[Forth04] Groundwater and Geotechnical Aspect of Excavation in Hong Kong

Embed Size (px)

Citation preview

  • 8/8/2019 [Forth04] Groundwater and Geotechnical Aspect of Excavation in Hong Kong

    1/8

    Groundwater and geotechnical aspects of deep

    excavations in Hong Kong

    R.A. Forth*

    School of Civil Engineering and Geosciences, University of Newcastle upon Tyne, Drummond Building, Newcastle upon Tyne NE1 7RU, UK

    Received 6 March 2002; accepted 18 September 2003

    Abstract

    Consideration of groundwater is a key element in almost every construction project. The design of deep excavations for

    basements or underground railway station concourses below the water table require that the water pressures are taken into

    account. Whilst these can be considered to be hydrostatic in soil, the decreasing permeability of rock with depth and the fact that

    groundwater flow is invariably along discrete fractures means that the water pressure is unlikely to be hydrostatic at depth.

    Groundwater control for deep excavations can be achieved by a number of methods such as grouting, pumping or structural

    walls or a combination of these. For tunnelling projects grouting is extensively used, but the development of sophisticated

    tunnelling machines has led in many cases to the demise of compressed air as a means of groundwater control.

    D 2003 Published by Elsevier B.V.

    Keywords: Permeability; Rock; Groundwater; Dewatering; Settlement

    1. Introduction

    The measurement of groundwater pressure in soil

    and rock is carried out by installing piezometers and

    measuring the water pressure whether continuously

    or, more commonly, at intervals. Hydraulic piezom-

    eters are usually employed in soil but in rock, where

    flow is often along discrete discontinuities, thegroundwater pressure is more accurately measured

    using pneumatic piezometers.

    In Hong Kong, the distinction between soil and

    rock in engineering terms is that rock is cored by

    rotary drilling using diamond bits and excavated by

    percussive methods or blasting. Thus weathered rock

    (e.g. completely weathered granite) which is obtained

    by Mazier or Triefus sampling tubes with tungsten

    carbide bits is considered to be soil for the purposes of

    this paper. A typical Hong Kong ground profile

    consists of made ground overlying alluvial/colluvium

    which in turn overlies weathered rock before fresh

    rock is encountered.

    For a relatively homogeneous rock type, the dis-continuities tend to become less frequent and tighter

    with depth very often leading to extremely low per-

    meabilities. It is in fact possible that even at relatively

    shallow depths the water pressure reduces to zero. In

    many civil engineering projects, water in the rock

    need not be a problem in comparison with water in the

    overlying soil, unless artesian conditions are encoun-

    tered, and measurements are not often undertaken.

    Hoek and Bray (1981) addressed the problem

    proposing that hydrostatic pressure would buildup to

    0013-7952/$ - see front matterD 2003 Published by Elsevier B.V.doi:10.1016/j.enggeo.2003.09.003

    * Fax: +44-191-222-6613.

    E-mail address: [email protected] (R.A. Forth).

    www.elsevier.com/locate/enggeo

    Engineering Geology 72 (2004) 253260

  • 8/8/2019 [Forth04] Groundwater and Geotechnical Aspect of Excavation in Hong Kong

    2/8

    the mid-point of the excavation followed by a decline

    to zero at the base of the excavation (Fig. 1). Matson

    et al. (1986), working at the North Point, Hong Kong,

    Metro concourse, recorded fracture frequency with

    depth and showed that the number of fractures per

    meter reduced from about five at t he rockhead to

    about two at 3035 m depth (Fig. 2). From this, they

    considered that the Hoek and Bray approach wasconservative and suggested an alternative pressure

    distribution (Fig. 3).

    However, in order to check fracture flow pneu-

    matic piezometers were installed at specific loca-

    tions in the rock, where discontinuities were

    present. The head of water measured at these loca-

    tions was recorded and found to be in the range

    0.2 0.4 of hydrostatic (Morton et al., 1984), thus

    confirming Matson et al.s (1986) assumptions. In

    fact, the water pressure reduced almost to zero at

    about 30 m below ground level. The use of mea-

    sured water pressures reduced the required rock

    anchor capacity up to 30%, with considerable cost

    savings.

