SULTANATE OF OMAN
MINISTRY OF TRANSPORT AND COMMUNICATIONS DIRECTORATE GENERAL OF ROADS & LAND TRANSPORT
MUSCAT
UPGRADING OF FALAJ AL QABAIL ROUNDABOUT TENDER NO. 51/2012
MONTHLY PROGRESS REPORT NO. 10
OCTOBER 2014
CONSULTANT:
RENARDET S.A. & PARTNERS CONSULTING ENGINEERS LLC. P.O. Box 579, Muscat, P.C. 100, Sultanate of Oman
CONTRACTOR:
CONSOLIDATED CONTRACTORS CO. LLC P.O. Box 614, Muscat, P.C. 100, Sultanate of Oman
Project: Upgrading of Falaj Al Qabail Roundabout Monthly Progress Report October 2014
RENARDET S.A. & PARTNERS Page 1
Table of Contents
1. PROJECT PARTICULARS .............................................................................................................................................. 2
2. SCOPE OF WORK ....................................................................................................................................................... 3
3. TYPICAL CROSS SECTIONS .......................................................................................................................................... 4
4. SITE VISITS/ MEETINGS .............................................................................................................................................. 6
5. ENGINEERS SITE STAFF ............................................................................................................................................. 7
6. PROGRESS S-CURVE ................................................................................................................................................... 8
7. STATUS OF MAJOR ACTIVITIES ................................................................................................................................ 10
8. BRIDGE SUB-STRUCTURE PROGRESS SCHEDULE ...................................................................................................... 11
9. MSE WALLS PROGRESS SCHEDULE ........................................................................................................................... 12
10. BOX CULVERTS PROGRESS SCHEDULE ...................................................................................................................... 15
11. PROGRESS STATUS OF UTILITY CROSSING DUCTS .................................................................................................... 19
12. PROJECT STRIP CHART ............................................................................................................................................. 23
13. FINANCIAL STATUS OF PAYMENTS .......................................................................................................................... 29
14. DETAILS OF EQUIPMENT AVAILABLE AT SITE ........................................................................................................... 30
15. DETAILS OF MANPOWER AVAILABLE AT SITE .......................................................................................................... 32
16. QA/QC REPORTS ...................................................................................................................................................... 34
17. STATUS OF MATERIAL APPROVALS .......................................................................................................................... 39
18. ENGINEERS COMMENTS ......................................................................................................................................... 40
19. DETAILS OF CORRESPONDENCE DURING THE MONTH ............................................................................................. 41
20. PROGRESS PHOTOGRAPHS ...................................................................................................................................... 42
Project: Upgrading of Falaj Al Qabail Roundabout Monthly Progress Report October 2014
RENARDET S.A. & PARTNERS Page 2
1. Project Particulars
Client: Ministry of Transport & Communications
P.O. Box 684, Muscat, Postal Code 113
Directorate General of Roads
Sultanate of Oman.
Consultant: Renardet S.A & Partners L.L.C.
P.O. Box 579, Muscat, Postal Code 100
Sultanate of Oman.
Contractor: Consolidated Contractors Company L.L.C.
P.O. Box 614, Muscat, Postal Code 100
Sultanate of Oman.
Project Commencement Date: 30.10.2013
Mobilization Period: 60 Days
Construction Period: 548 Days
Completion date: 29.06.2015
Original Contract Value:
(Including Contingencies) R.O. 17,884,403.000
Amount of Contingencies: R.O. 1,402,155.613
Original Contract Value:
(Excluding Contingencies) R.O. 16,482,247.387
Planned Physical Progress for September
2014 8.49%
Actual Physical Progress for September
2014 6.20%
Planned physical progress cumulative up to
end of September 2014
48.35%
Achieved physical progress cumulative up
to end of September 2014 45.39%
Project: Upgrading of Falaj Al Qabail Roundabout Monthly Progress Report October 2014
RENARDET S.A. & PARTNERS Page 3
2. Scope of Work
This project is located in Batinah Region on existing Batinah Highway in the Wilayat Sohar and
consists of construction of an interchange in place of existing roundabout along with allied works.
Total length of the project along Batinah highway is about 4.0 km which shall be converted from four
lanes to six lanes with tapering back to 4lanes, all as shown on plans. Also included in the scope of
work is the construction of service roads, pedestrian underpasses.
The work also includes expropriation of properties, relocation/protection of services (sewerage,
telephone, electricity, water, irrigation) road lighting works and traffic signals.
Major items within the scope of work consist of but not limited to the following:
Removal of existing asphalt surface, extension of existing embankment and earthwork to
achieve the designed profile and gradient.
Removal of existing drainage structures and construction of new ones including protection
works as shown on construction drawings and as directed.
Expropriation of open/built up properties and removal of existing structures thereupon.
Construction of interchange ramps, Box Girder Bridge, roundabout, pedestrian underpasses and
service roads.
Provision of new street lighting system/traffic signals and removal/disposal of existing street
light poles including conductors/cables, transformers, feeder pillars, foundations etc., all for the
proper completion of the job.
Construction of earthen embankment/sub grade, sub-base, aggregate base course, bituminous
base course and bituminous wearing course as per details on the construction drawings.
Installation of road side furniture (traffic signs, road marking etc.) and protection works on
embankment slopes.
Relocation/Protection of existing LT, 11KV and 33KV transmission lines and allied items
(transformers etc.) as per the requirements of concerned authority.
Relocation/Protection of existing utilities (sewerage, telephone, electricity, water lines and
irrigation) as per the requirements of concerned authorities.
Provision of ducts for future utilities as per the requirements of utility operator.
Construction of concrete safety barriers, fixing of guard rails and paving tiles.
Provision of traffic diversion in coordination with concerned authorities.
Project: Upgrading of Falaj Al Qabail Roundabout Monthly Progress Report October 2014
RENARDET S.A. & PARTNERS Page 4
3. Typical Cross Sections
Project: Upgrading of Falaj Al Qabail Roundabout Monthly Progress Report October 2014
RENARDET S.A. & PARTNERS Page 5
Project: Upgrading of Falaj Al Qabail Roundabout Monthly Progress Report October 2014
RENARDET S.A. & PARTNERS Page 6
4. Site visits/ Meetings
S. No. Details of Site Visit/ meeting Date Final Outcome/ Decisions
1 Meeting with Dr. Ramadan, Director
of Planning, Sohar Municipality
14.10.2014 Land owner of Plot adjacent to
Sohar Airport Access Road details
are obtained.
Project: Upgrading of Falaj Al Qabail Roundabout Monthly Progress Report October 2014
RENARDET S.A. & PARTNERS Page 7
5. Engineers Site Staff
S.
No. Name Designation
Date of
Joining
1. Roberto Benigni Head Supervision Projects
2. Muneer Abdul Resident Engineer 19.03.2014
3. Hussein Shah Material Engineer 04.01.2014
4. Ernesto B. Paredes Bridge Engineer 16.04.2014
5. Sande H Tangaras Civil Engineer 08.06.2014
6. Danilo Quantity Surveyor 19.06.2014
6. Mohamed Safie Land Surveyor 04.01.2014
7. Aseef Iqbal Site Inspector 10.02.2014
8. Alaa Aldin Abdelfatah Site Inspector 30.03.2014
9. Walid Samy Abdoh Mostafa Material Inspector 01.04.2014
10. Haneefa Mohmmed Al Zadjali Secretary 13.04.2014
6. Progress S-Curve
2013
Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct
0.01 0.25 1.42 4.23 7.25 10.06 9.42 9.73 10.21 9.79 8.49 5.72 4.55 3.56 2.79 3.83 3.55 3.47 1.67 - - - -
0.11 0.14 0.23 0.28 1.71 3.18 6.84 9.16 9.14 9.08 8.49 7.90 8.08 6.71 6.25 4.68 3.59 3.34 4.42 3.29 1.64 1.11 0.62
- 0.28 0.18 1.01 2.92 5.63 5.18 7.36 7.30 9.33 6.20 - - - - - - - - - - - -
0.01 0.26 1.67 5.91 13.15 23.21 32.64 42.37 52.58 62.37 70.86 76.59 81.13 84.69 87.48 91.31 94.86 98.33 100.00 100.00 100.00 100.00 100.00
0.11 0.25 0.48 0.76 2.47 5.64 12.48 21.64 30.78 39.87 48.35 56.26 64.34 71.05 77.31 81.99 85.59 88.93 93.35 96.64 98.27 99.38 100.00
- 0.28 0.45 1.46 4.38 10.01 15.19 22.55 29.86 39.18 45.39
CUMULATIVE PROGRESS
CL14 Org Plan Cumulative %
Actual Cumulative
2014 2015
MONTHLY PROGRESS
CL14 Org Plan per Month %
Actual per Month
Revised Sch. per Month %
Revised Sch. Cummulative %
0.00
20.00
40.00
60.00
80.00
100.00
120.00
-
2
4
6
8
10
12
Dec
Jan
Fe
b
Ma
r
Apr
Ma
y
Jun
Jul
Aug
Sep
Oct
Nov
Dec
Jan
Fe
b
Ma
r
Apr
Ma
y
Jun
Jul
Aug
Sep
Oct
2013 2014 2015
% C
um
ula
tive
% M
ON
TH
LY
MONTHS
UPGRADING OF FALAJ AL QABAIL ROUNDABOUT PROJECT - OMANMONTHLY CL 14 PLANNED VS. ACTUAL MANHOURS
CL14 Org Plan per Month % Revised Sch. per Month % Actual per Month CL14 Org Plan Cumulative % Revised Sch. Cummulative % Actual Cumulative
REV.: 0
PERIOD ENDING: Oct-14
2013
Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct
CL14 Plan % 0.30 8.67 19.23 26.89 31.77 36.64 41.51 46.39 51.26 56.13 61.01 65.88 70.76 75.63 80.50 85.38 90.25 95.13 100.00 100.00 100.00 100.00 100.00
Revised Plan % 4.11 9.30 17.58 24.18 30.90 35.16 38.97 42.78 46.60 50.41 54.23 58.04 61.86 65.67 69.48 73.30 77.11 80.93 84.74 88.56 92.37 96.18 100.00
Actual - 6.62 13.03 22.36 37.31 43.00 44.11 51.21 56.24 60.13 65.67
CL14 Plan % 0.00 0.00 0.38 20.37 47.70 48.33 48.33 48.33 48.33 48.33 48.33 48.33 48.33 59.91 77.84 90.27 94.93 100.00 100.00 100.00 100.00 100.00 100.00
Revised Plan % - - - - - 7.40 29.85 78.13 78.13 78.13 78.13 78.13 78.13 78.13 78.13 78.13 78.13 80.66 87.59 88.57 100.00 100.00 100.00
Actual - 10.09 10.09 17.59 19.52 77.42 69.96 70.18 70.18 70.18 83.49
CL14 Plan % 0.00 0.00 0.00 0.78 6.58 16.76 29.38 41.37 58.64 66.60 74.18 82.85 84.75 84.75 85.24 92.34 92.34 98.36 100.00 100.00 100.00 100.00 100.00
Revised Plan % - - - - - - - 3.32 12.89 28.83 43.89 60.03 74.82 90.03 95.24 95.95 95.95 96.09 98.30 99.46 99.54 100.00 100.00
Actual - - - - 4.35 4.89 - 5.27 14.93 29.52 47.15
CL14 Plan % 0.00 0.00 1.01 9.21 29.30 45.91 56.90 62.24 64.59 67.94 69.08 69.08 75.05 82.85 93.48 98.64 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Revised Plan % - - - - - 4.26 8.17 16.03 32.68 53.13 67.05 67.47 67.47 67.90 68.32 68.32 68.32 81.11 93.02 97.11 100.00 100.00 100.00
Actual - - - 5.00 5.00 53.23 62.16 74.91 78.29 91.86 98.62
CL14 Plan % 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 11.07 26.27 41.98 59.98 78.73 79.90 79.90 85.20 89.45 92.60 100.00 100.00 100.00 100.00 100.00
Revised Plan % - - - - - - - - - - - 3.58 17.42 31.37 51.32 75.82 75.82 75.82 75.82 87.25 87.25 98.60 100.00
Actual 1.26 3.19
CL14 Plan % 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.08 7.77 19.32 31.22 44.94 51.98 52.14 90.14 90.14 100.00 100.00 100.00 100.00 100.00
Revised Plan % - - - - - - - - - - - - - 0.08 8.44 22.42 46.57 51.97 51.97 86.66 90.05 93.03 100.00
Actual
CL14 Plan % 0.00 0.00 0.23 1.43 2.97 10.17 23.65 36.51 51.47 63.06 74.26 75.97 77.37 80.05 82.40 88.97 92.13 98.55 100.00 100.00 100.00 100.00 100.00
Revised Plan % - - - 0.26 2.64 7.33 20.62 35.14 50.06 62.76 68.40 72.78 74.07 74.67 83.42 84.04 84.30 87.32 95.58 98.11 99.44 100.00 100.00
Actual - - - 0.48 1.26 5.59 14.93 27.72 40.08 55.38 66.20
CL14 Plan % 0.00 0.00 4.02 15.21 34.62 57.89 69.26 81.40 83.38 83.46 84.50 92.89 99.96 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Revised Plan % - - - - 2.77 7.75 13.76 22.09 29.64 39.02 49.64 59.51 71.33 85.14 87.00 93.50 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Actual - - - 0.01 6.05 14.73 18.14 22.33 26.30 30.75 34.14
CL14 Plan % 0.00 0.00 0.00 0.00 0.00 0.38 1.21 2.63 3.42 4.23 5.50 6.08 6.08 34.35 99.38 99.76 99.76 100.00 100.00 100.00 100.00 100.00 100.00
Revised Plan % - - - - - - - - - - 61.45 74.69 90.19 94.70 94.70 94.70 94.70 94.70 98.41 100.00 100.00 100.00 100.00
Actual - - - 2.50 17.74 14.39 13.24 16.19 16.72 27.56 21.22
CL14 Plan % 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2.80 17.87 43.85 61.59 72.98 81.15 83.94 84.42 85.35 92.86 96.39 100.00 100.00 100.00 100.00 100.00
Revised Plan % - - - - - - - - - - 7.02 20.33 38.29 50.60 59.52 72.89 81.07 83.55 86.89 90.26 95.34 98.27 100.00
Actual - - - - - 2.61 4.98 6.42 8.31 10.67 12.36
CL14 Plan % 0.00 0.00 0.00 4.43 17.23 33.36 49.13 65.07 80.79 93.82 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Revised Plan % - - - - - 0.99 2.30 17.26 33.64 49.01 64.70 79.88 95.44 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
Actual - - - 6.16 9.87 17.63 25.69 35.90 49.03 65.95 72.27
CL14 Plan % 0.00 0.00 0.00 0.00 0.00 0.17 0.79 1.43 5.65 13.41 21.84 30.56 32.94 70.94 75.04 94.02 96.43 100.00 100.00 100.00 100.00 100.00 100.00
Revised Plan % - - - - - - - 0.33 2.34 9.42 17.07 23.51 31.40 41.66 47.49 47.55 47.55 83.28 93.95 97.61 100.00 100.00 100.00
Actual - - - 0.13 5.52 9.26 13.38 16.87 17.75 20.45 14.38
Revised Plan 0.11 0.25 0.48 0.76 2.47 5.64 12.48 21.64 30.78 39.87 48.35 56.26 64.34 71.05 77.31 81.99 85.59 88.93 93.35 96.64 98.27 99.38 100.00
Actual Cum - 0.28 0.45 1.46 4.38 10.01 15.19 22.55 29.86 39.18 45.39 - - - - - - - - - - - -
2013
Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct
0.01 0.25 1.42 4.23 7.25 10.06 9.42 9.73 10.21 9.79 8.49 5.72 4.55 3.56 2.79 3.83 3.55 3.47 1.67 - - - -
0.11 0.14 0.23 0.28 1.71 3.18 6.84 9.16 9.14 9.08 8.49 7.90 8.08 6.71 6.25 4.68 3.59 3.34 4.42 3.29 1.64 1.11 0.62
- 0.28 0.18 1.01 2.92 5.63 5.18 7.36 7.30 9.33 6.20
0.01 0.26 1.67 5.91 13.15 23.21 32.64 42.37 52.58 62.37 70.86 76.59 81.13 84.69 87.48 91.31 94.86 98.33 100.00 100.00 100.00 100.00 100.00
0.11 0.25 0.48 0.76 2.47 5.64 12.48 21.64 30.78 39.87 48.35 56.26 64.34 71.05 77.31 81.99 85.59 88.93 93.35 96.64 98.27 99.38 100.00
- 0.28 0.45 1.46 4.38 10.01 15.19 22.55 29.86 39.18 45.39
UPGRADING OF FALAJ AL QABAIL ROUNDABOUT - OMAN
MANHOURS OVERALL PROJECT S-CURVE
Item Description Wtd.
