93
1 HIMACHAL PRADESH STATE ELECTRICITY BOARD LIMITED BID DOCUMENTS FOR STATIC EXCITATION SYSTEM AND DIGITAL AVRFOR (3x5.65 MW) ANDHRA HYDRO-ELECTRIC PROJECT (Bid Specification No. HPSEBL/CEG/DB-3-4/2012) Prepared by Checked by Approved by (Rajiv Kumar Verma) (Rajesh Kapoor) (Rajnish Kumar Sharma) Assistant Executive Engineer Superintending Engineer Chief Engineer Chief Engineer (Gen.) HPSEBL, Sunder Nagar Distt. Mandi (H.P.) – 175 019. Tel: - 01907 – 265337, Fax: 01907-265338, Email –[email protected] Month:- Oct./2012 Rs. 1500/-

FOR (3x5.65 MW) ANDHRA HYDRO-ELECTRIC PROJECT Document Excitation System.pdf · 1 himachal pradesh state electricity board limited bid documents for “static excitation system and

Embed Size (px)

Citation preview

Page 1: FOR (3x5.65 MW) ANDHRA HYDRO-ELECTRIC PROJECT Document Excitation System.pdf · 1 himachal pradesh state electricity board limited bid documents for “static excitation system and

1

HIMACHAL PRADESH STATE ELECTRICITY BOARD LIMITED

BID DOCUMENTS

FOR

“STATIC EXCITATION SYSTEM AND DIGITAL AVR”

FOR

(3x5.65 MW)

ANDHRA HYDRO-ELECTRIC PROJECT

(Bid Specification No. HPSEBL/CEG/DB-3-4/2012)

Prepared by Checked by Approved by

(Rajiv Kumar Verma) (Rajesh Kapoor) (Rajnish Kumar Sharma)

Assistant Executive Engineer Superintending Engineer Chief Engineer

Chief Engineer (Gen.)

HPSEBL, Sunder Nagar

Distt. Mandi (H.P.) – 175 019.

Tel: - 01907 – 265337, Fax: 01907-265338, Email –[email protected]

Month:- Oct./2012 Rs. 1500/-

Page 2: FOR (3x5.65 MW) ANDHRA HYDRO-ELECTRIC PROJECT Document Excitation System.pdf · 1 himachal pradesh state electricity board limited bid documents for “static excitation system and

2

TABLE OF CONTENTS

Volume 1

Section No. I Information for Bidders (INFB)

Section No. II Instruction to Bidder (ITB)

Section No. III General Conditions of Contract (GCC)

Section No. IV Forms and Procedure (FP)

1 Bid Forms

2 Attachments Including Security

Forms

3 Price Schedule

4 Form of 'Notification of Award Contract' for supply of Plant and Equipment and their installation Services.

5 From of Contract Agreement.

6 Performance Security Forms.

7 Form of Completion Certificate. 8 Form of Operational Acceptance

Certificate.

Section No. V Technical Specification

Page 3: FOR (3x5.65 MW) ANDHRA HYDRO-ELECTRIC PROJECT Document Excitation System.pdf · 1 himachal pradesh state electricity board limited bid documents for “static excitation system and

3

SECTION-I

Information For Bidders (INFB)

Page 4: FOR (3x5.65 MW) ANDHRA HYDRO-ELECTRIC PROJECT Document Excitation System.pdf · 1 himachal pradesh state electricity board limited bid documents for “static excitation system and

4

INDEX

INFORMATION FOR BIDDERS

TABLE OF CONTENTS

CLAUSE NO. PARTICULARS PAGE NO. 1.0 INTRODUCTION 5 2.0 PROJECT DETAILS 5

3.0 TRANSPORT LIMITATION 5

4.0 COMMUNICATION FACILITIES & WORK SITE 5

5.0 CLIMATE/WEATHER 6

6.0 SEISMICITY OF THE PROJECT AREA 6

7.0 LABOUR AVAILABILITY 6

8.0 TEMPORARY/TRANSIT ACCOMODATION 6

9.0 ELECTRIC POWER 6

10.0 MATERIAL AND WORKSHOP FACILITIES 6

11.0 LABOUR LICENCE 6

12.0 MEDICAL FACILITIES 6

Page 5: FOR (3x5.65 MW) ANDHRA HYDRO-ELECTRIC PROJECT Document Excitation System.pdf · 1 himachal pradesh state electricity board limited bid documents for “static excitation system and

5

INFORMATION FOR BIDDERS

1.0 INTRODUCTION

HPSEB Ltd. has undertaken the execution of dismantling/removing of the existing excitation

system and detailed design, manufacture, shop assembly & testing, & commissioning of three (3)

numbers static excitation and Digital AVR systems complete with accessories to be installed in

the 3 X 5.65 MW Andhra Power House.

The scope of work of this tender includes all works necessary for dismantling/removing the

existing excitation system including carriage, stacking at Owner’s store/ yard and detailed design,

manufacture, shop assembly & testing, comprehensive insurance, delivery, erection, testing &

commissioning at site, field acceptance tests of static excitation system before handing over to the

owner/HPSEB Ltd. and guaranteed for two years of three (3) numbers static excitation and

Digital AVR systems complete with accessories, equipment, devices, instruments, cabling and

wiring etc. including all services, labour, tools and tackles in all respects as per technical

specifications.

2.0 PROJECT DETAIL

ANDHRA POWER HOUSE is located at Chirgaon near Rohru in Distt. Shimla. The Power

House commissioned in 1987 has 3 Units each of 5.65 MW. The average annual generation of

this Power House ranges between 60 MU to 70 MU, against designed potential of 87 MU. The

reservoir capacity is 45450 Cum.

3.0 TRANSPORT LIMITATION

3.1 The transport limitation by road from Shimla to the Plant Site would be the governing factor in

respect of the permissible package size and weight. Bidder should consider all factors as can be

envisaged for transportation of equipment to avoid and overcome the hindrances/ limitations

on existing road on account of weather conditions and any other reasons without affecting

the schedule .

The project areas are situated in earthquake zone V as per BIS 1893(1984). Hence, the equipment

shall have to be suitable to withstand safely and not to maloperate under earthquake forces

corresponding to zone V.

3.2 The Bidder at his cost shall be responsible for all safety aspects during execution of the works. As

such necessary protection barriers, warning signals & devices, posting of flags & flagmen at

desired locations on the routes are to be used by Bidder.

3.3 The Bidder shall deemed to have familiarised himself with the nature, environment, conditions

and any limitations or restrictions on road to be used by him during the period of the Contract.

The Bidder shall also take into consideration access limitations that may results in the event of

slips/slides of hill slopes or due any other reasons arises due to the local climatic/geographical

conditions. HPSEBL shall not entertain any claim from the Bidder on this account.

4.0 COMMUNICATION FACILITIES AT WORKS SITE The work site is well connected with STD & ISD facilities.

Page 6: FOR (3x5.65 MW) ANDHRA HYDRO-ELECTRIC PROJECT Document Excitation System.pdf · 1 himachal pradesh state electricity board limited bid documents for “static excitation system and

6

5.0 CLIMATE / WEATHER The rainfall is scanty. The south-west monsoon precipitation during June to September is

generally not heavy but at some times may contribute significantly towards flood run off. The

winter precipitation falls mostly as rain or sometimes snow depending upon the altitude and other

meteorological conditions. Summers are warm and winter temperature falls upto -12 degree

Celsius.

6.0 SEISMICITY OF THE PROJECT AREA The project area falls within isoseismal IX of Rossi-Forrel scale of intensity. According to Indian

standard code no.1893 of 1972, the area has been placed in zone V and a suitable factor of safety

as required has to be incorporated in the design of engineering structures and equipment.

7.0 LABOUR AVAILABILITY No skilled labour is available locally. Most of the skilled labour has to be brought from outside.

However, the Bidder shall make maximum efforts to explore the availability of local labour of

various categories and employ them to the extent possible. Liaison and good relation with locals

is very essential. To accommodate labour, Bidders shall have to make their own arrangement

8.0 TEMPORARY / TRANSIT ACCOMMODATION There is acute shortage of accommodations nearby project site. HPSEB has

constructed/developed some accommodation at different locations of the project for its own

employees. Bidder has to make his own arrangement for the temporary/transit accommodation.

9.0 ELECTRIC POWER Construction power at 11kV/415Volts shall be provided to the contractor to various sites,

colonies, offices etc. Each supply point shall be treated as separate connection. Arrangement for

further distribution of power to the contractor's sites, plants equipment and machinery,

workshop, colonies, offices etc. from the point of supply shall be made by the contractor at his

own cost. The electric energy shall be measured by a suitable meter installed at the point of

supply.

The contractor will adhere strictly to provision of Indian Electricity Act 1910, Electricity

(Supply) Act 1948, Indian Electricity Rules 1956, HPSEBL's abridged condition of supply and

HPSEBL's schedule of tariff.

.

10.0 MATERIAL AND WORKSHOP FACILITIES 10.1 All the consumable material required for the works, shall have to be arranged & provided by the

Bidder and included in the quoted prices.

10.2 Nearest workshop facilities for carrying out major works facilities either at Chandigarh, Ludhiana

or Batala shall be available.

11.0 LABOUR LICENCE The Bidder shall be required to obtain labour licence for deployment of labour from competent.

11.2 The Bidder shall strictly adhere to the labour laws and minimum wage act prevailing in the State

of Himachal Pradesh.

12.0 MEDICAL FACILITIES

The Bidder shall provide necessary medical facilities at the project site at his own expenses for

his workers.

Page 7: FOR (3x5.65 MW) ANDHRA HYDRO-ELECTRIC PROJECT Document Excitation System.pdf · 1 himachal pradesh state electricity board limited bid documents for “static excitation system and

7

SECTION-II

Instructions to Bidders (ITB)

Page 8: FOR (3x5.65 MW) ANDHRA HYDRO-ELECTRIC PROJECT Document Excitation System.pdf · 1 himachal pradesh state electricity board limited bid documents for “static excitation system and

8

INDEX

INSTRUCTIONS TO BIDDERS

TABLE OF CONTENTS

CLAUSE NO. PARTICULARS .PAGES

A. INTRODUCTION

1.0 GENERAL 9

2.0 SCOPE 9

3.0 ELIGIBILITY AND QUALIFYING REQUIREMENTS 9

4.0 COST OF BINDING 9

5.0 LOCAL CONDITIONS 9

B. BID DOCUMENTS

6.0 CONTENT OF BID DOCUMENTS 10

7.0 TIME SCHEDULE 10

C. PREPARATION OF BIDS

8.0 LANGUAGE OF BID 11

9.0 DOCUMENTS COMPRISING THE BIDS 11

10.0 BID FORM AND PRICE SCHEDULE 11

11.0 BID PRICES 12

12.0 CURRENCY OF BID 12

13.0 BID VALIDITY PERIOD 12

14.0 BID SECURITY 12

15.0 FORMAT AND SIGNING OF THE BID 13

D. SUBMISSION OF BIDS

16.0 SEALING AND MARKING OF BIDS 13

17.0 DEAD LINE FOR SUBMISSION OF BIDS 14

18.0 LATE BIDS 14

E. BID OPENING AND EVALUATION

19.0 OPENING OF BIDS BY OWNER 14

20.0 CLARIFICATION OF BIDS 15

21.0 CORRECTION OF ERRORS 15

22.0 EVALUATION AND COMPARISON OF BIDS 15

F. AWARD OF CONTRACT

23.0 OWNER'S RIGHT TO ACCEPT ANY BID AND TO REJECT

ANY OR ALL BIDS 16

24.0 AWARD CRITERIA 16

25.0 NOTIFICATION OF AWARD 16

26.0 SIGNING THE CONTRACT AGREEMENT 16

27.0 CONTRACT PERFORMANCE SECURITY 16

Page 9: FOR (3x5.65 MW) ANDHRA HYDRO-ELECTRIC PROJECT Document Excitation System.pdf · 1 himachal pradesh state electricity board limited bid documents for “static excitation system and

9

INSTRUCTIONS TO BIDDER A. Introduction

1.0 GENERAL

1.1 Himachal Pradesh State Electricity Board, the Owner, has issued an invitation for Bidder (IFB)

and will receive Bids, from eligible Bidders, for the works mentioned in the schedule of works.

2.0 SCOPE

The scope of work of this bid includes all works necessary for dismantling/removing the existing

excitation system including carriage, stacking at Owner’s store/ yard and detailed design,

manufacture, shop assembly & testing, comprehensive insurance, delivery, erection, testing &

commissioning at site, field acceptance tests of static excitation system before handing over to the

owner/HPSEB Ltd. and guaranteed for two years of three (3) numbers static excitation and

Digital AVR systems complete with accessories, equipment, devices, instruments, cabling and

wiring etc. including all services, labour, tools and tackles in all respects as per technical

specifications and consideration.

3.0 ELIGIBILITY AND QUALIFICATION REQUIREMENTS

a) The Bidders should be a contracting firm well experienced in the design, supply,

installation & commissioning of static excitation and Digital AVR systems. b) The Bidders should have a team of qualified professionals & highly skilled artisans.

c) The Bidders shall have sufficient and adequate tools & tackles for executing the work.

d) The Bidders should have completed the execution of at least two (2) such contracts

valued not less than Rs.60.00 lacs each in the past 5 years and the same must be in

successful operation for at least 2 years. Performance certificates as proof of the same

shall be supplied. Bids not accompanying the performance certificates from the previous

customers shall be summarily rejected.

4.0 COST OF BIDDING

4.1 All costs and expenses incidental to preparation and submission of the Bids including pre-award

discussion with the interesting Bidders, technical and other documentation etc., shall be to the

account of the Bidders. Owner will in no case be responsible or liable for these costs and

expenses, regardless of the conduct or outcome of the Biding process.

5.0 LOCAL CONDITIONS

5.1 It will be imperative on each Bidders to fully inform himself of all local conditions and factors,

which may have any effect on the performance of the contract covered under these specifications

and documents. In their own interest, the Bidders are particularly requested to familiarise

themselves with the latest amended Income-tax Act, Companies Act, Custom Act, Sales Tax,

Service Tax Act and other related acts and laws prevalent in India. The Owner shall not entertain

any request for clarifications from the Bidders, regarding such local conditions. The Bidders are

also advised to visit the sites to judge the quantum of work before submitting their Bids.

5.2 It must be understood and agreed that such factors have properly been investigated and

considered while submitting the proposals. No claim whatsoever including those for financial

adjustment to the contract awarded under these specifications and documents will be entertained

by the Owner. Neither any change in the time schedule of the contract nor any financial

Page 10: FOR (3x5.65 MW) ANDHRA HYDRO-ELECTRIC PROJECT Document Excitation System.pdf · 1 himachal pradesh state electricity board limited bid documents for “static excitation system and

10

adjustments arising thereof shall be permitted by the Owner which are based on the lack of such

clear information or its effect on the contract.

5.3 The Bidders is strongly advised to visit and examine the sites of work and its surroundings

including approaches to project & work site, space for storage, ventilation, power and

communication and obtain for himself on his own responsibility all information that may be

necessary for preparing the Bid and entering into a contract. The cost of visiting the site shall be

at Bidder's own expense. The Owner will assist interested Bidders to see and inspect the site of

works.

B. Bid Documents

6.0 CONTENT OF BID DOCUMENTS 6.1 The Biding procedures, contract terms and technical requirements are prescribed in the Bid

documents. The Bid Documents will include the following:-

Section no. Name of Document.

I Information for Bidders (INFB).

II Instruction to Bidders (ITB).

III General Condition of Contract (GCC).

IV Forms and Procedure (FP).

1. Bid Forms

2. Attachments Including Security Forms

3. Price Schedule

4 Form of 'Notification of Award Contract' for supply of Plant and

Equipment and their installation Services.

5 From of Contract Agreement.

6. Performance Security Forms.

7 Form of Completion Certificate.

8 Form of Operational Acceptance Certificate.

V Technical Specifications.

6.2 The Bidders is expected to examine all instructions, forms, schedules, terms, specifications and

other information in the Bid Documents. Failure to furnish all information required by the Bid

Documents or submission of a Bid not substantially responsive to the Bid Documents will be at

Bidder's risk and may result in rejection of its Bid.

7.0 TIME SCHEDULE 7.1 The basic consideration and the essence of the contract shall be the strict adherence to the time

schedule for performing the works under the proposal/contract. The works awarded under the

Contract shall have the Commissioning period of Six months from the date of award of

work to contractor by HPSEB.

C. Preparation of Bids

Page 11: FOR (3x5.65 MW) ANDHRA HYDRO-ELECTRIC PROJECT Document Excitation System.pdf · 1 himachal pradesh state electricity board limited bid documents for “static excitation system and

11

8.0 LANGUAGE OF BID The Bid prepared by the Bidders and all correspondence and documents relating to the Bid

exchanged by the Bidders and the Owner shall be written in English. Supporting documents and

printed literature furnished by Bidders in any other language shall be accompanied by its true and

faithful translation of the pertinent passages in English. For the purpose of interpretation of the

Bid, the English translation shall govern. Failure to comply with this may disqualify a Bid.

9.0 DOCUMENTS COMPRISING THE BID 9.1 Bid submitted by the Bidders shall comprise the following documents:

a) Bid Form duly completed and signed by the Bidders, together with all Attachments

identified in ITB sub-clause 9.2 below.

b) Price Schedules duly completed by the Bidders.

9.2 Each Bidders shall submit with its Bid the following attachments.

(a) Attachment 1: Bid Security/earnest money deposit.

A Bid Security furnished in accordance with ITB Clause 14.0 (Bid Security).

(b) Attachment 2: Power of Attorney.

A power of attorney, duly authorised by a Notary Public, indicating that the person(s)

signing the Bid has the authority to sign the Bid and thus that the Bid is binding upon the

Bidders during the full period of its validity in accordance with ITB Clause 15.0 (Format

and Signing of Bids).

(c) Attachment 3: Bidder's Qualifications & Eligibility criteria.

(d) Attachment 4: List of Erection Tools & commissioning instruments which the Bidders

proposes to bring to site in case the contract is awarded to him.

(e) Attachment 5 : Milestone schedule showing the timing & sequence of all key activities

necessary for successful completion of the contract and giving important Mile Stones.

(f) Attachment 6 & 6A: Deviations

Deviations, if any, from the terms and conditions or Technical Specifications shall be

listed in the following attachments of the bid:-

i) Deviations in commercial terms and conditions: - Attachment- 6

ii) Deviations in technical specifications: - Attachments- 6A

The Bidder shall also provide the additional price, if any, for withdrawal of the deviations.

Bidders may further note that except for deviations listed in Attachment 6 and Attachment 6A,

the bid shall be deemed to comply with all the requirement in the bidding documents and the

Bidders shall be required to comply with all such requirements of bid documents and technical

specifications without any extra cost to the Owner irrespective of any mention to the contrary,

any where else in the bid.

Bidder may further note that deviations in commercial terms and conditions shall be listed in

attachment 6 & technical in attachment 6A respectively.

10.0 BID FORM AND PRICE SCHEDULE

Page 12: FOR (3x5.65 MW) ANDHRA HYDRO-ELECTRIC PROJECT Document Excitation System.pdf · 1 himachal pradesh state electricity board limited bid documents for “static excitation system and

12

The Bidders shall complete the Bid Form and the appropriate Price Schedules furnished in the

Bid Documents as indicated therein and in the Subsection "Bid Form and Price Schedule" of the

Bid Documents, following the requirements of ITB Clause, 11.0 and 12.0.

11.0 BID PRICES 11.1 Bidders quoting a system of pricing other than that specified run the risk of rejection.

11.2 The Bidders shall fill in prices for all items as specified in the Bid Form. Items against which no

price is entered by the Bidders will not be paid by the Owner when executed and shall be deemed

to be included in the other prices in the "Bid Form and Price Schedules".

11.3 The rates and amounts shall be quoted in decimal in such a manner that no interpolation is

possible. Corrections, if any, shall be made by crossing out, initialling, dating and rewriting.

Corrections should not be carried out by applying correcting fluid.

11.4 Bidders shall give a breakdown of the prices in the manner and details called for in the Price

Schedule.

11.5 Price quoted by the Bidders shall be “FIRM” and no price variation shall be paid.

12.0 CURRENCIES OF BID 12.1 Price shall be quoted in Indian Rupees only.

13.0 BID VALIDITY PERIOD 13.1 Bids should be kept valid for acceptance for a period of six (6) calendar months from the date of

opening of Bids prescribed in ITB Clause 19.0 (Opening of Bids by Owner).

13.2 In exceptional circumstances, prior to expiry of the original Bid validity period, Owner may

request the Bidders for a specified extension in the period of validity. The request and the

responses thereto shall be made in writing or by fax. A Bidders may refuse the request without

forfeiting his Bid Security. A Bidders agreeing to the request will neither be required nor

permitted to modify his Bid, but will be required to extend the validity of his Bid guarantee

correspondingly. The provision of ITB Clause 14.0 (Bid Security), hereof regarding discharge

and forfeiture of Bid Security shall continue to apply during the extended period of Bid validity.

14.0 BID SECURITY

14.1 Pursuant to ITB Clause 9.0 (Document Comprising the Bid), the Bidders shall deposit bid

Security of amount Rupees Seventy Five thousand only. Bid security of Rs. 50,000/- (Fifty

thousand) shall be furnished in the shape of a Crossed bank draft of any Indian Nationalized

Bank, drawn in favour of the Accounts Officer, O/O the Chief Engineer (Generation), Sunder

Nagar – 175 019 and payable at Sunder Nagar – 175 019 (H.P.) and for the balance amount an

irrevocable Bank Guarantee from an Indian Nationalized Bank valid for (Twelve ) 12 months

from the date of the opening of the bid, in favour of the Accounts Officer, O/O the Chief

Engineer (Generation), Sunder Nagar – 175 019shall be furnished.

14.2 Bid Security is required to protect Owner against risk of Bidder's conduct which would warrant

the security's forfeiture, pursuant to ITB Clause 14.7.

