Upload
others
View
2
Download
0
Embed Size (px)
Citation preview
IN THE UNITED STATES DISTRICT COURT FOR THE EASTERN DISTRICT OF ARKANSAS
HTTLE R-0€K DIVISION
MARLON BLACKWELL ARCHITECTS, P.A.
~ .. , FILED
U.S. DISTRICT COURT • EASTERN DISTRICT ARKANSAS
DEC 2 0 2019
JAMES W. McCORMACK, CLERIC
By: ~a?-:@.CLERK
Plaintiff, This case assigned to District Judge ~ and to Magistrate Judge VolP"-'
V.
HBG DESIGN, INC.; SARACEN DEVELOPMENT, LLC; and JOHN LANE BERREY in his official capacity as Chairman of the Quapaw Tribal Business Committee
Defendants.
Case No. J,{: /'f-CV'..-'f~5-J<.G0
COMPLAINT
* * * JURY TRIAL DEMANDED * * *
Plaintiff Marlon Blackwell Architects, P.A. brings this action for permanent injunctive
relief and damages for copyright infringement, tortious business interference, breach of contract,
and unjust enrichment.
NATURE OF THE CASE
1. In 2018 and early 2019, Plaintiff Marlon Blackwell Architects, P.A. ("MBA"), an
internationally recognized and award-winning architectural design firm, performed a substantial
amount of architectural design work for the Quapaw Nation's Saracen Casino Resort project in
'
Case 4:19-cv-00925-KGB Document 1 Filed 12/20/19 Page 1 of 55
Pine Bluff, Arkansas. Another architectural firm, Defendant HBG Design, Inc. ("HBG"), was
brought on to assist with the project. The Quapaw Nation agreed to pay MBA and HBG an
architectural fee of 6% of the project's overall budget. Based on that, MBA and HBG agreed to a
roughly 35% and 65% split of all net architectural fees on the project. But instead of honoring
these agreements, HBG and the Quapaw Nation have stolen MBA's copyright-protected
architectural designs for that project, and refused to pay MBA what it is owed for its work on the
project. To facilitate this misappropriation, HBG poisoned MBA's relationship with the Quapaw
Nation by telling falsehoods to tribal Chairman John Lane Berrey, causing MBA to be removed
from the Saracen Casino Resort project. The Defendants are continuing to use those copyright
protected designs without MBA's authorization, and without crediting MBA for its authorship of
them. MBA is bringing this lawsuit to hold them accountable for their wrongful and unlawful acts.
PARTIES AND JURISDICTION
2. Marlon Blackwell Architects, P.A. ("MBA") is an architectural firm having its
principal office in Fayetteville, Washington County, Arkansas. Its principal architect is Marlon
Blackwell. It is a Professional Association organized under the laws of Arkansas.
3. HBG Design, Inc., formerly known as Hnedak Bobo Group, Inc., is a corporation
organized under the laws of Tennessee. It advertises that it does "hospitality design," which means
it designs hotels, restaurants, and spas. HBG's principal office is located in Memphis, Shelby
County, Tennessee. Its registered agent for service of process in Arkansas is CT Corporation
System, 124 W. Capitol Ave., Ste. 1900, Little Rock, AR 72201. HBG is registered to do business
in Arkansas as a foreign corporation. It regularly transacts millions of dollars with Arkansas
residents, with businesses organized pursuant to the laws of Arkansas, or for Arkansas architectural
projects.
2
Case 4:19-cv-00925-KGB Document 1 Filed 12/20/19 Page 2 of 55
4. Saracen Development, LLC is a limited liability company organized under the laws
of Arkansas, having a principal place of business in Pine Bluff, Arkansas. The Quapaw Nation
expressly authorized the creation of Saracen Development, LLC, in order for the LLC "to own,
finance, manage, and operate the [Saracen] Casino." See Quapaw Nation Resolution No. 061019-
A. The Quapaw Nation has also expressly waived tribal sovereign immunity in connection with
the creation and operation of the Saracen Development, LLC. See Quapaw Nation Resolution No.
060519-A. Saracen Development, LLC does not enjoy any sovereign immunity. It is an Arkansas
created limited liability company, organized as a distinct legal entity under state law, with only
one organizing officer: Attorney Alex Gray of Little Rock, Arkansas. This for-profit entity's
purpose is to maximize revenue from Arkansas residents who are or will be gaming at the Saracen
Casino. It is a wholly-owned subsidiary of the Downstream Development Authority of the
Quapaw Nation.
5. John Lane Berrey is the duly elected Chairman of the Quapaw Tribal Business
Committee, which is the elected legislative body of the Quapaw Nation. The Quapaw Nation is
geographically situated inside the state of Oklahoma. In his official capacity, Chairman Berrey is
responsible for management of tribal government and oversight of tribal business, among other
things. Notwithstanding whatever tribal sovereign immunity the Quapaw Nation may enjoy from
suits for damages, Chairman Berrey and his successors in office may nevertheless be sued in their
official capacities for injunctive relief. See Michigan v. Bay Mills Indian Community, 572 U.S.
782, 796 (2014); Fed. R. Civ. P. 25(d). Chairman Berrey is being sued only for injunctive relief
in his official capacity as Chairman, and not for damages in his individual capacity.
3
Case 4:19-cv-00925-KGB Document 1 Filed 12/20/19 Page 3 of 55
6. Federal question jurisdiction is proper in this Court under 28 U.S.C. § 1331, as this
Court has original jurisdiction of all civil actions arising under the federal Copyright Act, 17 U.S.C.
§§ 101 et seq.
7. Under 28 U.S.C. § 1367(a), this Court has supplemental jurisdiction over all state
law claims arising from the same operative facts.
8. Venue is proper in this district under 28 U.S.C. § 1391(b)(2) because a substantial
part of the events or omissions giving rise to the claim occurred, or a substantial part
of property that is the subject of the action is situated, within this district. Venue is also proper in
this district under 28 U.S.C. § 1400(a) because all defendants or their agents have committed, and
are committing, acts of infringement of MBA's copyrighted works in this district, and have
established and regularly conducted business in Arkansas.
FACTS
9. Plaintiff MBA is an architectural services firm. MBA's founder and principal
architect is Marlon Blackwell. Mr. Blackwell is a Fellow of the American Institute of Architects
("F AIA") whose work is internationally known and respected. He is also the E. Fay Jones Chair
in Architecture and a Distinguished Professor in the Fay Jones School of Architecture and Design
at the University of Arkansas. He served as architecture department head from 2009 to 2015 and
was named among the "30 Most Admired Educators" by Designlntelligence in 2015.
10. In 2016, MBA was declared the No. 1 design firm in the United States by Architect
Magazine.
11. On December 11, 2019, Marlon Blackwell was awarded the American Institute of
Architects ("AIA") Gold Medal, which is the organization's highest honor, recognizing those
whose work has had an enduring impact on the theory and practice of architecture. "Every Marlon
4
Case 4:19-cv-00925-KGB Document 1 Filed 12/20/19 Page 4 of 55
Blackwell design is a new lesson in the transformative ability of architecture to reveal the
uniqueness of every site and give meaning to any program, to achieve an expressive clarity in
strong and simple forms," wrote Julie V. Snow, FAIA, in a letter supporting Blackwell's
nomination. "In every way, across all measures, the work raises our expectations for our own
architecture and teaches us that it is possible to exceed what appears to limit us."
12. In 2019, MBA's design for Shelby Farms Park was awarded the National Design
Award by AIA.
13. In 2014, Mr. Blackwell was named a United States Artists Ford Fellow in
Architecture and Design. In 2012, Mr. Blackwell received the Architecture Prize from
the American Academy of Arts and Letters.
14. Thirteen projects by MBA have been recognized with national awards by the AIA,
including the AIA Honor Awards for Vol Walker Hall/Steven L. Anderson Design Center at the
University of Arkansas (2018), the Crystal Bridges Museum Store at Crystal Bridges Museum of
American Art (2015), the Little Rock Creative Corridor (2014), St. Nicholas Eastern Orthodox
Church (2013), and the Ruth Lilly Visitors Pavilion at the Indianapolis Museum of Art (2012), as
well as AIA Housing Awards for Graphic House (2017) and L-Stack House (2008). MBA has an
international design reputation through recognition of its work in many publications, including
architectural design journals and books. The firm has received more than 120 design awards,
including state, regional, national and international awards.
15. MBA and Mr. Blackwell have worked with the Quapaw Nation in the past and
enjoyed an excellent business relationship.
16. Mr. Blackwell's primary connection and goodwill was with John Berrey, the
Chairman of the Quapaw Tribal Business Committee, with whom MBA and Mr. Blackwell have
5
Case 4:19-cv-00925-KGB Document 1 Filed 12/20/19 Page 5 of 55
worked on architectural projects dating back to before 2016. MBA did many different architectural
projects with the Quapaw Nation, including the John Berrey Wellness Center, an events center,
and a VIP entrance and VIP lounge for the Downstream Casino and Resort.
17. This past proven business relationship was built upon trust, and was excellent. For
example, in 2016 Chairman Berrey told Mr. Blackwell that "We love you, care about you and want
a long relationship."
18. In 2018, more than 85,000 petition signatures were collected to place Arkansas
ballot initiative Issue 4 on the ballot for consideration by the voters of the entire state, to authorize
gaming casinos in Crittenden, Garland, Pope and Jefferson Counties. A vote of "yes" to the
initiative would permit the Arkansas Racing Commission to authorize one casino in each of these
four counties. The cost of gathering such signatures was estimated at more than $1,416,481.
Attorney Alex Gray filed the initiative. Mr. Gray is also Saracen Development, LLC's sole
organizing officer.
19. The primary proponent of Issue 4 was the Downstream Development Authority of
the Quapaw Nation, which reportedly contributed at least $3,853,353.50 in support of Issue 4.
Arkansas campaign finance reports indicate the total amount spent advocating in support of Issue
4 was more than $10,209,129.15.
20. More than one year in advance of the election, Chairman Berrey personally
contacted Mr. Blackwell requesting architectural plans and conceptual designs of a proposed
gaming resort in Pine Bluff, Arkansas in order to "sell the deal" to the voters of Arkansas.
Chairman Berrey gave numerous explicit assurances to MBA and Mr. Blackwell that MBA would
do the architectural work on the project.
6
Case 4:19-cv-00925-KGB Document 1 Filed 12/20/19 Page 6 of 55
21. Over many weeks and months, MBA adopted an "all hands on deck" approach.
MBA invented and created copyright-protected inspirational images, architectural drafts,
architectural exterior and interior plans, computer line drawings, and design expertise to formulate
a unified material and formal logic having unique and never-before-seen kind of architectural
design for the proposed casino.
22. On July 6, 2017, Chairman Berrey declared that MBA's architectural ideas,
drawings, and renderings were critical and that he needed such work to be readied and prepared
before an important meeting that would occur ten days later in Little Rock. At that time, Chairman
Berrey stated the tribe did not have an actual site where the casino would go in Jefferson County,
but he again assured MBA that it would be the firm to do the architectural plans and design for the
casino in the event the voters passed Issue 4. No other architectural firm was being considered for
the project at that time.
23. MBA provided to Chairman Berrey a substantial volume of images, plans,
renderings, and architectural designs, and Chairman Berrey responded very favorably on July 13,
201 7. Over the next several days, MBA prepared and provided to Chairman Berrey a digital
presentation having designs, images, drawings, and architectural renderings that were unique to
MBA' s architectural inspiration and expertise. Chairman Berrey reported to MBA that the
meetings were going well and "our friends loved your vision." On information and belief, the use
of MBA' s architectural inspirations, designs, architectural visualizations, and renderings were
essential to the success of the meeting with the original investors and interested parties who later
provided substantial support in furtherance of Issue 4 as well as funding for the ultimate project.
24. MBA's original vision for the architecture of the new casino was dramatic and
constituted a substantial departure from other casinos around the country. The roof and tower had
7
Case 4:19-cv-00925-KGB Document 1 Filed 12/20/19 Page 7 of 55
an exceptionally unique design comprising a unified material and formal logic theory and
structure.
25. In August 2018, Chairman Berrey again contacted MBA with additional requests
to further develop and update the earlier Pine Bluff casino renderings, and to discuss moving
forward with the project in the event Arkansas voters passed Issue 4. Prior to August 2018, MBA
had already conducted design studies and initial concept reviews, submitted renderings, and had
meetings to discuss updates.
26. In September 2018, Chairman Berrey personally met with Mr. Blackwell to go over
the future direction of the project in the event the voters passed Issue 4. During that meeting,
Chairman Berrey repeatedly assured Mr. Blackwell that MBA would be the architectural firm to
handle the entire project. At that meeting and in the weeks following, Chairman Berrey requested
additional renderings, including even more aerial and interior renderings.
27. Polling conducted by the Talk Business & Politics-Hendrix Poll in September
2018 indicated only 41 % of the sampled voters supported Issue 4.
28. In the months leading up to the election, MBA prepared even more extensive
designs, drawings, concept renderings, and information in September 2018, to show potential
investors and the voters of Arkansas in support of Issue 4 and the Pine Bluff casino and resort.
Some of those materials are shown below:
8
Case 4:19-cv-00925-KGB Document 1 Filed 12/20/19 Page 8 of 55
VIEWS: AERIAL
Vl[W SUMMARY:: SUNSCT
VIEWS: ENTRY DRIVE
Vl(W SUMM AR Y: NtGKT
11 ..... , ... ,
''"""'"' !1!•!•111111, 1!!!!!111!1
1!!!!!!!!1+! Ill!!!!!!!!!
