13
Flexible Riser Cost Saving The New Economic Reality © Flexlife 2015 1

Flexible Riser Cost Saving - Subsea UK

  • Upload
    others

  • View
    3

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Flexible Riser Cost Saving - Subsea UK

Flexible Riser Cost Saving The New Economic Reality

© Flexlife 2015 1

Page 2: Flexible Riser Cost Saving - Subsea UK

Contents

Cost Saving – The New Economic Reality 1. Overview 2. Live case study (1) - Angola 3. Live case study cost savings - Design 4. Live case study cost savings – Global Analysis 5. Live case study cost savings – Installation 6. Live case study (2) – riser leak - Malaysia 7. Riser repair - Armadillo 8. Riser repair – FlexGel 9. Case study (3) – Ultrasonic Scanning - Angola 10. Summary

• ENGINEERING • DELIVERY • INTEGRITY • TECHNOLOGY © Flexlife 2015

2

Page 3: Flexible Riser Cost Saving - Subsea UK

Overview

• Flexlife is a riser specialist based in Aberdeen and Houston, founded 2007 • Many staff have held key roles at flexible pipe OEMs, Installation Contractors and Riser Engineering Companies • Revenue £8m (2015-6), 35 staff o Flexible riser engineering, delivery management and integrity o Complete range of patented flexible inspection and repair technologies

• Currently focused on projects with cost and FID gating issues..

• ENGINEERING • DELIVERY • INTEGRITY • TECHNOLOGY © Flexlife 2015

3

Page 4: Flexible Riser Cost Saving - Subsea UK

Live case study (1) - Angola

• New FPSO development 1700m WD • 7 x 7.5 inch ID flexible risers and flowlines (~ 47 km of flexible pipe) • Max DP 9000 psi, max DT 100°C • High value OEM tenders received : FID issues / sanction Q4 2015 • Flexlife joined the project team during the ITT phase

• ENGINEERING • DELIVERY • INTEGRITY • TECHNOLOGY © Flexlife 2015

4

Page 5: Flexible Riser Cost Saving - Subsea UK

Live case study cost savings - Design

Pre-Flexlife: • Common multi-service pipe design for Production, Gas Injection, Water Injection • Worst case design criteria combined temperature, flow assurance, chemical compatibility, pressure • Specified with PVDF liner, super-austenitic carcass, sour service wire, multiple insulation layers • Resulting pipe structures pushed OEM qualification limits -> complex clarifications Post-Flexlife review of field design requirements on a per-pipe basis: • PVDF only required for production lines ~30% • Insulation only required for production lines ~15% • Sour service requirements removed for water injection ~15% • Carcass material changed to duplex ~10% • Total design savings US $50-80 Mil

• ENGINEERING • DELIVERY • INTEGRITY • TECHNOLOGY © Flexlife 2015

5

Page 6: Flexible Riser Cost Saving - Subsea UK

Live case study savings - Global Analysis

Pre-Flexlife: • Riser configuration driven by umbilical clashing & compression configuration, no iterations • Resulting hang-off angle for risers = 10°, free hanging catenary. • Max top tension ~ 580 Te • Max TDP tension >100 Te • Substantial holdback suction piles unnoticed due to analysis issues Flexlife Modifications: • Decrease riser hang-off angle, greatly reducing tensions • Modify turret layout to optimize between risers and umbilicals • Re-run analysis with correct inputs and service specific pipe designs • Relocate smaller holdback anchors at optimum locations

• Total analysis savings US $10M

• ENGINEERING • DELIVERY • INTEGRITY • TECHNOLOGY © Flexlife 2015

6

Page 7: Flexible Riser Cost Saving - Subsea UK

Live case study savings – Installation The knock-on effects on installation were considerable:

• Reduced number of reels / trips required based on decreased pipe diameter • Reduced installation tensions allowing smaller vessels to install (previously only a few vessels that could install) • Simplified pull-in to FPSO with reduced hang-off angles • Reduced hold-back requirements = reduced fabrication costs, faster install

Total installation savings US $25M

• ENGINEERING • DELIVERY • INTEGRITY • TECHNOLOGY © Flexlife 2015

7

Page 8: Flexible Riser Cost Saving - Subsea UK

Live Case Study (2) – Malaysia – Riser Leak

• ENGINEERING • DELIVERY • INTEGRITY • TECHNOLOGY © Flexlife 2015

8

• 2015 : ROV inspection reveals catastrophic sheath failure below BSR • Signs of gas leakage into open water

• Failure of subsea vent ports, leading to gas buildup, no annulus test • Catastrophic sheath failure below BSR

Page 9: Flexible Riser Cost Saving - Subsea UK

Riser repair : Armadillo

• ENGINEERING • DELIVERY • INTEGRITY • TECHNOLOGY © Flexlife 2015

9

• Unique sheath repair product installed as a permanent dynamic riser solution • Encapsulates and seals sheath rupture using injected gel • Prevents ongoing water flow and corrosion of armour wire • Incorporates patented secondary vent ports • Annulus test @ 2.5 bar proves sheath integrity to 25m WD • Flexlife recalculates design life of flooded riser

Page 10: Flexible Riser Cost Saving - Subsea UK

Riser repair : FlexGel

• ENGINEERING • DELIVERY • INTEGRITY • TECHNOLOGY © Flexlife 2015

10

• Used within a confined area, such as Armadillo, J-tube, I-tube, or Caisson • Prevents further corrosion by excavating oxygenated water from risk area • Pumps as liquid and sets as rubber – suitable for dynamic risers • Predetermined density minimizes quantities • Environmentally friendly, CEFAS registered • Compatible with PA11

Page 11: Flexible Riser Cost Saving - Subsea UK

Case study (3) – Ultrasonic Scanning

• ENGINEERING • DELIVERY • INTEGRITY • TECHNOLOGY © Flexlife 2015

11

• In 2013 Flexlife ultrasonic service (NEPTUNE) was employed on a deepwater Angola field • Imagery suggested dropped object from host FPSO • The operator required detailed understanding of damage

• Neptune gives 100% accuracy regarding annulus status via ROV deployment • Over 140 risers scanned to date • 2013 results demonstrated ‘no urgent remedial repair required’ • Regular scanning clearly and consistently confirms riser status to operator

Page 12: Flexible Riser Cost Saving - Subsea UK

Summary

• ENGINEERING • DELIVERY • INTEGRITY • TECHNOLOGY © Flexlife 2015

12

Go the extra mile at design stage, question each specification line Consider feasibility of ‘repair over replacement’ – testing services are available

Page 13: Flexible Riser Cost Saving - Subsea UK

© Flexlife 2015 13