38
First Capital Connect Hertfordshire County Council Overview & Scrutiny Committee 20 May 2010 Larry Heyman Integration & Partnership Manager (D) (i)

First Capital Connect Hertfordshire County Council Overview & Scrutiny Committee 20 May 2010

  • Upload
    kathy

  • View
    26

  • Download
    1

Embed Size (px)

DESCRIPTION

(D) (i). First Capital Connect Hertfordshire County Council Overview & Scrutiny Committee 20 May 2010. Larry Heyman Integration & Partnership Manager. Overcrowding: How is it defined?. - PowerPoint PPT Presentation

Citation preview

Page 1: First Capital Connect Hertfordshire County Council Overview & Scrutiny Committee 20 May 2010

First Capital Connect

Hertfordshire County CouncilOverview & Scrutiny Committee

20 May 2010

Larry HeymanIntegration & Partnership

Manager

(D) (i)

Page 2: First Capital Connect Hertfordshire County Council Overview & Scrutiny Committee 20 May 2010

Overcrowding: How is it defined?

There is no simple definition of overcrowding as there is no maximum number of passengers that can be carried on a train - the upper limit being defined by passengers’ willingness (and ability) to physically squeeze into a carriage.

Crowding for peak commuter services in the London and South East area is measured by counts known as Passengers in Excess of Capacity (PIXC)

PIXC is administered by the DfT and applies to weekday commuter trains arriving into London between 07.00 and 09.59 and those departing between 16.00 and 18.59.

The counts are carried out once a year, on a typical weekday during the autumn.

PIXC capacity is deemed to be:–The number of standard class seats on the train for journeys of more than 20 minutes; –For journeys of 20 minutes or less, an allowance for standing room is also made. –The allowance for standing varies with the type of rolling stock.

The PIXC measure is derived from the number of passengers travelling in excess of capacity divided by the total number of people travelling, expressed as a percentage.

Page 3: First Capital Connect Hertfordshire County Council Overview & Scrutiny Committee 20 May 2010

Capacity on the GN route

Before May 2009 the GN route was one of the most overcrowded routes in the UK. Capacity and crowding was one of the biggest issues for our customers using the GN outer route.

The most severe overcrowding was on the AM peak Cambridge to London fast trains

The Thameslink Programme is addressing the capacity constraints on FCC’s TL route.

Capacity schemes focussed on the GN route are essential to accommodate existing patronage and growth.

Page 4: First Capital Connect Hertfordshire County Council Overview & Scrutiny Committee 20 May 2010

More capacity on the GN route

Five 4-car Class 321 trains were transferred from London Midland to FCC for the May 2009 timetable change

These extra trains enabled FCC to introduce the first ever 12-carriage trains running from Cambridge to London King’s Cross

From 17 May 2009 there was a significant improvement to capacity on peak and off-peak services

2,698 more seats were available in the morning peak from May 2009 (17,537) compared with May 2008 (14,839)

3,156 more seats were available in the evening peak from May 2009 (17,182) compared with May 2008 (14,026).

The biggest change to the GN timetable for at least 15 years

More to come in December this year through HLOS

Page 5: First Capital Connect Hertfordshire County Council Overview & Scrutiny Committee 20 May 2010

What is HLOS?

HLOS stands for High Level Output Specification The Railways Act 2005 places a statutory duty on the Government to set

out every five years how much public expenditure it wishes to devote to rail and to specify what it wants the railway to deliver.

The formal statement, including the High Level Output Specification and Statement of funds available, is contained within the White Paper ‘Delivering a Sustainable Railway’ which was published in July 2007.

It covers a five year period known as Control Period 4 (1 April 2009 to 31 March 2014).

The White Paper looks at the potential future challenges for the railway over a 30-year horizon. It identifies three long-term agendas for Government and the rail industry working in partnership: increasing the capacity of the railway, delivering a quality service for passengers, and fulfilling rail's environmental potential.

The paper defined how much additional capacity that the DfT wish to add into Moorgate and King’s Cross in the AM peak (0700 to 0959) and AM high peak hour (0800 to 0859).