%
Plan/
Actual
2014
C
Clearing &
Removal of
Obstructions
0.95
2015
B Road Diversions 2.73
Budgeted
Man-Hrs
56,423
19,558
EStructural
Excavation0.72
D Embankment 3.5974,043
14,821
GBituminous
Pavement3.57
FSubbase &
Aggregate Base2.4250,004
73,724
IConcrete for
Bridge22.12
H
Concrete for
Box Culvert
/Underpas
38.19788,138
456,522
L MSE walls 6.84
J Drainage Works 1.50
KIncidental
Construction13.33
30,920
275,037
141,190
2014 2015
MONTHLY PROGRESS
CL14 Org Plan per Month %
Actual per Month
CUMULATIVE PROGRESS
CL14 Org Plan Cumulative %
Actual Cumulative
MMEP Works &
Ducts4.03
TOTAL 100.000
Revised Sch. per Month %
Revised Sch. Cummulative %
83,264
2,063,644
7. Status of Major Activities
Sl. No.
Description Unit BOQ Qty.
(Revised)
Actual Qty.
% Completion
1 Clearing & Grubbing M2 162,000 129,901 80.19%
2 Borrow Excavation (to embankment)
M3 340,000 108,670 31.96%
3 Granular Sub-base M3 28,700 3,900 13.59%
4 Concrete for Culverts M3 15,000 12,421 82.81%
5 Concrete for Bridge M3 13,805 3,286 23.80%
6 Steel reinforcement Fixing ton 4,900 2,063 42.10%
7 Working Piles M3 2,826 2,826 100.00%
8 Mortared Stone Riprap M3 5,210 0.00 0.00%
9 MSE Walls M2 13,200 5,100 39.39%
11 RCC Drainage Pipes LM 4,530 788 17.39%
Project: Upgrading of Falaj Al Qabail Roundabout Monthly Progress Report September 2014
RENARDET S.A. & PARTNERS Page 11
8. Bridge Sub-Structure Progress Schedule
ACTIVITY AB1 L P1L P2L P3L P4L P5L AB2 L
PEDESTAL/POT BEARING - - - - - - -
PIER N/A - - - - - N/A
2nd Lift - 13-Aug-14 19-Aug-14 24-Jul-14 29-Sep-14 4-Sep-14 -
Height (m) - 6.920 6.920 6.920 6.920 6.920 -
1st Lift - 23-Jul-14 7-Aug-14 29-Jun-14 15-Sep-14 10-Aug-14 -
Height (m) - 1.153 1.210 1.440 1.248 1.225 -
BIT. PAINTING - 28-May-14 26-Jun-14 17-May-14 4-Sep-14 23-Jun-14 -
PILE CAP (Pier & Abut.) - 17-May-14 18-Jun-14 8-May-14 25-Aug-14 11-Jun-14 -
F/P & BLINDING 21-Oct-14 11-May-14 11-Jun-14 1-May-14 17-Aug-14 3-Jun-14 -
ACTIVITY AB1 R P1R P2R P3R P4R P5R AB2 R
PEDESTAL/POT BEARING 16-Oct-14 14-Oct-14 14-Oct-14 16-Oct-14 - - -
PIER N/A - - - - - N/A
2nd Lift N/A 9-Jun-14 28-Jun-14 22-Jun-14 20-Sep-14 10-Jul-14 N/A
Height (m) - 6.920 6.920 6.920 6.920 6.920 -
1st Lift N/A 20-May-14 11-Jun-14 26-May-14 10-Sep-14 22-Jun-14 N/A
Height (m) - 0.366 0.423 0.649 0.461 0.438 -
BIT. PAINTING - 12-May-14 25-May-14 8-May-14 4-Sep-14 31-May-14 -
PILE CAP (Pier & Abut.) 9-Oct-14 4-May-14 13-May-14 4/30/2014 27-Aug-14 20-May-14 -
F/P & BLINDING 2-Oct-14 27-Apr-14 7-May-14 22-Apr-14 20-Aug-14 14-May-14 -
PREVIOUSPREVIOUS
MONTHTHIS MONTH
SUB-STRUCTURE WORK PROGRESS (RHS)
SUB-STRUCTURE WORK PROGRESS (LHS)
Project: Upgrading of Falaj Al Qabail Roundabout Monthly Progress Report September 2014
RENARDET S.A. & PARTNERS Page 12
9. MSE Walls Progress Schedule
DATE Elevation DATE
FROM TOFOUNDATION
/BLINDINGFROM TO
FOUNDATION
/BLINDING
22+702.653 22+760 2-Oct-14 22+718.936 22+810 17-Sep-14
3-Oct-14 18-Sep-14
22+760 22+825 30-Sep-14 22+810 22+893.032 9-Aug-14
1-Oct-14 10-Aug-14
22+825 22+840 13-Jul-14 22+893.032 22+976.294 13-Aug-14
14-Jul-14 14-Aug-14
22+840 22+880 6-Jul-14 22+976.294 23+040 18-Aug-14
13-Jul-14 19-Aug-14
22+880 22+908.387 10-Aug-14 23+040 23+088.046 26-Jul-14
11-Aug-14 27-Jul-14
22+908.387 22+969.478 3-Jul-14 23+088.046 23+130 21-Jul-14
5-Jul-14 22-Jul-14
22+969.478 23+000 4-Aug-14 23+130 23+191.774 7-Jul-14
5-Aug-14 10-Jul-14
23+000 23+025 20-Jul-14 23+191.774 23+270.800 26-Jun-14
21-Jul-14 27-Jun-14
23+025 23+070 17-Jul-14
18-Jul-14
23+070 23+140 30-Jun-14
1-Jul-14 DATE
23+140 23+164.573 16-Jun-14 FROM TOFOUNDATION
/BLINDING
17-Jun-14 23+270.762 (L) 23+270.800 (R ) 26-Jun-14
23+164.573 23+237.536 23-Jun-14 27-Jun-14
24-Jun-14
23+237.536 23+270.762 17-Jun-14
18-Jun-14
PREVIOUSP R EVIOUS
M ON T HTHIS MONTH
El. 22.00
El. 22.80
El. 22.00
El. 20.40
El. 22.80
MSE WALLS FOUNDATION AT APPROACH 1as of 31 OCTOBER 2014
El. 21.20
LOCATION (AB 1)
Elevation
Elevation
LOCATION (LHS)
El. 21.20
El. 22.00
El. 22.00
LOCATION (RHS)
El. 20.40
El. 22.00
Project: Upgrading of Falaj Al Qabail Roundabout Monthly Progress Report September 2014
RENARDET S.A. & PARTNERS Page 13
DATE DATE
FROM TOFOUNDATION
/BLINDINGFROM TO
FOUNDATION
/BLINDING
23+508.239 23+520 15-Sep-14 23+508.239 (L) 23+508.197 (R) 15-Sep-14
16-Sep-14 16-Sep-14
23+520 23+580.877 20-Aug-14
21-Aug-14
23+580.877 23+650 26-Aug-14
27-Aug-14 DATE
23+650 23+735 1-Sep-14 FROM TOFOUNDATION
/BLINDING
2-Sep-14 23+508.197 23+607.634 8-Sep-14
23+735 23+790 19-Sep-14 9-Sep-14
20-Sep-14 23+607.634 23+740 22-Sep-14
23+790 23+827.635 - 23-Sep-14
- 23+740 23+950.153 -
El. 24.90 23+827.635 23+949.895 - -
-
PREVIOUSP R EVIOUS
M ON T HTHIS MONTH
LOCATION (RHS)
El. 23.30El. 24.10
El. 24.10
Elevation
El. 23.30
Elevation
MSE WALL FOUNDATIONS PROGRESS AT APPROACH 2as of 31 OCTOBER 2014
El. 23.30
LOCATION (LHS) LOCATION (AB 2)Elevation
23+520 23+580.877 23+650 23+703 23+750 23+827.635 23+949.895
34.500 - - - - - - -33.700 - - - - - - -32.900 - - - - - - -32.100 - - - - - - -31.300 - - - - - - -30.500 - - - - - - -29.700 - - - - - - -28.900 - - - - - - -28.100 - - - - - - -27.300 - - - - - - -26.500 - - - - - - -25.700 29-Oct-14 29-Oct-14 - - - - -24.900 13-Oct-14 13-Oct-14 26-Sep-14 26-Sep-14 - - -24.100 25-Sep-14 25-Sep-14 - - - - -23.300 - - - - - - -
23+508.239 (L)23+508.197 (R )23+607.634 23+690 23+740 23+950.15333.700 - - - - - -32.900 - - - - - -32.100 - - - - - -31.300 - - - - - -30.500 - - - - - -29.700 - - - - - -28.900 - - - - - -28.100 - - - - - -27.300 - - - - - -26.500 - - - - - -25.700 - - - - - -24.900 16-Oct-14 16-Oct-14 15-Oct-14 15-Oct-14 - -24.100 30-Sep-14 30-Sep-14 9-Oct-14 - - -23.300 - - - - - -
as of 31 OCTOBER 2014
ELEV.AB 2 Face
LHS (AB 2), from Sta. 23+508.239 to Sta. 23+949.895ELEV.