11111!!!!!!'! ltlli!I •
29. In advance of the election, MBA provided to Chairman Berrey more renderings
used by proponents of Issue 4 to advance the cause. Such renderings were widely distributed to
the press and the public to advertise and aggressively promote the benefits of the casino. Some of
the renderings provided to Chairman Berrey are shown below:
9
Case 4:19-cv-00925-KGB Document 1 Filed 12/20/19 Page 9 of 55
10
Case 4:19-cv-00925-KGB Document 1 Filed 12/20/19 Page 10 of 55
30. In late October 2018, in the weeks prior to the election, Mr. Blackwell asked
Chairman Berrey how the promoters and others were enjoying MBA's architectural designs,
renderings and images depicting the future casino. Chairman Berrey responded that "they love
them." In reply, Mr. Blackwell wished Chairman Berrey luck in the upcoming election, to which
Chairman Berrey responded "Thank you bro, I'm so glad you['re] part of it."
31. The voters narrowly changed the Arkansas Constitution by passing Issue 4 on
November 6, 2018, with 54% of the voters approving the initiative.
32. On November 7, 2018, when the vote count was official, Mr. Blackwell
congratulated Chairman Berrey, who responded "I'm so happy brother." Soon thereafter, the two
set up a meeting to discuss moving forward with the project and to further create plans to begin
construction, since time was of the essence.
33. On November 30, 2018, Chairman Berrey sent a photo of the headstone for Chief
Saracen to declare the name of the casino, to which Mr. Blackwell responded "Thank you. Let's
honor him well."
34. Chairman Berrey explicitly authorized MBA to begin working as the architectural
firm to design the entirety of the Saracen Casino Resort. MBA mobilized its architects, assistants,
and even hired additional staff to proceed in a time-of-the-essence project, as Chairman Berrey
had declared he wanted the entire construction project to be completed in less than eleven months.
This time line meant MBA' s initial design drawings, and its more refined construction drawings
and plans, would need to be expedited and completed in less than six months.
11
Case 4:19-cv-00925-KGB Document 1 Filed 12/20/19 Page 11 of 55
35. Over the next several months, MBA met with many members of the Quapaw
Nation, the directors of the casinos, the construction team, investors, financiers, financial advisors,
and planners in furtherance of the Saracen Casino Resort project.
36. In December 2018, MBA worked with the Quapaw Nation to identify and actively
interview and assist Chairman Berrey in the selection of construction firms, electrical engineers,
structural engineers, and other potential additional architectural firms who could assist in the
preparation of engineering and construction site plans.
37. In December 2018 and January 2019, MBA worked extensively and exhaustively
on an accelerated timeline, including working over the holidays in advance of a kickoff meeting
held January 9, 2019. MBA prepared scoping for the project, roof drawings and design, modeling,
lobby designs, mechanical designs, structural designs and coordination, mechanical room
drawings and designs, area estimates, consultant directions, revised renderings, Revit BIM
repositories for a collaborative approach, and many other essential elements to the architecture and
progress towards construction. During these months, MBA and its team worked cooperatively
with many people as the lead.
38. During December 2018 and January 2019, MBA discussed with Chairman Berrey
and other authorized representatives on this project the efficiencies that could be earned in working
with an additional architecture firm. MBA identified three potential architecture firms, and
recommended the Memphis, Tennessee design firm HBG. But for MBA, HBG would not have
been considered.
39. On December 19, 2018, HBG was selected to assist in the rendering of construction
drawings; but Chairman Berrey required MBA to retain primary responsibility in order to retain
12
Case 4:19-cv-00925-KGB Document 1 Filed 12/20/19 Page 12 of 55
the integrity of the original design, which was by this time very well known to all investors and to
the voters of Arkansas.
40. MBA was explicitly engaged to preserve the "Design Intent." To streamline the
process, a Responsibility Matrix was created and agreed to by MBA and HBG. MBA provided
HBG with documents identifying responsibilities for each party. The Responsibility Matrix
specifically outlined in Exhibit A to this Complaint, is generally outlined below:
RESPONSIBILITY MATRIX 1809- Saracen Casino Resort 2019.01.03
Throughout the project Marlon Blackwell Architects will have primary responsibility for the Design Intent of all Exteriors, Public Facing Spaces, including Public & Guest Space Interiors. MBA will provide oversite of the development of the project through phases marked as Secondary. MBA will identify critical design elements that which will have a greater continued involvement of the MBA team throughout the project. MBA will review critical elements and details to ensure adherence to Design Intent, but the details will be developed by HBG. HBG Design will provide support for program blocking and analysis, and production support where required by MBA. HBG will have primary responsibility for the functional arrangement and operational coordination of all back of house facilities. HBG will moreover have primary responsibility for Coordination and Documentation, including both drawings and specifications, and Construction Administration.
41. In furtherance of this forward-looking collaboration and sharing of responsibilities,
MBA provided to HBG assistants and architects its plans, drawings, sketches, schematics,
footprints, renderings, and many other essential work product, including architectural computer
files in .pdfformat, .rvt [for Revit BIM], .ai, .psd, .ls, .eml, and substantially complete architectural
schematic design plans for the Saracen Casino. Throughout this project, HBG had direct access
to MBA' s copyrighted architectural works and designs.
42. MBA worked closely with HBG representatives in order to design the overall
project and formalize the contractual relationship between HBG and the Downstream
Development Authority of the Quapaw Nation.
13
Case 4:19-cv-00925-KGB Document 1 Filed 12/20/19 Page 13 of 55
43. A January 15, 2019 Initial Authorization Agreement between HBG and Chairman
Berrey is attached to this Complaint as Exhibit B. That agreement specifically requires HBG to
"coordinate with Marlon Blackwell Architects to develop the scope of services for the full services
Project." Under the Initial Authorization Agreement, MBA and HBG were to be paid $250,000
as an initial mobilization towards the substantial amount of work that would be performed over
the duration of the construction project. That agreement explicitly identified how the parties would
later enter into a "full-services Agreement in substantial similar form as AIA Document B 103-
2017 Standard form of Agreement Between Owner and Architect." The Initial Authorization
Agreement was executed by Paul H. Bell on behalf of HBG, and by Chairman Berrey on behalf of
the Quapaw Nation's Downstream Development Authority.
44. The project was identified with a complete "Cash Flow Schedule" for the
architectural professional fees, as calculated using a budget of $248,000,000 for the entire
construction project. (The project has recently been reported in Arkansas Business as a
$350,000,000 project). That Cash Flow Schedule is attached as Exhibit C to this Complaint. It
estimated total architectural fees for the project at 6.25% of cost of work, or $15,500,000. This
amount was exclusive of $1,945,000 in additional fees for other services including civil
engmeermg.
45. The Downstream Development Authority subsequently agreed to pay an
architectural fee of 6.0% of cost of work, but insisted that the fee be all-inclusive, including civil
engineering. An email from Chris Roper on behalf of the Downstream Development Authority
memorializing that agreement is attached as Exhibit D to this Complaint.
46. MBA and HBG agreed to split all net architectural fees for the duration of the
project 34.42% and 65.58%, respectively, according to a Schedule that is attached to this
14
Case 4:19-cv-00925-KGB Document 1 Filed 12/20/19 Page 14 of 55
Complaint as Exhibit E. Consideration for this agreed split was adequate, in that MBA was
contributing its copyrighted designs and nationally acclaimed architectural professional services,
which formed the Design Intent and foundation for the project. Additional consideration included
MBA' s efforts to support HBG in securing this contract, and MBA' s substantial work in reviewing
HBG's work on the project.
4 7. The fee-splitting agreement between MBA and HBG was memorialized and
confirmed by HBG through its authorized principal, Paul H. Bell, in an email that is attached to
this Complaint as Exhibit F ("Since we have come to agreement on the percentage of fee split,
can you fill out the deliverables that MBA anticipates providing?").
48. In response, MBA's Project Architect Kertis Weatherby itemized the deliverables
in a Work Split Matrix for the project, which is attached to this Complaint as Exhibit G. MBA
relied upon this delegation of duties and the professional fee-split agreement for the duration of
the project.
49. MBA was to have the primary role in all aspects as the Design Firm, and also to
assist HBG with the construction-type architecture aspects by reviewing HBG's work in order to
maintain the Design Intent of the project. MBA retained the ability to review HBG's work in order
to retain the integrity of its designs, which were the foundation upon which the architectural work
for the project was built.
50. HBG identified for MBA and all other parties a design schedule, demonstrating that
all professional architectural services rendered by either HBG or MBA was to be completed in less
than twelve months. That design schedule is attached to this Complaint as Exhibit H.
51. HBG only paid to MBA $100,000 as an initial payment to mobilize on the project,
which was from sums paid to HBG by Downstream Development Authority or its Arkansas limited
15
Case 4:19-cv-00925-KGB Document 1 Filed 12/20/19 Page 15 of 55
liability company, Saracen Development, LLC. HBG proceeded forward with the agreement of
sharing responsibilities and proceeds.
52. MBA worked extensively with HBG and Chairman Berrey, and created a
substantial volume of work in furtherance of the fast-paced timelines established by Chairman
Berrey and others connected with this project.
53. For example, in February 2019, MBA provided to Chairman Berrey a Plan B roof
line for the casino, and explored and offered affordable alternatives for the roof design in an effort
to stay within budget, which was reportedly shrinking due to economic factors beyond MBA' s
control.
54. On February 18, 2019, MBA had already created a substantial body of work and
was providing substantial guidance in working cooperatively with HBG. MBA created and
circulated various plans for roof design and other updates on the project. MBA had productive
teleconferences with Chairman Berrey and others working on the construction and planning of the
Saracen Casino as MBA was actively involved and was devoting substantial time and its resources
to the casino project.
55. On February 23, 2019, the Pine Bluff Commercial reported that the plans for the
Saracen Casino Resort were underway, and that the construction costs would be as much as $240
million dollars. In the same article, Chairman Berrey indicated the casino would have soft
openings prior to 2020.
56. On February 26, 2019, Mr. Blackwell checked in with Chairman Berrey and offered
compliments and congratulations to the team by stating "Our design team and the construction
team are working diligently together to get issues resolved and get the project in on budget while
16
Case 4:19-cv-00925-KGB Document 1 Filed 12/20/19 Page 16 of 55
maintaining design and functional integrity .... I am confident of our direction and getting the
project in line with expectations ... and yes this is fun! All the best and have a great day!"
57. In response, Chairman Berrey confirmed the excellent working relationship and
declared, "You made my day brother!"
58. Plaintiff worked extensively with HBG and Chairman Berrey from January through
March without problem or incident, and the project was proceeding in due course without delay or
problems.
59. On March 6, 2019, MBA attended a meeting with Chairman Berrey and the
directors working on the project, along with HBG and contractors. The information MBA
prepared for that meeting met all the previously identified budgetary requirements. MBA left that
meeting with the understanding that everything was going well and that the project was on target.
60. On March 8, 2019, as demonstrated by an article in the Pine Bluff Commercial
dated March 9, 2019, Chairman Berrey boasted to the public that the Saracen Casino project could
be completed in less than eleven months, as it only took ten months and twenty-six days to
construct the Downstream Casino and Resort in Oklahoma. Chairman Berrey declared his desire
to have the same short timeline with the Saracen Casino Resort in Pine Bluff. See
https://www .pbcommercial.com/news/20190309/casino-operator-outlines-pb-project-at-meeting
(last visited on December 20, 2019).
61. At that March 8 public meeting, Chairman Berrey explicitly touted MBA's
architectural designs and renderings. Those designs were unique and were created by MBA. The
following photo from that meeting was published with the Pine Bluff Commercial article. It clearly
depicts the same images identified at Paragraph 29 of this Complaint:
17
Case 4:19-cv-00925-KGB Document 1 Filed 12/20/19 Page 17 of 55
l!! BUY PHOTO • HIDE CAPTION
John Berrey, a Quapaw Tribe chief and chairman of Downstream Media Group, speaks at a Thursday meeting at the Pine Bluff Convention Center. · Pine Bluff Commercial/Luke Matheson
62. At all times relevant to these claims, MBA worked in good faith and was
cooperative with HBG in full satisfaction of its obligations under its agreements with HBG and
the defendants. MBA was also the exclusive source of the foundational intellectual property for
the Saracen Casino project.
63. At all times relevant to these claims, MBA had completed a substantial amount of
work to get this project finalized, and the casino was on track to be completed within reasonable
timeframes and within the original budget.
64. At all times relevant to these claims, MBA was assisting HBG and was a substantial
contributor to the long-term success of the project.
65. Something happened prior to March 9, 2019 that caused Chairman Berrey to
become angry and agitated, and on information and belief, the information that upset Chairman
Berrey was false. On information and belief, HBG representatives-including HBG's principal
18
Case 4:19-cv-00925-KGB Document 1 Filed 12/20/19 Page 18 of 55
Rick Gardner-misled and misinformed Chairman Berrey about MBA' s conduct and role in the
Saracen Casino Resort project.
66. On information, HBG provided false information to Chairman Berrey to exclude
MBA from continued work in order to avoid paying the agreed 34.42% fee split.
