11
© 2012-13- Assoc Prof. Sami Fethi, EMU, Revision Revision MGMT 405, Production Man. MGMT 405/ FINAL EXAM/REVISION Business Department FALL 2014-15

Financial Management Review

Embed Size (px)

DESCRIPTION

Future Value, Retrospective Entities, Decisive functions.

Citation preview

Page 1: Financial Management Review

© 2012-13- Assoc Prof. Sami Fethi, EMU, Revision

Revision

MGMT 405, Production Man.

MGMT 405/ FINAL EXAM/REVISION

Business Department

FALL 2014-15

Page 2: Financial Management Review

MGMT 405, Production Man., 2012/13 © 2012-13- Assoc Prof. Sami Fethi, EMU, Revision

Revision

2

Section A/Multiple Choice-ExampleSection A/Multiple Choice-Example1) Which of the following part does not indicate the concept of project? A) TimeB) CostC) specific objectivesD) Operations

2) Which of the following is not one of project tools? A) Work breakdown structureB) Network diagramC) Gantt chartsD) Management

Page 3: Financial Management Review

MGMT 405, Production Man., 2012/13 © 2012-13- Assoc Prof. Sami Fethi, EMU, Revision

Revision

3

Section A/Multiple Choice-ExampleSection A/Multiple Choice-Example3) Which of the following part cannot be defined as inventory? A) final product B) raw materialsC) suppliesD) Delivered parts

4) Which of the following is not one of dependent demand goods ? A) ChipB) Mother boardC) Power unitD) Computer

5) Which of the following word means waste? A)AndonB)JidokaC)Poka-yokeD)Muda

Page 4: Financial Management Review

MGMT 405, Production Man., 2012/13 © 2012-13- Assoc Prof. Sami Fethi, EMU, Revision

Revision

4

Section B/type 1-Example- Section B/type 1-Example- KPA/KPM The following table contains information related to

the major activities of a research project. Use the information to do the following: each case may require the use of a dummy activity.

(a)Draw a precedence diagram using AOA(b)Find the critical path based AOA.(c)Determine the expected length of the project.(d)Calculate the amount of slack time for each path

as well as ES, EF, LS and LF

Page 5: Financial Management Review

MGMT 405, Production Man., 2012/13 © 2012-13- Assoc Prof. Sami Fethi, EMU, Revision

Revision

5

Section B/type 1-Example- Section B/type 1-Example- KPA/KPM

Activity Immediate

Predecessor

Expected

Time (days)

a - 5

b - 8

c - 2

d a 7

e b 3

f b 6

g c 10

h f 8

i f,g- 15

k d,e 2

end h,i,k -

Page 6: Financial Management Review

MGMT 405, Production Man., 2012/13 © 2012-13- Assoc Prof. Sami Fethi, EMU, Revision

Revision

6

Section B/Type2-Example-PERTSection B/Type2-Example-PERTGiven the following diagram:

Compute

(a) the expected time

(b) the expected duration

(c) Identify the critical

(d) path The variance

(e)The std. deviation

(f) the probability that the project can be completed within 26 weeks of its start (project manager receives a bonus of $ 1000)

(g) the probability that the project can be completed within 27 weeks of its start (project manager receives a bonus of $ 500).

Before complete the sections, do not forget to draw its AOA diagram.

Page 7: Financial Management Review

MGMT 405, Production Man., 2012/13 © 2012-13- Assoc Prof. Sami Fethi, EMU, Revision

Revision

7

Section B/Type2-Example-PERTSection B/Type2-Example-PERT

Activity Predecessor Time(weeks)A - 2-4-6 D A 6-8-10 E D 7-9-12 H E 2-3-5 F A 3-4-8 G F 5-7-9 B - 2-2-3 I B 2-3-6 J I 3-4-5 K J 4-5-8 C - 5-8-12 M C 1-1-1 N M 6-7-11 0 N 8-9-13 End H, G, K, 0  

Page 8: Financial Management Review

MGMT 405, Production Man., 2012/13 © 2012-13- Assoc Prof. Sami Fethi, EMU, Revision

Revision

8

Section C/type 1-Example-EOQSection C/type 1-Example-EOQA bakery buys flour in 25 pound bag. The bakery uses an average an average of 4860 bags a year. Preparing an order and receving a shipment of flour involves a cost of $ 10 per order. Annual carring cost is $ 75 per bag.(a) Determine the EOQ?(b) What is the average number of bags on hand?(c) How many orders per year will there be?(d) Compute the total cost of ordering and carring flour.(e) How much would that affect the minimum total annual cost if the ordering costs were to increase by $ 1 per order? 

Page 9: Financial Management Review

MGMT 405, Production Man., 2012/13 © 2012-13- Assoc Prof. Sami Fethi, EMU, Revision

Revision

9

A newspaper publisher uses roughly 800 feet of baling wire each day to secure bundles of newspapers while they are being distributed to carriers. The paper is published Monday through Saturday. Lead time is six working days. The company desires a service level of 95% when stock-out risk for various levels of safety stocks are as follows: 1500 feet, 0.10; 1800 feet, 0.05; 2100 feet, 0.02; and 2400 feet, 0.01? (a) What value of Z is appropriate? (b) Find the standard deviation of lead time? (c) What reorder point should be used?

Section C/type 2-Example-ROPSection C/type 2-Example-ROP

Page 10: Financial Management Review

MGMT 405, Production Man., 2012/13 © 2012-13- Assoc Prof. Sami Fethi, EMU, Revision

Revision

10

BONUS QUESTION-KanbanBONUS QUESTION-Kanban

A manager wants to determine the number of containers to use for incoming parts for a Kanban system to be installed next month. The process will have a usage rate of 80 pieces per hour. Because the process is new, the manager has assigned an inefficiency factor of 0.35. Each container holds 45 pieces and it takes an average of 75 minutes to complete a cycle .(a)How many containers should be used?(b)Will more or fewer containers be required as the system improves? Why?

Page 11: Financial Management Review

MGMT 405, Production Man., 2012/13 © 2012-13- Assoc Prof. Sami Fethi, EMU, Revision

Revision

11

ThanksThe answers can be found in the relevant chapters’ solutions

sets: 5,6 and 7