INDE 7397
Improving Productivity at Hardy Machines with Lean
Report
by
Kartheek Vadlapatla1278272
M.S., Industrial Engineering
University of Houston - Systems
8/11/2019 finalreport (Autosaved)
2/23
2 | P a g e
Acknowledgement
I wish to thank President Ankur Goel of Hardy Machine and Design and Dr. SharukhIrani for their tremendous contributions and support towards the completion of the
project. I am also grateful to my project supervisor Dr. Suresh Khator who without
his help and guidance this project would not have been completed. I also show my
gratitude to my friends who contributed in one way or the other in the course of theproject.
8/11/2019 finalreport (Autosaved)
3/23
3 | P a g e
Table of Contents
Title Page No:
Acknowledgement 2
Table of ContentsList of Tables
List of Figures
Introduction 4
Problem Statement
Goal and Objective 6
1. Proposal 15S
1.1Data collected at Hardy
1.2
Need for 5S
1.3Steps in 5S implementation
2. Proposal 2S.M.E.D
2.1Data collected at Hardy
2.2
Need for S.M.E.D
2.3Steps in implementation of S.M.E.D
3. Conclusion
References
8/11/2019 finalreport (Autosaved)
4/23
4 | P a g e
LIST OF TABLES
Table 1- Time studies performed during the CNC Lathe setup
Table 2 - Time studies are performed during the Milling machine setup
Table 3 - Internal and External activities during CNC Lathe machine 406 setup
Table 4 - Internal and External activities during CNC Lathe machine 408 setup
8/11/2019 finalreport (Autosaved)
5/23
5 | P a g e
LIST OF FIGURES
Figure 1Time consumed to perform various operations during CNC Lathe setup
Figure 2 - Time consumed to perform various operations during milling setup
Figure 3 - Percentage of Value added and Non Value Added Work
Figure 3Rack used for placing Milling Tools
Figure 4Empty Micrometer Box
Figure 5Milling tool Holder without screw
Figure 7Grinding Dust
Figure 8Machine is down for 3 Hours due to hydraulic pump failure caused by Oil Leak
Figure 9 - Oil spilling
Figure 10 - Scrap material on shop floor can cause trip hazard
Figure 11 - Fork Lift blocking the path of crane used for moving job pieces
Figure 12job Pieces damaged by the fork lift because the where not placed in the proper
location on the Shop floor
Figure 13 - Red Tag
Figure 14 - 5S Audit for Hardy Machine and Design
Figure 15
Percentage of internal and external activities during Machine 406 Setup
Figure 16Percentage of internal and external activities during Machine 406 Setup
8/11/2019 finalreport (Autosaved)
6/23
6 | P a g e
Introduction
Hardy Machine & Design, Inc. is a modern job shop specialized in manufacturingcomponents for Oil and Gas, Aerospace and Health Industry. The company has over
25 years of experience in its field and this experience is combined with current
working methods and techniques. The company has reached a leading position in
Precision Machining, Fabrication and Welding. The companys principles are toinvest into high class machines and the newest machining methods and to keep the
working environment in an excellent shape.
Hardy is a Make to Order (MTO) Job shop which manufactures a wide variety of
products in low volumes. In a job shop environment the demand for customized
products vary from day to day and Customers expectations are unpredictable. As aresult of customization, manufacturing environments gets complicated. Added to
this, customers also expect the product to be delivered only a short period of timeafter placing their orders. This situation creates competition among Hardy and their
competitors to manufacture and deliver products as fast as possible whileemphasizing the importance of minimizing lead times.
Problem Statement
Major problems at Hardy Machine and Design are their longer setup times and
inventory/Tooling management. Firstly, longer lead times are causing customerdissatisfactory. Secondly, regarding the Tooling management, Hardy loosing
machine spindle time due lack of point of use of tools and spending large amount ofmoney in purchasing misplaced and lost Tools.
Goal and Objective
The purpose of this project is to identify the root cause for Non value added activities
that increases the setup time and inventory, and to propose LEAN methodologies toincrease the productivity without sacrificing Quality
8/11/2019 finalreport (Autosaved)
7/23
7 | P a g e
1.Proposal 1 - 5S
The 5S-operation model is one part of the Lean model. It is just one of the manytools which the Lean-ideology includes.5S was originally developed by JIT expert
Hiroyuki Hirano. The 5S frame work is an extension of Hiranos earlier work on
Just in Time production Systems.5S represents a simple housekeeping approach to
improve work environment. In general, 5S approach include the control over thework flow rather than workers behavior. It is relatively inexpensive to implement.