14.3 Any Bid not secured in accordance with ITB Clause 14.1 above shall be rejected by the Owner as

being non responsive.

14.4 Unsuccessful Bidder's Bid Security will be discharged/ returned as promptly as possible as but

not later than thirty (30) days after expiration of the period of Bid validity prescribed by the

Owner pursuant to ITB Clause 13.0 (Bid Validity Period).

Page 13: FOR (3x5.65 MW) ANDHRA HYDRO-ELECTRIC PROJECT Document Excitation System.pdf · 1 himachal pradesh state electricity board limited bid documents for “static excitation system and

13

14.5 Successful Bidder's Bid Security will be discharged upon execution of the contract deed, pursuant

to ITB Clause 26.0 (Signing of Contract Agreement), and furnishing the required performance

security pursuant to ITB Clause 27.0 (Contract Performance Security).

14.6 No interest shall be paid by the Owner on the Bid Security.

14.7 The Bid Security may be forfeited:

(i) if the Bidders withdraws or modifies unilaterally his Bid during the period of Bid

validity;

or

(ii) if the Bidders does not accept the correction of his Bid price pursuant to ITB

Clause 21.0 ( Corrections of Error).

(iii) in the case of a successful Bidders, if the Bidders fails within the specified time limit to :

(a) accept the letter of award;

or

(b) sign the Contract Deed;

or

(c) furnish the required contract performance security.

15.0 FORMAT AND SIGNING OF THE BID 15.1 The Bidders shall prepare an original and two (2) copies/sets of the Bid clearly marking each one

as "Original Bid", "Copy No. 1", "Copy No.2". In the event of any discrepancy between them the

original shall govern.

15.2 The original and all copies of the Bid, each consisting of the documents listed in ITB Clause 9.0

(Documents Comprising Bid) , shall be typed or written in indelible ink and shall be signed by the

Bidders or a person or persons authorised to signing the Bid.

15.3 The name of all persons or persons signing the Bid should also be typed or printed below the

signature. All pages of the Bid, except for un-amended printed literature shall be initialled by the

person or persons signing the Bid.

15.4 Satisfactory evidence of authority of the person signing on behalf of the Bidders shall be

furnished with the Bid in the form of a Power of Attorney, duly authorised by a Notary Public,

indicating that the persons signing the Bid have the authority to sign the Bid and that the Bid is

binding upon the Bidders during the full period of its validity. This shall be submitted as

Attachment 2 to the Bid under ITB sub-clause 9.2 (b) (Power of Attorney).

15.5 The Bidder's name stated on the proposal shall be the exact legal name of the firm.

15.6 Any interlineations, erasures or overwriting shall only be valid if they are initialled by

signatory(ies) to the Bid.

15.7 Bids not conforming to the above requirements of signing may be disqualified.

D. Submission of Bids

16.0 SEALING AND MARKING OF BIDS.

16.1 The Bidders must submit the Bid in the following two separate sealed envelopes duly marking

envelopes as "Original Bid" and "Copy no.1 &2- ". The envelopes shall then be sealed in an outer

envelope.

(i) Bid Security

First Envelope.

(ii) Techno-Commercial and Price Bid Proposal (1 Original + 2

Copies) along with duly filled (wherever required) and signed

copies of conditions of contract, General technical specifications.

Second Envelope.

Page 14: FOR (3x5.65 MW) ANDHRA HYDRO-ELECTRIC PROJECT Document Excitation System.pdf · 1 himachal pradesh state electricity board limited bid documents for “static excitation system and

14

16.2 The inner and outer envelopes shall:

(a) be addressed to the Chief Engineer (Gen.), HPSEBL, Sunder Nagar Distt Mandi H.P.

and;

(b) super scribed as Proposal for Design, Engineering, Fabrication, Supply, Transportation,

Insurance, Installation, Erection, Commissioning & Testing of Static Excitation and

Digital AVR System and the statement "DO NOT OPEN BEFORE “30.10.2012, 15.00

hrs.”

16.3 The inner envelopes shall also indicate the name and address of the Bidders so that the Bid can be

returned unopened in case it is declared "late".

16.4 If the outer envelope is not sealed and marked as required by ITB sub-clause 16.2 above, the

Owner will assume no responsibility for the Bid's misplacement or premature opening. If the

outer envelope discloses the Bidder's identity, the Owner will not guarantee the anonymity of the

Bid submission, but this disclosure will not constitute grounds for Bid rejection.

17.0 DEAD LINE FOR SUBMISSION OF BIDS 17.1 Bids must be received in the office of the “Chief Engineer (Gen.), HPSEBL, Sunder Nagar

Distt Mandi H.P. " on or before 1300 hours (IST) of 30.10.2012”. In the event of the date of

submission of Bids being declared as holiday for the Owner, the Bids will be received upto the

appointed time on the next working day.

17.2 The Bidders has the option of sending the Bid by registered post/courier or by submitting the Bid

in person. Bids submitted by fax/telegram / telex letter shall not be accepted. No request from any

Bidders to the Owner to collect the proposal from airlines, cargo agents etc. shall be entertained.

17.3 The Owner may at its discretion, extend the dead line for submission of Bids, in which case all

rights and obligations of the Owner and the Bidders previously subject to the original dead line

shall thereafter be subject to the new deadline as extended.

18.0 LATE BIDS 18.1 Bids submitted after the time and date fixed for the receipt of Bids as set in ITB Clause 17.0 shall

be rejected and such Bids if so desired by the said Bidders may be permitted to be collected back

by such Bidders provided such requests are received by the Owner within fifteen (15) days from

the date of Bid opening.

E. Bid Opening and Evaluation

19.0 OPENING OF BIDS BY OWNER

19.1 All Bids received within the stipulated time will be opened in the office of the “Chief Engineer

(Gen.), HPSEBL, Sunder Nagar Distt Mandi H.P. " by the officer(s) duly authorised by the

Owner for this purpose at 15.00 hrs (IST) on 30.10.2012 in the presence of the Bidder's

authorised representatives who may wish to attend. In the event of specified date of Bid opening

being holiday for Owner, the Bids shall be opened at the appointed time and location on the next

working day.

Page 15: FOR (3x5.65 MW) ANDHRA HYDRO-ELECTRIC PROJECT Document Excitation System.pdf · 1 himachal pradesh state electricity board limited bid documents for “static excitation system and

15

19.2 Bidder's authorised representative (upto two persons) may attend the Bid opening and they have

to sign a register provided by the Owner for evidencing their participation. No electronic

recording device/mobile phones etc., shall be permitted during the Bid opening.

19.3 The techno-commercial and price Bid (second envelope) of only those Bidders shall be opened

whose Bids security envelope (first envelope) found to contain (after opening) the Bid Security of

requisite value in acceptable form. The Bids with Bid Security deficient in value and/or form will

not be opened further and Bid envelopes of such Bidders will be returned unopened.

19.4 The officer(s) of the Owner authorised for opening of Bids will announce the Bidder’s names, the

presence or absence of the requisite Bid Security, Bid Prices, any discounts, the presence of any

alternative Bid and other such details as the said officers at their discretion may consider

appropriate.

19.5 Bids (sent pursuant to ITB sub-clause 17.2) that are not opened and read out at Bid opening will

not be considered for further evaluation, regardless of the circumstances.

20.0 CLARIFICATION OF BIDS To assist in the examination, evaluation and comparison of Bids the Owner, may at its discretion

ask any Bidders for clarification of his Bid, including break-up of unit rates. The request for

clarification and the response shall be in writing or by fax, but no change in the price or

substance of the Bid shall be sought, offered or permitted except as required to confirm

the correction of arithmetic errors discovered by the Owner during the evaluation of the Bids in

accordance with ITB Clause 21.0 (Correction of Error) hereof.

21.0 CORRECTION OF ERRORS 21.1 The errors/ discrepancies in respect of the specified amount in Price Bid Part-of Bid Proposal

Sheets for an individual item and / or sub-item and or in the sub-total of a schedule and/or in the

Grand total of a schedule and/or in the lump-sum price of the package either due to discrepancy

between figures and words and/or simple arithmetical error while adding and/or multiplying

and/or due to wrong extension of unit rates etc ; the error will be rectified and computed by

Owner as per the following method: -

(i) In case of discrepancy between figure and words, the value specified in the words will be

considered for computation.

(ii) Firstly, the unit rates in words will be considered for computation.

(iii) In case unit rates are not indicated in words then unit rates indicated in figure will be

considered and will be used for deriving the amount from the quantities specified in the

Bid documents.

(iv) In case error is due to wrong extension of quantities, the quantities as specified in the Bid

documents will be considered and multiplied by the quoted unit rates to obtain the

amount. The amounts will be computed as per the extension of amount of individual

item, sub-item, sub-total of a schedule, grand total of a schedule and lump sum price of

the package based on the above consideration.

21.2 After computation of the amounts as above, the values as computed and as quoted will be

compared and higher of the two will be considered for the purpose of evaluation of Bid and lower

values will be considered for the purpose of award/payment (in case of successful Bidders). If the

Bidders does not accept the above consideration, his Bid will be rejected and the Bid Security

may be forfeited.

22.0 EVALUATION AND COMPARISON OF BIDS 22.1 The Bids will be evaluated by the Owner to ascertain the lowest evaluated, technically and

commercially responsive Bid for the complete scope of work, as detailed in the Bid Documents.

Page 16: FOR (3x5.65 MW) ANDHRA HYDRO-ELECTRIC PROJECT Document Excitation System.pdf · 1 himachal pradesh state electricity board limited bid documents for “static excitation system and

16

F. Award of Contract

23.0 OWNER'S RIGHT TO ACCEPT ANY BID AND TO REJECT ANY OR ALL BIDS The Owner reserves the right to accept or reject any Bid, and to annul the Bid process and reject

all Bids at any time prior to award of contract, without thereby incurring any liability to the

affected Bidders or Bidders or any obligation to inform the affected Bidders or Bidders of the

grounds for Owner's action.

24.0 AWARD CRITERIA 24.1 Subject to ITB Clause 23.0 (Owners Right to Accept any Bid) hereof, the Owner will award the

contract to the Bidders whose Bid has been determined to be substantially responsive to the Bid

Documents and who has offered the lowest Evaluated Bid Price pursuant to ITB Clause 22.0

(Evaluation and Comparison of Bid), further provided that such Bidders has been determined to

be eligible/ qualified to perform the contract satisfactorily.

24.2 The Bidders would be required to comply with all the requirements of Bid Documents failing

which his Bid Security will be forfeited.

24.3 The Owner reserves the right to vary the quantity or items of work altogether at the time of

Award of Contract.

25.0 NOTIFICATION OF AWARD 25.1 Prior to the expiration of the period of Bid validity, the Owner will notify the successful Bidders

in writing by registered letter or by fax to be confirmed in writing by registered letter that his Bid

has been accepted. The notification of award will constitute the formation of the Contract.

25.2 On furnishing of a performance security by the successful Bidders, pursuant to ITB Clause 27.0

(Contract Performance Security), of Owner will promptly notify each unsuccessful Bidders and

will discharge its Bids security.

26.0 SIGNING THE CONTRACT AGREEMENT 26.1 Within (15) fifteen days of receipt of the Letter of award, on a date and time mutually agreed

upon, the successful Bidders or his authorised representative shall attend the office of the Owner

for signing of the Agreement.

26.2 Failure on the part of the successful Bidders to comply with the requirements this Clause will

constitute sufficient grounds for the annulment of the award and forfeiture of the Bid Security.

27.0 CONTRACT PERFORMANCE SECURITY 27.1 Within (15) fifteen days after receipt of letter of award but not later than the signing of the

Contract Agreement, the successful Bidders shall be required to furnish to the Owner, a Contract

Performance Security in the form of an irrevocable Bank Guarantee for an amount equivalent to

10% (ten percent) of the contract price, as per proforma annexed to Bid document for the faithful

performance of contract in accordance with the conditions of the contract.

27.2 Failure of the successful Bidders to comply with the requirement of ITB Clause 26.0 (Signing of

Contract Agreement) and 27.0 (Contract Performance Security) shall constitute sufficient grounds

for the annulment of the award and forfeiture of the Bid Security, in which event Owner may

make the award to the next lowest evaluated Bidders or call for new Bids.

27.3 Should the Contract period, for whatever reason be extended, the Bidders, shall at his own cost,

get the validity period of Bank Guarantee in respect of performance security furnished by him

extended and shall furnish the extended/revised Bank Guarantee to Owner before the expiry date

of the Bank Guarantee originally furnished.

Page 17: FOR (3x5.65 MW) ANDHRA HYDRO-ELECTRIC PROJECT Document Excitation System.pdf · 1 himachal pradesh state electricity board limited bid documents for “static excitation system and

17

SECTION-III

General Conditions of Contract (GCC)

Page 18: FOR (3x5.65 MW) ANDHRA HYDRO-ELECTRIC PROJECT Document Excitation System.pdf · 1 himachal pradesh state electricity board limited bid documents for “static excitation system and

18

INDEX

GENERAL CONDITIONS OF CONTRACT

TABLE OF CONTENTS

CLAUSE NO. PARTICULARS PAGE NO.

1.0 DEFINITIONS 19

2.0 CONTRACT DOCUMENTS 20

3.0 INTERPRETATION 20

4.0 NOTICES 21

5.0 GOVERNING LAW 21

6.0 ARBITRATION 21

7.0 SCOPE OF WORK 21

8.0 TIME FOR COMMENCEMENT AND COMPLETION 22

9.0 CONTRACTOR'S RESPONSIBILITIES 22

10.0 OWNER'S RESPONSIBILITIES 22

11.0 CONTRACT PRICE 22

12.0 TERMS OF PAYMENT 22

13.0 SECURITIES 22

14.0 TAXES AND DUTIES 23

15.0 DEDUCTION FROM CONTRACT PRICE 23

16.0 CONFIDENTIAL INFORMATION 24

17.0 REPRESENTATIVES 24

18.0 WORK PROGRAMME 25

19.0 MAINTENANCE 26

20.0 . TEST AND INSPECTION 28

21.0 COMPLETION OF THE WORKS 28

22.0 COMMISSIONING AND OPERATIONAL ACCEPTANCE 29

23.0 COMPLETION TIME GUARANTEE 29

24.0 DEFECT LIABILITY 30

25.0 LOSS OF OR DAMAGE TO PROPERTY 31

26.0 INSURANCE 31

27.0 CHANGES IN LAWS AND REGULATIONS 31

28.0 FORCE MAJEURE 31

29.0 WAR RISKS 32

30.0 EXTENSION OF TIME FOR COMPLETION 33

31.0 SUSPENSION 33

32.0 TERMINATION 33

33.0 ASSIGNMENT 35

34.0 TEST SERVICE PERIOD 35

Page 19: FOR (3x5.65 MW) ANDHRA HYDRO-ELECTRIC PROJECT Document Excitation System.pdf · 1 himachal pradesh state electricity board limited bid documents for “static excitation system and

19

GENERAL CONDITIONS OF CONTRACT

1.0 DEFINITIONS 1.1 The following words and expressions shall have the meanings hereby assigned to them:

"Completion" means that the works detailed in the schedule of quantities and prices (or a

specific part thereof where specific parts are specified in the Contract Document) have been

completed operationally and structurally and put in a tight and clean condition, and that all work

in respect of Pre-commissioning of the Works or such specific part thereof has been completed.

"Contract" means the Contract Agreement entered into between the Owner and the Contractor,

together with the Contract Documents referred to therein; they shall constitute the Contract, and

the term "the Contract" shall in all such documents be construed accordingly.

"Contract Documents" means the documents listed in Article 1.1 (Contract Documents) of the

Form of Contract Agreement (including any amendments thereto).

"Contractor" means the person whose Bid to perform the Contract has been accepted by the

Owner and is named as such in the Contract Agreement, and includes the legal successors or

permitted assigns of the Contractor.

"Contractor's Equipment" means all plant, works, equipment, machinery tools, apparatus,

appliances or things of every kind required in completion of works that are to be provided by the

Contractor.

“Contract Price " means the sum specified in Article 2.1(Contract Price) of the Contract

Agreement, subject to such additions and adjustments thereto or deductions there from, as may be

made pursuant to the Contract.

"Contractor's Representative" means any person nominated by the Contractor and named as

such in the Contract Document as per GCC sub-clause 17.2 (Contractor's Representative) hereof

to perform the duties delegated by the Contractor.

"Day" means calendar day of the Gregorian calendar.

"Defect Liability Period" means the period of validity of the warranties given by the Contractor

commencing at completion of the Works or a part thereof, during which the Contractor is

responsible for defects with respect to the Works (or the relevant part thereof) as provided in

GCC Clause 24.0 (Defect Liability) hereof.

"Effective Date" means the date from which the Time for completion shall be determined as

stated in Article 3 (Effective Date for Determining Time for Completion) of the Form of Contract

Agreement.

"Engineer in-charge" means the person appointed by the Owner in the manner provided in GCC

sub-clause 17.1 (Engineer-in-Charge) hereof to perform the duties delegated by the Owner.

"Works" means the services to be carried out by the Contractor under the Contract.

"GCC" means the General Conditions of Contract hereof.

"Government" means Government of India or Government of Himachal Pradesh and ,

(i) "Government of India" means President of India and his successors.

(ii) "Government of Himachal Pradesh" means Governor of Himachal Pradesh and his

successors.

"Services" means those entire services which are to be provided by the Contractor under the

Contract.

"Month" means calendar month of the Gregorian calendar.

"Operational Acceptance" means the acceptance by the Owner of the Works (or any part of the

Works where the Contract provides for acceptance of the Works in parts), which certifies the

Contractor's fulfillment of the Contract in respect of the works in the scope of the Contract.

"Owner / HPSEBL" means the Himachal Pradesh State Electricity Board Limited having its

registered office at Vidyut Bhawan Shimla-India and includes the legal successors or permitted

assigns of the Owner.

Page 20: FOR (3x5.65 MW) ANDHRA HYDRO-ELECTRIC PROJECT Document Excitation System.pdf · 1 himachal pradesh state electricity board limited bid documents for “static excitation system and

20

“Pre-commissioning” means the testing, checking and other requirements specified in the General

Technical Specification/ technical requirements that are to be carried out by the Contractor.

"Site" means Barrage of Larji Power House.

"Time for Completion" means the time within which completion of the Works is to be attained in

accordance with the stipulations in the GCC and the relevant provisions of the Contract.

2.0 CONTRACT DOCUMENTS

2.1 The term Contract Documents shall mean and include the following which shall be deemed to

form an integral part of the Contract.

(a) The Contract Deed and the Appendices hereto.

(b) Notification of Award.

(c) Forms & Procedures (as listed)

(d) Technical Specification.

(e) General Conditions of Contract.

(f) Information for Bidders.

(g) The Bid and Price Schedules submitted by the Bidder.

2.2 All the aforesaid Contract Documents including the letter of award shall form an integral part of

the Contract, in so far as the same or any part thereof conform to the Bid Documents and what

has been specifically agreed to by the and brought out in its letter of Award . Any matter

inconsistent therewith, contrary or repugnant thereto or any deviation taken by the Contractor in

its "Proposal" but not agreed to specifically by the in its letter of Award shall be deemed to have

been withdrawn by the Contractor.

2.3 The documents mentioned at clause 2.1 above forming the Contract are to be taken as mutually

explanatory of one another.

2.4 The Contract as per proforma annexed is to be signed within fifteen (15) days of the date of the

Letter of Award, on a date and time to be mutually agreed and at the office of the Owner unless

otherwise agreed to. The Contractor shall provide for signing of the Contract, appropriate Power

of Attorney and the requisite documents. Till such time a formal Contract is prepared and

executed, the Letter of Award read in conjunction with the Contract Documents will continue to

constitute a binding Contract.

3.0 INTERPRETATION

3.1 Language 3.1.1 All Contract Documents, all correspondence and communications to be given, and all other

documentation to be prepared and supplied under the Contract shall be written in English, and the

Contract shall be construed and interpreted in accordance with that language .

3.1.2 If any of the Contract Documents, correspondence or communications are prepared in any

language other than the governing language under GCC sub-clause 3.1.1 above, the English

translation of such documents, correspondence or communications shall prevail in matters of

interpretation.

3.2 Entire Agreement The Contract constitutes the entire agreement between the Owner and the Contractor with respect

to the subject matter of Contract and supersedes all communications, negotiations and agreements

(whether written or oral) of parties with respect thereto made prior to the date of Contract.

3.3 Amendment No amendment or other variation of the Contract shall be effective unless it is in writing, is dated,

expressly refers to the Contract, and is signed by a duly authorized representative of each party

hereto.

Page 21: FOR (3x5.65 MW) ANDHRA HYDRO-ELECTRIC PROJECT Document Excitation System.pdf · 1 himachal pradesh state electricity board limited bid documents for “static excitation system and

21

3.4 Independent Contractor The Contractor shall be an independent Contractor performing the Contract. The Contract does

not create any agency, partnership, joint venture or other joint relationship between the parties

hereto.

Subject to the provisions of the Contract, the Contractor shall be solely responsible for the

manner in which the Contract is performed. All employees & representatives engaged by the

Contractor in connection with the performance of the Contract shall be under the complete

control of the Contractor and shall not be deemed to be employees of the Owner, and nothing

contained in the Contract shall be construed to create any Contractual relationship between any

such employees & representatives and the Owner.

3.5 Severability If any provision or condition of the Contract is prohibited or rendered invalid or unenforceable,

such prohibition, invalidity or unenforceability shall not affect the validity or enforceability of

any other provisions and conditions of the Contract.

4.0 NOTICES 4.1 Unless otherwise stated in the Contract, all notices to be given under the Contract shall be in

writing, and shall be sent by personal delivery, airmail post, special courier, cable, telegraph,

telex, facsimile or Electronic Data Interchange (EDI) to the address of the relevant party, set out

in the General Conditions of Contract.

4.2 Notices shall be deemed to include any approvals, consents, instructions, orders and certificates to

be given under the Contract.