    The assumption that permeability decreases at

    depth is also confirmed by studies in Sweden (Ahl-

    Fig. 1. Possible groundwater pressure models for excavated rock

    face.

    Fig. 2. Fracture frequency versus depth. Fig. 3. Comparison of possible water pressure versus hydrostatic.

    R.A. Forth / Engineering Geology 72 (2004) 253260254

  • 8/8/2019 [Forth04] Groundwater and Geotechnical Aspect of Excavation in Hong Kong

    3/8

    bom et al., 1991) where permeability of the order of

    10 10 m/s were measured in crystalline rock (Fig. 4),

    similar to the values obtained in the studies of the

    proposed nuclear waste repository site at Sellafield

    (Chaplow, 1996).

    This paper draws on the authors experience of

    dewatering projects in Hong Kong, notably on the

    construction of the Island Line of the Mass Transit

    Railway constructed between 1982 and 1986.

    2. Groundwater control

    For relatively near surface excavations for typical

    civil engineering projects in urban areas, groundwater

    control can be achieved by a number of methods such

    as grouting, pumping or structural walls, or a combi-

    nation of these. Typical ground treatment methods

    used in the construction of the Island Line (ISL) of the

    Hong Kong Mass Transit Railway (MTR) are illus-

    trated in Fig. 5.

    For the deep excavations, the diaphragm walls

    were very effective when founded in bedrock.

    However, where bedrock was deeper than the base

    of the excavation grout was injected beneath thewalls. In the context of the ISL project, the grout

    was only required to be fully effective for about a

    year or two as there were no significant delays in

    the programme of construction. However, research

    is needed into the performance of the grout in the

    longer term where, for example, building pro-

    grammes are delayed for technical or, more likely,

    financial reasons.

    For tunnelling, groundwater control was achieved

    by grouting and compressed air. The use of com-

    pressed air meant that all site investigation boreholes

    and piezometers along the route had to be backfilled

    and thoroughly sealed which, of course, prevented the

    collection of groundwater level data during the tun-

    nelling phase.

    Ground treatment designs were based on the soil

    conditions for each particular site and were generally

    specified as a grout percentage of the soil volume,

    and an injection pressure. In most cases, grouting for

    groundwater control was two stage: cementbenton-

    ite followed by chemical, with grout volumes spec-

    ified for each type. Typical volumes for cement

    bentonite grout were 5% to 30%, depending on soiltype (fill through to completely weathered granite

    as, for example, illustrated in Fig. 5) and for chem-

    ical grouts 20% to 40%. Jet Grout piling or Jet

    Special Grouting was also employed and may use

    greater than 50% grout by volume. The chemical

    grouts most commonly used were sodium silicates

    with hardener volumes depending on setting times

    required.

    Grouting pressures were dependent on depth of

    grouting and desired permeation rates, and were

    usually in excess of overburden or water pressure.Injection methods used varied from site to site and

    include, in soil, Tube-a-Manchette, Lag and Jet Spe-

    cial grouting (a replacement method). Rock grouting

    was usually done using a staged method.

    Generally, the soil grouting was effective both as

    groundwater control and ground consolidation. The

    chemical grouts appear to be able to permeate soils

    with up to 10% to 20% passing the 75 Am size,

    although this was by no means a general rule, as

    the cement bentonite grouts can penetrate the

    Fig. 4. Hydraulic conductivity plotted against depth for rock mass

    and fracture zones within crystalline rock in southeast Sweden.

    Polynomial regression lines have been fitted to the data (redrawn

    from Ahlbom et al., 1991).

    R.A. Forth / Engineering Geology 72 (2004) 253260 255

  • 8/8/2019 [Forth04] Groundwater and Geotechnical Aspect of Excavation in Hong Kong

    4/8

    coarser sands and gravel sizes. In most cases, the

    soils encountered were able to be effectively

    grouted using these two stage mixes. The major

    problems, which were encountered, tended to be in

    the loose alluvial sands (Cater et al., 1984). These

    coarser sands provided resistance to grouting. It is

    not known whether this was due to groundwater

    flows or excessive grout travel or a chemical effect.

