Upload
others
View
2
Download
0
Embed Size (px)
Citation preview
20 MARCH 2017
FINANCINGMERKUR OFFSHORE
2
3
20 MARCH 2017
FINANCINGMERKUR OFFSHORE
I N T R O D U C T I O N A M S C A PP A N E U R O P E A N E X P E R I E N C E
5
Prinses AmaliaCapacity: 120 MW
Sheringham ShoalCapacity: 317 MW
BelwindCapacity: 165 MW
NordergrundeCapacity: 110 MW
MerkurCapacity: 396 MW
GeminiCapacity: 600 MW
LuchterduinenCapacity: 129 MW
Borssele I & IICapacity: 700 MW
Borssele III & IVCapacity: 700 MW
Total offshorecapacity advised:
4,929 MW13 projects
Total onshorecapacity advised:
288 MW15 projects
TréportCapacity: 496 MW
NoirmoutierCapacity: 496 MW
DunkerqueCapacity: 600-700 MW
I N T R O D U C T I O N A M S C A PO F F S H O R E W I N D T R A C K R E C O R D
6
Prinses Amalia(120 MW)
First ever offshore wind project
financed with non recourse debt
Belwind(165 MW)
First ever project to include non-utility
equity only,First ever EIB
financing
Gemini(600 MW)
Largest ever project financed offshore
wind project
Nordergründe(111 MW)
Identified and fully negotiated potential acquisition incl. 3rd party equity raising
Luchterduinen(129 MW)
Managing the business case and
responsible for contracting PPA and
Construction Insurance Package
Gemini proved that a EUR 2.8 billion offshore wind project can be financed within record timelines. This significant achievement was further recognized by winning three financial awards: the Project Finance International 2014 Power Deal of the year, the Infrastructure Journal 2014 European Wind Deal of the year, and the Infrastructure Journal 2014 Overall Deal of the Year.
I N T R O D U C T I O N A M S C A PO F F S H O R E W I N D T R A C K R E C O R D
7
Borssele 1&2(700 MW)
Financial advisor, coordinated bid &
raised 100% of equity
Borssele 3&4(700 MW)
Financial advisor, coordinated bid &
raised 100% of equity
Merkur(396 MW)
First large scale deployment of the
GE - Haliade
Awards 2016
Undisclosed(75–150 MW)
Financial advisor, equity valuation &
coordination of binding offer
HKZ I&II(700 MW)
Strategic advisor, business case
assessment new technology
Amsterdam Capital Partners ranked joint fourth place oninspiratia’s 2016 financial adviser rankings in the top EUprimary market
Dunkirk(400–700 MW)
Financial advisor, Tender bid
management and arranging 100% of
debt & equity
8
MERKUR OF FS HORE
F I N A N C I N G M E R K U R O F F S H O R EI N T R O D U C T I O N
9
B A C K G R O U N D• The Merkur project (formerly known as MEG 1) was originally owned by German developer
Windreich, which went into administration• Following an unsuccessful approach to the debt market in 2014, DEME took over the project
development in late 2014• In April 2015, AMSCAP was appointed financial advisor and project director, assigned to restructure
the project, raise the equity and arrange the debt financing• Starting in April 2015, the project was completely restructured, including a new turbine supplier and
a new balance of plant contract, adjusted park lay out and a new grid connection• In record timelines:
the project development was finalized in October 2015 the equity raising process followed thereafter, with all equity committed by February 2016 the debt was launched in April 2016 and financial close was reached 4 months later
F I N A N C I N G M E R K U R O F F S H O R EP R O J E C T O V E R V I E W
10
P R O J E C T D E S C R I P T I O N• 396 MW• 45km north of Borkum• Average water depth: 30m• Average wind speed: ~10m/s• 2 contact structure, unique for German
offshore wind• GeoSea as EPCi contractor for the Balance
of Plant, GE as turbine supplier• 66 GE Haliade 150-6MW with a 150.95m
rotor diameter• Start offshore construction: April 2017• Commissioning: January 2019
F I N A N C I N G M E R K U R O F F S H O R EP R O J E C T O V E R V I E W
11
T E C H N I C A L S P E C I F I C AT I O N S• 66 GE Haliade 150-6MW WTG• Permanent magnet direct-drive generator with a
150.95m rotor diameter and blade length of 73.5m• WTG mounted on MP foundations with bolted
