FR-EE-403-00003-L

Embed Size (px)

Citation preview

  • 7/24/2019 FR-EE-403-00003-L

    1/20

    L 5-NOV-2014 Issued for COMPANY Review TAT NAS MTH

    Rev. Date Description Prepd By Chkd By Apprd By

    COMPANY EPC CONTRACTOR

    Abu Dhabi Polymers Company Limited (Borouge)

    PROJECT

    BOROUGE PO FLARE GAS RECOVERY PROJECT

    TITLE

    RELAY SETTINGS & PROTECTION COORDINATION STUDY

    Contractor Project No.:6502 Contractor Doc No: 6502-10-100-M1380-005-01

    Document Class: 1

    BOROUGE Document Inform ation:

    Project No. Document Number Page Rev.

    PE/000451 FR-EE-403-00003 1 OF 14 L

  • 7/24/2019 FR-EE-403-00003-L

    2/20

    Abu Dhabi Polymers Company Limited (Borouge)

    BOROUGE PO FLARE GAS RECOVERY PROJECT

    RELAY SETTINGS & PROTECTION COORDINATION STUDY

    Issued date Project No. Document Number Page Rev.

    5-NOV-2014 PE/000451 FR-EE-403-00003 2 OF 14 L

    Revision / Changes:

    RevisionNo.

    Page No. Section Change(s)

  • 7/24/2019 FR-EE-403-00003-L

    3/20

    Abu Dhabi Polymers Company Limited (Borouge)

    BOROUGE PO FLARE GAS RECOVERY PROJECT

    RELAY SETTINGS & PROTECTION COORDINATION STUDY

    Issued date Project No. Document Number Page Rev.

    5-NOV-2014 PE/000451 FR-EE-403-00003 3 OF 14 L

    TABLE OF CONTENTS

    1 INTRODUCTION .. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4

    2 STUDY OBJECTIVE . . . . . . .. . . . . . . . . . . . . . .. . . . . . . . . . . . . . . . .. . . . . . . . . . . . . . . .. . . . . . . . . . . . . . . . .. . . . . . . . . . . . . . . .. . . . . . . . 4

    3 REFERENCE DOCUMENTS .. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4

    4

    ETAP MODEL . . . . . . . . . . . . . . .. . . . . . . . . . . . . . . . .. . . . . . . . . . . . . . . .. . . . . . . . . . . . . . . . .. . . . . . . . . . . . . . . .. . . . . . . . . . . . . . . .. . . . . . . 5

    5

    BASIS & ASSUMPTIONS . . . . . . . . . . . . . .. . . . . . . . . . . . . . . . .. . . . . . . . . . . . . . .. . . . . . . . . . . . . . . .. . . . . . . . . . . . . . . .. . . . . . . . . . 6

    6 NETWORK DESCRIPTION FOR STUDY .. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6

    7 MODEL SIMULATION CONDITIONS .. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6

    8 FAULT CURRENT LEVELS . . . . .. . . . . . . . . . . . . . .. . . . . . . . . . . . . . . .. . . . . . . . . . . . . . . .. . . . . . . . . . . . . . . .. . . . . . . . . . . . . . .. . . 7

    9

    RELAY TYPE . . . . . . . . . . . . . .. . . . . . . . . . . . . . . .. . . . . . . . . . . . . . . . .. . . . . . . . . . . . . . . .. . . . . . . . . . . . . . .. . . . . . . . . . . . . . . . .. . . . . . . . . . 9

    10 HV PROTECTION RELAY SETTINGS DATA .. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 9

    11

    TIME CURRENT CURVES .. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 10

    12 CONCLUSION AND RECOMMENDATIONS .. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 14

    Attachments:

    Attachment A: ETAP SLD

    Attachment B: ETAP Report

  • 7/24/2019 FR-EE-403-00003-L

    4/20

    Abu Dhabi Polymers Company Limited (Borouge)

    BOROUGE PO FLARE GAS RECOVERY PROJECT

    RELAY SETTINGS & PROTECTION COORDINATION STUDY

    Issued date Project No. Document Number Page Rev.

