Upload
dangtruc
View
216
Download
2
Embed Size (px)
Citation preview
1
HIMACHAL PRADESH STATE ELECTRICITY BOARD LIMITED
BID DOCUMENTS
FOR
“STATIC EXCITATION SYSTEM AND DIGITAL AVR”
FOR
(3x5.65 MW)
ANDHRA HYDRO-ELECTRIC PROJECT
(Bid Specification No. HPSEBL/CEG/DB-3-4/2012)
Prepared by Checked by Approved by
(Rajiv Kumar Verma) (Rajesh Kapoor) (Rajnish Kumar Sharma)
Assistant Executive Engineer Superintending Engineer Chief Engineer
Chief Engineer (Gen.)
HPSEBL, Sunder Nagar
Distt. Mandi (H.P.) – 175 019.
Tel: - 01907 – 265337, Fax: 01907-265338, Email –[email protected]
Month:- Oct./2012 Rs. 1500/-
2
TABLE OF CONTENTS
Volume 1
Section No. I Information for Bidders (INFB)
Section No. II Instruction to Bidder (ITB)
Section No. III General Conditions of Contract (GCC)
Section No. IV Forms and Procedure (FP)
1 Bid Forms
2 Attachments Including Security
Forms
3 Price Schedule
4 Form of 'Notification of Award Contract' for supply of Plant and Equipment and their installation Services.
5 From of Contract Agreement.
6 Performance Security Forms.
7 Form of Completion Certificate. 8 Form of Operational Acceptance
Certificate.
Section No. V Technical Specification
3
SECTION-I
Information For Bidders (INFB)
4
INDEX
INFORMATION FOR BIDDERS
TABLE OF CONTENTS
CLAUSE NO. PARTICULARS PAGE NO. 1.0 INTRODUCTION 5 2.0 PROJECT DETAILS 5
3.0 TRANSPORT LIMITATION 5
4.0 COMMUNICATION FACILITIES & WORK SITE 5
5.0 CLIMATE/WEATHER 6
6.0 SEISMICITY OF THE PROJECT AREA 6
7.0 LABOUR AVAILABILITY 6
8.0 TEMPORARY/TRANSIT ACCOMODATION 6
9.0 ELECTRIC POWER 6
10.0 MATERIAL AND WORKSHOP FACILITIES 6
11.0 LABOUR LICENCE 6
12.0 MEDICAL FACILITIES 6
5
INFORMATION FOR BIDDERS
1.0 INTRODUCTION
HPSEB Ltd. has undertaken the execution of dismantling/removing of the existing excitation
system and detailed design, manufacture, shop assembly & testing, & commissioning of three (3)
numbers static excitation and Digital AVR systems complete with accessories to be installed in
the 3 X 5.65 MW Andhra Power House.
The scope of work of this tender includes all works necessary for dismantling/removing the
existing excitation system including carriage, stacking at Owner’s store/ yard and detailed design,
manufacture, shop assembly & testing, comprehensive insurance, delivery, erection, testing &
commissioning at site, field acceptance tests of static excitation system before handing over to the
owner/HPSEB Ltd. and guaranteed for two years of three (3) numbers static excitation and
Digital AVR systems complete with accessories, equipment, devices, instruments, cabling and
wiring etc. including all services, labour, tools and tackles in all respects as per technical
specifications.
2.0 PROJECT DETAIL
ANDHRA POWER HOUSE is located at Chirgaon near Rohru in Distt. Shimla. The Power
House commissioned in 1987 has 3 Units each of 5.65 MW. The average annual generation of
this Power House ranges between 60 MU to 70 MU, against designed potential of 87 MU. The
reservoir capacity is 45450 Cum.
3.0 TRANSPORT LIMITATION
3.1 The transport limitation by road from Shimla to the Plant Site would be the governing factor in
respect of the permissible package size and weight. Bidder should consider all factors as can be
envisaged for transportation of equipment to avoid and overcome the hindrances/ limitations
on existing road on account of weather conditions and any other reasons without affecting
the schedule .
The project areas are situated in earthquake zone V as per BIS 1893(1984). Hence, the equipment
shall have to be suitable to withstand safely and not to maloperate under earthquake forces
corresponding to zone V.
3.2 The Bidder at his cost shall be responsible for all safety aspects during execution of the works. As
such necessary protection barriers, warning signals & devices, posting of flags & flagmen at
desired locations on the routes are to be used by Bidder.
3.3 The Bidder shall deemed to have familiarised himself with the nature, environment, conditions
and any limitations or restrictions on road to be used by him during the period of the Contract.
The Bidder shall also take into consideration access limitations that may results in the event of
slips/slides of hill slopes or due any other reasons arises due to the local climatic/geographical
conditions. HPSEBL shall not entertain any claim from the Bidder on this account.
4.0 COMMUNICATION FACILITIES AT WORKS SITE The work site is well connected with STD & ISD facilities.
6
5.0 CLIMATE / WEATHER The rainfall is scanty. The south-west monsoon precipitation during June to September is
generally not heavy but at some times may contribute significantly towards flood run off. The
winter precipitation falls mostly as rain or sometimes snow depending upon the altitude and other
meteorological conditions. Summers are warm and winter temperature falls upto -12 degree
Celsius.
6.0 SEISMICITY OF THE PROJECT AREA The project area falls within isoseismal IX of Rossi-Forrel scale of intensity. According to Indian
standard code no.1893 of 1972, the area has been placed in zone V and a suitable factor of safety
as required has to be incorporated in the design of engineering structures and equipment.
7.0 LABOUR AVAILABILITY No skilled labour is available locally. Most of the skilled labour has to be brought from outside.
However, the Bidder shall make maximum efforts to explore the availability of local labour of
various categories and employ them to the extent possible. Liaison and good relation with locals
is very essential. To accommodate labour, Bidders shall have to make their own arrangement
8.0 TEMPORARY / TRANSIT ACCOMMODATION There is acute shortage of accommodations nearby project site. HPSEB has
constructed/developed some accommodation at different locations of the project for its own
employees. Bidder has to make his own arrangement for the temporary/transit accommodation.
9.0 ELECTRIC POWER Construction power at 11kV/415Volts shall be provided to the contractor to various sites,
colonies, offices etc. Each supply point shall be treated as separate connection. Arrangement for
further distribution of power to the contractor's sites, plants equipment and machinery,
workshop, colonies, offices etc. from the point of supply shall be made by the contractor at his
own cost. The electric energy shall be measured by a suitable meter installed at the point of
supply.
The contractor will adhere strictly to provision of Indian Electricity Act 1910, Electricity
(Supply) Act 1948, Indian Electricity Rules 1956, HPSEBL's abridged condition of supply and
HPSEBL's schedule of tariff.
.
10.0 MATERIAL AND WORKSHOP FACILITIES 10.1 All the consumable material required for the works, shall have to be arranged & provided by the
Bidder and included in the quoted prices.
10.2 Nearest workshop facilities for carrying out major works facilities either at Chandigarh, Ludhiana
or Batala shall be available.
11.0 LABOUR LICENCE The Bidder shall be required to obtain labour licence for deployment of labour from competent.
11.2 The Bidder shall strictly adhere to the labour laws and minimum wage act prevailing in the State
of Himachal Pradesh.
12.0 MEDICAL FACILITIES
The Bidder shall provide necessary medical facilities at the project site at his own expenses for
his workers.
7
SECTION-II
Instructions to Bidders (ITB)
8
INDEX
INSTRUCTIONS TO BIDDERS
TABLE OF CONTENTS
CLAUSE NO. PARTICULARS .PAGES
A. INTRODUCTION
1.0 GENERAL 9
2.0 SCOPE 9
3.0 ELIGIBILITY AND QUALIFYING REQUIREMENTS 9
4.0 COST OF BINDING 9
5.0 LOCAL CONDITIONS 9
B. BID DOCUMENTS
6.0 CONTENT OF BID DOCUMENTS 10
7.0 TIME SCHEDULE 10
C. PREPARATION OF BIDS
8.0 LANGUAGE OF BID 11
9.0 DOCUMENTS COMPRISING THE BIDS 11
10.0 BID FORM AND PRICE SCHEDULE 11
11.0 BID PRICES 12
12.0 CURRENCY OF BID 12
13.0 BID VALIDITY PERIOD 12
14.0 BID SECURITY 12
15.0 FORMAT AND SIGNING OF THE BID 13
D. SUBMISSION OF BIDS
16.0 SEALING AND MARKING OF BIDS 13
17.0 DEAD LINE FOR SUBMISSION OF BIDS 14
18.0 LATE BIDS 14
E. BID OPENING AND EVALUATION
19.0 OPENING OF BIDS BY OWNER 14
20.0 CLARIFICATION OF BIDS 15
21.0 CORRECTION OF ERRORS 15
22.0 EVALUATION AND COMPARISON OF BIDS 15
F. AWARD OF CONTRACT
23.0 OWNER'S RIGHT TO ACCEPT ANY BID AND TO REJECT
ANY OR ALL BIDS 16
24.0 AWARD CRITERIA 16
25.0 NOTIFICATION OF AWARD 16
26.0 SIGNING THE CONTRACT AGREEMENT 16
27.0 CONTRACT PERFORMANCE SECURITY 16
9
INSTRUCTIONS TO BIDDER A. Introduction
1.0 GENERAL
1.1 Himachal Pradesh State Electricity Board, the Owner, has issued an invitation for Bidder (IFB)
and will receive Bids, from eligible Bidders, for the works mentioned in the schedule of works.
2.0 SCOPE
The scope of work of this bid includes all works necessary for dismantling/removing the existing
excitation system including carriage, stacking at Owner’s store/ yard and detailed design,
manufacture, shop assembly & testing, comprehensive insurance, delivery, erection, testing &
commissioning at site, field acceptance tests of static excitation system before handing over to the
owner/HPSEB Ltd. and guaranteed for two years of three (3) numbers static excitation and
Digital AVR systems complete with accessories, equipment, devices, instruments, cabling and
wiring etc. including all services, labour, tools and tackles in all respects as per technical
specifications and consideration.
3.0 ELIGIBILITY AND QUALIFICATION REQUIREMENTS
a) The Bidders should be a contracting firm well experienced in the design, supply,
installation & commissioning of static excitation and Digital AVR systems. b) The Bidders should have a team of qualified professionals & highly skilled artisans.
c) The Bidders shall have sufficient and adequate tools & tackles for executing the work.
d) The Bidders should have completed the execution of at least two (2) such contracts
valued not less than Rs.60.00 lacs each in the past 5 years and the same must be in
successful operation for at least 2 years. Performance certificates as proof of the same
shall be supplied. Bids not accompanying the performance certificates from the previous
customers shall be summarily rejected.
4.0 COST OF BIDDING
4.1 All costs and expenses incidental to preparation and submission of the Bids including pre-award
discussion with the interesting Bidders, technical and other documentation etc., shall be to the
account of the Bidders. Owner will in no case be responsible or liable for these costs and
expenses, regardless of the conduct or outcome of the Biding process.
5.0 LOCAL CONDITIONS
5.1 It will be imperative on each Bidders to fully inform himself of all local conditions and factors,
which may have any effect on the performance of the contract covered under these specifications
and documents. In their own interest, the Bidders are particularly requested to familiarise
themselves with the latest amended Income-tax Act, Companies Act, Custom Act, Sales Tax,
Service Tax Act and other related acts and laws prevalent in India. The Owner shall not entertain
any request for clarifications from the Bidders, regarding such local conditions. The Bidders are
also advised to visit the sites to judge the quantum of work before submitting their Bids.
5.2 It must be understood and agreed that such factors have properly been investigated and
considered while submitting the proposals. No claim whatsoever including those for financial
adjustment to the contract awarded under these specifications and documents will be entertained
by the Owner. Neither any change in the time schedule of the contract nor any financial
10
adjustments arising thereof shall be permitted by the Owner which are based on the lack of such
clear information or its effect on the contract.
5.3 The Bidders is strongly advised to visit and examine the sites of work and its surroundings
including approaches to project & work site, space for storage, ventilation, power and
communication and obtain for himself on his own responsibility all information that may be
necessary for preparing the Bid and entering into a contract. The cost of visiting the site shall be
at Bidder's own expense. The Owner will assist interested Bidders to see and inspect the site of
works.
B. Bid Documents
6.0 CONTENT OF BID DOCUMENTS 6.1 The Biding procedures, contract terms and technical requirements are prescribed in the Bid
documents. The Bid Documents will include the following:-
Section no. Name of Document.
I Information for Bidders (INFB).
II Instruction to Bidders (ITB).
III General Condition of Contract (GCC).
IV Forms and Procedure (FP).
1. Bid Forms
2. Attachments Including Security Forms
3. Price Schedule
4 Form of 'Notification of Award Contract' for supply of Plant and
Equipment and their installation Services.
5 From of Contract Agreement.
6. Performance Security Forms.
7 Form of Completion Certificate.
8 Form of Operational Acceptance Certificate.
V Technical Specifications.
6.2 The Bidders is expected to examine all instructions, forms, schedules, terms, specifications and
other information in the Bid Documents. Failure to furnish all information required by the Bid
Documents or submission of a Bid not substantially responsive to the Bid Documents will be at
Bidder's risk and may result in rejection of its Bid.
7.0 TIME SCHEDULE 7.1 The basic consideration and the essence of the contract shall be the strict adherence to the time
schedule for performing the works under the proposal/contract. The works awarded under the
Contract shall have the Commissioning period of Six months from the date of award of
work to contractor by HPSEB.
C. Preparation of Bids
11
8.0 LANGUAGE OF BID The Bid prepared by the Bidders and all correspondence and documents relating to the Bid
exchanged by the Bidders and the Owner shall be written in English. Supporting documents and
printed literature furnished by Bidders in any other language shall be accompanied by its true and
faithful translation of the pertinent passages in English. For the purpose of interpretation of the
Bid, the English translation shall govern. Failure to comply with this may disqualify a Bid.
9.0 DOCUMENTS COMPRISING THE BID 9.1 Bid submitted by the Bidders shall comprise the following documents:
a) Bid Form duly completed and signed by the Bidders, together with all Attachments
identified in ITB sub-clause 9.2 below.
b) Price Schedules duly completed by the Bidders.
9.2 Each Bidders shall submit with its Bid the following attachments.
(a) Attachment 1: Bid Security/earnest money deposit.
A Bid Security furnished in accordance with ITB Clause 14.0 (Bid Security).
(b) Attachment 2: Power of Attorney.
A power of attorney, duly authorised by a Notary Public, indicating that the person(s)
signing the Bid has the authority to sign the Bid and thus that the Bid is binding upon the
Bidders during the full period of its validity in accordance with ITB Clause 15.0 (Format
and Signing of Bids).
(c) Attachment 3: Bidder's Qualifications & Eligibility criteria.
(d) Attachment 4: List of Erection Tools & commissioning instruments which the Bidders
proposes to bring to site in case the contract is awarded to him.
(e) Attachment 5 : Milestone schedule showing the timing & sequence of all key activities
necessary for successful completion of the contract and giving important Mile Stones.
(f) Attachment 6 & 6A: Deviations
Deviations, if any, from the terms and conditions or Technical Specifications shall be
listed in the following attachments of the bid:-
i) Deviations in commercial terms and conditions: - Attachment- 6
ii) Deviations in technical specifications: - Attachments- 6A
The Bidder shall also provide the additional price, if any, for withdrawal of the deviations.
Bidders may further note that except for deviations listed in Attachment 6 and Attachment 6A,
the bid shall be deemed to comply with all the requirement in the bidding documents and the
Bidders shall be required to comply with all such requirements of bid documents and technical
specifications without any extra cost to the Owner irrespective of any mention to the contrary,
any where else in the bid.
Bidder may further note that deviations in commercial terms and conditions shall be listed in
attachment 6 & technical in attachment 6A respectively.
10.0 BID FORM AND PRICE SCHEDULE
12
The Bidders shall complete the Bid Form and the appropriate Price Schedules furnished in the
Bid Documents as indicated therein and in the Subsection "Bid Form and Price Schedule" of the
Bid Documents, following the requirements of ITB Clause, 11.0 and 12.0.
11.0 BID PRICES 11.1 Bidders quoting a system of pricing other than that specified run the risk of rejection.
11.2 The Bidders shall fill in prices for all items as specified in the Bid Form. Items against which no
price is entered by the Bidders will not be paid by the Owner when executed and shall be deemed
to be included in the other prices in the "Bid Form and Price Schedules".
11.3 The rates and amounts shall be quoted in decimal in such a manner that no interpolation is
possible. Corrections, if any, shall be made by crossing out, initialling, dating and rewriting.
Corrections should not be carried out by applying correcting fluid.
11.4 Bidders shall give a breakdown of the prices in the manner and details called for in the Price
Schedule.
11.5 Price quoted by the Bidders shall be “FIRM” and no price variation shall be paid.
12.0 CURRENCIES OF BID 12.1 Price shall be quoted in Indian Rupees only.
13.0 BID VALIDITY PERIOD 13.1 Bids should be kept valid for acceptance for a period of six (6) calendar months from the date of
opening of Bids prescribed in ITB Clause 19.0 (Opening of Bids by Owner).
13.2 In exceptional circumstances, prior to expiry of the original Bid validity period, Owner may
request the Bidders for a specified extension in the period of validity. The request and the
responses thereto shall be made in writing or by fax. A Bidders may refuse the request without
forfeiting his Bid Security. A Bidders agreeing to the request will neither be required nor
permitted to modify his Bid, but will be required to extend the validity of his Bid guarantee
correspondingly. The provision of ITB Clause 14.0 (Bid Security), hereof regarding discharge
and forfeiture of Bid Security shall continue to apply during the extended period of Bid validity.
14.0 BID SECURITY
14.1 Pursuant to ITB Clause 9.0 (Document Comprising the Bid), the Bidders shall deposit bid
Security of amount Rupees Seventy Five thousand only. Bid security of Rs. 50,000/- (Fifty
thousand) shall be furnished in the shape of a Crossed bank draft of any Indian Nationalized
Bank, drawn in favour of the Accounts Officer, O/O the Chief Engineer (Generation), Sunder
Nagar – 175 019 and payable at Sunder Nagar – 175 019 (H.P.) and for the balance amount an
irrevocable Bank Guarantee from an Indian Nationalized Bank valid for (Twelve ) 12 months
from the date of the opening of the bid, in favour of the Accounts Officer, O/O the Chief
Engineer (Generation), Sunder Nagar – 175 019shall be furnished.
14.2 Bid Security is required to protect Owner against risk of Bidder's conduct which would warrant
the security's forfeiture, pursuant to ITB Clause 14.7.
14.3 Any Bid not secured in accordance with ITB Clause 14.1 above shall be rejected by the Owner as
being non responsive.
14.4 Unsuccessful Bidder's Bid Security will be discharged/ returned as promptly as possible as but
not later than thirty (30) days after expiration of the period of Bid validity prescribed by the
Owner pursuant to ITB Clause 13.0 (Bid Validity Period).
13
14.5 Successful Bidder's Bid Security will be discharged upon execution of the contract deed, pursuant
to ITB Clause 26.0 (Signing of Contract Agreement), and furnishing the required performance
security pursuant to ITB Clause 27.0 (Contract Performance Security).
14.6 No interest shall be paid by the Owner on the Bid Security.
14.7 The Bid Security may be forfeited:
(i) if the Bidders withdraws or modifies unilaterally his Bid during the period of Bid
validity;
or
(ii) if the Bidders does not accept the correction of his Bid price pursuant to ITB
Clause 21.0 ( Corrections of Error).
