First Parish Meeting House Interior Renovation Tyngsborough, Massachusetts Existing Conditions Report & Schematic Design Recommendations April 11, 2017

First Parish Meeting House Interior Renovation ... Renovation. Tyngsborough, Massachusetts: Existing Conditions Report & Schematic Design : Recommendations. April 11, 2017: Table of

  • Upload
    hoangtu

  • View
    217

  • Download
    0

Embed Size (px)

Citation preview

Page 1: First Parish Meeting House Interior Renovation ... Renovation. Tyngsborough, Massachusetts: Existing Conditions Report & Schematic Design : Recommendations. April 11, 2017: Table of

First Parish Meeting House

Interior Renovation

Tyngsborough, Massachusetts

Existing Conditions Report

&

Schematic Design

Recommendations

April 11, 2017

Page 2: First Parish Meeting House Interior Renovation ... Renovation. Tyngsborough, Massachusetts: Existing Conditions Report & Schematic Design : Recommendations. April 11, 2017: Table of

Table of Contents

Cover Consultant Team Section 1

Table of Contents Cover Letter

Section 2

Existing Conditions Report

2.1 Architectural Existing Conditions

2.2 Mechanical, Electrical, Plumbing, and Fire Protection Existing Conditions

Section 3 - Appendix

3.1 Hazardous Materials Report (Peer)

3.2 Code Review (Code Red)

3.3 Cost Estimates

3.4 Proposed floor plans

Page 3: First Parish Meeting House Interior Renovation ... Renovation. Tyngsborough, Massachusetts: Existing Conditions Report & Schematic Design : Recommendations. April 11, 2017: Table of

Page 2 First Parish Meeting House RE: Interior Renovation CBI Job No.: 17009 April 11, 2017

Consultant Team

CBI Consulting Inc.

Wayne R. Lawson, P.E., SECB – Principal in Charge

Honorata Loomis, Associate AIA, LEED AP – Project Manager

Andrea M. Willett, AIA, LEED AP BD+C – Project Architect

BLW Engineers

John Pierga – Electrical Engineer

Bill Scanlon – HVAC Engineer

George Baberkov – Plumbing and Fire Protection Engineer

Peer

David Gorder – Project Manager

Code Red

Paul Moan – Code Consultant

PM & C

Peter Bradley – Cost Estimator

Page 4: First Parish Meeting House Interior Renovation ... Renovation. Tyngsborough, Massachusetts: Existing Conditions Report & Schematic Design : Recommendations. April 11, 2017: Table of

April 11, 2017

Matthew HansonAssistant Town AdministratorTown of Tyngsborough25 Bryants LaneTyngsborough, MA 01871

Tel.: (978) 649-2314Fax: (978) 649-2320Email: [email protected]

Proj.: First Parish Meeting House Interior RenovationRe: Feasibility Study/Design Development

CBI Job No.: 17009

Dear Mr. Hanson:

CBI Consulting (CBI) has performed a review of the interior conditions at the First Parish Meeting House in Tyngsborough, MA.

The Town of Tyngsborough commissioned the Feasibility Study following the purchase of the building in order to assess the existing interior conditions and to develop a program for repairs/renovations. The study also included evaluation of MEP and accessibility upgrades needed to satisfy planned use of the building based on the information provided by the Town of Tyngsborough.

The building is a significant historic structure to the historic fabric of the town and is listed on the National Register of Historic Places. The result of this study will provide options and recommendations to extend the life of the building, and provide better use of the structure and site while respecting the historic character of the building and the original materials.

Very truly yours,CBI Consulting Inc.

Wayne R. Lawson, P.E., SECB, [email protected]

Page 5: First Parish Meeting House Interior Renovation ... Renovation. Tyngsborough, Massachusetts: Existing Conditions Report & Schematic Design : Recommendations. April 11, 2017: Table of

April 7, 2017

Matthew Hanson

Assistant Town Administrator

Town of Tyngsborough

25 Bryants Lane

Tyngsborough, MA 01871

Tel.: (978) 649-2314

Fax: (978) 649-2320

Email: [email protected]

Project: First Parish Meeting House Interior Renovation

Re: Existing Conditions Report

CBI Job No.: 17009

Dear Mr. Hanson:

CBI has prepared this Existing Conditions Assessment to outline the scope and extent of

recommended repairs and replacements to various interior building components and

materials, based on their condition and historical integrity. The recommendations listed in

the report also include new programming for the building developed based on the information

received from the Town of Tyngsborough.

CBI visited the site on January 25, 2017 to evaluate the existing interior conditions. To assist

with incidental demolition during the exploration, CBI engaged Complete Restoration &

Waterproofing, Inc. to perform the investigation. Mechanical, electrical, plumbing, fire

protection and alarm systems were assessed and recommendations provided by BLW

Engineers, Inc. Compliance with the current building code and accessibility upgrades were

evaluated by Code Red Consultants. The interior finishes were visually inspected and

samples collected to determine the presence of hazardous materials by PEER Consultants,

P.C.

The following sections summarize our findings and repair recommendations. Attached to the

report are findings from our consultants as well as a preliminary cost estimate developed for

the budgeting of future repairs and upgrades by PM&C.

Basement Level

Observations: The Basement level is approximately 2,700 square feet and consists of three

(3) classrooms, open meeting space, kitchen, Men’s and Women’s Bathrooms and the

Mechanical Room. The Basement is accessible from the First Floor level by a wooden

staircase (Stair 1) located on the right-hand side of the building (facing Sanctuary) and from

the exterior by a concrete staircase located at the rear of the building. The existing finishes

are in fair to poor condition and are slated to be demolished.

Recommendations and New Design: The new layout of the Basement will accommodate the

program for the Recreation Department consisting of a large meeting room, open meeting

space, commercial kitchen, Men’s and Women’s accessible bathrooms, storage rooms as well

Page 6: First Parish Meeting House Interior Renovation ... Renovation. Tyngsborough, Massachusetts: Existing Conditions Report & Schematic Design : Recommendations. April 11, 2017: Table of

Page 2

First Parish Meeting House Interior Renovation

Existing Conditions Assessment

CBI Job No.: 17009

April 7, 2017

as mechanical, electrical, plumbing and elevator machine rooms. A new wooden stair

leading from the Basement level up to the Attic will be reconstructed in place of Stair 2. The

Rear Stair will be reconstructed to provide uniform treads and risers per the requirements of

521 CMR. The exterior foundation wall will receive spray foam insulation to improve the

energy efficiency of the building and new vinyl windows will be installed throughout the

Basement. New durable and low-maintenance finishes will be installed throughout.

First Floor Level

Observations: The First Floor level is approximately 2,500 square feet and consists of the

Lobby area, Sanctuary and two (2) stairwells – a wooden stairwell (Stair 1) located on the

right-hand side of the building, facing Sanctuary, leading to the Basement level and a wooden

winding stairwell (Stair 2) located on the left-hand side of the building, facing Sanctuary,

leading to the Mezzanine level. The majority of existing finishes are in fair to good condition

with some of the finishes in poor condition.

Recommendations and New Design: The Sanctuary and the Lobby will remain in their

current configuration and the intent is to retain the original finishes to the fullest extent

possible. A new handicapped accessible entry will be provided on the former Stair 1 space

with an exterior ramp to provide assessible access for the patrons.

The carpet in the Lobby will be removed existing wood flooring throughout the First Floor

will be repaired as needed and refinished. The existing decorative floor grates in the

Sanctuary isles will remain and will be refinished. The ramps leading up the Altar in the

Sanctuary will be extended to meet the current slope requirements of 521 CMR and will

receive railings on each side of the ramps. The body of the pews will be prepared for paint

and seats will be stripped of the paint and polyurethane and varnished. CBI recommends that

the plaster at the walls be removed and walls filled in with spray foam insulation and finished

with gypsum wall board. The existing plaster and lathe and tin covered barrel vault ceiling

will be prepared for paint. The existing wood paneled wall between the Lobby and the

Sanctuary will remain and will be prepared for paint. Wood trim will be prepared for paint

and the existing original and replacement windows will be replaced with wood clad windows.

The existing chandelier in the Sanctuary will be rewired and retrofitted with new LED lamps.

Additional period and architecturally appropriate lighting will be provided throughout the

First Floor level.

The current 521 CMR requirements call for the installation of a chair lift at the Altar. The

Town of Tyngsborough would like to pursue a variance for this requirement.

Mezzanine Level

Observations: The Mezzanine level is approximately 600 square feet and consists of one (1)

large open room that was at some point in time divided into two smaller rooms and one (1)

room located in the space above Stair 1. The Mezzanine is accessible from the First Floor

level by a winding wooden staircase (Stair 2) located on the left-hand side of the building

(facing Sanctuary) with access to the Attic level provided by the same stairwell. The

majority of existing finishes are in fair to poor condition.

Page 7: First Parish Meeting House Interior Renovation ... Renovation. Tyngsborough, Massachusetts: Existing Conditions Report & Schematic Design : Recommendations. April 11, 2017: Table of

Page 3

First Parish Meeting House Interior Renovation

Existing Conditions Assessment

CBI Job No.: 17009

April 7, 2017

Recommendations and New Design: The interior partition for the smaller meeting room will

be removed to create one large open room. The smaller room over the Stair 1 space will be

utilized to accommodate the LULA and a small storage closet. The access to the Mezzanine

level and to the Attic level will be provided by a newly reconfigured wooden stairwell located

in the former Stair 2 space.

The existing wood flooring will be filled in as needed and refinished. The wood paneling at

the wall between the Mezzanine and the Sanctuary will be removed and a new wood

guardrail will be installed to meet the current building code requirements. New guardrails

will be installed at the large windows to address the gap between the window and the floor.

CBI recommends that the plaster at the walls and barrel vault ceiling at the Mezzanine level

be removed and walls filled in with spray foam insulation and finished with gypsum wall

board. Wood trim will be prepared for paint and the existing original and replacement

windows will be replaced with wood clad windows. Period and architecturally appropriate

lighting will be provided throughout the space.

Mechanical, Electrical, Plumbing, Fire Protection (MEPFP) and Fire Alarm

The existing conditions and recommendations for repairs or replacement of the MEPFP and

Fire Alarm systems are described in the attached report provided by BLW Engineers, Inc.

Accessibility

The cost of the recent exterior renovation on the building and the slated repairs and upgrades

to the interior will exceed 30% of the full and fair cash value of the building. Therefore, all

public portions of the building are required to meet the current requirements of the 521 CMR.

The full description of the required upgrades is described in the attached report provided by

Code Red Consultants.

Hazardous Materials

The existing finishes that may be disturbed during the renovation project were visually

surveyed and multiple samples were collected and later tested to determine the presence of

lead paint and asbestos. The full description of the sampling and analysis is described in the

attached report provided by PEER Consultants, P.C.

Please contact the undersigned with any questions.

Very truly yours,

CBI Consulting Inc.

Wayne R. Lawson, P.E., SECB

Principal [email protected]

Attachments: Photo Index

Page 8: First Parish Meeting House Interior Renovation ... Renovation. Tyngsborough, Massachusetts: Existing Conditions Report & Schematic Design : Recommendations. April 11, 2017: Table of

Page 4

First Parish Meeting House Interior Renovation

Existing Conditions Assessment

CBI Job No.: 17009

April 7, 2017

First Parish Meeting House

Photo Index

CBI Job No.: 17009

April 7, 2017

Photo No. Description

1

Open meeting space in the

Basement level looking

towards the rear of the

building.

2

Open meeting space in the

Basement level looking

towards the front of the

building.

Page 9: First Parish Meeting House Interior Renovation ... Renovation. Tyngsborough, Massachusetts: Existing Conditions Report & Schematic Design : Recommendations. April 11, 2017: Table of

Page 5

First Parish Meeting House Interior Renovation

Existing Conditions Assessment

CBI Job No.: 17009

April 7, 2017

3

Kitchen in the Basement

level.

4

Bathrooms in the Basement

level.

Page 10: First Parish Meeting House Interior Renovation ... Renovation. Tyngsborough, Massachusetts: Existing Conditions Report & Schematic Design : Recommendations. April 11, 2017: Table of

Page 6

First Parish Meeting House Interior Renovation

Existing Conditions Assessment

CBI Job No.: 17009

April 7, 2017

5

Stair 1 leading from the

Basement level to the First

Floor level.

6

Rear Stair in the Basement

level.

Page 11: First Parish Meeting House Interior Renovation ... Renovation. Tyngsborough, Massachusetts: Existing Conditions Report & Schematic Design : Recommendations. April 11, 2017: Table of

Page 7

First Parish Meeting House Interior Renovation

Existing Conditions Assessment

CBI Job No.: 17009

April 7, 2017

7

Mechanical Room in the

Basement level.

8

Selective destructive testing

of the exterior foundation

wall in the Basement level.

9

Selective destructive testing

of the ceiling in the

Basement level.

Page 12: First Parish Meeting House Interior Renovation ... Renovation. Tyngsborough, Massachusetts: Existing Conditions Report & Schematic Design : Recommendations. April 11, 2017: Table of

Page 8

First Parish Meeting House Interior Renovation

Existing Conditions Assessment

CBI Job No.: 17009

April 7, 2017

10

Sanctuary looking towards

the rear of the building on

the First Floor level.

11

Sanctuary looking towards

the front of the building on

the First Floor level.

12

Altar in the Sanctuary in

the rear of the building.

Page 13: First Parish Meeting House Interior Renovation ... Renovation. Tyngsborough, Massachusetts: Existing Conditions Report & Schematic Design : Recommendations. April 11, 2017: Table of

Page 9

First Parish Meeting House Interior Renovation

Existing Conditions Assessment

CBI Job No.: 17009

April 7, 2017

13

Aisle with ramp up to the

Altar in the Sanctuary.

14

Decorative floor grate in

the aisle inside the

Sanctuary.

15

Wood pews with painted

frames and various finishes

at the seats.

Page 14: First Parish Meeting House Interior Renovation ... Renovation. Tyngsborough, Massachusetts: Existing Conditions Report & Schematic Design : Recommendations. April 11, 2017: Table of

Page 10

First Parish Meeting House Interior Renovation

Existing Conditions Assessment

CBI Job No.: 17009

April 7, 2017

16

Original chandelier inside

the Sanctuary.

17

Selective destructive testing

of the walls in the

Sanctuary.

18

Selective destructive testing

of the plaster and lathe and

tin panel covered ceiling in

the Sanctuary.

Page 15: First Parish Meeting House Interior Renovation ... Renovation. Tyngsborough, Massachusetts: Existing Conditions Report & Schematic Design : Recommendations. April 11, 2017: Table of

Page 11

First Parish Meeting House Interior Renovation

Existing Conditions Assessment

CBI Job No.: 17009

April 7, 2017

19

Vinyl replacement windows

with original half round

wood windows in the

Sanctuary.

20

Wooden stairwell (Stair 1)

on the First Floor level.

Page 16: First Parish Meeting House Interior Renovation ... Renovation. Tyngsborough, Massachusetts: Existing Conditions Report & Schematic Design : Recommendations. April 11, 2017: Table of

Page 12

First Parish Meeting House Interior Renovation

Existing Conditions Assessment

CBI Job No.: 17009

April 7, 2017

21

Lobby on the First Floor

level.

22

Winding wooden stairwell

(Stair 2) on the First Floor

level.

Page 17: First Parish Meeting House Interior Renovation ... Renovation. Tyngsborough, Massachusetts: Existing Conditions Report & Schematic Design : Recommendations. April 11, 2017: Table of

Page 13

First Parish Meeting House Interior Renovation

Existing Conditions Assessment

CBI Job No.: 17009

April 7, 2017

23

Open meeting room

looking towards the parking

lot side of the building on

the Mezzanine level.

24

Wood paneled wall at the

wall between the

Mezzanine and Sanctuary.

Page 18: First Parish Meeting House Interior Renovation ... Renovation. Tyngsborough, Massachusetts: Existing Conditions Report & Schematic Design : Recommendations. April 11, 2017: Table of

Page 14

First Parish Meeting House Interior Renovation

Existing Conditions Assessment

CBI Job No.: 17009

April 7, 2017

25

Open meeting room

looking towards the garden

side of the building on the

Mezzanine level.

26

Smaller room on the

Mezzanine level.

Page 19: First Parish Meeting House Interior Renovation ... Renovation. Tyngsborough, Massachusetts: Existing Conditions Report & Schematic Design : Recommendations. April 11, 2017: Table of

Page 15

First Parish Meeting House Interior Renovation

Existing Conditions Assessment

CBI Job No.: 17009

April 7, 2017

27

Small room located over

Stair 1 on the Mezzanine

level.

28

Floor grate on the

Mezzanine level.

Page 20: First Parish Meeting House Interior Renovation ... Renovation. Tyngsborough, Massachusetts: Existing Conditions Report & Schematic Design : Recommendations. April 11, 2017: Table of

Prepared For:

CBI Consultants Inc.

250 Dorchester Avenue

Boston, MA

2017

Prepared By:

BLW Engineers, Inc.

311 Great Road

P.O. Box 1551

Littleton, MA 01460

3/29/2017

MEP Systems Evaluation

First Parish Meeting House Interior Renovations

Tyngsborough, MA

Page 21: First Parish Meeting House Interior Renovation ... Renovation. Tyngsborough, Massachusetts: Existing Conditions Report & Schematic Design : Recommendations. April 11, 2017: Table of

MEP Systems Evaluation Page I 2 March 29, 2017

FIRE PROTECTION

Summary of Existing Conditions

Currently the existing building is not provided

with automatic fire sprinkler system.

Recommendations

The building shall be provided with automatic

fire suppression system in accordance with

NFPA 13.

All areas within the building conditioned

envelope will be provided with automatic wet

fire protection system. This should include

basement, first floor and possible mezzanine

level. For all areas subject to freezing the

system shall be automatic dry type, large attic.