    5-NOV-2014 PE/000451 FR-EE-403-00003 4 OF 14 L

    1 INTRODUCTION

    The intent of this study report is to carry out electrical power system analysis by performing protectioncoordination study of the electrical network under the scope of Borouge PO Flare Gas Recovery project (B3).

    2 STUDY OBJECTIVEThe main objectives of protection coordination study are as follows:

    To determine the characteristics, ratings, and settings of over current protective devices that minimizes plantoutages and interrupts short circuits as rapidly as possible.

    To verify the existing protection device settings.

    To verify the proper margin between protective devices in series to enable a back-up protection system.That is, upstream devices are on a standby basis to act expeditiously in case the immediate device nearer

    to the fault location fails to operate.

    Relay Coordination study is performed on the basis & recommendations of following international standards

    IEEE Std 399-1997. (IEEE Recommended Practice for Industrial & Commercial PowerSystem Analysis)

    IEEE Std 242-2001. (IEEE Recommended Practice for Protection and Coordination ofIndustrial and Commercial Power Systems)

    3 REFERENCE DOCUMENTS

    The documents listed below have been considered as the basis/reference for the relay settings & protectioncoordination study:

    Document Name Borouge Document No. Contractor Document No.

    Electrical Cable Schedule FR-EE-403-00006 6502-10-100-D1-1382-001-01

    Electrical Load Summary (B3) STU-EE-FR-003 6502-10-100-D1381-002-01

    Electrical One Line DiagramB3 PE5 Process Substation Unit N-42(11KV, 3.3

    KV, 0.415 KV)TEC-EE-FR-0044 ----

    11 KV SWITCHGEAR 42-ES-9001Protection and Metering One Line Diagram

    TEC-EE-FR-0045 ----

    Electrical One Line DiagramB3 PP4 Process Substation UNIT N-45

    TEC-EE-FR-0046 ----

    11 KV SWITCHGEAR 45-ES-9001Protection and Metering One Line Diagram

    TEC-EE-FR-0047 ----

    3.3 KV SWITCHGEAR 45-ES-9002

    Protection and Metering One Line Diagram

    TEC-EE-FR-0048 ----

    3.3 KV SWITCHGEAR 42-ES-9002Protection and Metering One Line Diagram

    TEC-EE-FR-0050 ----

    BOR 3 PO SUBSTATIONProtection and Metering Diagram 0.415 KV

    SwitchgearTEC-EE-FR-0049 ----

    Electrical One Line DiagramPE5 Extrusion Substation

    Unit N-42(11KV, 3.3 KV, 0.415 KV)42-EE-153-920001 ----

    Electrical One Line DiagramPP4 Extrusion Substation

    Unit N-42(11KV, 3.3 KV, 0.415 KV)45-EE-153-920001 ----

  • 7/24/2019 FR-EE-403-00003-L

    5/20

    Abu Dhabi Polymers Company Limited (Borouge)

    BOROUGE PO FLARE GAS RECOVERY PROJECT

    RELAY SETTINGS & PROTECTION COORDINATION STUDY

    Issued date Project No. Document Number Page Rev.

    5-NOV-2014 PE/000451 FR-EE-403-00003 5 OF 14 L

    4 ETAP MODEL

    As per Descon / Contractor scope (DOC: Electrical System Description and Scope Definition for EPCPackage) in Borouge 3 expansion project, Descon has to analyze the impact of newly added loads (which arein Descon scope, DOC: Electrical Load Summary B3) on the electrical network of B3 by performing theprotection coordination study.

    The details of ETAP model provided by Company are as follows:

    Name:ETAP-3583-PO

    This contains the following switchgears with associated electrical equipment (Motors, Transformers, andCables etc).