RHS (AB 2), from Sta. 23+508.197 to Sta. 23+950.153
MSE WALL PANELS FIXING AT APPROACH 2
Project: Upgrading of Falaj Al Qabail Roundabout Monthly Progress Report September 2014
RENARDET S.A. & PARTNERS Page 14
22+825 22+840 22+880 22+908.38 22+969.47 22+991 23+084 23+164.57 23+237.53 23+270.76
34.800 - - - - - - - - - -34.000 - - - - - - - - - -33.200 - - - - - - - - - -32.400 - - - - - - - - - -31.600 - - - - - - - - - -30.800 - - - - - - - - - -30.000 - - - - - - - - - -29.200 - - - - - - - 19-Oct-14 1-Oct-14 1-Oct-1428.400 - - - - - - - 18-Oct-14 24-Sep-14 24-Sep-1427.600 - - - - - - - 20-Sep-14 18-Sep-14 18-Sep-1426.800 - - - - - - - 9-Sep-14 15-Sep-14 15-Sep-1426.000 - - - - - - 20-Oct-14 4-Sep-14 28-Aug-14 28-Aug-1425.200 - - - - - - 16-Sep-14 26-Aug-14 19-Aug-14 19-Aug-1424.400 - - - - 29-Oct-14 29-Oct-14 4-Sep-14 18-Aug-14 6-Aug-14 6-Aug-1423.600 - - - - 21-Sep-14 17-Sep-14 27-Aug-14 13-Aug-14 24-Jul-14 24-Jul-1422.800 - 22-Sep-14 22-Sep-14 22-Sep-14 11-Sep-14 24-Aug-14 9-Aug-14 28-Jul-14 - 13-Jul-1422.000 - 3-Sep-14 3-Sep-14 3-Sep-14 28-Aug-14 - - - - -21.200 - 28-Aug-14 28-Aug-14 28-Aug-14 - - - - - -
20.400 - - - - - - - - - -
22+810 22+893.03 22+976.29 23+035 23+088.04 23+191.77 23+270.8023+270.762
(L)
23+270.800
(R )
33.200 - - - - - - - - -32.400 - - - - - - - - -31.600 - - - - - - - - -30.800 - - - - - - - - -30.000 - - - - - - - - -29.200 - - - - - - 30-Sep-14 28-Sep-14 28-Sep-1428.400 - - - - - 30-Sep-14 24-Sep-14 24-Sep-14 24-Sep-1427.600 - - - - - 27-Sep-14 18-Sep-14 19-Sep-14 19-Sep-1426.800 - - - - - 13-Sep-14 13-Sep-14 11-Sep-14 11-Sep-1426.000 - - - 20-Oct-14 20-Oct-14 2-Sep-14 31-Aug-14 28-Aug-14 28-Aug-1425.200 - - - 18-Oct-14 18-Oct-14 24-Aug-14 18-Aug-14 18-Aug-14 18-Aug-1424.400 - - 23-Oct-14 20-Sep-14 20-Sep-14 13-Aug-14 6-Aug-14 7-Aug-14 7-Aug-1423.600 - - 25-Sep-14 8-Sep-14 8-Sep-14 9-Aug-14 24-Jul-14 24-Jul-14 24-Jul-1422.800 - 19-Oct-14 18-Sep-14 21-Aug-14 18-Aug-14 - 13-Jul-14 13-Jul-14 13-Jul-1422.000 - 23-Sep-14 26-Aug-14 - - - - - -21.200 - 4-Sep-14 - - - - - - -
20.400 - - - - - - - - -
PREVIOUSP R EVIOUS
M ON T HTHIS MONTH
RHS (AB 1), from Sta. 22+718.936 to Sta. 23+270.800
LHS (AB 1), from Sta. 22+702.653 to Sta. 23+270.762
MSE WALL PANELS FIXING @ APPROACH 1as of 31 OCTOBER 2014
ELEV.
ELEV.
AB 1 Face
10. Box Culverts Progress Schedule
Rebars Concrete Rebars Concrete Rebars Concrete
1 21+260 3 cells - 2.0 x 1.5 25.546 0 - - - - - - - -LHS Block 1 3 cells - 2.0 x 1.5 19.526 0 18-Oct-14 26-Oct-14 26-Oct-14 - - - - -RHS Block 2 3 cells - 2.0 x 1.5 14.473 0 - - - - - - - -RHS Block 3 3 cells - 2.0 x 1.5 6.000 0 - - - - - - - -
2 21+485 1 cell - 2.0 x 1.5 39.750 0 - - - - - - - -Block 1a 1 cell - 2.0 x 1.5 3.000 0 - - - - - - - -Block 1b 1 cell - 2.0 x 1.5 17.290 0 1-Jul-14 31-Aug-14 31-Aug-14 31-Aug-14 31-Aug-14 31-Aug-14 31-Aug-14 1-Sep-14Block 2a 1 cell - 2.0 x 1.5 7.710 0 1-Jul-14 31-Aug-14 31-Aug-14 31-Aug-14 31-Aug-14 31-Aug-14 31-Aug-14 1-Sep-14Block 2b 1 cell - 2.0 x 1.5 10.000 0 21-Oct-14 25-Oct-14 25-Oct-14 25-Oct-14 25-Oct-14 25-Oct-14 25-Oct-14 25-Oct-14Block 2C 1 cell - 2.0 x 1.5 11.730 0 - - - - - - - -
3 21+838 2 x 4 cells (8) - 2.0 x 1.5 57.210 0 - - - - - - - -Block 1a 1 x 4 cells - 2.0 x 1.5 5.000 0 21-Jul-14 4-Sep-14 5-Sep-14 13-Oct-14 13-Oct-14 13-Oct-14 13-Oct-14 -Block 1b 1 x 4 cells - 2.0 x 1.5 17.600 0 3-Jul-14 4-Sep-14 5-Sep-14 13-Oct-14 13-Oct-14 13-Oct-14 13-Oct-14 -Block 2 1 x 4 cells - 2.0 x 1.5 22.600 0 3-Jul-14 20-Aug-14 20-Aug-14 30-Oct-14 30-Oct-14 30-Oct-14 30-Oct-14 -Block 3 1 x 4 cells - 2.0 x 1.5 11.970 0 - - - - - - - -
Block 4a 1 x 4 cells - 2.0 x 1.5 5.000 0 21-Jul-14 10-Sep-14 12-Sep-14 18-Oct-14 19-Oct-14 18-Oct-14 19-Oct-14 -Block 4b 1 x 4 cells - 2.0 x 1.5 17.600 0 3-Jul-14 10-Sep-14 12-Sep-14 18-Oct-14 19-Oct-14 18-Oct-14 19-Oct-14Block 5 1 x 4 cells - 2.0 x 1.5 22.600 0 3-Jul-14 23-Sep-14 24-Sep-14 24-Oct-14 25-Oct-14 24-Oct-14 25-Oct-14 -Block 6 1 x 4 cells - 2.0 x 1.5 11.970 0 - - - - - - - -
4 21+972.4 11 x 4 cel l s (44) - 3.0 x 2.0 57.629 0 - - - - - - - -Block 1 1 x 4 cells - 3.0 x 2.0 28.038 0 24-May-14 5-Jun-14 5-Jun-14 24-Jun-14 24-Jun-14 15-Jul-14 16-Jul-14 16-Aug-14Block 2 1 x 4 cells - 3.0 x 2.0 28.031 0 24-May-14 9-Jul-14 10-Jul-14 3-Aug-14 4-Aug-14 13-Aug-14 14-Aug-14 8-Sep-14Block 3 1 x 4 cells - 3.0 x 2.0 28.026 0 17-May-14 25-May-14 25-May-14 3-Jun-14 3-Jun-14 23-Jun-14 23-Jun-14 8-Sep-14Block 4 1 x 4 cells - 3.0 x 2.0 28.022 0 18-May-14 12-Jul-14 13-Jul-14 5-Aug-14 6-Aug-14 18-Aug-14 19-Aug-14 1-Oct-14Block 5 1 x 4 cells - 3.0 x 2.0 28.019 0 18-May-14 29-May-14 29-May-14 8-Jun-14 8-Jun-14 2-Jul-14 2-Jul-14 1-Oct-14Block 6 1 x 4 cells - 3.0 x 2.0 28.018 0 18-May-14 31-Jul-14 31-Jul-14 12-Aug-14 13-Aug-14 27-Aug-14 28-Aug-14 1-Oct-14Block 7 1 x 4 cells - 3.0 x 2.0 28.019 0 18-May-14 10-Jun-14 10-Jun-14 1-Jul-14 1-Jul-14 23-Jul-14 24-Jul-14 5-Oct-14Block 8 1 x 4 cells - 3.0 x 2.0 28.022 0 26-May-14 9-Aug-14 10-Aug-14 25-Aug-14 26-Aug-14 9-Sep-14 10-Sep-14 -Block 9 1 x 4 cells - 3.0 x 2.0 28.026 0 26-May-14 15-Jun-14 15-Jun-14 7-Jul-14 8-Jul-14 4-Aug-14 5-Aug-14 -
Block 10 1 x 4 cells - 3.0 x 2.0 28.031 0 28-May-14 17-Aug-14 18-Aug-14 14-Sep-14 14-Sep-14 24-Sep-14 25-Sep-14 -Block 11 1 x 4 cells - 3.0 x 2.0 28.038 0 28-May-14 19-Jun-14 19-Jun-14 20-Jul-14 20-Jul-14 2-Sep-14 3-Sep-14 25-Sep-14
RHS
LHS
RHS
LHS
LHS
LHS
RHS
TYPE & DIMENSIONSTATIONBASE SLAB WALL
NO.TOP SLAB Bituminous
Paint (2 Coats)LENGTH (m) SKEW ( )
F/P &
BLINDING
Project: Upgrading of Falaj Al Qabail Roundabout Monthly Progress Report September 2014
RENARDET S.A. & PARTNERS
Rebars Concrete Rebars Concrete Rebars Concrete
Block 12 1 x 4 cells - 3.0 x 2.0 21.015 0 10-Aug-14 25-Aug-14 26-Aug-14 2-Sep-14 3-Sep-14 1-Oct-14 1-Oct-14 -Block 13 1 x 4 cells - 3.0 x 2.0 21.010 0 27-Jul-14 22-Sep-14 22-Sep-14 29-Sep-14 29-Sep-14 18-Oct-14 19-Oct-14 -Block 14 1 x 4 cells - 3.0 x 2.0 21.006 0 27-Jul-14 12-Oct-14 12-Oct-14 15-Oct-14 15-Oct-14 26-Oct-14 26-Oct-14 -Block 15 1 x 4 cells - 3.0 x 2.0 21.003 0 25-Jul-14 23-Aug-14 23-Aug-14 8-Sep-14 8-Sep-14 18-Sep-14 19-Sep-14 -Block 16 1 x 4 cells - 3.0 x 2.0 21.001 0 16-Jun-14 27-Jul-14 27-Jul-14 14-Aug-14 14-Aug-14 3-Sep-14 4-Sep-14 -Block 17 1 x 4 cells - 3.0 x 2.0 21.000 0 16-Jun-14 14-Sep-14 15-Sep-14 23-Sep-14 24-Sep-14 14-Oct-14 15-Oct-14 -Block 18 1 x 4 cells - 3.0 x 2.0 21.001 0 12-Jun-14 24-Oct-14 24-Oct-14 30-Oct-14 30-Oct-14 - - -Block 19 1 x 4 cells - 3.0 x 2.0 21.003 0 12-Jun-14 16-Sep-14 16-Sep-14 21-Oct-14 21-Oct-14 30-Oct-14 30-Oct-14 -Block 20 1 x 4 cells - 3.0 x 2.0 21.006 0 8-Jun-14 29-Sep-14 30-Sep-14 1-Oct-14 1-Oct-14 21-Oct-14 21-Oct-14 -Block 21 1 x 4 cells - 3.0 x 2.0 21.010 0 8-Jun-14 1-Sep-14 2-Sep-14 21-Sep-14 21-Sep-14 30-Sep-14 30-Sep-14 -Block 22 1 x 4 cells - 3.0 x 2.0 21.015 0 8-Jun-14 25-Jun-14 25-Jun-14 30-Jul-14 30-Jul-14 16-Sep-14 17-Sep-14 25-Sep-14
