Upload
others
View
1
Download
0
Embed Size (px)
Citation preview
Vertase F.L.I. Limited3000 Aviator WayManchester Business ParkManchester M22 5TG
Tel +44 (0) 161 437 2708Fax +44 (0) 161 437 6300
Email [email protected]
Further Quantitative Risk Assessment for Controlled Waters and Preliminary Post-Remediation Validation Model
Former Bayer Crop Science SiteHauxtonCambridgeshire
June 2011
On behalf of:
Harrow Estates Plc
Executive Summary The report has been prepared to reassess the risk assessment with respect to controlled waters at the former BayerScience site, Hauxton following the collection of further data during the ongoing remediation. This report describes the site setting and outlines previous work undertaken to date with respect to the controlled waters risk assessment. It takes on board information gathered during the current remedial works and builds upon previous investigation data to provide a revised conceptual site model for the post remediation conditions that has significantly more certainty with regard to volumes and types of soil material and thus the geometry of restored soil horizons compared to previous models. This assessment follows the previous risk assessment (Further Quantitative Risk Assessment for Risks to Groundwater and Surface Water, Former Bayer Crop Science Site, Hauxton, Cambridgeshire February 2011) and has been adapted to the new post remediation conceptual site model for and expanded to cover all contaminants of concern. This is now a major step towards the final post remediation risk assessment model that was discussed in the remediation method statement. This assessment will now be updated on a continual and ongoing basis with site data from the ongoing validation. An appropriate level of conservatism and variation within parameters has been built in to allow for any future variability in the treated soils at site. Geotechnical and hydrogeolgical parameters for the treated soils have been assessed through laboratory and in-situ testing. These site specific parameters have subsequently been used in the risk assessment model to enable the potential risks from any residual contaminants in the reinstated remediated soils to be assessed. The output from the model represents the maximum concentrations in soils and leachate that would not result in an exceedance of the selected compliance target at the receptor, the Riddy Brook (i.e. the Environment Agency Environmental Quality Standards or equivalent.) These maximum concentrations will be used as such and in most cases material will be treated much below these concentrations to ensure that the risks are minimised further. The actual achieved concentrations post treatment so far can be as much as several orders of magnitude lower than these maximum concentrations. In order to be protective of human health also a set of ‘working targets’ has been prepared to ensure remediated soils are both acceptable within the controlled waters risk assessment and that of human health. These are presented in separate documents. We will now continue to build on this model and will add further data to the model as we continue to progress with validation and restoration of material. Once material is restored at the site we wil have final residual contaminants of concern concentrations in the reinstated soil materials, updated geotechnical and hydrogeological parameters and fraction organic carbon which will be entered into the models as probability density functions (or PDF’s) to represent actual material at the site. The model will be ‘re-run’ periodically to ensure that no risk to controlled waters remain resulting ultimately in a post remediation model accurately reflecting ground conditions at the site.
Further Quantitative Risk Assessment for Controlled Waters and Preliminary Post-Remediation Validation Model
i
Rev A 907BRI
Table of Contents
1.0 Introduction .......................................................................................................................................... 1
1.1 Limitations ..................................................................................................................................... 1
2.0 Remediation Strategy and Approach to Risk Assessment ............................................................... 2
3.0 Environmental Setting ......................................................................................................................... 4
3.1 Site Description.............................................................................................................................. 4
3.2 Pre Remediation Conditions .......................................................................................................... 4 3.2.1 Pre-Remediation Ground Conditions..................................................................................... 4 3.2.2 Existing Remedial Measures ................................................................................................. 5 3.2.3 Hydrogeology ........................................................................................................................ 5 3.2.4 Hydrology.............................................................................................................................. 7
3.3 Observed Conditions During Remedial Works............................................................................... 7 3.3.1 Ground Conditions ................................................................................................................ 7 3.3.2 Additional Contaminant Source ............................................................................................. 7 3.3.3 Hydrogeology ........................................................................................................................ 8
4.0 Review of Previous Reports ................................................................................................................ 9
4.1 Enviros Consulting ‘Part IIA Site Investigation Report’ for Bayer Crop Science, January 2005...... 9
4.2 Atkins Environment, ‘Remediation of Former Bayer Site, Hauxton, Preliminary Conceptual Model Report’ August 2006................................................................................................................................. 10
4.3 Atkins Environment, ‘Former Bayer Site, Hauxton, Groundwater Modelling Report’, June 2007.. 11 4.3.1 MODFLOW ......................................................................................................................... 12 4.3.2 QRA .................................................................................................................................... 13
4.4 Vertase FLI, Further Quantitative Risk Assessment for Risks to Groundwater and Surface Waters, January 2011............................................................................................................................................ 15
4.5 Summary of Previous Works ....................................................................................................... 15
5.0 Conceptual Site Model....................................................................................................................... 16
5.1 Original CSM ............................................................................................................................... 16
5.2 Post Remediation Site Conditions................................................................................................ 16 5.2.1 Ground Conditions .............................................................................................................. 16 5.2.2 Groundwater Flow Through the Site.................................................................................... 18 5.2.3 Aquifer Parameters ............................................................................................................. 20
5.3 Post Remediation CSM................................................................................................................ 21 5.3.1 Contaminant Source............................................................................................................ 21 5.3.2 Pathways ............................................................................................................................ 22 5.3.3 Receptor ............................................................................................................................. 22
6.0 Selection of Risk Assessment Software and Modelling Approach ................................................ 23
6.1 Environment Agency Remedial Targets Methodology ................................................................. 23 6.1.1 Assessment of Risks from Soils .......................................................................................... 23 6.1.2 Assessment of Risks from Contaminated Groundwater ...................................................... 23 6.1.3 Conceptual Model ............................................................................................................... 24
6.2 Comparison of EA RTM and Site Conceptual Site Model ............................................................ 24
6.3 Risk Assessment Approach ......................................................................................................... 24 6.3.1 Applicability of EA RTM Risk Assessment Levels ............................................................... 24 6.3.2 Selection of Modelling Software .......................................................................................... 25 6.3.3 Assessing Risks from Type B and C Soil Material ............................................................... 26 6.3.4 Assessing Risks from Type A Soil Material ......................................................................... 27
Further Quantitative Risk Assessment for Controlled Waters and Preliminary Post-Remediation Validation Model
ii
Rev A 907BRI
7.0 Model Inputs ....................................................................................................................................... 29
7.1 Contaminant Sources .................................................................................................................. 29
7.2 Receptors .................................................................................................................................... 30
7.3 Selection of Screening Criteria .................................................................................................... 30
7.4 Selection of Aquifer Pathway Parameters – Level 3a Assessment .............................................. 31 7.4.1 Aquifer Thickness................................................................................................................ 32 7.4.2 Dry Bulk Density.................................................................................................................. 32 7.4.3 Mixing Zone Thickness........................................................................................................ 32 7.4.4 Hydraulic Conductivity......................................................................................................... 32 7.4.5 Effective Porosity ................................................................................................................ 33 7.4.6 Hydraulic Gradient............................................................................................................... 33 7.4.7 Groundwater Flow Direction ................................................................................................ 33 7.4.8 Dispersivity.......................................................................................................................... 34 7.4.9 Fraction of Organic Carbon ................................................................................................. 34 7.4.10 Summary............................................................................................................................. 34 7.4.11 Model Settings .................................................................................................................... 35 7.4.12 Model Correlations .............................................................................................................. 35
7.5 Soil Source Parameters – Level 1 Assessment ........................................................................... 35
7.6 Contaminant Parameters ............................................................................................................. 37 7.6.1 Selection of Parameters ...................................................................................................... 41
8.0 Model Outputs .................................................................................................................................... 42
8.1 Leachate/Groundwater Maximum CoC Threshold Values ........................................................... 42
8.2 Soil Maximum CoC Threshold Values ......................................................................................... 43 8.2.1 Comparison of Leachate and Soil CoC concentrations ....................................................... 43 8.2.2 ConSim Level 1 Assessment............................................................................................... 44 8.2.3 Comparison of Soil Threshold Values ................................................................................. 45
9.0 Summary............................................................................................................................................. 47
9.1 Further Work................................................................................................................................ 47
Further Quantitative Risk Assessment for Controlled Waters and Preliminary Post-Remediation Validation Model
iii Rev A 907BRI
Appendices
Appendix A Vertase FLI Drawings
Drawing D907_87 – Surveyed Geological Section
Drawing D907_154 –Post Remediation Conceptual Site Model
Drawing D907_134 - ConSim Graphical Input of Source Zones and Receptor, Type B and C model
Drawing D907_169 – ConSim Graphical Input of Source Zones and Receptor, Type A model
Appendix B Atkins Drawings
Drawing 5036759/002, Conceptual Site Model for Proposed
Site Development, July 2006
Drawing 5036759/Figure 5, Groundwater Contours (mAOD)
April 29th 2006
Drawing 5036759/Figure 6, Groundwater Contours (mAOD)
May 11 to 16th 2006
Drawing 5036759/Figure 7, Groundwater Contours (mAOD)
16th December 2006
Appendix C Water Pumping Volumes
Appendix D Geotechnical Results
Appendix E Soil Source Parameter Supporting Data
Fraction of Organic Carbon
Moisture Content
Appendix F Contaminant of Concern – Input Value Justifications
Appendix G Contaminants of Concern – Literature Values
Appendix H ConSim Model Inputs – Type A Material
Appendix I ConSim Model Inputs – Type B and C Material
Appendix J Relationship Between Soil and Leachate CoC
Further Quantitative Risk Assessment for Controlled Waters and Preliminary Post-Remediation Validation Model
iv Rev A 907BRI
Concentrations
Appendix K Data CD
ConSim Model Outputs
Further Quantitative Risk Assessment for Controlled Waters and Preliminary Post-Remediation Validation Model
1
Rev A 907BRI
1.0 Introduction
VertaseFLI have been appointed by Harrow Estates Plc to undertake remedial works at the
former Bayer Crop Science agrochemicals works in Hauxton, Cambridgeshire (the site).
The site has been determined as a Special Site under Part IIa of the Environmental
Protection Act (EPA) 1990 due to identified significant pollutant linkages being present with
respect to groundwater and surface water resulting from the former use in the production
and storage of agrochemicals.
The majority of the buildings and structures at the site have been demolished, and at the
time of writing, remedial works comprising the excavation of contaminated soil material, the
formation of biopiles (including the addition of organic matter) and turning of the
contaminated soil material were being undertaken. On completion the remediated soils will
be reinstated at the site and the site will be developed for primarily residential use.
In order for the remediated soil material to be reinstated, it must be demonstrated through
the development of an appropriately detailed risk assessment, that the reinstated soils do
not present a significant risk to local receptors such as groundwater and surface water. The
initial risk assessment and remedial targets were based on site investigation data collected
prior to remediation. As the remedial works have progressed, more data has been obtained
on the volumes and properties of the different soil material present at the site so that a more
detailed and representative post remedial conceptual site model can be developed.
Therefore, in accordance with the remediation method statement (VertaseFLI, Apr 2010)
this report reassesses and where necessary revises the risk assessment for the site in light
of the additional data collected during the remedial works.
1.1 Limitations
It is important to note that this document refers to the CSM with respect to the controlled
waters risk assessment only. A human health risk assessment has been undertaken and
presented in the report, Derivation of Pesticide Soil Screening Values & Evaluation of the
Spatial Extent of Contamination (Atkins, July 2007). It is also discussed in the VertaseFLI
Remediation Strategy Report (VertaseFLI, Nov 2008).
Further Quantitative Risk Assessment for Controlled Waters and Preliminary Post-Remediation Validation Model
2
Rev A 907BRI
2.0 Remediation Strategy and Approach to Risk Assessment
The main strategy for the remediation at the site was to excavate all materials at the site to
ensure that all uncertainty regarding contaminants and geological conditions are removed.
All excavated soil material was to be segregated, classified and treated as appropriate
before being reinstated and validated. Any contaminated groundwater was to be
separated, treated and disposed from the site under discharge consent. Following the
remediation and reinstatement of soils, a clean cover system will be imported from off-site
above the finished levels.
Paragraphs 6.3 and 6.4 of the Remediation Strategy set out the approach to be used in
developing the risk assessment with respect to environmental receptors as follows:
6.3 An important part of the approach of our remedial strategy will be to collect
further information on the geology, hydrogeology, contamination, material
parameters and characteristics during the remedial works. It is our intention
that this information will be used to further develop the site model to re-
evaluate the remediation targets. This will be continually re-assessed as the
remediation is continued and may ultimately result in the preparation of a
numerical model that represents exact site conditions with a high degree of
certainty to prove that materials present on site post remediation do not
represent a significant risk of significant harm to the environment and that
adequate remediation works have been completed to satisfy the
requirements under Part IIa of the Environmental Protection Act 1990.
6.4 This modelling approach will be calibrated by site based monitoring and the
mode calibrated appropriately. It does mean that some material will be
replaced at the site that does not meet the present generic criteria but
through the remediation we will have detailed data and knowledge of this
material which will allow clearer understanding of the site. This knowledge
and understanding will be used to present a new conceptual model and
appropriate risk assessment.
Therefore, an iterative approach has been used to allow the groundwater risk assessment
to be further developed as more data becomes available during the risk assessment, so
that the post remediation site conditions and conceptual model, and therefore the site
specific remedial targets, can be developed with as much accuracy as possible. The level
Further Quantitative Risk Assessment for Controlled Waters and Preliminary Post-Remediation Validation Model
3
Rev A 907BRI
of data now available has enabled a robust model for all contaminants of concern to be
developed with revised risk based remediation targets to work towards. As the remedial
work continues and soil material is reinstated, the validation data for the reinstated soils will
be incorporated into the risk assessment model as part of the validation process so that on
completion of the work the final model will accurately represent the remediated conditions at
the site.
Further Quantitative Risk Assessment for Controlled Waters and Preliminary Post-Remediation Validation Model
4
Rev A 907BRI
3.0 Environmental Setting
3.1 Site Description
The site is situated approximately 200 m northwest of the village of Hauxton (National Grid
Ref TL 432524), and covers an area of approximately 9 hectares. It was previously
occupied by Bayer CropScience and used for the production and storage of agrochemicals
including pesticides, insecticides and herbicides.
The site is bounded to the west by the A10 trunk road beyond which is agricultural land and
the Waste Water Treatment Plant (WWTP) for the Site. The northern and eastern site
boundaries are formed by the Riddy Brook, with Church Road forming the southern site
boundary and the southeast of the site bounded by agricultural land.
The site is generally level with a ground elevation of between 12 and 13 m AOD.
3.2 Pre Remediation Conditions
3.2.1 Pre-Remediation Ground Conditions
Based on the information provided by Enviros (2005) and Atkins (2006), the pre-
remediation ground conditions at the site are presented in Table 1.
Table 1: Ground Conditions
Description Thickness
Made Ground (consisting of reworked sand and gravel, chalk marl, alluvium, brick rubble and clinker), foundations, drainage features and voids
Typically up to 2 m bgl, with a maximum thickness of 5 m
Superficial Deposits – Alluvium and River Terrace Gravels
Generally < 3 m thick where present. Completely replaced by Made Ground in parts of the site
West Melbury Marly Chalk Formation (WMMCF) – Marly chalk with thin limestone bands, typically described in available logs as a stiff light grey clay
Present in the south and northwest of the Site only. Typically less than 3m thick with a maximum thickness of 7m in some areas.
Gault Clay
Typically present at a depth of 5 m bgl underlying Made Ground/Superficial Deposits/WMMCF, the thickness is understood to be up to 50 m (based on historic borehole data presented in Atkins (2006)
Further Quantitative Risk Assessment for Controlled Waters and Preliminary Post-Remediation Validation Model
5
Rev A 907BRI
Lower Greensand 15 – 20 m
3.2.2 Existing Remedial Measures
Prior to the current remedial works at the site, the following measures had been undertaken
at the site to control groundwater:
A bentonite and cement cut-off wall was constructed along the Riddy Brook. It is
understood to have been installed in 1974;
A groundwater abstraction system was in use in the north of the site to prevent the
migration of contaminated groundwater to the north of the bentonite wall. The
system comprised several sumps which were pumped to the waste water treatment
works (WWTW) to the north of the site; and
A dewatering system was present in the south of the site associated with the
warehousing in this area. The construction of the warehouse and associated
loading areas is understood to have included the excavation of soil material such
that they were constructed below the natural water level on the site. As a result, a
dewatering system comprising a sump was constructed to artificially lower the
groundwater level in this area with all waste water pumped to the adjacent WWTW.
3.2.3 Hydrogeology
3.2.3.1 Geological Units
Made Ground and Drift Deposits
The natural drift deposits at the site comprise River Terrace Gravels and Alluvium and are
classified by the Environment Agency as a Secondary A Aquifer which are described as:
‘permeable layers capable of supporting water supplies at a local rather than
strategic scale, and in some cases forming an important source of base flow to
rivers. These are generally aquifers formerly classified as minor aquifers.’
The granular Made Ground was considered by Atkins to be part of the same hydraulic units
for modelling purposes. The presence of cohesive Made Ground was considered to be
associated with the presence of perched groundwater.
Further Quantitative Risk Assessment for Controlled Waters and Preliminary Post-Remediation Validation Model
6
Rev A 907BRI
West Melbury Marly Chalk Formation
The Lower Chalk (which includes the WMMCF) is classified by the Environment Agency as
a Primary Aquifer. A Primary Aquifer is described as:
‘These are layers of rock or drift deposits that have high intergranular and/or fracture
permeability - meaning they usually provide a high level of water storage. They may
support water supply and/or river base flow on a strategic scale. In most cases,
principal aquifers are aquifers previously designated as major aquifer.’
However, the investigations undertaken by Enviros and Atkins indicated that the WMMCF
was largely absent from the centre and north of the main site. The WMMCF had a high
content (typically described in available borehole logs as a stiff light grey clay) and was
considered by Atkins to have poor aquifer properties
Gault Clay
The underlying Gault Clay is considered to act as an aquiclude, preventing continuity
between any shallow groundwater present in on the site and the Lower Greensand which
underlies the Gault.
3.2.3.2 Groundwater Levels and Flow Direction
Groundwater was typically present at depths between 0.69 and 2.42 m below ground level
(bgl) with an average depth on the site of 1.3 m bgl. Based on the available site
investigation data, pre remediation, groundwater flow was assumed to occur within the
granular Made Ground and drift deposits, site infrastructure, and within the dis-continuous
sand and gravel lenses within the underlying WMMCF.