(iii) in the case of a successful Bidders, if the Bidders fails within the specified time limit to :
(a) accept the letter of award;
or
(b) sign the Contract Deed;
or
(c) furnish the required contract performance security.
15.0 FORMAT AND SIGNING OF THE BID 15.1 The Bidders shall prepare an original and two (2) copies/sets of the Bid clearly marking each one
as "Original Bid", "Copy No. 1", "Copy No.2". In the event of any discrepancy between them the
original shall govern.
15.2 The original and all copies of the Bid, each consisting of the documents listed in ITB Clause 9.0
(Documents Comprising Bid) , shall be typed or written in indelible ink and shall be signed by the
Bidders or a person or persons authorised to signing the Bid.
15.3 The name of all persons or persons signing the Bid should also be typed or printed below the
signature. All pages of the Bid, except for un-amended printed literature shall be initialled by the
person or persons signing the Bid.
15.4 Satisfactory evidence of authority of the person signing on behalf of the Bidders shall be
furnished with the Bid in the form of a Power of Attorney, duly authorised by a Notary Public,
indicating that the persons signing the Bid have the authority to sign the Bid and that the Bid is
binding upon the Bidders during the full period of its validity. This shall be submitted as
Attachment 2 to the Bid under ITB sub-clause 9.2 (b) (Power of Attorney).
15.5 The Bidder's name stated on the proposal shall be the exact legal name of the firm.
15.6 Any interlineations, erasures or overwriting shall only be valid if they are initialled by
signatory(ies) to the Bid.
15.7 Bids not conforming to the above requirements of signing may be disqualified.
D. Submission of Bids
16.0 SEALING AND MARKING OF BIDS.
16.1 The Bidders must submit the Bid in the following two separate sealed envelopes duly marking
envelopes as "Original Bid" and "Copy no.1 &2- ". The envelopes shall then be sealed in an outer
envelope.
(i) Bid Security
First Envelope.
(ii) Techno-Commercial and Price Bid Proposal (1 Original + 2
Copies) along with duly filled (wherever required) and signed
copies of conditions of contract, General technical specifications.
Second Envelope.
14
16.2 The inner and outer envelopes shall:
(a) be addressed to the Chief Engineer (Gen.), HPSEBL, Sunder Nagar Distt Mandi H.P.
and;
(b) super scribed as Proposal for Design, Engineering, Fabrication, Supply, Transportation,
Insurance, Installation, Erection, Commissioning & Testing of Static Excitation and
Digital AVR System and the statement "DO NOT OPEN BEFORE “30.10.2012, 15.00
hrs.”
16.3 The inner envelopes shall also indicate the name and address of the Bidders so that the Bid can be
returned unopened in case it is declared "late".
16.4 If the outer envelope is not sealed and marked as required by ITB sub-clause 16.2 above, the
Owner will assume no responsibility for the Bid's misplacement or premature opening. If the
outer envelope discloses the Bidder's identity, the Owner will not guarantee the anonymity of the
Bid submission, but this disclosure will not constitute grounds for Bid rejection.
17.0 DEAD LINE FOR SUBMISSION OF BIDS 17.1 Bids must be received in the office of the “Chief Engineer (Gen.), HPSEBL, Sunder Nagar
Distt Mandi H.P. " on or before 1300 hours (IST) of 30.10.2012”. In the event of the date of
submission of Bids being declared as holiday for the Owner, the Bids will be received upto the
appointed time on the next working day.
17.2 The Bidders has the option of sending the Bid by registered post/courier or by submitting the Bid
in person. Bids submitted by fax/telegram / telex letter shall not be accepted. No request from any
Bidders to the Owner to collect the proposal from airlines, cargo agents etc. shall be entertained.
17.3 The Owner may at its discretion, extend the dead line for submission of Bids, in which case all
rights and obligations of the Owner and the Bidders previously subject to the original dead line
shall thereafter be subject to the new deadline as extended.
18.0 LATE BIDS 18.1 Bids submitted after the time and date fixed for the receipt of Bids as set in ITB Clause 17.0 shall
be rejected and such Bids if so desired by the said Bidders may be permitted to be collected back
by such Bidders provided such requests are received by the Owner within fifteen (15) days from
the date of Bid opening.
E. Bid Opening and Evaluation
19.0 OPENING OF BIDS BY OWNER
19.1 All Bids received within the stipulated time will be opened in the office of the “Chief Engineer
(Gen.), HPSEBL, Sunder Nagar Distt Mandi H.P. " by the officer(s) duly authorised by the
Owner for this purpose at 15.00 hrs (IST) on 30.10.2012 in the presence of the Bidder's
authorised representatives who may wish to attend. In the event of specified date of Bid opening
being holiday for Owner, the Bids shall be opened at the appointed time and location on the next
working day.
15
19.2 Bidder's authorised representative (upto two persons) may attend the Bid opening and they have
to sign a register provided by the Owner for evidencing their participation. No electronic
recording device/mobile phones etc., shall be permitted during the Bid opening.
19.3 The techno-commercial and price Bid (second envelope) of only those Bidders shall be opened
whose Bids security envelope (first envelope) found to contain (after opening) the Bid Security of
requisite value in acceptable form. The Bids with Bid Security deficient in value and/or form will
not be opened further and Bid envelopes of such Bidders will be returned unopened.
19.4 The officer(s) of the Owner authorised for opening of Bids will announce the Bidder’s names, the
presence or absence of the requisite Bid Security, Bid Prices, any discounts, the presence of any
alternative Bid and other such details as the said officers at their discretion may consider
appropriate.
19.5 Bids (sent pursuant to ITB sub-clause 17.2) that are not opened and read out at Bid opening will
not be considered for further evaluation, regardless of the circumstances.
20.0 CLARIFICATION OF BIDS To assist in the examination, evaluation and comparison of Bids the Owner, may at its discretion
ask any Bidders for clarification of his Bid, including break-up of unit rates. The request for
clarification and the response shall be in writing or by fax, but no change in the price or
substance of the Bid shall be sought, offered or permitted except as required to confirm
the correction of arithmetic errors discovered by the Owner during the evaluation of the Bids in
accordance with ITB Clause 21.0 (Correction of Error) hereof.
21.0 CORRECTION OF ERRORS 21.1 The errors/ discrepancies in respect of the specified amount in Price Bid Part-of Bid Proposal
Sheets for an individual item and / or sub-item and or in the sub-total of a schedule and/or in the
Grand total of a schedule and/or in the lump-sum price of the package either due to discrepancy
between figures and words and/or simple arithmetical error while adding and/or multiplying
and/or due to wrong extension of unit rates etc ; the error will be rectified and computed by
Owner as per the following method: -
(i) In case of discrepancy between figure and words, the value specified in the words will be
considered for computation.
(ii) Firstly, the unit rates in words will be considered for computation.
(iii) In case unit rates are not indicated in words then unit rates indicated in figure will be
considered and will be used for deriving the amount from the quantities specified in the
Bid documents.
(iv) In case error is due to wrong extension of quantities, the quantities as specified in the Bid
documents will be considered and multiplied by the quoted unit rates to obtain the
amount. The amounts will be computed as per the extension of amount of individual
item, sub-item, sub-total of a schedule, grand total of a schedule and lump sum price of
the package based on the above consideration.
21.2 After computation of the amounts as above, the values as computed and as quoted will be
compared and higher of the two will be considered for the purpose of evaluation of Bid and lower
values will be considered for the purpose of award/payment (in case of successful Bidders). If the
Bidders does not accept the above consideration, his Bid will be rejected and the Bid Security
may be forfeited.
22.0 EVALUATION AND COMPARISON OF BIDS 22.1 The Bids will be evaluated by the Owner to ascertain the lowest evaluated, technically and
commercially responsive Bid for the complete scope of work, as detailed in the Bid Documents.
16
F. Award of Contract
23.0 OWNER'S RIGHT TO ACCEPT ANY BID AND TO REJECT ANY OR ALL BIDS The Owner reserves the right to accept or reject any Bid, and to annul the Bid process and reject
all Bids at any time prior to award of contract, without thereby incurring any liability to the
affected Bidders or Bidders or any obligation to inform the affected Bidders or Bidders of the
grounds for Owner's action.
24.0 AWARD CRITERIA 24.1 Subject to ITB Clause 23.0 (Owners Right to Accept any Bid) hereof, the Owner will award the
contract to the Bidders whose Bid has been determined to be substantially responsive to the Bid
Documents and who has offered the lowest Evaluated Bid Price pursuant to ITB Clause 22.0
(Evaluation and Comparison of Bid), further provided that such Bidders has been determined to
be eligible/ qualified to perform the contract satisfactorily.
24.2 The Bidders would be required to comply with all the requirements of Bid Documents failing
which his Bid Security will be forfeited.
24.3 The Owner reserves the right to vary the quantity or items of work altogether at the time of
Award of Contract.
25.0 NOTIFICATION OF AWARD 25.1 Prior to the expiration of the period of Bid validity, the Owner will notify the successful Bidders
in writing by registered letter or by fax to be confirmed in writing by registered letter that his Bid
has been accepted. The notification of award will constitute the formation of the Contract.
25.2 On furnishing of a performance security by the successful Bidders, pursuant to ITB Clause 27.0
(Contract Performance Security), of Owner will promptly notify each unsuccessful Bidders and
will discharge its Bids security.
26.0 SIGNING THE CONTRACT AGREEMENT 26.1 Within (15) fifteen days of receipt of the Letter of award, on a date and time mutually agreed
upon, the successful Bidders or his authorised representative shall attend the office of the Owner
for signing of the Agreement.
26.2 Failure on the part of the successful Bidders to comply with the requirements this Clause will
constitute sufficient grounds for the annulment of the award and forfeiture of the Bid Security.
27.0 CONTRACT PERFORMANCE SECURITY 27.1 Within (15) fifteen days after receipt of letter of award but not later than the signing of the
Contract Agreement, the successful Bidders shall be required to furnish to the Owner, a Contract
Performance Security in the form of an irrevocable Bank Guarantee for an amount equivalent to
10% (ten percent) of the contract price, as per proforma annexed to Bid document for the faithful
performance of contract in accordance with the conditions of the contract.
27.2 Failure of the successful Bidders to comply with the requirement of ITB Clause 26.0 (Signing of
Contract Agreement) and 27.0 (Contract Performance Security) shall constitute sufficient grounds
for the annulment of the award and forfeiture of the Bid Security, in which event Owner may
make the award to the next lowest evaluated Bidders or call for new Bids.
27.3 Should the Contract period, for whatever reason be extended, the Bidders, shall at his own cost,
get the validity period of Bank Guarantee in respect of performance security furnished by him
extended and shall furnish the extended/revised Bank Guarantee to Owner before the expiry date
of the Bank Guarantee originally furnished.
17
SECTION-III
General Conditions of Contract (GCC)
18
INDEX
GENERAL CONDITIONS OF CONTRACT
TABLE OF CONTENTS
CLAUSE NO. PARTICULARS PAGE NO.
1.0 DEFINITIONS 19
2.0 CONTRACT DOCUMENTS 20
3.0 INTERPRETATION 20
4.0 NOTICES 21
5.0 GOVERNING LAW 21
6.0 ARBITRATION 21
7.0 SCOPE OF WORK 21
8.0 TIME FOR COMMENCEMENT AND COMPLETION 22
9.0 CONTRACTOR'S RESPONSIBILITIES 22
10.0 OWNER'S RESPONSIBILITIES 22
11.0 CONTRACT PRICE 22
12.0 TERMS OF PAYMENT 22
13.0 SECURITIES 22
14.0 TAXES AND DUTIES 23
15.0 DEDUCTION FROM CONTRACT PRICE 23
16.0 CONFIDENTIAL INFORMATION 24
17.0 REPRESENTATIVES 24
18.0 WORK PROGRAMME 25
19.0 MAINTENANCE 26
20.0 . TEST AND INSPECTION 28
21.0 COMPLETION OF THE WORKS 28
22.0 COMMISSIONING AND OPERATIONAL ACCEPTANCE 29
23.0 COMPLETION TIME GUARANTEE 29
24.0 DEFECT LIABILITY 30
25.0 LOSS OF OR DAMAGE TO PROPERTY 31
26.0 INSURANCE 31
27.0 CHANGES IN LAWS AND REGULATIONS 31
28.0 FORCE MAJEURE 31
29.0 WAR RISKS 32
30.0 EXTENSION OF TIME FOR COMPLETION 33
31.0 SUSPENSION 33
32.0 TERMINATION 33
33.0 ASSIGNMENT 35
34.0 TEST SERVICE PERIOD 35
19
GENERAL CONDITIONS OF CONTRACT
1.0 DEFINITIONS 1.1 The following words and expressions shall have the meanings hereby assigned to them:
"Completion" means that the works detailed in the schedule of quantities and prices (or a
specific part thereof where specific parts are specified in the Contract Document) have been
completed operationally and structurally and put in a tight and clean condition, and that all work
in respect of Pre-commissioning of the Works or such specific part thereof has been completed.
"Contract" means the Contract Agreement entered into between the Owner and the Contractor,
together with the Contract Documents referred to therein; they shall constitute the Contract, and
the term "the Contract" shall in all such documents be construed accordingly.
"Contract Documents" means the documents listed in Article 1.1 (Contract Documents) of the
Form of Contract Agreement (including any amendments thereto).
"Contractor" means the person whose Bid to perform the Contract has been accepted by the
Owner and is named as such in the Contract Agreement, and includes the legal successors or
permitted assigns of the Contractor.
"Contractor's Equipment" means all plant, works, equipment, machinery tools, apparatus,
appliances or things of every kind required in completion of works that are to be provided by the
Contractor.
“Contract Price " means the sum specified in Article 2.1(Contract Price) of the Contract
Agreement, subject to such additions and adjustments thereto or deductions there from, as may be
made pursuant to the Contract.
"Contractor's Representative" means any person nominated by the Contractor and named as
such in the Contract Document as per GCC sub-clause 17.2 (Contractor's Representative) hereof
to perform the duties delegated by the Contractor.
"Day" means calendar day of the Gregorian calendar.
"Defect Liability Period" means the period of validity of the warranties given by the Contractor
commencing at completion of the Works or a part thereof, during which the Contractor is
responsible for defects with respect to the Works (or the relevant part thereof) as provided in
GCC Clause 24.0 (Defect Liability) hereof.
"Effective Date" means the date from which the Time for completion shall be determined as
stated in Article 3 (Effective Date for Determining Time for Completion) of the Form of Contract
Agreement.
"Engineer in-charge" means the person appointed by the Owner in the manner provided in GCC
sub-clause 17.1 (Engineer-in-Charge) hereof to perform the duties delegated by the Owner.
"Works" means the services to be carried out by the Contractor under the Contract.
"GCC" means the General Conditions of Contract hereof.
"Government" means Government of India or Government of Himachal Pradesh and ,
(i) "Government of India" means President of India and his successors.
(ii) "Government of Himachal Pradesh" means Governor of Himachal Pradesh and his
successors.
"Services" means those entire services which are to be provided by the Contractor under the
Contract.
"Month" means calendar month of the Gregorian calendar.
"Operational Acceptance" means the acceptance by the Owner of the Works (or any part of the
Works where the Contract provides for acceptance of the Works in parts), which certifies the
Contractor's fulfillment of the Contract in respect of the works in the scope of the Contract.
"Owner / HPSEBL" means the Himachal Pradesh State Electricity Board Limited having its
registered office at Vidyut Bhawan Shimla-India and includes the legal successors or permitted
assigns of the Owner.
20
“Pre-commissioning” means the testing, checking and other requirements specified in the General
Technical Specification/ technical requirements that are to be carried out by the Contractor.
"Site" means Barrage of Larji Power House.
"Time for Completion" means the time within which completion of the Works is to be attained in
accordance with the stipulations in the GCC and the relevant provisions of the Contract.
2.0 CONTRACT DOCUMENTS
2.1 The term Contract Documents shall mean and include the following which shall be deemed to
form an integral part of the Contract.
(a) The Contract Deed and the Appendices hereto.
(b) Notification of Award.
(c) Forms & Procedures (as listed)
(d) Technical Specification.
(e) General Conditions of Contract.
(f) Information for Bidders.
(g) The Bid and Price Schedules submitted by the Bidder.
2.2 All the aforesaid Contract Documents including the letter of award shall form an integral part of
the Contract, in so far as the same or any part thereof conform to the Bid Documents and what
has been specifically agreed to by the and brought out in its letter of Award . Any matter
inconsistent therewith, contrary or repugnant thereto or any deviation taken by the Contractor in
its "Proposal" but not agreed to specifically by the in its letter of Award shall be deemed to have
been withdrawn by the Contractor.
2.3 The documents mentioned at clause 2.1 above forming the Contract are to be taken as mutually
explanatory of one another.
2.4 The Contract as per proforma annexed is to be signed within fifteen (15) days of the date of the
Letter of Award, on a date and time to be mutually agreed and at the office of the Owner unless
otherwise agreed to. The Contractor shall provide for signing of the Contract, appropriate Power
of Attorney and the requisite documents. Till such time a formal Contract is prepared and
executed, the Letter of Award read in conjunction with the Contract Documents will continue to
constitute a binding Contract.
3.0 INTERPRETATION
3.1 Language 3.1.1 All Contract Documents, all correspondence and communications to be given, and all other
documentation to be prepared and supplied under the Contract shall be written in English, and the
Contract shall be construed and interpreted in accordance with that language .
3.1.2 If any of the Contract Documents, correspondence or communications are prepared in any
language other than the governing language under GCC sub-clause 3.1.1 above, the English
translation of such documents, correspondence or communications shall prevail in matters of
interpretation.
3.2 Entire Agreement The Contract constitutes the entire agreement between the Owner and the Contractor with respect
to the subject matter of Contract and supersedes all communications, negotiations and agreements
(whether written or oral) of parties with respect thereto made prior to the date of Contract.
3.3 Amendment No amendment or other variation of the Contract shall be effective unless it is in writing, is dated,
expressly refers to the Contract, and is signed by a duly authorized representative of each party
hereto.
21
3.4 Independent Contractor The Contractor shall be an independent Contractor performing the Contract. The Contract does
not create any agency, partnership, joint venture or other joint relationship between the parties
hereto.
Subject to the provisions of the Contract, the Contractor shall be solely responsible for the
manner in which the Contract is performed. All employees & representatives engaged by the
Contractor in connection with the performance of the Contract shall be under the complete
control of the Contractor and shall not be deemed to be employees of the Owner, and nothing
contained in the Contract shall be construed to create any Contractual relationship between any
such employees & representatives and the Owner.
3.5 Severability If any provision or condition of the Contract is prohibited or rendered invalid or unenforceable,
such prohibition, invalidity or unenforceability shall not affect the validity or enforceability of
any other provisions and conditions of the Contract.
4.0 NOTICES 4.1 Unless otherwise stated in the Contract, all notices to be given under the Contract shall be in
writing, and shall be sent by personal delivery, airmail post, special courier, cable, telegraph,
telex, facsimile or Electronic Data Interchange (EDI) to the address of the relevant party, set out
in the General Conditions of Contract.
4.2 Notices shall be deemed to include any approvals, consents, instructions, orders and certificates to
be given under the Contract.
5.0 GOVERNING LAW The Contract shall be governed by and interpreted in accordance with laws of India.
6.0 ARBITRATION 6.1 Any dispute(s) or differences(s) arising out of or in connection with the Contract shall, to the
extent possible in the first instance be resolved amicably between the Contractor and the Owner's
Engineer.