5.0 GOVERNING LAW The Contract shall be governed by and interpreted in accordance with laws of India.

6.0 ARBITRATION 6.1 Any dispute(s) or differences(s) arising out of or in connection with the Contract shall, to the

extent possible in the first instance be resolved amicably between the Contractor and the Owner's

Engineer.

6.2 The arbitration proceedings shall be conducted in accordance with "Indian Arbitration and

Conciliation Act 1996 or any statutory modification thereof. Language of the arbitration

proceedings shall be in English.

6.3 The venue of Arbitration shall be Shimla, India. The courts of Shimla shall have exclusive

jurisdiction.

6.4 Notwithstanding any reference to the arbitration herein;

(a) the parties shall continue to perform their respective obligations under the Contract unless

they otherwise agree.

(b) the Owner shall pay the Contractor any monies due to the Contractor.

7.0 SCOPE OF WORKS 7.1 Unless otherwise expressly limited in the Technical Specifications, the Contractor's obligations

cover the provision of all installation, commissioning and engineering services, supply of labour,

materials, equipment and accessories; Contractor's equipment, construction utilities and supplies,

temporary materials.

7.2 The Contractor shall, unless specifically excluded in the Contract, perform all such work and/ or

supply all such items and materials not specifically mentioned in the Contract but that can be

reasonably inferred from the Contract as being required for attaining Completion of the Works as

if such work and /or items and materials were expressly mentioned in the Contract.

Page 22: FOR (3x5.65 MW) ANDHRA HYDRO-ELECTRIC PROJECT Document Excitation System.pdf · 1 himachal pradesh state electricity board limited bid documents for “static excitation system and

22

8.0 TIME FOR COMMENCEMENT AND COMPLETION 8.1 The Contractor shall commence work from the fifteenth day after the notification of award of

work.

8.2 The Contractor shall attain completion of the total works under the Contract within such extended

time to which the Contractor shall be entitled under GCC Clause 30.0 (Extension of Time for

Completion) hereof.

9.0 CONTRACTOR'S RESPONSIBILITES 9.1 The Contractor shall execute the entire work with due care and diligence in accordance with the

Contract.

9.2 The Contractor confirms that it has entered into this Contract on the basis of a proper examination

of the data relating to the works provided by Owner, and on the basis of information that the

Contractor could have obtained from a visual inspection of the site and of other data readily

available to it relating to the works. The Contractor acknowledges that any failure to acquaint

itself with all such data and information shall not relieve its responsibility for properly estimating

the difficulty or cost of successfully performing the works.

9.3 The Contractor shall acquire in its name all permits, approvals and/or licenses from all local, state

or national government authorities or public service undertakings that are necessary for the

performance of the Contract.

9.4 The Contractor shall comply with all laws in force where the services are carried out. The laws

will include all national, provincial, municipal or other laws that affect the performance of the

Contract and bind upon the Contractor. The Contractor shall indemnify and hold harmless the

Owner from and against any and all liabilities, damages, claims, fines, penalties and expenses of

whatever nature arising or resulting from the violation of such laws by the Contractor or its

personnel but without prejudice to GCC sub-clause 8.1 hereof.

9.5 The Contractor shall supply and make available all raw materials, utilities, and works and shall

perform all work and services of whatsoever nature required by him to properly carry out the

works under the Contract.

10.0 OWNER'S RESPONSIBILITIES 10.1 The Owner shall ensure the accuracy of all the information and/or data to be supplied by the

Owner to the contract except when otherwise expressly stated in the contract.

11.0 CONTRACT PRICE

11.1 The Contract Price shall be as specified in Article 2 (Contract Price and Term of Payment) of the

Form of Contract Agreement.

12.0 TERMS OF PAYMENT 12.1 The Contract Price shall be paid as specified in Appendix-1 (Terms and Procedures of Payment)

to the Contract Agreement. The procedures to be followed in making application for and

processing payments shall be those outlined in the same Appendix-1.

12.2 No payment made by the Owner herein shall be deemed to constitute acceptance by the Owner of

the Works or any part(s) thereof.

12.3 All the payments under this Contract shall be made to the Contractor in Indian Rupees only.

13.0 SECURITIES

13.1 Contract Performance Security 13.1.1 The Contractor shall, within fifteen days (15) days of the notification of award, provide a security

for the due performance of the Contract for an amount equivalent to ten percent (10%) of

Contract price with a validity upto ninety (90) days beyond the Defect Liability Period.

Page 23: FOR (3x5.65 MW) ANDHRA HYDRO-ELECTRIC PROJECT Document Excitation System.pdf · 1 himachal pradesh state electricity board limited bid documents for “static excitation system and

23

13.1.2 The security shall be denominated in Indian Rupees and shall be in the form of bank guarantee

attached hereto in the section on Forms and Procedures, or in another form acceptable to the

Owner.

13.1.3 If the Defects Liability Period has been extended on any part of the works pursuant to GCC sub-

clause 24.8 hereof, the Contractor shall issue an additional security in an amount proportionate to

the Contract Price of that part. The security shall be returned to the Contractor immediately after

its expiration.

13.1.4 The Performance Security will be returned to the Contractor without any interest 90 days after

successful completion of the Defects Liability Period on submission of no claim certificate unless

otherwise specified.

13.1.5 It is expressly understood and agreed that the above Contract Performance Security is intended to

secure the performance of entire Contract. It is also expressly understood and agreed that the

Contract Performance security is not to be construed as limiting the damages as detailed under the

Technical Specification and any other damages stipulated in other clauses in the Contract

Documents.

13.2 Claims under Security Whether or not the Performance Security is stated by its terms to be payable on the demand of the

Owner, the Owner shall not make a claim under the Performance Security unless one of the

following conditions is satisfied:

a) the Contractor is in breach of the Contract and fails to remedy the breach with in 30 days

after receiving written notice from the Owner requiring him to do so. The notice shall

state the intention to claim under Performance Security, the amount claimed and the

breach relied upon, or

b) the Owner has obtained an award in arbitration and the amount awarded has not been

paid within 45 days after the award, or

c) the Contractor has gone into liquidation or is bankrupt, or

d) any other reason specifying the default of the Contractor by the Owner.

In every case the Owner shall, when making the claim, send a copy to the Contractor.

14.0 TAXES AND DUTIES 14.1 The Sales tax on works Contract shall be borne by the Contractor. The Owner shall make the

deduction of the same from the Contractor’s invoices at the rates prevalent at that time and

deposit the same with the Excise & Taxation Department under intimation to the Contractor.

14.2 As regards the Indian income tax, surcharge on income tax and any other corporate tax the Owner

shall not bear any tax liability whatsoever. The Contractor shall be liable and responsible for

payment of such tax, if attracted under the provisions of the law present or future and Owner will

make deductions at source as applicable.

14.3 Service Tax & education cess on service tax shall be paid to the Contractor at the rates prevailing

at that time against documentary proof of Service Tax Number of the Contractor. Thereafter it

shall be the sole responsibility of the Contractor to deposit the same with the concerned

authorities. It shall be mandatory on the Contractor to submit evidence of his having service tax

registration and the service tax registration number shall be printed on the invoices raised by him

for payment.

15.0 DEDUCTION FROM CONTRACT PRICE

15.1 All the costs, damages or expenses which the Owner may have paid for which, under the

Contract, the Contractor is liable, will be claimed by Owner. All such claim shall be billed by the

Owner to the Contractor regularly as and when they fall due. Such bills shall be supported by

appropriate and certified vouchers to the extent possible or explanations, to enable to the

Contractor to properly identify such claims.

Page 24: FOR (3x5.65 MW) ANDHRA HYDRO-ELECTRIC PROJECT Document Excitation System.pdf · 1 himachal pradesh state electricity board limited bid documents for “static excitation system and

24

15.2 Such claims shall be paid by the Contractor within twenty eight (28) days of the receipt of the

corresponding bills and if not paid by the Contractor within the said period, the Owner may then

deduct the amount from any money due or becoming due by him to Contractor under the Contract

or may be recovered by action of law or otherwise, if the Contractor fails to satisfy the Owner of

non- pay ability of such claims by the Contractor.

16.0 CONFIDENTIAL INFORMATION 16.1 The Owner and the Contractor shall keep confidential and shall not, without the written consent

of the other party hereto, divulge to any third party any documents, data or other information

furnished directly or indirectly by the other party hereto in connection with the Contract, whether

such information has been furnished prior to, during or following termination of the Contract.

16.2 The Owner shall not use such documents, data and other information received from the

Contractor for any purpose other than the operation and maintenance of the works. Similarly, the

Contractor shall not use such documents, data and other information received from the Owner for

any purpose other than the design, procurement of plant and equipment construction of or such

other work and services as are required for the performance of the Contract.

16.3 The obligation of a party under GCC sub-clause 16.1 and 16.2 above, however, shall not apply to

that information which

a) now or hereafter enters the public domain through no fault of that party.

b) can be proven to have been possessed by that party at the time of disclosure and which

was not previously obtained directly or indirectly, from the other party hereto.

c) otherwise lawfully becomes available to that party from a third party that has no

obligation of confidentiality.

16.4 The above provisions of this GCC Clause 16.0 shall not in any way modify any undertaking of

confidentiality given by either of the parties hereto prior to the date of the Contract in respect of

the works or any part thereof.

16.5 The provisions of this GCC Clause 16.0 shall survive termination, for whatever reason, of the

Contract.

17.0 REPRESENTATIVES

17.1 Engineer-in-charge The Engineer-in-charge shall be named before or at the time of signing the Contract. The Owner

may from time to time appoint some other person as the Engineer-in-charge in place of the person

previously so appointed, and shall give a notice of the name of such other persons to the

Contractor without delay. The Owner shall take all reasonable care to see that no such

appointment is made at such a time or in such a manner as to impede the progress of work on the

works. The Engineer-in-charge shall represent and act for the Owner at all times during the

currency of the Contract. All notices, instructions, orders, certificates, approvals and all other

communications under the Contract shall be given by the Engineer-in-charge except as herein

otherwise provided.

All notices, instructions, information and other communications given by the Contractor to the

Owner under the Contract shall be given to the Engineer-in-charge except as herein otherwise

provided.

17.2 Contractor's Representative 17.2.1 The Contractor's Representative at site shall be named before or at the time of signing the

Contract.

17.2.2 The Contractor's Representative shall represent and act for the Contractor at all times during the

currency of the Contract and shall give to the Engineer-in-charge all the Contractor's notices,

instructions, information and all other communications under the Contract.

Page 25: FOR (3x5.65 MW) ANDHRA HYDRO-ELECTRIC PROJECT Document Excitation System.pdf · 1 himachal pradesh state electricity board limited bid documents for “static excitation system and

25

All notices, instructions, information and all other communications given by the Owner or the

Engineer-in-charge to the Contractor under the Contract shall be given to the Contractor's

representative or, in its absence, its deputy, except as herein otherwise provided.

The Contractor shall not revoke the appointment of the Contractor's representative without the

Owners prior written consent, which shall not be unreasonably withheld.

17.2.3 The Contractor's representative may, subject to the approval of the Owner (which shall not be

unreasonably withheld), at any time delegate to any person any of the powers, functions and

authorities vested in him or her. Any such delegation may be revoked at any time. Any such

delegation or revocation shall be subject to a prior notice signed by the Contractor's

representative and shall specify the powers, functions and authorities thereby delegated or

revoked. No such delegation or revocation shall take effect unless and until a copy thereof has

been delivered to the Owner and the Engineer-in-charge.

Any act or exercise by any person of powers, functions, and authorities so delegated to him or her

in accordance with this GCC sub-clause 17.2.3 shall be deemed to be an act or exercise by the

Contractor's Representative.

17.2.4 Notwithstanding anything stated in GCC sub-clause 17.1 and 17.2 above, for the purpose of

execution of Contract the Owner and the Contractor shall finalize and agree to a Contract

coordination procedure and all the communication under the Contract shall be in accordance with

such Contract co-ordination procedure.

17.2.5 The Owner may by notice to the Contractor object to any representative or person employed by

the Contractor in the execution of the Contract who, in the reasonable opinion of the Owner, may

behave inappropriately, may be incompetent or negligent, or may commit a serious breach of the

site regulations provided under GCC sub-clause 19.3. The Owner shall provide evidence of the

same, whereupon the Contractor shall remove such person from the works.

17.2.6 If any representative or person employed by the Contractor is removed in accordance with GCC

sub-clause 17.2.5, the Contractor shall, where required, promptly appoint a replacement.

18.0 WORK PROGRAMME

18.1 Contractor's Organization

The Contractor shall supply to Engineer-in-charge a chart showing the proposed organization to

be established by the Contractor for carrying out the works. The chart shall include the identities

of the key personnel together with the curricula vitae of such key personnel to be employed

within twenty-one (21) days of the effective date. The Contractor shall promptly inform the

Owner and the Engineer-in-charge in writing of any revision or alteration of such an organization

chart.

18.2 Programme of Performance Within seven (7) days after the date of notification of Award, the Contractor shall prepare and

submit to the Engineer-in-charge a detailed program of performance of the Contract, showing the

sequence in which it proposes to execute & complete the works as well as the date by which the

Contractor reasonably requires that the Owner shall have fulfilled its obligations under the

Contract so as to enable the Contractor to execute the Contract in accordance with the programme

and to achieve completion and acceptance of the works in accordance with the Contract. The

programme so submitted by the Contractor shall accord with the Time Schedule included in

Appendix 4 (Time Schedule) to the Contract. The Contractor shall update and revise the

programme as and when appropriate or when required by Engineer-in-charge, but without

modification in the Times for Completion and any extension granted in accordance with GCC

Clause 30.0, and shall submit all such revisions to the Engineer-in-charge.

18.3 Progress Report

Page 26: FOR (3x5.65 MW) ANDHRA HYDRO-ELECTRIC PROJECT Document Excitation System.pdf · 1 himachal pradesh state electricity board limited bid documents for “static excitation system and

26

The Contractor shall monitor progress of all the activities specified in the programme referred to

in GCC sub-clause 18.2 (Programme of Performance) above and supply a progress report to the

Engineer-in-charge every week. The progress report shall be in a form acceptable to the

Engineer-in-charge and besides indicating (a) percentage completion achieved compared with the

planned percentage completion for each activity, and (b) where any activity is behind the

programme, giving comments and likely consequences and stating the corrective action being

taken.

18.4 Progress performance

If at any time the Contractor's actual progress falls behind the programme referred to in GCC

sub-clause 18.2 (Programme of Performance), or it becomes apparent that it will so fall behind,

the Contractor shall at the request of the Owner or the Engineer-in-charge prepare and submit to

the Engineer-in-charge a revised programme, taking into account the prevailing circumstances,

and shall notify the Engineer-in-charge of the steps being taken to expedite progress so as to

attain completion of the works within the Time for Completion under GCC sub-clause 8.2 (Time

for Commencement and Completion), any extension thereof entitled under GCC sub-clause 30.0

(Extension of Time for Completion), or any extended period as may otherwise be agreed upon

between the Owner and the Contractor.

18.5 Work Procedures The Contract shall be executed in accordance with the Contract documents and the procedures

given in the section on Sample Forms and Procedures of the Contract Documents.

19.0 MAINTENANCE

19.1 Setting Out/Supervision/Labour If, at any time during the progress of the works, any error shall appear in the position, level or

alignment of the works, the Contractor shall forthwith notify the Engineer-in-charge of such error

and at its own expense, immediately rectify such error to the reasonable satisfaction of the

Engineer-in-charge.

19.1.2 Contractor's Supervision: The Contractor shall give or provide all necessary superintendence

during the progress of the works, and the Contractor’s Representative or its deputy shall be

constantly on the Site to provide fulltime superintendence of the Maintenance work. The

Contractor shall provide and employ technical personnel who are skilled and experienced in their

respective professions and supervisory staff who are competent to adequately supervise the work

at hand.

19.1.3 Labour: a) The Contractor shall provide and employ on the Site such skilled, semi-skilled and

unskilled labour as is necessary for the proper and timely execution of the Contract. The

Contractor is encouraged to use local labor that has the necessary skills.

b) Unless otherwise provided in the Contract, the Contractor shall be responsible for the

recruitment, transportation accommodation and catering of all labor, local, or expatriate,

required for the execution of the Contract and for all payments in connection therewith.

c) The Contractor shall be responsible for obtaining all necessary permit(s) and/or visa(s)

from the appropriate authorities for the entry of all labour and personnel to be employed

on the Site.

d) The Contractor shall at its own expense provide the means of repatriation to all of its and

its sub-Contractor's personnel employed on the Contract at the Site to their various home

states. It shall also provide suitable temporary maintenance of all such persons from the

Page 27: FOR (3x5.65 MW) ANDHRA HYDRO-ELECTRIC PROJECT Document Excitation System.pdf · 1 himachal pradesh state electricity board limited bid documents for “static excitation system and

27

cessation of their employment on the Contract to the date programmed for their

departure. In the event that the Contractor defaults in providing such means of

transportation and temporary maintenance, the Owner may provide the same to such

personnel and recover the cost of doing so from the Contractor.

e) The Contractor shall at all times during the progress of the Contract use its best

endeavors to prevent any unlawful, riotous or disorderly conduct or behavior by or

amongst its employees and the labour of its sub-Contractors.

f) The Contractor shall, in all dealings with its labour currently employed on or connected

with the Contract, pay due regard to all recognized festivals, official holidays, religious or

other customs and all local laws and regulations pertaining to the employment of labour.

19.2 Contractor's Equipment 19.2.1 All Contractor's equipment brought by the Contractor onto the Site shall be deemed to be

intended to be used exclusively for the execution of the Contract. The Contractor shall not

remove the same from the Site without the Engineer-in-charge's consent that such Contractor's

equipment is no longer required for the execution of the Contract.

19.2.2. Unless otherwise specified in the Contract, upon completion of the works, the Contractor shall

remove from the Site all equipment brought by the Contractor onto the Site and any surplus

materials remaining thereon.

19.3 Site Regulations and Safety The Owner and the Contractor shall establish Site regulations setting out the rules to be observed

in the execution of the Contract at the Site and shall comply therewith. The Contractor shall

prepare and submit to the Owner, with a copy to the Engineer-in-charge proposed Site regulations

for the Owner's approval, which approval shall not be unreasonably withheld.

Such Site regulations shall include, but shall not be limited to rules in respect of security, safety

of the works, gate control, sanitation, medical care, and fire prevention.

19.4 Emergency Work If, by reason of an emergency arising in connection with and during the execution of the Contract

any protective `or remedial work is necessary as a matter of urgency to prevent damage to the

works, the Contractor shall immediately carry out such work.

If, the Contractor is unable or unwilling to do such work immediately, the Owner may do or

cause such work to be done as the Owner may determine is necessary in order to prevent damage

to the works. In such event the Owner shall, as soon as practicable after the occurrence of any

such emergency, notify the Contractor in writing of such emergency, the work done and the

reasons thereof. If the work done or caused to be done by the Owner is work that the Contractor

was liable to do at its own expense under Contract, the reasonable costs incurred by the Owner in

connection therewith shall be paid by the Contractor to the Owner. Otherwise, the cost of such

remedial work shall be borne by the Owner.

19.5 Site Clearance 19.5.1 Site clearance in course of performance:

In the course of carrying out the Contract, the Contractor shall keep the Site reasonably free from

all unnecessary obstruction, store or remove any surplus materials, clear away any wreckage,

rubbish or temporary works from the Site and remove any Contractor's equipment no longer

required for execution of the Contract.

19.5.2 Clearance of Site after completion:

After completion of all parts of the works, the Contractor shall clear away and remove all

wreckage, rubbish and debris of any kind from the Site and shall leave the Site and works clean

and safe.

Page 28: FOR (3x5.65 MW) ANDHRA HYDRO-ELECTRIC PROJECT Document Excitation System.pdf · 1 himachal pradesh state electricity board limited bid documents for “static excitation system and

28

19.6 Work at Night and on Holidays 19.6.1 Unless otherwise provided in the Contract, no work shall be carried out during the night and on

public holidays without prior written consent of the Owner, except where work is necessary or

required to ensure safety of the works or for the protection of life, or to prevent loss or damage to

property, when the Contractor shall immediately advise the Engineer-in-charge provided that

provisions of this GCC Sub-clause 19.6.1 shall not apply to any work which is customarily

carried out by rotary or double-shifts.

19.6.2 Notwithstanding GCC Sub-clause 19.6.1 or 19.1.3 if and when the Contractor considers it

necessary to carry out work at night or on public holidays so as to meet the time for completion

and requests the Owners consent thereto, the Owner shall not unreasonably withhold such

consent.

20.0 TEST AND INSPECTION 20.1 The Contractor shall at its own expense carry out at Site all such tests and/or inspections of the

Plant and equipment and any part of the works as are specified in the Contract.

20.2 The Owner and the Engineer-in-charge or their designated representatives shall be entitled to

attend the aforesaid test and/or inspection.

20.3 The Contractor shall provide the Engineer-in-charge with a certified report of the results of any

such test and/or inspection.

20.4 The Engineer-in-charge may require the Contractor to carry out any test and/or inspection not

required by the Contract, provided that the Contractor's reasonable costs and expenses incurred in

the carrying out of such test and/or inspection shall be added to the Contract price. Further, if

such test and/or inspection impede the progress of work on the works and/or the Contractor's

performance of its other obligations under the Contract, due allowance will be made in respect of

the Time for completion and the other obligations so affected.

20.5 If any Plant and equipment or any part of the works fails to pass any test and/or inspection, the

Contractor shall either rectify or replace such plant and equipment or part of the works and shall

repeat the test and/or inspection.

20.6 The Contractor agrees that neither the execution of a test and/or inspection of Plant and

equipment or any part of the works, nor the attendance by the Owner or the Engineer-in-charge

shall release the Contractor from any other responsibilities under the Contract.

