Framework PMO Best

Embed Size (px)

Citation preview

  • 7/31/2019 Framework PMO Best

    1/38

    PROJECTMANAGEMENT

    OFFICE

    FRAMEWORK PROJECTNAMEPMOFramework

    DOCUMENTAUTHOR

    PMOTeam

    FILENAMEandVERSION

    ISSUED

    08.08.11

    LASTREVISED

    12.01.11

    Thisdocumentisprovidedforguidanceinthe

    overarchingapproachtoProjectManagement

    implementedbytheUNCInformation

    TechnologyServicesProjectManagement

    Office.This

    document

    also

    includes

    the

    variousITSPMOtemplatedocuments.

  • 7/31/2019 Framework PMO Best

    2/38

    ITSPMOProjectManagementFramework.docx2

    TABLEOFCONTENTSITSPROJECTMANAGEMENTOFFICE:WELCOME...............................................................................................5ITSPMO:PMSTANDARDSANDRESOURCES.....................................................................................................6FRAMEWORKDOCUMENTORGANIZATION........................................................................................... 6

    SectionOne:ProjectManagementLifecycles.................................................................................................... 6

    Section

    Two:

    Project

    Management

    Skill

    Areas

    ..................................................................................................

    6

    PROJECTMANAGEMENTLIFECYCLES..................................................................................................... 7

    PROJECTDOCUMENTRESOURCES......................................................................................................... 8

    PROJECTDOCUMENTTEMPLATES......................................................................................................... 9

    PROJECTCHECKPOINTS.......................................................................................................................... 9

    WHENISAPROJECTAPROJECT?......................................................................................................... 10

    PROCESSSELECTIONGUIDE................................................................................................................. 11

    ITSPMORESOURCES............................................................................................................................ 12SECTION1:PROJECTMANAGEMENTCYCLES...................................................................................................13PROJECTMANAGEMENTCYCLE:INITIATE........................................................................................................13INITIATE:PROJECTDOCUMENTRESOURCES....................................................................................... 13

    ProjectInitiate.................................................................................................................................................. 13

    INITIATE:PROJECT

    DOCUMENT

    TEMPLATES

    ........................................................................................

    13

    INITIATE:PROJECTCHECKPOINTS........................................................................................................ 13

    Checkpoint#1.................................................................................................................................................. 13PROJECTMANAGEMENTCYCLE:PLAN.............................................................................................................13PLAN:PROJECTDOCUMENTRESOURCES............................................................................................. 14

    ProjectCharter................................................................................................................................................. 14

    ProjectPlan...................................................................................................................................................... 14

    PLAN:PROJECTDOCUMENTTEMPLATES............................................................................................. 14

    CostTracking|MicrosoftExcel,SharePoint.................................................................................................... 14

    ProjectSchedule|MicrosoftProject,Excel,SharePoint................................................................................. 14

    StakeholderLog |MicrosoftExcel,SharePoint............................................................................................ 15

    CommunicationManagementPlan|MicrosoftWord,SharePoint................................................................ 15

    RiskForm

    |Microsoft

    Word,

    SharePoint

    .........................................................................................................

    15

    RiskLog|MicrosoftExcel,Sharepoint............................................................................................................. 15

    ProjectStatusReport|MicrosoftWord,SharePoint...................................................................................... 15

    IssueForm|MicrosoftWord,SharePoint....................................................................................................... 15

    IssueLog|MicrosoftExcel,SharePoint........................................................................................................... 15

    PLAN:PROJECTCHECKPOINTS.............................................................................................................. 16

    Checkpoint#2.................................................................................................................................................. 16

    Checkpoint#3.................................................................................................................................................. 16PROJECTMANAGEMENTCYCLE:EXECUTE.......................................................................................................16EXECUTE:PROJECTDOCUMENTRESOURCES....................................................................................... 16

    EXECUTE:PROJECTDOCUMENTTEMPLATES....................................................................................... 16

    EXECUTE:PROJECT

    CHECKPOINTS

    ........................................................................................................

    16

    PROJECTMANAGEMENTCYCLE:MONITORANDCONTROL.............................................................................16MONITORANDCONTROL:PROJECTDOCUMENTRESOURCES............................................................ 17

    MONITORANDCONTROL:PROJECTDOCUMENTTEMPLATES............................................................ 17

    ChangeRequestForm|MicrosoftExcel,Sharepoint...................................................................................... 17

    ChangeLog|MicrosoftWord,Sharepoint...................................................................................................... 17

    MONITORANDCONTROL:PROJECTCHECKPOINTS............................................................................. 17

    Checkpoint#4.................................................................................................................................................. 17PROJECTMANAGEMENTCYCLE:CLOSE...........................................................................................................17

  • 7/31/2019 Framework PMO Best

    3/38

    ITSPMOProjectManagementFramework.docx3

    CLOSE:PROJECTDOCUMENTRESOURCES........................................................................................... 18

    ProjectClose..................................................................................................................................................... 18

    CLOSE:PROJECTDOCUMENTTEMPLATES........................................................................................... 18

    AcceptanceForm|MicrosoftWord,Sharepoint............................................................................................. 18

    AcceptanceLog|MicrosoftExcel,Sharepoint................................................................................................ 18

    ProjectCloseout

    Checklist

    |Microsoft

    Word,

    Sharepoint

    ...............................................................................

    18

    LessonsLearned|MicrosoftWord,SharePoint.............................................................................................. 19

    CLOSE:PROJECTCHECKPOINTS............................................................................................................ 19

    Checkpoint#5.................................................................................................................................................. 19SECTIONTWO:PROJECTMANAGEMENTSKILLAREAS.....................................................................................20COMMUNICATIONMANAGEMENT.................................................................................................................20BENEFITSOFMANAGEDCOMMUNICATION........................................................................................ 20

    COMMUNICATIONMANAGEMENT:DOCUMENTTEMPLATES............................................................ 20

    StakeholderLog................................................................................................................................................ 20

    CommunicationManagementPlan................................................................................................................. 21

    ProjectStatusReport|MicrosoftWord.......................................................................................................... 21

    ASPECTSOFCOMMUNICATION........................................................................................................... 22

    WhoIs

    The

    Audience?

    ......................................................................................................................................

    22

    WhatDoTheyWantToHearFromYou?......................................................................................................... 23

    WhenDoTheyWantToHearFromYou?........................................................................................................ 23

    HowDoYouReachThem?............................................................................................................................... 23

    STRATEGICVS.TACTICALCOMMUNICATIONS..................................................................................... 24

    StrategicCommunications............................................................................................................................... 24

    TacticalCommunications................................................................................................................................. 24

    COMMUNICATIONMETHODS.............................................................................................................. 25ISSUEMANAGEMENT......................................................................................................................................26ISSUEMANAGEMENTPURPOSEANDOBJECTIVES............................................................................... 26

    ISSUEMANAGEMENTPROCESSANDPROCEDURE.............................................................................. 26

    ISSUETYPES.......................................................................................................................................... 27

    ORDER/TIMINGOFESCALATIONFORISSUES....................................................................................... 27

    ISSUEASSESSMENT.............................................................................................................................. 27

    ISSUEMANAGEMENTTRACKING......................................................................................................... 28SCOPEANDTIMEMANAGEMENT....................................................................................................................29COLLECTDETAILEDPROJECTREQUIREMENTS..................................................................................... 30

    SCOPEDEFINITION............................................................................................................................... 30

    DETAILEDBREAKDOWNOFPROJECTWORK(WBS)............................................................................. 30

    IDENTIFICATIONOFACTIVITIESANDTHEIRSEQUENCE....................................................................... 30

    ACTIVITYRESOURCEANDDURATIONESTIMATES............................................................................... 30

    SCHEDULE............................................................................................................................................. 30

    REVIEWOFPROJECTWITHCUSTOMER/SPONSOR.............................................................................. 31

    PROJECTSCOPE

    BASELINE

    IS

    CREATED

    ................................................................................................

    31

    PROJECTSCOPEANDSCHEDULEMANAGEMENT................................................................................ 31

    RECOGNIZINGPROJECTSCOPECHANGE.............................................................................................. 31

    PROPERPLANNINGANDSCOPING....................................................................................................... 32

    FORMALCHANGECONTROLPROCESS................................................................................................. 32

    INTEGRATEDPROJECTCHANGECONTROLPROCESS........................................................................... 32COSTMANAGEMENT......................................................................................................................................33INTEGRATEDCHANGECONTROL.....................................................................................................................33CHANGETYPES..................................................................................................................................... 34

  • 7/31/2019 Framework PMO Best

    4/38

    ITSPMOProjectManagementFramework.docx4

    OrganizationalChangeManagement.............................................................................................................. 34

    OperationalChangeManagement................................................................................................................... 34RISKMANAGEMENT.......................................................................................................................................35HIGHLEVELPROJECTRISK.................................................................................................................... 35

    IDENTIFYPROJECTRISK........................................................................................................................ 35

    ASSESS

    RISK

    PROBABILITIES

    AND

    IMPACTS

    ..........................................................................................

    35

    PRIORITIZERISKS.................................................................................................................................. 36

    PLANRISKRESPONSES.......................................................................................................................... 37

    MANAGERISKS..................................................................................................................................... 37LESSONSLEARNED..........................................................................................................................................37LESSONSLEARNEDAPPROACH............................................................................................................. 38

    LESSONSLEARNEDFROMAPROJECT.................................................................................................. 38

  • 7/31/2019 Framework PMO Best

    5/38

    ITSPMOProjectManagementFramework.docx5

    ITSPROJECTMANAGEMENTOFFICE:WELCOMEITSiscommittedtosupportingandfurtheringProjectManagement(PM)tobetterensurethequalityofwork

    andservicerequiredofanyUniversityofNorthCarolinaatChapelHillendeavour.

    Toimproveprojectoutcomes,mitigaterisk,andimproveserviceconsistency,theInformationTechnology

    ServicesProject

    Management

    Office

    (ITS

    PMO)

    developed

    this

    framework

    resource

    document

    for

    ITS

    Project

    Managers,andthoseindividualswhomaynothavethetitleofProjectManager,butfindthemselvesmanaginga

    projectorprojects.

    TheITSPMOisdedicatedtocontinuousimprovementassuch;theframeworkdocumentandotherresources

    areupdatedregularlytoreflectstandardswithinbothinformationtechnologyandprojectmanagementfields.

    TheITSPMOdevelopedthefollowingmaterialsusingacombinationofexperiencegainedbymanagingprojects

    atTheUniversityofNorthCarolinaatChapelHillandotherorganizationsandprojectmanagementaccepted

    standards,suchastheProjectManagementInstitute(PMI)andtheirProjectManagementBodyofKnowledge

    (PMBOK)4th

    edition.

    TheITSPMOProjectManagementFrameworkexplainstheprojectmanagementprocessareasandtheir

    relationshiptotheprojectmanagementlifecycle.Additionally,thedefinitionofaproject,theproject

    managementlifecycle,andprojectmanagementresourcesaredefined.

    Theunderlyingtenetofprojectmanagementisthatyouplanforyourprojectbeforeexecution,andthatyou

    monitorallworktoensurealignmentwiththeapprovedgoals.TheITSPMOservesallofITSandseeksto

    providethebestresourcespossibletosupportyourproject.