4 21+972.4 11 x 4 cells - 3.0 x 2.0 57.629 0 - - - - - - - -Block 23 1 x 4 cells - 3.0 x 2.0 6.635 0 - - - - - - - -Block 24 1 x 4 cells - 3.0 x 2.0 6.782 0 - - - - - - - -Block 25 1 x 4 cells - 3.0 x 2.0 6.819 0 - - - - - - - -Block 26 1 x 4 cells - 3.0 x 2.0 7.217 0 - - - - - - - -Block 27 1 x 4 cells - 3.0 x 2.0 7.975 0 - - - - - - - -Block 28 1 x 4 cells - 3.0 x 2.0 8.571 0 - - - - - - - -Block 29 1 x 4 cells - 3.0 x 2.0 9.267 0 - - - - - - - -Block 30 1 x 4 cells - 3.0 x 2.0 9.949 0 - - - - - - - -Block 31 1 x 4 cells - 3.0 x 2.0 10.260 0 - - - - - - - -Block 32 1 x 4 cells - 3.0 x 2.0 10.262 0 - - - - - - - -Block 33 1 x 4 cells - 3.0 x 2.0 10.265 0 - - - - - - - -
5 22+655 2 x 4 cells (8) - 2.0 x 2.0 95.482 45 R - - - - - - - -(9 cells) 1 cell - 2.0 x 2.0 - - - - - - - -Block 1 1 x 4 cells - 2.0 x 2.0 9.675 45 R - - - - - - - -Block 2 1 x 4 cells - 2.0 x 2.0 32.711 45 R 30-Jun-14 6-Aug-14 7-Aug-14 1-Sep-14 2-Sep-14 1-Sep-14 2-Sep-14 13-Oct-14Block 3 1 x 4 cells - 2.0 x 2.0 32.711 45 R 24-Jun-14 21-Jul-14 21-Jul-14 17-Aug-14 18-Aug-14 17-Aug-14 18-Aug-14 13-Oct-14Block 4 1 x 4 cells - 2.0 x 2.0 20.315 45 R 11-Sep-14 12-Oct-14 13-Oct-14 22-Oct-14 22-Oct-14 22-Oct-14 22-Oct-14 -Block 5 1 x 4 cells - 2.0 x 2.0 19.035 45 R - - - - - - - -Block 6 1 x 4 cells - 2.0 x 2.0 32.711 45 R 29-Jun-14 27-Jul-14 28-Jul-14 13-Sep-14 14-Sep-14 13-Sep-14 14-Sep-14 13-Oct-14Block 7 1 x 4 cells - 2.0 x 2.0 32.711 45 R 24-Jun-14 28-Aug-14 28-Aug-14 24-Sep-14 26-Sep-14 24-Sep-14 26-Sep-14 13-Oct-14Block 8 1 x 4 cells - 2.0 x 2.0 10.95 45 R - - - - - - - -Block 9 1 cell - 2.0 x 2.0 25.03 45 R - - - - - - - -
Block 10 1 cell - 2.0 x 2.0 32.711 45 R 28-Jun-14 20-Aug-14 23-Aug-14 2-Oct-14 3-Oct-14 2-Oct-14 3-Oct-14 13-Oct-14Block 11 1 cell - 2.0 x 2.0 32.711 45 R 29-Jun-14 3-Aug-14 4-Aug-14 2-Oct-14 3-Oct-14 2-Oct-14 3-Oct-14 13-Oct-14Block 12 1 cell - 2.0 x 2.0 4.960 45 R - - - - - - - -
6 23+492 1 x 4 cells (4) - 3.0 x 2.0 79.065 15 R - - - - - - - -(5 cells) 1 cell - 3.0 x 2.0 - - - - - - - -
BASE SLAB WALL TOP SLAB Bituminous Paint (2 Coats)
NO. STATION TYPE & DIMENSION LENGTH (m) SKEW ( )F/P &
BLINDING
RHS
LHS
RHS
RHS
RHS
LHS
RHS
LHS
Project: Upgrading of Falaj Al Qabail Roundabout Monthly Progress Report September 2014
RENARDET S.A. & PARTNERS
Rebars Concrete Rebars Concrete Rebars Concrete
Block 1 1 x 4 cells - 3.0 x 2.0 6.457 15 R - - - - - - - -Block 2 1 x 4 cells - 3.0 x 2.0 31.546 15 R 24-Jun-14 9-Jul-14 9-Jul-14 30-Jul-14 30-Jul-14 16-Aug-14 17-Aug-14 6-Sep-14Block 3 1 x 4 cells - 3.0 x 2.0 31.546 15 R 24-Jun-14 14-Jul-14 15-Jul-14 3-Aug-14 3-Aug-14 21-Aug-14 21-Aug-14 6-Sep-14Block 4 1 x 4 cells - 3.0 x 2.0 7.982 15 R 9/172014 23-Sep-14 24-Sep-14 28-Sep-14 28-Sep-14 1-Oct-14 2-Oct-14 18-Oct-14Block 5 1 cell - 3.0 x 2.0 7.039 15 R - - - - - - - -Block 6 1 cell - 3.0 x 2.0 31.546 15 R 24-Jun-14 5-Aug-14 5-Aug-14 9 & 20/8/2014 9 & 23/8/2014 28-Aug-14 28-Aug-14 4-7/9/2014Block 7 1 cell - 3.0 x 2.0 31.546 15 R 24-Jun-14 6-Aug-14 6-Aug-14 11 & 25/8/2014 11 & 26/8/2014 31-Aug-14 1-Sep-14 4-7/9/2014Block 8 1 cell - 3.0 x 2.0 5.525 15 R 17-Sep-14 28-Sep-14 28-Sep-14 2-Oct-14 2-Oct-14 11-Oct-14 11-Oct-14 18-Oct-14
11-Oct-14 11-Oct-14 - - -7 23+756.5 1 cell - 2.0 x 1.5 67.550 0 - - - - - - - -
Block 1 1 cell - 2.0 x 1.5 12.090 0 - - - - - - - -Block 2 1 cell - 2.0 x 1.5 20.180 0 12-Jul-14 23-Jul-14 23-Jul-14 23-Jul-14 23-Jul-14 23-Jul-14 23-Jul-14 24-Jul-14
Block 3a 1 cell - 2.0 x 1.5 14.430 0 12-Jul-14 23-Jul-14 23-Jul-14 23-Jul-14 23-Jul-14 23-Jul-14 23-Jul-14 24-Jul-14Block 3b 1 cell - 2.0 x 1.5 8.700 0 11-Aug-14 26-Aug-14 26-Aug-14 26-Aug-14 26-Aug-14 26-Aug-14 26-Aug-14 28-Aug-14Block 4 1 cell - 2.0 x 1.5 12.090 0 - - - - - - - -
8 23+997 1 cell - 2.0 x 1.5 70.268 0 - - - - - - - -Block 1 1 cell - 2.0 x 1.5 16.128 0 - - - - - - - -
Block 2a 1 cell - 2.0 x 1.5 4.933 0 - - - - - - - -Block 2b 1 cell - 2.0 x 1.5 13.860 0 8-Jul-14 23-Jul-14 23-Jul-14 23-Jul-14 23-Jul-14 23-Jul-14 23-Jul-14 24-Jul-14Block 3a 1 cell - 2.0 x 1.5 16.300 0 8-Jul-14 23-Jul-14 23-Jul-14 23-Jul-14 23-Jul-14 23-Jul-14 23-Jul-14 24-Jul-14Block 3b 1 cell - 2.0 x 1.5 4.942 0 10-Aug-14 26-Aug-14 26-Aug-14 26-Aug-14 26-Aug-14 26-Aug-14 26-Aug-14 31-Aug-14Block 4a 1 cell - 2.0 x 1.5 7.848 0 10-Aug-14 26-Aug-14 26-Aug-14 26-Aug-14 26-Aug-14 26-Aug-14 26-Aug-14 31-Aug-14Block 4b 1 cell - 2.0 x 1.5 6.197 0
9 24+235 1 cell - 2.0 x 1.5 59.106 0 - - - - - - - -Block 1a 1 cell - 2.0 x 1.5 15.566 0 - - - - - - - -Block 1b 1 cell - 2.0 x 1.5 15.000 0 12-Jul-14 23-Jul-14 23-Jul-14 23-Jul-14 23-Jul-14 23-Jul-14 23-Jul-14 24-Jul-14Block 2a 1 cell - 2.0 x 1.5 8.900 0 12-Jul-14 23-Jul-14 23-Jul-14 23-Jul-14 23-Jul-14 23-Jul-14 23-Jul-14 24-Jul-14Block 2b 1 cell - 2.0 x 1.5 15.600 0 10-Aug-14 26-Aug-14 26-Aug-14 26-Aug-14 26-Aug-14 26-Aug-14 26-Aug-14 31-Aug-14Block 2c 1 cell - 2.0 x 1.5 4.020 0 - - - - - - - -
10 24+570 1 cell - 2.0 x 1.5 51.953 0 - - - - - - - -LHS Block 1 1 cell - 2.0 x 1.5 25.846 0 14-Aug-14 25-Aug-14 25-Aug-14 25-Aug-14 25-Aug-14 25-Aug-14 25-Aug-14 31-Aug-14
Block 2a 1 cell - 2.0 x 1.5 13.500 0 14-Aug-14 25-Aug-14 25-Aug-14 25-Aug-14 25-Aug-14 25-Aug-14 25-Aug-14 31-Aug-14Block 2b 1 cell - 2.0 x 1.5 12.587 0 - - - - - - - -
Note: Precast RCBC were used for all 1 cell - 2.0m x 1.5m locations.
PREVIOUSP R EVIOUS
M ON T HTHIS MONTH
NO. STATION TYPE & DIMENSION LENGTH (m) SKEW ( )F/P &
BLINDING
RHS
LHS
RHS
RHS
RHS
BASE SLAB WALL TOP SLAB Bituminous Paint (2 Coats)
LHS
LHS
LHS
RHS
LHS
RHS
Project: Upgrading of Falaj Al Qabail Roundabout Monthly Progress Report September 2014
RENARDET S.A. & PARTNERS
Rebars Concrete Rebars Concrete Rebars Concrete
1 21+300 2 cells - 4.0 x 3.0 37.700 0 - - - - - - - -LHS Block 1 2 cells - 4.0 x 3.0 15.780 0 9-Oct-14 26-Oct-14 26-Oct-14 - - - - -RHS Block 2 2 cells - 4.0 x 3.0 21.900 0 - - - - - - - -
2 24+300 2 cells - 4.0 x 3.0 44.051 0 - - - - - - - -LHS Block 1 2 cells - 4.0 x 3.0 21.620 0 22-Oct-14 - - - - - - -RHS Block 2 2 cells - 4.0 x 3.0 22.411 0 - - - - - - - -
Rebars Concrete Rebars Concrete Rebars Concrete
1 23+290, SOL-1 1 cells - 4.0 x 4.0 - 0 - - - - - - - -LHS Block 1 1 cells - 4.0 x 4.0 - 0 - - - - - - - -RHS Block 2 1 cells - 4.0 x 4.0 - 0 - - - - - - - -
2 24+360, SOL-1 1 cells - 4.0 x 4.0 59.614 0 - - - - - - - -LHS Block 1 1 cells - 4.0 x 4.0 9.000 0 - - - - - - - -LHS Block 2 1 cells - 4.0 x 4.0 20.777 0 15-Sep-14 1-Oct-14 1-Oct-14 19-Oct-14 19-Oct-14 30-Oct-14 30-Oct-14 -RHS Block 3 1 cells - 4.0 x 4.0 22.777 0 - - - - - - - -RHS Block 4 1 cells - 4.0 x 4.0 7.000 0 - - - - - - - -
3 0+050, SOL-3 1 cells - 4.0 x 4.0 83.223 0 - - - - - - - -LHS Block 1 1 cells - 4.0 x 4.0 17.721 0 - - - - - - - -LHS Block 2 1 cells - 4.0 x 4.0 17.721 0 - - - - - - - -LHS Block 3 1 cells - 4.0 x 4.0 17.721 0 - - - - - - - -RHS Block 4 1 cells - 4.0 x 4.0 30.000 0 - - - - - - - -
PREVIOUSPREVIOUS
MONTHTHIS MONTH
WALLNO.
LENGTH (m) SKEW ()F/P &
BLINDINGTYPE & DIMENSION
PEDESTRIAN UNDERPASS PROGRESS SCHEDULE (BARREL)
TYPE & DIMENSION LENGTH (m)SKEW
( )
TOP SLABBituminous
Paint (2 Coats)STATION
STATIONBASE SLAB WALL
F/P &
BLINDING
BASE SLAB
NO.
VEHICLE UNDERPASS PROGRESS SCHEDULE (BARREL) As of 31 OCTOBER 2014
TOP SLABBituminous
Paint (2 Coats)
11. Progress Status of Utility Crossing Ducts
DRAWING NO.