    Consequently, they often provided an opening in

    the grout curtain allowing water ingress during

    excavation or tunnelling. Fig. 6 shows the grout-

    penetration ranges in the Hong Kong soils as

    determined from experience gained by the MTRC

    on the ISL.

    3. Case histories

    A number of buildings were carefully monitored

    before, during and after construction of tunnels and/or

    Fig. 5. Ground treatment methods.

    R.A. Forth / Engineering Geology 72 (2004) 253260256

  • 8/8/2019 [Forth04] Groundwater and Geotechnical Aspect of Excavation in Hong Kong

    5/8

    deep excavations. As previously stated the tunnelling

    operations carried out under compressed air precluded

    the collection of hydrogeological data during this

    important phase. For the station concourses, the

    dewatering took place simultaneously with the exca-

    vation of spoil from within diaphragm walls. Hence, itis not possible to separate ground movements caused

    by excavation and those caused by the dewatering

    process. Some typical time-settlement plots are in-

    cluded for three buildings (Buildings A, B and C as

    described below) adjacent to construction activities in

    Central Hong Kong (Fig. 7). From this plot, it can be

    seen that the total amount of settlement due to

    excavation (including dewatering) is significant but

    not substantial in comparison with the settlement due

    to preliminary works and diaphragm walling.

    4. Building descriptions

    Building A is a 15-storey reinforced concrete

    building constructed in 1956. It measures 29 m by

    49 m in plan, is 54 m high (15 storeys), and has a

    small basement and lift-pit along the centre of thewestern side (see Forth and Thorley, 1994).

    The foundations are 432 mm diameter vibro cast

    in situ reinforced concrete piles. The piles are in

    groups of 310 with isolated pile caps of 1.31.8

    m thickness. Pile spacings are at two pile diame-

    ters within the group and groups are generally

    spaced 4 7 m apart. The founding level of the

    piles is not recorded but is thought to be at the top

    of the completely weathered granite strata. The

    piles therefore would be founded at 1517 m

    Fig. 6. Grout penetration ranges.

    R.A. Forth / Engineering Geology 72 (2004) 253260 257

  • 8/8/2019 [Forth04] Groundwater and Geotechnical Aspect of Excavation in Hong Kong

    6/8

    below ground level. The design capacity of the

    piles is 61 t.

    Building B was constructed in the mid-to-late

    1970s (Building Plan approval was given in 1973).

    The building is a reinforced concrete framed structure,

    31 storeys (110 m) high and measures 74 by 45 m in

    plan. It has one basement below ground level (see

    Forth and Thorley, 1996).

    The foundations consist of 2 m diameter bored

    reinforced concrete piles varying in length from 41 to

    64 m. The central piles support a 3.2- to 4.1-m-thickraft with the perimeter piles, in groups of 1 to 4,

    supporting 2.4- to 4.6-m-thick caps. Founding levels

    of the piles vary from 48 mPD on the south side to

    60 mPD on the north side. All piles are founded on

    what was logged as completely to moderately weath-

    ered granite. A trial pile on the site was founded at

    an SPT N value reported to be 400.

    Building C was also constructed in the mid-

    1970s, the Building Plan approval being given in

    1972. The building is a reinforced concrete framed

    structure, 16 storeys (53 m) in height, and is L-

    shaped to fit the site geometry. In plan, the building

    is 30.5 m long and from 5 to 9 m wide (see Forth

    and Thorley, 1993).

    This building, unlike the others considered, has

    foundations consisting of 305305 high yield steel

    H-piles, varying in length from 31 to 33 m. Pile

    founding levels range from 27 to 29 mPD,

    which is some 3 to 8 m below the upper surface

    of the completely weathered granite strata. The

    piles support four separate pile caps from 1.5 to1.9 m thick. A test pile on the site, loaded with

    twice the design load of 150 t is reported to have

    settled 21 mm. This pile was founded in CWG at

    28.7 mPD.