67. On March 13, 2019, MBA was excluded from an important meeting involving HBG
and other members of the team. Two days later, Chairman Berrey suggested to Mr. Blackwell that
''we should part ways on this project." Despite Mr. Blackwell's continuous attempts after that to
learn what had gone wrong and how to mend the relationship, those efforts were to no avail. On
March 26, 2019, Chairman Berrey informed Mr. Blackwell that after "talking to all of the team"
he could not see MBA "returning in the current capacity."
68. On information, an HBG representative later bragged to a disinterested witness
about "schmoozing the Indians" in order to force MBA off of this project in order to save the
agreed 34.42% fee split.
69. Notwithstanding the express agreement with MBA, HBG stopped working with
MBA and has not paid to MBA its 34.42% share.
70. Notwithstanding the express agreement with MBA, HBG continued using all plans
and carried forward with the entire project without compensation to MBA.
71. MBA created the original architectural plans and design for this casino.
72. MBA was authorized by Chairman Berrey to create these unique designs, which
are the product of Mr. Blackwell and many other members of MBA' s architectural team. They
are original and substantial contributions to architecture, and are the product of many hours of
work and years of expertise. Such intellectual property and drawings and designs are copyrighted
and protected by federal law.
19
Case 4:19-cv-00925-KGB Document 1 Filed 12/20/19 Page 19 of 55
73. MBA reached express agreements with both HBG and other defendants to perform
high quality professional architectural services and designs, among an enormous amount of other
substantial work, as demonstrated by the Responsibility Matrix, the fee sharing schedules, the
timeframe for professional fees for the project that was due and legally owing to Plaintiff by HBG,
and the continued work MBA did to develop this project by freely sharing its work product with
HBG.
74. At all times MBA operated in good faith. MBA introduced HBG to Chairman
Berrey to expedite this project, given the short timelines ofless than one year to do this substantial
job. Yet HBG has apparently elected to proceed forward in making derivative works from MBA' s
intellectual property, in violation of copyright laws and of the parties' express agreement to share
the fees for the entire project on a 34.42% / 65.58% split.
75. HBG was brought into the project to assist MBA in the implementation ofMBA's
designs for this casino. HBG continued working with MBA's designs and has made derivative
works without MBA' s authorization.
76. HBG continued forward on the project in willful disregard to its agreement to split
the professional fees on this project.
77. HBG continued forward on the project in willful disregard of the norms of
architectural practices.
78. HBG then claimed original authorship to the project in submitting to the Pine Bluff
Planning Commission design plans dated July 15, 2019 having exclusive authorship and stamping
from Paul Bell and HBG Design, Inc. stamps, making no reference to MBA. In such plans, the
work by MBA is retained in all material respects.
20
Case 4:19-cv-00925-KGB Document 1 Filed 12/20/19 Page 20 of 55
79. In communications updating the public as to the status of the project, on December
2, 2019, HBG released to the public press images depicting the Saracen Casino and HBG claimed
exclusive authorship to the iconic designs created by MBA, and such information was republished
to the public via Arkansas Business in an article that referenced he current status of the project.
See https:/ /www. arkansasbusiness.corn/article/ 128983/casino-expansion-upside-includes-hotels
tourism-boost (last visited on December 13, 2019).
An architectura l rendering of the $350 million Saracen Casino Resort in Pine Bluff. Construction is expected to be completed by the end of 2020 . (Saracen Casino/HBG Design of Memphis)
80. HBG continued forward on the project and made only insubstantial changes to
MBA' s designs, keeping the main features of the design that were touted by Chairman Berrey and
all proponents in support of Issue 4.
81 . HBG elected to cut costs and make some functional changes; however, HBG
elected to retain all material aspects of MBA' s design, preserving the images, architectural drafts,
architectural exterior and interior plans, computer line drawings, and design expertise to formulate 21
Case 4:19-cv-00925-KGB Document 1 Filed 12/20/19 Page 21 of 55
a unified material and formal logic having unique and never-before-seen kind of architectural
design for a proposed casino.
82. HBG has misappropriated MBA's original designs and architectural works for its
own benefit and is now advertising its work to the general public.
83. By its conduct described above, HBG violated Rule 1.402 of the AIA's Code of
Ethics and Professional Conduct, which states that "Members shall not engage in conduct
involving wanton disregard of the rights of others."
84. By its conduct described above, HBG has violated Rule 2.106 of the AIA's Code
of Ethics and Professional Conduct, which states that "Members shall not counsel or assist a client
in conduct that the architect knows, or reasonably should know, is fraudulent or illegal."
85. By its conduct described above, HBG has violated Ethical Standard 3.3 of the
AIA's Code of Ethics and Professional Conduct, which states that "Members should be candid and
truthful in their professional communications and keep their clients reasonably informed about the
client's projects."
86. By its conduct described above, HBG has violated Ethical Standard 4.1 of the
AIA's Code of Ethics and Professional Conduct, which states that "Members should pursue their
professional activities with honesty and fairness."
87. By its conduct described above, HBG has violated Rule 4.103 of the AIA' s Code
of Ethics and Professional Conduct, which states that "Members speaking in their professional
capacity shall not knowingly make false statements of material fact."
88. By its conduct described above, HBG has violated Rule 5.101 of the AIA's Code
of Ethics and Professional Conduct, which states that "Members shall treat their colleagues ...
with mutual respect, and provide an equitable working environment."
22
Case 4:19-cv-00925-KGB Document 1 Filed 12/20/19 Page 22 of 55
89. By its conduct described above, HBG has violated Ethical Standard 5.3 of the
AIA' s Code of Ethics and Professional Conduct, which states that "Members should build their
professional reputation on the merits of their own service and performance and should recognize
and give credit to others for the professional work they have performed."
90. By its conduct described above, HBG has violated Rule 5.301 of the AIA's Code
of Ethics and Professional Conduct, which states that "Members shall recognize and respect the
professional contributions of their ... professional colleagues, and business associates."
91. Marlon Blackwell received the highest award available to an architect, the AIA
Gold Medal. HBG' s conduct stands opposite the ethics and ideals of architecture and business.
CAUSES OF ACTION
COUNT ONE - COPYRIGHT INFRINGEMENT against all Defendants
92. MBA owns all right and title to MBA-E _ 20181130 scr preliminary scoping, having
registration No. VA 2-172-502, and MBA-B _ 20170715 scr concept, having registration No. VA
2-172-372 (the "Registrations"). MBA has applied for but has not yet received the Certificate of
Registration for numerous other copyrighted works connected to the Saracen Project.
93. Defendants, by virtue of their continued reproduction, distribution, displaying, and
performance of MBA' s protected architectural and design works, including those described by the
Registrations, and by their making of derivative works from the same, are infringing the exclusive
rights of MBA to these architectural and design works.
94. Only MBA has rights to reproduce, distribute, display, or perform these protected
architectural and design works, or to make derivative works therefrom.
23
Case 4:19-cv-00925-KGB Document 1 Filed 12/20/19 Page 23 of 55
95. Defendants are infringing upon MBA's exclusive rights, and Defendants are not
authorized to use, reproduce, distribute, display, perform, or make derivative works from MBA's
protected architectural or design works.
96. MBA has been damaged by such conduct and is entitled to an award of statutory
damages or actual damages, upon MBA' s election prior to trial.
COUNT TWO - TORTIOUS BUSINESS INTERFERENCE against HBG
97. MBA had a valid contractual relationship and/or business expectancy with the
Quapaw Nation and Saracen Development, LLC regarding the Saracen Casino Resort project.
98. HBG had knowledge of that contractual relationship and/or business expectancy.
99. HBG induced or caused a disruption or termination of that contractual relationship
and/or business expectancy by intentional and improper interference.
100. HBO's disruption or termination of that contractual relationship and/or business
expectancy was a proximate cause of damage to MBA.
COUNT THREE-BREACH OF CONTRACT against HBG
101. MBA and HBG entered into an agreement and contract which could be performed
within one year and as memorialized and detailed through numerous communications and written
schedules, itemized fee splitting agreements, and detailed allocation of collaborative work
responsibilities, all of which were authorized and made using an authorized agent for HBG and
MBA.
102. The agreements were supported by adequate consideration comprising not only the
compensation schedules but also the implied license to continue to develop derivative works from
MBA' s foundational designs and other copyrighted works.
24
Case 4:19-cv-00925-KGB Document 1 Filed 12/20/19 Page 24 of 55
103. The agreement required HBG to perform or not to perform certain acts, including
payment to MBA of 34.42% of all net architectural fees for the duration of the Saracen Casino
Resort project, together with other potential architectural fees generated from this project.
104. MBA did what the agreement and contract required of it.
105. HBG did not do what the agreement and contract required of it.
106. HBG's breach of the agreement and contract caused damage to Plaintiff.
107. Such damage is easily and readily identifiable by the documents provided with this
complaint and as exchanged between the parties, and the direct calculation establishes a sum
certain of not less than $4,452,227.00.
COUNT FOUR - UNJUST ENRICHMENT against HBG and Saracen Development, LLC
108. MBA provided services to HBG and Saracen Development, LLC, who received the
benefit of such services.
109. The circumstances were such that MBA reasonably expected to be paid the value
of such services by HBG and Saracen Development, LLC.
110. HBG and Saracen Development, LLC were aware that MBA was providing such
services with the expectation of being paid, and accepted the services.
111. HBG and Saracen Development, LLC have not paid MBA the reasonable value of
such services received by HBG and Saracen Development, LLC.
COUNT FIVE - PERMANENT INJUNCTION against all Defendants
112. Plaintiff seeks a permanent injunction against Defendants from use of the entire
architectural and design works created by MBA for the Saracen Casino Resort project, and from
making any further derivative works therefrom.
25
Case 4:19-cv-00925-KGB Document 1 Filed 12/20/19 Page 25 of 55
113. Plaintiff seeks an order directing Defendants to account for all instances of their
efforts to sell, transfer, market, or disclose to third parties the architectural and design works that
form the subject matter of this controversy.
114. Plaintiff seeks an order directing Defendants to destroy and not retain or again use
without permission all copies of such architectural and design works owned by Plaintiff.
115. Plaintiff seeks an order directing Defendants to revisit every document associated
with the Saracen Project and insert the following declaration to avoid any misperception that HBG
is an owner, author, or creator of the designs and works connected to the Saracen Casino and
Resort as follows: "This work is derivative of copyrights owned by Marlon Blackwell
Architects, P.A."
PRAYER FOR RELIEF
116. MBA is entitled to have and recover judgment against HBG and Saracen
Development, LLC in a sum not less than $4,452,227.00.
117. MBA is entitled to a permanent injunction against all Defendants prohibiting them
from using the architectural and design works MBA created for the Saracen Casino Resort project,
and from making any further derivative works therefrom.
118. MBA is entitled to an award of damages for copyright infringement pursuant to
statute, to be ascertained at trial at the election of MBA.
119. MBA demands a trial by jury.
Wherefore, Plaintiff Marlon Blackwell Architects, P.A. prays this Court award it
permanent injunctive relief against all Defendants, and enter judgment in its favor against
Defendants HBG Design, Inc. and Saracen Development, LLC in a sum not less than $4,452,227,
26
Case 4:19-cv-00925-KGB Document 1 Filed 12/20/19 Page 26 of 55
together with interest as allowed by law and the costs of this action including a reasonable attorney
fee, and award it all other appropriate relief.
By: Mark Murphey Henry, rk. Bar No. 97170 Joseph Hall, Ark. Bar o. 2012191 ROSE LAW FIRM, a Professional Association P.O. Box. 4800 Fayetteville, AR 72702 Telephone: (479) 695-1330 Fax: (479) 695-1332 [email protected] [email protected]
and
Jack East III, Ark. Bar No. 75036 1100 N. University Ave., Ste. 140 Little Rock, AR 72207 Telephone: (501) 372-3278
Counsel for Plaintiff
27
Case 4:19-cv-00925-KGB Document 1 Filed 12/20/19 Page 27 of 55
MARLON BLACKWELL ARCHITECTS
RESPONSIBILITY MATRIX 1809 - Saracen Casino Resort 2019.01.03
42 East Center Street
Fayetteville, Arkansas 72701
P 479.973.9121
marlonblackwell.com
Throughout the project Marlon Blackwell Architects will have primary responsibility for the Design Intent of all Exteriors, Public Facing Spaces, including Public & Guest Space Interiors. MBA will provide oversite of the development of the project through phases marked as Secondary. MBA will identify critical design elements that which will have a greater continued involvement of the MBA team throughout the project. MBA will review critical elements and details to ensure adherence to Design Intent, but the details will be developed by HBG. HBG Design will provide support for program blocking and analysis, and production support where required by MBA. HBG will have primary responsibility for the functional arrangement and operational coordination of all back of house facilities. HBG will moreover have primary responsibility for Coordination and Documentation, including both drawings and specifications, and Construction Administration.
• Understanding that this project will not move in a traditional phase schedule, we will still refer to phase levels in our narrative below, in order to rely on standard understandings of the level of development.
Definitions: Primary:
Secondary:
Support:
Responsible for guiding the direction and schedule of progress, as well as establishing the standards of deliverables. Responsible for supporting the capacity of the Primary Architect according to the standards above. [MBA to develop selected portions, oversee design intent; HBG to review for expertise (program, compliance, etc) and to provide supplemental production capacity.] Responsible for guiding the direction and schedule of progress, as well as establishing the standards of deliverables.