  • 7/31/2019 Framework PMO Best

    6/38

    ITSPMOProjectManagementFramework.docx6

    PROJECT

    Aprojectisatemporaryendeavour

    undertakentocreateauniqueproduct,

    serviceorresult.Thetemporarynatureof

    projectsindicatesadefinitebeginningand

    end.Theendisreachedwhentheprojects

    objectiveshavebeenachievedorwhenthe

    projectisterminatedbecauseitsobjectives

    willnotorcannotbemet,orwhentheneed

    forthe

    project

    no

    longer

    exists.

    PROJECTMANAGER

    AProjectManageristhepersonresponsible

    formanagingallaspectsofaprojectto

    ensurethegoalsanddeliverablesaremet.

    Often,theProjectManagerrepresentsthe

    interestsoftheprojectclient(orSponsor)

    withintheprojecttoguidetheworktowards

    projectgoals.TheProjectManagerisgiven

    theauthority

    by

    the

    Sponsors

    to

    guide

    projectwork,maintaindocumentation,track

    work,andoverseetheProjectTeam.

    ITSPMO:PMSTANDARDSANDRESOURCESAfundamentalITSPMOgoalistoimprovethemanagementofCarolinasInformationTechnology(IT)projects

    andtoensuresuccessfulprojectoutcomes.Basedontheconceptofprogressiveelaboration,theITSPMOs

    ProjectManagement(PM)processallowstheProjectManagertoincorporatemoredetailsastheproject

    evolvesandinformationisdetermined.Inthisway,asnewinformationisavailable,theProjectPlanand

    managementapproaches

    can

    adapt

    to

    fit.

    TheITSPMOProjectManagementprocessisachievedwitha

    combinationofstandardizedtemplatesandresources

    customizedforCarolinasITprojects.Projectsofanysize

    benefitfromuseofseveralkeydocumentresources,

    specifically:ProjectInitiate,ProjectCharter,ProjectPlan,and

    ProjectClose.Thedepthofdetailanduseofdocument

    templateswillvarydependingontheprojectsgoals,budget,

    andlevelofrisk.

    FRAMEWORKDOCUMENT

    ORGANIZATION

    TheFrameworkisorganizedwithtwomainsections,eachwith

    interconnectedsubsections.Alltopicsareincludedinthe

    TableofContentsforeasyreference.

    SectionOne:ProjectManagementLifecycles

    TherearefiveProjectManagementLifecycles,andwithin

    each,theFrameworkdocumentdescribesthecycleitself,the

    requireddocumentresources,thedocumenttemplates,and

    thecyclecheckpoints.

    SectionTwo:ProjectManagementSkillAreas

    Throughoutallprojects,theProjectManagermustapply

    interpersonal,organizational,andleadershipskillstoguidethe

    Teamandensurethatworkalignswithstatedgoals.

    ThePMSkillAreasofChangeManagement,Communication

    Management,IssueManagement,ScopeandTime

    Management,CostManagement,andRiskManagement,are

    describedwithintheFrameworktoprovideProjectManagers

    acontextfortheassociateddocumenttemplates.

  • 7/31/2019 Framework PMO Best

    7/38

    ITSPMOProjectManagementFramework.docx7

    PROJECTMANAGEMENTLIFECYCLES

    Everyprojecthasalifecycle,andprojectmanagementforthatprojecthasitsownlifecycle.TheITSPMO

    FrameworkreflectstheProjectManagementlifecyclesofInitiate,Plan,Execute,MonitorandControl,followedbyClose.

    Figure1:PMLifecycles

    Forsimplicityssake,theProjectManagementLifecyclesareshowninaverylinear,starttofinishapproach.This

    linearrepresentationisusedtoreinforcethefactthattheworkofonecyclewilldirectlyimpacttheworkinthe

    followingcycle.

    Butinpractice,boththeentireProjectManagementLifecycleandthecycleswithinitareiterative.Project

    Managersmay

    be

    in

    the

    Execute

    cycle,

    but

    due

    to

    Stakeholder

    or

    budget

    changes,

    or

    other

    factors,

    must

    return

    tothePlanoreventheInitiatecycle.OneoftheresponsibilitiesoftheProjectManageristoknowwhichcycle

    theprojectisin,howclosetheprojectistocompletingthatcycle,andwhenacycleneedstoberepeatedor

    regressed.

    TheITSPMOdocumentandtemplateresourcesprovideavaluabletoolforProjectManagersastheyoversee

    thelaunch,workwithin,andcloseofeachProjectManagementcycleoftheirproject.

  • 7/31/2019 Framework PMO Best

    8/38

    ITSPMOProjectManagementFramework.docx8

    AtCarolina,StakeholdersandSponsors

    areoftenthesamegrouporperson.

    STAKEHOLDERStakeholdersarepersonsor

    organizations(e.g.Customers,Sponsors,

    andthe

    performing

    organization)

    who

    areactivelyinvolvedintheprojector

    whoseinterestsmaybepositivelyor

    negativelyaffectedbytheperformance

    orcompletionoftheproject.Theymay

    exertinfluenceovertheproject,

    deliverablesorteammembers.(ProjectManagementBodyofKnowledge(PMBOK)4thedition)

    SPONSORSponsoristhepersonorgroupthat

    provides(financial)resourcesfortheproject.TheSponsoristhechampion

    andspokespersontogathersupport

    throughouttheorganization.Theyplaya

    significantroleinthescopeandthe

    charter.TheSponsoristheescalation

    pointfortheProjectManager.(ProjectManagementBodyofKnowledge(PMBOK)4thedition)

    PROJECTDOCUMENTRESOURCES

    TheITSPMOprovidesProjectManagementdocumentresourcesthatalignwiththeworkofeachPMLifecycle

    andtheProjectCheckpoints.TheProjectManagementdocumentresourcesare:ProjectInitiation(Initiatecycle),ProjectCharter(Plancycle),ProjectPlan(Plancycle),ChangeControl(MonitorandControlcycle),andProjectClose(Closecycle).Withinthelifecycles,asthedocumentresourcesarecompletedtheyaresubmittedto

    the

    Project

    Stakeholders

    (or

    Advising

    Committee

    or

    other

    authorized

    management

    body)

    for

    review

    and

    approval.Therequiredreviewofthedocumentresourcesprovidestheformalcheckpointswithintheproject.

    Thedocumentresourcesandassociatedplanningactivitiesare

    mosteffectivewhenStakeholdersareactivelyinvolvedingathering

    projectdocumentation.Itisalsorecommendedthatthe

    documentsbetreatedaslivingdocumentsmeaningthat

    revisionsandreviewsoccurthroughoutyourprojecttoensurethat

    projectworkalignswiththeplan,andviceversa.

    Goalsandtargetsaremorelikelyreachedwhenplannedand

    monitoredagainsttheactualworkoftheproject.

    Figure2DocumentResourcesrequireCheckpoints

  • 7/31/2019 Framework PMO Best

    9/38

    ITSPMOProjectManagementFramework.docx9

    DOCUMENTLOCATION

    ThefilescanbefoundatITSPMO

    SharePointsite:

    https://share.unc.edu/sites/its/pmo/

    DOCUMENTACCESS

    NotethatanactiveONYEN(University

    username)isrequiredforlogintothe

    ITSPMOSharePointsitetodownload

    documentresourceanddocument

    templatefiles.LearnabouttheONYEN

    at:http://onyen.unc.edu.

    PROJECTDOCUMENTTEMPLATES

    Thedocumenttemplatesareavailabletofurthersupportand

    expanduponinformationcapturedinthedocumentresources.

    Templatesmaybeplanningtoolsusedwithinadocument

    resource(for

    example,

    the

    Risk

    Management

    Plan

    document

    templateforusewithintheProjectPlandocumentresource)or

    worktoolsusedinconjunctionwithadocumentresource(for

    example,theRiskLogtosupporttheProjectPlandocument

    resourcewithintheExecutecycle).

    Themajorityoftemplatesarelistedwithintheframeworks

    SectionTwo:ProjectSkillAreas.Templatesareprovidedas

    MicrosoftWord(docx)andMicrosoftExcel(xlsx)files.Some

    templatesareMicrosoftSharePointfilesforusewithinyourown

    SharePointsite.

    PROJECTCHECKPOINTS

    TheProjectCheckpointprocessprovidesprojectSponsors,StakeholdersandExecutiveManagementoversight

    oncost,scheduleandscopeastheprojectproceeds.

    TherearefivecheckpointswithintheProjectManagementcycles EachcheckpointistiedtoaProjectManagementdocumentresource Eachcheckpointrequiresaprojectauthoritysapprovaltocomplete Checkpointapprovalisprovidedbytheprojectauthorityappropriate

    toanindividualproject;approvalcancomefrom:

    o Stakeholder/so Sponsor/so ExecutiveManagemento AdvisoryCommittee

    Acheckpointcanberepeatedifacycleisrepeated

  • 7/31/2019 Framework PMO Best

    10/38

    ITSPMOProjectManagementFramework.docx10

    WHENISAPROJECTAPROJECT?

    OurgoalistoengenderacultureofprojectmanagementinITStohelpusimproveourabilitytoplanand

    executeonourcommitments. However,wearealsosensitivetotheneedtoavoidaddingunnecessary

    overhead/bureaucracytoourenvironment,soweneedtoclarifywhatconstitutesaprojectnecessitatingthe

    additionalstructure

    PM

    inherently

    requires.

    The

    following

    establishes

    that

    initial

    definition

    and

    we

    will

    adjust

    thisovertimeaswegainmoreexperience. Theintentistofocusonlarge/complex/highimpactprojectsand

    avoidmaintenanceactivities.

    Projects,asdefinedearlierinthisdocument,areendeavorsthataretemporaryinnatureandundertakento

    createsomething. Clearlythisisabroaddefinitionandonedesignedtogivetheperson/personsmanagingtheir

    workamplelatitudetodefinehowmuchstructuretoapplytoaparticularblockofwork. Yeteveryorganization

    thatundertakesformalprojectmanagementneedstoanswerthefundamentalquestionofwhatisthethresholdthatanactivitymustcrossbeforeitbecomesaformalprojectandwhatactionsmustbeundertakenatthattime? TheanswerforInformationTechnologyServices(ITS)atthetimeofthiswritingisasfollows:

    Aprojectbecomesaformalprojectwhenitmeetstwo(2)ofthethree(3)followingcriteria:

    A) Theprojectinvolvesfunds>=$100,000.00andisnotpartofroutinemaintenanceorequipmentrefresh.B) Theprojectwilltakesix(6)ormorecalendarmonthstocomplete.C) Theprojectishighrisk/hascampuswideimpact/projectfailurewouldnegativelyimpactITS. TherequiredactiontobeundertakenistocreateaProjectInitiatedocumentformanagementreview.

    ThepreferredactionistocreateaProjectInitiatedocumentandmanagetheprojectaccordingtothemethodologyespousedinthisframework.

    TheoptiontoengagetheITSProjectManagementOfficeinyourprojectplanning,managementandexecutionisalwaysopenandwelcomed.

