Upload
haquynh
View
216
Download
1
Embed Size (px)
Citation preview
FIRE MITIGATION IN FACADE DESIGN & MATERIAL CHOICE
@ AUGUST 2017 By Satria Ramadhana
@ AUGUST 2017
1. MECHANISM OF FIRE SPREAD IN FACADES AND EXAMPLE OF FIRES INVOLVING BUILDING ENVELOPES
2. PERIMETER CURTAIN WALL FIRE PROTECTION
3. FIRE HAZARDS OF BUILDING ENVELOPES CONTAINING COMBUSTIBLE COMPONENTS
FAÇADE DESIGN
@ AUGUST 2017
CURTAIN WALL – BASICS FOR DESIGN
- GAP BETWEEN SLAB EDGE AND FAÇADE
- WHAT IS INSIDE THE BUILDING OR THE BUILDING TYPE
- WHERE AND WHEN IS IT A BENEFIT FOR COMPARTMENTALIZATION
- FIRE
- SMOKE BARRIER
- SOUND ATTENUATION
- WATER INFILTRATION AND DRAINAGE
- HORIZONTALITY AND VERTICALITY
- THE ACCOMMODATION OF MOVEMENT
FAÇADE DESIGN
@ AUGUST 2017
EXTERNAL WALL CLADDING – BASICS FOR DESIGN
- GAP BETWEEN EXTERNAL WALL AND CLADDING
- WHAT IS OUTSIDE THE BUILDING
- FIRE
- ACCOMMODATE AIR FLOW (SPECIAL CASE FOR RAIN SCREEN OR VENTILATED FAÇADE)
- HORIZONTALITY AND VERTICALITY
- AGE RESISTANT
@ AUGUST 2017
BEHAVIOUR OF FIRE
OXYGEN
FIRE CLASSIFACTION :
@ AUGUST 2017
ACCORDING TO THE AMERICAN STANDARD, FIRES ARE CLASSIFIED BY THE TYPES OF FUEL THEY BURN.
CLASS ACLASS A FIRES CONSIST OF ORDINARY COMBUSTIBLES SUCH AS WOOD, PAPER, TRASH OR ANYTHING ELSE THAT LEAVES AN ASH. WATER WORKS BEST TO EXTINGUISH A CLASS A FIRE.
CLASS BCLASS B FIRES ARE FUELED BY FLAMMABLE OR COMBUSTIBLE LIQUIDS, WHICH INCLUDE OIL, GASOLINE, AND OTHER SIMILAR MATERIALS. SMOTHERING EFFECTS WHICH DEPLETE THE OXYGEN SUPPLY WORK BEST TO EXTINGUISH CLASS B FIRES.
CLASS CCLASS C FIRES. ENERGIZED ELECTRICAL FIRES ARE KNOWN AS CLASS C FIRES. ALWAYS DE-ENERGIZE THE CIRCUIT THEN USE A NON-CONDUCTIVE EXTINGUISHING AGENT. SUCH AS CARBON DIOXIDE.
@ AUGUST 2017
FIRE CLASSIFICATION :
CLASS DCLASS D FIRES ARE COMBUSTIBLE METAL FIRES. MAGNESIUM AND TITANIUM ARE THE MOST COMMON TYPES OF METAL FIRES. ONCE A METAL IGNITES DO NOT USE WATER IN AN ATTEMPT TO EXTINGUISH IT. ONLY USE A DRY POWDER EXTINGUISHING AGENT. DRY POWDER AGENTS WORK BY SMOTHERING AND HEAT ABSORPTION.
CLASS KCLASS K FIRES ARE FIRES THAT INVOLVE COOKING OILS, GREASE OR ANIMAL FAT AND CAN BE EXTINGUISHED USING PURPLE K, THE TYPICAL AGENT FOUND IN KITCHEN OR GALLEY EXTINGUISHERS.
@ AUGUST 2017
EFFECTS OF FIRE
FIRE ORIGIN
HEAT
SMOKE
PROBLEMS FOR HIGH RISE BUILDINGS
@ AUGUST 2017
• Fuel Load & Fire Spread
• Smoke Development and Movement
• Life Safety & Occupant Evacuation
• Fire Brigade Operations
MECHANISM OF FIRE SPREAD IN FACADES AND EXAMPLE OF FIRES INVOLVING BUILDING ENVELOPE
@ AUGUST 2017
@ AUGUST 2017
BREAKDOWN OF MECHANISMS OF FIRE SPREAD IN FACADES
The key initiating types of Fire Spread ;
1. Fire spread though open areas
2. Fire spread though vertical cavity
@ AUGUST 2017
MECHANISMS OF FIRE SPREAD IN FACADES
EXTERNAL FIRE SPREAD
Fire spread though open area
Fire, allowed to develop, may flash over and break out through windows.