Sitg (Parking, RV Park, Q Store)
• MBA: Concept+ Design Intent Primary/ SD Secondary I DD Secondary I CD Secondary I CA Support • HBG: Program Primary/ SD Primary/ DD Primary/ CD Primary/ CA Primary
Outbuildings (Warehouse, Daycare, Fire, EMS+Police, Q Store)
• MBA: Concept+ Design Intent Primary/ SD Secondary I DD Secondary I CD Secondary I CA Support • HBG: Program Primary/ SD Primary/ DD Primary/ CD Primary/ CA Primary
outdoor Events
• MBA: SD Primary/ DD Primary/ CD Secondary/ CA Support • HBG: SD Secondary I DD Secondary/ CD Primary/ CA Primary
EXHIBIT ,~
Case 4:19-cv-00925-KGB Document 1 Filed 12/20/19 Page 28 of 55
Main Facility
Core/ Shell
• MBA: SD Primary/ DD Primary/ CD Secondary I CA Support • HBG: SD Secondary I DD Secondary I CD Primary/ CA Primary
Gaming (Floor/ Table Games/ EGM / Poker/ VIP)
• MBA: SD Primary/ DD Equals/ CD Secondary I CA Support • HBG: SD Secondary/ DD Equals/ CD Primary/ CA Primary
Food + Beverage (Kitchens / Dining Areas / Walk-ins)
• Front of House o MBA: SD Primary/ DD Primary/ CD Secondary I CA Support o HBG: SD Secondary/ DD Secondary I CD Primary/ CA Primary
• Back of House o MBA: SD Secondary/ DD Secondary I CD Secondary I CA Support o HBG: SD Primary/ DD Primary/ CD Primary/ CA Primary
Hotel (Guest Services/ Guest Rooms/ Amenities/ Retail/ VIP)
• MBA: SD Primary/ DD Equals/ CD Secondary I CA Support • HBG: SD Secondary I DD Equals/ CD Primary/ CA Primary
Events (Meeting Spaces/ Banquet Hall / Indoor Venue I Gaming Stage)
• MBA: SD Primary/ DD Primary/ CD Secondary I CA Support • HBG: SD Secondary/ DD Secondary I CD Primary/ CA Primary
RESPONSIBILITY MATRIX Saracen Casino Resort
2018.01.03
Administration (Compliance/ DDA / Directors/ Finance/ HR/ Marketing + Promotions/ Employee Services)
• MBA: Concept Primary/ SD Secondary I DD Secondary I CD Secondary I CA Support • HBG: Program Primary/ SD Primary/ DD Primary/ CD Primary/ CA Primary
Technical Operations (Cage/ Surveillance/ Security/ IT)
• MBA: Concept Primary/ SD Secondary I DD Secondary I CD Secondary I CA Support • HBG: Program Primary/ SD Primary/ DD Primary/ CD Primary/ CA Primary
Physical Operations (Housekeeping/ Maintenance/ Warehouse I Shipping + Receiving/ Central Plant)
• MBA: Concept Primary/ SD Secondary/ DD Secondary I CD Secondary/ CA Support • HBG: Program Primary/ SD Primary/ DD Primary/ CD Primary/ CA Primary
PAGE 2 OF 10 MARLON BLACKWELL ARCHITECTS
Case 4:19-cv-00925-KGB Document 1 Filed 12/20/19 Page 29 of 55
Design Architect in Tandem with Architect of Record DRAFT Matrix of Responsibility and Deliverables
P = Prime Responsibility S = Support Role
EC= Elevator Consultant CW= Curtainwall Consultant
N = No Role N/A = Not Appl icable
CC= Code Consultant SV=Surveyor/Exi sting Conditions Analyst ZA=Zoning Attorney MEP = MEP Engineer MC= Measurement Consultant
Design Phase/ Activity Design Architect
MBA
Project Start-up I Due Diligence Phase
Client Conferences p
Project Document Website (Box) s Programming & Planning
Establishment of Program Requirements s Program Analysis p
Space Requirements/ Relationships p
Design Concept p
Building Massing p
Site Investigation Site Survey & Topographic Mapping s Geotechnical Investigation s Existing Conditions N/A
Preliminary Energy Model & System Analysis (As s Required)
Building and Zoning Code Analysis Zoning Analysis s Preliminary Building Code Analysis s Preliminary Civil/ Site Analysis s Energy Code Analysis s Quantification analysis - SF & BOMA Cales p
Quantification analysis - Energy Envelope s LEED (As Determined to be Required)
LEED Charrette s Project Registration s Preliminary Scorecard & Strategy s
Phasing & Constructability Preliminary Phasing Plans m Constructability Testing m
Preparation of Conceptual Design Documents
Site Plan p
Plans (typ ical) p
Sections (typical) p
PAGE 3 OF 10
RESPONSIBILITY MATRIX Saracen Casino Resort
2018.01.03
CV=Civil Engineer CM=Construction Manager SC=Sustainability Consu ltant PE=Permit Expediter LD=Landscape Designer SE= Structural Engineer
Architect Consultant of Record or CM
HBG Consultant
or CM
s s
s p
p
s
s p (CV)
s p (CV)
N/A P (CV,SV)
s P (SC/MEP)
s P(ZA) p S(CC)
s P(CV)
s P(SC/CC)
s P(MC)
s P(MEP)
s P(SC)
s P(SC)
s P(SC)
m P(CM)
m P(CM)
s s s
Owner
ODA
p
p
p
p
p
p
p
s
p
p
MARLON BLACKWELL ARCHITECTS
Case 4:19-cv-00925-KGB Document 1 Filed 12/20/19 Page 30 of 55
Design Phase/ Activity
Elevations {typical) Digital Models Concept Renderings Preliminary Materials/ Finishes Preliminary Core(s)
Preliminary Structural Grid(s) Collation of Concept Design Documents Cost Estimating Presentation to Owner Design Guidelines Outline Specifications (Issue templates) Outline Specifications (Architecture Design Intent) Outline Specifications (Architecture, Back of House)
Design Description Coordination of Structural/MEP Engineers
Owners Full Concept Design Approval and Approval to proceed to SD
Schematic Design Phase Client Meetings & Administration
Project Management Design Management Project Document Website (Box) Programming & Planning Establishment of Program Requirements Program Analysis Site Analysis Space Requirements/ Relationships Building and Zoning Code Analysis
Preparation of Schematic Design Documents:
Site Plan Floor Plans (typical)
Amenity Floor Plans Sections and Details (typical) Elevations and Details (typical) Exterior Envelope (typical conditions) Materials Core (typical floors) ¼"= 1 '-0"
Lobby Elevations¼"= 1 '-0" Lobby Plans¼"= 1'-0"
Sta irs Elevator Cabs 3-D Working Images
Preliminary Unit Layouts and Finishes
PAGE 4 OF 10
Design Architect Architect of Record
MBA HBG
p s p s p s p s p p
p p
p s s s p p
p s s p
p s s p
p s s p
s p
p s s s
s s p p
p s p p
s p
p s p s p p
p s p s p s p s p p
p s p s s p
s p
p s p p
RESPONSIBILITY MATRIX Saracen Casino Resort
2018.01.03
Consultant Owner or CM
Consultant DOA
or CM
S (MEP)
S (SE)
P (CM)
p
s p
p
p
p
p
P (ZAIC() p
S(CW)
MARLON BLACKWELL ARCHITECTS
Case 4:19-cv-00925-KGB Document 1 Filed 12/20/19 Page 31 of 55
Design Phase/ Activity
Prel iminary Unit Matrix Area Calculations - SF & SOMA
Design Guidelines
Outline Specifications (Issue Templates)
Outline Specifications (Architecture Design Intent)
Outline Specifications (Architecture, Back of House)
Design Description
Coordination of Structura l/Mechanical/E lectrical Engineers
Coordination of Design Consultants (Fa<;ade, Lighting, Landscape, Graphics etc.)
Sample Tenant Layout (As Required) City Agency Approvals Meetings
Permitting/ Entitlements Investigation & Assistance
Coordination of Renderings, Models, Photos
Collation of Schematic Design Documents
Presentation of Schematics to Owner Selection of Major Building Materials
Cost Estimating
Review of Owner's Project cost estimate and generation/presentation of value engineering suggestions
Incorporation of Owner's approved value-engineering elements into the design documents.
Owners Full Schematic Design Approval and Approval to proceed to DD
Design Development Phase Project Management
Design Management
Cl ient Meetings & Administration
Project Document Website (Box)
Sample Tenant Layouts
Coordination of Structural /Mechanical/Electrical Engineers
Coordination of Design Consultants (Fa<;ade, Lighting, Landscape, Graphics etc.)
Coord ination and Incorporation of Design Details and Specifications recommended or prepared by other subconsultants.
Selection of Major Building Materials
Preparation of Design Development Documents:
Site Plan Plans (Public floors) 1 /8" = 1 '-0"
Plans (Service Floors) 1 /8" = 1 '-0"
Elevations (all) 1 /8" = 1 '-0"
PAGE 5 OF 10
Design Architect Architect of Record
MBA HBG
p p
s p p s s p p s s p p s p p
p p
p s s s s p p s s p p s p s s s p p
p p
p s s p
s s p s p p
p p
p p
p s p s p s p s s p p s
RESPONSIBILITY MATRIX Saracen Casino Resort
2018.01 .03
Consultant Owner or CM
Consultant DOA
or CM
p (MC)
p (ZA) p
P (ZA, CV, PE)
P(CM) p
P(CM) p
p
p
p
MARLON BLACKWELL ARCHITECTS
Case 4:19-cv-00925-KGB Document 1 Filed 12/20/19 Page 32 of 55
Design Phase/ Activity
Sections (typical) 1 /8" = 1 '-0" Curtain Wall/Storefront Details 1 /2" =1 '-0" Core Plans¼"= 1 '-0" (after core layout freeze)
Lobby Elevations (all)½"= 1 '-0" Lobby Plans (all)¼"= 1 '-0"
Public Area Flooring Plans 1 /8" = 1 '-0" Publ ic Area Reflected Ceiling Plans Public Area Wall Sections Stairs (after core layout freeze) Materials Elevator Cabs
Area Calculations - SF & BOMA Design Guidelines
Development of Architectural Specifications Development of Architectural Design Specification Sections Review Plan with applicable Agencies Coordination of Renderings, Models, Photography, Brochures Collation of Completed Design Development Documents
Presentation of Design Development Documents to Owner/Developer Cost Estimating Review of Owner's Project cost estimate and generation/presentation of value engineering sueeestions Incorporation of Owner's approved value-engineering elements into the design documents. Owners Full Design Development Approval and Approval to proceed to CDs
Construction Documents Phase Project Management Client Meetings & Administration Project Document Website (Box) Consultant Coordination Preparation of Construction Documents:
Site Plan Floor Plans 1/8" = 1'-0" Core Plans ¼"= 1 '-0" Building Elevations 1 /8" = 1 '-0" Building Sections 1 /8" = 1 '-0" Stair Plans ¼"= 1 '-0" Stair Sections¼"= 1'-0"
PAGE 6 OF 10
Design Architect Architect of Record
MBA HBG
p s p s s p
p s p s p s p s p s s p
p s p s
s p
p s s p
p s
s p
p s
p p
p s
s s p p
p p
s p
s s s p
s p
s p
s p
s p
s p
s p
s p
s p
RESPONSIBILITY MATRIX Saracen Casino Resort
2018.01.03
Consultant Owner or CM Consultant
ODA or CM
P(CW)
P(MC)
P(CC)
P(CM) p
p
p
p
p
MARLON BLACKWELL ARCHITECTS
Case 4:19-cv-00925-KGB Document 1 Filed 12/20/19 Page 33 of 55
Design Phase/ Activity
Stair Details Elevator Plans ¼" = 1 '-0"
Elevator Sections ¼"= 1 '-0"
Escalator Plans and Sections Wall Sections at Building Base ½" = 1 '-0"
Cladding Details Elevations at Exterior Storefronts½"= 1 '-0" Exterior Storefront Details½"= 1 '-0" Public Area/Amenity Floor Plans 1 /8" = 1 '-0" Public Area/Amenity Reflected Ceiling Plans Public Area/Amenity Wall Sections Washroom Plans, Elevations and Details Elevator Cab Plans, Elevations, and Details Enlarged Unit Plans¼"= 1 '-0"
Cost Estimating
Unit Matrix Room Finish Schedule Color Schedule
Specifications (as applicable): Division 1 (tender forms, general conditions) Technical Sections
Concrete Masonry Metals Steel, Stairs, and Rail ings Carpentry Waterproofing Roofing Insulation Fire Proofing
Doors and Frames Entrances and Screens Skylights Hardware Windows Plaster, Gypsum Board Tile Marble, Granite
Flooring Painting Louvers Washroom Accessories Mirrors Colors
PAGE 7 OF 10
Design Architect Architect of Record
MBA HBG
s p
s p
s p
s p
s p p s s p
s p
s p
s p
s p
s p
s p
s p
s s s p
s p p s
s s s p
s p
s p
s p
s p
s p
s p
s p
s p
s p
s p
s p
s p
s p
s p
s p
s p
s p
s p
s p
s p
s p p s
RESPONSIBILITY MATRIX Saracen Casino Resort
2018.01.03
Consultant Owner orCM
Consultant DOA
or CM
S(CW)
S(CW)
P(CM) p
p
P(CW) s
P(CW)
MARLON BLACKWELL ARCHITECTS
Case 4:19-cv-00925-KGB Document 1 Filed 12/20/19 Page 34 of 55
Design Phase/ Activity
Technical refinement of exterior public space elevations, details for build ing enclosure, curtain wa ll, lobby fin ishes, landscape and elevator cabs fo r incorporation into Construction Documents* Area Calculations - SF & BOMA Collation of Contract Documents Submittal of CDs to applicable Agencies Presentation of CDs to Owner Coordination of Engineering Services/Specialty Consultants Owners Approval
Code & Permitting Code Interpretation Presentation of Local Authorities Presentation to Community Groups Zoning Calculations Building Permit Filing Building Department Liaison Issues Review drawings for Code Compliance (all design phases) Certificate of Occupancy filing (including sign-off for work)
Bidding and Negotiation Project Management Bid Meetings & Administration Preparation of Bid Documents (Drawings and specs) Reproduction and Distribution of Plans and Specs Process of Contractor's Questions and Information during Bidding Preparation of Addenda Receive and review bids with Owner Prepare Bid Analysis Recommend award for negotiation Negotiate front end documents & qualifications Contract Document review and markup Issue conformed set to confirm clarifications Issue Bulletin No. 1 / Issued for Construction Set
Construction Administration Phase Project management Construction Meetings & Administration Coordination of Engineering Services Construction Administration
PAGE 8 Of 10
Design Architect Architect of Record
MBA HBG
s p
s p
s p
s p
s p
s p
I~ p
p p
p p
s p
s s m p
p
s
s s s s s p
m s s p
s p
s s m m m m m ~ m In s p
s p
s s
s p
s p
RESPONSIBILITY MATRIX Saracen Casino Resort
2018.01.03
Consultant Owner or CM Consultant
DOA or CM
P(CW,LD)
P(MC)
p
p
S(CC) p
S(ZA) S(ZA) P(PE) s S(PE) s P(CC)
P(CM) s
p
P(CM) p
p
p
p
p
p
p
p
p
p
P(CM)
MARLON BLACKWELL ARCHITECTS
Case 4:19-cv-00925-KGB Document 1 Filed 12/20/19 Page 35 of 55
Design Phase/ Activity Design Architect Architect of Record
MBA HBG
Continu ing On Site Presence s p
Periodic Site Reviews p p
Manage Submittal Process s s Construction Management Software Review/Action shop drawings, mock-ups and samples P (Design p
of all architectural items for common areas, facades, Intent) main lobby, typical floor lobbies, bathrooms, etc.