  • 7/31/2019 Framework PMO Best

    11/38

    ITSPMOProjectManagementFramework.docx11

    PROCESSSELECTIONGUIDE

    Whichversion(theStandardorLight)processdoIneedtousetoinitiate/managemyproject?ThetermsStandardandLighthavebeenusedtodifferentiatebetweenprojectsofaveragecomplexity

    (Standard)andlesscomplexity(Light).TheframeworkcurrentlyfocusesonStandardtoensurefull

    informationand

    resources

    are

    available.

    However,

    within

    the

    ITS

    PMO

    resources,

    some

    files

    and

    templates

    have

    beenlabelledasLighttodesignatetheirpurposeasanabbreviatedversionofthefullStandardcounterpart.

    TheITSPMObelievesitisuptotheprojectmanagerandtheirteamsdiscretiontodeterminethebestfitof

    processtotheirproject. Foracomplexproject,thestandardprocessislikelythemostappropriate. Foraless

    complexproject,thePMandteamcouldchoosetodothelightversion. Aprojectsomewhereinthemiddle

    coulduseasubsetofthestandardprocess. Itishighlyrecommendedtheprojectclosechecklistiscompletedso

    thatallprojectshaveabeginning(projectinitiate)andanend(projectclose.)

    STANDARDPROCESSRecommendedTemplates

    LIGHTPROCESSRecommendedTemplates(inblack)

    Initiate Charter ProjectPlan CostTrackingWorksheet Schedule PMOStakeholderLog PMOCommunicationPlanForm PMORiskDocumentationForm PMORiskLog PMOStatusReportForm PMOIssueDocumentationForm PMOIssueLog ChangeRequestForm ChangeRequestLog CloseReportForm AcceptanceLog CloseChecklist LessonsLearned

    Initiate CharterLight

    ProjectPlan

    CostTrackingWorksheet

    Schedule

    PMOStakeholderLog

    PMOCommunicationPlanForm

    PMORiskDocumentationForm

    PMORiskLog

    PMOStatusReportForm

    PMOIssue

    Documentation

    Form

    PMOIssueLog

    ChangeRequestForm

    ChangeRequestLog

    CloseReportForm

    AcceptanceLog

    CloseChecklist StronglyRecommended

    LessonsLearned

  • 7/31/2019 Framework PMO Best

    12/38

    ITSPMOProjectManagementFramework.docx12

    ITSPMORESOURCES

    Thetablebelowlistsdocumentresources,documenttemplates,andadditionalresourcesprovidedbytheITS

    PMOtoensureyouhavethetoolsyouneedtoreachasuccessfulprojectcompletion.

    PHASE INITIATE PLAN EXECUTEMONITOR

    and

    CONTROLCLOSE

    DOCUMENT

    RESOURCE

    ProjectInitiate

    (includes

    Business

    Case)

    CHECKPOINT

    ProjectCharterLightProjectCharterProjectPlano RiskManagemento Cost

    Management

    o ScopeandTimeManagement

    o CommunicationManagement

    CHECKPOINT

    CHECKPOINT

    CHECKPOINT

    ProjectCloseReport

    CHECKPOINT

    DOCUMENT

    TEMPLATE

    StakeholderLogStatusReportIssueFormIssueLogScheduleRiskFormRiskLog

    ChangeRequestForm

    ChangeLogAcceptance

    Form

    AcceptanceLog

    ProjectCloseChecklist

    LessonsLearned

    ADDITIONAL

    RESOURCES

    ProjectSelection

    Guide

    ITSPMOFramework

    ITSPMOSharePoint

    site

    SharePointSiteTemplates

    SharePointListTemplates

    ITSPMOSharePointsite

    ITSPMOSharePoint

    site

    ITSPMOSharePoint

    site

    ITSPMOSharePoint

    site

  • 7/31/2019 Framework PMO Best

    13/38

    ITSPMOProjectManagementFramework.docx13

    SECTION1:PROJECTMANAGEMENTCYCLESPROJECTMANAGEMENTCYCLE:INITIATEEveryprojectofanysize,scope,orbudgetmusthaveadocumentedbusinesscasethatcapturestheneedthat

    the

    projects

    results

    and

    deliverables

    should

    address.

    The

    project

    requestor,

    with

    guidance

    from

    the

    PM,

    shouldhaveawrittenbusinesscaseavailablebeforeworkingonanyProjectInitiateactivityordocument.

    INITIATE:PROJECTDOCUMENTRESOURCES

    ThereisonedocumentresourcefortheInitiatecycle:ProjectInitiate.TheProjectManagerwillneedtowork

    closelywiththeProjectRequestor,Sponsors,andotherstoguidethecompletionofthisfoundationaldocument

    resource.

    ProjectInitiate

    Thebusinesscasemustbearticulatedandvettedbeforeanyotherprojectdocumentationandincorporatedinto

    theProject

    Initiate

    document.

    The

    purpose

    of

    the

    Project

    Initiate

    document

    resource

    is

    to

    describe

    at

    ahigh

    levelthevalueandscope/deliverablesofaprojectthatisbeingpresentedforfundingandscheduling

    consideration.

    AbudgetestimateispartoftheProjectInitiatetodevelopanapproximationofthemonetaryresourcesneeded

    tocompletetheproject.Inaddition,theInitiatedocumentoutlinesknownvendorresourcesrequiredto

    completetheprojectwork.Vendoreffortsareoftenrequiredtocomplementinternalresourcesortoprovide

    productsnotavailablewithintheorganization.

    TocompletetheProjectInitiate,theprojectrequestorand/orSponsorareaskedtoprovideprojectdetails

    neededbyITSExecutiveManagementtoprioritizeandfundprojects.

    INITIATE:PROJECTDOCUMENTTEMPLATES

    TherearenosupplementalprojectdocumenttemplatesfortheInitiateProjectManagementcycle.TheProject

    Initiatedocumentresource,withthebusinessplanandotherkeyprojectdetails,servesastheprimary

    documentforthiscycle.

    INITIATE:PROJECTCHECKPOINTS

    Checkpoint#1

    AftertheProjectInitiateiscompleted,itisreviewedandapprovedbytheappropriateprojectauthority(e.g.,

    Stakeholder,Sponsor,orExecutiveManagement).

    PROJECTMANAGEMENTCYCLE:PLANAfoundationalbeliefinprofessionalprojectmanagementisthatyoumustPLANbeforeyouACTorDO.

    Itisalsorecommendedthatthedocumentsaretreatedaslivingdocumentsmeaningthatrevisionsand

    reviewsshouldoccurthroughoutyourprojecttomakesuretheworkalignswiththeplan,andviceversa.Goals

    andtargetsaremorelikelyreachedwhenplannedandmonitoredagainsttheactualworkoftheproject.

  • 7/31/2019 Framework PMO Best

    14/38

    ITSPMOProjectManagementFramework.docx14

    PROJECTBASELINE

    Afterreviewandapprovalbythe

    Sponsorand/orExecutiveManagement,

    aProjectBaselineisrecorded.This

    includesusingtheBaselinefunctionin

    MicrosoftProjectorsavingacopyofthe

    Excelspreadsheet.

    TheProjectBaselineisusedduringall

    IntegratedChangeControlRequestsand

    atProjectClose.

    PLAN:PROJECTDOCUMENTRESOURCES

    ThePlanProjectManagementcycleincludestwodocumentresources:ProjectCharterandProjectPlan.TheITS

    PMOprovidestheprojectselectionguidetohelpProjectManagersdetermineiftheirprojectwouldbebest

    servedbytheCharterStandardorLight.BothversionsoftheCharterareprovidedbytheITSPMO.Your

    ProjectPlanwillincorporatemanyProjectManagementdocumenttemplates,andthePMwillneedtodecide

    howmany

    of

    the

    templates

    are

    required

    for

    agiven

    project.

    The

    default,

    or

    Standard

    Charter,

    uses

    all

    of

    the

    templateswithinthePlan.

    ProjectCharter

    TheProjectCharteristheofficialprojectapprovaldocument;

    withoutsignoffoftheCharter,theprojectdoesnotexistand

    resourcesshouldnotbeassignedtoit.TheCharterbuildsupon

    informationdocumentedintheBusinessCaseandProjectInitiate.

    Additionally,theinformationwithintheCharterinformsthelater

    ProjectPlandocument.

    ProjectPlan

    ProjectSchedulemilestonesandworktasksarebestidentified

    throughthecreationoftheProjectPlan.ThisProjectManagement

    documentresourceiscoretoallprojects.TheProjectPlanisusedto

    execute,manage,monitorandcontroltheprojectasthedeliverables

    aredeveloped,testedandaccepted.

    AspartofdevelopingtheProjectPlan,theProjectTeamshould

    collaboratewithStakeholdersandSubjectMatterExperts(SMEs)to

    adddetailtotheprojectrequirementssothatworkcanbebroken

    down

    to

    a

    task

    level,

    which

    in

    turn,

    can

    set

    resource

    needs

    and

    the

    overallProjectSchedule.

    PLAN:PROJECTDOCUMENTTEMPLATES

    TheProjectPlanTemplateusestenProjectManagementdocumenttemplatestoplanfortheProject

    Managementskillareasofcommunication,issues,scopeandtime,cost,changecontrol,riskmanagement,and

    LessonsLearned.

    CostTracking|MicrosoftExcel,SharePoint

    Cost

    Tracking

    is

    a

    tool

    to

    plan

    and

    monitor

    the

    project

    budget

    and

    set

    the

    budget

    baseline.

    Updating

    the

    budget

    involvesrecordingactualcostsspenttodate.Theauthorizedbudgetcanonlybechangedusingtheintegrated

    changecontrolprocess.

    ProjectSchedule|MicrosoftProject,Excel,SharePoint

    ProjectScheduleisatooltoplanandmonitorattheminimumtheplannedstartandfinishdateforeachactivity.

    AsacomponentoftheProjectManagementPlan,thescheduleisrefinedasresourcesaredeterminedanddates

    arefinalized.Thefinalizedversionofthescheduleistheschedulebaselinewhichcanonlybemodifiedusingthe

  • 7/31/2019 Framework PMO Best

    15/38

    ITSPMOProjectManagementFramework.docx15

    integratedchangecontrolprocess.StatusreportingisofteninthecontextoftheProjectSchedule.Toolslike

    MicrosoftProjectenhancetheabilitytoreactquicklytoresourcefluidity.

    StakeholderLog|MicrosoftExcel,SharePoint

    Atool

    to

    identify

    all

    persons

    or

    organizations

    actively

    involved

    in

    the

    project,

    or

    to

    show

    interests

    potentially

    impactedbytheproject.TheStakeholderLogisessentialinpreparingtheCommunicationManagementPlan. It

    includesthemajorexpectations,theprojectphaseinwhichtheStakeholderwillbethemostactiveandthe

    potentialinfluenceoftheStakeholderontheproject.

    CommunicationManagementPlan|MicrosoftWord,SharePoint

    AtooltoidentifyallStakeholders,Sponsorsandothersinvolvedintheprojectandclearlyidentifywhat,how

    andwhenyouwillcommunicatewiththem.TheIssueLogtoolisalsousedheavilyincommunicationstoraise

    anddiscussissuesthatariseandtodocumenttheirdisposition.Byraisingandcommunicatingissuesbroadly

    acrossallpersonsinvolvedintheproject,conflictthatmayarisefromlackofcommunicationisminimized.