The local groundwater flow direction was generally from the south and west towards the
Riddy Brook and the River Cam. However, groundwater flows on site were significantly
altered due to the presence of a bentonite cut off wall along the northeast site boundary and
the ongoing abstraction of groundwater in both the north and the south of the site. As can
be seen from the 2006 Atkins groundwater contours presented in Appendix B, a
groundwater low was present in the south of the site as a result of the
dewatering/groundwater abstraction in this area which resulted in groundwater flow towards
this area and a steeper hydraulic gradient over much of the site compared to off-site.
Following remediation including the removal of the bentonite wall and cessation of
groundwater abstraction, it is anticipated that groundwater flow across the site will generally
be to the northeast, towards the Riddy Brook.
Further Quantitative Risk Assessment for Controlled Waters and Preliminary Post-Remediation Validation Model
7
Rev A 907BRI
3.2.4 Hydrology
The Riddy Brook and Hauxton Mill Race are the closest water bodies to the site, forming
much of the northern and eastern site boundary. The Riddy Brook and Hauxton Mill race
meet immediately to the north of the site where they enter the River Cam. Shallow
groundwater at the site is considered to be in direct continuity with the Riddy Brook.
Due to the existing bentonite wall and groundwater abstraction system, the site does not
currently contribute significantly to the Riddy Brook base flow.
3.3 Observed Conditions During Remedial Works
As the remediation has progressed, the excavation of soil material across the site has
allowed a far more detailed understanding of the pre-remediation ground conditions
including the extent of contamination, and the hydrogeological properties of the soil material
to be developed. The following sections describe the additional observations made during
the remediation of the site so far.
3.3.1 Ground Conditions
The excavation of soil material as part of the remedial works has generally confirmed the
distribution and thickness of the Made Ground, WMMCF and Gault Clay described by
Enviros and Atkins.
The presence of natural superficial deposits typically comprising sand and gravel was also
confirmed. The excavations showed the deposits to have been discontinuous across the
site, as described in the previous site investigations, and comprised several large shallow
lenses of sand and gravel with a maximum thickness of 3m.
Thin discontinuous lenses of sand and gravel were also identified in the WMMCF. Drawing
907_85 in Appendix 1 shows a surveyed section of the excavation with exposed isolated
sand and gravel lenses present within the surrounding stiff grey clay material.
It is important to note, that post remediation, the ground conditions and properties may be
significantly different to the pre-remediation conditions due to the homogenisation of soil
material during the remediation and the compaction on reinstatement.
3.3.2 Additional Contaminant Source
The excavations generally confirmed the contaminant distribution identified in the previous
reports with contaminant levels generally highest in the former process areas. However,
during the excavations a discreet lens of sand and gravel in the top of the WMMCF was
identified to the northeast of the site (surveyed on Drawing 907_85), adjacent to the Riddy
Further Quantitative Risk Assessment for Controlled Waters and Preliminary Post-Remediation Validation Model
8
Rev A 907BRI
Brook which also contained between 20 and 30 corroded steel drums. The sand and gravel
was associated with significantly elevated contaminant concentrations. The sand and gravel
lens extended to the Riddy Brook and may have acted as a direct contaminant pathway
until the bentonite wall was constructed,
On discovery, the drums were appropriately disposed of and the associate sand and gravel
moved to a treatment bed.
3.3.3 Hydrogeology
Prior to remediation, groundwater flow to the Riddy Brook through the site was assumed to
be through granular Made Ground and granular drift deposits with the majority of any flow
through the discontinuous lenses of sand and gravel within the WMMCF as shown in the
original Atkins CSM (Appendix B).
However, as described in 3.2.1 and 3.3.1, the WMMCF predominantly comprises stiff clay
with thin isolated discontinuous lenses of sand and gravel. The full thickness of WMMCF
has been exposed in the sides of the remediation excavations. Based on the exposed
sections, groundwater flow within the in-situ WMMCF surrounding the site is very low with
any flow generally occurring as seepages through the discontinuous sand and gravel
lenses. These seepages through the exposed lenses typically decrease with time
suggesting negligible recharge through natural strata as would be expected given the
discontinuous nature of the sand and gravel lenses and the surrounding stiff clay/marl. As a
result, the excavations which are to depths significantly below the natural water table over
much of the site, have largely remained dry (with the exception of rainfall) for the duration of
the remediation so far.
In areas where excavations have not commenced groundwater flow appears to be largely
associated with the presence of drainage features and other site infrastructure, and the
presence of granular Made Ground following periods of rainfall.
The pumping system in the north of the site is no longer in use. The remaining pumping
system in the south of the site receives all water from the site drainage system. The sump
for the pumping system is located adjacent to a lens of sand and gravel and this is likely to
contribute to the total volume of water removed from the site.
Further Quantitative Risk Assessment for Controlled Waters and Preliminary Post-Remediation Validation Model
9
Rev A 907BRI
4.0 Review of Previous Reports
A number of investigations and risk assessments have been undertaken at the site since
1991. For clarity, a summary is provided in the following sections of some of the previous
work carried out.
The following reports relevant to the assessment of risks to groundwater and surface waters
were made available to VertaseFLI for review:
Enviros Consulting Ltd, ‘Part IIA Site Investigation Report, Report for Bayer Crop
Science’, January 2005, Reference SH0250008A;
Atkins Environment, ‘Remediation of Former Bayer Site, Hauxton, Preliminary
Conceptual Model Report’ Prepared for Bridgemere UK Limited and Harrow Estates
Plc, August 2006;
Atkins Environment, ‘Former Bayer Site, Hauxton, Groundwater Modelling Report’,
Prepared for Harrow Estates Plc, June 2007; and
Vertase FLI, ‘Former Bayer Crop Science Site, Hauxton – Further Quantitative Risk
Assessment for Risks to Groundwater and Surface Waters’, February 2011, 907BRI
Rev A.
In accordance with the Remediation Strategy, a review of the previous site investigations
and risk assessments was undertaken. The principal findings of previous investigations and
risk assessments at the site are detailed in the following sections.
4.1 Enviros Consulting ‘Part IIA Site Investigation Report’ for Bayer Crop Science,
January 2005
The report details the findings of the site investigation undertaken to satisfy the
determination of the site as a Special Site under Part IIa of the Environmental Protection
Act 1990. The report built on previous work at the site from 1991 onwards which had
included installation and monitoring of 59 No. piezometers and 19 No. monitoring
boreholes. Additional intrusive work comprised the drilling of 10 No. new boreholes and 41
window sample holes. The key findings of the report were:
Identified soil contamination was largely restricted to localised hot spots within the
site, typically in the immediate vicinity of the former production areas. Identified
contaminants included a wide range of pesticides and VOCs;
Further Quantitative Risk Assessment for Controlled Waters and Preliminary Post-Remediation Validation Model
10 Rev A 907BRI
Soil contamination was considered to make a small and localised contribution to the
contaminant source with only small volumes of contaminated soil identified in the
unsaturated zone. It was considered that greatest potential impact on controlled
water receptors would be from the presence of contaminants within groundwater;
The greatest concentration of contaminants in groundwater was identified in the
centre of the site;
Contaminant concentrations in groundwater were significantly lower outside of the
identified contaminant source areas. The decrease in concentrations was much
greater than would be anticipated through contaminant migration alone and it was
therefore considered that biodegradation of contaminants was occurring.
Additionally, one of the main solvent contaminants in groundwater at the site was
trichloroethene (TCE) and the presence in groundwater of breakdown products
which increased as TCE decreased away from the source was taken as further
evidence of biodegradation occurring;
The WMMCF was proven to be absent under much of the site and less than 4m
thick downstream of the contaminant sources. The WMMCF was also of low
permeability. Therefore, the WMMCF was not considered to be a significant receptor
and the potential pollutant linkage between the site and the WMMCF was
considered invalid; and
A significant pollutant linkage was confirmed between contaminated shallow
groundwater and the Riddy Brook and River Cam.
4.2 Atkins Environment, ‘Remediation of Former Bayer Site, Hauxton, Preliminary
Conceptual Model Report’ August 2006
Atkins Environmental (Atkins) prepared the report on behalf of Harrow Estates to further
develop and refine the conceptual site model (CSM) for the site and to address
uncertainties identified in the Enviros report. An additional 12 boreholes and 17 window
sample holes were drilled over the site to further assess the ground conditions overlying the
Gault Clay and to install new groundwater monitoring boreholes. Samples of soil and
groundwater were analysed for contaminants including individual pesticides and herbicides,
some geotechnical testing was also undertaken and, falling head tests were conducted
between 1.5 m and 3.6 m bgl during drilling.
The principal findings of the work were:
Further Quantitative Risk Assessment for Controlled Waters and Preliminary Post-Remediation Validation Model
11 Rev A 907BRI
The investigations confirmed the highest contaminant concentrations were in the
former production and storage areas of the site;
Leachate analysis indicated that there was the potential for contaminants, including
pesticides and herbicides to leach into groundwater at the site;
Groundwater analysis identified high levels of pesticides and organic substances
although there did not appear to be a consistent pattern of groundwater
contamination, transport or migration across the site, with the presence of cohesive
soil material appearing to limit migration;
Concentrations of light non aqueous phase liquids (LNAPL) and dense non-aqueous
phase liquids (DNAPL) were identified in concentrations that may have been
indicative of free phase contaminants to be present;
The report confirmed the Enviros findings that biodegradation of pesticides,
herbicides and organic compounds was occurring;
The report considered that both the WMMCF and surface water courses (Riddy
Brook and the River Cam) should be considered as receptors; and
The report recommended the use of the use of MODFLOW and the Environment
Agency Remedial Targets Worksheet to derive suitable remedial targets for the
site.
4.3 Atkins Environment, ‘Former Bayer Site, Hauxton, Groundwater Modelling
Report’, June 2007
Based on the findings of the Preliminary CSM report (discussed in Section 4.2), a
quantitative risk assessment (QRA) was conducted using MODFLOW and the Environment
Agency Remedial Targets Worksheet (EA RTW). Additionally, further assessment of the
presence of DNAPL was carried out and pumping tests were also undertaken to provide
more information on the hydraulic conductivity in the soil material overlying the Gault Clay.
The approach taken for the groundwater modelling for the QRA was as follows:
Development of a detailed water balance for the site and surrounding catchment
area;
Further Quantitative Risk Assessment for Controlled Waters and Preliminary Post-Remediation Validation Model
12 Rev A 907BRI
The development of the MODFLOW model based on the local geography, geology
and hydrogeology which was calibrated based on observed groundwater levels and
hydraulic conductivities from the site investigation data;
The calibrated MODFLOW model was used to plot travel pathways and the relative
unretarded travel times between known contaminant sources and the controlled
water receptor (the Riddy Brook) using MODPATH;
Qualitative risk screening was conducted based on contaminant concentrations,
distance and travel time to receptor and the retardation characteristics of individual
contaminants to select a representative list of priority contaminants at the site; and
Quantitative Risk Assessment of the priority contaminants was using the EA
Remedial Targets Worksheet (EA RTW) which set the preliminary remedial targets.
4.3.1 MODFLOW
The modelled catchment which included the site covered an area of 213.9 ha. A water
balance calculation was undertaken for the catchment area based upon the estimated
groundwater base flow to the River Cam and predicted infiltration rates for grassland. This
gave an infiltration rate of 1.45 x 10-4 m/day which was used to derive a total water balance
for the catchment of 310 m3/day.
A groundwater flow model for the site was developed using MODFLOW. An iterative
approach was taken in the development of the model with input parameters being refined to
reflect observed site conditions and data obtained from the site investigation such as the
hydraulic conductivities obtained from the pumping tests. A total of 20 models were run to
develop the final model of the site which included the modelling of the bentonite wall and
groundwater abstraction which was ongoing at the time of writing.
Two additional models were also run for the proposed redevelopment of the site with the
groundwater abstraction and bentonite wall removed from the model although it was not
clear if any other groundwater parameters were altered to reflect the likely changed in
groundwater flow. Uniform infiltration rates of 0.0001 m/d for residential properties and
0.00001 m/d for commercial properties were assumed, the modelling conducted with a
uniform distribution between the two values. It was considered that the models gave a
reasonable representation of the likely future groundwater flux rates and therefore the
hydraulic conductivity and hydraulic gradients developed for the models were considered
appropriate to use in the QRA.
Further Quantitative Risk Assessment for Controlled Waters and Preliminary Post-Remediation Validation Model
13 Rev A 907BRI
4.3.2 QRA
The QRA used the EA RTW to model the potential risks. UK Drinking Water Standards
were used as appropriate target criteria for the risk assessment due to the limited number of
Environment Agency Fresh Water Environmental Quality Standards (EQS) available for
organic compounds.
The site was divided into two zones which were modelled separately. The first zone
comprised the area within 20 m of the Riddy Brook (the receptor) with the second zone
comprising the remainder of the site. Twenty three contaminants of concern (CoC) were
identified and remedial targets were developed for all CoCs in both zones. However, there
were recognised issues with assessing the cumulative impact on the Riddy Brook from two
separate sources. As a result for the outer zone, remedial targets were derived based on
90% of the modelled remedial target assuming a distance of 60 m to the receptor. For the
inner zone, the distance to receptor was assumed to be 1 m.
4.3.2.1 Aquifer Parameters
The modelled aquifer was the Made Ground, and the inputs for bulk density and porosity
were based on assumed values for cohesive and granular soils. The hydraulic conductivity
and hydraulic gradient were determined through the MODFLOW analysis. Typically, for
each parameter a range of values was obtained and a representative distribution
(Probability Distribution Function (PDF)) selected so that the natural variability of the aquifer
could be represented. The aquifer parameters used in the model are presented in Table 2.
Table 2 – Aquifer Properties Used in Atkins QRA
Parameter Units PDF Minimum Most Likely Maximum
Water filled soil porosity % Triangular 2 10 30
Effective Aquifer Porosity % Triangular 2 10 30
Air Filled Porosity % Uniform 1 - 2
Bulk Density of soil material in aquifer
gcm-3 Uniform 1.05 - 2
Infiltration rate m/day Uniform 1x10-5 - 1 x 10-4
Hydraulic Conductivity m/day Log
Triangular 0.01 0.1
1.0
Hydraulic Gradient m/m Triangular 0.01 0.08 0.13
Further Quantitative Risk Assessment for Controlled Waters and Preliminary Post-Remediation Validation Model
14 Rev A 907BRI
4.3.2.2 Contaminant Parameters
Contaminant parameters (Kd, Henrys Law Constant and half-life in groundwater) were
obtained from literature values, primarily obtained from the following references:
‘Handbook of Physical-Chemical Properties and Environmental Fate for Organic
Chemicals’ Second Edition, Mackay et al;
ToxNet: The United States Natural Library of Medicine, Hazardous Substances Data
Bank – http://toxnet.nlm.nih.gov;
EEC active substance reports –
http://ec.europa.eu/food/plants/protection/evaluation/exist_subs_rep_en.htm; and
Relevant Environment Agency publications.
A representative range of values and PDF was selected for each contaminant parameter.
Values of partition coefficient Kd were calculated based on literature values of the soil
organic carbon partition Coefficient Koc and averaged site specific values for the fraction of
organic carbon (FOC) using the equation Kd = Koc x FOC. As an additional factor of safety,
10% of the calculated value of Kd for each contaminant was used to develop the remedial
targets.
For several pesticides and herbicides, there were no published values for contaminant half
life in water. In these cases, a range of half lives considered by Atkins to be conservative
(relative to modern pesticides) were used in the model, typically 100 to 730 days.
4.3.2.3 Selection of Input Values
The EA RTW requires single inputs for each aquifer and contaminant parameter. However,
as detailed above, the aquifer and contaminant properties comprised a range of values and
representative PDFs. Therefore, the predictive modelling software Crystal BallTM was used
with the parameter ranges and PDFs to derive a single value based on the 95th percentile
value for each parameter.
4.3.2.4 Remedial Targets
Remedial targets were developed for soil and groundwater in both the inner and outer
zones of the site. A number of the calculated remedial targets were below the commercially
available limits of detection, and for these contaminants the remedial targets were set at the
detection limit.
Further Quantitative Risk Assessment for Controlled Waters and Preliminary Post-Remediation Validation Model
15 Rev A 907BRI
4.4 Vertase FLI, Further Quantitative Risk Assessment for Risks to Groundwater
and Surface Waters, January 2011
The report reassessed the remedial targets for five priority contaminants of concern
(dicamba, schradan, Bis(2-chloroethyl)ether, ethofumesate and 1,2-dichloroethane) using
ConSim. ConSim was selected as a suitable risk assessment tool as it can assess the
combined effects of different contaminant sources at a receptor and it allowed a range of
input values (in the form of probability functions) for all parameters using Monte-Carlo
analysis so that natural variations in inputs can be modelled to produce 95th percentile
probability.
Due to the geometry of the site, for the modelling, the site was divided into four zones, Zone
1 (the 20 m buffer zone), Zone 2S and 2N (in the centre of the site) and Zone 3 in the
southwest. For consistency, and where appropriate, inputs from the Atkins RTW model
were used. Soil material was divided into three types, Type A (Granular Made Ground and
sand and gravel), Type B (WMMCF) and Type C (Gault Clay).
Environment Agency EQS values for freshwater were used for screening criteria at the
Riddy Brook, or if not available UK drinking water standards. If neither was available either
detection limits or screening values from other regulatory frameworks (such as United
States Environmental Protection Agency) were used.
Remedial targets were derived for each soil type in each zone with respect to the Riddy
Brook for soil, leachate and groundwater.
4.5 Summary of Previous Works
A CSM and initial remedial targets were developed by Atkins using EA RTW before
remediation commenced for twenty three contaminants of concern. The initial CSM and
derivation of remedial targets was largely based on the existing pre-remediation conditions,
available Enviros and Atkins site investigation data and modelling of the groundwater
regime at the site using MODFLOW.
Subsequently five CoCs (dicamba, schradan, Bis(2-chloroethyl)ether, ethofumesate and
1,2-dichloroethane) were identified as priority CoCs by VertaseFLI and remedial targets for
these were reassessed using ConSim to provide a more detailed probabilistic risk
assessment.
Further Quantitative Risk Assessment for Controlled Waters and Preliminary Post-Remediation Validation Model
16 Rev A 907BRI
5.0 Conceptual Site Model
5.1 Original CSM
The original CSM for the site was developed by Atkins in 2006 to 2007 and is presented in
Appendix B. The CSM presents a detailed model of the sub-surface contaminant pathways
prior to remediation. The contaminant source is shown as granular Made Ground and
cohesive Made Ground, much of which was located below the water table. The main
environmental receptors were groundwater and surface water (Riddy Brook).