21.0 COMPLETION OF THE WORKS 21.1 As soon as the works or any part thereof has, in the opinion of the Contractor, been completed

operationally and structurally and put in a tight and clean condition as specified in the Technical

Specifications, excluding minor items not materially affecting the operation or safety of the

works, the Contractor shall so notify the Owner in writing.

21.2 As soon as all works in respect of Pre-commissioning are completed and, in the opinion of the

Contractor, the works or any part thereof is ready for commissioning, the Contractor shall

commence commissioning (Trial operation) as per procedures stipulated in technical

specifications and as soon as commissioning is satisfactorily completed, the Contractor shall so

notify the Engineer-in-charge in writing.

21.3 The Engineer-in-charge shall within fourteen (14) days after receipt of the Contractor's notice

under GCC sub-clause 21.2 either issue a completion certificate in the form specified in the

Forms and Procedures section in the Bid Documents, stating that the works or that part thereof

have reached completion as at the date of the Contractor's notice under GCC sub-clause 21.2 or

notify the Contractor in writing of any defects and/or deficiencies.

If the Engineer-in-charge notifies the Contractor of any defects and/or deficiencies, the

Contractor shall then correct such defects and/or deficiencies, and shall repeat the procedure

described in GCC sub-clause 21.2.

Page 29: FOR (3x5.65 MW) ANDHRA HYDRO-ELECTRIC PROJECT Document Excitation System.pdf · 1 himachal pradesh state electricity board limited bid documents for “static excitation system and

29

If the Engineer-in-charge is satisfied that the works or that part thereof have reached completion,

the Engineer-in-charge shall, within seven (7) days after receipt of the Contractor's repeated

notice, issue a completion certificate stating that the works or that part thereof have reached

completion as at the date of the Contractor's repeated notice.

If the Engineer-in-charge is not so satisfied, than it shall notify the Contractor in writing of any

defects and/or deficiencies within seven (7) days after receipt of the Contractor's repeated notice,

and the above procedure shall be repeated.

21.4 As soon as possible after completion, the Contractor shall complete all outstanding minor items

so that the works are fully in accordance with the requirements of the Contract, failing which the

Owner will undertake such completion and deduct the costs thereof from any monies owing to the

Contractor.

21.5 Upon completion and handing over the works or the relevant part thereof, by the Contractor to the

Owner, shall be responsible for the care and custody of the works or the relevant part thereof.

22.0 COMMISSIONING AND OPERATIONAL ACCEPTANCE

22.1 Commissioning: - Commissioning (Trial Operation) of the works or any part thereof shall be completed by the

Contractor as per procedures detailed in technical Specifications.

22.2 Operational Acceptance: -

22.2.1 The operational Acceptance shall occur in respect of the works or any part thereof after

successful completion of the Test Service Period and any minor items relevant to the works or

that part thereof have been completed.

22.2.2 Pursuant to GCC sub-clause 22.2.1, the Contractor may give a notice to the Engineer-in-charge

requesting the issue of an Operational Acceptance Certificate in the form provided in the Bid

Documents or in another form acceptable to the Owner in respect of the works or the part thereof

specified in such notice as at the date of such notice.

22.2.3 The Engineer-in-charge shall, after consultation with the Owner, and within forty five (45 days)

after receipt of the Contractor's notice, issue an Operational Acceptance Certificate.

22.2.4 If within forty five (45) days after receipt of the Contractor's notice, the Engineer-in-charge fails

to issue the Operational Acceptance Certificate or fails to inform the Contractor in writing of the

justifiable reasons why the Engineer-in-charge has not issued the Operational Acceptance

Certificate, the works or the relevant part thereof shall be deemed to have been accepted as at the

date of the Contractor's said notice.

23.0 COMPLETION TIME GUARANTEE

23.1 The Contractor guarantees that it shall attain commissioning of the works (or a part for which a

separate time for completion is specified in the Contract) within the Time for Completion

specified in the Contract pursuant to GCC sub-clause 10.2 or within such extended time to which

the Contractor shall be entitled under GCC Clause 30.0 (Extension of Time for completion)

hereof.

23.2 If Contractor fails to attain completion of the works or any part thereof within the Time for

Completion or any extension thereof under GCC Clause 30.0 (Extension of Time for

Completion), the Contractor shall pay to the Owner liquidated damages in the amount computed

@ half percent (0.5) of the Contract price per week. The aggregate amount of such liquidate

damages shall in no event exceed the five (5%) of the Contract price. Once the "Maximum" is

reached, the Owner may consider termination of the Contract, pursuant to GCC Sub-clause 32.2.

Such payment shall completely satisfy the Contractor's obligation to attain completion of the

works or the relevant part thereof within the Time for Completion or any extension thereof under

Page 30: FOR (3x5.65 MW) ANDHRA HYDRO-ELECTRIC PROJECT Document Excitation System.pdf · 1 himachal pradesh state electricity board limited bid documents for “static excitation system and

30

GCC Clause 30.0 (Extension of Time for Completion). The Contractor shall have no further

liability whatsoever to the Owner in respect thereof.

However, the payment of liquidated damages shall not in any way relieve the Contractor from

any of its obligations to complete the works or from any other obligations and liabilities of the

Contractor under the Contract.

Save for liquidated damages payable under this GCC sub-clause 23.2, the failure by the

Contractor to attain any milestone or other act, matter or thing by any date specified in Appendix

4(Time Schedule to the Contract Agreement and/or other programme of work prepared pursuant

to GCC Clause 18.2 (Programme of Performance) shall not render the Contractor liable for any

loss or damage thereby suffered by the Owner.

23.3 No bonus shall be given for earlier completion of works or part thereof.

24.0 DEFECT LIABILITY

24.1 The Contractor warrants that the works carried out under this Contract shall be free from defects.

24.2 The Defect Liability Period shall be twenty four (24) months from the date of Operational

Acceptance of the works unless specified otherwise in the Contract.

If during the Defect Liability Period any defect should be found in the work executed by the

Contractor, the Contractor shall promptly, in consultation and agreement with the Owner

regarding appropriate remedying of the defects, and at its cost, repair, replace or other wise make

good (as the Contractor shall, at its discretion, determine) such defect as well as any damage to

the works caused by such defect. The Contractor shall not be responsible for the repair,

replacement or making good of any defect or of any damage to the works arising out of or

resulting from any of the following causes:

a) improper operation or maintenance of the works by the Owner.

b) operation of the works outside specifications provided in the Contract.

c) normal wear and tear.

24.3 The Contractor's obligations under this GCC Clause 24.0 shall not apply to: -

a) any materials that are supplied by the Owner are normally consumed in operation, or

have a normal life shorter than the Defect Liability Period stated herein.

b) any designs, specifications or other data designed, supplied or specified by or on behalf

of the Owner or any matters for which the Contractor has disclaimed responsibility

herein.

24.4 The Owner shall give the Contractor a notice stating the nature of any such defect together with

all available evidence thereof, promptly following the discovery thereof. The Owner shall afford

all reasonable opportunity for the Contractor to inspect any such defect.

24.5 If the repair, replacement or making good is of such a character that it may affect the efficiency of

the works or any part thereof, the Owner may give to the Contractor a notice requiring that tests

of the defective part of the works shall be made by the Contractor immediately upon completion

of such remedial work, whereupon the Contractor shall carry out such tests.

If such part fails the tests, the Contractor shall carry out further repair, replacement or making

good (as the case may be) until that part of the works passes such tests. The tests in character

shall in any case be not less than what has already been agreed upon by the Owner and the

Contractor for the original equipment/part of the works.

24.6 If the Contractor fails to commence the work necessary to remedy such defect or any damage to

the works caused by such defect within a reasonable time (which shall in no event be considered

to be less than fifteen (15 days) the Owner may following notice to the Contractor, proceed to do

such work and the reasonable costs incurred by the Owner in connection therewith shall be paid

to the Owner by the Contractor or may be deducted by the Owner from any monies due the

Contractor or claimed under the Performance Security.

24.7 If works or any part thereof cannot be used by reason of such defect and/or making good of such

defect, the Defect Liability Period of the Works or such part, as the case may be, shall be

Page 31: FOR (3x5.65 MW) ANDHRA HYDRO-ELECTRIC PROJECT Document Excitation System.pdf · 1 himachal pradesh state electricity board limited bid documents for “static excitation system and

31

extended by a period equal to the period during which the works or such part cannot be used by

the Owner be cause of any of the aforesaid reasons.

24.8 Upon correction of the defects in the works or any part thereof by repair/replacement, such

repair/replacement shall have the Defect Liability Period extended by a period of Twenty four

(24) months from the time of such replacement/repair of the works or any part thereof.

25.0 LOSS OF OR DAMAGE TO PROPERTY; ACCIDENT OR INJURY TO WORKERS;

INDEMNIFICATION 25.1 The Contractor shall indemnify and hold harmless the Owner and its employees and officers from

and against any and all suits, actions or administrative proceedings, claims, demands, losses,

damages, costs, and expenses, of whatsoever nature, including attorney's fees and expenses , in

respect of the death or injury of any person or loss of or damage to any property (other than the

works whether accepted or not), arising in connection with the supply and maintenance of the

works and by reason of the negligence of the Contractor or their employees, officers or agents,

except any injury, death or property damage caused by the negligence of the Owner, its

Contractors, employees, officers or agents.

25.2 If any proceedings are brought or any claim is made against the Owner that might subject the

Contractor to liability under GCC sub-clause 25.1 the Owner shall promptly give the Contractor a

notice thereof and the Contractor may at its own expense and in the Owner's name conduct such

proceedings or claim and any negotiations for the settlement of any such proceedings or claim.

If the Contractor fails to notify the Owner within twenty-eight (28) days after receipt of such

notice that it intends to conduct any such proceedings or claim, then the Owner shall be free to

conduct the same on its own behalf. Unless the Contractor has so failed to notify the Owner

within the twenty eight (28) days period the Owner shall make no admission that may be

prejudicial to the defense of any such proceedings or claim.

26.0 INSURANCE

26.1 To the extent specified in Appendix 3 (Insurance Requirements) to the Contract Agreement, the

Contractor shall at its expense take out and maintain in effect, during the performance of the

Contract, the insurances set forth below in the sums and with the deductibles and other conditions

specified in the said Appendix.

a) Third Party Liability Insurance

Covering bodily injury or death suffered by third parties occurring in connection with the

works under the Contract.

b) Worker's Compensation

In accordance with the statutory requirements applicable in any country where the

Contract or any part thereof is executed.

27.0 CHANGE IN LAWS AND REGULATIONS

27.1 If, after the date twenty-eight (28) days prior to the date of Bid submission, any law, regulation,

ordinance, order or by-law having the force of law is enacted, promulgated, abrogated or changed

(which shall be deemed to include any change in interpretation or application by the competent

authorities) that subsequently affects the costs and expenses of the Contractor and/or the Time for

Completion, the Contract Price shall be correspondingly increased or decreased, and/or the Time

for Completion shall be reasonably adjusted to the extent that the Contractor has thereby been

affected in the performance of any of its obligations under the Contract.

28.0 FORCE MAJEURE

28.1 " Force Majeure " shall mean any event beyond the reasonable control of the Owner or of the

Contractor, as the case may be and which is unavoidable notwithstanding the reasonable care of

the party affected and shall include, without limitation, the following: -

Page 32: FOR (3x5.65 MW) ANDHRA HYDRO-ELECTRIC PROJECT Document Excitation System.pdf · 1 himachal pradesh state electricity board limited bid documents for “static excitation system and

32

a) war and other hostilities (whether war be declared or not), invasion, act of foreign

enemies or embargo;

b) rebellion, revolution, insurrection, military or usurped power and civil war;

c) ionising, radiation or contamination by radio-activity from any nuclear fuel or from any

nuclear waste from the combustion of nuclear fuel, radio-active toxic explosives, or

other hazardous properties of any explosive nuclear assembly or nuclear components

thereof;

d) riot, commotion or disorder, except where solely restricted to employees of the

Contractor;

e) Acts of God such as earthquake (above magnitude of 7 on Richter's scale), unprecedented

floods.

28.2 If either party is prevented, hindered or delayed from or in performing any of its obligations

under the Contract by an event of Force Majeure, then it shall notify the other in writing of the

occurrence of such event and the circumstances thereof within fourteen (14) days after the

occurrence of such event.

28.3 The party who has given such notice shall be excused from the performance or punctual

performance of its obligations under the Contract for so long as the relevant event of Force

Majeure continues and to the extent that such party's performance is prevented, hindered or

delayed. The Time for Completion shall be extended in accordance with GCC Clause 30.0

(Extension of Time for Completion).

28.4 The party or parties affected by the event of Force Majeure shall use reasonable efforts to

mitigate the effect thereof upon its or their performance of the Contract and to fulfill its or their

obligations under the Contract.

28.5 No delay or non-performance by either party thereto caused by the occurrence of any event of

Force Majeure shall

a) constitute a default or breach of the Contract

b) (subject to GCC sub-clause 29.3) give rise to any claim for damages or additional cost or

expense occasioned thereby

if and to the extent that such delay or nonperformance is caused by the occurrence of an event of

Force Majeure .

28.6 If the performance of the Contract is substantially prevented, hindered or delayed for a single

period of more than sixty (60) days or an aggregate period of more than one hundred and twenty

(120) days on account of one or more events of Force Majeure during the currency of the

Contract, the parties will attempt to develop a mutually satisfactory solution failing which the

dispute shall be resolved in accordance with GCC Clause 6.

28.7 Notwithstanding GCC sub-clause 28.5, Force Majeure shall not apply to any obligation of the

Owner to make payments to the Contractor herein.

29.0 WAR RISKS

29.1 " War Risks" shall mean any event specified in paragraphs (a) and (b) of GCC sub-clause 28.1

and any explosion or impact of any mine, bomb-shell, grenade or other projectile, missile,

munitions or explosive of war, occurring or existing in or near the country (or countries) where

the Site is located.

29.2 Notwithstanding anything contained in the Contract, the Contractor shall have no liability

whatsoever for or with respect to: -

a) destruction of or damage to Works, Plant & Equipment, or any part thereof.

b) destruction of or damage to property of the Owner or any third party.

c) injury or loss life

29.3 If during the performance of the Contract any War Risks shall occur that financially or otherwise

materially affect the execution of the Contract by the Contractor, the Contractor shall use its

reasonable efforts to execute the Contract with due and proper consideration give to the safety of

Page 33: FOR (3x5.65 MW) ANDHRA HYDRO-ELECTRIC PROJECT Document Excitation System.pdf · 1 himachal pradesh state electricity board limited bid documents for “static excitation system and

33

its and its sub-Contractor's personnel engaged in the work on the works, provided, however, that

if the execution of the work on the works becomes impossible or is substantially prevented for a

single period of more than sixty (60) days or an aggregate period of more than one hundred and

twenty (120) days on account of any War Risks, the parties will attempt to develop a mutually

satisfactory solution, failing which the dispute will be resolved in accordance with GCC Clause

No. 6.0.

30.0 EXTENSION OF TIME FOR COMPLETION

30.1 The time(s) for completion specified in the Contract shall be extended if the Contractor is delayed

or impeded in the performance of any of its obligations under the Contract by reason of any of the

following:

a) any occurrence of Force Majeure as provided in GCC Clause 28.0 (Force majeure).

b) any suspension order given by the Owner under GCC clause 31.0 (Suspension) hereof.

c) any changes in laws and regulations as provided in GCC Clause 27.0 (Change in Laws

and Regulations) or

d) any default or breach of the Contract by the Owner specifically including failure to

supply the items in Scope of Works and Supply by the Owner to the Contract Agreement,

or any activity, act or omission of any other Contractors employed by the Owner or

e) any other matter specifically mentioned in the Contract:

by such period as shall be fair and reasonable in all the circumstances and as shall fairly reflect

the delay or impediment sustained by the Contractor .

30.2 Except where otherwise specifically provided in the Contract, the Contractor shall submit to the

Engineer-in-charge a notice of a claim for an extension of the Time for completion, together with

particulars of the event or circumstance justifying such extension as soon as reasonably

practicable after the commencement of such event or circumstance. As soon as reasonably

practicable after receipt of such notice and supporting particulars of the claim, the Owner and the

Contractor shall agree upon the period of such extension.

30.3 The Contractor shall at all times use its reasonable efforts to minimize any delay in the

performance of its obligations under the Contract.

31.0 SUSPENSION

31.1 The Owner may request the Engineer-in-charge by notice to the Contractor, to order the

Contractor to suspend performance of any or all of its obligations under the Contract. Such notice

shall specify the obligations of which performance is to be suspended, the effective date of the

suspension and the reasons thereof. The Contractor shall thereupon suspend performance of such

obligations (except those obligations necessary for the care or preservation of the works) until

ordered in writing to resume such performance by the Engineer-in-charge.

31.2 During the period of suspension, the Contractor shall not remove from the Site any Plant and

equipment, any part of the works or any Contractor's equipment, without the prior written consent

of the Owner.

32.0 TERMINATION

32.1 The Owner without prejudice to any other rights or remedies it may possess, may terminate the

Contract forthwith in the following circumstances by giving a notice of termination and its

reasons therefor to the Contractor.

a) if the Contractor becomes bankrupt or insolvent, has a receiving order issued against it,

compounds with its creditors, or, if the Contractor is a corporation, a resolution is passed

or order is made for its winding up (other than a voluntary liquidation for the purposes of

amalgamation or reconstruction) a receiver is appointed over any part of its under taking

Page 34: FOR (3x5.65 MW) ANDHRA HYDRO-ELECTRIC PROJECT Document Excitation System.pdf · 1 himachal pradesh state electricity board limited bid documents for “static excitation system and

34

or assets, or if the Contractor takes or suffers any other analogous action in consequence

of debt.

b) if the Contractor assigns or transfers the Contract or any right or interest.

c) if the Contractor, in the judgment of the Owner has engaged in corrupt or fraudulent

practices in competing for or in executing the Contract.

For the purpose of this sub-clause:

"Corrupt practice" means the offering, giving receiving or soliciting of any thing of value

of influence the action of a public official in the procurement process or in Contract

execution.

"Fraudulent practice" means a misrepresentation of facts in order to influence a

procurement process or the execution of a Contract to the detriment of the Owner and

includes collusive practice among Bidders (prior to or after Bid submission) designed to

establish Bid prices at artificial non-competitive levels and to deprive the Owner of the

benefits of free and open competition .

32.2 If the Contractor

a) has abandoned or repudiated the Contract.

b) has without valid reason failed to commence work on the works promptly or has

suspended, the progress of Contract performance for more than twenty-eight (28) days

after receiving a written instruction from the Owner to proceed.

c) persistently fails to execute the Contract in accordance with the Contract or persistently

neglects to carry out its obligations under the Contract without just cause.

d) refuses or is unable to provide sufficient materials, services or labour to execute and

complete the works in the manner specified in the program furnished under GCC Clause

18.2 (Programme of Performance) at rates of progress that give reasonable assurance to

the Owner that the Contractor can attain completion of the works by the Time for

Completion as extended;

then the Owner may, without prejudice to any other rights it may possess under the Contract, give

a notice to the Contractor stating the nature of the default and requiring the Contractor to remedy

the same. If the Contractor fails to remedy or to take steps to remedy the same within fourteen

(14) days of its receipt of such notice, then the Owner may terminate the Contract forthwith by

giving a notice of termination to the Contractor.

32.3 Upon receipt of the notice of termination under the Contract shall either immediately or upon

such date as is specified in the notice of termination:

a) cease all further work, except for such work as the Owner may specify in the notice of

termination for the sole purpose of protecting that part of the works already executed, or

any work required to leave the Site in a clean and safe condition.

b) terminate all sub-Contracts, except those to be assigned to the Owner pursuant to

paragraph (d) below.

c) deliver to the Owner the parts of the works executed by the Contractor up to the date of

termination.

d) to the extent legally possible, assign to the Owner all right, title and benefit of the

Contractor to the Work and to the plant and equipment as at the date of termination, and,

as may be required by the Owner, in any sub-Contracts concluded between the Contractor

and its sub-Contractors.

e) deliver to the Owner all drawings, specifications and other documents prepared by the

Contractor or its sub-Contractors as at the date of termination in connection with the

works.

Page 35: FOR (3x5.65 MW) ANDHRA HYDRO-ELECTRIC PROJECT Document Excitation System.pdf · 1 himachal pradesh state electricity board limited bid documents for “static excitation system and

35

32.4 The Owner may enter upon the Site, expel the Contractor, and complete the works itself or by

employing any third party. The Owner may, to the exclusion of any right of the Contract over the

same, take over and use with the payment of a fair rental rate to the Contractor, with all the

maintenance costs to the account of the Owner and with an indemnification by the Owner for all

liability including damage or injury to persons arising out of the Owner's use of such equipment,

any Contractor's equipment owned by the Contractor and on the Site in connection with the works

for such reasonable period as the Owner considers expedient for the works.

Upon completion of the works or at such earlier date as the Owner thinks appropriate, the Owner

shall give notice to the Contractor that Contractor's equipment will be returned to the Contractor

at or near the Site and shall return such Contractor's equipment to the Contractor in accordance

with such notice . The Contractor shall thereafter without delay and at its cost remove or arrange

removal of the same from the Site.

32.5 The Contractor shall be entitled to be paid the Contract price attributable to the works executed as

at the date of termination, the value of any unused or partially used Plant and equipment on the

Site, and the costs, if any, incurred in protecting the works and in leaving the Site in a clean and

safe condition pursuant to paragraph. Any sums due to the Owner from the Contractor accruing

prior to the date of termination shall be deducted from the amount to be paid to the Contractor

under this Contract.

32.6 If the Owner completes the works, the cost of completing the works by the Owner shall be

determined.

If the sum that the Contractor is entitled to be paid pursuant to GCC sub-clause 32.5, plus the

reasonable costs incurred by the Owner, in completing the works, exceeds the Contract price, the

Contractor shall be liable for such excess.If such excess is greater than the sums due the

Contractor under GCC sub-clause 32.5, the Contractor shall pay the balance to the Owner, and if

such excess is less than the sums due the Contractor the Owner shall pay the balance to the

Contractor.