    RiskForm|MicrosoftWord,SharePoint

    Atooltoidentifyanddefineaprojectrisk(apotentialeventorconditionthatmayoccur),assessthelevelofthe

    risk,andtodocumentpotentialmitigationstrategy.TheRiskFormshouldbeascompleteaspossibleandmay

    requireadditionalinformationfromtheProjectTeampriortothereviewprocess.Risksfortheprojectare

    loggedintheRiskLog.

    RiskLog|MicrosoftExcel,Sharepoint

    Atooltomaintainarunninglogofprojectrisks,comments,mitigationstrategyanddisposition.Itmaybeused

    inconjunctionwiththeRiskForm.Whenmitigationactionistakenonarisk,itmayimpactotherareasofthe

    ProjectPlanwhichshouldbeupdatedaspartoftheprocess.Unidentifiedrisksmayariseoverthelifecycleof

    theprojectandshouldbeaddedtotheRiskLogfollowingthenormalprocess.

    ProjectStatusReport|MicrosoftWord,SharePoint

    TheProjectStatusReportisatooltocommunicatetheprogressoftheprojectagainsttheProjectScheduleand

    costbaselines.Activeissuesandrisksshouldalsobediscussedinthestatusreport.

    IssueForm|MicrosoftWord,SharePoint

    Atoolforidentifying,tracking,andresolvinganissuethatisaroadblockorhasthepotentialtobearoadblock

    toproject

    success.

    Project

    issues

    can

    be

    raised

    by

    anyone

    involved

    with

    the

    project,

    but

    the

    Project

    Manager

    has

    theresponsibilitytomanagetheissuetoresolution.ProjectStatusReportsshouldincludeareviewofproject

    Issues.

    IssueLog|MicrosoftExcel,SharePoint

    TheIssueLogisatooltomaintainarunninglogofissues,commentsanddisposition.

  • 7/31/2019 Framework PMO Best

    16/38

    ITSPMOProjectManagementFramework.docx16

    PLAN:PROJECTCHECKPOINTS

    Checkpoint#2

    ThecompletedProjectCharterisreviewedandapprovedbytheappropriateprojectauthority(e.g.Sponsor

    and/orExecutiveManagement)toofficiallylaunchtheproject.WithoutasignedProjectCharter,theprojectis

    notapproved.

    Checkpoint#3

    WithacompleteProjectPlan,includingtheappropriatedocumenttemplateresources,thePMandProject

    TeamthencomparethePlan,Initiate,andChartertoidentifyanyvariancesindeliverables,goals,schedule,

    Sponsors,etc.AftertheProjectPlanTemplateandsupportingtemplateshavebeeninitiallycompletedtheyare

    reviewedandcomparedto/withtheProjectInitiateTemplateandProjectCharterTemplate.Thisisanimportant

    pointintimeintheproject.

    TheProjectPlanshouldbepresentedtotheappropriateprojectauthorityforapprovalbeforemovingtothe

    Executecycle.

    PROJECTMANAGEMENTCYCLE:EXECUTETheExecutecycleincludesperformingtheactivitiestoaccomplishtheprojectrequirements,creatingproject

    deliverables,managingtheProjectTeamandallotheractivitiesforasuccessfulprojectoutcome.

    EXECUTE:PROJECTDOCUMENTRESOURCES

    TheExecutecyclereliesupontheProjectPlan,createdinthePlanPMcycle,toguidetheprojectwork.The

    ProjectPlanisusedbytheProjectTeamtoexecuteworkdefinedintheprojecttoachievetheprojectgoalson

    behalfoftheSponsor.

    EXECUTE:PROJECTDOCUMENTTEMPLATES

    TherearenosupplementalprojectdocumenttemplatesfortheExecuteProjectManagementcycle.TheProject

    CharterandProjectPlandocumenttheProjectTeamfromthepreviouscyclestoserveastheProjectTeamfor

    keyprojectinformationforthiscycle.

    EXECUTE:PROJECTCHECKPOINTS

    TherearenoprojectdocumentcheckpointsfortheExecuteProjectManagementcycle.

    PROJECTMANAGEMENTCYCLE:MONITORANDCONTROLTheProjectPlanisusedbytheProjectTeamtotrack,reviewandregulatetheprogressoftheproject.Thisis

    donethroughouttheprojectandincludescomparingactualprojectperformanceagainsttheProjectPlan,

    identifying,accessingandmanagingnewrisks,andstatusreporting.

  • 7/31/2019 Framework PMO Best

    17/38

    ITSPMOProjectManagementFramework.docx17

    ThenumberonecauseofProjectScheduleandcostoverrunsisprojectscopechange.Ifscopechangesarenotcontrolled,theProjectScheduleandbudgetwillbenegativelyimpacted.Thechangecontrolprocess,alongwith

    properplanningoftheprojectsscope,willassisttheProjectManagerandTeamincontrollingscopecreep.

    Projectscopechangescanbeadditionalfunctionalenhancementstotheproduct,additionalcostsorchangesin

    ProjectSchedule.

    Excessive

    scope

    changes

    are

    directly

    related

    to

    poorly

    defined

    product

    requirements

    and

    specifications.Toavoidexcessivescopechanges,theProjectTeamshouldclearlydocumentalltheproject

    requirementsintheProjectCharter.

    MONITORANDCONTROL:PROJECTDOCUMENTRESOURCES

    TheIntegratedChangeControldocumentisatoolforidentifying,tracking,andtakingactiononrequestedor

    otherwisenecessarychangestothescope,timeorcostoftheproject.Achangecontrolboardorother

    authorizedperson(s)shouldbeidentifiedasthefinalauthorizationforallchanges.

    MONITORANDCONTROL:PROJECTDOCUMENTTEMPLATES

    TheProject

    Baseline

    is

    used

    for

    all

    Change

    Control

    Requests

    and

    at

    Project

    Closeout.

    ChangeRequestForm|MicrosoftExcel,Sharepoint

    TheChangeRequestFormisatooltoidentifyanddefinearequestedchangetoprojectscope,timeorcost.The

    changeformshouldbeascompleteaspossibleandmayrequireadditionalinformationfromtheProjectTeam

    priortothereviewprocess.ChangeRequestFormsareloggedintheChangeLog.

    ChangeLog|MicrosoftWord,Sharepoint

    Atooltomaintainarunninglogofchangerequests,commentsanddisposition.Itmaybeusedinconjunction

    withtheChangeRequestForm.Actionsapprovedthroughtheintegratedchangecontrolprocesswillimpact

    otherareas

    of

    the

    Project

    Plan

    which

    should

    be

    updated

    as

    part

    of

    the

    process.

    MONITORANDCONTROL:PROJECTCHECKPOINTS

    Checkpoint#4

    EachchangerequestisdocumentedusingaChangeRequestFormandrecordedintheChangeLogforthe

    project.TheChangeRequestisreviewedandcomparedtothecurrentProjectBaseline.Afterreviewand

    approvalbytheSponsorand/orExecutiveManagementallprojectsdocumentsandtemplatesareupdated

    includingtheProjectBaseline.TheupdatedProjectBaselinebecomesthecurrentversionofthebaselineused

    bytheProjectTeamandfutureChangeRequests.

    PROJECTMANAGEMENTCYCLE:CLOSEProjectCloseoutisthefinalphaseoftheITSPMOProjectManagementStandardProcess.Itensuresthatall

    appropriatedeliverableapprovalsarereceivedandthatprojectfilesareupdatedwithinformationgathered

    throughoutthelifecycleoftheproject.

    ThepurposesofProjectCloseoutaretoformalizethedeliveryofprojectobjectives,updatehistoricalproject

    resourcesforfutureprojectuse,andupdateprojectfiles.

  • 7/31/2019 Framework PMO Best

    18/38

    ITSPMOProjectManagementFramework.docx18

    TheprimaryobjectivesofProjectCloseoutare:

    AcceptanceofdeliverablesbyStakeholdersandSponsor(s) Updateofprojectfiles Projectorphaseclosuredocuments Documentationofprojectsuccesses DocumentationofprojectLessonsLearned

    ProjectfilesupdatedduringProjectCloseoutmayincludeStakeholdernotifications,projectreports,project

    presentations,projectrecords(includingemails,memos,andmeetingminutes),feedbackfromStakeholders,

    andLessonsLearned.LessonsLearnedaregatheredthroughouttheprojectlifecycle.DuringProjectCloseout,all

    LessonsLearnedarereviewedandtheirresolutionisdocumentedbytheProjectTeam.

    CLOSE:PROJECTDOCUMENTRESOURCES

    Everyprojectrequiresadocumentsignofftoacknowledgeandapprovetheendofworkandprojectactivities.

    CloseactivitiesareconductedonadeliverablelevelusingAcceptanceFormsandtheAcceptanceLog. Assuch,

    theclose

    of

    deliverables

    can

    occur

    during

    earlier

    Project

    Management

    cycles.

    But

    the

    entire

    project

    is

    closed

    onlyattheendandrequiresthecompletedProjectClosedocument.

    ProjectClose

    ProjectCloseisatooltodocumentthefinalstateoftheprojectanddeliverables,acceptance,conditionsor

    contingencies.Scopechanges,LessonsLearned,approvalsandotherprojectdocumentationandtheirlocation

    areidentifiedinthereport.

    CLOSE:PROJECTDOCUMENTTEMPLATES

    Another

    aspect

    of

    Project

    Close

    is

    the

    update

    of

    historical

    project

    information

    for

    use

    by

    future

    projects.

    The

    ProjectManagementClosecycleTemplatesareusedduringtheProjectCloseout.AProjectTeamcloseout

    meetingisheldduringwhichtheLessonsLearnedTemplateisalsoreviewedandupdated.

    AcceptanceForm|MicrosoftWord,Sharepoint

    AcceptanceFormisatoolthatclearlyidentifiesaprojectdeliverableorproductandacceptance/approvalbythe

    Customer.

    AcceptanceLog|MicrosoftExcel,Sharepoint

    AcceptanceLogisatooltomaintainarunninglogofdeliverable/productacceptancefortheproject.Thistoolis

    often

    useful

    in

    large

    projects

    with

    phased

    roll

    outs.

    ProjectCloseoutChecklist|MicrosoftWord,Sharepoint

    ProjectCloseoutChecklistisatooltoensurethatallprojectactivitieshavebeencompletedandtheprojectis

    readyforclose.Itensuresthatallacceptancecriteriahavebeenmet,managementplanshavebeenfinalized

    andthatresourceshavebeenreleased.ImportantcomponentsoftheProjectChecklistincludeaformalreview

    ofLessonsLearnedaswellasarchivalofprojectdata.

  • 7/31/2019 Framework PMO Best

    19/38

    ITSPMOProjectManagementFramework.docx19

    LessonsLearned|MicrosoftWord,SharePoint

    LessonsLearnedisatooltocaptureinformationforusebyfutureprojects.Itmaybecapturedduringproject

    executionoratProjectClose.AformalreviewofLessonsLearnedisscheduledaspartoftheProjectClose

    checklist.