OF
SETOUT/
EXCV/BE
NO. Stages DIA TYPE WAYS LAYING CONCRETE BACKFILL
LEFT
MIDDLE
RIGHT
LEFT
MIDDLE
RIGHT
LEFT
MIDDLE
RIGHT
LEFT
MIDDLE
RIGHT
LEFT 9/24/14 9/24/14 10/18/14 UTL-LAY- 104 UTL-CON-131A
MIDDLE
RIGHT
LEFT 5/15/14 5/15/14 5/18/14 6/12/14 UTL-LAY- 81 UTL-CON- 65 UTL-BF- 01
MIDDLE 6/11/14 6/11/14 6/12/14 7/10/14 UTL-LAY- 104 UTL-CON- 83 UTL-BF- 20
RIGHT
LEFT 5/19/14 5/19/14 5/20/14 6/4/14 UTL-LAY- 87 UTL-CON- 66 UTL-BF- 03
MIDDLE 6/14/14 14/06/14 6/14/14 6/21/14 UTL-LAY- 108 UTL-CON- 84 UTL-BF- 21
RIGHT
LEFT 5/19/14 5/19/14 5/20/14 5/31/14 UTL-LAY- 85 UTL-CON- 63 UTL-BF- 02
MIDDLE 6/15/14 6/15/14 6/15/14 UTL-LAY- 107UTL-CON- 85
RIGHT
LEFT 5/20/14 5/20/14 5/25/14 6/4/14 UTL-LAY- 86 UTL-CON- 64 UTL-BF- 05
MIDDLE 6/15/14 6/15/14 6/15/14 7/8/14 UTL-LAY- 109UTL-CON- 87 UTL-BF- 23
RIGHT
LEFT 5/25/14 5/25/14 5/25/14 6/4/14 UTL-LAY- 90 UTL-CON-68 UTL-BF- 07
MIDDLE 6/16/14 6/16/14 6/17/14 7/10/14 UTL-LAY- 111UTL-CON- 88 UTL-BF- 28
RIGHT
LEFT 6/17/14 6/17/14 6/18/14 7/9/14 UTL-LAY- 112UTL-CON- 89 UTL-BF- 33
MIDDLE 7/20/14 7/20/14 7/21/14 7/27/14 UTL-LAY- 131UTL-CON- 106UTL-BF-44
RIGHT
LEFT 6/19/14 6/19/14 6/19/14 7/6/14 UTL-LAY- 114UTL-CON- 92 UTL-BF- 31
MIDDLE 7/20/14 7/20/14 7/21/14 7/17/14 UTL-LAY- 132UTL-CON- 107UTL-BF-46
RIGHT
LEFT 6/19/14 6/19/14 6/19/14 7/5/14 UTL-LAY- 113 UTL-CON- 91 UTL-BF- 30
MIDDLE 7/20/14 7/20/14 7/21/14 7/17/14 UTL-LAY- 133UTL-CON- 108UTL-BF-45
RIGHT
LEFT
MIDDLE
RIGHT
LEFT
MIDDLE
RIGHT
LEFT 5/26/14 5/26/14 5/26/14 6/8/14 UTL-LAY- 88 UTL-CON- 69 UTL-BF- 08
MIDDLE 6/11/14 6/11/14 6/11/14 7/22/14 UTL-LAY-106 UTL-CON- 81 UTL-BF-26
RIGHT
LEFT
MIDDLE
RIGHT
LEFT 6/16/14 6/16/14 6/16/14 7/20/14 UTL-LAY- 102UTL-CON- UTL-BF-19
MIDDLE 7/8/14 7/8/14 7/9/14 7/27/14 UTL-LAY- 125UTL-CON-99 UTL-BF-42
RIGHT
LEFT 5/25/14 5/25/14 5/26/14 6/14/14 UTL-LAY- 91 UTL-CON- 71 UTL-BF- 06
MIDDLE 11/06/201 6/11/14 6/11/14 6/23/14 UTL-LAY- 105UTL-CON- 82 UTL-BF- 25
RIGHT
LEFT 5/27/14 5/27/14 5/27/14 6/17/14 UTL-LAY- 92 UTL-CON- 72 UTL-BF- 09
MIDDLE
RIGHT
LEFT 5/28/14 5/28/14 5/28/14 6/17/14 UTL-LAY- 93 UTL-CON- 70 UTL-BF- 10
MIDDLE
RIGHT
3
2
3
3
3
2
2
2
3
1
1
3
4
3
200
200
200
150
300
900
UPVC
UPVC
UPVC
UPVC
UPVC
UPVC
UPVC
UPVC
UPVC
150
150
RC
UPVC
UPVC
UPVC
19 CCC/FQI/EL/13
CCC/FQI/EL/0820
23+060
23+210
23+240
150
150
BACKFIL
LING
RFI REF.S.
NO.CHAINAGE
PIPE
2
2UPVC
INSTALL
ATION
CONCRE
TE
1CCC/FQI/IR/06
SERVICE ROAD-30+030 200 UPVC
2CCC/FQR/IR/11
SOL-20+150 300
2
3
2
4CCC/FQR/WA/0
5 SR-10+600 300 UPVC
5 CCC/FQI/EL/01
9 CCC/FQI/EL/03 21+880
CCC/FQI/EL/04 22+260
11
300 UPVC
7 CCC/FQI/EL/02 21+660
10
150
6 CCC/FQI/IR/01 21+460
UPVC
8 CCC/FQI/IR/02 21+780 300
CCC/FQI/EL/05 22+510 150
14
CCC/FQI/IR/05
JUNCTION
CROSSING
22+587 LHS
12 CCC/FQI/IR/03
21+360 150 UPVC
18 CCC/FQI/EL/07
15 CCC/FQI/EL/06
22+520
13
CCC/FQI/IR/04
JUNCTION
CROSSING
22+520 LHS
CCC/FQI/WA/01
CCC/FQI/WA/02
JUNCTION16
17
23+008 LHS
23+020
22+760
150
23CCC/FQR/IR/10
SOL-30+300 200 UPVC
CCC/FQI/SL/01 21+160 150 UPVC 44A
Project: Upgrading of Falaj Al Qabail Roundabout Monthly Progress Report September 2014
RENARDET S.A. & PARTNERS Page 20
DRAWING NO.
OF
SETOUT/
EXCV/BE
NO. Stages DIA TYPE WAYS LAYING CONCRETE BACKFILL
LEFT 5/29/14 5/29/14 5/29/14 6/17/14 UTL-LAY- 94 UTL-CON- 73 UTL-BF- 11
MIDDLE 7/30/14 8/12/14 7/30/14 8/26/14 UTL-LAY-142 UTL-CON- 115UTL-BF-48
RIGHT
LEFT 5/29/14 6/2/14 6/2/14 6/17/14 UTL-LAY- 95 UTL-CON- 75 UTL-BF- 15
MIDDLE 7/14/14 7/14/14 7/14/14 8/20/14 UTL-LAY- 124UTL-CON- 102UTL-BF- 36
RIGHT
LEFT 5/29/14 6/2/14 6/2/14 6/17/14 UTL-LAY-97 UTL-CON- 76 UTL-BF- 13
MIDDLE 7/14/14 7/14/14 7/15/14 8/20/14 UTL-LAY- 127UTL-CON- 101UTL-BF- 38
RIGHT
LEFT
MIDDLE 8/10/14 8/11/14 8/11/14 8/26/14 UTL-LAY-149AUTL-CON- 120AUTL-BF- 58
RIGHT 10/27/14 10/27/14 UTL-LAY- 206UTL-CON- 153
LEFT 5/29/14 6/2/14 6/3/14 6/19/14 UTL-LAY- 98 UTL-CON- 77 UTL-BF- 14
MIDDLE 8/6/14 8/6/14 8/9/14 8/13/14 UTL-LAY- 134-R1UTL-CON- 109AUTL-BF- 53
RIGHT
LEFT
MIDDLE
RIGHT
LEFT 6/3/14 6/4/14 6/4/14 6/23/14 UTL-LAY- 99 UTL-CON- 78 UTL-BF- 16
MIDDLE 8/11/14 8/11/14 8/19/14 8/26/14 UTL-LAY-140 R1UTL-CON-114UTL-BF- 52
RIGHT
LEFT 6/4/14 6/5/14 6/10/14 23/06/201 UTL-LAY- 100UTL-CON- 79 UTL-BF- 17
MIDDLE 7/23/14 7/24/14 8/19/14 8/26/14 UTL-LAY-139 UTL-CON-112-R1UTL-BF- 47
RIGHT
LEFT 6/9/14 6/9/14 6/10/14 6/23/14 UTL-LAY- 101UTL-CON- 80 UTL-BF- 18
MIDDLE 8/6/14 8/6/14 8/6/14 8/26/14 UTL-LAY-138-R1UTL-CON-111-BUTL-BF- 56
RIGHT
LEFT 7/5/14 7/5/14 7/5/14 8/19/14 UTL-LAY- 123UTL-CON- 94 UTL-BF- 39R1
MIDDLE
RIGHT
LEFT 7/16/14 7/16/14 7/17/14 UTL-LAY- 130UTL-CON- 105
MIDDLE 10/27/14 10/27/14 10/27/14 10/27/14 UTL-LAY-190R1UTL-CON- 148UTL-BF- 72
RIGHT
LEFT 9/14/14 9/14/14 10/14/14 10/20/14 UTL-LAY- 166UTL-CON-125UTL-BF-81
MIDDLE 10/27/14 10/27/14 10/27/14 UTL-LAY- 205UTL-CON- 150
RIGHT
LEFT 9/16/14 9/20/14 UTL-LAY- 173
MIDDLE 10/27/14 10/27/14 10/27/14 UTL-LAY- 203UTL-CON- 149
RIGHT
LEFT
MIDDLE
RIGHT
LEFT 5/21/14 5/21/14 5/21/14 6/4/14 UTL-LAY- 89 UTL-CON- 67 UTL-BF- 04
MIDDLE 6/16/14 6/16/14 6/18/14 7/10/14 UTL-LAY- 110UTL-CON- 90 UTL-BF- 29
RIGHT
LEFT 5/29/14 5/31/14 5/31/14 6/17/14 UTL-LAY- 96 UTL-CON- 74 UTL-BF- 12
MIDDLE 7/10/14 7/10/14 8/13/14 8/26/14 UTL-LAY- 120 R1UTL-CON- 95 UTL-BF- 49
RIGHT
LEFT 7/21/14 8/4/14 8/5/14 UTL-LAY-137-R1UTL-CON- 118
MIDDLE 8/8/14 8/9/14 8/9/14 9/22/14 UTL-LAY-148AUTL-CON- 117UTL-BF- 57
RIGHT 9/16/14 9/16/14 9/16/14 UTL-LAY-172 UTL-CON- 126
LEFT 7/7/14 7/8/14 7/8/14 UTL-LAY-103AUTL-CON-98
MIDDLE 8/12/14 8/13/14 8/14/14 8/15/14 UTL-LAY-150 UTL-CON-122AUTL-BF- 37A
RIGHT
LEFT
MIDDLE
RIGHT
LEFT 7/9/14 7/9/14 7/9/14 UTL-LAY- 116UTL-CON-100
MIDDLE 8/12/14 8/13/14 8/14/14 9/25/14 UTL-LAY-151 UTL-CON-121UTL-BF-81
RIGHT 10/12/14 10/13/14 10/12/14 UTL-LAY-187 UTL-CON-137
LEFT 7/2/14 7/3/14 7/3/14 UTL-LAY-122 UTL-CON-93R1
MIDDLE 7/10/14 7/10/14 7/14/14 UTL-LAY-126 UTL-CON-103
RIGHT 7/22/14 7/22/14 7/23/14 8/20/14 UTL-LAY-136 UTL-CON-110UTL-BF- 50
LEFT 8/30/14 8/31/14 9/14/14 9/30/14 UTL-LAY-158 UTL-CON-96 UTL-BF-64
MIDDLE
RIGHT
4
4
3
1
3
2
3
2
3
2
24+220
24+340
24+520
UPVC
UPVC
UPVC150
23+820
23+900
23+980
24+000
24+020
24+120
37CCC/FQI/OMAN
TEL.1
33
CCC/FQI/OMAN
TEL.2100
150
38 0+140 SOL-3
22+810 100
100
21+870
23+580
24+720
150
100
100
150
UPVC
UPVC
UPVC
UPVC300
150
300
UPVC
UPVC
RC
UPVC
RC
UPVC
UPVC
UPVC
150
CCC/FQI/IR/0726
34
35
36
CCC/FQI/EL/14
CCC/FQI/IR/08
CCC/FQI/EL/15
CCC/FQI/EL/16
CCC/FQI/IR/09
CCC/FQI/EL/17
CCC/FQI/NAW.2
CCC/FQI/NAW.3
CCC/FQI/NAW.4
CCC/FQI/EL/1227
24 CCC/FQI/EL/11
CCC/FQI/EL/0921
CCC/FQI/WA/0425
23+560
CCC/FQI/EL/1022
CCC/FQI/WA/0323
150
150
600
24+820
24+960
25+160
28
29
30
31
32
223A 23+960 UPVC
2
3
1
2
600
300
150
150
3
3
UPVC
2
4
22+080
UPVC
UPVC
UPVC
UPVC 4
39CCC/FQI/SL/03
Rev A22+820 150 UPVC
S.
NO.CHAINAGE
PIPEINSTALL
ATION
CONCRE
TE
BACKFIL
LING
RFI REF.
4
40 CCC/FQI/SL/04 22+990
41 CCC/FQI/SL/02 4
Project: Upgrading of Falaj Al Qabail Roundabout Monthly Progress Report September 2014
RENARDET S.A. & PARTNERS Page 21
DRAWING NO.
OF
SETOUT/
EXCV/BE
NO. Stages DIA TYPE WAYS LAYING CONCRETE BACKFILL
LEFT 9/7/14 9/7/14 10/14/14 10/27/14 UTL-LAY-162 UTL-CON-124UTL-BF-69
MIDDLE 9/15/14 9/15/14 UTL-LAY-162R1
RIGHT 10/27/14 10/28/14 10/27/14 10/30/14 UTL-LAY-207 UTL-CON-152UTL-BF-92
LEFT 9/16/14 9/17/14 9/30/14 10/16/14 UTL-LAY-174 UTL-CON-127UTL-BF-83
MIDDLE 10/14/14 10/18/14 10/14/14 UTL-LAY-188 UTL-CON-138
RIGHT 10/27/14 10/27/14 10/27/14 UTL-LAY-204 UTL-CON-151
LEFT 10/2/14 10/2/14 10/2/14 UTL-LAY-184 UTL-CON-135
MIDDLE
RIGHT
LEFT 10/2/14 10/2/14 10/2/14 UTL-LAY-164 R1UTL-CON-134
MIDDLE
RIGHT
LEFT 10/2/14 10/2/14 10/2/14 UTL-LAY-185 UTL-CON-136
MIDDLE
RIGHT
LEFT
MIDDLE
RIGHT
DRAWING NO.
