Target FinishCurrent Status: 0% 1. Land Bidding Process 土地招拍挂流程 Target StartTarget FinishDuration20 Business Day Current Status: 0% 7. Project Utility Consultation 项目供应设施征询 Target StartTarget FinishDuration5 Business Day Current Status: 0% 3. Land Contract Sign Off 签订土地合同 Target StartTarget FinishDuration7 Business Day Current Status: 0% 2. Land Bidding Confirmation Letter 土地中标通知书 Target StartTarget FinishDuration1 Business Day Current Status: 0% 6. EIA Approval( Including Waste Water Certificate) 环评审批(包括污水纳管证明) Target StartTarget FinishDuration15 Business Day Current Status: 0% 11. Conceptual Design Consultation 方案设计征询 Target StartTarget FinishDuration10 Business Day Current Status: 0% 8. Project Registration 项目备案 Target StartTarget FinishDuration15 Business Day Current Status: 0% 4. Land Payment 土地出让金支付 Target StartTarget FinishDuration22 Business Day Current Status: 0% 12. Conceptual Design Approval 方案设计审批 Target StartTarget FinishDuration10 Business Day Current Status: 0% 10. Project Register 项目报建 Target StartTarget FinishDuration1 Business Day Current Status: 0% 9. ODHA Approval 职业病情评价审核 Target StartTarget FinishDuration10 Business Day Current Status: 0% 5. Land Usage Certificate 建设用地批准书 Target StartTarget FinishDuration15 Business Day Current Status: 0% 14. General Design Review 总体设计文件审查 Target StartTarget FinishDuration30 Business Day Current Status: 0% 17. GI/DI Tender/Contract Registration 勘查/设计直接发包/ 合同备案 Target StartTarget FinishDuration8 Business Day Current Status: 0% 16. Engineering Planning Permit 建设工程规划许可证 Target StartTarget FinishDuration10 Business Day Current Status: 0% 15. Third Party Drawing Review 第三方审核 Target StartTarget FinishDuration20 Business Day Current Status: 0% 24. Piling Vetting Survey 布线测量 Target StartTarget FinishDuration10 Business Day Current Status: 0% 13. Land Planning Permit 建设用地规划许可证 Target StartTarget FinishDuration10 Business Day Current Status: 0% 20. Lightning Proof Drawing Review 防雷图纸审核 Target StartTarget FinishDuration10 Business Day Current Status: 0% 18. GC/JL Tender/Contract Registration 总包/监理标书发包/ 合同备案 Target StartTarget FinishDuration8 Business Day Current Status: 0% 25. Planning Piling Vetting 规划复验布线 Target StartTarget FinishDuration5 Business Day Current Status: 0% 19. Worker and CAR Insurance 外来务工保险和一切责任险 Target StartTarget FinishDuration3 Business Day Current Status: 0% 21. Q&S Station Registration 安全质量报监 Target StartTarget FinishDuration1 Business Day Current Status: 0% Start Construction 开工 23. Temporary Utilities Connections 临时设施 Target StartTarget FinishDuration90 Business Day Current Status: 0% 22. Construction Permit 施工许可证 Target StartTarget FinishDuration3 Business Day Current Status: 0% Land Tax 契税 Target StartTarget FinishDuration20 Business Day Current Status: 0% Land Certificate 土地证 Target StartTarget FinishDuration20 Business Day Current Status: 0%

Flow Chart

Embed Size (px)

Citation preview

Page 1: Flow Chart

Target Start: Target Finish: Duration:7 Business Day Current Status: 0%

1. Land Bidding Process 土地招拍挂流程

Target Start:Target Finish:Duration:20 Business Day Current Status: 0%

7. Project Utility Consultation 项目供应设施征询

Target Start:Target Finish:Duration:5 Business Day Current Status: 0%

3. Land Contract Sign Off 签订土地合同

Target Start:Target Finish:Duration:7 Business Day Current Status: 0%

2. Land Bidding Confirmation Letter 土地中标通知书

Target Start:Target Finish:Duration:1 Business Day Current Status: 0%

6. EIA Approval( Including Waste Water Certificate)

环评审批(包括污水纳管证明)

Target Start:Target Finish:Duration:15 Business Day Current Status: 0%

11. Conceptual Design Consultation 方案设计征询

Target Start:Target Finish:Duration:10 Business Day Current Status: 0%

8. Project Registration 项目备案

Target Start:Target Finish:Duration:15 Business Day Current Status: 0%

4. Land Payment 土地出让金支付

Target Start:Target Finish:Duration:22 Business Day Current Status: 0%

12. Conceptual Design Approval 方案设计审批

Target Start:Target Finish:Duration:10 Business Day Current Status: 0%

10. Project Register项目报建

Target Start:Target Finish:Duration:1 Business Day Current Status: 0%

9. ODHA Approval 职业病情评价审核

Target Start:Target Finish:Duration:10 Business Day Current Status: 0%

5. Land Usage Certificate 建设用地批准书

Target Start:Target Finish:Duration:15 Business Day Current Status: 0%

14. General Design Review 总体设计文件审查

Target Start:Target Finish:Duration:30 Business Day Current Status: 0%

17. GI/DI Tender/Contract Registration 勘查/设计直接发包/

合同备案Target Start:Target Finish:Duration:8 Business Day Current Status: 0%

16. Engineering Planning Permit 建设工程规划许可证

Target Start:Target Finish:Duration:10 Business Day Current Status: 0%

15. Third Party Drawing Review 第三方审核

Target Start:Target Finish:Duration:20 Business Day Current Status: 0%

24. Piling Vetting Survey 布线测量

Target Start:Target Finish:Duration:10 Business Day Current Status: 0%

13. Land Planning Permit 建设用地规划许可证

Target Start:Target Finish:Duration:10 Business Day Current Status: 0%

20. Lightning Proof Drawing Review 防雷图纸审核

Target Start:Target Finish:Duration:10 Business Day Current Status: 0%

18. GC/JL Tender/Contract Registration 总包/监理标书发包/

合同备案Target Start:Target Finish:Duration: 8 Business Day Current Status: 0%

25. Planning Piling Vetting 规划复验布线

Target Start:Target Finish:Duration:5 Business Day Current Status: 0%

19. Worker and CAR Insurance 外来务工保险和一切责任险

Target Start:Target Finish:Duration:3 Business Day Current Status: 0%

21. Q&S Station Registration 安全质量报监

Target Start:Target Finish:Duration:1 Business Day Current Status: 0%

Start Construction 开工

23. Temporary Utilities Connections 临时设施

Target Start:Target Finish:Duration:90 Business Day Current Status: 0%

22. Construction Permit 施工许可证

Target Start:Target Finish:Duration:3 Business Day Current Status: 0%

Land Tax 契税

Target Start:Target Finish:Duration:20 Business Day Current Status: 0%

Land Certificate土地证

Target Start:Target Finish:Duration:20 Business Day Current Status: 0%