    CLOSE:PROJECTCHECKPOINTS

    Checkpoint#5

    ProjectCloseoutbeginswhentheSponsorsandStakeholders(orappropriateprojectauthority)acceptthe

    projectdeliverablesandestablishedprojectgoalshavebeenmet.AfterreviewandapprovalbytheSponsor

    and/orExecutiveManagement,allprojectsdocumentsandtemplatesarearchivedincludingtheProject

    Baseline.

  • 7/31/2019 Framework PMO Best

    20/38

    ITSPMOProjectManagementFramework.docx20

    SECTIONTWO:PROJECTMANAGEMENTSKILLAREASCOMMUNICATIONMANAGEMENTProjectCommunicationsManagementincludestheactivitiesandtasksneededtoensureeffectiveStakeholder

    andProject

    Team

    communications.

    Communications

    can

    make

    or

    break

    any

    project,

    and

    it

    falls

    to

    the

    Project

    Managertoactasabridgebetweenthetechnicalandbusinessneedsofaprojectaswellasnavigatingthrough

    organizational,cultural,andphilosophicalneedstoensuretherightinformationreachestherightpeopleina

    timelymanner.

    BENEFITSOFMANAGEDCOMMUNICATION

    CommunicationisanessentialpartofdaytodayUniversityactivity.Communicationisespeciallyimportant

    whentheUniversitycommunitywillbeimpactedbyanupcomingchangethataffectsthewaydailyactivitiesare

    conducted.TheProjectTeammustprimetheCustomer(ortargetaudience)fortheimpacttheprojectwill

    haveinordertoincreaseuseracceptance,preparethemforchange,helpthemunderstandreasonsforit,and

    assisttheminunderstandingtheimpacttheprojectwillhaveontheirUniversityactivities.

    BENEFITSOFMANAGEDCOMMUNICATIONSINTERNALTEAMCOMMUNICATIONS EXTERNALCLIENTCOMMUNICATIONS Developingcommonunderstanding Gainingconsensus Clarifyingrolesandresponsibilities Providingopportunityforfeedback Providingintergroupcoordination Understandingdetailedworkplan Understandingprojectoperations IssueManagement

    Raisingawareness Increasingunderstanding Buildingsupport Encouraginginvolvement Securingcommitment Managingexpectations

    COMMUNICATIONMANAGEMENT:DOCUMENTTEMPLATES

    SeveralITSPMOdocumenttemplatessupportandareusedaspartofthePMOProjectManagementFramework

    aspartofCommunicationsManagement.

    StakeholderLog

    TheStakeholder

    Log

    is

    used

    to

    analyze

    the

    communication

    and

    distribution

    requirements

    of

    each

    Stakeholder.

    ThegoalistoensurethatStakeholders,includingtheProjectTeam,areinformedregardingallaspectsofthe

    projectrelatedtotheirinvolvementandresponsibilities.UpdatestotheStakeholderLogareusedasinputto

    updatetheCommunicationsManagementPlanTemplate.

    Toensureeffectivecommunications,identifyallprojectStakeholders.TheInitiatedocumentincludesthelistof

    primaryStakeholders.TheProjectTeamshouldusebrainstormingtechniquestocreateanextensivelistthat

  • 7/31/2019 Framework PMO Best

    21/38

    ITSPMOProjectManagementFramework.docx21

    shouldincludebothinternalandexternalStakeholders.Usingthislist,interviewtheidentifiedStakeholdersin

    anefforttoexpandyourlistuntilallpotentialStakeholdersareidentified.

    ExpandthedetailsinyourlistofeachStakeholderusingtheStakeholderLogTemplate.Fieldsincludedinthislog

    include:

    GeneralInformationo Name,contactinformation,position,division,officelocation,roleintheproject,internalor

    externalStakeholder

    Assessmentinformationo Majorrequirements,mainexpectations,potentialinfluenceontheproject,mostimportant

    phaseintheprojectlifecycle

    VariousprojectreportsanddocumentshelpcommunicateandmanagetheProjectSchedule,progress,and

    statustotheStakeholders.Itisessentialtoprovidethisinformationatthecorrectlevelofdetailandtousethe

    correct

    communication

    medium

    each

    Stakeholder

    requires.

    CommunicationManagementPlan

    TheexpectedresultfromtheProjectCommunicationManagementPlanistoensurethataccurateandeffective

    communicationstakeplaceduringtheproject.Theuseofconsistentcommunicationsthrough

    documents/templatesandmeetingswillensureacompleteunderstandingfortheentireProjectTeamand/or

    endusersrelatedtoeachindividualsrequirements,tasks,andresponsibilities.

    ProjectStatusReport|MicrosoftWord

    TheProjectStatusReportisatooltocommunicatetheprogressoftheprojectagainsttheProjectScheduleand

    costbaselines.

    Active

    issues

    and

    risks

    should

    also

    be

    discussed

    in

    the

    status

    report.

  • 7/31/2019 Framework PMO Best

    22/38

    ITSPMOProjectManagementFramework.docx22

    WHOisyouraudience?

    WHAT

    dothey

    want

    to

    hear

    from

    you?

    WHENdotheywanttohearit

    fromyou?

    HOWdoyoureachthem?

    ASPECTSOFCOMMUNICATION

    Thefollowingareasmustbeaddressedwhendevelopinganeffectivecommunicationmanagementstrategy:

    WhoIsTheAudience?

    Faculty,staff,andstudentswillbeaffecteddifferentlybyanychangetheprojectcauses.Thefollowing

    audiencesmustbeconsideredwhenpreparingcommunication:

    EachofyourStakeholders,Clients,andotherProjectMembersneedsadifferentdegreeandtypeofinformation

    basedonhowtheprojectchangewillaffectthem.Messagesmustbeuserfriendly,targetedtotheneedsofthe

    audience,andwritteninthestyleandatalevelofunderstandingwithwhichtheyarecomfortable.

  • 7/31/2019 Framework PMO Best

    23/38

    ITSPMOProjectManagementFramework.docx23

    WhatDoTheyWantToHearFromYou?

    Affectedpartiesshouldbeadvisedofwhytheprojectisbeingimplementedandtheneworchanging

    functionalitythatwillbedeployed.Itisimportantthattheyunderstandthatthereisanupcomingchangeaswell

    aswhyandhowitrelatestooveralluniversityobjectives.Directlyaffectedusersmustbeinformedofthe

    implementationscope,timelines,goals,objectives,andwhattheywillexperience.Wemustmanageuser

    expectationso

    users

    clearly

    understand

    what

    they

    can

    realistically

    expect.

    Considerationsforkeymessagesinclude:

    Howwillitimpactme? DoIneedtotakeanyaction? Whatwillthenewsystemlooklike? Whatcanitdo? Whatwillchange?When?Why? WhenwillIgetaccess? WhenwillIbetrained? Whywillittakesolong?WhenDoTheyWantToHearFromYou?

    Communicationmuststartearlytominimizeanymisconceptionsorincorrectinformation.Keyusersmustbe

    involvedintheprojectrightfromthebeginning,butcommunicationcannotendthere.Itmustcontinue

    throughouttheentireprojectlifecycle.Timelycommunicationmustbedeliveredtoeachspecificaudience,with

    thecorrectmessagetargetedtotheneedsofeachspecificaudience.

    Thetimingofmessagedeliverymustbeconsideredtogiveenoughnoticeto

    preparetheaudiencesforchange,completeanyactionsrequired,andallow

    forapsychologicaladjustmentperiod.Butthemessageshouldnotbe

    deliveredtoofarinadvancesothatinterestwanesorthatthemessageis

    forgotten.Also,

    please

    keep

    in

    mind

    that

    this

    project

    may

    be

    only

    one

    of

    severalotherITchangesbeingimplemented.Wemustensuresufficient

    notificationisgiventodepartmentssothattheycancoordinateanyother

    changesthatmayalsobeimpactingthem.

    HowDoYouReachThem?

    Thedeliveryapproachmustbeconsideredforeachuniqueaudience,using

    differentstrategiesandmessagesbasedonwhattheyneedtoknow.

    Messagesmustbetailoredtothevarioususerslevelsofunderstandingand

    knowledge

    of

    the

    project.

    Technical

    terminology

    and

    jargon

    must

    be

    minimizedincommunicationmaterial.

    Youmustmaintainconsistentpresentationofallcommunicationscirculated

    outsidetheimmediateProjectTeam.Thispracticewillgiveeachprojecta

    uniqueidentitythatdistinguishesitfromotherprojectsandactivitiesthat

    maybetakingplaceatthesametime.

    Themostappropriatewaytoreachthetargetaudiencemustbedetermined.Avarietyofmethodsof

    communicationshouldbeuseddependingonthemessagetobedeliveredandtheaudiencetowhichitwillbe

    Figure3CommunicationincludesinformationsenttoandfromPM

  • 7/31/2019 Framework PMO Best

    24/38

    ITSPMOProjectManagementFramework.docx24

    delivered.Criticalandpersonnelchangesareoftenbestconveyedusingindividualletterstoemployees,whereas

    generalprojectupdatesandstrategiescouldbebettercommunicatedviaemail,webpages,usergroup

    meetings,etc.Thecorrectbalanceofformalvs.informalanddirectvs.indirect,communicationsisessentialto

    projectsuccess.

    STRATEGICVS.

    TACTICAL

    COMMUNICATIONS

    Asuccessfulcommunicationsplanenablesthetargetedaudiencetounderstandandtakeactioninatimelyand

    robustmanner.Totailorthecommunicationmessageappropriately,youmustfirstdeterminetheintentbehind

    thecommunicationanddecideifthemessageisstrategicortacticalinnature.

    StrategicCommunications

    Strategicformsofcommunicationbroadlyconveyaconceptorplan.Notonlyisthelevelofunderstanding

    intendedtobeofageneralnature,buttheaudienceisalsoexpectedtobebroad.

    TacticalCommunications

    Tacticalformsofcommunicationaremeanttoconveyspecificinformationaboutaconceptorplan.This

    targetedcommunicationismeantforuserswhowillbeapplyingthecontentofthecommunicationsmessage

    intotangibleaction.Thereforethecontentmustbeclearandconcise.

  • 7/31/2019 Framework PMO Best

    25/38

    ITSPMOProjectManagementFramework.docx25

    COMMUNICATIONMETHODS

    Therearenumerouscommunicationmethods;thefollowingprovidesasummaryofthemorepopularoneswith

    theadvantagesanddisadvantageslistedforeach.

    METHOD ADVANTAGES DRAWBACKS COMMENTSMeetings,Briefings Direct Informative

    Interactive Suitableforsensitiveissues,

    discussion,decisions

    Oftenseenasaninterruptiontowork

    Difficulttokeeptoagenda Providesopportunitytoraise

    questions,issues,status

    updates

    Actsasacheckpointamongpartiesforintegrationissues

    Workshops Interactive,promotesinvolvement,discussion

    Allowsspecificfeedback Encouragesbuyin

    Difficulttoorganize Requireslengthyleadtime Returnoninvestmentis

    difficulttogaugeandsuccess

    isnotguaranteed

    Mustcarefullyselectthemixofparticipantsandensure

    thesessioniswellfacilitated

    andhighlyinteractiveto

    maximizeparticipantstime.