    80-ES-1802 (33 KV) 41-ES-9001 (11 KV) 41-ES-9002 (3.3 KV)

    41-ES-9203 (3.3 KV) 41-ES-9011 (0.415) 41-ES-9211 (0.415 KV)

    42-ES-9213 (0.415 KV) 41-ES-9212 (0.415 KV) 41-ES-9201 (11 KV)

    42-ES-9201 (11 KV) 42-ES-9001 (11 KV) 42-ES-9002 (11 KV)

    42-ES-9203 (3.3 KV) 42-ES-9011 (0.415 KV) 42-ES-9211 (0.415 KV)

    42-ES-9212 (0.415 KV) 44-ES-9001 (11 KV) 44-ES-9002 (3.3 KV)

    44-ES-9202 (3.3 KV) 44-ES-9011 (0.415 KV) 44-ES-9211 (0.415 KV)

    44-ES-9212 (0.415 KV) 45-ES-9001 (11 KV) 45-ES-9002 (3.3 KV)

    45-ES-9202 (3.3 KV) 45-ES-9011 (0.415 KV) 45-ES-9211 (0.415 KV)

    Loads in Contractors scope have been modeled along with associated cables.

  • 7/24/2019 FR-EE-403-00003-L

    6/20

    Abu Dhabi Polymers Company Limited (Borouge)

    BOROUGE PO FLARE GAS RECOVERY PROJECT

    RELAY SETTINGS & PROTECTION COORDINATION STUDY

    Issued date Project No. Document Number Page Rev.

    5-NOV-2014 PE/000451 FR-EE-403-00003 6 OF 14 L

    5 BASIS & ASSUMPTIONS

    The basis and assumptions are listed below

    The protection data for motors i.e starting time, thermal withstand limits, thermal time constants etc arebased on technical data provided by vendor and assumptions are made where vendor data is pending.

    Thermal overload settings of motors shall be performed at site during commissioning stage.

    For simulation purposes, exact Relay/ETU model is used as available in standard ETAP device library. Incase of unavailability of particular model, nearest match having similar characteristics is used.

    In this report, following switchgears of Unit 42 (PE5) and Unit 45 (PP4) are under observation as most ofthe loads under contractors scope are being fed from theses switchgears. However attached ETAP reportwill reflect the results of other switchgears as well.

    42-ES-9001 (11 KV) 45-ES-9001 (11 KV) 42-ES-9011 (0.415 KV) 45-ES-9011 (0.415 KV)

    6 NETWORK DESCRIPTION FOR STUDY

    For the simulation, ETAP models have been updated as per the reference documents mentioned in section 3of this report. The Network Description for the study is as follows:

    The main power sources for 11 KV switchgear 42-ES-9001 are 2 Nos. 33 KV feeders supplied byswitchgear 80-EE-1802 through 31.5 MVA, 33/11.5 KV transformers (42-EP-9011, 42-EP-9012).

    2 Nos. 11 KV feeders (from switchgear 42-ES-9001) are stepped down by 2 Nos. 3.15 MVA, 11/0.433 KVtransformers (42-EP-9031, 42-EP-9032) to feed 0.415 KV switchgear 42-ES-9011.

    The main power sources for 11 KV switchgear 45-ES-9001 are 2 Nos. 33 KV feeders supplied byswitchgear 80-EE-1803 through 31.5 MVA, 33/11.5 KV transformers (45-EP-9011, 45-EP-9012).

    2 Nos. 11 KV feeders (from switchgear 45-ES-9001) are stepped down by 2 Nos. 2.5 MVA, 11/0.433 KVtransformers (45-EP-9031, 45-EP-9032) to feed 0.415 KV switchgear 45-ES-9011.

    Following Generators are operating in Standby mode and considered OFF in the analysis.

    42-EG-9201 42-EG-9001 45-EG-9001 45-EG-9201

    7 MODEL SIMULATION CONDITIONS

    Following are the basis of model simulation conditions.

    Loads are categorized into Continuous, Intermittent and Stand by 100%, 50% & 0% loading respectively.

    All Lump Loads are considered as Continuous and operating at 80% loading.

    Loading Category is selected as Normal.

    Primary tap positions are set at +2.5% of nominal voltage, for all transformers (for Unit 42 & 45).

