"Strengthening Fisheries Management in ACP
Countries"
Project Funded by the European Union.
“This publication has been produced with the assistance of the European Union. The contents of this publication are the sole responsibility of ”name of the author” and can in no way be taken to reflect the views of the European Union.”
“The content of this document does not necessarily reflect the views of the concerned governments.”
Final Technical Report
Training for Regional Beach Management Unit Network (RBN)
in East Africa
Project ref. N°
EA-4.1-B18
Region: Eastern Africa
Countries: Kenya, Tanzania, Uganda
25 July 2012
Assignment by:
Training for Regional Beach Management Unit Network (RBN) in East Africa
i Project Funded by the European Union A project implemented by (Harewelle International Limited)
TABLE OF CONTENTS
ACKNOWLEDGEMENTS ................................................................................................................................................. II
ABBREVIATIONS AND ACRONYMS ............................................................................................................................... III
EXECUTIVE SUMMARY ................................................................................................................................................. IV
1. BACKGROUND ..................................................................................................................................................... 1
2. COMMENTS ON TERMS OF REFERENCE ............................................................................................................... 1
3. APPROACH TO THE ASSIGNMENT ........................................................................................................................ 2
3.1 PHASING OF ASSIGNMENT ............................................................................................................................................. 2 3.1.1 Mobilisation and Inception ........................................................................................................................... 2 3.1.2 Implementation Phase .................................................................................................................................. 2 3.1.3 Closure Phase ................................................................................................................................................ 3
3.2 AGREED IMPLEMENTATION SCHEDULE ............................................................................................................................. 3
4. ORGANISATION AND METHODOLOGY ................................................................................................................. 5
4.1 DELIVERY OF TOR ....................................................................................................................................................... 5 4.1 CONDUCT AND DETAILS OF THE ASSIGNMENT ................................................................................................................... 6
4.1.1 Briefing at ACP FISH II RFU ............................................................................................................................ 6 4.1.2 Administrative Preparation for Training ....................................................................................................... 6 4.1.3 Document Review ......................................................................................................................................... 6 4.1.4 Situation Analysis .......................................................................................................................................... 7 4.1.5 Training Needs Assessment........................................................................................................................... 7 4.1.6 Development of Training Manual ................................................................................................................. 9 4.1.7 Training of RBN Members ............................................................................................................................. 9 4.1.8 RBN evaluation of training .......................................................................................................................... 12 4.1.9 Post-training performance monitoring of RBN ........................................................................................... 12 4.1.10 Communication and visibility ................................................................................................................. 13 4.1.11 Putting RBN training into practice ......................................................................................................... 13 4.1.12 Sustainability of EU ACP FISH II support to RBN ..................................................................................... 14
5. CONCLUSIONS AND RECOMMENDATIONS ......................................................................................................... 14
5.1 CONCLUSIONS ........................................................................................................................................................... 14 5.2 RECOMMENDATIONS.................................................................................................................................................. 15
ANNEX 1 TERMS OF REFERENCE ................................................................................................................................. 16 ANNEX 2 ITINERARY AND CONSULTATIONS ............................................................................................................... 29 ANNEX 3 PERSONS MET ............................................................................................................................................. 30 ANNEX 4 ACP FISH II RFU BRIEFING ............................................................................................................................ 32 ANNEX 5 REFERENCE DOCUMENT LIST ...................................................................................................................... 33 ANNEX 6 RBN SITUATION ANALYSIS ........................................................................................................................... 35 ANNEX 7 FA SITUATION ANALYSIS .............................................................................................................................. 39 ANNEX 8 BMU SITUATION ANALYSIS .......................................................................................................................... 41 ANNEX 9 TNA CHECKLIST ............................................................................................................................................ 42 ANNEX 10 COHERENCE OF BMU NETWORKS .......................................................................................................... 44 ANNEX 11 TRAINING NEEDS ASSESSMENT MATRIX ................................................................................................ 48 ANNEX 12 RBN PARTICIPANTS IN TRAINING ............................................................................................................ 55 ANNEX 13 RBN TRAINEES IN LOWER BMU NETWORKS ........................................................................................... 56 ANNEX 14 RBN TRAINING OF TRAINERS MANUAL ................................................................................................... 57 ANNEX 15 EVALUATION OF RBN TRAINING ........................................................................................................... 152 ANNEX 16 PHOTOGRAPHS OF RBN TRAINING ....................................................................................................... 154 ANNEX 17 RBN STRATEGIC PLAN ........................................................................................................................... 155 ANNEX 18 RBN PROJECT PROPOSAL ...................................................................................................................... 180 ANNEX 19 MINUTES OF RBN 2
ND REGULAR MEETING ............................................................................................ 202
Training for Regional Beach Management Unit Network (RBN) in East Africa
ii Project Funded by the European Union A project implemented by (Harewelle International Limited)
ACKNOWLEDGEMENTS The consultant would like to express his thanks to the people and their organisations who contributed
to the smooth planning and implementation of this assignment. The ACP FISH II programme‘s
Regional Manager based in Kampala, Koane Mindjimba, provided full support to assignment. At the
Secretariat in Jinja, Uganda, the Lake Victoria Fisheries Organisation, through its Executive
Secretary, Mr Dick Nyeko, Deputy Executive Secretary, Mr Mathius Wafula, and Information and
Database Officer, Mr Sam Abura, provided sound advice, a warm welcome and hospitality and use
of a LVFO vehicle and driver to visit a landing site.
Thanks go to staff of Fisheries Administrations in each country who gave their time to answer many
questions as part of Situation Analyses and Training Needs Assessment. These include Mr Jackson
Wadanya, acting Commissioner for Fisheries, Uganda, Dr Rhoda Tumwebaze, Assistant
Commissioner for Fisheries, Uganda, Mr Lameck Mongo, Head of the Department of Fisheries
Mwanza, Tanzania, Mr Michael Obadha, Provincial Director of Fisheries, Nyanza Province Kenya
and Mr Vincent Ogwang, Chairman of the LVFO Co-Management Regional Working Group.
Special thanks go to Mike Obadha who kindly awarded certificates of attendance to trainees of the
training course and lead the official closing ceremony of the meeting on the last weekend of the
assignment.
The RBN appreciated the effort of Mr Timothy Odende, Principal Fisheries Officer, who linked the
RBN training meeting to a visit by representatives of the recently formed Nile Perch Traders
Network of Kenya. The meeting was grateful to hear about this Network from Mr Joannes Andiego,
its Chairman, Mr Chrispinus Masiga, Treasurer, and Mr Absalom Odira, Secretary. The RBN
members also appreciated learning from Mr George Okeyo, Fisheries Value Chain Officer at the
Micro Enterprise Support Programme Trust (MESPT) Kenya who provided advice at the training
meeting on possible future funding sources to BMU Networks in Kenya.
Thanks go to the representatives of BMUs at Igungu and Masese in Uganda, Igombe in Tanzania and
Dunga in Kenya for providing a warm welcome and much useful information on BMU Networks.
Thanks also go to Mr Philip Borel, Chairman of the East Africa Industrial Fishing and Fish
Processors Association, who gave much time to answer questions as part of the Situation Analyses
and Training Needs Assessment.
Thanks are due to all staff at WIFIP, especially its Head, Jennipher Atieno, for taking care of all
logical arrangements leading up to and for running the training meeting. The smooth running of the
training meeting was also due to the effort of interpreter, Mr Kennedy Odongo, who did an excellent
job in maintaining the pace of training without any undue interruption. Finally, thanks go to RBN
members who collaborated closely during field visits to each country, including Tom Guda in Kenya,
Robert Bakaaki in Uganda and Pius Mazima in Tanzania and to all RBN members who fully
participated in every aspect of the training course.
Training for Regional Beach Management Unit Network (RBN) in East Africa
iii Project Funded by the European Union A project implemented by (Harewelle International Limited)
ABBREVIATIONS AND ACRONYMS
ACP Africa, Caribbean and the Pacific
AIDS Auto Immune Disease Syndrome
ANAF Aquaculture Network for Africa
BMU Beach Management Unit
BMUC Beach Management Unit Committee
CU Coordination Unit of ACP FISH II
CBN County BMU Network (in Kenya)
DBN District BMU Network
DFR Department of Fisheries Resources Uganda
DFTR Draft Final technical Report
DivBN Division BMU Network
DoF Department of Fisheries
EAC East African Community
EAIFFPA East Africa Industrial Fishing and Fish Processing Association
EU European Union
FA Fisheries Administration
FMC Fisheries Management Committee of the LVFO
FMP2 Lake Victoria Fisheries Management Plan 2009-2014
FTR Final Technical Report
GTZ German Development Agency, Deutsche Gesellschaft für Technische
Zusammenarbeit
HIV Human immunodeficiency virus
ICEIDA Icelandic International Development Agency
IFMP Implementation of a Fisheries Management Plan project
LBN Location BMU Network
LVEMP Lake Victoria Environmental Management Project
LVFO Lake Victoria Fisheries Organization
MCS Monitoring, Control and Surveillance
MESPT Micro Enterprise Support Programme Trust
MoFD Ministry of Fisheries Development Kenya
NBN National BMU Network
NGO Non Governmental Organization
NPTN Nile Perch Trader Network
RBN Regional BMU Network of Lake Victoria
RFU Regional Facilitation Unit of ACP FISH II
RM Regional Manager
RWG Regional Working Group of LVFO
SBN Sub-county BMU Network
SC Scientific Committee of the LVFO
SME Small and Medium Enterprises (business)
TNA Training Needs Assessment
TOR Terms of Reference
ToT Training of Trainers
UFPEA Uganda Fish Processors and Exporters Association
VBN Village BMU Network
WBM Ward BMU Network
WIFIP Women in Fishing Industry Programme
Training for Regional Beach Management Unit Network (RBN) in East Africa
iv Project Funded by the European Union A project implemented by (Harewelle International Limited)
EXECUTIVE SUMMARY
The Lake Victoria Regional Beach Management Unit Network (RBN) was formed in February 2010
as the apex body representing the concerns and interests of 215, 000 members registered in 1,069
Beach Management Units (BMUs) along the shores of Lake Victoria in Kenya, Tanzania and
Uganda. In 2011, the RBN called for support from the EU ACP FISH II programme for training of
trainers for its 9 members in areas of strategic planning, advocacy and project proposal writing.
Harewelle International Ltd was subsequently selected to undertake the training assignment with Dr
James Scullion as its Key Expert who visited the region from 16th
July to 4th
August 2012.
Training Needs Assessment
After initial consultations with the RBN and briefing with the ACP FISH II Regional Facilitation
Unit (RFU) in Kampala, Uganda, it was agreed that the assignment could go further than training by
adopting a ―training-by-doing‖ approach to formulate a 3-year RBN Strategic Plan and a project
proposal ready for submission to identified development partners. In this way, the assignment could
also serve as a stimulus to action by the RBN members using the roadmap contained in their strategic
plan.
Consultations with key stakeholders in each country were completed as part of a Situation Analysis
linked to developing a strategic plan and a Training Needs Assessment (TNA). The stakeholders
included RBN members, national fisheries administrations, BMUs, the Secretariat of the inter-
governmental Lake Victoria Fisheries Organisation (LVFO) and the East African Fishing and Fish
Processors Association (EAIFFPA). The TNA confirmed the urgent need for training in the three
areas previously identified by the RBN.
Inception Report
An Inception Report was produced immediately on completion of the TNA. The report was
submitted within the deadline specified in the TOR and there were no comments other than one
regarding minor editing.
RBN Training Manual
A Training of Trainers Manual was produced prior to holding the RBN training. The manual
comprised three modules covering topics identified by the RBN:
1. Module 1: Strategic planning (including 7 training sessions)
2. Module 2: Advocacy and lobbying (including 2 training sessions)
3. Module 3: Project proposal writing (including 2 training sessions)
A total of 34 separate Information Sheets was prepared as training aids. These were also included in
manual. The training was fully attended by all 9 RBN members from 30th
July to 4th
August 2012.
Training was held at the WIFIP office in Kisumu, Kenya, an NGO which also provided logistical and
administrative support to planning and running the training meeting.
RBN Strategic Plan
The adopted ―training-by-doing‖ approach resulted in the formulation of a 3-year RBN Strategic
Plan, July 2012 – June 2015, which provides a roadmap for immediate and medium-term actions.
The strategic plan also provides an umbrella framework for annual action planning at all lower levels
of BMU Networks.
Training for Regional Beach Management Unit Network (RBN) in East Africa
v Project Funded by the European Union A project implemented by (Harewelle International Limited)
RBN Prioritised Advocacy Issues
Training under module 2: advocacy and lobbing also adopted the training-by-doing approach and
procedures learned during training were applied in the identification of priority advocacy issues
incorporated in the strategic plan. These comprised:
a) National legislation recognising the BMU Networks at all levels.
b) Price transparency at all points along the Nile perch market chain from fishing boat to final
foreign markets.
c) Eradication of the tendering of fisheries tax collection in Tanzania and Uganda.
RBN Project Proposal
Training under module 3, project proposal writing, resulted in the production of one budgeted project
proposal ready for submission to development partners. The proposal is entitled:
―Unleashing the Potential of an International Small-Scale Fisheries Association in East Africa‖.
The proposal involves setting up a permanent RBN office and Secretariat to support the RBN
undertake priority actions extracted from its strategic plan.
RBN Evaluation of training
Training was evaluated at the end of each day when still very fresh in the minds of trainees. The
LVFO evaluation format was used for first 2 days but replaced by new format sent by RFU which
was applied for the whole training course. Evaluation scoring was high – good or very good for
criteria covering the course in general and individual training modules and sessions.
Monitoring
Formats for monitoring performance of participants after the training were developed using a logical
framework and performance indicators of the RBN Strategic Plan. This provided the most
sustainable way ensuring such performance indicators would be routinely used in the future. The
performance of the trained RBN members will from now on be evaluated against the implementation
of their 3-year Strategic Plan, July 2012 – June 2015.
Communication and visibility
Communication and visibility of EU support to the RBN was achieved in a number of different
ways. A national Kenya Broadcasting Corporation (KBC) team arrived with television cameras and
filmed the RBN Chairman whilst he made a speech about the training event and key advocacy issues.
The film crew also filmed the training in action at WIFIP. A reporter from a national newspaper, the
People, also arrived and interviewed the RBN Chairman. Details of the meeting were broadcast on
two local radio stations in local language. No permanent record of the interviews were available.
T-shirts with the RBN and EU logos were procured for each RBN member and photographs taken.
Certificates of Attendance were developed, printed and awarded to each of the 9 RBN members by
the Provincial Director of Fisheries, Nyanza Province Kenya during the training course closing
ceremony. Acknowledgement of EU ACP FISH II support was noted in the text of the RBN
Strategic Plan document.
Sustainability
The sustainability of training support provided to the RBN through this assignment is strengthened
by having as outputs, the RBN 3-year Strategic Plan and one project proposal to take forward in their
effort to secure grant aid from development partners. Key actions from the Strategic Plan guided the
Training for Regional Beach Management Unit Network (RBN) in East Africa
vi Project Funded by the European Union A project implemented by (Harewelle International Limited)
agenda of the 2nd
Regular meeting of the RBN held on 4th
August, in the afternoon of the final day of
training. The RBN Strategic Plan and project proposal were formally approved and adopted in this
meeting and commitments were by members to undertake immediate actions to implement the plan.
Recommendations
Planning:
1. RBN members should convene National BMU Network meetings in their respective
countries and provide training of trainers in action planning to develop linked Annual Action
Plans based on the Strategic Plan, 2012-2015.
2. RBN members and the NBN members trained by them should convene District (and County
in Kenya) BMU Network meetings in their respective countries and provide training of
trainers in action planning to develop linked Annual Action Plans based on the Strategic Plan,
2012-2015.
3. RBN members should keep abreast of current regional fisheries plans for Lake Victoria,
including the Nile Perch Fisheries Management Plan 2009-2014 (NPFMP) and the broader
development plan – the Lake Victoria Fisheries Management Plan 2009-2014 (FMP2).
4. RBN members should lobby for a responsive Lake Victoria Fisheries Research Plan which
commits to undertaking stakeholder driven research to guide key management issues and
decision-making.
Advocacy:
5. More detailed action planning by the RBN should be undertaken by email between members
to address the three high priority advocacy issues identified in the Strategic Plan and actions
implemented accordingly.
6. RBN members should lobby, if necessary, for the LVFO regional technical advisory
committee to be held later this year to enable the RBN to influence policy, legislation, plans
and guidelines in the interests of their members.
Project proposal writing:
7. The RBN should formally approach the LVFO Secretariat to provide temporary office space
for the RBN in the LVFO headquarters in Jinja, Uganda.
8. The RBN should submit the project proposal developed during training to development
partners for technical and financial support.
Training for Regional Beach Management Unit Network (RBN) in East Africa
1 Project Funded by the European Union A project implemented by (Harewelle International Limited)
1. BACKGROUND
Experience from Lake Victoria clearly shows that the process to attain meaningful and lasting
improvements in fisheries management and governance is lengthy, multi-dimensional and often
intermittent. It involves institutional, policy and legislative development. Key components involve
building co-management structures, empowering communities and the private sector and establishing
processes which efficiently link these structures at all levels. Sensitization and capacity building of
the communities, private industry and governments are essential to increase understanding and to
modify attitudes and behaviour. Policy and legislative reforms alone are not sufficient to counter
long-standing governance problems. To achieve this, demands a much more active and influential
part played by BMU Networks led by their regional apex body the RBN.
Community Beach Management Units were established on Lake Victoria as the foundation of a
fisheries co-management approach in which the legally empowered BMUs work in close partnership
with government and the private industrial fish processors and exporters. Unrealistically high
expectations continue to be placed on BMUs to resolve the century-old problem of non-compliance
to fisheries regulations. BMUs acting alone can do little to tackle lake-wide challenges. To do this
they need to be linked to one another. This was achieved through the formation of BMU Networks.
These are associations of BMUs established at levels coinciding with levels of government which
have planning, decision-making and budgeting authority. The Regional BMU Network is the apex
body of the BMU associations and as such represents 1,069 BMUs on the lake with a membership of
at least 215,000 people working in fisheries.
Following its inauguration in February 2010, the Regional BMU Network has struggled to mobilise
itself and become operational. Key challenges are holding it back, the most crucial of which is
financing RBN activities. A second is the urgent need to raise the RBN profile and image through
self-promotion. A third is the need to prove to BMU members that the RBN is capable of delivering
effective services to them that are worth paying for.
With the exception of the EU ACP FISH II programme, the absence of significant support by
development partners to the RBN is startling given that it is the pinnacle of the largest fisheries co-
management organisation in the world operating on a single water body. This is an issue which
requires urgent redress.
The current EU ACP FISH II assignment is the second short-term training support targeting RBN
members. The TOR for the current assignment were developed in close consultation with the client,
the RBN, and the indicative areas listed for training support were identified by the RBN themselves
and as such, the assignment responds directly to needs of the RBN.
2. COMMENTS ON TERMS OF REFERENCE
The Terms of Reference (TOR) for the assignment stated that the purpose of this assignment was ―to
strengthen the capacity of the Regional Beach Management Unit Network to effectively participate in
the management of the fisheries of Lake Victoria‖. This was to be achieved through training. The
target beneficiaries for the training are ―members and executives of the Regional Beach Management
Unit Network on Lake Victoria‖. The TOR (Annex 1) clearly specified the results and specific tasks
of the Key Expert (KE) for this assignment. Only two queries/comments on the TOR were raised by
the KE. The first was that whilst the indicative list of proposed training topics clearly implied that a
Strategic Plan will be a documented output of the assignment, this was not explicitly listed in Section
Training for Regional Beach Management Unit Network (RBN) in East Africa
2 Project Funded by the European Union A project implemented by (Harewelle International Limited)
7.1 of the TOR, ―Reporting Outputs‖. At briefings with the ACP FISH II Regional Manager and with
RBN chairman, it was agreed that a Strategic Plan was an expected output and that it should be a
budgeted Strategic Plan. The KE agreed with this as an output and that training on this topic would
be achieved through training by doing by the trainees.
Secondly, the TOR included 4 days for training manual preparation which was reduced to 3 days in
the Consultant‘s bid document to allow for the preparation of the Inception Report, a required
reporting output of this assignment.
3. APPROACH TO THE ASSIGNMENT
3.1 Phasing of Assignment
The assignment was divided into three phases:
a) Mobilisation and Inception
b) Implementation Phase
c) Closure Phase
In accordance to the TOR, the work schedule of Key Expert was planned so that he spent 85% of
working days in the region.