    Groupsshould

    not

    be

    too

    largeandshouldhavesimilar

    needs

    Roadshows,Demos Interactive,promotesinvolvement

    Immediatefeedback Reacheswidetargetaudience Includesconsistent,prepared

    messages

    Ishighimpact

    Difficulttoorganize Requireslengthyleadtime Requirescrediblepresenters

    Importanttoinvolveusersandencouragebuyin.Starts

    gettingusersaccustomedto

    lookofnewsystem,

    generalterminology,thereby,

    reducinglearningcurve

    WebPage/s Consistentmessage Lowcost Paperless Creativeformat

    Impersonal Notfortimesensitive

    messages

    Onewaycommunication Requiresunderstandingand

    accessibilitytotechnology

    Effectiveforcommunicatinggenericmessagesthatare

    nottimesensitiveor

    confidential

    EmailListserv,MassMail,DepartmentalMailing,ElectronicMailingLists

    Consistentpreparedmessage Lowcost Paperless Targetspecificaudiences Immediate

    AccessiblevialinkedPConly Easilyignored Allowsforthequickestdisseminationofinformation

    acrossmultiplesitesiftarget

    audiencehas

    required

    technology

  • 7/31/2019 Framework PMO Best

    26/38

    ITSPMOProjectManagementFramework.docx26

    ISSUEMANAGEMENTIssuesareunplannedorunexpectedproblemsthatariseduringthecourseofaproject.Issueswilldevelopover

    theprojectlifecycle.Issuemethod,means,andefficiencybywhichtheseissuesareaddressedand

    communicatedtotheStakeholderswillhelpdetermineiftheprojectremainsonbudgetandontimeorifthere

    willbeprojectoverruns.Someissuesmayimpactprojectscope,schedule,cost,resources,integration,orquality

    andaregenerallybeyondaparticularprojectworkgroupsauthorityorcapacitytoresolve.

    Anissuediffersfromariskinthatanissueisanactualfact,whileariskisaneventthatmayormaynotoccurin

    thefuture.TheProjectTeamexecutestheIssueManagementprocessunderthedirectionoftheProject

    Manager.IssueswillbebroughttotheattentionoftheProjectManager.

    ISSUEMANAGEMENTPURPOSEANDOBJECTIVES

    Issuesarealwaysassociatedwithsomedegreeofimpacttotheprojectandthereforeneedtobeassessedand

    resolvedinatimelyfashion.ThepurposeofdefiningissuemanagementproceduresistoassisttheProjectTeam

    toidentify,assess,monitorandresolveprojectissues.Thisensuresthattheissuesaredealtwithinanorderly

    andtimely

    manner

    while

    managing

    potential

    impact

    to

    the

    project.

    TheprimaryobjectivesofIssueManagementare:

    CommunicatetheimpactofissuestoappropriateStakeholders Manageeachissueasaconcernfromidentificationtoclosure Alloweachissuetoberesolvedandmonitoredbasedupondirectionfromtheappropriate

    authority

    AllowlesssignificantissuestobemanagedwithaminimumofoverheadISSUEMANAGEMENTPROCESSANDPROCEDURE

    Theinitiation

    of

    the

    formal

    Issue

    Management

    procedure

    begins

    when

    issues

    are

    discovered.

    The

    Project

    ManagementTeamsupportstheIssueManagementprocess.Thedocumentationandtrackingofallissuesis

    managedusingadefinedprocedureandfacilitatedbytheuseoftheIssueReportTemplateandIssueLog

    Template.

    AnyoneontheProjectTeamcaninitiateanissuebycontactingtheProjectManager.TheProjectManager

    reviewstheissueinthecontextoftheprojectmanagementplan.IftheProjectManagerdeterminesthatthe

    issueisrelevant,anIssueReportTemplateandtheIssueLogTemplatearecompleted,andtheIssue

    ManagementProcessisexecuted.

    ThepurposeoftheIssueReportandtheIssueLogistoactasthesourcedocumentsforallthedetailsrelatedto

    aspecificissue.TheIssueReportandtheIssueLogaretobeusedforalltypesofissuesorproblemsthatare

    encounteredduringtheproject(functional,technical,orprojectmanagementissues).Moreover,theIssue

    ReportandIssueLogarethedocumentsthathousethehistoryoftheissue,sotheycanprovidealltheactivities

    thathavehappenedduringtheissuelifespanfromidentificationtoresolution.

  • 7/31/2019 Framework PMO Best

    27/38

    ITSPMOProjectManagementFramework.docx27

    Ownershipfortheissuefallsupontheparticularresource(s)assignedtoitsfulfilment;itistheirresponsibilityfor

    themaintenanceoftheissue.Toensurevisibilityoftheoverallissuemanagementprocess,theProjectManager

    ischargedwithproperlydocumentingtheissueswithintheIssueReportandIssueLog.

    TheProjectTeamhasregularlyscheduledmeetingsonafrequentbasisandmeetingswithStakeholdersthat

    includeissue

    discussion

    as

    an

    agenda

    topic.

    Within

    these

    discussions

    the

    Team

    provides

    greater

    details

    and

    the

    ProjectManagerleadsdiscussionofeachopen,deferred,orinprocessissue.Thestatusofeachnonclosed

    issueisreviewed/determined(open,closed,deferred,orinprocess),andfollowonactivitiesarescheduledas

    appropriate.ISSUETYPES

    IssuetypesaredeterminedwhentheIssueReportandIssueLogiscreatedorupdated.

    ORDER/TIMINGOFESCALATIONFORISSUES

    OncetheIssuehasbeenidentified,documented,andassignedtheresolutionandescalationprocessbegins.The

    personassignedtotheissueisresponsibleforensuringthatallavailable/appropriateinformationisprovidedfor

    theissueonatimelybasis.Generallyspeaking,informationshouldbegatheredfortheprojectmeetingas

    determinedbytheProjectManager.TheProjectManagerwilldetermineatimeframeforresolutionofhigh

    priorityissueswithinthecontextoftheproject.

    Whenresolutionofanissuerequiresachangetothescope,schedule,orcostoftheproject,theChange

    Management/ControlProcessmustbefollowedtocontrolandimplementtheresolution.

    ISSUEASSESSMENT

    UsetheIssuePriorityMatrixtoidentifytheimportanceofaspecificissuewithregardtoitspriorityandpotential

    negativeimpactontheproject.Anissuewithhighseverityandhighpriorityisanurgentandcriticalissue;itmay

    causetheprojecttostopuntiltheissueisresolved.Incontrast,iftheissueisrankedasmediumseverityand

  • 7/31/2019 Framework PMO Best

    28/38

    ITSPMOProjectManagementFramework.docx28

    mediumpriority,monitoringtheissuemanagementprocessshouldbesufficient.Lowseverityandpriorityissues

    maybehandledoutsidetheissuemanagementprocess.

    Issueseveritywillnotchangeoverthelifeofanissue,buttheprioritycanbeadjustedupwardastimepasses

    withoutaresolution.Forexample,anissuemayhavehighseverityifnotresolved,butitsprioritymaybe

    mediumbecause

    there

    is

    enough

    time

    to

    resolve

    it.

    However,

    ifthe

    issue

    is

    not

    resolved

    in

    time,

    it

    may

    become

    highpriority.

    ISSUEMANAGEMENTTRACKING

    Tofurtherdefinetheissuemanagementprocess,eachissuewillbetrackedthrough:

    STEP STEPPURPOSE ACTIONS RESPONSIBILITY Initiate identifyanddocumentthe

    issue Identifytheissue.ReporttheissuetotheProjectManager. ProjectTeamMember

    Validate verifytheissueisvalidand

    requiresmanagement

    IdentifymemberoftheProjectTeamastheissueowner(s).

    Validate/investigateissuewithProjectTeammembersasappropriate.

    ProjectManager

    Analyze assesspriorityandseverity

    andassignresponsibilityto

    investigatealternatives

    AnalyzeurgencyandimpactofissueandupdatetheIssueReportwiththeanalysis.

    ProjectManager

    Assignresponsibilitytoinvestigatetheissueandactionalternatives.

    UpdatetheIssueReportwiththeassignment. IssueOwner

    Plan investigateandrecommenda

    courseofaction

    Investigate,recommendthebestapproach,andestimatetheefforttoresolvetheissue.

    Escalateunresolvableissues.UpdateIssueReportwithfindings,

    recommendations,orotherinformation.

    IssueOwner, AssignedTeam Member

    Control decideonacourseofaction Reviewtherecommendation.Approvetherecommendation,identify

    alternativeaction,orescalatetheissue.

    Initiateachangerequest,ifrequired.Assignthetaskofimplementingtheresolution.UpdateIssueReportwithdecisionand

    assignmentinformation.

    ProjectManager

    Monitor executeandmonitor

    implementationofthe

    approvedcourseofaction

    TrackIssueResolutionatStatusmeetings.CommunicateissuestatustoProjectTeam

    members.

    ProjectManager

    Close verifythatactioniscomplete,issueisresolved,andclose

    issue

    Verifythatissueisresolved.Recordissueresolutionandthedecision

    maker(s)

    MakeanyplanchangesnecessaryUpdateBudgetifChangeControlwithbudget

    impactisapproved.

    CloseinIssueReportwithresolutionactionontheIssueLog

    ProjectManager

  • 7/31/2019 Framework PMO Best

    29/38

    ITSPMOProjectManagementFramework.docx29

    SCOPEANDTIMEMANAGEMENTProjectScopeandTimeManagementincludesdefiningtheworkrequired(andonlytheworkrequired)and

    developingthescheduletocompletetheprojectsuccessfully.ThehighlevelscopestatementisincludedintheProjectInitiatedocumentandisdetailedtothenextlevelintheProjectCharter.

    ScopeManagementcontinuestheprogressiveelaborationprocessbycollectingdetailedrequirements,defining

    scope,dividingtheprojectdeliverablesandprojectworkintosmaller,manageablecomponents,gaining

    acceptanceforthescope,monitoringtheprojectscope,andmanagingchangestothescopebaseline.Upon

    finalizationofthedetailedworktobecompletedfortheproject,aProjectScheduleisdevelopedandproject

    activitiesaremanagedtothisschedule.

    Itisimportanttonotethatnormally,especiallyinanInformationTechnologyenvironment,eachproject

    typicallydealswithmanagingboththeprojectlifecycleandtheproductdevelopmentlifecycle.Project

    Managementfollowsalifecyclethatdefineshowtobringtheprojectfrominceptiontoclose.

    TheproductdevelopmentlifecycleinanITenvironmentdefineshowtobringtheproduct(s)frominceptionto

    operationaldelivery.ThedevelopmentlifecycleforanITproducttypicallyincludesfunctionaldesign,technical

    design,technicalbuild,testinganddeployment.TheProjectSchedulewillembodyactivitiesinboththeproject

    managementlifecycleandthedevelopmentlifecyclefortheproductstobedelivered.Thiswillimpacthowthe

    milestonesandworkpackagesaredefinedandtranslatedtothescheduletoproducetheprojectdeliverables.

    Changes(additionsorremovals)totimeframe,requiredscopeand/orbudgetaremanagedusingtheIntegrated

    ChangeManagementprocess.

