Upload
lythuy
View
226
Download
5
Embed Size (px)
Citation preview
Front End Engineering Design (FEED) Challenges in EPC Projects: Design, LLI Strategy & Fast Track
By Armando Bianco, Engineering Manager, Eniprogetti
Global Conference on EPC Contract & Project Management
9th-10th November 2017 Lisbon, Portugal
progetti
Index
Eni
Design Basis, Key Deliverables & Battery Limits: how to approach a Front End Engineering Design
Balance between engineering freezing and early procurement: Long Lead Items strategy
Fast Track: Basic, FEED & Detail Design phases in overlap aiming at Project goals
Conclusions
eniprogetti 2
3
Eni
eniprogetti
Design Basis, Key Deliverables & Battery Limits: how to approach a Front End Engineering Design
eniprogetti 4
eniprogetti 5
Feasibility 2-4 MM (typical ref.)
Basic - FEED 3-9 MM (typical ref.)
Detail Design & Procurement
9-18 MM (typical ref.)
Construction Commissioning
12+ MM (typical ref.)
Pre-feasibily 1-3 MM (typical ref.)
Appraisal / Evaluation: assess e t of the opportu it ’s eco o ic alue
Selection: choice of optimal development configuration
Definition: finalization of the development concept
Execution: detailed development and physical
realizatio of the scope of the project’s ork
Project expenditure
Capital Risk
Difficulty to implement
changes
Personnel involved
Stakeholders’ e pectatio s
Time
G1 G2 G3
Oil and Gas Project Development Phases
eniprogetti 6
Identification and analysis of the main process and
utilities for each generated concept alternative
Preparation of process specifications, design criteria, for all
processes , utilities and transportation systems. Preliminary
engineering, safety and constructability.
Finalization of all processes, utilities and
transportation systems.
Design of all engineering systems
Constructability reviews finalization
3D model
Detail Engineering Design
Procurement and Construction
Technology selection report
Preliminary Heat & Material balance
Block Flow Diagram
Preliminary Site Plan
Process Flow Diagrams
Battery Limits Table
Preliminary P&I Ds
Equipment Data Sheets Design Criteria
Preliminary Plot Plan
Finalization of Heat & Material balance, P&ID & Equipment and
packages DS
Plot Plan, Equipment layouts, Underground layouts
Finalization of Technical Specifications (Stress analysis Criteria)
Single lines for steel structures
Preli i ar MTO’s Pipi g ( st MTO)
P&ID (with vendor information)
Equipment DS (for all items)
Details MTO (2nd and 3rd)
Isometrics
Construction drawings
Stress Reports
Project Development Phases Key Activities -> Key Deliverables (es. for process and piping and layout engineering)
Feasibility 2-4 MM (typical ref.)
Basic - FEED 3-9 MM (typical ref.)
Detail Design & Procurement 9-18 MM
(typical ref.)
Construction Commissioning
12+ MM (typical ref.)
Pre-feasibily 1-3 MM (typical ref.)
Support to Construction
and commissioning
Feasibility
Red-marked and as-built
What if… … Desig Bases are not finalized
Example: the pressure of the Sea Water Make-up (rely upon information) was significantly different from the reality.
Technical resolution: lower the pumps with an additional basin (groundwater level very high).
Impact: additional costs and delay in schedule
… Key Deliverables are not ready as needed
Example: the supply of a critical reactor was assigned to a vendor in the Far East and a shipping to North Africa was
fixed in advance. Due to the delay in the 3D model, the nozzle orientation was not ready as per original plan agreed
with the vendor resulting in late finalization of the vendor engineering and eventually of the supply.
Recovery plan: an acceleration plan was agreed with the vendor to meet shipping window.
Impact: additional costs
… Battery Li its are not aligned (process-wise)
Example: two different mechanical contractors were assigned to install the cooling water circuits in the relevant area
and a battery limits was established. During the commissioning phase after the battery limits were connected it was
noticed that one contractor inverted the connection from a process point of view.