3.1.1 Mobilisation and Inception
This phase involved preparatory work in UK, Entebbe and Jinja, including finalising arrangements
with the RBN and NBN Chairs and document review; briefing by the ACP Fish II Regional
Facilitation Unit (RFU) for Eastern Africa in Kampala; and development of a work plan, including
agreeing the methodology for the assignment with the NBN Chairs and RFU. It also involved a
Situation Analysis and Training Needs Assessment (TNA) in the three LVFO Partner States, Kenya,
Tanzania and Uganda (Annexes 2 and 3). A Situation Analysis was an integral component of the
TNA relating especially to the training in, and making, a Strategic Plan.
The Situation Analysis and TNA involved consultations with key stakeholders including BMUs at
landing sites in each country, Fisheries Administrations (FAs) and the private industrial fish
processors and exporters. At regional level the latter are represented by a regional organisation, the
East African Industrial Fishing and Fish Processing Association (EAIFFPA). The current Chairman
of the organisation is based in Entebbe and this afforded an opportunity of consultation on arrival of
the KE in the region. The TNA was conducted through in depth interviews with members of the
RBN in each country using a semi-structures interview approach with checklists. The same approach
was used for the Situation Analyses in each country.
In parallel to these activities untaken by the Key Expert, logistical arrangements for the training were
undertaken through a sub-contract. This phase of the assignment culminated in the preparation and
submission of an Inception Report to the RBN, the RFU and the CU within 10 days of arrival of the
KE.
3.1.2 Implementation Phase
This phase involved the development of training modules, including Trainers Manual and materials.
There was need for translation of Trainers Manual into Kiswahili and planning of training logistics
through sub-contract. Then followed training 9 members and executives of the Regional BMU
Network, including monitoring and training evaluation.
Training for Regional Beach Management Unit Network (RBN) in East Africa
3 Project Funded by the European Union A project implemented by (Harewelle International Limited)
3.1.3 Closure Phase
This phase involves submission of a Draft Final Technical Report (DFTR) within one week of the
KE leaving the region and incorporation of comments (provided within 14 days of receipt by RBN,
RFU, CU). If no comments on the report are given within the time limit of 14 days, the DFTR shall
be considered as the FTR. This is followed by printing and distribution of 100 Trainers Manuals
including Information Sheets. After receiving approval of FTR, the last step in the closure period
involves preparation of Final Report, including final invoice and financial report accompanied by the
expenditure verification report submitted by the Consultant.
3.2 Agreed Implementation Schedule
The initial implementation schedule developed at the start of the assignment was adjusted slightly to
accommodate travel from Kisumu, Kenya to Mwanza, Tanzania by land (8-9 hour journey) rather by
air. This was due to lack of a direct flight from Kisumu to Mwanza and the need to fly back to
Nairobi to reach Mwanza. The rest of the proposed work plan remained unchanged from the draft
version submitted at the start of the assignment.
The Implementation Schedule approved at Inception is presented in Table 1.
Training for Regional Beach Management Unit Network (RBN) in East Africa
4 Project Funded by the European Union A project implemented by (Harewelle International Limited)
Table 1 Implementation Schedule
PHASES AND ACTIVITIES
DAYS WEEKS
KE 1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15
MOBILISATION AND INCEPTION
1.1. Preparatory work from home base and in Jinja (2 days) 2.00 1.0 1.0
1.2. Briefing by the ACP Fish II Regional Facilitation Unit in Kampala; (0.5 days) 0.50 0.5
1.3. Elaboration of a work plan for the assignment; (0.5 day) 0.50 0.5
1.4. Conduct of TNA in three countries; (5 days) 5.00 3.0 2.0
1.5. Make logistical arrangements for the training; (sub-contract) 0.00
1.6. Preparation and Submission of an Inception Report; (1 day) 1.00 1.0
IMPLEMENTATION
2.1. Module development, including Trainers Manual and Trainee Resource Pack; (3 days) 3.00 3.0
2.2. Translation of Trainers Manual and Trainee Resource Pack into Kiswahili and planning
training logistics; (sub-contract) 0.00
2.3. Training 9 members and executives of the Regional BMU Network; (6 days) 6.00 6.0
PROJECT CLOSURE
3.1 Submission of Draft Final Technical Report (DFTR) within one week of Expert leaving Jinja
(executive summary in Kiswahili); (1 day).
1.00 1.0
3.2. Incorporation of comments, if any, and production of Final Technical Report (FTR) (1day). 1.00 1.0
3.3. Printing and distribution of 100 Trainers Manuals including Information Sheets; (subcontract)
3.4. Preparation of Final Report, including final invoice and financial report and expenditure
verification report. (Harewelle).
0.00
Total 20
Training for Regional Beach Management Unit Network (RBN) in East Africa
5 Project Funded by the European Union A project implemented by (Harewelle International Limited)
4. ORGANISATION AND METHODOLOGY
4.1 Delivery of TOR
The Terms of Reference for the assignment were completed successfully. Progress in delivering each
of the specific tasks of the TOR is summarised in Table 2.
Table 2 Delivery of TOR Specific Tasks
Terms of Reference How delivered through the assignment
1 Briefing by ACP Fish II and RBN; Completed:
Briefing held on 18th
July at RFU, Kampala.
2 Collect and review relevant documents; Completed:
Relevant documents were collected, reviewed
and listed in Annex 5.
3 Conduct a TNA through consultations
with key stakeholders in Kenya,
Tanzania and Uganda;
Completed:
Situation Analyses and TNA were conducted
with BMUs, FAs, RBN, LVFO, EAIFFPA
covering Kenya, Tanzania and Uganda.
4 Make all the logistical arrangements to
complete the training itself (including
invite participants, arrange travel, book
and pay for flights and vehicles for
participants as necessary, training venue
costs, and field visit) – subcontracting
for training organisation is allowed;
Completed:
WIFIP, a NGO in Kisumu was sub-contracted
and it undertook all logistical arrangements to
complete the training.
5 Conduct the training for the nine (9)
RBN members for 6 days;
Completed:
9 RBN members were trained for 5 days at
WIFIP, Kisumu from 30th
July to 3rd
August;
6th
day was spent on recap of the course, final
questions and answers, RBN chairman training
members in using email; RBN meeting to
commit to actions from training.
6 Evaluate the training; Completed:
Training was evaluated at the end of each day
when still very fresh in the minds of trainees.
LVFO evaluation format used for first 2 days
but replaced by new format sent by RFU which
was applied for the whole training course.
7 Develop formats for monitoring
performance of participants after the
training and provide the monitoring
frame to be used by the RBN;
Completed:
Formats for monitoring performance of
participants after training were developed and
set into the logframe of RBN Strategic Plan
thereby increasing sustainability of its use.
8 Prepare 100 copies of a practical
Training Manual for use by the RBN.
Completed:
100 copies of the Training Manual including
Information Sheets were made by WIFIP for
use by the RBN members.
Training for Regional Beach Management Unit Network (RBN) in East Africa
6 Project Funded by the European Union A project implemented by (Harewelle International Limited)
4.1 Conduct and Details of the Assignment
4.1.1 Briefing at ACP FISH II RFU
A briefing was held with the ACP FISH II Regional Manager (RM) at his office in Kampala, Uganda
on 18th
July and the RM produced a Briefing Note of the meeting with the KE (Annex 4). The RM
raised points of discussion on opening and closing the training workshop, certificates for trainees and
visibility material (T-shirts). It was confirmed that KE will cover the three topics listed in the TOR
and compile them as a single practical Training Manual for use by the RBN, including Strategic
Planning Development, Capacity Building for Advocacy and Lobbying (regionally and
internationally), and Capacity Building for Grant-making Process/Proposal. The KE will use the
learning-by-doing approach for these topics. The KE will also develop formats for monitoring
performance of participants after the training using logframe and performance indicators embedded
in the Strategic Plan.
4.1.2 Administrative Preparation for Training
The logistical planning and organisation of the training was sub-contracted to an organisation known
as Women in Fishing Industry Programme (WIFIP), an experienced NGO in Kisumu with whom the
Consultant has worked effectively in the past. WIFIP worked in parallel to the Key Expert providing
logistical support whilst the KE engaged in technical activities of the assignment. They coordinated
activities and plans immediately after arrival of the KE in Uganda and held a meeting as the KE
travelled though Kisumu on his way to visit the Kenyan stakeholders before travelling to Mwanza in
Tanzania. WIFIP provided access to banking facilities to finance the training meeting and the
logistics of the visit by the KE and RBN Chairman to Mwanza. In the absence of a RBN Secretariat,
the RBN Chairman took on administrative duties on behalf of the RBN and worked closely with
WIFIP on preparations for the training meeting.
The logistic planning and organisation of the training was done by WIFIP who:
Identified and organised the training venue at WIFIP, equipment required,
refreshments and lunches, transport and registration; procured T shirts for RBN and
produced certificates for each trainee;
Provided access to banking facilities for the Consultant company and currency
conversion for RBN members; and
Ensured that all necessary attendance, financial and operational records were prepared,
processed and submitted in accordance with 10th
EDF rules, avoiding any issues of non-
compliant expenditure.
WIFIP also provided interpretation from English to Kiswahili during training for Tanzanian
members of the RBN and translation of the Trainers Manual, Information Sheets and Executive
Summary of the Draft and Final Technical Reports.
4.1.3 Document Review
An initial document review (Annex 5) was undertaken by the KE revealing several issues and
opportunities for the RBN especially with regard to potential legislative and institutional
development. The latter were confirmed during the Situation Analyses (see section 4.1.4 for details).
Training for Regional Beach Management Unit Network (RBN) in East Africa
7 Project Funded by the European Union A project implemented by (Harewelle International Limited)
4.1.4 Situation Analysis
Situation analyses were completed by collecting information from key stakeholder groups including
the RBN members, BMUs, Fisheries Administrations (national and regional) and private industrial
fisheries enterprises (EAIFFPA). The results of the analyses are shown in Annexes 6, 7 and 8. The
KE conducted the Situation Analyses and TNA in three countries, travelling with RBN Chair or his
representative (in Uganda) and liaising with NBN Chairs and, where available, the LVFO Co-
Management Regional Working Group Chairs. The latter was possible only in Kisumu Kenya due to
engagement in field activities by these officers in Uganda and Tanzania. The key points arising from
the Situation Analysis were as follows:
At regional level, there are moves towards the establishment of an East African Fisheries
Administration incorporating the 5 Partner States of the EAC and covering marine and inland
waters;
There are major policy, institutional and legislative changes occurring in Kenya and Uganda
which require the RBN to be aware of and to influence in the interests of their members. The
principal fisheries legislation is being rewritten in both countries and neither have explicit
mention of BMU Networks. This requires immediate sustained lobby action by the RBN and
respective NBNs. In Kenya, a new National BMU Network has been established but the
functions of the Network require harmonisation with existing functions in Uganda and
Tanzania.
The BMU Networks at local levels – at district and below – are financed and active in all 3
countries but the NBNs in Uganda and Tanzania are dormant compared to a very active NBN
in Kenya. This gives a chance for lesson learning across countries.
There is urgent need to complete the registration of Networks in Uganda and Tanzania and
seek clear legal identity. In Kenya, the abandonment of local BMU Networks as set out in the
new National Guidelines needs careful consideration and possibly more extensively
discussion with BMU Networks and BMUs.
4.1.5 Training Needs Assessment
The TNA methodology followed the system outlined in the LVFO HRD Strategy and Action Plan
2006. This focussed on detailed consultations with three RBN members, one from each country
using checklist approach exploring progress on official functions of the RBN Annexes 9, 10 and 11.
The latter were extracted from the RBN Operating Procedures 2010. These are similar to a set of
organisational objectives – a wish list for an emergent organisation such as the RBN. An initial
check was made to assess functional coherence of BMU Networks operating at different hierarchical
levels in the system. The finding showed a very high degree of functional coherence between
different levels of Networks (Annex 10). This means that there are clear operational consistencies
from one level of Network to another which provides the basis for developing and implementing
linked strategic and action plans from BMUs up to the RBN.
Constraints on achieving progress for each of the RBN functions/tasks were examined to see whether
or not they could be addressed by training, and specifically what kind of training. The TNA was
undertaken in the context of pre-identification of training needs by the RBN itself which are set out
in the TOR of this assignment. The checklist also explored whether or not there are any significant
gaps in RBN functions as listed in the Operating Procedures and whether these need training support.
The KE took note of the significant changes made to Network functions in the new National BMU
Networks Guidelines in Kenya. This is an issue for RBN deliberation when led through the making
its first Strategic Plan during training.
Training for Regional Beach Management Unit Network (RBN) in East Africa
8 Project Funded by the European Union A project implemented by (Harewelle International Limited)
The RBN functions can be categorised under 5 main headings listed and discussed below.
RBN Effectiveness in Financing and Operations
Financing of the RBN is the greatest bottleneck affecting almost all other activities expected to be
undertaken by this regional body. Unless ways are found of financing the RBN then it is likely to
remain dormant and virtually unknown. There are two routes to financing the RBN – through self-
financing by BMUs as stipulated in the RBN Operating Procedures or by finding external support
from governments or development partners. This has been the case since inauguration with no
progress made to secure funding of the RBN. Both routes of financing can be addressed by the
training topics identified by the RBN. Training in proposal writing is one step to help the RBN
access development partner or government support. Strategic planning provides the vehicle to drive
forward a series of co-ordinated actions needed to secure self-financing by the BMU members.
RBN Effectiveness in Communication and Self-Promotion
There is an issue concerning the capacity of the RBN to become actively involved and effective in
international public relations and image-building. To date, whilst some notable achievements have
been made at local levels, significantly more effort is needed to attain widespread reach at the
international level. A well-planned systematic approach will be needed to ensure efficiency and
effectiveness of the organisation. With regard to communication and information flow between
Networks and co-management partners, training in making a Strategic Plan will provide an
opportunity to reflect on immediate needs and action areas.
RBN Effectiveness in Fisheries Co-Management
In an increasingly competitive world of regional and global markets, there is increasing concern
about illegal fishing and fish trading activities. The move in the large markets of Europe and USA is
towards certification of fish products based not only on quality assurance standards but also on
sustainable and legal fisheries. If these markets continue to be important destinations for Lake
Victoria fish products, the issue of illegalities becomes even more urgent. Training in planning will
enable the RBN and other Networks develop linked plans of action to address this issue. The issue
also requires strong advocacy skills and actions and both the advocacy training and the Strategic Plan
should help considerably.
RBN Effectiveness in RBN Advocacy
Whilst some achievements have been made there is concern from RBN themselves that their capacity
to engage in a systematic, well-planned way to lobby on behalf of their members needs to be
improved. The TNA revealed inadequacies in engagement by the RBN on key issues affecting their
members, for example, the recent price reduction of Nile perch. The BMU Networks at national and
regional levels should be leading the way on such an issue as the main ―champion of the lake‖ on
behalf of members. Instead, other organisations step into the advocacy void, with no valid
representation credentials and may do more harm than good.
It is imperative for the RBN to keep abreast of key developments in areas of policy, legislation,
planning and guidelines which may affect their current and future operations, and to use their
knowledge, experience and advocacy skills to influence these areas in ways that respond to the needs
of their members. It is particularly important to make use of their membership of the LVFO regional
advisory committees, the FMC and SC, to influence regional decision-making. The RBN realise that
advocacy training and identification of advocacy priorities to be embedded in their Strategic Plan
will greatly improve the current situation.
Training for Regional Beach Management Unit Network (RBN) in East Africa
9 Project Funded by the European Union A project implemented by (Harewelle International Limited)
RBN Effectiveness in Business Development
The role of BMUs and BMU Networks in the area of business development and operations has
largely been ignored to date, even by the BMUs and Networks themselves. For instance, there is no
information on the number, distribution and nature of small and medium sized fisheries business
enterprises (SMEs) currently operating on Lake Victoria. There are in fact tens of thousands of
businesses operating within BMUs under the RBN umbrella. This represents one of the largest
groups of fisheries SMEs in the world brought together under a single organisation. There has so far
been little systematic training in business development and operation despite being crucial to
fisheries livelihoods. The TNA revealed this as a function omitted from the RBN Operating
Procedures but one which needs to be included.
4.1.6 Development of Training Manual
The KE prepared a Training of Trainers Manual following the LVFO Guidelines on format and
process set out in its Human Resources Development Strategy and Action Plan for Lake Victoria
2006. The content of the manual was developed in accordance to the TOR and the briefing with the
ACP FISH II Regional Manager and consultation with the RBN. The training topics for RBN
members were as follows:
Strategic Planning Development – the Consultant will be required to guide participants in
preparing a 3–5 year strategic plan document for the RBN operations for effective
engagement with other stakeholders.
Capacity Building for Advocacy and Lobbying – as a lobby organisation RBN needs such
capacity.
Capacity Building for Grant-making Process/Proposal – effective operation of the RBN has
severely been hampered by lack of proper funding mechanisms. This calls for the RBN to
urgently mobilise funds for the establishment of a Secretariat and find an office space. This
will be included in the strategic plan document.
The topics listed above were covered in 3 training modules 1, 2 and 3 respectively. Module 1
covered 7 sessions, modules 2 and 3 with 2 sessions each. For this ‗training of trainers‘ and for the
downstream training of National BMU Networks by RBN members, a total of 34 Information Sheets
were prepared and used as hand-outs during the training sessions. The topics for training were of
unequal magnitude and therefore required varying times for delivery. Module 1 – the most detailed
topic – was allocated 2.5 days; module 2: 1 day and module 3: 1.5 days.
4.1.7 Training of RBN Members
Approach and Expectations
The training was designed as a training of trainers course and as such, Information Sheets prepared
as hand-outs, were developed taking into account capabilities of trainers and the needs of
―downstream‖ trainees in lower BMU Networks who are to be trained by the new trainers. The
training approach followed basic principles of adult learning, including:
Trainees learn most efficiently when they are actively involved and participate in the learning
process.
Trainees learn better when any new information is related to existing knowledge or prior
experiences.
What trainees learn in the training situation is more likely to be applied on the job if the
training conditions resemble real-life situations.
Training for Regional Beach Management Unit Network (RBN) in East Africa
10 Project Funded by the European Union A project implemented by (Harewelle International Limited)
The expectations of training expressed by the RBN Members during the opening session on 30th
July
2012, included:
1. To make 3 year strategic plan.
2. To get skills about planning and proposal writing so as to get funds to help the RBN in the
future.
3. To get funds to implement strategic plan
4. Proposal writing skills so as to sensitise fisher people
5. To know more about advocacy.
6. To get skills for lobbying.
7. To get skills on running the RBN.
8. To learn more to help the RBN work.
9. To learn more about how to share with others on what we have been trained in.
It was anticipated by the KE that by the end of the training, the RBN members should be able to do
the following:
Module 1: Strategic Planning
a) Leave the training venue with the RBN Strategic Plan with a Logical Framework (logframe)
for performance monitoring of implementing the Plan;
b) Have RBN Vision and Mission statements which need to heard, understood and adopted by
lower Networks;
c) Have sufficient understanding to be able to guide Action Plan training of respective NBNs
and link these to the Strategic Plan;
d) Have a road map of priority actions which each individual member of the RBN has agreed to
implement during discussions in making the Plan.
Module 1: Advocacy
a) Have a better understanding of taking a more systematic, planned approach to lobbying;
b) Leave the training venue with key issues identified by the RBN that require prioritized
lobbying actions by members,
Module 3: Project Proposal Writing
a) Leave the training venue with at least one completed project proposal to be presented to
identified development partners;
b) Have a better understanding of the core structure of a project proposal and how to write one.
The document outputs of training together with the individual evaluations of the course by RBN
trainees evidenced the successful delivery of all of the above expectations.
Opening Session of Training
The procedural norms of the meeting were agreed by RBN members at the opening. These included:
a) Respect all participants views;
b) Respect time-keeping of meeting activities;
c) All participants engage fully in proceedings;
d) Mobile phones switched off or to silent mode.
Training for Regional Beach Management Unit Network (RBN) in East Africa
11 Project Funded by the European Union A project implemented by (Harewelle International Limited)
All RBN members respected the meeting norms and participated fully in being trained as future
trainers. They engaged as future trainers when requested by the KE. This included organising their
own recaps of each previous days training; presenting plenary comments on flip charts; preparing
advocacy positions for the media and presenting them to TV crews and reporters; and engaging with
potential allies in advocacy, the Nile Perch Traders Network on meeting their team during training.
Module 1 Strategic Planning Development
Initial training session focussed on an introduction to planning and the development of RBN Vision
and Mission Statements which were later included in the Strategic Plan. The RBN Chairman had
previously developed draft versions of vision and mission statements and these served as useful
starting points for discussion. The final versions are:
RBN Vision Statement
―Thriving East African fisheries bringing social and economic benefits to all members of
Beach Management Units served by their efficient and supportive associations in partnership
with industrial fisheries enterprises and government‖.
RBN Mission Statement
―The Regional Beach Management Unit Network is an international association that serves
the interests of a quarter of a million members on Lake Victoria by acting as their united
voice, fighting for their rights, lobbying for their livelihood and business interests based on
well co-managed fisheries‖.