Coordinate Material Selections and Colors p p
Manage RFI Process s Provide Clarifications - Drawings and Specifications s p
Respond to RFls s p
Manage Bulletin Process - Drawings and ~ p
Specifications Issue Bul letin Drawings and Specifications s p
Review Change Order Proposals (PCOs) s s Review & Approve Payment Certificates ~ p
Process Payment Certificates Complete Substantial Completion review s p
Prepare and Issue Substantial Completion certifi cate Im p
Receive and review As-Bu ilt drawings and ID m. specifications Receive and review Warranty data m m Conduct/administer punch list s p
Furniture, Furnishings, and Equipment Project Management s s Furn iture and Furnishings p s
Publ ic Area/Amenity Furniture and Furnish ings p s Design Intent and Review Model Hotel Unit Furniture and Furnishings Design p s Intent and Review Coord ination of Furniture and Furnish ing s p
Installation Coordination of Equipment Planning and Instal lation s p
Notes: (All consultants to read notes listed below together with responsibility matrix)
RESPONSIBILITY MATRIX Saracen Casino Resort
2018.01.03
Consultant Owner or CM
Consultant DOA
or CM P(CM) p
P(CM)
P(CM) S(CM)
P(CM)
s
p
p
p
S(CM) p
p
P(CM) p
S(CM) s
p
1. Design Architect to review shop drawings, architectural submittals and mock-ups for design intent. 2. Each engineering and specialist consultant to review Shop Drawings for which they are the prime
responsible. ie. The consultant that writes their respective specification section is the prime review of the corresponding shop drawings and other submittals. The AoR shall provide overall review gatekeeping responsibility for submittals.
3. Architect of Record will collaborate with the Construction Manager to establ ish a Shop Drawing Review process for all consultants. Design Arch itect shall review submittal log to identify all submittals requiring Design Architect review and support.
PAGE 9 OF 10 MARLON BLACKWELL ARCHITECTS
Case 4:19-cv-00925-KGB Document 1 Filed 12/20/19 Page 36 of 55
RESPONSIBILITY MATRIX Saracen Casino Resort
2018.01.03
4. Design Architect to review items of design interest during Construction Documents, Shop Drawing Review and Field Review.
5. Architect of Record to provide periodic site review for which they are prime responsible as listed above. 6. Bid packages and performance specifications (e.g. design assist) for certain items of the work may be
required out of sequence and prior to completion of DD or CD phases. CM shall identify all such areas. 7. Design Architect to obtain all requisite Design Approvals from the client for each phase. Design
Architect's designs must be coordinated with up to date program, technical, tenant fit-out, and area requirements
8. Design Architect to be available for presentations to City Planning and local Community Boards, if required .
9. Each team member (architects and consultants) is responsible for the completeness of their own separate packages and submitting at the required deadlines.
PAGE 10 OF 10 MARLON BLACKWELL ARCHITECTS
Case 4:19-cv-00925-KGB Document 1 Filed 12/20/19 Page 37 of 55
January 15, 2019
Downstream Development Authority
Attn: John L. Berrey, Chairman
69300 E. Nee Road
Quapaw, OK 74363
RE: Downstream Development Authority - Saracen Casino Resort - Pine Bluff, Arkansas
Initial Authorization for NE Design Services
Ladies and Gentlemen:
HBG Design, Inc. (the "Architecn is pleased to submit its initial authorization for professional design services
for the above referenced project. We are excited about the opportunity to join your team and see this
important project through to completion. This letter will serve as a letter of authorization to allow HBG Design
to continue to proceed with work. The parties intend, at the earliest possible date, to enter into a full-services
Agreement in substantially similar form as AIA Document 8103-2017 - Standard form of Agreement Between
Owner and Architect (the "Owner-Architect Agreement") .
The initial services will be based on the attached Preproposal Presentation Package. HBG Design will
coord inate wit h Marlon Blackwell Architects to develop the scope of services for the fu ll services Project. The
Scope of Work, proposed consu ltant teams, Cost of Work budget and design and construction schedule will
be defined based on Owner information and will be incorporated into the Owner-Architect Agreement.
During the initial authorization, the Architect will submit a mobilization fee in the amount of $250,000 to be
paid as a first payment. We anticipate reaching a mutual agreement for a fu ll services fee with in 3 to 4
weeks. Upon agreement, of fu ll services fee , we will send a second invoice for services rendered as of March
1, 2019 to be paid in our normal billing cycle. We will continue to invoice month ly based on percent complete th ru completion of basic services. Upon approval by the Owner of the Architect's fee for the full services
Project. amo'lmts paid by the Owner under th is in itia l authorization for the Arch itect's services wi ll be cred ited
against the Architect's tota l approved Basic Services fee for the Project.
Designing Experience. , MEMPH IS , S AN [)l f (;Q , wwwhbgde, ,gn
EXHIBIT
i b
One Commerce 5Quare 40 South Main Street. Suite 2300
Memphis. TN 38103 901-525·2557
Case 4:19-cv-00925-KGB Document 1 Filed 12/20/19 Page 38 of 55
HBG has developed this initial authorization based on our understanding of the Owner's requirements. After reviewing the proposal, if you require additional information or clarification, please don 't hesitate to contact me so that we can prepare revision to reflect your intentions.
Sincerely,
HBG DESIGN, INC.
QJtlwff Paul H. Bell, AIA Principal
Approved:
:i:::~:;~:gFt~ Chairman
Attachments: Exhibit A - Assumptions and Exclusions Exhibit B - Terms and Conditions
CC:
Exhibit C - Preproposal Presentation Package
Rick Gardner, AIA Marlon Blackwell, AIA Josh Flowers, AIA Jeff Bailey, C
Date: 1/Jr,,/;9 7 /
www hbg design
Case 4:19-cv-00925-KGB Document 1 Filed 12/20/19 Page 39 of 55
Exhibit A: Assumptions and Exclusions
ASSUMPTIONS Our proposal is based upon the following assumptions:
• We anticipate executing an Owner-Architect Contract with the owner based on AIA Document 8103-2017 Standard Form of Agreement Between Owner and Architect with terms and conditions modified as mutually agreed. Until such agreement is executed, the attached Terms and Conditions will govern.
• We anticipate that the owner will contract directly with a General Contractor or Construction Manager who will provide pre-construction services, including cost estimating and analysis, scheduling, and advice regarding construction methods during the course of the design and construction.
• The owner will furnish to the Design Team site surveys showing existing grades, buildings, utility lines, setbacks, Limits of Trust, vegetation, wetlands (if any), boundaries and roads and soil testing information. If required, we anticipate that the owner will administer and provide environmental surveys and administer remediation through other consultants contracted directly with the owner.
• Owner will provide soil boring/exploration, topographic and boundary survey, and geo-technical analysis of the building footprint areas as required to inform the design.
• It is anticipated that the local building department will be the Authority Having Jurisdiction (AHJ) thus a third-party code consultant will not be required and provided by the Owner.
Designing Experience. ,' MEMPH IS SAN DI EGO , www.hbgdesign
One Commerce Square 40 South Main Street, Suite 2300
Memphis, TN 38103 901-525-2557
Case 4:19-cv-00925-KGB Document 1 Filed 12/20/19 Page 40 of 55
Exhibit B: Terms and Conditions
1. ARCHITECT'S RESPONSIBIUTIES The Architect's services shall be performed as expeditiously as is consistent with professional skill and care and the orderly progress of the Work. The Architect's schedule for the performance of the Architect's services may be adjusted as the Project proceeds, and shall include allowances for periods of time required for the Owner's review and for approval of submissions by authorities having jurisdiction over the Project.
The Architect shall not have control over or charge of and shall not be responsible for construction means, methods, techniques, sequences or procedures, or for safety precautions and programs in connection with the Work. The Architect shall not be responsible for the Contractor's schedules or failure to carry out the Work
according to the Contract Documents. The Architect shall not have control over or charge of acts or omissions of the Contractor, Subcontractors, or their agents or employees, or of any other persons performing portions of the Work.
Drawings, Specifications and other documents, including those in electronic form, prepared by the Architect are Instruments of Service for use solely with respect to this Project. The Architect shall be deemed the author and owner of such Instruments of Service and shall retain all rights accorded under applicable law, including copyrights
under the Berne Convention . Upon execution of this Agreement, the Architect grants to the Owner a nonexclusive license to reproduce the Architect's Instruments of Service solely for use with this Project, provided that the Owner
shall comply with all obligations, including prompt payment of all sums when due, under this Agreement. The Architect shall have the right to withhold the Instruments of Service in the event the Owner fails to make payments in a timely manner.
Recognizing the relative risks and benefits of the Project to both the Owner and the Architect, the risks have been
allocated such that the Owner agrees, to the fullest extent allowed by law, to limit the liability of the Architect and its consultants to the Owner and to all construction contractors and subcontractors on the Project for any and all claims, losses, costs, damages of any nature whatsoever or claims expenses from any cause or causes, so that the
total aggregate liability of the Arch itect and its consultants to all those named shall not exceed the Architect's total compensation for basic services rendered on this Project. Such claims and causes Include, but are not limited to
negligence, professional errors or omissions, strict liability, and breach of contract or warranty. This limitation shall apply regardless of the cause of action, legal theory, or nature of the loss, damage, liability, or expense sustained or allegedly sustained by the Owner. This limitation shall survive termination or expiration of this Agreement.
2. PAYMENTS TO THE ARCHITECT Payments on account of the Architect's Services and for Reimbursable Expenses shall be made monthly upon presentation of the Architect's statement of services rendered or expenses incurred. For Reimbursable Expenses the compensation shall be the expenses incurred by the Architect and the Architect's consultants. Payments not received by the Architect within 30 days of invoice date will accrue service charges at 1% per month.
3. RESPONSIBILITY FOR CONSTRUCTION COST Evaluations of the Owner's Project budget, preliminary estimates of Construction Cost and detailed estimates of Construction Cost, if any, prepared by the Architect, represent the Arch itect's judgment as a design professional
familiar with the construction industry. Neither the Architect nor the Owner has control over the cost of labor,
materials or equipment. over the Contractor's methods of determining bid prices, or over competitive bidding,
Designing Experience. / MEMPHIS ; SAM D I EGO , www.hbg.des,gn
One Commerce Square 40 South Main Street, Suite 230 0
Memphis; TN 38103 901-525-2557
Case 4:19-cv-00925-KGB Document 1 Filed 12/20/19 Page 41 of 55
PAGE 15
market or negotiating conditions. Accordingly, the Architect does not warrant or represent that bids or negotiated prices will not vary from the Owner's Project budget or from any estimate of Construction Cost or evaluation prepared or agreed to by the Architect. No f ixed limit of Construction Cost shall be established as a condition of this Agreement by the furnishing, proposal or establishment of a Project budget, unless such fixed limit has been agreed upon in writing and signed by both parties.