Sprinkler heads shall be a quick response type

with temperature rating in accordance with

their location with respect to a heat source(s).

New underground water fire main shall be

provided for the building, to supply the

automatic fire suppression system. The new

main shall be provided with backflow preventer

in accordance with Massachusetts Department

of Environmental Protection. The fire

suppression system shall be provided with main

fire department hose connection at location

approved by the local Fire Department. The fire

suppression system valves and flow controls

shall be electronically supervised in accordance

with NFPA 72.

The basement level will have a commercial

kitchen setup. If there will be a gas fired

equipment provided, specialty fire suppression,

wet chemical, shall be utilized for the

protection over that equipment.

Page 22: First Parish Meeting House Interior Renovation ... Renovation. Tyngsborough, Massachusetts: Existing Conditions Report & Schematic Design : Recommendations. April 11, 2017: Table of

MEP Systems Evaluation Page I 3 March 29, 2017

PLUMBING

Summary of Existing Conditions

Domestic Water System

Existing 1” service has been observed on the

north side of the building under a stair. The

service appears to be disconnected with the

water meter removed and the domestic water

system permanently winterized. The domestic

hot water system was served by an existing 40

gallon electric water heater

Storm System

Currently the building does not have a storm

system and the roof structure does not require

one.

Sanitary System

The existing sanitary system is connected to an

outdoor septic tank. The Town has provided

information that the system is not functioning,

therefore the current sanitary system is not

reusable.

Plumbing Fixtures

All existing plumbing fixtures appear to be

winterized, but intact and in good visual

condition. The existing bathrooms are not

MAAB (ADA) compliant.

Fuel Oil System

The building is currently provided with oil fuel

tank, serving the existing heating equipment.

Recommendations

Domestic Water System

Based on a final occupancy count and plumbing

fixture requirements the existing 1” service

shall be evaluated and if required replaced with

a larger size service. At this time based on the

preliminary plumbing fixture count, 1 ¼” water

service shall be required. Based on the fixture

Page 23: First Parish Meeting House Interior Renovation ... Renovation. Tyngsborough, Massachusetts: Existing Conditions Report & Schematic Design : Recommendations. April 11, 2017: Table of

MEP Systems Evaluation Page I 4 March 29, 2017

count the domestic hot water system shall be

sized and provided with electric water heater or

if natural gas service is available, gas fired

tankless, on-demand water heater(s) shall be

provided. All domestic water system piping shall

be replaced with new piping, properly insulated

as required by code.

Storm System

N/A

Sanitary System

The existing sanitary system and outdoor septic

tank shall be properly serviced (pumped-out)

infilled and abandoned in place. New 4”

sanitary sewer shall be extended from the

nearby municipal sewer and connect to all new

plumbing fixtures in the building.

Grease Waste

The basement commercial kitchen plumbing

operation will be served by a dedicated grease

waste drainage that will be connected to the

sanitary system downstream from a grease

interceptor. After coordination with

Department of Health it will be determined if an

indoor floor recessed unit will be acceptable

means of grease waste collection or an outdoor

unit will be required, in addition to the interior

unit serving the three compartment sink, floor

drains and dishwasher.

Plumbing Fixtures

All existing plumbing fixtures shall be removed,

and replaced with new commercial grade

fixtures MAAB (ADA) compliant. The plumbing

fixture count determined at this time is based

on a total occupancy of 291 people and is as

follow:

o 3 female toilets

o 2 male toilets (1 can be substituted for

urinal)

o 1 sink for each sex

Fuel Oil System

If there is no natural gas available in the area

the existing oil tank shall be inspected and

replaced.

CO Detection

If the commercial kitchen is provided with an

open flame gas burning equipment the area in

proximity of that equipment shall have a CO

detection system provided and interconnected

to the equipment gas supply piping.

Page 24: First Parish Meeting House Interior Renovation ... Renovation. Tyngsborough, Massachusetts: Existing Conditions Report & Schematic Design : Recommendations. April 11, 2017: Table of

MEP Systems Evaluation Page I 5 March 29, 2017

HEATING, VENTILATING AND AIR

CONDITIONING

Summary of Existing Conditions

The building is heated with a gas fired hot water

boiler, hot water pumps and water specialties.

Hot water is distributed throughout the building

with a supply and return piping system. Spaces

are then heated with finned tube radiation. The

boiler, piping, radiators, and finned tube

radiation appears to be more than 20 years old.

The bathroom have been provided with toilet

exhaust fans, but don’t appear to be vented to

the outdoors.

There are no cooling systems or ventilation

systems currently within the spaces.

Recommendations

The existing heating system is past its useful

operating life expectancy and should be

replaced in its entirety.

Heating and cooling the new spaces shall be

provided with a new gas fired furnaces. This

will allow for zone control. New gas furnaces

will be provided in each zone. The amount of

gas furnaces and location of the gas furnace

shall depend on the space heating and cooling

requirements. The gas furnaces will either be

installed within the ceiling or floor mounted.

Air cooled condensing units shall be installed

around the perimeter of the building as

required for the cooling zones required.

Ventilation shall be provide with energy

recovery ventilators as required to meet the

code. Supply ductwork and exhaust ductwork

shall be run throughout the building from the

ERV and then extended to the outdoors. Each

room shall be provided with supply and exhaust

registers to distribute the air. The ERV units

shall be installed within the basement within

Existing Finned Tube Radiation

Existing Hot Water Boiler

Existing Hot Water Pump

Page 25: First Parish Meeting House Interior Renovation ... Renovation. Tyngsborough, Massachusetts: Existing Conditions Report & Schematic Design : Recommendations. April 11, 2017: Table of

MEP Systems Evaluation Page I 6 March 29, 2017

the mechanical room. An ERV would be

provided for the main level/mezzanine and

lower level. Bathroom exhaust shall be

provided with a bathroom exhaust fan and

exhaust ductwork extend to the outdoors.

Page 26: First Parish Meeting House Interior Renovation ... Renovation. Tyngsborough, Massachusetts: Existing Conditions Report & Schematic Design : Recommendations. April 11, 2017: Table of

MEP Systems Evaluation Page I 7 March 29, 2017

ELECTRICAL SYSTEMS

Electrical Service and Distribution

The main service originates from a utility pole

on Middlesex Road and runs overhead to a

weatherhead attached to the building. The

service enters the basement through a 1 ½”

conduit and terminates in a panelboard. The

service size is 100 amp 120/240 volt, 1-phase, 3-

wire service.

The main panelboard is a 100 amp 120/240

volt, 1-phase, 3-wire, 30-circuit panel with no

spares or spaces available. There is (1) 8-circuit

panel located adjacent to the service panel.

The panelboards are well beyond their

expected useful lives. One panel is showing

signs of a possible fire within the panel.

Recommendations

Due to the proposed elevator and condition of

the existing equipment, and the addition of

proposed HVAC, plumbing and kitchen

equipment, this report recommends

updating/replacing the existing single-phase

service with a new 400 amp, 120/208 volt, 3-

phase, 4-wire service from the same pole on

Middlesex Road. The new service would

require 4# 500 KCMIL, 1#3G 3 1/2”C from the

utility pole underground to a new meter

attached to the building. A new 400 amp

feeder would be provided (4#500 KCMIL, 1#3G

3 1/2”C) to a new 400 amp, 120/208 volt, 3-

phase, 4-wire, 42 circuit Main Circuit Breaker

panelboard. The new panel would include all

new breakers to feed existing circuits, new

proposed circuits for HVAC, plumbing and

kitchen equipment and an 80 amp, 208 volt, 3-

pole (estimated) breaker to feed the proposed

elevator.

A new electrical room, to house the new

electrical service panel should be provided. The

room will need to be approximately 5’ x 5’, with

3 feet of clearance in front of the panel for code

required work space.

q

Page 27: First Parish Meeting House Interior Renovation ... Renovation. Tyngsborough, Massachusetts: Existing Conditions Report & Schematic Design : Recommendations. April 11, 2017: Table of

MEP Systems Evaluation Page I 8 March 29, 2017

Fire Alarm

Summary of Existing Conditions

The building is protected by a 10-zone MIRCOM

FA-1000 Series fire alarm control panel. The

panel transmits signal to the Tyngsborough Fire

Department via telephone lines. The panel is 8-

10 years old. The typical expected life of a fire

alarm control panel and system is 20 years,

therefore the existing panel should be able to

function for another 10 years. The building

contains smoke detectors, manual pull stations.

The age of the devices was reported to be 25

years old. There were 2 different vintages of

pull stations. Newer horn/strobe devices were

installed 2-3 years ago.

Recommendations

The fire alarm control panel is in decent

working condition and could support the new

devices needed for the proposed elevator. The

devices are approaching the end of their life

and should be replaced during this renovation.

New smoke detectors will be required on each

elevator lobby level for elevator recall function.

A smoke and heat detector will be required for

the elevator machine room. New horn/strobe

devices will be required for the proposed

upgrades to the bathrooms. New tamper and

flow switches are being provided for he

proposed fire sprinkler system. New control

modules would be required to tie in the

switches into the fire alarm control panel. It is

recommended to provide upgrades to the

bathrooms. It is recommended to provide a

zone expander, to ensure the proposed devices

can be added to the control panel.

Page 28: First Parish Meeting House Interior Renovation ... Renovation. Tyngsborough, Massachusetts: Existing Conditions Report & Schematic Design : Recommendations. April 11, 2017: Table of

MEP Systems Evaluation Page I 9 March 29, 2017

Lighting

Summary of Existing Conditions

All of the light fixtures are inefficient, past their

expected useful life and should be replaced

with new energy efficient LED type fixtures.

Some fixtures are not supported properly and

are falling down. Some lenses are missing.

There is an existing chandelier on the main

floor, which may be retrofitted with new wiring

and new LED lamps.

Recommendations

The building’s lighting needs a complete

upgrade as soon as possible. New LED lighting

is recommended for the proposed renovated

bathrooms and new elevator lobbies. The

bathrooms should be provided with new ceiling

or wall-mounted occupancy sensors.

Emergency drivers should be included in the

new proposed light fixtures, to provide

emergency lighting in bathrooms and elevator

lobbies. New fixtures should be provided

throughout. The existing chandelier should be

retrofitted, rewired and provided with new LED

lamps.

Page 29: First Parish Meeting House Interior Renovation ... Renovation. Tyngsborough, Massachusetts: Existing Conditions Report & Schematic Design : Recommendations. April 11, 2017: Table of

MEP Systems Evaluation Page I 10 March 29, 2017

Emergency & Exit Lighting

Summary of Existing Conditions

There are approximately (2) exit

sign/emergency lights and (2) self- contained

emergency lights. These items appear to be in

good working condition. However, there is

inadequate lighting coverage and exit signage.

Recommendations

The building’s emergency and exit lighting

should be enhanced with added LED self-

contained exit signs and emergency lights. New

lighting could be provided with integral

emergency drivers, to serve as emergency

egress/lighting.

END OF REPORT

Page 30: First Parish Meeting House Interior Renovation ... Renovation. Tyngsborough, Massachusetts: Existing Conditions Report & Schematic Design : Recommendations. April 11, 2017: Table of

REPORT TO

CBI Consulting, Inc. February 16, 2017

HAZARDOUS MATERIAL INSPECTION FIRST PARISH MEETING HOUSE – 214 MIDDLESEX ROAD

TYNGSBOROUGH, MASSACHUSETTS

Submitted by:

David Gorden (AI-900459) PEER CONSULTANTS, P.C. 99 SOUTH BEDFORD STREET, SUITE 200 BURLINGTON, MA 01803 Project Number: 6698

Page 31: First Parish Meeting House Interior Renovation ... Renovation. Tyngsborough, Massachusetts: Existing Conditions Report & Schematic Design : Recommendations. April 11, 2017: Table of

PEER Consultants Page 1 2/16/2017 fpmh hazmat project 021617

1. Introduction Limited hazardous material sampling and analysis was conducted by PEER Consultants, P.C. (PEER) on the interior of the First Parish Meeting House, located at 214 Middlesex Road, Tyngsborough, Middlesex County, Massachusetts as part of its interior renovation project. The objective of this investigation was to inspect constructs, finishes, and other materials that may be affected by the project and that may contain asbestos or lead. 2. Sampling Mr. David Gorden, PEER Consultants (MA Asbestos Inspector License AI 900459 and MA lead Inspector license I-4057) surveyed the suspect asbestos containing building materials (ACBM) and lead paint at this building on January 25, 2017, and conducted a subsequent survey on February 16, 2017. Locations were selected and areas were accessed with the assistance of the architect, CBI Consulting, Inc. to facilitate the sampling of suspect building materials that may be disturbed by the future renovation proposed as part of the First Parish Meeting House renovation project. Multiple samples of suspect materials were collected to meet the requirements of the sampling protocols established in EPA regulation 40 CFR Part 763 Subpart E 763.86, (Asbestos Hazard Emergency Response Act (AHERA) and OSHA regulations. PEER collected sixty-six (66) bulk ACBM samples from thirty (30) homogeneous areas of suspect ACM. The suspect ACBM materials included gypsum board, fiberboard, tape, joint compound, ceiling tile, floor tile, caulk, mastic, transite board, laminate, veneer, coating, paint, and plaster. Suspect lead in paint samples included paint on wood, cement, and metal. PEER collected twenty-six (26) paint samples to be screened or analyzed for lead. These suspect hazardous materials are further described in the laboratory summary report within Appendices A and B. Samples were labeled with unique identifiers, and appropriate chain-of-custody documentation was completed for the samples. The suspect ACBM samples were sent to EMSL Analytical, Inc. (EMSL) of Woburn, MA for laboratory analysis. The suspect lead samples were field-screened using LeadCheck™ colorimetric paint test kits. Suspect ACBM and lead paint were assessed by PEER in readily accessible areas associated with the future renovation proposed as part of the First Parish Meeting House project. Suspect ACBM and lead paint may be present, hidden in other non-accessible areas, associated with the future renovation proposed as part of the First Parish Meeting House project. PEER did not collect samples from suspect ACBM and lead paint associated with any other portions of the building or areas on the subject property, not specifically identified in the attached chain of custody (COC). 3. Analysis Bulk asbestos samples were analyzed using Polarized Light Microscopy (PLM) coupled with dispersion staining in accordance with the Environmental Protection Agency's (EPA) "Method for the Determination of Asbestos in Bulk Building Materials" (EPA/600/R-93/116, July 1993).

Page 32: First Parish Meeting House Interior Renovation ... Renovation. Tyngsborough, Massachusetts: Existing Conditions Report & Schematic Design : Recommendations. April 11, 2017: Table of

PEER Consultants Page 2 2/16/2017 fpmh hazmat project 021617

Coating or paint samples for lead were screened by cutting and swabbing painted surfaces with LeadCheck™ colorimetric paint test kits manufactured by 3M, Inc. This procedure provides an accurate but qualitative (yes/no) confirmation of the presence of any lead paint. EMSL is accredited under the National Institute of Standards and Technology (NIST), National Voluntary Laboratory Accreditation Program (NVLAP), American Industrial Hygiene Association (AIHA), and the Commonwealth of Massachusetts Department of Labor and Workforce Development (DLWD). 4. Findings 4.1 Asbestos Visual inspection of selected materials indicated the presence of suspect ACBM including gypsum board, fiberboard, joint compound, tape, ceiling tile, floor tile, caulk, mastic, transite board, laminate, veneer, coating, paint, and plaster. Please note that the room descriptions below in the asbestos section follow the Massachusetts CLPPP Lead Inspection/Risk Assessment Report room designation template, which assigns room numbers from the street side of the building in a clockwise pattern. This is illustrated for the basement, in Figure 1, attached. Figures 2 and 3 provide existing condition information for the first and second floor of the building. The full sample log with a description of sample locations and the ACBM analytical data is provided in Appendix A. A summary of the ACBM results is provided in Table 1. An ACBM contains more than 1% asbestos and is regulated by the EPA and OSHA.

