Upload
sorcha
View
36
Download
0
Embed Size (px)
DESCRIPTION
Florida Water Forum Everglades Restoration June 3, 2011. SFWMD Restoration Progress. C-111 Spreader Canal Western Project Biscayne Bay Coastal Wetlands Lakeside Ranch Stormwater Treatment Area (STA). Restoration. Land Acquisition Southern CREW Imperial River Flow-way - PowerPoint PPT Presentation
Citation preview
Florida Water ForumFlorida Water ForumEverglades RestorationEverglades Restoration
June 3, 2011June 3, 2011
Florida Water ForumFlorida Water ForumEverglades RestorationEverglades Restoration
June 3, 2011June 3, 2011
SFWMD Restoration ProgressSFWMD Restoration Progress
C-111 Spreader Canal Western Project
Biscayne Bay Coastal Wetlands
Lakeside Ranch Stormwater Treatment Area (STA)
C-111 Spreader Canal Western Project
Biscayne Bay Coastal Wetlands
Lakeside Ranch Stormwater Treatment Area (STA)
RestorationRestoration
Land Acquisition• Southern CREW Imperial River Flow-way
• Purchased 26,800 acres of land from U.S. Sugar Corporation
• $197,396,088 cash
• Options to acquire 153,200 acres over next ten years
• Kissimmee River Restoration
• United States Army Corps of Engineers (USACE) Herbert Hoover Dike Project
Public/Private Partnerships• Develop and implement Dispersed Water
Management program
C-111 Spreader Canal Western ProjectC-111 Spreader Canal Western ProjectC-111 Spreader Canal Western ProjectC-111 Spreader Canal Western Project
Improve the quantity, timing and distribution of water delivered to Florida Bay via Taylor Slough
Improve coastal zone salinities in Florida Bay
Construction began January 2010
Frog Pond Impoundment - anticipated completion June 2011
Aerojet Canal- anticipated completion June 2011
Plugging C-110 and L-31E Canals - completed August 2010
Pump Stations anticipated completion July 2011
Picayune Strand RestorationPicayune Strand Restoration
55,000 acres restored wetlands
20,000+ parcels acquired
Project Components3 Spreader Canals
3 Pump Stations
100+ Canal Plugs
227 Miles Roadway Removal
Before
After
Biscayne Bay Coastal WetlandsBiscayne Bay Coastal Wetlands
Kissimmee River Restoration ProjectKissimmee River Restoration Project
Acquire 102,000 acres of historical river floodplain • Nearly complete; $300 million invested
Remove 2 large water control structures• 1 structure removed
Backfill 22 miles of canal• 65% complete
Recarve 9 miles of remnant river channel • 60% complete
Rehydrate 25,000 acres of river floodplain• 60% complete
1994 - 2014
14 miles of C-38 Canal backfilled
24 miles of continuous river channel restored
Approximately 15,000 acres of floodplain habitat restored
Backfilled C-38
Canal
Backfilled C-38
Canal
RemnantRiver
Channel
RemnantRiver
Channel
RemnantRiver
Channel
RemnantRiver
Channel
Degraded Spoil Area
Degraded Spoil Area
New River ConnectionNew River Connection
Kissimmee River RestorationCanal Backfilling Progress Kissimmee River RestorationCanal Backfilling Progress
Looking north at Montsdeoca Run and adjacent inundated floodplain in the Phase I restoration area.Looking north at Montsdeoca Run and adjacent inundated floodplain in the Phase I restoration area.
Sept 9, 2010
Looking south at Micco and MacArthur Runs at lower extent of Phase I restoration areaLooking south at Micco and MacArthur Runs at lower extent of Phase I restoration area
Sept 23, 2010
Kissimmee River RestorationResponse: River Channel VegetationKissimmee River RestorationResponse: River Channel Vegetation
Pre-restoration Post-restoration
Tamiami Trail Modifications Tamiami Trail Modifications
Corps awarded $81 million contract
Corps and Department of Interior funded project
Construct one-mile bridge, and raising and reinforcing more than nine miles of existing Tamiami Trail
Key component to restore historical flows to Everglades National Park
Construction ongoing
State and Federal AppropriationsState and Federal Appropriations
Original Assumption for CERP: State and Federal appropriations for CERP would average $200 million per year for each agency• Federal government has
appropriated $755 million through FY11 for CERP since WRDA-2000 compared with over $2.1billion appropriated by the State to date
Federal AppropriationsFederal Appropriations
The Federal government recently appropriated significant funds for the CERP
• Federal Stimulus Package –
• Over $86 million for CERP restoration projects in FY2009 and FY2010
• President’s Budget for FY2011 (enacted)
• $180 million for SFER restoration (includes $152M for CERP)
• President’s Budget for FY2012 (proposed)
• $163 million for SFER restoration (includes $80M for CERP)
CERP Project AuthorizationsCERP Project Authorizations
Currently authorized
• Indian River Lagoon – South
• Picayune Strand Restoration
• Site 1 Impoundment
• Melaleuca Eradication and Other Exotic Plants – Implement Biological Controls
Targeted for next WRDA
• C-43 West Basin Storage Reservoir
• C-111 Spreader Canal – Western
• Biscayne Bay Coastal Wetlands – Phase 1
• Broward County Water Preserve Areas
QuestionsQuestions QuestionsQuestions