The KE emphasised a point from the Information Sheets - the importance of sharing and owning the
vision and mission statements at all levels of BMU Networks and by grassroots BMUs. This should
be an essential part of future ―downstream‖ training by RBN trainers.
Subsequent training sessions focussed on explaining the detailed structure of a strategic plan before
going on to develop RBN Plan. In order to accelerate the planning process, the KE presented a draft
version of the plan as a basis for review and plenary discussion. The logical links between different
levels of the plan – from Activities, Activity Areas to Results, Purpose and Goal of the plan were
carefully explained, ensuring all RBN members understood these relationships. The members agreed
with the overall plan structure and the 5 Results which are based on the key functions of the RBN as
set out in its Operating Procedures.
Once the overall structure of the plan had been discussed and agreed, the training then focussed on
agreeing detailed activity areas, activities and budgets. Each result was taken in turn over the course
of 1.5 days. A component of the plan dealing with RBN advocacy was scheduled for completion
once the initial training was concluded as part of Module 2.
The final half-day of training covered monitoring performance and implementation of the plan. A
logical framework approach was introduced. This was completely new to all but the Chairman.
Members struggled with logframe and more time than available is needed to give them all a solid
understanding of this methodology. A draft logframe prepared previously by the KE was used as a
teaching aid and as a core component of the plan. After review, questions and deliberation by the
RBN members, the logframe was finalised and accepted.
Module 2 Advocacy and Lobbying
The module was divided into two sessions. The first session involved an introduction to advocacy
and lobbying and was supported by 4 Information Sheets as training aids.
Training under module 2: advocacy and lobbing also adopted the training-by-doing approach and
procedures learned during training were applied in the identification of priority advocacy issues
incorporated in the strategic plan. These comprised:
Training for Regional Beach Management Unit Network (RBN) in East Africa
12 Project Funded by the European Union A project implemented by (Harewelle International Limited)
a) National legislation recognising the BMU Networks at all levels.
b) Price transparency at all points along the Nile perch market chain from fishing boat to final
foreign markets.
c) Eradication of the tendering of fisheries tax collection in Tanzania and Uganda.
Module 3 Project Proposal Writing
The module was divided into two sessions. The first session involved an introduction to project
proposal writing and was supported by 6 Information Sheets as training aids.
In the second session, which lasted a day, the RBN members remained in plenary where they were
guided through the planning stages of making a project proposal. They then divided into three groups
of three persons, one from each country, to write a sub-section of the proposal based on bullet-point
topics agreed in plenary. This was the most challenging part of the training course for all members,
with the exception of the Chairman who is, fortunately for the RBN, a skilled writer.
Unlike Modules 1 and 2, there was no draft framework for the project proposal. This meant it had to
be written from the plan made in plenary. The outputs of writing session were the first of their kind
for 8 RBN members and as such, were fairly basic needing refinement by the KE. Using guidance
contained in the Information Sheets, the KE demonstrated how a proposal could be finalised. This
was presented to the members and adopted for their future action.
4.1.8 RBN evaluation of training
Training was evaluated at the end of each day when still very fresh in the minds of trainees. The
LVFO evaluation format was used for first 2 days but replaced by new format sent by RFU which
was applied for the whole training course. The results of evaluations using this method are presented
in Annex 15.
The scoring was high – good or very good for criteria covering the course in general and individual
training modules and sessions. There were detailed comments from 5 of the 9 RBN members with 2
evaluation forms having no additional comments – possibly the Tanzanian members since the form
was in English. An interpreter helped in translation for completing the form for those who needed it.
The comments were all fairly general and highly complimentary about the trainer. The only
suggestion was that they should have more training like this course. They appreciated the pace taken
and personal attention given by the trainer. One trainee noted that they were given a chance twice
during training to put their advocacy into practice – once when the TV and press arrived and again
when they met the team from the Nile perch Traders Network of Kenya. One participant praised the
efforts of WIFIP and the interpreter for making the course run smoothly.
4.1.9 Post-training performance monitoring of RBN
The TOR of the assignment required the KE to develop ―formats for monitoring performance of
participants after the training‖ using the logframe and performance indicators. The most sustainable
way of doing this was to incorporate such performance indicators as OVIs in the logframe of the
RBN Strategic Plan. The performance of the trained RBN members will from now on be evaluated
against the implementation of their 3-year Strategic Plan, July 2012 – June 2015.
Training for Regional Beach Management Unit Network (RBN) in East Africa
13 Project Funded by the European Union A project implemented by (Harewelle International Limited)
4.1.10 Communication and visibility
The Consultant addressed the need for communication and visibility of the EU support in a number
of different ways. First, WIFIP organised a visit by the media to WIFIP whilst the training course
was taking place. A national Kenya Broadcasting Corporation (KBC) team arrived with television
cameras and filmed the RBN Chairman whilst he made a speech about the training event and key
advocacy issues. The film crew also filmed the training in action at WIFIP. A reporter from a
national newspaper, the People, also arrived and interviewed the RBN Chairman.
The local radio station, called "Mayienga" owned by the National Broadcasting House KBC, shared
content of the RBN meeting with another national radio station known as "Ramogi" owned by Royal
Media Services. Both stations broadcast in local Dholuo language the following points:
The RBN meeting brought together the leadership of fishermen in Lake Victoria under the
umbrella of Regional BMU Network.
The organizer of the meeting was the EUACP Fish II programme.
The issues raised by the RBN were reported as decline in Nile perch prices in the region and
need for the industry to share their pricing with RBN for effective dissemination to the
fishers; invasion of water hyacinth on the Kenyan waters; and seasonal omena fishery closure
in Kenya which the RBN promised to push for its review.
T-shirts with the RBN and EU logos were procured for each RBN member and photographs taken
(Annex 16). The KE helped members create a slogan to be printed on the back of the T-shirts.
Certificates of Attendance were developed, printed and awarded to each of the 9 RBN members by
the Provincial Director of Fisheries, Nyanza Province Kenya during the training course closing
ceremony. Acknowledgement of EU ACP FISH II support was noted in the text of the RBN
Strategic Plan document.
4.1.11 Putting RBN training into practice
The meeting of the full contingent of nine RBN members for training triggered several important
actions by them.
1) A request to hold the Second Regular Meeting of the RBN on the afternoon of the 6th
day of
training. It was important to hold this meeting because the organisation had not officially met
since its inauguration in February 2010. It was also an ideal opportunity to formally adopt
outputs of the training course (RBN Strategic Plan 2012-2015 and the RBN project Proposal
for grant support) and commit to actions emanating from the course.
2) Email addresses were set up for all RBN members. At the start of training, only two members
had email addresses but by the end of the week, all 9 members had addresses due to the effort
of the by RBN Chairman.
3) The RBN Chairman and the KE updated and amended the RBN register forms for re-
submission to the LVFO. The amendments included changes in membership and the
inclusion of email addresses.
4) An informal request was made by the RBN to the LVFO Secretariat for office space for the
RBN in the LVFO Secretariat in Jinja, Uganda. The request was made during the visit by the
KE to the LVFO.
Training for Regional Beach Management Unit Network (RBN) in East Africa
14 Project Funded by the European Union A project implemented by (Harewelle International Limited)
5) Advocacy training was put into practice during RBN preparation to meet the media (TV and
press) at WIFIP and subsequent interviews of the RBN Chairman the media. The RBN
Chairman also drafted and submitted a letter to EAIFFPA on the issue of Nile perch price
transparency along the value chain.
4.1.12 Sustainability of EU ACP FISH II support to RBN
The sustainability of training support provided to the RBN through this assignment is strengthened
by having as outputs, the RBN 3-year Strategic Plan and one project proposal to take forward in their
effort to secure grant aid from development partners. Key actions from the Strategic Plan guided the
agenda of the 2nd
Regular meeting of the RBN held on 4th
August, in the afternoon of the final day of
training. The RBN Strategic Plan and project proposal were formally approved and adopted in this
meeting and commitments were by members to undertake immediate actions to implement the plan.
5. CONCLUSIONS AND RECOMMENDATIONS
5.1 Conclusions
Planning:
1. The RBN Strategic Plan, 2012-2015, provides an umbrella framework for the development of
Annual Action Plans by the National BMU Networks and lower Networks on Lake Victoria.
2. RBN members will act as trainers in developing Annual Action Plans at the next NBN
meetings in their respective countries.
3. Holding NBN meetings is a major funding challenge in Tanzania and Uganda which
respective RBN members must find a way of overcoming learning from the Kenya NBN
experience.
4. A cascade of training trainers in action planning down the BMU Network system using
increasing numbers of trainers at each lower level, maximises outreach to grassroots BMU
members.
Advocacy:
5. Three high priority advocacy issues were identified by RBN members and included in the
Strategic Plan for their immediate actions. There are as follows:
a) National legislation recognising the BMU Networks at all levels.
b) Price transparency at all points along the Nile perch market chain from fishing boat
to final foreign markets.
c) Eradication of the tendering of fisheries tax collection in Tanzania and Uganda.
Proposal writing:
6. One project proposal was developed during training for immediate RBN action. The
proposed project is entitled:
“Unleashing the Potential of an International Small-Scale Fisheries Association
in East Africa”
Training for Regional Beach Management Unit Network (RBN) in East Africa
15 Project Funded by the European Union A project implemented by (Harewelle International Limited)
5.2 Recommendations
Planning:
1. RBN members should convene National BMU Network meetings in their respective
countries and provide training of trainers in action planning to develop linked Annual Action
Plans based on the Strategic Plan, 2012-2015.
2. RBN members and the NBN members trained by them should convene District (and County
in Kenya) BMU Network meetings in their respective countries and provide training of
trainers in action planning to develop linked Annual Action Plans based on the Strategic Plan,
2012-2015.
3. RBN members should keep abreast of current regional fisheries plans for Lake Victoria,
including the Nile Perch Fisheries Management Plan 2009-2014 (NPFMP) and the broader
development plan – the Lake Victoria Fisheries Management Plan 2009-2014 (FMP2).
4. RBN members should lobby for a responsive Lake Victoria Fisheries Research Plan which
commits to undertaking stakeholder driven research to guide key management issues and
decision-making.
Advocacy:
5. More detailed action planning by the RBN should be undertaken by email between members
to address the three high priority advocacy issues identified in the Strategic Plan and actions
implemented accordingly.
6. RBN members should lobby, if necessary, for the LVFO regional technical advisory
committee to be held later this year to enable the RBN to influence policy, legislation, plans
and guidelines in the interests of their members.
Project proposal writing:
7. The RBN should formally approach the LVFO Secretariat to provide temporary office space
for the RBN in the LVFO headquarters in Jinja, Uganda.
8. The RBN should submit the project proposal developed during training to development
partners for technical and financial support.
Training for Regional Beach Management Unit Network (RBN) in East Africa
16 Project Funded by the European Union A project implemented by (Harewelle International Limited)
ANNEX 1 TERMS OF REFERENCE
TERMS OF REFERENCE
FOR TRAINING FOR REGIONAL BEACH MANAGEMENT UNIT NETWORK (RBN) IN
EAST AFRICA
(REFERENCE: EA-4.1-B18)
1 BACKGROUND INFORMATION
1.1 Beneficiary countries
The direct beneficiary countries for the implementation of this contract are the three Lake Victoria
riparian countries, namely Kenya, Tanzania and Uganda.
1.2 Contracting Authority
ACP Fish II Coordination Unit
36/21 Av. de Tervuren
5th
Floor
Brussels 1040, Belgium
Tel.: +32 (0)2.7390060
Fax: +32 (0)2.7390068
1.3 Relevant regional background
The Eastern Africa (EA) region for the purposes of the implementation of the ACP Fish II
Programme, operating through the Regional Facilitation Unit (RFU) in Kampala, Uganda is made up
of Fisheries Administrations (FAs) in Burundi, Djibouti, Eritrea, Ethiopia, Kenya, Rwanda, Somalia,
South Sudan, Sudan, Tanzania, and Uganda. These countries are members of a variety of Regional
Fishery Bodies (RFBs), including the Lake Victoria Fisheries Organisation (LVFO), the Lake
Tanganyika Authority (LTA), the Indian Ocean Tuna Commission (IOTC), and the Southwest Indian
Fisheries Commission (SWIOFC), as well as Regional Economic Communities (RECs), including
the Common Market for Eastern and Southern Africa (COMESA), the East African Community
(EAC), the Intergovernmental Authority on Development (IGAD), and the Southern African
Development Community (SADC).
Within the region the direct subjects of this contract are Kenya, Tanzania and Uganda. These
countries have significant fisheries, which play a critical part in their respective economies ―
contributing 0.5% (Kenya), 1.3% (Tanzania), and 1.6% (Uganda) of their GDP annually according to
various estimates ― in terms of foreign exchange earnings, while supporting the livelihoods of
millions of people, a major proportion of which originates from Lake Victoria‘s resources. In fact,
covering a surface area of approximately 68,800 km², Lake Victoria is the largest freshwater lake in
Africa and the second largest in the world. It is shared between Kenya (6% of the total area),
Tanzania (51%) and Uganda (43%). Its shoreline is around 3,440 km long and a catchment area of
about 184,000 km² extending into Rwanda and Burundi through Kagera River, and lies at the head of
the Nile River Basin system. Of about 30 million people of the Lake Basin, it is estimated that Lake
Victoria‘s resources contribute directly to supporting the livelihoods of over 2 million of them
through income, food and employment generation. Additionally, the lake is an important source of
water (for domestic, industry and agriculture uses) and transport.
Training for Regional Beach Management Unit Network (RBN) in East Africa
17 Project Funded by the European Union A project implemented by (Harewelle International Limited)
1.4 Current state of affairs in the relevant sector
According to available statistics (LVFO), Lake Victoria fisheries are currently dominated by three
species: Nile perch (Lates niloticus), Nile tilapia (Oreochromis niloticus), and mukene
(Rastrineobola argentea).1 These three species are also the most commercially important ones,
contributing up to 90% of the catch altogether. The explosive population growth of the Nile perch in
the 1970s and the increase in landings, coupled with overfishing, however led to dramatic changes in
the ecology and a reduction in biodiversity of the lake.
The emerging European market for high-quality white fish meat prompted the establishment of
processing and exporting factories on the shores of the lake in Kisumu, Musoma, Mwanza, Entebbe
and Jinja during the 1980s and early 1990s. In 2005, there were 35 factories, up from 15 in 1990. At
the same time, fishing effort increased tremendously from 129,300 fishers in 2000 (up from
30,000 fishers in 1980) to 199,200 in 2008, and the number of fishing boats from 42,500 to
69,400 units during the same period (LVFO Frame Survey Report, 2008). By the year 2000, there
were signs that most fish species and especially the Nile perch (currently the dominant and most
valuable species) were under threat from both legal fishing and significant levels of illegal fishing, as
reflected in the downward catches observed since then. Available statistics suggest that the Nile
perch is now overfished and urgent measures are required so that the stock can recover.
Efforts to address these threats and to reduce illegalities, as spearheaded by the LVFO Secretariat
and its Council of Ministers (CoM), are translated in a number of actions, some of which involving
the resource users in a co-management approach include:
The adoption by the Partner States of the co-management approach to fisheries in 1998 (and
its operationalisation under LVFO in 2002) and the establishment of Beach Management
Units (BMUs) as the foundation for this approach.2
Lake-wide Guidelines for Beach Management Units (2007) and Guidelines for Fisheries Co-
management (2010). These guidelines have been harmonised and domesticated nationally for
field use regionally.
The establishment of thematic National Working Groups (NWGs) and Regional Working
Groups (RWGs) with a view to providing regional coordination services and quality control,
as well as bringing standardisation in BMU and co-management.
The lake-wide co-management system is founded on legally empowered BMUs at the landing site
level and these organisations supply representatives to village, ward or sub-district and then to
district level where they provide representation to regional or provincial level and ultimately to the
National BMU Network (NBN) whereby the Chairperson is a national representative of the BMUs.
BMUs bring together everyone involved in fisheries at a beach (boat owners, boat crew, traders,
processors, boat builders and repairers, net repairers and others) to work with government and other
1 Mukene is the local name of this native cyprinid in Uganda, while it is called dagaa in Tanzania and omena in Kenya. It forms
with tilapia the basis of domestic and regional trade, while Nile perch is mainly destined for international markets (in the form of
fresh and frozen fillets). Nile perch was introduced mainly from Lake Albert and accessorily from Lake Turkana as a means to
convert the small and abundant, but bony, haplochromine cichlids to suitable table fish, while Nile tilapia was introduced to boost
the then declining fish production of native tilapiines.
2 Co-management ― a partnership arrangement whereby government, resource users and other key stakeholders work together,
share experiences and contribute to decisions with a view to ensuring sustainable utilisation and conservation of natural resources
― is an internationally recognised approach to ensuring wise use and sustainable management of natural resources, contributing to
improving livelihoods and alleviating poverty. The approach is being widely adopted in fisheries. Within the African continent,
Lake Victoria is known to be the largest fishery governed by such system, serving as a model for artisanal and shared fishery
resources.
Training for Regional Beach Management Unit Network (RBN) in East Africa
18 Project Funded by the European Union A project implemented by (Harewelle International Limited)
stakeholders in managing fishery resources and improving the livelihoods of the community
members. Some of the key functions of BMUs are the management of landing sites and the
supervision of the landing and handling of fish in collaboration with district and national level Fish
Inspectors. This is the critical first stage in the long and documented route of Nile perch from the
lake to the consumer in Europe or elsewhere. BMUs therefore have a critical role to play in ensuring
that only legal fishing and trading activities are conducted using the landing sites and also that fish
landed at the site maintains its quality during the transhipment process.
In line with the regional plan in 2009, the NBNs from the three riparian countries came together to
form a Regional BMU Network (RBN) and were recognised as a key partner in the technical
committees of the LVFO. The Organisation indeed facilitated and guided this process. As a new
organisation (inaugurated in March 2010), the RBN requires considerable support and mentoring to
ensure that it remains viable.3
The RBN members adopted the RBN Operating Procedures in March 2010 while elections of
executives followed thereafter.4 The RBN is constituted by 3 members (including the Chair,
Secretary and Treasurer) from each NBN in Kenya, Uganda and Tanzania. The Network represents
all 1,069 BMUs on Lake Victoria by 2007 (including 281 BMUs in Kenya, 433 BMUs in Tanzania,
and 355 BMUs in Uganda) with up to 215,000 members. This is the largest community-based
fisheries organisation (CBFO) in the world operating on a single water body. As BMUs are
increasingly formed across Eastern Africa, the RBN has to ensure its future survival. In fact, there is
need for individual members from the three riparian countries to work together for effective lake-
wide management of shared stocks with their partners in governments and industry. This is
particularly crucial in a co-management context.
With the formation of the RBN new challenges have emerged, such as: (i) managing and co-
ordinating a large network of organisations based at landing sites in three countries; (ii) liaising with
different levels of government administration (e.g., sub-district, district, national) to integrate with
government development plans and budgets; (iii) liaising with the industrial processing and export
sector (iv); maintaining information links and flows between national networks; and (v) low levels of
capacity within the RBN to use these complex institutional and organisational networks and links to
the best advantage for the fisherfolk themselves. Some BMUs continue to face power struggles with
local institutions/agencies due to misunderstanding of the co-management approach. The present
assignment is intended to address these challenges by strengthening the capacity of the RBN and by
improving their institutional memory and backstopping. It is a follow-up of previous training
programmes for BMU representatives on the one hand, and Regional and National BMU Chairs on
the other but with longer duration and higher number of participants. By raising the profile of the
RBN and the BMUs in general through visibility materials such as T-shirts, this assignment will also
serve as an important opportunity for advocacy and communication to a wider audience.
3 The necessity to form this RBN was expressed at the 6th Regular Session of the LVFO CoM of 2006.
4 According to Article 11 (1) of Operating Rules for RBN Meetings, ―at the first meeting of the Regional BMU Network, the RBN
shall adopt its own Operating Procedures and Rules and the LVFO Co-management RWG and LVFO Secretariat will provide
technical steerage to the proceedings‖. To this end, a series of meetings were held in March 2010 with financial and technical
assistance from GTZ. The first meeting held on 9th March 2010 was between the Co-management Regional Working Group
(RWG) and GTZ. In this meeting the group reviewed the draft RBN Operation Procedures. The RWG provided their inputs into
the document thereby producing the final document which was adopted by the RBN members in their first meeting on
10th March 2010.
Training for Regional Beach Management Unit Network (RBN) in East Africa
19 Project Funded by the European Union A project implemented by (Harewelle International Limited)
1.5 Related programmes and other donor activities
The countries included in this contract have received a variety of support for their fisheries sector in
recent years but few have specifically targeted the management of inland resources. The EU and the
Icelandic International Development Agency (ICEIDA) have been the most influential in this regard.