    5. Construction activities

    In the vicinity of the building, the construction

    activities associated with the MTR Island Line con-

    Fig. 7. Buildings A, B and C: time-settlement plots.

    R.A. Forth / Engineering Geology 72 (2004) 253260258

  • 8/8/2019 [Forth04] Groundwater and Geotechnical Aspect of Excavation in Hong Kong

    7/8

    sisted of diaphragm walling, deep excavations and

    soft-ground tunnelling.

    Excavation of the boxes within the 1.2-m-thick

    diaphragm walls was done in all instances by topdown methods using temporary strutting in addition to

    progressive installation of the permanent floor slabs.

    Dewatering for these excavations was by deep wells

    within the box, the soil being dewatered to 12 m

    below excavation levels.

    Readings from an inclinometer in one of the

    diaphragm walls adjacent to Building A showed

    considerable horizontal movement of the base of

    the wall towards the excavation. The bottom of the

    inclinometer in this case was founded below the

    base of the diaphragm wall in completely weathered

    granite. An inward movement of up to 80 mm was

    measured (Fig. 8) at the base of the inclinometer.

    Based on a theoretical dewatering settlement calcu-

    lation a value of over 20 mm settlement is sug-

    gested due to drawdown. This would indicate 510

    mm settlement due to wall deflection, which repre-sents 0.07 0.15 deflection/settlement ratio. This

    compares with 0.17 0.25 reported by Morton et

    al. (1980, 1981).

    An interesting groundwater effect on this and

    other buildings was that of settlement rebound after

    construction was completed and the compressed

    air employed during adjacent tunnelling was swit-

    ched off. This is observed in particular in the time-

    settlement record for Buildings A and C (Fig.

    7) and was of the order of 10% of the total set-

    tlement. Minor architectural damage occurred to

    Building A.

    Building B settled a total of 20 mm during

    excavation and dewatering and, as was the case

    for A above, the building tilted towards the exca-

    vation by a maximum of 1:4900. This settlement is

    surprising given that the building is founded some

    10 to 18 m below the diaphragm walls and 20 to 30

    m below excavation level. It is considered the most

    l ikely reason for the 20 mm of settlement is

    dewatering effects causing down drag on the piles

    during consolidation of the CWG and superficial

    deposits, in conjunction with probably high pileloads. As extensive piezometric data is not available

    around the building, a theoretical estimate cannot be

    undertaken. It is unlikely, however, to be conclusive

    as the pre-construction estimates based on flow-net

    analysis showed negligible movement. It is also

    possible that inward movement of the diaphragm

    walls may have had a similar down drag effect on

    the foundations resulting in the 10 to 20 mm of

    settlement. In either case, it should be noted that

    this degree of movement had no effect on a

    building of that size, rigidity and condition. Nodamage occurred to this building.

    Building C settled some 22 to 45 mm during

    excavation although the direction of tilt was away

    from the adjacent site. The reasons for this apparently

    unusual behaviour are:

    (a) the effect of piling on a nearby site;

    (b) ground treatment drilling near the northwest corner

    which is not able to be completely separated from

    the excavation settlement; andFig. 8. Building A: adjacent diaphragm walling inclinometer

    readings.

    R.A. Forth / Engineering Geology 72 (2004) 253260 259

  • 8/8/2019 [Forth04] Groundwater and Geotechnical Aspect of Excavation in Hong Kong

    8/8

    (c) the complexity and rigidity of the diaphragm walls

    adjacent to the building which may have the effect

    of minimising settlement due to wall deflection in

    that area.