    33kV Grid bus is considered as slack/swing bus.

    The by-pass switches for VFDs are closed to get maximum short circuit contribution from motors.

    Maximum short circuit power from utility to switchgears of unit 42 and 45 is considered 1257 MVA (3-phase)as per etap model/etap report submitted by Company described in section 5 of this report.

    Minimum short circuit power from utility to switchgears of unit 42 and 45 is considered 850 MVA (3-phase)as per etap model/etap report submitted by Company described in section 5 of this report.

  • 7/24/2019 FR-EE-403-00003-L

    7/20

    Abu Dhabi Polymers Company Limited (Borouge)

    BOROUGE PO FLARE GAS RECOVERY PROJECT

    RELAY SETTINGS & PROTECTION COORDINATION STUDY

    Issued date Project No. Document Number Page Rev.

    5-NOV-2014 PE/000451 FR-EE-403-00003 7 OF 14 L

    8 FAULT CURRENT LEVELS

    Initial Symmetrical Short Circuit Current (maximum):

    BusNominal

    Voltage (kV)Rated ShortCircuit (kA)

    Initial Symmetrical RMS Current kA (Ik )

    Three Phase Line to Ground Line to LineDouble Line to

    Ground

    42-ES-9001 A 11 31.5 26.3 0.4 23.1 23.2

    42-ES-9001 B 11 31.5 26.3 0.4 23.1 23.2

    42-ES-9011 A 0.415 80 54.2 47.3 46.8 52.8

    42-ES-9011 B 0.415 80 54.2 47.3 46.8 52.845-ES-9001 A 11 31.5 25.1 0.4 21.8 21.9

    45-ES-9001 B 11 31.5 25.1 0.4 21.8 21.9

    45-ES-9011 A 0.415 80 47.7 42.8 41.2 46.845-ES-9011 B 0.415 80 47.7 42.8 41.2 46.8

    Peak Short Circuit Current (maximum):

    BusNominal

    Voltage (kV)Rated ShortCircuit (kA)

    Peak Short Circuit Current kA (ip)

    Three Phase Line to Ground Line to LineDouble Line to

    Ground

    42-ES-9001 A 11 31.5 67.7 1.08 59.4 59.7

    42-ES-9001 B 11 31.5 67.7 1.08 59.4 59.7

    42-ES-9011 A 0.415 80 124.3 108.6 107.3 121.3

    42-ES-9011 B 0.415 80 124.3 108.6 107.3 121.3

    45-ES-9001 A 11 31.5 64.9 1.08 56.4 56.7

    45-ES-9001 B 11 31.5 64.9 1.08 56.4 56.7

    45-ES-9011 A 0.415 80 110.4 99.1 95.3 108.2

    45-ES-9011 B 0.415 80 110.4 99.1 95.3 108.2

    Symmetrical Short Circuit Breaking Current (maximum):

    BusNominal

    Voltage (kV)Rated ShortCircuit (kA)

    Symmetrical Short Circuit Breaking Current kA (Ib)

    Line to Ground Line to Line Double Line to Ground

    42-ES-9001 A 11 31.5 0.4 23.1 23.2

    42-ES-9001 B 11 31.5 0.4 23.1 23.2

    42-ES-9011 A 0.415 80 47.3 46.8 52.8

    42-ES-9011 B 0.415 80 47.3 46.8 52.8

    45-ES-9001 A 11 31.5 0.4 21.8 21.9

    45-ES-9001 B 11 31.5 0.4 21.8 21.9

    45-ES-9011 A 0.415 80 42.8 41.2 46.8

    45-ES-9011 B 0.415 80 42.8 41.2 46.8

  • 7/24/2019 FR-EE-403-00003-L

    8/20

    Abu Dhabi Polymers Company Limited (Borouge)

    BOROUGE PO FLARE GAS RECOVERY PROJECT

    RELAY SETTINGS & PROTECTION COORDINATION STUDY

    Issued date Project No. Document Number Page Rev.