The EU-funded Implementation of a Fisheries Management Plan (IFMP) Project supported the three
riparian States, through the LVFO between 2004 and 2010. The project aimed to harmonise and
develop the co-management system on Lake Victoria through capacity building for the BMUs
themselves and a range of related activities at beach level, with Fisheries Officers and in
collaboration with the industrial processing and export sector.
The programme Implementation of a Regional Fisheries Strategy for the ESA-IO (SmartFish),
funded by the 10th EDF is, amongst other things, providing targeted support to the BMUs around
Lake Victoria. The SmartFish Programme aims at contributing to an increased level of social,
economic and environmental development and deeper regional integration in the ESA-IO region
through improved capacities for the sustainable exploitation of fisheries resources. The Programme
is implemented through a Financing Agreement signed by the IOC as Regional Authorizing Officer.
There is regular communication between the RFU and the SmartFish Programme to ensure synergies
are maximised.
The EU has also provided limited support to BMUs through the Strengthening Fishery Products
(SFP) Health Conditions in ACP/OCT countries programme. This programme ―aims to improve the
access of ACP countries fish and fishery products to the world markets by strengthening export
related health controls and improving production conditions in beneficiary countries.‖ Among other
things, it assisted Fisheries Inspectors from the industry and also the relevant Competent Authorities
(CAs) to improve their practices of monitoring BMUs and sanitary practices at landing sites.
In Uganda ICEIDA has supported training programmes for BMUs and functional adult literacy
programmes (FALP) for the fishing communities to improve sanitary practices.
For its part, the ACP Fish II Programme has, at the request of the BMUs, conducted the following
training programmes during Programme Estimate 1:
24 BMU representatives from key landing sites in Kenya, Tanzania and Uganda were trained
as trainers on business skills and good fish handling, hygiene, sanitation and processing for
7 days in Mwanza, Tanzania in May 2011 as part of Project A10;
The Regional and National BMU Chairs from the three countries were trained in institutional
and organisational development for 3 days in Mukono, Uganda in May 2011 as part of
Project A11.
The above training programmes reflect the need for additional training and mentoring to the RBN. In
particular the latter training programme on institutional and organisational development should be
rolled down to the county or district BMU networks for backstopping and enhanced institutional
memory.
2 OBJECTIVE, PURPOSE & EXPECTED RESULTS
2.1 Overall objective
The overall objective of the ACP Fish II Programme is to contribute to the sustainable and equitable
management of fisheries in ACP regions, thus leading to poverty alleviation and improving food
security in ACP States.
Training for Regional Beach Management Unit Network (RBN) in East Africa
20 Project Funded by the European Union A project implemented by (Harewelle International Limited)
2.2 Purpose
The purpose of this assignment is to strengthen the capacity of the Regional Beach Management Unit
Network (RBN) to effectively participate in the management of the fisheries of Lake Victoria.
2.3 Results to be achieved by the Consultant
The Consultant will achieve the following results as part of this assignment:
i. A training module on capacity building for strategic planning, advocacy and lobbying, and
grant-making process/proposal for the RBN is devised and implemented;
ii. The nine (9) members of the RBN are trained accordingly;
iii. 100 copies of the Training Manual are prepared and delivered to the RBN to help them roll-
out the training to the lower networks and members.
3 ASSUMPTIONS & RISKS
3.1 Assumptions underlying the project intervention
An important assumption underlying project intervention is that the target groups are well prepared
to allocate official hours to this project and to support its implementation. It is also assumed that
those trained will not only put the newly acquired knowledge and skills into practice, but also share
them with other members, for their effective participation in the management of Lake Victoria
fisheries; and that the RBN will be able to roll out this training to lower BMU networks and to
mobilise the necessary funds.
The relevance and need for this assignment was identified in the previous training programmes
targeting BMUs. They were further confirmed by BMU representatives and the Regional and
National Chairs in all meetings and discussions with the Regional Facilitation Unit (RFU) Manager
including the Programme Planning Workshop in Dar es Salaam, Tanzania in October 2010, and
Monitoring Workshops in Kisumu, Kenya and Addis Ababa, Ethiopia in March and December 2011,
respectively. These ToR have been produced in cooperation with the target groups.
ACP Fish II, through this intervention, sets out to respond to this felt need. Since it is a demand-
driven programme, it is assumed that counterpart institutions will take all the necessary measures to
ensure their fulfilment of obligations and responsibilities as set forth under this project. Failure to
meet this requirement is likely to end up in the project not achieving the desired results.
3.2 Risk factors underlying project intervention
The security situation around Lake Victoria is generally satisfactory but if there are any incidents in
areas covered by this study, then local travel advice will always be followed.
4 SCOPE OF THE WORK
4.1 General
4.1.1 Project description
As earlier indicated, the three LVFO Partner States of Kenya, Tanzania and Uganda have adopted
the co-management approach to fisheries in 1998, and have established the BMUs as the foundation
for this approach since then. Despite these efforts (including training programmes), most BMUs at
all levels still lack the necessary capacity that would enable them to better perform their functions in
the co-management context. In particular they still have some weaknesses with regard to resource
management, governance and business management. They lack capacity to contribute to formulation
and promotion of regulations and advising the LVFO and national Fisheries Administrations on
sound resource management based on their indigenous knowledge. Their governance is weak since
Training for Regional Beach Management Unit Network (RBN) in East Africa
21 Project Funded by the European Union A project implemented by (Harewelle International Limited)
their role is sometimes misconstrued. Finally, their networks have limited entrepreneurial skills for
identifying financial mechanisms to sustain activities and maximising their economic benefits from
the fishery. Some of these gaps were filled during the previous training programmes for BMUs.
While the BMus themselves have weaknesses, the RBN as a network also has weaknesses which this
assignment is intended to address by strengthening their capacity.
The Consultant will be required to undertake a Training Needs Assessment (TNA) and develop the
training module for RBN through national consultations. The Consultant, accompanied by the RBN
Chair, will be expected to visit at least one landing site in each country as part of the TNA.
The Consultant will then deliver the training to the nine (9) RBN members based on the findings
of the TNA. This training will last 5 days. The following indicative topics will be covered with the
Consultant expected to refine the list in collaboration with the RBN members:
Strategic Planning Development – the Consultant will be required to guide participants in
preparing a 3–5 year strategic plan document for the RBN operations for effective
engagement with other stakeholders.
Capacity Building for Advocacy and Lobbying – as a lobby organisation RBN needs such
capacity.
Capacity Building for Grant-making Process/Proposal – effective operation of the RBN has
severely been hampered by lack of proper funding mechanisms. This calls for the RBN to
urgently mobilise funds for the establishment of a Secretariat and find an office space. This
will be included in the strategic plan document.
The training will be organised in collaboration with the RBN and in consultation with the LVFO
Secretariat during the whole exercise including the identification, information and mobilisation of
stakeholders. In order to maximise learning, the Consultant will be required to use adult learning
techniques and to lay as much emphasis as possible on practical training (e.g., preparing a strategic
plan document). The Consultant will also be required to compile the above training content as a
practical Training Manual for use by the RBN, the first draft of which will be handed out to
participants during the training and refined upon completion of the training based on comments and
inputs from participants.
The Consultant must give a full recognition of EC funding, ACP Secretariat‘s involvement and
visibility to the ACP Fish II Programme, in all the activities implemented during the project.
4.1.2 Geographic area to be covered
The geographic area to be covered by the contract is Lake Victoria and its three riparian countries
(Kenya, Tanzania and Uganda).
4.1.3 Target groups
The target group for this training are members and executives of the Regional Beach Management
Unit Network (RBN) on Lake Victoria.
4.2 Specific activities
4.2.1 Specific activities
The Consultant will complete the following tasks:
i. Briefing by ACP Fish II and RBN;
ii. Collect and review relevant documents;
Training for Regional Beach Management Unit Network (RBN) in East Africa
22 Project Funded by the European Union A project implemented by (Harewelle International Limited)
iii. Conduct a TNA through consultations with key stakeholders in Kenya, Tanzania and
Uganda;
iv. Make all the logistical arrangements to complete the training itself (including invite
participants, arrange travel, book and pay for flights and vehicles for participants as
necessary, training venue costs, and field visit) – subcontracting for training organisation is
allowed;
v. Conduct the training for the nine (9) RBN members for 5 days;
vi. Evaluate the training;
vii. Develop formats for monitoring performance of participants after the training and provide the
monitoring frame (to be used by the RBN);
viii. Prepare 100 copies of a practical Training Manual for use by the RBN.
On approval of the Final Technical Report, the Consultant will be in charge of the translation of the
Training Materials and Manual, as well as the Executive Summary of the Draft and Final Technical
Report into Swahili.
4.2.2 Communication and project visibility
a) ACP Fish II projects should follow the EU requirements and guidelines for communication
and visibility available on the Programme website at:
http://acpfish2-eu.org/index.php?page=templates&hl=en
b) The CU will provide ACP Fish II templates for various communication products.
c) When validation workshops (where technical documents are presented to stakeholders for
validation) are needed, given their importance for disseminating the results of the Project and
ACP Fish II Programme, the following activities will be requested:
1) The Consultant will provide all necessary information in press-release style
(―information note‖) on the project objectives and results, the activities to undertake,
the main axes or strategic goals proposed and the future role of the beneficiaries.
2) The concerned Fisheries Administrations/Regional Fishery Bodies/Regional
Economic Communities will receive the information note at least 3 days before the
workshop, through their Government communication/press bodies or officials, in
order to mobilise local media and to assure full coverage of the event. Financial
support to media coverage is included in the ―Incidental Expenditure‖. Receipt(s) of
the incurred cost for media coverage will be required to verify the costs incurred.
d) The Consultant will provide photographic record of the project activities including the
workshop, as well as visibility materials such as T-shirts.
4.3 Project management
4.3.1 Responsible body
The Coordination Unit (CU) of the ACP Fish II Programme, based in Brussels, on behalf of the ACP
Secretariat is responsible for managing the implementation of this assignment.
4.3.2 Management structure
The ACP Fish II Programme is implemented through the CU in Brussels and six Regional
Facilitation Units (RFUs) across the ACP countries. The RFU in Kampala, Uganda, covering ACP
Training for Regional Beach Management Unit Network (RBN) in East Africa
23 Project Funded by the European Union A project implemented by (Harewelle International Limited)
member countries in Eastern Africa, will closely supervise the implementation of this intervention
and equally monitor its execution pursuant to these Terms of Reference. For the purposes of this
assignment, the ACP Fish II Programme Coordinator will act as the Project Manager.
All contractual communications including requests for contract modifications or changes to the
Terms of Reference during the execution period of the contract must be addressed with a formal
request to the CU and copied to the RFU. Beneficiary‘s support for these changes is required.
4.3.3 Facilities to be provided by the Contracting Authority and/or other parties
Not applicable.
5 LOGISTICS AND TIMING
5.1 Location
The place of posting for this assignment will be the LVFO Secretariat in Jinja, Uganda, and the
training activity will be held at the agreed location, ideally close to a landing site such as Kisumu,
Kenya. Missions and field visits in the region will be carried out according to the approved timeline
and work plan presented by the Consultant.
5.2 Commencement date & Period of implementation
The intended commencement date is 1st July 2012 and the period of implementation of the contract
will be four (4) months from this date. Please refer to Articles 4 and 5 of the Special Conditions for
the actual commencement date and period of implementation.
6 REQUIREMENTS
6.1 Personnel
6.1.1 Key experts
All experts who have a crucial role in implementing this assignment are referred to as key experts.
Their profiles are described as follows:
Key Expert 1: Inland Fisheries Management Expert
Qualifications and skills
A degree or equivalent in a relevant subject area (e.g., fisheries management, natural resources
management, biology, geography, economics, sociology);
A high level of proficiency in spoken and written English; knowledge of Swahili will be an
advantage.
General professional experience
A minimum of 8 years of experience in inland fisheries management;
Proven report-writing and project management skills.
Specific professional experience
Experience in working with fishing communities and fisheries associations, with a special
focus on co-management of fishery resources (minimum of 5 assignments);
Experience in training and capacity building of fisherfolk and fisheries associations (minimum
of 3 assignments);
Related experience in Lake Victoria will be an advantage;
Training for Regional Beach Management Unit Network (RBN) in East Africa
24 Project Funded by the European Union A project implemented by (Harewelle International Limited)
Experience in carrying out consultancy assignments for the EU or other equivalent
international development partner (minimum of 2 assignments).
There will be 2 missions outside the normal place of posting requiring overnights for this expert.
There will be in-country field visits outside the normal place of posting not requiring overnights, for
this expert.
Indicative number of working days by expert and task
No
.
Indicative Task Key Expert 1
(Days)
1 Briefing by ACP Fish II and RBN and preparatory
activities
3
2 Training needs assessment and module
development
5
3 Elaboration of Training Materials and Manual 4
4 Training delivery and evaluation 6
5 Finalisation of Training Manual and Reporting 2
Total 20
Additional information
a) The Key Expert is expected to spend at least 80% of the total indicative number of working days
in the countries concerned.
b) Note that civil servants and other staff of the public administration of the beneficiary country
cannot be recruited as experts, unless prior written approval has been obtained from the European
Commission (EC).
c) The Consultant must complete a timesheet using the ACP Fish II template provided by the CU at
the start of the implementation period. The Consultant is entitled to work a maximum of 6 days
per week. Mobilisation and demobilisation days will not be considered as working days.
6.1.2 Other experts
No other experts will be recruited under this assignment.
6.1.3 Support staff & backstopping
Backstopping and support staff costs are considered to be included in the fee rates of the experts.
6.2 Office accommodation
Office accommodation of a reasonable standard and of approximately 10 square metres for each
expert working on the contract is to be provided by the Consultant. The costs of the office
accommodation are to be covered by the fee rates of the experts.
6.3 Facilities to be provided by the Consultant
The Consultant shall ensure that experts are adequately supported and equipped (transport, laptop,
printing services, internet and appropriate communication tools). In particular it shall ensure that
there is sufficient administrative, secretarial and interpreting provision to enable experts to
concentrate on their primary responsibilities. It must also transfer funds as necessary to support its
Training for Regional Beach Management Unit Network (RBN) in East Africa
25 Project Funded by the European Union A project implemented by (Harewelle International Limited)
activities under the assignment and to ensure that its employees are paid regularly and in a timely
fashion.
If the Consultant is a consortium, the arrangements should allow for the maximum flexibility in
project implementation. Arrangements offering each consortium member a fixed percentage of the
work to be undertaken under the contract should be avoided.
6.4 Equipment
No equipment is to be purchased on behalf of the Contracting Authority or beneficiary country as
part of this service contract or transferred to the Contracting Authority or beneficiary country at the
end of the contract. Any equipment related to this contract which is to be acquired by the beneficiary
country must be purchased by means of a separate supply tender procedure.
6.5 Incidental expenditure
The Provision for incidental expenditure covers the ancillary and exceptional eligible expenditure
incurred under this contract. It cannot be used for costs which should be covered by the Consultant as
part of its fee rates, as specified above. Its use is governed by the provisions in the General
Conditions and the notes in Annex V of the contract. It covers:
a) KEY EXPERTS
Travel costs and daily subsistence allowances (per diems) for missions for Key Experts,
outside the normal place of posting, to be undertaken as part of this contract. If applicable,
indicate if the provision includes costs for environmental measures, for example CO2
offsetting.
Travel costs for field visits for the Key Experts (car or boat rental, fuel and domestic flights or
other appropriate means of transport).
Any subsistence allowances to be paid for missions undertaken as part of this contract must not
exceed the per diem rates published on the European Union (EU) website at:
http://ec.europa.eu/europeaid/work/procedures/implementation/per_diems/index_en.htm
b) WORKSHOP/TRAINING/CONSULTATIONS ORGANISATION
The cost of organisation of the National Consultations and Regional Validation Workshop
including cost for venue, communication and media activities, transport (domestic travel or car
or boat rental to/from);
The payment of a lump sum to participants requiring an overnight stay to cover
accommodation and meals. This lump sum payment will be up to EUR 150 and must not
exceed the published EU per diem rate for the country;
The payment of a lump sum, up to 30% of the published EU per diem rate for the country, to
all participants not requiring an overnight stay, to cover the cost of transport and meals;
In the two cases above, an attendance list signed by each participant and a separate list stating
that the lump sum was received (with an indication of the amount) shall be used to justify the
expenditure.
c) FUNDING OF NATIONAL/REGIONAL ADMINISTRATION OFFICERS
ACCOMPANYING KEY EXPERTS ON MISSIONS
Training for Regional Beach Management Unit Network (RBN) in East Africa
26 Project Funded by the European Union A project implemented by (Harewelle International Limited)
Exceptionally, the cost of flights, accommodation and meals for the representatives of FAs,
BMU Networks, RFBs or RECs accompanying the Key Experts on regional or national
missions or in-country field visits, under the following conditions:
i) Request of a prior approval to the CU, attaching to this request the declaration issued
by local FAs, BMU, RFBs or RECs stating that the cost of this extra activity for
their officers cannot be covered given the internal budget restrictions. The
administration should acknowledge, despite this, the need of the attendance of its
officer for an effective project implementation.
ii) The total cost for accommodation and meals based on actual cost (invoices to be
provided) cannot exceed the EU per diem rate for the country.
iii) If private or administration‘s means of transport are used by the representatives of FAs,
RFBs or RECs accompanying the Key Experts on regional or national missions, fuel cost
will be reimbursed upon receipt of the officer‘s reimbursement request based on distance
travelled and local price for fuel per unit. In case of field visits, not requiring overnights,
the same procedures apply for meal and transport costs.
d) TRANSLATION
The cost of translation of the Training Materials and Manual, as well as the Executive
Summary of the Draft and Final Technical Report from English into Swahili.
e) OTHER
The cost of producing and delivering 100 Training Manuals for the use of the RBN and the
trained officers to train other community‘s members.
The Provision for incidental expenditure for this contract is EUR 21,990. This amount must be
included without modification in the Budget breakdown.
6.6 Expenditure verification
The Provision for expenditure verification relates to the fees of the auditor who has been charged
with the expenditure verification of this contract in order to proceed with the payment of further pre-
financing instalments if any and/or interim payments if any.
The Provision for expenditure verification for this contract is EUR 1,000. This amount must be
included without modification in the Budget breakdown. This provision cannot be decreased but can
be increased during the execution of the contract.
7 REPORTS
7.1 Reporting requirements
Please refer to Article 26 of the General Conditions. There must be a final report, a final invoice and
the financial report accompanied by an expenditure verification report at the end of the period of
implementation of the tasks. The approved Final Technical Report (FTR) must be annexed to the
Final Report (FR). The final report must be submitted to the CU after receiving the approval of the
Final Technical Report (FTR).
The Final Report (FR) shall consist of a narrative section and a financial section. The financial
section must contain details of the time inputs of the experts, of the incidental expenditure and of the
provision for expenditure verification.
Training for Regional Beach Management Unit Network (RBN) in East Africa
27 Project Funded by the European Union A project implemented by (Harewelle International Limited)
To summarise, the Consultant shall provide the following reports:
Title of Report Content Time of Submission
Inception Report
(IR)
Analysis of existing situation and work
plan for the project. The 10-page report
will be submitted to the RBN and
RFU/CU, for comments.
No later than 10 days after the
first expert arriving in the place
of posting for the first time.
Comments, if any, on the IR
must be provided within 5 days
from receipt.
Draft Final
Technical Report
(DFTR)
Description of achievements, problems
encountered, proposed methodology,
calendar of activities, places to visit and
people to consult and outline of the
content of Final Technical Report.
Within one week of the experts
leaving the country on
conclusion of the assignment.
Comments on the DFTR, if any,
must be provided by the RBN
and RFU/CU within 14 days.
Final Technical
Report (FTR)
Revised DFTR taking into account
changes and comments from the RBN
and RFU/CU.
Within 10 days after receiving
comments on the DFTR. If no
comments on the report are
given within the time limit of
14 days, the DFTR shall be
considered as the FTR.
Final Report (FR) Short description of achievements
including problems encountered,
recommendations and suggestions
together with the FTR and a final
invoice and the FR accompanied by the
expenditure verification report.
Within 1 month of receiving the
approval of the FTR.
The formats of technical reports are available on the ACP Fish II website at:
http://acpfish2-eu.org/index.php?page=templates&hl=en
7.2 Submission & approval of reports
One electronic copy of the reports referred to above must be submitted to the Project Manager
identified in the contract (CU), RFU and RBN. Two hard copies of the approved Final Technical
Report must be submitted to the Project Manager identified in the contract (CU), one hard copy to
the RFU and two hard copies to the RBN. The original and a hard copy of the Final Report (FR)
must be submitted to the CU together with its annexes and supporting documents. All Reports must
be written in English. The Training Materials and Manual and the Executive Summary of the Draft
and Final Technical Report must be translated into Swahili. The Project Manager is responsible for
approving the reports. The cost of producing such material will be included in the fees.