6.2 The arbitration proceedings shall be conducted in accordance with "Indian Arbitration and
Conciliation Act 1996 or any statutory modification thereof. Language of the arbitration
proceedings shall be in English.
6.3 The venue of Arbitration shall be Shimla, India. The courts of Shimla shall have exclusive
jurisdiction.
6.4 Notwithstanding any reference to the arbitration herein;
(a) the parties shall continue to perform their respective obligations under the Contract unless
they otherwise agree.
(b) the Owner shall pay the Contractor any monies due to the Contractor.
7.0 SCOPE OF WORKS 7.1 Unless otherwise expressly limited in the Technical Specifications, the Contractor's obligations
cover the provision of all installation, commissioning and engineering services, supply of labour,
materials, equipment and accessories; Contractor's equipment, construction utilities and supplies,
temporary materials.
7.2 The Contractor shall, unless specifically excluded in the Contract, perform all such work and/ or
supply all such items and materials not specifically mentioned in the Contract but that can be
reasonably inferred from the Contract as being required for attaining Completion of the Works as
if such work and /or items and materials were expressly mentioned in the Contract.
22
8.0 TIME FOR COMMENCEMENT AND COMPLETION 8.1 The Contractor shall commence work from the fifteenth day after the notification of award of
work.
8.2 The Contractor shall attain completion of the total works under the Contract within such extended
time to which the Contractor shall be entitled under GCC Clause 30.0 (Extension of Time for
Completion) hereof.
9.0 CONTRACTOR'S RESPONSIBILITES 9.1 The Contractor shall execute the entire work with due care and diligence in accordance with the
Contract.
9.2 The Contractor confirms that it has entered into this Contract on the basis of a proper examination
of the data relating to the works provided by Owner, and on the basis of information that the
Contractor could have obtained from a visual inspection of the site and of other data readily
available to it relating to the works. The Contractor acknowledges that any failure to acquaint
itself with all such data and information shall not relieve its responsibility for properly estimating
the difficulty or cost of successfully performing the works.
9.3 The Contractor shall acquire in its name all permits, approvals and/or licenses from all local, state
or national government authorities or public service undertakings that are necessary for the
performance of the Contract.
9.4 The Contractor shall comply with all laws in force where the services are carried out. The laws
will include all national, provincial, municipal or other laws that affect the performance of the
Contract and bind upon the Contractor. The Contractor shall indemnify and hold harmless the
Owner from and against any and all liabilities, damages, claims, fines, penalties and expenses of
whatever nature arising or resulting from the violation of such laws by the Contractor or its
personnel but without prejudice to GCC sub-clause 8.1 hereof.
9.5 The Contractor shall supply and make available all raw materials, utilities, and works and shall
perform all work and services of whatsoever nature required by him to properly carry out the
works under the Contract.
10.0 OWNER'S RESPONSIBILITIES 10.1 The Owner shall ensure the accuracy of all the information and/or data to be supplied by the
Owner to the contract except when otherwise expressly stated in the contract.
11.0 CONTRACT PRICE
11.1 The Contract Price shall be as specified in Article 2 (Contract Price and Term of Payment) of the
Form of Contract Agreement.
12.0 TERMS OF PAYMENT 12.1 The Contract Price shall be paid as specified in Appendix-1 (Terms and Procedures of Payment)
to the Contract Agreement. The procedures to be followed in making application for and
processing payments shall be those outlined in the same Appendix-1.
12.2 No payment made by the Owner herein shall be deemed to constitute acceptance by the Owner of
the Works or any part(s) thereof.
12.3 All the payments under this Contract shall be made to the Contractor in Indian Rupees only.
13.0 SECURITIES
13.1 Contract Performance Security 13.1.1 The Contractor shall, within fifteen days (15) days of the notification of award, provide a security
for the due performance of the Contract for an amount equivalent to ten percent (10%) of
Contract price with a validity upto ninety (90) days beyond the Defect Liability Period.
23
13.1.2 The security shall be denominated in Indian Rupees and shall be in the form of bank guarantee
attached hereto in the section on Forms and Procedures, or in another form acceptable to the
Owner.
13.1.3 If the Defects Liability Period has been extended on any part of the works pursuant to GCC sub-
clause 24.8 hereof, the Contractor shall issue an additional security in an amount proportionate to
the Contract Price of that part. The security shall be returned to the Contractor immediately after
its expiration.
13.1.4 The Performance Security will be returned to the Contractor without any interest 90 days after
successful completion of the Defects Liability Period on submission of no claim certificate unless
otherwise specified.
13.1.5 It is expressly understood and agreed that the above Contract Performance Security is intended to
secure the performance of entire Contract. It is also expressly understood and agreed that the
Contract Performance security is not to be construed as limiting the damages as detailed under the
Technical Specification and any other damages stipulated in other clauses in the Contract
Documents.
13.2 Claims under Security Whether or not the Performance Security is stated by its terms to be payable on the demand of the
Owner, the Owner shall not make a claim under the Performance Security unless one of the
following conditions is satisfied:
a) the Contractor is in breach of the Contract and fails to remedy the breach with in 30 days
after receiving written notice from the Owner requiring him to do so. The notice shall
state the intention to claim under Performance Security, the amount claimed and the
breach relied upon, or
b) the Owner has obtained an award in arbitration and the amount awarded has not been
paid within 45 days after the award, or
c) the Contractor has gone into liquidation or is bankrupt, or
d) any other reason specifying the default of the Contractor by the Owner.
In every case the Owner shall, when making the claim, send a copy to the Contractor.
14.0 TAXES AND DUTIES 14.1 The Sales tax on works Contract shall be borne by the Contractor. The Owner shall make the
deduction of the same from the Contractor’s invoices at the rates prevalent at that time and
deposit the same with the Excise & Taxation Department under intimation to the Contractor.
14.2 As regards the Indian income tax, surcharge on income tax and any other corporate tax the Owner
shall not bear any tax liability whatsoever. The Contractor shall be liable and responsible for
payment of such tax, if attracted under the provisions of the law present or future and Owner will
make deductions at source as applicable.
14.3 Service Tax & education cess on service tax shall be paid to the Contractor at the rates prevailing
at that time against documentary proof of Service Tax Number of the Contractor. Thereafter it
shall be the sole responsibility of the Contractor to deposit the same with the concerned
authorities. It shall be mandatory on the Contractor to submit evidence of his having service tax
registration and the service tax registration number shall be printed on the invoices raised by him
for payment.
15.0 DEDUCTION FROM CONTRACT PRICE
15.1 All the costs, damages or expenses which the Owner may have paid for which, under the
Contract, the Contractor is liable, will be claimed by Owner. All such claim shall be billed by the
Owner to the Contractor regularly as and when they fall due. Such bills shall be supported by
appropriate and certified vouchers to the extent possible or explanations, to enable to the
Contractor to properly identify such claims.
24
15.2 Such claims shall be paid by the Contractor within twenty eight (28) days of the receipt of the
corresponding bills and if not paid by the Contractor within the said period, the Owner may then
deduct the amount from any money due or becoming due by him to Contractor under the Contract
or may be recovered by action of law or otherwise, if the Contractor fails to satisfy the Owner of
non- pay ability of such claims by the Contractor.
16.0 CONFIDENTIAL INFORMATION 16.1 The Owner and the Contractor shall keep confidential and shall not, without the written consent
of the other party hereto, divulge to any third party any documents, data or other information
furnished directly or indirectly by the other party hereto in connection with the Contract, whether
such information has been furnished prior to, during or following termination of the Contract.
16.2 The Owner shall not use such documents, data and other information received from the
Contractor for any purpose other than the operation and maintenance of the works. Similarly, the
Contractor shall not use such documents, data and other information received from the Owner for
any purpose other than the design, procurement of plant and equipment construction of or such
other work and services as are required for the performance of the Contract.
16.3 The obligation of a party under GCC sub-clause 16.1 and 16.2 above, however, shall not apply to
that information which
a) now or hereafter enters the public domain through no fault of that party.
b) can be proven to have been possessed by that party at the time of disclosure and which
was not previously obtained directly or indirectly, from the other party hereto.
c) otherwise lawfully becomes available to that party from a third party that has no
obligation of confidentiality.
16.4 The above provisions of this GCC Clause 16.0 shall not in any way modify any undertaking of
confidentiality given by either of the parties hereto prior to the date of the Contract in respect of
the works or any part thereof.
16.5 The provisions of this GCC Clause 16.0 shall survive termination, for whatever reason, of the
Contract.
17.0 REPRESENTATIVES
17.1 Engineer-in-charge The Engineer-in-charge shall be named before or at the time of signing the Contract. The Owner
may from time to time appoint some other person as the Engineer-in-charge in place of the person
previously so appointed, and shall give a notice of the name of such other persons to the
Contractor without delay. The Owner shall take all reasonable care to see that no such
appointment is made at such a time or in such a manner as to impede the progress of work on the
works. The Engineer-in-charge shall represent and act for the Owner at all times during the
currency of the Contract. All notices, instructions, orders, certificates, approvals and all other
communications under the Contract shall be given by the Engineer-in-charge except as herein
otherwise provided.
All notices, instructions, information and other communications given by the Contractor to the
Owner under the Contract shall be given to the Engineer-in-charge except as herein otherwise
provided.
17.2 Contractor's Representative 17.2.1 The Contractor's Representative at site shall be named before or at the time of signing the
Contract.
17.2.2 The Contractor's Representative shall represent and act for the Contractor at all times during the
currency of the Contract and shall give to the Engineer-in-charge all the Contractor's notices,
instructions, information and all other communications under the Contract.
25
All notices, instructions, information and all other communications given by the Owner or the
Engineer-in-charge to the Contractor under the Contract shall be given to the Contractor's
representative or, in its absence, its deputy, except as herein otherwise provided.
The Contractor shall not revoke the appointment of the Contractor's representative without the
Owners prior written consent, which shall not be unreasonably withheld.
17.2.3 The Contractor's representative may, subject to the approval of the Owner (which shall not be
unreasonably withheld), at any time delegate to any person any of the powers, functions and
authorities vested in him or her. Any such delegation may be revoked at any time. Any such
delegation or revocation shall be subject to a prior notice signed by the Contractor's
representative and shall specify the powers, functions and authorities thereby delegated or
revoked. No such delegation or revocation shall take effect unless and until a copy thereof has
been delivered to the Owner and the Engineer-in-charge.
Any act or exercise by any person of powers, functions, and authorities so delegated to him or her
in accordance with this GCC sub-clause 17.2.3 shall be deemed to be an act or exercise by the
Contractor's Representative.
17.2.4 Notwithstanding anything stated in GCC sub-clause 17.1 and 17.2 above, for the purpose of
execution of Contract the Owner and the Contractor shall finalize and agree to a Contract
coordination procedure and all the communication under the Contract shall be in accordance with
such Contract co-ordination procedure.
17.2.5 The Owner may by notice to the Contractor object to any representative or person employed by
the Contractor in the execution of the Contract who, in the reasonable opinion of the Owner, may
behave inappropriately, may be incompetent or negligent, or may commit a serious breach of the
site regulations provided under GCC sub-clause 19.3. The Owner shall provide evidence of the
same, whereupon the Contractor shall remove such person from the works.
17.2.6 If any representative or person employed by the Contractor is removed in accordance with GCC
sub-clause 17.2.5, the Contractor shall, where required, promptly appoint a replacement.
18.0 WORK PROGRAMME
18.1 Contractor's Organization
The Contractor shall supply to Engineer-in-charge a chart showing the proposed organization to
be established by the Contractor for carrying out the works. The chart shall include the identities
of the key personnel together with the curricula vitae of such key personnel to be employed
within twenty-one (21) days of the effective date. The Contractor shall promptly inform the
Owner and the Engineer-in-charge in writing of any revision or alteration of such an organization
chart.
18.2 Programme of Performance Within seven (7) days after the date of notification of Award, the Contractor shall prepare and
submit to the Engineer-in-charge a detailed program of performance of the Contract, showing the
sequence in which it proposes to execute & complete the works as well as the date by which the
Contractor reasonably requires that the Owner shall have fulfilled its obligations under the
Contract so as to enable the Contractor to execute the Contract in accordance with the programme
and to achieve completion and acceptance of the works in accordance with the Contract. The
programme so submitted by the Contractor shall accord with the Time Schedule included in
Appendix 4 (Time Schedule) to the Contract. The Contractor shall update and revise the
programme as and when appropriate or when required by Engineer-in-charge, but without
modification in the Times for Completion and any extension granted in accordance with GCC
Clause 30.0, and shall submit all such revisions to the Engineer-in-charge.
18.3 Progress Report
26
The Contractor shall monitor progress of all the activities specified in the programme referred to
in GCC sub-clause 18.2 (Programme of Performance) above and supply a progress report to the
Engineer-in-charge every week. The progress report shall be in a form acceptable to the
Engineer-in-charge and besides indicating (a) percentage completion achieved compared with the
planned percentage completion for each activity, and (b) where any activity is behind the
programme, giving comments and likely consequences and stating the corrective action being
taken.
18.4 Progress performance
If at any time the Contractor's actual progress falls behind the programme referred to in GCC
sub-clause 18.2 (Programme of Performance), or it becomes apparent that it will so fall behind,
the Contractor shall at the request of the Owner or the Engineer-in-charge prepare and submit to
the Engineer-in-charge a revised programme, taking into account the prevailing circumstances,
and shall notify the Engineer-in-charge of the steps being taken to expedite progress so as to
attain completion of the works within the Time for Completion under GCC sub-clause 8.2 (Time
for Commencement and Completion), any extension thereof entitled under GCC sub-clause 30.0
(Extension of Time for Completion), or any extended period as may otherwise be agreed upon
between the Owner and the Contractor.
18.5 Work Procedures The Contract shall be executed in accordance with the Contract documents and the procedures
given in the section on Sample Forms and Procedures of the Contract Documents.
19.0 MAINTENANCE
19.1 Setting Out/Supervision/Labour If, at any time during the progress of the works, any error shall appear in the position, level or
alignment of the works, the Contractor shall forthwith notify the Engineer-in-charge of such error
and at its own expense, immediately rectify such error to the reasonable satisfaction of the
Engineer-in-charge.
19.1.2 Contractor's Supervision: The Contractor shall give or provide all necessary superintendence
during the progress of the works, and the Contractor’s Representative or its deputy shall be
constantly on the Site to provide fulltime superintendence of the Maintenance work. The
Contractor shall provide and employ technical personnel who are skilled and experienced in their
respective professions and supervisory staff who are competent to adequately supervise the work
at hand.
19.1.3 Labour: a) The Contractor shall provide and employ on the Site such skilled, semi-skilled and
unskilled labour as is necessary for the proper and timely execution of the Contract. The
Contractor is encouraged to use local labor that has the necessary skills.
b) Unless otherwise provided in the Contract, the Contractor shall be responsible for the
recruitment, transportation accommodation and catering of all labor, local, or expatriate,
required for the execution of the Contract and for all payments in connection therewith.
c) The Contractor shall be responsible for obtaining all necessary permit(s) and/or visa(s)
from the appropriate authorities for the entry of all labour and personnel to be employed
on the Site.
d) The Contractor shall at its own expense provide the means of repatriation to all of its and
its sub-Contractor's personnel employed on the Contract at the Site to their various home
states. It shall also provide suitable temporary maintenance of all such persons from the
27
cessation of their employment on the Contract to the date programmed for their
departure. In the event that the Contractor defaults in providing such means of
transportation and temporary maintenance, the Owner may provide the same to such
personnel and recover the cost of doing so from the Contractor.
e) The Contractor shall at all times during the progress of the Contract use its best
endeavors to prevent any unlawful, riotous or disorderly conduct or behavior by or
amongst its employees and the labour of its sub-Contractors.
f) The Contractor shall, in all dealings with its labour currently employed on or connected
with the Contract, pay due regard to all recognized festivals, official holidays, religious or
other customs and all local laws and regulations pertaining to the employment of labour.
19.2 Contractor's Equipment 19.2.1 All Contractor's equipment brought by the Contractor onto the Site shall be deemed to be
intended to be used exclusively for the execution of the Contract. The Contractor shall not
remove the same from the Site without the Engineer-in-charge's consent that such Contractor's
equipment is no longer required for the execution of the Contract.
19.2.2. Unless otherwise specified in the Contract, upon completion of the works, the Contractor shall
remove from the Site all equipment brought by the Contractor onto the Site and any surplus
materials remaining thereon.
19.3 Site Regulations and Safety The Owner and the Contractor shall establish Site regulations setting out the rules to be observed
in the execution of the Contract at the Site and shall comply therewith. The Contractor shall
prepare and submit to the Owner, with a copy to the Engineer-in-charge proposed Site regulations
for the Owner's approval, which approval shall not be unreasonably withheld.
Such Site regulations shall include, but shall not be limited to rules in respect of security, safety
of the works, gate control, sanitation, medical care, and fire prevention.
19.4 Emergency Work If, by reason of an emergency arising in connection with and during the execution of the Contract
any protective `or remedial work is necessary as a matter of urgency to prevent damage to the
works, the Contractor shall immediately carry out such work.
If, the Contractor is unable or unwilling to do such work immediately, the Owner may do or
cause such work to be done as the Owner may determine is necessary in order to prevent damage
to the works. In such event the Owner shall, as soon as practicable after the occurrence of any
such emergency, notify the Contractor in writing of such emergency, the work done and the
reasons thereof. If the work done or caused to be done by the Owner is work that the Contractor
was liable to do at its own expense under Contract, the reasonable costs incurred by the Owner in
connection therewith shall be paid by the Contractor to the Owner. Otherwise, the cost of such
remedial work shall be borne by the Owner.
19.5 Site Clearance 19.5.1 Site clearance in course of performance:
In the course of carrying out the Contract, the Contractor shall keep the Site reasonably free from
all unnecessary obstruction, store or remove any surplus materials, clear away any wreckage,
rubbish or temporary works from the Site and remove any Contractor's equipment no longer
required for execution of the Contract.
19.5.2 Clearance of Site after completion:
After completion of all parts of the works, the Contractor shall clear away and remove all
wreckage, rubbish and debris of any kind from the Site and shall leave the Site and works clean
and safe.
28
19.6 Work at Night and on Holidays 19.6.1 Unless otherwise provided in the Contract, no work shall be carried out during the night and on
public holidays without prior written consent of the Owner, except where work is necessary or
required to ensure safety of the works or for the protection of life, or to prevent loss or damage to
property, when the Contractor shall immediately advise the Engineer-in-charge provided that
provisions of this GCC Sub-clause 19.6.1 shall not apply to any work which is customarily
carried out by rotary or double-shifts.
19.6.2 Notwithstanding GCC Sub-clause 19.6.1 or 19.1.3 if and when the Contractor considers it
necessary to carry out work at night or on public holidays so as to meet the time for completion
and requests the Owners consent thereto, the Owner shall not unreasonably withhold such
consent.
20.0 TEST AND INSPECTION 20.1 The Contractor shall at its own expense carry out at Site all such tests and/or inspections of the
Plant and equipment and any part of the works as are specified in the Contract.
20.2 The Owner and the Engineer-in-charge or their designated representatives shall be entitled to
attend the aforesaid test and/or inspection.
20.3 The Contractor shall provide the Engineer-in-charge with a certified report of the results of any
such test and/or inspection.