Flame spread up over or through the cladding.
Flame can extend over 2 meters above window opening. Regardless of cladding materials.
If fire re-enters building secondary fires may then develop.
@ AUGUST 2017
MECHANISMS OF FIRE SPREAD IN FACADES
ANOTHER EXAMPLE OF FIRE SPREAD THROUGH OPEN AREAS
@ AUGUST 2017
MECHANISMS OF FIRE SPREAD IN FACADES
EXTERNAL FIRE SPREAD
Fire spread though External cladding panel
Cavities either- Part of the system- Created by delamination
Flame in the cavities can extend 5 to 10 times original length regardless of the material present.
FACADE FIRE EXAMPLES
@ AUGUST 2017
FIRE SPREAD IN BUILDING ENVELOPES
A few points to consider with fires involving multi-storey buildings
- Risk to life
- Loss of personal or commercial property
- Disruption to commercial bussiness
- Domestic life impact where dwellings are involved
PERIMETER CURTAIN WALL FIRE PROTECTION
@ AUGUST 2017
@ AUGUST 2017
VISION GLASS
SPANDREL GLASS
Fire begins on a floor, as products of combustion fuel the fire. Pressure and heat accumulate between the floors as positive pressure builds and the heat rises to the ceiling
DYNAMICS OF VERTICAL FIRE SPREAD IN HIGH-RISE BUILDING
UNPROTECTED PERIMETER JOINT
@ AUGUST 2017
DYNAMICS OF VERTICAL SPREAD IN HIGH-RISE BUILDING
The fire will follow the flow of air currents and if the void between the floor and curtain wall is not properly sealed, flames will spread vertically…
@ AUGUST 2017
DYNAMICS OF VERTICAL SPREAD IN HIGH-RISE BUILDING
Fire attacks the curtain wall structure from both sides causing a premature failure of the wall structure and potentially the breaking of the vision glass above!
Flames may erupt through the windows as oxygen fuels the fire further.
Elevated temp. and pressure breaks lower
vision glass
@ AUGUST 2017
DYNAMICS OF VERTICAL SPREAD IN HIGH-RISE BUILDING
PROTECTED PERIMETER JOINTFirestop Coating or Sealant over mineral wool safingA properly designed & tested
Perimeter Fire Barrier Systemnot only protects the perimeter joint but critical wall framing and support elements as well!
Properly installed & supported mineral wool spandrel insulation
@ AUGUST 2017
DYNAMICS OF VERTICAL SPREAD IN HIGH-RISE BUILDING
WHAT DOES THE CODE SAY?
“The perimeter joint must be sealed with an approved material or system that extends this rating to the exterior wall surface”
CODE COMPLIANCE
Firestopping the perimeter joint is mandatory.
1. Designing the wall to keep the firestop system in place for the rated period of the floor is an obvious necessity.
Protecting the perimeter joint:
2. Designing and installing the firestop correctly is the final step!
@ AUGUST 2017
Main risk to the building other than the perimeter joints is
@ AUGUST 2017
The Leap Frog Effect…
@ AUGUST 2017
Fire may break out of a window and leap back to the floor above!
That being the case…
The Leap Frog effect…
@ AUGUST 2017
VISION GLASS
SPANDREL GLASS
Why bother to protect the perimeter???
While sprinklers can help in containing and slowing of some types of fires they are not a total solution. They do not reduce the requirements for protection of the safing slot! and are not a total solution for the Leap Frog effect
The Leap Frog effect…
@ AUGUST 2017
VISION GLASS
SPANDREL GLASS
Due to this many engineers are requested to reduce sprinkler requirements as a cost savings.
The Leap Frog affect…
The fact is, depending on window spacing and other factors, the fire may jump!
So what exactly does a Perimeter Fire Barrier System do?
@ AUGUST 2017
What is the purpose of Fire Barrier System on Façade ?
Slows the process down. Of course it depends on window spacing and other construction factors…
As well as the nature and severity of the fire…
The Perimeter Fire Barrier System
@ AUGUST 2017
Along with sealing the slot area, a well engineered system provides structural protection and maximizes the integrity of the wall system…
Keeping the wall and window system above the fire, intact for longer!