8 MONITORING AND EVALUATION
8.1 Definition of indicators
The results to be achieved by the Consultant are included in Section 2.3 above. Progress to achieving
these results will be measured through the following indicators:
i. Quality of experts fielded (in terms of demonstrated skills and experience);
ii. Speed of mobilisation of experts to the beneficiary country will indicate a positive start of the
assignment;
iii. Identification of methodology, issues and problems, as recorded in the Inception Report;
Training for Regional Beach Management Unit Network (RBN) in East Africa
28 Project Funded by the European Union A project implemented by (Harewelle International Limited)
iv. Reported involvement and degree of satisfaction of the stakeholders in conduct of activities;
v. Quality of Training Materials/Manual produced, as measured by approval by the RBN and
ACP Fish II;
vi. Level of attendance at the training session;
vii. Nature and quality of training evaluation reports from participants;
viii. Number and nature of comments received on the Draft Final Technical Report;
ix. Respect of project milestones with regard to timeframe and report delivery.
The Consultant may suggest additional monitoring tools for the contract duration.
8.2 Special requirements
Not applicable.
Training for Regional Beach Management Unit Network (RBN) in East Africa
29 Project Funded by the European Union A project implemented by (Harewelle International Limited)
ANNEX 2 ITINERARY AND CONSULTATIONS
Date Organisation Location Purpose
16/7/12 International travel UK/Uganda Mobilisation
17/7/12 RBN & NBN Uganda Entebbe, Ug Briefing on ToR; RBN TNA
17/7/12 Kigungu landing site/BMU Kigungu, Ug RBN TNA & Situation Analysis
17/7/12 EAIFFPA (Uganda rep) Entebbe, Ug Situation Analysis
18/7/12 ACP FISH II RFU Kampala, Ug Briefing on TOR
18/7/12 Dept of Fisheries Resources Kampala, Ug Situation Analysis
19/7/12 LVFO Jinja, Ug RBN TNA
19/7/12 Masesi landing site/BMU Masesi, Ug RBN TNA & Situation Analysis
20/7/12 Travel to Kisumu Kisumu, Ke
20/7/12 RBN Chairman & Dept of
Fisheries
Kisumu, Ke Situation Analysis; briefing on ToR
21/7/12 RBN (Chairman) Kisumu, Ke RBN TNA
21/7/12 LVEMP II Kisumu, Ke Discuss possible support to RBN
21/7/12 Dunga landing site/ BMU Dunga, Ke RBN TNA & Situation Analysis
21/7/12 WIFIP Kisumu, Ke Briefing on training course preparation
22/7/12 Travel to Tanzania, Mwanza Mwanza, Tz
23/7/12 Tz NBN Chairman (RBN
Sec)
Mwanza, Tz Briefing on ToR; RBN TNA; Situation
Analysis
23/7/12 Dept of Fisheries Mwanza, Tz Briefing on ToR; RBN TNA; Situation
Analysis
23/7/12 Igombe BMU & landing site Mwanza, Tz RBN TNA & Situation Analysis
24/7/12 Travel to Kenya, Kisumu Kisumu, Ke TNA compilation
25/7/12 Kisumu, Ke Inception Report preparation
26/7/12 Kisumu, Ke Training Manual preparation
27/7/12 Kisumu, Ke Training Manual preparation
28/7/12 Kisumu, Ke Training Manual preparation
29/7/12 Kisumu, Ke Arrival of RBN members
30/7/12 Regional BMU Network Kisumu, Ke Training 9 RBN members
31/7/12 Regional BMU Network Kisumu, Ke Training 9 RBN members
1/8/12 Regional BMU Network Kisumu, Ke Training 9 RBN members
2/8/12 Regional BMU Network Kisumu, Ke Training 9 RBN members
3/8/12 Regional BMU Network Kisumu, Ke Training 9 RBN members
4/8/12 Regional BMU Network Kisumu, Ke Training 9 RBN members
5/8/12 Kisumu, Ke Finalise RBN project proposal; depart
Kenya
6/8/12 UK Arrive UK
Training for Regional Beach Management Unit Network (RBN) in East Africa
30 Project Funded by the European Union A project implemented by (Harewelle International Limited)
ANNEX 3 PERSONS MET
Name Position and Institution Tel Email & website
Mr Godfrey Yiga Kigungu BMU Committee member,
Entebbe, Uganda
- -
Mr Philip Borel EAIFFPA Chairman & UFPEA vice-
Chairman, Entebbe, Uganda
+256752764764 [email protected]
Mr Koane Mindjimba ACP FISH II Regional Manager Eastern
Africa, Kampala, Uganda
+256788786852 [email protected]
Mr. Wadanya LD
Jackson
Acting Commissioner for Fisheries,
DFR Kampala, Uganda
+256772482076 [email protected]
Dr. Rhoda Tumwebaze Assistant Commissioner for Fisheries
Regulation and Control, DFR Kampala,
Uganda
+256772927889
Mr Dick Nyeko Executive Secretary, LVFO, Jinja +256772721455 [email protected]
Mr Mathias Wafula Deputy Executive Secretary, LVFO,
Jinja
+256775201166 [email protected]
Mr Sam Abura Information & Database Officer, LVFO,
Jinja
+256782643204 [email protected]
Mr Marumiga Magio BMU Chairman, Masese landing
site/BMU & DBN member, Jinja
District, Uganda
+256752446352 -
Mr Karomeko Abubaker BMU V-Chairman, Masese landing
site/BMU & DBN Chairman, Jinja
District, Uganda
+256752617593 -
Mr Nsereko Bosco BMU Secretary, Masese landing
site/BMU, Jinja District, Uganda
+256752550023 -
Mr Magara Francis Masese landing site/BMU, Jinja District,
Uganda
+256752475678 -
Mr Mike Obadha Provincial Director of Fisheries, Nyanza
Province, Kisumu, Kenya
+254715720078 [email protected]
Mr Vincent Ogwang LVFO Co-management RWG Chair,
Kisumu, Kenya
+254725351341 [email protected]
Ms Ruth Mungao Business Development Officer, DoF,
Kisumu, Kenya
+254723852355 [email protected]
Mr George Owiti Principal Fisheries Offer, DoF, Kisumu,
Kenya
+254721971882 gowiti2002@yahoo,com
Mrs Jennipher Atieno Executive Director, WIFIP, Kisumu +254733054017 [email protected]
Mr Godfrey Agong Treasurer, Dunga BMU, Dunga, Kisumu
East District, Kenya
+254728348513 [email protected]
Mr Nicholas Didi Secretary, Dunga BMU, Dunga, Kisumu
East District, Kenya
+254724662534 [email protected]
Mr Maurice Owilo BMUC member, Dunga BMU, Dunga,
Kisumu East District, Kenya +254720065472 [email protected]
Mr Richard Ojizo Asst Secretary, Dunga BMU, Dunga,
Kisumu East District, Kenya +254723049228 -
Mr Rodrick Kundu LVEMP II Fisheries Specialist, Kisumu,
Kenya
+254712978816 [email protected]
Mr Lameck Mongo Director of Fisheries, Mwanza, Tz +255787410317 [email protected]
Mr John Kilosa Igombe BMU Committee member +255753661186 -
Mr Salomwa Mjumbo Igombe BMU Committee member +255788440090 -
Mr Chankaga Mnaku Igombe BMU Committee member +255757471128 -
Mr Tim Odende Principal Fisheries officer +254722312889 [email protected]
Mr George Okeyo Value Chain Programme Officer-
Fisheries
Micro Enterprises Support Programme
+254203746764 [email protected]
Training for Regional Beach Management Unit Network (RBN) in East Africa
31 Project Funded by the European Union A project implemented by (Harewelle International Limited)
Name Position and Institution Tel Email & website
Trust (MESPT), Nairobi, Kenya
Mr Joanes Andiego Chairman Lake Victoria Nile Perch
Traders Network – Kenya
+254725727964 [email protected]
Mr Chrispinus Masiga Treasurer Lake Victoria Nile Perch
Traders Network – Kenya
+254724129634 [email protected]
Mr Absalom Odira
Secretary Lake Victoria Nile Perch
Traders Network – Kenya
+254727644231 [email protected]
Mr Tom Guda RBN Chairman, Kenya +254727371074 [email protected]
Mrs Caroline Juma RBN member, Kenya +254720792541 [email protected]
Mrs Carolyn Oduor RBN member, Kenya +254713900861 [email protected]
Mr Robert Bakaaki RBN member, Uganda +256782622945 [email protected]
Mr James Niwagaba RBN member, Uganda +256772417093
+256752417093
Mr Benson Bwire RBN Treasurer, Uganda +25677431104 [email protected]
Mr Simon Rwekaza RBN Deputy Chairman, Tanzania +255752 753522 [email protected]
Mr Pius Maziima RBN member, Tanzania +255784 678347 [email protected]
Mrs Pili Moro RBN Secretary, Tanzania +255788 334048
+255786 994331
Mr Kennedy Odongo Interpreter at RBN training meeting +254722256536 [email protected]
Training for Regional Beach Management Unit Network (RBN) in East Africa
32 Project Funded by the European Union A project implemented by (Harewelle International Limited)
ANNEX 4 ACP FISH II RFU BRIEFING
BRIEFING NOTES MADE BY REGIONAL MANAGER, ACP FISH II
Venue: Offices of the Regional Facilitation Unit, Kampala, Uganda
Date: 18 July 2012
Time: 10:30–12:00
Subject: Initial briefing for Project EA-4.1-B18 on training for Regional Beach Management Unit
Network (RBN) in East Africa
Purpose: Review and agree on the purpose and proposed organisation and methodology of the
assignment
Present: - James Scullion, Key Expert (KE) for Project EA-4.1-B18
- Koane Mindjimba, Regional Manager (RM), ACP Fish II Programme for Eastern
Africa
Methodology: Review major issues of the ToR requiring clarification and common understanding
Issues addressed
and way forward:
1. Opening of the training workshop – KE to seek confirmation from the Assistant
Director of Fisheries (ADF), Nyanza Province in Kisumu (Mr. Michael Obadha) that
he will come and officially open the event on 30/07/2012; KE to forward to the RM
the e-mail sent to the ADF regarding this request.
2. Closing of the training workshop – RM to arrange to travel to Kisumu on 01–
02/08/2012.
3. Certificates of attendance – KE was reminded of the necessity to prepare certificates
of attendance to be handed to participants on completion of the training on
03/08/2012; certificates of attendance to be countersigned by KE and RM.
4. Visibility materials (Section 4.2.2 (d) of the ToR) – KE to arrange with Consultant
(Harewelle International Limited) and local partner in Kisumu (WIFIP Education &
Development) to produce T-shirts for workshop participants.
5. Project description (Section 4.1.1) – KE to cover the three topics listed and compile
them as a single practical Training Manual for use by the RBN, including Strategic
Planning Development, Capacity Building for Advocacy and Lobbying (regionally
and internationally), and Capacity Building for Grant-making Process/Proposal; KE
to use the learning-by-doing approach for that matter.
6. Formats for monitoring performance of participants after the training (Section 4.2.1
(vii)) –this is one of the specific tasks that the KE will be required to complete as part
of this assignment using the logframe and performance indicators.
Communication: KE to update the RM on progress in project execution.
Training for Regional Beach Management Unit Network (RBN) in East Africa
33 Project Funded by the European Union A project implemented by (Harewelle International Limited)
ANNEX 5 REFERENCE DOCUMENT LIST
Cardno, 2012.
The Proposed Fisheries (National BMU Networks) Guidelines 2012. Proposed draft prepared by
Cardno Emerging Markets (East Africa) Ltd on behalf of the Micro Enterprise Support Programme
Trust for the Ministry of Fisheries Development Kenya, July 2012.
Department of Fisheries, 2006a.
National Beach Management Unit Guidelines for Kenya. Department of Fisheries, Nairobi, Kenya
January 2006.
Department of Fisheries, 2006b.
Draft Beach Management Regulations, Department of Fisheries, Nairobi, Kenya, 2006.
Ministry of Fisheries Development, 2011.
Draft Fisheries Management Bill. Ministry of Fisheries Development, Nairobi, Kenya, 2011.
Ministry of Fisheries Development, 2008.
National Fisheries and Oceans Policy. Ministry of Fisheries Development, Nairobi, Kenya
September, 2008.
Department of Fisheries Resources 2011.
The Fish (Amendment) Act 2011. DFR/MAAIF, Entebbe, Uganda.
Department of Fisheries Resources 2004.
Draft National Fisheries Bill, DFR/MAAIF, Uganda.
Department of Fisheries Resources, 2003.
Guidelines for Beach Management Units, DFR/MAAIF, Uganda.
LVFO, 2010.
Operating Procedures for the Regional Beach Management Unit Network of Lake Victoria. Lake
Victoria Fisheries Organisation, Jinja Uganda, February 2010.
LVFO, 2009.
The Fisheries Management Plan for Lake Victoria, 2009 – 2014. Lake Victoria Fisheries
Organisation, Jinja Uganda, August 2008.
LVFO, 2008.
Guidelines for fisheries co-management on Lake Victoria. Guidelines prepared with support from the
Implementation of a Fisheries Management Plan Project (IFMP), EDF Project No 8ACP ROR 029.
Lake Victoria Fisheries Organisation, Jinja, Uganda.
LVFO, 2006.
LVFO HRD Strategy and Action Plan for Lake Victoria, LVFO Secretariat, Jinja, Uganda.
LVFO, 2005. LVFO Harmonised Beach Management Unit Guidelines for Lake Victoria, LVFO
Secretariat, Jinja, Uganda.
Training for Regional Beach Management Unit Network (RBN) in East Africa
34 Project Funded by the European Union A project implemented by (Harewelle International Limited)
Ministry of Agriculture, Animal Industry and Fisheries, 2004.
The National Fisheries Policy, Department of Fisheries Resources, Entebbe, Uganda, May 2004,
Ministry of Livestock and Fisheries Development, 2005.
National Beach Management Unit Guidelines, Kenya, Department of Fisheries, Nairobi, Kenya,
October 2005
Ministry of Natural Resources and Tourism, 2005.
National Guidelines for Beach Management Units, Fisheries Division, Dar es Salaam, Tanzania,
October 2005
Ministry of Natural Resources and Tourism, 2003.
The Fisheries Act, Fisheries Division, Dar es Salaam, Tanzania
Training for Regional Beach Management Unit Network (RBN) in East Africa
35 Project Funded by the European Union A project implemented by (Harewelle International Limited)
ANNEX 6 RBN SITUATION ANALYSIS
Query Response
Organisational Capacity
1. Is RBN registered? Ug -Yes, at LVFO
Ke - Not fully, a certificate of registration still needs to be issued by
LVFO. Original register form needs to be corrected to include the name
and details of the Tanzanian NBN Chairman before certificate is issued.
Tz –Yes, at LVFO
2. Are constituent BMU
Networks registered?
Ug -Submitted details of NBN but no certificate given by DFR but
lower networks are not.
Ke – BMU networks registered but no certificates issued. County BMU
Networks are yet to be registered.
Tz - NBN registered with DoF, Mwanza & DBNs registered but
Since there are no certificates, not sure if fully registered.
3. Where are the BMU
Networks‘ registers and is
there an e copy of them?
Ug – Not sure if NBN Secretary holds them as hard copy, she has no
computer so no e-copy. Government not systematically
recording/compiling registers
Ke – NBN Chairman has e copy on his personal laptop. Location &
Division Networks registered at Provincial Fisheries office but not sure
who holds record/compilation of registers.
Tz - NBN Chair does not have registers and Government not
systematically recording/compiling registers
4. Are there any changes to the
structure, functions & legal
mandates of any BMU
Networks?
Ug – We must check revised Fisheries Bill to see if it empowers
Networks. There are 2 new districts on Lake Victoria which do not have
Networks yet.
Ke - County Government will increase in importance and needs
Networks to be established. New National Guidelines for BMU
Networks has changed the procedure for holding chairmanships of
Networks at different levels in the system. Now, an individual can only
be chair of 2 networks – water body and national network but can be a
member of other networks. There are 4 new districts on the lake that
have no BMU Networks. Sub-Location, Location and Division
Networks will eventually disappear leaving the nearest network to a
BMU as the district. All BMU chairs (281) will become members of
respective DBNs.
Tz – None other than 2 new districts formed that need Networks to be
formed.
5. Are any BMU networks
registered as NGOs. If not, has
this caused any problems?
Ug - No, (KE discussed possible international NGO membership
difficulties)
Ke – No, (KE discussed possible international NGO membership
difficulties)
Tz – No, (KE discussed possible international NGO membership
difficulties)
6. Are there any changes to
individuals who are RBN
members since inauguration?
Ug – No
Ke – Yes, 2 members changed due to BMU Network elections in 2011
Tz – Yes, name of Chairman NBN is incorrect on LVFO register; the
RBN Chairman needs to inform LVFO prior to issue of RBN
registration certificate.
7. Any assets owned by RBN esp
laptops, phones?
Ug – No
Ke - No
Tz - No
8. Does RBN have a Vision and Ke - Yes, partly done during ACP FISH II training in 2010. Need to
Training for Regional Beach Management Unit Network (RBN) in East Africa
36 Project Funded by the European Union A project implemented by (Harewelle International Limited)
Mission Statements i.e. Goal &
Purpose?
present draft to RBN members for their approval at next RBN meeting.
9. Which RBN members use own
laptops for RBN business?
Ug – No
Ke - Yes
Tz – No
10. Which RBN members have
email addresses?
Ug - Yes, Chair NBN Ug has email address.
Ke - Yes, Chair NBN Ke has email address.
Tz - Yes, Chair NBN Tz has email address (to be confirmed).
11. Which RBN members have
internet mobile phones?
Ug – None
Ke - Chair NBN only
Tz – None
12. Which NBN members use
(own) laptops for NBN
business?
Ug - Not now but did previously when laptop was working
Ke - Chairman and Homa Bay County Chairman
Tz - None
13. Which NBN members have
email addresses, why only
some and not all?
Ug - Only Chairman since others live in areas without internet services
Ke - All NBN members = all County Chairmen
Tz - NBN Chair only
14. Which NBN members have
internet mobile phones?
Ug - None because cost too high, around Ush 500,000
Ke - 3 NBN = County Chairmen
Tz - None
15. How and when was RBN logo
and email address and tel nos
agreed?
Ke - RBN Chairmen during ACP FISH II training in September 2010 in
collaboration with 2 other RBN members. Approval of full RBN will be
sought at next meeting.
16. How many NBN meetings
have been held and how many
has each RBN member
attended
Ug - 3 (2 before RBN inauguration and 1 after)
Ke - NBN: 3 times in 2012; 4 times in 2011.
Tz - Once in March 2012 to discuss enforcement/patrols
17. How many DBN meetings
have been held and how many
has each RBN member
attended
Ug - Not sure
Ke - Many but not recorded systematically
Tz - 6 this year, file with records at landing site
18. RBN name may need to
change now there is National
BMU Network in Kenya?
Ug – Agrees
Ke - Already changed the name of NBN to LVNBN
Tz - Agrees
19. How many new districts have
been formed since January
2010?
Ug – 2
Ke - 4
Tz - 2
20. How is information
transmitted between BMU
Networks?
Ug - By phone, SMS, letters and visits
Ke - By phone, SMS, letters and visits
Tz - By phone, SMS, letters and visits
21. Is bulk SMS a potentially
useful way of communicating
between BMU Networks?
Ug - Yes, and has been used
Ke - Yes, and has been used
Tz - Yes, and has been used
22. Is there other mobile phone
uses available to help BMU
Networks transfer
information?
Ug - No specific example given
Ke - No specific example given
Tz - No specific example given
Organisational delivery
23. How has the RBN benefitted
its member Networks and
BMUs in the past 2 years?
Ug - By getting access to RBN training by ACP FISH II and hence the
NBNs benefitted since it‘s the same individuals being trained.
Ke - ACP FISH II training – 2 courses; conflict resolution at Migingo
Island
Training for Regional Beach Management Unit Network (RBN) in East Africa
37 Project Funded by the European Union A project implemented by (Harewelle International Limited)
Tz - No examples
Donor Environment
24. What national and regional
fisheries donor support
programmes have been done in
last 3 years?
Ug - Iceida; ACP FISH II
Ke - EU support via MESPT to restructure BMU network & training in
business development; forming Nile Per Trader Network
LVEMP2 water hyacinth removal; BMU livelihoods training done;
planning training in fish & financial management
Tz- private industry and gov assist
25. What national and regional
donor support programmes in
other sectors relevant to the
RBN have been done in last 3
years?
Ug - SIDA-AMREF HIV/AIDS, safe male circumcision
Ke - HIV/AIDS programmes
Tz - Health education via NGOs using BMUs
Financing RBN
26. Have BMUs or their Networks
paid for RBN member
activities in past 2 years?