Table 1

Suspect ACBM Associated with the First Parish Meeting House Interior Renovation Project

Location Building Material

Material Description Sample ID Asbestos

(%)

Basement Room 5 Gypsum Board White Gypsum Wallboard with Paper Backing

A-1 NAD

Basement Room 5 Gypsum Board White Gypsum Wallboard with Paper Backing

A-2 NAD

Basement Room 5 Tape/Joint Compound

Tan Tape (Joint Compound) Associated with A1

A-3 NAD

Basement Room 5 Tape/Joint Compound

Tan Tape (Joint Compound) Associated with A2

A-4 NAD

Basement Room 5 Ceiling Tile White Coated Light Brown Fibrous 12x12" Ceiling Tile with Holes

A-5 NAD

Basement Room 5 Ceiling Tile White Coated Light Brown Fibrous 12x12" Ceiling Tile with Holes

A-6 NAD

Basement Room 5 Fiber Board White Coated Brown Fibrous 4'x8' Ceiling Fiber Board

A-7 NAD

Basement Room 5 Fiber Board White Coated Brown Fibrous 4'x8' Ceiling Fiber Board

A-8 NAD

Basement Room 5 Floor Tile Tan 9x9" Floor Tiles/Specks A-9A 3

Page 33: First Parish Meeting House Interior Renovation ... Renovation. Tyngsborough, Massachusetts: Existing Conditions Report & Schematic Design : Recommendations. April 11, 2017: Table of

PEER Consultants Page 3 2/16/2017 fpmh hazmat project 021617

Location Building Material

Material Description Sample ID Asbestos

(%)

Basement Room 5 Mastic Associated Black Mastic A-9B 5

Basement Room 5 Floor Tile Tan 9x9" Floor Tiles/Specks A-10A 3

Basement Room 5 Mastic Associated Black Mastic A-10B 3

Basement Room 5 Floor Tile Brown 9x9" Floor Tiles/Specks A-11A 3

Basement Room 5 Mastic Associated Black Mastic A-11B 4

Basement Room 5 Floor Tile Brown 9x9" Floor Tiles/Specks A-12A 3

Basement Room 5 Mastic Associated Black Mastic A-12B 4

Basement Room 1 Ceiling Tile White Coated Grey 12x12" Fibrous Ceiling Tile

A-13 NAD

Basement Room 1 Ceiling Tile White Coated Grey 12x12" Fibrous Ceiling Tile

A-14 NAD

Basement Room 4 Floor Tile White 12x12" Floor Tile/Specks A-15A NAD

Basement Room 4 Mastic Associated Black/Yellow Mastic A-15B 4

Basement Room 4 Floor Tile White 12x12" Floor Tile/Specks A-16A NAD

Basement Room 4 Mastic Associated Black/Yellow Mastic A-16B 4

Basement Room 4 Floor Tile Brown 12x12" Floor Tile/Specks A-17A NAD

Basement Room 4 Mastic Associated Black/Yellow Mastic A-17B 4

Basement Room 4 Floor Tile Brown 12x12" Floor Tile/Specks A-18A NAD

Basement Room 4 Mastic Associated Black/Yellow Mastic A-18B 4

Basement Boiler Room

Gypsum Board White Gypsum Wallboard A-19A NAD

Basement Boiler Room

Joint Compound

Associated Grey Joint Compound A-19B 2

Basement Boiler Room

Gypsum Board White Gypsum Wallboard A-20A NAD

Basement Boiler Room

Joint Compound

Associated Grey Joint Compound A-20B 2

Basement Boiler Room

Caulk White/Tan Caulk/Sealant on Walls A-21 3

Basement Boiler Room

Caulk White/Tan Caulk/Sealant on Walls A-22 3

Basement Boiler Room

Caulk Caulk/Sealant at Pipes on Furnace A-23 NAD

Basement Boiler Room

Caulk Caulk/Sealant at Pipes on Furnace A-24 NAD

Basement Boiler Room

Transite Board White (Black Stained) Transite Boards on Ceiling

A-25 40

Basement Boiler Room

Transite Board White (Black Stained) Transite Boards on Ceiling

A-26 40

Basement Kitchen Floor Tile Tan 12x12" Floor Tile A-27A NAD

Basement Kitchen Mastic Associated Yellow Mastic A-27B NAD

Basement Kitchen Floor Tile Tan 12x12" Floor Tile A-28A NAD

Basement Kitchen Mastic Associated Yellow Mastic A-28B NAD

Basement Kitchen Tape/Joint Compound

White Joint Tape/Compound on Ceiling I-beam

A-29 NAD

Basement Kitchen Tape/Joint Compound

White Joint Tape/Compound on Ceiling I-beam

A-30 NAD

Basement Kitchen Laminate White Coated-Brown Wall Laminate

A-31 NAD

Page 34: First Parish Meeting House Interior Renovation ... Renovation. Tyngsborough, Massachusetts: Existing Conditions Report & Schematic Design : Recommendations. April 11, 2017: Table of

PEER Consultants Page 4 2/16/2017 fpmh hazmat project 021617

Location Building Material

Material Description Sample ID Asbestos

(%)

Basement Kitchen Laminate White Coated-Brown Wall Laminate

A-32 NAD

Basement Kitchen Veneer White Tan Kitchen Counter Veneer/Glue

A-33 NAD

Basement Kitchen Veneer White Tan Kitchen Counter Veneer/Glue

A-34 NAD

Basement Kitchen Coating Black Sink Underside Coating A-35 8

Basement Kitchen Coating Black Sink Underside Coating A-36 8

Basement Kitchen Ceiling Tile White 4'x2' and 2'x2' Ceiling Tiles with Small Holes

A-37 NAD

Basement Kitchen Ceiling Tile White 4'x2' and 2'x2' Ceiling Tiles with Small Holes

A-38 NAD

Basement Bathroom Floor Tile Brown 12x12" Self-Adhesive Floor Tile (Over A15/A16)

A-39 NAD

Basement Bathroom Floor Tile Brown 12x12" Self-Adhesive Floor Tile (Over A17/A18)

A-40 NAD

Basement Room 1 Mastic Green/Yellow Mastic on Styrofoam Behind Wood Laminate Board

A-41 5

Basement Room 1 Mastic Green/Yellow Mastic on Styrofoam Behind Wood Laminate Board

A-42 5

Basement Room 1 Mastic Yellow Brown Mastic on Wood Board on Wall

A-43 5

Basement Room 1 Mastic Yellow/Brown Mastic on Wood Board on Wall

A-44 5

Basement Room 1 Paint Green Textured Paint on Cement Wall

A-45 NAD

Basement Room 1 Paint Green Textured Paint on Cement Wall

A-46 NAD

1st Floor/Sanctuary Plaster White Skim Coat Plaster A-47A NAD

1st Floor/Sanctuary Plaster Associated Light Grey Base Coat Plaster

A-47B NAD

1st Floor/Sanctuary Plaster White Skim Coat Plaster A-48A NAD

1st Floor/Sanctuary Plaster Associated Light Grey Base Coat Plaster

A-48B NAD

1st Floor/Sanctuary Plaster White Skim Coat Plaster A-49A NAD

1st Floor/Sanctuary Plaster Associated Light Grey Base Coat Plaster

A-49B NAD

1st Floor/Sanctuary Plaster White Skim Coat Plaster A-50A NAD

1st Floor/Sanctuary Plaster Associated Light Grey Base Coat Plaster

A-50B NAD

1st Floor/Sanctuary Plaster White Skim Coat Plaster A-51A NAD

1st Floor/Sanctuary Plaster Associated Light Grey Base Coat Plaster

A-51B NAD

1st Floor/Sanctuary Plaster White Skim Coat Plaster A-52A NAD

1st Floor/Sanctuary Plaster Associated Light Grey Base Coat Plaster

A-52B NAD

1st Floor/Sanctuary Plaster White Skim Coat Plaster A-53A NAD

1st Floor/Sanctuary Plaster Associated Light Grey Base Coat Plaster

A-53B NAD

Page 35: First Parish Meeting House Interior Renovation ... Renovation. Tyngsborough, Massachusetts: Existing Conditions Report & Schematic Design : Recommendations. April 11, 2017: Table of

PEER Consultants Page 5 2/16/2017 fpmh hazmat project 021617

Location Building Material

Material Description Sample ID Asbestos

(%)

1st Floor/Stair Hall Caulk White/Grey Window Glazing Caulk A-54 NAD

1st Floor/Stair Hall Caulk White/Grey Window Glazing Caulk A-55 NAD

2nd Floor/Office Ceiling Tile White 2x2' Ceiling Tile with Holes & Ridges

A-56 NAD

2nd Floor/Office Ceiling Tile White 2x2' Ceiling Tile with Holes & Ridges

A-57 NAD

2nd Floor/Office Plaster White Skim Coat Plaster A-58A NAD

2nd Floor/Office Plaster Associated Light Grey Base Coat A-58B NAD

2nd Floor/Office Plaster White Skim Coat Plaster A-59A NAD

2nd Floor/Office Plaster Associated Light Grey Base Coat A-59B NAD

2nd Floor/Office Plaster White Skim Coat Plaster A-60A NAD

2nd Floor/Office Plaster Associated Light Grey Base Coat A-60B NAD

2nd Floor/Office Ceiling Tile White 2x2' Ceiling Tile with Small Holes

A-61 NAD

2nd Floor/Office Ceiling Tile White 2x2' Ceiling Tile with Small Holes

A-62 NAD

1st Floor/Pew Caulk White Frame Caulk Around New Vinyl Windows

A-63 NAD

1st Floor/Pew Caulk White Frame Caulk Around New Vinyl Windows

A-64 NAD

Basement/Rooms 1 through 5

Joint Compound

White Joint Compound Associated with the Gypsum Board/Fiberboard Walls and Ceiling

A-65 NAD

Basement/Rooms 1 through 5

Joint Compound

White Joint Compound Associated with the Gypsum Board/Fiberboard Walls and Ceiling

A-66 NAD

Notes: NAD = No Asbestos Detected (in the sample)

4.2 Lead Paint Suspect lead paint surfaces included wood, cement, and metal. A paint which contains more than 0.5% lead is considered a lead paint and is regulated by the EPA. The OSHA Lead in Construction Standard (29 CFR 1926.62) applies to all construction work where an employee may be occupationally exposed to lead. The full sample log with a description of sample locations and the lead paint screening data is provided in Appendix B. A summary of the lead paint results is provided in Table 2.

Page 36: First Parish Meeting House Interior Renovation ... Renovation. Tyngsborough, Massachusetts: Existing Conditions Report & Schematic Design : Recommendations. April 11, 2017: Table of

PEER Consultants Page 6 2/16/2017 fpmh hazmat project 021617

Table 2

Suspect Lead Paint Associated with the First Parish Meeting House Interior Renovation Project

Area Material Paint Color Screening

(Yes or No)

Sample ID

1st Floor Ceiling tin – sanctuary Pink/tan Yes L1

Basement Wood trim – door White No L2

Basement Gypsum wallboard – room 5 White No L3

Basement Gypsum wallboard – room 3 Tan No L4

Basement Metal I-beam – kitchen White No L5

Basement Cement wall – room 1 White No L6

Basement Cement wall – room 1 Green No L7

Basement Metal pole – room 1 Brown No L8

Exterior Wood clapboard White/green Yes L9

Basement – 1st Floor

Wood floor – stairs Light green Yes L10

1st Floor Plaster wall – gathering hall Tan/light green Yes L11

1st Floor Wood door – gathering hall White/light green Yes L12

1st Floor Wood pew – sanctuary Tan/dark green Yes L13

1st Floor Wood pew - sanctuary Brown/black/dark green

Yes L14

1st Floor Wood floor – sanctuary Light brown shellac No L15

1st Floor Plaster wall – sanctuary Tan/light green Yes L16

1st Floor Wood sill – sanctuary White/tan Yes L17

1st – 2nd Floor Wood floor – stairs Gray Yes L18

1st – 2nd Floor Plaster wall – stairwell White Yes L19

1st – 2nd Floor Plaster ceiling – stairwell White Yes L20

1st – 2nd Floor Wood sash – stairwell White Yes L21

2nd Floor Wood floor – observation hall Brown shellac No L22

2nd Floor Wood window – observation hall

White Yes L23

2nd Floor Wood wallboard – storage White Yes L24

2nd Floor Plaster wall – storage White No L25

2nd Floor Wood door - storage White Yes L26

Notes: Analytical: Regulated Lead Paint contains > 0.5% lead (Pb) Screening: No = Concentration <0.2% lead (Pb), Yes = Concentration >0.2% lead (Pb)

5. Discussion and Conclusions 5.1 Asbestos Inspection and sampling of suspect ACBM identified the presence of asbestos containing materials by laboratory analysis. The following homogeneous areas of suspect ACBM contained > 1% asbestos:

Page 37: First Parish Meeting House Interior Renovation ... Renovation. Tyngsborough, Massachusetts: Existing Conditions Report & Schematic Design : Recommendations. April 11, 2017: Table of

PEER Consultants Page 7 2/16/2017 fpmh hazmat project 021617

Interior:

Tan 9” x 9” floor tiles with specks in the basement

Brown 9” x 9” floor tiles with specks in the basement

Black mastic associated with 9” x 9” floor tiles with specks, and brown 9” x 9” floor tiles with specks in the basement

Black/yellow mastic associated with white 12” x 12” floor tiles with specks and brown 12” x 12” floor tiles with specks in the basement

Grey joint compound on the gypsum board walls in the boiler room in the basement

White/tan caulk/sealant on the gypsum board walls in the boiler room in the basement

Black-stained white transite board on the ceiling of the boiler room in the basement

Black coating on the underside of the two sinks in the kitchen of the basement

Green/yellow mastic on the wood laminate board attached to the Styrofoam insulation on the concrete/granite walls of the basement

Green/yellow mastic on the Styrofoam insulation on the concrete/granite walls of the basement

The following additional building materials are assumed to contain >1% asbestos: furnace in the basement, window caulking in the basement. In the Commonwealth of Massachusetts, asbestos activities are regulated by the Massachusetts Department of Environmental Protection (DEP) under 310 CMR 7.15 and by the Massachusetts Department of Labor Standards (DLS) under 453 CMR 6.00. Massachusetts regulations require that any asbestos-related activity conducted in the Commonwealth be performed by a contractor and workers licensed by DLS. Asbestos abatement must be performed in accordance with a Project Design prepared by a MA-Licensed Asbestos Designer. Third-party air monitoring must be conducted at the completion of abatement activities. 5.2 Lead The EPA regulates use, removal, and disposal of lead-based paint (LBP) and OSHA regulates lead exposure to workers. The EPA defines lead-based paint as paint, varnish, stain, or other applied coating that contains lead equal to or greater than 1.0 mg/cm2; 5,000 mg/kg, or 0.5% by dry weight as determined by laboratory analysis. The following paint was screened by PEER to contain >0.2% lead in paint.

White paint on the plaster wall, plaster ceiling, and wood sash in the stairwell between the 1st and 2nd floor

White paint on the wooden window, wallboard, and door on the second floor

Brown/black/dark green and tan/dark green paint associated with the sanctuary pews on the 1st floor

Tan/light green paint associated with the plaster wall of the sanctuary and gathering hall on the 1st floor

Gray paint on the wooden stairs between the 1st and 2nd floors

Light green paint on the wooden stairs between the basement and 1st floors

Pink/tan paint on the tin ceiling within the sanctuary on the 1st floor

Page 38: First Parish Meeting House Interior Renovation ... Renovation. Tyngsborough, Massachusetts: Existing Conditions Report & Schematic Design : Recommendations. April 11, 2017: Table of

PEER Consultants Page 8 2/16/2017 fpmh hazmat project 021617

White/light green paint on the wooden door in the gathering hall on the 1st floor

White/tan paint on the wooden window sill in the sanctuary on the 1st floor

White/green wooden clapboards on the exterior of the building In addition, there may be additional areas of paint, which may contain lead, which may not have been screened as part of the results within Table 2.

The OSHA Lead in Construction Standard (29 CFR 1926.62) applies to all construction work where an employee may be occupationally exposed to lead. The lead-in-construction standard applies to any detectable concentration of lead in paint, as even very low concentrations of lead can result in unacceptable employee exposures depending upon on the method of removal and other workplace conditions. All work related to construction, alteration, or repair (including painting and decorating) must include provisions for worker safety and protection as specified in these standards. The EPA Renovation, Repair and Painting Rule (40 CFR Part 745) and MA Division of Occupational Safety (DOS) 454 CMR 22) Lead Safe Renovation Regulations must be followed in target housing and schools. This building did not appear to be currently operating as target housing or a school. 6. Abatement Cost Estimate 6.1 Asbestos Abatement Costs Asbestos abatement costs were estimated based on the presence of asbestos (>1%) in the following materials at the First Parish Meeting House. The abatement cost for removal of these materials prior to renovation or demolition is estimated in the following table. Please note that the abatement of the assumed asbestos-containing window sealants in the basement is easiest to conduct during removal of the entire window system and the cost typically adds a factor of approximately 1.5 times the window removal cost. If this basement window system can be made accessible, PEER would be able to collect samples of caulk from the window system for ACM analysis.

Estimated Asbestos Abatement Cost at First Parish Meeting House

Item Material Estimated Quantity

Unit Cost ($)

Total Cost ($)

Floor tiles, glue/mastic (1)

Tan 9” x 9” floor tiles with specks in the basement, Brown 9” x 9” floor tiles with specks in the basement, Black mastic associated with 9” x 9” floor tiles with specks, and brown 9” x 9” floor tiles with specks in the basement, Black/yellow mastic associated with white 12” x 12” floor tiles with specks and brown 12” x 12” floor tiles with specks in the basement (and other homogenous areas).

2,600 (SF) 5-7/SF 13,000-18,200

Joint compound, caulk, sealant (2)

Grey joint compound on the gypsum board walls in the boiler room in the basement, white/tan caulk/sealant on the gypsum board walls in the boiler room in the basement.

1,100 SF 10-15/SF 11,000-16,500

Page 39: First Parish Meeting House Interior Renovation ... Renovation. Tyngsborough, Massachusetts: Existing Conditions Report & Schematic Design : Recommendations. April 11, 2017: Table of

PEER Consultants Page 9 2/16/2017 fpmh hazmat project 021617

Item Material Estimated Quantity

Unit Cost ($)

Total Cost ($)

Transite Board

Black-stained, white transite board on the ceiling of the boiler room in the basement

200 SF 10-15/SF 2,000-3,000

Kitchen Sink

Black coating on the underside of the two sinks in the kitchen of the basement

1 Unit

250 250

Mastic (3) Green/yellow mastic on the wood laminate board attached to the Styrofoam insulation on the concrete/granite walls of the basement, Green/yellow mastic on the Styrofoam insulation on the concrete/granite walls of the basement

900 SF 5-7/SF 4,500-6,300

Caulk Assumed caulk (>1% asbestos) basement windows 6 Units 150-200 900-1,200

Thermal System Insulation

Assumed furnace TSI (>1% asbestos) 1 Unit 1,000-2,500

1,000-2,500

(1) Unit cost is based on removal of carpet, multiple layers of tile, and mastic on concrete. (2) Unit cost is based on removal of only gypsum board walls in the boiler room in the basement. (3) Unit cost is based on disposal of Styrofoam and wood laminate board as part of waste stream.

This material occurs in the basement behind the interior walls of Rooms 1, 3 through 5, the bathrooms, and is presumed behind the kitchen wall.

