval of FBC 12 May 2003

SEHD Approval of the FBC 14 May 2003

Financial Close 28 May 2003

Complete Construction 31 May 2005

Service Commencement 1 July 2005

4.16 A Base Date of 1st March 2003 has been adopted for the price quoted in the

PPP/PFI bid with an assumed RPI rate of inflation of 2.5% for the full Unitary

Charge.

4.17 Given a projected service commencement date of 1 July 2005, the Unitary

Charge requires to be indexed from March 2003 to July 2005. Indexation will

occur at the commencement of a new project financial year and with a year

end of May this will be for 1 July of each year.

4.18 The price quoted in the Consortium‟s bid is fixed until financial close.

4.19 The assumed interest rate on which the price of the scheme is based, including

the interest rate buffer is shown in the following table.

Interest Rates – Senior Debt

LIBOR Swap Rate 4.8%

Buffer 0.5%

Margin (construction/operations) 1.00%

Credit Spread 0.10%

MLA 0.04%

4.20 A margin of 0.50% is included in Canmore‟s senior debt funding proposals to

act as a buffer against short-term increases in interest rates. It is therefore

Page 27 of 78

unlikely that the cost of their bid will increase prior to financial close. The

Trust has carried out sensitivity analysis to assess the impact of reduction in

interest rates prior to financial close. The results of this are shown in the table

below.

Sensitivity of Unitary charge to Interest Rate Reductions - £’000

Rate Unitary charge

Reduction in Unitary Charge

compared with base

£’000 £’000 %

Standard model 5.3% 1,689

0.25% reduction 1,660 29 1.70

0.50% reduction 1,634 55 3.25

4.21 It can be seen that valuable affordability savings would be achieved if the

interest rate buffer is reduced prior to financial close.

4.22 A review of market rates has been undertaken to assess the current position.

The prevailing market rate for a 28 year swap arrangement proposed by

Canmore as at 24th

April 2003 was 4.92%. This represents a 0.38% reduction

in the rate used to calculate the Canmore base unitary charge at current interest

rates. This indicates that there is provision within the unitary charge used for

determining the affordability of the scheme.

5 The Public Sector Comparator

5.1 Development of the PSC

5.2 The Public Sector Comparator (PSC) is used to test the value for money of

Private Finance Initiative (PFI) proposals. The preferred PFI solution must not

only represent the best value for money of all the PFI options, but also show

better value for money than the most realistic public funded scheme. It also

represents the most developed expression of the Trust‟s design requirements

and is therefore of great use in guiding the PFI bidders in the development of

their design. This section describes the content of the PSC and how it has been

developed.

5.3 Following approval of the OBC the Trust carried out a number of technical

and design feasibility studies based around the OBC preferred option of

developing an integrated health and social care facility on the existing Mid

Argyll Hospital site. These studies led to three clear planning and design

options emerging:

Option 2A/1: A three zoned design solution on the lower part of the

site.

Option 2A/2: A compact, integrated design solution on the higher part

of the site.

Page 28 of 78

Option 2A/3: A design solution located on the higher part of the site

that would involve linking together a number of buildings with

corridors.

5.4 The Trust engaged a wide range of professional and public representatives in

this exercise of further developing the preferred option through a series of

open meetings, roadshows and workshops. This culminated in a major

workshop event on 7 December 2001 which evaluated the three planning and

design options for developing on the Mid Argyll Hospital site and identified a

preferred option which was to become the Public Sector Comparator (PSC).

5.5 The approach adopted for the evaluation of the options was similar to and

consistent with the option appraisal methodology described in the Scottish

Capital Investment Manual. The options were evaluated in terms of the non-

financial benefits that can be expected from implementing the options and a

weighted benefit score was determined for each option as shown in the table

below.

5.6 The option appraisal exercise showed that under three scoring scenarios

(consensus, optimistic and pessimistic) Option 2A/2 was the option most

likely to maximise the non-financial benefits from the project.

5.7 This appraisal was the main contributor to the decision making process that

has steered the choice of design solution in the Public Sector Comparator and

the subsequent development of an output specification and operational policies

that formed part of the Invitation to Negotiate that was issued to potential

private sector partners.

5.8 The following service changes have taken place from the preferred option in

the OBC to the current PSC:

Additional accommodation to enable the number of GPs to increase

from 6 to 10 and the number of GP trainees from 2 to 3.

Additional treatment rooms to allow for the extension of nurse

practitioner roles.

Additional accommodation for the Scottish Ambulance service to

enable the relocation Para-medical teams adjacent to the A&E

Department and to enable the garage/workshop to move to more

suitable accommodation more closely linked to the main service

base.

An increase in the size of gymnasium to support its use for

progressive rehabilitation and assistance with self care.

No Description Consensus Optimistic Pessimistic

2A/1 Three zones - lower site 649 659 639

2A/2 Integrated, compact - higher site 768 786 735

2A/3 Linked buildings - higher site 587 587 564

Option Overall Weighted Benefits Score

Page 29 of 78

Sterilising rooms for dental surgery and podiatry to comply with

emergent SEHD guidance on the decontamination of surgical

instruments.

Minor adjustments to departmental areas as a result of development

of the operational policies post OBC

5.9 These have added 1373 square metres of departmental area to the schedule of

accommodation on which the PSC was based.

5.10 Further non-service led changes to the PSC are as follows:

Change of tender price inflation projection from the OBC business

case level (MIPS 325) to current forecast for the start on site period

(MIPS 383). Hence, this will set the PSC costs at a comparable

level with the PPP/PFI cost level.

Update of the Planning Contingency to accurately reflect the risk

profile of the project.

5.11 The comparison of the OBC and PSC costs are shown in the table below.

OBC Agreed Funding Levels and Update to PSC

Total Total Revenue Profile

Gross Capital Capital Service External Additional

Area Cost Charges Costs Income Revenue

(m2) (£m) £'000 £'000 £'000 £'000

OBC (as approved) 6,158 13,234 1,044 595 (250) 1,389

Adjustments at ITN / preferred bidder

stage :-

Additional functional content and

amendment to asset life 896 1,893 324 324

MIPS 325 to 372 2,393 210 210

Pay and prices to 2002/03 36 36

Total Adjustments 896 4,286 534 36 570

Gross Affordability Envelope at

2002/03 outturn prices & MIPS 372 7,054 17,520 1,578 631

1 (250) 1,959

Adjustments at Full Business Case

stage:-

Additional functional content inc SAS

depot and garage 407 1,011 91 91

MIPS 372 to 383 668 48 48

Total Adjustments 407 1,679 139 139

Gross Affordability Envelope at

Quarter 2 2003 capital cost base

(MIPS 383)

7,461 19,199 1,717 631 (250) 2,098

Additional Contributions :-

Page 30 of 78

Capital charges savings on demolition (106) (106)

Additional external contributions (191) (191)

Total Additional Contributions (106) (191) (297)

Inflation adjusted year 1 affordability

envelope at MIPS 383 7,461 19,199 1,611 631 (441) 1,801

1 Includes £103 K of Hard Facilities Management services at 2002/3 prices

6 The PPP/PFI Procurement Process

6.1 The Trust adopted a PPP/PFI procurement process based on European

Procurement Regulations Negotiated Procedure.

6.2 The advisers used by the Trust were as follows:

Project management, technical and healthcare planning consultancy support:

STRATEGEM Management and Technical Consultants Ltd

31 Station Road

Steeton

West Yorkshire

BD20 6RL

Legal advisers:

Central Legal Office

Common Services Agency for NHSScotland

Trinity Park House

South Trinity Road

Edinburgh

EH5 3SE

The financial adviser appointed to assist the Trust is:

Secta

Tribune Court

2 Roman Road

Glasgow

G61 2SW

6.3 The Trust placed a Services Negotiated Procedure Contract Notice in the

Official Journal of the European Community (OJEC) on 17 January 2002. The

Contract Notice invited suitably qualified consortia/companies to express

interest in the provision of the services for the design, construction, finance

and operation of serviced accommodation for the provision of primary,

community health and social care facilities in Mid Argyll.

6.4 Prior to issuing the Contract Notice the Trust had carried out a value for

money review of soft facilities management services for the proposed new

facilities. The Trust was assisted in this review by external management

Page 31 of 78

consultants and facilities management specialists. The review concluded that

the current provision of soft FM services from the adjoining Argyll & Bute

Hospital was most likely to provide best value for money for the proposed new

facilities. The review report was presented to the Trust‟s Board at a meeting

on 27 November 2001, at which meeting the Board accepted the

recommendation that the soft facilities management services should be

excluded from the PPP/PFI contract.

6.5 In accordance with Government guidance on PPP/PFI contracts, clinical

services were also excluded from the contract.

6.6 Pre-qualification questionnaires (PQQ) and a memorandum of information

(MOI) were sent out to all eighteen organisations that expressed an interest in

the project. Six organisations completed the PQQ and provided the required

information by the deadlines set by the Trust.

6.7 The Trust‟s Project Board/Steering Group established an evaluation panel to

consider the responses to the Contract Notice and the Pre-qualification

questionnaires. The evaluation panel comprised:

Mr R Arbuckle – Acting Head of Service

Mr G Morrison – Deputy Director of Finance

Dr M Simpson – GP/Clinical Director

Miss C Pollock – Trust Non Executive Director

The Very Rev R Flatt – Public Member

Mrs K Murray – Public Member

Mr S Whiston – Head of Planning & Performance

Mrs J Bett – Locality Manager

Mr S Wilson – Trust Estate Manager

Mr J Mungall – Director of Acute Services Planning Argyll

& Clyde Health Board

6.8 STRATEGEM Management & Technical Consultants facilitated the

evaluation process and provided technical support to the panel but did not take

part in the scoring of bidder‟s responses.

6.9 The expressions of interest were assessed and evaluated using a methodology

based on EC Procurement Regulations which require the following criteria to

be used:

Exclusions – bankruptcy etc

Professional certification

Financial and economic standing

Technical capability and capacity

6.10 The evaluation process led to the following three consortia being invited to

negotiate for the contract:

Canmore Partnership

Page 32 of 78

Melville Dundas

Barr Holdings

6.11 Invitations to negotiate (ITN) were issued to the three short listed

organisations on 31 April 2002.

6.12 The Invitation to Negotiate comprised a suite of documents that included:

Output Specification – a detailed performance specification outlining

the scope of the project and performance standards required by the Trust

Project Agreement – a draft document including schedules that

described the legal framework and agreement upon which the Trust

intended to contract with a private sector partner.

Operational Policies – detailed descriptions of how the Trust will

operate the services it intends to provide from the proposed new

facilities

Generic Room Data Sheets – descriptions of the detailed functional

requirements of all the key rooms in the proposed facility

6.13 All three short listed consortia initially responded positively to the ITN and

took part in a series of clarification meetings with the Trust and it‟s advisers.

However, Barr Holdings subsequently withdrew prior to the deadline for

submission of responses to the ITN (2 August 2002).

