45
A51 : MONESTIER DE CLERMONT VIADUCT Dominique Quivy VINCI Construction France Laurent Bastard-Rosset GTM TP Lyon Michel Londez Independent expert Mécasol FOUNDATIONS OF MONESTIER VIADUCT

FOUNDATIONS OF MONESTIER VIADUCT - cfms … · MONESTIER DE CLERMONT VIADUCT PARTNERS Contracting Authority Design and built joint venture MECASOL VINCI Construction B.E.T. STRATES

Embed Size (px)

Citation preview

A51 : MONESTIER DE CLERMONT VIADUCT

• Dominique Quivy VINCI Construction France• Laurent Bastard-Rosset GTM TP Lyon• Michel Londez Independent expert Mécasol

FOUNDATIONS OF MONESTIER VIADUCT

MONESTIER DE CLERMONT VIADUCT

MONESTIER DE CLERMONT VIADUCT

MONESTIER DE CLERMONT VIADUCT

PARTNERS

� Contracting Authority

� Design and built joint

venture

� MECASOL

� VINCI Construction B.E.T.

� STRATES

� PAYSAGE PLUS

� BAUDIN-CHATEAUNEUF

Les Autoroutes Rhône-Alpes

GTM TP Lyon, mandatary

Geotechnical engineering

Civil engineering design office

Architect : Jean-Vincent

Berlottier

Landscape painter

Structural steel Construction

MONESTIER DE CLERMONT VIADUCT

PLANNING

MONESTIER DE CLERMONT VIADUCT

MONESTIER DE CLERMONT VIADUCT

MONESTIER DE CLERMONT VIADUCT

GEOTECHNICAL ENVIRONMENTMichel LONDEZ

MONESTIER DE CLERMONT VIADUCT

Che

min

de fe

r

Geological Cross section

grey clay

Clay and blocksvvy

Moraines

Moraines

Sliding Area

P5 P6

Rock Rock

RockVarved clay

MONESTIER DE CLERMONT VIADUCT

PIERS SETTING OUT

Che

min

de fe

r

MONESTIER DE CLERMONT VIADUCT

SLIDING ZONE

MONESTIER DE CLERMONT VIADUCT

P3 & P4 FOUNDATIONS CONSTRUCTIONLaurent BASTARD -ROSSET

MONESTIER DE CLERMONT VIADUCT

FOUNDATIONS

Five different types of foundations :

� C0 & P1 : Large pits (4 m diameter)

� P2 : Concrete piles (1,5 m diameter)

� P3 & P4 : semi-deep Foundations

� P5 & P6 : Piles inside circular diaphragm wall

� P7, P8 & C9 : Spread footing

C0 P1 P2 P3 P4 P5 P6 P7 P8 C9

MONESTIER DE CLERMONT VIADUCT

P3 & P4 FOUNDATIONS

Bellow P3 and P4, varved clay which is

water saturated, is present up to 80m

deep.

Ground is therefore not stiff enough to

carry heavy loads.

The design of the foundations is quite

unusual : the principle consists in taking

off a quantity of clay equivalent to the

load brought by the pier itself (weights

of the foundation + pier + deck ).

P 3

MONESTIER DE CLERMONT VIADUCT

P3 FOUNDATION INCLUDES :

- a diaphragm wall (20m diameter and 22m

deep).

- 20m long steel profiles (HEA 300) driven into

clay

- a 1,50m thick concrete slab, poured above a

1,00m thick gravel layer.

- 80cm thick concrete walls stiffening the

structure and allowing transfer of pier load to

the diaphragm wall and concrete slab.

