BIMP: Fortnightly Progress Review: Agreed Steps in AIDE MEMOIRE-3 Date: 12th Nov.2013
(Next data collection date 29th Nov.2013)
Next Step Responsibility DeadlineStatus as of Nov.12, 2013 Action Plan (for next
two weeks) Remarks
Project Development Indicator
Funding secured, procurement process underway for study team
WB
Bank has developed a work plan. Questionnaires are being finalized. Consultants TORs are being developed.
The Bank team will finalize baseline data collection plan
Action Plan implementation
Under technical action (i)
DOR to arrange dedicated server or hosting service for BMS
DOR
RfP to be issued for short listed Consultants by Oct 31, 2013
Not achieved yet RfP is still not issued Procurement process yet
to be decided
To extend existing contract for further 6 month from 15 July-13 (needs to be agreed by PD)
Linked to DLI-5
BP to procure medium-term contract for BMS software maintenance and updates
BP
RfP to be issued for short listed Consultants by Oct. 31, 2013.
Ditto Ditto Linked to DLI-5
Training program to include basic training in BMS, CMS, and other software
Capacity building consultants
December 30, 2013
No further development No action identified till Annual Training Program being developed and approved
Linked to DLI-5
Under technical action (ii) Training program (see below)
to include materials lab operations/specific tests
Capacity building consultants
During annual training period & annually thereafter
No further development Ditto
Next Step Responsibility DeadlineStatus as of Nov.12, 2013 Action Plan (for next
two weeks) Remarks
Under technical action (v)
Capacity Building Consultants engaged
BP/RSDP
RSDP to get WB’s NOL by Nov.15, 2013
EoI publish by Nov.30, 2013
Awaiting WB’s NOL (RSDP requested on 4th Oct. 2013)
NOL from WB
Under fiduciary action (i)
BP to engage and mobilize internal audit consultant
BP Mobilized by
Nov.15, 2013
Technical and financial proposal opened on 4th Oct. 2013
Evaluation started
Complete evaluation And submit for DoR
approval
Under fiduciary action (ii)
Next Step Responsibility DeadlineStatus as of Nov.12, 2013 Action Plan (for next
two weeks) Remarks
WB to support BP with development of 5 year bridge-by-bridge investment plan and to seek MoF and NPC endorsement
Planning and Design Branch, BP and WB
DoR approval by Dec 30, 2013
All divisions are provided a list of respective bridges (generated from BMS) for field verification during BIMP orientation between Sept. to Oct.-13.
Division Chiefs were explained important of field verification and requested to submit verified data to BP at the earliest.
No field verified data from divisions have been received by BP yet
E-address has been submitted by 23divisions and 2 regions for BMS authorization soft key (it is necessary for BMS operation and carry few corrections within the division)
Issue reminder letter to DROs for submission of field verified data
Issue reminder letter for E-address to remaining divisions and regions
BP intend to verify BMS data by respective division before detail review of 5 year investment plan
Under fiduciary action (iii)
DOR planning branch to maintain register of procurement unit chiefs and to include this within trimester reports
Planning and Design Branch
Continuous throughout implementation
All BIMP Trimester Report to include updated register
Register is not yet maintained
Formation of PUC in divisions and projects copied to PMU at Planning Branch
Request for maintaining register (written request from BP to Planning DDG)
Under fiduciary action (iv) All outstanding audit
observations from 2009/10 to be addressed
DOR Audit Committee
> 40% by Oct 30, 2013
No information available till now
Detail data to be collected from DoR by VS
As of June, 2013 only 36.47% achieved
Next Step Responsibility DeadlineStatus as of Nov.12, 2013 Action Plan (for next
two weeks) Remarks
Under social and environmental action (i) DoR/BP implement revised
ESMF incorporating into bridge Project Implementation Cycle (PMC) and ensures inclusion of ESMF through review/acceptance and monitoring by the GESU till release of Defect Liability Period Certificate
GESU / DG’s office
On-going process
BP and GESU agreed in recent meeting to form a team to find out all possible linkages in Oct.9, 2013
No action identified Such team to be formed after engagement of Consultants in GESU so will be formed only in Dec.-13
BP and GESU maintain close coordination for effective implementation of revised ESMF by conducting formal meeting at least once in a month with maintaining minutes. Progress status to be included in each Trimester Report
BP, GESU, DOR
1st meeting on Oct 9, 2013
Every month
1st meeting held on Oct.9, 2013
Agreed to organized such meeting in every two months or as and when required
Need of conducting such meeting to be reviewed by BP and GESU
GESU to develop templates for environmental social assessments reports including IEE and other review and compliance monitoring reports
GESU/BP Nov.15, 2013 Not yet commenced GESU develop
template for bridges not requiring IEE
Under social and environmental action (ii)
DOR to approve medium-term budget for strengthening GESU
GESU / BP / Planning and Design Branch
DoR approval for business plan by October 2013
Done
BP to allocate dedicated budget from the share of 5% of budget head 337-320-4 with authorization in name of Unit Chief, GESU
BP/GESU/DOR
DOR approval of budget by Oct.31, 2013
5 million dedicated budget allocated to GESU
Awaiting DG, DoR approval
DG, DoR approval
Under social and environmental action (iii)
Next Step Responsibility DeadlineStatus as of Nov.12, 2013 Action Plan (for next
two weeks) Remarks
Social and environmental consultants to support GESU engaged
GESU Mobilized by Nov.