Technical resolution: the connections were modified during commissioning and with acceleration in procurement for
the unforeseen additional material during commissioning
Impact: delay during commissioning phase
eniprogetti 7 Note: Lesson Learnt not related with ENI projects
How Design Basis, Key Delivery and B.L. can affect a Project
eniprogetti 8
Feasibility 3-6 MM
Basic - FEED 3-9 MM (typical ref.)
Detail Design & Procurement 9-18 MM
(typical ref.)
Construction 12 – 32 MM (typical
ref.)
Construction Commissioning
12+ MM (typical ref.)
Pre-feas. 1-3 MM
va
lue
time
Project Cost
Curvet
Availability of
InformationPeak
Material
Cost
Peak
Construction
Cost
Material
Selection &
Take-off
BOQ &
Construction
strategy
Why Basic-FEED is the most important part of a Project?
During Basic – FEED project costs can be properly evaluated by finalization of material
selectio a d MTOs, owi g to that this phase is the ost i porta t for the go/ o go final assessment
$
(typical ref.)
Design approach – Key points
eniprogetti 9
The Basic - FEED engineering shall be tailor fit to allow the correct definition of
the i vest e t cost a d to support the go / o go decisio gate 3 (key deliverables fit for purpose to the activities and not vice-versa);
In Basic – FEED phase, the key deliverables allow to fix the material selection
and estimate material take-offs which are the input for the procurement and
construction strategy based on the project drivers;
Balance between engineering freezing and early procurement: Long Lead Items strategy
eniprogetti 10
Long Lead Items definitions
eniprogetti 11
Those components of a system or piece of equipment for
which the times to design and fabricate are the longest and
for which an early commitment of funds may be desirable or
necessary in order to meet the earliest possible date of
system completion.
Critical Path
eniprogetti 12
The critical path is the sequence of activities that represents the longest path through a project, which
determines the shortest possible project duration [PMBOK 6.6.2.2 Critical Path Method]
Appling Critical Path method for all the systems of a project, even material with a rather short
delivery can result to be critical, owing to that we can split LLI in two categories:
Typical LLI such as:
• High pressure equipment
• High temperature equipment
• Special Material equipment
Not Typical LLI such as:
• Tie-ins: integration with existing Facilities
• Bulk material for early commissioning system
Tie-ins: integration with existing Facilities
eniprogetti 13
Dismantelling
Detail Design & Procurement
PRODUCTION PLAN of EXISTING FACILITIES
Production Shut-
down UNIT 10
UNIT 20
UNIT 30
TIE-INS
OVERALL SCHEDULE INTEGRATED WITH PRODUCTION PLAN
Plant to be disinvested
Production Shut-
down
EARLY PROCUREMENT
EARLY CONSTRUCTION
EARLY COMMISSIONING
FEED 3-9 MM (typical ref.)
Detail Design & Procurement 9-18 MM
(typical ref.)
Construction 12 – 32 MM (typical
ref.) PROCUREMENT FOR LLI
Commissioning 3- 12 MM (typical ref.)
Feasibility Study
FEED
Construction
Commissioning
TIE-INS
TIE-INS
INSTAL.
Dismantelling Dismantling
Shut-
down
Shut-
down
Shut-
down
EARLY ENGINEERING
Shut-
down
TIE-INS INSTAL.
Dismantling Shut-
down
PROCUREMENT FOR TRADITIONAL LLI
Shut-
down
REFERENCE GREEN-FIELD PROJECT SCHEDULE
Tie-ins shall be planed in an early stage of the project, with a dedicated engineering,
construction and commissioning team. The project schedule incorporates the production
plan in terms of turn-around or critical milestones.
Feasibility 3-6 MM
(typ.Ref.)
Pre-feas. 1-3 MM
(typ.Ref.)
Bulk Material for Early Commissioning System
eniprogetti 14
Engineering design for bulk material is
aimed to produce MTOs with increased
levels of definition
Procurement generally follows the
MTO by engineering based on master
agreements or project agreements
Construction strategy is divided into:
1st phase by area
2nd phase by system
During the engineering phase it is important to verify that the delivery of bulk material
fits the Mechanical Completion dates (additional specific MTOs can be envisaged).
