Upload
jessamine-french
View
38
Download
2
Embed Size (px)
DESCRIPTION
FLOW SHOPS: F2 ||Cmax. n JOBS BANK OF m MACHINES (SERIES). Mm. M1. M2. 1. 2. 3. 4. n. FLOW SHOP SCHEDULING (n JOBS, m MACHINES). FLOW SHOPS. PRODUCTION SYSTEMS FOR WHICH: A NUMBER OF OPERATIONS HAVE TO BE DONE ON EVERY JOB. - PowerPoint PPT Presentation
Citation preview
FLOW SHOPS: F2||Cmax
FLOW SHOPS: JOHNSON'S RULE 2
FLOW SHOP SCHEDULING(n JOBS, m MACHINES)
n JOBS BANK OF m MACHINES (SERIES)
12
3
4 n
M1 M2 Mm
FLOW SHOPS: JOHNSON'S RULE 3
FLOW SHOPS
PRODUCTION SYSTEMS FOR WHICH:
A NUMBER OF OPERATIONS HAVE TO BE DONE ON EVERY JOB.
THESE OPERATIONS HAVE TO BE DONE ON ALL JOBS IN THE SAME ORDER, i.e., THE JOBS HAVE TO FOLLOW THE SAME ROUTE.
THE MACHINES ARE ASSUMED TO BE SET UP IN SERIES.
COMMON ASSUMPTIONS:
UNLIMITED STORAGE OR BUFFER CAPACITIES IN BETWEEN SUCCESIVE MACHINES (NO BLOCKING).
A JOB HAS TO BE PROCCESSED AT EACH STAGE ON ONLY ONE OF THE MACHINES (NO PARALLEL MACHINES).
FLOW SHOPS: JOHNSON'S RULE 4
PERMUTATION FLOW SHOPS
FLOW SHOPS IN WHICH THE SAME SEQUENCE OR PERMUTATION OF JOBS IS MAINTAINED THROUGHOUT: THEY DO NOT ALLOW
SEQUENCE CHANGES BETWEEN MACHINES.
PRINCIPLE FOR Fm||Cmax:
THERE ALWAYS EXISTS AN OPTIMAL SCHEDULE WITHOUT SEQUENCE CHANGES BETWEEN THE FIRST TWO MACHINES AND
BETWEEN THE LAST TWO MACHINES.
THERE ARE OPTIMAL SCHEDULES FOR F2||Cmax AND F3||Cmax THAT DO NOT REQUIRE SEQUENCE CHANGES BETWEEN
MACHINES.
FLOW SHOPS: JOHNSON'S RULE 5
JOHNSON’S F2||Cmax PROBLEM
FLOW SHOP WITH TWO MACHINES IN SERIES WITH UNLIMITED STORAGE IN BETWEEN THE TWO MACHINES.
THERE ARE n JOBS AND THE PROCESSING TIME OF JOB j ON MACHINE 1 IS p1j AND THE PROCESSING TIME ON MACHINE 2 IS
p2j.
THE RULE THAT MINIMIZES THE MAKESPAN IS COMMONLY REFERRED TO AS JOHNSON’S RULE.
FLOW SHOPS: JOHNSON'S RULE 6
JOHNSON’S PRINCIPLE
ANY SPT(1)-LPT(2) SCHEDULE IS OPTIMAL FOR Fm||Cmax.
(THE SPT(1)-LPT(2) SCHEDULES ARE NOT THE ONLY SCHEDULES THAT ARE OPTIMAL. THE CLASS OF OPTIMAL SCHEDULES
APPEARS TO BE HARD TO CHARACTERIZE AND DATA DEPENDENT).
FLOW SHOPS: JOHNSON'S RULE 7
DESCRIPTION OF JOHNSON’S ALGORITHM
1. IDENTIFY THE JOB WITH THE SMALLEST PROCESSING TIME (ON EITHER MACHINE).
2. IF THE SMALLEST PROCESSING TIME INVOLVES:
• MACHINE 1, SCHEDULE THE JOB AT THE BEGINNING OF THE SCHEDULE.
• MACHINE 2, SCHEDULE THE JOB TOWARD THE END OF THE SCHEDULE.