20.4 The Engineer-in-charge may require the Contractor to carry out any test and/or inspection not
required by the Contract, provided that the Contractor's reasonable costs and expenses incurred in
the carrying out of such test and/or inspection shall be added to the Contract price. Further, if
such test and/or inspection impede the progress of work on the works and/or the Contractor's
performance of its other obligations under the Contract, due allowance will be made in respect of
the Time for completion and the other obligations so affected.
20.5 If any Plant and equipment or any part of the works fails to pass any test and/or inspection, the
Contractor shall either rectify or replace such plant and equipment or part of the works and shall
repeat the test and/or inspection.
20.6 The Contractor agrees that neither the execution of a test and/or inspection of Plant and
equipment or any part of the works, nor the attendance by the Owner or the Engineer-in-charge
shall release the Contractor from any other responsibilities under the Contract.
21.0 COMPLETION OF THE WORKS 21.1 As soon as the works or any part thereof has, in the opinion of the Contractor, been completed
operationally and structurally and put in a tight and clean condition as specified in the Technical
Specifications, excluding minor items not materially affecting the operation or safety of the
works, the Contractor shall so notify the Owner in writing.
21.2 As soon as all works in respect of Pre-commissioning are completed and, in the opinion of the
Contractor, the works or any part thereof is ready for commissioning, the Contractor shall
commence commissioning (Trial operation) as per procedures stipulated in technical
specifications and as soon as commissioning is satisfactorily completed, the Contractor shall so
notify the Engineer-in-charge in writing.
21.3 The Engineer-in-charge shall within fourteen (14) days after receipt of the Contractor's notice
under GCC sub-clause 21.2 either issue a completion certificate in the form specified in the
Forms and Procedures section in the Bid Documents, stating that the works or that part thereof
have reached completion as at the date of the Contractor's notice under GCC sub-clause 21.2 or
notify the Contractor in writing of any defects and/or deficiencies.
If the Engineer-in-charge notifies the Contractor of any defects and/or deficiencies, the
Contractor shall then correct such defects and/or deficiencies, and shall repeat the procedure
described in GCC sub-clause 21.2.
29
If the Engineer-in-charge is satisfied that the works or that part thereof have reached completion,
the Engineer-in-charge shall, within seven (7) days after receipt of the Contractor's repeated
notice, issue a completion certificate stating that the works or that part thereof have reached
completion as at the date of the Contractor's repeated notice.
If the Engineer-in-charge is not so satisfied, than it shall notify the Contractor in writing of any
defects and/or deficiencies within seven (7) days after receipt of the Contractor's repeated notice,
and the above procedure shall be repeated.
21.4 As soon as possible after completion, the Contractor shall complete all outstanding minor items
so that the works are fully in accordance with the requirements of the Contract, failing which the
Owner will undertake such completion and deduct the costs thereof from any monies owing to the
Contractor.
21.5 Upon completion and handing over the works or the relevant part thereof, by the Contractor to the
Owner, shall be responsible for the care and custody of the works or the relevant part thereof.
22.0 COMMISSIONING AND OPERATIONAL ACCEPTANCE
22.1 Commissioning: - Commissioning (Trial Operation) of the works or any part thereof shall be completed by the
Contractor as per procedures detailed in technical Specifications.
22.2 Operational Acceptance: -
22.2.1 The operational Acceptance shall occur in respect of the works or any part thereof after
successful completion of the Test Service Period and any minor items relevant to the works or
that part thereof have been completed.
22.2.2 Pursuant to GCC sub-clause 22.2.1, the Contractor may give a notice to the Engineer-in-charge
requesting the issue of an Operational Acceptance Certificate in the form provided in the Bid
Documents or in another form acceptable to the Owner in respect of the works or the part thereof
specified in such notice as at the date of such notice.
22.2.3 The Engineer-in-charge shall, after consultation with the Owner, and within forty five (45 days)
after receipt of the Contractor's notice, issue an Operational Acceptance Certificate.
22.2.4 If within forty five (45) days after receipt of the Contractor's notice, the Engineer-in-charge fails
to issue the Operational Acceptance Certificate or fails to inform the Contractor in writing of the
justifiable reasons why the Engineer-in-charge has not issued the Operational Acceptance
Certificate, the works or the relevant part thereof shall be deemed to have been accepted as at the
date of the Contractor's said notice.
23.0 COMPLETION TIME GUARANTEE
23.1 The Contractor guarantees that it shall attain commissioning of the works (or a part for which a
separate time for completion is specified in the Contract) within the Time for Completion
specified in the Contract pursuant to GCC sub-clause 10.2 or within such extended time to which
the Contractor shall be entitled under GCC Clause 30.0 (Extension of Time for completion)
hereof.
23.2 If Contractor fails to attain completion of the works or any part thereof within the Time for
Completion or any extension thereof under GCC Clause 30.0 (Extension of Time for
Completion), the Contractor shall pay to the Owner liquidated damages in the amount computed
@ half percent (0.5) of the Contract price per week. The aggregate amount of such liquidate
damages shall in no event exceed the five (5%) of the Contract price. Once the "Maximum" is
reached, the Owner may consider termination of the Contract, pursuant to GCC Sub-clause 32.2.
Such payment shall completely satisfy the Contractor's obligation to attain completion of the
works or the relevant part thereof within the Time for Completion or any extension thereof under
30
GCC Clause 30.0 (Extension of Time for Completion). The Contractor shall have no further
liability whatsoever to the Owner in respect thereof.
However, the payment of liquidated damages shall not in any way relieve the Contractor from
any of its obligations to complete the works or from any other obligations and liabilities of the
Contractor under the Contract.
Save for liquidated damages payable under this GCC sub-clause 23.2, the failure by the
Contractor to attain any milestone or other act, matter or thing by any date specified in Appendix
4(Time Schedule to the Contract Agreement and/or other programme of work prepared pursuant
to GCC Clause 18.2 (Programme of Performance) shall not render the Contractor liable for any
loss or damage thereby suffered by the Owner.
23.3 No bonus shall be given for earlier completion of works or part thereof.
24.0 DEFECT LIABILITY
24.1 The Contractor warrants that the works carried out under this Contract shall be free from defects.
24.2 The Defect Liability Period shall be twenty four (24) months from the date of Operational
Acceptance of the works unless specified otherwise in the Contract.
If during the Defect Liability Period any defect should be found in the work executed by the
Contractor, the Contractor shall promptly, in consultation and agreement with the Owner
regarding appropriate remedying of the defects, and at its cost, repair, replace or other wise make
good (as the Contractor shall, at its discretion, determine) such defect as well as any damage to
the works caused by such defect. The Contractor shall not be responsible for the repair,
replacement or making good of any defect or of any damage to the works arising out of or
resulting from any of the following causes:
a) improper operation or maintenance of the works by the Owner.
b) operation of the works outside specifications provided in the Contract.
c) normal wear and tear.
24.3 The Contractor's obligations under this GCC Clause 24.0 shall not apply to: -
a) any materials that are supplied by the Owner are normally consumed in operation, or
have a normal life shorter than the Defect Liability Period stated herein.
b) any designs, specifications or other data designed, supplied or specified by or on behalf
of the Owner or any matters for which the Contractor has disclaimed responsibility
herein.
24.4 The Owner shall give the Contractor a notice stating the nature of any such defect together with
all available evidence thereof, promptly following the discovery thereof. The Owner shall afford
all reasonable opportunity for the Contractor to inspect any such defect.
24.5 If the repair, replacement or making good is of such a character that it may affect the efficiency of
the works or any part thereof, the Owner may give to the Contractor a notice requiring that tests
of the defective part of the works shall be made by the Contractor immediately upon completion
of such remedial work, whereupon the Contractor shall carry out such tests.
If such part fails the tests, the Contractor shall carry out further repair, replacement or making
good (as the case may be) until that part of the works passes such tests. The tests in character
shall in any case be not less than what has already been agreed upon by the Owner and the
Contractor for the original equipment/part of the works.
24.6 If the Contractor fails to commence the work necessary to remedy such defect or any damage to
the works caused by such defect within a reasonable time (which shall in no event be considered
to be less than fifteen (15 days) the Owner may following notice to the Contractor, proceed to do
such work and the reasonable costs incurred by the Owner in connection therewith shall be paid
to the Owner by the Contractor or may be deducted by the Owner from any monies due the
Contractor or claimed under the Performance Security.
24.7 If works or any part thereof cannot be used by reason of such defect and/or making good of such
defect, the Defect Liability Period of the Works or such part, as the case may be, shall be
31
extended by a period equal to the period during which the works or such part cannot be used by
the Owner be cause of any of the aforesaid reasons.
24.8 Upon correction of the defects in the works or any part thereof by repair/replacement, such
repair/replacement shall have the Defect Liability Period extended by a period of Twenty four
(24) months from the time of such replacement/repair of the works or any part thereof.
25.0 LOSS OF OR DAMAGE TO PROPERTY; ACCIDENT OR INJURY TO WORKERS;
INDEMNIFICATION 25.1 The Contractor shall indemnify and hold harmless the Owner and its employees and officers from
and against any and all suits, actions or administrative proceedings, claims, demands, losses,
damages, costs, and expenses, of whatsoever nature, including attorney's fees and expenses , in
respect of the death or injury of any person or loss of or damage to any property (other than the
works whether accepted or not), arising in connection with the supply and maintenance of the
works and by reason of the negligence of the Contractor or their employees, officers or agents,
except any injury, death or property damage caused by the negligence of the Owner, its
Contractors, employees, officers or agents.
25.2 If any proceedings are brought or any claim is made against the Owner that might subject the
Contractor to liability under GCC sub-clause 25.1 the Owner shall promptly give the Contractor a
notice thereof and the Contractor may at its own expense and in the Owner's name conduct such
proceedings or claim and any negotiations for the settlement of any such proceedings or claim.
If the Contractor fails to notify the Owner within twenty-eight (28) days after receipt of such
notice that it intends to conduct any such proceedings or claim, then the Owner shall be free to
conduct the same on its own behalf. Unless the Contractor has so failed to notify the Owner
within the twenty eight (28) days period the Owner shall make no admission that may be
prejudicial to the defense of any such proceedings or claim.
26.0 INSURANCE
26.1 To the extent specified in Appendix 3 (Insurance Requirements) to the Contract Agreement, the
Contractor shall at its expense take out and maintain in effect, during the performance of the
Contract, the insurances set forth below in the sums and with the deductibles and other conditions
specified in the said Appendix.
a) Third Party Liability Insurance
Covering bodily injury or death suffered by third parties occurring in connection with the
works under the Contract.
b) Worker's Compensation
In accordance with the statutory requirements applicable in any country where the
Contract or any part thereof is executed.
27.0 CHANGE IN LAWS AND REGULATIONS
27.1 If, after the date twenty-eight (28) days prior to the date of Bid submission, any law, regulation,
ordinance, order or by-law having the force of law is enacted, promulgated, abrogated or changed
(which shall be deemed to include any change in interpretation or application by the competent
authorities) that subsequently affects the costs and expenses of the Contractor and/or the Time for
Completion, the Contract Price shall be correspondingly increased or decreased, and/or the Time
for Completion shall be reasonably adjusted to the extent that the Contractor has thereby been
affected in the performance of any of its obligations under the Contract.
28.0 FORCE MAJEURE
28.1 " Force Majeure " shall mean any event beyond the reasonable control of the Owner or of the
Contractor, as the case may be and which is unavoidable notwithstanding the reasonable care of
the party affected and shall include, without limitation, the following: -
32
a) war and other hostilities (whether war be declared or not), invasion, act of foreign
enemies or embargo;
b) rebellion, revolution, insurrection, military or usurped power and civil war;
c) ionising, radiation or contamination by radio-activity from any nuclear fuel or from any
nuclear waste from the combustion of nuclear fuel, radio-active toxic explosives, or
other hazardous properties of any explosive nuclear assembly or nuclear components
thereof;
d) riot, commotion or disorder, except where solely restricted to employees of the
Contractor;
e) Acts of God such as earthquake (above magnitude of 7 on Richter's scale), unprecedented
floods.
28.2 If either party is prevented, hindered or delayed from or in performing any of its obligations
under the Contract by an event of Force Majeure, then it shall notify the other in writing of the
occurrence of such event and the circumstances thereof within fourteen (14) days after the
occurrence of such event.
28.3 The party who has given such notice shall be excused from the performance or punctual
performance of its obligations under the Contract for so long as the relevant event of Force
Majeure continues and to the extent that such party's performance is prevented, hindered or
delayed. The Time for Completion shall be extended in accordance with GCC Clause 30.0
(Extension of Time for Completion).
28.4 The party or parties affected by the event of Force Majeure shall use reasonable efforts to
mitigate the effect thereof upon its or their performance of the Contract and to fulfill its or their
obligations under the Contract.
28.5 No delay or non-performance by either party thereto caused by the occurrence of any event of
Force Majeure shall
a) constitute a default or breach of the Contract
b) (subject to GCC sub-clause 29.3) give rise to any claim for damages or additional cost or
expense occasioned thereby
if and to the extent that such delay or nonperformance is caused by the occurrence of an event of
Force Majeure .
28.6 If the performance of the Contract is substantially prevented, hindered or delayed for a single
period of more than sixty (60) days or an aggregate period of more than one hundred and twenty
(120) days on account of one or more events of Force Majeure during the currency of the
Contract, the parties will attempt to develop a mutually satisfactory solution failing which the
dispute shall be resolved in accordance with GCC Clause 6.
28.7 Notwithstanding GCC sub-clause 28.5, Force Majeure shall not apply to any obligation of the
Owner to make payments to the Contractor herein.
29.0 WAR RISKS
29.1 " War Risks" shall mean any event specified in paragraphs (a) and (b) of GCC sub-clause 28.1
and any explosion or impact of any mine, bomb-shell, grenade or other projectile, missile,
munitions or explosive of war, occurring or existing in or near the country (or countries) where
the Site is located.
29.2 Notwithstanding anything contained in the Contract, the Contractor shall have no liability
whatsoever for or with respect to: -
a) destruction of or damage to Works, Plant & Equipment, or any part thereof.
b) destruction of or damage to property of the Owner or any third party.
c) injury or loss life
29.3 If during the performance of the Contract any War Risks shall occur that financially or otherwise
materially affect the execution of the Contract by the Contractor, the Contractor shall use its
reasonable efforts to execute the Contract with due and proper consideration give to the safety of
33
its and its sub-Contractor's personnel engaged in the work on the works, provided, however, that
if the execution of the work on the works becomes impossible or is substantially prevented for a
single period of more than sixty (60) days or an aggregate period of more than one hundred and
twenty (120) days on account of any War Risks, the parties will attempt to develop a mutually
satisfactory solution, failing which the dispute will be resolved in accordance with GCC Clause
No. 6.0.
30.0 EXTENSION OF TIME FOR COMPLETION
30.1 The time(s) for completion specified in the Contract shall be extended if the Contractor is delayed
or impeded in the performance of any of its obligations under the Contract by reason of any of the
following:
a) any occurrence of Force Majeure as provided in GCC Clause 28.0 (Force majeure).
b) any suspension order given by the Owner under GCC clause 31.0 (Suspension) hereof.
c) any changes in laws and regulations as provided in GCC Clause 27.0 (Change in Laws
and Regulations) or
d) any default or breach of the Contract by the Owner specifically including failure to
supply the items in Scope of Works and Supply by the Owner to the Contract Agreement,
or any activity, act or omission of any other Contractors employed by the Owner or
e) any other matter specifically mentioned in the Contract:
by such period as shall be fair and reasonable in all the circumstances and as shall fairly reflect
the delay or impediment sustained by the Contractor .
30.2 Except where otherwise specifically provided in the Contract, the Contractor shall submit to the
Engineer-in-charge a notice of a claim for an extension of the Time for completion, together with
particulars of the event or circumstance justifying such extension as soon as reasonably
practicable after the commencement of such event or circumstance. As soon as reasonably
practicable after receipt of such notice and supporting particulars of the claim, the Owner and the
Contractor shall agree upon the period of such extension.
30.3 The Contractor shall at all times use its reasonable efforts to minimize any delay in the
performance of its obligations under the Contract.
31.0 SUSPENSION
31.1 The Owner may request the Engineer-in-charge by notice to the Contractor, to order the
Contractor to suspend performance of any or all of its obligations under the Contract. Such notice
shall specify the obligations of which performance is to be suspended, the effective date of the
suspension and the reasons thereof. The Contractor shall thereupon suspend performance of such
obligations (except those obligations necessary for the care or preservation of the works) until
ordered in writing to resume such performance by the Engineer-in-charge.
31.2 During the period of suspension, the Contractor shall not remove from the Site any Plant and
equipment, any part of the works or any Contractor's equipment, without the prior written consent
of the Owner.
32.0 TERMINATION
32.1 The Owner without prejudice to any other rights or remedies it may possess, may terminate the
Contract forthwith in the following circumstances by giving a notice of termination and its
reasons therefor to the Contractor.
a) if the Contractor becomes bankrupt or insolvent, has a receiving order issued against it,
compounds with its creditors, or, if the Contractor is a corporation, a resolution is passed
or order is made for its winding up (other than a voluntary liquidation for the purposes of
amalgamation or reconstruction) a receiver is appointed over any part of its under taking
34
or assets, or if the Contractor takes or suffers any other analogous action in consequence
of debt.
b) if the Contractor assigns or transfers the Contract or any right or interest.
c) if the Contractor, in the judgment of the Owner has engaged in corrupt or fraudulent
practices in competing for or in executing the Contract.
For the purpose of this sub-clause:
"Corrupt practice" means the offering, giving receiving or soliciting of any thing of value
of influence the action of a public official in the procurement process or in Contract
execution.
"Fraudulent practice" means a misrepresentation of facts in order to influence a
procurement process or the execution of a Contract to the detriment of the Owner and
includes collusive practice among Bidders (prior to or after Bid submission) designed to
establish Bid prices at artificial non-competitive levels and to deprive the Owner of the
benefits of free and open competition .
32.2 If the Contractor
a) has abandoned or repudiated the Contract.
b) has without valid reason failed to commence work on the works promptly or has
suspended, the progress of Contract performance for more than twenty-eight (28) days
after receiving a written instruction from the Owner to proceed.
c) persistently fails to execute the Contract in accordance with the Contract or persistently
neglects to carry out its obligations under the Contract without just cause.
d) refuses or is unable to provide sufficient materials, services or labour to execute and
complete the works in the manner specified in the program furnished under GCC Clause
18.2 (Programme of Performance) at rates of progress that give reasonable assurance to
the Owner that the Contractor can attain completion of the works by the Time for
Completion as extended;
then the Owner may, without prejudice to any other rights it may possess under the Contract, give
a notice to the Contractor stating the nature of the default and requiring the Contractor to remedy
the same. If the Contractor fails to remedy or to take steps to remedy the same within fourteen
(14) days of its receipt of such notice, then the Owner may terminate the Contract forthwith by
giving a notice of termination to the Contractor.
32.3 Upon receipt of the notice of termination under the Contract shall either immediately or upon
such date as is specified in the notice of termination:
a) cease all further work, except for such work as the Owner may specify in the notice of
termination for the sole purpose of protecting that part of the works already executed, or
any work required to leave the Site in a clean and safe condition.
b) terminate all sub-Contracts, except those to be assigned to the Owner pursuant to
paragraph (d) below.
c) deliver to the Owner the parts of the works executed by the Contractor up to the date of
termination.
d) to the extent legally possible, assign to the Owner all right, title and benefit of the
Contractor to the Work and to the plant and equipment as at the date of termination, and,
as may be required by the Owner, in any sub-Contracts concluded between the Contractor
and its sub-Contractors.
e) deliver to the Owner all drawings, specifications and other documents prepared by the
Contractor or its sub-Contractors as at the date of termination in connection with the
works.