@ AUGUST 2017
The Perimeter Fire Barrier System
• Prevents the migration of flame, hot gases and smoke through to floors above.
• Buys time for occupants to escape.
• Buys time for first responders to secure the building
• Provides additional protection in the event of a sprinkler or detection failure.
@ AUGUST 2017
The Perimeter Fire Barrier System
• Extends the rating of the floor to the wall.
• Forces the fire to exit the building in order to propagate to upper floors.
• Protects structural elements and helps prevent catastrophic failure of the spandrel system.
• Maximizes fire protection afforded by the non-rated wall.
@ AUGUST 2017
The Perimeter Fire Barrier System
Provides energy savings through increased thermal efficiencies throughout the life of the building…
When considered this way, the life safety benefits are free!
@ AUGUST 2017
The Perimeter Fire Barrier System
How Are Perimeter Fire Barrier Systems on the
Curtain wall Tested?
@ AUGUST 2017
Testing on the curtain wall systems :
@ AUGUST 2017
3 Main standards :1. ASTM E2307 : “Standard Test Method for Determining Fire Resistance
of Perimeter Fire Barriers Using Intermediate-Scale, Multi-Story Test Apparatus”.
2. EN 1364 – Part 3 : “Fire resistance curtain walling systems - full configuration” – Fire resistant Glazing.
3. EN 1364 – Part 4 : “Fire resistance of parts of curtain walling ” – Fire resistant Glazing.
Comparison Each Codes Methodology :
@ AUGUST 2017
ASTM E2307
Standard Test Method for Determining Fire Resistance of Perimeter Fire Barriers Using
Intermediate-Scale, Multi-Story Test Apparatus
@ AUGUST 2017
@ AUGUST 2017
ASTM E2307 Chamber
ELEVATION SECTION
Curtain Wall Test Assembly
Pre-Burn
Transom above floor
Transom below floor
Mechanical attachments
supporting insulation
Mineral wool insulation at
spandrel area
Mullions
@ AUGUST 2017
AssemblyInterior View
Pre-Burn
Thermocouples measuring
temperature rise
@ AUGUST 2017
Interior Burner Lit - Time: 0:00 minute
@ AUGUST 2017
Exterior Burner Lit - Time: 0:05 minutes
@ AUGUST 2017
Flames Climbing Exterior
Time: 0:15 minutes
@ AUGUST 2017
Melting of Mullions &
Transoms
Time: 0:45 minutes
@ AUGUST 2017
@ AUGUST 2017
Vision Glass Breaks
Time: 2:00 hrs
@ AUGUST 2017
Burner Off at 2 hours
@ AUGUST 2017
Post Test:
Close up Detail of Mullion and Transom
Damage
@ AUGUST 2017
Post Test – Interior View
@ AUGUST 2017
Perimeter Fire Barrier Evaluation for Curtain Wall
Design
@ AUGUST 2017
• Mechanically Attached Curtain Wall Insulation
• Protect Aluminum Mullions
• Compression-fit Safing Insulation -as required per tested assembly Install Safing Impaling Clips -as required per tested assembly
• Provide Backing/Reinforcement Member at Safing Line
Basic Design Criteria to be used for future facades –Perimeter Fire Barrier Curtain Wall
@ AUGUST 2017
@ AUGUST 2017
WHAT IS THE PRIMARY CAUSE OF DEATH IN FIRE ?
• Mechanically Attached Curtain Wall Insulation
• Protect Aluminum Mullions
• Compression-fit Safing Insulation -as required per tested assembly Install Safing Impaling Clips -as required per tested assembly
• Provide Backing/Reinforcement Member at Safing Line
Basic Design Criteria – Perimeter Fire Barrier Curtain Wall
@ AUGUST 2017
• Applied Firestop Coating , for “Smoke Containment,”
Benefits of Specifying A Listed Perimeter Joint System
• Completes the curtain wall package
• Applies pedigreed testing and competent engineering
• Assists the local authority civil defense
• Standardizes design and cost
• Limits liability
• Provides energy conservation from insulation value
@ AUGUST 2017
3. FIRE HAZARDS OF BUILDING ENVELOPE CONTAINING COMBUSTIBLE COMPONENTS
@ AUGUST 2017
Many combustible materials are in use for building envelope assemblies ;
@ AUGUST 2017
1. To improve energy performance
2. Reduce water and air infiltration
3. To allow aesthetic design flexibility
THERE HAVE BEEN A NUMBER OF DOCUMENTED FIRE INCIDENTS INVOLVING COMBUSTIBLE MATERIAL ON THE BUILDING ENVELOPES…
Type of combustible material on the building envelope in common use ;
@ AUGUST 2017
1. Synthetic stucco
2. Aluminium composite panel (non fire rated type)
3. High pressure laminates
4. Rain screen cladding or ventilated facade
5. Gaskets, seismic and expansion joints, etc.
These façade systems are typically complex assemblies of different material types and layers which may include insulation layers and vertical cavities.