    Theprimaryobjectivesofprojectscopeandtimemanagementare:

    Collectdetailedprojectrequirements Scopedefinition Detailedbreakdownofprojectwork Identificationofactivitiesandtheirsequence Activityresourceanddurationestimates Schedule GatereviewofprojectdeliverableswithCustomerorSponsor Managingchangestoscope Controloftheschedulebymanagingchanges.

    ProcessescompletedinscopeandtimemanagementprovidethebasisfortheProjectSchedule.TheProject

    Scheduleis

    normally

    prepared

    using

    Microsoft

    Project

    or

    an

    Excel

    spread

    sheet

    of

    tasks

    and

    associated

    estimatesaswellasstartdatesandenddatesforeachtask.

    AbaselineiscreatedandprojectprogressisthenreportedagainstthisbaselineandtheactualProjectSchedule.

    PeriodicbaselinesarerecordedtotrackchangestotheProjectScheduleasmanagedthroughtheIntegrated

    ChangeManagementprocess.

  • 7/31/2019 Framework PMO Best

    30/38

    ITSPMOProjectManagementFramework.docx30

    COLLECTDETAILEDPROJECTREQUIREMENTS

    Toolsnormallyusedtocollectrequirementsincludeinterviews,focusgroups,facilitatedworkshopsand

    prototypes.Requirementsdocumentationshouldinclude:

    Businessneedaddressed Functionalrequirementsdescribingthebusinessprocesses,informationandinteraction.Thesemaybe

    gatheredindocumentationorflowchartform.

    Otherrequirementssuchasserviceexpectations Qualityrequirements Acceptancecriteria Impacts Supportandtrainingrequirements

    SCOPEDEFINITION

    DevelopmentoftheScopeDefinitionbuildsuponmajordeliverables,assumptionsandconstraintsprovidedin

    theProjectCharter.TheProjectManagerusesexpertjudgmenttoanalyzeinformationneededtodefinescope.

    UsingtheStakeholderLog,theProjectTeamidentifiesandinterviewsStakeholdersthatcanprovidedetailed

    requirementsandmilestones.Thesearethendefinedanddocumented.

    DETAILEDBREAKDOWNOFPROJECTWORK(WBS)

    AtthispointStakeholdersaswellasotherresourceswithintheorganizationsuchassubjectmatterexperts,

    otherunitswithinUNCaswellasoutsidesourcessuchasconsultantsarecontacted.

    Usingthedetailedrequirementsandmilestonesadetailedbreakdownoftheprojectworkandsubdivisionof

    theproject

    into

    actionable

    components

    is

    performed.

    Often

    aWork

    Breakdown

    Structure

    (WBS)

    is

    utilized

    to

    facilitatethisprocess.EachleveloftheWBSprogressesfurtherintothedetailedactivitiesthatsupportthe

    higherlevelactivities.Detailedbreakdownoftheworkprovidesamoreconciseidentificationandtherefore

    estimationofprojectactivities.

    IDENTIFICATIONOFACTIVITIESANDTHEIRSEQUENCE

    Onceprojectactivitiesarebrokendowntotheirlowestlevel,allactivitiesrequiredtoproducetheproject

    deliverablesareidentifiedasworkpackages.Workpackagesarefurtherbrokendownintoactivitieswhichcan

    besequencedandestimated.

    ACTIVITY

    RESOURCE

    AND

    DURATION

    ESTIMATES

    Activityresourceestimatescanbedeterminedbyusingavarietyoftools.Theseincludeexpertjudgment,

    bottomupestimatingandtypesofestimatingsoftware.Onceresourceestimatesaredetermined,resource

    typesandtheiravailability,numbersofresourcesandtheresourcecalendarcanbeusedtoestimatedurations.

    SCHEDULE

    TypicallyaschedulingtoolsuchasMicrosoftProjectisutilizedtodeveloptheschedule.Activitysequences,

    durations,resourcerequirementsandschedulingconstraintsareutilizedasprojectactivities,activitydurations

  • 7/31/2019 Framework PMO Best

    31/38

    ITSPMOProjectManagementFramework.docx31

    andresourcesaremappedintotheschedulingsoftware.TheProjectScheduleconsistsofprojectactivity,

    plannedstartandfinishdatesforeachactivity,milestonedates,resourceestimatesandresourcenames.

    REVIEWOFPROJECTWITHCUSTOMER/SPONSOR

    UsingtheexpectationsintheProjectInitiatedocumentandtheProjectCharter,adetailedreviewbetweenthe

    ProjectCustomerorSponsorandtheProjectTeamisperformed.ThedetailedProjectSchedule,ProjectPlan,requirementsanddeliverablesarereviewed.

    IftheProjectInitiatedocumentandtheProjectCharterarenotinagreementwiththedetailedProjectSchedule,

    ProjectPlan,requirementsanddeliverablestheprojectCustomerorSponsorwillneedtoapprovechangesto

    theProjectInitiatedocumentandtheProjectCharter.Withoutthisagreementtheprojectcannotmove

    forward.OncetheProjectInitiatedocumentandtheProjectCharteragreewiththedetailedProjectSchedule,

    ProjectPlan,requirementsanddeliverablestheprojectwillmoveforward.

    PROJECTSCOPEBASELINEISCREATED

    Afterthe

    Project

    Customer

    or

    Sponsor

    agrees

    with

    the

    detailed

    Project

    Schedule,

    Project

    Plan,

    requirements

    and

    deliverablesandtheProjectCharterisinagreement,aprojectbaselineiscreated.TheProjectPlanwillbe

    updatedwiththebaseline.Atthispointanychangestotheprojectscope,budgetortimelinewillrequirea

    ChangeRequest.

    PROJECTSCOPEANDSCHEDULEMANAGEMENT

    Usingtheagreedbaseline,theProjectManagerandtheProjectTeamworktoensureprojectscope,including

    theschedule,isalignedwiththebaseline.PerformancereportskeeptheStakeholdersapprisedoftheprojects

    status.

    RECOGNIZINGPROJECTSCOPECHANGE

    IfanactivityisnotlistedintheapprovedProjectCharter,itindicatesascopechange.Scopechangesare

    commonlyrequestedas:

    Formalclientrequests:TheClientmakesaformalrequestforanadditionalfunctiontobeincorporatedintotheprojectafterthescopehasbeendefinedandapproved.

    Informalclientrequests:TheClientmaymakeaninformalrequestforadditionalfunctionalityorprocess.

    ProjectTeamsuggestions:ThesescopechangesrepresentfunctionsintroducedbyaProjectTeammemberthatinvolvedesign,build,orotherfeaturesnotincludedintheProjectCharter.

    ProblemReports:Thesechangesaretheresultofasystemissueorproblemresolutionreportthatidentifiesnoncompliancetobusinessrequirementsordetaileddesigndocument.Problemreportswill

    usuallyresultinachangerequest.

    OperationalIncidents:Operationalincidentswillariseduringtheprojectlifecyclethatmaydirectlyimpactthetimeline,scope,orresources.Operationalincidentsmustbereviewed,estimated,and

  • 7/31/2019 Framework PMO Best

    32/38

    ITSPMOProjectManagementFramework.docx32

    approvedbymanagement.Someissuesmayresultinaprojectchangerequest,andothersmaybe

    addressedthroughtheOperationalChangecontrolprocess(SMC/Remedy).

    ControllingProjectScopeChanges

    Three(3)stepsarenecessarytocontrolscopechanges:

    1. Properplanningandscoping2. Agreementfromtheprojectapprovers3. Formalchangecontrolprocess

    PROPERPLANNINGANDSCOPING

    Properplanningandscopingentailscompletelydefining theproject/product in theProjectCharter.Most

    projectsspecificationsdefinethelevelofdetailthatallowsallprojectgroupstoperformtheirreviewsand

    assessmentsproductively.Theprojectscopedefinestheprojectsoutput.

    FORMALCHANGE

    CONTROL

    PROCESS

    Projectsarenever static.Changesare tobeexpected during project lifecycle.A formalprocesshas been

    establishedtoensureallprojectchangesareidentifiedandmadeinanorderlymanner.

    Asprojectchangerequestsaremade,achangecontrolprocess isnecessarytoconfirmthatthe following

    occurs:

    Onlynecessarychangesaremade. Changesarecommunicatedtoallaffectedparties. Changesthatinvolveprojectscopecost,schedule,orresourcesarecapturedandapproved,andthe

    projectdocumentationisupdated.

    Changes

    are

    implemented

    in

    an

    orderly

    fashion.

    INTEGRATEDPROJECTCHANGECONTROLPROCESS

    ProjectChangeControlensuresthattheProjectTeamhasaprocesstorequestchangeswhileensuringthata

    consistentprocessisfollowedtodeterminetheoutcomeofeachrequest.EnsuretheTeamunderstandsthe

    ChangeControlpurposeanditsimportancetotheproject.

    IdentifytheChangeControlParticipants. ChangeRequestorCustomerorProjectTeam ChangeAuthorizers(ProjectManager,ProjectSponsorand/orITSExecutiveManagement)

    ReviewtheChangeControlProcesswiththeProjectTeam. ProjectManagercompletesandsubmitstheChangeRequestForm. ProjectManagersubmitstheChangeRequestFormviaemailtoProjectTeam,ProjectSponsor,

    and/orITSExecutiveManagement.

    ConductChangeRequestreviewmeetingsforChangeDecision.

  • 7/31/2019 Framework PMO Best

    33/38

    ITSPMOProjectManagementFramework.docx33

    ProjectManagerwillscheduleameetingwiththechangerequestapproverstoreviewtheproposedchangewithinfive(5)businessdaysofemailsubmission.Allcriticalchangerequestsmustbeacknowledgedandstepstakentowardsresolutionwithinfive(5)workingdays.

    ProjectManagerwillasktheauthorizerstosigntheChangeRequestFormanddocumentthedecision.

    ProjectManagerwillupdatetheProjectPlan,changerequestlog,andotherappropriatedocumentationbasedonthechangerequestdecision.

    TrackChangeRequests. Whenchangerequestsaremade,regardlessoftheirdisposition(approval/rejection),theyare

    enteredintotheChangeRequestLogandtheirdispositionistrackedtoprojectcompletion.

    When/ifthechangerequestisaccepted,thetasksandactivitiesrequiredtoexecutethechange

    areenteredintotheProjectPlan.

    TheProjectManagerupdatestheProjectPlanwiththenewactivitiesandtasks,ascreatedbythechangerequest,andadjuststheProjectSchedule,plans,dates,deliverablesand

    dependencies.

    Log

    the

    change

    request

    into

    the

    projects

    Change

    Request

    Log

    and

    tracks

    the

    change

    through

    taskcompletion.

    COSTMANAGEMENTTheCostManagementprocessincludesestimating,budgetingandcontrollingcostssothattheprojectis

    completedwithintheapprovedbudget.CostManagementconsidersStakeholder

    requirementsforcapturingcosts,thecostoftheresourcesneededtocompletetheproject,

    andtheeffectthatprojectdecisionshaveontheoverallcostoftheproject(including

    recurringcostofmaintainingandsupportingtheproduct,serviceorresultoftheproject).