35
32.4 The Owner may enter upon the Site, expel the Contractor, and complete the works itself or by
employing any third party. The Owner may, to the exclusion of any right of the Contract over the
same, take over and use with the payment of a fair rental rate to the Contractor, with all the
maintenance costs to the account of the Owner and with an indemnification by the Owner for all
liability including damage or injury to persons arising out of the Owner's use of such equipment,
any Contractor's equipment owned by the Contractor and on the Site in connection with the works
for such reasonable period as the Owner considers expedient for the works.
Upon completion of the works or at such earlier date as the Owner thinks appropriate, the Owner
shall give notice to the Contractor that Contractor's equipment will be returned to the Contractor
at or near the Site and shall return such Contractor's equipment to the Contractor in accordance
with such notice . The Contractor shall thereafter without delay and at its cost remove or arrange
removal of the same from the Site.
32.5 The Contractor shall be entitled to be paid the Contract price attributable to the works executed as
at the date of termination, the value of any unused or partially used Plant and equipment on the
Site, and the costs, if any, incurred in protecting the works and in leaving the Site in a clean and
safe condition pursuant to paragraph. Any sums due to the Owner from the Contractor accruing
prior to the date of termination shall be deducted from the amount to be paid to the Contractor
under this Contract.
32.6 If the Owner completes the works, the cost of completing the works by the Owner shall be
determined.
If the sum that the Contractor is entitled to be paid pursuant to GCC sub-clause 32.5, plus the
reasonable costs incurred by the Owner, in completing the works, exceeds the Contract price, the
Contractor shall be liable for such excess.If such excess is greater than the sums due the
Contractor under GCC sub-clause 32.5, the Contractor shall pay the balance to the Owner, and if
such excess is less than the sums due the Contractor the Owner shall pay the balance to the
Contractor.
The Owner and the Contractor shall agree, in writing, on the computation described above and
the manner in which any sums shall be paid.
33.0 ASSIGNMENT
33.1 Neither the Owner nor the Contractor shall, without the express prior written consent of the other
(which consent shall not be unreasonably withheld), assign to any third party the Contract or any
part thereof, or any right, benefit, obligation, or interest therein or there under, except that the
Contractor shall be entitled to assign either absolutely or by way of charge any money due and
payable to it or that may become due and payable to it under the Contract.
34.0 TEST SERVICE PERIOD
As soon as the works or part thereof has passed the Commissioning Tests, the Engineer-in-charge
shall issue a Completion Certificate to the Contractor to that effect with copy to the Owner.
The Completion Certificate shall indicate any outstanding works and/or minor unattended defects
of the works which shall be rectified by the Contractor.
The Test Service Period shall commence immediately after the Completion Certificate has been
issued. Tests shall be carried out in accordance with the specifications and as requested by the
Owner under the sole responsibility of the Contractor.
The duration of the Test Service Period shall be 35 days.
After successful completion of the Test Service Period, the Engineer-in-charge shall issue a
Taking-Over Certificate to the Contractor with copy to the Owner.
The Owner and /or Engineer-in-charge reserve the right to delay the issuance of Taking-Over
Certificate until such time he is satisfied that defects enlisted in the Test Certificate and other
defects, if any, during the Test Service Period are rectified.
36
SECTION-IV
Forms & Procedure (FP)
37
INDEX
FORMS AND PROCEDURE
1.Bid Forms
2. Attachments Including Security Forms
3. Price Schedule
4. Form of 'Notification of Award Contract' for supply of Plant and Equipment and their installation.
5. From of Contract Agreement.
6.Performance Security Forms.
7.Form of Completion Certificate. 8.Form of Operational Acceptance Certificate
38
BID FORM
Date-------------------------------------------
Bid Spec. No. –
Name of Contract-----------------------------------------------
To
Chief Engineer (Gen.),
HPSEBL, Sunder Nagar-175019 (HP).
Sir,
1.0 With reference to the Bid Documents forwarded to us vide your letter no-------------------- dated --
------------, we the undersigned, having examined the Bid Documents, including Addenda Nos.,
(Insert numbers------------------), the receipt of which is hereby acknowledged, offer to execute the
work under the above named Contract in full conformity with the said Bid Documents for the
sum of:
-------------------------------------------------------------------------------------------------------------
(Amount in 'Words)
------------------------------------------------------- (----------------------------------------------)
(Amount in Figures)
or such other sums as may be determined in accordance with the terms and conditions of the
Contract.
2.0 Attachments to the Bid Form: In line with the requirement of the Bid Documents, we enclose herewith the following
Attachments to the Bid Form:
a) Attachment 1: Bid Security in the form of ----------------------------------(Please fill in the
alternative chosen) for a sum of -------------------------------------------(Name of currency
and amounts in words & figures) valid for a period of six (6) calendar months from the
date set for opening of Bids.
b) Attachment 2: A power of attorney duly authorised by a Notary Public indicating that the
person signing the Bid have the authority to sign the Bid and that the Bid is binding upon
us during the full period of its validity in accordance with the ITB Clause 13.0.
c) Attachment 3: The documentary evidence establishing in accordance with ITB Clause 3.0
that we are eligible to Bid.
d) Attachment 4: List of tools and tackles which we propose to bring to site in case the
contract is awarded to us.
e) Attachment 5: The mile stone schedule showing the timing and sequence of all key
activities necessary for successful completion of the contract is enclosed.
39
f) Attachment 6: The variation and deviations from the requirements of the conditions of
contract and commercial conditions in your format enclosed with the Bid Documents,
indicating, inter alia, the cost of withdrawal of the variation and deviations indicated
therein.
g) Attachment 6A: The variation and deviations from the requirements of provisions of
Technical specifications and Drawings in your format enclosed with the bid documents,
indicating, inter alia, the cost of withdrawal of the variation and deviations indicated
therein.
3.0 PRICE SCHEDULES: 3.1 In line with the requirements of the Bid Documents, we enclose herewith the following Price
Schedules, duly filled-in as per your proforma:
Schedule No.1 Plant and Equipment (including Mandatory
Spare Parts)
Schedule No.2 Transportation including Insurance.
Schedule No.3 Installation Services (including dismantling charges
of existing panel)
Schedule No.4 Grand Summary (Schedules Nos. 1 to 3)
Schedule No.5 Recommended Spare Parts.
Schedule No.6 Taxes and Duties. (Not included in Bid Price)
Any other Schedules, if required, shall be added here.
3.2 We are aware that the Price Schedules do not generally give a full description of the work to be
performed under each item and we shall be deemed to have visited the sites of work and read
other Bid Documents to ascertain the full scope of work included in each item while filling-in the
rates and prices. We agree that the entered rates and prices shall be deemed to include for the full
scope as aforesaid, including overheads and profit.
3.3 We declare that as specified in the Conditions of Contract, prices quoted by us in the Price
Schedules are Firm.
3.4 We understand that in the price schedule, where there are errors between the total of the amounts
given under the column for the Price Breakdown and the amount given under the Total Price, the
former shall prevail and the latter will be corrected accordingly. We further understand that
where there are discrepancies between amounts stated in figures and amounts stated in words, the
amount stated in words shall prevail. Similarly, any discrepancy in the total bid price and that of
the summation of Schedule prices (price indicated in a Schedule indicating the total of that
schedule,) the total bid price shall be corrected to reflect the actual summation of the Schedule
prices.
40
3.5 We declare that items left blank in the Schedules will be deemed to have been included in other
items, The TOTAL for each Schedule shall be deemed to be the total price for executing the
works and sections thereof in complete accordance with the Contract, whether or not each
individual item has been priced.
4.0 We confirm that we shall also get registered with the concerned Sales Tax Authorities, in the state
where the Projects are located.
5.0 We have read the provisions of following clause and confirm that the specified stipulations of
these clauses are acceptable to us:
a) GCC 5.0 Governing Law
b) GCC 6.0 Arbitration
c) GCC 12.0 Terms of payment
d) GCC 13.0 Performance Security
e) GCC 14.0 Taxes and Duties
f) GCC 23.0 Completion Time Guarantee
g) GCC 24.0 Defect Liability
6.0 We undertake, if our Bid is accepted, to commence the work on Facilities immediately upon your
Notification of Award to us, and to achieve completion within the time stated in the Bid
Documents.
7.0 We agree to abide by this Bid for a period of 180 days from the date fixed for submission of Bids
as stipulated in the Bid Documents, and it shall remain binding upon us and may be accepted by
you at any time before the expiration of that period.
8.0 Until a formal Contact is prepared and executed between us, this Bid, together with your written
acceptance thereof in the form of your Notifications of Award shall constitute a contract between
us.
9.0 We understand that you are not bound to accept the lowest or any Bid you may receive.
10.0 We, hereby, declare that only the persons or firms interested in this proposal as principals are
named here and that no other persons or firms other than those mentioned herein have any interest
in this proposal or in the Contract to be entered into, if the award is made on us, that this proposal
is made without any connection with any other person, firm or party likewise submitting a
proposal is in all respects for and in good faith, without collusion or fraud.
Dated this-----------------------day of -----------------------------------
Thanking you, we remain,
Yours faithfully,
(Signature)
(Printed Name)
(Designation)
(Common Seal)
Date :
Place :
Business Address :
Note: For the Attachments 2,3 & 5 Bidders may use their own proforma for furnishing the required
information with the Bid.
41
ATTACHMENT- 1
PROFORMA OF BANK GUARANTEE FOR BID SECURITY
(To be stamped in accordance with Stamp Act)
To
The Accounts Officer,
O/O the Chief Engineer (Generation),
HPSEB Ltd., Sunder Nagar,Distt. Mandi H.P. – 175 019.
WHERAS, (Name of Bidder) ---------------------------------------------(hereinafter called "the Bidder") has
submitted his Bid dated-------------------for (Name of Contract)-------------------------(hereinafter called
"the Bid").
KNOW ALL MEN BY these presents that we (Name of Bank)-----------------------------------------------
having our registered office at (address)------------------------------------------------(hereinafter called " the
Bank" are bound unto HPSEBL in the sum of Rs. ---------------------------------------for which payment
will and truly to be made to the HPSEBL the Bank binds himself, his successors and assigns by these
presents.
SEALED with the Common Seal of the said Bank this------------------------day of-----------------------2012.
THE CONDITIONS of this obligation are:
1. If the Bidder withdraws his Bid during the period of Bid validity specified in the Proforma of
Bid; or
2. If the Bidder having been notified of the acceptance of his Bid by the HPSEBL during the period
of Bid validity:
a) fails or refuses to execute the Contract Agreement, when required; or
b) fails or refuses to furnish the performance security, in accordance with the Bid
Documents.
We undertake to pay to the HPSEBL upto the above amount upon receipt of its first written demand
without the HPSEBL having to substantiate its demand, provided that in its demand the HPSEBL will
note that the amount claimed by it is due to it owing to the occurrence of one or both of the two
conditions, specifying the occurred condition or conditions.
This Guarantee will remain in force upto and including the date ---------- (ninety (90) days after the period
of Bid validity) and any demand in respect thereof should reach the Bank not later than the above date.
DATE--------------------- --------------------------- For and on behalf of the Bank.
(Signature)
in the capacity of
(Common Seal of Bank)
42
ATTACHMENT-4
(Name of the Project)
(List of Erection and Maintenance Tools & Tackles)
(Bidder's Name & Address):
To
Chief Engineer (Gen.),
HPSEBL, Sunder Nagar-175019 (HP)
Sir,
We are furnishing below the list of erection and commissioning instruments which we intend to bring to
site for executing the work detailed in the schedule of work & prices. These tools & tackles shall be taken
back after issue of operational acceptance certificate to us.
Sr. No. Description of tools & instruments Quantity Remarks
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
Notwithstanding what is stated above we further confirm that any additional erection and maintenance
tools and tackles, required for the completion of the works mentioned in the Bid documents shall be
arranged/brought to site by us at no extra cost to the Owner.
Date: ----------------------- (Signature)-------------------
Place:---------------------- (Printed Name)-------------
(Designation)----------------
(Common Seal)-------------
43
ATTACHMENT-6
(Name of the Project)
Cost of withdrawal of deviation from the requirement of the Commercial terms and conditions. (To be furnished by the Bidders)
(Bidder's Name & Address):
To:---------------------------------------------------
(Name of the Owner)
Dear Sir,
Following are the deviations from the requirement of the commercial terms and conditions.
-----------------------------------------------------------------------------------------------------------------------
Sr. no. Clause no. Deviation. Cost of withdrawal (Rs.)
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
Yours faithfully,
Date: ------------------------- (Signature)---------------------------
Place: ------------------------- (Printed Name)----------------------
(Designation)------------------------
(Common Seal)----------------------
Note: - Bidders may note that the bids containing the deviations without the cost of withdrawal
shall be rejected.
44
ATTECHMENT -6A
(Name of the Project)
Cost of withdrawal of deviations from the requirement of the Technical specifications.
(Bidder's Name & Address)
To:--------------------------------------------------
(Owner's Name & Address)
Dear Sir,
Following are the deviation from the requirement of the Technical Specification, Drawings etc.
-----------------------------------------------------------------------------------------------------------------------
Sr. no. Clause no. Deviation. Cost of withdrawal (Rs.)
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
Yours faithfully,
Date: ------------------------- (Signature)---------------------------
Place: ------------------------- (Printed Name)----------------------
(Designation)------------------------
(Common Seal)----------------------
Note: Bidders may note that bids containing deviations without the cost of withdrawal shall be
rejected.
45
Price Schedules
46
Schedule No. - 1.
Plant, Equipment and Mandatory Spare Parts
Name of Work: Design, manufacture, shop assembly & testing, & commissioning of three (3)
numbers static excitation and Digital AVR systems complete with accessories
to be installed in the 3 X 5.65 MW Andhra Power House and
dismantling/removing of the existing excitation system.
Name of Bidder:-----------------------------
Signature of Bidder:-----------------------------
-
Sr. no
Description of material Qty EXW. Unit price
(Rs.)
EXW. Total price
(Rs.)
1. 2. 3. 4. 5.
1 Providing static excitation system and Digital
AVR systems complete with accessories,
equipment, devices, instruments, cabling and
wiring etc.
3 Sets
2 Providing Excitation Transformer (Optional)
as per technical specification.
3 Nos.
3 Providing field circuit breakers (Optional)
as per technical specification.
3 Nos.
4 Providing discharge resistors (Optional) as per
technical specification.
3 Nos.
5. Mandatory Spares 1 Lot
Above quantities are minimum and contractor shall provide all the required material/ quantity weather
mentioned above or not, to complete the job as per technical specifications without any extra financial
implication to HPSEBL.
47
Schedule 2. Transportation and Insurance
Unit Price (Rs.)
Item
Description
Unit
Qty.
(1)
Transportation &
Insurance
(2)
Total Price (Rs.)
(1x2)
1 Transportation
2. Insurance
Total (to Schedule 4. Grand Summary)
Name of Bidder:------------------------
Signature of Bidder:-------------------
48
Schedule 3. Installation Services (including dismantling charges of existing panel)
Unit Price (Rs.)
Total Price
(Rs.)
Item
Description.
Unit.
Qty.
(1)
(2)
(1x2)
Total (to Schedule 4. Grand Summary)
Name of Bidder:------------------------------
Signature of Bidder:-------------------------
49
Schedule 4. Grand Summary
Item Description Total Price (Rs.)
1.
Total Schedule 1: Plant, equipment and mandatory spare
parts.
2.
Total Schedule 2: Transportation & insurance
3.
Total Schedule 3: Installation services
GRAND TOTAL (to Bid form)
Name of Bidder:------------------------------
Signature of Bidder:-------------------------
50
Schedule 5. Recommended Spare Parts
Item Description Unit Qty.
(1)
Unit Price
EXW (Rs.)
(2)
Total price
(Rs.)
(1x2)
(3)
Transportation including
Insurance.
(4)
Total
Name of Bidder:--------------------
Signature of Bidder:---------------
51
Schedule No. - 6.
Taxes and Duties
Name of Bidder:-------------------------
Signature of Bidder:------------------------------
Item
Description of
Taxes / duties/
levies etc.
Rate of Taxes/
duties/ levies
application
Amount on which
Taxes / duties / levies
applicable
Taxes duties/ levies
payable in Rupees.
1 2 3 4 5
52
4. FORM OF 'NOTIFICATION OF AWARD OF CONTRACT'
NOTE: INSTRUCTIONS INDICATED IN ITALICS IN THIS NOTIFICATION OF
AWARD ARE TO BE TAKEN CARE OF BY THE ISSUING AUTHORITY.
Ref. No.:
Date:
-------------- (Contractor's Name & Address)-----------------------
------------------------------------------------------------------------------
------------------------------------------------------------------------------
------------------------------------------------------------------------------
Attn: Mr.-----------------------
Sub: Notification of Award of Contract.
Dear Sir,
1.0 This has reference to the following:
i) Bid Documents issued to you vide our letter no.------------------------------------- dated ---
--------------------------
ii) Clarifications furnished to you on the Bid Documents vide our letter no.-----------------
dated------------------------
iii) Your Proposal for the subject package submitted vide your letter no.-------------------------
dated-------------------.
iv) Our Fax message/letter no.-------------------------------dated--------------------------------
regarding extension of validity of Bid and that of the Bank Guarantee towards Bid
Security.
(Applicable only if any extension has been sought subsequently)
v) Post Bid discussions and meetings we had with you from ----------------to -------
vi) Clarification/ Confirmation furnished by you vide your letter No.------------------------
dated ------------------------.
2.0 We confirm having accepted your proposal submitted vide letter no.-----------------------------
dated --------------------------- read in conjunction with all the specifications, terms & conditions of
the Bid Documents and your subsequent letters (Use if relevant) referred to in para 1.0 above
and award on you the contract for the work of ------------------------------------------(Indicate brief
Scope of Work)---------------------------------------------------------------------------- for (Name of
project).------------------------------------------ as per Bid Documents No .-------------------
(hereinafter referred to as the ‘Contract') .
53
3.0 The total Contract Price for the entire scope of work under the Contract shall be
-----------------(Specify the amount)--------- as per the following break up:
i) Ex-manufacturing works/place -----------------------------------------
of despatch price for main Equipment
& mandatory spare
ii) Transportation and Insurance -----------------------------------------
iii) Unloading and handling at site, -----------------------------------------
installation, testing and
commissioning including performance
testing.
TOTAL (i+ii+iii) -----------------------------------------
(--------------------------(Specify the total amount in words)--------------------------------)
4.0 You shall prepare and finalise the Contract Documents for signing of the formal Contract and
shall enter into the Contract Agreement with us, as per the proforma enclosed with the Bid
Documents, on non-judicial stamp paper of appropriate value within 15 days from the date of this
Notification of Award.
5.0 This Notification of Award is being issued to you in duplicate. We request to return its duplicate
copy duly signed and stamped on each page including all the enclosed Appendices, by the
authorised signatory of your company as a proof of your acknowledgement and confirmation.
Please take the necessary action to commence the work and confirm action.
Yours faithfully,
For and on behalf of
---------(Name of the Owner)-------------
Encl.: As above.