6.2 Lead Disposal Costs As per Section 5.2, lead paint containing materials were identified on building materials within the 1st and 2nd floors, as well as in the wooden clapboards on the exterior of the building. A Toxicity Characteristic Leachate Procedure (TCLP) analysis was not requested by the Client as part of this project. Since many of the painted items may not be disposed of or abated as part of the asbestos abatement, PEER suggests that the architect for the project carry a financial contingency for hazardous waste disposal from the First Parish Meeting House project. 6.3 Universal Waste According to the Code of Federal Regulations (CFR) Title 40, Chapter 1, Subchapter 1, Part 273, Universal Waste means any of the following hazardous wastes that are subject to the universal waste requirements of this part 273: • Batteries as described in §273.2; • Pesticides as described in §273.3; • Mercury-containing equipment as described in §273.4; and • Lamps as described in §273.5. The following universal wastes or other items which could be recycled may be present, associated with the project building: fluorescent lamps, compact fluorescent light bulbs, polychlorinated biphenyl (PCB) ballast, high-intensity discharge (HID) lamps, mercury thermostats and switches, batteries, cathode ray tubes (CRTs), electronic waste, refrigeration and cooling system Freon and other chlorofluorocarbons (CFCs), air conditioners, smoke detectors, exit displays.

Page 40: First Parish Meeting House Interior Renovation ... Renovation. Tyngsborough, Massachusetts: Existing Conditions Report & Schematic Design : Recommendations. April 11, 2017: Table of

PEER Consultants Page 10 2/16/2017 fpmh hazmat project 021617

Figure 1 Basement Layout – Existing Conditions

Room 5

Room 2

Room 3

Room 4

Room 1

Kitchen

Boiler

Bathrooms

Page 41: First Parish Meeting House Interior Renovation ... Renovation. Tyngsborough, Massachusetts: Existing Conditions Report & Schematic Design : Recommendations. April 11, 2017: Table of

PEER Consultants Page 11 2/16/2017 fpmh hazmat project 021617

Figure 2 First Floor – Existing Conditions

Gathering Hall

Stair

Sanctuary

Page 42: First Parish Meeting House Interior Renovation ... Renovation. Tyngsborough, Massachusetts: Existing Conditions Report & Schematic Design : Recommendations. April 11, 2017: Table of

PEER Consultants Page 12 2/16/2017 fpmh hazmat project 021617

Figure 3 Second Floor – Existing Conditions

Observation Hall

Office

Storage Stairs

Page 43: First Parish Meeting House Interior Renovation ... Renovation. Tyngsborough, Massachusetts: Existing Conditions Report & Schematic Design : Recommendations. April 11, 2017: Table of

PEER Consultants Page 13 2/16/2017 fpmh hazmat project 021617

Appendix A Asbestos Sample Log and Analytical Data

Page 44: First Parish Meeting House Interior Renovation ... Renovation. Tyngsborough, Massachusetts: Existing Conditions Report & Schematic Design : Recommendations. April 11, 2017: Table of
Page 45: First Parish Meeting House Interior Renovation ... Renovation. Tyngsborough, Massachusetts: Existing Conditions Report & Schematic Design : Recommendations. April 11, 2017: Table of
Page 46: First Parish Meeting House Interior Renovation ... Renovation. Tyngsborough, Massachusetts: Existing Conditions Report & Schematic Design : Recommendations. April 11, 2017: Table of
Page 47: First Parish Meeting House Interior Renovation ... Renovation. Tyngsborough, Massachusetts: Existing Conditions Report & Schematic Design : Recommendations. April 11, 2017: Table of
Page 48: First Parish Meeting House Interior Renovation ... Renovation. Tyngsborough, Massachusetts: Existing Conditions Report & Schematic Design : Recommendations. April 11, 2017: Table of
Page 49: First Parish Meeting House Interior Renovation ... Renovation. Tyngsborough, Massachusetts: Existing Conditions Report & Schematic Design : Recommendations. April 11, 2017: Table of
Page 50: First Parish Meeting House Interior Renovation ... Renovation. Tyngsborough, Massachusetts: Existing Conditions Report & Schematic Design : Recommendations. April 11, 2017: Table of
Page 51: First Parish Meeting House Interior Renovation ... Renovation. Tyngsborough, Massachusetts: Existing Conditions Report & Schematic Design : Recommendations. April 11, 2017: Table of

EMSL Analytical, Inc.5 Constitution Way, Unit A Woburn, MA 01801

Tel/Fax: (781) 933-8411 / (781) 933-8412

http://www.EMSL.com / [email protected]

131700658EMSL Order:

Customer ID: PEER42

Customer PO: 6698

Project ID:

Attention: Phone:Dave Gorden (781) 238-8880

Fax:PEER Consultants (781) 238-8884

Received Date:99 South Bedford Street 02/16/2017 11:40 AM

Analysis Date:Suite 200 02/16/2017

Collected Date:Burlington, MA 01803 02/16/2017

Project: 6698

Test Report: Asbestos Analysis of Bulk Materials via EPA 600/R-93/116 Method using Polarized

Light Microscopy

Sample Description Appearance % Fibrous % Non-Fibrous

Non-Asbestos Asbestos

% Type

A65

131700658-0001

None DetectedNon-fibrous (Other)100%White

Non-Fibrous

Homogeneous

GB Walls & Ceilings

in Rooms 1-5 - White

Joint Compound

A66

131700658-0002

None DetectedNon-fibrous (Other)100%White

Non-Fibrous

Homogeneous

GB Walls & Ceilings

in Rooms 1-5 - White

Joint Compound

Analyst(s)

Michael Mink (2) Steve Grise, Laboratory Manager

or Other Approved Signatory

EMSL maintains liability limited to cost of analysis . This report relates only to the samples reported and may not be reproduced, except in full, without written approval by EMSL. EMSL bears no

responsibility for sample collection activities or analytical method limitations. Interpretation and use of test results are the responsibility of the client. This report must not be used by the client to claim

product certification, approval, or endorsement by NVLAP, NIST or any agency of the federal government . Non-friable organically bound materials present a problem matrix and therefore EMSL

recommends gravimetric reduction prior to analysis. Samples received in good condition unless otherwise noted. Estimated accuracy, precision and uncertainty data available upon request. Unless

requested by the client, building materials manufactured with multiple layers (i.e. linoleum, wallboard, etc.) are reported as a single sample. Reporting limit is 1%

Samples analyzed by EMSL Analytical, Inc. Woburn, MA NVLAP Lab Code 101147-0, CT PH-0315, MA AA000188, RI AAL-107T3, VT AL998919, Maine Bulk Asbestos BA039

Initial report from: 02/16/2017 12:34:36

Page 1 of 1ASB_PLM_0008 - 1.71 Printed: 2/16/2017 12:34 PM

Page 52: First Parish Meeting House Interior Renovation ... Renovation. Tyngsborough, Massachusetts: Existing Conditions Report & Schematic Design : Recommendations. April 11, 2017: Table of
Page 53: First Parish Meeting House Interior Renovation ... Renovation. Tyngsborough, Massachusetts: Existing Conditions Report & Schematic Design : Recommendations. April 11, 2017: Table of
Page 54: First Parish Meeting House Interior Renovation ... Renovation. Tyngsborough, Massachusetts: Existing Conditions Report & Schematic Design : Recommendations. April 11, 2017: Table of
Page 55: First Parish Meeting House Interior Renovation ... Renovation. Tyngsborough, Massachusetts: Existing Conditions Report & Schematic Design : Recommendations. April 11, 2017: Table of
Page 56: First Parish Meeting House Interior Renovation ... Renovation. Tyngsborough, Massachusetts: Existing Conditions Report & Schematic Design : Recommendations. April 11, 2017: Table of
Page 57: First Parish Meeting House Interior Renovation ... Renovation. Tyngsborough, Massachusetts: Existing Conditions Report & Schematic Design : Recommendations. April 11, 2017: Table of

OrderID: 131700658

Page 1 Of 1

Page 58: First Parish Meeting House Interior Renovation ... Renovation. Tyngsborough, Massachusetts: Existing Conditions Report & Schematic Design : Recommendations. April 11, 2017: Table of

PEER Consultants Page 14 2/16/2017 fpmh hazmat project 021617

Appendix B Lead Screening Data

Page 59: First Parish Meeting House Interior Renovation ... Renovation. Tyngsborough, Massachusetts: Existing Conditions Report & Schematic Design : Recommendations. April 11, 2017: Table of
Page 60: First Parish Meeting House Interior Renovation ... Renovation. Tyngsborough, Massachusetts: Existing Conditions Report & Schematic Design : Recommendations. April 11, 2017: Table of
Page 61: First Parish Meeting House Interior Renovation ... Renovation. Tyngsborough, Massachusetts: Existing Conditions Report & Schematic Design : Recommendations. April 11, 2017: Table of

© 2017 Code Red Consultants, LLC. All Rights Reserved.

First Parish Meeting Hall Renovation Project 214 Middlesex Road, Tyngsborough, MA

Existing Building Code Report

March 2, 2017

Prepared for:

CBI Consulting, Inc.

350 Dorchester Avenue Boston, MA 02127

Page 62: First Parish Meeting House Interior Renovation ... Renovation. Tyngsborough, Massachusetts: Existing Conditions Report & Schematic Design : Recommendations. April 11, 2017: Table of

March 2, 2017 Project #: 165086

Page 2

Table of Contents 1. Introduction ........................................................................................................................................ 3

1.1 Existing Building Description .................................................................................................. 3

1.2 Project Description ..................................................................................................................... 4

2. Applicable Codes ............................................................................................................................... 5

3. Existing Building Code Scoping Requirements ............................................................................. 6

4. Compliance Method & Classification of Work .............................................................................. 6

5. Existing Building Summary.............................................................................................................. 7

6. MEBC Analysis ................................................................................................................................... 8

6.1 Use and Occupancy Classifications ......................................................................................... 8

6.2 Building Construction ............................................................................................................... 8

6.3 Vertical Openings ....................................................................................................................... 9

6.4 Interior Walls and Partitions .................................................................................................. 10

6.5 Interior Finishes ........................................................................................................................ 13

6.6 Fire Protection Systems ........................................................................................................... 13

6.7 Emergency Systems ................................................................................................................. 15

6.8 Means of Egress ........................................................................................................................ 15

6.9 Structural ................................................................................................................................... 22

6.10 Accessibility .............................................................................................................................. 23

6.11 Energy Use ................................................................................................................................ 25

6.12 Plumbing Fixtures .................................................................................................................... 25

Appendix A: Occupant Load and Exit Capacity Analysis ................................................................. 28

Page 63: First Parish Meeting House Interior Renovation ... Renovation. Tyngsborough, Massachusetts: Existing Conditions Report & Schematic Design : Recommendations. April 11, 2017: Table of

March 2, 2017 Project #: 165086

Page 3

1. Introduction CBI Consulting has retained Code Red Consultants to provide fire protection, life safety and accessibility code consulting services for the First Parish Meeting House renovation project located in Tyngsborough, MA.

This document has been prepared to describe the overall code compliance approach to active and passive fire protection and life safety systems in the building in the context of the renovation project proposed. Additionally, this report has been prepared to meet the requirements of Section 101.5.4.0 of the Massachusetts Existing Building Code, which requires the written submission of an investigation and evaluation in accordance with its requirements as a condition of permit.

The information contained within this report is based on a site survey completed on January 25, 2017 by Paul Moan, P.E. of Code Red Consultants.

1.1 Existing Building Description

The existing First Parish Meeting House is a one-story building with a below-grade Basement and mezzanine. The building houses main gathering functions in the primary First Floor sanctuary area and smaller gathering and educational functions in the Basement. The mezzanine area houses non-public office and storage spaces. The building also contains an unoccupied attic above the Mezzanine that provides access to the bell tower.

FIGURE 1: EXISTING LOT CONFIGURATION

FIGURE 2: EXISTING BUILDING

Page 64: First Parish Meeting House Interior Renovation ... Renovation. Tyngsborough, Massachusetts: Existing Conditions Report & Schematic Design : Recommendations. April 11, 2017: Table of

March 2, 2017 Project #: 165086

Page 4

1.2 Project Description

Based on the project concept plans and conversations with CBI, it is our understanding that the project to the First Parish Meeting House will consist of the following:

Full renovation of the Basement to reconfigure the meeting areas, relocate the existing kitchen, and provide new accessible toilet rooms.

Provide a LULA within the existing footprint to provide vertical access between the Basement and First Floor.1

Construct new exterior ramps for accessible access to the building entrances and exits. Remove a single wall on the Mezzanine to open up the space. The only reconfigurations of walls and doors on the First Floor are those associated

with the new LULA and new exterior doors. The primary sanctuary area is expected to remain in its current configuration.

No addition or change of occupancy is planned as part of the project.

1 The LULA is required to serve the mezzanine if the mezzanine contains public areas.

Page 65: First Parish Meeting House Interior Renovation ... Renovation. Tyngsborough, Massachusetts: Existing Conditions Report & Schematic Design : Recommendations. April 11, 2017: Table of

March 2, 2017 Project #: 165086

Page 5

2. Applicable Codes Building 780 CMR - Massachusetts State Building Code 8th Edition, which is

an amended version of the 2009 International Building Code (IBC).2

780 CMR 34.00 is deleted and replaced by the Massachusetts Existing Building Code (MEBC), which is an amended version of the 2009 International Existing Building Code (IEBC).

Fire Code 527 CMR - Massachusetts Comprehensive Fire Safety Code which is an amended version of the 2012 Edition of NFPA 1.

Plumbing Code 248 CMR 10.00 - Uniform State Plumbing Code.

Electrical Code 527 CMR 12.00 – Massachusetts Electrical Code, which is an amended version of the 2017 Edition of NFPA 70, National Electrical Code.

Mechanical Code International Mechanical Code (IMC) 2009 Edition as amended by 780 CMR 28.00.

Energy Code 2015 Edition of the International Energy Conservation Code (IECC) as amended by the State of Massachusetts.

Elevator Code 524 CMR - Massachusetts Board of Elevator Regulations, which adopts and amends the 2004 Edition of ANSI A 17.1, Safety Code for Elevators and Escalators.

Accessibility Regulations

521 CMR - Architectural Access Board (AAB) Rules and Regulations

2010 ADA Standards for Accessible Design

Other Various National Fire Protection Association (NFPA) codes and standards as referenced by the codes listed above.

This report addresses the key features of these codes and standards. The primary intent of this document is to (1) coordinate the fire protection and life safety approach between all design disciplines, (2) demonstrate building, fire and life safety code compliance to the Authorities Having Jurisdiction, and (3) serve as a record document for the building owner. Details of compliance are left to the construction documents and the contractors. This report is intended to address code requirements as enforced by Authorities Having Jurisdiction only. It is the responsibility of the design team to ensure that any owner or insurance carrier requirements, which may exceed the provisions of the applicable codes and standards, are met.

2 The 9th Edition of 780 CMR is planned to be adopted on July 1, 2017 and is expected to include a 6-month concurrency period during which either edition is permitted to be used. It is expected that this project will be design and permitted using the 8th Edition.

Page 66: First Parish Meeting House Interior Renovation ... Renovation. Tyngsborough, Massachusetts: Existing Conditions Report & Schematic Design : Recommendations. April 11, 2017: Table of

March 2, 2017 Project #: 165086

Page 6

3. Existing Building Code Scoping Requirements Portions of an existing building undergoing repair, alteration, addition, or a change in use are subject to the requirements of the MEBC. In general, existing materials and conditions can remain provided they were installed in accordance with the code at the time of original installation and are not deemed a hazardous condition by an authority having jurisdiction (AHJ). Work to existing buildings is required to be performed in accordance with 780 CMR for new construction unless otherwise specified by the MEBC. Alterations to existing buildings are not permitted to reduce the level of safety currently provided within the building unless the portion altered complies with the requirements of 780 CMR for new construction.

Except for structural work, where compliance with the code is impractical due to construction difficulties or regulatory conflicts, building officials are permitted to approve compliance alternatives. Any compliance alternatives being sought are required to be identified on the submittal documents (MEBC 101.5.0.1).

4. Compliance Method & Classification of Work The MEBC has three different compliance methods that can be used to evaluate a renovation project:

Prescriptive Method (MEBC Chapter 3) Work Area Method (MEBC Chapters 4-10) Performance Method (MEBC Chapter 13)

Based on the proposed scope of work, the Work Area Method has been selected to evaluate this project in accordance with MEBC Section 101.5.

The proposed scope of work includes alterations of more than 50% of the aggregate floor area. As such, the proposed work is classified as a Level 3 Alteration. The project is required to comply with MEBC Chapters 6, 7, and 8.

There will not be a change of occupancy or addition as part of the project.

Page 67: First Parish Meeting House Interior Renovation ... Renovation. Tyngsborough, Massachusetts: Existing Conditions Report & Schematic Design : Recommendations. April 11, 2017: Table of

March 2, 2017 Project #: 165086

Page 7

5. Existing Building Summary The following summary of the First Parish Meeting House is based on the site survey completed Code Red Consultants and information provided CBI Consulting, Inc.

Use and Occupancy: Primary Use(s): Group A-3, Assembly (First Floor & Basement) Group S-2 (Mezzanine)

Accessory Use(s): Groups S-2, Storage (First Floor & Basement)

Construction Type:

The building consists of non-rated, combustible interior structural members, and combustible exterior walls, which is consistent with Type VB construction.

Height: 1 story above grade with a basement, mezzanine, and unoccupied attic. The Basement is classified as a level below grade (780 CMR 202). The mezzanine is classified as a true “mezzanine” as the area does not exceed 1/3 of the area of the First Floor, and the calculated occupant load is less than 10 people (see occupant load analysis in Appendix A) (780 CMR 505.2 & 505.4(1)).

Area: Approximate Footprint Area: 2,700 sf Approximate Aggregate Area: 5,900 sf (including mezzanine)

Vertical Openings: Two interior exit stairs are provided, one that connects the Basement and First Floor, and one that connects the First Floor and Mezzanine. The stair enclosures and associated doors are not fire-resistance rated.