Long Lead Items strategy – Key points
eniprogetti 15
The critical path developed for all the project systems allows us to recognize
critical delivery items which do not have the longest delivery such as tie-ins or
bulk material for early commissioning system, which shall be focused since the
start of the project with a dedicated integrated team (engineering,
construction and commissioning);
For a revamping project, the integration of the production plan in the project
baseline allows to execute tie-ins during turn-around, minimizing the number
of shut-downs and avoiding unnecessary loss of production;
Fast Track: Basic, FEED & Detail Design phases in overlap aiming at Project goals
eniprogetti 16
If you're not confused, you're
not paying attention.
Tom Peters
Project objectives and Fast-Track Projects
eniprogetti 17
Detail Design & Procurement
Feasibility 3-6 MM
(typ.Ref.)
Basic - FEED 3-9 MM (typical ref.)
Detail Design & Procurement 9-18 MM
(typical ref.)
Construction 12 – 32 MM (typical
ref.)
Commissioning 3- 12 MM (typical ref.)
Feasibility Study
FEED
Detail Design & Procurement
Pre-F.
FEED
Pre-feas. 1-3 MM
(typ.Ref.)
Feasibil.
• Opt.1) Compress the activity lengths
• Opt.2) Fast-Track by parallelization
of phases
Possible outcomes when implementing a Fast-Track in a project
eniprogetti 18
Relying
upon preliminary
information
Higher
Cost
Higher
Risk
More
Engineering
Man-hours
More
Reworks
More difficult
engagement of
personnel
Overdesign
material
Design based
on assumptions
Increased
interface
management
Not linear
approach in
decision making
Increased
possibility of
inconsistencies
Which it the greatest
objective?
How to mitigate risks in fast-track projects
eniprogetti 19
Detail Design & Procurement
Feasibility Study
FEED
Final alignment
TEAM
If the approach is aligned
since the beginning with a
common goal, all the team
is aimed to support
unavoidable project changes
and reworks activities
ENGINEERING
Preliminary information
evaluated from Basic (used
for detail design) are
always re-checked when
more information are
available
MATERIAL
Material check/re-rated
is re-consolidated both in
Basic and Detail Design
to avoid reworks during
construction and
commissioning
Re-cycling
Design inputs/outputs
D
ENGINEERING
Final alignment mitigates risk
of further phases for critical
aspects
MATERIAL
When procurement cycle
is long, procurement can
be start with preliminary
data, updating more
consolidated information
during the vendor
alignment before PO
Case Study
eniprogetti 20
Detail Design & Procurement
Feasibility Study
FEED
D
Project Organization
Engineering Approach: Re-cycling Design
1. Process and Layout for critical circuit
2. 3D Model Review 30% and 60%
3. Material Selection
4. Vendor design
5. Design Philosophy – Operating manual
eniprogetti
OWNER
BASIC –FEED
CONTRACTOR DETAIL ENG.
CONTRACTOR
VENDOR
SUB.
CONTRACTOR
VENDOR
FEASIB
ILI
TY
BASIC
-
FEED
DETAIL
ED
EN
G.
PRE-
FEAS.
CONSTRUCTION
CONTRACTOR
CONSTRUCTION
CONTRACTOR
CO
NSTRU
CTIO
N
SUB.
CONTRACTOR
SUB.
CONTRACTOR
SUB.