It makes job safer and easier. It encourages preventive approach that preventsproblems before they occur. It provides a practical approach for dealing with real
problems, faced by the workers. 5S consists of five (5) different phases. The names
of the phases come from Japanese and all of them begin with the letter s. That is
where the name 5S stems from. The phases are:
- Seiri = Sort- Seiton = Stabilize/Set in order
- Seiso = Shine/Sweep
- Seiketsu = Standardize
- Shitsuke = Sustain.
The two most important elements are Sort and Set in Order. The success of
improvement activities depends on them. The 5S system sounds so simple but it onimportant lean methodology, without implementing 5S other Lean concepts cannot
be implemented [1]. Moreover, Cleanliness and order characterize significant issuesboth for customers and potential labor force. The starting point is that profitable and
high-quality tasks can be conducted only in a clean environment. The basic idea is
to increase productivity, to improve the level of quality and to raise work ethic.
These factors are reached when the working environment is clean and in good order.5S is a practical tool for maintaining these. It helps to find and eliminate problems
in time. The 5S-model is special because it can be applied in to an office as well asin the production of a company. Systematic and disciplined operations are developed
with the 5S-model.
8/11/2019 finalreport (Autosaved)
8/23
8 | P a g e
1.1 Data Collected at Hardy
Table 1- Time studies performed during the CNC Lathe setup
8/11/2019 finalreport (Autosaved)
9/23
9 | P a g e
Figure 6Time consumed to perform various operations during CNC Lathe setup
Setup31%
Search for Supervisor
3%Discussion with
Supervisor
1%Search for Tools
7%Search for Bolt
6%
Search for Handle
17%
Operator is out of office
35%
Setup Search for Supervisor Discussion with Supervisor
Search for Tools Search for Bolt Search for Handle
Operator is out of office
Work Time
31%
Non value added
Time
69%
Work Time Non value added Time
8/11/2019 finalreport (Autosaved)
10/23
10 | P a g e
Table 2 - Time studies are performed during the Milling machine setup
Figure 7 - Time consumed to perform various operations during milling setup
0
5
10
15
20
25
30
DurationSetup Search for Holder Search for Drill
Fixing Drill and Holder Search for two collets Fixing collet to Drill Holder
Search for second tool Holder Fixing Tool holder and Tool
8/11/2019 finalreport (Autosaved)
11/23
11 | P a g e
Figure 8Percentage of Value added and Non Value Added Work
Figure 9Rack used for placing Milling Tools
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%100%
Value added Work Non Value Added work
VA vs. NVA Work
8/11/2019 finalreport (Autosaved)
12/23
12 | P a g e
Figure 10Empty Micrometer Box Figure 11Milling tool Holder without
screw
Figure 8Machine is down for 3 Hours
due to hydraulic pump failure caused by
Oil Leak
Figure 9 - Oil spilling Figure 10 - Scrap material on shop
floor can cause trip hazard
Figure 7Grinding Dust
8/11/2019 finalreport (Autosaved)
13/23
13 | P a g e
1.2 Need for 5S:
During interaction with Operators and Management, and after performing Timestudies for Setup Operation, we had noticed that time for searching and picking up
tools, equipment and other materials was significantly too long. Added to this rework
due improper material Handling Techniques is also high. Useless time goes by and
it harms the fluency of work. Hence by implementing 5S Philosophy, theproductivity and the quality can be increased, work in-processes and lead-times canbe reduced, better working circumstances can be created, searching times and costs
can be decreased, Moreover, it also helps in rising company image.
In fig-1, the activities marked yellow, performed by the Lathe operator can beeliminated by implementing 5S.This activities add up to 30% of setup time.
Similarly, in fig-2, the non-value added time that adds up to 41% can be eliminated
by 5S. It is found that the milling operators needs 10-15 mins to find the tools placed
the rack (Fig4) and some of the tools are lost or misplaced due lack of dedicatedstorage place(Fig5,6). This can be eliminated by implementing First S and Second
S (sort and set in order) in 5S Philosophy. Grinding dust (Fig -7) can lead to healthhazard and Oil spills (Fig 9) on shop floor can lead to slipping hazard. This can
eliminated by implementing shine.
Figure 11 - Fork Lift blocking the path of
crane used for moving job pieces
Figure 12 job Pieces damaged by the fork lift
because the where not placed in the proper
location on the Shop floor
8/11/2019 finalreport (Autosaved)
14/23
14 | P a g e
Added to this, other benefits of implementing 5S are:
To gain control on equipment, material & inventory placement and position
To eliminate the waste that result from uncontrolled processes.