HOW IMPORTANT IS USING NON-COMBUSTIBLE PRODUCTS FOR FAÇADE ASSEMBLIES?
EXAMPLE: ALUMINIUM COMPOSITE MATERIALS
FINDINGS FROM RESEARCH
FOUR PRIMARY REASONS FOR SPREAD OF FIRE IN A TYPICAL LDPE CORE ACP CLADDED BUILDINGS.
• The Foam Backer Rod is one of the first to ignite and burns the polyethylene sealant. Fire movesswiftly through the continuous sealant and backer rod aided by bitumen paint .
• The cavity caused due to sealed façade and lack of cavity barrier creates a tunnel effect for fire to spread up the floors very quickly.
• The LDPE core of ACP panel and aluminium skin both melt and droplets contribute to furtherspread of fire, as well as onto any fire personnel below.
• The fire spreads both from the back of the facade and front of the façade, aided by winds and cavities and further fuelled by droplets of LDPE and falling debris of burning panels .
BUILDINGS ARE ENGULFED IN FIRE WITHIN MINUTES !
Fire Incident cases involving combustible exterior wall assembly;
Note : Literature of fire incident cases involving exterior wall assemblies has been found to be limited, base on report of the news paper articles with no specific information on material, fire behaviour or mechanism of fire spread
Al Tayer Tower – Sharjah, UAE, 2012
Residential building with 408 unit, 34 residential floors and 6 parking storey
Building clad with aluminiumcomposite panels consisting of aluminium with polyethylene core (PE).
Fire Incident cases involving combustible exterior wall assembly;
Note : Literature of fire incident cases involving exterior wall assemblies has been found to be limited, base on report of the news paper articles with no specific information on material, fire behaviour or mechanism of fire spread
Saif Belhasa Building – TecomDubai, UAE, 2012
Residential building with 156 unit, 13 residential floors and lower level parking place
Building clad with aluminiumcomposite panels consisting of aluminium with polyethylene core (PE).
Fire Incident cases involving combustible exterior wall assembly;
Note : Literature of fire incident cases involving exterior wall assemblies has been found to be limited, base on report of the news paper articles with no specific information on material, fire behaviour or mechanism of fire spread
The Wooshin Golden Suites –Busan, South Korea, 2005
140m high mixed use (mostly apartment) Building.
Building clad with aluminiumcomposite panels consisting of aluminium with polyethylene core (PE).
The fire was examined in details in “fire science and technology” journal article.
Fire Incident cases involving combustible exterior wall assembly;
Note : Literature of fire incident cases involving exterior wall assemblies has been found to be limited, base on report of the news paper articles with no specific information on material, fire behaviour or mechanism of fire spread
Grenfell Tower – London, England, 2017
Residential building with 24 residential floors
Building clad with aluminiumcomposite panels consisting of aluminium with polyethylene core (PE).
Fire Incident cases involving combustible exterior wall assembly;
Note : Literature of fire incident cases involving exterior wall assemblies has been found to be limited, base on report of the news paper articles with no specific information on material, fire behaviour or mechanism of fire spread
The Address Downtown –Dubai, UAE, 31 December 2015
Hotel Residential building – 22nd
tallest building in Dubai.
Building clad with aluminiumcomposite panels consisting of aluminium with polyethylene core (PE).
• ACP PANELS - CLASS B - has over 70% Mineral Core and A2 has over 90% Mineral Core with major component being MAGNESIUM HYDROXIDE . Solid magnesium hydroxide has smoke and fire retarding properties. This is due to the endothermic decomposition it undergoes at 332 degrees celsius.
• Mg(OH)2 (s) → MgO (s) + H2O (g)
• The heat absorbed by the reaction acts as a retardant by delaying ignitionof the associated substance. The water released dilutes any combustible gas and inhibits oxygen from aiding the combustion.
WHAT GIVES MINERAL CORE B & A2 PANELS SUCH SUPERIOR FIRE PENETRATION PROPERTIES ?