3. IF THERE IS SOME UNSCHEDULED JOB, GO TO 1. OTHERWISE STOP.
FLOW SHOPS: JOHNSON'S RULE 8
EXAMPLE
CONSIDER THE FOLLOWING INSTANCE OF THE JOHNSON’S (Fm||Cmax) PROBLEM:
JOB 1 2 3 4 5 p1j 4 4 10 6 2 p2j 5 1 4 10 3
SEQUENCE:
FLOW SHOPS: JOHNSON'S RULE 9
EXAMPLE: SCHEDULE
SEQUENCE:5 1 4 3 2
JOB 1 2 3 4 5 p1j 4 4 10 6 2 p2j 5 1 4 10 3
t
M1
M2
FLOW SHOPS: JOHNSON'S RULE 10
A BOUND ON THE MAKESPAN
FOR JOHNSON’S PROBLEM:
n
1jj2j1
n,..,1j
n
1jj1j2
n,..,1jmax ppmin,ppminmax)OPT(C
FLOW SHOPS: JOHNSON'S RULE 11
JOHNSON’S ALGORITHM
LET U = {1, 2,..., n} BE THE SET OF UNSCHEDULED JOBS.k =1,l = n,Ji = 0, i = 1, 2, ..., n.
STEP 1: IDENTIFICATION OF SMALLEST PROCESSING TIME
IF U = , GO TO STEP 4.
LET
j2n,..,1j
,j1n,..,1j
*j*i pminpminminp
IF i* = 1 GO TO STEP 2; OTHERWISE GO TO STEP 3.
FLOW SHOPS: JOHNSON'S RULE 12
JOHNSON’S ALGORITHM(CONTINUED)
STEP 2: SCHEDULING A JOB ON EARLIEST POSITION
• SCHEDULE JOB j* IN THE EARLIEST AVAILABLE POSITION: Jk = j*.• UPDATE k: k = k + 1.• REMOVE THE JOB FROM THE SCHEDULABLE SET, U = U – {j*}.• GO TO STEP 1.
STEP 3: SCHEDULING A JOB ON LATEST POSITION
• SCHEDULE JOB j* IN THE EARLIEST AVAILABLE POSITION: Jl = j*.• UPDATE l: l = l - 1.• REMOVE THE JOB FROM THE SCHEDULABLE SET, U = U – {j*}.• GO TO STEP 1.
FLOW SHOPS: JOHNSON'S RULE 13
JOHNSON’S ALGORITHM(CONTINUED)
STEP 4: SEQUENCE OF JOBS
THE SEQUENCE OF JOBS IS GIVEN BY Ji, WITH J1 THE FIRST JOB, AND SO FORTH.
FLOW SHOPS: JOHNSON'S RULE 14
Fm||Cmax
Fm||Cmax IS A STRONGLY NP-HARD PROBLEM.
AN EXTENSION OF JOHNSON’S ALGORITHM YIELDS AN OPTIMAL SOLUTION FOR THE F3||Cmax PROBLEM WHEN THE MIDDLE MACHINE IS DOMINATED BY EITHER THE FIRST OR
THIRD MACHINE.
FLOW SHOPS: JOHNSON'S RULE 15
MACHINE DOMINANCE: F3||Cmax
A MACHINE IS DOMINATED WHEN ITS LARGEST PROCESSING TIME IS NO LARGER THAN THE SMALLEST PROCESSING TIME
ON ANOTHER MACHINE.
FOR F3||Cmax PROBLEM:
j3j1j
j2 pmin,pminmaxp
WHICH IMPLIES THAT MACHINE 2 (DOMINATED MACHINE) CAN NEVER CAUSE A DELAY IN THE SCHEDULE.
FLOW SHOPS: JOHNSON'S RULE 16
JOHNSON’S ALGORITHM FOR 3 MACHINES
FOR F3||Cmax, WHENEVER MACHINE 2 IS DOMINATED, i.e.,
OR }p{max}p{min j2j
j1j
SOLVING AN EQUIVALENT TWO-MACHINE PROBLEM WITH PROCESSING TIMES:
p’1j = p1j + p2j AND p’2j = p2j + p3j
GIVES THE OPTIMAL MAKESPAN SEQUENCE TO THE DOMINATED THREE-MACHINE PROBLEM.
}p{max}p{min j2j
j3j
FLOW SHOPS: JOHNSON'S RULE 17
EXAMPLE: F3||Cmax
CONSIDER F3||Cmax WITH THE FOLLOWING JOBS:
JOB 1 2 3 4 5 p1j 4 9 8 6 5 p2j 5 6 2 3 4 p3j 8 10 6 7 11
}p{min j1j
}p{max j2j
}p{min j3j
FLOW SHOPS: JOHNSON'S RULE 18
EXAMPLE: PROCESSING TIMES, DUMMY MACHINES
JOB 1 2 3 4 5 p1j 4 9 8 6 5 p2j 5 6 2 3 4 p3j 8 10 6 7 11 p'1j p'2j
SEQUENCE:
FLOW SHOPS: JOHNSON'S RULE 19
EXAMPLE: SCHEDULE
SEQUENCE:1 4 5 2 3
JOB 1 2 3 4 5 p1j 4 9 8 6 5 p2j 5 6 2 3 4 p3j 8 10 6 7 11
t
M1
M2
M3