4. MEDIATION Claims, disputes or other matters in question between the parties to this Agreement arising out of or relating to
this Agreement or breach thereof shall be subject to non-binding mediation in accordance with the Construction
Industry Mediation Rules of the American Arbitration Association currently in effect as a condition precedent to arbitration or the institution of legal or equitable proceedings by either party.
Requests for mediation shall be filed in writing with the other party to this Agreement and with the American Arbitration Association. Requests may be made concurrently with the filing of a demand for arbitration but, in such event, mediation shall proceed in advance of arbitration or legal or equitable proceedings, which shall be stayed pending mediation for a period of 60 days from the date of filing, unless stayed for a longer period by agreement of the parties or court order.
Requests for mediation shall not be made after the date when institution of legal or equitable proceedings based
on such claim , dispute or other matter in question would be barred by applicable statutes of limitations. The
parties agree to share mediation costs equally. The mediation shall be held in the locale of Project, unless another location is mutually agreed upon. Agreements reached in mediation shall be enforceable as settlement
agreements in any court having jurisdiction thereof.
5. CLAIMS FOR CONSEQUENTIAL DAMAGES The Owner and Arch itect waive all claims for consequential damages or losses arising out of or relating to the Agreement against each other and against any persons or entities performing services on behalf of the Architect,
including the Architect's consultants, any separate contractor employed by the Owner, the Contractor and any
persons or entities performing Work or supplying materials on behalf of the Contractor.
6. TERMINATION, SUSPENSION, OR ABANDONMENT This Agreement may be terminated by either party upon not less than 7 days' written notice should the other party fail substantially to perform according to the terms of this Agreement through no fault of the party initiating
termination. If the Project is suspended by the Owner for more than 30 consecutive days, the Architect shall be compensated for services performed before notice of suspension . When the Project is resumed, the Architect's compensation shall be equitably adjusted.
This Agreement may be terminated by the Owner upon not less than 7 days' written notice to the Architect if the Project is permanently abandoned. If the Project is abandoned by the Owner for more than 90 consecutive days, the Architect may terminate this Agreement by giving written notice. Failure of the Owner to make payments to the Architect according to this Agreement shall be considered substantial nonperformance and cause for termination. If the Owner fails to pay the Architect for services and expenses when due, the Architect may upon 7 days' written notice to the Owner, suspend performance of services under th is Agreement. Unless the Architect receives full payment within 7 days of the date of the notice, the suspension shall take effect without further notice. If services
are suspended, the Architect shall have no liability to the Owner for delay or damage caused the Owner because of
www hbg design
Case 4:19-cv-00925-KGB Document 1 Filed 12/20/19 Page 42 of 55
PAGEl6
suspension of services. If termination is not the fault of the Architect, the Architect shall be compensated for services performed before termination, together with Reimbursable Expenses then due and equitable Termination Expenses. Termination Expenses are in addition to compensation for Basic and Additional Services, and include expenses that are directly attributable to termination.
7. MISCELLANEOUS PROVISIONS This Agreement and the accompanying letter of proposal comprise the entire and integrated agreement between the Owner and the Architect and supersede all prior negotiations, representations or agreements, either written or oral. This Agreement may be amended only by written instrument signed by both Owner and Architect. Nothing contained in this Agreement shall create a contractual relationship with or a cause of action in favor of a
third party against either the Owner or Architect.
www hbg.desogn
Case 4:19-cv-00925-KGB Document 1 Filed 12/20/19 Page 43 of 55
ll s
~ • " ~
~ ~ • i 5 ll !: s
~ • ll s §
~ • § s •
EXHIBIT
Case 4:19-cv-00925-KGB Document 1 Filed 12/20/19 Page 44 of 55
Kertis Weatherby
From: Kertis Weatherby Sent: Monday, March 11 , 2019 3:57 PM To: Cc: Subject: Attachments:
FW: DOWNSTREAM-PB: Comments on Proposed HBG Initial Authorization 19-01-14 HBG Authorization for Design Services (dda redline).PDF; ATT00001 .htm
Kertis Weatherby, AIA, LEED AP BD+C Marlon Blackwell Architects
From: Kertis Weatherby Sent: Monday, January 14, 2019 3:04 PM To: Ati Blackwell <[email protected]> Subject: FW: DOWNSTREAM-PB: Comments on Proposed HBG Initial Authorization
Kertis Weatherby, AIA, LEED AP BD+C Marlon Blackwell Architects
From: Marlon Blackwell Sent: Monday, January 14, 2019 3:03 PM To: Kertis Weatherby <kertis@marlonblackwel l.com> Subject: Fwd: DOWNSTREAM-PB: Comments on Proposed HBG Initial Authorization
Marlon Blackwell, FAIA Marlon Blackwell Architects 42 East Center Street Fayetteville, Arkansas 72701
Begin forwarded message:
From: "Chris Roper" <[email protected]> To: "Paul Bell" <[email protected]>, "[email protected]" <[email protected]>, " [email protected] " <[email protected]> Cc: "John Berrey" <[email protected]>, "Marlon Blackwell" <marlon@marlonblackwel l.com> Subject: DOWNSTREAM-PB: Comments on Proposed HBG Initial Authorization
Attached is the marked up Authorization letter.
We have corrected the address and signature information
EXHIBIT
Case 4:19-cv-00925-KGB Document 1 Filed 12/20/19 Page 45 of 55
We have marked up the mobilization fee to $250,000. We are not comfortable fronting $500,000 for startup of design We have removed all references to reimbursable costs. We will not agree to any reimbursable costs. These need to be inside your fee. We have removed Exhibit A. We do not agree to hourly design fees. All fees and expenses need to be quoted for approval We have removed the reference to hiring a third party code consultant that will act as the Authority having jurisdiction. City of Pine Bluff will have Jurisdiction We have marked up the terms and conditions as noted We have modified the exclusion statement regarding on site representation . On site representation as needed should be included in the Architects fee
In regards to the Architects Fee listed on the Cash Flow Schedule. We will agree to 6% fee on Cost of work This needs to be an all inclusive fee. Including the civil engineering and on site representation as needed
Please review these modification and let me know if you have any questions
Thank you
Chris Roper 304 Main Street Quapaw Oklahoma 74363 918-238-3099 Office 573-247-8181 Cellular
2
Case 4:19-cv-00925-KGB Document 1 Filed 12/20/19 Page 46 of 55
Sar
acen
Cas
ino
Res
ort
Pha
se S
plit
s
tabb
ies°
FULL
SC
OPE
Pro
ject
Ma
na
ge
me
nt
Clie
nt
Re
latio
nsh
ip
AO
R
SIT
E+
AC
CE
SS
OR
Y S
TRU
CTU
RE
S S
ite
Ou
tdo
or
Eve
nts
Ou
tbu
ildin
gs/
No
t in
Sco
pe
MA
IN F
AC
ILIT
Y
m
Cor
e+S
hell
Gam
ing
Flo
or
Foo
d+B
ever
age
Ho
tel
Eve
nts
Ad
min
istr
atio
n
Tec
hnic
al O
pe
ratio
ns
Phy
sica
l Op
era
tion
s
FF&
E /
In
teri
ors
f\\-
~
m
=i
%T
OT
AL
%SC
OPE
3.00
%
1.00
%
5.00
%
5.00
%
86.0
0%
60.0
0%
40
.00
%
38.0
0%
7.5
0%
7.5
0%
20.0
0%
5.0
0%
1.0
0%
1.0
0%
1.0
0%
19.0
0%
MB
A
HB
G
34.4
2%
65
.58
%
2S.0
0%
75
.00
%
100
.00
%
0.0
0%
0.0
0%
1
00
.00
%
50.1
0%
49.9
0%
43.5
0%
56
.50
%
60.0
0%
4
0.0
0%
35. 0
8%
64
.93
%
41.0
0%
59
.00
%
39.0
0%
61
.00
%
39.0
0%
61
.00
%
39.0
0%
61
.00
%
31.0
0%
69
.00
%
16.5
0%
83
.50
%
16.5
0%
83
.50%
16.5
0%
83
.. 50
%
20.0
0%
80.0
0%
W
DD
ro
~
20
%
25%
35
%
20
%
MB
A
HB
G
MB
A
HB
G
MB
A
HB
G
MB
A
HB
G
62.
2%
37.8
%
43.3
%
56.7
%
25.
4%
74
.6%
11
.3%
88
.8%
25.0
% 7
5. 0
%
25.0
% 7
5.0%
25
.0%
75.
0%
25.0
% 7
5.0
%
10
0.0%
0.0
%
10
0.0
% 0
.0%
1
00.
0% 0
.0%
1
00
.0%
0.0
%
0.0
% 1
00.0
%
0. 0
% 1
00.
0%
0.0%
10
0.0%
0
.0%
10
0.0
%
84
.0%
16.
0%
60.0
% 4
0.0%
4
2.0
% 5
8.0%
18
.0%
82.
0%
80
. 0%
20
.0%
60
.0%
40
.0%
30
.0%
70.
0%
10
.0%
90.
0%
90
. 0%
10.
0%
60.0
% 4
0.0
%
60.0
% 4
0.0
%
30.0
% 7
0. 0
%
SD
DD
C
D
CA
65.5
% 3
4.6%
44
.8%
55
.2%
25
.1%
74.
9%
10.0
% 9
0.0
%
80
.0%
20
.0%
50
.0%
50
.0%
30
.0%
70.
0%
10.0
% 9
0.0%
70.0
% 3
0.0
%
50.0
% 5
0.0
%
30.0
% 7
0.0%
10
.0%
90.
0%
70.0
% 3
0.0
%
50.0
% 5
0.0
%
30.0
% 7
0.0%
1
0.0
% 9
0.0
%
70.0
% 3
0.0
%
50.0
% 5
0.0
%
30.0
% 7
0.0%
1
0.0%
90
.0%
60.0
% 4
0.0%
40
.0%
60
.0%
20
.0%
80.
0%
10
.0%
90.
0%
30.0
% 7
0.0
%
20.0
% 8
0.0
%
10
.0%
90
.0%
1
0.0
% 9
0.0
%
30.0
% 7
0.0%
20
.0%
80
. 0%
1
0.0
% 9
0.0%
1
0.0
% 9
0.0%
30.0
% 7
0.0
%
20.0
% 8
0. 0
%
10
.0%
90
.0%
1
0.0
% 9
0.0%
35.0
% 6
5.0
%
30.0
% 7
0.0
%
10
.0%
90.
0%
10.0
% 9
0.0%
Case 4:19-cv-00925-KGB Document 1 Filed 12/20/19 Page 47 of 55
Kertis Weatherby
From: Sent:
To: Cc: Subject: Attachments:
FW: HBG /MBA Deliverables Matrix 20190222 mba-hbg work split matrix.xlsx
See emails below which note the agreement to the fee split from HBG
Kertis Weatherby, AIA, LEED AP BD+C Marlon Blackwell Architects
From: Kertis Weatherby Sent: Friday, February 22, 2019 5:22 PM
To: Paul Bell <[email protected]>
Subject: RE: HBG /MBA Deliverables Matrix
Paul,
Please see the attached for our take on the deliverables matrix.
We will in general have provide design direction and intent for the full project and will provide design review over aesthetics of material selections, documentation and details. We will expect that HBG will provide technical review of MBA drawings and building operations critical elements.
We do not want to have design decisions made with out conversation or without design direction & review by MBA, even where HBG has a primary role for that scope of deliverable.
Please let me know if there area any questions relative to what we are submitting here.
Thanks, Kertis
Kertis Weatherby, AIA, LEED AP BD+C Marlon Blackwell Architects
From: Kertis Weatherby Sent: Friday, February 8, 2019 7:28 AM To: Paul Bell <[email protected] ign> Subject: Re: HBG /MBA Deliverables Matrix
I will certainly work through that.
Sent from my iPhone
Kertis Weatherby, AIA, LEED AP BD+C
Marlon Blackwell Architects
42 East Center Street Fayetteville, AR 72701 479.973 .9121 (w) 315.882.2968 (cell) EXHIBIT
Case 4:19-cv-00925-KGB Document 1 Filed 12/20/19 Page 48 of 55
On Feb 7, 2019, at 5:50 PM, Paul Bell <[email protected]> wrote:
Kertis,
I sent a Deliverables Matrix in excel spreadsheet form last week. Since we have come to agreement on the percentage of fee split, can you fill out the deliverables that MBA anticipates providing? If you could just place an "x" in each cell of the MBA column and return to me, that will be helpful in our planning and schedule development. Thanks .
Paul Bell, AIA Principal [email protected]
HBG Design One Commerce Square 40 South Main Street, Suite 2300 Memphis, TN 38103
(0) 901-525-2557 (D) 901- 577-0408 (C) 901-351-6344
www.hbg.design
This email has been scanned by the Symantec Email Security.cloud service. For more information please visit http://www.symanteccloud .com
2
Case 4:19-cv-00925-KGB Document 1 Filed 12/20/19 Page 49 of 55
Saracen Professional Services Deliverables Matrix Discipline
EXHIBIT
I 0
Case 4:19-cv-00925-KGB Document 1 Filed 12/20/19 Page 50 of 55
Saracen Professional Services Deliverables Matrix DlSdpllne Architecture/ Interiors Others
~ =· ~~-~=====
., .• ,u••·• ~
Case 4:19-cv-00925-KGB Document 1 Filed 12/20/19 Page 51 of 55
Saracen Professional Services Deliverables Matrix Ol!dpllne
·----------------------------
Case 4:19-cv-00925-KGB Document 1 Filed 12/20/19 Page 52 of 55
Saracen Professional Services Deliverables Matrix Dl>clpllne Architecture/ rntertors Others
Case 4:19-cv-00925-KGB Document 1 Filed 12/20/19 Page 53 of 55
Sa
race
n C
asi
no
Re
sort
P
ine
Blu
ff, A
rka
nsa
s A
19.0
00
1.0
1
ID~["'
~ io
~·-1
""" l "
-· ....