Ug – No
Ke - No
Tz - No
27. Have BMUs or their Networks
paid for NBN member
activities in past 2 years?
Ug - No but one meeting held in Uganda after RBN inauguration paid
for personally by NBN Chairman
Ke – payments from lower Networks or from BMUs of members often
occurs but in an ad hoc manner without adequate accountability of
expenditure by members.
Tz – No
28. Have BMUs paid for DBN or
lower BMU Networks member
activities in past 2 years?
Ug - Yes, examples reported in Jinja District of DBN and SCBN
meetings being funded by BMUs (but only 7 BMUs in District).
Ke - Yes
Tz – Yes, a little
29. Has any national or regional
donor programme financially
or technically supported the
RBN or the NBNs?
Ug - Yes, ACP FISH II provided training of RBN members and BMUs
but not direct financial support. GTZ supported RBN inauguration and
initial training in operating as the RBN and engaging in the LVFO
regional technical advisory committees. No further support.
Ke - ACP FISH II training support but not financial.
Tz - ACP FISH II training support but not financial.
30. Has government at national or
regional levels supported the
RBN or NBNs?
Ug – No
Ke - No
Tz - No
31. Who pays when RBN use
phones etc on RBN business?
Ug – Personal
Ke - Personal
Tz - Personal or his BMU
Planning
32. Was the Planning Framework
contained in the RBN
Operating procedures further
developed by the RBN?
Ke – No
33. Have any RBN members
experience of making
budgeted plans related to
BMUs, BMU Networks or
other activities?
Ug – No
Ke - Yes at lower BMU levels
Tz - Yes all 3 RBN members do BMU Plan in Village Plan
34. Have any RBN members
experience of making log
frames related to BMUs, BMU
Networks or other activities?
Ug - No
Ke - No
Tz – No
Training for Regional Beach Management Unit Network (RBN) in East Africa
38 Project Funded by the European Union A project implemented by (Harewelle International Limited)
Project proposals
35. Have any RBN members
experience of making
budgeted project proposals
related to BMUs, BMU
Networks or other activities?
Ug - No
Ke - Not at RBN level but yes at lower levels
Tz - Yes for 2 RBN members Chair and Secretary
RBN Image, profile
36. Have any RBN members
experience of making
promotional materials or
involved in promotional
activities related to BMUs,
BMU Networks or other
activities?
Ug – No
Ke - Yes in making brochures, T shirts etc
Tz - No
Advocacy
37. Have any RBN members
experience of lobbying related
to fisheries activities?
Ug – Yes, on compliance issues
Ke - Yes Chairman has been involved in bringing fishers together in
several campaigns.
Tz - Yes, on issues on HIV and on compliance to fisheries laws
Business development
38. Has any BDS approach been
introduced to BMU Networks
through donors or govs?
Ug – No
Ke - Yes via MESPT – National BMU Network will make a Business
Plan but the RBN Chairman intends to develop one for the LVNBN Tz -
Yes, financial planning training by government & LVEMP
39. Has any training been given to
BMUs or their Networks in
business development &
operation?
Ug - Yes, ACP FISH II providing a component on business
development in training of BMUs in 2011.
Ke – Yes BMU networks received training through MESPT. DoF,
Kisumu has a Business Development Officer whose salary was paid by
GIZ for 2 years ending this year. The officer provided training to omena
traders.
Tz- Yes, a little by ACP FISH II.
Training for Regional Beach Management Unit Network (RBN) in East Africa
39 Project Funded by the European Union A project implemented by (Harewelle International Limited)
ANNEX 7 FA SITUATION ANALYSIS
Query Response Institutions and Policy 1. Are there any changes or
planned changes to National
Fisheries Policy affecting
BMUs and Networks?
Ug – Plan to update policy and requested support from ACP FISH II.
Ke – Policy recently formulated. No need to amend.
Tz – No need to amend.
2. Are there structural changes to
institutions affecting BMUs
and Networks?
LVFO – Has vision to create an East African Community fisheries
administration covering the current 5 countries of the EAC with the
possibility of expanding by the future inclusion of South Sudan. The
private needs to keep pace with such planned reforms by thing of
creating national and regional BMU Networks.
Ug – The establishment of a Fisheries Directorate has been approved by
Ministries of Finance and Public Service. The Fisheries Bill 2004
revised over years still not approved but contains setting up the Uganda
Fisheries Authority (UFA) which is seen as essential by fish industry.
Technical support is needed to guide the institutional relationships
between the UFA and Directorate before the First Principles of the Bill
go back to Cabinet.
Ke – Fisheries restructuring to form Fisheries Service and Fish
Marketing Authority. Fisheries Development Fund to be established
under a Board of Trustees
Tz – None
3. Do you have a register of
RBN/NBN?
LVFO – Yes, RBN register only
Ug – If records are kept, they are not compiled systematically
Ke – Yes, have compilation of details of NBN
Tz – No systematic compilation
4. Are lower BMU Networks
registered?
LVFO - RBN certificate not yet issued
Ug – Not systematically compiled
Ke – Hold records of registers.
Tz – No systematic compilation
Legislation, Guidelines, Plans
5. Are there any changes to
fisheries legislation affecting
BMUs and Networks?
Ug – Fisheries Bill not yet finalised: Cabinet Secretariat must approve
Principles of the Bill again. A Fisheries Amendment Bill has been
approved which establishes a Fisheries development Fund with income
from fisheries licence fees and levies. The Fund requires a further
Regulation covering its operation.
Ke – Fisheries Bill finalisation on-going
Tz – None
6. What is the basis of the legal
identity of BMU Networks?
LVFO - The RBN has unclear legal identity. It should include technical
support in the Strategic Plan to develop legislation to gain legal identity
under EAC via the East African Legislature Assembly to have a
regional BMU Network recognised as a body under the EAC within
which the RBN, among others, would be contained.
Ug – Not clear
Ke – Obtained from imminent gazette notice of the national BMU
Network. (The KE pointed out that BMU Networks are not mentioned
in the Kenya Fisheries Bill)
Tz – No legal basis
7. Have BMU Guidelines been
amended in any way?
Ug – Yes, but process on-going, final version not yet approved. BMUs
were involved in making changes e.g. extending Term of Office from 2
to 4 years on BMUC.
Training for Regional Beach Management Unit Network (RBN) in East Africa
40 Project Funded by the European Union A project implemented by (Harewelle International Limited)
Ke – No
Tz – No
Regional Networking
8. When were the last regional
technical advisory meetings of
the FMC and SC of LVFO?
LVFO – The LVFO Council of Ministers will convene in December
2012. Prior to this the normal LVFO statutory meetings will take place
including the FMC and SC meetings. The RBN and EAIFFPA, as full
members of these committees, will be invited and expected to attend and
participate fully.
Ug – 2010 maybe.
Ke – Long time ago, these days there is little harmonisation of national
activities as a regional programme.
Tz - Long ago, now lost co-ordination.
Support to BMU Networks
9. Have you included any support
to BMUs and Networks in
your Annual Plan and budget
for this financial year?
Ug – Annual budget suffers from incomplete release of funds; allocated
funds for general support to communities but Networks not specifically
mentioned.
Ke – Annual budget suffers from incomplete release of funds; allocated
funds for general support to communities but Networks not specifically
mentioned.
Tz - Annual budget suffers from incomplete release of funds; allocated
funds for general support to communities but Networks not specifically
mentioned.
BMU Performance M&E
10. Have you ever completed a
survey of BM U performance
using the M&E Framework in
the BMU Guidelines since first
done by IFMP in 2007?
Ug – No, due to shortage of funds
Ke – No, due to shortage of funds
Tz – No, due to shortage of funds
Training for Regional Beach Management Unit Network (RBN) in East Africa
41 Project Funded by the European Union A project implemented by (Harewelle International Limited)
ANNEX 8 BMU SITUATION ANALYSIS
Query Response Organisational Capacity 1. What is the name of your
nearest BMU Network and the
Network at the next higher
level?
Ug – BMU members knew names of local BMU Networks
Ke – BMU members knew names of local BMU Networks
Tz – BMU members knew names of local BMU Networks
2. Do these local Networks meet
and how often?
Ug – Yes, the SCBN and DBN meet regularly
Ke – Yes they meet but not sure how often
Tz – Yes they meet at VBN met twice per year, WBN also meet but not
the DBN
3. Who pays for these local BMU
Network meetings?
Ug – Mixed picture of ad hoc payment from individual BMUs to
members who are representatives of local Networks and some with
more systematic, regular funding by BMUs of SCBN. Some funding up
to DBN e.g Jinja DBN has bank account but not to NBN or RBN.
Ke –More systematic payments by BMUs for Networks e.g. Ksh
300/month by all BMUs to pay for LBN & DivBN and ad hoc payments
up to DBNs
Tz – Individual BMUs from where the member belongs but no shared
payment across BMUs
4. Why to these Networks meet? Ug – patrols
Ke – enforcement and patrols; conflict resolution
Tz – Discuss enforcement/patrols, water hyacinth problem
5. What benefits do these local
Networks bring to BMU
members?
Ug – organise patrols
Ke – Give BMUs information on conflict resolution, patrols, coordinate
training, organise self-help saving schemes
Tz – None
6. Does the NBN meet and help
BMU members?
Ug – No
Ke – Yes
Tz – No
Training for Regional Beach Management Unit Network (RBN) in East Africa
42 Project Funded by the European Union A project implemented by (Harewelle International Limited)
ANNEX 9 TNA CHECKLIST
Why Assess Training Needs?
To ensure that training activities actually solve some real problem faced by the trainees, rather than a
problem perceived by an ‗expert‘. The training needs may already be specified, but even in this case
it is usually valuable to examine them more closely with relation to the potential target group before
developing the curriculum and planning the training.
Step 1 Training Needs Identification
The first step is to identify the problem, which is the gap between desired performance and actual
performance, i.e.
Desired Performance – Actual Performance = A Problem or Gap
These problems or gaps will normally be identified by:
a) Informal feedback/requests for training from stakeholders
b) Critical Incident Analysis (what specific things have gone wrong?)
c) The introduction of a new concept, technique or approach
d) Observation of performance (no substitute for this one!)
e) Interviews or group discussions against a pre-determined set of questions or Job Description (best
conducted in the workplace)
Then it is important to look at the cause of the problem or gap. The reasons that the target group are
not behaving as desired may be due to:
a) Lack of knowledge or skill
b) Lack of motivation, or
c) Organisational, social, economic or environmental factors.
This way true Training Needs can be identified, i.e. problems caused by a), or to some extent b)
above. Otherwise training is not the answer.
Problems or gaps that can be addressed by training = Training Needs
N.B. Where we are looking at pre-service training, there is no ‗Actual Performance‘ so the Training
Needs are simply the Desired Performance, based on the future job requirements of the student.
Step 2 Training Needs Analysis
Where it is decided training is the solution (or part of it) it is necessary to analyse the training need
more closely to determine the knowledge, attitudes or skills that trainees need to perform more
effectively.
Analysis means breaking a complex whole into its component parts. So in this context it involves
breaking down the training need into its basic parts so that training content can be identified and
understood.
The needs analysis process can be done at two distinct levels:
a) Job analysis (task identification): This involves breaking down the work into its component parts
so that the trainer understands what, say Fisheries Officers or fishers actually do in the course of their
Training for Regional Beach Management Unit Network (RBN) in East Africa
43 Project Funded by the European Union A project implemented by (Harewelle International Limited)
work. This may cover all aspects of a person‘s work or, more usually, on one part or aspect of a
person‘s work. This is usually by:
A Job Description (in the case of an employee in the formal sector)
Observation, interview or discussion
Experts identify and list critical tasks
Procedures and forms should be developed for this process.
b) Task analysis: This involves breaking these tasks down into their component parts so that they can
be better understood. This is critical to the development of training objectives and content and also
helps in determining the most important elements of a task so that training can focus on these.
Again, procedures and forms should be developed for this process.
This will lead to a series of topics that can be classified as knowledge, skills or attitudes, which
should then be prioritised and presented in a logical sequence.
Step 3 Prepare Training Objectives
Now these lists of topics should be used to write precise statements of what each training session is
to achieve. These statements are called Training Objectives. A Training Objective provides a
detailed description of the skills each trainee will acquire and the essential knowledge trainee will be
able to demonstrate an understanding of by the end of each training session. Objectives should
always include a ‗doing‘ word, e.g. explain, demonstrate, describe, list……….
Training for Regional Beach Management Unit Network (RBN) in East Africa
44 Project Funded by the European Union A project implemented by (Harewelle International Limited)
ANNEX 10 COHERENCE OF BMU NETWORKS
Sub-District BMU Network
Functions
District BMU Network Functions National BMU Network Functions Regional BMU Network Functions
Convene meetings on at least
quarterly basis;
Convene meetings on at least
quarterly basis;
Convene meetings at least twice a
year;
Convene at least two meetings a
year, prepare minutes of meetings
and annual budgeted plans for RBN
activities and submit these to other
BMU Networks and the LVFO
Secretariat.
Harmonize local markings for
identification of fishing gears and
outboard engines by licensed fishers;
Harmonize local markings for
identification of fishing gears and
outboard engines by licensed fishers;
Harmonize local markings for
identification of fishing gears and
outboard engines by licensed fishers
at national level;
Review and harmonise proposals for
the development of fisheries by-laws;
Review and harmonise proposals for
the development of fisheries by-laws
and recommend for approval by the
relevant authority;
Review identified fish breeding areas
on the basis of indigenous knowledge
and clearly demarcate prohibited
fishing zones;
Review and recommend the
demarcation of prohibited fishing
zones;
Review and recommend the
demarcation of prohibited fishing
zones;
Agree on areas of jurisdiction of
BMUs in collaboration with
government;
Lobby for completion of the
demarcation and gazettement of
jurisdictional areas of BMUs and
BMU Networks in each Partner
State.
Review and harmonize actions to
reduce illegal fishing practices;
Review and harmonize actions to
reduce illegal fishing practices;
Review and harmonize actions to
reduce illegal fishing practices in line
with RPOA-IUU and RPOA-
Capacity;
Review and harmonize actions to
reduce illegal fishing and fish trade
in line with the NPFMP, other
fishery specific plans, the RPOA-
IUU and the RPOA-Capacity.
Undertake joint Monitoring, Control
and Surveillance in collaboration
with the relevant authorities;
Undertake joint Monitoring, Control
and Surveillance in collaboration
with the relevant authorities;
Review outcomes of district joint
Monitoring, Control and Surveillance
(MCS) and make recommendations;
Review outcomes of national joint
Monitoring, Control and Surveillance
(MCS) and make recommendations
Training for Regional Beach Management Unit Network (RBN) in East Africa
45 Project Funded by the European Union A project implemented by (Harewelle International Limited)
Sub-District BMU Network
Functions
District BMU Network Functions National BMU Network Functions Regional BMU Network Functions
on future actions.
Contribute to the development and
review of national plans, policies and
legislation;
Contribute to the development and
review of national plans, policies and
legislation;
Contribute to the development and
review of national plans, policies and
legislation;
Contribute to the development,
review and co-ordination of
implementation of harmonized
regional fisheries plans, policies and
legislation.
Compile and synthesise fisheries
management priorities and agree on
appropriate actions using available
data;
Compile and synthesise fisheries
management priorities and agree on
appropriate actions using available
data;
Compile and synthesise national
fisheries management priorities and
agree on appropriate actions using
available data;
Compile and synthesise regional
fisheries management priorities of
BMUs and agree on appropriate
actions using available data.
Network with other BMU Networks
to ensure marketing and fair pricing
of fish and fish products;
Network with other BMU Networks
to ensure marketing and fair pricing
of fish and fish products;
Lobby the fish processing and
exporters association to ensure
marketing and fair pricing of fish and
fish products;
Negotiate a fair system of fish and
fish products pricing for BMU
members.
Prepare annual workplans and
budgets;
Prepare annual workplans and
budgets;
Prepare annual workplans and
budgets;
Included in Function No.1
Formulate funding proposals for
development plans and submit to
funding agencies;
Formulate funding proposals for
development plans and submit them
to funding agencies;
Formulate funding proposals for
development plans and submit to
funding agencies;
In collaboration with other LVFO
bodies, formulate proposals for
regional management and
development interventions and
submit to funding agencies.
Arbitrate in fisheries disputes
between BMUs;
Arbitrate in fisheries disputes
between BMUs;
Arbitrate in fisheries disputes; Assist government and private
industry in the resolution of cross-
border fisheries conflicts.
Lobby for integration of BMU
fisheries management and
community development plans in
government plans;
Lobby for integration of BMU
fisheries management and
community development plans in
government plans;
Contribute to development of district
fisheries plans;
Contribute to development of district
fisheries plans;
Lobby for action from higher
government institutions, including
for the improved provision of health
and social services;
Lobby for action from higher
government institutions, including
the provision of improved health and
social services;
Lobby for action from central
government institutions for provision
of health and social services for
fisheries communities;
In collaboration with other LVFO
bodies, lobby for regional action
from EAC for the provision of health
and social services for fisheries
Training for Regional Beach Management Unit Network (RBN) in East Africa
46 Project Funded by the European Union A project implemented by (Harewelle International Limited)
Sub-District BMU Network
Functions
District BMU Network Functions National BMU Network Functions Regional BMU Network Functions
communities.
Facilitate information flow at various
levels;
Facilitate information flow at various
levels;
Facilitate information flow at various
levels;
Ensure information flows between
the RBN, other BMU Networks and
other stakeholders in furtherance of
RBN objectives.
Monitor the performance of BMUs
and provide supportive measures;
Monitor the performance of BMUs
and provide supportive measures;
Monitor the performance of BMU
Networks at lower levels and provide
supportive measures;
Monitor the performance of BMU
Networks at national level and
recommend supportive measures.
Submit quarterly reports to
Division/District BMU Networks,
member BMUs and the relevant
Fisheries Co-management
Committee.
Advocate for the removal and
prevention of invasive water weeds;
Advocate for the proper disposal of
industrial and urban waste and for
environmental protection in the
catchment;
Open and operate a RBN bank
account, set up a transparent financial
accounting system and may acquire
assets to facilitate its operations.
Collaborate closely with the LVFO
and its Secretariat and provide a
representative to serve as a member
of the LVFO regional technical
advisory committees, the Fisheries
Management Committee and the
Scientific Committee.
Provide a joint forum that represents
and lobbies on behalf of the interests
of all Lake Victoria BMUs and raises
their international profile.
Training for Regional Beach Management Unit Network (RBN) in East Africa
47 Project Funded by the European Union A project implemented by (Harewelle International Limited)
Sub-District BMU Network
Functions
District BMU Network Functions National BMU Network Functions Regional BMU Network Functions
Interact with international, regional
and national government and non-
government agencies and
organisations in the LVFO Partner
States, the industrial fish processors
and export associations, research and
academic institutions, the
international community and
development partners and
programmes for the management of
Lake Victoria aquatic resources and
the furtherance of BMU interests and
objectives.
Training for Regional Beach Management Unit Network (RBN) in East Africa
48 Project Funded by the European Union A project implemented by (Harewelle International Limited)
ANNEX 11 TRAINING NEEDS ASSESSMENT MATRIX
The RBN functions in the TNA matrix are those listed in the RBN Operating Procedures
RBN Functions RBN Progress on Functions Constraint Requiring Training Non-Training Constraint
1. Convene at least two meetings a
year, prepare minutes of meetings
and annual budgeted plans for
RBN activities and submit these to
other BMU Networks and the
LVFO Secretariat.
No RBN meetings have been convened
since inauguration in March 2010 due
to shortage of funds. As a result no
annual budgeted plan has been made
for RBN activities. At local level, there
has been some success in holding self-
financed meetings of BMU Networks
at district level and below but beyond
these levels has proved extremely
difficult for NBNs to meet in Uganda
and Tanzania (only once each). The
meeting in Uganda was held in April
2010 and funded personally by the
NBN Chairman. In contrast, quarterly
NBN meetings have been held in
Kenya in 2011 and 2012. The RBN has
received one training course in 2010 as
part of the ACP FISH II 1 in
strengthening organisational abilities.
The RBN has not yet been able to set up a self-
financing system by BMUs to support NBN and
RBN activities. The RBN has received no
external financial support for its activities and
very limited technical support during the
critically important period after its inception. It
is during this period when guiding and nurturing
support to the very young organisation is most
needed. Training in planning and proposal
writing will address this constraint by:
a) strengthening planning skills;
b) making the first budgeted RBN Strategic
Plan;
c) assist in seeking external financial and
technical support by training in making project
proposals;
d) making the first project proposals;
e) designing extensive and better linked self-
financing system as part of the Strategic Plan.
Success ultimately depends on implementing
post-training actions by RBN members.