OF
SETOUT/
EXCV/BE
NO. Stages DIA TYPE WAYS LAYING CONCRETE BACKFILL
LEFT 9/4/14 9/28/14 UTL-LAY-159-BUTL-CON-132
MIDDLE
RIGHT
LEFT
MIDDLE
RIGHT
LEFT
MIDDLE
RIGHT
LEFT
MIDDLE
RIGHT
LEFT 9/16/14 9/17/14 9/30/14 10/18/14 UTL-LAY-167 UTL-CON-128UTL-BF-78
MIDDLE
RIGHT
LEFT
MIDDLE
RIGHT
LEFT
MIDDLE
RIGHT
UPVC 2
5
UPVC 2
UPVC 6
Existing
Road front
SOL-3 Ch.
150 UPVC
Buraimi Road (SOL-3)
CCC/FQI/SL/13
UPVC 2
CCC/FQI/SD/07
CCC/FQI/SD/08
CON
C PI
PECO
NC
PIPE
21+500
21+560
2
Setting Out
, Excavation
and Laying
of UPVC
Street
Lighting
150
42 CCC/FQI/EL/19 23+740 150
150CCC/FQI/SL/01
0+130 150
21+620 450
0+140 150
1CCC/FQI/Omant
el/020+138.348 110
45 CCC/FQI/SD/09
2
24+850
450
46 CCC/FQI/SD 23+400 600
CON
C PI
PE
UPVC 2-4WAY
UPVC 4
42
43
44
450
CON
C PI
PE
S.
NO.CHAINAGE
PIPE
2ACCC/FQI/Omant
el/024UPVC
INSTALL
ATION
CONCRE
TE
BACKFIL
LING
RFI REF.S.
NO.CHAINAGE
PIPE
INSTALL
ATION
CONCRE
TE
BACKFIL
LING
RFI REF.
6
CCC/FQI/SL/14
CCC/FQI/SL/15
CCC/FQI/SL/16
CCC/FQI/SL/17
0+415 1503
4
Existing
Road front
SOL-3 Ch.
150
UPVC 2
Project: Upgrading of Falaj Al Qabail Roundabout Monthly Progress Report September 2014
RENARDET S.A. & PARTNERS Page 22
DRAWING NO.
OF
SETOUT/
EXCV/BE
NO. Stages DIA TYPE WAYS LAYING CONCRETE BACKFILL
LEFT
MIDDLE
RIGHT
LEFT
MIDDLE
RIGHT
LEFT
MIDDLE
RIGHT
LEFT
MIDDLE
RIGHT
LEFT
MIDDLE
RIGHT
LEFT
MIDDLE
RIGHT
DRAWING NO.
OF
SETOUT/
EXCV/BE
NO. Stages DIA TYPE WAYS LAYING CONCRETE BACKFILL
LEFT
MIDDLE
RIGHT
LEFT
MIDDLE
RIGHT
LEFT
MIDDLE
RIGHT
DRAWING NO.
OF
SETOUT/
EXCV/BE
NO. Stages DIA TYPE WAYS LAYING CONCRETE BACKFILL
LEFT
MIDDLE
RIGHT
LEFT
MIDDLE
RIGHT
LEFT
MIDDLE
RIGHT
SERVICE ROAD-01
CCC/FQI/SL/07 0+530 150 UPVC
4
6CCC/FQI/OMAN
TEL/060+648.103 100 UPVC
4
CCC/FQI/SL/10
0+550
100 UPVC 4
4
0+472.8
CCC/FQI/SL/06 UPVC150
CCC/FQI/OMAN
TEL/04
5CCC/FQI/OMAN
TEL/05100 UPVC
1
0+060 4
3 CCC/FQI/SL/08 0+600 100 UPVC 4
2
2
SERVICE ROAD-02
1 1+050 150 UPVC 2
CCC/FQI/SL/12 1+530 150 UPVC 2
S.
NO.CHAINAGE
PIPE
2
2
3
3 CCC/FQI/SL/08
1 CCC/FQI/SL/23 0+020 150 UPVC 6
2 CCC/FQI/SL/24 0+120
S.
NO.CHAINAGE
PIPE INSTALL
ATION
CONCRE
TE
BACKFIL
LING
RFI REF.
INSTALL
ATION
CONCRE
TE
BACKFIL
LING
RFI REF.
S.
NO.CHAINAGE
PIPE INSTALL
ATION
CONCRE
TE
BACKFIL
LING
RFI REF.
SERVICE ROAD-03
12. Project Strip Chart
SUBGRADE IN CUT COMPLETED 21+150-21+500 As of Oct 2014BWC 6 cmTack Coat BBC 12 cmPRIME COAT ABC 2 ND 15 cmABC 1 ST 15 cmGSB 20 cmSubgrade Layr 9Layr 8Layr 7Layr 6Layr 5Layr 4Layr 3Layr 2
EMBANKMENT Layer 1 BED PREPRATION OGL SURVEY
21+0
00
21+0
20
21+0
40
21+0
60
21+0
80
21+1
00
21+1
20
21+1
40
21+1
60
21+1
80
21+2
00
21+2
20
21+2
40
21+2
60
21+2
80
21+3
00
21+3
20
21+3
40
21+3
60
21+3
80
21+4
00
21+4
20
21+4
40
21+4
60
21+4
80
21+5
00
OGL SURVEY BED PREPRATION EMBANKMENT Layer 1layer 2layer 3layer 4layer 5layer 6layer 7layer 8layer 9Subgrade
GSB 20 cmABC 1 ST 15 cmABC 2 ND 15 cmPRIME COAT BBC 12 cmTack Coat BWC 6 cm
21+500-22+000BWC 6 cmTack Coat BBC 12 cmPRIME COAT ABC 2 ND 15 cmABC 1 ST 15 cmGSB 20 cmsub gradeLayer 9Layer 8Layer 7Layer 6Layer 5Layer 4Layer 3Layer 2
EMBANKMENT Layer 1BED PREPRATION OGL SURVEY
21+5
00
21+5
20
21+5
40
21+5
60
21+5
80
21+6
00
21+6
20
21+6
40
21+6
60
21+6
80
21+7
00
21+7
20
21+7
40
21+7
60
21+7
80
21+8
00
21+8
20
21+8
40
21+8
60
21+8
80
21+9
00
21+9
20
21+9
40
21+9
60
21+9
80
22+0
00
OGL SURVEY BED PREPRATION EMBANKMENT Layer 1layer 2layer 3layer 4layer 5layer 6layer 7layer 8layer 9sub grade
GSB 20 cmABC 1 ST 15 cmABC 2 ND 15 cmPRIME COAT BBC 12 cmTack Coat BWC 6 cm
RH
S
FQI PROJECT - PROGRESS STRIP CHART FOR ROAD WORKS
LHS
RH
SLH
S
Project: Upgrading of Falaj Al Qabail Roundabout Monthly Progress Report September 2014
RENARDET S.A. & PARTNERS Page 25
COMPLETED 22+000-22+500 As of Oct 2014BWC 6 cmTack Coat BBC 12 cmPRIME COAT ABC 2 ND 15 cmABC 1 ST 15 cmGSB 20 cmLayr 10 SUB GRADE LAYER Layr 9Layr 8Layr 7Layr 6Layr 5Layr 4Layr 3Layr 2EMBANKMENT Layer 1 BED PREPRATION OGL SURVEY
22+0
00
22+0
20
22+0
40
22+0
60
22+0
80
22+1
00
22+1
20
22+1
40
22+1
60
22+1
80
22+2
00
22+2
20
22+2
40
22+2
60
22+2
80
22+3
00
22+3
20
22+3
40
22+3
60
22+3
80
22+4
00
22+4
20
22+4
40
22+4
60
22+4
80
22+5
00
OGL SURVEY BED PREPRATION EMBANKMENT Layer 1layer 2layer 3layer 4layer 5layer 6layer 7layer 8layer 9layer 10 SUBGRADEGSB 20 cmABC 1 ST 15 cmABC 2 ND 15 cmPRIME COAT BBC 12 cmTack Coat BWC 6 cm
22+500-23+000BWC 6 cmTack Coat BBC 12 cmPRIME COAT ABC 2 ND 15 cmABC 1 ST 15 cmGSB 20 cmLayer 10Layer 9Layer 8Layer 7 5th layer of rock soil Layer 6 layer 15Layer 5Layer 4 4th layer roock soil Layer 3Layer 2EMBANKMENT Layer 1BED PREPRATION OGL SURVEY
22+5
00
22+5
20
22+5
40
22+5
60
22+5
80
22+6
00
22+6
20
22+6
40
22+6
60
22+6
80
22+7
00
22+7
20
22+7
40
22+7
60
22+7
80
22+8
00
22+8
20
22+8
40
22+8
60
22+8
80
22+9
00
22+9
20
22+9
40
22+9
60
22+9
80
23+0
00
OGL SURVEY BED PREPRATION EMBANKMENT Layer 1layer 2layer 3layer 4 4th layer roock soil layer 5layer 6 layer 15layer 7 5th layer of rock soil layer 8layer 9layer 10 SUB GGSB 20 cmABC 1 ST 15 cmABC 2 ND 15 cmPRIME COAT BBC 12 cmTack Coat BWC 6 cm
LHS
RH
SLH
SR
HS
Project: Upgrading of Falaj Al Qabail Roundabout Monthly Progress Report September 2014
RENARDET S.A. & PARTNERS Page 26
COMPLETED 23+000-23+500 As of Oct 2014BWC 6 cmTack Coat BBC 12 cmPRIME COAT ABC 2 ND 15 cmABC 1 ST 15 cmGSB 20 cmLayr 10 rock siol layer no 3Layr 9 5th layer of rock soil layer no 28Layr 8 layer 15 of embankmentLayr 7Layr 6Layr 5Layr 4Layr 3Layr 2EMBANKMENT Layer 1 BED PREPRATION OGL SURVEY
23+0
00
23+0
20
23+0
40
23+0
60
23+0
80
23+1
00
23+1
20
23+1
40
23+1
60
23+1
80
23+2
00
23+2
20
23+2
40
23+2
60
23+2
80
23+3
00
23+3
20
23+3
40
23+3
60
23+3
80
23+4
00
23+4
20
23+4
40
23+4
60
23+4
80
23+5
00
OGL SURVEY BED PREPRATION EMBANKMENT Layer 1layer 2layer 3layer 4layer 5layer 6 layer 15 of embankmentlayer 7 5th layer of rock soil layer no 28layer 8 rock siol layer no 3layer 9layer 10GSB 20 cmABC 1 ST 15 cmABC 2 ND 15 cmPRIME COAT BBC 12 cmTack Coat BWC 6 cm
23+500-24+000BWC 6 cmTack Coat BBC 12 cmPRIME COAT ABC 2 ND 15 cmABC 1 ST 15 cmGSB 20 cmLayer 10Layer 9Layer 8Layer 7Layer 6Layer 5Layer 4 4th layer of Rock siolLayer 3 3rd layer of Rock siolLayer 2 2nd layer of Rock siolEMBANKMENT Layer 11st layer of Rock siolBED PREPRATION OGL SURVEY
24+5
00
24+5
20
24+5
40
24+5
60
24+5
80
24+6
00
24+6
20
24+6
40
24+6
60
24+6
80
24+7
00
24+7
20
24+7
40
24+7
60
23+7
80
23+8
00
23+8
20
23+8
40
23+8
60
23+8
80
23+9
00
23+9
20
23+9
40
23+9
60
23+9
80
24+0
00
OGL SURVEY BED PREPRATION EMBANKMENT Layer 11st layer of rock siollayer 2 2nd layer of rock siollayer 3 3rd layer of rock siollayer 4 4th layer of rock siollayer 5layer 6layer 7layer 8layer 9layer 10GSB 20 cmABC 1 ST 15 cmABC 2 ND 15 cmPRIME COAT BBC 12 cmTack Coat BWC 6 cm
LHS
RH
SLH
SR
HS
Project: Upgrading of Falaj Al Qabail Roundabout Monthly Progress Report September 2014
RENARDET S.A. & PARTNERS Page 27
COMPLETED 24+000-24+500 As of Oct 2014
BWC 6 cmTack Coat BBC 12 cmPRIME COAT ABC 2 ND 15 cmABC 1 ST 15 cmGSB 20 cmLayer 10Layer 9Layer 8Layer 7Layer 6Layer 5Layer 4Layer 3Layer 2
EMBANKMENT Layer 1 BED PREPRATION OGL SURVEY
24+0
00
24+0
20
24+0
40
24+0
60
24+0
80
24+1
00
24+1
20
24+1
40
24+1
60
24+1
80
24+2
00
24+2
20
24+2
40
24+2
60
24+2
80
24+3
00
24+3
20
24+3
40
24+3
60
24+3
80
24+4
00
24+4
20
24+4
40
24+4
60
24+4
80
24+5
00
OGL SURVEY BED PREPRATION EMBANKMENT Layer 1layer 2layer 3layer 4layer 5layer 6layer 7layer 8layer 9layer 10
GSB 20 cmABC 1 ST 15 cmABC 2 ND 15 cmPRIME COAT BBC 12 cmTack Coat BWC 6 cm
24+500-25+000
BWC 6 cmTack Coat BBC 12 cmPRIME COAT ABC 2 ND 15 cmABC 1 ST 15 cmGSB 20 cmLayer 10Layer 9Layer 8Layer 7Layer 6Layer 5Layer 4Layer 3Layer 2
EMBANKMENT Layer 1BED PREPRATION OGL SURVEY
24+5
00
24+5
20
24+5
40
24+5
60
24+5
80
24+6
00
24+6
20
24+6
40
24+6
60
24+6
80
24+7
00
24+7
20
24+7
40
24+7
60
24+7
80
24+8
00
24+8
20
24+8
40
24+8
60
24+8
80
24+9
00
24+9
20
24+9
40
24+9
60
24+9
80
25+0
00
OGL SURVEY BED PREPRATION EMBANKMENT Layer 1layer 2layer 3layer 4layer 5layer 6layer 7layer 8layer 9layer 10
GSB 20 cmABC 1 ST 15 cmABC 2 ND 15 cmPRIME COAT BBC 12 cmTack Coat BWC 6 cm
LHS
RH
SLH
SR
HS
Project: Upgrading of Falaj Al Qabail Roundabout Monthly Progress Report September 2014
RENARDET S.A. & PARTNERS Page 28
COMPLETED 25+000-25+500 As of Oct 2014
BWC 6 cm
Tack Coat
BBC 12 cm
PRIME COAT
ABC 2 ND 15 cm
ABC 1 ST 15 cm
GSB 20 cm
Layr 10
Layr 9
Layr 8
Layr 7
Layr 6
Layr 5
Layr 4
Layr 3
Layr 2
EMBANKMENT Layer 1
BED PREPRATION
OGL SURVEY
25+0
00
25+0
20
25+0
40
25+0
60
25+0
80
25+1
00
25+1
20
25+1
40
25+1
60
25+1
80
25+2
00
25+2
20
25+2
40
25+2
60
25+2
80
25+3
00
25+3
20
25+3
40
25+3
60
25+3
80
25+4
00
25+4
20
25+4
40
25+4
60
25+4
80
25+5
00
OGL SURVEY
BED PREPRATION
EMBANKMENT Layer 1
layer 2
layer 3
layer 4
layer 5
layer 6
layer 7
layer 8
layer 9
layer 10
GSB 20 cm
ABC 1 ST 15 cm
ABC 2 ND 15 cm
PRIME COAT
BBC 12 cm
Tack Coat
BWC 6 cm
LHS
RH
S
13. Financial Status of Payments
Sl. No. DESCRIPTIONPAYMENT FOR
THE MONTH OF
GROSS
AMOUNT
(R.O.)