- The inside volume (1700m3) remains empty

except during construction of the pier when it

is filled with water.

diaphragm

wall

Steel

inclusions

22 m

raft

20 m

P3 & P4 FOUNDATIONS

MONESTIER DE CLERMONT VIADUCT

P3 & P4 : DIAPHRAGM WALLS GROUND EXTRACTION

MONESTIER DE CLERMONT VIADUCT

P3 & P4 : DIAPHRAGM WALLS GROUND EXTRACTION

MONESTIER DE CLERMONT VIADUCT

P3 & P4 : DIAPHRAGM WALLS REINFORCEMENT AND CONCRETE

MONESTIER DE CLERMONT VIADUCT

P3 & P4 : STEEL PROFILESDRIVEN INTO CLAY (STAGE 1)

MONESTIER DE CLERMONT VIADUCT

P3 & P4 : CLAY EXCAVATIONINSIDE DIAPHRAGM WALLS

MONESTIER DE CLERMONT VIADUCT

P3 & P4 : FINAL PREPARATION

FINAL PREPARATION OF THE GROUND BEFORE GRAVEL LAYING OPERATIONS AND CUTTING BACK OF STEEL PROFILES

MONESTIER DE CLERMONT VIADUCT

P3 & P4 : STATE OF THE FOUNDATION JUST BEFORE GRAVEL IS LAY DOWN

MONESTIER DE CLERMONT VIADUCT

P3 & P4 : GRAVEL LAYER AND PIEZOMETER IN PLACE

MONESTIER DE CLERMONT VIADUCT

P3 & P4 : REINFORCEMENT OF CONCRETE SLAS

MONESTIER DE CLERMONT VIADUCT

P3 & P4 : STIFFENING STRUCTURE WALLS

MONESTIER DE CLERMONT VIADUCT

P3 & P4 : GENERAL VIEW

MONESTIER DE CLERMONT VIADUCT

SETTLEMENTS CALCULATIONSMichel LONDEZ

¨Pile 3 - Radier à -7m/TN

0

10

20

30

40

50

-0,09 -0,07 -0,05 -0,03 -0,01 0,01 0,03 0,05

Tassements de la paroi (m)

Num

éro

de

s p

as d

e ca

lcu

l

P3C1CasA P3C1CasB P3C1CasC

Fin d 'excavation

Fin de mise en place du gravier

Radier

Avant clavage+remplissage

Relachemenent nappe

Ouvrage terminéVidange de la fouille effectuée

Mise en place de la charge de service

Consolidation

Point sur la paroi

-20.000 0.000 20.000 40.000

-60.000

-40.000

-20.000

0.000

P3CPT3

- 60

- 50

- 40

- 30

- 20

- 10

00 50 100 150 200

Cu (kPa)

Pro

fond

eur

(m)

C (qt/12) C (qt/10) Pressiomètre P3S2

MONESTIER DE CLERMONT VIADUCT

THE STUDIESSurvey program

� P3 to P6� Core borings,

� CPTU 65 m deep

� Pressiometric tests

� Cross hole

� Pumping test

� Inclinometres

� Laboratory tests

MONESTIER DE CLERMONT VIADUCT

MAIN RESULTS

� Accross the valley:

� South west area:

- Rock at 50 m.

- Fluvio-glacial permeable till between 40 à 50 m

- Gravelly clays below soft and remolded clays

� Centre and north of the valley:

- Deepening of rock (P2)

- Argiles homogeneous clays at the surface, varved b elow

MONESTIER DE CLERMONT VIADUCT

GEOLOGICAL PROFILE

Che

min

de fe

r

Rock

Rock

Geological Cross

section

Rock

Morainesgrey clay

Varved stiffer clay

Rock

varved clayClay and blocks

ClSliding Areay and blocks

MONESTIER DE CLERMONT VIADUCT

PENETRATION TEST FOR P3

MONESTIER DE CLERMONT VIADUCT

CU (KPA) FROM CPTU AND PRESSURMETRES

P3CPT3

- 60

- 50

- 40

- 30

- 20

- 10

00 50 100 150 200

Cu (kPa)P

rofo

ndeu

r (m

)

C (qt/12) C (qt/10) Pressiomètre P3S2

MONESTIER DE CLERMONT VIADUCT

OCR FOR P3

P3CPT3

- 60

- 50

- 40

- 30

- 20

- 10

0

1 1,5 2 2,5 3OCR

MONESTIER DE CLERMONT VIADUCT

FOUNDATION OF BEARINGS P3 & P4

The foundations of P3 and P4 include :

- a cylindral skirt made of diaphragm wall,

20m diameter and 22 to 26 m deep.