The key groundwater contaminant pathways in the model are:
Vertical migration through the unsaturated zone;
Migration of contaminants through sand and gravel lenses within the cohesive Made
Ground and WMMCF; and
Migration through existing site infrastructure such as sumps and utility trenches.
The original CSM and therefore the initial risk assessment and remedial targets were based
on the available data at the time which comprised the findings of the site investigations and
therefore reflected the pre-remediation site conditions (See sections 4.2 and 4.3) and it was
assumed that the majority of groundwater flow was through the sand and gravel lenses
associated with the WMMCF. Although significant amount of data had been collected, the
investigations were still limited by the presence of buildings and site infrastructure. As
described in Section 3.3.2, additional contaminant sources have been located and treated
during the remediation process that were not identified during the site investigations.
The presence of the bentonite cut off wall and the on-going groundwater abstraction are
also likely to have affected groundwater levels and flow directions on the site and the
presence of site infrastructure such as sumps, and trenches may also have impacted on the
results of pumping tests.
5.2 Post Remediation Site Conditions
5.2.1 Ground Conditions
Post remediation, ground conditions at the site will generally comprise the following three
remediated soil types (see Drawing D907_153, Appendix A):
Further Quantitative Risk Assessment for Controlled Waters and Preliminary Post-Remediation Validation Model
17 Rev A 907BRI
Type A – Sand and gravels, including granular Made Ground. The total volume is
approximately 10,000 m3 at present;
Type B – Cohesive soils largely comprising the West Melbury Marly Chalk
Formation (WMMCF) including previously reworked material. The total volume is
approximately 62,000 m3 at present; and
Type C – Gault Clay. The total volume is approximately 12,000 m3 at present.
The soil material will be reinstated in layers replicating the distribution of undisturbed soils
prior to development of the site, so that the Type A overlies Type B which will overlie Type
C.
As described in Section 2.1, prior to remediation the distribution of the natural granular
deposits at the site were limited to several shallow discontinuous lenses of sand and gravel.
As a result of this and the limited presence of granular Made Ground there is only a
relatively small volume (10,000 m3 at present) of the Type A material present which is
insufficient to provide cover over the entire site. Given a thickness of 0.3 m the Type A
material would cover approximately 3.5 ha, less than half the area of the site. Therefore, no
Type A material will be placed in Zone 1 and the Type A material is also unlikely to be
continuous over Zones 2S, 2N and 3 replicating the pre remediation distribution of sands
and gravel. The anticipated shortfall in reinstated Type A material in will be made up with
Type B material.
Given the volumes of remediated material and the area of the site, typical thicknesses of
the reinstated units are likely to be as follows:
Type A – Between 0.3 and 0.6 m (where present);
Type B – Between 3 and 5 m; and
Type C – Approximately 0.5 m.
The Type C material (comprising remediated Gault Clay) will be placed directly over a
significant thickness of undisturbed Gault Clay. It should also be noted the development
proposals include the placement of imported low permeability cover material on top of the
reinstated soil material. The cover material will be imported from an off-site source by the
developer following the completion of the remedial works.
Further Quantitative Risk Assessment for Controlled Waters and Preliminary Post-Remediation Validation Model
18 Rev A 907BRI
5.2.2 Groundwater Flow Through the Site
5.2.2.1 Pre Remediation and Observed Groundwater Conditions
The original CSM for the site assumed groundwater flow at the site was predominantly
through the WMMCF and the associated lenses of sand and gravel. However, as discussed
in Section 3, the lenses of sand and gravel within the WMMCF are relatively small and
discontinuous with the WMMCF typically comprising a stiff clay. Site observations during
the ongoing remediation have indicated that the majority of groundwater flow on site was
through the granular Made Ground, site drainage system and site services result from
periods of rainfall.
The excavations undertaken for the remediation provide a complete cross section through
the top and base of the in-situ WMMCF and there has been negligible flow observed in the
excavation walls other than very slight seepages through the discontinuous lenses of sand
and gravel. The seepages have generally decreased with time following exposure
suggesting very limited recharge from the surrounding marl material as would be expected
from a stiff clay. As a result, the excavations including those below the water table have
also remained dry (with the exception of rainfall) for the duration of the remedial works so
far.
The groundwater contours presented in Appendix B represent the pre-remediation site
conditions. The impact of the dewatering system in the south of the site can be seen with
the presence of a groundwater low and the surrounding groundwater contours indicating
groundwater flow towards the dewatering system. It is likely that the artificial lowering of
groundwater in this area was driving groundwater flow through the sand and gravel lenses
within the WMMCF on site. It is important to note that the sump for the dewatering system
is situated adjacent to a sand and gravel lens so that the volume of groundwater removed is
higher than may be anticipated if it had been installed in the ‘stiff light grey clay’ marl
material.
Therefore, as a result of the groundwater flow induced by the dewatering, the observed flow
in the WMMCF prior to remediation is not considered representative of the post remediation
conditions. Without the dewatering, groundwater levels in the south of the site would return
to natural levels (in the order of 1 m bgl) and the likely groundwater flow rate would be
significantly reduced to rates more comparable with the observed low hydraulic conductivity
and hydraulic gradient in the surrounding natural WMMCF.
Further Quantitative Risk Assessment for Controlled Waters and Preliminary Post-Remediation Validation Model
19 Rev A 907BRI
5.2.2.2 Comparison of Waste Water Pumping and Rainfall Data
Drainage at the site is designed to collect all surface water, including any groundwater that
may flow into the excavations. Given the existing ground conditions and ground cover it is
anticipated that the majority of rainfall will be collected by the drainage system. Over an 8
month period between September 2010 and April 2011, a total volume of 31,963 m3 was
pumped from the site to the waste water treatment plant (see Appendix C).
Based on the average annual rainfall for the area of 586 mm/year and an approximate site
area of 8.5 ha, over an 8 month period a total rainfall volume of 33,207 m3 would be
anticipated which is very similar to the volume of water pumped from the site. Recorded
rainfall data for Cambridge gave a total rainfall for the same 8 month period of 256.7 mm,
equivalent to 21820 m3 over the site.
A significant proportion of the difference between pumped groundwater volume and total
rainfall volume (approximately 10,000 m3) is likely to result from the very low rainfall in
March and April 2011 (a total of 4.7 mm over both months) and the subsequent use of large
volumes of water on site for dust suppression. During this period, approximately 180 m3 of
water a day was used for dust suppression, equivalent to total of approximately 8,100 m3.
Based on the recorded pumped water volumes relative to local rainfall, and making
allowance for loss of rainfall as evaporation etc there appears to be only a very low
contribution to the pumped water volumes from groundwater ingress into the excavations.
Considering the depth of dewatering achieved (approximately 1 m) this suggests that the
volume of water present in the natural WMMCF including the sand and gravel lenses and
the hydraulic conductivity are generally very low.
5.2.2.3 Reinstated Soil Material and Likely Impact on Local Groundwater Regime
The reinstated Type B and Type C soil material will have been homogenised during the
remediation and compacted. As a result of the sorting and homogenisation of the Type B
material, the discontinuous sand and gravel lenses will no longer be present. Additionally,
all historic site infrastructure and drainage will have been removed and the limited volume
of granular material will be replaced in isolated lenses above the water table. These
activities will have removed the majority of previously identified contaminant pathways and
reduced the hydraulic conductivity/permeability of the reinstated material relative to the
surrounding natural strata.
Without the impact of the current dewatering system in the south of the site and based on
the observed negligible flow through sides of excavations, groundwater flow through the
Further Quantitative Risk Assessment for Controlled Waters and Preliminary Post-Remediation Validation Model
20 Rev A 907BRI
natural strata surrounding the site and therefore through the reinstated soil material is likely
to be very low. Although the reinstatement of reduced permeability soil material may locally
alter the groundwater regime, given the relatively low hydraulic gradient observed in the
surrounding area, and the lack of significant groundwater flow through the natural WMMCF
and associated sand and gravel lenses, any changes to groundwater levels in and
surrounding the site are not likely to be significant.
5.2.3 Aquifer Parameters
5.2.3.1 Groundwater Levels
Monitoring of groundwater levels before and during remediation indicates that groundwater
levels at the site are shallow, with groundwater typically being encountered between 0.8
and 2 m below ground level.
5.2.3.2 Hydraulic Gradient
The presence of the bentonite cut-off wall and groundwater abstraction on site make
accurately determining the post remediation hydraulic gradient and groundwater flow
direction across the site very difficult. It should also be noted that the MODFLOW models
previously developed by Atkins were based on the original CSM (discussed in Section 5.1)
and site investigation data and reflect the ground conditions at the time including the
presence of granular Made Ground, drainage channels and assumed flow through the
WMMCF. Therefore the modelled groundwater parameters used in previous reports are
unlikely to be fully representative of the remediated site conditions.
Available Atkins groundwater monitoring data from the adjacent wastewater treatment plant
(immediately to the northwest of the site) appears to be outside of the influence of both the
bentonite wall and groundwater abstraction. It is therefore considered most representative
of the local groundwater conditions and the likely post remediation groundwater conditions
on site. The local groundwater flow is in a northeastern direction towards the Riddy Brook
and the local hydraulic gradient is typically between 0.007 and 0.009.
5.2.3.3 Hydraulic Conductivity and Permeability Testing
As the soil material has been largely homogenised as part of the remediation process, the
variability within the reinstated compacted soil material and therefore the variability in
hydraulic conductivity is likely to be significantly reduced relative to ground conditions prior
to remediation. The reinstated soil materials will also be compacted which will further
reduce variability.
Further Quantitative Risk Assessment for Controlled Waters and Preliminary Post-Remediation Validation Model
21 Rev A 907BRI
In the absence of in-situ soil material that is representative of post remediation conditions,
laboratory permeability testing of the soil material has been undertaken will be broadly
representative of the hydraulic conductivity in the reinstated material.
Results of the laboratory permeability testing are presented in Appendix D.
To date, testing results indicate the permeability of the Type A material to be in the range of
1 x 10-7 to 5 x 10-6 m/s, which is similar to the majority of the hydraulic conductivities
determined by the pumping tests and rising/falling head slug tests undertaken by Atkins.
Testing results in the Type B material indicate permeability of Type B material (in laboratory
conditions) material is in the order of 1 x 10-10 ms-1 with the Type C material likely to have a
permeability in the order of 1 x 10-11 ms-1.
5.3 Post Remediation CSM
The post remediation CSM is presented in Drawing D907_154, Appendix A, based on the
requirement to reinstate soils in their natural sequence (Type A over Type B over Type C).
Due to the relatively small volume of the Type A material (discussed in Section 5.2.1), there
is insufficient material to provide cover over the entire site. Therefore, no Type A material
will be placed in Zone 1 and the Type A material will not be reinstated over all of Zones 2S,
2N and 3. Any shortfall in reinstated material will be made up with Type B material.
Following remediation and reinstatement of the remediated soil material, a 1 m thick clean
cover layer comprising topsoil and low permeability material will be placed on the site. All
material for the cover material will be imported from off-site. The topsoil and low
permeability should have a sufficiently large permeability contrast to maximise run-off and
minimise infiltration of rainwater through the low permeability layer.
5.3.1 Contaminant Source
The contaminant source in the post remediation CSM will comprise the residual
contaminant concentrations remaining in the remediated soils. The source will therefore
extend across the entire site to depths of approximately 5 m below ground level. Soil
material used to create the 20 m buffer zone (Zone 1) will be subject to more stringent soil
assessment criteria which may require the importing of soil material from off-site to ensure
that the reinstated material does not present a significant risk to receptors.
Based on the available volume of each soil type and the typical groundwater depths, it is
anticipated that all Type A material will be reinstated above the current water table with the
majority of the Type B material and all Type C material reinstated below the water table. As
Further Quantitative Risk Assessment for Controlled Waters and Preliminary Post-Remediation Validation Model
22 Rev A 907BRI
a result of the small volume on site, the Type A material will reinstated so that it is
surrounded by Type B material, isolating the Type A material from contact with the in-situ
natural strata.
5.3.2 Pathways
As a result of the sorting and homogenisation of soil material during remediation, and the
compaction of materials during reinstatement, the pathway through the sand and gravel
lenses in the Type B material will no longer be present. Additionally, the demolition of the
former site buildings and excavation of soil material will have removed the previous
pathways through former site infrastructure such as drainage runs, sumps and trenches.
The following potential pathway is anticipated at the site with respect to controlled waters:
A potential pathway will still exist for vertical migration of contaminants through the
Type B material into groundwater. The groundwater may also act as a pathway to
the nearest surface water course (Riddy Brook). However, given the low
permeability of the reinstated Type B and Type C material, and the negligible
groundwater flow observed in the in-situ WMMCF (discussed in Section 5.2.2.1) any
migration of contaminants is likely to be relatively limited.
It should also be noted that the placement of the low permeability post remediation cover
layer by the developer will further reduce infiltration into the reinstated soil material and
therefore further reduce the potential for leaching of the residual contaminants within the
reinstated soils.
As the Type A will be reinstated as a shallow layer surrounded by low permeability Type B
material and covered with the low permeability cover layer there will be negligible
groundwater flow through the Type A material. No pathway will exist through the Type A
material with the exception of very limited vertical migration through the unsaturated zone,
although given the large permeability contrast between the Type A and Type B materials
any significant migration is unlikely to occur.
5.3.3 Receptor
The primary receptor is considered to be the Riddy Brook, located between 1 and 6 m from
the northeast boundary of the site.
Further Quantitative Risk Assessment for Controlled Waters and Preliminary Post-Remediation Validation Model
23 Rev A 907BRI
6.0 Selection of Risk Assessment Software and Modelling Approach
6.1 Environment Agency Remedial Targets Methodology
In order to accurately model the risks to the Riddy Brook from the presence of residual
contaminants within the reinstated remediated soils, it is necessary to select a software
model or modelling approach that uses a conceptual model that is applicable to the CSM for
the site. In the UK, most groundwater modelling is conducted in accordance with the
Environment Agency Remedial Targets Methodology (Environment Agency, 2006) (EA
RMT).
6.1.1 Assessment of Risks from Soils
The EA RMT provides the following tiers of risk assessment for contaminated soils:
Level 1: Soil Zone – Considers whether contaminants concentrations in pore water
(leachate) in contaminated soil are sufficiently elevated to represent a risk to the
receptor ignoring all dilution, dispersion and attenuation.
Level 2: Unsaturated Zone and Dilution at the Water Table – Assesses the
attenuation of contaminants in the unsaturated zone and dilution within the aquifer to
determine if these processes are sufficient to reduce the contaminant concentrations
in the aquifer to acceptable levels; and
Level 3: Attenuation in the aquifer – Assesses if attenuation in the aquifer is
sufficient to reduce contaminant concentrations to acceptable levels.
6.1.2 Assessment of Risks from Contaminated Groundwater
The EARTM also provides an assessment framework for situations where elevated
contaminant concentrations recorded in groundwater:
Level 1: Soil Zone – Level 1 is not included in the assessment as the contaminants
are already present in groundwater;
Level 2: Unsaturated Zone and Dilution at the Water Table – Recorded contaminant
concentrations are compared directly with the appropriate groundwater screening
criteria, attenuation in the unsaturated zone and dilution are assumed to have
occurred prior to sampling; and
Level 3: Attenuation in the aquifer - Assessment of attenuation in the aquifer is the
same as the soils assessment.
Further Quantitative Risk Assessment for Controlled Waters and Preliminary Post-Remediation Validation Model
24 Rev A 907BRI
6.1.3 Conceptual Model
The conceptual model used in the EA RTM assumes the following:
The soil source zone is situated entirely in the unsaturated zone (above the water
table);
All leaching and contaminant movement in the unsaturated zone is vertical; and
Dilution and attenuation of contaminants will occur in the aquifer. All movement of
groundwater is laminar and constant throughout the aquifer.
6.2 Comparison of EA RTM and Site Conceptual Site Model
The principal differences between the conceptual site model described in the EA RTM and
the post remediation CSM (Drawing D907_153) for the site (described in Section 5) are as
follows:
The conceptual model in the EA RTM assumes the contaminant source zone is
located in the unsaturated zone above the water table. However, post remediation
the contaminant source will comprise the residual contamination in the remediated
Type A, B and C material, of which all Type C and much of the Type B material will
be reinstated below the water table; and
The EA RTM assumes vertical migration only in the unsaturated zone. Post
remediation the unsaturated zone will comprise Type A and B material and much
higher permeability in the Type A material is like to result in the majority of any
contaminant migration occurring horizontally in the Type A material.
Given the above, the post remediation CSM is more complex than the conceptual model
detailed in the EA RTM (Level 1 to 3) and a revised approach to modelling the risk to
groundwater and Riddy Brook from the reinstated remediated soil material is therefore
required.
6.3 Risk Assessment Approach
6.3.1 Applicability of EA RTM Risk Assessment Levels
To develop a risk assessment approach and methodology that is appropriate to the site
conditions, consideration to each of the EA RTM levels and therefore the applicability of
groundwater modelling software is needed. Although the overall CSM is more complex
than the EA RTM conceptual model the following assessment levels will still apply to the
site:
Further Quantitative Risk Assessment for Controlled Waters and Preliminary Post-Remediation Validation Model
25 Rev A 907BRI
Level 1: This level of assessment is still considered to apply to all soil material on
site as it is based on fundamental properties of the soil material (porosity and bulk
density) and contaminants (Henry’s Law constant and soil/water partition coefficient)
only and does not include any allowance for dilution, dispersion or attenuation.
However, it is only intended for use where there is insufficient site specific soil and
leachate analysis to assess the potential leaching of CoCs; and
Level 3 (Groundwater): This level of assessment (Level 3a in ConSim) is suitable to
assess the risks to the Riddy Brook from contaminated groundwater already present
within the Type B and C materials and to derive appropriate remedial groundwater
targets. However, Level 3a of the assessment will not apply to Type A material as
this will be reinstated above the water table.
EA RTM Level 2 and Level 3 assessments will not be appropriate to assess the risks to
groundwater and Riddy Brook as both levels assume the contaminant source is located in
the unsaturated zone whereas the majority of the reinstated soil material (the contaminant
source) will be below the water table with no unsaturated zone. Additionally, for the Type A
material, leachate migration is likely to be predominantly horizontal through the Type A
material towards Riddy Brook without entering the aquifer and the processes modelled in
Level 2 (attenuation and dilution via vertical migration) are therefore not applicable.