Page 6: First Capital Connect Hertfordshire County Council Overview & Scrutiny Committee 20 May 2010

More seats on GN from December 2010

HLOS – GN– 6500 extra peak seats each day from December timetable change

– 11 extra trains (8 x 4-car 321s from London Midland and 3 x 3-car 313s from LOROL)

– Additional services and longer trains

– Three-year programme will see 12-carriage trains at a further six stations

– Four extra morning services into London Moorgate from either Gordon Hill or Welwyn Garden City

– Three additional evening services to either Gordon Hill or Hertford North from London Moorgate

– The lengthening of a number of existing services serving London King’s Cross or London Moorgate

– Power supply upgrades and the lengthening of platforms at six stations including: Royston, Letchworth Garden City, Finsbury Park, Arlesley, Biggleswade and Sandy

Page 7: First Capital Connect Hertfordshire County Council Overview & Scrutiny Committee 20 May 2010

More seats on GN Moorgate trains

Planned improvements from 2010 include: Additional 06:57 to Moorgate service formed of 6 carriages 3 additional Gordon Hill to Moorgate services at 07:33, 08:37 and

09:27 formed of 6 carriages Strengthening of 07:06 Gordon Hill to Moorgate from 3 to 6 carriages

Additional 16:33 Moorgate to Hertford North service formed of 6 carriages

Two additional Moorgate to Gordon Hill services at 17:43 and 18:13 formed of 6 carriages

Strengthening the 16:53 and 17:08 Moorgate to Welwyn Garden City services from 3 to 6 carriages

Page 8: First Capital Connect Hertfordshire County Council Overview & Scrutiny Committee 20 May 2010

More seats on GN King’s Cross Trains

Planned morning peak improvements from 2010 include:

Strengthening the 07:20 Letchworth Garden City to King’s Cross from 6 carriages to 8

Strengthening the 08:16 Peterborough to King’s Cross service from 4 carriages to 8

Strengthening the 08:34 Royston to King’s Cross service from 4 carriages to 8

Additional 06:40 Huntingdon to King’s Cross service formed of 8 carriages

Strengthening the 06:21 Peterborough to King’s Cross service from 8 carriages to 12 (Will call at Stevenage instead of Biggleswade as the platform length at Biggleswade currently allows a maximum of 8 carriages.)

Page 9: First Capital Connect Hertfordshire County Council Overview & Scrutiny Committee 20 May 2010

More seats on GN King’s Cross Trains

Planned evening peak improvements from 2010 include:

Strengthening the 17:22 King’s Cross to Cambridge service from 4 carriages to 8

Strengthening the 17:57 King’s Cross to Welwyn Garden City service from 6 carriages to 8

Strengthening the 18:52 King’s Cross to Cambridge service from 4 carriages to 8

Strengthening the 18:57 King’s Cross to Welwyn Garden City service from 4 carriages to 6

Strengthening the 17:10 King’s Cross to Peterborough service from 8 carriages to 12

Page 10: First Capital Connect Hertfordshire County Council Overview & Scrutiny Committee 20 May 2010

Thameslink Programme Update

All 23 new Electrostars delivered Another 2,400 peak seats in Dec 09 timetable 5,000 more peak seats now year on year Number of short 4-car peak trains halved

Page 11: First Capital Connect Hertfordshire County Council Overview & Scrutiny Committee 20 May 2010

TLP Infrastructure Progress

Blackfriars: Over 400 people working on site; strengthening; riveting (37,000 replaced in all)!