    5-NOV-2014 PE/000451 FR-EE-403-00003 8 OF 14 L

    Initial Symmetrical Short Circuit Current (minimum):

    BusNominal

    Voltage (kV)Rated ShortCircuit (kA)

    Initial Symmetr ical RMS Current kA (I k)

    Three Phase Line to Ground Line to Line Double Line toGround

    42-ES-9001 A 11 31.5 14.1 0.3 12.2 12.3

    42-ES-9001 B 11 31.5 14.1 0.3 12.2 12.3

    42-ES-9011 A 0.415 80 29.7 30.6 25.7 30.2

    42-ES-9011 B 0.415 80 29.7 30.6 25.7 30.2

    45-ES-9001 A 11 31.5 14.1 0.3 12.2 12.3

    45-ES-9001 B 11 31.5 14.1 0.3 12.2 12.3

    45-ES-9011 A 0.415 80 28.1 28.9 24.3 28.5

    45-ES-9011 B 0.415 80 28.1 28.9 24.3 28.5

    Peak Short Circuit Current (minimum):

    BusNominal

    Voltage (kV)Rated ShortCircuit (kA)

    Peak Short Circuit Current kA (ip)

    Three Phase Line to Ground Line to LineDouble Line to

    Ground

    42-ES-9001 A 11 31.5 36.7 0.9 31.8 32

    42-ES-9001 B 11 31.5 36.7 0.9 31.8 32

    42-ES-9011 A 0.415 80 74.7 77.1 64.7 76

    42-ES-9011 B 0.415 80 74.7 77.1 64.7 76

    45-ES-9001 A 11 31.5 36.7 0.9 31.8 32

    45-ES-9001 B 11 31.5 36.7 0.9 31.8 32

    45-ES-9011 A 0.415 80 70.2 72.3 60.8 71.4

    45-ES-9011 B 0.415 80 70.2 72.3 60.8 71.4

    Symmetrical Short Circuit Breaking Current (minimum):

    BusNominal

    Voltage (kV)Rated ShortCircuit (kA)

    Symmetrical Short Circuit Breaking Current kA (Ib)

    Line to Ground Line to Line Double Line to Ground

    42-ES-9001 A 11 31.5 0.3 12.2 12.3

    42-ES-9001 B 11 31.5 0.3 12.2 12.3

    42-ES-9011 A 0.415 80 30.6 25.7 30.2

    42-ES-9011 B 0.415 80 30.6 25.7 30.2

    45-ES-9001 A 11 31.5 0.3 12.2 12.3

    45-ES-9001 B 11 31.5 0.3 12.2 12.3

    45-ES-9011 A 0.415 80 28.9 24.3 28.5

    45-ES-9011 B 0.415 80 28.9 24.3 28.5

  • 7/24/2019 FR-EE-403-00003-L

    9/20

    Abu Dhabi Polymers Company Limited (Borouge)

    BOROUGE PO FLARE GAS RECOVERY PROJECT

    RELAY SETTINGS & PROTECTION COORDINATION STUDY

    Issued date Project No. Document Number Page Rev.

    5-NOV-2014 PE/000451 FR-EE-403-00003 9 OF 14 L

    9 RELAY TYPE

    The relays used for HV motor feeder protection are ABB make REF630 with following protection functions.

    Motor FeederREF 630

    50P Phase definite time OC

    51P Phase inverse OC

    50N Earth definite time OC

    51N Earth inverse OC

    87M Differential protection

    74 Alarm

    42R Running CB

    86 Lockout

    46 Phase balance current relay

    38 Bearing protection49 Thermal protection

    49T Temperature protection

    48 Incomplete Sequence Relay

    66 Jogging device

    10 HV PROTECTION RELAY SETTINGS DATA

    Only over current protection function settings (50P, 50G, 51P, 51G) are proposed in this document. All othersettings shall be performed at site during commissioning stage.