To ensure that improvements are sustained
To Standardize critical processes such as Tool storage ,Machine clean up andMachine maintenance
To improve consistency of shop supervision
1.3 Steps in 5S implementation:
Phase 1 - Sort
The first phase is called Sort. Main point in this first phase is simply to sort
everything. Every tool, object and instrument is looked through and every one ofthose will be recognized and the demands of those are evaluated. This phase also
includes a task where criterions are created. Removable products will be sorted and
after that, disposed of. Also useful products will be sorted and new places are createdafter sorting.
Mostly used method in sorting-phase is Red-tag program. The removable or
somewhere else storable products are marked with a red tag. That tag tells, for
example, as shown in Fig 1, the name of the inspector, date, demand, reason of the
tag, storage place and disposition date. Jigs, molds, junk and work-in process are
often accumulated all over the stations and the purpose is to get rid of all these. First,all the tagged products are moved into the red tag area and after that, eitherpositioned again or removed for good.
8/11/2019 finalreport (Autosaved)
15/23
15 | P a g e
Figure 13 - Red Tag
Removing useless items clarifies working environment and gives more space to act.Sorting helps everybody to keep places clean and in good order. Moving and safety
at work gets better, it saves and increases space, clarifies processes and gives achance to save up in cleaning.
Phase 2
Set in Order
The main purpose of stabilization is to find practical depository for every requisiteinstrument and those depositories should be marked properly. Every single item,
which is necessary in working, will be organized in a way that those can be foundeasily when needed. Setting in order assures that it is a snap for everyone to find,
take in use and put away the needed item. Target of all these actions is to eliminatepointless searching, improve safety at work and make working environment better.
Places of the equipment are not the only things which are marked. It is advisable tomark tools itself for example with colored cable ties. Marking off the floor and
dividing it into stations is a wise thing to do. That creates passages and clarifiesmovements in the production areas. When pulling the lines, it is useful to mark
places for pallets, pallet jacks and garbage cans at the same time. Color-codes and
signs are used to prevent the equipment getting mixed-up.
8/11/2019 finalreport (Autosaved)
16/23
16 | P a g e
Phase 3 - Shine
It is not enough if phases one and two alone are implemented. First two phases
remove problems in relation to space but one problem is hiding around the corner.
Dirt wear down machines and makes quality worse. Third phase, Shine, is createdfor these problems. Everything will be cleaned up when operation model reaches
this point, Floors, tools, tool racks, devices and especially machines. Engine lifeincreases and everything will be ready for instant use when those are cleaned. This
leads automatically into situation where everything is kept in top condition.
Phase 4 - Standardize
Carrying out a 5S-campaign once in a cell or work station is a pushover. Withoutdaily discipline and clear follow-up and operation routines it is too easy to return
into old habits. That is why the management level should set annual 5S-goals for
every station and employee. Fourth phase is Standardization. This stage is destinedto create procedures and routines. Those should be guiding three (3) earlier phasesinto continuous and developing course of actions. Purpose of this phase is to take in
use and maintain all that, which is created earlier in sorting, stabilizing and shining.
Target is to change constant methods into standards which employees are expectedto obey. Mundane tasks are established and those are followed precisely. Instructions
should be so crystal clear that almost everyone could check the station with the help
of those standard methods. Actions are being supervised and followed by persons.Everyone should know what to do. Check lists are created in standardization phase
and on by a way of those the level of operation model is monitored.
Phase 5 - Sustain
Last phase is sustaining the level which is reached with four earlier phases. Standardsmethods and balanced workplace are maintained and followed all the time. Methods
that are under adoption are improved continuously. Improvement has to be one part
of sustain because the environment should be improved with the help of results from
follow-up. Internal audition lists should be created in the phase five, and auditions
should be made at regular intervals. The results from the auditions should begathered and put on to bulletin boards so that everyone can see and follow up the
development of 5S-actions. Evaluation should include, happened changes andcomparison to earlier months. Audition is essential tool in progress of pushing
cleanliness and sustaining a creditable level of order.
8/11/2019 finalreport (Autosaved)
17/23
17 | P a g e
Figure 14 - 5S Audit for Hardy Machine and Design
8/11/2019 finalreport (Autosaved)
18/23
18 | P a g e
Proposal 2 - S.M.E.D
Single Minute Exchange of Die is one of the many Lean production methods for
reducing waste in manufacturing process. It provides a rapid and efficient way of
converting a manufacturing process from running current product to running the nextproduct. This rapid changeover is helpful in reducing production lot sizes andthereby improving flow. It is also often referred to as Quick Changeover (QCO).