6.14 The two remaining shortlisted organisations submitted bids prior to the Trust‟s

deadline of 2 August 2002. An initial evaluation of these submissions

confirmed that both bidders had submitted compliant bids.

6.15 The Trust adopted a rigorous but equitable methodology for the detailed

evaluation of the two bids received in response to the ITN.

6.16 The evaluation methodology provided for each bid to be assessed under four

main headings and responsibility was allocated to different member of the

Project Team for each aspect of the bid as follows:

Non-financial factors – Trust‟s Evaluation Panel

Design and Services – STRATEGEM Management and Technical

Consultants

Financial Criteria – Secta, Financial Advisers

Legal Criteria – Central Legal Office, Common Services Agency for

NHSScotland

6.17 The diagram overleaf shows the ITN evaluation process and evaluation criteria

adopted for the selection of preferred bidder and the relative importance

(weights) of given to each aspect of the bids.

Page 33 of 78

Page 34 of 78

6.18 The results of the evaluation of the Canmore and Melville Dundas responses

to the ITN against the weighted criteria are given below.

Non-Financial Benefits Total Score

Available

Weighted Benefit Score

Canmore Melville

Dundas

Clinical Effectiveness 10.5% 7.2% 6.3%

Accessibility to services and facilities 9% 6.2% 4.8%

Effective and efficient service delivery 8.5% 5.1% 5.0%

Flexibility for change 8% 3.6% 6.0%

Acceptability to patients, staff and public 7.5% 5.5% 4.3%

Quality of Physical Environment 6.5% 5.0% 3.8%

50% 32.6% 30.2%

Design Reflects Operational Policies Total Score

Available

Weighted Benefit Score

15% Canmore Melville

Dundas

Design reflects operational policies 15% 10.2% 9.15%

Design and Layout Total Score

Available

Weighted Benefit Score

13% Canmore Melville

Dundas

Facilities are secure, efficient, flexible

and easy to maintain

3.25% 2.50% 2.34%

Building services achieve physical

integration with building

2% 1.7% 1.26%

Good planning logic of entrances, main

circulation routes and key spaces

2% 1.56% 1.11%

Facility provides appropriate level of

accommodation for functional content

and activity levels

3.25% 1.79% 2.11%

Capable of flexibility in space and usage 1.25% 0.79% 1.04%

Building and external landscaping reflect

locality, architectural style and blend of

clinical efficiency and aesthetics

1.25%

0.91%

0.94%

13% 9.25% 8.80%

Page 35 of 78

Specification Issues Total Score

Available

Weighted Benefit Score

Canmore Melville

Dundas

Design and specification demonstrates

best practice

6.5% 4.23% 4.88%

Aesthetically pleasing materials used 2.5% 1.50% 1.75%

Creative use of natural light and

materials

1% 0.80% 0.70%

10% 6.53% 7.33%

Site Issues Total Score

Available

Weighted Benefit Score

Canmore Melville

Dundas

Solution maximises potential of site 0.5% 0.50% 0.50%

Solution is sensitive to local environment 0.5% 0.25% 0.50%

Location permits possible future sale of

spare land

0.5% 0.50% 0.50%

Capability for future expansion 0.5% 0.25% 0.50%

2% 1.50% 2%

Management and Service Method

Statements

Total Score

Available

Weighted Benefit Score

10% Canmore Melville

Dundas

Contract management 1.5% 1.07% 1.05%

Repairs and maintenance 4% 3.00% 3.12%

Grounds maintenance 1.5% 1.13% 0.80%

Furniture and equipment 3% 1.14% 2.1%

6.34% 7.07%

6.19 The final outturn evaluation scores for non-financial factors, design and

development objectives and management and service method statements are

outlined in the following table.

Overall Evaluation Scores Total Score

Available

Weighted Benefit Score

100% Canmore Melville

Dundas

Non-Financial Benefits 50% 32.6% 30.2%

Design Reflects Operational Policies 15% 10.2% 9.15%

Design and Layout 13% 9.25% 8.80%

Specification Issues 10% 6.53% 7.33%

Site Issues 2% 1.50% 2.00%

Management and Service Method Statements 10% 6.34% 7.07%

66.42% 64.55%

Page 36 of 78

6.20 On the basis of the above evaluation results, Canmore was identified as the

bidder most likely to meet the Trust‟s technical and design requirements but

by a narrow margin compared to Melville Dundas.

6.21 The financial evaluation of the bids identified that the unitary charges in both

bids were in excess of the costs associated with the updated PSC. In the case

of Canmore the unitary charge was £170,000 in excess of the PSC and

Melville Dundas was £375,000 in excess of the PSC.

6.22 The value for money analysis of the bids indicated that the Canmore bid had

marginally lower Net Present Costs than the PSC whereas the Melville Dundas

bid had higher Net Present Cost than the PSC. Therefore, the Canmore bid

offered marginal value for money against the PSC whereas the Melville

Dundas bid did not.

6.23 The legal evaluation of the bids indicated that both bids were broadly

acceptable.

6.24 On the basis of the above evaluation, Canmore were identified as the preferred

bidder with Melville Dundas held in reserve. The Trust‟s Project

Board/Steering Group accepted the Evaluation Panel‟s recommendation that

Canmore be selected as the preferred bidder.

7 The Appraisal Process

7.1 Financial Appraisal (Affordability Analysis)

7.2 The purpose of the financial appraisal (affordability analysis) is to assess the

impact of the scheme on the Trust‟s future income and expenditure position.

The affordability analysis is therefore an absolute measure of the scheme on

the financial viability of the Trust. Because of this it includes, where

appropriate, transfer payments such as capital charges.

7.3 The affordability analysis has been based on financial models provided by

Canmore on 25 April 2003 (file reference Lochgilphead Final 05.xls) which

reflects the most recent capital, lifecycle and operating cost estimates. It is

accepted that further analysis and change of this models may take place over

the period between submitting the FBC and financial & commercial close as

part of the normal contract negotiations. Any changes which do take place in

this period will be described in the FBC – PPP/PFI Addendum to be submitted

on financial close.

7.4 Capital charges have been calculated using a 6% rate of return.

7.5 Baseline Costs for Mid Argyll Hospital

7.6 Figure 7-1 shows the baseline costs, at 2000/01 prices, for the services that are

provided by the Trust which are included in the scheme. These have been split

between:

Page 37 of 78

Core services – these are services that will remain with the Trust

regardless of the procurement route. These include clinical services, as

well as soft facilities management services such as cleaning, catering and

portering;

Services within scope of PFI – these are services that are currently

provided by the Trust, but would be provided by Project Co under the

Project Agreement. These include hard facilities management and

capital charges for both estate and equipment.

Figure 7-1 - Baseline Costs of Services at 2000/01 prices

Core Services

Services

within scope

of PFI

Total

£000 £000 £000

Capital charges 108 108

Pay and non pay costs 2,047 98 2,145

Total Baseline costs 2,047 206 2,253

The services within the scope of PFI under Pay and non-pay costs relate to building and engineering maintenance

7.7 Funding agreed at OBC stage

7.8 Figure 7-2 shows the funding envelope that was agreed with commissioners at

Outline Business Case stage. Within the OBC funding envelope the Trust

anticipated that the required income contributions from third parties were

secure. Analysis of the income position is provided in sections 7.15 to 7.18.

7.9 In developing the PSC as part of the bidder selection process, the Trust

subsequently updated the OBC to reflect amendment in the functional content

and price inflation. Price inflation included an increase in capital and revenue

costs to MIPS 383 and 2002/3 outturn prices respectively.

7.10 It is important to note that the Trust did not incorporate the impact of residual

interest under land and buildings guidance as part of the original cost envelope

for the project.

Figure 7-2 - OBC Agreed Funding Levels and Update to PSC

Total Total Revenue Profile

Gross Capital Capital Service External Additional

Area Cost Charges Costs Income Revenue

(m2) (£m) £'000 £'000 £'000 £'000

OBC (as approved) 6,158 13,234 1,044 595 (250) 1,389

Adjustments at ITN / preferred bidder

stage :-

Additional functional content and

amendment to asset life 896 1,893 324 324

MIPS 325 to 372 2,393 210 210

Pay and prices to 2002/03 36 36

Page 38 of 78

Total Adjustments 896 4,286 534 36 570

Gross Affordability Envelope at

2002/03 outturn prices & MIPS 372 7,054 17,520 1,578 631

2 (250) 1,959

Adjustments at Full Business Case

stage:-

Additional functional content inc SAS

depot and garage 407 1,011 91 91

MIPS 372 to 383 668 48 48

Total Adjustments 407 1,679 139 139

Gross Affordability Envelope at

Quarter 2 2003 capital cost base

(MIPS 383)

7,461 19,199 1,717 631 (250) 2,098

Additional Contributions :-

Capital charges savings on demolition (106) (106)

Additional external contributions (191) (191)

Total Additional Contributions (106) (191) (297)

Inflation adjusted year 1 affordability

envelope at MIPS 383 7,461 19,199 1,611 631 (441) 1,801

1 Includes £103 K of Hard Facilities Management services at 2002/3 prices

7.11 In Figure 7-2 the affordability envelope has increased due to amendment in

functional content, amendment of the lives used to calculate capital charges

and inflation (both capital and revenue). This has been partly offset by the

impact of additional capital charge savings (calculated @ 6% rate of return)

accruing from an extension to the proposed demolition programme.

7.12 The costs associated with the Scottish Ambulance Service (SAS) depot and

workshop were not included in the proposed development at the time of

developing the original PSC as part of the bidder evaluation process.

7.13 The affordability envelope has been updated to reflect the capital costs at

MIPS 383 for the 2nd Qtr 2003. This provides consistency with the price base

used by Canmore for developing their unitary charge and as used in their

financial model.

7.14 In addition the costs of the Scottish Ambulance Service (SAS) depot and

workshop have been incorporated. It has been assumed that the additional cost

of this space is fully recovered from SAS as outlined in the next section.

7.15 The Outline Business case incorporated estimates of likely income

contributions accruing from third party tenants, specifically :-

General practitioners;

Dental services;

Scottish Ambulance Service (embedded accommodation and garage /

depot) and,

Argyll and Bute Council Social Work department

Page 39 of 78

7.16 These contributions have been reviewed in light of the changes that have taken

place since the development of the OBC. Additional contributions of £191k

were built into the PSC to reflect the additional space allocated to third parties.

7.17 A breakdown of the required contributions is provided at Figure 7-8. These

take account of anticipated usage of both exclusive and shared

accommodation.

Figure 7-8 – Analysis of Third Party Income Contributions

Component of

Unitary Charge

GP’s

Dental

Services

SAS

(embedded

space)

Social

Work

SAS

(depot &

garage) Total

(Ref Fig

7-2)

Rental 184.0 30.0 31.0 75.0 46.3 366.3

Hard FM 28.0 5.0 5.0 11.0 7.1 56.1

Insurance 9.0 1.5 1.5 4.0 2.3 18.3

Total 221.0 36.5 37.5 90.0 55.7 440.7

7.18 Notices have been issued to the tenant partners and the Trust are in the process

of securing formal agreement with each party and the District Valuer.