The Owner and the Contractor shall agree, in writing, on the computation described above and

the manner in which any sums shall be paid.

33.0 ASSIGNMENT

33.1 Neither the Owner nor the Contractor shall, without the express prior written consent of the other

(which consent shall not be unreasonably withheld), assign to any third party the Contract or any

part thereof, or any right, benefit, obligation, or interest therein or there under, except that the

Contractor shall be entitled to assign either absolutely or by way of charge any money due and

payable to it or that may become due and payable to it under the Contract.

34.0 TEST SERVICE PERIOD

As soon as the works or part thereof has passed the Commissioning Tests, the Engineer-in-charge

shall issue a Completion Certificate to the Contractor to that effect with copy to the Owner.

The Completion Certificate shall indicate any outstanding works and/or minor unattended defects

of the works which shall be rectified by the Contractor.

The Test Service Period shall commence immediately after the Completion Certificate has been

issued. Tests shall be carried out in accordance with the specifications and as requested by the

Owner under the sole responsibility of the Contractor.

The duration of the Test Service Period shall be 35 days.

After successful completion of the Test Service Period, the Engineer-in-charge shall issue a

Taking-Over Certificate to the Contractor with copy to the Owner.

The Owner and /or Engineer-in-charge reserve the right to delay the issuance of Taking-Over

Certificate until such time he is satisfied that defects enlisted in the Test Certificate and other

defects, if any, during the Test Service Period are rectified.

Page 36: FOR (3x5.65 MW) ANDHRA HYDRO-ELECTRIC PROJECT Document Excitation System.pdf · 1 himachal pradesh state electricity board limited bid documents for “static excitation system and

36

SECTION-IV

Forms & Procedure (FP)

Page 37: FOR (3x5.65 MW) ANDHRA HYDRO-ELECTRIC PROJECT Document Excitation System.pdf · 1 himachal pradesh state electricity board limited bid documents for “static excitation system and

37

INDEX

FORMS AND PROCEDURE

1.Bid Forms

2. Attachments Including Security Forms

3. Price Schedule

4. Form of 'Notification of Award Contract' for supply of Plant and Equipment and their installation.

5. From of Contract Agreement.

6.Performance Security Forms.

7.Form of Completion Certificate. 8.Form of Operational Acceptance Certificate

Page 38: FOR (3x5.65 MW) ANDHRA HYDRO-ELECTRIC PROJECT Document Excitation System.pdf · 1 himachal pradesh state electricity board limited bid documents for “static excitation system and

38

BID FORM

Date-------------------------------------------

Bid Spec. No. –

Name of Contract-----------------------------------------------

To

Chief Engineer (Gen.),

HPSEBL, Sunder Nagar-175019 (HP).

Sir,

1.0 With reference to the Bid Documents forwarded to us vide your letter no-------------------- dated --

------------, we the undersigned, having examined the Bid Documents, including Addenda Nos.,

(Insert numbers------------------), the receipt of which is hereby acknowledged, offer to execute the

work under the above named Contract in full conformity with the said Bid Documents for the

sum of:

-------------------------------------------------------------------------------------------------------------

(Amount in 'Words)

------------------------------------------------------- (----------------------------------------------)

(Amount in Figures)

or such other sums as may be determined in accordance with the terms and conditions of the

Contract.

2.0 Attachments to the Bid Form: In line with the requirement of the Bid Documents, we enclose herewith the following

Attachments to the Bid Form:

a) Attachment 1: Bid Security in the form of ----------------------------------(Please fill in the

alternative chosen) for a sum of -------------------------------------------(Name of currency

and amounts in words & figures) valid for a period of six (6) calendar months from the

date set for opening of Bids.

b) Attachment 2: A power of attorney duly authorised by a Notary Public indicating that the

person signing the Bid have the authority to sign the Bid and that the Bid is binding upon

us during the full period of its validity in accordance with the ITB Clause 13.0.

c) Attachment 3: The documentary evidence establishing in accordance with ITB Clause 3.0

that we are eligible to Bid.

d) Attachment 4: List of tools and tackles which we propose to bring to site in case the

contract is awarded to us.

e) Attachment 5: The mile stone schedule showing the timing and sequence of all key

activities necessary for successful completion of the contract is enclosed.

Page 39: FOR (3x5.65 MW) ANDHRA HYDRO-ELECTRIC PROJECT Document Excitation System.pdf · 1 himachal pradesh state electricity board limited bid documents for “static excitation system and

39

f) Attachment 6: The variation and deviations from the requirements of the conditions of

contract and commercial conditions in your format enclosed with the Bid Documents,

indicating, inter alia, the cost of withdrawal of the variation and deviations indicated

therein.

g) Attachment 6A: The variation and deviations from the requirements of provisions of

Technical specifications and Drawings in your format enclosed with the bid documents,

indicating, inter alia, the cost of withdrawal of the variation and deviations indicated

therein.

3.0 PRICE SCHEDULES: 3.1 In line with the requirements of the Bid Documents, we enclose herewith the following Price

Schedules, duly filled-in as per your proforma:

Schedule No.1 Plant and Equipment (including Mandatory

Spare Parts)

Schedule No.2 Transportation including Insurance.

Schedule No.3 Installation Services (including dismantling charges

of existing panel)

Schedule No.4 Grand Summary (Schedules Nos. 1 to 3)

Schedule No.5 Recommended Spare Parts.

Schedule No.6 Taxes and Duties. (Not included in Bid Price)

Any other Schedules, if required, shall be added here.

3.2 We are aware that the Price Schedules do not generally give a full description of the work to be

performed under each item and we shall be deemed to have visited the sites of work and read

other Bid Documents to ascertain the full scope of work included in each item while filling-in the

rates and prices. We agree that the entered rates and prices shall be deemed to include for the full

scope as aforesaid, including overheads and profit.

3.3 We declare that as specified in the Conditions of Contract, prices quoted by us in the Price

Schedules are Firm.

3.4 We understand that in the price schedule, where there are errors between the total of the amounts

given under the column for the Price Breakdown and the amount given under the Total Price, the

former shall prevail and the latter will be corrected accordingly. We further understand that

where there are discrepancies between amounts stated in figures and amounts stated in words, the

amount stated in words shall prevail. Similarly, any discrepancy in the total bid price and that of

the summation of Schedule prices (price indicated in a Schedule indicating the total of that

schedule,) the total bid price shall be corrected to reflect the actual summation of the Schedule

prices.

Page 40: FOR (3x5.65 MW) ANDHRA HYDRO-ELECTRIC PROJECT Document Excitation System.pdf · 1 himachal pradesh state electricity board limited bid documents for “static excitation system and

40

3.5 We declare that items left blank in the Schedules will be deemed to have been included in other

items, The TOTAL for each Schedule shall be deemed to be the total price for executing the

works and sections thereof in complete accordance with the Contract, whether or not each

individual item has been priced.

4.0 We confirm that we shall also get registered with the concerned Sales Tax Authorities, in the state

where the Projects are located.

5.0 We have read the provisions of following clause and confirm that the specified stipulations of

these clauses are acceptable to us:

a) GCC 5.0 Governing Law

b) GCC 6.0 Arbitration

c) GCC 12.0 Terms of payment

d) GCC 13.0 Performance Security

e) GCC 14.0 Taxes and Duties

f) GCC 23.0 Completion Time Guarantee

g) GCC 24.0 Defect Liability

6.0 We undertake, if our Bid is accepted, to commence the work on Facilities immediately upon your

Notification of Award to us, and to achieve completion within the time stated in the Bid

Documents.

7.0 We agree to abide by this Bid for a period of 180 days from the date fixed for submission of Bids

as stipulated in the Bid Documents, and it shall remain binding upon us and may be accepted by

you at any time before the expiration of that period.

8.0 Until a formal Contact is prepared and executed between us, this Bid, together with your written

acceptance thereof in the form of your Notifications of Award shall constitute a contract between

us.

9.0 We understand that you are not bound to accept the lowest or any Bid you may receive.

10.0 We, hereby, declare that only the persons or firms interested in this proposal as principals are

named here and that no other persons or firms other than those mentioned herein have any interest

in this proposal or in the Contract to be entered into, if the award is made on us, that this proposal

is made without any connection with any other person, firm or party likewise submitting a

proposal is in all respects for and in good faith, without collusion or fraud.

Dated this-----------------------day of -----------------------------------

Thanking you, we remain,

Yours faithfully,

(Signature)

(Printed Name)

(Designation)

(Common Seal)

Date :

Place :

Business Address :

Note: For the Attachments 2,3 & 5 Bidders may use their own proforma for furnishing the required

information with the Bid.

Page 41: FOR (3x5.65 MW) ANDHRA HYDRO-ELECTRIC PROJECT Document Excitation System.pdf · 1 himachal pradesh state electricity board limited bid documents for “static excitation system and

41

ATTACHMENT- 1

PROFORMA OF BANK GUARANTEE FOR BID SECURITY

(To be stamped in accordance with Stamp Act)

To

The Accounts Officer,

O/O the Chief Engineer (Generation),

HPSEB Ltd., Sunder Nagar,Distt. Mandi H.P. – 175 019.

WHERAS, (Name of Bidder) ---------------------------------------------(hereinafter called "the Bidder") has

submitted his Bid dated-------------------for (Name of Contract)-------------------------(hereinafter called

"the Bid").

KNOW ALL MEN BY these presents that we (Name of Bank)-----------------------------------------------

having our registered office at (address)------------------------------------------------(hereinafter called " the

Bank" are bound unto HPSEBL in the sum of Rs. ---------------------------------------for which payment

will and truly to be made to the HPSEBL the Bank binds himself, his successors and assigns by these

presents.

SEALED with the Common Seal of the said Bank this------------------------day of-----------------------2012.

THE CONDITIONS of this obligation are:

1. If the Bidder withdraws his Bid during the period of Bid validity specified in the Proforma of

Bid; or

2. If the Bidder having been notified of the acceptance of his Bid by the HPSEBL during the period

of Bid validity:

a) fails or refuses to execute the Contract Agreement, when required; or

b) fails or refuses to furnish the performance security, in accordance with the Bid

Documents.

We undertake to pay to the HPSEBL upto the above amount upon receipt of its first written demand

without the HPSEBL having to substantiate its demand, provided that in its demand the HPSEBL will

note that the amount claimed by it is due to it owing to the occurrence of one or both of the two

conditions, specifying the occurred condition or conditions.

This Guarantee will remain in force upto and including the date ---------- (ninety (90) days after the period

of Bid validity) and any demand in respect thereof should reach the Bank not later than the above date.

DATE--------------------- --------------------------- For and on behalf of the Bank.

(Signature)

in the capacity of

(Common Seal of Bank)

Page 42: FOR (3x5.65 MW) ANDHRA HYDRO-ELECTRIC PROJECT Document Excitation System.pdf · 1 himachal pradesh state electricity board limited bid documents for “static excitation system and

42

ATTACHMENT-4

(Name of the Project)

(List of Erection and Maintenance Tools & Tackles)

(Bidder's Name & Address):

To

Chief Engineer (Gen.),

HPSEBL, Sunder Nagar-175019 (HP)

Sir,

We are furnishing below the list of erection and commissioning instruments which we intend to bring to

site for executing the work detailed in the schedule of work & prices. These tools & tackles shall be taken

back after issue of operational acceptance certificate to us.

Sr. No. Description of tools & instruments Quantity Remarks

1.

2.

3.

4.

5.

6.

7.

8.

9.

10.

Notwithstanding what is stated above we further confirm that any additional erection and maintenance

tools and tackles, required for the completion of the works mentioned in the Bid documents shall be

arranged/brought to site by us at no extra cost to the Owner.

Date: ----------------------- (Signature)-------------------

Place:---------------------- (Printed Name)-------------

(Designation)----------------

(Common Seal)-------------

Page 43: FOR (3x5.65 MW) ANDHRA HYDRO-ELECTRIC PROJECT Document Excitation System.pdf · 1 himachal pradesh state electricity board limited bid documents for “static excitation system and

43

ATTACHMENT-6

(Name of the Project)

Cost of withdrawal of deviation from the requirement of the Commercial terms and conditions. (To be furnished by the Bidders)

(Bidder's Name & Address):

To:---------------------------------------------------

(Name of the Owner)

Dear Sir,

Following are the deviations from the requirement of the commercial terms and conditions.

-----------------------------------------------------------------------------------------------------------------------

Sr. no. Clause no. Deviation. Cost of withdrawal (Rs.)

-----------------------------------------------------------------------------------------------------------------------

-----------------------------------------------------------------------------------------------------------------------

Yours faithfully,

Date: ------------------------- (Signature)---------------------------

Place: ------------------------- (Printed Name)----------------------

(Designation)------------------------

(Common Seal)----------------------

Note: - Bidders may note that the bids containing the deviations without the cost of withdrawal

shall be rejected.

Page 44: FOR (3x5.65 MW) ANDHRA HYDRO-ELECTRIC PROJECT Document Excitation System.pdf · 1 himachal pradesh state electricity board limited bid documents for “static excitation system and

44

ATTECHMENT -6A

(Name of the Project)

Cost of withdrawal of deviations from the requirement of the Technical specifications.

(Bidder's Name & Address)

To:--------------------------------------------------

(Owner's Name & Address)

Dear Sir,

Following are the deviation from the requirement of the Technical Specification, Drawings etc.

-----------------------------------------------------------------------------------------------------------------------

Sr. no. Clause no. Deviation. Cost of withdrawal (Rs.)

-----------------------------------------------------------------------------------------------------------------------

-----------------------------------------------------------------------------------------------------------------------

Yours faithfully,

Date: ------------------------- (Signature)---------------------------

Place: ------------------------- (Printed Name)----------------------

(Designation)------------------------

(Common Seal)----------------------

Note: Bidders may note that bids containing deviations without the cost of withdrawal shall be

rejected.

Page 45: FOR (3x5.65 MW) ANDHRA HYDRO-ELECTRIC PROJECT Document Excitation System.pdf · 1 himachal pradesh state electricity board limited bid documents for “static excitation system and

45

Price Schedules

Page 46: FOR (3x5.65 MW) ANDHRA HYDRO-ELECTRIC PROJECT Document Excitation System.pdf · 1 himachal pradesh state electricity board limited bid documents for “static excitation system and

46

Schedule No. - 1.

Plant, Equipment and Mandatory Spare Parts

Name of Work: Design, manufacture, shop assembly & testing, & commissioning of three (3)

numbers static excitation and Digital AVR systems complete with accessories

to be installed in the 3 X 5.65 MW Andhra Power House and

dismantling/removing of the existing excitation system.

Name of Bidder:-----------------------------

Signature of Bidder:-----------------------------

-

Sr. no

Description of material Qty EXW. Unit price

(Rs.)

EXW. Total price

(Rs.)

1. 2. 3. 4. 5.

1 Providing static excitation system and Digital

AVR systems complete with accessories,

equipment, devices, instruments, cabling and

wiring etc.

3 Sets

2 Providing Excitation Transformer (Optional)

as per technical specification.

3 Nos.

3 Providing field circuit breakers (Optional)

as per technical specification.

3 Nos.

4 Providing discharge resistors (Optional) as per

technical specification.

3 Nos.

5. Mandatory Spares 1 Lot

Above quantities are minimum and contractor shall provide all the required material/ quantity weather

mentioned above or not, to complete the job as per technical specifications without any extra financial

implication to HPSEBL.

Page 47: FOR (3x5.65 MW) ANDHRA HYDRO-ELECTRIC PROJECT Document Excitation System.pdf · 1 himachal pradesh state electricity board limited bid documents for “static excitation system and

47

Schedule 2. Transportation and Insurance

Unit Price (Rs.)

Item

Description

Unit

Qty.

(1)

Transportation &

Insurance

(2)

Total Price (Rs.)

(1x2)

1 Transportation

2. Insurance

Total (to Schedule 4. Grand Summary)

Name of Bidder:------------------------

Signature of Bidder:-------------------

Page 48: FOR (3x5.65 MW) ANDHRA HYDRO-ELECTRIC PROJECT Document Excitation System.pdf · 1 himachal pradesh state electricity board limited bid documents for “static excitation system and

48

Schedule 3. Installation Services (including dismantling charges of existing panel)

Unit Price (Rs.)

Total Price

(Rs.)

Item

Description.

Unit.

Qty.

(1)

(2)

(1x2)

Total (to Schedule 4. Grand Summary)

Name of Bidder:------------------------------

Signature of Bidder:-------------------------

Page 49: FOR (3x5.65 MW) ANDHRA HYDRO-ELECTRIC PROJECT Document Excitation System.pdf · 1 himachal pradesh state electricity board limited bid documents for “static excitation system and

49

Schedule 4. Grand Summary

Item Description Total Price (Rs.)

1.

Total Schedule 1: Plant, equipment and mandatory spare

parts.

2.

Total Schedule 2: Transportation & insurance

3.

Total Schedule 3: Installation services

GRAND TOTAL (to Bid form)

Name of Bidder:------------------------------

Signature of Bidder:-------------------------

Page 50: FOR (3x5.65 MW) ANDHRA HYDRO-ELECTRIC PROJECT Document Excitation System.pdf · 1 himachal pradesh state electricity board limited bid documents for “static excitation system and

50

Schedule 5. Recommended Spare Parts

Item Description Unit Qty.

(1)

Unit Price

EXW (Rs.)

(2)

Total price

(Rs.)

(1x2)

(3)

Transportation including

Insurance.

(4)

Total

Name of Bidder:--------------------

Signature of Bidder:---------------

Page 51: FOR (3x5.65 MW) ANDHRA HYDRO-ELECTRIC PROJECT Document Excitation System.pdf · 1 himachal pradesh state electricity board limited bid documents for “static excitation system and

51

Schedule No. - 6.

Taxes and Duties

Name of Bidder:-------------------------

Signature of Bidder:------------------------------

Item

Description of

Taxes / duties/

levies etc.

Rate of Taxes/

duties/ levies

application

Amount on which

Taxes / duties / levies

applicable

Taxes duties/ levies

payable in Rupees.

1 2 3 4 5

Page 52: FOR (3x5.65 MW) ANDHRA HYDRO-ELECTRIC PROJECT Document Excitation System.pdf · 1 himachal pradesh state electricity board limited bid documents for “static excitation system and

52

4. FORM OF 'NOTIFICATION OF AWARD OF CONTRACT'

NOTE: INSTRUCTIONS INDICATED IN ITALICS IN THIS NOTIFICATION OF

AWARD ARE TO BE TAKEN CARE OF BY THE ISSUING AUTHORITY.

Ref. No.:

Date:

-------------- (Contractor's Name & Address)-----------------------

------------------------------------------------------------------------------

------------------------------------------------------------------------------

------------------------------------------------------------------------------

Attn: Mr.-----------------------

Sub: Notification of Award of Contract.

Dear Sir,

1.0 This has reference to the following:

i) Bid Documents issued to you vide our letter no.------------------------------------- dated ---

--------------------------

ii) Clarifications furnished to you on the Bid Documents vide our letter no.-----------------

dated------------------------

iii) Your Proposal for the subject package submitted vide your letter no.-------------------------

dated-------------------.

iv) Our Fax message/letter no.-------------------------------dated--------------------------------

regarding extension of validity of Bid and that of the Bank Guarantee towards Bid

Security.

(Applicable only if any extension has been sought subsequently)

v) Post Bid discussions and meetings we had with you from ----------------to -------

vi) Clarification/ Confirmation furnished by you vide your letter No.------------------------

dated ------------------------.

2.0 We confirm having accepted your proposal submitted vide letter no.-----------------------------

dated --------------------------- read in conjunction with all the specifications, terms & conditions of

the Bid Documents and your subsequent letters (Use if relevant) referred to in para 1.0 above

and award on you the contract for the work of ------------------------------------------(Indicate brief

Scope of Work)---------------------------------------------------------------------------- for (Name of

project).------------------------------------------ as per Bid Documents No .-------------------

(hereinafter referred to as the ‘Contract') .

Page 53: FOR (3x5.65 MW) ANDHRA HYDRO-ELECTRIC PROJECT Document Excitation System.pdf · 1 himachal pradesh state electricity board limited bid documents for “static excitation system and

53

3.0 The total Contract Price for the entire scope of work under the Contract shall be

-----------------(Specify the amount)--------- as per the following break up:

i) Ex-manufacturing works/place -----------------------------------------

of despatch price for main Equipment

& mandatory spare

ii) Transportation and Insurance -----------------------------------------

iii) Unloading and handling at site, -----------------------------------------

installation, testing and

commissioning including performance

testing.

TOTAL (i+ii+iii) -----------------------------------------

(--------------------------(Specify the total amount in words)--------------------------------)

4.0 You shall prepare and finalise the Contract Documents for signing of the formal Contract and

shall enter into the Contract Agreement with us, as per the proforma enclosed with the Bid

Documents, on non-judicial stamp paper of appropriate value within 15 days from the date of this

Notification of Award.

5.0 This Notification of Award is being issued to you in duplicate. We request to return its duplicate

copy duly signed and stamped on each page including all the enclosed Appendices, by the

authorised signatory of your company as a proof of your acknowledgement and confirmation.

Please take the necessary action to commence the work and confirm action.

Yours faithfully,

For and on behalf of

---------(Name of the Owner)-------------

Encl.: As above.

(Authorised Signatory)

Page 54: FOR (3x5.65 MW) ANDHRA HYDRO-ELECTRIC PROJECT Document Excitation System.pdf · 1 himachal pradesh state electricity board limited bid documents for “static excitation system and

54

5. Form of Contract Deed

THIS CONTRACT is made the ----------------------day of -------------------------2012

BETWEEN

(1) Himachal Pradesh State Electricity Board, a body corporate, incorporated under section 5 of Electricity

(Supply) Act, 1948 (54 of 1948)] and having its principal place of business at Vidyut Bhawan Shimla

171001 (H.P) India (hereinafter called "the Owner"), and (2) [Name of Contractor], having its principal

place of business at [address of Contractor] (hereinafter called "the Contractor").