(Authorised Signatory)
54
5. Form of Contract Deed
THIS CONTRACT is made the ----------------------day of -------------------------2012
BETWEEN
(1) Himachal Pradesh State Electricity Board, a body corporate, incorporated under section 5 of Electricity
(Supply) Act, 1948 (54 of 1948)] and having its principal place of business at Vidyut Bhawan Shimla
171001 (H.P) India (hereinafter called "the Owner"), and (2) [Name of Contractor], having its principal
place of business at [address of Contractor] (hereinafter called "the Contractor").
WHEREAS the Owner desires to engage the Contractor for execution of the work of design,
Engineering, Fabrication, supply, transportation, insurance, installation, erection, commissioning
& testing of three (3) numbers static excitation and Digital AVR systems complete with accessories to be
installed in the 3 X 5.65 MW Andhra Power House and the Contractor have agreed to such engagement
upon and subject to the terms and conditions hereinafter appearing.
NOW IT IS HEREBY AGREED as follows: -
Article 1. Contract 1.1 Contract Documents (Reference GCC Clause 2.0)
Document The following document shall constitute the Contract between the
Owner and the Contractor, and each shall be read and construed
as an integral part of the Contract:
a) This Contract Agreement and the Appendices hereto.
b) Notification of Award.
c) Forms & Procedures (as listed).
d) Technical Specifications.
e) General Conditions of Contract.
f) Information for Bidders.
g) The Bid and Price Schedule submitted by the Contractor.
1.2 Order of Precedence
In the event of any ambiguity or conflict between the Contract
Documents listed above, the order of precedence shall be the
order in which the Contract Documents are listed in Article 1.1
(Contract Documents) above.
1.3 Definitions (Reference GCC Clause 1.0)
Capitalised words and phrases used herein shall have the same
meanings as are ascribed to them in the General Conditions of
Contract.
Article 2. Contract 2.1 Contract Price (Reference GCC Clause 11.0)
Price and The Owner hereby agrees to pay to the Contractor the
Terms of Contract Price in consideration of the performance by the
Payment Contract of its obligations hereunder. The Contract Price shall be
the aggregate of: [amount in words], [amount in figures], or such
55
other sums as may be determined in accordance with the terms
and conditions of the Contract,
2.2 Terms of Payment (Reference GCC Clause 12.0)
The terms and procedures of payment according to which the
Owner will reimburse the Contractor are given in Appendix 1
(Terms and Procedures of Payment hereto).
Article 3: Effective 3.1 Effective Date (Reference GCC Clause 1.0)
Date for The Time of Completion of the works shall be
Determining determined from the date of Notification of Award
Time for
Completion
Article 4. (This is applicable It is expressly understood and agreed by and between the
only if the Owner is Contractor and the Owner that the Owner is entering into
a Public Sector this Contract solely on its own behalf and not on behalf of
Enterprises) any other person or entity. In particular it is expressly understood
and agreed that the Government of Himachal Pradesh and
Government of India is not a party to this Agreement and has no
liabilities, obligations or rights hereunder .It is expressly
understood and agreed that the Owner is an independent legal
entity with power and authority to enter into contracts solely on
its own behalf under the applicable laws of India and the general
principles of Contract Law. The Contractor expressly agrees,
acknowledges and understands that the Owner is not an Agent,
Representative or Delegate of the Government of Himachal
Pradesh/ Government of India. It is further understood and agreed
that the Government of Himachal Pradesh/ Government of India
is not and shall not be liable for any acts, omission, and
commissions, breaches or other wrongs arising out of the
Contract. Accordingly, the Contractor expressly waives, releases
and foregoes any and all actions or claims, including cross claims,
or counter claims against the Government of Himachal Pradesh/
Government of India arising out of this Contract and covenants
not to sue the Government of Himachal Pradesh/ Government of
India as to any manner, claim, cause of action or thing whatsoever
arising of or under this Agreement.
Article 5. Appendices The Appendices listed in the attached list of Appendices shall be
deemed to form an integral part of this Contract Agreement.
Reference in the Contract to any Appendix shall mean the
Appendices attached hereto, and the Contract shall be read and
construed accordingly.
IN WITNESS WHEREOF of the Owner and the Contractor have caused this Agreement to be duly
executed by their duly authorised representatives the day and year first above written.
Signed by for and on behalf of the Owner
56
____________________________________________________
[Signature]
____________________________________________________
[Title]
in the presence of ______________________________________
Signed by for and on behalf of the Contractor
_________________________________________________________________
[Signature]
__________________________________________________________________
[Title]
in the presence of ____________________________________________________
CONTRACT AGREEMENT
Dated the______________________ day of ________________________ ____________
BETWEEN
____________________________________________________________________________
["the Owner"]
and
____________________________________________________________________________
____________________________________________________________________________
["the Contractor"]
APPENDICES
Appendix 1 Terms and Procedures of Payment
Appendix 2 Price Adjustment
Appendix 3 Insurance Requirements.
Appendix 4 Time Schedule/Programme of Performance.
Sample Forms of Appendices 1 & 3 are provided herein.
57
Appendix - 1.
Terms and Procedures of Payment
1.0 In accordance with the provisions of GCC Clause 12.0 (Terms of Payment), the Owner shall pay
the Contractor in the following manner and at the following times, on the basis of the Price
Break-up given in the Price Schedules No. – 1 & 2.
2.0 TERMS OF PAYMENT
2.1 Ninety percent (90%) of the measured value of work performed by the Contractor, as identified in
the said Program of Performance, during the preceding month, as evidenced by the Owner's
authorization of the Contractor's application along with full taxes will be made within forty five
(45) days after receipt of bill and successful commissioning of Real Time Online WDS
monitoring System by the Owner/ HPSEBL.
2.2 Balance ten percent (10%) of the total value of work performed by the Contractor, upon issue of
the Operational Acceptance Certificate, within forty five (45) days after receipt of invoice.
3.0 Taxes & Duties
3.1 All taxes, duties and levies including sales tax on works Contract, as applicable on the materials
used for such erection portion of the Contract shall be to the Contractor’s account and no separate
claim in this regard will be entertained by the Owner.
3.2 The Service tax and education cess on service tax shall be paid by the Owner to the Contractor at
the rates prevailing at that time against documentary evidence given by the Contractor of his
having the Service Tax number.
3.3 As regards the Indian income tax, surcharge on income tax and any other corporate tax, the
Owner shall not bear any tax liability whatsoever. The Contractor shall be liable and responsible
for payment of such tax, if attracted under the provisions of the law present or future and Owner
will make deductions at source as applicable and issue TDS certificates to the Contractor.
4.0 PAYMENT PROCEDURES
The procedures to be followed in applying for certification and making payments shall be as
follows:
4.1 All payments shall be made in line with the Schedule Nos. -1& 2.
4.2 Upon completion of the particular activity, the Owner’s Site In-charge and the Contractor’s
Representative shall jointly sign a completion protocol giving the details of the activity carried
out with the start & finish dates.
4.3 The Contractor shall raise the invoice for the activity completed and submit copies of the
completion protocol to substantiate his claim.
4.4 Five sets of invoices shall be sent to the Engineer - in - charge .
4.5 The invoices should be accompanied by a statement showing the detail of invoices along with
their claimed amount already sent release of payment.
58
Appendix-2. Price Adjustment
The Prices are:-
“FIXED & FIRM”
No Price Variation claim (PVC) is allowed.
59
Appendix - 3.
Insurance Requirements
Insurances to be taken out by the Contractor
In accordance with the provisions of GCC Clause 26.0, the Contractor shall at its expense take out and
maintain in effect, during the performance of the Contract, the insurances set forth below in the sums and
with the deductibles and other conditions specified. The identity of the insurers and the form of the
policies shall be subject to the approval of the Owner, such approval not to be unreasonably withheld.
a) Third Party Liability Insurance
Covering bodily injury or death suffered by third parties (including the Owner's personnel) and
loss of or damage to property (including the Owner property and any parts of the facilities that
have been accepted by the Owner) occurring in connection with the supply and installation of the
facilities.
Amount Deductible limits Parties insured From To
b) Worker's Compensation
In accordance with the statutory requirements applicable where the facilities or any part thereof is
executed.
60
Appendix-4. Completion Time Period
The plant and equipment covered by the bid are to be supplied & installed and the
facilities shall have the commissioning completed within Six months from the date
of Notification of Award of Work to contractor by HPSEB. The necessary
Programme of performance to achieve the commissioning within Six months from
the date of Notification of Award of Work to contractor by HPSEB to be submitted
by the contractor.
61
Appendix 5. List of Approved Sub-contractors
Prior to award of Contract, the following details shall be completed, indicating those
Subcontractors proposed by the Bidder in the corresponding Attachment to its bid that are
approved by the Owner for engagement by the Contractor during he performance of the Contract.
The following Subcontractors are approved for carrying out the item of the facilities indicated.
Where more than one Subcontractor is listed, the Contractor is free to choose between them, but it
must notify the Owner of its choice in good time prior to appointing any selected Subcontractors.
No Subcontractors shall be placed with any such Subcontractors for additional items until the
Subcontractor have been approved in writing by the Owner and their names have been added to
this list of Approved Subcontractors.
Item of Facilities Approved Subcontractors Address
62
6. Performance Security Forms
Performance Bank Guarantee (To be stamped in accordance with Stamp Act )
Bank Guarantee No……………………
Date………………………….
To
[Owner's name & Address]
Dear Sir,
In consideration of the ………….[Owner's Name]………..(hereinafter referred to as the 'Owner which
expression shall unless repugnant to the context or meaning thereof, include its successors, administrators
and assigns) having awarded to M/s……..[Contractor's Name}…………with its Registered/Head Office
at………..(hereinafter referred to as the Contractor, which expression shall unless repugnant to the
context or meaning thereof, include its successors administrators, executors and assigns), a Contract by
issue of Owner's Notification of Award No ……………dated ……….and the same having been
unequivocally accepted by the contractor, resulting into a Contract bearing No………
dated……….valued at------------- for …… and the contractor having agreed to provide a Contractor
Performance Guarantee for the faithful performance of the entire Contract equivalent to
………(*)………….%…….(…….percent) of the said value of the Contract to the Owner.
We……..[Name & Address of the Bank]…………..having its Head Office at ……..(hereinafter referred
to as the 'Bank', which expression shall, unless repugnant to the context of meaning thereof, include its
successors, administrators, executors and assigns) do hereby guarantee and undertake to pay the Owner,
on demand any and all monies payable by the Contractor to the extent of ………………
(*)……………………… as aforesaid at any time upto ……….. (@)…………………[days/month/year]
without any demur, reservation, contest, recourse or protest and/or without any reference to the
Contractor. Any such demand made by the Owner on the Bank shall be conclusive and binding
notwithstanding any difference between the Owner and the Contractor or any dispute pending before any
Court, Tribunal, Arbitrator or any other authority. The Bank undertakes not to revoke this guarantee
during its currency without previous consent to the Owner and further agrees that the guarantees herein
contained shall continue to be enforceable till the Owner discharges this guarantee.
The owner shall have the fullest liberty, without affecting in any way the liability of the Bank under this
guarantee, from time to time extend the time for performance of the Contract by the Contractor. The
Owner shall have the fullest liberty, without affecting this guarantee, to postpone from time to time the
exercise of any powers vested in them or of any right which they might have against the Contractor, and
to exercise the same at any time in any manner, and either to enforce or to forbear to enforce any
covenants, contained or implied, in the Contract between the Owner and the Contractor or any other
course or remedy or security available to the Owner. The bank shall not be released of its obligations
under these presents by any exercise by the Owner of its liberty with reference to the matters aforesaid or
any of them or by reason of any other act or forbearance or other acts of omission or commission on the
part of the Owner or any other indulgence shown by the Owner or by any other matter or thing
whatsoever which under law would, but for this provision have the effect of relieving the Bank.
The bank also agrees that the Owner at its option shall be entitled to enforce this Guarantee against the
bank as a principle debtor, in the first instance without proceeding against contractor and notwithstanding
any security or other guarantee the Owner may have in relation to the Contractor's liabilities.
63
Notwithstanding anything contained herein above our liability under this guarantee is restricted to
………………(*) …………….. and it shall remain in force upto and including ………….
@………………… and shall be extended from time to time for such period (not exceeding one year), as
may be desired by M/s……………[Contractor's Name]………….on whose behalf this guarantee has
been given.
Dated this ………………………..day of ………………2012………..at………………………..
WITNESS
……………………………… (Signature)…………………...
(Signature)
……………………………… (Name)………………………..
(Name) ………………………………...
……………………………….. (Designation with Bank Stamp).
…………………………………
(Official Address) ………………………………...
Attorney as per Power of
Attorney No…………………..
Dated…………………………
Notes: 1. (*) This sum shall be ten percent (10%) of the Contract Price.
@ This date will be ninety (90) days beyond the Defects liability period as specified
in the Contract.
2. The stamp papers of appropriate value shall be purchased in the name of guarantee
issuing Bank.
64
7. Form of Completion Certificate
Date: --------------------------------------
Contract No: ----------------------------------
[Name of Contract]
To: [Name and address of Contractor]
Dear Sir,
Pursuant to GCC Clause 21 (Completion of the Facilities) of the General Conditions of the Contract
entered into between yourselves and the Owner dated [date], relating to the [brief description of the
facilities], we hereby notify you that the following parts(s) of the Facilities was (were) complete on the
date specified below, and that, in accordance with the terms of the Contract, the Owner hereby takes over
the said part(s) of the Facilities on the date mentioned below.
1. Description of the Facilities or part thereof: [description]
2. Date of Completion: [date]
However, you are required to complete the outstanding items listed in the attachment hereto as soon as practicable.
This letter does not relieve you of your obligation to complete the execution of the Facilities including
Guarantee Test(s) in accordance with the Contract nor of your obligations during the Defects Liability
Period.
Very truly yours,
Title
(Engineer- in-charge)
65
8. Form of Operational Acceptance Certificate
Date:_____________________________
Bid Spec. No: ___________________________
[Name of Contract]
To: [Name and address of Contractor]
Dear Sir,
Pursuant to GCC Sub- Clause 22.2 (Operational Acceptance) of the General Conditions of the Contract
entered into between yourselves and the Owner dated [date], relating to the [brief description of the
Works], we hereby notify you that the tests of the following parts(s) of the works were satisfactorily
carried out on the dates specified below and the works are hereby taken over by the Owner on the dates
specified.
1. Description of the Facilities or part thereof: [description]
2. Date of Operational Acceptance: [date]
This letter does not relieve you of your obligation to during the Defects Liability Period.
Very truly yours,
Title
(Engineer-in-charge)
66
SECTION-V
Technical Specifications
67
INDEX
TECHNICAL SPECIFICATIONS
TABLE OF CONTENTS
CLAUSE NO. PARTICULARS PAGE NO
1.0 Static Excitation System and Digital AVR 68
2.0 General Requirement 68
3.0 Scope of Supply 69
4.0 Codes & Standards 69
5.0 Rating and Output 70
6.0 Design and Construction 70
7.0 Field Flashing Equipment 79
8.0 De-Excitation System 79
9.0 Excitation Control Cubicle 80
10.0 Protection of Static Excitation Equipment 80
11.0 Excitation Connection 81
12.0 Communication Channels 81
13.0 Wiring Requirements 81
14.0 INSPECTION, TESTING AND COMMISSIONING 82
68
TECHNICAL SPECIFICATIONS FOR STATIC EXCITATION SYSTEM AND DIGITAL AVR
1 Static Excitation System and Digital AVR:-
This section of the specifications covers the detailed requirements of all works necessary
for dismantling/removing the existing excitation system including carriage, stacking at
Owner’s store/ yard and detailed design, manufacture, shop assembly & testing,
comprehensive insurance, delivery, erection, testing & commissioning at site, field
acceptance tests of static excitation system before handing over to the owner/HPSEB
Ltd. and guaranteed for two years of three (3) numbers static excitation and Digital
AVR systems complete with accessories, equipment, devices, instruments, cabling and
wiring etc. including all services, labour, tools and tackles in all respects.
2 General Requirement:-
The proposed excitation system is to be installed in the 3 x 5.65 MW Andhra Power
House. Tenderers are strongly advised to make the necessary site visit for first hand
information on design, arrangements, installation and layout of excitation equipments,
control, protection and instrumentation required and access the drawings of the existing
excitation system available at the site.
The Bidder shall submit the proposal of the new excitation system along with the Bid
Document suitable to replace the existing excitation system with necessary block and
system diagrams. The submitted proposal shall justify such replacements in totality.
The cost pertaining to relocation of equipments, modifications and adjustments
whatsoever necessary to complete the specified scope of works shall not be subjected to
additional costs.
The layout of various components in the cabinet, protection panel incorporating the
hardware and control wiring diagrams and schematics shall be prepared by the
Contractor and be sent to the Owner for approval.
All auxiliary components, if and when required for the completeness of the various
proposed excitation system schemes covered in this order, shall be deemed to be
included in the scope of supply whether or not such items are specifically mentioned in
the given bill of quantity.
A ground bus of bare copper strip of required size panel shall be provided and shall be
connected to the ground mat of the power station.
The buyer shall have a royalty free, non-exclusive and irrevocable license to use all the
software furnished necessary to operate the equipment. This shall apply to any software
procured by the Contractor from the Sub-Contractor for this application.
69
3 Scope of Supply
- Three (3) sets of excitation systems complete in all respects comprising of: -
- Three (3) sets of rectifier systems with 100% stand by capacity complete with
firing circuit, control system etc.
- Three (3) sets of Digital automatic voltage regulators.
- Three (3) sets of power supply units.
- Three (3) sets of field flashing equipment including transformers.
- Three (3) sets of digital control and metering equipment.
- Any other items not specified above, but are necessary for satisfactory operation
of the system.
- Mandatory spares.
Optional Items: -
- Three (3) sets of excitation transformers, dry type
- Three (3) nos. field circuit breakers.
- Three (3) nos. discharge resistors.
- Recommended spares.
4 Codes & Standards
The excitation equipment shall be developed in conformity with the following
requirements of the standards and specifications.
IEC 60034-16
Excitation systems for synchronous machines
IEEE Std421
Excitation Systems for Synchronous Machines
GB/T7409
Excitation system for synchronous electrical machines
GB 10585 Fundamental requirements of excitation systems medium and
small synchronous machines
Except as provided in the specifications, all materials, equipment, and fabrication and
testing thereof shall confirm to the latest applicable standards contained in the following
list: -
American Society for Testing and Materials (ASTM)
American Welding Society (AWS)
American Society of Mechanical Engineers (ASME)
International Electromechanical Commission (IEC)
National Electrical Manufacturers Association (NEMA)
Deutsche Industrie Normen (DIN)
Verband Deutcher Electrotechnicker (VDE)
International Organization for Standardization (ISO)
European Color Selection Chart (RAL)
The Bidder shall provide the testimonials of the adoption of the aforesaid codes and
standards in the proposed equipments and materials.