7.19 PSC PFI Resource Envelope

7.20 The costs associated with the PSC that will be used to compare against the PFI

unitary charge is presented below. This will be used as the basis for assessing

the affordability of Canmore‟s unitary charge.

Figure 7-3 – PFI Resource Envelope Relative Affordability

Affordability Element Resource Expressed @

2002/03 Outturn Prices

£’000

Gross capital charges Ref Figure 7-2 1,717

Hard facilities management Ref Figure 7-2 103

Total PSC Affordability 1,820

The Hard facilities management figure has been updated to 2002/03 price base

7.21 Capital charge savings accruing from demolitions have not been netted off

against the gross capital charges for the PSC to ensure comparability with the

PFI solution.

7.22 The remaining elements of the overall PSC affordability not included in Figure

7-3 relate to the cost of core services, which will continue to be delivered by

the Trust.

7.23 Proposed PFI Unitary Charge

7.24 The Year 0 unitary charge proposed by Canmore is £1,689k at 2002/03 outturn

prices. This incorporates a prudent 0.50% buffer on the senior debt interest

Page 40 of 78

rate to protect the scheme affordability against increases in prevailing rates up

to financial close. The unitary charge is subject to indexation by the Retail

Price Index (RPI). The payment is a single tariff, subject to availability and

service performance.

7.25 The main assumptions underpinning Canmore‟s unitary charge (extracted

from their latest financial model – file name Lochgilphead Final 05.xls) are set

out in Figure 7-4.

Figure 7-4 – Canmore Baseline Financial Model Assumptions

Category Canmore

Headline Information

Concession Period Construction period plus 30 years operating

period

Senior Debt funder Senior debt funding proposed from Bank of

Ireland Equity provided by Canmore and third

party investors.

Year 0 Unitary charge 3 £1,689m

Year 1 Unitary charge (1/8/05 to 31/5/06) part

year effect 4

£1,485m

Year 2 Unitary charge (1/6/06 to 31/05/07) 5 £1,826m

Capital costs (inc equipment but excl rolled

up interest) 6

£14.937m

Lifecycle capital costs (construction only) 7 £3.782m (1 June 2005 price)

FM costs (over operating period). Nominal

value 8

£5.808m

Libor SWAP rate incl. 0.50% buffer &

margin/MLA

6.44% (detailed analysis below)

Senior debt life 28 years

Interest Rates – Senior Debt

LIBOR Swap Rate 4.8%

Buffer 0.5%

Margin (construction / operations) 1.00%

Credit Spread 0.10%

MLA 0.04%

Total (construction /operations) 6.44%

Subordinated debt 13.13%

Construction and Development Costs

3 This value has been re-calculated to derive the tariff at 31 March 2003 prices.

4 Values taken from Canmore‟s financial model

5 Values taken from Canmore‟s financial model. The model assumes 2.5% indexation subject to RPI inflation

6 Values taken from Canmore‟s financial model

7 Values taken from Canmore‟s financial model

8 Values taken from Canmore‟s financial model

Page 41 of 78

Category Canmore

Capital costs (excl rolled up interest and

group 2 & 3 equipment)

£13.849m

Group 2 & 3 equipment £1.088m

Construction period 24 months

Internal Rates of Return (IRR)

Project IRR – pre tax (real) 6.03

Project IRR – pre tax (nominal) 8.85

Equity IRR – post tax (nominal) 30.19

Blended IRR (real) 11.34

Banking Ratios and Fees Minimum

Required Model Average

Model

Minimum

Annual debt service cover ratio (ADSCR) 1.15 1.231 1.150

Loan life cover ratio (LLCR) 1.25 1.453 1.234

7.26 Two further comments regarding the above latest financial model are outlined

below.

The nominal equity IRR (post tax) is still at the higher range and MLA

margin is high but Secta consider that the combination of these two

provide an overall acceptable IRR.

It is noted that the minimum LLCR is not met but this is marginal issue

that should not impact upon the Unitary Charge.

7.27 Composite Trader (Contract Debtor) Approach

7.28 Canmore have provided a financial model that incorporates a contract debtor

approach. They have however been reluctant to pursue formal Inland Revenue

approval for this tax treatment of the scheme. This results from uncertainties

in relation to the standing of a licence in Scots law, which is a critical factor in

securing contract debtor status for the scheme. Consequently Canmore require

that the Trust accept an amendment to the Project Agreement which would

compensate them if, following financial close, the inland revenue refuse to

approve the SPV as a composite trader. The Trust has sought the view of

Private Finance and Capital Unit on this matter. They have indicated that this

is not acceptable and contrary to guidance.

7.29 Canmore and specifically, their senior debt funder, Bank of Ireland have

offered only a marginal reduction, less than 1.5%, in the tariff through the

adoption of contract debtor. Whilst few health PFI projects have reached

financial close adopting a contract debtor approach, early indications suggest a

range of 1.6% to 3.0% reduction in the tariff could be achieved through the

adoption of a contract debtor approach, compared with a traditional capital

allowances approach.

Page 42 of 78

7.30 On the basis of Canmore‟s stance on this issue and guidance from the Private

Finance and Capital Unit, the Trust are concerned that undue delay associated

with concluding this issue to the satisfaction of both parties would

undoubtedly result in Canmore requiring to review their costs, specifically

capital costs. The likely impact of this would be to increase the unitary charge

which would in turn dilute any benefit accruing from composite tax treatment.

7.31 The Trust propose that the issue of contract debtor will continue to be pursued

with Canmore post financial close. Should the licensing issues be concluded

to the satisfaction of all parties then there would be an opportunity to secure

retrospective approval from the Inland Revenue. This could result in a

reduction in the unitary charge.

7.32 The financial model used for the purposes of conducting the financial

appraisal has been constructed using a traditional capital allowances taxation

approach. During the course of negotiations with Canmore on composite tax it

has proved possible to drive out some improvements in the unitary charge

arising from detailed discussions with their funder, the Bank of Ireland. This

has allowed a review of the funding structure of the project to be carried out,

the outcome of which has delivered some small improvements in the tariff.

7.33 Affordability of Canmore’s PFI Proposal

7.34 The revenue implications of the proposed PFI unitary charge as measured

against the relevant comparable elements of the PSC are set out in Figure 7-5.

Figure 7-5 – Relative Affordability of Canmore PFI Proposal Compared with PSC

7.35 This illustrates that the scheme would be broadly affordable if the proposed

unitary charge can be covered from the resource envelope restated using the

second quarter 2003 capital price base. This provides consistency with the

price base used by Canmore for developing their unitary charge and as per

their financial model.

7.36 It is important to note that the Trust did not incorporate the impact of residual

interest under land and buildings guidance as part of the overall cost envelope.

7.37 The affordability position set out above is subject to agreement of third party

income contributions.

Resource Expressed @

2002/03 Outturn Prices

£’000

Canmore Unitary Charge 1,689

Affordability envelope Ref Figure 7-3 at MIPS 383 1,820

Scheme Affordability Surplus 131

Page 43 of 78

7.38 Overall Affordability of the Project (excluding residual interest)

7.39 The table below shows the overall costs associated with the preferred PPP/PFI Option

and compares it in overall cost terms with the updated PSC and the original OBC

revenue profile. It is important to note that the Trust did not incorporate the impact of

residual interest under land and buildings guidance as part of the original cost

envelope for the project. This incorporates the impact on both core services and

services within the scope of the PFI deal as described in 7.5.

Figure 7-6 – Overall FBC Affordability

Revenue Profile

Capital

Charges /

Unitary

Charge

Capital

Charges

Savings from

Demolitions

Service

Costs

External

Income

Additional

Revenue

OBC (as approved) 1,044 595 (250) 1,389

Updated PSC to MIPS 383 (ref Fig 7-2) 1,717 (106) 631 (441) 1,801

Preferred PPP/PFI Option 1,689 (106) 528 (441) 1,670

The Unitary Charge already includes provision for Hard FM; to avoid double counting the Hard FM costs included in the PSC have been netted off against service costs (i.e £631k - £103k per the PSC) for the PFI option.

7.40 The affordability position set out above is subject to agreement of third party

income contributions.

7.41 Sensitivity Testing of Affordability

7.42 A margin of 0.50% is included in Canmore‟s senior debt funding proposals to

act as a buffer against short-term increases in interest rates. The Trust has

carried out sensitivity analysis to assess the impact of reduction in interest

rates prior to financial close.

7.43 The prevailing market rate for a 28 year swap arrangement proposed by

Canmore as at 7th

February was 4.80% which has been used as the planning

assumption in Canmore‟s modelling. This gives an overall base senior debt

rate of 5.3% (excluding margins, credit spread and MLA adjustments) when

the interest rate buffer is incorporated.

7.44 The Trust has requested that Canmore run a number of interest rate

sensitivities to assess the impact of changes in interest rates prior to financial

close. These have been modelled as a series of reductions in the base rate (inc

interest rate buffer) used in Canmore‟s core model. The impact of these

sensitivities on the level of unitary charge is shown in Figure 7-7.

Page 44 of 78

Figure 7-7 - Sensitivity of Unitary charge to Interest Rate Reductions - £’000

Rate Unitary charge

Reduction in Unitary Charge

compared with base

£’000 £’000 %

Standard model 5.3% 1,689

0.25% reduction 1,660 29 1.70

0.50% reduction 1,634 55 3.25

7.45 It can be seen that valuable affordability savings would be achieved if the

interest rate buffer is reduced prior to financial close.

7.46 A review of market rates has been undertaken to assess the current position.

The prevailing market rate for a 28 year swap arrangement proposed by

Canmore as at 24th

April 2003 was 4.92%. This represents a 0.38% reduction

in the rate used to calculate the Canmore base unitary charge at current interest

rates. This indicates that there is provision within the unitary charge used for

determining the affordability of the scheme.

7.47 Technical Issues

7.48 A number of technical issues have arisen in respect of the PFI. These

include:-

Treatment of Land and Buildings in PFI Schemes

Impact of the introduction of 3.5% rate of return

VAT treatment

7.49 Land and Buildings in PFI Schemes

7.50 Under the „Standard Form‟ Contract, facilities revert to trust ownership at the

end of the tariff period. Because this is at no cost, part of the unitary charge

that the trust is paying to Project Co is, in effect, a payment to acquire the

facility at the contract end. In accordance with Treasury Technical Note No.1

(Revised) the residual interest of the asset must be built up over the life of the

contract in order to ensure a proper allocation of payments made between the

cost of services under the contract and the acquisition of the residual.

7.51 The residual interest is required to be recognised in the appropriate heading

within tangible fixed assets in the Trust‟s balance sheet. Residual interests fall

within net relevant assets and are subject to capital cost absorption duty. The

impact of residual interest has not been included within the OBC or ITN by

the Trust.

7.52 Figure 7.8 shows the estimated impact of this capital cost absorption

requirement on the Trust, assuming a 6% rate of return. This assumes that at

handover the capital value of the building mirrors the original construction

cost. This analysis is based on an annuity approach. Further discussions with

commissioners are required to determine how this gap would be funded.