6.3.2 Selection of Modelling Software
Level 1 and Level 3 (groundwater) assessments are suitable for use in the assessment of
risks to groundwater and Riddy Brook. Of the available software used undertake Level 1
and Level 3 assessments, it is proposed to use ConSim. ConSim has a number of
advantages over the EA RTW which include the following:
ConSim can take into account multiple contaminant source zones containing
different contaminant concentrations;
ConSim provides a more detailed assessment of attenuation and movement of
contaminants in the aquifer; and
ConSim can undertake probabilistic modelling using Monte-Carlo analysis so that
variations in the model input values can be taken into account to give a 95th
percentile probability of achieving a water quality standard at the receptor.
ConSim is forward modelling software in that it predicts a contaminant concentration at a
receptor based on initial inputs at the contaminant source. Therefore, to determine the CoC
Further Quantitative Risk Assessment for Controlled Waters and Preliminary Post-Remediation Validation Model
26 Rev A 907BRI
concentrations that do not represent a risk to the receptor (Riddy Brook) it is necessary to
use the software iteratively, continually refining the source CoC concentrations until the
predicted concentration at the receptor does not exceed the selected screening criteria.
6.3.3 Assessing Risks from Type B and C Soil Material
6.3.3.1 Deriving Groundwater/Leachate Target Values
The site CSM is shown in Drawing D907_154, Appendix A. For the type B and C soil
material reinstated below the water table, the Level 3a assessment in ConSim (EARTM
Level 3 groundwater assessment) is suitable to model the movement of contaminants
already present in the aquifer. Using the appropriate screening criteria for the Riddy Brook
as the target threshold, it is therefore possible to use Level 3a to derive target values for
groundwater/leachate within the type B and C material that do not represent a significant
risk to the Riddy Brook.
6.3.3.2 Deriving Soil Target Values
To derive soil target values that are protective of Riddy Brook, the results of laboratory
analysis of soil samples will be directly compared with analysis of leachate from the same
sample. By comparing sufficient data, it should be possible to determine the linear
relationship between contaminant concentrations in soil and leachate and therefore develop
a site specific relationship for each CoC.
Once derived, the linear relationship between soil and leachate contaminant concentrations
will enable concentrations of each CoC in soil to be compared to leachate concentrations.
Therefore, by using the leachate target derived in the Level 3a assessment a soil remedial
target value can also be derived.
Additionally, a Level 1 assessment for each CoC will also be undertaken in ConSim using
site specific input parameters. Using an iterative approach, soil concentrations will be
identified for which the leachate concentration modelled through the Level 1 assessment
does not exceed the groundwater/leachate concentrations derived in Level 3a.
As a conservative measure, the lowest concentration obtained for each CoC from the linear
leachate-soil relationship and Level 1 assessment will be used to provide the soil target
value.
Both approaches for deriving soil target values do not allow for any Level/Tier 2 assessment
and do not allow for any processes in the unsaturated zone or dilution in the aquifer. Both
approaches are therefore appropriate given the presence of the majority of the potential
Further Quantitative Risk Assessment for Controlled Waters and Preliminary Post-Remediation Validation Model
27 Rev A 907BRI
contaminant source below the water table and will give potentially conservative values as it
is assumed that there is no dilution of leachate concentrations within the aquifer
It should also be noted, that this method of deriving soil target values will also be suitable to
provide a conservative assessment of the Type B material that is reinstated above the
water table.
6.3.3.3 Site Zoning
As in the previous risk assessment model developed by Vertase, for the purposes of the
risk assessment, the site will be split into four zones (shown in drawing D907_134,
Appendix A) as follows:
Zone 1 - Zone 1 represents a 20m buffer zone between the site boundary adjacent
to Riddy Brook and the rest of the site. The site boundary is typically between 1 and
6 m from the Riddy Brook. This buffer zone would have lower remedial targets in
order to offer a degree of protection and allow more achievable remedial targets in
the rest of the site;
Zone 2N and 2S - Zone 2 covers the area between 20 m and approximately 150 m
from Riddy Brook. To give further flexibility in the risk assessment and due to the
large area covered Zone 2 has been divided into Zone 2S and Zone 2N. The
boundary between 2S and 2N was selected so that 2N is largely outside the
influence of Zone 3 and therefore any cumulative effects of contaminants within this
area; and
Zone 3 - Zone 3 is located to the southwest of the site at distance greater than 150
m from Riddy Brook.
6.3.4 Assessing Risks from Type A Soil Material
Due to the small volumes of Type A material on site (approximately 10,000 m3) there is not
sufficient Type A material to be reinstated over the entire site. As shown in the CSM
(drawing D907_154, Appendix A), no Type A material will be present in Zone 1 and it will
not be continuous over the whole of Zones 2S, 2N and 3. Where Type A material is absent,
it is proposed that it is replaced in Zone 1 by Type B material.
To provide an assessment of the potential risks from any migration of residual CoC from the
Type A material the following assumptions will be made about its properties and
distribution:
Further Quantitative Risk Assessment for Controlled Waters and Preliminary Post-Remediation Validation Model
28 Rev A 907BRI
The Type A material is uniform across the site (where present) will extend to the
boundary with Zone 1. In reality, the Type A material is likely to be reinstated further
away from the Riddy Brook (as shown in Drawing D907_154);
All leachate generated within the Type A material will migrate horizontally towards
the Riddy Brook through the Type A material to within 2 m of the boundary with
Zone 1;
There will be no attenuation or biodegradation of leachate concentrations within the
Type A material;
Leachate from the Type A material will directly enter the groundwater within the
Type B material with no attenuation in the unsaturated zone or dilution in the aquifer;
and
The Type A material will also be assumed to be a non declining source.
Therefore, the risks from the Type A Soil Material will be modelled using two zones as
shown in drawing D907_169:
Zone 1 – The 20m buffer zone between Riddy Brook and the rest of the site; and
Zone 2a – A thin strip running the length of the boundary with Zone 1, representing the
area where all Type A leachate will flow to before entering groundwater.
To provide targets for the Type A material, the same approach will be taken as the Type B
and C, with the aquifer flow (through the 20m buffer zone) modelled using the ConSim
Level 3a analysis, and assessment of soil-leachate relationships and/or Level 1 assessment
to provide a conservative comparison of soil concentrations and leachate/groundwater
concentrations.
Further Quantitative Risk Assessment for Controlled Waters and Preliminary Post-Remediation Validation Model
29 Rev A 907BRI
7.0 Model Inputs
7.1 Contaminant Sources
Each of the different zones in the model is set as a contaminant source.
Leachate/groundwater concentrations are specified for each CoC for each source. Table 5
below lists the CoC identified by Atkins for further risk assessment.
Table 5: Contaminants of Concern
Contaminant Contaminant Type
Dicamba Pesticide/Herbicide
MCPA Pesticide/Herbicide
Mecoprop Pesticide/Herbicide
Bis(2-chloroethyl)ether Chlorinated Hydrocarbon (Breakdown product)
Schradan Pesticide/Herbicide
Dichloroprop Pesticide/Herbicide
4,6-Dinitro-o-cresol Pesticide/Herbicide
1,2-Dichloroethane Chlorinated Hydrocarbon (Breakdown product)
Ethofumesate Pesticide/Herbicide
Cyclohexanone Aromatic Hydrocarbon (Solvent)
Hempa Pesticide/Herbicide
Vinyl chloride Chlorinated Hydrocarbon (Breakdown Product)
Phenol Aromatic Hydrocarbon (Breakdown Product)
Trichloroethene Chlorinated Hydrocarbon (Breakdown Product)
Tetrachloroethene Chlorinated Hydrocarbon (Breakdown Product)
1,2-Dichorobenzene Chlorinated Aromatic Hydrocarbon (Breakdown Product)
Toluene Aromatic Hydrocarbon (Process Chemical – BTEX)
Simazine Pesticide/Herbicide
Dimefox Pesticide/Herbicide
2,4,6-Trichlorophenol Chlorinated Aromatic Hydrocarbon (Breakdown Product)
Xylene Aromatic Hydrocarbon (Process Chemical –
Further Quantitative Risk Assessment for Controlled Waters and Preliminary Post-Remediation Validation Model
30 Rev A 907BRI
BTEX)
4-chloro-2-methylphenol Chlorinated Aromatic Hydrocarbon (Process Chemical and Breakdown Product)
Cis-1,2-Dichloroethene Chlorinated Hydrocarbon (Breakdown Product)
7.2 Receptors
Two receptor points were selected along the Riddy Brook. “Riddy Brook 1” is situated at
the Riddy Brook down hydraulic-gradient (based on the presumed groundwater flow
direction to the northeast) of the widest part of zone 2N. “Riddy Brook 1” therefore receives
groundwater moving through Zone 2N and Zone1 at their widest point. “Riddy Brook 2” is
the second receptor point and is situated down groundwater gradient of the southern part of
the site, again down hydraulic-gradient of the widest part of the site including Zone 3, Zone
2S and Zone 1 and is potentially most sensitive to the cumulative effects of the three zones.
7.3 Selection of Screening Criteria
To assess the risks to the Riddy Brook, Environmental Quality Standards (EQS) values are
used where available. Where EQS values are not available UK Drinking Water Standards
(DWS) are used, and where neither is available detection limit is used, unless a value from
another regulatory framework is considered appropriate. The selected water quality
standards are presented in Table 6.
Table 6 - CoC Selected Water Quality Standards
Contaminant Screening Criteria
(ug/l) Source Justification
1,2-Dichloroethane
10 EQS Freshwater
Dicamba 10 Canadian EQS for
Fresh Water
Water quality guidelines for the protection of aquatic life more appropriate for protecting
Riddy Brook than UK DWS
Schradan 0.1 UK DWS Limit for pesticides other than Aldrin,
Dieldrin, Heptachlor and Heptachlor epoxide
Bis(2-chloroethyl)ether
1 Limit of Detection No other screening value available
Ethofumesate 0.1 UK DWS Limit for other Pesticides
Trichloroethene 10 UK DWS Limit for other Pesticides
Tetrachloroethene 10 UK DWS Limit for other Pesticides
Further Quantitative Risk Assessment for Controlled Waters and Preliminary Post-Remediation Validation Model
31 Rev A 907BRI
Contaminant Screening Criteria
(ug/l) Source Justification
Cis 1,2, Dichloroethene
0.1 Limit of Detection
Vinyl Chloride 0.5 UK DWS
Cyclohexanone 1 Limit of Detection No other screening value available
Hempa 0.1 UK DWS Limit for other Pesticides
1,2 Dichlorobenzene
1 Canadian
Freshwater EQS
2,4,6 Trichlorophenol
2 Limit of Detection No other screening value available
4,6 Dinitro-o-cresol
0.1 UK DWS Limit for other Pesticides
4-Chloro-2 methylphenol
1 Limit of Detection No other screening value available
Dichlorprop 0.1 UK DWS Limit for other Pesticides
Dimefox 0.1 UK DWS Limit for other Pesticides
MCPA 0.1 UK DWS Limit for other Pesticides
Mecoprop 0.1 UK DWS Limit for other Pesticides
Phenol 0.5 UK DWS
Simazine 0.1 UK DWS Limit for other Pesticides
Toluene 50 EQS Freshwater
Xylenes 30 EQS Freshwater
7.4 Selection of Aquifer Pathway Parameters – Level 3a Assessment
As discussed above, the Level 3a assessment is only relevant for modelling the migration of
contaminants through the Type B and Type C soil material as all Type A material will be
situated above the water table. For the Level 3a assessment, the following hydrogeological
parameters are required:
Aquifer Thickness;
Dry Bulk Density;
Mixing Zone Thickness;
Hydraulic Conductivity;
Effective Porosity;
Hydraulic Gradient;
Further Quantitative Risk Assessment for Controlled Waters and Preliminary Post-Remediation Validation Model
32 Rev A 907BRI
Groundwater Flow direction;
Longitudinal and Lateral Dispersivity; and
Fraction of Organic Carbon.
For the purposes of modelling, the reinstated Type B and Type C materials are considered
to form a single aquifer. As most of the aquifer will be formed by the Type B material and
this is more permeable, the risk assessment will be conservatively conducted using the
parameters for the Type B soil material.
7.4.1 Aquifer Thickness
The assumed reinstated aquifer thickness is conservatively based on the original site
investigation data and the volume of Type B material excavated. A triangular probability
distribution function (PDF) has been used within ConSim with minimum and maximum
aquifer thicknesses of 3 and 5 m respectively and typical thickness of 4 m.
7.4.2 Dry Bulk Density
The dry bulk density of the Type B material is based on geotechnical laboratory data
presented in Appendix D. For the Type B material, the dry bulk density ranged from 1.51 to
1.7 gcm-3 with an average value of 1.63 gcm-3. Based on the available data a triangular
distribution was selected.
7.4.3 Mixing Zone Thickness
The mixing zone thickness is calculated by ConSim.
7.4.4 Hydraulic Conductivity
Permeability testing has been undertaken on compacted samples taken from the site.
Given the homogenisation of the soil material that has taken place as part of the remedial
works and the likely compaction of soil material when it is reinstated it is considered that the
permeability values obtained will be representative of the reinstated soil material.
For the Type B material, geotechnical testing has given a range of permeabilities in the
order of 1 x 10-10 ms-1 and the Type C material permeability was in the order of 1 x 10-11
ms-1. Given the testing was undertaken under laboratory conditions and may not be
completely representative of the post remediation site conditions, a range of hydraulic
conductivities of 1 x 10-9 to 1 x 10-7 m/s with a loguniform PDF has been selected. The
loguniform PDF was chosen due to the variation of 2 order of magnitude in the selected
inputs.
Further Quantitative Risk Assessment for Controlled Waters and Preliminary Post-Remediation Validation Model
33 Rev A 907BRI
7.4.5 Effective Porosity
As part of the remediation, reinstated soil material will be significantly compacted as it is
placed. Effective porosity can be estimated from geotechnical compaction tests. At the time
of writing compaction tests had been undertaken on Type B material which indicated a
minimum air voids percentage (taken as equal to the effective porosity) of approximately
3%. The compaction testing indicated that for the upper levels of compaction achievable in
the Type B soil material, an air voids percentage of 3 to 7 % would be representative.
Therefore, a uniform PDF between 3 and 7 % effective porosity has been assumed for the
soil material in the model.
7.4.6 Hydraulic Gradient
As discussed in Section 5.2.2, current groundwater conditions are significantly affected by
the presence of the bentonite wall along the Riddy Brook and the continued groundwater
abstraction both of which will be removed as part of the remediation of the site.
Consequently, all groundwater data obtained from the site to date and therefore the
hydraulic gradient values obtained from the MODFLOW model based on this data are not
considered representative of the likely post remediation groundwater regime.
For the purposes of developing the ConSim model, groundwater data obtained as part of
the Atkins 2006 investigation in the waste water treatment plant (WWTP) has been used to
provide an assessment of the likely hydraulic gradient. The WWTP is located immediately
to the northwest of the site and the groundwater contours (see Appendix B) indicate that it
is outside the zone of influence of both the bentonite cut-off wall and the groundwater
abstraction. Given the proximity to the site and similar topography it is therefore considered
that groundwater data from this area will be indicative of the likely hydraulic gradient at the
site on completion of remediation.
The groundwater contours in Appendix B give a hydraulic gradient between 0.007 and
0.009 across the WWTP. However, to reflect the lack of site specific data a conservative
range of hydraulic gradients of 0.01 to 0.03 with a uniform PDF has been included in the
model.
7.4.7 Groundwater Flow Direction
Post remediation, and following the removal of the bentonite wall and cessation of the
groundwater abstraction, groundwater flow on the site is anticipated to be in a northeastern
direction towards Riddy Brook. This is confirmed by groundwater monitoring data from the
WWTP which shows groundwater flow direction to the northeast (see Appendix B).
Further Quantitative Risk Assessment for Controlled Waters and Preliminary Post-Remediation Validation Model
34 Rev A 907BRI
7.4.8 Dispersivity
Based on the guidance given in both the EARTM and ConSim help files longitudinal
dispersivity is assumed to be 10% of the contaminant pathway, with the lateral dispersivity
assumed to be 30% of the longitudinal dispersivity.
Based on the most conservative pathway length, the distance from the buffer zone to Riddy
Brook (1 to 6 m), uniform PDF has been used for both longitudinal and lateral dispersivity
with values in the range 0.1 to 0.6 m and 0.033 to 0.2 m respectively.
7.4.9 Fraction of Organic Carbon
At the time of writing, values for FOC had been obtained for 33 soil samples taken from the
remediated Type B material which are presented in Appendix E together with histograms
showing the distribution. Based on the histograms, a logtriangular distribution was selected
with minimum and maximum values of 0.75 and 4.8 respectively and a mean value of 1.78.
It should be noted that the FOC values are for the remediated soil materials which include
organic material added as part of the remedial process. Given the available validation data,
residual levels of CoCs in any of the treatment beds are generally limited to a few CoCs and
it is considered that FOC is therefore sufficient to be available to all remaining residual
CoCs in the reinstated soil material.
7.4.10 Summary
Table 7: Summary of ConSim Aquifer Inputs
Aquifer Property (unit)
PDF (Property value) Source
Aquifer thickness (m) Triangular (3.0, 4.0, 5.0) Site specific data from previous site investigations
Dry bulk density (g/cm3)
Triangular (1.51,1.63,1.7) Site specific geotechnical data
Mixing Zone thickness (m)
NA Calculated by ConSim
Hydraulic conductivity (m/s)
Log Uniform (1e-9, 1e-7)
Conservative values given laboratory calculated values in the order of 1 x 10-10 m/s for Type B material
Effective Porosity (%) Uniform (3,7) Conservative assumption based on low permeability material
Hydraulic gradient Uniform (0.01,0.03) Conservative
Groundwater flow Single (45o) Site specific groundwater observations and off site
Further Quantitative Risk Assessment for Controlled Waters and Preliminary Post-Remediation Validation Model
35 Rev A 907BRI
Aquifer Property (unit)
PDF (Property value) Source
direction (degrees) groundwater monitoring data
Longitudinal Dispersivity (m)
Uniform (0.1,0.6) 10% of distance from Zone 1 to Riddy Brook
Lateral Dispersivity (m) Uniform (0.033,0.2) 30% of Longitudinal Dispersivity
Fraction of organic carbon (%)
Logtriangular (0.75,1.78,4.8)
Site specific data for Type B soil material
7.4.11 Model Settings
The model have been run with 1001 iterations and the following time slices: 1; 2; 5; 10; 25;
50; 100; 250; 500; 1,000; and 10,000 years.