    Motor TAG 47-XK-921-KM-921 47-XK-931-KM-931

    Description Motor feeder Motor feeder

    Relay REF 630 REF 630

    CT Ratio 250-1 200-1OVERCURRENT STAGE I> (51) Settings

    Pickup Value 0.9 0.9

    TMS 3.5 2.11

    Characteristic CurveIEC-

    Extremely InverseIEC-

    Extremely Inverse

    OVERCURRENT INSTANTANEOUS I>> (50) Settings

    Pickup Value 6.71 6.41

    Time 0.05 0.05

    RESIDUAL CURRENT INSTANTANEOUS I02 > (50N) Settings

    Pickup Value 0.21 0.18

    Time 0.05 0.05

  • 7/24/2019 FR-EE-403-00003-L

    10/20

    Abu Dhabi Polymers Company Limited (Borouge)

    BOROUGE PO FLARE GAS RECOVERY PROJECT

    RELAY SETTINGS & PROTECTION COORDINATION STUDY

    Issued date Project No. Document Number Page Rev.

    5-NOV-2014 PE/000451 FR-EE-403-00003 10 OF 14 L

    11 TIME CURRENT CURVES

    Time current curves (TCC) are plotted to verify the present state of coordination.

    a. 47-XK-921-KM-921 PE compressor motor relay phase TCC.

    Figure 1

  • 7/24/2019 FR-EE-403-00003-L

    11/20

    Abu Dhabi Polymers Company Limited (Borouge)

    BOROUGE PO FLARE GAS RECOVERY PROJECT

    RELAY SETTINGS & PROTECTION COORDINATION STUDY

    Issued date Project No. Document Number Page Rev.

    5-NOV-2014 PE/000451 FR-EE-403-00003 11 OF 14 L

    b. 47-XK-921-KM-921 PE compressor motor relay earth time current curves

    Figure 2

  • 7/24/2019 FR-EE-403-00003-L

    12/20

    Abu Dhabi Polymers Company Limited (Borouge)

    BOROUGE PO FLARE GAS RECOVERY PROJECT

    RELAY SETTINGS & PROTECTION COORDINATION STUDY

    Issued date Project No. Document Number Page Rev.

    5-NOV-2014 PE/000451 FR-EE-403-00003 12 OF 14 L

    c. 47-XK-931-KM-931 PP compressor motor relay phase time current curves

    Figure 3

  • 7/24/2019 FR-EE-403-00003-L

    13/20

    Abu Dhabi Polymers Company Limited (Borouge)

    BOROUGE PO FLARE GAS RECOVERY PROJECT

    RELAY SETTINGS & PROTECTION COORDINATION STUDY

    Issued date Project No. Document Number Page Rev.

    5-NOV-2014 PE/000451 FR-EE-403-00003 13 OF 14 L

    d. 47-XK-931-KM-931 PP compressor motor relay earth time current curves

    Figure 4

  • 7/24/2019 FR-EE-403-00003-L

    14/20

    Abu Dhabi Polymers Company Limited (Borouge)

    BOROUGE PO FLARE GAS RECOVERY PROJECT

    RELAY SETTINGS & PROTECTION COORDINATION STUDY

    Issued date Project No. Document Number Page Rev.

    5-NOV-2014 PE/000451 FR-EE-403-00003 14 OF 14 L

    12 CONCLUSION AND RECOMMENDATIONS

    Relay coordination study has been performed after incorporating protection settings of existing system andproposed protection settings of newly added loads. The study reflects that both HV & LV electrical systemsare adequate and properly coordinated after the Borouge project load additions and no modification/updatein protection settings of existing system is required at this stage.