Page 45 of 78

Figure 7-8 –Residual Interest Capital Cost Absorption Charges (full cost)

Residual Interest Year

1

£’000

2

£’000

5

£’000

10

£’000

20

£’000

30

£’000

Annual cost @ 6% 4 13 45 115 363 877

Cumulative cost @ 6% 4 18 119 544 2,910 9,057

7.53 Whilst the value at handover will ultimately be determined by the District

Valuer there is potential that the building could be handed over in Estatecode

Condition B standard. A sensitivity has been modelled on the basis that the

value on handover is only 38% of the initial cost. The results of this are

shown in Figure 7-9.

Figure 7-9 –Residual Interest Capital Cost Absorption Charges (38% cost)

Residual Interest Year

1

£’000

2

£’000

5

£’000

10

£’000

20

£’000

30

£’000

Annual cost @ 6% 2 5 17 43 137 333

Cumulative cost @ 6% 2 7 45 207 1,105 3,442

7.54 Impact of the introduction of 3.5% rate of return

7.55 In January 2003 HM Treasury published a new edition of The Green Book –

Appraisal and Evaluation in Central Government.. Revised interim guidance

under HDL(2003)13 has recently been issued to cover the specific

requirements of the new green book and comes into effect from 1 April 2003.

7.56 The revised guidance alters the procedures for appraisal and evaluation in

health. One of the key changes introduced under this guidance is a revised

discount rate of 3.5% for economic appraisal of options. In line with the

guidance as the project has reached Invitation to Negotiate (ITN) prior to 1

April 2003, previous guidance should continue to apply. There is therefore no

requirement as part of this FBC to adopt the new guidance.

7.57 VAT Treatment

7.58 The Trust has appointed specialist advisers Liaison VAT Consultancy Limited

to ensure that the Trust can maximise the benefits it can receive in relation to

VAT treatment of the scheme. These advisers are part of the Trust‟s

negotiation team that is progressing the project to financial close.

7.59 Conclusions from the Financial Appraisal (Affordability Analysis)

7.60 The conclusions reached from the affordability analysis is that the scheme is

broadly affordable when comparing Canmore‟s tariff against the updated PSC

resource envelope (exclusive of the impact of residual interest). There is some

further scope for improving the affordability position in the likely event that

the agreed senior debt interest rate at financial close is lower than the modelled

rate of 5.3% which included a 0.5% buffer.

Page 46 of 78

7.61 Economic Appraisal (Value for Money Analysis)

7.62 The purpose of the value for money analysis is to rank the Options, in terms of

their relative Value For Money (VFM). The VFM is measured by the Net

Present Value (NPV) or Net Present Cost (NPC) of the scheme, or for projects

with different life spans, by the Equivalent Annual Cost (EAC). The EAC is

calculated by dividing the NPV by the cumulative discount factor, for the

relevant period of time.

7.63 All relevant actual cashflows are taken into account and consequently indirect

taxes such as VAT and non-cash financial items such as capital charges are

excluded. The time-value of money is taken into account by the use of an

appropriate discount rate. For real cashflows this discount rate is 6%. In any

one year the discount factor to be applied is given by the following formula:

DFn = 1 / ( 1 + r )n

Where;

DFn is the Discount Factor for year n

r is the appropriate discount rate (in this case 6%)

n is the year

7.64 Nominal cashflows are deflated by 2.5% to give real cashflows (i.e base year

price level), which is then discounted at 6%, in line with current Treasury

guidance. The project that has the lowest NPV and/or EAC is deemed to

deliver the best Value For Money.

7.65 The evaluation has been carried out in accordance with the Scottish Capital

Investment Manual (incorporating interim capital planning guidance issued in

NHS HDL (2002) 87), HM Treasury‟s “Appraisal and Evaluation in Central

Government” (“The Green Book”), and the guidance on PFI from the Scottish

Executive Health Department (SEHD) Private Finance and Capital Unit.

7.66 The costing methodology has been developed with the involvement at all

stages of our advisers and where appropriate, employees and advisers have

worked together to quantify the financial effects of the options being

modelled.

7.67 Description of Assumptions Made for Economic Appraisal

7.68 All the expenditure and income cash flows represent only those directly

related to the project.

7.69 The cash flow analysis must also include an assessment of the cash flows

related to risk. This is because under the PFI option some risks (or parts

thereof) are borne by Canmore and not the Trust. The transfer of these risks

has an economic value to the public sector that must be reflected in the

analysis. The Trust undertook a detailed risk assessment to identify the value

and timing of the risks under the two options. The methodology behind this

Page 47 of 78

process is detailed in Section 7.79. The financial results of the risk evaluation

are incorporated in the value for money analysis.

7.70 Key assumptions are shown in Figure 7-10.

Figure 7-10- Key Assumptions for Economic Appraisal

Category Assumption Option

Price base Prices are based on 2002/03 Both

Time period The analysis has been carried out over both 33 and 60

year periods. Thirty three years is the life of the

concession, excluding construction. Sixty years is the

deemed useful economic life of the building. This is

therefore the relevant evaluation period for the asset.

Both

Capital,

lifecycle and

FM costs

The capital, lifecycle and equipment costs for the PSC

have been provided by the Trust‟s design and technical

advisors, STRATEGEM Consultants.

PSC

MIPS index The capital cost has been calculated at a FP MIPS

index of 383. This has been updated from the OBC

level of 325 to reflect capital construction inflation.

PSC

Unitary

Payment

The PFI model presents a year 0 Unitary Payment of

£1,685 expressed at 1 March 2003 price base. This

has been updated to 2002/03 outturn prices for

comparability purposes. This value is £1,689k.

PFI

Discount

Factors

Discount factors are calculated using a discount rate of

6%. This is the standard Treasury rate used for all

public sector economic appraisals.

Both

Transfer

payments

Transfer payments e.g. VAT have been excluded from

the analysis. To the extent that VAT is not recoverable

by Canmore, this will be reflected as a cost within

their model, and will flow through to the Unitary

Payment. However, from the Trust perspective all

VAT is excluded from the analysis.

Both

7.71 VFM Results

7.72 The results of the Net Present Cost (NPC) and Equivalent Annual Cost (EAC)

analysis are summarised in Figure 7-11 and 7-12. Further details of the risk

analysis is provided in section 7.83. A detailed breakdown of the NPC and

EAC calculations can be found in the financial appendices.

Figure 7-11 - NPC analysis

33 year analysis 60 year analysis

Net Present Cost PFI PSC PFI PSC

£’000 £’000 £’000 £’000

NPC of project cashflows 20,185 18,829 21,199 19,499

NPC of retained risk 3,965 5,911 4,805 6,751

Risk-adjusted NPV of project 24,150 24,740 26,004 26,250

Page 48 of 78

Figure 7-12 - EAC analysis

33 year analysis 60 year analysis

Net Present Cost PFI PSC PFI PSC

£’000 £’000 £’000 £’000

EAC of project cashflows 1,325 1,236 1,235 1,136

EAC of retained risk 269 400 280 394

Risk-adjusted EAC of project 1,594 1,636 1,515 1,530

7.73 The analysis shows that the PFI option asset offers both the lowest NPC and

the lowest EAC, and therefore best Value For Money, over both the contract

period and the economic life of the building.

7.74 The preferred solution (the PFI solution) demonstrates better Value For

Money than the PSC because, whilst the individual cost elements of the PFI

solution are not significantly cheaper than the Public Sector Comparator

equivalents, the overall quantum and timing of costs, taking into account the

significant amount of risk assumed by the private sector, delivers a better

overall package than a publicly funded route.

7.75 Description of the quantification of costs and benefits included in the

appraisal

7.76 The costs and benefits in the appraisal include all the relevant cash flows

associated with the project, and the cash-value of the risk transferred to the

private sector. Cash flows that have been excluded from the assessment

include those that effectively represent flows from one government department

to another, such as VAT and capital charges.

7.77 Sensitivity Testing of VFM Analysis

7.78 In common with the work undertaken as part of the affordability analysis, the

Trust has carried out sensitivity analysis to assess the impact on project VFM

of movement in senior debt in interest rates prior to financial close.

7.79 The results are summarised in Figure 7-13 and Figure 7-14

Figure 7-13 - Sensitivity of NPC to Interest Rate Reductions

Rate

33 year analysis 60 year analysis

NPC

£’000

Reduction on Base

NPC

NPC

£’000

Reduction on Base

NPC

£’000 % £’000 %

Standard model 5.3% 20,185 21,199

0.25% reduction 19,842 343 1.7 20,852 347 1.6

0.50% reduction 19,718 467 2.3 20,728 471 2.2

Page 49 of 78

Figure 7-14 - Sensitivity of EAC to Interest Rate Reductions

Rate

33 year analysis 60 year analysis

EAC

£’000

Reduction on Base

EAC

EAC

£’000

Reduction on Base

EAC

£’000 % £’000 %

Standard model 5.3% 1,325 1,235

0.25% reduction 1,303 22 1.7 1,215 20 1.6

0.50% reduction 1,295 30 2.3 1,208 27 2.2

7.80 The sensitivities modelled illustrate that the VFM position would improve if

interest rates were below 5.3%. Canmore‟s model currently assumes a base

interest rate of 4.8% plus a prudent buffer of 0.5%. As stated earlier the base

rate prevailing on 24 April 2003 was 4.92% which is 38 base points below the

rate currently adopted in the model..

7.81 Summary

7.82 The results of the VFM analysis indicate that the PFI solution offers better

overall value for money when compared to the PSC over both 33 and 60 year

appraisal periods. The base case incorporates a significant buffer to protect

the Trust against interest rate movements prior to financial close. Based on

prevailing rates at the time of completing the FBC there is the potential that

the overall VFM could be improved from the baseline position set out. This is

supported through sensitivity testing.

7.83 Risk Analysis

7.84 Overview

7.85 In order to carry out a valid comparison of overall cost between the PSC and

the PFI proposals, the value of risk inherent in the project is valued. The party

bearing that risk is identified and the overall cost of the PSC and PFI options

are adjusted by value of the risk borne under each.

7.86 A detailed risk valuation exercise was undertaken by the Trust and its advisers,

using SEHD guidance, identifying a range of risks present during the design,

construction and operational phases of the project. Probabilities of these risks

being realised were computed, along with an assessment of the likely impact,

to produce an overall forecast value of the risk.

7.87 The total value of risks identified in the project is £6.751 million. Of this sum,

it was determined that the private sector will bear £1.946 million of this under

the contractual arrangements that will apply, with the Trust retaining £4.805

million. The Value For Money analysis in section 7.71 is based on a PSC

adjusted by this risk value as compared to the PFI proposals. Further details of

the quantification and allocation of risk is provided in section 7.95.

Page 50 of 78

7.88 Risk Allocation

7.89 The objective of performing a risk analysis is to enable a more complete

assessment of the total relevant cost of the options under consideration. It is

used within the Value For Money analysis to show which option demonstrates

the best Value For Money, and also forms the basis for the assessment of

accounting treatment.