7.4.12 Model Correlations
Several aquifer parameters are directly related to other aquifer parameters. ConSim allows
these relationships to be included in the model by enabling the user to set correlations
between parameters. Correlations can be set between -1 to +1 where +1 is a total
correlation, -1 is an inverse correlation and 0 is equal to no correlation. For the purposes of
the model, the following correlations have been set:
Longitudinal and Lateral dispersivity are both functions of the length of the
contaminant pathway with Longitudinal dispersivity set at 10% of the contaminant
pathway and lateral dispersivity 30% of the longitudinal dispersivity. Therefore a
correlation of 1 between the two values has been selected;
Hydraulic gradient and hydraulic conductivity are inversely proportional. However,
to allow for some natural variation in aquifer properties a correlation of -0.5 was
selected; and
Effective porosity is generally proportional to hydraulic conductivity. Therefore, to
model this relationship, but allow for natural variations in the aquifer properties a
correlation between the two parameters of 0.5 was selected.
7.5 Soil Source Parameters – Level 1 Assessment
The ConSim Level 1 assessment requires the following soil parameters
Dry Bulk Density;
Further Quantitative Risk Assessment for Controlled Waters and Preliminary Post-Remediation Validation Model
36 Rev A 907BRI
Fraction of Organic Carbon (FOC); and
Total soil Porosity – Calculated from soil moisture content, dry density and particle
density.
With the exception of the dry bulk density for the Type A soil material, values for all
parameters have been obtained from laboratory analysis (geotechnical and chemical) of the
different soil types although it should be noted that the FOC for the Type A material is
based on the range of values in the Atkins and Enviros reports and additional organic
matter has since been added to the soil material as part of the remediation process. The
model will be revised with site specific values for the dry bulk density and FOC of the
remediated Type A material when this data is available.
Where sufficient data has been obtained, appropriate PDFs have been selected based on
the histogram of the data. The inputs are summarised in Table 8
Table 8: Summary of ConSim Soil Source Inputs
Aquifer Property (unit)
PDF (Property value) Source
Type A Soil Material
Particle Density (g/cm3) Single (2.78) Standard value taken from EA RTW
Dry bulk density (g/cm3)
Uniform (1.37,1.81) ConSim suggested range for gravelly sand
Moisture Content (%) Normal (10.33,2.95) Based on distribution of site specific data.
Fraction of Organic Carbon (%)
Loguniform (0.72,5.8) Site specific values taken from Atkins and Enviros reports
Type B and C Soil Material
Particle Density (g/cm3) Uniform (2.69,2.73) Site specific geotechnical data
Dry bulk density (g/cm3)
Triangular (1.51,1.63,1.7) Site specific geotechnical data
Moisture Content (%) Triangular (8.5,16,22) Based on distribution of site specific data.
Fraction of Organic Carbon (%)
Logtriangular (0.75,1.78,4.8)
Site specific data for Type B soil material
Further Quantitative Risk Assessment for Controlled Waters and Preliminary Post-Remediation Validation Model
37 Rev A 907BRI
7.6 Contaminant Parameters
For the purposes of the risk assessment four physio-chemical properties were required for
each CoC:
Soil Organic Carbon to Water Partition Coefficient - Koc (ml/g);
Henry’s Law Constant (Dimensionless);
Biodegradation half life in groundwater (days or years); and
Maximum solubility in water (mg/l).
Since the risk assessments were first undertaken by Atkins in 2006 to 2007, a number of
new sources of physio chemical properties have been released including the Environment
Agency document ‘Compilation of Data for Priority Organic Pollutants for Derivation of Soil
Guideline Values, Scientific Report, SC050021/SR7’. As a result of the availability of this
and other new sources of data, all the four physio-chemical properties were reassessed for
each CoC. The revised CoC parameters are presented in Appendix F together with
justification for the selection of appropriate PDFs. The literature values for the four physio-
chemical parameters for each CoC together with histograms of Koc and Henry’s Law
Constant (where sufficient data was available) are presented in Appendix G. The chemical
parameters are summarised in Table 9 below.
Table 9 - Contaminant Physio-chemical Properties
Contaminant Parameter Unit PDF Min Most Likely
Max S/D
1,2-Dichloroethane
Koc ml/g Uniform 11.48 ~ 76 ~
Henry’s Law constant Normal 0.049 ~ ~ 0.025
Aquifer Half Life days Uniform 400 ~ 720 ~
Maximum Solubility mg/l Uniform 8520 ~ 8680 ~
Dicamba Koc ml/g Log triangular 0.1 2.5 42.65 ~
Henry’s Law constant Uniform 8.87e-9 ~ 8.91e-8 ~
Aquifer Half Life days Uniform 151 ~ 443 ~
Maximum Solubility mg/l Single 8310 ~ ~ ~
Schradan Koc ml/g Loguniform 0.31 ~ 7 ~
Henry’s Law constant Loguniform 2.58e-15 ~ 1.55e-8 ~
Further Quantitative Risk Assessment for Controlled Waters and Preliminary Post-Remediation Validation Model
38 Rev A 907BRI
Contaminant Parameter Unit PDF Min Most Likely
Max S/D
Aquifer Half Life days Uniform 1825 ~ 3650 ~
Maximum Solubility mg/l Single 1e6 ~ ~ ~
Bis(2-chloroethyl)ether
Koc ml/g Uniform 13.8 ~ 76 ~
Henry’s Law constant Uniform 5.34e-4 ~ 8.71e-4 ~
Aquifer Half Life days Uniform 360 ~ 720 ~
Maximum Solubility mg/l Uniform 10200 ~ 17200 ~
Ethofumesate Koc ml/g Uniform 97 ~ 245 ~
Henry’s Law constant Loguniform 2.74e-7 ~ 1.5e-6 ~
Aquifer Half Life days Uniform 1825 ~ 3650 ~
Maximum Solubility mg/l Single 50 ~ ~ ~
Trichloroethene Koc ml/g Logtriangular 25.12 141 776.24 ~
Henry’s Law constant Uniform 0.275 ~ 0.55 ~
Aquifer Half Life days Uniform 321 ~ 1654 ~
Maximum Solubility mg/l Uniform 1180 ~ 1370 ~
Tetrachloroethene Koc ml/g Triangular 50 296 500 ~
Henry’s Law constant Triangular 0.1 0.68 1.21 ~
Aquifer Half Life days Uniform 720 ~ 1653 ~
Maximum Solubility mg/l Triangular 200 225 230 ~
Cis 1,2, Dichloroethene
Koc ml/g Uniform 35.6 ~ 69.18 ~
Henry’s Law constant LogTriangular 0.129 0.185 0.303 ~
Aquifer Half Life days Uniform 720 ~ 2875 ~
Maximum Solubility mg/l Uniform 4900 ~ 6410 ~
Vinyl Chloride Koc ml/g Triangular 2.99 16.6 57 ~
Henry’s Law constant Triangular 0.184 1.085 2.29 ~
Aquifer Half Life days Uniform 720 ~ 2875 ~
Maximum Solubility mg/l Uniform 2700 ~ 2760 ~
Cyclohexanone Koc ml/g Uniform 10 ~ 66.53 ~
Henry’s Law constant Uniform 3.68e-4 ~ 9.16e-4 ~
Aquifer Half Life days Uniform 1825 ~ 3650 ~
Maximum Solubility mg/l Uniform 23000 ~ 25000 ~
Hempa Koc ml/g Single 34 ~ ~ ~
Henry’s Law constant Single 8.17e-7 ~ ~ ~
Aquifer Half Life days Uniform 1825 ~ 3650 ~
Further Quantitative Risk Assessment for Controlled Waters and Preliminary Post-Remediation Validation Model
39 Rev A 907BRI
Contaminant Parameter Unit PDF Min Most Likely
Max S/D
Maximum Solubility mg/l Single 1e6 ~ ~ ~
1,2 Dichlorobenzene
Koc ml/g Triangular 109 379 891 ~
Henry’s Law constant LogTriangular 0.049 0.0786 0.151 ~
Aquifer Half Life days Uniform 365 ~ 720 ~
Maximum Solubility mg/l Triangular 125 133 156 ~
2,4,6 Trichlorophenol
Koc ml/g Logtriangular 109 1513 6918 ~
Henry’s Law constant Triangular 5.32e-5 1.176e-4 3.18e-4 ~
Aquifer Half Life days Uniform 169 ~ 1820 ~
Maximum Solubility mg/l Triangular 434 750 800 ~
4,6 Dinitro-o-cresol
Koc ml/g Triangular 100 257 602 ~
Henry’s Law constant Loguniform 5.77e-5 ~ 1.743e-2 ~
Aquifer Half Life days Uniform 28 ~ 42 ~
Maximum Solubility mg/l Uniform 150 ~ 290 ~
4-Chloro-2 methylphenol
Koc ml/g Uniform 124 ~ 700 ~
Henry’s Law constant Uniform 4.44e-5 ~ 5.31e-5 ~
Aquifer Half Life days Uniform 1825 ~ 3650 ~
Maximum Solubility mg/l Uniform 2300 ~ 4000 ~
Dichlorprop Koc ml/g Uniform 34 ~ 170 ~
Henry’s Law constant Loguniform 1.09e-7 3.6e-4 ~
Aquifer Half Life days Uniform 824 ~ 1235 ~
Maximum Solubility mg/l Single 350 ~ ~ ~
Dimefox Koc ml/g Single 2.2 ~ ~ ~
Henry’s Law constant Uniform 8.17e-7 ~ 9.12e-7 ~
Aquifer Half Life days Uniform 1825 ~ 3650 ~
Maximum Solubility mg/l Single 1e6 ~ ~ ~
MCPA Koc ml/g Uniform 10 ~ 154 ~
Henry’s Law constant Uniform 1.96e-8 ~ 1.96e-7 ~
Aquifer Half Life days Uniform 20 ~ 25 ~
Maximum Solubility mg/l Uniform 630 ~ 835 ~
Mecoprop Koc ml/g Uniform 5.3 ~ 68 ~
Henry’s Law constant Loguniform 4.48e-9 ~ 7.44e-7 ~
Aquifer Half Life days Uniform 28 ~ 280 ~
Further Quantitative Risk Assessment for Controlled Waters and Preliminary Post-Remediation Validation Model
40 Rev A 907BRI
Contaminant Parameter Unit PDF Min Most Likely
Max S/D
Maximum Solubility mg/l Uniform 620 ~ 895 ~
Phenol Koc ml/g Uniform 10 ~ 46.77 ~
Henry’s Law constant Uniform 1.29e-5 ~ 2.9e-5 ~
Aquifer Half Life days Uniform 8 ~ 20 ~
Maximum Solubility mg/l Uniform 82800 ~ 91000 ~
Simazine Koc ml/g Triangular 39.81 140 421.7 ~
Henry’s Law constant Loguniform 1.37e-8 ~ 1.37e-7 ~
Aquifer Half Life days Uniform 75 ~ 174 ~
Maximum Solubility mg/l Uniform 3.5 ~ 7.4 ~
Toluene Koc ml/g Triangular 38.9 160 269.15 ~
Henry’s Law constant Triangular 0.193 0.266 0.273 ~
Aquifer Half Life days Uniform 110 ~ 210 ~
Maximum Solubility mg/l Uniform 526 ~ 590 ~
Xylenes Koc ml/g Triangular 74 250 616.59 ~
Henry’s Law constant Triangular 0.12 0.25 0.636 ~
Aquifer Half Life days Uniform 112 ~ 360 ~
Maximum Solubility mg/l Uniform 161 ~ 200 ~
Further Quantitative Risk Assessment for Controlled Waters and Preliminary Post-Remediation Validation Model
41 Rev A 907BRI
7.6.1 Selection of Parameters
The range of literature values was assessed to find the best fit range of values and PDF.
For a number of the CoCs, several literature values were significantly higher or lower than
the typical range of values. In these cases, values that were not considered representative
or those which did not fit the most appropriate PDF were discounted.
7.6.1.1 Aquifer Half Lives
The only available source of half life data for the CoCs was Physical – Chemical Properties
and Environmental Fate for Organic Chemicals, 2nd Edition, Mackay et al, 2006 where half
lives were typically reported as a range based upon a maximum and minimum half life.
Conservatively, anaerobic biodegradation half lives in water were used in the model.
Where more than one range of values were available, the two most conservative values in
any of the ranges was used as the input
For a number of CoCs, no literature values for half life in water were available. In these
cases a conservative anaerobic half life range of 5 to 10 years was assumed, which was
more conservative than the range 100 to 730 days used in previous models (see Section
4.3.2.2)
7.6.1.2 Calculating Kd
The values for Koc are multiplied by the fraction of organic carbon to derive Kd, the soil-water
patrician coefficient. In previous risk assessments for the site, Kd was calculated based
upon average values of the Fraction of Organic Carbon (FOC) for soil material, above and
below the water table. As detailed in Section 3.3.2.2, as an extra factor of safety was
incorporated into the Atkins model by only using 10% of the calculated Kd value.
ConSim can either use inputs for Kd or calculate Kd from the Koc and FOC. As ConSim is
designed to model a range of inputs using PDFs it was considered more appropriate to use
the available range of Koc and FOC data and suitable PDF to provide the most realistic
model. Given that the output model reflects the 95th percentile worst case values it was not
considered necessary to add any additional factor of safety to the model at this stage.
Further Quantitative Risk Assessment for Controlled Waters and Preliminary Post-Remediation Validation Model
42 Rev A 907BRI
8.0 Model Outputs
8.1 Leachate/Groundwater Maximum CoC Threshold Values
Based upon the model inputs and screening criteria discussed in Section 7, the following
models have been run to derive leachate/groundwater maximum CoC threshold values:
ConSim Level 3a assessment for Type A material as detailed in Section 6.4.3; and
ConSim Level 3a assessment for Type B and C material as detailed in Section
6.4.2.
Due to the number of CoCs each model was split into two parts:
Part 1 – 1,2 Dichloroethane, Dicamba, Schradan, Bis(2-chloroethyl)ether,
Ethofumesate, Trichloroethane, Tetrachloroethane, Cis 1,2 dichloroethane, Vinyl
Chloride, Cylohexanone and Hempa; and
Part 2 – 1,2 Dichlrobenzene, 2,4,6 Trichlorophenol, 4,6 Dinitro-o-cresol, 4 Chloro 2
methylphenol, Dichlorprop, Dimefox, MCPA, Mecoprop, Phenol, Simazine, Toluene
and Xylene.
The threshold values represent the maximum concentration of each CoC that will not
represent a significant risk to the Riddy Brook, the closest controlled water receptor. The
model inputs and outputs are presented in Appendixes H and I. The derived
leachate/groundwater maximum thresholds for the Type A and Type B and C soil material
are summarised in Table 10 below. It should be noted that as in the post remediation CSM,
no Type A material will be placed in Zone 1.
Table 10 - Leachate/Groundwater Maximum CoC Threshold Values Zones - Type A Material (µg/l)
Zones - Type B & C Material (µg/l) Contaminant
2 1 2S 2N 3
1,2-Dichloroethane
8,000,000 1,000 8,000,000 8,000,000
8,000,000
Dicamba 5,000 50 5,000 10,000 20,000
Schradan 5 0.1 200 2,000 5,000
Bis(2-chloroethyl)ether
1,000,000 50 1,000,000 1,000,000
5,000,000
Ethofumesate 20,000 50 20,000 50,000 50,000
Further Quantitative Risk Assessment for Controlled Waters and Preliminary Post-Remediation Validation Model
43 Rev A 907BRI
Zones - Type A Material (µg/l)
Zones - Type B & C Material (µg/l) Contaminant
2 1 2S 2N 3
Trichloroethene 1,200,000 1,000 1,200,000 1,200,000 1,200,000
Tetrachloroethene 230,000 1,000 230,000 230,000 230,000
Cis 1,2, Dichloroethene
4,900,000 1,000 4,900,000 4,900,000
4,900,000
Vinyl Chloride 10,000 10 1,000,000 2,700,000 2,700,000
Cyclohexanone 25,000 50 1,000,000 5,000,000 10,000,000
Hempa 15,000 1 700,000 5,000,000 10,000,000
1,2 Dichlorobenzene
100,000 1,000 100,000 100,000
150,000
2,4,6 Trichlorophenol
50,000 1,000 50,000 50,000
500,000
4,6 Dinitro-o-cresol
200,000 1,000 200,000 200,000
250,000
4-Chloro-2 methylphenol
100,000 1,000 100,000 100,000
1,000,000
Dichlorprop 10 0.1 5,000 10,000 20,000
Dimefox 5 0.1 200 1,000 2,000
MCPA 500,000 1,000 500,000 500,000 600,000
Mecoprop 620,000 1,000 620,000 620,000 500,000
Phenol 100,000 1,000 100,000 200,000 1,000,000
Simazine 7,400 1,000 7,400 7,400 7,400
Toluene 100,000 1,000 100,000 200,000 500,000
Xylenes 100,000 1,000 100,000 200,000 200,000
8.2 Soil Maximum CoC Threshold Values
8.2.1 Comparison of Leachate and Soil CoC concentrations
CoCs were analysed for both soil and leachate from the same soil sample and the results
plotted on a graph for each CoC. This was repeated for several samples for each soil
material type and the graph was then used to determine the linear relationship between soil
and leachate concentrations for each CoC.
As a result of the CoC concentrations being below detection limits in a large number of the
soil samples analysed, at the time of writing sufficient data was only available to assess
Ethofumesate and Schradan in the Type B soil material. As more data is obtained, where
Further Quantitative Risk Assessment for Controlled Waters and Preliminary Post-Remediation Validation Model
44 Rev A 907BRI
the data allows, all CoCs will be assessed and the graphs for Ethofumesate and Schradan
reassessed.
The graphs for Ethofumesate and Schradan are presented in Appendix J.
8.2.1.1 Ethofumesate
Based on the graph for Ethofumesate, there is a clear linear relationship between the
concentration in soil and the resulting concentrations in the Type B soil material.