The main sanctuary area is a double-height space is architecturally separated from the mezzanine by non-rated partitions.

Automatic Sprinkler System:

The building is not provided with an automatic sprinkler system, nor is it provided with a kitchen hood suppression system.

Fire Alarm System:

A fire alarm system is provided throughout building and consisting of visual & audible notification, smoke detection throughout the building, heat detection in the kitchen, and manual pull stations.

Means of Egress (existing):

Basement: Served by two exit stairs. First Floor: Served by two doors to the exterior at the front of the building. Mezzanine: Served by a single exit stair. See Appendix A which contains an occupant load and exit capacity analysis for the new building.

Exit Signage and Emergency Lighting:

Emergency lighting was sporadically provided within the building and is powered by battery backup. Internally illuminated exit signage was provided at most stair doors and doors to the exterior. Adequate exit signage coverage was not provided within all rooms.

Page 68: First Parish Meeting House Interior Renovation ... Renovation. Tyngsborough, Massachusetts: Existing Conditions Report & Schematic Design : Recommendations. April 11, 2017: Table of

March 2, 2017 Project #: 165086

Page 8

6. MEBC Analysis The following analysis has been prepared to illustrate compliance with the requirements of the MEBC based on the compliance method and classification of work identified above. This section of the report focuses on the existing building code requirements. In general, new work is required to comply with the new construction requirements of 780 CMR unless otherwise stated herein (MEBC 602.4 & 701.3).

6.1 Use and Occupancy Classifications

6.1.1 Primary Occupancies

The building contains Group A-3, Assembly occupancies (Sanctuary, Gathering/Education Areas) on the Basement & First Floor and Group B, Business or Group S-2, Storage occupancy on the Mezzanine. The building is designed as a non-separated mixed occupancy (780 CMR 508.3).

6.1.2 Accessory Occupancies

The building also contains accessory Group S-2, Storage occupancies (780 CMR 508.2.1) on the Basement & First Floor.

6.2 Building Construction

6.2.1 Construction Classification and Occupancy Approach

The building is constructed of a combustible, unprotected structure, consistent with Type VB Construction.

Table 1 indicates the minimum fire-resistance ratings required for the structure (780 CMR 601).

Fire Resistance Rating of Building Elements Building Element Type VB Construction

Primary Structural Frame 0 Hour

Interior Bearing Walls 0 Hour

Exterior Bearing Walls 0 Hour

Exterior Nonbearing Walls See Section 6.2.3

Floor construction and secondary members 0 Hours

Roof construction and secondary members 0 Hour

TABLE 1: FIRE-RESISTANCE RATINGS

Page 69: First Parish Meeting House Interior Renovation ... Renovation. Tyngsborough, Massachusetts: Existing Conditions Report & Schematic Design : Recommendations. April 11, 2017: Table of

March 2, 2017 Project #: 165086

Page 9

6.2.2 Building Height and Area

As the project scope does not include an addition or a change of occupancy, a height and area analysis is not required to be completed (MEBC 912.5 & 1002).

6.2.3 Exterior Walls

No work to the exterior walls of the building are planned and existing portions of the façade are permitted to remain (MEBC 601.2).

6.3 Vertical Openings

The existing building contains two non-rated exit stairs, one which connects the Basement and First Floor (Stair 1), and the other which connects the First Floor and the Mezzanine (Stair 2). There is also a non-rated stair that serves as a means of egress from the Basement Level and discharges occupants directly to the exterior at grade (Rear Stair). The interior face of the rear stair enclosure coincides with the exterior wall of the Sanctuary on the First Floor.

As part of the project, the following work will occur to the vertical openings:

Stair 1 will be removed. The resulting space will be infilled with floor construction consistent with the construction type of the building.

A new LULA will be installed connecting the Basement and First Floor. The new LULA is required to be enclosed in a 1-hour fire-resistance rated shaft (780 CMR 708.2). This rated enclosure is required to be supported with 1-hour rated construction, which the existing floors are not capable of without upgrades (780 CMR 707.5.1).

Stair 2 will be extended down to also serve the Basement (resulting stair will connect two stories and a mezzanine). The existing Rear Stair will remain and continue to serve the Basement.

The compliance options for the Rear Stair and Stair 2 are as follows:

o Option 1: Rate Rear Stair

Enclose the Rear Stair in 30-minute construction (MEBC 703.2.1(4) & 803.1).

Remove the enclosure around Stair 2 on the First Floor, and design Stair 2 as an unenclosed exit access stair in accordance with 780 CMR Sections 708.2(11) & 1016.1(3)). For the use of this exception, the stair is required to be open on the Basement and First Floor. If an enclosure is provided, then it is required to be 1-hour rated per the second option below.

o Option 2: Rate Stair 2

The Rear Stair is permitted to remain in its existing non-rated condition (780 CMR 708.2(11) & 1016.1(3)).

Enclose Stair 2 in 1-hour FRR construction. The rating is minimally required to enclose the Basement and First Floors and can either (1) extend the rating up

Page 70: First Parish Meeting House Interior Renovation ... Renovation. Tyngsborough, Massachusetts: Existing Conditions Report & Schematic Design : Recommendations. April 11, 2017: Table of

March 2, 2017 Project #: 165086

Page 10

through the mezzanine, or (2) be separated from the stair traveling up to the mezzanine by 1-hour construction.

o Option 3: Sprinkler Entire Building

If the building is sprinklered throughout, the rear stair is permitted to remain as is and Stair 2 is permitted to be either open or 1-hour rated between the Basement and First Floor (MEBC 703.2.1 Exception 1 & 780 CMR 1016.1 Exception 4).

o Option 4: 9th Edition Submission/Variance

Under the 9th Edition, option 3 above is permitted in a non-sprinklered building (2015 IEBC 803.2.1 Exception 1 & 2015 IBC 1019.3-1). This allowance could be used if the project is filed under the 9th Edition (either by waiting until it is adopted or by submitting for a variance).

A shaft enclosure that does not extend to the underside of the roof sheathing, deck or slab is required to be enclosed at the top with construction of the same fire-resistance rating as the topmost floor penetrated by the shaft, but not less than the fire-resistance rating required for the shaft enclosure (780 CMR 708.4).

6.4 Interior Walls and Partitions

6.4.1 Fire/Smoke Resistive Assemblies

The existing building does not have fire-resistance rated corridor walls, occupancy separations, or tenant separations. Table 2 identifies the interior walls and partitions that are required to be constructed as fire rated assemblies. These requirements will apply to the new and altered portions of the building only.

Fire Rated Assemblies Type of Assembly Construction Code Reference

Occupancy Separations

Nonseparated Mixed Use – fire-resistance ratings not required between different occupancies 780 CMR 508.3

Corridors

Serving All Occupancies 1-hour fire partition 780 CMR 1018.1

Special Rooms/Incidental Uses

Nonsprinklered Electrical Room 2-hour fire barrier NFPA 13, 8.15.10.3

Shafts

Connecting 3 stories or less 1-hour fire barrier 780 CMR 708.4 TABLE 2: FIRE/SMOKE RESISTIVE ASSEMBLIES

Page 71: First Parish Meeting House Interior Renovation ... Renovation. Tyngsborough, Massachusetts: Existing Conditions Report & Schematic Design : Recommendations. April 11, 2017: Table of

March 2, 2017 Project #: 165086

Page 11

6.4.2 Identification

All new fire barriers, fire partitions or any other wall required to have protected openings or penetrations are required to be permanently identified with signs or stenciling (780 CMR 703.6). The identification will:

Be located in accessible concealed floor, floor-ceiling, or attic spaces.

Be located within 15 feet of the end of each wall and at intervals not exceeding 30 feet measured horizontally along the wall or partition.

Include lettering not less than 3 inches in height with a minimum 3/8 inch stroke in a contrasting color incorporating the suggested wording “FIRE AND/OR SMOKE BARRIER – PROTECT ALL OPENINGS”.

6.4.3 Doors

New doors and their corresponding components in fire-resistance rated walls are required to have fire-resistance ratings and meet the required testing standards as specified in Table 3. All doors required to be fire-resistance-rated are required to be designed, installed, and labeled in accordance with NFPA 80 (780 CMR 715.4):

Door Requirements

Wall Type

Required Wall Rating

Minimum Fire Door

Rating

Performance Criteria3 Code Reference

Fire barriers for shafts, exit enclosures

1 hour 1 hour NFPA 252 or UL 10C

780 CMR 715.4 Other fire barriers

1 hour 45-minute NFPA 252 or UL 10C

2 hour 90-minutes NFPA 252 or UL 10C

Fire Partitions 1 hour 20-minute

NFPA 252 or UL 10C

without hose stream test

TABLE 3: DOOR RATING REQUIREMENTS

6.4.4 Penetrations

New penetrations of fire-resistance-rated walls and horizontal assemblies that are not protected with dampers or a shaft are required to comply with this section. Ducts and

3 All doors will be self- or automatic closing and provided with an active latch bolt that will secure the door when it is closed (780 CMR 715.5.9)

Page 72: First Parish Meeting House Interior Renovation ... Renovation. Tyngsborough, Massachusetts: Existing Conditions Report & Schematic Design : Recommendations. April 11, 2017: Table of

March 2, 2017 Project #: 165086

Page 12

air transfer openings that are protected by dampers are required to comply with Section 0 of this report.

Fire-Resistance-Rated Walls and Partitions

New penetrations of fire-resistance-rated walls are required to comply with the following (780 CMR 713.3.1):

Penetrations are installed as tested in an approved fire-resistance-rated assembly (780 CMR 713.3.1.1); or

Penetrations are protected by an approved penetration firestop system installed as tested in accordance with ASTM E 814 or UL 1479, with a minimum positive pressure differential of 0.01 inch of water and will have an F rating of not less than the required fire-resistance rating of the wall penetrated (780 CMR 713.3.1.2); or

Membrane penetrations by electrical boxes are permitted without an approved firestop system when protected in accordance with 780 CMR 713.3.2.

Horizontal Assemblies

New penetrations of non-fire-resistance rated floor, floor/ceiling assembly, or roof/ceiling is permitted within the building provided that the annular space is filled with an approved material to resist the free passage of flame and the products of combustion (780 CMR 713.4.2.2).

New penetrations of new fire-resistance rated floors are required to comply with 780 CMR 713.4.1. Through penetrations are protected by an approved penetration firestop system installed as tested in accordance with ASTM E 814 or UL 1479, with a minimum positive pressure differential of 0.01 inch of water and will have an F rating/T rating of not less than 1 hour but not less than the required fire-resistance rating of the floor penetrated (780 CMR 713.4.1.1.2).

Ducts and Air Transfer Openings

New ducts are permitted to connect both floors of the building and the mezzanine without a shaft enclosure since the floors are not rated, provided the annular space around the penetrating duct is protected with an approved noncombustible material that resists the free passage of flame and the products of combustion (780 CMR 716.6.3-2).

Fire and smoke dampers are required where ducts and air transfer openings penetrate rated shaft enclosures, unless the penetration is designed using one of the exceptions in 780 CMR 716.5.3). Where dampers are installed, they must be listed and bear the label of an approved testing agency (780 CMR 716.3.1). Fire dampers must be tested in accordance with UL 555 and smoke dampers must be tested in accordance with UL 555S. Combination fire/smoke dampers must comply with both test standards.

Page 73: First Parish Meeting House Interior Renovation ... Renovation. Tyngsborough, Massachusetts: Existing Conditions Report & Schematic Design : Recommendations. April 11, 2017: Table of

March 2, 2017 Project #: 165086

Page 13

Fire dampers are required to be rated for 1.5 hours (780 CMR 716.3.2.1). Smoke damper leakage ratings must be Class I or II. Elevated temperature ratings must not be less than 250°F (780 CMR 716.3.2.2). Combination fire/smoke dampers must comply with both rating requirements (780 CMR 716.3.2.3). Refer to 780 CMR 716.3.3 for required damper actuation methods.

6.5 Interior Finishes

6.5.1 Wall and Ceiling Finishes

Existing wall and ceiling finishes within exits and corridors in the work area are required to be consistent with the requirements of 780 CMR for new construction (MEBC 703.4 & 803.3). Newly installed interior finish materials are required to comply with the requirements of 780 CMR Chapter 8 for new construction. The table below summarizes the interior flame spread requirements (tested in accordance with ASTM E 84 or UL 723) for interior wall and ceiling finishes contained in 780 CMR Section 803.9.

Minimum Interior Wall & Ceiling Finish Requirements4

Occupancy Classification

Exit Enclosures

Corridors, Exit Access

Stairways/Ramps

Rooms and Enclosed Spaces

A-3 A A A, B, or C B A A or B A, B, or C

S-2 A or B A or B A, B, or C TABLE 4: INTERIOR WALL & CEILING FINISH REQUIREMENTS

Wood used for ornamental purposes, trusses, paneling or chancel furnishing is permitted (780 CMR T.803.9(f)). Wood in the lobby space is required to be Class A or B finish (780 CMR T803.9(d)).

6.5.2 Interior Floor Finish

New interior floor covering materials are required to be not less than Class II, as classified by NFPA 253 (780 CMR 804.4.1).

6.6 Fire Protection Systems

6.6.1 Automatic Sprinkler Systems

The existing building is not provided with an automatic sprinkler system.

4 Interior finishes are grouped in the following classes: Class A – flame spread index 0-25, Class B – flame spread index 26-75, Class

C – flame spread index 76-200. All classes are required to have a smoke-developed index that does not exceed 450 in accordance with ASTM E84.

Page 74: First Parish Meeting House Interior Renovation ... Renovation. Tyngsborough, Massachusetts: Existing Conditions Report & Schematic Design : Recommendations. April 11, 2017: Table of

March 2, 2017 Project #: 165086

Page 14

The Basement is required to be sprinkler protected as it satisfies the following conditions (MEBC 704.2.2; 780 CMR 903.2):

The Basement work area contains exits serving an occupant load greater than 30; The Basement work area exceeds 50% of the floor area; The building has sufficient municipal water supply for design of a fire sprinkler

system available to the Basement without installation of a new fire pump; and The calculated occupant load of the building exceeds 300 people.

Sprinkler protection is not required in the balance of the building as the aggregate area of the building, including the mezzanine, is approximately 5,900 sf (MGL ch. 148 s. 26G).

6.6.2 Kitchen Hood Suppression System

Each commercial kitchen exhaust hood and duct system required by Section 609 of the International Fire Code or Chapter 5 of the International Mechanical Code to have a Type I hood, is required to be protected with an approved automatic fire-extinguishing system (780 CMR 904.2.1).

6.6.3 Standpipe Systems

The building does not have a standpipe system, nor is one required to be provided as the highest floor level is not more than 50 feet above the lowest level of fire department access (780 CMR 905.3.1).

6.6.4 Fire Extinguishers

Portable fire extinguishers are required in all occupancies within the building and are required to be selected and installed in accordance with this 780 CMR 906 and NFPA 10 (780 CMR 906.1).

Fire extinguishers are required in the following locations (780 CMR 906.1):

Within 30 feet of commercial cooking equipment.

Such that the maximum travel distance to an extinguisher for Class A fire hazards does not exceed 75 feet (780 CMR 906.3).

Fire extinguishers are required to be manually inspected at intervals not exceeding 31 days (NFPA 10, 7.2.1.2), and are required to be externally examined annually (NFPA 10, 7.3.2). The tags on the fire extinguishers within the building showed the last inspection occurring in 2009. All fire extinguishers in the building are required to be inspected in accordance with NFPA 10.

Page 75: First Parish Meeting House Interior Renovation ... Renovation. Tyngsborough, Massachusetts: Existing Conditions Report & Schematic Design : Recommendations. April 11, 2017: Table of

March 2, 2017 Project #: 165086

Page 15

6.7 Emergency Systems

6.7.1 Fire Alarm and Detection Systems

The building is currently provided with a fire alarm system consisting horn/strobe notification devices with clear lenses, automatic smoke and heat detection, and manual pull stations. The existing system is permitted to remain provided it is in good working order. The condition of the existing system, and the extent to which it can be reused is required to be evaluated by the project fire protection engineer.

The fire alarm system is required to be modified as necessary within the renovated areas. New and modified portions of the fire alarm system are required to be in accordance with 780 CMR and NFPA 72, 2010 Edition. The existing level of protection is not permitted to be reduced as a result of the renovation project (MEBC 601.2).

6.8 Means of Egress

780 CMR Section 102.6.4 contains provisions related to means of egress, lighting, and ventilation within existing buildings. These provisions are intended to provide a minimum level of health and safety for occupants within the building at all times. If these provisions are not met, the building official may cite the condition in writing as a violation and order abatement within a time frame deemed necessary. These items include:

Inadequate number of means of egress. Egress components with insufficient width or so arranged to be inadequate, including

signage and lighting. Inadequate lighting and ventilation.

Where full compliance for egress, lighting, and ventilation are not practical, the building official may accept compliance alternatives, engineering, and other evaluations that adequately address the deficiency.

6.8.1 Existing Means of Egress

The existing means of egress consists of the following:

Basement: Served by two exit stairs. The one in the rear of the building leads directly to the exterior, while the one in the front of the building exits to the exterior by means of the main lobby.

First Floor: Served by two exit doors to the front of the building. Mezzanine: Served by a single exit stair.

6.8.2 Number of Means of Egress

The number of exits required from every story or portion thereof is not permitted to be less than that specified in Table 5 (780 CMR 1021.1).

Page 76: First Parish Meeting House Interior Renovation ... Renovation. Tyngsborough, Massachusetts: Existing Conditions Report & Schematic Design : Recommendations. April 11, 2017: Table of

March 2, 2017 Project #: 165086

Page 16

Minimum Number of Exits Required Occupant Load Number of Exits Required

1 – 500 2 501 – 1,000 3

> 1,000 4 TABLE 5: MINIMUM NUMBER OF EXITS REQUIRED

The mezzanine is permitted to be served by one means of egress since the common path of travel distance is less than 75 feet and the calculated occupant load is less than 29 people (780 CMR 505.3 Exception & 1015.1).