7.90 Our treatment of risk is based on the PFI guidance “Public Private

Partnerships in the National Health Service: The Private Finance Initiative”.

This guidance splits the project risks into ten broad categories and these

categories are subdivided into individual risks. The ten categories are:

Design Risks

Construction and Development Risks

Availability and Performance Risks

Operating Costs Risks

Variability of Revenue Risks

Termination Risks

Technology and Obsolescence Risks

Control Risks

Residual Value Risks

Other Project Risks

7.91 For each risk an expected value was derived based on a three-point analysis

and an assessment was made of the likely proportion that would be retained.

The expected values were extrapolated over the period to which they pertained

and discounted at 6% (refer Value For Money Analysis for a description of

discounting technique). Monte Carlo simulation was then conducted to derive

Net Present Values (NPVs) of the risks. For the PFI proposal it was assumed

that the risk profile for the PSC could be used as a proxy to extend the analysis

for the PFI to 60 years, to provide the most appropriate like-for-like

comparison.

7.92 The risk quantification group consisted of the Trust FM and operational

managers, technical advisers, and financial advisers.

7.93 The risk analysis contains the following information:

Risk reference number

Risk name

Risk description

Range of possible outcomes (minimum, medium, maximum)

Likelihood of occurrence (minimum, medium, maximum)

Expected value of total risk

Percentage risk retained under PSC

Percentage risk retained under PFI

Start and end years

Page 51 of 78

7.94 The risk matrix shows which party is responsible for managing which risk

(public sector, private sector, or shared). Details of the risk analysis can be

found in the financial appendices.

7.95 Quantitative Risk Analysis

7.96 The results of the discounted cashflow appraisal of risk indicate that a

significant proportion of the risks under the PFI option are assumed by the

private sector, whereas under the public sector comparator (a traditional

develop and construct contract) the Trust retains more of the risk. This

satisfies the principle that risk should be borne by the party best able to

manage and control it.

7.97 The comparative NPVs of the risks under the two options are detailed in

Figure 7.15.

Figure 7-15 – Comparison of Project Risk NPV

Net Present Value (simulated

values)

33 year analysis 60 year analysis

PFI PSC PFI PSC

£’000 £’000 £’000 £’000

NPV of project risks

- Retained 3,965 5,911 4,805 6,751

- Transferred 1,946 1,946

Total 5,911 5,911 6,751 6,751

7.98 The net present value of the Unitary Payment under the PFI contract (60 year

base case analysis) is approximately £21.2 million. This gives an overall risk

transfer of 9.2% calculated as:

Risk transfer = NPV (risk transfer) divided by NPV (Unitary Payment)

7.99 Figure 7-16 provides a breakdown of the risks retained by the Trust for each

category of risk. Further details can be found in the financial appendices.

Figure 7-16 - Risks Retained by the Trust

Risk Category

NPV over 33 year analysis NPV over 60 year analysis

PFI PSC PFI PSC

£’000 £’000 £’000 £’000

Design 36 152 36 152

Construction and Development 143 801 143 801

Availability and Performance 2 335 93 425

Operating Cost 425 1,128 617 1,320

Variability of Revenue 3,263 3,287 3,820 3,845

Termination 0 0 0 0

Technology and Obsolescence 0 0 0 0

Control 0 0 0 0

Residual Value 0 0 0 0

Other Project 96 208 96 208

Total 3,965 5,911 4,805 6,751

Page 52 of 78

7.100 As the table clearly shows, the majority of the risk transfer is associated with

the design, construction, performance and operating cost risks. As expected,

significant risk transfer comes from:

placing the onus on the operator to correctly interpret the output

specification for the building;

responsibility for time and cost overruns being assumed by the operator;

responsibility for the performance and availability of the facility being

assumed by the operator;

exposure to incorrect estimates for FM and lifecycle being assumed by

the operator.

7.101 Switching Point Sensitivity

7.102 The NPVs of the project risks in Figure 7-16 are based on the expected value

of the risks (i.e. the statistical mean based on the assumed size of risk,

likelihood of occurrence and distribution across the possible range of

outcomes).

7.103 To assess the overall reasonableness of the risk transfer, the switching point

i.e. the point at which the PSC becomes better overall VFM than the PFI, has

been calculated. This would indicate that the risk transfer under the PFI

contract would have to fall from 9.2% to 8.0%.

7.104 Summary

7.105 Whilst it is true that this scheme is relatively small in capital value and

contains only hard FM services, and that both these factors tend to indicate

less risk transfer, nevertheless the overall level of risk transfer to the PFI

provider appears to be is appropriate in light of the overall nature of the

project.

7.106 At this stage the Project Agreement has not yet been finally agreed and

therefore each risk identified in the risk register has not been linked to clauses

or schedules in the Project Agreement. Once this is closer to agreement then

individual risks will be linked to the Project Agreement.

8 Summary of the contract structure

8.1 This project has been progressed primarily using the Standard Form Contract

documentation issued by the NHS Executive as last updated in October 2000

and recommended for use by the Scottish Executive Health Department in

Scottish PFI/PPP projects.

8.2 The following is a diagram showing the legal relationships between the

various parties in the project.

Page 53 of 78

CONSTRUCTION PHASE OPERATING PHASE

Trust

Project Co

Construction

Contractor

Hard FM

Contractor

Funder

Direct

Agreement Direct Agreements

The Parties:- Trust: Lomond & Argyll Primary Care NHS Trust Project Co: Lochgilphead Healtcare Services Limited Construction Contractor: Balfour Beatty plc Hard FM Contractor : Parsons Brinckerhoff Funder: Bank of Ireland

Page 54 of 78

8.3 The following is a summary of the main provisions of the contract agreement,

the position reached on the key issues and a note of those matters still

outstanding.

The principle applied in this project was to adhere to the terms of the Standard

Form Project Agreement with project specific matters being incorporated

through bespoke drafting. Given this principle, it is not intended to set out the

terms of the Standard Form documentation in detail where they have been

adopted without material change.

The Standard Form Contract documentation has been departed from only in

the following respects:-

1. Payment Mechanism – the Standard Form Payment Mechanism

currently in use throughout the UK has not been adopted for this

project. Instead a payment mechanism has been specifically drafted for

this project. The payment mechanism provides for deductions from the

Monthly Service Payment in the event of failures in Availability and

Performance. Detailed criteria for determining Unavailability have

been established and are set out in the Payment Mechanism.

2. Energy Costs - it has been agreed that all energy costs and property

rates will be paid directly by the Trust. Project Co are obliged to design

and construct the Facility in such a way as to meet the energy

consumption and effeciency targets set out in the Trust‟s

Requirements. In the event that the Trust reasonably believes that these

targets are not being met, the parties will carry out a test of the energy

consumption under controlled conditions and agree a remedial plan to

be undertaken by Project Co if appropriate.

3. Composite Trader Tax Treatment – it is proposed that this tax

treatment not be adopted in this project at the outset. However, in the

event that Project Co do successfully achieve this status at a later date,

they will undertake to pass 100% of the net benefit to the Trust.

4. Market Testing- as only hard FM Services are to be provided by

Project Co, it is agreed that these shall not be market tested and all the

provisions on market testing have been deleted.

The following project specific matters have been addressed:-

1. Equipment - Project Co will supply an agreed list of Groups 2 and 3

Equipment at the Payment Commencement Date. Thereafter Project

Co will have no further responsibility for repair, maintenance or

renewal of Groups 2 and 3 Equipment.

2. Demolition of Existing Hospital – The actual completion date shall

occur on completion of the new Facility but prior to demolition of the

existing Mid-Argyll Hospital which demolition works form part of the

Page 55 of 78

Construction Requirements. It has been agreed that demolition must

be completed by a set date, failing which liquidate and ascertained

damages will be paid by Project Co. No agreement as yet reached as to

the amount of L & A damages or the basis upon which they are to be

recovered by the Trust, ie payment by Project Co or set-off against the

Service Payments.

9 Accounting Treatment

9.1 Introduction

9.2 The purpose of this section is to demonstrate that the scheme will be off

balance sheet. The principle guidance upon which this assessment will be

based is the Treasury Taskforce Technical Note No 1 (Revised) (July 1999).

This prescribes a process by which a NHS organisation should follow in order

to ascertain the accounting treatment of a scheme in relation to whether to

follow the alternative approaches set out by Accounting Standards SSAP 21

Accounting for Leases and Hire Purchase Contracts and FRS5 Reporting the

Substance of Transactions.

9.3 There must be a written indication from the Trust‟s external auditors that they

have no objection to the proposed accounting treatment of the project. (See

Note for Guidance 96/6 published by the Accounts Commission or any

subsequent Note for Guidance published by Audit Scotland.)

9.4 Status of Scheme

9.5 It is important to note that the payment mechanism outlined in the Project

Agreement forms a part of the off balance sheet assessment. Since, the

calibrated payment mechanism has only just been agreed, Secta have not had

the opportunity to complete its off balance sheet assessment and present it to

the Director of Finance. However based on Secta‟s experience of similar

schemes, Secta would anticipate that that this scheme should be off balance

sheet on the basis a robust calibrated payment mechanism as agreed.

10 Project Management Arrangements

10.1 This section provides a summary of the steps that are being taken to ensure

that the implementation of the project is managed effectively through financial

close to service commencement and through the lifetime of the partnership

agreement.

10.2 Project Management Structure

10.3 Board/Steering Group

10.4 This Group will:

Page 56 of 78

Work with the consortium to monitor and manage the risks retained

by the Trust and shared with the consortium.

Agree equipment schedules, budgets and specifications in

accordance with the consortium‟s programme.

Oversee delivery of the benefits realisation plan

Oversee the commissioning of services and equipment.

Monitor progress against the construction and equipping

programmes regularly, normally on the basis of exception

reporting.

Be satisfied that appropriate steps are being taken if problems are

identified.

Demonstrate a visible commitment to the project, ensuring that the

project is actively promoted throughout the NHS Argyll and Clyde.

Commission the post project evaluation and ensure that its

conclusions are reported to the NHS Argyll and Clyde Board.

Agree and oversee the implementation of structures and processes

for working in partnership with the consortium to ensure effective

and uninterrupted use of the facility provided.

Oversee the development and implementation of detailed

operational policies that embrace the principles set out in the ITN

and output specification.

10.5 Project Director

10.6 NHS Argyll and Clyde uses the principle of identifying an individual

Executive Director to lead projects. The Project Director for this project will

be Mr R Arbuckle – Acting Head of Service. Once the Project Steering

Group has approved the Business Case, this Executive Director will be given

full responsibility for the delivery of the project as Project Director.

10.7 The role of the Project Director is key to the successful outcome of the project.

10.8 He will:

Manage NHS Argyll and Clyde‟s interest in the project, including

the co-ordination of user‟s interest and the production and

agreement of operational policies and commissioning programmes.