WHEREAS the Owner desires to engage the Contractor for execution of the work of design,

Engineering, Fabrication, supply, transportation, insurance, installation, erection, commissioning

& testing of three (3) numbers static excitation and Digital AVR systems complete with accessories to be

installed in the 3 X 5.65 MW Andhra Power House and the Contractor have agreed to such engagement

upon and subject to the terms and conditions hereinafter appearing.

NOW IT IS HEREBY AGREED as follows: -

Article 1. Contract 1.1 Contract Documents (Reference GCC Clause 2.0)

Document The following document shall constitute the Contract between the

Owner and the Contractor, and each shall be read and construed

as an integral part of the Contract:

a) This Contract Agreement and the Appendices hereto.

b) Notification of Award.

c) Forms & Procedures (as listed).

d) Technical Specifications.

e) General Conditions of Contract.

f) Information for Bidders.

g) The Bid and Price Schedule submitted by the Contractor.

1.2 Order of Precedence

In the event of any ambiguity or conflict between the Contract

Documents listed above, the order of precedence shall be the

order in which the Contract Documents are listed in Article 1.1

(Contract Documents) above.

1.3 Definitions (Reference GCC Clause 1.0)

Capitalised words and phrases used herein shall have the same

meanings as are ascribed to them in the General Conditions of

Contract.

Article 2. Contract 2.1 Contract Price (Reference GCC Clause 11.0)

Price and The Owner hereby agrees to pay to the Contractor the

Terms of Contract Price in consideration of the performance by the

Payment Contract of its obligations hereunder. The Contract Price shall be

the aggregate of: [amount in words], [amount in figures], or such

Page 55: FOR (3x5.65 MW) ANDHRA HYDRO-ELECTRIC PROJECT Document Excitation System.pdf · 1 himachal pradesh state electricity board limited bid documents for “static excitation system and

55

other sums as may be determined in accordance with the terms

and conditions of the Contract,

2.2 Terms of Payment (Reference GCC Clause 12.0)

The terms and procedures of payment according to which the

Owner will reimburse the Contractor are given in Appendix 1

(Terms and Procedures of Payment hereto).

Article 3: Effective 3.1 Effective Date (Reference GCC Clause 1.0)

Date for The Time of Completion of the works shall be

Determining determined from the date of Notification of Award

Time for

Completion

Article 4. (This is applicable It is expressly understood and agreed by and between the

only if the Owner is Contractor and the Owner that the Owner is entering into

a Public Sector this Contract solely on its own behalf and not on behalf of

Enterprises) any other person or entity. In particular it is expressly understood

and agreed that the Government of Himachal Pradesh and

Government of India is not a party to this Agreement and has no

liabilities, obligations or rights hereunder .It is expressly

understood and agreed that the Owner is an independent legal

entity with power and authority to enter into contracts solely on

its own behalf under the applicable laws of India and the general

principles of Contract Law. The Contractor expressly agrees,

acknowledges and understands that the Owner is not an Agent,

Representative or Delegate of the Government of Himachal

Pradesh/ Government of India. It is further understood and agreed

that the Government of Himachal Pradesh/ Government of India

is not and shall not be liable for any acts, omission, and

commissions, breaches or other wrongs arising out of the

Contract. Accordingly, the Contractor expressly waives, releases

and foregoes any and all actions or claims, including cross claims,

or counter claims against the Government of Himachal Pradesh/

Government of India arising out of this Contract and covenants

not to sue the Government of Himachal Pradesh/ Government of

India as to any manner, claim, cause of action or thing whatsoever

arising of or under this Agreement.

Article 5. Appendices The Appendices listed in the attached list of Appendices shall be

deemed to form an integral part of this Contract Agreement.

Reference in the Contract to any Appendix shall mean the

Appendices attached hereto, and the Contract shall be read and

construed accordingly.

IN WITNESS WHEREOF of the Owner and the Contractor have caused this Agreement to be duly

executed by their duly authorised representatives the day and year first above written.

Signed by for and on behalf of the Owner

Page 56: FOR (3x5.65 MW) ANDHRA HYDRO-ELECTRIC PROJECT Document Excitation System.pdf · 1 himachal pradesh state electricity board limited bid documents for “static excitation system and

56

____________________________________________________

[Signature]

____________________________________________________

[Title]

in the presence of ______________________________________

Signed by for and on behalf of the Contractor

_________________________________________________________________

[Signature]

__________________________________________________________________

[Title]

in the presence of ____________________________________________________

CONTRACT AGREEMENT

Dated the______________________ day of ________________________ ____________

BETWEEN

____________________________________________________________________________

["the Owner"]

and

____________________________________________________________________________

____________________________________________________________________________

["the Contractor"]

APPENDICES

Appendix 1 Terms and Procedures of Payment

Appendix 2 Price Adjustment

Appendix 3 Insurance Requirements.

Appendix 4 Time Schedule/Programme of Performance.

Sample Forms of Appendices 1 & 3 are provided herein.

Page 57: FOR (3x5.65 MW) ANDHRA HYDRO-ELECTRIC PROJECT Document Excitation System.pdf · 1 himachal pradesh state electricity board limited bid documents for “static excitation system and

57

Appendix - 1.

Terms and Procedures of Payment

1.0 In accordance with the provisions of GCC Clause 12.0 (Terms of Payment), the Owner shall pay

the Contractor in the following manner and at the following times, on the basis of the Price

Break-up given in the Price Schedules No. – 1 & 2.

2.0 TERMS OF PAYMENT

2.1 Ninety percent (90%) of the measured value of work performed by the Contractor, as identified in

the said Program of Performance, during the preceding month, as evidenced by the Owner's

authorization of the Contractor's application along with full taxes will be made within forty five

(45) days after receipt of bill and successful commissioning of Real Time Online WDS

monitoring System by the Owner/ HPSEBL.

2.2 Balance ten percent (10%) of the total value of work performed by the Contractor, upon issue of

the Operational Acceptance Certificate, within forty five (45) days after receipt of invoice.

3.0 Taxes & Duties

3.1 All taxes, duties and levies including sales tax on works Contract, as applicable on the materials

used for such erection portion of the Contract shall be to the Contractor’s account and no separate

claim in this regard will be entertained by the Owner.

3.2 The Service tax and education cess on service tax shall be paid by the Owner to the Contractor at

the rates prevailing at that time against documentary evidence given by the Contractor of his

having the Service Tax number.

3.3 As regards the Indian income tax, surcharge on income tax and any other corporate tax, the

Owner shall not bear any tax liability whatsoever. The Contractor shall be liable and responsible

for payment of such tax, if attracted under the provisions of the law present or future and Owner

will make deductions at source as applicable and issue TDS certificates to the Contractor.

4.0 PAYMENT PROCEDURES

The procedures to be followed in applying for certification and making payments shall be as

follows:

4.1 All payments shall be made in line with the Schedule Nos. -1& 2.

4.2 Upon completion of the particular activity, the Owner’s Site In-charge and the Contractor’s

Representative shall jointly sign a completion protocol giving the details of the activity carried

out with the start & finish dates.

4.3 The Contractor shall raise the invoice for the activity completed and submit copies of the

completion protocol to substantiate his claim.

4.4 Five sets of invoices shall be sent to the Engineer - in - charge .

4.5 The invoices should be accompanied by a statement showing the detail of invoices along with

their claimed amount already sent release of payment.

Page 58: FOR (3x5.65 MW) ANDHRA HYDRO-ELECTRIC PROJECT Document Excitation System.pdf · 1 himachal pradesh state electricity board limited bid documents for “static excitation system and

58

Appendix-2. Price Adjustment

The Prices are:-

“FIXED & FIRM”

No Price Variation claim (PVC) is allowed.

Page 59: FOR (3x5.65 MW) ANDHRA HYDRO-ELECTRIC PROJECT Document Excitation System.pdf · 1 himachal pradesh state electricity board limited bid documents for “static excitation system and

59

Appendix - 3.

Insurance Requirements

Insurances to be taken out by the Contractor

In accordance with the provisions of GCC Clause 26.0, the Contractor shall at its expense take out and

maintain in effect, during the performance of the Contract, the insurances set forth below in the sums and

with the deductibles and other conditions specified. The identity of the insurers and the form of the

policies shall be subject to the approval of the Owner, such approval not to be unreasonably withheld.

a) Third Party Liability Insurance

Covering bodily injury or death suffered by third parties (including the Owner's personnel) and

loss of or damage to property (including the Owner property and any parts of the facilities that

have been accepted by the Owner) occurring in connection with the supply and installation of the

facilities.

Amount Deductible limits Parties insured From To

b) Worker's Compensation

In accordance with the statutory requirements applicable where the facilities or any part thereof is

executed.

Page 60: FOR (3x5.65 MW) ANDHRA HYDRO-ELECTRIC PROJECT Document Excitation System.pdf · 1 himachal pradesh state electricity board limited bid documents for “static excitation system and

60

Appendix-4. Completion Time Period

The plant and equipment covered by the bid are to be supplied & installed and the

facilities shall have the commissioning completed within Six months from the date

of Notification of Award of Work to contractor by HPSEB. The necessary

Programme of performance to achieve the commissioning within Six months from

the date of Notification of Award of Work to contractor by HPSEB to be submitted

by the contractor.

Page 61: FOR (3x5.65 MW) ANDHRA HYDRO-ELECTRIC PROJECT Document Excitation System.pdf · 1 himachal pradesh state electricity board limited bid documents for “static excitation system and

61

Appendix 5. List of Approved Sub-contractors

Prior to award of Contract, the following details shall be completed, indicating those

Subcontractors proposed by the Bidder in the corresponding Attachment to its bid that are

approved by the Owner for engagement by the Contractor during he performance of the Contract.

The following Subcontractors are approved for carrying out the item of the facilities indicated.

Where more than one Subcontractor is listed, the Contractor is free to choose between them, but it

must notify the Owner of its choice in good time prior to appointing any selected Subcontractors.

No Subcontractors shall be placed with any such Subcontractors for additional items until the

Subcontractor have been approved in writing by the Owner and their names have been added to

this list of Approved Subcontractors.

Item of Facilities Approved Subcontractors Address

Page 62: FOR (3x5.65 MW) ANDHRA HYDRO-ELECTRIC PROJECT Document Excitation System.pdf · 1 himachal pradesh state electricity board limited bid documents for “static excitation system and

62

6. Performance Security Forms

Performance Bank Guarantee (To be stamped in accordance with Stamp Act )

Bank Guarantee No……………………

Date………………………….

To

[Owner's name & Address]

Dear Sir,

In consideration of the ………….[Owner's Name]………..(hereinafter referred to as the 'Owner which

expression shall unless repugnant to the context or meaning thereof, include its successors, administrators

and assigns) having awarded to M/s……..[Contractor's Name}…………with its Registered/Head Office

at………..(hereinafter referred to as the Contractor, which expression shall unless repugnant to the

context or meaning thereof, include its successors administrators, executors and assigns), a Contract by

issue of Owner's Notification of Award No ……………dated ……….and the same having been

unequivocally accepted by the contractor, resulting into a Contract bearing No………

dated……….valued at------------- for …… and the contractor having agreed to provide a Contractor

Performance Guarantee for the faithful performance of the entire Contract equivalent to

………(*)………….%…….(…….percent) of the said value of the Contract to the Owner.

We……..[Name & Address of the Bank]…………..having its Head Office at ……..(hereinafter referred

to as the 'Bank', which expression shall, unless repugnant to the context of meaning thereof, include its

successors, administrators, executors and assigns) do hereby guarantee and undertake to pay the Owner,

on demand any and all monies payable by the Contractor to the extent of ………………

(*)……………………… as aforesaid at any time upto ……….. (@)…………………[days/month/year]

without any demur, reservation, contest, recourse or protest and/or without any reference to the

Contractor. Any such demand made by the Owner on the Bank shall be conclusive and binding

notwithstanding any difference between the Owner and the Contractor or any dispute pending before any

Court, Tribunal, Arbitrator or any other authority. The Bank undertakes not to revoke this guarantee

during its currency without previous consent to the Owner and further agrees that the guarantees herein

contained shall continue to be enforceable till the Owner discharges this guarantee.

The owner shall have the fullest liberty, without affecting in any way the liability of the Bank under this

guarantee, from time to time extend the time for performance of the Contract by the Contractor. The

Owner shall have the fullest liberty, without affecting this guarantee, to postpone from time to time the

exercise of any powers vested in them or of any right which they might have against the Contractor, and

to exercise the same at any time in any manner, and either to enforce or to forbear to enforce any

covenants, contained or implied, in the Contract between the Owner and the Contractor or any other

course or remedy or security available to the Owner. The bank shall not be released of its obligations

under these presents by any exercise by the Owner of its liberty with reference to the matters aforesaid or

any of them or by reason of any other act or forbearance or other acts of omission or commission on the

part of the Owner or any other indulgence shown by the Owner or by any other matter or thing

whatsoever which under law would, but for this provision have the effect of relieving the Bank.

The bank also agrees that the Owner at its option shall be entitled to enforce this Guarantee against the

bank as a principle debtor, in the first instance without proceeding against contractor and notwithstanding

any security or other guarantee the Owner may have in relation to the Contractor's liabilities.

Page 63: FOR (3x5.65 MW) ANDHRA HYDRO-ELECTRIC PROJECT Document Excitation System.pdf · 1 himachal pradesh state electricity board limited bid documents for “static excitation system and

63

Notwithstanding anything contained herein above our liability under this guarantee is restricted to

………………(*) …………….. and it shall remain in force upto and including ………….

@………………… and shall be extended from time to time for such period (not exceeding one year), as

may be desired by M/s……………[Contractor's Name]………….on whose behalf this guarantee has

been given.

Dated this ………………………..day of ………………2012………..at………………………..

WITNESS

……………………………… (Signature)…………………...

(Signature)

……………………………… (Name)………………………..

(Name) ………………………………...

……………………………….. (Designation with Bank Stamp).

…………………………………

(Official Address) ………………………………...

Attorney as per Power of

Attorney No…………………..

Dated…………………………

Notes: 1. (*) This sum shall be ten percent (10%) of the Contract Price.

@ This date will be ninety (90) days beyond the Defects liability period as specified

in the Contract.

2. The stamp papers of appropriate value shall be purchased in the name of guarantee

issuing Bank.

Page 64: FOR (3x5.65 MW) ANDHRA HYDRO-ELECTRIC PROJECT Document Excitation System.pdf · 1 himachal pradesh state electricity board limited bid documents for “static excitation system and

64

7. Form of Completion Certificate

Date: --------------------------------------

Contract No: ----------------------------------

[Name of Contract]

To: [Name and address of Contractor]

Dear Sir,

Pursuant to GCC Clause 21 (Completion of the Facilities) of the General Conditions of the Contract

entered into between yourselves and the Owner dated [date], relating to the [brief description of the

facilities], we hereby notify you that the following parts(s) of the Facilities was (were) complete on the

date specified below, and that, in accordance with the terms of the Contract, the Owner hereby takes over

the said part(s) of the Facilities on the date mentioned below.

1. Description of the Facilities or part thereof: [description]

2. Date of Completion: [date]

However, you are required to complete the outstanding items listed in the attachment hereto as soon as practicable.

This letter does not relieve you of your obligation to complete the execution of the Facilities including

Guarantee Test(s) in accordance with the Contract nor of your obligations during the Defects Liability

Period.

Very truly yours,

Title

(Engineer- in-charge)

Page 65: FOR (3x5.65 MW) ANDHRA HYDRO-ELECTRIC PROJECT Document Excitation System.pdf · 1 himachal pradesh state electricity board limited bid documents for “static excitation system and

65

8. Form of Operational Acceptance Certificate

Date:_____________________________

Bid Spec. No: ___________________________

[Name of Contract]

To: [Name and address of Contractor]

Dear Sir,

Pursuant to GCC Sub- Clause 22.2 (Operational Acceptance) of the General Conditions of the Contract

entered into between yourselves and the Owner dated [date], relating to the [brief description of the

Works], we hereby notify you that the tests of the following parts(s) of the works were satisfactorily

carried out on the dates specified below and the works are hereby taken over by the Owner on the dates

specified.

1. Description of the Facilities or part thereof: [description]

2. Date of Operational Acceptance: [date]

This letter does not relieve you of your obligation to during the Defects Liability Period.

Very truly yours,

Title

(Engineer-in-charge)

Page 66: FOR (3x5.65 MW) ANDHRA HYDRO-ELECTRIC PROJECT Document Excitation System.pdf · 1 himachal pradesh state electricity board limited bid documents for “static excitation system and

66

SECTION-V

Technical Specifications

Page 67: FOR (3x5.65 MW) ANDHRA HYDRO-ELECTRIC PROJECT Document Excitation System.pdf · 1 himachal pradesh state electricity board limited bid documents for “static excitation system and

67

INDEX

TECHNICAL SPECIFICATIONS

TABLE OF CONTENTS

CLAUSE NO. PARTICULARS PAGE NO

1.0 Static Excitation System and Digital AVR 68

2.0 General Requirement 68

3.0 Scope of Supply 69

4.0 Codes & Standards 69

5.0 Rating and Output 70

6.0 Design and Construction 70

7.0 Field Flashing Equipment 79

8.0 De-Excitation System 79

9.0 Excitation Control Cubicle 80

10.0 Protection of Static Excitation Equipment 80

11.0 Excitation Connection 81

12.0 Communication Channels 81

13.0 Wiring Requirements 81

14.0 INSPECTION, TESTING AND COMMISSIONING 82

Page 68: FOR (3x5.65 MW) ANDHRA HYDRO-ELECTRIC PROJECT Document Excitation System.pdf · 1 himachal pradesh state electricity board limited bid documents for “static excitation system and

68

TECHNICAL SPECIFICATIONS FOR STATIC EXCITATION SYSTEM AND DIGITAL AVR

1 Static Excitation System and Digital AVR:-

This section of the specifications covers the detailed requirements of all works necessary

for dismantling/removing the existing excitation system including carriage, stacking at

Owner’s store/ yard and detailed design, manufacture, shop assembly & testing,

comprehensive insurance, delivery, erection, testing & commissioning at site, field

acceptance tests of static excitation system before handing over to the owner/HPSEB

Ltd. and guaranteed for two years of three (3) numbers static excitation and Digital

AVR systems complete with accessories, equipment, devices, instruments, cabling and

wiring etc. including all services, labour, tools and tackles in all respects.

2 General Requirement:-

The proposed excitation system is to be installed in the 3 x 5.65 MW Andhra Power

House. Tenderers are strongly advised to make the necessary site visit for first hand

information on design, arrangements, installation and layout of excitation equipments,

control, protection and instrumentation required and access the drawings of the existing

excitation system available at the site.

The Bidder shall submit the proposal of the new excitation system along with the Bid

Document suitable to replace the existing excitation system with necessary block and

system diagrams. The submitted proposal shall justify such replacements in totality.

The cost pertaining to relocation of equipments, modifications and adjustments

whatsoever necessary to complete the specified scope of works shall not be subjected to

additional costs.

The layout of various components in the cabinet, protection panel incorporating the

hardware and control wiring diagrams and schematics shall be prepared by the

Contractor and be sent to the Owner for approval.

All auxiliary components, if and when required for the completeness of the various

proposed excitation system schemes covered in this order, shall be deemed to be

included in the scope of supply whether or not such items are specifically mentioned in

the given bill of quantity.

A ground bus of bare copper strip of required size panel shall be provided and shall be

connected to the ground mat of the power station.

The buyer shall have a royalty free, non-exclusive and irrevocable license to use all the

software furnished necessary to operate the equipment. This shall apply to any software

procured by the Contractor from the Sub-Contractor for this application.

Page 69: FOR (3x5.65 MW) ANDHRA HYDRO-ELECTRIC PROJECT Document Excitation System.pdf · 1 himachal pradesh state electricity board limited bid documents for “static excitation system and

69

3 Scope of Supply

- Three (3) sets of excitation systems complete in all respects comprising of: -

- Three (3) sets of rectifier systems with 100% stand by capacity complete with

firing circuit, control system etc.

- Three (3) sets of Digital automatic voltage regulators.

- Three (3) sets of power supply units.

- Three (3) sets of field flashing equipment including transformers.

- Three (3) sets of digital control and metering equipment.

- Any other items not specified above, but are necessary for satisfactory operation

of the system.

- Mandatory spares.

Optional Items: -

- Three (3) sets of excitation transformers, dry type

- Three (3) nos. field circuit breakers.

- Three (3) nos. discharge resistors.

- Recommended spares.

4 Codes & Standards

The excitation equipment shall be developed in conformity with the following

requirements of the standards and specifications.

IEC 60034-16

Excitation systems for synchronous machines

IEEE Std421

Excitation Systems for Synchronous Machines

GB/T7409

Excitation system for synchronous electrical machines

GB 10585 Fundamental requirements of excitation systems medium and

small synchronous machines

Except as provided in the specifications, all materials, equipment, and fabrication and

testing thereof shall confirm to the latest applicable standards contained in the following

list: -

American Society for Testing and Materials (ASTM)

American Welding Society (AWS)

American Society of Mechanical Engineers (ASME)

International Electromechanical Commission (IEC)

National Electrical Manufacturers Association (NEMA)

Deutsche Industrie Normen (DIN)

Verband Deutcher Electrotechnicker (VDE)

International Organization for Standardization (ISO)

European Color Selection Chart (RAL)

The Bidder shall provide the testimonials of the adoption of the aforesaid codes and

standards in the proposed equipments and materials.