L
I JI
OK_J
-455
~ 1
/1/1
9 M
on 1
0/5
/20
3 it • t~
u 12:Jo
'_'._J'
H_j
_,.
_,c
..in
oR
..o
tt
,.,_ ..
.....
Wo
n.h
op
1 D
NI_
, lff
llMf'N
Ol'l
• ~•n
cl e
Ml«
,n
fM -
Si&
ned
len
ero
!Au
lho
rwn
,on
eono
..-1
Pto
tnm
mln
c
f>ro
&r•
m •
nd
8to
c:I.
0,1
a,,m
Dev
eloQ
!nen
l
w--
,.. 2
; °"
""9f
" .,.
....
... "'S
chlcM
I. ,,.,.
..,.., _
. ~
0.,1
11
11
35
.01
Sch
lm11
lc o
..li,'
I
TH
1 D
N,s
n e
nd D
ocu
m-t
ion
DN
li,'
1W
OfM
Nft
3 1
"'1
,_,_
l_..
.._
foo
tl"m
t.
c..
.-~
can
..en
c1a.
..,_
.. ,.
, ...
.. 8M
llch
R
epen
-O
lffl
m.-
""-b
a"'t
len
OO
.~O
MM
,'1
(:h
l
~--&
I\'~
...
...
1,,
. 2
0•i
snen
d0
ocu
men
tllb
on
k1,.
..P
eck•
&•
o..
li,'1
.,.
,.,.
_ -4
W
wne
11c 0
-.,
l"r•
enta
"-"
Tilr
2
App
,w.1
•111
11 l
"la
fl.O
r,,e
nl,.
._P
w\.
er..,~
. ID
o..n
erR
,Y11
W1n
dApp
o-ov
al
, .... T
u.1
/l/1
'Wed
1/1
1/1
t
·-TN
l/1
/11
T
hu
.t/1
0/1
'
ldly
W
•dl/
16
/19
WM
ll/1
6/1
9
15
dl)
'I
Th
ui/
11
/19
w.d
2/e
/1"2
2"'4
ll
Th
ul/
11
/19
Wee1
1/3
0/1
94
•·
Mon
2/4
/11
W
M 2
/tll
t
.... ,.
Th
u2
/1/1
9 T
N-4
/1
8/lt
·-T
hu
2/7
/19
W
ed
3/6
/19
7
,_ T
hu
l/1
/1t
"""1
11
'1
4 "'
4ll
Mo
n3
/11
/19
F
11
4/5
/19
10
lMy
M
on
4/8
/19
M
on4/
8/1
91
1
1-,
TN
-4
/t/1
1
T-
4/1
/lt
12
1w11
W
ed4/1
0/1
9
r,..
.4/1
6/1
91
3
" .. --4
0.0
1 D
N,l
lfl
Dew
lop
men
t 1
13
de,-
?
W-.:
1-4/
11/1
9 F
1111
/29/
19
12
,, ,,
Ow
ner
tHo
w.e
toP
'lo
cNd
l~
y
Wed
4/1
7/1
9 W
ed4/1
7/1
91
•
" ,0 ,CJD
" '' ,.- " 2i7
n 21
-·
,.- " 30 31-,..
" - !! j
;;J!n
37
" " 40-1
41
1
42
i .,-,
T..
, 3
Gem
,nt
Floo
r 11
\d C
11on
o 8
0H
O.•
•tn
1n
d l
)ocy
men
t.lb
on
RM
IOW
,np
~w
~a
Tiw
s.-
..-1
-111
1fff'
CF
'INr.~
10
H
o..r
,., -"
"p-o
vet t
o P,
OC
Nd
w,lh
CO
, fo
, G
1m1n
& f
loo
r
T,e
,4A
Ht.
1u<
1nt1
11nd
8111
0.11
anal
'klO
ocum
•nll
bOn
A1n
de<
lllp
0-..~
• T
\er-4
~-R
N..
_..
,_ .. ,.
Ow
ner
Jrc)
prov
1I to
P,O
CN
d W
l(ti
C01
r,.,
5 a
....
. 11o
om,
& ,.
,..,, .
. H
ottt
Pv
bk
~c ..
in
d B
OH
0.1
111
Ren
der
,np
DN
ilf'
oW
otN
,-7
Tilr
l~
l·G
-~
aM
IN,
t-..
1~
---IO
H.•
nd
S.-
T,e
18E
vent
C.n
te1
. 5pa
1n
dAff
lph,
th11
11,
0.11
1f11
n<10
ocum
,n
R1n
oe<
,np
DM
ii,'
IWo
rbN
pt T
lerl~
I-E
¥M
to.n
.,-•n
d~
OO
QA
R,.,
...,..
00
RH
po
nu
to Q
A C
Om
men
u
11,u
eDM
,snD
ev.O
pmen
tP1e
1.1,
-
DN
l1W
1W
otW
wJ,
t lll
nel 0
-. ~~-
Ow
ner
R1V
1tW
•n
d .l
t)o,
oval
Ow
ner
Nq
uc,
to P
rocN
d M
lt\ c
o,
lo,
Int.
not
F"II
Out
P1e
Ml&
H
-45
.01
C-I
NC
1:l
on
Ooo
umen
ta!M
n
45
o..n
,11N
ot1c
1tof
>l'o
cHd
46
51
'91J
tili1
rl"M
kl .. •T
o&
.oo
nft
nud
-9
yo
.n.t
'lct
v1
1C
on
eult
a
47
M-G
11
din
i~
•To
llC
on
ftrm
N•l
yo
.n.r
<.C
MIC
on
e
48
Wor
i(pe
d(a .
. 1:
DN
p "-
nd
etl
on
t C
Nin
o •
ndud
ell
PIIN
, C
lpt.
F-o
otin
et,.
Ind
R11
tffl
of C
olu
mM
In
d«
WIi
k
49
O
ocum
enll
qo
n
50
Q
AR
,,,,
.w
51
QA
AM
pont
e
52
0-
,v.,
,1,c
at,,
onR
,,,,
.w
53
O
r1w
rio
Ind
SP
KI
d,...
II
HB
G
54
, A
AH
mbl
ePac
k11•
55
jD
lu
ueW
o,k
P1
ek1
&•
56
j
.,~
.. 2°
"9F
ou
nd
lUO
Ntt
otl
lt:P
ll•
.Cl1
11.
~.
, 1
nd
firl
tllf
taJf
Col
umna
•nd
or
WII
II
4-..t
<5
Th
u4
/18
/19
Wee
l5/1
5/1
91
7
!wk
T
hu
5/1
6/1
9W
ed
5/2
2/1
91
9
1-,
Thu
15
/21
/lt
Thu
e/2
lllt
20
ld
1y
F1
15
/24
/19
F
n5
/2,t
/19
21
8w
k1
Th
u4
/18
/19
Wed
6/1
2/1
91
7
1.W
. T
hu
6/1
3/U
Wed
6/1
9/1
92
4
1-,
Thu
1/2
0/l
t Th
u l,
/'2
0/l
t 2
5
""
Fn
6/2
1/1
9
Fft
6/2
1/1
92
6
8..
..,.
M
on
6/2
-4/1
9
Fn
l/1
6/1
92
7
1-..4
1 M
on
l/1
9/1
9
Fn
l/2
3/1
92
9
1-,
Mot
l 1/f
f/lt
Mor
i "2
fl1
.t 3
0
8w
k1
T
u1
8/2
1/1
9M
on 1
0/2
l/ ..
1 w1
1 r .
... 1
0122
119
Mon
t0
/28
/ . 3
3
111,
,ty T
N 1
0/2
9/l
t T
w 1
0/29
/ 1-
4
lwl<
Wed
10
/30
/19
J,..
. 1
1/5
/19
35
2"'4
ll
Wed
ll/6
/19
T
uell
/19
/.3
7
1d
lyW
ed
11
/20
/19
Wed
1l/
20
/ 3
8
1.,
. Th
u U
/21
/U T
hu U
/21
/ at
lwl<
F
n1
l/2
2/1
9T
hu
11
/28
/.
,t0
ld1
y?
Fn
U/2
9/1
9
foll
/29
/19
"1
U1
d1
,-M
on
J/1
1/1
1M
on
5/1
1/2
0
1 da
y M
on
3/1
1/1
9 M
on
3/1
1/1
91
0
-4 M
a
Mo
n S
/U/1
1
Ft1
4/5
/19
10
I ll
lb
Mon
3/U
/lt
Fl'l
-4/1
9/1
9 1
0
28
di,
-M
on S
/11
/lt
Mon
4/1
.15/
11
3"'
4ll
M
on
3/1
1/U
F
nl/
29
/19
10
2d
1,-
. M
on
4/l/
19
J,
...4
/2/1
9"9
1.W
. W
1d
,t/J
/19
T
ue,t
/9/1
95
0
1~
y
W1
d4
/10
/19
Wed
4/1
0/t
95
1
l~y
T
hu
4/l
l/1
t T
h...4
/11
/19
52
Idly
F
11
4/1
2/1
9
Fn
-4/1
2/1
95
3
Idly
M
on4
/15
/19
Mon
4/1
5/1
95
4
31
de,-
Tu
. -4
/ltl
/19
T
u1 1
5/2
1/1
9
:: -i
~;:
::1
1u
on
2\::
~~: ;~
::~
:: :: :~
::~
;: !!
: L
_::
:,~
~~
':,R
.,,,
.w
/: ~::
~~:~~:
~=:~;~~
~:::
I 1=-
-- --
- - -Th
u 2/
21
/19
De
sig
n S
che
du
le
20
19
h
tQu
11
tar ~
2n
dQ
u~
j
lld
Qu
11
te, ~
_J1
n_
LF1
b._
.l..
_M
al_
!-._
Af!t
__
J_
__
M11_
l_
.>un_
l_
_>u
1__
i_
Au1
.L
S.p
~ 4t
h Q
uir
t., ~
lltQ
uer
tt1
L
N
a..--
-1...
____
o.~
n__
__
_l_
F1b
___
_l__
M1,
i- i ~ n
h:
E;r
1;.
,, ~ t ~ lo
___ _
LL
-'
c::
..._
:J
o..
-...
....
_
_ s
....
-,
, .. ,
,,.,
,,.,
.,.
_,..,_
,~
. ❖
..........
.... .
-- -EXHIBI
T
j H
·L.,
· ·-
\
--- -
-,
-h
bg
D
ES
IG
N
2020
j
21\d
Qu1
rtlf
__
L
3rd
Qv
arte
, L
41
t\ Q
ulr
taf
L_
~M
1y
L_
J,.
.n
. ~
.-..,_
Ls.
p 0
ct_
LN
ov
Page
11
Case 4:19-cv-00925-KGB Document 1 Filed 12/20/19 Page 54 of 55
Sa
race
n C
asin
o R
eso
rt
Pin
e B
luff
, Ark
ansa
s A
19.0
00
1.0
1
:1r··
-l-
---8
l !
Dr1
ww
,1,1
1n
d~
du
e1
1H
BG
-~
I
Ow_•
-__
,_1 ·
~· l ""
" rt °
" r
,~ 1
d.ly
Fn
5/2
"/11
1 Fl
o 5
/21/
1118
0
1 <1
.ar
Mon
5/2
7/11
1 M
on
5/2
7/t
ll 6
1 ld
.ly
T
.,.5
/28/
111
J.,.
5/2
8/1
91
12
,,j
83
!i
~
~~~ ~ 9 -, 11
jB
__"J "-l
4R 'G
11
.._?.•
H
l j
ao]
"--..I ~ -·~ 85 jE
i ''
J :Hc
...i " " 911
92
"i
.,7
.. J
•w
9'
I 97
~ •• 1 ---4
--j ~ --=i J ~
~
1----
-l --
j ~
Thu
2/2
1/1
9
MH
mb
19
PK
ka&
•
lnu
1W
orl
<P
ack
a11
w~
.. J
Sh.
a 11
nc1
eo,.
Strvc
u•• Ff
•m..
Stan
. •n
d
Ekw
lDt h
tt. •
CM
lno,
Hau
l, E
wef
ft M
el M
lpN
1tl
NtM
O
oC'u
mltf
ltltlO
f'I
QA
R•-
w
QA
RH
po
OH
QA
V•u
l,c,
tio
nR
•"'•
w
Or1
win
&11
ndS
pe,c
1du•
1tH
8G
M1
emb
l•P
1ck
1&
•
l11u
•Wor
kP1c
k1&
•
W~
S-8
5M
I IM
'ld
Co
r.~
:On
lno,
Hot
.II,
•nd
..,,
__..,
QA
R•"
'•w
QA
RH
po
""
QA
V.,
rflc
abo
nR
•-w
DrlW
W'II
P an
d $
pK
I, O
U. It
HBG
MH
ffib
MP
ack1
&•
111.