Discounting some of the highest soil concentrations from the best fit (so the relationship
becomes more conservative) gives a soil:leachate gradient of 0.0884. Therefore, based on
the ConSim Level 3a leachate targets presented in Section 8.1, the soil CoC maximum
threshold value for Ethofumesate are:
Zone 1: 565 ug/kg;
Zone 2 Type A: 226,244 ug/kg;
Zone 2S Type B & C: 226,244 ug/kg; and
Zone 2N and Zone 3 Type B & C: 565,610 ug/kg
8.2.1.2 Schradan
The graph for of the soil leachate relationship for Schradan shows no clear relationship
between concentrations in soil and leachate. This relationship will be reassessed as further
data becomes available.
8.2.2 ConSim Level 1 Assessment
As discussed in Section 6.3, in addition to the direct comparison of soil and leachate CoC
concentrations, a ConSim Level 1 risk assessment has also been carried out to provide
further assessment of maximum CoC threshold values that will not represent a risk to the
Riddy Brook. The model inputs of the Type A and Type B & C material are presented in
Appendixes H and I respectively and the models presented in Appendix K. The derived
threshold values are presented in Table 11 below.
Further Quantitative Risk Assessment for Controlled Waters and Preliminary Post-Remediation Validation Model
45 Rev A 907BRI
Table 11 - Soil Maximum CoC Threshold Values with Respect to Controlled Waters
Zones - Type A Material (µg/kg)
Zones - Type B & C Material (µg/kg) Contaminant
2 1 2S 2N 3
1,2-Dichloroethane
1,500,000 300 2,000,000 2,000,000 2,000,000
Dicamba 250 5 500 1,000 2,500
Schradan 0.3 0.01 20 200 500
Bis(2-chloroethyl)ether
200,000 20 200,000 400,000 2,000,000
Ethofumesate 20,000 80 20,000 50,000 50,000
Trichloroethene 550,000 700 650,000 650,000 650,000
Tetrachloroethene 225,000 800 270,000 270,000 270,000
Cis 1,2, Dichloroethene
1,900,000 80 2,500,000 2,500,000 2,500,000
Vinyl Chloride 2,000 2 400,000 800,000 800,000
Cyclohexanone 5,000 1 200,000 1,000,000 2,000,000
Hempa 3,000 0.3 300,000 2,000,000 4,500,000
1,2 Dichlorobenzene
100,000 2,000 100,000 100,000 150,000
2,4,6 Trichlorophenol
50,000 2,000 50,000 50,000 500,000
4,6 Dinitro-o-cresol
175,000 1,000 200,000 200,000 250,000
4-Chloro-2 methylphenol
100,000 2,000 100,000 100,000 1,000,000
Dichlorprop 5 0.05 1,000 2,000 5,000
Dimefox 0.3 0.01 20 50 200
MCPA 125,000 400 200,000 200,000 225,000
Mecoprop 70,000 100 100,000 100,000 100,000
Phenol 20,000 100 20,000 50,000 200,000
Simazine 2,250 1,000 3,500 3,500 3,500
Toluene 100,000 1,000 100,000 200,000 400,000
Xylene 100,000 2,000 100,000 200,000 200,000
8.2.3 Comparison of Soil Threshold Values
Presently, remedial targets based on the soil-leachate CoC concentration relationship have
been derived for Ethofumesate only. These values are typically an order of magnitude
greater than those derived using the ConSim Level 1 risk assessment. Therefore, the
Further Quantitative Risk Assessment for Controlled Waters and Preliminary Post-Remediation Validation Model
46 Rev A 907BRI
threshold values derived for Ethofumesate using ConSim are conservatively recommended
to assess the risks to the Riddy Brook.
Further comparison and selection of the threshold values will be undertaken as the
relationship between leachate and soil CoCs are determined.
Further Quantitative Risk Assessment for Controlled Waters and Preliminary Post-Remediation Validation Model
47 Rev A 907BRI
9.0 Summary
The previous risk assessments undertaken by both Atkins and VertaseFLI at the site were
based on a conceptual model developed before remediation commenced at the site. The
remediation, which at the time of writing was still continuing, has allowed the collection of
large amounts of data leading to an improved understanding of the post remedial ground
conditions so that a revised conceptual site model (CSM) could be developed which
accurately reflects the likely conditions once remediation is complete.
As a result of the revisions to the CSM, the risk assessment approach has also been
revised so that it is appropriate to fully assess the risks to controlled waters (i.e. the Riddy
Brook) from the remediated site. The revised methodology used ConSim to derive
maximum COC threshold values for leachate and groundwater at the site. ConSim was also
used to assess the relationship between soil and leachate CoC concentrations together with
site specific relationships based on lab testing results.
To derive maximum CoC threshold values using ConSim, the contaminant inputs for all 23
CoCs have been reassessed based on a review of available literature values and if
necessary revised. Aquifer parameters were revised based on site specific data. Using
these reassessed values and the revised risk assessment approach has enabled a model
more representative of the post remediation site conditions to be developed and therefore
more representative maximum CoC threshold values to be derived.
9.1 Further Work
The threshold values listed in Table 11 represent the maximum CoC concentrations in the
reinstated soils that will not represent a significant risk to the Riddy Brook. However, it is
intended that the soil material will be remediated to a much higher standard and therefore
where possible, much more stringent remedial targets will be used. The remedial targets
will be detailed in a subsequent report and will take into account the human health risk
assessment (being revised by Atkins at the time of writing) to ensure that the remediated
ground conditions do not represent a risk to any of the identified receptors.
As the remediation of the site continues, further data will be collected as part of the
remediation and validation process. All additional data will continue to be incorporated into
the risk assessment model, increasing the certainty of the modelled site geometry and
hydrogeological parameters and further increasing the accuracy of the model. This in turn
Further Quantitative Risk Assessment for Controlled Waters and Preliminary Post-Remediation Validation Model
48 Rev A 907BRI
will allow the continued development and of the maximum CoC threshold values and
therefore the remedial targets, and will ultimately provide a satisfactory demonstration that
the remediated site does not represent a risk to controlled waters.
Further Quantitative Risk Assessment for Controlled Waters and Preliminary Post-Remediation Validation Model
Rev A 907BRI
APPENDIX A
VERTASE FLI DRAWINGS
Further Quantitative Risk Assessment for Controlled Waters and Preliminary Post-Remediation Validation Model
Rev A 907BRI
APPENDIX B
ATKINS DRAWINGS
Key
Con
tour
s of
Gro
undw
ater
leve
l in
mA
OD
Dra
wn
byD
ate
Rev
.D
ate
DR
AW
N
EL
DA
TE
07/0
1/20
07
RE
V -
|---
--|-
----
|---
--|-
----
|---
--|
0
NT
S
SH
EE
TP
LOT
DA
TE
CLI
EN
T
Har
row
Est
ates
PR
OJE
CT
Ap
ril 2
9th
200
6
Fo
rmer
Bay
er C
rop
scie
nce
, Hau
xto
n
Gro
un
dw
ater
Co
nto
urs
(m
AO
D)
SC
ALE
S
DR
AW
ING
TIT
LE
Atk
ins
Lim
ited
TH
IS D
RA
WIN
G IS
NO
T T
O B
E S
CA
LE
D
--
CO
-OR
D C
HE
CK
CH
EC
KE
D
DA
TE
DA
TE
5036
759/
Fig
ure
507
/01/
2007
A3
DR
AW
ING
NO
©B
irmin
gham
B
1 1T
F
Con
sulti
ng E
ngin
eers
The
Axi
s 1
0 H
ollid
ay S
tree
tF
ax
0121
483
585
8
Tel
0
121
483
5000
PU
RP
OS
E O
F IS
SU
EA
utho
rised
for
issu
e
RE
VIS
ION
SC
heck
edby
5036
759/
Fig
ure
5
N
MILLLANE
CAM BRID GE ROAD
1.22
mR
H
1.22mRH
1.22mRH
De
f
CD
y
HASLINGFIELD AND THE EVERSDENS WARDP HAUXTON CP HARSTON AND HAUXTON WARD(a)
Def
Def
1.22mRH
Def
FF
FW Und FW
De
f
Und
ED
&W
ard
Bd
y
CD
CD
CR
SAWSTON ED
Def
ED
Bdy
Rec
tory
Far
m
The
Cot
tage
Pavilion
She
lter
War
ehou
seT
ank
Pum
pin
g S
tatio
nT
ank
s
Ch
y
Pa
vilio
n
Hau
xton
Mill
Pum
p H
ouse
12 W
estfi
eld
Co
ttag
es
90
4
Gas
Gov
erno
r
Ta
nks
Tan
ks
Tan
k
El S
ub
Sta
Mill
Hou
se
Tan
ks
The
Mill
Hou
se
Ne
w
Tan
ks
Tan
ks
Th
e W
hite
Ho
use
Ta
nk??
Track
Track
Trac
k
Track
Cou
rt
Sports Ground
Indu
stria
l Eff
lue
nt
Dis
po
sal P
lan
t
Te
nnis
Bo
wlin
g
Gre
enTrack
Pipeline
E
13.
8m
12.9
m
BM
13.
56m
LB
El
Sub
Sta
WB
Che
mic
al W
ork
s
FB
11.6
m
Sp
orts
Gro
und
Ten
nis
Cou
rts
Path
(um
)
FB
FB
Slu
ice
Slu
ice
Slu
ice
Hau
xto
nM
illB
ridge
12.
8m
Tra
ck
T rac
k
BM
13
.08
m
Slu
ice
Track
Ha
uxt
on
Tra c
k
Mile
Sto
ne
FB
Tank
FBW
eir
FB
Tr a
ck
Path
(um
)
Wei
r
Pipeline
Pip
elin
e
Pip
elin
e
PipelinePipeline
Pip
elin
e
Pipel ine
Ta
nk
Tan
kT
ank
Tan
k
Ta
nk
orG
rant
a
Drain
River Cam or Granta
Drain
Dra
in
Dra
in
BH
1
BH
2
BH
3
BH
4
BH
5
BH
6
BH
7
BH
8
BH
9
BH
10
BH
11
BH
12
BH
13
BH
14
BH
15
BH
16
BH
18
BH
19
BH
20
S1
/8
S1
/15
S1
/24
S1
/31
S2/
3S
2/6
S3
/10
S7
/1
S9/
4
S9/
5
BH
1/0
6 BH
2/0
6
BH
3/0
6
BH
4/0
6
BH
5/0
6
BH
6/0
6
BH
7/0
6
BH
8/0
6
BH
9/0
6BH
10
/06
BH
11
/06
BH
12
/06
P6
7
Key
Con
tour
s of
Gro
undw
ater
leve
l in
mA
OD
Dra
wn
byD
ate
Rev
.D
ate
DR
AW
N
EL
DA
TE
07/0
1/20
07
RE
V -
|---
--|-
----
|---
--|-
----
|---
--|
0
NT
S
SH
EE
TP
LOT
DA
TE
CLI
EN
T
Har
row
Est
ates
PR
OJE
CT
May
11t
h -
16t
h 2
006
Fo
rmer
Bay
er C
rop
scie
nce
, Hau
xto
n
Gro
un
dw
ater
Co
nto
urs
(m
AO
D)
SC
ALE
S
DR
AW
ING
TIT
LE
Atk
ins
Lim
ited
TH
IS D
RA
WIN
G IS
NO
T T
O B
E S
CA
LE
D
--
CO
-OR
D C
HE
CK
CH
EC
KE
D
DA
TE
DA
TE
5036
759/
Fig
ure
607
/01/
2007
A3
DR
AW
ING
NO
©B
irmin
gham
B
1 1T
F
Con
sulti
ng E
ngin
eers
The
Axi
s 1
0 H
ollid
ay S
tree
tF
ax
0121
483
585
8
Tel
0
121
483
5000
PU
RP
OS
E O
F IS
SU
EA
utho
rised
for
issu
e
RE
VIS
ION
SC
heck
edby
5036
759/
Fig
ure
6
MILLLANE
CAMB RIDG E RO AD
1.2 2
mR
H
1.22mRH
1.22mRH
De
f
CD
dW
ardBdy
CR
HASLINGFIELD AND THE EVERSDENS WARDY EDLD CP HAUXTON CP HARSTON AND HAUXTON WARD(a)
De
f
De
f
1.22m
RH
Def
FF
FW Und FW
De
f
Und
1.22
ED
&W
ard
Bdy
CD
CD
CR
SAWSTON ED
Def
ED
Bd
y
Rec
tory
Fa
rm
The
Cot
tage
Pavilion
She
lter
Wa
reho
use
Ta
nk
Pum
pin
g S
tati
onT
ank
s
Ch
y
Pav
ilion
Ha
uxt
on M
ill
Pu
mp
Ho
use
12 W
estf
ield
Co
ttag
es
90
4
Gas
Go
vern
or
Tan
ks
Tan
ks
Ta
nk
El
Su
bS
ta
Mill
Hou
se
Ta
nks
The
Mill
Hou
se
Ne
w
Tan
ks
Tan
ks
The
Wh
iteH
ouse
Ta
nk?
?
Track
Track
Tra
ck
Track
Co
urt
Sports Ground
Indu
stri
al E
fflu
en
t
Dis
po
sal P
lan
t
Ten
nis
Bow
ling
Gre
en
Track
Pipeline
El S
ub
Sta
13.
8m
12.9
m
BM
13
.56m
LB
El
Su
bS
ta
WB
Ch
em
ical
Wo
rks
FB
11.
6m
Spo
rts
Gro
und
Te
nnis
Cou
rts
Pa t
h(u
m)
FB
FB
Slu
ice
Slu
ice
Slu
ice
Hau
xto
nM
illB
ridg
e
12.8
m
Tra
ck
Tra
ck
BM
13.
08
m
Slu
ice
Track
Ha
uxto
nT
rack
Mile
Sto
ne
FB
Ta
nk
FB
We
ir
FB
Tra
ck
Pat
h(u
m)
Wei
r
Pipeline
Pip
elin
e
Pip
elin
e
PipelinePipeline
Pip
elin
e
Pipeline
Tan
k
Tan
kT
an
k
Tan
k
Tan
k
Drain
am
orGra
nta
Drain
River Cam or Granta
Drain
Dra
in
Dra
in
Drain
BH
1
BH
2
BH
3
BH
4
BH
5
BH
6
BH
7
BH
8
BH
9
BH
10
BH
11
BH
12
BH
13
BH
14
BH
15
BH
16
BH
18
BH
19
BH
20
S1
/8
S1
/15
S1/
24
S1/
31
S2/
3S
2/6
S3
/10
S7/
1
S9/
4
S9/
5
BH
1/0
6 BH
2/0
6
BH
3/0
6
BH
4/0
6
BH
5/0
6
BH
6/0
6
BH
7/0
6
BH
8/06
BH
9/0
6BH
10
/06
BH
11/
06
BH
12/0
6
P6
7N
Key
Con
tour
s of
gro
undw
ater
leve
l in
mA
OD
Dra
wn
byD
ate
Rev
.D
ate
DR
AW
N
EL
DA
TE
07/0
1/20
07
RE
V -
5036
759/
Fig
ure
7
PU
RP
OS
E O
F IS
SU
EA
utho
rised
for
issu
e
RE
VIS
ION
SC
heck
edby
©B
irmin
gham
B
1 1T
F
Con
sulti
ng E
ngin
eers
The
Axi
s 1
0 H
ollid
ay S
tree
tF
ax
0121
483
585
8
Tel
0
121
483
5000
5036
759/
Fig
ure
707
/01/
2007
A3
DR
AW
ING
NO
--
CO
-OR
D C
HE
CK
CH
EC
KE
D
DA
TE
DA
TE
DR
AW
ING
TIT
LE
Atk
ins
Lim
ited
TH
IS D
RA
WIN
G IS
NO
T T
O B
E S
CA
LE
D
Gro
un
dw
ater
Co
nto
urs
(m
AO
D)
SC
ALE
S
CLI
EN
T
Har
row
Est
ates
PR
OJE
CT
Dec
emb
er 1
2th
200
6
Fo
rmer
Bay
er C
rop
scie
nce
, Hau
xto
n
|---
--|-
----
|---
--|-
----
|---
--|
0
NT
S
SH
EE
TP
LOT
DA
TE
N
MILLLANE
CAMB RIDG E RO AD
1.22
mR
H
1.22mRH
1.22mRH
De
f
CD
War
dBdy
CR
HASLINGFIELD AND THE EVERSDENS WARDED
D CP HAUXTON CP HARSTON AND HAUXTON WARD(a)
Def
De
f
1. 22m
RH
Def
FF
FW Und FW
Def
Und
ED
&W
ar d
Bd
y
CD
CD
CR
SAWSTON ED
Def
ED
Bd
y
Rec
tory
Fa
rm
The
Cot
tage
Pavilion
She
lter
Wa
reho
use
Ta
nk
Pum
pin
g S
tati
onT
ank
s
Ch
y
Pav
ilion
Hau
xto
n M
ill
Pum
p H
ous
e
12 W
est
field
Co
tta
ge
s
90
4
Ga
s G
over
nor
Ta
nks
Tan
ks
Tan
k
El S
ub
Sta
Mill
Hou
se
Tan
ks
The
Mill
Hou
se
New
Tan
ks
Ta
nks
The
Whi
teH
ouse
Ta
nk??
Track
Track
Tra
ck
Track
Co
urt
Sports Ground
Indu
stri
al E
fflu
en
t
Dis
po
sal P
lan
t
Ten
nis
Bo
wlin
g
Gre
en
Track
Pipeline
El S
ub
13
.8m
12.
9m
BM
13
.56m
LB
El
Sub
Sta
WB
Ch
emic
al W
ork
s
FB
11.
6m
Sp
orts
Gro
un
d
Ten
nis
Cou
rts
Pat
h(u
m)
FB
FB
Slu
ice
Slu
ice
Slu
ice
Hau
xto
nM
illB
ridge
12.8
m
Tra
ck
Tra
ck
BM
13.