Page 70: FOR (3x5.65 MW) ANDHRA HYDRO-ELECTRIC PROJECT Document Excitation System.pdf · 1 himachal pradesh state electricity board limited bid documents for “static excitation system and

70

5 Rating and Output: -

The rating of existing generator is as under: -

1. Output capacity: 6647 /5650kW.

2. Rated power Factor 0.85 lag

3. Rated frequency. 50 + 3% Hz

4. Number of phases 03

5. Rated Voltage between phases 11 + 10% kV

6. Speed 500 rpm

7. Stator winding connection. Star

8. Stator winding resistance / phase at 750C 0.115 Ohm

9. Field winding resistance at 750C 0.18 Ohm

10. D.A. Synchronous reactance Xd (Unsat) 1.2 p.u.

11. Q.A. Synchronous reactance Xq (Unsat) 0.7 p.u.

12. Transient Reactance Xd’ (Sat) 0.24 p.u.

13. Transient Reacatance Xd’ (unsat) 0.28 p.u.

14. Subtransient Reactance Xd” (Sat) 0.15 p.u.

15. Ratio Sq”/Xd” 1.45

16. Short circuit ratio 0.95

17. Excitation at no load 280 Amps.

18. Excitation at rated load, p.f. and voltage 400 Amps.

19. Slip Ring Brushes ( 5 per ring) Total 10

6 Design and Construction:-

The static excitation system shall be microprocessor based AVR (digital) with thyristors

and shall include all necessary devices to supply excitation current to the generator. The

system shall be capable of controlling the generator terminal voltage under all operating

conditions.

The static excitation system offered shall be of static, digital, constant voltage type with

controlled thyristors. The excitation system shall be of reliable design with very

sensitive, quick acting control of generator voltage and reactive power.

The excitation system continuous rating shall be approximately twice the rating required

when the generator is operated at rated output, rated power factor, rated frequency and

110% rated voltage.

The equipment shall be capable of withstanding lightning & switching surges and

dynamic over-voltages to which they may be subjected and shall meet all the

performance requirements and tests described in the specifications. The equipment shall

conform to the latest issue of IEEE 421 or equivalent standard.

The equipment shall be capable of fully reversing its output voltage in response to

control signal in order to minimize generator iron burning in the event of generator fault.

Direct current measuring equipment consisting of shunts and leads etc. and all other

equipment required to provide indication of field current/voltage at AVR panels shall be

Page 71: FOR (3x5.65 MW) ANDHRA HYDRO-ELECTRIC PROJECT Document Excitation System.pdf · 1 himachal pradesh state electricity board limited bid documents for “static excitation system and

71

furnished. Copper conductor power cables shall be provided for connection from rectifier

transformer to thyristor cubicle and field breaker and slip rings.

The excitation system shall be capable of operation of the machines in parallel

maintaining even distribution of the reactive load between machines. Paralleling of the

generators shall be achieved on 66 kV side of the generator transformers.

The static excitation equipment shall be of modular design in such a way that it can be

readily removed for inspection or replacement of parts. Indicating lights shall be

provided at each module to indicate and locate rectifier failure.

All the equipment of static excitation and digital type AVR shall be suitably housed in

sheet metal dust proof cubicles. These cubicles shall be located at one place in a row

without any gap in between. The dimensions of the cubicle shall be identical to present a

neat and functional line up.

6.1 Excitation Transformer:-

The existing excitation transformers are in operation and are in healthy conditions. The

Tenderer shall quote the prices of equipment excluding the cost of Excitation

Transformer. In case bidders recommend to replace these transformers in case of non-

compatibility with their system, the price of excitation transformers may be quoted as an

optional item. The name plate specifications of the existing transformers is as under: -

Sr.No Description As per existing detail

1. Exciation Transformer:

i. Rated capacity 100kVA

ii. Type DG100-15SP

iii. Rated frequency 50Hz

iv. Primary Volatage 11000 V

v. Secondary Volatage 110V

vi. Vector Group DYn5

vii. Weight 650kg

2. Generator PT Data

i. Ratio 11kV/3/110/3

ii. Burden 200VA

3. CT on Excitation Transformer Primary

side

i. Ratio 10/1A

Page 72: FOR (3x5.65 MW) ANDHRA HYDRO-ELECTRIC PROJECT Document Excitation System.pdf · 1 himachal pradesh state electricity board limited bid documents for “static excitation system and

72

ii. Accuracy class 5P10

iii. Burden 20VA

4 CT on Excitation Transformer Secondary

side

i. Ratio 4001A

ii. Accuracy class 3

iii. Burden 15VA

The excitation system shall be supplied a.c power by means of cables through a high

performance 3 phase dry type excitation transformer. The primary winding of the

excitation transformer shall be connected to the 11 KV system of the generator. A

suitable means (power cable) shall be provided to connect the primary winding of transformer with 11 KV system of the generator.

The excitation transformer shall be air natural cooled, metal enclosed, designed &

constructed to match perfectly with common switchgear assembly, indoor cast-resin dry

type, having class F insulation. The high voltage and low voltage windings shall be

impregnated and vacuum cast into moulds of glass fibre reinforced epoxy resin. The

windings shall be provided with temperature sensors and static alarm and tripping

device. Ratings of the excitation transformers shall be sufficient to meet the duties

specified herein.

The excitation transformer shall be in the cubicle part of the excitation cubicle, which

shall be made of removable panels. The arrangement shall be such that it is possible to

remove the transformer without dismantling the cubicle completely.

Since the high voltage winding is connected directly to the generator terminals, full

design consideration shall be given to the frequency increase rate, generator voltage

build-up rate and insulation co-ordination. Surge transmission from high voltage side to

the low voltage side shall be prevented by suitable means.

Metallic barriers of suitable design shall be installed between phases, inside the

transformer, to prevent any short circuit between phases. Necessary CT's shall be

provided on the primary side for over current protection besides other required safety and

monitoring devices.

6.2 Power Rectifier: -

The power rectifier equipment shall consist of 3- phase full wave power SCR thyristor

bridges, its associated firing circuits complete with power fuses in series with each

thyristor (fuses shall be monitored individually or in groups providing alarms and trips as

required) gate pulse transformer, RC snubbers and status light indicators for each bridge

on the front panel of rectifier cubicle. The design shall provide 100% redundancy i.e. at

Page 73: FOR (3x5.65 MW) ANDHRA HYDRO-ELECTRIC PROJECT Document Excitation System.pdf · 1 himachal pradesh state electricity board limited bid documents for “static excitation system and

73

full load operation (including ceiling voltage) the thyristor shall be working at 50% of

their nominal rating. The ceiling voltage shall be more than 2.0 p.u.

Two independent ignition circuits shall be provided for the manual and automatic control

respectively. The rectifier shall be rated for the following duty cycle:

a) Continuous operation at its rating.

b) Three-phase fault adjacent to HV terminals of the generator.

c) Short circuit on high voltage side of the transformer with duration of 2 seconds.

The modules shall be capable of coping with three phase short circuits at the generator

terminals or on the H.V side of the step up transformers of 3-sec. Duration.

The following monitoring and protection features shall be provided: -

- Thyristor and field circuit over voltage protection.

- A.C system over voltage and over current.

- D.C. short circuits.

- Temperature monitoring of thyristors

- Thyristor failure

- Transient over voltage originating from the A.C system, lightning or switching

surges.

The thyristor cubicles shall be cooled by forced air. For this purpose 100% capacity

reserve fans shall be supplied with provision of automatic switching to the reserve unit,

activated by fall in pressure and rise in temperature of exit air from main unit.

Calculation for the capacity of rectifier shall be submitted. While determining the

capacity, effect of ageing shall also be considered. The rectifier PIV (Peak Inverse

voltage) rating shall not be less than four times the maximum r.m.s. voltage of the inputs.

The system shall operate correctly with supply voltage upto 120% rated voltage or

unbalanced supply voltage.

The equipment shall have sufficient capacity to provide ceiling voltage and current

required by the generator. The voltage regulator shall provide suitable firing pulses to the

thyristors for stable control of terminal voltage and quick compensation of voltage

deviations caused by sudden load changes in the system.

6.3 Automatic Voltage Regulator: -

The voltage regulator shall be of quick acting microprocessor based and shall respond

continuously and instantaneously to correct any change in generator voltage. It shall

contain all the functionality necessary to limit, control and protect the generator from

operating outside of its capability. It shall be having Proportional Integral and Derivative

(PID) stability control. It shall maintain the generator voltage for steady state load

conditions without hunting, with 0.5% accuracy for any excitation with in the operating

range of the generator. For steady state conditions with the generator circuit open the

regulator shall maintain the generator terminal voltage at or below 110% of its setting for

speeds ranging from rated speed to an over speed of 120% rated speed. The system

limiting control shall be provided to limit the generator voltage to maximum 125% of

rated voltage in the event that the AVR is tripped co-incidentally with 100% load

rejection and generator speed rising to runaway speed. The voltage regulator will control

Page 74: FOR (3x5.65 MW) ANDHRA HYDRO-ELECTRIC PROJECT Document Excitation System.pdf · 1 himachal pradesh state electricity board limited bid documents for “static excitation system and

74

through different modes the voltage and / or current of the field of the generator.

Depending on the application, these modes can either be:

� Voltage regulation (Island mode).

� Droop regulation (Paralleled machines sharing the reactive current).

� VAR / Power factor (When connected to a grid).

6.3.1 Main features and functions

Main features

• Digital Signal Controllers (DSCs) shall be adopted in the main control unit of

excitation regulator, as the core chip. High-performance static CMOS technology

shall be implemented; the operating frequency can achieve 30 MHZ. The chip shall

have not only the data-processing capability but also the event-management ability

and embedded control functions, which shall improve the integration and reliability

of the system greatly.

• Ferro-electric memory (FRAM) with high-speed serial SPI interface shall be used for

storing required parameters. All of the parameters can achieve display real-time and

on-line modifying, and after modification the parameter can be preserved for a long

time from the effects of power down.

• Series communication port for communication with the host computer.

• Synchronous signal conditioning circuit, greatly reduce the interference by the signal

ditch.

• Three-phase full-bridge thyristor rectifiers with inversion function and high

efficiency hot-tube heat sink

• LED Push Buttons.

• Reliable AC, DC redundancy power supply.

• Independent dual hardware channel with automatic change-over function.

• Self-diagnosis and watch-dog.

• Test function to check the equipment even at generator standstill condition.

• Asynchronous interrupt programming method to avoid the faulty change over and

faulty trip by net interference. Update of the data acquisition, PID algorithm and

triggering angle calculation shall be fulfilled in less than 5 ms.

• Intelligent LCD display unit uses 16-bit MCU as the control core, adopts convenient

operation key and 192 X 128 dot-matrix LCD module. It shall provide a friendly

man-machine interface for users. Data displaying, parameter modifying and fault

recording of the excitation installation and the communication with host computer

can be realized through the interface.

Main functions

• Generator voltage regulating mode

• Field current regulating mode

• Constant power factor regulating mode

• Constant reactive power factor regulating mode

• Over-excitation limiting

• Under-excitation limiting

Page 75: FOR (3x5.65 MW) ANDHRA HYDRO-ELECTRIC PROJECT Document Excitation System.pdf · 1 himachal pradesh state electricity board limited bid documents for “static excitation system and

75

• Stator current limiter

• Field current limiter.

• Load angle limiter

• Line droop compensation

• Paralleling compensation

• Excitation fault supervision

• Under frequency limiter or V/Hz limiting

• De-excitation system

• Over voltage protection

• Voltage matching

• PT fault supervision

• Self start build up

• Series communication function

Auxiliary functions

• Power Supply Protection: Standby channel power supply fault alarm.

• Switch over from operating channel to standby channel alarm.

• Field Flashing Protection: Automatic cutoff on failure of flashing or flashing

overtime.

• Excitation Fault Protection: Switchover from operating channel to standby

channel, trip if switchover failed.

• Over-excitation and Under-excitation Protection

• V/Hz limitation

• Potential Transformer Failure Protection: Changeover from Auto channel to

manual Channel.

• Pulse Monitoring: Changeover from operation channel to standby channel.

• Auxiliary Supply Monitoring

Remote/Local control commands (the control push buttons)

• FIELD BREAKER ON (FCB ON)

• FIELD BREAKER OFF (FCB OFF)

• FLASHING ON

• AVR (AUTO) ON

• FCR (MANUAL) ON

• CH I ON

• CH II ON

• RAISE

• LOWER

• RESET

Status indicators and alarm signals to Control Room

• FIELD BREAKER ON

• FIELD BREAKER OFF

Page 76: FOR (3x5.65 MW) ANDHRA HYDRO-ELECTRIC PROJECT Document Excitation System.pdf · 1 himachal pradesh state electricity board limited bid documents for “static excitation system and

76

• PT FAILURE

• CONTROL BUS FAILURE

• OVER EXCITATION LIMITATION

• UNDER EXCITATION LIMITATION

Additional Features

• Auto tracking between excitation system operating modes

• Auto tracking between proposed excitation system units

• Sequence of events recording (SER)

• Oscillography

• Real time monitoring

• Internal testing provisions

• Password protection

• Firing module options

• Fast discharge circuit options

• Field Flashing the generator

6.3.2 Hardware Configuration of Voltage Regulator System:

Hardware channel shall consist of the following units: -

• Input adaptor unit,

• Active/ reactive transducer unit,

• Analog input unit,

• Input isolating unit,

• Output isolating unit,

• Digital input unit,

• Output unit,

• Central control unit,

• Pulse output unit,

• Keyboard and LCD display unit.

The input signals in input adaptor unit shall be generator terminal voltage (from VT),

generator current (from CT), field current and the output signals in the unit shall be the

conditioned input signals for sampling.

Active/reactive transducer unit shall be used to simulate the active and reactive

component of the generator current.

The analog input unit shall be used for generator voltage rectification and filtering,

synchronous signal pretreatment, frequency measuring signal generating, active/reactive

component adapting. The output of this unit shall be fed to the main central control unit.

Input isolation unit shall be used to isolate input signals such as generator status, control

operation

Digital input unit shall be used to isolate and convert the 24 V level signal (already

isolated) to 5 V level for CPU.

Page 77: FOR (3x5.65 MW) ANDHRA HYDRO-ELECTRIC PROJECT Document Excitation System.pdf · 1 himachal pradesh state electricity board limited bid documents for “static excitation system and

77

Digital output unit shall be used to opt-isolate CPU control and output signals.

Output isolating unit shall be used to isolate the signals from digital output unit via relays

for logic control circuit.

Central Processing Unit (CPU) shall be the core of the regulator. The following functions

shall be done here in this unit namely set-point value, PID filtering, trigger pulses,

channel follow-up, series communication, limitation and protection, parameter display,

parameter setting, parameter storage.

Pulse output unit shall be used to output trigger pulses to converter cubicles. The trigger

pulses shall be amplified in the final pulse unit in converter to trigger the thyristors in the

cubicles.

Keyboard and LCD display unit shall provide a friendly man-machine interface for users.

Data displaying, parameter modifying and fault recording of the excitation installation

and the communication with host computer can be realized through the interface.

The excitation cubicle shall be designed for local/remote control and shall include as a

minimum the following: -

• Pushbuttons: lamp test, reset, excitation ON, excitation OFF (with protection

cover)

• Switches: voltmeter phase switch (if applicable), AUTO/MANUAL mode switch

(with centre position), AVR Raise/Lower (with centre position), Remote/Local

control key selector switch.

The selection between the local or remote control mode shall be done by means of a key

protected switch. The key can only be removed in the remote position, and this function

shall disable the front door pushbuttons in the normal mode of operation. During

commissioning if specific operations such as maintenance are required, the key shall be

necessary to enable local control mode. This will, in turn, disable the remote I/O.

6.3.3 Manual Channel (Field Current Regulator):

The manual control mode shall be used as test facility (e.g. during commissioning or

maintenance of the equipment) or as back-up control mode in case of incorrect of the

AVR (e.g. loss of actual value, due to potential transformer failure)

When operating in the manual control mode, excitation controls the field current of the

synchronous machine by means of a field current regulator FCR. The actual value of the

field current it is taken inside of the excitation cabinet in order to ensure a control loop

which is independent of external measuring circuits and/or transducers.

The set-point function for the manual control mode has the similar functions as the set-

points as well as two different running times can be adjusted. When operating in manual

control mode, the set-point for field current may be controlled by raise of lower

commands.

An immediate reset input is provided in order to avoid over voltages caused by reactive

load rejections while operating in the manual control mode. If the machine breaker trips,

a pulse command is applied to the reset input which sets the field current immediately

Page 78: FOR (3x5.65 MW) ANDHRA HYDRO-ELECTRIC PROJECT Document Excitation System.pdf · 1 himachal pradesh state electricity board limited bid documents for “static excitation system and

78

back to pre-set value which normally corresponds to 90..100% of the no-load field

current of the synchronous machine.

The resulting error signal at the output of the set-point is applied to a filter circuit with PI

characteristics. The optimum settings of this PI-Filter are achieved by setting the DC

gain Vo, the proportional gain Vp and the integral time constant Ta.

6.3.4 Follow-up Control :

An automatic follow-up control ensures a surge-free change-over from automatic (AVR)

to manual control mode. When operating in the AVR mode, the difference signal

between automatic channel output and manual control output is used for the automatic

follow-up. This difference signal is also used as a feedback signal for the channel which

is presently not in operation and therefore in open loop condition. This is necessary for a

stable balancing between the AVR and the FCR.

In a double channel system the inactive channel follows automatically the leading

channel.

The AVR shall be provided with over & under excitation limiters. The intervention of

the limiters shall not cause perceptible deviations or oscillations of the generator active

& reactive power. Such devices shall allow the regulator to reduce the excitation voltage

to zero in order to prevent over voltage in case of operation, under line reactive load

conditions and over speeding of the unit. The characteristics of the under excitation

limiting curve shall match the static and dynamic stability curves of the generator.

The field current limiter shall act on AVR with a time delay so as not to disturb transient

response of the system during voltage dips/faults. A slip stabilizer unit shall be provided

to surpass the low frequency power oscillation during the operative conditions.

The AVR shall be equipped with a sensitivity-adjusting device and with adjustable

voltage droop compensation (compounding). The voltage regulating system shall include

device for improving the damping of active electromechanical oscillations. These

devices shall operate to supplement the voltage regulation action by addition of an

additional control signal into the excitation system input. This supplemental input signal

shall influence the excitation system a.c. to cause a change in field current of the

machine for stabilised operation.

After, the generator voltage attaining initial maximum value neglecting the instantaneous

rises following any load rejection upto 100% of rated load, DVR shall restore the

generator terminal voltage to a value not more than 10% above or below the voltage

being held before load rejection and shall maintain the voltage within these limits

throughout the period of the generator over speed.

The voltage setting device provided shall be of the solid-state digital type having a range

of + 10% for local & remote control and indication. For testing purposes setting of 10%

to 115% shall be adjustable at the AVR cubicle.

The excitation system shall be designed for manual and automatic operation with

provision for manual to auto changeover and vice versa. The change over from automatic

to manual control shall be performed automatically following a failure of the regulator

Page 79: FOR (3x5.65 MW) ANDHRA HYDRO-ELECTRIC PROJECT Document Excitation System.pdf · 1 himachal pradesh state electricity board limited bid documents for “static excitation system and

79

when operating on automatic control. The generator voltage shall be controlled with in

the range of + 10% of rated voltage. A static follower shall be provided so that, in the

event of change over from automatic to manual control or vice versa, it prevents the

excitation current from deviating more than 5% of no load excitation current under

steady state conditions. An alarm and visual indication shall be provided to indicate

change from "AUTO" to 'MANUAL'. The automatic and manual control circuit shall be

fully independent. Local & remote control shall also be possible.

7 Field Flashing Equipment: -

In order to over-come the deficiency of permanent magnetism when starting the

machine, initial excitation shall be applied to the field winding. The respective power

shall be derived from the a.c. supply system via transformer and rectifier. All equipment

for automatic field flashing i.e. circuit breakers, blocking diodes, control devices,

protection etc. shall be included. Provision shall also be made for field flashing through

station batteries as stand by arrangement. The field flashing circuit shall get disconnected

when 70% of the rated voltage is achieved at the generator terminals and normal

excitation circuit takes over.

The kVA rating and voltage ratio of field flashing transformer (forming part of supply)

and requirement of DC for field flashing shall be indicated in the bid alongwith other

details. While using batteries for field flashing the corresponding over voltage protection

shall be provided as a part of excitation equipment.

The system shall also cope with the requirements of excitation necessary for test runs.

8 De-Excitation System:-

The existing De-Excitation Systems are in-operation and are in healthy conditions. The

Tenderer shall quote the prices of the equipment excluding the cost of De-Excitation

System i.e. field circuit breakers & discharge resistors. In case bidders recommend to

replace these field circuit breakers & discharge resistors in case of non-compatibility

with their system, the price of these equipment/components may be quoted as optional

items. The name plate specifications of the existing field circuit breakers & discharge

resistors is as under: -

Sr.No Description As per existing detail

1. Field Circuit Breaker

i. Type of field breaker. UNILEC Field Circuit Breaker

ii. Rating of field breaker 80A- to 3000 A.

iii. Make BHEL.

iv. Auxilary contacts for field breaker 6NO + 6NC

v. Control Volatage of field breaker. 220V DC

2. Discharge Resister.

i. Type of Discharge resister NER/126

Page 80: FOR (3x5.65 MW) ANDHRA HYDRO-ELECTRIC PROJECT Document Excitation System.pdf · 1 himachal pradesh state electricity board limited bid documents for “static excitation system and

80

ii. Rating 126A

iii. Resistance in Ohm 1.0

To achieve a quick suppression of the generator field and thus the voltage, a discharge

resistor (voltage dependent type) shall shunt the field winding. Field circuit breakers

shall be provided for isolation of field circuit for ensuring definite disconnection of field

from the supply source and subsequent discharge of energy in the field circuit.

The energy shall be dissipated through a field discharge resistor, which shall be

connected across the field by the operation of field circuit breaker. The volt-ampere

characteristic of the discharge resistor shall permit a quick field current damping. The

normal operation of the circuit breaker shall be automatic through sequential controller.

The circuit breaker shall also be manually operated by means of control switches

provided on excitation panel.