    Thepurpose

    of

    Cost

    Management

    is

    to

    ensure

    that

    the

    project

    delivers

    the

    expected

    Return

    onInvestment(ROI)calculatedforjustificationoftheproject.Althoughatprojectinitiation

    theseestimatesmaybehighlevel,throughprogressiveelaboration,thebudgetnumbers

    willbecomemoreaccurate.Costthresholdsareestablishedduringcostmanagement

    planningthatdrivetheneedforactionwithintheprojectifcostsexceedthesethresholds.

    INTEGRATEDCHANGECONTROLTheIntegratedChangeControlprocessisusedforrequesting,reviewing,approving,carryingout,andcontrolling

    changes

    to

    the

    project's

    deliverables.

    The

    Integrated

    Change

    Control

    Process

    becomes

    effective

    immediately

    aftertheProjectCharter(fromtheProjectManagementCyclePlan)hasbeensignedandremainsineffectuntil

    ProjectCloseissigned.

    Aprojectwilllikelyundergochanges;theProjectManagercontrolsthechangestomanagetheimpacttothe

    ProjectPlan,budget,andimplementationschedulethroughthechangecontrolprocess.

    Somechangeswillbeunavoidableinstanceswherechangeshavetobemadetocomplywithlegalor

    federal/stateregulations;policychanges;regulatoryrequests;changesinthebusinessdirection;orsituationsin

  • 7/31/2019 Framework PMO Best

    34/38

    ITSPMOProjectManagementFramework.docx34

    whichtechnologymaydictateachange.Othernonessentialchangescanbeavoidedthroughmanagementofa

    formalchangecontrolprocessasitprovidesforreviewandapprovalofeachrequestedchange.

    CHANGETYPES

    TheframeworkaddressesProjectChangeManagement(ChangeControl),butitisimportanttounderstand

    differentchangemanagementtypesasallcouldimpactyourproject.

    OrganizationalChangeManagement

    OrganizationalChangeManagementencompassesallactivitiesaimedathelpinganorganizationsuccessfully

    acceptandadoptnewtechnologiesandnewwaystoserveitsCustomers.Effectivechangemanagement

    enablesthetransformationofstrategy,processes,technology,andpeopletoenhanceperformanceandensure

    continuousimprovementinaneverchangingenvironment.Acomprehensiveandstructuredapproachto

    organizationalChangeManagementiscriticaltothesuccessofanyproject/orbusinesschange.

    OperationalChange

    Management

    Theoverridingthemeofeffectiveoperationalchangemanagementiscommunication.ITgovernancestructure,

    changeandconfigurationmanagementprocesses,andsupportingtoolsservetoensuretheintegrityofthe

    infrastructurebaselineandthesystematiccommunicationofchangestothatbaseline.Integrationofchange

    controlwithIncidentManagementprocessesfosterscommunicationofservicedisruptioninformationtothose

    responsibleandaffected.

    InformationTechnologyServices(ITS)hastwoformsofoperationalchangemanagement.

    1. TheServiceManagementCouncil(SMC)isthegroupthatcoordinatesandcommunicateschangeshappeningtothesystemsbaseline.ThegroupmeetsweeklyandhasacalendarthatkeepstheTeam

    informedregardingimpendingchanges.Ifyouhaveanoperationalchangebeingintroduced,itisthe

    ProjectManagement

    Teams

    responsibility

    to

    update

    the

    calendar

    as

    to

    what

    the

    change

    is

    and

    when

    it

    ishappening.Itisalsoimportanttohavesomeone(suchastheProjectManager)attendthemeetingto

    discussthechangeandansweranyquestionsthatmaycomeup.Ensuringthegrouphasacontactname

    todiscussanyconcernsorupdatesiscritical.Presentingthechangeasearlyaspossibleisalwaysbest.

    2. TheRemedyChangePlanapplicationsupportsalloperationalchangerequestsandthenotificationofchanges.AnychangetothebaselineoftheITSinfrastructureandapplicationsneedstohaveaRemedy

    ChangePlancompletedandapprovedthroughtheworkflowprocessembeddedintheRemedy

    application.

    Changemanagementcanbeachievedthroughuseofrequestformsandlog.Itisimportanttodocumenteach

    changerequest,andtotrackthosechangerequests,inordertomanagechangethroughthelifeofyourproject.

  • 7/31/2019 Framework PMO Best

    35/38

    ITSPMOProjectManagementFramework.docx35

    RISK

    Riskisaneventorconditionthatmayoccur

    withimpacttoatleastoneprojectobjective.

    Acausemaybearequirement,assumption,

    constraintorconditionthatcreatesthe

    possibilityofpositiveornegativeoutcomes.

    Risksareassessedaccordingtothepotential

    impacttotheprojectandtheprobabilityof

    theiroccurrence.

    A

    risk

    may

    also

    occur

    due

    to

    the

    environment

    inwhichtheprojectisoccurringi.e.immature

    projectmanagementpractices,concurrent

    multipleprojectsordependencyonexternal

    resourcesforprojectcompletion.

    Aprojectcontingencyplaniscreatedtodeal

    withunknownrisksthatmaybecomeknown

    astheprojectcontinues.

    RISKMANAGEMENTRiskmanagementisusedtodefineuncertaintyinaproject

    andtoplanforactionstoaddresstheeventorcondition

    shoulditoccur.Riskmanagementembodiesamethodology

    thatdefines

    the

    tools

    and

    data

    sources

    to

    be

    used

    for

    risk

    management.Datasourcesforriskmanagementincludethe

    scopestatement,costmanagementplan,schedule

    managementplan,communicationsmanagementplanaswell

    asexistingconditionsandprocessesthatmayimpactproject

    success.

    Yourprojectsriskmanagementplanincludesthefollowing

    steps:

    1. Identifyhighlevelrisk2. Identifyprojectrisks3. Assessriskprobabilityandimpact4. Prioritizerisks5. Planriskresponses6. Managerisk

    HIGHLEVELPROJECTRISK

    HighlevelrisksshouldbeidentifiedbytheProjectSponsor

    andProjectManageratthetimethattheProjectCharteris

    prepared.Probabilityandimpactforeachriskshouldbe

    assessedandprioritydocumentedintheProjectCharterfor

    considerationduringprojectapproval.Iftheprojectcarries

    significantrisks

    from

    its

    inception,

    these

    risks

    should

    be

    reviewedandconsideredasapartoftheprojectapproval

    process.Ifsignificantrisksareidentified,theyshouldbe

    reviewedbythegroupapprovingtheprojecttodetermineif

    theseriskscanbemitigatedorotherwiseassignedpriorto

    beginningtheproject.Highlevelrisksmaybesubstantial

    enoughtocausetheprojecttobestopped.

    IDENTIFYPROJECTRISK

    ProjectrisksareidentifiedbyProjectSponsorsandStakeholders.Riskidentificationisaniterativeprocess.ARisk

    IdentificationWorkshopisscheduledduringprojectplanningtoreviewprojectriskmanagementprocessandto

    developthe

    initial

    Risk

    Log.

    The

    Log

    is

    then

    reviewed

    routinely

    throughout

    the

    project.

    Identification

    of

    risks

    shouldbeconsistentacrossriskssothatriskscanbecompared.

    ASSESSRISKPROBABILITIESANDIMPACTS

    TheRiskPriorityMatrixisusedtoassessrisks.Thereisalwaysameasureofriskandconsequencesassociated

    withbusinessdecisions.Dependingontheprojectstructure,risksareidentifiedeitherduringaRiskWorkshop

    orongoingriskreviews.TheProjectManagerandtheProjectTeamwilldraftmitigationplans.

  • 7/31/2019 Framework PMO Best

    36/38

    ITSPMOProjectManagementFramework.docx36

    Stakeholders/Sponsors/ProjectManager/Teamwillidentifytheprobabilityandimpacttotheprojectassociated

    witheachrisk.TheProjectManagerwillassigntheownersofeachriskandreviewtheRiskLogandplanwiththe

    riskownersandProjectStakeholderstogainapproval.

    Thebasicstepsforassessingriskprobabilitiesandimpactareasfollows:

    1. Identifyrisktoassess2. Determinetheriskprobabilityandnoteitonthematrix(low,medium,orhigh)3. Determinetheriskimpactandnoteitonthematrix4. Notethepointsofintersectionwithprobabilityandimpact5. Ifpointsareadjacent,usethehigherrating

    Wherethepointsofintersectionfall,inlow,medium,orhigh,indicatestheactionneeded. Low/greendoesnot

    requirearesponseplan,butbothmedium/yellowandhigh/red,dorequirearesponseplan.

    PRIORITIZERISKS

    Thereviewofeachrisk,andthefinalagreementandjudgmentoftheleveloftheprobabilityandimpactofeach,

    needstobemadebythewholeTeam.Ifyoudonothaveconsensus;determineusingtiebreakerrules.

    DeterminetheintersectionoftheProbabilityandImpacttofindyourRiskpriority.

    IfyourProbabilityandImpactareimmediatelyadjacenttooneanotheronthematrix,thehigherPriorityshould

    beassigned.

    Figure4:exampleRiskPriorityMatrix

  • 7/31/2019 Framework PMO Best

    37/38

    ITSPMOProjectManagementFramework.docx37

    PLANRISKRESPONSES

    RiskprioritiesareupdatedintheRiskFormtotheRiskLog.Foreachriskthatrequiresaresponse,thestrategyis

    plannedby

    the

    Project

    Manager,

    Project

    Team

    and

    Stakeholders.

    Risk

    strategies

    exist

    for

    negative

    and

    positive

    risks.

    NegativeRiskStrategies

    AvoidchangetheProjectManagementPlantoavoidtherisk.ThisresponseshouldinvokethechangemanagementprocesstochangetheProjectManagementPlan.

    Transfershiftthenegativeimpactofthethreatandtheownershipoftheresponsetoathirdpartysuchasaconsultant.

    Mitigate reducetheprobabilityorimpactoftherisktoanacceptablelevel. Accept documentthestrategywithnochangestotheProjectManagementPlantodealwiththe

    risk.TheriskcanbedealtwithbytheProjectTeamwhen/ifitoccursorcontingencycanbeidentified

    to

    address

    the

    threat

    should

    it

    occur.

    PositiveRiskStrategies(Opportunities)

    Exploitstrategytoensurethattheopportunityisrealized. Shareallocatesomeoftheownershiporopportunitytoathirdparty. Enhancestrategytoincreasethepossibilityorpositiveimpactoftherisk. Acceptstrategytobewillingtotakeadvantageoftheopportunityifitcomesalong.

    MANAGERISKS

    Risksaremanagedthroughoutthelifecycleoftheproject.Risksarereassessedroutinelyinregularlyscheduled

    RiskWorkshops.DuringRiskWorkshops,newrisksmaybeidentified,existingrisksareassessedandrisksare

    closed.

    BasicmethodologyforriskmanagementwillbeimplementedviatheRiskFormandRiskLogtemplates.Through

    thesedocumenttemplates,risksareidentified,prioritizedandriskresponseplannedanddocumented.

    ProbabilityandImpactmatricesprovidedonpage35areusedtoprioritizerisks.

    LESSONSLEARNEDThepurposeoftheLessonsLearneddocumentistocapturetheprojectsLessonsLearnedinaformaldocument

    foruse

    by

    Project

    Managers

    on

    similar

    future

    projects.

    The

    ITS

    Lessons

    Learned

    encompasses

    teamwork

    and