08
m
Slu
ice
Track
Ha
uxt
on
Tra c
k
Mile
Sto
ne
FB
Ta
nk
FBW
eir
FB
Trac
k
Pat
h(u
m)
Wei
r
P ipeline
Pip
elin
e
Pip
elin
e
PipelinePipeline
Pip
elin
e
Pipeline
Tan
k
Tan
kT
ank
Ta
nk
Ta
nk
Drai
m
orG
rant
a
Drain
River Cam or Granta
Drain
Dra
in
Dra
in
DraB
H1
BH
2
BH
3
BH
4
BH
5
BH
6
BH
7
BH
8
BH
9
BH
10
BH
11
BH
12
BH
13
BH
14
BH
15
BH
16
BH
18
BH
19
BH
20
S1
/8
S1
/15
S1/
24
S1/
31
S2
/3S
2/6
S3
/10
S7/
1
S9
/4
S9/
5
BH
1/0
6 BH
2/0
6
BH
3/0
6
BH
4/0
6
BH
5/0
6
BH
6/0
6
BH
7/0
6
BH
8/06
BH
9/0
6BH
10
/06
BH
11/
06
BH
12
/06
P6
7
Further Quantitative Risk Assessment for Controlled Waters and Preliminary Post-Remediation Validation Model
Rev A 907BRI
APPENDIX C
WATER PUMPING VOLUMES
Site Pumping and Rainfall Data Comparison
Month Rainfall(mm) Site Rainfall Volume (m3) Volume Pumped (m3)
Sep 55.1 4683.5 4654
Oct 55.2 4692 4264
Nov 26 2210 3829
Dec 22.7 1929.5 3028
Jan 61.6 5236 5769
Feb 31.4 2669 3592
Mar 3 255 4052
Apr 1.7 144.5 2775
Total 256.7 21819.5 31963
Monthly pumped volumes from site pumping data
Rainfall volume calculated based on an approximate site area of 8.5 ha
Local Rainfall data taken from Cambridge Universtiy botanic gardens ‐
http://www.botanic.cam.ac.uk/Botanic/Page.aspx?p=27&ix=2830&pid=0&prcid=0&ppid=0
Average rainfall for the site (from MORECS data) ‐ 586 mm/year
For a 8 month period (Sep to Apr) this would give a site rainfall volume of 33206.67 m3
Further Quantitative Risk Assessment for Controlled Waters and Preliminary Post-Remediation Validation Model
Rev A 907BRI
APPENDIX D
GEOTECHNICAL RESULTS
BS1377 : Part 5 : Clause 5 :1990
Determination of Permeability by the Constant Head Method
Description:Sample Id: TB 124 Brown silty slightly clayey SAND with much fine to medium gravel
SPECIMEN DETAILS
Depth within original sample n/a
Orientation within original n/a
Specimen preparation Firmly hand tamped in 4 layers.
TEST DETAILS
INITIAL
Diameter mm 77.0
Height mm 174.0
Moisture Content % 8.9
Bulk Density Mg/m³ 2.04
Dry Density Mg/m³ 1.88
Permeability, k m/s 4.1 x 10-6
Checked and Project Number:
Approved GEO / 16602
Initials: Project Name: GEOLABSCFW 907BRI
Date: 01/03/11
Test Report by GEOLABS Limited Bucknalls Lane, Garston, Watford, Hertfordshire, WD25 9XX © GEOLABS LIMITED (Ref4603.617130) Page 1 of 1
Authorised Signatories: [] J R Masters (Qual Mgr) [x] C F Wallace (Tech Mgr) • J M M Powell (Tech Dir)
Client: Vertase FLI Limited, Number One, Middle Bridge Business Park, Bristol Road, Portishead BS20 6PN GEOLABS®GEOLABS LIMITED ®
0 1 2 3 4 50
2
4
6
Hydraulic Gradient
Flo
w R
ate
(m
L/m
in)
Measured Values Laminar Flow Best Fit
®
BS1377 : Part 5 : Clause 5 :1990
Determination of Permeability by the Constant Head Method
Description:Sample Id: TB 127 Brown silty clayey SAND with much fine to medium gravel
SPECIMEN DETAILS
Depth within original sample n/a
Orientation within original n/a
Specimen preparation Firmly hand tamped in 4 layers.
TEST DETAILS
INITIAL
Diameter mm 77.0
Height mm 180.9
Moisture Content % 8.7
Bulk Density Mg/m³ 1.93
Dry Density Mg/m³ 1.77
Permeability, k m/s 3.3 x 10-7
Checked and Project Number:
Approved GEO / 16602
Initials: Project Name: GEOLABSCFW 907BRI
Date: 01/03/11
Test Report by GEOLABS Limited Bucknalls Lane, Garston, Watford, Hertfordshire, WD25 9XX © GEOLABS LIMITED (Ref4603.623438) Page 1 of 1
Authorised Signatories: [] J R Masters (Qual Mgr) [x] C F Wallace (Tech Mgr) • J M M Powell (Tech Dir)
Client: Vertase FLI Limited, Number One, Middle Bridge Business Park, Bristol Road, Portishead BS20 6PN GEOLABS®GEOLABS LIMITED ®
0 2 4 6 80
0.2
0.4
0.6
0.8
Hydraulic Gradient
Flo
w R
ate
(m
L/m
in)
Measured Values Laminar Flow Best Fit
®
BS1377 : Part 2 : Clause 9 : 1990
Determination of Particle Size Distribution
Borehole Number: TB21 Description:Sample Number: - Brown silty sandy gravelly CLAYDepth (m): -
BS1377 : Part 2 : Clause 9.2 : 1990 Wet Sieving MethodBS1377 : Part 2 : Clause 9.4 : 1990 Sedimentation by the Pipette Method
SIEVE
Sieve % pass
200 mm 100
125 mm 100
90 mm 100
75 mm 100
63 mm 100
50 mm 100
37.5 mm 100
28 mm 96
20 mm 94
14 mm 92
10 mm 86
6.3 mm 79
5 mm 76
3.35 mm 73
2 mm 69
1.18 mm 66
600 µm 61
425 µm 56 Particle Proportions
300 µm 47 Cobbles 0.0 %
212 µm 40 Gravel 30.8 %
150 µm 36 Sand 37.2 %
63 µm 32 Silt 16.8 %
Clay 15.2 %
PIPETTE
Particle size % pass
20.0 µm 31
6.0 µm 23
2.0 µm 15Preparation:
No Pre-treatment used
Temp (°C) 20
Checked and Project Number:
Approved GEO / 16602
Initials: Project Name: GEOLABS ®
SB 907BRI
Date: 09/03/2011
Test Report by GEOLABS Limited Bucknalls Lane, Garston, Watford, Hertfordshire, WD25 9XX © GEOLABS LIMITED (Ref4611.471458) Page 1 of 1
Authorised Signatories: • J R Masters (Qual Mgr) • C F Wallace (Tech Mgr) • G J Corio (Tech Mgr) • J Sturges (Tech Mgr) [X] S Burke (Snr Tech) GEOLABS®
Client: Vertase FLI Limited, Number One, Middle Bridge Business Park, Bristol Road, Portishead BS20 6PN
0.001 0.01 0.1 1 10 1000
10
20
30
40
50
60
70
80
90
100
Particle Size (mm)
Per
cent
age
Pas
sing
SILT
CLA
Y
0.001 0.01 0.1 1 10 1000102030405060708090100
Fine CoarseMedium Fine CoarseMedium Fine CoarseMedium
SAND GRAVEL
CO
BB
LES
SILT
CLA
Y
BS1377 : Part 2 : Clause 9 : 1990
Determination of Particle Size Distribution
Borehole Number: TB124 Description:Sample Number: - Brown clayey SAND and GRAVELDepth (m): -
BS1377 : Part 2 : Clause 9.2 : 1990 Wet Sieving Method
SIEVE
Sieve % pass
200 mm 100
125 mm 100
90 mm 100
75 mm 100
63 mm 100
50 mm 100
37.5 mm 100
28 mm 96
20 mm 87
14 mm 80
10 mm 74
6.3 mm 67
5 mm 64
3.35 mm 60
2 mm 57
1.18 mm 52
600 µm 47
425 µm 39 Particle Proportions
300 µm 28 Cobbles 0.0 %
212 µm 18 Gravel 42.7 %
150 µm 14 Sand 46.2 %
63 µm 11 Silt & Clay 11.1 %
Checked and Project Number:
Approved GEO / 16602
Initials: Project Name: GEOLABS ®
SB 907BRI
Date: 09/02/2011
Test Report by GEOLABS Limited Bucknalls Lane, Garston, Watford, Hertfordshire, WD25 9XX © GEOLABS LIMITED (Ref4611.471481) Page 1 of 1
Authorised Signatories: • J R Masters (Qual Mgr) • C F Wallace (Tech Mgr) • G J Corio (Tech Mgr) • J Sturges (Tech Mgr) [X] S Burke (Snr Tech) GEOLABS®
Client: Vertase FLI Limited, Number One, Middle Bridge Business Park, Bristol Road, Portishead BS20 6PN
0.001 0.01 0.1 1 10 1000102030405060708090100
Fine CoarseMedium Fine CoarseMedium Fine CoarseMedium
SILT SAND GRAVEL
CO
BB
LES
CLA
Y
0.001 0.01 0.1 1 10 1000
10
20
30
40
50
60
70
80
90
100
Particle Size (mm)
Per
cent
age
Pas
sing
BS1377 : Part 2 : Clause 9 : 1990
Determination of Particle Size Distribution
Borehole Number: TB127 Description:Sample Number: - Brown clayey gravelly SANDDepth (m): -
BS1377 : Part 2 : Clause 9.2 : 1990 Wet Sieving Method
SIEVE
Sieve % pass
200 mm 100
125 mm 100
90 mm 100
75 mm 100
63 mm 100
50 mm 100
37.5 mm 100
28 mm 100
20 mm 99
14 mm 97
10 mm 93
6.3 mm 88
5 mm 86
3.35 mm 82
2 mm 76
1.18 mm 72
600 µm 65
425 µm 54 Particle Proportions
300 µm 35 Cobbles 0.0 %
212 µm 21 Gravel 23.8 %
150 µm 17 Sand 62.7 %
63 µm 13 Silt & Clay 13.5 %
Checked and Project Number:
Approved GEO / 16602
Initials: Project Name: GEOLABS ®
SB 907BRI
Date: 09/02/2011
Test Report by GEOLABS Limited Bucknalls Lane, Garston, Watford, Hertfordshire, WD25 9XX © GEOLABS LIMITED (Ref4611.471539) Page 1 of 1
Authorised Signatories: • J R Masters (Qual Mgr) • C F Wallace (Tech Mgr) • G J Corio (Tech Mgr) • J Sturges (Tech Mgr) [X] S Burke (Snr Tech) GEOLABS®
Client: Vertase FLI Limited, Number One, Middle Bridge Business Park, Bristol Road, Portishead BS20 6PN
0.001 0.01 0.1 1 10 1000102030405060708090100
Fine CoarseMedium Fine CoarseMedium Fine CoarseMedium
SILT SAND GRAVEL
CO
BB
LES
CLA
Y
0.001 0.01 0.1 1 10 1000
10
20
30
40
50
60
70
80
90
100
Particle Size (mm)
Per
cent
age
Pas
sing
BS1377 : Part 4 : 1990
Moisture Content / Dry Density Relationship
Description:
Sample No: TB 5 Grey brown silty very sandy gravelly CLAY
BS1377 : Part 4 : Clause 3.4.4.1 : 1990 2.5 kg Compaction Test
Sample Preparation: Material was air dried. Single sample
Particles greater than 37.5mm were removed.
Particle Density: 2.69 (measured by small pyknometer method)
Material Retained
on 20 mm test sieve: 8 %
on 37.5 mm test sieve: 2 %
Maximum Dry Density 1.89 Mg/m³
Optimum Moisture Content 13 %
Checked and Project Number:
Approved GEO / 16761
Initials: Project Name: GEOLABS ®
JS HAUXTON
Date:26/04/2011 907BRI
Test Report by GEOLABS Limited Bucknalls Lane, Garston, Watford, Hertfordshire, WD25 9XX © GEOLABS LIMITED (Ref4659.701030) Page 1 of 1
Authorised Signatories: � J R Masters (Qual Mgr) � C F Wallace (Tech Mgr) � G J Corio (Tech Mgr) [X] J Sturges (Tech Mgr) � S Burke (Snr Tech) GEOLABS®
Client: Vertase FLI Limited, Number One, Middle Bridge Business Park, Bristol Road, Portishead BS20 6PN
6 8 10 12 14 16 18
1.75
1.80
1.85
1.90
1.95
Moisture Content (%)
Dry
De
nsity
(Mg
/m³)
0% air voids
5% air voids
10% air voids
BS1377 : Part 4 : 1990
Moisture Content / Dry Density Relationship
Description:
Sample No: TB26 Grey silty sandy CLAY with rare fine
to medium gravel and chalk fragments
BS1377 : Part 4 : Clause 3.3.4.1 : 1990 2.5 kg Compaction Test
Sample Preparation: Material was air dried. Single sample
No particles were removed
Particle Density: 2.73 (measured by small pyknometer method)
Material Retained
on 20 mm test sieve: 0 %
on 37.5 mm test sieve: 0 %
Maximum Dry Density 1.69 Mg/m³
Optimum Moisture Content 20 %
Checked and Project Number:
Approved GEO / 16761
Initials: Project Name: GEOLABS ®
JS HAUXTON
Date:26/04/2011 907BRI
Test Report by GEOLABS Limited Bucknalls Lane, Garston, Watford, Hertfordshire, WD25 9XX © GEOLABS LIMITED (Ref4659.701181) Page 1 of 1
Authorised Signatories: � J R Masters (Qual Mgr) � C F Wallace (Tech Mgr) � G J Corio (Tech Mgr) [X] J Sturges (Tech Mgr) � S Burke (Snr Tech) GEOLABS®
Client: Vertase FLI Limited, Number One, Middle Bridge Business Park, Bristol Road, Portishead BS20 6PN
10 15 20 25
1.55
1.60
1.65
1.70
Moisture Content (%)
Dry
De
nsity
(Mg
/m³)
0% air voids
5% air voids
10% air voids
Project Name: PROJECT 907BRI Date 07/04/2011
Approved J STURGES Project Number: GEO / 16715 Page 1 of 1
Bulk Dry Moisture Particle Density Saturation Voids Porosity Degree of
Borehole Sample Depth Density Content (Mg/m³) Moisture Content Ratio (Total Vol of Voids) Saturation Description
Number Number (m) Mg/m³ % (Measured) (Assumed) (%) (%) (%)
- TB9 - 2.03 1.68 20.8 2.73 22.60 0.622 0.384 91.3 Firm brown sandy silty CLAY with rare fine to medium gravel
- TB10 - 2.04 1.70 19.7 2.71 21.70 0.594 0.373 89.9 Firm brown sandy silty gravelly CLAY,
gravel is fine to medium grained
DENSITY, MOISTURE CONTENTS, POROSITY RESULTS GEOLABS ®
Test Report by GEOLABS Limited Bucknalls Lane, Garston, Watford, Hertfordshire, WD25 9XX (Ref 4640.402801) Page 1 of 1
Authorised Signatories: [ ] J R Masters (Qual Mgr) [ ] C F Wallace (Tech Mgr) [x] J Sturges (Tech Mgr) [ ] S Burke (Snr Tech) DensPoros.WK4 ISSUE 1 (02/10)
Client: Vertase FLI Limited, Number One, Middle Bridge Business Park, Bristol Road, Portishead BS20 6PN GEOLABS LIMITED ®
BS1377 : Part 6 : Clause 6 :1990
Determination of Permeability in a Triaxial Cell
Borehole / TP: Description:Sample No: TB4 Brown sandy gravelly CLAY, gravel is fine to coarse sand is fine toDepth: coarse
SPECIMEN DETAILS
Depth within original sample N/A
Orientation within original N/A Specimen preparation Remoulded using 4.5kg effort at natural moisture content
TEST DETAILS
Cell Preparation Performed in accordance with Clause 3.5
INITIAL FINAL
Diameter mm 104.5 104.4
Height mm 115.3 115.1
Moisture Content % 13 14Bulk Density Mg/m³ 2.21 2.23
Dry Density Mg/m³ 1.96 1.96
SATURATION STAGE
Saturation initially by constant moisture content, followed by back-pressure assistance using 5-10 kPa differential
'B' value 0.79 0.92
CONSOLIDATION STAGE
Effective pressure kPa 50
Volume change mL 4.2
PERMEABILITY STAGE
Pressure difference across specimen 10 Coefficient of permeability at 20ºC =
Mean effective stress kPa 45
1.3 x 10 m/s TEST DURATIONS
Saturation days 3 Hydraulic Gradient = 8.9Consolidation days 2 Flow days 2
Checked and Project Number:
Approved GEO / 16801Initials: Project Name: GEOLABS
PTH HAUXTON 907BRIDate:
09/05/11 Schedule 5
Test Report by GEOLABS Limited Bucknalls Lane, Garston, Watford, Hertfordshire, WD25 9XX © GEOLABS LIMITED (Ref4672.467535) Page 1 of 1
Authorised Signatories: [ ] J R Masters (Qual Mgr) [ ] C F Wallace (Tech Mgr) [X] P T Heritage (Tech Mgr) [ ] J M M Powell (Tech Dir)
Client: Vertase FLI Limited, Number One, Middle Bridge Business Park, Bristol Road, Portishead BS20 6PN GEOLABS ®
0 500 1000 1500 20000
0.2
0.4
0.6
0.8
1
1.2
1.4
Time (min)
Cum
ulat
ive
Flo
w (
mL)
0
0.2
0.4
0.6
0.8
1
1.2
-10
®
BS1377 : Part 6 : Clause 6 :1990
Determination of Permeability in a Triaxial Cell
Borehole / TP: Description:Sample No: TB5 Grey silty CLAY and fine gravelDepth:
SPECIMEN DETAILS
Depth within original sample
Orientation within original Specimen preparation Remoulded @ NMC using 4.5kg compactive effort
TEST DETAILS
Cell Preparation Performed in accordance with Clause 3.5
INITIAL FINAL
Diameter mm 104.0 103.7
Height mm 116.2 115.9
Moisture Content % 15 16Bulk Density Mg/m³ 2.19 2.23
Dry Density Mg/m³ 1.90 1.92
SATURATION STAGE
Saturation initially by constant moisture content, followed by back-pressure assistance using 5-10 kPa differential
'B' value 0.50 0.96
CONSOLIDATION STAGE
Effective pressure kPa 50
Volume change mL 8.0
PERMEABILITY STAGE
Pressure difference across specimen 10 Coefficient of permeability at 20ºC =
Mean effective stress kPa 45
8.4 x 10 m/s TEST DURATIONS
Saturation days 5 Hydraulic Gradient = 8.8Consolidation days 3 Flow days 2
Checked and Project Number:
Approved GEO /16761Initials: Project Name: GEOLABS
PTH HAUXTONDate:
28/04/11 907BRI
Test Report by GEOLABS Limited Bucknalls Lane, Garston, Watford, Hertfordshire, WD25 9XX © GEOLABS LIMITED (Ref4661.429201) Page 1 of 1
Authorised Signatories: [ ] J R Masters (Qual Mgr) [ ] C F Wallace (Tech Mgr) [X] P T Heritage (Ops Mgr) [ ] J M M Powell (Tech Dir)
