Sl. No Description Source Building Destination Building Source of Panel Number Destination Panel Number Cable Size Length in Meters Remarks
1 HT cable -1 Boiler Fuel Oil Pump House SS1A1 FOT 1A 3 C x 240 Sq.mm 1200
2 HT cable - 2 Boiler Fuel Oil Pump House SS1A2 FOT 1B 3 C x 240 Sq.mm 1200
3 LT Power Cable -1 Boiler Fuel Oil Pump House DCDB FOS Switch gear-1 2F 2 CX 16 Sq.mm 1200
4 LT Power Cable -2 Boiler Fuel Oil Pump House Unit Service Board (USB)-1 FOS Switch gear-1 8F 2 CX 16 Sq.mm 1100
5 LT Power Cable -3 Boiler Fuel Oil Pump House Station Service Board (SSB) FOS Switch gear-1 8F 2 CX 16 Sq.mm 1100
6 LT Power Cable -4 Boiler Fuel Oil Pump House Unit Service Board (USB)-1 FOS Switch gear-1 15F 2 CX 16 Sq.mm 1100
7 LT Power Cable -5 Ultratech Ash handling System Dry ash silo area ultratech MCC dry ash silo-1 3.5 CX 185 Sq.mm 700
8 LT Power Cable -6 Ultratech Ash handling System Dry ash silo area ultratech MCC dry ash silo-1 4 CX 4 Sq.mm 700
9 LT Power Cable -7 Ultratech Ash handling System Dry ash silo area ultratech MCC dry ash silo-1 4 CX 4 Sq.mm 700
10 LT Power Cable -8 Ultratech Ash handling System Dry ash silo area ultratech MCC dry ash silo-1 4 CX 2.5 Sq.mm 700
11 LT Power Cable -9 Ultratech Ash handling System Dry ash silo area ultratech MCC dry ash silo-1 4 CX 2.5 Sq.mm 700
12 LT Power Cable -10 Ultratech Ash handling System Dry ash silo area ultratech MCC dry ash silo-1 4 CX 2.5 Sq.mm 700
13 LT Power Cable -11 Ultratech Ash handling System Dry ash silo area ultratech MCC dry ash silo-1 4 CX 2.5 Sq.mm 700
14 LT Power Cable -12 Ultratech Ash handling System Dry ash silo area ultratech MCC dry ash silo-1 4 CX 2.5 Sq.mm 700
15 LT Power Cable -13 Ultratech Ash handling System Dry ash silo area ultratech MCC dry ash silo-2 4 CX 2.5 Sq.mm 700
16 LT Power Cable -14 Ultratech Ash handling System Dry ash silo area ultratech MCC dry ash silo PDB 4 CX 16 Sq.mm 700
17 LT Power Cable -15 ESP Fuel Oil Pump House ESP MCC FOS Switch Gear-1 3C X 35 Sq.mm 900
18 Control Cable -1 Ultratech Ash handling System Dry ash silo area ultratech MCC dry ash silo-1 19C X 1.5 Sqmm 700
19 Control Cable -2 Ultratech Ash handling System Dry ash silo area ultratech MCC dry ash silo-1 19C X 1.5 Sqmm 700
20 Control Cable -3 Ultratech Ash handling System Dry ash silo area ultratech MCC dry ash silo-1 19C X 1.5 Sqmm 700
21 Control Cable -4 Ultratech Ash handling System Dry ash silo area ultratech MCC dry ash silo-1 19C X 1.5 Sqmm 700
22 Control Cable -5 Boiler Fuel Oil Pump House Auxiliary Control Board (ACB) FOS Switch gear-1 2F 7C X 2.5 Sqmm 1100
23 Control Cable -6 Boiler Fuel Oil Pump House Auxiliary Control Board (ACB) FOS Switch gear-1 2F 4 CX 2.5 Sq.mm 1100
