From: Akaruchai Nochaiwong [email protected] Subject: Daily Operation update on R&D S1 Electromagnetic survey for Waterflood Monitoring in Tap Reat Area: 2 March 2016 Date: March 3, 2016 at 7:56 AM To: Somporn Rassadanukul [email protected], Geerati Pombunmee [email protected], Phathompat Boonyasaknanon [email protected], Sumeth Anantasate [email protected], Panumat Yoosin [email protected], Udom Arayatanon [email protected], Chiradet Khachamart [email protected], Angkana Sriwantaneeyakul [email protected], Saovajit Nanruksa [email protected], Worravit Tragunveerayut [email protected], Nontapong Panudulkitti [email protected], Prapun Sooksawat [email protected] Cc: Chalermkiat Tongtaow [email protected], Piya Sukhumpanumet [email protected], Nopadon Chinabutr [email protected], Supakorn Krisadasima [email protected], Tawee Limsoontorn [email protected], Suwit Pabchanda [email protected], Phanachit Dhanasin [email protected], Sutus Preuksjamas [email protected], Songkram Noikongdee [email protected], Patchara Chacharoen [email protected], Piti Akrapipatkul [email protected], Poonsawat Prachukbunchong [email protected], Padsakorn Suwanruji [email protected], Sarawut Uparawanna [email protected], Panlop Limsakul [email protected], Chalong Jaruwattanasakul [email protected], Alisara Ngamlurdwongsakul [email protected], Inthira Kongbua [email protected], Kurt Strack ([email protected]) [email protected], Sophon Jumras [email protected], Anupong Kongsub [email protected], Ing-orn Soisuwan [email protected], Patcharin Kaewkert [email protected] , GGS-O Staff [email protected] Dear All, Please see below for daily operation update: Site preparation - Fence preparation is 90% complete. - Foundation preparation: o lighting system and foundation is in progress. - Cabin, toilet, oil tank and guard house will arrive on Friday. - Preparation of electrical work is in progress. - Trench digging: PTW for trench digging complete à Trench digging is about 15% complete (300m) - Security guard will be available on Friday. - Fuel service is available at LKU. Need one day notice in advance for fuel delivery. Equipment mobilization - Wire (5000m): confirm mobilization on Saturday - HDPE (5000m): confirm mobilization on Saturday - Generators: confirm mobilization on Saturday - EM equipment: Plan to mobilization on Monday à contact PCRC for mobilization PR / CSR / DMF - Letter of invitation to DMF is in progress. à 3 DMF will join PR during 8 March 2016. - Public relationship (PR) at Tambol Bung Thap raet: all documents (Short brochure, presentation, and questionnaire) will finalize soon. - Plan to have public communication on 8 March 2016 SSHE - Wire deviation complete - Generators deviation is complete - PTW for Site preparation was endorsed by S1 construction team and GGS/O (as area owner) - PTW for trench digging was endorsed by S1 construction team and GGS/O (as area owner). - Prepare PTW for lifting work. Review documents on Wednesday. - HSE statistic: No HSE issue yet. Drilling program (GGS/O team, S1 Planning teams) - There is drilling program in TRT-E à Rig E09 complete drilling program. Rig move to LKU-Y07. PERF program will be around April 2016.

From: Akaruchai Nochaiwong - KMS Technologies MOU/daily reports/Daily... · From: Akaruchai Nochaiwong [email protected] Subject: Daily Operation update on R&D S1 Electromagnetic

Embed Size (px)

Citation preview

From: Akaruchai Nochaiwong [email protected]: Daily Operation update on R&D S1 Electromagnetic survey for Waterflood Monitoring in Tap Reat Area: 2 March 2016

Date: March 3, 2016 at 7:56 AMTo: Somporn Rassadanukul [email protected], Geerati Pombunmee [email protected], Phathompat Boonyasaknanon

[email protected], Sumeth Anantasate [email protected], Panumat Yoosin [email protected],Udom Arayatanon [email protected], Chiradet Khachamart [email protected], Angkana [email protected], Saovajit Nanruksa [email protected], Worravit Tragunveerayut [email protected],Nontapong Panudulkitti [email protected], Prapun Sooksawat [email protected]

Cc: Chalermkiat Tongtaow [email protected], Piya Sukhumpanumet [email protected], Nopadon [email protected], Supakorn Krisadasima [email protected], Tawee Limsoontorn [email protected],Suwit Pabchanda [email protected], Phanachit Dhanasin [email protected], Sutus [email protected], Songkram Noikongdee [email protected], Patchara Chacharoen [email protected],Piti Akrapipatkul [email protected], Poonsawat Prachukbunchong [email protected], Padsakorn [email protected], Sarawut Uparawanna [email protected], Panlop Limsakul [email protected],Chalong Jaruwattanasakul [email protected], Alisara Ngamlurdwongsakul [email protected], Inthira [email protected], Kurt Strack ([email protected]) [email protected], Sophon Jumras [email protected],Anupong Kongsub [email protected], Ing-orn Soisuwan [email protected], Patcharin Kaewkert [email protected], GGS-O Staff [email protected]

Dear All, Please see below for daily operation update: Site preparation

- Fence preparation is 90% complete.- Foundation preparation:

o lighting system and foundation is in progress.- Cabin, toilet, oil tank and guard house will arrive on Friday.- Preparation of electrical work is in progress.- Trench digging: PTW for trench digging complete à Trench digging is about 15%

complete (300m)- Security guard will be available on Friday.- Fuel service is available at LKU. Need one day notice in advance for fuel delivery.

Equipment mobilization

- Wire (5000m): confirm mobilization on Saturday- HDPE (5000m): confirm mobilization on Saturday- Generators: confirm mobilization on Saturday- EM equipment: Plan to mobilization on Monday à contact PCRC for mobilization

PR / CSR / DMF

- Letter of invitation to DMF is in progress. à 3 DMF will join PR during 8 March 2016.- Public relationship (PR) at Tambol Bung Thap raet: all documents (Short brochure,

presentation, and questionnaire) will finalize soon.- Plan to have public communication on 8 March 2016

SSHE

- Wire deviation complete- Generators deviation is complete- PTW for Site preparation was endorsed by S1 construction team and GGS/O (as area

owner)- PTW for trench digging was endorsed by S1 construction team and GGS/O (as area

owner).- Prepare PTW for lifting work. Review documents on Wednesday.- HSE statistic: No HSE issue yet.

Drilling program (GGS/O team, S1 Planning teams)

- There is drilling program in TRT-E à Rig E09 complete drilling program. Rig move toLKU-Y07. PERF program will be around April 2016.

Best regards,Akaruchai N.

ELECTRONIC MAIL DISCLAIMER:The electronic transmission, information and any attached documents contained in this e-mail are confidential, proprietaryto the sender, and are intended only for the person or entity to which it is addressed. If you have received this electronictransmission in error, please immediately notify the sender and delete or destroy the original electronic transmission andany attached documents from your system without copying it, disclosure or distribution or the taking of any actionconcerning the contents of this electronic transmission or any attachments. Any review, distribution, copying,retransmitting, dissemination, disclosure or use of this electronic transmission or any part of it in any form for any purposewhatsoever is strictly prohibited and subject to liability and legal claim. Please be aware that electronic transmissioncannot be guaranteed to be secure or error free as information could be intercepted, corrupted, lost, destroyed, arrive lateor incomplete, or contain viruses. The sender therefore does not accept liability for any errors or omissions in the contentsof this message which arise as a result of electronic transmission. If verification is required please request a hard copyversion.