  • 7/24/2019 FR-EE-403-00003-L

    15/20

    PROTECTION COORDINATION STUDY

    ETAP SLD

    ATTACHMENT A

  • 7/24/2019 FR-EE-403-00003-L

    16/20

    -Line Diagram - SCMAX (Star Sequence-of-Operation)

    12:05:32 Oct 31, 2014 Project File: ETAP-3583-PO

    42- ES- 9001 A

    42-

    XE-

    705-

    NM-

    701A

    1400kW

    42-XE- 705- EC- 701A

    42- XE-705-EP- 701A1750 kVA

    R

    CB330

    42-EP-9233

    R

    CB331

    42- EP-9031

    R

    CB332

    C/ 42- ES-9001 B

    XC/42-

    ES-

    001B

    0 A

    CB326

    42-EP-9032

    CB32R

    CB338Open

    80- ES-1802 B

    I>

    R

    42-EP-901231. 5 MVA

    CB339

    R

    CB341

    R

    CB334

    C/ 42- ES-9001 A

    XC/42-

    ES-

    001A

    0 A

    R

    CB335

    80- ES- 1802 A

    I>

    R

    42- EP-901131. 5 MVA

    CB336

    R

    42-EP-9231

    R

    CB337

    42-

    XK-

    402-

    KM-

    402

    2300kW

    R

    CB17CB40

    R

    47-ECC

    -500

    01

    1-3/

    C18

    5

    47-

    XK-

    921-

    KM-

    921

    3300kW

    42- XE-705-EP- 701A1750 kVA

    42-XE- 705- EC- 701A

    42-

    XE-

    705-

    NM-

    701A

    1400kW

    80- ES- 1802 A 80- ES- 1802 B

    42- ES- 9001 A

    CB335CB334CB332CB331CB330

    CB338Open

    CB32CB341CB326

    CB336CB339

    42- EP-901131. 5 MVA

    42-EP-901231. 5 MVA

    C/ 42- ES-9001 A

    XC/42-

    ES-

    001A

    0 A

    C/ 42- ES-9001 B

    XC/42-

    ES-

    001B

    0 A

    CB337

    42- EP-9031

    42-EP-903242- EP- 9231 42- EP- 9233

    42-

    XK-

    402-

    KM-

    402

    2300kW

    CB17

    47-ECC

    -500

    01

    1-3/

    C18

    5

    47-

    XK-

    921-

    KM-

    921

    3300kW

    CB40

  • 7/24/2019 FR-EE-403-00003-L

    17/20

    -Line Diagram - SCMAX (Star Sequence-of-Operation)