BMU elections take up
considerable time and the
timing of elections needs
to be harmonised across
countries. The duration of
the Terms of Office of
RBN members needs to be
extended to make best use
of any training and skills
acquisition.
2. Open and operate a RBN bank
account, set up a transparent
financial accounting system and
may acquire assets to facilitate its
operations.
Since no funds have been received by
the RBN then no bank account has
been opened. At lower levels BMU
Networks receiving funds have opened
bank accounts.
Training in project proposal writing and the
preparation of a project proposal related to
obtaining donor financial support will be one
strategy of RBN financing. A second is by
focusing the attention of RBN members on
establishing self-financing systems for the RBN
as part of activities included in the RBN
Strategic Plan.
LVFO promised to issue a
RBN certificate of
registration has not done
so. The RBN Chairman
should pressure for this to
be done but before doing
so, he should amend the
register to include new
Training for Regional Beach Management Unit Network (RBN) in East Africa
49 Project Funded by the European Union A project implemented by (Harewelle International Limited)
RBN Functions RBN Progress on Functions Constraint Requiring Training Non-Training Constraint
It is only when the RBN is sure to receive funds
that a bank account will be opened. At that
point, training will be needed to set financial
management and accounting systems.
members and email
contacts.
3. Lobby for completion of the
demarcation and gazettement of
jurisdictional areas of BMUs and
BMU Networks in each Partner
State.
No progress has been made because of
lack of funds and also it was not
viewed as an urgent priority by RBN
members. There is some progress
through making BMU by-laws which
set out BMU areas but no survey work
has been done by government and no
BMU areas have been gazetted.
In the absence of jurisdictional areas, BMUs
and their Networks have a significant structural
gap, especially in legal terms. This will be
addressed through advocacy training with a
possibility of selecting this issue as one to be
incorporated into the Strategic Plan for clear
actions to be taken by members.
The creation of 6 new
districts along the lake
shoreline of the 3
countries adds urgency to
the need for demarcating
BMU and BMU Network
jurisdictional areas.
4. Provide a joint forum that
represents and lobbies on behalf of
the interests of all Lake Victoria
BMUs and raises their international
profile.
This is a generalised purpose of the
RBN but to date the organisation has
remained dormant with very low
profile and no advocacy campaigns on
behalf of members‘ interests.
There is urgent need for advocacy training not
only to make the RBN members more
conversant with a systematic approach to be
taken but also to stimulate the organisation into
specific action areas relevant to the immediate
interests of their members in BMUs. An
effectively run campaign should greatly
improve the image and visibility of the
organisation. Selected priority advocacy issues
will be incorporated into the Strategic Plan.
5. Ensure information flows
between the RBN, other BMU
Networks and other stakeholders in
furtherance of RBN objectives.
RBN members, specifically the 3 NBN
Chairmen, communicate with each
other as the RBN by phone, SMS,
letters and visits. The RBN Chairman
communicates similarly with the NBN
in Kenya and recently formed County
Network Chairman. He does not
usually communicate with the other 4
members of the RBN in Uganda and
Tanzania directly but leaves this to the
respective NBN chairs. Constraints on
information flow include:
a) lack of phones to connect to internet,
Training in planning and making a Strategic
Plan will help address this constraint by:
a) Allotting tasks to members to complete
specific information flow related tasks by
agreed deadlines which can be monitored
through using the plan to guide progress.
b) Address financing constraints in the Plan and
its related project proposals to acquire
equipment for members e.g. phones accessing
internet and laptops.
c) Use the Plan and its related project proposals
to establish a small Secretariat to co-ordinate
much of the day-to-day information flow.
The acquisition of an
office for the RBN
Secretariat is costly. In
response, the LVFO
Secretariat has informally
offered a rent-free room at
its headquarters in Jinja,
Uganda as a temporary
arrangement to help set up
a RBN Secretariat.
Training for Regional Beach Management Unit Network (RBN) in East Africa
50 Project Funded by the European Union A project implemented by (Harewelle International Limited)
RBN Functions RBN Progress on Functions Constraint Requiring Training Non-Training Constraint
b) lack of internet services for several
members;
c) lack of computers
d) lack of action plan to steer
communication needs
e) lack of impetus by some members
6. Collaborate closely with the
LVFO and its Secretariat and
provide a representative to serve as
a member of the LVFO regional
technical advisory committees, the
Fisheries Management Committee
(FMC) and the Scientific
Committee (SC).
The RBN Chairman gained
membership of the two regional
advisory committees at the LVFO
Council of Ministers meeting in
November 2009. It was not without
resistance from some LVFO executives
that membership was eventually
obtained. Since that time, there has
been only one meeting of the FMC and
SC, and that was the meeting in March
2010 when the RBN and EAIFFPA
participated for the first time as full
members. The RBN has not lobbied the
LVFO to hold these meets at the
statutory interval of twice per year.
Advocacy training is needed to address this
critically important issue not only for the
purpose of convening FMC and SC meetings at
6-monthly intervals but also for identifying the
key issues of the day to take up on behalf of
BMU members at these meetings. The latter are
the best entry points to regularly influence
policy, legislation, guidelines and plans.
Identification of the key prevailing issues for
each meeting will be incorporated in RBN
Strategic Plan for further action.
7. Interact with international,
regional and national government
and non-government agencies and
organisations in the LVFO Partner
States, the industrial fish
processors and export associations,
research and academic institutions,
the international community and
development partners and
programmes for the management
of Lake Victoria aquatic resources
and the furtherance of BMU
interests and objectives.
In the absence of any Plan, activities
have been undertaken in an ad hoc
manner in response to opportunities
arising. For instance, the RBN Chair
has linked well to the ACP FISH II
programme and attracted various
training for RBN members. Links have
been established with NEPAD fisheries
programme PAF and AMREF in
relation to health services (HIV/AIDs
and male circumcision) in fisheries
communities. The RBN Chairman also
participated in the EU ProInvest
meeting 2011. The RBN Chair is also
closely involved in the LVEMP II
This multi-dimensional set of tasks are
constrained by inadequate networking
experience and skills at international level by
RBN members and the means to physically link
into the numerous meetings and other means of
international dialogue. Advocacy training will
help overcome these constraints and training in
planning will link directly to advocacy training
by incorporating actions related to institutional
linkage into the Strategic Plan.
Training for Regional Beach Management Unit Network (RBN) in East Africa
51 Project Funded by the European Union A project implemented by (Harewelle International Limited)
RBN Functions RBN Progress on Functions Constraint Requiring Training Non-Training Constraint
support to fisheries which amounts to
over $1 million per year. There is less
close connection with LVEMP and the
RBN in Uganda and Tanzania which is
a matter of concern.
8. Compile and synthesise regional
fisheries management priorities of
BMUs and agree on appropriate
actions using available data.
No progress has been made due to
inadequate information compilation
and transfer. This in turn is due to lack
of a permanent Secretariat and lack of
funds for networking, information
sharing, analyses, and meetings to
agree appropriate actions. The lack of
basic equipment such as computers and
printers make this task extremely
challenging.
The constraints can be addressed by training in
making a Strategic Plan to at least develop a
road map of specific actions to gather and
examine the very many BMU priorities and
select the most important to be addressed at
regional level.
9. Contribute to the development,
review and co-ordination of
implementation of harmonized
regional fisheries plans, policies
and legislation.
No progress mainly because the LVFO
regional advisory meetings have not
been held since early 2010. The
significance of these meetings in
influencing regional policies,
legislation and plans has been under-
estimated by the RBN and no pressure
has been put on LVFO by the RBN to
hold the meetings. In other ways the
RBN has contributed e.g. the NBN
Chairman Uganda contributed to
amending Fisheries Bill & BMU
Guideline (as annex to Bill) and the
RBN Chairman is involved in review
and development of the Fisheries Bill
in Kenya.
Advocacy training is very much needed to
address this constraint. Key advocacy issues
will be incorporated into the RBN Strategic
Plan. There is need for further training to
increase the skills for engagement as a dynamic
FMC and SC member representing the interests
of BMU members and their innumerable SMEs.
10. Review and harmonize actions
to reduce illegal fishing and fish
trade in line with the NPFMP,
other fishery specific plans, the
Little progress at regional level with
the exception of the RBN Chairman‘s
involvement in various international
meetings during which he raises issues
Training in planning and making the first
Strategic Plan will provide the opportunity for
incorporation of specific actions into a RBN
Strategic Plan.
Training for Regional Beach Management Unit Network (RBN) in East Africa
52 Project Funded by the European Union A project implemented by (Harewelle International Limited)
RBN Functions RBN Progress on Functions Constraint Requiring Training Non-Training Constraint
RPOA-IUU and the RPOA-
Capacity.
of the need to tackle illegalities on lake
Victoria e.g. NEPAD AU PAF
Governance Working Group meeting
in 2012.
More progress has been made at
national level where NBNs have been
involved in reviewing MCS plans.
11. Review outcomes of national
joint Monitoring, Control and
Surveillance (MCS) and make
recommendations on future
actions.
No progress made. The MCS system is
not harmonised across countries and
the unaccountable nature of patrols in
Uganda is reported to be worsening by
the RBN. Donor support through the
regional EU-funded programme,
SMARTFISH supports MCS training
and has made another MCS manual.
The RBN Chairman is involved with
this initiative. The LVNBN also co-
ordinates the use of government funds
received for MCS in Kenya.
Training in planning and making the first
Strategic Plan will provide the opportunity for
incorporation of specific actions into a RBN
Strategic Plan.
12. Negotiate a fair system of fish
and fish products pricing for BMU
members.
No co-ordinated regional has been
undertaken despite this issue hitting
world press headlines in recent months.
In the lobby vacuum, other NGOs
filled the gap at national level.
And hit the international press
headlines. RBN members made some
progress through NBNs but these
activities are not well known by BMUs
and any future progress that might
emerge is not likely to be widely
recognised at grassroots level.
Advocacy training and the existence of a
Strategic Plan with prioritised advocacy issues
contained within it would have greatly assisted
the RBN in the current issue of Nile perch price
reductions to fish producers and collecting
agents. The specific issue also has cross-cutting
links to information flow between fisheries
stakeholders.
The absence of a strong RBN or NBN voice on
this latest issue highlights the urgent need for
the RBN to much more proactive and visible on
issues that concern fisher‘s welfare. This was an
opportunity missed to act as spokesperson for
BMus all around the lake, to lobby on their
behalf. If successful, the profile and image of
the RBN would have increased enormously –
getting warranted recognition for services
Training for Regional Beach Management Unit Network (RBN) in East Africa
53 Project Funded by the European Union A project implemented by (Harewelle International Limited)
RBN Functions RBN Progress on Functions Constraint Requiring Training Non-Training Constraint
delivered to BMU members. Chances of future
funding of the RBN by BMUs would also likely
increase by proving to be effective.
13. Assist government and private
industry in the resolution of cross-
border fisheries conflicts.
Three RBN members received training
in conflict resolution through ACP
FISH II in 2010. The RBN chair has
been active in helping resolve conflict
between Uganda and Kenya over
Migingo Island. No major cross-border
conflicts have arisen on the Tanzania
borders according to the RBN member
of Tanzania. There is, however, an
issue of fishing vessel confiscation on
the border with Uganda reported by
Kansensero BMU in Uganda. The
NBN Chairman in Uganda has been
involved to help reduce conflict.
Advocacy training will assist in improving
lobbying skills of RBN members and a provide
more systematic approach of the RBN to
lobbying on key issues. Training in planning
and making the first Strategic Plan will provide
the opportunity for incorporation of specific
actions in the RBN Strategic Plan.
14. In collaboration with other
LVFO bodies, formulate proposals
for regional management and
development interventions and
submit to funding agencies.
No progress has been made at regional
level due to lack of RBN meetings and
LVFO statutory technical advisory
committee meetings
Training needed in making project proposals
will improve the abilities of RBN members in
attracting investments. Training in making a
Strategic Plan will enable RBN members to take
a more systematic approach to making
proposals and monitoring progress in
implementation.
LVFO should hold
regional technical
advisory committee
meetings (FMC and SC)
at designated interval of
twice per year.
15. In collaboration with other
LVFO bodies, lobby for regional
action from EAC for the provision
of health and social services for
fisheries communities.
No co-ordinated region actions have
been undertaken by the RBN but at
national level members have lobbied
for improved health services to be
delivered to fisheries communities. For
example, in Uganda the NBN
Chairman was involved in a campaign
for safe male circumcision; liaised with
AIDS support organisation to help
BMUs; worked with Uganda AIDS
Commission as the NBN involving in
Advocacy training will assist in improving
lobbying skills of RBN members and provide
more systematic approach of the RBN to
lobbying on key issues. Training in planning
and proposal writing will also assist in attracting
regional support for the provision of health and
social services to fisheries communities.
Training for Regional Beach Management Unit Network (RBN) in East Africa
54 Project Funded by the European Union A project implemented by (Harewelle International Limited)
RBN Functions RBN Progress on Functions Constraint Requiring Training Non-Training Constraint
distribution of condoms.
16. Monitor the performance of
BMU Networks at national level
and recommend supportive
measures.
No progress due mainly to lack of a
Secretariat to co-ordinate monitoring
and lack of funding.
Performance monitoring within an organisation
is essential to maintain efficiency and
effectiveness. It is by this means strengths and
weaknesses are identified and capacity building
can be planned and implemented to address
identified weaknesses. M&E is an integral part
of making the RBN Strategic Plan and training
on this topic will help the RBN understand the
importance of monitoring. M&E is a topic that
warrants further specific training of the RBN
and lower Networks.
Any other significant RBN
functions identified by RBN
members not listed above but
which were or were not
undertaken:
The RBN members felt the need for
exchange visits to relevant
organisations for lesson learning;
systematic MCS training; training in
alternative livelihoods; training in
fisheries business development; ways
of increasing the profile of the RBN.
The fisheries administrations felt a
need for inclusion of credit and savings
activities in the RBN Plan; production
of an RBN electronic Newsletter (1
page); use of bulk SMS to
communicate between Networks; and
the inclusion of performance indicators
to monitor the RBN Plan. The LVFO
expressed the need for an RBN Vision
on which to base bankable investment
proposals.
Training for Regional Beach Management Unit Network (RBN) in East Africa
55 Project Funded by the European Union A project implemented by (Harewelle International Limited)
ANNEX 12 RBN PARTICIPANTS IN TRAINING
Name M/F Stakeholder
Group
Post in
RBN
Age ID No. Tel. No. Email Postal Address & Email
Address
Tom Guda M Boat Owner Chairman 40 001 +254 727
371074
+254 733
979942
P.O. Box 1-40301, Kendu-
Bay, Kenya
Caroline Juma F Fish Trader Member 33 21240329 +254 720
792541
P.O. Box 102, Pap Onditi,
Kenya
Carolyn Oduor F Fish Trader Member 37 13599778 +254 713
900861
P.O. Box 175, Bondo, Kenya
Robert Bakaaki M Boat Owner Member 40 0239 +256 782
622945
+256 752
946978
[email protected] Kigungu Landing Site,
Entebbe, Uganda
James
Niwagaba
M Boat Owner
(Fisherman)
Treasurer 38 0240 +256 774
311044
+256 752
417093
Lambu Landing Site
Masaka, Uganda
Benson Bwire M Boat Owner Member 40 0245 +256 783
894624
[email protected] Buduma BMU,Sigulu;
Subcounty,Namayingo,
Uganda
Simon
Rwekaza
M Boat Owner
(Fisherman)
Vice
Chairman
63 08265138 +255 752
753522
P.O. Box 171, Muleba,
Tanzania
Pius Maziima M Boat Owner
(Fisherman)
Secretary 54 07 +255 784
678347
P.O. Box 164, Magu,
Mwanza, Tanzania
Pili Moro F Trader Member 38 120 +255 788
334048
+255 786
994331
P.O. Box 16861, Bukoba,
Tanzania
Training for Regional Beach Management Unit Network (RBN) in East Africa
56 Project Funded by the European Union A project implemented by (Harewelle International Limited)
ANNEX 13 RBN TRAINEES IN LOWER BMU NETWORKS
Name Country
of
National
BMU
Network
Position in
National
BMU
Network
Name of
District BMU
Network
Position
in District
BMU
Network
Name of
location/ward/SC
BMU Network
Position in
location/ward/SC
BMU Network
Name of
BMU
Position in
BMU
Tom Guda Kenya Chairperson Rachuonyo Member N/A N/A Rakwaro Chairman
Caroline
Juma
Kenya Treasurer Nyando Member N/A N/A Kombewa Treasurer
Carolyn
Oduor
Kenya Secretary Bondo Member N/A N/A Saga Secretary
Robert
Bakaaki
Uganda Chairman Wakiso
District
Chairman Entebbe
Municipality
Chairman Kigungu Vice Chairman
James
Niwagaba
Uganda Treasurer Masaka Chairman Bukakata General Secretary Lambu Vice Chairman
Benson Bwire Uganda Secretary Namayingo Chairman Sigulu Chairman Buduma Chairman
Simon
Rwekaza
Tanzania Chairman Muleba Chairman Mazinga-
Mulumo
Chairman Mulumo Chairman
Pius Mazima Tanzania Secretary Magu-
Mwanza
Chairman Kiloleli-Magu-
Mwanza
Chairman Ihale-
Magu-
Mwanza
Chairman
Pili Moro Tanzania Treasurer Bukoba-
Kagera
Treasurer Kagya-Bukoba Member Kyonge Storekeeper
Training for Regional Beach Management Unit Network (RBN) in East Africa
57 Project Funded by the European Union A project implemented by (Harewelle International Limited)
ANNEX 14 RBN TRAINING OF TRAINERS MANUAL
Training for Regional Beach Management Unit Network (RBN) in East Africa
58 Project Funded by the European Union A project implemented by (Harewelle International Limited)
"Strengthening Fisheries Management in ACP
Countries"
Training of Trainers Manual
Training of Trainers for Regional Beach Management Unit
Network (RBN) in East Africa
Project ref. N°
EA-4.1-B18
Region: Eastern Africa
Countries: Kenya, Tanzania, Uganda
28 July 2012
Assignment by:
Training for Regional Beach Management Unit Network (RBN) in East Africa
59 Project Funded by the European Union A project implemented by (Harewelle International Limited)
Table of Contents
1. INTRODUCTION .................................................................................................................................... 61
2. TRAINING COURSE TIMETABLE ............................................................................................................. 63
3. TRAINING SESSION PLANNING .............................................................................................................. 65
4. TRAINING SESSION OPENING ................................................................................................................ 66
4.1 TRAINING SESSION PLAN ........................................................................................................................ 66 4.2 TRAINERS NOTES .................................................................................................................................... 66 4.3 TRAINING AIDS ....................................................................................................................................... 67 4.4 REFERENCE MATERIAL ........................................................................................................................... 68
5. TRAINING ON STRATEGIC PLANNING .................................................................................................... 69
5.1 MODULE 1- SESSION 1 ............................................................................................................................ 69 5.1.1 Training Session Plan ................................................................................................................... 69 5.1.2 Trainers Notes .............................................................................................................................. 69 5.1.3 Training Aids ................................................................................................................................ 71 5.1.4 Reference Material ....................................................................................................................... 84
5.2 MODULE 1- SESSION 2 ............................................................................................................................ 85 5.2.1 Training Session Plan .................................................................................................................. 85 5.2.2 Trainers Notes .............................................................................................................................. 85 5.2.3 Training Aids ................................................................................................................................ 86 5.2.4 Reference Material ....................................................................................................................... 90
5.3 END OF DAY EVALUATION OF TRAINING .......................................................................................................... 91 5.4 MODULE 1- SESSION 3 ................................................................................................................................ 94
5.4.1 Training Session Plan ................................................................................................................... 94 5.4.2 Trainers Notes .............................................................................................................................. 94 5.4.3 Training Aids ................................................................................................................................ 95 5.4.4 Reference Material ....................................................................................................................... 97
5.5 MODULE 1- SESSION 4 ............................................................................................................................ 98 5.5.1 Training Session Plan .................................................................................................................. 98 5.5.2 Trainers Notes .............................................................................................................................. 98 5.5.3 Training Aids ................................................................................................................................ 99 5.5.4 Reference Material ..................................................................................................................... 102
5.6 MODULE 1- SESSION 5 .......................................................................................................................... 103 5.6.1 Training Session Plan ................................................................................................................ 103 5.6.2 Trainers Notes ............................................................................................................................ 103 5.6.3 Training Aids .............................................................................................................................. 104 5.6.4 Reference Material ..................................................................................................................... 106
5.7 MODULE 1- SESSION 6 .......................................................................................................................... 107 5.7.1 Training Session Plan ................................................................................................................ 107 5.7.2 Trainers Notes ............................................................................................................................ 107 5.7.3 Training Aids .............................................................................................................................. 108 5.7.4 Reference Material ..................................................................................................................... 110
5.8 END OF DAY EVALUATION OF TRAINING ............................................................................................. 111 5.9 MODULE 1- SESSION 7 .......................................................................................................................... 112
5.9.1 Training Session Plan ................................................................................................................ 112 5.9.2 Trainers Notes ............................................................................................................................ 112 5.9.3 Training Aids .............................................................................................................................. 113 5.9.4 Reference Material ..................................................................................................................... 120
Training for Regional Beach Management Unit Network (RBN) in East Africa
60 Project Funded by the European Union A project implemented by (Harewelle International Limited)
6. TRAINING ON ADVOCACY ................................................................................................................... 121
6.1 MODULE 2- SESSION 1 .......................................................................................................................... 121 6.1.1 Training Session Plan ................................................................................................................ 121 6.1.2 Trainers Notes ............................................................................................................................ 121 6.1.3 Training Aids .............................................................................................................................. 123 6.1.4 Reference Material ..................................................................................................................... 131
6.2 END OF DAY EVALUATION OF TRAINING ........................................................................................................ 131 6.3 MODULE 2- SESSION 2 .......................................................................................................................... 132
6.3.1 Training Session Plan ................................................................................................................ 132 6.3.2 Trainers Notes ............................................................................................................................ 132 6.3.3 Training Aids .............................................................................................................................. 133 6.3.4 Reference Material ..................................................................................................................... 135
7. TRAINING ON PROJECT PROPOSAL WRITING ...................................................................................... 136
7.1 MODULE 3- SESSION 1 .......................................................................................................................... 136 7.1.1 Training Session Plan ................................................................................................................ 136 7.1.2 Trainers Notes ............................................................................................................................ 136 7.1.3 Training Aids .............................................................................................................................. 137 7.1.4 Reference Material ..................................................................................................................... 146
7.2 END OF DAY EVALUATION OF TRAINING ............................................................................................. 146 7.3 MODULE 3- SESSION 2 .......................................................................................................................... 150
7.3.1 Training Session Plan ................................................................................................................ 150 7.3.2 Trainers Notes ............................................................................................................................ 150 7.3.3 Training Aids .............................................................................................................................. 151 7.3.4 Reference Material ..................................................................................................................... 151
7.4 END OF DAY EVALUATION OF TRAINING ............................................................................................. 151
Training for Regional Beach Management Unit Network (RBN) in East Africa
61 Project Funded by the European Union A project implemented by (Harewelle International Limited)
TRAINING OF TRAINERS MANUAL FOR THE LAKE
VICTORIA REGIONAL BMU NETWORK
TRAINING TOPICS: STRATEGIC PLANNING, ADVOCACY AND PROJECT
PROPOSAL WRITING
1. INTRODUCTION
The structure and format of this manual is based on the LVFO Guidelines for the process of
developing training manuals contained in the LVFO Human Resource Development Strategy
and Action Plan for Lake Victoria Fisheries 2008. This is a training of trainers course
specifically for the members of the Lake Victoria Regional BMU Network (RBN). The RBN
was inaugurated in February 2010 and contains 9 members, 3 members nominated by
National BMU Networks in each Partner State. There are 3 female members of the RBN. The
RBN has a Chairman, Assistant Chairman, Secretary and Treasurer. There are RBN
Operating Procedures adopted in February 2010 which define the functions of the RBN.