Performing faster changeovers is important in manufacturing, or any process,because they make low cost flexible operations possible.
The concept of SMED is created by shigeo shingo, one of the main contributors toToyota Production system. According to Shingo, if the change over time can be
reduced, then the economic lot size could be reduced, directly reducing expenses.
Shingo also stated that large lot sizes requires higher stock levels to be kept in restof the process and these hidden costs, are also reduced by smaller lot sizes through
implementing SMED [2].
The following eight techniques [3] should be considered during the implementation
of SMED:
1. Separate internal from external setup operations
2. Convert internal to external setup.
3. Standardize function, not shape.
4. Use functional clamps or eliminate fasteners altogether.5. Use intermediate jigs.
6. Adopt parallel operations.
7. Eliminate adjustments.
8. Mechanization.
In general, the idea behind the SMED methodology is to convert internal setup
operations to external operations. This method is highly recommended to reducechangeover time, thereby allowing extra production time to increase output [4].
8/11/2019 finalreport (Autosaved)
19/23
19 | P a g e
2.1 Data collected at Hardy:
Further analysis has been made, to identify the percentage Non value added
internal activities performed during setup operation and results are shown in table
3 and table 4.Table 3 - Internal and External activities during CNC Lathe machine 406 setup
8/11/2019 finalreport (Autosaved)
20/23
20 | P a g e
Figure 15Percentage of internal and external activities during Machine 406 Setup
Results:
Total Time required for setup60 mins
Time for Internal setup34 Mins
Time for External Setup26 mins
External40%
Internal60%
Machine 406 SetuExternal Internal
Table 4 - I nternal and External activiti es dur ing CNC Lathe machine 408 setup
8/11/2019 finalreport (Autosaved)
21/23
21 | P a g e
Figure 16Percentage of internal and external activities during Machine 406 Setup
Results:
Total Time required for setup31 mins
Time for internal setup16 Mins
Time for External Setup15 mins
2.2 Need for SMED:
As seen in figure 1 and figure 2, Non-Value Added can be reduce to 40% by
implementing 5S, the activities like discussion with the supervisor, and fixing drill
and holder cannot be eliminated.
From table 2 and table 3, it can be noted that the more than 50 % of activities
performed during the setup are external operation. This activities are performed
as internal operation. By implementing the concept of S.M.E.D, Non Value Added
time can be further reduced.
External48%Internal
52%
Machine 408 Setu
External Internal
8/11/2019 finalreport (Autosaved)
22/23
22 | P a g e
2.3 Steps in implementation of SMED:
The SMED methodology consists of two phases. In the first phase, a distinction is
made between internal and external setup tasks. Internal setup operations are
those that must be performed when the machine is stopped. These operations
occur on-line to the machine. External operations are those that can be performed
while the machine is in operation. It is more efficient to perform these tasks off-
line from the machine. Once the operations are classified as either external or
internal, the external operations can be moved off-line to reduce machine
downtime.
In the second phase of SMED, all aspects of the setup, both internal and external,
are streamlined to make them more efficient. Internal setup efficiency results in
labor savings and less downtime machine capacity. External efficiency does notdirectly improve downtime, but gives better utilization of labor. Since at the factory
or line level labor can be a constraint on doing setups, it can also indirectly reduce
downtime.
Conclusion:
By implementing 5S and S.M.E.D the setup time can be reduced by 70%.This
projects can also help Hardy to minimize tooling issues and reduce inventory.
8/11/2019 finalreport (Autosaved)
23/23
23 | P a g e
References:
[1] 5S for Operators: 5 Pillars of the Visual Workplace (For Your
Organization!) PaperbackMarch 1, 1996 byHiroyuki Hirano
[2] Eliyahu Goldratt, 1990, Theory of Constraints, North River Press, Massachusetts,
pp. 40
[3] Shigeo Shingo, 1989, A study of Toyota Production System, Productivity Press,
New York, pp. 47
[4] Greg Lane, 2007, MadeToOrder Lean, Productivity Press, New York, pp. 66
http://www.amazon.com/Hiroyuki-Hirano/e/B001K8OF3O/ref=dp_byline_cont_book_1http://www.amazon.com/Hiroyuki-Hirano/e/B001K8OF3O/ref=dp_byline_cont_book_1http://www.amazon.com/Hiroyuki-Hirano/e/B001K8OF3O/ref=dp_byline_cont_book_1http://www.amazon.com/Hiroyuki-Hirano/e/B001K8OF3O/ref=dp_byline_cont_book_1