Monitor the project to minimise any construction and

commissioning time overruns

Page 57 of 78

Ensure that the clinical service is delivered according to the project

commissioning programme and the clinical service costs identified

in the final business case.

Ensure that arrangements are in place for controlling and

accounting for the use of the facilities for services provided by

third parties.

Act as the point of contact in all dealings with the consultants,

contractors, and other external organisations involved in the project

and provide all decisions and directions on behalf of the NHS

Argyll and Clyde.

Be aware of the business objectives and corporate management

structure as it relates to the project.

Ensure that adequate communications channels exist between the

project and external organisations and the project and the NHS

Argyll and Clyde.

Ensure that procedures are in place to involve users at all phases of

the commissioning and mobilisation of health and social care

services to be provided from the facility.

Liaise with and formally report to the SEHD on contract progress.

Ensure that the project is completed and handed over to the NHS

Argyll and Clyde in a managed way.

Arrange the post completion evaluation of the project.

Demonstrate commitment to the project and promote the benefits

that it will bring.

10.9 Project Manager

10.10 Mr S Whiston – Head of Planning & Performance will act as Project

Manager with responsibility for carrying out the day to day management of the

project. He will report directly to the Project Director.

10.11 The Project Manager will ensure that systems are in place to control and

manage the project, in particular, time and NHS Argyll and Clyde‟s revenue

costs, to monitor the execution of the construction and equipping of the

building by the consortium, and to make regular reports to the Project

Director.

10.12 The Project Manager will be responsible for the day to day management,

including execution of the Project Director‟s responsibilities for

Page 58 of 78

commissioning and mobilisation of the operational services to be provided

from the new facility, and co-ordination of the Project Team.

10.13 Project Team

10.14 A Project Team has already been created and has provided much of the input

to the development of the outline business case and this full business case.

10.15 The Project Team includes:

Mr R Arbuckle – Acting Head of Service

Mrs J Stojak – General Manager

Dr M Simpson – Clinical Director

Mr S P Whiston – Head of Planning and Performance

Mr S Wilson – Estates Manager

Mrs S Greer – Head of Service/Community Care

Mrs J Bett – Locality Manager

Mr J Barnett – Clinical Manager, Mental Health

Mrs A McNichol – Social Services Manager

Mrs J Gill – Directorate Manager, VOLDGH

Mr A Smith – Social Services Manager Argyll and Bute Council

Mrs K Murray – Public Member

The Very Rev. R Flatt – Public Member

Ms K Grunewald – Partnership Forum Representative

Mr R Lilly – Head of NES Service South West Division

Mr R Reynolds – General Manager, South West SAS

11 Benefits Assessment and Benefits Realisation Plan

11.1 The benefits expected from the project are:

Clinical Effectiveness

Accessibility

Effective and Efficient Delivery of Services

Flexibility for change

Acceptability

Quality of Physical Environment

11.2 Achievement of these benefits requires the preferred solution to achieve the

criteria listed as follows.

Page 59 of 78

Clinical Effectiveness

Enables good clinical practice

Enables specialities to cope with increases in workload

Good relationships between services/collaborative working

Maximizes patient/staff safety

Minimises disaster risk

Maximizes patient satisfaction

Accessibility

Easy Patient Access to a Wide Range of Health & Social Services

Easy Accessible location using public private transport

Adequate Car Parking Provision

Easy Access to Buildings for Disabled Patients

Effective and Efficient Delivery of Services

Promotes Effective and Efficient Working Practices

Minimizes Travel Distances/Times for Patients/Staff

Facilitates Efficient Support Services

Optimizes Use of Site, Buildings and Land

Flexibility for change

Building that can change in the future

Minimizes Constraints on Developing existing and New Services

Acceptability

Meets patients, families expectations

Demonstrates Positive Plans to Improve Service/Facilities

Promotes Good Staff Morale

Improves Retention & Recruitment of Staff

Quality of Physical Environment

Pleasant calm Environment conducive to healthcare/patient

wellbeing

High Quality Visual, Thermal and Aural Environment

Visual and Aural Privacy for Patients

11.3 These benefits have been used to evaluate the non financial benefits of options

at each stage of the project and this enables comparisons to be made between

the level of benefits delivered under the PSC and the proposal developed by

the PPP/PFI consortium. The formal of comparison of the PSC and the

PPP/PFI proposals were undertaken in a workshop with the project steering

group. The results of this workshop showed a difference of barely 5 per cent

Page 60 of 78

in the scores and support a conclusion that at that stage the two proposals were

equally capable of achieving an acceptable level of benefits. The decision in

favour of the PPP/PFI procurement route was mainly influenced at that stage

by its advantages in terms of value for money and affordability.

11.4 In this context the principle strengths (PPP/PFI as good or better than the PSC)

and weaknesses (PPP/PFI not as good as the PSC) of the PPP/PFI proposal as

compared with the PSC were:

Strengths

Good Relationships Between Services/Collaborative Working

Maximizes Patient/Staff Safety

Minimises Disaster Risk

Maximizes patient satisfaction

Easy Patient Access to a Wide Range of Health & Social Services

Easy Accessible location using public private transport

Minimizes Travel Distances/Times for Patients/Staff

Promotes Good Staff Morale

Improves Retention & Recruitment of Staff

Pleasant calm Environment conducive to healthcare/patient

wellbeing

High Quality Visual, Thermal and Aural Environment

Weaknesses

Enables Good Clinical Practice

Enables Specialities to cope with Increases in Workload

Adequate Car Parking Provision

Easy Access to Buildings for Disabled Patients

Promotes Effective and Efficient Working Practices

Facilitates Efficient Support Services

Optimizes Use of Site, Buildings and Land

Building that can change in the future

Minimizes Constraints on Developing existing and New Services

Meets patients, families expectations

Demonstrates Positive Plans to Improve Service/Facilities

Visual and Aural Privacy for Patients

11.5 In essence this suggested that at the ITN response evaluation stage the

PPP/PFI proposal met the criteria associated with the provision of a good

quality facility with the potential for design development to meet the criteria

associated with service modernisation. The consortium has since worked

closely with the managers from NHS Argyll and Clyde and local professional

staff to develop a design that is capable of matching or bettering the PSC

against all benefit criteria.

11.6 These benefits will be realised through the actions set out in the following

plan:

Page 61 of 78

Expected Benefit Action Required to Achieve the

Benefit

Performance

Measure

Lead

Responsibility

Clinical

Effectiveness

Develop and implement plans for

managed clinical networks

Waiting times for

first appointments/

inter service

referrals.

LHCC Clinical

Director

Develop and implement

integrated care pathways

Waiting times for

first appointments/

inter service

referrals.

LHCC Clinical

Director

Develop and implement policies

and systems for allocation of

shared clinical rooms

Utilisation rates. LHCC Clinical

Director

Develop and implement plans for

commissioning clinical services

Compliance with

commissioning plan

dates.

LHCC Clinical

Director

Accessibility Continue to develop and

implement plans for improved

public transport in collaboration

with service operators.

Complaints.

Results of periodic

patient satisfaction

surveys

Project Manager

Develop and implement policies

for the allocation of car parking

spaces

Complaints.

Results of periodic

patient satisfaction

surveys

LHCC Estate

Manager

Develop and implement patient

centred booking systems.

Waiting times for

admission/ first

appointments.

LHCC Locality

Manager

Develop and implement plans for

providing care closer to home and

using technology to improve

service access.

Telemedicine

activity.

In patient/ out

patient turnover.

New services

activity.

LHCC Clinical

Director

Effective and

Efficient

Delivery of

Services

Develop and implement detailed

operational policies that reflect

the general principles set out in

the output specification.

Complaints.

Unit costs of service

provision.

LHCC Locality

Manager

Flexibility for

change

Develop detailed operational

policies for clinical and support

services. (As above)

Ease of expanding

service/ absorbing

increases in

workload.

LHCC Clinical

Director/ LHCC

Locality Manager

Acceptability Maintain process for public

information and engagement

Uptake of services

provided.

Results of periodic

patient satisfaction

surveys

Project Manager

Page 62 of 78

Quality of

Physical

Environment

Work with the consortium to

develop strategies for creating an

attractive and welcoming

environment.

Results of periodic

patient satisfaction

surveys

Estates Manager

Work with the consortium to

develop standards of design and

workmanship through the detailed

design and construction stages

Availability of

accommodation.

Results of periodic

satisfaction surveys

Estates Manager Work with the consortium to

develop details of frequency of

servicing and testing of services

Work with the consortium to

develop detailed grounds

maintenance schedules

12 Risk Management Strategy

12.1 Details of plans for managing risks retained by NHS Argyll and Clyde which

might arise during the implementation of the project. This will cover all

potential risks retained by the public sector.

12.2 A review of potential risks to the project was undertaken through a series of

workshops with the Trust Steering Group. This review identified risks in the

following categories:

Design risks.

Construction and development risks.

Performance risks.

Operating cost risks.

Variability of revenue risks.

Termination risks.

Technology and obsolescence risks.

Control risks.

Residual value risks.

Other project risks.

12.3 The risks in each category were allocated to identify those that would be

managed by the public sector, managed by the private sector or shared. The

tables that follow identify the risks in each category that will be managed by

the public sector and the proposed risk management strategy.

Page 63 of 78

Design Risks

Risk

Heading

Definition Management Strategy Lead

Responsibility

Change in

requirements

of the NHS

Trust

The NHS Trust may require

changes to the design, leading

to additional design and

construction costs.

The design develop process has

been careful to consider the

need for flexibility in the

design. A number of

transferable and shared work

areas have been identified that

create significant flexibility in

the use of accommodation to

meet changes in service

requirements. NHS Argyll and

Clyde will use these features of

the broad design to ensure that

any changes do not disrupt the

detailed design process.

Locality

Manager

Change in

design

required due

to external

influences

specific to

the

NHS

There is a risk that the designs

will need to change due to

legislative or regulatory

changes specific to the NHS.

The design development process

has kept abreast of current

legislation and regulations and

anticipated changes (e.g.

decontamination of surgical

instruments). The design is

therefore an advanced one in

this respect. It also includes

construction and building

services design features that will

make changes easier and less

costly than other solutions.

NHS Argyll and Clyde will

work with the consortium to

ensure this where the need

arises in the detailed design

process. Any change involving

cost will be financed through

the NHS Argyll and Clyde

budget development process.

Estates

Manager

Page 64 of 78

Construction and development risks

Risk

Heading

Definition Management Strategy Lead

Responsibility

Unforeseen

ground/site

conditions

under the

footprint of

existing

facilities

Additional costs resulting

from where the private sector

is unable to carry

out necessary surveys prior to

commencing work because

facilities

are currently occupied.

Develop plans to vacate existing

accommodation on the site at

the earliest possible date.

Estate

Manager

“Compensati

on

Events”

An event of this kind may

delay or impede the

performance of the

contract and cause additional

expense.

Legislative/

regulatory

change:

NHS specific

A change in NHS specific

legislation/regulations,

leading to a change in the

requirements and variations in

costs.