Blackfriars: Rebuilding east side of bridge; closed 20 Nov-16 Jan with trains running through

Page 12: First Capital Connect Hertfordshire County Council Overview & Scrutiny Committee 20 May 2010

Blackfriars – 50,000 man hours a week

Page 13: First Capital Connect Hertfordshire County Council Overview & Scrutiny Committee 20 May 2010

TL North route

Farringdon – new roof; ticket hall started New stations – West Hampstead; Bedford

Page 14: First Capital Connect Hertfordshire County Council Overview & Scrutiny Committee 20 May 2010

City Thameslink

£4.5m upgrade Platforms brought into

use for 12-car Brighter, more secure More seats Lifts improved New ticket gate (Ludgate

entrance)

Page 15: First Capital Connect Hertfordshire County Council Overview & Scrutiny Committee 20 May 2010

Platform extensions to 12-car length

Completed Mill Hill Broadway and Luton Airport Parkway

Building now at Harpenden, St Albans, Leagrave, Luton, West Hampstead

Starting this summer at Elstree & Borehamwood

Radlett and Flitwick – starting mid 2011 Bedford – part of station redesign

Page 16: First Capital Connect Hertfordshire County Council Overview & Scrutiny Committee 20 May 2010

December 2011 – initial 12-car trains

Three four-carriage Electrostars will be allocated to FCC from Southern

Anticipate eight services per day (three southbound and one northbound in the morning and vice versa in the evening)

Approx 1,900 extra seats per day

Page 17: First Capital Connect Hertfordshire County Council Overview & Scrutiny Committee 20 May 2010

From 2014 – new trains

Fixed length Two designs Lightweight Walk-through 2+2 seating Different customer

needs Cutting-edge

information systems

Page 18: First Capital Connect Hertfordshire County Council Overview & Scrutiny Committee 20 May 2010

From December 2016

New fleet complete; many more 12-cars Up to 24 trains per hour in central London Great Northern route linked to TL New cross-

London destinations

London Bridgerebuilt

Page 19: First Capital Connect Hertfordshire County Council Overview & Scrutiny Committee 20 May 2010

Reliability on the Thameslink route

Service October 2009 to January 2010 simply not good enough – driver action, winter weather impact

Worked hard to improve services

Plus investment plans in key areas

Page 20: First Capital Connect Hertfordshire County Council Overview & Scrutiny Committee 20 May 2010

£10 million investment

Spread between:

Improvements to Customer Information Systems

Enhanced maintenance regime for class 319 trains e.g. door mechanisms, heating elements

Ticket barriers to be installed at Harpenden, Finsbury Park, Leagrave and West Hampstead – improved security, reduced fare evasion

Increased discount and refund scheme

Page 21: First Capital Connect Hertfordshire County Council Overview & Scrutiny Committee 20 May 2010

Improved customer informationMore on all of this later

Upgrades to infrastructure and software behind Customer Information Screens – by end of year with priority to Thameslink route

New FCC website by end of July (involving key stakeholders in design)

260 PDAs gives frontline staff real-time information

Page 22: First Capital Connect Hertfordshire County Council Overview & Scrutiny Committee 20 May 2010

Increased fleet reliability Class 377:

– Full fleet finally available on 18 January (over 300 days late)– Poor reliability addressed through travelling fitters and reliability improvement programme for June 2010

Deferred class 319 C6 / traction reliability improvements re-commenced Aug 2009 for completion on schedule (May 2010)

319 door fault investment in new diagnostics equipment to aid early identification of train faults

Repaired snow damaged 319 traction motors– Initially 36 damaged motors, affecting 19 units– Repairs completed by 10 February

Page 23: First Capital Connect Hertfordshire County Council Overview & Scrutiny Committee 20 May 2010

Investment in you and our people

Customer and stakeholder engagement– Regular Meet the Manager events– Passenger Panel (under consideration)– Honest communication

‘Your Voice’ staff survey– Action plans by department to affect change– Do what we say we will do

Page 24: First Capital Connect Hertfordshire County Council Overview & Scrutiny Committee 20 May 2010

Driver recruitment

Working to become much less reliant on rest day and overtime work

On TL 7 fresh recruits in training now and 8 more from Monday next week

On TL 34 more qualified drivers (10 in training now + 24 to follow)

Page 25: First Capital Connect Hertfordshire County Council Overview & Scrutiny Committee 20 May 2010

Driver recruitment

GN route – 18 more trainees

Takes into account numbers expected to retire/leave/sickness

Plus: 15 more for Thameslink Programme14 more for GN ‘More Seats for You’ - HLOS

Page 26: First Capital Connect Hertfordshire County Council Overview & Scrutiny Committee 20 May 2010

Performance update

Page 27: First Capital Connect Hertfordshire County Council Overview & Scrutiny Committee 20 May 2010

Performance – all FCC

89.39% of trains arrived on time last

financial year

PPM for 09-10 full year was 89.39% against a target of 91.65%. Fleet and Infrastructure and problems affected TL performance. Infrastructure problems have affected GN performance.