CONTRACTOR
VENDOR
LICENSOR
FAST
-TR
AC
K
FEASIBIL. CNT
Case Study Organization Chart
Interface Management
#1: Process and Layout for critical circuit
eniprogetti 22
File by
A B C IN OUT IN OUT IN OUT IN OUT IN OUT IN OUT
EST9 4 SA 1 351 351 351 351 351 351 351 351 351 351 351 351 351 351 351
EST9 4 SA 2 380 380 380 380 380 380 380 380 380 380 380 380 380 380 380
EST9 4 SA 3 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5
EST9 4 SA 4 351 351 250 351 351 351 351 250 250 351 351 351 351 250 250
EST9 4 SA 5 250 351 351 250 250 351 351 351 351 250 250 351 351 351 351
EST9 4 SA 6 351 250 351 351 351 250 250 351 351 351 351 250 250 351 351
EST9 4 SA 7 351 351 351 351 351 351 351 351 351 250 250 250 250 250 250
x x x x x x x x x x x x x x x
CEER 4 CEER 1 351 351 250 351 351 351 351 250 250 250 250 250 250 250 250
CEER 4 CEER 2 351 250 351 351 351 250 250 351 351 250 250 250 250 250 250
CEER 4 CEER 3 250 351 351 250 250 351 351 351 351 250 250 250 250 250 250
CEER 4 CEER 4 351 351 250 351 351 351 351 250 250 351 351 351 351 250 250
CEER 4 CEER 5 351 250 351 351 351 250 250 351 351 351 351 250 250 351 351
CEER 4 CEER 6 250 351 351 250 250 351 351 351 351 250 250 351 351 351 351
CEER 4 CEER 7 351 351 351 351 351 351 351 351 351 351 351 351 351 351 351
CEER 4 CEER 8 380 380 380 380 380 380 380 380 380 380 380 380 380 380 380
CEER 4 CEER 9 351 351 351 250 250 250 250 250 250 250 250 250 250 250 250
CEER 4 CEER
CEER 4 CEER
CEER 4 CEER
In Process: Pump Nozzle Alignment for installation case, Pumps ABC at ambient
temperature , piping not anchored to the pumps.
In Process: Pump Nozzle Alignment for maintenaince case, Pump A, B or C as spare.
In Process: Tracing Failure Scenario analysis
Ca
se
PUMP
DISCHARGEFV s Valves Flow PSVs Valves Flow
FVA FVB FVC PSVA PSVB PSVC
BASIC-FEED
CONTRACTOR
DETAIL ENGINEERING
CONTRACTOR
1) PRELIMINARY
SIZE CALCULATION &
PLOT PLAN
2) PROCESS SCENARIOS
(DESIGN CASES AND
TRANSIENTS)
3) STRESS
CRITERIA
WITH
PRELIMINARY
CRITICAL
VERIFICATION
AND TYPICAL
DETAILS
6) UPDATING PROCESS LINE
CALCULATION & PLOT PLAN
4) 3D
LAYOUT
5) STRESS
CALCULATION
#2: 3D Model Review 30% AND 60%
eniprogetti 23
BASIC-FEED
CONTRACTOR
DETAIL ENGINEERING
CONTRACTOR
BASIC-FEED
CONTRACTOR
DETAIL ENGINEERING
CONTRACTOR
#3: Material Selection (Piping)
eniprogetti 24
Fluid list
Process Fluid List
Material Requirements
Vendor
Follow-up
Piping Classes
Material requisition &
Purchase Order
BASIC-FEED
CONTRACTOR
DETAIL ENGINEERING
CONTRACTOR
#4: Vendor design
eniprogetti 25
Process DataSheet
Mechanical and
Material Check
Vendor
Follow-up
Material Requisition
BASIC-FEED
CONTRACTOR
DETAIL ENGINEERING
CONTRACTOR
#5: Design Philosophy – Operating manual
eniprogetti 26
Updating Process
Design
Updated Control
Philosophy
Operating
Manual
Process Philosophy
Operating Scenarios
Design
Scenarios
BASIC-FEED
CONTRACTOR
DETAIL ENGINEERING
CONTRACTOR
Fast Track – Key points
eniprogetti 27
The Fast Track with parallelization of phases which traditionally are developed
sequentially is a possible strategy to meet Project Objectives when the
schedule is challenging;
To mitigate the risk associated to fast track (more interfaces, reworks,
designing by conservative assumptions rather that consolidated data etc.)
project team needs to be integrated with an interface management plan and
dedicated engineering methods such as re-cycling and final alignment need to
be set-up in the engineering execution plan.
Conclusions - Key Factors for Basic-FEED Projects
eniprogetti 28
Tailor fit Design by Project Objectives
Advanced monitor of costs with correct Basic-FEED data
System-wise approach since the beginning of the project
For revamping, integration of project schedule with production plan
Interface management, re-cycling and final alignment for fast-track project