A NFPA 285 OR BS 8414 COMPLIANT FIRE RATED ASSEMBLY REQUIRES A HIGH FIRE RATED PANEL. NORMALLY ONLY B RATED AND ABOVE PANELS CAN PASS THE FULL ASSEMBLY TEST.
OVER
PERFORMANCE
100% LDPE CORE
ACP
OVER 70%
MINERAL CORE
ACP
OVER 90%
MINERAL CORE
ACP
OVER 95%
ALUMINIUM
HONEYCOMB
EN13501 A1 SOLID
ALUMINIUM 3 MM
COMBUSTIBILTY
RATING COMBUSTIBLE
LOW
COMBUSTIBILITY
NON
COMBUSTIBLE
NON
COMBUSTIBLE
NON
COMBUSTIBLE
NFPA 285/ BS 8414
PASS NO YES YES YES YES
ASTM E 84 CORE
BURNING CLASS A
RATING NO YES YES YES YES
ASTM D 1929
IGNITION TEST PASS NO YES YES YES YES
EN 13501 s1
d0 Rating E B A2 A2 A1
How Are External wall Materials Tested?
@ AUGUST 2017
Steel stud
41 x 92 mm
Gypsum
wallboard
16 mm
w=4.3m
2.0m
h=5.5m
h=0.76m
0.5m
0.76m1.2m
Room burner
Aluminium
composite panel
Foil backed
fiber glass
insulation
Test duration: 30
min.
Pass/Fail: No spread
of flame beyond the
area directly exposed
to flame from fire
source.
Test apparatus Fixation method
Window burner
ISMA TEST METHOD FOR COMPOSITE PANELS AS EXTERNAL CLADDING (FULL SCALE)
@ AUGUST 2017
(CAN / ULC-S134-92)
FULL-SCALE EXTERIOR WALL FIRE TEST
@ AUGUST 2017
Comparison of Fire Safety
Test method: Intermediate Scale Multi-story Apparatus
(ISMA) in accordance with UBC 26-9, U.S.A.
Specimen: Fire Rated ACM with Non-Combustible Mineral Filled Core
Test method: Full-scale Exterior Wall Fire Test in accordance
with CAN/ULC-S 134-92, Canada
Specimen: Conventional ACM with 100% Polyethylene Core
6100
9800
2600
1370 Crib and Gas Burner
4200
55001980
760 Window burner
Room burner
17:30 Flame at top of sample27:00 Smoke continuous from across the top and from sides of the test structure
ACM (100% PE Core) Fire Rated ACM
Before test – Panels are installed Before test – Panels are installed
Fire Rated ACMACM (100% PE Core)
0:00 Ignition of main burner 0:00 Ignition of room burner
Fire Rated ACMACM (100% PE Core)
4:00 Flame continuously issuing from the window. 5:00 Window burner is ignited and moved into position.
Fire Rated ACMACM (100% PE Core)
7:15 Bright flame attached to the wall above the window. 7:30 Flames sustained to 7 ft and discoloration of paint left side at 6 ft. Warping to 11 ft.
Fire Rated ACMACM (100% PE Core)
13:00 Flame attached to the caulking joint above the lintel. 12:30 Discoloration of paint to 13 ft.
Fire Rated ACMACM (100% PE Core)
16:00 Flame attached to the wall 1 m above the window. 15:00 Flames intermittent to 9 ft. Flame sustained to 8 ft.
Fire Rated ACMACM (100% PE Core)
16:07Flame attached to the wall 2 m above the window.
16:22 Flame attached to the wall 3 m above the window.
16:55 Flame attached to the wall 6 m above the window.
ACM (100% PE Core) ACM (100% PE Core) ACM (100% PE Core)
17:30 Flame at top of sample. 17:35 Gas was shut off. End of test. 18:00 Light gray smoke from top of structure
Fire Rated ACMACM (100% PE Core)
24:00
27:00Smoke continuous from across the top and from sides of the test structure.
30:00Burner flame off. Residual smoking lightly from top, sides, and window.
Fire Rated ACMFire Rated ACMFire Rated ACM
After extinguishing After cooling down
Fire Rated ACMACM (100% PE Core)
Conclusion and Reaction to the fire requirement
@ AUGUST 2017
1. No action according to the fire regulations,
2. Requirements for non combustible materials, (EN 13501, ASTM E84, BS 476)
The various regulations around the world generally fit into one of the four categories and how they influence the choice of materials :
3. Requirements for small scale reaction to fire test only,
4. Requirements for the full scale façade test
THANK YOU
@ AUGUST 2017