The number of exits serving the building are shown in the means of egress analysis in Appendix A.

6.8.3 Capacity of Means of Egress

A means of egress analysis using the occupant load factors of 780 CMR Section 1004.1 and the exit capacity factors of 780 CMR Section 1005.1 has been completed for the existing building and is located in Appendix A of this report. Adequate egress capacity is provided from each floor.

6.8.4 Exit Signage

The existing building contains multiple exit signs which are internally illuminated on battery backup. Generally, exit signage coverage was provided for the stairs and exit doors to the exterior, but was deficient within the main function rooms.

Where two or more exits are required from a space, exit and exit access doors are required to be marked by an approved exit sign readily visible from any direction of egress travel (780 CMR 1011.1).

As part of the project, it should be confirmed that all new and existing areas are provided with adequate exit signage coverage in accordance with 780 CMR Section 1011. Exit signage will have to be coordinated with any new exit locations from the sanctuary, and with the main exit from the front of the First Floor. All exit signs are required to be internally or externally illuminated (780 CMR 1011.2).

6.8.5 Egress Illumination

The existing building contains multiple emergency lighting devices on battery backup power, but there are several areas in the building that visually appeared to be lacking coverage. Lighting levels under normal and emergency conditions were not measured during the survey.

Page 77: First Parish Meeting House Interior Renovation ... Renovation. Tyngsborough, Massachusetts: Existing Conditions Report & Schematic Design : Recommendations. April 11, 2017: Table of

March 2, 2017 Project #: 165086

Page 17

As part of the project, it should be confirmed that adequate coverage of lighting and emergency lighting is provided throughout the building in accordance with 780 CMR Section 1006, and that all devices are properly functioning.

6.8.6 Existing Hazardous Means of Egress

780 CMR Section 102.6.4 states that existing means of egress elements can retroactively be required to be upgraded regardless of the planned scope of work if deemed hazardous by the building official. Additionally, 527 CMR requires existing means of egress components to be maintained in a safe and operable condition. The following table summarizes means of egress conditions that were observed to be out of compliance with the requirements of 780 CMR and 527 CMR which could potentially be deemed hazardous and require upgrades by the AHJ to be brought in compliance with 780 CMR Chapter 10.

Panic Hardware

No panic hardware is provided on the exit doors from the First Floor and Basement. The code for new construction requires doors serving assembly spaces with more than 50 people (the Sanctuary and the Basement gathering areas) to be equipped with panic hardware (780 CMR 1008.1.10).

Page 78: First Parish Meeting House Interior Renovation ... Renovation. Tyngsborough, Massachusetts: Existing Conditions Report & Schematic Design : Recommendations. April 11, 2017: Table of

March 2, 2017 Project #: 165086

Page 18

Emergency Lighting

As discussed in Section 6.8.5 of this report above, emergency lighting is required to be provided within the building in accordance with 780 CMR Chapter 1006.3 regardless of the scope of work (780 CMR 102.6.4). Portions of the building are lacking coverage from existing devices and in most instances existing devices are non-functioning. It is recommended as part of the project that a full review of emergency lighting coverage and functionality be performed for the entire building. Note that all egress lighting is required to be provided with battery backup power (780 CMR 1006.3).

Exit Signage

As discussed in Section 6.8.4 of this report above, it was observed that multiple exit signs were non-illuminated and do not comply with the exit sign requirements per 780 CMR Section 1011.5 for size and contrast. 780 CMR Section 1011.2 requires exit signs to be internally or externally illuminated. Existing, non-compliant exit signs should be replaced with compliant internally or externally illuminated.

Furthermore, existing exit signage coverage was lacking from the main assembly spaces. Exit signs are required to be placed in all rooms where the exit or the path of egress travel is not

Page 79: First Parish Meeting House Interior Renovation ... Renovation. Tyngsborough, Massachusetts: Existing Conditions Report & Schematic Design : Recommendations. April 11, 2017: Table of

March 2, 2017 Project #: 165086

Page 19

immediately visible to the occupants (780 CMR 1011.1).

Storage in Stair

A storage closet was observed in Stair 2. Exit stairs are not permitted to be used for any purpose other than means of egress (780 CMR 1022.1). If Stair 2 is enclosed with 1-hour rated construction, then the storage room should be relocated.

Ceiling Tiles

There are several missing or damaged ceiling tiles in the Basement, which can affect smoke detector activation.

All missing or damaged ceiling tiles should be replaced regardless of work performed in order to maintain the detection system in safe and operable condition.

Door Locks

There were several bolt- or latch-type locks observed throughout the building. Manual locks are not permitted on egress doors serving the occupancies within the building (780 CMR 1008.1.9.4).

Page 80: First Parish Meeting House Interior Renovation ... Renovation. Tyngsborough, Massachusetts: Existing Conditions Report & Schematic Design : Recommendations. April 11, 2017: Table of

March 2, 2017 Project #: 165086

Page 20

Rear Stair Treads & Risers

The treads and risers in the Rear Stair are non-uniform. Tread depths and risers height are required to be uniform (780 CMR 1009.4.4).

Stair 2 Winders

Stair 2 is provided with winder treads, which is not permitted by new construction (780 CMR 1009.4.3). It is our understanding that these treads are being replaced with compliant treads as part of this project.

Stair 1 Guard

Stair 1 is not provided with a guard that prohibits the passage of a 4” sphere (780 CMR 1013.3). This stair is being demolished as part of this project.

Page 81: First Parish Meeting House Interior Renovation ... Renovation. Tyngsborough, Massachusetts: Existing Conditions Report & Schematic Design : Recommendations. April 11, 2017: Table of

March 2, 2017 Project #: 165086

Page 21

First Floor Exits

The First Floor is provided with two means of egress that are not sufficiently remote from each other.

A new exit is required to be provided from the Sanctuary that is separated from one of the existing exits by a distance not less than one-half of the maximum diagonal of the floor (780 CMR 1015.2.1).

Note that the exit door is required to swing in the direction of egress, is required to be provided with panic hardware and a manual pull station, and is required to be signed as an exit.

Door Swings

All means of egress doors serving the Basement or Sanctuary are required to swing in the direction of egress (780 CMR 1008.1.2). There were several means of egress doors at the back of the sanctuary (towards main entrance) that did not swing in the direction of egress.

6.8.7 Doors

New doors are required to be a minimum of 32 inches in clear width and are not permitted to have a swinging door leaf greater than 48 inches in nominal width (780 CMR 1008.1.1)

New egress doors are required to be of the pivoted or side-swinging type and doors are required to swing in the direction of egress travel where serving an occupant load of 50 or more persons (780 CMR 1008.1.2). It should be confirmed that all means of egress doors serving the Basement and the Sanctuary Area swing in the direction of egress.

Space between two doors in series is required to be 48 inches minimum plus the width of a door swinging into the space. Doors in series are required to swing either in the

Page 82: First Parish Meeting House Interior Renovation ... Renovation. Tyngsborough, Massachusetts: Existing Conditions Report & Schematic Design : Recommendations. April 11, 2017: Table of

March 2, 2017 Project #: 165086

Page 22

same direction or away from the space between the doors. The minimum distance between horizontal sliding doors is required be 48 inches (780 CMR 1008.1.8).

New doors serving rooms or spaces with an occupant load of 50 or more in a Group A occupancy are not permitted to be provided with a lock or latch unless it is panic or fire exit hardware (780 CMR 1008.1.10.1). It is required to be confirmed that all doors (new and existing) from the Group A-3 spaces, including those along egress paths of travel and into stairs, are provided with panic hardware.

6.8.8 Stair Enclosures

Exit enclosures are not permitted to be used for any purpose other than means of egress (780 CMR 1022.1). Penetrations into and openings through an exit enclosure are prohibited except for required exit doors and equipment serving the stair (780 CMR 1022.4). Stairs are required to have sufficient width to accommodate the calculated occupant load, but are not permitted to be less than 44 inches (780 CMR 1009.1)

The code for new construction requires exit enclosures to discharge directly to the exterior of the building (780 CMR 1027.1). If stair 2 is enclosed with rated construction, it is required to discharge directly to the exterior.

6.8.9 Ramps

New ramps are planned as part of this project. Ramps shall have a running slope not steeper than one unit vertical in 12 units horizontal (8-percent slope). If the ramp is not part of an accessible route or used as a means of egress, the slope is permitted to be up to one unit vertical in eight units horizontal (12.5-percent slope) (780 CMR 1010.2). The slope measured perpendicular to the direction of travel of a ramp shall not be steeper than one unit vertical in 48 units horizontal (2-percent slope) (780 CMR 1010.3). The rise for any ramp run shall be 30 inches maximum (780 CMR 1010.4).

Ramps shall have landings at the bottom and top of each ramp, points of turning, entrance, exits and at doors (780 CMR 1010.7). Landings shall have a slope not steeper than one unit vertical in 48 units horizontal (2-percent slope) in any direction. Changes in level are not permitted (780 CMR 1010.7.1). The landing shall be at least as wide as the widest ramp run adjoining the landing and a minimum length of 60 inches (780 CMR 1010.7.2 & 1010.7.3). Where changes in direction of travel occur at landings provided between ramp runs, the landing shall be 60 inches by 60 inches minimum (780 CMR 1010.7.4). Ramps with a rise greater than 6 inches shall have handrails on both sides that comply with 780 CMR 1012 (780 CMR 1010.9).

6.9 Structural

The review of existing conditions and application of the structural requirements listed below will be performed by the structural engineer on the project. The following

Page 83: First Parish Meeting House Interior Renovation ... Renovation. Tyngsborough, Massachusetts: Existing Conditions Report & Schematic Design : Recommendations. April 11, 2017: Table of

March 2, 2017 Project #: 165086

Page 23

requirements assume that the work area of the project does not exceed 50% of the aggregate building area.

The evaluation of structural elements and their connections is required consider the cumulative effects of alterations, additions, or changes of occupancy since the original construction, except where permitted by MEBC Section 101.9.

New Structure

New structural elements, including connections and anchorage, are required to meet the requirements of 780 CMR for new construction (MEBC 707.2).

Gravity Load-Carrying Structure

The load carrying capacity of structural members is not permitted to be reduced as a result of the project unless it can be demonstrated that the members meet the requirements of 780 CMR for new construction. If a structural element’s stress is increased by more than 5% since the time of original installation, it is required to comply with the provisions of 780 CMR for new construction (MEBC 707.4).

Lateral & Seismic Load-Carrying Structure

Voluntary seismic upgrades that are not otherwise required and are initiated for the purpose of improving the performance of the seismic force-resisting system are permitted, provided that they are supported by an engineering analysis (MEBC 707.6).

Any existing lateral load carrying element whose demand-capacity ratio is increased by more than 10% with the alteration considered (compared to when the alteration is ignored) is required to comply with the requirements of MEBC Section 807.4, which requires a structural investigation and analysis. Additionally, where the alteration results in a structural irregularity as defined in ASCE 7, the lateral load resisting structural elements are required to comply with MEBC Section 807.4 (MEBC 707.5).

6.10 Accessibility

6.10.1 521 CMR Application

The requirements of 521 CMR are limited to buildings or portions thereof that are open to the public. Employee-only spaces are exempt from these requirements; however, employee-only spaces that are occasionally visited by visitors are not.

Where the cost of the project exceeds 30% of the full and fair cash value of the building, then all public portions of the building are subject to the requirements of 521 CMR (521 CMR 3.3).

Page 84: First Parish Meeting House Interior Renovation ... Renovation. Tyngsborough, Massachusetts: Existing Conditions Report & Schematic Design : Recommendations. April 11, 2017: Table of

March 2, 2017 Project #: 165086

Page 24

6.10.1.1 Building Value

The full and fair cash value is shown as $271,200 on the Town of Tyngsborough Assessor’s Website5. The Massachusetts Department of Revenue has assigned Boston an assessment ratio of 0.956. Thus 30% of the full and fair cash value is $271,200 / 0.95 x 30% = $85,642. It is our understanding that the total cost of this project and all projects in the past 36 months will exceed this 30% threshold.

6.10.1.2 Existing Building Application

As the cost of the project will exceed 30% of the full and fair cash value of the building, all public portions of the building are subject to the requirements of 521 CMR. The following are some of the major upgrades that would be required for this building:

All entrances are required to be accessible (521 CMR 25.1). All restrooms are required to be accessible (521 CMR 30.1). All doors are required to have compliant maneuvering clearances and

hardware (521 CMR 26.6). Doors are required to have a minimum clear width of 32” (521 CMR 26.5). Door thresholds? Door landings? All stair treads are required to have uniform depths and rise (521 CMR 27.2). Handrails are required on both sides of stairs with compliant extensions (521

CMR 27.4.1). The kitchen is required to be accessible if used by non-employees (521 CMR

32.1). Accessible seating in Sanctuary? Assisted listening devices in the Sanctuary (521 CMR 14.5.1).

6.10.1.3 Variances

MAAB also has variance process where relief may be granted based on illustrating that complying with the code is either not technically feasible given existing conditions or that the level of accessible benefit is disproportionate when compared with the cost to perform the work.

6.10.2 ADA Application

Although not enforced by any authority having jurisdiction on the project, the requirements of ADA are also applicable and enforced through civil litigation only. Code Red Consultants did not perform a comprehensive accessibility review of the

5 http://tyngsborough.patriotproperties.com/Summary.asp?AccountNumber=1697 6 http://www.mass.gov/dor/local-officials/assessor-info/equalized-valuations-eqvs.html

Page 85: First Parish Meeting House Interior Renovation ... Renovation. Tyngsborough, Massachusetts: Existing Conditions Report & Schematic Design : Recommendations. April 11, 2017: Table of

March 2, 2017 Project #: 165086

Page 25

facility for ADA compliance. The scope of our analysis was limited to entrances, main accessible routes, and bathrooms which were available for inspection.

As the cost of the project exceeds 30% of the full and fair cash value of the building, and a full accessibility evaluation in accordance with 521 CMR is required, it is expected that numerous accessible upgrades are planned to be made to the building as part of the project. These upgrades should be coordinated with the requirements of ADA where new work occurs.

The Americans with Disabilities Act Accessibility Guidelines (ADAAG) requires that altered portions of an existing building must be readily accessible to and usable by individuals with disabilities to the maximum extent feasible (ADAAG 36.402(a)(1)). Further, alterations to primary function areas should be made such that the level of accessibility, including the path of travel to the space, is made accessible to the maximum extent feasible. When determining if the upgrade is feasible, the ADAAG requirements state that the upgrade to the path of travel is disproportionate to the project when the cost to perform the work exceeds 20% of the cost of the alteration to the primary function area. In choosing which accessible elements to provide if the cost is disproportionate, priority should be given to those elements that will provide the greatest access, in the following order:

1. An accessible entrance

2. An accessible route to the altered area

3. At least one accessible restroom for each sex or a single unisex restroom

4. Accessible drinking fountains

5. Accessible telephones

When possible, additional accessible elements such as parking, storage, and alarms should be addressed if within the disproportionality criteria.

6.11 Energy Use

The proposed work is required to comply with the commercial provisions of the 2015 International Energy Conservation Code (IECC) with Massachusetts Amendments.

Additions, alterations, renovations, or repairs to an existing building, building system, or portion thereof are required to conform to the provisions of the 2015 IECC as they relate to new construction without requiring the unaltered portions of the existing building or building system to comply with the 2015 IECC (IECC 101.4.3).

6.12 Plumbing Fixtures

The existing building is served by a total of two toilets, two urinals, and three sinks. There are two single-user toilet rooms and a third room with the two urinals and an additional sink. All existing fixtures are located on the Basement Level.

Page 86: First Parish Meeting House Interior Renovation ... Renovation. Tyngsborough, Massachusetts: Existing Conditions Report & Schematic Design : Recommendations. April 11, 2017: Table of

March 2, 2017 Project #: 165086

Page 26

As part of the project, it is planned to remove all existing toilet rooms and replace them with a new male and a new female toilet room on the Basement Level. These new group toilet rooms will be located in approximately the same location as the existing fixtures.

6.12.1 Quantities

248 CMR does not contain any provisions which outline when an updated plumbing fixture analysis is required in an existing building. Where existing fixtures are renovated or new fixtures are provided, the plumbing official could technically require the project to provide new toilet rooms throughout the building in accordance with new code requirements, sized using factors below.

Toilets

Urinals Lavatories

Female Male Female Male

A-3: Halls, Museums, Libraries, etc.

1 per 50 1 per 100 50%

substitution (permitted)

1 per 200 1 per 200

Based on our conversations with CBI, the maximum expected program occupant load of the building consists of the following:

Scenario 1 o Basement: 50 people o First Floor: 6 people at alter, 200 people in pews o Second Floor: 35 people {program load from CBI} o Total: 291 assembly occupants (146 females, 146 males)

Scenario 2 o Basement: 50 people o First Floor: 6 people at alter, 200 people in pews o Second Floor: 0 people {program load from CBI based on unoccupied storage

functions} o Total: 256 assembly occupants {128 females, 128 males}

Using the above occupant load schemes and plumbing fixture factors, the required number of fixtures for the building is as follows:

3 female toilets 2 male toilets (1 of which is permitted to be substituted for a urinal) 1 sink for each sex

6.12.2 Plumbing Fixture Locations

Occupants in Assembly occupancies are not permitted to travel up or down a floor to reach the required fixtures. It is our understanding that the project proposes to only provide plumbing fixtures in the Basement (as currently configured). The proposed

Page 87: First Parish Meeting House Interior Renovation ... Renovation. Tyngsborough, Massachusetts: Existing Conditions Report & Schematic Design : Recommendations. April 11, 2017: Table of

March 2, 2017 Project #: 165086

Page 27

approach of only providing toilet rooms on the Basement should be confirmed with the local plumbing official, with the following justification:

1. The quantity of new fixtures meet or exceed existing quantity.

2. There is no increase in the program occupant load of the building as a result of the project.

3. All new toilet room fixtures will be accessible, while none of the existing fixtures are.

4. Access to fixtures has been improved with the installation of the LULA.

5. The new fixtures will be provided in approximately the same location as the existing fixtures, thereby not appreciably increasing the travel distance.