,.W
OO
.PK
M&
•
w~
.. tl
nti
lrio
l'R
t0u
t-c..
1n
o
Doc
um•n
llD
on
QA
R•-
QA
RH
po
oH
QA
V•1
1fic
1t10
0 R
•-w
....
.. w
o,k
P1
ek1
&•
w~
.. 11
ntar
1orf
lt.O
ut-H
o111
1.'9
e.•n
dE
Yw
'llC
..W
Do
cum
•otl
llo
n
QA
R•l
l'IIW
QA
RH
po
nH
QA
V•1
1fie
atxM
'IR•"
'•w
Or1
ww
,1,1
1n
d~
(I ..
. II
H8
G
MH
ml>
M-P
ack1
&•
111.
,.W
Ofk
PK
ka&
•
80
.0lC
on
a~
Ad
mlt
wln
lto
n
C.1
on
oC
on
iDU
Cb
on
C.1
ino
Su
blt
10
U1
IC
om
plH
on
Ho1
91
[...
.,tC
l,n
tl>
f lr
.dk
np
hrt
h9
1t•
rC
ol\
ltN
cbo
n
Ho
t.I[
....
,\ C
en1 .
. In
d "
"1,p
hlth
Hta
f S
uml.
ln!,
al C
om
pl•b
on
81dl
l)'t
WM
4/1
1/1
1W
Ml/
21
/11
ti..
.._.
W
ff•/
11
/li
J.,.
5/2
8/1
11
1•
lM
W•d
5/2
i/li
lu
•8/•/
tllt
l5
2w
kl
W•d
tl/5
/111
J.
,.8
/18
/19
66
3d1
y1
W•d
8/1
i/li
f1
18
/21
/lll
67
1 di
~
Mo
n8
/2.,
,/ll
l M
on
8/2
"!1
9tl
8
ldly
T
u•8
/25
/1i
Tu
18
/25
/19
6i
Idly
W
ff8
/28
/19
W•d
6/2
6/l
i70
10
1d
•~
WM
4/U
/lt
WM
t/4
/19
lClw
kl
w.c
1•t
11
/1i
J.,.
8/8
/11
11
"
I""<
W
•d8
/1/l
i f.
,.8
/l:J
/19
73
2 ...
...
Wff
8/1
"/l
i J.
,.8
/27
/11
17
•
Jdl)
ll
Wff
8/2
8/l
i F
,14
/30
/19
75
Idly
M
on
i/2
/li
Mo
ni/
2/1
11
78
Idly
T
iall
/3/1
11
Ti.
.9/3
/19
71
lday
W
•dll
/4/1
9
Wff
i/"/1
97
8
'9 0
IIY9
Mon
1/2
1/1
1 T
Iil.i
10
/10
/,_
18w
t,,.,
Mo
n5/
27/1
11
"'11
1/13
/111
22
1""<
M
on
i/H
l/1
9
"'11
1/20
/111
81
2"'4
11
Mo
ni/
23
/11
1
"'1
10
/•/1
98
2
Jd1)
11
Mon
10
/7/1
11
Wlt
d1
0/l
l/1
iSJ
1d
ay
lhu
10
/10
/11
1lh
ul0
/10
/.8
•
121
d-,.
M
on 1
2/2
/11
Mon
8/l
l/2
0
20
wiu
M
on12
/2/1
11
F,,
4/1
7/2
0"2
1 w
k M
on
4/2
0/2
0
F""
l2"/
20
87
2
wk
l M
on.,,
/27
/20
F
,oS
/8/2
08
8
J d•
~•
Mon
5/1
1/2
0 W
ff 5
/13
/20
81
1
1 da
1 T
hu
5/1
"/2
0
Th
u5
/1"/
20
i0
, .. , fn
5/1
5/2
0
floS
/15/
2011
1
1 d.
ly
Mon
5/1
1/1
0 "
4oo
5/1
8/2
01
12
,u
.,.
Mon
•/1
/11
Mon
10
/5/2
0 •
•
..... Uo
n"/
8/11
1 F
r,2
JT/2
04
8
ldly
M
on
2/1
0/2
0 "
4oo2
/10/
2011
5 ,. ...
Uon•/8
/19
F
nl0
/2/2
0"8
1 d
ly
Mor
, 1
0/5
/20
Mo
n 1
0/5/
2011
7
1-.c
l ::· -
,,._,.......,
.,..
.._
__
....
. E
,,,..-
....
,..
.__
---
-
UtQ
u1
r1-,
f•t>_
l
l.
-..
. s..
..-,
De
sig
n S
ched
ule
''"'
... r:=
2r.d
:~
n_
J_
Ju
l _l
_l<d'.
t;".,1
'
J l
....... 't r,
··1
C. ~
0..
..--
<>
flly
MI .
....
. Su
rno
,wyll:o
&,p
•
,0
Ml.
....
tSu
,n,,
w'f
•
•._ I l
~-, , ........
...
j
---r
-4
thQ
u1
1\ .
. S
.p_
L0e
t__
_j_
_Nc
w
\ ... ~.
""
E,,1
., ..
.. M
,._
_ _
...,_ -
l h
lQu
ll\.
, l
F•b
____
l___
_u1
,
t
I 2n
<1Q
u1rt
•r
.,._
Ap,
__
__
.l_
_U
1y
_j Ju
n
'1oi
.. \ ~
hb
g
DE
SIG
N
Jul
L ~:
:.i_
S.p
I
0d
""
'Qui
n.,
L
...
Page
I 2
Case 4:19-cv-00925-KGB Document 1 Filed 12/20/19 Page 55 of 55
I
I
JS 44 (Rev 09/19) CIVIL COVER SHEET The JS 44 civil cover sheet and the information contained herein neither replace nor supplement the Iii ing and service of pleadings or other papers as required by law, except as provided by local rules of court. This form, approved by the Judicial Conference of the United States in September 1974, is required for the use of the Clerk of Court for the purpose of initiating the civil docket sheet. (SEE INSTR/ICT/ONS ON NJ:'.'(TPAGE OF THIS FORM!
I. (a) PLAINTIFFS
MARLON BLACKWELL ARCHITECTS, P.A.
(b) County of Residence of First Listed Plaintiff Washington (J;XCEl'T I,\· l IS Pf.AIN1Jl·F < 'AS/:SJ
( C) Attorneys {/·inn Name. Addre.u·, und Telephone Number)
Mark Murphey Henry, Joe Hall, Jack East P.O. Box 4800 Fayetteville, AR 72702 (479)856-6017
DEFENDANTS
HBG DESIGN, INC.; SARACEN DEVELOPMENT, LLC; and JOHN LANE BERREY in his official capacity as Chairman of the Quapaw
County of Residence of First Listed Defendant
(IN US l'I.AIN71FF C' ASES ONLY)
NOTE IN LAND CONDEMNATION CASES, USE THE LOCATION OF THE TRACT OF LAND INVOLVED.
Attorneys (If Known/
II. BASIS OF JURISDICTION (Place an "x·· in One Box Only; Ill. CITIZENSHIP OF PRINCIPAL PARTIES (Place an "X-- ,n One Box for Plaintiff
0 I U.S. Government
PlamutT
0 2 U S Government Defendant
IV NATURE OF SUIT CON w.&CT
0 I IO Insurance 0 120 Marine 0 I 30 Miller Act 0 I 40 Negotiable Instrument 0 I SO Recovery of Overpayment
& Enforcement of Judgment 0 IS I Medicare Act 0 I 52 Recovery of Defaulted
Student Loans (Excludes Veterans)
0 153 Recover)' ofO,e.,,ayment of Veteran· s Benefits
0 160 Stockholders' Suits 0 190 Other Contract 0 195 Contract Product Liability 0 196 Franchise
REAL PROPERTY 0 210 Land Condemnation 0 220 Foreclosure 0 230 Rent Lease & EJectment 0 240 Tons to Land 0 245 Ton Product L1abihty 0 290 All Other Real Property
QI!: 3 Federal Question
(lf.S. Government Nor u Parry)
0 4 Diversity (Indicate ( '//lumh1p vf Part,e.1· ,n Item Ill)
(!'lace an "X" ,n ( lne Hox Only)
TORTS
PERSONAL INJURY PERSONAL INJURY 0 3 IO Airplane 0 365 Personal Injury -0 3 I 5 Airplane Product Product Liability
Liability 0 367 Health Care/ 0 320 Assault. Libel & Pharmaceutical
Slander Personal lnJury 0 330 Federal Employers' Product Liability
Liability 0 368 Asbestos Personal 0 340 Manne Injury Product 0 345 Manne Product Liability
Liability PERSONAL PROPERTY 0 350 Motor Vehicle 0 3 70 Other Fraud 0 355 Motor Vehicle '.J 3 71 Truth m Lending
Product L1ab11ity 0 380 Other Personal 0 360 Other Personal Property Damage
Injury 0 385 Propeny Damage 0 362 Personal Injury - Product Liability
Medical Malpractice CMLRJGHTS PRISONER PETITIONS
0 440 Other Civil Rights Habeas Corpus: 0 441 Voting 0 463 Alien Detainee 0 442 Employment 0 S 10 Motions to Vacate 0 443 Housing/ Sentence
Accommodations 0 S 30 General 0 445 Amer w/Disab1ht1es - 0 535 Death Penalty
Employment Other: 0 446 An1er. w/Disabthties - 0 540 Mandamus & Other
Other 0 550 Civil Rights 0 448 Education 0 555 Prison Condition
0 560 Civil Detainee -Conditions of Confinement
V. ORIGIN /1'/a,·ean 'X"inOneHoxOn(11
( For D11•ermy C'a.,e., Onl>) and One Box for Defendant) PTF DEF PTF DEF
Citizen of This State IX I 0 I Incorporated or Principal Place 0 4 04 of Business In This State
C111zen of Another State 0 2 0 2 Incorporated and Principal Place 0 s 0 S of Business In Another State
Citizen or Subiect of a O 3 0 3 Foreign Nation 0 6 0 6 Fore1 n Coun
Click here for Nature of Sutt Code Descrtottons.
FORFE ,w~•~EN,. TY KAN ._y UTff.-.ll STATUTES
0 625 Drug Related Seizure 0 422 Appeal 28 USC 158 0 375 False Claims Act of Propeny 21 USC 881 0 423 Withdrawal 0 376 Qui Tam (31 USC
0 690 Other 28 use 1s1 3729(a)) O 400 State Reapponionment
. • w D • -.;.-·1·:"llli 0 410 Antitrust QI!: 820 Copynghts 0 430 Banks and Banking 0 830 Patent 0 450 Commerce 0 835 Patent - Abbreviated 0 460 Deponation
New Drug Application 0 470 Racketeer Influenced and 0 840 Trademark Corrupt Organizations
AH .. K ,• N 1.111. ,1111 IJU ,, 0 480 Consumer Credit 0 7 IO Fair Labor Standards 0 861 HIA ( 1395ft) (IS USC 1681 or 1692)
Act 0 862 Black Lung (923) 0 485 Telephone Consumer 0 720 Labor/Management 0 863 DIWC/DIWW (40S(g)) Protection Acl
Relations 0 864 SSID Title XVI 0 490 Cable/Sat TV 0 740 Railway Labor Act 0 865 RSI (40S(g)) 0 850 Secunues/Commodities/ 0 75 I Family and Medical Exchange
Leave Act 0 890 Other Statutory Actions 0 790 Other Labor Litigation FEDERAL TAX SUITS 0 891 Agricultural Acts
0 791 Employee Retirement 0 870 Taxes (U S. Plaintiff 0 893 Environmental Matters Income Security Act or Defendant) 0 895 Freedom of lnfonnation
0 871 IRS-Third Pany Act 26 USC 7609 O 896 Arbitration
0 899 Administrative Procedure IMMIGRATION Act/Review or Appeal of
0 462 Naturalization Application Agency Decisoon 0 465 Other Immigration 0 950 Constitutionality of
Actions State Statutes
0 I Original O 2 Removed from Proceeding State Court
0 3 Remanded from Appellate Court
0 4 Reinstated or Reopened
0 5 Transferred from Another District (specify)
0 6 Multidistrict Litigation -Transfer
0 8 Multtdistrict Litigation -
Direct File
I
Cifr.,1f.s.E!~i VI. CAUSE OF ACTION i---,;...;.....;;..;..;;..;..,;;.,;......,,i....;;..;;..;;....;;..;..;;..;;..;,i ________________________ _
Brief de~crmtloll of cause b f , · h · · f · · ·
VII. REQUESTED IN COMPLAINT:
VIII. RELATED CASE(S) IFANY
D.ATE LJecember 20, 2019
copyngm mmngement; reach o contract, uniust enr1c ment, tort1ous mtere erence, permanent m1unct1on
0 CHECK IF THIS IS A CLASS ACTION DEMAND$ CHECK YES only if demanded in complaint
UNDER RULE 23, F.R Cv P JURY DEMAND: ~ Yes ONo
(See 1m·1ruc:lfom'): DOCKET NUMBER
RNEY OF RECORD
FOR OFFICE USE ONL \'
RECEIPT# AMOUNT JUDGE MAG. JUDGE
Case 4:19-cv-00925-KGB Document 1-1 Filed 12/20/19 Page 1 of 1