First Capital Connect PPM Comparison

70%

74%

78%

82%

86%

90%

94%

98%

01 02 03 04 05 06 07 08 09 10 11 12 13

Period

PP

M %

09/10 07/08 08/09 This Year Target

First period this year (month of April) 93.09% of trains

arrived on time (target is 92.56%)

All FCC – full year to 31 March 2010

Page 28: First Capital Connect Hertfordshire County Council Overview & Scrutiny Committee 20 May 2010

Performance – TL route

PPM MAA was 86.54% against a target of 89.69%. PPM MAA is 2.42% lower than at the same time last year.

Thameslink PPM Comparison

60%

64%

68%

72%

76%

80%

84%

88%

92%

96%

01 02 03 04 05 06 07 08 09 10 11 12 13

Period

PP

M %

09/10 07/08 08/09 This Year Target

86.54% of trains arrived on time last

financial year. 92.00% were on time in final period of year

First period this year (month of April) 92.15% of trains

arrived on time (target is 90.59%)

Thameslink route – full year to 31 March 2010

Page 29: First Capital Connect Hertfordshire County Council Overview & Scrutiny Committee 20 May 2010

Performance – GN route

92.96% of trains of trains arrived on

time last financial year

PPM for 09/10 year 92.96% compared to 93.62% last year. GN PPM MAA was 92.96% against target of 93.62%. PPM MAA was below target, and hampered by snow in periods 10 and 11.

Great Northern PPM Comparison

70%

74%

78%

82%

86%

90%

94%

98%

01 02 03 04 05 06 07 08 09 10 11 12 13

Period

PP

M %

09/10 07/08 08/09 This Year Target

First period this year (month of April) 94.29% of trains arrived on time in (target is 94.93%)

Great Northern route – full year to 31 March 2010

Page 30: First Capital Connect Hertfordshire County Council Overview & Scrutiny Committee 20 May 2010

Engineering performance

GN Route

TL Route

0

10000

20000

30000

40000

50000

P10

02

P10

03

P10

04

P10

05

P10

06

P10

07

P10

08

P10

09

P10

10

P10

11

P10

12

P10

13

P11

01

313 mpc 317/1 mpc 365 mpc 321 mpc313MAA 317/1 MAA 365 MAA 321 MAA

0

5000

10000

15000

20000

P1

00

2

P1

00

3

P1

00

4

P1

00

5

P1

00

6

P1

00

7

P1

00

8

P1

00

9

P1

01

0

P1

01

1

P1

01

2

P1

01

3

P1

10

1

377 mpc 319 mpc 377 MAA 319 MAAMidlife EMU Unit Miles P13 MP5MD MAASouth West Trains Class 455 590,134 34,714 29,660First Capital Connect Class 365 467,864 27,521 27,852Southern Class 455/8 227,056 28,382 23,012NXEA Class 321 507,727 24,177 22,729First Capital Connect Class 321 36,772 36,772 22,624Southern Class 456 98,660 19,732 19,225NXEA Class 317/7&8 212,814 21,281 18,465First Scotrail Class 320 90,352 8,214 15,777Northern Class 323 122,153 13,573 15,072Southeastern Class 465/1 255,855 11,630 13,670NXEA Class 317/6 199,534 13,302 13,607Southeastern Class 466 200,091 11,770 12,857NXEA Class 315 317,340 10,237 12,855Southeastern Class 465/9 206,570 13,771 12,791First Scotrail Class 318 133,244 26,649 12,759London Midland Class 323 179,417 14,951 12,755First Capital Connect Class 313 230,744 9,614 12,652First Capital Connect Class 319 781,235 13,021 12,634Southeastern Class 465/0 271,812 12,943 11,663First Scotrail Class 322 24,891 12,446 11,513First Capital Connect Class 317/1 78,868 13,145 10,843Southeastern Class 465/2 80,574 20,144 10,441NXEA Class 317/5 109,897 10,990 10,090Southern Class 442 77,840 19,460 9,499London Overground Class 313 46,367 46,367 9,247Merseyrail Class 507 153,142 6,126 9,051Merseyrail Class 508 140,132 10,009 8,449Northern Class 321 19,960 6,653 6,965First Scotrail Class 314 54,100 3,607 5,663Average 14,605 14,527