GROSS
AMOUNT
CLAIMED (R.O.)
NET AMOUNT
CLAIMED
(R.O.)
DATE
SUBMITTED
AMOUNT
CERTIFIED (R.O.)DATE CERTIFIED
AMOUNT
RECEIVED
(R.O.)
DATE
PAYMENT DUE
DATE
PAYMENT
RECEIVED
1PAYMENT APPLICATION No. 1
(ADVANCE PAYMENT)Dec-13 1,648,225 1,648,225 1,648,225 23-Nov-13 1,648,225 29-Jan-14 1,648,225 28-Mar-14 6-Feb-14
2 PAYMENT APPLICATION No. 2 Jan-14 2,291,277 643,052 514,442 12-Feb-14 514,442 02-Apr-14 513,608 30-May-14 10-Apr-14
3 PAYMENT APPLICATION No. 3 Feb&Mar-14 2,808,644 517,367 504,147 06-Apr-14 434,917 03-May-14 414,674 30-Jun-14 6-Aug-14
4 PAYMENT APPLICATION No. 4 Apr-14 3,315,692 507,048 417,900 08-May-14 407,538 05-Jun-14 395,257 2-Aug-14 6-Aug-14
5 PAYMENT APPLICATION No. 5 May-14 4,109,460 793,768 650,802 05-Jun-14 445,708 04-Jul-14 374,172 31-Aug-14 6-Aug-14
6 PAYMENT APPLICATION No. 6 Jun-14 4,293,764 184,304 382,116 15-Jul-14 382,116 16-Jul-14 418,721 12-Sep-14 9-Sep-14
7 PAYMENT APPLICATION No. 7 Jul&Aug-14 5,749,546 1,455,782 1,164,626 14-Sep-14 1,123,023 18-Sep-14 1,123,023 15-Nov-14 27-Oct-14
8 PAYMENT APPLICATION No. 8 Sep-14 6,857,752 1,108,206 928,167 21-Oct-14
9 PAYMENT APPLICATION No. 9 Oct-14
10 PAYMENT APPLICATION No. 10 Nov-14
11 PAYMENT APPLICATION No. 11 Dec-14
12 PAYMENT APPLICATION No. 12 Jan-15
13 PAYMENT APPLICATION No. 13 Feb-15
14 PAYMENT APPLICATION No. 14 Mar-15
15 PAYMENT APPLICATION No. 15 Apr-15
16 PAYMENT APPLICATION No. 16 May-15
17 PAYMENT APPLICATION No. 17 Jun-15
6,857,752 6,857,752 6,210,425 4,955,969 4,887,679 TOTAL AMOUNT (R.O.)
14. Details of Equipment Available At Site
Sl.
No.CCC HIRED
TOTAL
AVAILABLE
AT SITE
1 COMPRESSOR
2 AIR COMPRESSOR 2 1 3
3 MILLER WELDING MECHINE 2 2
4 GENERATOR 3 3
5 CRANES -
6 CRANES 30 TON / 25 TON / 70 TON 2 2 4
7 VEHICLES H.D. -
8 DIESEL TANKER -
9 FLAT TRAILER 2 2
10 HIAB TRUCK 2 2
11 P/MOVER + TIPPING TRAILER 5 5
12 TIPPER TRUCKS 11 4 15
13 WATER TANKER 5000 & 10000 GAL 1 5 6
14 EARTH MOVING PLANT
15 BOBCAT 1 2 3
16 EXCAVATOR 1 1
17 JCB 4CX / 3CX 1 4 5
18 SHOVEL / WHEEL LOADER 3 2 5
19 DOZER D9N/D8R 2 2
20 TELEHANDLER -
21 CIVIL ENGINEERING EQUIPMENT
22 GREENE STABILIZER PLANT 1 1
23 DYNAPAC S/ROLLER -
24 E/WORK ROLLER 1 3 4
25 MOTOR GRADER 1 4 5
26 TITAN PAVER MACHINE -
27 TYRE / PTR ROLLER -
28 PAVER MACHINE -
29 L. D. VEHICLES & TRUCKS
30 DYNA TRUCK 1 2 3
31 MAINTENANCE TRUCKS 1 1
32 ASHOK LEYLAND BUS 55 SEAT 5 5
33 TOYOTA COASTER BUS 24 S 1 1
34 TOYOTA COROLLA/CIVIC/YARIS 12 12
35 TOYOTA PICKUP/ISUZU 5 8 13
36 NISSAN PATHFINDER/X-TRAIL 5 5
37 TOYOTA LAND CRUISER/FORTUNER 4 4
38 Total 47 65 112
DESCRIPTION
Jan-14 Feb-14 Mar-14 Apr-14 May-14 Jun-14 Jul-14 Aug-14 Sep-14 Oct-14 Nov-14 Dec-14 Jan-15 Feb-15 Mar-15 Apr-15 May-15 Jun-15 Jul-15 Aug-15 Sep-15 Oct-15 Total
PLANNED TOTAL PER MONTH 47 68 87 95 93 107 110 108 102 100 98 87 82 79 77 66 53 41 1500
REVISED PLANNED TOTAL PER MONTH 68 87 95 93 107 110 108 102 100 98 87 82 79 77 66 53 41
PLANNED CUMULATIVE 47 115 202 297 390 458 545 640 733 840 950 1,058 1,160 1,260 1,358 1,445 1,527 1,606 1,683 1,749 1,802 1,843
ACTUAL TOTAL PER MONTH 33 55 66 68 77 86 88 100 109 112 794
ACTUAL CUMULATIVE 33 88 154 222 299 385 473 573 682 794
2014 2015
47
68
87
95
93
10
7 110
10
8
10
2
100
98
87
82
79
77
66
53
41
33
55
66 68
77
86 88
10
0
10
9 112
68
87
9593
107110
108
102100
98
87
8279
77
66
53
41
0
20
40
60
80
100
120
Jan
-14
Feb-1
4
Mar-
14
Apr-
14
Ma
y-1
4
Ju
n-1
4
Ju
l-14
Aug
-14
Sep-1
4
Oct-
14
No
v-1
4
Dec-1
4
Jan
-15
Feb-1
5
Mar-
15
Apr-
15
Ma
y-1
5
Ju
n-1
5
Ju
l-15
Aug
-15
Sep-1
5
Oct-
15
No
. o
f E
QU
IPM
EN
T
PROJECT MONTHS
PLANNED TOTAL PER MONTH
ACTUAL TOTAL PER MONTH
REVISED PLANNED TOTAL PER MONTH
15. Details of Manpower Available At Site
BUDGET ACTUAL BUDGET ACTUAL BUDGET ACTUAL
A - MANAGEMENT *** 3 3
B - COMMERCIAL STAFF * 9 1 10
C - ENGINEERS 6 6
D - FOREMAN & C/H 21 2 23
E - ENGINEERING TECHNICIANS ** 23 6 29
F - DAILY RATED EMPLOYEES :
1 - SKILLED CRAFTSMEN 143 65 208
2 - SEMI-SKILLED/UNSKILLED 506 53 559
TOTAL AS OF END OF THE MONTH 0 711 0 127 0 838
G - SUBCONTRACTORS
Number of Personnel employed by Subcontractor on Company Work : 29
STAFF & LABOUR
EXPATRIATES NATIONALS TOTAL
2013Dec-13 Jan-14 Feb-14 Mar-14 Apr-14 May-14 Jun-14 Jul-14 Aug-14 Sep-14 Oct-14 Nov-14 Dec-14 Jan-15 Feb-15 Mar-15 Apr-15 May-15 Jun-15 Jul-15 Aug-15 Sep-15 Oct-15 Total
PLANNED TOTAL PER MONTH - ( DIRECT ) 6 34 186 375 586 791 792 799 794 793 701 480 381 269 246 307 307 305 149 8301
565 756 754 750 700 652 667 554 516 387 297 276 365 271 135 92 51 7788
PLANNED TOTAL PER MONTH - ( INDIRECT ) 5 23 36 50 52 57 59 59 60 61 63 61 61 57 51 47 44 35 30 914
REVISED - PLANNED TOTAL PER MONTH-(INDIRECT) 63 84 84 83 78 72 74 61 57 43 33 31 40 30 15 10 6 862
PLANNED TOTAL PER MONTH - ( DIRECT + INDIRECT ) 11 57 222 425 638 848 851 858 854 854 764 541 442 326 297 354 351 340 179 9215
REVISED - PLANNED - ( DIRECT + INDIRECT ) 627 840 838 833 778 725 741 616 573 429 330 306 406 301 150 102 57 8651
PLANNED CUMULATIVE 11 68 291 715 1,353 2,202 3,052 3,910 4,764 5,618 6,383 6,923 7,365 7,691 7,988 8,342 8,693 9,033 9,212 9,212
ACTUAL TOTAL PER MONTH - ( DIRECT ) 322 365 550 581 603 691 709 756 734 773 767 6851
ACTUAL TOTAL PER MONTH - ( INDIRECT ) 18 26 46 49 54 57 64 69 68 70 71 592
ACTUAL TOTAL PER MONTH - ( DIRECT + INDIRECT ) 340 391 596 630 657 748 773 825 802 843 838 0 0 0 0 0 0 0 0 7443
ACTUAL CUMULATIVE 340 731 1,327 1,957 2,614 3,362 4,135 4,960 5,762 6,605 7,443
REVISED - PLANNED TOTAL PER MONTH - ( DIRECT )
2014 2015
11
57
222
425
638
848
851
858
854
854
764
541
442
326
297
354
351
340
179
340
391
596 6
30 657
748 773
825
802 8
43
838
0 0 0 0 0 0 0 00
100
200
300
400
500
600
700
800
900
Dec-1
3
Jan
-14
Feb-1
4
Mar-
14
Apr-
14
May-1
4
Ju
n-1
4
Ju
l-14
Aug
-14
Sep-1
4
Oct-
14
Nov-1
4
Dec-1
4
Jan
-15
Feb-1
5
Mar-
15
Apr-
15
May-1
5
Ju
n-1
5
Ju
l-15
Aug
-15
Sep-1
5
Oct-
15
No
. o
f M
en
PROJECT MONTHS
PLANNED TOTAL PER MONTH - ( DIRECT + INDIRECT ) ACTUAL TOTAL PER MONTH - ( DIRECT + INDIRECT ) REVISED - PLANNED - ( DIRECT + INDIRECT )
16. QA/QC Reports
Project: Upgrading of Falaj Al Qabail Roundabout Monthly Progress Report September 2014
RENARDET S.A. & PARTNERS Page 35
Project: Upgrading of Falaj Al Qabail Roundabout Monthly Progress Report September 2014
RENARDET S.A. & PARTNERS Page 36
Project: Upgrading of Falaj Al Qabail Roundabout Monthly Progress Report September 2014
RENARDET S.A. & PARTNERS Page 37
Project: Upgrading of Falaj Al Qabail Roundabout Monthly Progress Report September 2014
RENARDET S.A. & PARTNERS Page 38
17. Status of Material Approvals
Date
Submitted
CCC/FQI/REN/MAS/001 MAS/CCC/FQI/BBC/001 Bituminous Base Course Tarmac Zawawi LLC Oman 22/12/2013 Renardet APPROVED 01/04/2014 SO/FQI/CCC/087 07/04/2014
CCC/FQI/REN/MAS/002 MAS/CCC/FQI/GTI/002 Geotechnical Investigation Swissboring & Company LLC 26/12/2013 Renardet APPROVED 02/02/2014 SO/FQI/CCC/015 12/02/2014
CCC/FQI/REN/MAS/003 MAS/CCC/FQI/MSE/003 MSE Wall System Freyssinet Arabian Sea LLC 26/12/2013 Renardet APPROVED 02/02/2014 SO/FQI/CCC/014 12/02/2014
CCC/FQI/REN/MAS/004 MAS/CCC/FQI/PVC/004 UPVC Pipes Amiantit Oman 26/12/2013 Renardet APPROVED 09/02/2014 SO/FQI/CCC/019 18/02/2014
CCC/FQI/REN/MAS/005 MAS/CCC/FQI/HDPE/005 HDPE Pipes & Fittings Amiantit Oman 26/12/2013 Renardet APPROVED 09/02/2014 SO/FQI/CCC/020 18/02/2014
CCC/FQI/REN/MAS/006 MAS/CCC/FQI/PW/006 Piling Works APCC LLC 26/01/2014 Renardet APPROVED 19/02/2014 SO/FQI/CCC/026 25/02/2014
CCC/FQI/REN/MAS/007 MAS/CCC/FQI/MC/007 Bitnuminous Prime Coat (MC-70) Emirates Lube Oil Co. (Muscat) 30/01/2014 Renardet APPROVED 09/03/2014 SO/FQI/CCC/069 27/03/2014
CCC/FQI/REN/MAS/008 MAS/CCC/FQI/RS/008 Reinforcing Steel Muscat Steel Industries 02/02/2014 Renardet APPROVED 20/03/2014 SO/FQI/CCC/063 24/03/2014