The design development process

has kept abreast of current

legislation and regulations and

anticipated changes (e.g.

decontamination of surgical

instruments). The design is

therefore an advanced one in

this respect. It also includes

construction and building

services design features that will

make changes easier and less

costly than other solutions.

NHS Argyll and Clyde will

work with the consortium to

ensure this where the need

arises in the detailed design

process. Any change involving

cost will be financed through

the NHS Argyll and Clyde

budget development process.

Estates

Manager

Changes in

the rate of

VAT

Changes in the rate of VAT

may increase the costs of the

project. VAT

should generally be

refundable to the NHS Trust.

Maximise the opportunity for

claiming refunds and deal with

unavoidable increases through

normal budget development

processes.

Assistant

Finance

Director Other

changes

in VAT

Changes in VAT legislation

other than

changes in the rate of VAT

payable.

Page 65 of 78

Construction and development risks – continued

Risk

Heading

Definition Management Strategy Lead

Responsibility

Incorrect

time

and cost

estimates for

decanting

from existing

buildings

The estimated cost of

decanting from existing

buildings may be incorrect,

there may also be delays

leading to

further costs. Public sector

risk unless delays and cost

attributable to the private

sector operator.

Avoid risk by completing works

as early as possible. Provide

contingent funding for cost

variations through normal

budget management procedures.

Estate

Manager

Performance Risks

Risk

Heading

Definition Management Strategy Lead

Responsibility

Change in

specification

initiated by

procuring

entity

There is a chance that, during

the operating phase of the

project, the

procuring entity of the

services will require changes

to the specification.

A robust output specification

has been prepared. Mid Argyll

and the consortium will work

together to neutralise the cost of

any change. Unavoidable

increases in cost will be dealt

with through normal budget

development processes.

Estate

Manager

Page 66 of 78

Operating Cost Risks

Risk

Heading

Definition Management Strategy Lead

Responsibility

Incorrect

estimated

cost

of providing

specific

services

under

the contract:

at point of

market

testing

The cost of providing these

services may be different to

the expected

because of unexpected

changes in the cost of

equipment, labour, utilities,

and other supplies. This risk

would

be shared if the PFI contract

envisages that changes in cost

at the point of market testing

are shared between the

NHS Trust and the operator.

Mid Argyll and the consortium

will work together to neutralise

the cost of any change.

Unavoidable increases in cost

will be dealt with through

normal budget development

processes.

Estate

Manager

Legislative/

regulatory

change

having

capital cost

consequences

:

NHS

specific.

NHS specific changes to

legislation /regulations may

lead to additional

construction costs, and higher

building, maintenance,

equipment,

or labour costs.

The design development process

has kept abreast of current

legislation and regulations and

anticipated changes (e.g.

decontamination of surgical

instruments). The design is

therefore an advanced one in

this respect. It also includes

construction and building

services design features that will

make changes easier and less

costly than other solutions.

NHS Argyll and Clyde will

work with the consortium to

ensure this where the need

arises in the detailed design

process. Any change involving

cost will be financed through

the NHS Argyll and Clyde

budget development process.

Estate

Manager

Changes in

VAT

This may increase the cost of

the provision of services to

the NHS Trust. However

changes in VAT

are generally refundable to the

NHS Trust.

Maximise the opportunity for

claiming refunds and deal with

unavoidable increases through

normal budget development

processes.

Assistant

Finance

Director

Page 67 of 78

Operating Cost Risks - continued

Risk

Heading

Definition Management Strategy Lead

Responsibility

Incorrect

estimated

cost

of providing

clinical

services

The cost of providing clinical

services may be different to

the expected. These costs

include: staff, recruitment,

training, equipment, and

supplies.

Continue service redesign and

development of new ways of

working to increase service cost

effectiveness and absorb

inflationary pressures that are

not matched by increased

income streams. Deal with any

unavoidable overall cost

increases through normal

budgeting processes.

Clinical

Director

Patient

infection –

other

Patient infection caused by

staff employed by and

controlled by the

procuring body. This risk may

lead to increased treatment

costs, and, possibly, legal

costs.

Deal with through normal

clinical risk management

processes.

Clinical

Director

Page 68 of 78

Variability of Revenue Risk

Risk

Heading

Definition Management Strategy Lead

Responsibility

Changes in

the

size of the

allocation of

resources for

the provision

of health care

There is a risk that the

resources allocated to the area

are reduced or

increased. If such changes do

occur, there may be a need to

re-scale the provision of

services.

Seek additional income streams

or alternative uses of

accommodation.

Head of

Planning &

Performance

Changes in

the volume

of

demand for

patient

services

There is a risk that the volume

of demand for health care will

change,

because of changes in the size

of the catchment area. This

may occur

because there is, for example:

an unexpected increase in the

size of the

population, leading to an

increase in demand; or the

provision of a new

alternative provider health

care, leading to a reduction in

demand.

The flexibility built into the

operational policies and the

design will allow significant

increases in activity and in the

range of services to be made

available. Further expansion

capacity is also available. Any

costs associated with this would

be prioritised and funded

through the normal service

development process.

In the event of reductions NHS

Argyll and Clyde will seek

additional income streams or

alternative uses of

accommodation.

Head of

Planning &

Performance

Unexpected

changes in

medical

technology

Unexpected changes in

medical technology may lead

to a need to re-scale or

reconfigure the

provision of services. For

example, if the increase in day

surgery is greater than

expected, the total number of

required beds may fall.

The flexibility built into the

operational policies and the

design will allow significant

variations in activity and in the

range of services to be made

available. . Further expansion

capacity is also available. Any

costs associated with this would

be prioritised and funded

through the normal service

development process.

Head of

Planning &

Performance Unexpected

changes in

the

epidemiology

of the people

in the

catchment

area

Unexpected changes to the

epidemiology of the people in

the catchment area may lead

to a

reconfiguration or rescaling of

the provision of services.

Page 69 of 78

Termination Risks

Risk

Heading

Definition Management Strategy Lead

Responsibility

Termination

due to default

by the

procuring

entity

The risk that the procuring

entity defaults leading to

contract termination and

compensation for the

private sector.

In the event of default due to

loss of service need NHS Argyll

and Clyde would work with the

consortium to identify

alternative uses for the facility.

In the event of continuing

service need alternative revenue

streams would be sought.

Head of

Planning &

Performance

Technology and Obsolescence Risks

Risk

Heading

Definition Management Strategy Lead

Responsibility Technological

change Technical changes may cause

the NHS Trust to revise its

output specifications.

A robust output specification

has been prepared. Mid Argyll

and the consortium will work

together to neutralise the cost of

any change. Unavoidable

increases in cost will be dealt

with through normal budget

development processes.

Estate

Manager

Control Risks

Risk

Heading

Definition Management Strategy Lead

Responsibility

Control of

clinical

services

The NHS Trust retains control

of clinical services which

means that it retains

significant control of the

nature of the services

provided by the operator

Develop policies that ensure

that the consortium‟s

obligations are not diluted by

the clinical needs of services

provided.

Locality

Manager

Residual Value Risks

None of the risks in this category is retained by the public sector.

Other Project Risks

None of the risks in this category is retained by the public sector.

Page 70 of 78

13 Post Project Evaluation Plan

13.1 The consortium will agree with NHS Argyll and Clyde detailed programmes

for developing the detailed design of the new facility, for building and

equipping it and for its technical and operational commissioning. During the

detailed design and construction period NHS Argyll and Clyde will receive

regular reports from the consortium on progress against the agreed

programme.

After service commencement NHS Argyll and Clyde will undertake

evaluations of the project, the facility and resultant changes in service delivery.

The evaluation of the project will be carried out within 6 months of the

completion of the building. This evaluation will focus on the processes of

project management to test the extent to which that they have secured value for

money, an appropriate balance of risk between the Trust and the Consortium

and project decisions that are consistent with the interests of the Trust and the

public sector overall. The ongoing monitoring of the project throughout the

design, construction and initial service operation periods will inform this

evaluation.

Eighteen to twenty four months after service commencement NHS Argyll and

Clyde will carry out an evaluation of the facility and the services that it is

delivering. The conclusions of this evaluation will be considered in public by

the NHS Board and reported to SEHD. The purpose of the evaluation will be

to complement both the project evaluation and the routine periodic monitoring

of the performance of services in Lochgilphead and will focus on:

An objective assessment of the achievement of the benefits

expected from the project.

A review of new services provided from the facility and their

impact on accessibility for patients.

Public opinion about the success of the project.

Staff satisfaction.

Financial performance.

An assessment of the impact of the new facility on referrals to

DGH services in Oban, Alexandria and Glasgow.

The occurrence of risk and the performance of the consortium and

NHS Argyll and Clyde in the management of risk.

The performance of the consortium as a provider of serviced

accommodation.

Page 71 of 78

Over the longer term NHS Argyll and Clyde will review the impact that the

project has had on improving the health of the population.

14 Information Management and Technology Strategy

14.1 Lomond and Argyll Primary Care NHS Trust Strategy is being developed to

reflect the National Strategy for IM&T. As such it is aimed at the need for

NHS Scotland information systems to reflect the patients need for co-

ordination and excellence in the service they receive.

14.2 Trusts have therefore been directed to produce Local IM&T plans whose aim

is to raise the level of information and communications technology support

available to clinical teams and patients to a level that provides real support for

the care process. Further NHS IT systems should look to extend the reach of

such systems to other caring agencies such as social work under agreed

clinical and professional protocols and with informed patient consent.

14.3 National and Local work programs are to be established under three headings

to make progress on these aims. These are:

Support for Direct Patient Care

Establish the Community Health Index (CHI number) as the unique tag for

NHS Scotland communication by march 2003 This will ensure that for patients

there is an assured and rapid means of transmitting and assembling

information at the point of care.

Clinical Information systems are provided supporting the broad range of

clinical specialists which support national care priorities within primary

care/community/mental health and acute secondary care, for integrated NHS

care and for interagency care. The interface for these systems will be the

continuation of the Scottish Care Information (SCI) program as an integrated

program of IM&T developments aimed at delivering products and standards

across Scotland. These products will support clinical communication between

primary, community and secondary care and will therefore serve as a basis for

the Electronic Patient Record (EPR) and Electronic Health Record (EHR). For

the patient this means that their health care worker has access to legible and

structured information about their needs and treatment advice on their

condition.

Providing Information

This requires information to be delivered in new ways and through modern

systems. This is focused on providing access to information on the desk top, in

the surgery, in the outpatient clinic, at the bedside and on the move.

Page 72 of 78

Patients, their carers and the public will have access to accredited information

and guidance to help to stay healthy, avoid illness and cope with their

conditions. Access to reliable information will help to enable greater

involvement of patients in their care.

Clinical staff will have electronic access to the latest knowledge, evidence

base and clinical guidelines for improved decision making and professional

development

Underpinning this access to information will be maintenance of Patient

confidentiality and patient rights to be assured of the security of their

information and systems and processes must be in place to ensure this.

Developing the necessary Infrastructure

Ensuring that the underpinning IM&T infrastructure is in place, e.g.