30,2013
EOI submitted by 6 candidates opened on 12th Nov. -13
Eligibility evaluation to be completed
Cross cutting action (i) DOR to report on complaints
received via GRM and actions taken in trimester reports
DOR/ Divisions
Dec 31, 2013 Software on
development stage Continue software
development Target date of completion xx
Cross cutting action (ii) BP to hold toolkit feedback and
revision workshop BP
Review by mid -November, 2013,
No action Conduct review Linked to DLI-4
Disbursement Linked Indicators BP to procure design services
of additional 56 urgent major maintenance bridges
BP Design Consultants
on board by Oct31, 2013,
Technical and financial proposal received and opened on 25th Oct. 2013
Proceed evaluation Linked to DLI-2
BP to confirm whether 19 bridges identified for minor maintenance in FY 2012/13 are completed or not
DROs, BP Mid-Nov, 2013
Reminded to all DROs in BIMP orientation
Till no data received from DROs
To remind all DROs by issuing official notice (letter)
Linked to DLI-2
BP to confirm whether 19 bridges for minor maintenance in FY 2013/14 are identified or not
DROs, BP Oct.31, , 2013
Ditto Ditto
BP to complete agreements of 29 new bridges under appropriate procurement procedures including design/build contracts option
BP
Preparation of document including cost estimate , tender document etc for procuring design services, civil works under Design and Build, and for bridges having design by Nov.15, 2013
Consultants on work of design of 13 bridges (under > design packages)
Document preparation for procuring design of 9 bridges and letting out 7 bridges under design and bridge option
Continuation of design of 13 bridges
Document preparation in continue
Note: next steps for DLIs 4, 5, and 6 included within action plan itemsOthers
Next Step Responsibility DeadlineStatus as of Nov.12, 2013 Action Plan (for next
two weeks) Remarks
BP, GESU and NVC to meet and finalize 3 year budget plan including TOR
BP, GESU, NVC
Oct.31, 2013
No further development for 3year budget plan
ToR draft is in discussion
To conduct a meeting between concerns
Present draft ToR for wider discussion
Project Support Consultants engaged
BP Mobilize by end-
December,2013
EoI submitted by candidate of Procurement Contract management Expert and Geotechnical Engineer on 1st Nov. 2013
Agreement completed for one (out of 6) CSSE and one Hydrologist on 13th Nov.-13
Interview of 6 candidates of Social Mobilizer completed on 21st Oct.2013
Technical / financial proposal opened for Structure Engineer and interview completed on 22nd Oct-2013
Complete evaluation of EoI submitted
To engage CSSE in starting compilation of Dossiers
Evaluate financial proposal and issue 15days notice to 6 Social Mobilzers for their acceptance
Evaluate financial proposal and issue 15 days notice for acceptance
A spillover from last review actions
Submission of Dossiers for DLI verification to NPC for Year 1
BP Submit to NPC by
December 15, 2013
No significant action taken
Reconsidering engaging Consultant to compile Dossiers
Procure Consultant for compiling Dossier