6. There is minimal renovation work on the other floors of the building that would make installation of new fixtures technically infeasible.

7. The quantity of new fixtures can accommodate the maximum program occupant load expected at any time in the building (as evaluated above).

If you have any questions or comments on the above information, please do not hesitate to contact us.

CODE RED CONSULTANTS Prepared By: Reviewed By:

Paul Moan, P.E. Jeff Perras, P.E.

Page 88: First Parish Meeting House Interior Renovation ... Renovation. Tyngsborough, Massachusetts: Existing Conditions Report & Schematic Design : Recommendations. April 11, 2017: Table of

March 2, 2017 Project #: 165086

Page 28

Appendix A: Occupant Load and Exit Capacity Analysis

Page 89: First Parish Meeting House Interior Renovation ... Renovation. Tyngsborough, Massachusetts: Existing Conditions Report & Schematic Design : Recommendations. April 11, 2017: Table of

Schematic Design Estimate

First Parish Meeting HouseInterior Restoration

Tyngsborough, MA

PM&C LLC Prepared for:

20 Downer Ave, Suite 1CHingham, MA 02043 CBI Consulting Inc.

(T) 781-740-8007(F) 781-740-1012 April 10, 2017

Page 90: First Parish Meeting House Interior Renovation ... Renovation. Tyngsborough, Massachusetts: Existing Conditions Report & Schematic Design : Recommendations. April 11, 2017: Table of

First Parish Meeting House

Interior Restoration 10-Apr-17

Tyngsborough, MA

Schematic Design Estimate

MAIN CONSTRUCTION COST SUMMARY

Bid Date Estimated

Construction Cost

$1,144,698

SITEWORK $85,650

HAZMAT REMOVALS per PEER Consultant letter dated 2-16-17 $47,950

SUB-TOTAL Sep-17 $1,278,298

GENERAL CONDITIONS 10% $127,830

BONDS 1.50% $19,174

INSURANCE 2.25% $28,762

PERMIT Not Required

OVERHEAD AND FEE 8% $102,264

1.50% Included

9.5% $147,851

TOTAL OF ALL CONSTRUCTION $1,704,179

INTERIOR RESTORATION COSTS

ESCALATION TO BID-DATE

DESIGN AND PRICING CONTINGENCY

Summary Page 1 PMC - Project Management Cost

Page 91: First Parish Meeting House Interior Renovation ... Renovation. Tyngsborough, Massachusetts: Existing Conditions Report & Schematic Design : Recommendations. April 11, 2017: Table of

First Parish Meeting House

Interior Restoration 10-Apr-17

Tyngsborough, MA

Schematic Design Estimate

ITEMS NOT CONSIDERED IN THIS ESTIMATE

Items not included in this estimate are:

All professional fees and insurance

Land acquisition, feasibility, and financing costs

All Furnishings, Fixtures and Equipment

Items identified in the design as Not In Contract (NIC)

Items identified in the design as by others

Owner supplied and/or installed items (e.g. draperies, furniture and equipment)

Utility company back charges, including work required off-site

Work to City streets and sidewalks, (except as noted in this estimate)

Construction or occupancy phasing or off hours’ work, (except as noted in this estimate)

The estimate is based on prevailing wage rates for construction in this market and represents a reasonable opinion of cost. It is not a

prediction of the successful bid from a contractor as bids will vary due to fluctuating market conditions, errors and omissions,

proprietary specifications, lack or surplus of bidders, perception of risk, etc. Consequently the estimate is expected to fall within the

range of bids from a number of competitive contractors or subcontractors, however we do not warrant that bids or negotiated prices

will not vary from the final construction cost estimate.

This Schematic Design cost estimate was produced from drawings, outline specifications and other documentation prepared by

CBI Consulting Inc. and their design team dated April 3rd 2017. Design and engineering changes occurring subsequent to the

issue of these documents have not been incorporated in this estimate.

This estimate includes all direct construction costs, general contractor’s overhead and profit and design contingency. Cost escalation

assumes start dates indicated.

Bidding conditions are expected to be public bidding under Chapter 149 of the Massachusetts General Laws to pre-qualified general

contractors, and pre-qualified sub-contractors, open specifications for materials and manufacturers.

Summary Page 2 PMC - Project Management Cost

Page 92: First Parish Meeting House Interior Renovation ... Renovation. Tyngsborough, Massachusetts: Existing Conditions Report & Schematic Design : Recommendations. April 11, 2017: Table of

First Parish Meeting House 10-Apr-17

Interior Restoration

Tyngsborough, MA

Schematic Design Estimate

CONSTRUCTION COST SUMMARYBUILDING SYSTEM SUB-TOTAL TOTAL %

RESTORATIONS

A10 FOUNDATIONS

A1010 Standard Foundations $1,500

A1020 Special Foundations $0

A1030 Lowest Floor Construction $4,500 $6,000 0.5%

A20 BASEMENT CONSTRUCTION

A2010 Basement Excavation $0

A2020 Basement Walls $900 $900 0.1%

B10 SUPERSTRUCTURE

B1010 Upper Floor Construction $9,800

B1020 Roof Construction $0 $9,800 0.9%

B20 EXTERIOR CLOSURE

B2010 Exterior Walls $43,965

B2020 Windows $52,207

B2030 Exterior Doors $15,203 $111,375 9.7%

B30 ROOFING

B3010 Gutter and Fascia Work $64,688

B3020 Roof Openings $0 $64,688 5.7%

C10 INTERIOR CONSTRUCTION

C1010 Partitions $72,480

C1020 Interior Doors $23,530

C1030 Specialties/Millwork $54,358 $150,368 13.1%

C20 STAIRCASES

C2010 Stair Construction $53,820

C2020 Stair Finishes $5,850 $59,670 5.2%

C30 INTERIOR FINISHES

C3010 Wall Finishes $36,730

C3020 Floor Finishes $55,898

C3030 Ceiling Finishes $31,970 $124,598 10.9%

WRL edits of First Parish Church Tyngsboro 4.18.17 SD Estimate - Rev1 (2).xlsxPage 1 PMC - Project Management Cost

Page 93: First Parish Meeting House Interior Renovation ... Renovation. Tyngsborough, Massachusetts: Existing Conditions Report & Schematic Design : Recommendations. April 11, 2017: Table of

First Parish Meeting House 10-Apr-17

Interior Restoration

Tyngsborough, MA

Schematic Design Estimate

CONSTRUCTION COST SUMMARYBUILDING SYSTEM SUB-TOTAL TOTAL %

RESTORATIONS

D10 CONVEYING SYSTEMS

D1010 Elevator $84,200 $84,200 7.4%

D20 PLUMBING

D20 Plumbing $77,167 $77,167 6.7%

D30 HVAC

D30 HVAC $204,804 $204,804 17.9%

D40 FIRE PROTECTION

D40 Fire Protection $53,445 $53,445 4.7%

D50 ELECTRICAL

D5010 Service & Distribution $50,170

D5020 Lighting & Power $49,512

D5030 Communications $15,439

D5040 Other Electrical $5,689 $120,810 10.6%

E10 EQUIPMENT

E10 Equipment $7,800 $7,800 0.7%

E20 FURNISHINGS

E2010 Fixed Furnishings $5,950

E2020 Movable Furnishings NIC $5,950 0.5%

F10 SPECIAL CONSTRUCTION

F10 Special Construction $0 $0 0.0%

F20 SELECTIVE BUILDING DEMOLITION

F2010 Building Elements Demolition $63,123

F2020 Hazardous Components Abatement $0 $63,123 5.5%

TOTAL DIRECT COST (Trade Costs) $1,144,698 100.0%

WRL edits of First Parish Church Tyngsboro 4.18.17 SD Estimate - Rev1 (2).xlsxPage 2 PMC - Project Management Cost

Page 94: First Parish Meeting House Interior Renovation ... Renovation. Tyngsborough, Massachusetts: Existing Conditions Report & Schematic Design : Recommendations. April 11, 2017: Table of

First Parish Meeting House 10-Apr-17

Interior Restoration

Tyngsborough, MA

Schematic Design Estimate

CSI UNIT EST'D SUB TOTAL

CODE DESCRIPTION QTY UNIT COST COST TOTAL COST

RESTORATIONS

1 GROSS FLOOR AREA CALCULATION2

3 Basement 2,6454 First floor 2,4455 Second floor 5996

7 TOTAL GROSS FLOOR AREA (GFA) 5,689 sf

8

9

10 A10 FOUNDATIONS11

12 A1010 STANDARD FOUNDATIONS13 002200 Allowance for new footing for lally column 1 ls 1,500.00 1,500

14 SUBTOTAL 1,500 15

16 A1030 LOWEST FLOOR CONSTRUCTION

17 002200 Allowance to patch slab after new MEP work 1 ls 2,500.00 2,500

18 002200 Create slab depression for LULA elevator 50 sf 40.00 2,000

19 SUBTOTAL 4,500 20

21 TOTAL - FOUNDATIONS $6,000

22

23

24 A20 BASEMENT CONSTRUCTION

25

26 A2020 BASEMENT WALLS

27 002200 Fill in window in concrete foundation 6 sf 150.00 900

28 SUBTOTAL 900

29

30 TOTAL - BASEMENT CONSTRUCTION $900

31

32 B10 SUPERSTRUCTURE

33

34 B1010 FLOOR CONSTRUCTION35 002200 New floor framing at removed stair location; LULA

vestibule

1 ls 5,000.00 5,000

36 New lally column in basement woman's bathroom 1 ea 800.00 800

37 Reinforce existing beam at new lally column location 1 ea 1,500.00 1,500

38 Allowance to patch upper floor structure after new

MEP work

1 ea 2,500.00 2,500

39 SUBTOTAL 9,800 40

41 TOTAL - SUPERSTRUCTURE $9,800

42

43 B20 EXTERIOR ENCLOSURE

44

45 B2010 EXTERIOR WALLS46 Exterior skin

47 007462 Patch exterior wall at new single exterior door

opening

1 loc 1,500.00 1,500

48 Interior skin

49 1.5" closed cell spray foam insulation at basement 1,700 sf 3.00 5,100

50 3.5" closed cell spray foam at first and mezzanine

floors

5,180 sf 5.00 25,900

51 GWB at interior side of exterior wall 6,880 sf 3.00 20,640

52 2x4 wood stud 1,700 sf 3.25 5,525

53 6" polyethylene vapor barrier at basement exterior

wall base plate

170 lf 6.00 1,020

54 Allowance for staging for upper level window

replacement

1 ls 5,000.00 5,000

WRL edits of First Parish Church Tyngsboro 4.18.17 SD Estimate - Rev1 (2).xlsx Page 1 PMC - Project Management Cost

Page 95: First Parish Meeting House Interior Renovation ... Renovation. Tyngsborough, Massachusetts: Existing Conditions Report & Schematic Design : Recommendations. April 11, 2017: Table of

First Parish Meeting House 10-Apr-17

Interior Restoration

Tyngsborough, MA

Schematic Design Estimate

CSI UNIT EST'D SUB TOTAL

CODE DESCRIPTION QTY UNIT COST COST TOTAL COST

RESTORATIONS

ALTERNATE #1 Blown in cellulose insulation add (20,720)

55 SUBTOTAL 43,965

56

57 B2020 WINDOWS 557 sf -

58 007462 New vinyl windows at basement level 45 sf 65.00 2,925

59 New wood clad windows at upper level 470 sf 95.00 44,650

60 070001 Membrane flashing at new windows 386 lf 4.00 1,544

61 070001 Backer rod & double sealant at windows 386 lf 8.00 3,088

62 SUBTOTAL 52,207

63

64 B2030 EXTERIOR DOORS

65 New hinges at existing front door - double 1 ea 400.00 400

66 Modify frame at existing front door to allow for

switched swing direction- double

1 ea 750.00 750

67 New wood exterior door and hardware in existing

frame at basement - single

1 ea 1,450.00 1,450

68 New wood exterior door, frame and hardware at rear

stair- single

1 ea 2,050.00 2,050

69 New wood exterior door with auto opener both sides

& frames at accessible entrance- single

1 ea 10,000.00 10,000

70 090007 Prep and paint doors and frames 2 loc 200.00 400

71 070001 Backer rod & double sealant at doors 17 lf 9.00 153

72 SUBTOTAL 15,203 73

74 TOTAL - EXTERIOR CLOSURE $111,375

75

76 B30 ROOF COVERINGS 77

78 B3010 ROOF COVERINGS79 Sloped roofing80 6.5" closed cell spray foam insulation at underside of

roof sheathing

3,608 sf 8.00 28,864

81 Intumescent fire retardant paint at roof 3,608 sf 3.00 10,824

82 Bell support repairs & waterproofing of cupola base

roof

1 ls 25,000.00 25,000

83 SUBTOTAL 64,688

84

85 TOTAL - ROOFING $64,688

86

87 C10 INTERIOR CONSTRUCTION

88

89 C1010 PARTITIONS

90 Elevator wall - 8" CMU, fully grouted 711 sf 32.50 23,108

91 6" MS, 1 lyr 5/8" GWB b/s, insulation at basement 546 sf 13.50 7,371

92 3-5/8" MS, 1 lyr 5/8" GWB b/s. insulation at

basement

2,079 sf 11.50 23,909

93 Shaft wall 113 sf 15.00 1,695

94 09300 Patch interior GWB wall at new single door opening 2 loc 1,000.00 2,000

95 092900 Sealants & caulking at partitions 3,449 sf 0.35 1,207

96 092900 Rough blocking 230 lf 3.00 690

97 09300 Miscellaneous plaster repairs to interior walls 1 ls 12,500.00 12,500

98 SUBTOTAL 72,480

99

100 C1020 INTERIOR DOORS101 081113 New HM frames - single 11 loc 280.00 3,080

102 081113 New HM frames - double 1 loc 500.00 500

103 081416 New flush wood interior door 13 leaf 550.00 7,150

104 081416 Hardware 13 leaf 800.00 10,400

WRL edits of First Parish Church Tyngsboro 4.18.17 SD Estimate - Rev1 (2).xlsx Page 2 PMC - Project Management Cost

Page 96: First Parish Meeting House Interior Renovation ... Renovation. Tyngsborough, Massachusetts: Existing Conditions Report & Schematic Design : Recommendations. April 11, 2017: Table of

First Parish Meeting House 10-Apr-17

Interior Restoration

Tyngsborough, MA

Schematic Design Estimate

CSI UNIT EST'D SUB TOTAL

CODE DESCRIPTION QTY UNIT COST COST TOTAL COST

RESTORATIONS

105 090007 Finish to doors and frames 12 loc 140.00 1,680

106 070001 Sealants & caulking 12 loc 60.00 720

107 SUBTOTAL 23,530

108

109 C1030 SPECIALTIES / MILLWORK110 Sand church pew surfaces for repainting 9'-6" long x

14" deep, including two end pieces

33 ea 288.83 9,531

111 Repaint pew end pieces and back section 33 ea 414.19 13,668

112 Varnish church pew seats 33 ea 55.43 1,829

113 Allowance to prep and paint wood trim at first floor

and mezzanine level

1 ls 5,000.00 5,000

114 Repair half wall at mezzanine level 38 lf 25.00 950

115 Wood guardrail at mezzanine half wall 38 lf 210.00 7,980

116 Metal guardrail at two story exterior windows at

mezzanine level

12 lf 225.00 2,700

117 102110 Single bathroom accessories 1 ea 1,100.00 1,100

118 102110 Gang bathroom accessories 1 ea 2,000.00 2,000

119 Toilet partitions120 102110 ADA 2 ea 1,900.00 3,800

121 102110 Standard 2 ea 1,600.00 3,200

122 102110 Urinal screen 1 ea 600.00 600

123 102110 Miscellaneous support at toilet partitions 4 loc 500.00 2,000

124 SUBTOTAL 54,358 125

126 TOTAL - INTERIOR CONSTRUCTION $150,368

127

128 C20 STAIRCASES

129

130 C2010 STAIR CONSTRUCTION131 New 3 flight wood stairs with wood treads & risers &

code compliant metal railings

3 flt 15,000.00 45,000

132 New wood treads and risers at rear stairs 45 lfr 100.00 4,500

133 New ADA railings at rear stairs 24 lf 180.00 4,320

134 SUBTOTAL 53,820 135

136 C2020 STAIR FINISHES137 090007 Prep and paint treads/risers to new & existing stair 150 lfr 15.00 2,250

138 06200 Prep and paint to staircases 3 flt 1,200.00 3,600

139 SUBTOTAL 5,850

140

141 TOTAL - STAIRCASES $59,670

142

143 C30 INTERIOR FINISHES144

145 C3010 WALL FINISHES

146 090007 Paint to GWB walls 12,243 sf 1.00 12,243

147 090007 Paint to CMU walls at elevator 711 sf 1.50 1,067

148 Prep and paint wood wall paneling at lobby and

sanctuary

2,680 sf 4.00 10,720

149 Inside wall repairs/finishes at removed partition's 1 ls 5,000.00 5,000

ALTERNATE #1 Blown in cellulose insulation 7,700

150 SUBTOTAL 36,730 151

152

153 C3020 FLOOR FINISHES154 Add wood flooring to ramps at sanctuary 34 sf 22.00 748

155 Patch wood flooring 33 sf 18.00 594

156 Refinish ornamental floor vent - 40 SF each 2 ea 200.00 400

157 Refinish wood flooring 2,331 sf 7.50 17,483

158 Ceramic tile flooring at basement 1,945 sf 12.00 23,340

WRL edits of First Parish Church Tyngsboro 4.18.17 SD Estimate - Rev1 (2).xlsx Page 3 PMC - Project Management Cost