24 Control Cable -7 Boiler Fuel Oil Pump House Auxiliary Control Board (ACB) FOS Switch gear-1 2F 4 CX 2.5 Sq.mm 1100
25 Control Cable -8 Boiler Fuel Oil Pump House Auxiliary Control Board (ACB) FOS Switch gear-1 2F 4 CX 2.5 Sq.mm 1100
26 Control Cable -9 Boiler Fuel Oil Pump House DAS Panel FOS Switch gear-1 2F 2CX 1 Sq.mm 1100
27 Control Cable -10 Boiler Fuel Oil Pump House Auxiliary Control Board (ACB) FOS Switch gear-1 2F 4C X 1 Sq.mm 1100
28 Control Cable -11 Boiler Fuel Oil Pump House Auxiliary Control Board (ACB) FOS Switch gear-1 3F 3C X 2.5 Sq.mm 1100
29 Control Cable -12 Boiler Fuel Oil Pump House DAS Panel FOS Switch gear-1 3F 2CX 1 Sq.mm 1100
30 Control Cable -13 Boiler Fuel Oil Pump House Auxiliary Control Board (ACB) FOS Switch gear-1 8F 4C X 2.5 Sqmm 1100
31 Control Cable -14 Boiler Fuel Oil Pump House Auxiliary Control Board (ACB) FOS Switch gear-1 8F 7C X 2.5 Sqmm 1100
32 Control Cable -15 Boiler Fuel Oil Pump House DAS Panel FOS Switch gear-1 8F 2C X 2.5 Sqmm 1100
33 Control Cable -16 Boiler Fuel Oil Pump House Auxiliary Control Board (ACB) FOS Switch gear-1 14F 3C X 2.5 Sq.mm 1100
34 Control Cable -17 Boiler Fuel Oil Pump House DAS Panel FOS Switch gear-1 14F 5C X 2.5 sq.mm 1100
35 Control Cable -18 Boiler Fuel Oil Pump House DAS Panel FOS Switch gear-1 14F 5C X 2.5 sq.mm 1100
Volume - II A Lead Specification
(Contract Document) Section -
XIV , Rerouting / Relocating of
Existing Facilities.Clause :
2.01.00 Rerouting of pipes &
cable Racks from Boiler to Fuel
Oil Pump House.
Annexure - B
PROJECT : IB THERMAL POWER STATION 2 X 660 MW UNITS 3 & 4
TITLE : EXISTING PLANT UNIT 1 &2 CABLE REROUTING DETAILS REQUIRED
The Follwing Document for Existing Plant for 2 X 210 MW Unit 1 & 2 are required for Rerouting of Power & Control Cables.
1) Source & Destination of Building & Panel Numbers
2) Panel, JB's and Local Panels ( if any ) General arrangement drawing, Internal arrangement drawings and Termination details of these Panels.
3) Cable schedule (for Cable Sizing)
Sl. No Description Source Building Destination Building Source of Panel Number Destination Panel Number Cable Size Length in Meters Remarks
Annexure - B
PROJECT : IB THERMAL POWER STATION 2 X 660 MW UNITS 3 & 4
TITLE : EXISTING PLANT UNIT 1 &2 CABLE REROUTING DETAILS REQUIRED
The Follwing Document for Existing Plant for 2 X 210 MW Unit 1 & 2 are required for Rerouting of Power & Control Cables.
1) Source & Destination of Building & Panel Numbers
2) Panel, JB's and Local Panels ( if any ) General arrangement drawing, Internal arrangement drawings and Termination details of these Panels.