- A 1,50m thick concrete slab

- Steel inclusions (HEA 300), down to 20m

below the slab,

- Stiffening walls 80cm thick to tranfert the

shaft efforts to the slab and the diaphragm

walls

An inner volume of 1700m3 above the slab

remains empty.

MONESTIER DE CLERMONT VIADUCT

Steel profiles setting out

MONESTIER DE CLERMONT VIADUCT

PARAMETRES OF CALCULATIONS

Strength

Volumetric mass(KN/M3)

C’(KN/M2) φ’(°) OCR

Depth

(m)Type of soil

18.5 5 24σ’0+50 KN/M2

0 - 18 Upper clay

18.5 0 24 σ’018 –

37/55Medium clay

18.5 10 301.2 σ’0 37/55 -

80Lower clay

MONESTIER DE CLERMONT VIADUCT

PARAMETRES OF CALCULATIONS

Deformation

CASE A CASE B CASE C

Triaxial Interpretation

Oedometric

InterpretationOedometric

methodSoil

E50réf

(kN/m2)

Eoedréf

(kN/m2)

E50réf

(kN/m2)

Eoedréf

(kN/m2)Cc/1+e Cg/1+e

7500 6000 3150 2500 0.12 0.024Upper

clay

7500 6000 3150 2500 0.12 0.024Medium

clay

7500 6000 7500 6000Hardening

Model

Lower

Clay

MONESTIER DE CLERMONT VIADUCT

CALCULATION MODEL

-20.000 0.000 20.000 40.000

-60.000

-40.000

-20.000

0.000

MONESTIER DE CLERMONT VIADUCT

SEQUENCES OF CALCULATIONS

• Excavation of a mass of soil close to the estimated load brought by the pier

• Inclusions to control the soil relaxation , reduce the recompression

settlement

• Maximum loads during construction ( pre-loading with water)

• After final bearings installation, settlements calculations under final loads and

surcharges, consolidation.

• Acceptable differential settlements between piers: 6 cm.

MONESTIER DE CLERMONT VIADUCT

SETTLEMENTS ESTIMATIONS

Calculation

Cases

Soil parametres Raft

construction

Loads without

Superstructures

+ water

Total + service

loads +

Consolidation

P3 P4 P3 P4 P3 P4

ATriaxial

interpretation5 6 33 35 21 21

BTriaxial

interpretation*0.427 6 62 56 50 38

C Oedometric model 7 7 50 44 30 35

Design loadsSettlements in mm

MONESTIER DE CLERMONT VIADUCT

PARAMETRES OF CALCULATIONS

Deformation

CASE A CASE B CASE C

Triaxial Interpretation

Oedometric

InterpretationOedometric

methodSoil

E50réf

(kN/m2)

Eoedréf

(kN/m2)

E50réf

(kN/m2)

Eoedréf

(kN/m2)Cc/1+e

Cg/1+e

7500 6000 3150 2500 0.12 0.024Upper

clay

7500 6000 3150 2500 0.12 0.024Medium

clay

7500 6000 7500 6000Hardening

Model

Lower

Clay

MONESTIER DE CLERMONT VIADUCT

OBSERVATIONS DURING CONSTRUCTION

MONESTIER DE CLERMONT VIADUCT

OBSERVATIONS DURING CONSTRUCTION

MONESTIER DE CLERMONT VIADUCT

COMMENTS

• For P3, settlements during construction were close or slightly higher than those

estimated with the triaxial interpretation (case A)

• Needs for setlements reductions have been estimated necessary

• Adaptations of the design have been done:

- Preload with water, removed when superstructures have been completed.

- Deck level set out 20 mm above designed level to increase the acceptable differencial

settlements to 80 mm instead of 60 mm initialy considered in the design.

• For P4, the setlements are much lower due to the longer length of the diaphragm wall

skirt.

MONESTIER DE CLERMONT VIADUCT

SETTLEMENTS VERSUS TIME

MONESTIER DE CLERMONT VIADUCT

Comparison between estimations and observations

End of construction In service

P3 P4 P3 P4

Estimations 33 to 62 37 to 56 21* 21*

Observations 37 19 11.5** 13.5**

•* End of consolidation~ 80 years •** After ~4 years: Consolidation not completed • **To be compared to 80 mm acceptable differential s ettlements

Settlements in mm