Page 31: First Capital Connect Hertfordshire County Council Overview & Scrutiny Committee 20 May 2010

Fares – background to regulation

In June 2003 the Strategic Rail Authority (SRA) published the conclusions of its year long rail fares review. This major review of fares regulation - the first since privatisation - was aimed at redressing the balance between taxpayers and fare payers.

The report said that there were are only two principal sources of funds for the railway – fare payers and taxpayers. Revenue from fares had increased by 26% from 1997-98 to 2001-022, while railway investment had grown by 164% in the same period.

The SRA said that there had been a period of consultation from July - October 2002. Local authorities, train operating companies, rail industry bodies, rail user groups, Rail Passenger Councils and Passenger Transport Executives (PTEs) had been included in the consultation process.

Following the implementation of the review, the SRA said that approximately 45% of all fares would be regulated. The balance, as under the 1997 policy at the time of privatisation, would either be controlled by simplified fares “baskets” or would be open to market competition.

Page 32: First Capital Connect Hertfordshire County Council Overview & Scrutiny Committee 20 May 2010

Fares – more background info

Until the SRA’s fares’ review in 2003, the regulated fares price cap for annual increases was RPI minus 1.0%, based on the previous July’s RPI

This changed to RPI plus 1.0% from January 2004, based on the July 2003 RPI

The mechanism for fares regulation would be that all regulated fares would regulated by means of a fares basket

Each fares basket was constructed using January 2003 fares, weighted by the revenue received by that operator from the sale of that fare in 2002/03

Increases to individual fares within baskets was then to be limited to 5% above the basic policy (RPI plus 6.0%) in any given year.

A copy of the Press Release issued by the SRA on 19 June 2003 is available with the handouts of these slides

Page 33: First Capital Connect Hertfordshire County Council Overview & Scrutiny Committee 20 May 2010

Car park charges

They are not hidden; full details of the charges at each car park are available as a PDF on our website

Leaflets are available, showing the tariffs at all stations operated by FCC

Prices related to those in other, town centre car parks in same location

Major investment in high quality free cycle parking at all FCC stations and more on way

Page 34: First Capital Connect Hertfordshire County Council Overview & Scrutiny Committee 20 May 2010

Customer service update

Page 35: First Capital Connect Hertfordshire County Council Overview & Scrutiny Committee 20 May 2010

Customer Information Update

CIS replacement software tender progressing Will create one system for all FCC More accurate information Fewer late notice platform alterations Easier to manage during disruption Driver announcements: good practices

being developed and encouraged

Page 36: First Capital Connect Hertfordshire County Council Overview & Scrutiny Committee 20 May 2010

Customer information update

Problem – how to get real-time information to our ticket inspectors, gate line and platform staff?

Solution – Blackberry smart phones with internet access.

260 devices by June 2010. 133 already issued to most ticket inspectors as well as gate line staff

This week: Blackfriars, St Albans, Luton Airport Parkway, Elephant & Castle

Page 37: First Capital Connect Hertfordshire County Council Overview & Scrutiny Committee 20 May 2010

Customer information update Blackberry gives access to:

• National Rail Enquiry staff services and other real-time information systems

• Emails sent from control

• Company information

www.firstcapitalconnect to be overhauled:

– more user friendly

– disruption updates clearer, more informative

– will involve key stakeholders in design

Page 38: First Capital Connect Hertfordshire County Council Overview & Scrutiny Committee 20 May 2010

Any Questions

?