3) Cable schedule (for Cable Sizing)
36 Control Cable -19 Boiler Fuel Oil Pump House DAS Panel FOS Switch gear-1 14F 5C X 2.5 sq.mm 1100
37 Control Cable -20 Boiler Fuel Oil Pump House DAS Panel FOS Switch gear-1 14F 19C X 2.5 Sq.mm 1100
38 Control Cable - 21 Boiler Fuel Oil Pump House DAS Panel FOS Switch gear-1 15F 2C X 1 Sq.mm 1100
39 Control Cable - 22 Boiler Fuel Oil Pump House Auxiliary Control Board (ACB) FOS Switch gear-1 15F 7C X 2.5 Sqmm 1100
40 Control Cable - 23 Boiler Fuel Oil Pump House Auxiliary Control Board (ACB) FOS Switch gear-1 15F 4C X 2.5 Sqmm 1100
41 Control Cable - 24 Boiler Fuel Oil Pump House Auxiliary Control Board (ACB) FOS Switch gear-1 15F 4C X 2.5 Sqmm 1100
42 Control Cable - 25 Boiler Fuel Oil Pump House Auxiliary Control Board (ACB) FOS Switch gear-1 15F 4C X 2.5 Sqmm 1100
43 Control Cable - 26 Boiler Fuel Oil Pump House Auxiliary Control Board (ACB) FOS Switch gear-1 15F 4C X 1 Sq.mm 1100
44 Control Cable - 27 Boiler Fuel Oil Pump House DAS Panel FOS Switch gear-1 14R 4C X 1 Sq.mm 1100
45 Control Cable - 28 Boiler Fuel Oil Pump House DAS Panel FOS Switch gear-1 14R 5C X 2.5 sq.mm 1100
46 Control Cable - 29 Boiler Fuel Oil Pump House DAS Panel FOS Switch gear-1 14R 7C X 2.5 Sqmm 1100
47 Control Cable - 30 Boiler Fuel Oil Pump House DAS Panel FOS Switch gear-1 14R 4C X 2.5 Sqmm 1100
48 Control Cable - 31 Boiler Fuel Oil Pump House DAS Panel FOS Switch gear-1 14R 5C X 2.5 sq.mm 1100
49 Control Cable - 32 Boiler Fuel Oil Pump House DAS Panel FOS Switch gear-1 13R 5C X 2.5 sq.mm 1100
50 Control Cable - 33 Boiler Fuel Oil Pump House DAS Panel FOS Switch gear-1 13R 7C X 2.5 Sqmm 1100
51 Control Cable - 34 Boiler Fuel Oil Pump House DAS Panel FOS Switch gear-1 7R 5C X 2.5 sq.mm 1100
52 Control Cable - 35 Boiler Fuel Oil Pump House DAS Panel FOS Switch gear-1 7R 7C X 2.5 Sqmm 1100
53 Control Cable - 36 Boiler Fuel Oil Pump House DAS Panel FOS Switch gear-1 6R 7C X 2.5 Sqmm 1100
54 Control Cable - 37 Boiler Fuel Oil Pump House DAS Panel FOS Switch gear-1 6R 5C X 2.5 sq.mm 1100
55 Control Cable - 38 Boiler Fuel Oil Pump House DAS Panel FOS Switch gear-1 5R 3C X 6 Sq.mm 1100
56 Control Cable - 39 Boiler Fuel Oil Pump House DAS Panel FOS Switch gear-1 5R 5C X 2.5 sq.mm 1100
57 Control Cable - 40 Boiler Fuel Oil Pump House DAS Panel FOS Switch gear-1 3R 4C X 1.5 Sq.mm 1100
58 Control Cable - 41 Boiler Fuel Oil Pump House DAS Panel FOS Switch gear-1 3R 7C X 1 Sq.mm 1100
59 Control Cable - 42 Boiler Fuel Oil Pump House Auxiliary Control Board (ACB) FOT-1A 4C X 1Sq.mm 1100
60 Control Cable - 43 Boiler Fuel Oil Pump House DAS Panel FOT-1A 7C X 2.5 Sqmm 1100
61 Control Cable - 44 Boiler Fuel Oil Pump House Auxiliary Control Board (ACB) FOT-1B 4C X 1Sq.mm 1100
62 Control Cable - 45 Boiler Fuel Oil Pump House DAS Panel FOT-1B 7C X 2.5 Sqmm 1100
Note: Cables of size 35 sq.mm and above will be Alluminium cables and below 35 sq.mm size will be copper cables.
Volume - II A Lead Specification
(Contract Document) Section -
XIV , Rerouting / Relocating of
Existing Facilities.Clause :
2.01.00 Rerouting of pipes &
cable Racks from Boiler to Fuel
Oil Pump House.