Workstations with telecommunications in appropriate locations for all

appropriate staff.

Equally as important is ensuring that the underpinning people issues including

appropriate IM&T support and training for NHS staff and HR policies that

address recruitment and retention of specialist IM&T staff.

13.4 New Mid Argyll Hospital

This project to achieve the Modernisation and Redesign of Primary and

Community Health and Social Care services in Mid Argyll has from its outset

focused on service redesign integration and whole system service provision

and this has led the building design and development process.

The New Mid Argyll Hospital project in Lochgilphead is undoubtedly the

model for future Health and Social care provision in not only remote rural

communities but also potentially fragile urban acute and primary health care

services.

It is focused on true integration and partnership bringing together Primary

Care, Community, Mental Health, Acute, Ambulance Services and Social

Service. This bringing together is not simply under one roof, but as an

integrated health and social care system providing fast and effective access for

patients and clients to health maintenance and ill health treatment services with

a focus on rapid intervention, treatment and rehabilitation.

The project embraces all National, Health Board and local policies and

objectives, significantly supports the future sustainability of clinical services

and by default rural communities.

The project meets the strategic agenda for Health Care as identified in “Our

National Health - A Plan for Action, A Plan for Change” and is also consistent

Page 73 of 78

with the publication from the Primary Care Modernisation Group “Making the

Connections - Developing Best Practice into common Practice, RARARI

report “ Solutions for the provision of Health Care in the remote and Rural

areas of Scotland in the 21st Century” and the Temple Report “Future Practice

– A Review of the Scottish Medical Work Force”.

13.5 New Service Models

The new service model developed as part of the FBC process focuses very

much on true integration between Primary & Community Care and Hospital

services.

There is a shared central reception housing medical records for Dental, GP,

Community hospital and AHP‟s. Clinical consulting accommodation will be

available for multiuse by different professions to maximise asset utilisation.

Clinical administration work will be housed within a number of open plan

rooms occupied by different professionals as and when the need arises

Practice Nurses and hospital nurses will be working side by side providing

triage and A&E and Nurse practitioner services.

There will be one-stop shops for patients for chronic disease management

seeing a multidisciplinary team for assessment, treatment, and ongoing review

in multi use/functional consulting rooms

Access to appropriate patient information, co-ordination of appointments

between services and agencies for transport provision and secondary care

services will require to be streamlined and available at one point to support

effective working to ensure seamless service provision to the patient.

The co-location of Social services into the same building offers significant

opportunities for closer and effective working re patient and clients whole care

needs. Therefore the opportunity to address not only the joint future agenda

but also future shared services re children, learning disability etc will also be

maximised. However, it is expected that over the next 3-5 years this service

will operate as a discreet and separate entity.

13.6 IM&T Implications

To truly support this way of working will require a review and streamlining of

paper based and IM&T systems for health service provision in the new facility.

Work has already commenced in bring the reception and admin staff from all

areas together to work through what the new model of care and service will

mean in practice to service operation and patient need.

Clinicians in all professions are very keen to utilise new Technology to

enhance the service they offer to patients and assist in measuring clinical

service performance and effectiveness. In addition the opportunity to conduct

Page 74 of 78

needs analysis by having access to local epidemilogical information e.g.

morbidity will support service refinement and development.

Underpinning this must be a practical and effective IM&T network/system to

allow the professionals and support staff to concentrate on patient care

providing a first class service re patient/clients needs e.g. when they wish to

find information, access services and require health care.

13.7 Next Steps

A number of meetings have been held with service users and IM&T

professional including representatives from the SEHD over the last 6 months

to assess the service operation needs.

It is recognised by all users that an operational solution to support this

model/vision of integrated health service provision is not derived from IM&T

systems. It is developed from operational service need .

The Trust and locality will therefore complete a formal mapping exercise of

the existing service and overlay the requirements for the future service. To this

end the Trust will be commissioning a 6-month systems mapping project to

develop the operating systems for the new service by utilising consultant

expertise with extensive patient, user, IM&T and SEHD input.

The results of this exercise will be used to identify the operational system

requirement including IM&T solutions to implement the new service in April

2005. The Trust will be including within its development planning process the

identification of resources to implement the service systems/processes/staff

training/change management process required.

15 Equipment

15.1 The service to be provided by the consortium will cover:

The purchase, installation and commissioning, where appropriate,

of all NHS standard Group 1, 2, and 3 furniture and equipment for

all hospital specific needs, all hospital support needs and all

administrative and management purposes.

The delivery of the „Required Outcomes‟ relating to the initial

procurement of equipment detailed in the Output Specification and

consolidated into the contract.

Training for the use of certain categories of equipment provided at

service commencement.

Page 75 of 78

Liaison with Trust staff to ensure appropriate choice of furniture

and equipment is available to them.

Procurement of whole hospital type equipment which is not

normally associated with specific departments or rooms i.e.

wheelchairs, trolleys etc.

15.2 The Consortium will not be responsible for providing:

Group 4 equipment except window blinds, curtain tracks, curtains

etc.

Group 3 computers.

15.3 None of the Trust‟s existing equipment can be transferred into the new

hospital except the following items, which will be replaced by the Trust once

they have reached the end of their useful life:

A general purpose radiographic system.

The Trust‟s telemedicine equipment.

Medical records storage / racking system

15.4 The Consortium will be responsible for ensuring that the new facility is

capable of accommodating this existing equipment once it is ready to be

moved. To ensure that this is achieved the Consortium has given careful

consideration to the method to be used for transporting the equipment into the

new development, its sensitivity to excessive movement, its size and bulk and

its requirements for specialist technical commissioning procedures to be

carried out much earlier than normal equipment. Care has been taken in the

development of the design over the width and height of doors, loading

specifications for floors, the turning circles of the equipment and location of

engineering services. The responsibility for arranging and effecting its

removal will generally remain with the Trust.

15.5 At Service Commencement, i.e. following technical commissioning of the new

hospital, the Consortium will have provided a fully furnished and equipped

hospital with everything in place, tested and commissioned, and ready for use.

The specification of equipment to be provided at service commencement is

being developed between the Trust and the Consortium through joint

agreement of:

Room data sheets for each functional area to be provided in the

new building.

Page 76 of 78

Room layout drawings at 1:50 scale of jointly agreed exemplar

functional areas.

The specification and general suitability criteria of items costing

more than £1000.

The final schedule of equipment.

The overall operational commissioning strategy for all the

furniture and equipment and the technical commissioning details

for specialist equipment.

15.6 Throughout this process the Consortium has retained the risk and

responsibility for providing a fully furnished and equipped hospital to meet the

needs and demands of the Trust that is suitable for providing a modern and

efficient healthcare service to its patients at service commencement.

15.7 The replacement of Group 1 equipment will be the Consortium‟s

responsibility. The Consortium will not be responsible for the maintenance or

replacement of group 2, 3 or 4 equipment. By retaining responsibility for this

the Trust will retain flexibility to respond to technological and service

developments and to continuously improve ways of working.

15.8 Furniture or equipment that is identified as being damaged by the Consortium

will be repaired and / or replaced by the Consortium and will not be included

within the Trust‟s annual equipment budget expenditure.

15.9 The PPP/PFI Contract imposes an obligation on the Consortium for providing

all necessary information to enable the Trust to monitor the extent to which it

is fulfilling its responsibility for the furniture and equipment procurement

service. The payment mechanism within the contract exposes the Consortium

to payment deductions and Trust “step in” rights in the event of failure to meet

the defined performance standards relating to equipment for the practical

completion of the facility.

16 Personnel Issues

16.1 The numbers and mix of staff employed in the services provided from the new

facility will change radically. In all cases these changes involve increased

staffing to provide the extended range of services enabled by the new facility.

The main human resource challenges for NHS Argyll and Clyde are therefore:

Recruitment and retention of a skilled and motivated workforce to deliver

the high quality services that it will be able to offer from the new facility.

Page 77 of 78

Seeing through the change management process that has so far driven the

concept, high level operational policies and design of the new facility.

Alignment of terms and conditions for support staff.

Adoption of common working practices.

16.2 To achieve successful change management outcomes key staff will continue to

be involved in a process of developing detailed operational policies and

service commissioning plans that will be incorporated into the benefits

realisation plan described in section 11 of this FBC.

16.3 In line with the service commissioning plan NHS Argyll and Clyde will

actively promote the modernised service in order to attract the best staff.

Features of the service that it will particularly highlight are:

The broadening of the skill base of staff working in the service.

The focus on health maintenance, prevention of illness and the promotion

of independence.

A culture of continuous improvement seeking the provision of evidence

based services, delivering better outcomes for people using them through

quality assured processes.

The opportunity that staff will be given to continuously review and

develop their skills. The Human Resource Plan backs this up by making

provision for periodic formal skills assessment to identify priority

training needs and to inform the development of training plans. The first

of these is being carried out now in preparation for the commissioning of

new services.

The opportunity to pursue modern ways of working, with modern

equipment, using modern technology including telemedicine and tele-

radiology, in modern surroundings.

The encouragement of integrated multidisciplinary working between all

services and agencies using the facility.

The encouragement of flexible working practices and the provision of

high quality staff facilities.

16.4 The recruitment and retention plan will involve working together with other

agencies to identify partner skills and joint recruitment opportunities. It will

also incorporate back to work initiatives.

16.5 A process has been put in place to examine the differences between staff terms

and conditions and propose ways of aligning them.

Page 78 of 78

16.6 To prepare staff for the adoption of common working practices, NHS Argyll

and Clyde are launching a programme of organisation development events

including informal meetings, away days, job swaps, role assessment and job

redesign forums. This will followed through for all staff with an extensive

induction and training programme.

16.7 The Human Resource Plan is supported by the NHS Argyll and Clyde policy

on openness and communications. This policy has been demonstrated in

practice in the participative planning and formal consultation processes that

have been a feature of the management of the project to date. It will continue

to drive the way in which NHS Argyll and Clyde will work with its staff as

key stakeholders over the detailed planning and operation of the new facility.

16.8 None of the existing staff is transferring to the consortium and there are no

issues under TUPE for NHS Argyll and Clyde to resolve.

17 Conclusion

17.1 This FBC is based on a rigorous appraisal of the options available to the Trust

for delivering the required changes in service provision. A preferred option

has emerged from this process which will fully meet the Project Brief. This

option can be delivered through the PPP/PFI procurement route using the

private sector partner selected by the Trust following the European

Procurement Regulations Negotiated Procedure. This option provides best

value for money, is broadly affordable and enables the private sector partner to

bear significant risks associated with the project. The Trust is seeking

approval from the NHS Argyll & Clyde Board and the SEHD to the Business

Case and to authorise the Trust‟s partnership with Canmore Consortium to

progress to commercial and financial close.

18 Specific Statements to confirm:

18.1 Statements required from NHS Argyll & Clyde that the development fits with

the Local Health Plan, the Financial Plan, the Property Strategy and the

objectives of the NHS Board will be provided following the Board meeting on

12 May 2003.

Financial Appendices

Financial Appendices