flange connections• MP diameter from 7.6 m at shallow locations to 8.1
m at deeper locations.• MP thickness from 70 mm to 90 mm• WTG connected to the offshore substation through
12 strings (33kV) with a total length of 77.1km
F I N A N C I N G M E R K U R O F F S H O R EP R O J E C T O V E R V I E W
12
C O N T R A C T I N G S T R U C T U R E• 2 contact structure, unique for German offshore wind• GeoSea as EPCi contractor for the Balance of Plant• GE as turbine supplier• Both contractors take full weather risk• Interface mitigated through a Cooperation Agreement • 15 year full maintenance (un/scheduled) including availability guarantees
BoP Contract Turbine Supply Agreement
Wind turbine supplyFoundations Inter Array Cabling Installation & Logistics
Offshore Substation
BoP Service & Maintenance
Turbine Service & Maintenance
F I N A N C I N G M E R K U R O F F S H O R EP R O J E C T O V E R V I E W
13
EQUITY 30%(EUR500m)
DEBT 70%(EUR1,150m)
KfW – EUR350m Commercial Lenders – EUR800m
50% 25% 12.5% 12.5%
F I N A N C I N G S T R U C T U R E• All financial stakeholders on board as of start construction
F I N A N C I N G M E R K U R O F F S H O R EU S E S A N D S O U R C E S
14
Facilities (EUR M) Funding Risk Senior debt Standby debt
Commercial Facilities:
Commercial Term Loan Facility CL CL 789
Contingent Loan Facility CL CL 28
KfW Facility
KfW Term Loan Facility CL CL 350
KfW Contingent Loan Facility CL CL 12
Decommissioning LC Facility 53
Total 1,192 41
Uses EUR M %Construction costs 1,406 86%Base contingency 60 4%Financing costs & DSRA funding 161 10%Total 1,628 100%Standby budget 58
Sources EUR M %Equity 391 24%Pre-completion revenues 98 6%Senior debt 1,139 70%Total 1,628 100%Standby equity 17 30%Standby debt 41 70%
F I N A N C I N G M E R K U R O F F S H O R EC R I T I C A L S U C C E S S F A C T O R S
15
T O TA L R E D E S I G N B A S E D O N P R I M A R Y F I N A N C I N G R E Q U I R E M E N T S• Swift and successful project re-design (no MEG 1 legacy), including all-new contractors, advisors and
equity investors• Approach aligned with equity partnering and debt raising processes and strategy• Dual contracting structure, lowering of risk profile and enabling financial investors to get
comfortable with the minimised construction risks• Strong governance structure from the outset
R E A L I S T I C A N D E F F I C I E N T F I N A N C I N G P R O C E S S• Targeted equity approach, including a pre-defined and agreed highly orchestrated process, allowing
for the equity raising within 4 months of finalizing business case• Agreement on governance structure at early stage, with equity documentation negotiated in parallel• Well-structured financing package and unique negotiating process enabling a record breaking 4
months from debt launch to close
F I N A N C I N G M E R K U R O F F S H O R ET I M E L I N E S
16
April 2015: Amscap appointedfinancial advisor, establishmentgovernance structure, appointproject advisors, agree contracting/ financing strategy and timelines
April – June: turbine selection andcontracting, hire project team and buildbusiness case
July – August: prepare businesscase, draft Equity InformationMemorandum, preparemarketing material, shortlistpotential investors
September: send outinitial materials, obtainNBO’s, short listinvestors
October – December: detailed duediligence with short listed investors
January 2016: select finalequity consortium
February: finalise equity terms(equity term sheet, commercialterms SPA, governance) andequity close
March: align sponsor consortium onproject and debt terms, preparedebt package
April: bank launch
April – May: lenders duediligence
End May: lenderscredit approval andbank selection,appointment MLAs
June – July: debtdocumentationnegotiations
Financial Close
2015
Apr Jun Jul Sep Dec
2016
May NovOctAug
Jan Apr May JulMar AugJunFeb
Q U E S T I O N S
NIEUWE PRINSENGRACHT 25-1 / 1018 EE AMSTERDAM / THE NETHERLANDS / www.amscap.eu