9 Excitation Control Cubicle:-

The excitation control and voltage regulating equipment shall be suitable for manual and

automatic control and shall comprise of all control and supervisory devices required for

the operation of the entire excitation system. Suitable circuit containing position switches

and internal wiring within the equipment required to give correct operation & indication

and all other equipment necessary for the operation shall be provided. The necessary

relays and contactors for initiating and performing the automatic transfer of the generator

starting field-flashing source to the normal supply source (power rectifier) when the

generator terminal voltage has increased to sufficient value shall also be provided. The

minimum requirements for instrumentation are: -

- A.C. Generator Output voltage

- D.C. Field current

- D.C. Field Voltage

- Set point indicator for Auto control

- Delta voltage between auto and manual control.

- Power factor.

The digital voltage regulating and excitation control equipment shall be capable to

communicate via serial interface and the field bus.

10 Protection of Static Excitation Equipment:-

The excitation equipment shall be protected against internal faults, failure of thyristor

bridges, cooling fans etc. for which contacts shall be provided for alarm and shutdown of

the unit. The items of protection covered shall be the following but not limited to: -

- Excitation equipment internal faults

- Over current protection for overload and short circuit protection of the excitation

transformer and rectifiers.

- Over voltage protection for detection of sustained field over -voltage.

- Loss of regulator DC power.

Page 81: FOR (3x5.65 MW) ANDHRA HYDRO-ELECTRIC PROJECT Document Excitation System.pdf · 1 himachal pradesh state electricity board limited bid documents for “static excitation system and

81

- Failure of AVR.

- Individual cooling fan failure.

- Cooling fan failure (main and reserve)

- Failure of thyristor firing circuit.

- Current asymmetry protection (more than two stacks faulty).

- Loss of regulator D.C. power.

- Rectifier cubicle exit air high temperature.

- Excitation transformer winding temperature.

- Preventing of over fluxing of the transformer.

- Operation at maximum excitation limit.

- Operation at minimum excitation limit

- Operation of slip stabilizing unit.

- Current asymmetry, one thyristor stack faulty.

- Failure of field flashing circuit equipment.

- Loss of sensing.

- Field winding over temperature protection.

11 Excitation Connection: -

Power cable connections between the generator slip rings and the excitation cubicle shall

be provided. The power cables shall be of adequate copper cross section to continuously

carry the rated current of the excitation system and the maximum current. They shall be

made of highly flexible conductors and the cable insulation shall be of the heat resistant

type, taking into account the maximum temperature rise of 50 oC at 40 oC ambient

temperature in the slip ring compartment. The cables shall be adequately spaced and

supported with consideration to the electromechanical forces involved and designed to

prevent undue heating during continuous operation.

12 Communication Channels:

The AVR shall be capapble to communicate to a PC with suitable port for local

programming, mtering and communication along with complete window based software

equipment shall be provided with RS- 232 / RS-485 port for PID selelction program that

allow the user to selelct the stability settings and software.

13 Wiring Requirements

Excitation system internal wiring shall be carried out according to the following:

• Cables- Flexible multi-strand copper wire

• Insulation- Polyethylene insulation

• Terminals- Crimped, insulated sleeves on each end of wire

• Maximum number of 2 wires per terminals or pins

• Cable marking- Markers on each end of every wire, made with individual color

coded sleeves corresponding to the drawings.

• EN 60204-1 Compliant.

Bidders are requested to submit the proper documentation/evidence to justify the

achievement of afore-mentioned technical specifications, features and functions.

Page 82: FOR (3x5.65 MW) ANDHRA HYDRO-ELECTRIC PROJECT Document Excitation System.pdf · 1 himachal pradesh state electricity board limited bid documents for “static excitation system and

82

14 INSPECTION, TESTING AND COMMISSIONING

The whole of the Works supplied under the Contract shall be subject to inspection and test

by the purchaser or their Representative during manufacture, erection and after completion.

The inspection and tests shall include, but not be limited to, the requirements of this Section

of the Specification.

The Contractor shall provide all appliances, apparatus, supervision, labor and services

necessary to carry out all tests unless specifically stated otherwise.

The costs of all tests, including traveling expenses, cost of accommodation, per-diem and all

other relevant expenses for the inspecting personnel who will attend the factory tests shall

be borne by the Contractor.

The scope of the commissioning program includes the Site testing of all excitation

equipments. Testing of instrumentation and certification of their accuracy is also to be

provided.

The objectives of commissioning work, prior to the successful energisation of Plant at full

voltage and connection to the system, are the following:

- Confirm the integrity (correctness) of installation.

- Confirm the integrity of insulation, connections and phasing.

- Ensure proof of equipment characteristics.

- Review workmanship.

- Confirm the correct implementation of the design.

- Check equipment ratings.

- Check settings and operation of control and protection equipments.

- Check and measure resistivity of earthing grid and earthing system.

14.1 TESTS AT MANUFACTURER’S WORKS

14.1.1 General

Where no specific test is specified, then the various items of materials and equipment

shall be tested in accordance with the relevant British, IEC, or American Standards.

Where no appropriate standard is available, tests shall be carried out in accordance with

the maker's standard practice, which must meet with the approval of the Purchaser.

At least fourteen days notice in writing or by telefax shall be given to the Purchaser of

the readiness of plant for test or inspection and every facility shall be provided by the

Contractor and sub-Contractor(s) to enable the Purchaser or their Representative to carry

out the inspections and witness the tests. This includes progress, test rig and packing

inspection.

Inspection of equipment will not be carried out unless copies of the relevant sub-orders,

drawings and test procedures have been approved by the Purchaser.

No equipment shall be packed, prepared for shipment, or dismantled for the purpose of

packing for shipment, unless it has been satisfactorily inspected, or inspection has been

waived by the purchaser.

Functional electrical and mechanical tests shall be carried out on the completed plant

after assembly in the Works. The extent and method of recording the results shall be

agreed by the Purchaser in sufficient time to enable the tests to be satisfactorily

witnessed or to make any change to the proposed program of tests.

All instruments and apparatus used in the performance of the tests shall be to the

approval of the Purchaser and, if required by the Purchaser, shall be calibrated to an

Page 83: FOR (3x5.65 MW) ANDHRA HYDRO-ELECTRIC PROJECT Document Excitation System.pdf · 1 himachal pradesh state electricity board limited bid documents for “static excitation system and

83

agreed standard at a laboratory of national standing to be nominated by the Contractor

and approved by the Purchaser.

The cost of carrying out such calibration shall be borne by the Contractor in all cases.

The cost of making any test shall be borne by the Contractor. This shall apply to tests

performed at the site or elsewhere.

Under completion of manufacture at the factory the Purchaser will depute his personnel

to the Contractor’s factory to witness the fabrication, assembly and testing of any or all

parts of major equipment. The number of the Purchaser's personnel and equipment to be

witnessed will be as per explained in the special condition of Contract.

Following tests shall be conducted on static excitation system .

14.1.2 TEST AT WORKS :-

(a) Routine Tests At works :-

• Visual inspection for mechanical assembly on AVR, converter, field breaker &

wiring check.

• High voltage test

• Checking of control & regulation signal flow including electronic modules by

simulation.

• Power supply check.

• Light load test on each thyristor bridge.

• Control sequence interlock & protection tests on integrated equipment with all

cubicles interconnected as schematic diagram except excitation transformer

cubicles.

• Routine tests on excitation transformer as per IEC-726 or equivalent standards.

(b) Type Test At Works :

• Heat run test on thyristor bridge on one set of static excitation equipment.

• Heat run test on one excitation transformer.

14.1.3 Test Certificates

Within 30 days of the completion of any test, triplicate sets of all principal test records,

test certificates and performance curves shall be supplied to the Purchaser.

These test records, certificates and performance curves shall be supplied for all tests,

whether or not the Purchaser or his Representative has witnessed them. The information

given on such test certificates and curves shall be sufficient to identify the material or

equipment to which the certificate refers and should also bear the Contract reference

title. Specified requirements shall be shown on each certificate for comparison with

actual test results.

When all equipment has been tested and test certificates from all Works and Site tests

shall be compiled by the Contractor into volumes and bound in an approved form

complete with index. Two copies of each volume shall be supplied to the Engineer and

five copies to the Purchaser.

14.1.4 Type Tests

Page 84: FOR (3x5.65 MW) ANDHRA HYDRO-ELECTRIC PROJECT Document Excitation System.pdf · 1 himachal pradesh state electricity board limited bid documents for “static excitation system and

84

Type tests are required to prove the general design of the equipment and the Contractor

may submit test certificates of tests, which have been carried out on identical equipment.

Notwithstanding any provision in a BS, IEC or ANSI Standard, the Purchaser shall have

the right to accept such certificates in lieu of the specified type tests or to reject them.

The type tests prescribed shall be carried out at the Contractor's cost in all cases where

such certificates are not available or are rejected.

14.1.5 Safety Procedures:

The Contractor shall share the responsibility for safety procedures with the Purchaser.

The Contractor shall establish and implement a work permit and tagging system and

associated safety procedures (subject to the review of Purchaser) for all equipment,

systems and areas not covered by the Purchaser’s safety procedures.

The Purchaser will assume responsibility for the establishment and implementation of

tagging, safety and work permit procedures for the protection of personnel and

equipment, as soon as equipment and systems are connected to or are energized able

from the existing system.

14.2 Training of Staff:

14.2.1 The Contractor shall plan for the Purchaser’s staffs’ participation, either continuously or

on a regularly recurring basis, in the commissioning work and:

Allow the Purchaser staff to become familiar with the operating and maintenance aspects

of the new equipment.

Maintain a continuing assessment with the Purchaser of the precautions required in, or

possible consequences of, initial energisation of equipment.

Allow for the above two necessary objectives in the preparation of schedules.

The Contractor shall station at site at least one technical expert for a minimum of

required period continuously after commissioning to rectify any problems as well as train

the Purchaser’s attending staffs. If required the length of his stay shall be extended as per

requirement depending upon the seriousness of the problem encountered, which shall be

at the Purchaser’s discretion.

14.2.2 A Special Training class at site for seven days shall be conducted by the Contractor for

giving in detail of the Equipment in view of maintenance purpose. The refreshment

during training for above 7 Engineers/Technical personnel shall be on the account of the

Contractor.

14.3 COMMISSIONING STAFF

The Contractor shall provide commissioning personnel including skilled and unskilled

labor as required. `Submit a list with names, experience and proposed duration of the

presence of key personnel on Site, consistent with the construction schedule, at the same

time as the commissioning program. The refreshment including paying for above

Ensure that only staff assigned to commissioning fulfills that duty for the duration of the

assignment.

Ensure that commissioning staff has authorization, and the competence, to undertake

minor repairs or to make temporary redesigns and to reconnect systems to meet the

specified system performance to preclude delays in energization and putting into

commercial service of any part of the works.

The Contractor should arrange for the manufacturer's commissioning Engineer to carry

out the field test & commissioning of main equipment like AVR, FCB, Excitation

Transformer and Surge Protection Devices etc. Such personnel should certify the

completeness of such commissioning of the Equipments.

Page 85: FOR (3x5.65 MW) ANDHRA HYDRO-ELECTRIC PROJECT Document Excitation System.pdf · 1 himachal pradesh state electricity board limited bid documents for “static excitation system and

85

14.4 Test Equipment

The Contractor shall ensure that all instruments, tools and other equipment required for

testing and commissioning are available on site, ensure that the test equipment is of

satisfactory quality and condition and, where necessary, is calibrated by an approved

authority or standard.

Make arrangements for the provision of power supplies for testing with necessary vector

configuration, voltage and current rating.

14.5 Commissioning Program

Prepare a commissioning program for approval by the Contractor and for incorporation

into the Project master construction program. Allocate adequate time in this program to

permit full commissioning of all components.

Carry out all testing during normal working hours as for as is practicable. Tests, which

involve existing apparatus and system outages, may be carried out outside normal

working hours. Give to the Purchaser sufficient notice to allow for the necessary outage

arrangements to be made in conformity with the testing program.

Note that no tests listed in the agreed program will be waived except upon the instruction

or agreement of the Purchaser in writing.

14.6 Test Procedures

The following basic tests shall be carried out in addition to the other required tests:

- Measurement of insulation resistance.

- Electrical Operation Test

- Characteristic Test

14.7 Requirements for Field Tests

• Visual inspection.

• Dielectric test on excitation transformer.

• Pre-commissioning checks for control logic and electronic modules.

• Voltage build-up test in auto and manual mode of control.

• Test for determining control range in auto and manual mode of operation.

• Adjustment of AVR.

• Step response test for checking the response of AVR in auto control.

• Step response test for limiters.

• Tests on maximum excitation limiter.

• Tests of volts per cycle regulation.

• Minimum excitation limiter tests.

• Overall response of machine and excitation system voltage changes.

• Excitation system time response.

• Load rejection tests.

Page 86: FOR (3x5.65 MW) ANDHRA HYDRO-ELECTRIC PROJECT Document Excitation System.pdf · 1 himachal pradesh state electricity board limited bid documents for “static excitation system and

86

• Effectiveness of voltage regulator forcing action in de-magnetising the main regulator

field.

• Steady state accuracy of voltage control from no load to full load.

The field tests shall be carried out in the presence of Purchaser under the following

conditions:

The field tests shall be carried out by the Contractor after adjustment of all the equipment

have been completed.

Expandable and lead wires and other materials required for the field tests shall be

provided by the Contractor. The Contractor shall be responsible for providing all

measuring instruments test equipment and tools required for the tests.

Preparation of the test record sheets and test reports shall be the responsibility of the

Contractor and the results of the field tests shall be submitted by the Contractor to

Purchaser for approval.

Measurement of insulation resistance of the equipment shall be performed by at least

1000 V Megger.

After completion of the measurement of insulation resistance mentioned above,

Electrical Operation Tests shall be performed by the normal operation voltage of the

existing power system in accordance with the following procedure:

Submit test procedures, consisting of detailed test methods and samples of the related

test record forms, for all equipment to be tested, to the Purchaser for approval at the

same time as the commissioning program. Strictly adhere to these procedures for the

commissioning tests.

14.8 Records

Maintain an up-to-date record of all commissioning activities on site.

Record the results of the tests clearly on forms approved by the Purchaser and with clear

references to the equipment and items tested, so that the record can be used as the basis

for maintenance tests during the working life of the equipment. Submit the required

number of site test result records to the Purchaser as soon as possible after completion of

the tests.

Record the details of the test equipment and instruments used in the test sheets, in those

cases where the instrument or equipment characteristics can have a bearing on the test

results.

14.9 “As Built” Drawings

Keep an ongoing record of all changes on a master set of drawings. Produce and supply a

minimum of two complete sets of marked-up “As Constructed” drawings before leaving

the Site. Correct and re-issue the original drawings as soon as possible as per this

specification.

14.10 Test Methods

Carry out all necessary tests for commissioning the substations. The following clauses

detail tests which are considered to represent the minimum required in addition to those

specified under the appropriate IEC Publications, other approved standards and the

manufacturer’s instructions for each item of equipment.

Strictly adhere to the methods of testing approved by the Purchaser.

a) Site and Commissioning Tests for Main and Auxiliary Equipment

General Checks

Page 87: FOR (3x5.65 MW) ANDHRA HYDRO-ELECTRIC PROJECT Document Excitation System.pdf · 1 himachal pradesh state electricity board limited bid documents for “static excitation system and

87

Make a general check of all main and auxiliary equipments. Include a check of the

completeness, correctness and condition of ground connections, labeling, arcing ring,

paint surfaces, cables, wiring, pipe work, valves, blanking plates and all other auxiliary

and ancillary items.

Check for tightness of nuts and bolts and that insulators are clean and free from external

damage. Check that loose items, which are to be handed over to the Purchaser, e.g.,

tools, spares, are in order and are correctly stored or handed over.

AVR, Field Cabinets and Excitation Transformers

Carry out general testing and inspection, as referred to above. The Contractor shall also

carry following tests: a) AVR mode testing b) FCR mode testing c) VAR testing c) PF

control mode testing d) Voltage Build-up and perform timing tests on field circuit

breakers e) AC and DC circuits associated with stand by auxiliary supplies f) Protection

Function testing g) Discharge Circuitry Testing.

Carry out insulation secondary circuits tests with a 1000 V DC megger before and after

high voltage testing.

Check shutters, interlocking, earth procedures and the interchangeability of components.

Interlocking

Check all interlocking arrangements, both electrical and mechanical.

b) Earthing System

Carry out the tests and measurements in accordance with IEEE Standard 80.

c) Particular Constraints and Special Tests

The Contractor shall be prepared to cooperate with any special tests requested by the

Purchaser.

14.11 Excitation System Documentation :

The Documentation system shall be delivered with 2 sets of documentation, each set

containing:

• Instruction manual of each major component.

• Drawing package containing mechanical and electrical drawings, interconnection

drawing and equipment lists.

• Instruction manual of the complete system.

• Storage instructions details.

• Recommended Spare Parts of the Excitation System (Detail List)

• PC Software for all manufactured digital devices.

All the above shall be also included on a CD.

The drawings are subjected to approval prior to the commencement of the manufacturing

works.

Language of documentation

All the Excitation system documentation shall be supplied in the English language.

Page 88: FOR (3x5.65 MW) ANDHRA HYDRO-ELECTRIC PROJECT Document Excitation System.pdf · 1 himachal pradesh state electricity board limited bid documents for “static excitation system and

88

Page 89: FOR (3x5.65 MW) ANDHRA HYDRO-ELECTRIC PROJECT Document Excitation System.pdf · 1 himachal pradesh state electricity board limited bid documents for “static excitation system and

89

ANNEXURE-I

SCHEDULE OF REQUIREMENT AND PRICES

Name of work:

Sr.

no

Description of material Qty Ex-

works

price/

Excise

duty on

Ex-

works

price

Sales tax

& surcharge

on ST if any

on Ex works

price + ED

per no.

Freight

charges

per set

Comprehensive

Insurance

per set

Entry Tax

on Ex

works

Price +

Excise

duty +

sales Tax

per no.

Total

FOR

price

of

each.

4. 5. 6. 7. 8. 9. 10. 11. 12. 13.

1 Design, manufacture, shop assembly &

testing, comperhensive insurance, delivery,

erection, testing & commissioning at site,

field acceptance tests of static excitation

system before handing over to the

owner/HPSEB Ltd. and guaranteed for two

years of three (3) numbers static excitation

and Digital AVR systems complete with

accessories, equipment, devices, instruments,

cabling and wiring etc. including all services,

labour, tools and tackles in all respects.

3 Sets

2 Dismantling of existing panel and erection of

new panels, testing and commissioning

of new panels.

3 Jobs

3 Any other items which are left

out but necessary for the SES to perform

successfully should also be included.* Refer

detailed Technical

4 Design, manufacture, shop assembly &

testing, comperhensive insurance, delivery,

erection, testing & commissioning at site,

field acceptance tests of Excitation

3 Nos.

Page 90: FOR (3x5.65 MW) ANDHRA HYDRO-ELECTRIC PROJECT Document Excitation System.pdf · 1 himachal pradesh state electricity board limited bid documents for “static excitation system and

90

Transformer (Optional)

5 Design, manufacture, shop assembly &

testing, comperhensive insurance, delivery,

erection, testing & commissioning at site,

field acceptance tests of field circuit breakers

(Optional)

3 Nos.

6 Design, manufacture, shop assembly &

testing, comperhensive insurance, delivery,

erection, testing & commissioning at site,

field acceptance tests of discharge resistors

(Optional)

3 Nos.

DATE SIGNATURE :

PLACE : NAME :

SEAL:

DESIGNATI0N : Notes: - 1. The prevailing rates of EXCISE DUTY shall be specifically mentioned on each item. 2. The prevailing rate of central sales tax against form C shall be clearly mentioned. 3. The freight charges shall be separately quoted for each item. 4. The insurance charges shall be separately quoted for each item. 5. The tenderer is required to specifically state in his offer, if quoted prices are inclusive or exclusive

of amount of entry tax.

Signature of the Tenderer

Page 91: FOR (3x5.65 MW) ANDHRA HYDRO-ELECTRIC PROJECT Document Excitation System.pdf · 1 himachal pradesh state electricity board limited bid documents for “static excitation system and

91

ANNEXURE-II

TECHNICAL PARAMETERS OF SEE & AVR

1. Accuracy of voltage regulation in normal operating

condition.

:

2. Range of voltage settings :

• Auto Mode :

• Manual mode :

• For testing purpose in manual mode :

3. Voltage regulation from no-load to full load :

4. Response time :

5. Operating frequency :

6. Dead band :

7. Range of Reactive droop adjustment :

8. Ambient conditions

• Temperature : Up to 50 deg. Celsius

• Humidity : Upto 95% ( non-condensing)

9. Power for excitation equipment :

10. Type of converter :

11. Protection class of all panels :

Note :- All other technical parameters as per tender documents shall be taken care of while designing

of the equipment.

Certified that the offered values are within limits of relevant IEC/IS specification. Dated: Signature Place: Name & Designation .

Page 92: FOR (3x5.65 MW) ANDHRA HYDRO-ELECTRIC PROJECT Document Excitation System.pdf · 1 himachal pradesh state electricity board limited bid documents for “static excitation system and

92

Annexure-III Schedule of Spare Parts

Tenderer must quote for the set of recommended spare parts for five years trouble free service for each item. Sr. No. Description Qty. Unit Price Total Price

Signature of the Tenderer

Page 93: FOR (3x5.65 MW) ANDHRA HYDRO-ELECTRIC PROJECT Document Excitation System.pdf · 1 himachal pradesh state electricity board limited bid documents for “static excitation system and

93

ANNEUXRE-IV

DELIVERY & COMPLETION PERIOD

Sr. No. Item

Period in days

1. Period required to commence supply from the date of Letter of Intent, LOI

2. Period for supplying drawings for engineer’s approval

3. Period when equipment will be ready for inspection before dispatch

4. Period when the equipment will received FOR at 3 x 5.65 MW Andhra power house site.

5. Period by which all the existing equipment will be dismentalled and completely erected, tested and commissioned.

Signature of the Tenderer