70
5 Rating and Output: -
The rating of existing generator is as under: -
1. Output capacity: 6647 /5650kW.
2. Rated power Factor 0.85 lag
3. Rated frequency. 50 + 3% Hz
4. Number of phases 03
5. Rated Voltage between phases 11 + 10% kV
6. Speed 500 rpm
7. Stator winding connection. Star
8. Stator winding resistance / phase at 750C 0.115 Ohm
9. Field winding resistance at 750C 0.18 Ohm
10. D.A. Synchronous reactance Xd (Unsat) 1.2 p.u.
11. Q.A. Synchronous reactance Xq (Unsat) 0.7 p.u.
12. Transient Reactance Xd’ (Sat) 0.24 p.u.
13. Transient Reacatance Xd’ (unsat) 0.28 p.u.
14. Subtransient Reactance Xd” (Sat) 0.15 p.u.
15. Ratio Sq”/Xd” 1.45
16. Short circuit ratio 0.95
17. Excitation at no load 280 Amps.
18. Excitation at rated load, p.f. and voltage 400 Amps.
19. Slip Ring Brushes ( 5 per ring) Total 10
6 Design and Construction:-
The static excitation system shall be microprocessor based AVR (digital) with thyristors
and shall include all necessary devices to supply excitation current to the generator. The
system shall be capable of controlling the generator terminal voltage under all operating
conditions.
The static excitation system offered shall be of static, digital, constant voltage type with
controlled thyristors. The excitation system shall be of reliable design with very
sensitive, quick acting control of generator voltage and reactive power.
The excitation system continuous rating shall be approximately twice the rating required
when the generator is operated at rated output, rated power factor, rated frequency and
110% rated voltage.
The equipment shall be capable of withstanding lightning & switching surges and
dynamic over-voltages to which they may be subjected and shall meet all the
performance requirements and tests described in the specifications. The equipment shall
conform to the latest issue of IEEE 421 or equivalent standard.
The equipment shall be capable of fully reversing its output voltage in response to
control signal in order to minimize generator iron burning in the event of generator fault.
Direct current measuring equipment consisting of shunts and leads etc. and all other
equipment required to provide indication of field current/voltage at AVR panels shall be
71
furnished. Copper conductor power cables shall be provided for connection from rectifier
transformer to thyristor cubicle and field breaker and slip rings.
The excitation system shall be capable of operation of the machines in parallel
maintaining even distribution of the reactive load between machines. Paralleling of the
generators shall be achieved on 66 kV side of the generator transformers.
The static excitation equipment shall be of modular design in such a way that it can be
readily removed for inspection or replacement of parts. Indicating lights shall be
provided at each module to indicate and locate rectifier failure.
All the equipment of static excitation and digital type AVR shall be suitably housed in
sheet metal dust proof cubicles. These cubicles shall be located at one place in a row
without any gap in between. The dimensions of the cubicle shall be identical to present a
neat and functional line up.
6.1 Excitation Transformer:-
The existing excitation transformers are in operation and are in healthy conditions. The
Tenderer shall quote the prices of equipment excluding the cost of Excitation
Transformer. In case bidders recommend to replace these transformers in case of non-
compatibility with their system, the price of excitation transformers may be quoted as an
optional item. The name plate specifications of the existing transformers is as under: -
Sr.No Description As per existing detail
1. Exciation Transformer:
i. Rated capacity 100kVA
ii. Type DG100-15SP
iii. Rated frequency 50Hz
iv. Primary Volatage 11000 V
v. Secondary Volatage 110V
vi. Vector Group DYn5
vii. Weight 650kg
2. Generator PT Data
i. Ratio 11kV/3/110/3
ii. Burden 200VA
3. CT on Excitation Transformer Primary
side
i. Ratio 10/1A
72
ii. Accuracy class 5P10
iii. Burden 20VA
4 CT on Excitation Transformer Secondary
side
i. Ratio 4001A
ii. Accuracy class 3
iii. Burden 15VA
The excitation system shall be supplied a.c power by means of cables through a high
performance 3 phase dry type excitation transformer. The primary winding of the
excitation transformer shall be connected to the 11 KV system of the generator. A
suitable means (power cable) shall be provided to connect the primary winding of transformer with 11 KV system of the generator.
The excitation transformer shall be air natural cooled, metal enclosed, designed &
constructed to match perfectly with common switchgear assembly, indoor cast-resin dry
type, having class F insulation. The high voltage and low voltage windings shall be
impregnated and vacuum cast into moulds of glass fibre reinforced epoxy resin. The
windings shall be provided with temperature sensors and static alarm and tripping
device. Ratings of the excitation transformers shall be sufficient to meet the duties
specified herein.
The excitation transformer shall be in the cubicle part of the excitation cubicle, which
shall be made of removable panels. The arrangement shall be such that it is possible to
remove the transformer without dismantling the cubicle completely.
Since the high voltage winding is connected directly to the generator terminals, full
design consideration shall be given to the frequency increase rate, generator voltage
build-up rate and insulation co-ordination. Surge transmission from high voltage side to
the low voltage side shall be prevented by suitable means.
Metallic barriers of suitable design shall be installed between phases, inside the
transformer, to prevent any short circuit between phases. Necessary CT's shall be
provided on the primary side for over current protection besides other required safety and
monitoring devices.
6.2 Power Rectifier: -
The power rectifier equipment shall consist of 3- phase full wave power SCR thyristor
bridges, its associated firing circuits complete with power fuses in series with each
thyristor (fuses shall be monitored individually or in groups providing alarms and trips as
required) gate pulse transformer, RC snubbers and status light indicators for each bridge
on the front panel of rectifier cubicle. The design shall provide 100% redundancy i.e. at
73
full load operation (including ceiling voltage) the thyristor shall be working at 50% of
their nominal rating. The ceiling voltage shall be more than 2.0 p.u.
Two independent ignition circuits shall be provided for the manual and automatic control
respectively. The rectifier shall be rated for the following duty cycle:
a) Continuous operation at its rating.
b) Three-phase fault adjacent to HV terminals of the generator.
c) Short circuit on high voltage side of the transformer with duration of 2 seconds.
The modules shall be capable of coping with three phase short circuits at the generator
terminals or on the H.V side of the step up transformers of 3-sec. Duration.
The following monitoring and protection features shall be provided: -
- Thyristor and field circuit over voltage protection.
- A.C system over voltage and over current.
- D.C. short circuits.
- Temperature monitoring of thyristors
- Thyristor failure
- Transient over voltage originating from the A.C system, lightning or switching
surges.
The thyristor cubicles shall be cooled by forced air. For this purpose 100% capacity
reserve fans shall be supplied with provision of automatic switching to the reserve unit,
activated by fall in pressure and rise in temperature of exit air from main unit.
Calculation for the capacity of rectifier shall be submitted. While determining the
capacity, effect of ageing shall also be considered. The rectifier PIV (Peak Inverse
voltage) rating shall not be less than four times the maximum r.m.s. voltage of the inputs.
The system shall operate correctly with supply voltage upto 120% rated voltage or
unbalanced supply voltage.
The equipment shall have sufficient capacity to provide ceiling voltage and current
required by the generator. The voltage regulator shall provide suitable firing pulses to the
thyristors for stable control of terminal voltage and quick compensation of voltage
deviations caused by sudden load changes in the system.
6.3 Automatic Voltage Regulator: -
The voltage regulator shall be of quick acting microprocessor based and shall respond
continuously and instantaneously to correct any change in generator voltage. It shall
contain all the functionality necessary to limit, control and protect the generator from
operating outside of its capability. It shall be having Proportional Integral and Derivative
(PID) stability control. It shall maintain the generator voltage for steady state load
conditions without hunting, with 0.5% accuracy for any excitation with in the operating
range of the generator. For steady state conditions with the generator circuit open the
regulator shall maintain the generator terminal voltage at or below 110% of its setting for
speeds ranging from rated speed to an over speed of 120% rated speed. The system
limiting control shall be provided to limit the generator voltage to maximum 125% of
rated voltage in the event that the AVR is tripped co-incidentally with 100% load
rejection and generator speed rising to runaway speed. The voltage regulator will control
74
through different modes the voltage and / or current of the field of the generator.
Depending on the application, these modes can either be:
� Voltage regulation (Island mode).
� Droop regulation (Paralleled machines sharing the reactive current).
� VAR / Power factor (When connected to a grid).
6.3.1 Main features and functions
Main features
• Digital Signal Controllers (DSCs) shall be adopted in the main control unit of
excitation regulator, as the core chip. High-performance static CMOS technology
shall be implemented; the operating frequency can achieve 30 MHZ. The chip shall
have not only the data-processing capability but also the event-management ability
and embedded control functions, which shall improve the integration and reliability
of the system greatly.
• Ferro-electric memory (FRAM) with high-speed serial SPI interface shall be used for
storing required parameters. All of the parameters can achieve display real-time and
on-line modifying, and after modification the parameter can be preserved for a long
time from the effects of power down.
• Series communication port for communication with the host computer.
• Synchronous signal conditioning circuit, greatly reduce the interference by the signal
ditch.
• Three-phase full-bridge thyristor rectifiers with inversion function and high
efficiency hot-tube heat sink
• LED Push Buttons.
• Reliable AC, DC redundancy power supply.
• Independent dual hardware channel with automatic change-over function.
• Self-diagnosis and watch-dog.
• Test function to check the equipment even at generator standstill condition.
• Asynchronous interrupt programming method to avoid the faulty change over and
faulty trip by net interference. Update of the data acquisition, PID algorithm and
triggering angle calculation shall be fulfilled in less than 5 ms.
• Intelligent LCD display unit uses 16-bit MCU as the control core, adopts convenient
operation key and 192 X 128 dot-matrix LCD module. It shall provide a friendly
man-machine interface for users. Data displaying, parameter modifying and fault
recording of the excitation installation and the communication with host computer
can be realized through the interface.
Main functions
• Generator voltage regulating mode
• Field current regulating mode
• Constant power factor regulating mode
• Constant reactive power factor regulating mode
• Over-excitation limiting
• Under-excitation limiting
75
• Stator current limiter
• Field current limiter.
• Load angle limiter
• Line droop compensation
• Paralleling compensation
• Excitation fault supervision
• Under frequency limiter or V/Hz limiting
• De-excitation system
• Over voltage protection
• Voltage matching
• PT fault supervision
• Self start build up
• Series communication function
Auxiliary functions
• Power Supply Protection: Standby channel power supply fault alarm.
• Switch over from operating channel to standby channel alarm.
• Field Flashing Protection: Automatic cutoff on failure of flashing or flashing
overtime.
• Excitation Fault Protection: Switchover from operating channel to standby
channel, trip if switchover failed.
• Over-excitation and Under-excitation Protection
• V/Hz limitation
• Potential Transformer Failure Protection: Changeover from Auto channel to
manual Channel.
• Pulse Monitoring: Changeover from operation channel to standby channel.
• Auxiliary Supply Monitoring
Remote/Local control commands (the control push buttons)
• FIELD BREAKER ON (FCB ON)
• FIELD BREAKER OFF (FCB OFF)
• FLASHING ON
• AVR (AUTO) ON
• FCR (MANUAL) ON
• CH I ON
• CH II ON
• RAISE
• LOWER
• RESET
Status indicators and alarm signals to Control Room
• FIELD BREAKER ON
• FIELD BREAKER OFF
76
• PT FAILURE
• CONTROL BUS FAILURE
• OVER EXCITATION LIMITATION
• UNDER EXCITATION LIMITATION
Additional Features
• Auto tracking between excitation system operating modes
• Auto tracking between proposed excitation system units
• Sequence of events recording (SER)
• Oscillography
• Real time monitoring
• Internal testing provisions
• Password protection
• Firing module options
• Fast discharge circuit options
• Field Flashing the generator
6.3.2 Hardware Configuration of Voltage Regulator System:
Hardware channel shall consist of the following units: -
• Input adaptor unit,
• Active/ reactive transducer unit,
• Analog input unit,
• Input isolating unit,
• Output isolating unit,
• Digital input unit,
• Output unit,
• Central control unit,
• Pulse output unit,
• Keyboard and LCD display unit.
The input signals in input adaptor unit shall be generator terminal voltage (from VT),
generator current (from CT), field current and the output signals in the unit shall be the
conditioned input signals for sampling.
Active/reactive transducer unit shall be used to simulate the active and reactive
component of the generator current.
The analog input unit shall be used for generator voltage rectification and filtering,
synchronous signal pretreatment, frequency measuring signal generating, active/reactive
component adapting. The output of this unit shall be fed to the main central control unit.
Input isolation unit shall be used to isolate input signals such as generator status, control
operation
Digital input unit shall be used to isolate and convert the 24 V level signal (already
isolated) to 5 V level for CPU.
77
Digital output unit shall be used to opt-isolate CPU control and output signals.
Output isolating unit shall be used to isolate the signals from digital output unit via relays
for logic control circuit.
Central Processing Unit (CPU) shall be the core of the regulator. The following functions
shall be done here in this unit namely set-point value, PID filtering, trigger pulses,
channel follow-up, series communication, limitation and protection, parameter display,
parameter setting, parameter storage.
Pulse output unit shall be used to output trigger pulses to converter cubicles. The trigger
pulses shall be amplified in the final pulse unit in converter to trigger the thyristors in the
cubicles.
Keyboard and LCD display unit shall provide a friendly man-machine interface for users.
Data displaying, parameter modifying and fault recording of the excitation installation
and the communication with host computer can be realized through the interface.
The excitation cubicle shall be designed for local/remote control and shall include as a
minimum the following: -
• Pushbuttons: lamp test, reset, excitation ON, excitation OFF (with protection
cover)
• Switches: voltmeter phase switch (if applicable), AUTO/MANUAL mode switch
(with centre position), AVR Raise/Lower (with centre position), Remote/Local
control key selector switch.
The selection between the local or remote control mode shall be done by means of a key
protected switch. The key can only be removed in the remote position, and this function
shall disable the front door pushbuttons in the normal mode of operation. During
commissioning if specific operations such as maintenance are required, the key shall be
necessary to enable local control mode. This will, in turn, disable the remote I/O.
6.3.3 Manual Channel (Field Current Regulator):
The manual control mode shall be used as test facility (e.g. during commissioning or
maintenance of the equipment) or as back-up control mode in case of incorrect of the
AVR (e.g. loss of actual value, due to potential transformer failure)
When operating in the manual control mode, excitation controls the field current of the
synchronous machine by means of a field current regulator FCR. The actual value of the
field current it is taken inside of the excitation cabinet in order to ensure a control loop
which is independent of external measuring circuits and/or transducers.
The set-point function for the manual control mode has the similar functions as the set-
points as well as two different running times can be adjusted. When operating in manual
control mode, the set-point for field current may be controlled by raise of lower
commands.
An immediate reset input is provided in order to avoid over voltages caused by reactive
load rejections while operating in the manual control mode. If the machine breaker trips,
a pulse command is applied to the reset input which sets the field current immediately
78
back to pre-set value which normally corresponds to 90..100% of the no-load field
current of the synchronous machine.
The resulting error signal at the output of the set-point is applied to a filter circuit with PI
characteristics. The optimum settings of this PI-Filter are achieved by setting the DC
gain Vo, the proportional gain Vp and the integral time constant Ta.
6.3.4 Follow-up Control :
An automatic follow-up control ensures a surge-free change-over from automatic (AVR)
to manual control mode. When operating in the AVR mode, the difference signal
between automatic channel output and manual control output is used for the automatic
follow-up. This difference signal is also used as a feedback signal for the channel which
is presently not in operation and therefore in open loop condition. This is necessary for a
stable balancing between the AVR and the FCR.
In a double channel system the inactive channel follows automatically the leading
channel.
The AVR shall be provided with over & under excitation limiters. The intervention of
the limiters shall not cause perceptible deviations or oscillations of the generator active
& reactive power. Such devices shall allow the regulator to reduce the excitation voltage
to zero in order to prevent over voltage in case of operation, under line reactive load
conditions and over speeding of the unit. The characteristics of the under excitation
limiting curve shall match the static and dynamic stability curves of the generator.
The field current limiter shall act on AVR with a time delay so as not to disturb transient
response of the system during voltage dips/faults. A slip stabilizer unit shall be provided
to surpass the low frequency power oscillation during the operative conditions.
The AVR shall be equipped with a sensitivity-adjusting device and with adjustable
voltage droop compensation (compounding). The voltage regulating system shall include
device for improving the damping of active electromechanical oscillations. These
devices shall operate to supplement the voltage regulation action by addition of an
additional control signal into the excitation system input. This supplemental input signal
shall influence the excitation system a.c. to cause a change in field current of the
machine for stabilised operation.
After, the generator voltage attaining initial maximum value neglecting the instantaneous
rises following any load rejection upto 100% of rated load, DVR shall restore the
generator terminal voltage to a value not more than 10% above or below the voltage
being held before load rejection and shall maintain the voltage within these limits
throughout the period of the generator over speed.
The voltage setting device provided shall be of the solid-state digital type having a range
of + 10% for local & remote control and indication. For testing purposes setting of 10%
to 115% shall be adjustable at the AVR cubicle.
The excitation system shall be designed for manual and automatic operation with
provision for manual to auto changeover and vice versa. The change over from automatic
to manual control shall be performed automatically following a failure of the regulator
79
when operating on automatic control. The generator voltage shall be controlled with in
the range of + 10% of rated voltage. A static follower shall be provided so that, in the
event of change over from automatic to manual control or vice versa, it prevents the
excitation current from deviating more than 5% of no load excitation current under
steady state conditions. An alarm and visual indication shall be provided to indicate
change from "AUTO" to 'MANUAL'. The automatic and manual control circuit shall be
fully independent. Local & remote control shall also be possible.
7 Field Flashing Equipment: -
In order to over-come the deficiency of permanent magnetism when starting the
machine, initial excitation shall be applied to the field winding. The respective power
shall be derived from the a.c. supply system via transformer and rectifier. All equipment
for automatic field flashing i.e. circuit breakers, blocking diodes, control devices,
protection etc. shall be included. Provision shall also be made for field flashing through
station batteries as stand by arrangement. The field flashing circuit shall get disconnected
when 70% of the rated voltage is achieved at the generator terminals and normal
excitation circuit takes over.
The kVA rating and voltage ratio of field flashing transformer (forming part of supply)
and requirement of DC for field flashing shall be indicated in the bid alongwith other
details. While using batteries for field flashing the corresponding over voltage protection
shall be provided as a part of excitation equipment.
The system shall also cope with the requirements of excitation necessary for test runs.
8 De-Excitation System:-
The existing De-Excitation Systems are in-operation and are in healthy conditions. The
Tenderer shall quote the prices of the equipment excluding the cost of De-Excitation
System i.e. field circuit breakers & discharge resistors. In case bidders recommend to
replace these field circuit breakers & discharge resistors in case of non-compatibility
with their system, the price of these equipment/components may be quoted as optional
items. The name plate specifications of the existing field circuit breakers & discharge
resistors is as under: -
Sr.No Description As per existing detail
1. Field Circuit Breaker
i. Type of field breaker. UNILEC Field Circuit Breaker
ii. Rating of field breaker 80A- to 3000 A.
iii. Make BHEL.
iv. Auxilary contacts for field breaker 6NO + 6NC
v. Control Volatage of field breaker. 220V DC
2. Discharge Resister.
i. Type of Discharge resister NER/126
80
ii. Rating 126A
iii. Resistance in Ohm 1.0
To achieve a quick suppression of the generator field and thus the voltage, a discharge
resistor (voltage dependent type) shall shunt the field winding. Field circuit breakers
shall be provided for isolation of field circuit for ensuring definite disconnection of field
from the supply source and subsequent discharge of energy in the field circuit.
The energy shall be dissipated through a field discharge resistor, which shall be
connected across the field by the operation of field circuit breaker. The volt-ampere
characteristic of the discharge resistor shall permit a quick field current damping. The
normal operation of the circuit breaker shall be automatic through sequential controller.
The circuit breaker shall also be manually operated by means of control switches
provided on excitation panel.