CCC/FQI/REN/MAS/009-1 MAS/CCC/FQI/PT/009-1 Post Tensioning Work - Anchorage Freyssinet Arabian Sea LLC 22/02/2014 Renardet APPROVED 27/03/2014 SO/FQI/CCC/089 14/04/2014
CCC/FQI/REN/MAS/009-2 MAS/CCC/FQI/PT/009-2 Post Tensioning Work - Duct Freyssinet Arabian Sea LLC 22/02/2014 Renardet APPROVED 27/03/2014 SO/FQI/CCC/090 14/04/2014
CCC/FQI/REN/MAS/009-3 MAS/CCC/FQI/PT/009-3 Post Tensioning Work - Strand Freyssinet Arabian Sea LLC 22/02/2014 Renardet APPROVED 27/03/2014 SO/FQI/CCC/091 14/04/2014
CCC/FQI/REN/MAS/010A-Rev.1 MAS/CCC/FQI/PB/010A-Rev.1 Bridge Pot Bearings Al Ammar International 07/05/2014 Renardet Not Approved --- REN/FQI/CCC/111 13/05/2014
CCC/FQI/REN/MAS/010B MAS/CCC/FQI/PB/010B Bridge Pot Bearings Building Supplies & Services 11/05/2014 Renardet APPROVED 25/05/2014 REN/FQI/CCC/122 31/05/2014
CCC/FQI/REN/MAS/011 MAS/CCC/FQI/HDPE/011 HDPE Water Pipes Amiantit Oman 22/02/2014 Renardet APPROVED 09/03/2014 SO/FQI/CCC/038 11/03/2014
CCC/FQI/REN/MAS/012 MAS/CCC/FQI/RCBC/012 Single cell Precast Box Culvert Amiantit Oman 22/02/2014 Renardet APPROVED 25/03/2014 SO/FQI/CCC/064 26/03/2014
CCC/FQI/REN/MAS/013 MAS/CCC/FQI/BP/013 Bituminous Paint Material (Rubberized) Al Inma Building Materilal LLC 02/03/2014 Renardet Not Approved 20/04/2014 REN/FQI/CCC/105 05/05/2014
CCC/FQI/REN/MAS/013A MAS/CCC/FQI/BP/013A Bituminous Paint Material (Rubberized) Henkel Polybit Industries Ltd. 17/06/2014 Renardet APPROVED 03/07/2014 REN/FQI/CCC/146 13/07/2014
CCC/FQI/REN/MAS/014A-Rev.1 MAS/CCC/FQI/EJ/014A-Rev.1 Bridge Expansion Joints Al Ammar International 07/05/2014 Renardet APPROVED 20/05/2014 REN/FQI/CCC/123 31/05/2014
CCC/FQI/REN/MAS/015 MAS/CCC/FQI/RC/015 Reinforced Concrete Pipe (450,600,700mm dia) Amiantit Oman 02/03/2014 Renardet APPROVED 23/03/2014 SO/FQI/CCC/077 02/04/2014
CCC/FQI/REN/MAS/016 B MAS/CCC/FQI/WS/016 B Water Stop G EE-25 Sika LLC Oman 25/03/2014 Renardet APPROVED 16/04/2014 REN/FQI/CCC/099 28/04/2014
CCC/FQI/REN/MAS/017 MAS/CCC/FQI/TW/017 Telephone Works National Telephone Services 12/03/2014 Renardet APPROVED 17/03/2014 SO/FQI/CCC/082 03/04/2014
CCC/FQI/REN/MAS/019 MAS/CCC/FQI/EW/019 Electrical Works United Engineering Projects 22/03/2014 Renardet APPROVED 29/05/2014 REN/FQI/CCC/131 16/06/2014
CCC/FQI/REN/MAS/020 MAS/CCC/FQI/EC/020 MV & LV Cables United Engineering Projects 19/03/2014 Renardet APPROVED 27/03/2014 SO/FQI/CCC/083 03/04/2014
CCC/FQI/REN/MAS/021 MAS/CCC/FQI/PS/021 Package Substation United Engineering Projects 22/03/2014 Renardet ---- ----
CCC/FQI/REN/MAS/021A MAS/CCC/FQI/PS/021A Package Substation Voltamp Energy SAOG 16/09/2014 Renardet
CCC/FQI/REN/MAS/022 MAS/CCC/FQI/LL/022 Street Lighting Luminaries Majees Lighting Industries LLC 27/03/2014 Renardet APPROVED 14/08/2014 REN/FQI/CCC/158 17/08/2014
CCC/FQI/REN/MAS/023A MAS/CCC/FQI/LP/023A Street Lighting Poles (Mid-Hinged)Al Babtain Power &
Telecomunication Co., S.Arabia22/05/2014 Renardet APPROVED 14/08/2014 REN/FQI/CCC/157 17/08/2014
CCC/FQI/REN/MAS/024 MAS/CCC/FQI/FP/024 Street Lighting Feeder Pillar Stars Light LLC 27/03/2014 Renardet APPROVED 08/06/2014 REN/FQI/CCC/130 16/06/2014
CCC/FQI/REN/MAS/025 MAS/CCC/FQI/JS/025 Joint Sealant (Polyseal) Al Inma Building Materilal LLC 27/03/2014 Renardet APPROVED 16/04/2014 REN/FQI/CCC/100 28/04/2014
CCC/FQI/REN/MAS/026 MAS/CCC/FQI/GT/026 Geotextile Modern East Trading & Con. 21/05/2014 RenardetNo meet the
HDS--- REN/FQI/CCC/119 27/05/2014
CCC/FQI/REN/MAS/026A MAS/CCC/FQI/GT/026A Geotextile (Bonar NW16) Bonar Technical Fabrics 15/06/2014 Renardet APPROVED 14/08/2014 REN/FQI/CCC/159 17/08/2014
CCC/FQI/REN/MAS/027 MAS/CCC/FQI/MS/027Masterseal 915
(formerly known as Masterflow 410 Plus)OBasf The Chemical Company 10/08/2014 Renardet
Required
latest test
Reports
--- REN/FQI/CCC/166 24/08/2014
CCC/FQI/REN/MAS/028 MAS/CCC/FQI/GG/028 Gully Gratings & Frames RBA Ferro Industries PVT. Ltd. 17/08/2014 Renardet APPROVED 25/09/2014 REN/FQI/CCC/192 15/10/2014
CCC/FQI/REN/MAS/030 MAS/CCC/FQI/FLC/030 MasterRoc FLC 100 (Cable Grout Admixture) BASF-The Chemical Company 02/10/2014 Renardet
CCC/FQI/REN/MAS/032 MAS/CCC/FQI/GR/032 Guardrails GK Wire Industries LLC 29/10/2014 Renardet
CANCELLED
Renardet
Letter
Dated
Reference No. MAR No. Material/ Work Manufacturer/Supplier/
Subcontractor
Submitte
d To
Remarks
By MOTC
MOTC
Comment
s dated
Via Renardet
Letter Ref. No.
18. Engineers Comments
The Planned progress as per the revised Project Execution Program for the month of
October is 8.49% and the Actual progress is 6.20% which shows 2.29% of delay
during the month of October. The actual cumulative progress up to October is
45.39% against Planned Cumulative Progress of 48.35% showing a lagging of
3.00% . Though four working days are reduced during the month due to holidays,
the delayed progress must be recovered in the coming month.
MSE Wall works are commenced on Abutment No. 2 side, and progressing.
Superstructure works are in progress in the Bridge and bottom slab of Bridge No. 1
is casted.
Project: Upgrading of Falaj Al Qabail Roundabout Monthly Progress Report September 2014
RENARDET S.A. & PARTNERS Page 41
19. Details of Correspondence during the month
S.
No.
Date
ReceivedFrom
Reference
NoSubject
Reply
date
Reference
No.Remarks
1
10/1/2014 CCC
FQI-REN-TR-
258
Shop Drawing for 4 way #
150mm upvc Street Lighting
Ducts at SOL-02 CH.0+130
2 10/2/2014 CCC
FQI-
RENARDET/258 Project Road Signs
3 10/2/2014 CCC
FQI-
RENARDET/257
Monthly Progress Report
No.9
410/18/2014 CCC
FQI-REN-TR-
261
Dimension & Details of 3
Cell Box Culvert 3(2.0*1.5)
Skew Angle 0 @ ch.21+260 10/18/2014 Approved
5 10/19/2014 CCC
FQI-
RENARDET/261
Confirmation of vethal
Instruction ( CVI)
6 10/19/2014 CCC
FQI-REN-TR-
267
Bar Bending Schedule for
Vehicular underpass at
ch.21+300 block (1-2) LHS-
RHS 11/2/2014
Approved as
Noted
710/20/2014 CCC
FQI-
RENARDET/264 Hijra New Year
8 20/10/201 CCC
FQI-
RENARDET/265
Access gate for Flyover Box
Girder -Test Certification of
Materials 10/28/2014
REN/FQI/CC
C/193
9 10/22/2014 CCC
FQI-REN-TR-
278
Shop Drawing for
Pedestrian underpass
section Elavation
Reinforcement Details 11/1/2014 Approved
1010/29/2014 CCC
FQI-
RENARDET/269
Additional Item - Friction
slab for Barrier above MSE
Wall
11 10/29/2014 CCC
CCC/FQI/REN/
MAS/032
Approval Guardrails MAR .
NO. MAS/CCC/FOI/GR/032
12 10/30/2014 CCC
FQI-
RENARDET/262
Project monthly progress
Videos & Pictures
Project: Upgrading of Falaj Al Qabail Roundabout Monthly Progress Report September 2014
RENARDET S.A. & PARTNERS Page 42
20. PROGRESS PHOTOGRAPHS
Mu
scat S
ide A
pp
roa
ch
ge
ttin
g R
ea
dy
Project: Upgrading of Falaj Al Qabail Roundabout Monthly Progress Report September 2014
RENARDET S.A. & PARTNERS Page 43
Abutment No. 2 side Approach Works in Progress
Scaffolding for LHS Flyover Superstructure in Progress
Project: Upgrading of Falaj Al Qabail Roundabout Monthly Progress Report September 2014
RENARDET S.A. & PARTNERS Page 44
Installation of Pot Bearings in Progress
Concrete Pouring in Box Girder Bottom Slab
Project: Upgrading of Falaj Al Qabail Roundabout Monthly Progress Report September 2014
RENARDET S.A. & PARTNERS Page 45
Field Tests of Earthwork Filling in Progress
Vehicular Underpass Works in Progress
Project: Upgrading of Falaj Al Qabail Roundabout Monthly Progress Report September 2014
RENARDET S.A. & PARTNERS Page 46
Earthworks for Soar Airport Approach Road in Progress
Asphalt Wearing Course in Sohar Airport Approach Road
Project: Upgrading of Falaj Al Qabail Roundabout Monthly Progress Report September 2014
RENARDET S.A. & PARTNERS Page 47
Completed View of 9 Cells Box Culvert
Status of 8 Cells Box Culvert Progress
Project: Upgrading of Falaj Al Qabail Roundabout Monthly Progress Report September 2014
RENARDET S.A. & PARTNERS Page 48
44 Cells Box Culvert Works in Progress
Pedestrian Underpass Works in Progress