Client: Vertase FLI Limited, Number One, Middle Bridge Business Park, Bristol Road, Portishead BS20 6PN GEOLABS ®
0 500 1000 1500 20000
0.2
0.4
0.6
0.8
1
Time (min)
Cum
ulat
ive
Flo
w (
mL)
0
0.2
0.4
0.6
0.8
1
1.2
-11
®
BS1377 : Part 6 : Clause 6 :1990
Determination of Permeability in a Triaxial Cell
Borehole / TP: Description:Sample No: TB9 Light grey silty CLAY with occasional fine gravelDepth:
SPECIMEN DETAILS
Depth within original sample N/A
Orientation within original N/A Specimen preparation Remoulded using a 2.5kg effort at NMC
TEST DETAILS
Cell Preparation Performed in accordance with Clause 3.5
INITIAL FINAL
Diameter mm 104.1 103.3
Height mm 115.2 114.3
Moisture Content % 23 22Bulk Density Mg/m³ 2.05 2.08
Dry Density Mg/m³ 1.66 1.70
SATURATION STAGE
Saturation initially by constant moisture content, followed by back-pressure assistance using 5-10 kPa differential
'B' value 0.83 0.98
CONSOLIDATION STAGE
Effective pressure kPa 50
Volume change mL 21.9
PERMEABILITY STAGE
Pressure difference across specimen 10 Coefficient of permeability at 20ºC =
Mean effective stress kPa 45
1.1 x 10 m/s TEST DURATIONS
Saturation days 4 Hydraulic Gradient = 8.9Consolidation days 5 Flow days 5
Checked and Project Number:
Approved GEO / 16715Initials: Project Name: GEOLABS
PTH PROJECT 907BRIDate:
15/04/11
Test Report by GEOLABS Limited Bucknalls Lane, Garston, Watford, Hertfordshire, WD25 9XX © GEOLABS LIMITED (Ref4648.590197) Page 1 of 1
Authorised Signatories: [ ] J R Masters (Qual Mgr) [ ] C F Wallace (Tech Mgr) [X] P T Heritage (Ops Mgr) [ ] J M M Powell (Tech Dir)
Client: Vertase FLI Limited, Number One, Middle Bridge Business Park, Bristol Road, Portishead BS20 6PN GEOLABS ®
0 2000 4000 6000 8000 10000 120000
2
4
6
Time (min)
Cum
ulat
ive
Flo
w (
mL)
0
0.2
0.4
0.6
0.8
1
1.2
-10
®
BS1377 : Part 6 : Clause 6 :1990
Determination of Permeability in a Triaxial Cell
Borehole / TP: Description:Sample No: TB10 Grey silty CLAY with occasional fine to medium gravelDepth:
SPECIMEN DETAILS
Depth within original sample N/A
Orientation within original N/A Specimen preparation Remoulded using a 2.5kg effort at NMC
TEST DETAILS
Cell Preparation Performed in accordance with Clause 3.5
INITIAL FINAL
Diameter mm 104.3 103.6
Height mm 114.6 113.8
Moisture Content % 22 21Bulk Density Mg/m³ 2.08 2.11
Dry Density Mg/m³ 1.71 1.75
SATURATION STAGE
Saturation initially by constant moisture content, followed by back-pressure assistance using 5-10 kPa differential
'B' value 0.85 0.96
CONSOLIDATION STAGE
Effective pressure kPa 50
Volume change mL 20.2
PERMEABILITY STAGE
Pressure difference across specimen 10 Coefficient of permeability at 20ºC =
Mean effective stress kPa 45
1.7 x 10 m/s TEST DURATIONS
Saturation days 4 Hydraulic Gradient = 9.0Consolidation days 5 Flow days 5
Checked and Project Number:
Approved GEO / 16715Initials: Project Name: GEOLABS
PTH PROJECT 907BRIDate:
15/04/11
Test Report by GEOLABS Limited Bucknalls Lane, Garston, Watford, Hertfordshire, WD25 9XX © GEOLABS LIMITED (Ref4648.592234) Page 1 of 1
Authorised Signatories: [ ] J R Masters (Qual Mgr) [ ] C F Wallace (Tech Mgr) [X] P T Heritage (Ops Mgr) [ ] J M M Powell (Tech Dir)
Client: GEOLABS ®
0 2000 4000 6000 8000 10000 12000-2
0
2
4
6
8
Time (min)
Cum
ulat
ive
Flo
w (
mL)
0
0.2
0.4
0.6
0.8
1
1.2
-10
®
BS1377 : Part 6 : Clause 6 :1990
Determination of Permeability in a Triaxial Cell
Description:Sample No: TB13 Soft to firm light grey silty CLAY
SPECIMEN DETAILS
Depth within original sample N/A
Orientation within original Vertical Specimen preparation remoulded using 4.5kg effort at NMC
TEST DETAILS
Cell Preparation Performed in accordance with Clause 3.5
INITIAL FINAL
Diameter mm 103.7 101.7
Height mm 114.3 112.2
Moisture Content % 26 23Bulk Density Mg/m³ 2.03 2.11
Dry Density Mg/m³ 1.61 1.71
SATURATION STAGE
Saturation initially by constant moisture content, followed by back-pressure assistance using 5-10 kPa differential
'B' value 0.98 1.03
CONSOLIDATION STAGE
Effective pressure kPa 50
Volume change mL 54.6
PERMEABILITY STAGE
Pressure difference across specimen 10 Coefficient of permeability at 20ºC =
Mean effective stress kPa 45
1.4 x 10 m/s TEST DURATIONS
Saturation days 1 Hydraulic Gradient = 9.1Consolidation days 5 Flow days 3
Checked and Project Number:
Approved GEO / 16602Initials: Project Name: GEOLABS
PTH 907BRIDate:
02/03/11
Test Report by GEOLABS Limited Bucknalls Lane, Garston, Watford, Hertfordshire, WD25 9XX © GEOLABS LIMITED (Ref4604.638507) Page 1 of 1
Authorised Signatories: [ ] J R Masters (Qual Mgr) [ ] C F Wallace (Tech Mgr) [X] P T Heritage (Ops Mgr) [ ] J M M Powell (Tech Dir)
Client: Vertase FLI Limited, Number One, Middle Bridge Business Park, Bristol Road, Portishead BS20 6PN GEOLABS ®
0 1000 2000 3000 4000 50000
1
2
3
Time (min)
Cum
ulat
ive
Flo
w (
mL)
0
0.2
0.4
0.6
0.8
1
1.2
-10
®
BS1377 : Part 6 : Clause 6 :1990
Determination of Permeability in a Triaxial Cell
Description:Sample No: TB19 Soft light grey silty CLAY with occasional fine to medium gravel (wet sample)
SPECIMEN DETAILS
Depth within original sample N/A
Orientation within original Vertical Specimen preparation Remoulded using a 4.5kg effort
TEST DETAILS
Cell Preparation Performed in accordance with Clause 3.5
INITIAL FINAL
Diameter mm 104.2 102.1
Height mm 112.1 109.9
Moisture Content % 31 26Bulk Density Mg/m³ 1.97 2.02
Dry Density Mg/m³ 1.51 1.60
SATURATION STAGE
Saturation initially by constant moisture content, followed by back-pressure assistance using 5-10 kPa differential
'B' value 1.00 1.00
CONSOLIDATION STAGE
Effective pressure kPa 50
Volume change mL 55.9
PERMEABILITY STAGE
Pressure difference across specimen 10 Coefficient of permeability at 20ºC =
Mean effective stress kPa 45
2.3 x 10 m/s TEST DURATIONS
Saturation days 1 Hydraulic Gradient = 9.3Consolidation days 3 Flow days 4
Checked and Project Number:
Approved GEO / 16602Initials: Project Name: GEOLABS
PTH 90 BRIDate:
02/03/11
Test Report by GEOLABS Limited Bucknalls Lane, Garston, Watford, Hertfordshire, WD25 9XX © GEOLABS LIMITED (Ref4604.641273) Page 1 of 1
Authorised Signatories: [ ] J R Masters (Qual Mgr) [ ] C F Wallace (Tech Mgr) [X] P T Heritage (Ops Mgr) [ ] J M M Powell (Tech Dir)
Client: Vertase FLI Limited, Number One, Middle Bridge Business Park, Bristol Road, Portishead BS20 6PN GEOLABS ®
0 2000 4000 60000
2
4
6
8
Time (min)
Cum
ulat
ive
Flo
w (
mL)
0
0.2
0.4
0.6
0.8
1
1.2
-10
®
BS1377 : Part 6 : Clause 6 :1990
Determination of Permeability in a Triaxial Cell
Borehole / TP: Description:Sample No: TB26 Light grey silty CLAY with occasional fine gravelDepth:
SPECIMEN DETAILS
Depth within original sample
Orientation within original Specimen preparation Remoulded @ NMC using a compactive effort of 4.5kg
TEST DETAILS
Cell Preparation Performed in accordance with Clause 3.5
INITIAL FINAL
Diameter mm 104.2 103.4
Height mm 116.3 115.4
Moisture Content % 11 23Bulk Density Mg/m³ 1.85 2.09
Dry Density Mg/m³ 1.67 1.70
SATURATION STAGE
Saturation initially by constant moisture content, followed by back-pressure assistance using 5-10 kPa differential
'B' value 0.92 0.96
CONSOLIDATION STAGE
Effective pressure kPa 50
Volume change mL 21.1
PERMEABILITY STAGE
Pressure difference across specimen 10 Coefficient of permeability at 20ºC =
Mean effective stress kPa 45
1.7 x 10 m/s TEST DURATIONS
Saturation days 5 Hydraulic Gradient = 8.8Consolidation days 3 Flow days 2
Checked and Project Number:
Approved GEO /16761Initials: Project Name: GEOLABS
PTH HAUXTONDate:
28/04/11 907BRI
Test Report by GEOLABS Limited Bucknalls Lane, Garston, Watford, Hertfordshire, WD25 9XX © GEOLABS LIMITED (Ref4661.445382) Page 1 of 1
Authorised Signatories: [ ] J R Masters (Qual Mgr) [ ] C F Wallace (Tech Mgr) [X] P T Heritage (Ops Mgr) [ ] J M M Powell (Tech Dir)
Client: Vertase FLI Limited, Number One, Middle Bridge Business Park, Bristol Road, Portishead BS20 6PN GEOLABS ®
0 500 1000 1500 20000
0.5
1
1.5
2
Time (min)
Cum
ulat
ive
Flo
w (
mL)
0
0.2
0.4
0.6
0.8
1
1.2
-10
®
BS1377 : Part 6 : Clause 6 :1990
Determination of Permeability in a Triaxial Cell
Description:Sample No: TB32 Soft to firm light grey slightly sandy CLAY with occational fine to medium gravel
SPECIMEN DETAILS
Depth within original sample N/A
Orientation within original Vertical Specimen preparation Remoulded using a 4.5kg effort
TEST DETAILS
Cell Preparation Performed in accordance with Clause 3.5
INITIAL FINAL
Diameter mm 103.7 102.7
Height mm 115.6 114.6
Moisture Content % 24 22Bulk Density Mg/m³ 2.05 2.08
Dry Density Mg/m³ 1.65 1.70
SATURATION STAGE
Saturation initially by constant moisture content, followed by back-pressure assistance using 5-10 kPa differential
'B' value 0.96 1.00
CONSOLIDATION STAGE
Effective pressure kPa 50
Volume change mL 26.4
PERMEABILITY STAGE
Pressure difference across specimen 10 Coefficient of permeability at 20ºC =
Mean effective stress kPa 45
1.1 x 10 m/s TEST DURATIONS
Saturation days 1 Hydraulic Gradient = 8.9Consolidation days 5 Flow days 3
Checked and Project Number:
Approved GEO / 16602Initials: Project Name: GEOLABS
PTH 907BRIDate:
02/03/11
Test Report by GEOLABS Limited Bucknalls Lane, Garston, Watford, Hertfordshire, WD25 9XX © GEOLABS LIMITED (Ref4604.642963) Page 1 of 1
Authorised Signatories: [ ] J R Masters (Qual Mgr) [ ] C F Wallace (Tech Mgr) [X] P T Heritage (Ops Mgr) [ ] J M M Powell (Tech Dir)
Client: Vertase FLI Limited, Number One, Middle Bridge Business Park, Bristol Road, Portishead BS20 6PN GEOLABS ®
0 1000 2000 3000 4000 50000
0.5
1
1.5
2
2.5
Time (min)
Cum
ulat
ive
Flo
w (
mL)
0
0.2
0.4
0.6
0.8
1
1.2
-10
®
BS1377 : Part 4 : 1990
Moisture Content / Dry Density Relationship
Trial Pit No: TB 66 Description:
Grey silty CLAY
BS1377 : Part 4 : Clause 3.5.4.1 : 1990 4.5 kg Compaction Test
Sample Preparation: Material was air dried. Single sample
No particles were removed
Particle Density: 2.65 (measured by small pyknometer method)
Material Retained
on 20 mm test sieve: 0 %
on 37.5 mm test sieve: 0 %
Maximum Dry Density 1.68 Mg/m³
Optimum Moisture Content 19 %
Checked and Project Number:
Approved GEO / 16683
Initials: Project Name: GEOLABS ®
JS 907BRI
Date:28/03/2011
Test Report by GEOLABS Limited Bucknalls Lane, Garston, Watford, Hertfordshire, WD25 9XX © GEOLABS LIMITED (Ref4630.632951) Page 1 of 1
Authorised Signatories: � J R Masters (Qual Mgr) � C F Wallace (Tech Mgr) � G J Corio (Tech Mgr) [X] J Sturges (Tech Mgr) � S Burke (Snr Tech) GEOLABS®
Client: Vertase FLI Limited, Number One, Middle Bridge Business Park, Bristol Road, Portishead BS20 6PN
5 10 15 20 25 30
1.50
1.55
1.60
1.65
1.70
Moisture Content (%)
Dry
De
nsity
(Mg
/m³)
0% air voids
5% air voids
10% air voids
BS1377 : Part 4 : 1990
Moisture Content / Dry Density Relationship
Trial Pit No: TB 67 Description:
Grey silty CLAY with rare iron pyrite
BS1377 : Part 4 : Clause 3.5.4.1 : 1990 4.5 kg Compaction Test
Sample Preparation: Material was air dried. Single sample
No particles were removed
Particle Density: 2.65 (measured by small pyknometer method)
Material Retained
on 20 mm test sieve: 0 %
on 37.5 mm test sieve: 0 %
Maximum Dry Density 1.67 Mg/m³
Optimum Moisture Content 19 %
Checked and Project Number:
Approved GEO / 16683
Initials: Project Name: GEOLABS ®
JS 907BRI
Date:28/03/2011
Test Report by GEOLABS Limited Bucknalls Lane, Garston, Watford, Hertfordshire, WD25 9XX © GEOLABS LIMITED (Ref4630.633056) Page 1 of 1
Authorised Signatories: � J R Masters (Qual Mgr) � C F Wallace (Tech Mgr) � G J Corio (Tech Mgr) � J Sturges (Tech Mgr) � R J Platt (Snr Tech) � J J M Powell (Tech Dir) GEOLABS®
Client: Vertase FLI Limited, Number One, Middle Bridge Business Park, Bristol Road, Portishead BS20 6PN
0 10 20 30
1.50
1.55
1.60
1.65
1.70
Moisture Content (%)
Dry
De
nsity
(Mg
/m³)
0% air voids
5% air voids
10% air voids
BS1377 : Part 4 : 1990
Moisture Content / Dry Density Relationship
Trial Pit No: TB 70 Description:
Grey silty CLAY
BS1377 : Part 4 : Clause 3.5.4.1 : 1990 4.5 kg Compaction Test
Sample Preparation: Material was air dried. Single sample
No particles were removed
Particle Density: 2.69 (measured by small pyknometer method)
Material Retained
on 20 mm test sieve: 0 %
on 37.5 mm test sieve: 0 %
Maximum Dry Density 1.68 Mg/m³
Optimum Moisture Content 18 %
Checked and Project Number:
Approved GEO / 16683
Initials: Project Name: GEOLABS ®
JS 907BRI
Date:28/03/2011
Test Report by GEOLABS Limited Bucknalls Lane, Garston, Watford, Hertfordshire, WD25 9XX © GEOLABS LIMITED (Ref4630.633102) Page 1 of 1
Authorised Signatories: � J R Masters (Qual Mgr) � C F Wallace (Tech Mgr) � G J Corio (Tech Mgr) [X] J Sturges (Tech Mgr) � S Burke (Snr Tech) GEOLABS®
Client: Vertase FLI Limited, Number One, Middle Bridge Business Park, Bristol Road, Portishead BS20 6PN
5 10 15 20 25 30
1.50
1.55
1.60
1.65
1.70
Moisture Content (%)
Dry
De
nsity
(Mg
/m³)
0% air voids
5% air voids
10% air voids
BS1377 : Part 4 : 1990
Moisture Content / Dry Density Relationship
Trial Pit No: TB 80 Description:
Grey silty CLAY with rare fine gravel
BS1377 : Part 4 : Clause 3.5.4.1 : 1990 4.5 kg Compaction Test
Sample Preparation: Material was air dried. Single sample
No particles were removed
Particle Density: 2.67 (measured by small pyknometer method)
Material Retained
on 20 mm test sieve: 0 %
on 37.5 mm test sieve: 0 %
Maximum Dry Density 1.68 Mg/m³
Optimum Moisture Content 21 %
Checked and Project Number:
Approved GEO / 16683
Initials: Project Name: GEOLABS ®
JS 907BRI
Date:28/03/2011
Test Report by GEOLABS Limited Bucknalls Lane, Garston, Watford, Hertfordshire, WD25 9XX © GEOLABS LIMITED (Ref4630.633160) Page 1 of 1
Authorised Signatories: � J R Masters (Qual Mgr) � C F Wallace (Tech Mgr) � G J Corio (Tech Mgr) [X] J Sturges (Tech Mgr) � S Burke (Snr Tech) GEOLABS®
Client: Vertase FLI Limited, Number One, Middle Bridge Business Park, Bristol Road, Portishead BS20 6PN
5 15 25 35
1.40
1.50
1.60
1.70
Moisture Content (%)
Dry
De
nsity
(Mg
/m³)
0% air voids
5% air voids
10% air voids