Target Start: Target Finish: Duration:7 Business Day Current Status: 0%
1. Land Bidding Process 土地招拍挂流程
Target Start:Target Finish:Duration:20 Business Day Current Status: 0%
7. Project Utility Consultation 项目供应设施征询
Target Start:Target Finish:Duration:5 Business Day Current Status: 0%
3. Land Contract Sign Off 签订土地合同
Target Start:Target Finish:Duration:7 Business Day Current Status: 0%
2. Land Bidding Confirmation Letter 土地中标通知书
Target Start:Target Finish:Duration:1 Business Day Current Status: 0%
6. EIA Approval( Including Waste Water Certificate)
环评审批(包括污水纳管证明)
Target Start:Target Finish:Duration:15 Business Day Current Status: 0%
11. Conceptual Design Consultation 方案设计征询
Target Start:Target Finish:Duration:10 Business Day Current Status: 0%
8. Project Registration 项目备案
Target Start:Target Finish:Duration:15 Business Day Current Status: 0%
4. Land Payment 土地出让金支付
Target Start:Target Finish:Duration:22 Business Day Current Status: 0%
12. Conceptual Design Approval 方案设计审批
Target Start:Target Finish:Duration:10 Business Day Current Status: 0%
10. Project Register项目报建
Target Start:Target Finish:Duration:1 Business Day Current Status: 0%
9. ODHA Approval 职业病情评价审核
Target Start:Target Finish:Duration:10 Business Day Current Status: 0%
5. Land Usage Certificate 建设用地批准书
Target Start:Target Finish:Duration:15 Business Day Current Status: 0%
14. General Design Review 总体设计文件审查
Target Start:Target Finish:Duration:30 Business Day Current Status: 0%
17. GI/DI Tender/Contract Registration 勘查/设计直接发包/
合同备案Target Start:Target Finish:Duration:8 Business Day Current Status: 0%
16. Engineering Planning Permit 建设工程规划许可证
Target Start:Target Finish:Duration:10 Business Day Current Status: 0%
15. Third Party Drawing Review 第三方审核
Target Start:Target Finish:Duration:20 Business Day Current Status: 0%
24. Piling Vetting Survey 布线测量
Target Start:Target Finish:Duration:10 Business Day Current Status: 0%
13. Land Planning Permit 建设用地规划许可证
Target Start:Target Finish:Duration:10 Business Day Current Status: 0%
20. Lightning Proof Drawing Review 防雷图纸审核
Target Start:Target Finish:Duration:10 Business Day Current Status: 0%
18. GC/JL Tender/Contract Registration 总包/监理标书发包/
合同备案Target Start:Target Finish:Duration: 8 Business Day Current Status: 0%
25. Planning Piling Vetting 规划复验布线
Target Start:Target Finish:Duration:5 Business Day Current Status: 0%
19. Worker and CAR Insurance 外来务工保险和一切责任险
Target Start:Target Finish:Duration:3 Business Day Current Status: 0%
21. Q&S Station Registration 安全质量报监
Target Start:Target Finish:Duration:1 Business Day Current Status: 0%
Start Construction 开工
23. Temporary Utilities Connections 临时设施
Target Start:Target Finish:Duration:90 Business Day Current Status: 0%
22. Construction Permit 施工许可证
Target Start:Target Finish:Duration:3 Business Day Current Status: 0%
Land Tax 契税
Target Start:Target Finish:Duration:20 Business Day Current Status: 0%
Land Certificate土地证
Target Start:Target Finish:Duration:20 Business Day Current Status: 0%