Page 97: First Parish Meeting House Interior Renovation ... Renovation. Tyngsborough, Massachusetts: Existing Conditions Report & Schematic Design : Recommendations. April 11, 2017: Table of

First Parish Meeting House 10-Apr-17

Interior Restoration

Tyngsborough, MA

Schematic Design Estimate

CSI UNIT EST'D SUB TOTAL

CODE DESCRIPTION QTY UNIT COST COST TOTAL COST

RESTORATIONS

159 Ceramic floor tile at basement bathrooms 260 sf 14.00 3,640

160 Tile base 95 lf 20.00 1,900

161 Sealed concrete 175 sf 1.50 263

162 Wood base 553 lf 10.00 5,530

163 09300 Protect existing floors 1 ls 2,000.00 2,000

164 SUBTOTAL 55,898 165

166 C3030 CEILING FINISHES

167 ACT ceiling in basement 2,380 sf 4.50 10,710

168 GWB ceiling 1,011 sf 10.00 10,110

169 Paint tin ceiling in sanctuary 1,830 sf 5.00 9,150

170 Allowance to patch ceilings after new MEP work 1 ls 2,000.00 2,000

171 SUBTOTAL 31,970 172

173 TOTAL - INTERIOR FINISHES $124,598

174

175

176 D10 CONVEYING SYSTEMS

177

178 D1010 LULA

179 142010 New 3 stop; LULA 1 ls 83,000.00 83,000

180 050001 Misc. metals to LULA 1 ls 1,200.00 1,200

181 SUBTOTAL 84,200

182

183 TOTAL - CONVEYING SYSTEMS $84,200

184

185

186 D20 PLUMBING

187

188 D20 PLUMBING, GENERALLY

189 220000 Equipment

190 220000 Allowance for replacing water heaters, pumps, etc 1 ls 15,000.00 15,000

191 220000 Plumbing Fixtures & Specialties

192 220000 WC's 4 ea 1,300.00 5,200

193 220000 Urinal 1 ea 1,300.00 1,300

194 220000 Lavatories 2 ea 1,300.00 2,600

195 220000 3 comp kitchen sink 1 ea 1,600.00 1,600

196 220000 Allowance for hand sink 1 ea 1,200.00 1,200

197 220000 Dishwasher connection 1 ea 500.00 500

198 220000 Domestic Water

199 220000 Allowance for domestic water to fixtures 10 ea 2,000.00 20,000

200 220000 Sanitary Waste & vent

201 220000 Allowance for sanitary waste to fixtures 10 ea 1,200.00 12,000

202 220000 Allowance for floor drains 1 ls 2,500.00 2,500

203 220000 Allowance for indoor grease trap 1 ls 2,000.00 2,000

204 220000 Storm Water

205 220000 Assumed to be no scope

206 220000 Natural Gas

207 220000 Allowance to extend gas pipework to new range

location including solenoid valve

1 ls 4,000.00 4,000

208 220000 Miscellaneous

209 220000 Allowance for demo 5,689 sf 0.75 4,267

210 Permits, shop drawings & testing 1 ls 5,000.00 5,000

211 SUBTOTAL 77,167

212

213 TOTAL - PLUMBING $77,167

214

215

WRL edits of First Parish Church Tyngsboro 4.18.17 SD Estimate - Rev1 (2).xlsx Page 4 PMC - Project Management Cost

Page 98: First Parish Meeting House Interior Renovation ... Renovation. Tyngsborough, Massachusetts: Existing Conditions Report & Schematic Design : Recommendations. April 11, 2017: Table of

First Parish Meeting House 10-Apr-17

Interior Restoration

Tyngsborough, MA

Schematic Design Estimate

CSI UNIT EST'D SUB TOTAL

CODE DESCRIPTION QTY UNIT COST COST TOTAL COST

RESTORATIONS

216 D30 HVAC

217

218 D30 HVAC, GENERALLY

219 230000 Allowance for HVAC 5,689 sf 35.00 199,115220 230000 Allowance for demo 5,689 sf 1.00 5,689221 SUBTOTAL 204,804

222

223 TOTAL - HVAC $204,804

224

225

226 D40 FIRE PROTECTION

227

228 D40 FIRE PROTECTION, GENERALLY

229 210000 Allowance for new wet sprinkler system 5,689 sf 5.00 28,445

230 Premium for dry valve assemblies for second / attic

levels

2 loc 7,500.00 15,000

231 210000 Premium for Ansul type system to kitchen hood 1 ls 5,000.00 5,000

232 Permits, shop drawings & testing 1 ls 5,000.00 5,000

233 SUBTOTAL 53,445

234

235 TOTAL - FIRE PROTECTION $53,445

236

237 D50 ELECTRICAL

238

239 D5010 SERVICE & DISTRIBUTION

240 Gear & Distribution

241 260000 Allowance for new 400A feeder from Middlesex Road 125 lf 220.00 27,500

242 260000 Excavation, backfill & make-good 125 lf 30.00 3,750

243 260000 New pole riser 1 ls 2,000.00 2,000

244 260000 New 400A main panel 1 ls 6,500.00 6,500

245 260000 New meter 1 ea By Utility

246 260000 Allowance to reconnect existing circuits 1 ls 2,920.00 2,920

247 260000 Allowance for equipment wiring 1 ls 7,500.00 7,500

248 SUBTOTAL 50,170

249

250 D5020 LIGHTING & POWER251 260000 Lighting & Branch Power

252 260000 Allowance for lighting 5,689 sf 5.00 28,445

253 260000 Allowance to repair chandelier and retrofit with LED

lamps

1 ls 4,000.00 4,000

254 260000

255 260000 Lighting Controls

256 260000 Allowance for lighting 5,689 sf 1.00 5,689

257 260000

258 260000 Branch Power

259 260000 Allowance for branch power 5,689 sf 2.00 11,378

260 SUBTOTAL 49,512

261

262 D5030 COMMUNICATION & SECURITY SYSTEMS263 260000 Fire Alarms

264 260000 Allowance for fire detection & alarm including CO

detection

5,689 sf 1.95 11,094

265 260000

266 260000 Voice & Data

267 260000 Allowance for voice & data 5,689 sf 0.50 2,845

268 260000

269 260000 Audio Visual

270 260000 Allowance for AV rough-in 1 ls 1,500.00 1,500

271 SUBTOTAL 15,439

WRL edits of First Parish Church Tyngsboro 4.18.17 SD Estimate - Rev1 (2).xlsx Page 5 PMC - Project Management Cost

Page 99: First Parish Meeting House Interior Renovation ... Renovation. Tyngsborough, Massachusetts: Existing Conditions Report & Schematic Design : Recommendations. April 11, 2017: Table of

First Parish Meeting House 10-Apr-17

Interior Restoration

Tyngsborough, MA

Schematic Design Estimate

CSI UNIT EST'D SUB TOTAL

CODE DESCRIPTION QTY UNIT COST COST TOTAL COST

RESTORATIONS

272

273 D5040 OTHER ELECTRICAL SYSTEMS274 Miscellaneous

275 260000 Allowance for demo 5,689 sf 1.00 5,689

276 SUBTOTAL 5,689

277

278 TOTAL - ELECTRICAL $120,810

279

280

281 E10 EQUIPMENT282

283 E10 EQUIPMENT, GENERALLY284 Kitchen Appliances285 30" dishwasher 1 ea 800.00 800

286 36" range 1 ea 2,000.00 2,000

287 36" refrigerator 1 ea 1,500.00 1,500

288 48" hood vent 1 ea 3,500.00 3,500

289 SUBTOTAL 7,800 290

291 TOTAL - EQUIPMENT $7,800292293294 E20 FURNISHINGS295

296 E2010 FIXED FURNISHINGS297 123553 New kitchen base cabinets and counters w/

backsplash

17 lf 350.00 5,950

298 SUBTOTAL 5,950

299

300 E2020 MOVABLE FURNISHINGS301 All movable furnishings to be moved by others302 SUBTOTAL NIC 303

304 TOTAL - FURNISHINGS $5,950305

306

307 F20 SELECTIVE BUILDING DEMOLITION

308

309 F2010 BUILDING ELEMENTS DEMOLITION

310 Create opening in exterior wall for new single door 1 ea 1,800.00 1,800

311 Create opening in interior wall for single door 2 ea 1,300.00 2,600

312 Demolish ACT ceiling at mezzanine 483 sf 2.00 966

313 Demolish casework 39 lf 10.00 390

314 Demolish ceilings 2,516 sf 2.00 5,032

315 Demolish interior partitions 239 lf 25.00 5,975

316 Demolish left hand wood stair - 2 flights 1 ea 2,000.00 2,000

317 Demolish plaster ceiling at lobby 501 sf 5.00 2,505

318 Demolish right hand wood stair - 2 flights 1 ea 2,000.00 2,000

319 Prep and paint tin ceiling panels in sanctuary 1,830 sf 3.00 5,490

320 Remove carpet at first floor lobby 501 sf 0.80 401

321 Remove masonry chimney from basement to attic -

40' high

1 ea 15,000.00 15,000

322 Remove cross from wall at sanctuary 1 ea 100.00 100

323 Remove existing lally column in basement 1 ea 250.00 250

324 Remove floor vent at mezzanine level 1 ea 50.00 50

325 Remove exterior door at bottom of rear stair- single 1 ea 190.00 190

326 Remove exterior windows 518 sf 8.00 4,144

327 Remove interior bifold door and frame - double 3 ea 150.00 450

328 Remove interior door at top of rear stair - single 1 ea 120.00 120

329 Remove interior door and frame - single 8 ea 100.00 800

330 Remove wood paneling at mezzanine 468 sf 10.00 4,680

WRL edits of First Parish Church Tyngsboro 4.18.17 SD Estimate - Rev1 (2).xlsx Page 6 PMC - Project Management Cost

Page 100: First Parish Meeting House Interior Renovation ... Renovation. Tyngsborough, Massachusetts: Existing Conditions Report & Schematic Design : Recommendations. April 11, 2017: Table of

First Parish Meeting House 10-Apr-17

Interior Restoration

Tyngsborough, MA

Schematic Design Estimate

CSI UNIT EST'D SUB TOTAL

CODE DESCRIPTION QTY UNIT COST COST TOTAL COST

RESTORATIONS

331 Remove plaster and lathe at walls to allow for

insulation at first and mezzanine floors

5,180 sf 4.00 20,720

332 Remove existing hand rails at rear stairs 12 lf 15.00 180

333 02050 Allowance to protect misc. finishes 1 ls 3,000.00 3,000

334 02050 Misc. Demolition 1 ls 5,000.00 5,000

ALTERNATE #1 Blown in cellulose insulation sub (20,720)

335 SUBTOTAL 63,123

336

337 F2020 HAZARDOUS COMPONENTS ABATEMENT338 See main summary 339 SUBTOTAL

340

341 TOTAL - SELECTIVE BUILDING DEMOLITION $63,123

342

343 SUBTOTAL - RESTORATION $1,144,698

WRL edits of First Parish Church Tyngsboro 4.18.17 SD Estimate - Rev1 (2).xlsx Page 7 PMC - Project Management Cost

Page 101: First Parish Meeting House Interior Renovation ... Renovation. Tyngsborough, Massachusetts: Existing Conditions Report & Schematic Design : Recommendations. April 11, 2017: Table of

First Parish Meeting House 10-Apr-17

Interior Restoration

Tyngsborough, MA

Schematic Design Estimate

CSI UNIT EST'D SUB TOTAL

CODE DESCRIPTION QTY UNIT COST COST TOTAL COST

ALTERNATE #1 Blown in cellulose insulation

B20 EXTERIOR ENCLOSURE

B2010 EXTERIOR WALLSInterior skin

8" blown in cellulose insulation 5,180 sf 4.00 20,720

3.5" closed cell spray foam at first and mezzanine

floors

(5,180) sf 5.00 (25,900)

GWB at interior side of exterior wall (5,180) sf 3.00 (15,540)

SUBTOTAL ($20,720)

TOTAL - EXTERIOR CLOSURE ($20,720)

C30 INTERIOR FINISHES

C3010 WALL FINISHES

Plaster repair after blown in insulation 5,180 sf 1.50 7,770

SUBTOTAL $7,770

TOTAL - INTERIOR FINISHES $7,770

F20 SELECTIVE BUILDING DEMOLITION

F2010 BUILDING ELEMENTS DEMOLITION

Remove plaster and lathe to allow for insulation at

first and mezzanine floors

(5,180) sf 4.00 (20,720)

SUBTOTAL ($20,720)

TOTAL - SELECTIVE BUILDING DEMOLITION ($20,720)

SUBTOTAL - ALTERNATE #1 ($33,670)

4.xlsx Page 1 PMC - Project Management Cost

Page 102: First Parish Meeting House Interior Renovation ... Renovation. Tyngsborough, Massachusetts: Existing Conditions Report & Schematic Design : Recommendations. April 11, 2017: Table of

2,010.8 sf

155.6 sf 175.3 sf

REAR STAIR52" STAIR29" DOOR

CAPACITY: 145 PEOPLERear Stair

Door Width: 29"Door Capacity: 145Stair Width: 52"Stair Capacity: 173

Exit Capacity: 145

Stair 2

Door Width: -Door Capacity: -Stair Width: 41"Stair Capacity: 136

Exit Capacity: 136

Floor Exit Capacity = 272* Occupants

Building is not fully sprinkler protected.

*Limited to double the capacity of the smaller exit, as theloss of a single exit is not permitted to reduce thecapacity of the floor by more than 50% (780 CMR 1005.1).

Storage = 156 SF (1/300 gross)OL = 1

Total Occupant Load = 136 Occupants

Kitchen = 176 SF (1/200 gross)OL = 1

Unconcentrated Assembly = 2,011 SF(1/15 net)OL = 134

Legend

Storage/MEP(1/300 gross)

UnconcentratedAssembly (1/15 net)

Kitchen (1/200 gross)

Office/General Circulation(1/200 gross)

Sanctuary Bench Seating(18"/occupant) 3 ft

STAIR 2 (APPROX.)41" STAIR

CAPACITY: 136 PEOPLE

Page 103: First Parish Meeting House Interior Renovation ... Renovation. Tyngsborough, Massachusetts: Existing Conditions Report & Schematic Design : Recommendations. April 11, 2017: Table of

594 sf

9 ft

18 ft

9 ft

Legend

Storage/MEP(1/300 gross)

UnconcentratedAssembly (1/15 net)

Kitchen (1/200 gross)

Office/General Circulation(1/200 gross)

Main Exit

Door Width: 72"Door Capacity: 180Stair Width: 60Stair Capacity: 200

Exit Capacity: 180

Back Exit

Door Width: 32"Door Capacity: 160Ramp Width: 48"Ramp Capacity: 160

Exit Capacity: 160

Floor Exit Capacity = 320* Occupants

Total Occupant Load = 206 Occupants

Alter = 595 SF (1/100 gross)OL = 6

Bench Seating = 300 linear feet(18" / Occupant)OL = 200

MAIN EXIT72" DOOR (TWO SINGLE DOORS)60" STAIR

CAPACITY: 200 PEOPLE

3 ft

Building is not fully sprinkler protected.

Sanctuary Bench Seating(18"/occupant) 3 ft

BACK EXIT32" DOOR48" RAMP

CAPACITY: 160 PEOPLE*Limited to double the capacity of the smaller exit, as theloss of a single exit is not permitted to reduce thecapacity of the floor by more than 50% (780 CMR 1005.1).

Page 104: First Parish Meeting House Interior Renovation ... Renovation. Tyngsborough, Massachusetts: Existing Conditions Report & Schematic Design : Recommendations. April 11, 2017: Table of

666.9 sf

STAIR 241" STAIR36" DOOR

CAPACITY: 136 PEOPLE

NOTE: IT IS OUR UNDERSTANDINGTHAT THIS SPACE WILL BENON-PUBLIC OFFICE ORSTORAGE. THE OFFICEOCCUPANT LOAD FACTORHAS BEEN CONSERVATIVELYUSED.

Stair 2

Door Width: 36"Door Capacity: 180Stair Width: 41"Stair Capacity: 136

Exit Capacity: 136

Floor Exit Capacity = 136 Occupants

Total Occupant Load = 7 Occupants

Office = 667 SF (1/100 gross)OL = 7

Building is not fully sprinkler protected.

Legend

Storage/MEP(1/300 gross)

UnconcentratedAssembly (1/15 net)

Kitchen (1/200 gross)

Office/General Circulation(1/200 gross)

Sanctuary Bench Seating(18"/occupant) 3 ft

Page 105: First Parish Meeting House Interior Renovation ... Renovation. Tyngsborough, Massachusetts: Existing Conditions Report & Schematic Design : Recommendations. April 11, 2017: Table of
Page 106: First Parish Meeting House Interior Renovation ... Renovation. Tyngsborough, Massachusetts: Existing Conditions Report & Schematic Design : Recommendations. April 11, 2017: Table of
Page 107: First Parish Meeting House Interior Renovation ... Renovation. Tyngsborough, Massachusetts: Existing Conditions Report & Schematic Design : Recommendations. April 11, 2017: Table of
Page 108: First Parish Meeting House Interior Renovation ... Renovation. Tyngsborough, Massachusetts: Existing Conditions Report & Schematic Design : Recommendations. April 11, 2017: Table of
Page 109: First Parish Meeting House Interior Renovation ... Renovation. Tyngsborough, Massachusetts: Existing Conditions Report & Schematic Design : Recommendations. April 11, 2017: Table of