    12:03:46 Oct 31, 2014 Project File: ETAP-3583-PO

    45- ES- 9001 A

    47-

    XK-

    931-

    KM-

    931

    2650kW

    47-ECC

    -500

    02

    1-3/

    C18

    5

    R

    CB38

    45- ES- 9001 A

    47-ECC

    -500

    02

    1-3/

    C18

    5

    CB38

    47-

    XK-

    931-

    KM-

    931

    2650kW

    45- ES-9001 B

    C/45-ES-9001

    B

    XC/4

    5-

    ES-

    9001B

    0 A

    CB571

    45- EP- 9031

    R

    CB577

    C/45-

    ES-

    9001A

    XC/45-

    ES-

    9001A

    0 A

    R

    CB580

    CB583 Open

    R

    80- ES-1803 A

    I>

    R

    45- EP- 901131. 5 MVA

    CB581

    R

    45- EP- 9231

    R

    CB582

    45-

    XK-

    401-

    KM-

    401

    3150kW

    R

    CB28 CB579

    R R

    CB586

    45- EP- 9032

    CB572

    45-

    XE-

    705-

    NM-

    701

    2 1 0 0

    k W

    80- ES- 1803 B

    I>

    R

    45- EP- 901231. 5 MVA

    CB584

    R

    45- EP- 9232

    CB585

    45-

    XE-

    705-

    NM-

    701

    2 1 0 0

    k W

    XC/45-

    ES-

    9001A

    0 A

    45- ES-9001 B

    XC/4

    5-

    ES-

    9001B

    0 A

    C/45-ES-9001

    B

    C/45-

    ES-

    9001A

    45- EP- 901131. 5 MVA

    45- EP- 901231. 5 MVA

    CB586CB571

    CB572

    CB583 Open

    CB577 CB579 CB580

    CB581

    CB582

    CB584

    CB585

    80- ES- 1803 A 80- ES- 1803 B

    45- EP- 9031

    45- EP- 9032

    45- EP- 9231

    45- EP- 9232

    45-

    XK-

    401-

    KM-

    401

    3150kW

    CB28

  • 7/24/2019 FR-EE-403-00003-L

    18/20

    PROTECTION COORDINATION STUDYETAP REPORT

    ATTACHMENT B

  • 7/24/2019 FR-EE-403-00003-L

    19/20

    Project: BOROUGE #3 ETAP

    Location: LHR PAK

    Contract: 6502

    Engineer: DIPL

    Filename: ETAP-3583-PO

    Page: 1

    Date: 29-10-2014

    Revision: Base

    12.5.0C

    Overcurrent Relay Settings

    OCR: R_42-ES-9001-A1

    MFR: ABB

    Model: RE_630

    Tag #:

    GND:

    If (kA)Base kVCT

    2500/1

    24.70

    0.40

    2500/1Phase:

    LG, (User-Defin

    3 ph, (User-Defi

    OC Level: OC1

    SettingRange

    Phase TOC IEC - Normal Inverse

    Pickup (Tap) 0.3 - 5 xCT Sec 0.790

    Time Dial 0.150

    Phase INST Pickup 0.01 - 35 xCT Sec 6.300

    Time Delay 0.04 - 30 Sec 0.400

    Ground INST Pickup 0.01 - 400 xCT Sec 0.100

    Time Delay 0.01 - 300 Sec 0.600

    OCR: R_42-ES-9001-KM-921

    MFR: ABB

    Model: RE_630

    Tag #:

    GND:

    If (kA)Base kVCT

    100/1

    24.70

    0.40

    250/1Phase:

    LG, (User-Defin

    3 ph, (User-Defi

    OC Level: OC1

    SettingRange

    Phase TOC IEC - Extremely Inverse

    Pickup (Tap) 0.3 - 5 xCT Sec 0.900

    Time Dial 3.500

    Phase INST Pickup 0.01 - 35 xCT Sec 6.710

    Time Delay 0.04 - 30 Sec 0.050

    Ground INST Pickup 0.01 - 400 xCT Sec 0.210

    Time Delay 0.01 - 300 Sec 0.050

    ATTACHMENT B

  • 7/24/2019 FR-EE-403-00003-L

    20/20

    Project: BOROUGE #3 ETAP

    Location: LHR PAK

    Contract: 6502

    Engineer: DIPL

    Filename: ETAP-3583-PO

    Page: 2

    Date: 29-10-2014

    Revision: Base

    12.5.0C

    Overcurrent Relay Settings

    OCR: R_45-ES-9001-A1

    MFR: ABB

    Model: RE_630

    Tag #:

    GND:

    If (kA)Base kVCT

    2500/1

    23.90

    0.40

    2500/1Phase:

    LG, (User-Defin

    3 ph, (User-Defi

    OC Level: OC1

    SettingRange

    Phase TOC IEC - Normal Inverse

    Pickup (Tap) 0.3 - 5 xCT Sec 0.790

    Time Dial 0.150

    Phase INST Pickup 0.01 - 35 xCT Sec 6.300

    Time Delay 0.04 - 30 Sec 0.400

    Ground INST Pickup 0.01 - 400 xCT Sec 0.100

    Time Delay 0.01 - 300 Sec 0.600

    OCR: R_45-ES-9001-KM-931

    MFR: ABB

    Model: RE_630

    Tag #:

    GND:

    If (kA)Base kVCT

    100/1

    23.90

    0.40

    200/1Phase:

    LG, (User-Defin

    3 ph, (User-Defi

    OC Level: OC1

    SettingRange

    Phase TOC IEC - Extremely Inverse

    Pickup (Tap) 0.3 - 5 xCT Sec 0.900

    Time Dial 2.110

    Phase INST Pickup 0.01 - 35 xCT Sec 6.410

    Time Delay 0.04 - 30 Sec 0.050

    Ground INST Pickup 0.01 - 400 xCT Sec 0.180

    Time Delay 0.01 - 300 Sec 0.050