    If the above factors are taken into consideration, it

    would seem that the building settled evenly by some

    20 to 40 mm due to the excavation. Based on reported

    maximum drawdown in the area, the likely dewater-

    ing settlement is theoretically of the order of 25 mm

    compared to the original estimate of 7 to 10 mm. This

    would suggest that the settlement due to wall deflec-

    tion would be 0 mm in the northeast corner and up to

    10 to 20 mm elsewhere. Inclinometer data is not

    available to determine the percentage of lateral move-

    ment this represents, although it agrees with the

    original estimate of 12 mm based on the structural

    design. No damage occurred to this building.

    6. Summary

    Control of groundwater in urban environments is a

    key element in successful construction. For deep

    excavations in rock, a realistic estimate of permeabil-

    ity has to be made to avoid over-design. In weathered

    rock or soft ground conditions, sound constructiontechniques and careful monitoring of ground and

    building movement gives confidence to designers in

    estimating the effects of groundwater drawdown nec-

    essary to construct large excavations.

    References

    Ahlbom, K., Andersson, J.-E., Nordqvist, R., Ljunggren, C., Tiren,

    S., Voss, C., 1991. Fjallveden study sitescope of activities and

    main results. SKB Technical Report 91-52. Svensk Karnbrans-

    lehantering AB, Stockholm.

    Cater, R.W., Shirlaw, J.N., Sullivan, C., Chan, W.T., 1984. Tunnels

    constructed for the Hong Kong mass transit railway. Hong Kong

    Eng. 12 (10), 3749.

    Chaplow, R., 1996. The geology and hydrogeology of the Sellafield

    area: an overview. Q. J. Eng. Geol. 29, S1S12.Forth, R.A., Thorley, C.B.B., 1993. Tunnelling in weathered gran-

    ite in Hong Kong. Proceedings of International Symposium on

    Geotechnical Engineering of Hard Soils and Soft Rocks, Athens.

    Balkema, Rotterdam, pp. 14331438.

    Forth, R.A., Thorley, C.B.B., 1994. Ground movements due to

    dewatering for the construction of deep excavations and tunnels

    in Hong Kong. Proceedings of International Conference on

    Groundwater Problems in Urban Areas, London. Thomas Tel-

    ford. Balkema, Rotterdam, pp. 401414.

    Forth, R.A., Thorley, C.B.B., 1996. Hong Kong Island Linepre-

    dictions and performance. Proceedings of International Confer-

    ence on Geotechnical Aspects of Underground Construction in

    Soft Ground, London. Balkema, Rotterdam, pp. 677682.

    Hoek, E., Bray, J.W., 1981. Rock Slope Engineering, 3rd ed. IMM,

    London, p. 358.

    Matson, C.R., Choy, H.H., Gibson, A.M., 1986. Rock support pre-

    diction in the deep basement of Causeway Bay East Concourse

    for the Mass Transit Railway, Hong Kong. Proceedings of Con-

    ference on Rock Engineering and Excavation on an Urban En-

    vironment. IMM, Hong Kong, pp. 285297.

    Morton, K., Cater, R.W., Linney, L., 1980. Observed settlements of

    buildings adjacent to stations constructed for the Modified Ini-

    tial System of the Mass Transit Railway, Hong Kong. Proceed-

    ings of the Sixth Southeast Asian Conference on Soil Engi-

    neering, Taipei, vol. 1, pp. 415429.

    Morton, K., Leonard, M.S.M., Cater, R.W., 1981. Building set-

    tlements and ground movements associated with constructionof two stations of the Modified Initial System of the Mass

    Transit Railway, Hong Kong. Proceedings of the Second

    International Conference on Ground Movements and Struc-

    tures, Cardiff, pp. 708 802. In: Geddes, J.D. (Ed.), Ground

    movements and structures, 1981. Pentech Press, London,

    pp. 946 947. Discussion.

    Morton, K., Sayer, P.R., Lam, K.M., Wu, S.H., 1984. Temporary

    support for a deep excavation at North Point, Hong Kong. In:

    Brown, E.T., Hudson, J.A. (Eds.), Design and Performance of

    Underground Excavations: ISRM Symposium, Cambridge.

    British Geotechnical Society, London, pp. 347352.

    R.A. Forth / Engineering Geology 72 (2004) 253260260