9 Excitation Control Cubicle:-
The excitation control and voltage regulating equipment shall be suitable for manual and
automatic control and shall comprise of all control and supervisory devices required for
the operation of the entire excitation system. Suitable circuit containing position switches
and internal wiring within the equipment required to give correct operation & indication
and all other equipment necessary for the operation shall be provided. The necessary
relays and contactors for initiating and performing the automatic transfer of the generator
starting field-flashing source to the normal supply source (power rectifier) when the
generator terminal voltage has increased to sufficient value shall also be provided. The
minimum requirements for instrumentation are: -
- A.C. Generator Output voltage
- D.C. Field current
- D.C. Field Voltage
- Set point indicator for Auto control
- Delta voltage between auto and manual control.
- Power factor.
The digital voltage regulating and excitation control equipment shall be capable to
communicate via serial interface and the field bus.
10 Protection of Static Excitation Equipment:-
The excitation equipment shall be protected against internal faults, failure of thyristor
bridges, cooling fans etc. for which contacts shall be provided for alarm and shutdown of
the unit. The items of protection covered shall be the following but not limited to: -
- Excitation equipment internal faults
- Over current protection for overload and short circuit protection of the excitation
transformer and rectifiers.
- Over voltage protection for detection of sustained field over -voltage.
- Loss of regulator DC power.
81
- Failure of AVR.
- Individual cooling fan failure.
- Cooling fan failure (main and reserve)
- Failure of thyristor firing circuit.
- Current asymmetry protection (more than two stacks faulty).
- Loss of regulator D.C. power.
- Rectifier cubicle exit air high temperature.
- Excitation transformer winding temperature.
- Preventing of over fluxing of the transformer.
- Operation at maximum excitation limit.
- Operation at minimum excitation limit
- Operation of slip stabilizing unit.
- Current asymmetry, one thyristor stack faulty.
- Failure of field flashing circuit equipment.
- Loss of sensing.
- Field winding over temperature protection.
11 Excitation Connection: -
Power cable connections between the generator slip rings and the excitation cubicle shall
be provided. The power cables shall be of adequate copper cross section to continuously
carry the rated current of the excitation system and the maximum current. They shall be
made of highly flexible conductors and the cable insulation shall be of the heat resistant
type, taking into account the maximum temperature rise of 50 oC at 40 oC ambient
temperature in the slip ring compartment. The cables shall be adequately spaced and
supported with consideration to the electromechanical forces involved and designed to
prevent undue heating during continuous operation.
12 Communication Channels:
The AVR shall be capapble to communicate to a PC with suitable port for local
programming, mtering and communication along with complete window based software
equipment shall be provided with RS- 232 / RS-485 port for PID selelction program that
allow the user to selelct the stability settings and software.
13 Wiring Requirements
Excitation system internal wiring shall be carried out according to the following:
• Cables- Flexible multi-strand copper wire
• Insulation- Polyethylene insulation
• Terminals- Crimped, insulated sleeves on each end of wire
• Maximum number of 2 wires per terminals or pins
• Cable marking- Markers on each end of every wire, made with individual color
coded sleeves corresponding to the drawings.
• EN 60204-1 Compliant.
Bidders are requested to submit the proper documentation/evidence to justify the
achievement of afore-mentioned technical specifications, features and functions.
82
14 INSPECTION, TESTING AND COMMISSIONING
The whole of the Works supplied under the Contract shall be subject to inspection and test
by the purchaser or their Representative during manufacture, erection and after completion.
The inspection and tests shall include, but not be limited to, the requirements of this Section
of the Specification.
The Contractor shall provide all appliances, apparatus, supervision, labor and services
necessary to carry out all tests unless specifically stated otherwise.
The costs of all tests, including traveling expenses, cost of accommodation, per-diem and all
other relevant expenses for the inspecting personnel who will attend the factory tests shall
be borne by the Contractor.
The scope of the commissioning program includes the Site testing of all excitation
equipments. Testing of instrumentation and certification of their accuracy is also to be
provided.
The objectives of commissioning work, prior to the successful energisation of Plant at full
voltage and connection to the system, are the following:
- Confirm the integrity (correctness) of installation.
- Confirm the integrity of insulation, connections and phasing.
- Ensure proof of equipment characteristics.
- Review workmanship.
- Confirm the correct implementation of the design.
- Check equipment ratings.
- Check settings and operation of control and protection equipments.
- Check and measure resistivity of earthing grid and earthing system.
14.1 TESTS AT MANUFACTURER’S WORKS
14.1.1 General
Where no specific test is specified, then the various items of materials and equipment
shall be tested in accordance with the relevant British, IEC, or American Standards.
Where no appropriate standard is available, tests shall be carried out in accordance with
the maker's standard practice, which must meet with the approval of the Purchaser.
At least fourteen days notice in writing or by telefax shall be given to the Purchaser of
the readiness of plant for test or inspection and every facility shall be provided by the
Contractor and sub-Contractor(s) to enable the Purchaser or their Representative to carry
out the inspections and witness the tests. This includes progress, test rig and packing
inspection.
Inspection of equipment will not be carried out unless copies of the relevant sub-orders,
drawings and test procedures have been approved by the Purchaser.
No equipment shall be packed, prepared for shipment, or dismantled for the purpose of
packing for shipment, unless it has been satisfactorily inspected, or inspection has been
waived by the purchaser.
Functional electrical and mechanical tests shall be carried out on the completed plant
after assembly in the Works. The extent and method of recording the results shall be
agreed by the Purchaser in sufficient time to enable the tests to be satisfactorily
witnessed or to make any change to the proposed program of tests.
All instruments and apparatus used in the performance of the tests shall be to the
approval of the Purchaser and, if required by the Purchaser, shall be calibrated to an
83
agreed standard at a laboratory of national standing to be nominated by the Contractor
and approved by the Purchaser.
The cost of carrying out such calibration shall be borne by the Contractor in all cases.
The cost of making any test shall be borne by the Contractor. This shall apply to tests
performed at the site or elsewhere.
Under completion of manufacture at the factory the Purchaser will depute his personnel
to the Contractor’s factory to witness the fabrication, assembly and testing of any or all
parts of major equipment. The number of the Purchaser's personnel and equipment to be
witnessed will be as per explained in the special condition of Contract.
Following tests shall be conducted on static excitation system .
14.1.2 TEST AT WORKS :-
(a) Routine Tests At works :-
• Visual inspection for mechanical assembly on AVR, converter, field breaker &
wiring check.
• High voltage test
• Checking of control & regulation signal flow including electronic modules by
simulation.
• Power supply check.
• Light load test on each thyristor bridge.
• Control sequence interlock & protection tests on integrated equipment with all
cubicles interconnected as schematic diagram except excitation transformer
cubicles.
• Routine tests on excitation transformer as per IEC-726 or equivalent standards.
(b) Type Test At Works :
• Heat run test on thyristor bridge on one set of static excitation equipment.
• Heat run test on one excitation transformer.
14.1.3 Test Certificates
Within 30 days of the completion of any test, triplicate sets of all principal test records,
test certificates and performance curves shall be supplied to the Purchaser.
These test records, certificates and performance curves shall be supplied for all tests,
whether or not the Purchaser or his Representative has witnessed them. The information
given on such test certificates and curves shall be sufficient to identify the material or
equipment to which the certificate refers and should also bear the Contract reference
title. Specified requirements shall be shown on each certificate for comparison with
actual test results.
When all equipment has been tested and test certificates from all Works and Site tests
shall be compiled by the Contractor into volumes and bound in an approved form
complete with index. Two copies of each volume shall be supplied to the Engineer and
five copies to the Purchaser.
14.1.4 Type Tests
84
Type tests are required to prove the general design of the equipment and the Contractor
may submit test certificates of tests, which have been carried out on identical equipment.
Notwithstanding any provision in a BS, IEC or ANSI Standard, the Purchaser shall have
the right to accept such certificates in lieu of the specified type tests or to reject them.
The type tests prescribed shall be carried out at the Contractor's cost in all cases where
such certificates are not available or are rejected.
14.1.5 Safety Procedures:
The Contractor shall share the responsibility for safety procedures with the Purchaser.
The Contractor shall establish and implement a work permit and tagging system and
associated safety procedures (subject to the review of Purchaser) for all equipment,
systems and areas not covered by the Purchaser’s safety procedures.
The Purchaser will assume responsibility for the establishment and implementation of
tagging, safety and work permit procedures for the protection of personnel and
equipment, as soon as equipment and systems are connected to or are energized able
from the existing system.
14.2 Training of Staff:
14.2.1 The Contractor shall plan for the Purchaser’s staffs’ participation, either continuously or
on a regularly recurring basis, in the commissioning work and:
Allow the Purchaser staff to become familiar with the operating and maintenance aspects
of the new equipment.
Maintain a continuing assessment with the Purchaser of the precautions required in, or
possible consequences of, initial energisation of equipment.
Allow for the above two necessary objectives in the preparation of schedules.
The Contractor shall station at site at least one technical expert for a minimum of
required period continuously after commissioning to rectify any problems as well as train
the Purchaser’s attending staffs. If required the length of his stay shall be extended as per
requirement depending upon the seriousness of the problem encountered, which shall be
at the Purchaser’s discretion.
14.2.2 A Special Training class at site for seven days shall be conducted by the Contractor for
giving in detail of the Equipment in view of maintenance purpose. The refreshment
during training for above 7 Engineers/Technical personnel shall be on the account of the
Contractor.
14.3 COMMISSIONING STAFF
The Contractor shall provide commissioning personnel including skilled and unskilled
labor as required. `Submit a list with names, experience and proposed duration of the
presence of key personnel on Site, consistent with the construction schedule, at the same
time as the commissioning program. The refreshment including paying for above
Ensure that only staff assigned to commissioning fulfills that duty for the duration of the
assignment.
Ensure that commissioning staff has authorization, and the competence, to undertake
minor repairs or to make temporary redesigns and to reconnect systems to meet the
specified system performance to preclude delays in energization and putting into
commercial service of any part of the works.
The Contractor should arrange for the manufacturer's commissioning Engineer to carry
out the field test & commissioning of main equipment like AVR, FCB, Excitation
Transformer and Surge Protection Devices etc. Such personnel should certify the
completeness of such commissioning of the Equipments.
85
14.4 Test Equipment
The Contractor shall ensure that all instruments, tools and other equipment required for
testing and commissioning are available on site, ensure that the test equipment is of
satisfactory quality and condition and, where necessary, is calibrated by an approved
authority or standard.
Make arrangements for the provision of power supplies for testing with necessary vector
configuration, voltage and current rating.
14.5 Commissioning Program
Prepare a commissioning program for approval by the Contractor and for incorporation
into the Project master construction program. Allocate adequate time in this program to
permit full commissioning of all components.
Carry out all testing during normal working hours as for as is practicable. Tests, which
involve existing apparatus and system outages, may be carried out outside normal
working hours. Give to the Purchaser sufficient notice to allow for the necessary outage
arrangements to be made in conformity with the testing program.
Note that no tests listed in the agreed program will be waived except upon the instruction
or agreement of the Purchaser in writing.
14.6 Test Procedures
The following basic tests shall be carried out in addition to the other required tests:
- Measurement of insulation resistance.
- Electrical Operation Test
- Characteristic Test
14.7 Requirements for Field Tests
• Visual inspection.
• Dielectric test on excitation transformer.
• Pre-commissioning checks for control logic and electronic modules.
• Voltage build-up test in auto and manual mode of control.
• Test for determining control range in auto and manual mode of operation.
• Adjustment of AVR.
• Step response test for checking the response of AVR in auto control.
• Step response test for limiters.
• Tests on maximum excitation limiter.
• Tests of volts per cycle regulation.
• Minimum excitation limiter tests.
• Overall response of machine and excitation system voltage changes.
• Excitation system time response.
• Load rejection tests.
86
• Effectiveness of voltage regulator forcing action in de-magnetising the main regulator
field.
• Steady state accuracy of voltage control from no load to full load.
The field tests shall be carried out in the presence of Purchaser under the following
conditions:
The field tests shall be carried out by the Contractor after adjustment of all the equipment
have been completed.
Expandable and lead wires and other materials required for the field tests shall be
provided by the Contractor. The Contractor shall be responsible for providing all
measuring instruments test equipment and tools required for the tests.
Preparation of the test record sheets and test reports shall be the responsibility of the
Contractor and the results of the field tests shall be submitted by the Contractor to
Purchaser for approval.
Measurement of insulation resistance of the equipment shall be performed by at least
1000 V Megger.
After completion of the measurement of insulation resistance mentioned above,
Electrical Operation Tests shall be performed by the normal operation voltage of the
existing power system in accordance with the following procedure:
Submit test procedures, consisting of detailed test methods and samples of the related
test record forms, for all equipment to be tested, to the Purchaser for approval at the
same time as the commissioning program. Strictly adhere to these procedures for the
commissioning tests.
14.8 Records
Maintain an up-to-date record of all commissioning activities on site.
Record the results of the tests clearly on forms approved by the Purchaser and with clear
references to the equipment and items tested, so that the record can be used as the basis
for maintenance tests during the working life of the equipment. Submit the required
number of site test result records to the Purchaser as soon as possible after completion of
the tests.
Record the details of the test equipment and instruments used in the test sheets, in those
cases where the instrument or equipment characteristics can have a bearing on the test
results.
14.9 “As Built” Drawings
Keep an ongoing record of all changes on a master set of drawings. Produce and supply a
minimum of two complete sets of marked-up “As Constructed” drawings before leaving
the Site. Correct and re-issue the original drawings as soon as possible as per this
specification.
14.10 Test Methods
Carry out all necessary tests for commissioning the substations. The following clauses
detail tests which are considered to represent the minimum required in addition to those
specified under the appropriate IEC Publications, other approved standards and the
manufacturer’s instructions for each item of equipment.
Strictly adhere to the methods of testing approved by the Purchaser.
a) Site and Commissioning Tests for Main and Auxiliary Equipment
General Checks
87
Make a general check of all main and auxiliary equipments. Include a check of the
completeness, correctness and condition of ground connections, labeling, arcing ring,
paint surfaces, cables, wiring, pipe work, valves, blanking plates and all other auxiliary
and ancillary items.
Check for tightness of nuts and bolts and that insulators are clean and free from external
damage. Check that loose items, which are to be handed over to the Purchaser, e.g.,
tools, spares, are in order and are correctly stored or handed over.
AVR, Field Cabinets and Excitation Transformers
Carry out general testing and inspection, as referred to above. The Contractor shall also
carry following tests: a) AVR mode testing b) FCR mode testing c) VAR testing c) PF
control mode testing d) Voltage Build-up and perform timing tests on field circuit
breakers e) AC and DC circuits associated with stand by auxiliary supplies f) Protection
Function testing g) Discharge Circuitry Testing.
Carry out insulation secondary circuits tests with a 1000 V DC megger before and after
high voltage testing.
Check shutters, interlocking, earth procedures and the interchangeability of components.
Interlocking
Check all interlocking arrangements, both electrical and mechanical.
b) Earthing System
Carry out the tests and measurements in accordance with IEEE Standard 80.
c) Particular Constraints and Special Tests
The Contractor shall be prepared to cooperate with any special tests requested by the
Purchaser.
14.11 Excitation System Documentation :
The Documentation system shall be delivered with 2 sets of documentation, each set
containing:
• Instruction manual of each major component.
• Drawing package containing mechanical and electrical drawings, interconnection
drawing and equipment lists.
• Instruction manual of the complete system.
• Storage instructions details.
• Recommended Spare Parts of the Excitation System (Detail List)
• PC Software for all manufactured digital devices.
All the above shall be also included on a CD.
The drawings are subjected to approval prior to the commencement of the manufacturing
works.
Language of documentation
All the Excitation system documentation shall be supplied in the English language.
88
89
ANNEXURE-I
SCHEDULE OF REQUIREMENT AND PRICES
Name of work:
Sr.
no
Description of material Qty Ex-
works
price/
Excise
duty on
Ex-
works
price
Sales tax
& surcharge
on ST if any
on Ex works
price + ED
per no.
Freight
charges
per set
Comprehensive
Insurance
per set
Entry Tax
on Ex
works
Price +
Excise
duty +
sales Tax
per no.
Total
FOR
price
of
each.
4. 5. 6. 7. 8. 9. 10. 11. 12. 13.
1 Design, manufacture, shop assembly &
testing, comperhensive insurance, delivery,
erection, testing & commissioning at site,
field acceptance tests of static excitation
system before handing over to the
owner/HPSEB Ltd. and guaranteed for two
years of three (3) numbers static excitation
and Digital AVR systems complete with
accessories, equipment, devices, instruments,
cabling and wiring etc. including all services,
labour, tools and tackles in all respects.
3 Sets
2 Dismantling of existing panel and erection of
new panels, testing and commissioning
of new panels.
3 Jobs
3 Any other items which are left
out but necessary for the SES to perform
successfully should also be included.* Refer
detailed Technical
4 Design, manufacture, shop assembly &
testing, comperhensive insurance, delivery,
erection, testing & commissioning at site,
field acceptance tests of Excitation
3 Nos.
90
Transformer (Optional)
5 Design, manufacture, shop assembly &
testing, comperhensive insurance, delivery,
erection, testing & commissioning at site,
field acceptance tests of field circuit breakers
(Optional)
3 Nos.
6 Design, manufacture, shop assembly &
testing, comperhensive insurance, delivery,
erection, testing & commissioning at site,
field acceptance tests of discharge resistors
(Optional)
3 Nos.
DATE SIGNATURE :
PLACE : NAME :
SEAL:
DESIGNATI0N : Notes: - 1. The prevailing rates of EXCISE DUTY shall be specifically mentioned on each item. 2. The prevailing rate of central sales tax against form C shall be clearly mentioned. 3. The freight charges shall be separately quoted for each item. 4. The insurance charges shall be separately quoted for each item. 5. The tenderer is required to specifically state in his offer, if quoted prices are inclusive or exclusive
of amount of entry tax.
Signature of the Tenderer
91
ANNEXURE-II
TECHNICAL PARAMETERS OF SEE & AVR
1. Accuracy of voltage regulation in normal operating
condition.
:
2. Range of voltage settings :
• Auto Mode :
• Manual mode :
• For testing purpose in manual mode :
3. Voltage regulation from no-load to full load :
4. Response time :
5. Operating frequency :
6. Dead band :
7. Range of Reactive droop adjustment :
8. Ambient conditions
• Temperature : Up to 50 deg. Celsius
• Humidity : Upto 95% ( non-condensing)
9. Power for excitation equipment :
10. Type of converter :
11. Protection class of all panels :
Note :- All other technical parameters as per tender documents shall be taken care of while designing
of the equipment.
Certified that the offered values are within limits of relevant IEC/IS specification. Dated: Signature Place: Name & Designation .
92
Annexure-III Schedule of Spare Parts
Tenderer must quote for the set of recommended spare parts for five years trouble free service for each item. Sr. No. Description Qty. Unit Price Total Price
Signature of the Tenderer
93
ANNEUXRE-IV
DELIVERY & COMPLETION PERIOD
Sr. No. Item
Period in days
1. Period required to commence supply from the date of Letter of Intent, LOI
2. Period for supplying drawings for engineer’s approval
3. Period when equipment will be ready for inspection before dispatch
4. Period when the equipment will received FOR at 3 x 5.65 MW Andhra power house site.
5. Period by which all the existing equipment will be dismentalled and completely erected, tested and commissioned.
Signature of the Tenderer