Since this is a training of trainers course, it is important to understand the future trainees
targeted by the newly trained trainers of the RBN. Their target trainees are situated at various
levels in the national BMU Networks of each Partner State of Kenya, Tanzania and Uganda.
The Regional BMU Network is the international apex body representing all BMUs operating
on Lake Victoria. The structure of the RBN is founded upon a pyramidal system of lower
BMU Networks and the BMUs themselves. There 1,069 BMUs on the lake organised into
higher level associations called Networks set up to coincide with different levels of
government administration. The level immediately above the BMUs varies between
countries. In Tanzania, there is a Village BMU Network where there is more than one BMU
in village. In 2007, 68 Village BMU Networks were formed. This level is not present in
Kenya and Uganda. The next level up in Tanzania is the Ward which is broadly equivalent to
the Location in Kenya, and the Parish in Uganda. In 2007, 129 Ward BMU Networks were
formed in Tanzania, 71 Location BMU Networks in Kenya and 44 Sub-county (next level up
from Parish) BMU Networks in Uganda. In Kenya, networks were also formed at the next
level above Location, called the Division. Here, 25 Division BMU Networks (DivBN) were
formed. At District level, 8 District BMU Networks in Kenya, 12 in Tanzania and 11 in
Uganda. There are now 6 new districts on the lake shore created since RBN inauguration.
These are still without BMU Networks. One National BMU Network operates in each Partner
State.
The immediate targets for training by the newly trained RBN members are the three National
BMU Networks. The RBN should decide whether the training they give is TOT or simply
training the target NBN members. The advantage of being a TOT is that the NBN members
then become trainers for lower Networks so that capacity building cascades downwards
through the pyramidal structures to reach many more BMU members. This is essential if
there are to be linked BMU Network plans.
The RBN received previous training in May 2011 with technical support provided by the EU
ACP FISH programme. The course covered institutional and organisational development and
introduced concepts such an organisation‘s vision, mission statements and action plan but
Training for Regional Beach Management Unit Network (RBN) in East Africa
62 Project Funded by the European Union A project implemented by (Harewelle International Limited)
without going into detail. The current training follows on from that course and is again
delivered with technical support of ACP FISH II.
The TOR of this assignment were developed in close collaboration with the RBN and
contains a list of training topics identified by the RBN as being of highest priority to address
their current needs. A Training Needs Assessment completed by an external consultant
confirmed this selection of topics as being of highest priority.
The topics identified by the RBN and the TNA for the training course, include:
Module 1: Strategic Planning Development
The RBN members will be guided in preparing a 3-year Strategic Plan for
RBN operations and effective engagement with other stakeholders.
Module 2: Capacity Building for Advocacy and Lobbying.
The RBN is a lobby organisation and requires capacity building to improve its
skills and systems.
Module 3: Capacity Building for Grant-making Process/Proposal
Effective operation of the RBN has severely been hampered by lack of
funding mechanisms. This calls for the RBN to urgently mobilise funds for the
establishment of a Secretariat and find an office space. This will also be
included in the strategic plan document.
The training is designed as a training of trainers course and as such materials such as
information sheets prepared as hand-outs, have been developed taking into account the
capabilities and needs of ―downstream‖ trainees in lower BMU Networks who are to be
trained by the new trainers. Training will last for 5 days. The training approach will follow
the basic principles of adult learning, including:
Trainees learn most efficiently when they are actively involved and participate in the
learning process.
Trainees learn better when any new information is related to existing knowledge or
prior experiences.
What trainees learn in the training situation is more likely to be applied on the job if
the training conditions resemble real-life situations.
By the end of the training, the RBN members should be able to do the following:
Module 1: Strategic Planning
e) Leave the training venue with the RBN Strategic Plan with a Logical Framework
(logframe) for performance monitoring of implementing the Plan;
f) Have RBN Vision and Mission statements which need to heard, understood and
adopted by lower Networks;
g) Have sufficient understanding to be able to guide Action Plan training of respective
NBNs and link these to the Strategic Plan;
h) Have a road map of priority actions which each individual member of the RBN has
agreed to implement during discussions in making the Plan.
Training for Regional Beach Management Unit Network (RBN) in East Africa
63 Project Funded by the European Union A project implemented by (Harewelle International Limited)
Module 1: Advocacy
c) Have a better understanding of taking a more systematic, planned approach to
lobbying;
d) Leave the training venue with key issues identified by the RBN that require
prioritized lobbying actions by members,
Module 3: Project Proposal Writing
c) Leave the training venue with at least one completed project proposal to be presented
to identified development partners;
d) Have a better understanding of the core structure of a project proposal and how to
write one.
2. TRAINING COURSE TIMETABLE
The timetable allocated 2.5 days to Module 1: Strategic Planning; 1 day to Module 2:
Advocacy and 1.5 days to Module 3: Project Proposal Writing.
Day/Date Schedule of Activities
Monday 30th
July
Session A (1h 30 min) 8.30 Registration
9.00 Official opening
9.15 Workshop introduction
9.30 Expectations
10.00 Break
Module 1: Session 1 (2h 45 min) 10.15 Module 1: Strategic Plan - Planning
Introduction
13.00 Lunch
Module 1: Session 2 (1h 45 min) 13.45 Module 1: Strategic Plan: Result 1
15.30 Break
Module 1: Session 2 (1h 15 min) 15.45 Module 1: Strategic Plan: Result 1
17.00 Daily evaluation & close
Tuesday 31st July
Module 1: Session 3 (1 hr) 9.00 Recap of day 1 & Introduction day 2
9.15 Module 1: Strategic Plan: Result 3
10.00 Break
Module 1: Session 4 (2h 45 min) 10.15 Module 1: Strategic Plan: Result 2
13.00 Lunch
Module 1: Session 5 (1h 45 min) 13.45 Module 1: Strategic Plan: Result 4
15.30 Break
Module 1: Session 6 (1h 15 min) 15.45 Module 1: Strategic Plan: Result 5
17.00 Daily evaluation & close
Wednesday 1st August
Module 1: Session 7 (1 hr) 9.00 Recap of day 2 & Introduction day 3
9.15 Module 1: Strategic Plan: Logframe
10.00 Break
Module 1: Session 7 (2h 45 min) 10.15 Module 1: Strategic Plan: Logframe
Training for Regional Beach Management Unit Network (RBN) in East Africa
64 Project Funded by the European Union A project implemented by (Harewelle International Limited)
13.00 Lunch
Module 2: Session 1 (1h 45 min) 13.45 Module 2: Advocacy: introduction
15.30 Break
Module 2: Session 1 (1h 15 min) 15.45 Module 2: Advocacy: introduction
17.00 Daily evaluation & close
Thursday 2nd
August
Module 2: Session 2 (1 hr) 9.00 Recap of day 3 & Introduction day 4
9.15 Module 2: Advocacy: insert in plan
10.00 Break
Module 2: Session 2 (2h 45 min) 10.15 Module 2: Advocacy: insert in plan
13.00 Lunch
Module 3: Session 1 (1h 45 min) 13.45 Module 3: Proposal writing: intro
15.30 Break
Module 3: Session 1 (1h15 min) 15.45 Module 3: Proposal writing: intro
17.00 Daily evaluation & close
Friday 3rd
August
Module 3: Session 2 (1 hr ) 9.00 Recap of day 4 & Introduction day 5
9.15 Module 3: Proposal writing: make prop
10.00 Break
Module 3: Session 2 (2h 45 min) 10.15 Module 3: Proposal writing: make prop
13.00 Lunch
Module 3: Session 2 (1h 45 hr) 13.45 Module 3: Proposal writing: make prop
15.30 Break
Module 3: Session 2 ( 1h 15 min) 15.45 Module 3: Proposal writing: make prop
17.00 Daily evaluation & close
Saturday 4th
August
9.00 Recap & overview of course
9.30 Plenary final questions & comments
10.00 Break
10.30 End of course evaluation
12.00 Official closure
12.30 Lunch
14.00 RBN meeting: training on agenda
Training for Regional Beach Management Unit Network (RBN) in East Africa
65 Project Funded by the European Union A project implemented by (Harewelle International Limited)
3. TRAINING SESSION PLANNING
For each of the sessions listed in the timetable the following set of documents are used to
design and deliver training of trainers:
a) Training Session Plans: to assist in planning before training
b) Trainers Notes: are reference material for use during training
c) Training aids: such as hand-outs, leaflets, posters, projected slides, audio/video tapes
These should be fully developed and form part of the Training Manual, so that
trainers can simply copy or reproduce them for use in their training.
d) Reference material: this is detailed text for each session, including illustrations where
necessary, on which the session is based. It provides information for the trainers when
they are preparing the sessions, including the raw material for the training aids which
will assist the trainees both during training and later. This material is too detailed to
use during training hence the inclusion of Trainers Notes.
Training for Regional Beach Management Unit Network (RBN) in East Africa
66 Project Funded by the European Union A project implemented by (Harewelle International Limited)
4. TRAINING SESSION OPENING
4.1 Training Session Plan
Opening Session A Date: 30th
July 2012 Duration: 1 hr 30 min
Title: Opening and Introduction to the Training Course
Objectives:
1. Know other members of the RBN better
2. Understand the purpose of the training and its importance to RBN & other Network
members
3. Understand how the course will be run, including logistical arrangements
4. Agree that training topics are a priority
5. Know participants‘ expectations of the training course
6. Know what will be received at the end of the course
Content: Training Points Methods Time
Introduction
Registration of Participants
Opening meeting by RBN Chairman
Official Opening by PDF Nyanza Province
Opening remarks by RBN Chairman &
Consultant
Presentations
Discussions
25 mins
Development
Introductions - participants introduce neighbour
Background & Purpose of the training course
Trainees expectations
Implementation & logistical arrangements
Documented output
Presentation
Cards filled
Info Sheets
Q & A
Discussion
1 hr
Conclusion Recap of main points, address any queries 5 mins
Training materials: Hand outs, Flip charts, Flip chart pens
Evaluation: Q & A
4.2 Trainers Notes
Opening Session p.1
Trainer Trainee
Introduction (25 min)
1. Registration of Participants Complete registration form
2. Opening meeting by RBN Chairman &
self-introductions
RBN Chairman welcomes participants
3. Official Opening by PDF Nyanza Province Receive official opening
4. Opening remarks by RBN Chairman &
Consultant
Receive opening remarks
5. Agreeing meeting norms
Include all 9 members being facilitators at
least once during meeting for practices as
trainers.
Develop and agree norms for running the
meeting.
Q&A
Development (60 min)
Introductions Introduce their RHS or nearest neighbour
Training for Regional Beach Management Unit Network (RBN) in East Africa
67 Project Funded by the European Union A project implemented by (Harewelle International Limited)
Background & purpose of the training course
RBN challenges –funds, skills,
systems;
ACP FISH II support to RBN (2
training courses);
TOR & RBN involvement
Difference between TOT & training
Q&A
Participants expectations
Review & list on flip chart
Compare with Information Sheet 1
done
Each trainee completes card giving 1
expectation for each module
Implementation of course
Make meeting norms on flip chart;
(encourage quiet indivs to answer)
Agree proposed course timetable
Discuss interpretation into Kiswahili
TOT so trainees may also facilitate as
part of training
Make their norms for running the meeting in
plenary
Review timetable and comment
Consider facilitating tasks
Document outputs from course
Certificate of training for trainees
Training manual including trainer
materials
RBN Strategic Plan including
advocacy targets
Monitoring Framework for Strategic
Plan (logframe)
One Project Proposal
Inception Report of Consultant
Final technical Report of Consultant
Other outputs: T shirts for trainees
Receive certificates, manual, Plan, proposal,
logframe, reports (later) and T shirt
Conclusion (5 min)
Recap of main points, address any queries Q&A
Training materials: Hand outs, Flip charts,
Flip chart pens; cards, pens
Evaluation: Confirm all are clear on topics
discussed
Q&A
4.3 Training Aids
Information Sheet 1, Opening Session
OPENING SESSION: INFORMATION SHEET 1
Expectations of Training
By the end of the training, the RBN members should be able to do the following:
Training for Regional Beach Management Unit Network (RBN) in East Africa
68 Project Funded by the European Union A project implemented by (Harewelle International Limited)
Module 1: Strategic Planning
i) Leave the training venue with the RBN Strategic Plan with a Logical Framework
(logframe) for performance monitoring of implementing the Plan;
j) Have RBN Vision and Mission statements which need to heard, understood and
adopted by lower Networks;
k) Have sufficient understanding to be able to guide Action Plan training of respective
NBNs and link these to the Strategic Plan;
l) Have a road map of priority actions which each individual member of the RBN has
agreed to implement during discussions in making the Plan.
Module 1: Advocacy
e) Have a better understanding of taking a more systematic, planned approach to
lobbying;
f) Leave the training venue with key issues identified by the RBN that require
prioritized lobbying actions by members,
Module 3: Project Proposal Writing
e) Leave the training venue with at least one completed project proposal to be presented
to identified development partners;
f) Have a better understanding of the core structure of a project proposal and how to
write one.
4.4 Reference Material
Reference material includes the ACP FISH II Terms of Reference for the training assignment.
Training for Regional Beach Management Unit Network (RBN) in East Africa
69 Project Funded by the European Union A project implemented by (Harewelle International Limited)
5. TRAINING ON STRATEGIC PLANNING
5.1 Module 1- Session 1
5.1.1 Training Session Plan
Module 1 - Session 1 Date: 30th
July 2012 Duration: 2hr 45 mins
Title: Introduction to Strategic Planning
Objectives:
Know why a plan is needed and what a strategic plan is
Know the difference between a strategic plan and an action plan
Understand what a Vision statement of an organisation is and make one for the RBN
Understand what a Mission statement of an organisation is and make one for the RBN
Understand what a Strategic Plan Purpose is and make one for the RBN Strategic Plan
Content: Training Points Methods Time
Introduction Overview of session 15 min
Development Reasons for planning
Strategic vs Action plans
Vision Statement
Mission Statement
Structure of a Strategic Plan
Presentation,
Info sheets,
Group work,
Plenary
Q&A,
discussion
2h 20 min
Conclusion Recap of main points, address any queries Q&A 10 min
Training materials: Hand outs, Flip charts, Flip chart pens
Evaluation: Standard forms completed
5.1.2 Trainers Notes
Opening Session p.1
Trainer Trainee
Introduction (15 min)
Overview of session content and relate to
time available. Why plan; Why a strategic
plan; need vision & mission; explain plan
structure.
Receive overview
Development (2 hr 20 min)
Strategic Plan vs Action Plan
Why a ―Strategic Plan‖? What is it?
Ask individuals for one reason each & record
Give responses – no more than one answer
per person then compare with Information
Sheet 1.
Training for Regional Beach Management Unit Network (RBN) in East Africa
70 Project Funded by the European Union A project implemented by (Harewelle International Limited)
on flip chart. Compare with ―text book‖
reasons (given in Information Sheet 1) after
trainees make own list to ensure on right
track with no gaps. (10 min)
Why make a plan?
Ask individuals for one reason each & record
on flip chart.
Compare with ―text book‖ reasons (given in
Info Sheet 1) done after trainees make own
list to ensure on right track with no gaps. (10
min)
Give responses – no more than one answer
per person then compare with Information
Sheet 1.
Vision & Mission Statements
Explain the terms and their uses for an
organisation using Information Sheet 2 hand-
out that includes examples. (20 min)
Ask who has experience of making these
statements – gather their examples if known.
Remind 3 RBN members of ACP FISH II
training that raised this topic – is there a draft
RBN Vision & Mission Statements to review
Info Sheet 3: Fisheries visions in EAC.
(15 min)
Look at Information Sheet 2 and compare
draft RBN vision and mission statements and
comment. Consider examples of vision from
fisheries organisations in EAC by looking at
Information Sheet 3 and comment.
Draft a RBN Vision.
When all trainees understand what a vision
statement is ask them to form groups to draft
their statement (or two if groups wish).
Ask the groups to imagine five years into the
future. In order to stimulate thinking,
consider the following questions:
• What kind of organization do you want the
RBN to become?
• What will the RBN look like in five years?
Review group work results, compile and
synthesise into final statement. Guide
statement structure if needed. (20 min)
Divide into 3 groups of 3 persons, one from
each country and prepare a Vision Statement
and an alternative. Use flip chart.
Draft a RBN Mission.
When all trainees understand what a vision
statement is ask them to form groups to draft
their statement (or two if groups wish).
Review group work results, compile and
synthesise into final statement. Guide
statement structure if needed.
Remember – need plan purpose & results to
finalise mission statement – return to it later
(20 min).
Divide into 3 groups of 3 persons, one from
each country and prepare a Mission
Statement and an alternative. Use flip chart.
Strategic Plan Structure Receive Information Sheet.
Training for Regional Beach Management Unit Network (RBN) in East Africa
71 Project Funded by the European Union A project implemented by (Harewelle International Limited)
Explain the core components of a Strategic
Plan. Refer trainees to Information Sheet 4
(20 min)
Q&A
RBN Strategic Plan Structure
Explain that RBN Strategic plan based on
RBN functions set out in Operating
Procedures. (Refer to Information Sheet 5:
RBN functions)
Explain grouping of RBN functions into
thematic areas and link these to Results of
Plan (15 min)
Look at Information Sheet 5 and review RBN
functions in thematic categories and relate to
possible Results of Strategic Plan. Reach
consensus on Result headings
Remember to go back to review and finalise
the RBN Mission Statement after agreeing
the Strategic Plan Purpose and Results
(10 min)
Review and amend, if necessary, the Mission
Statement after considering the Strategic Plan
Purpose and Results. Reach consensus in
plenary.
Conclusion (10 min)
Recap of main points, address any queries Q&A
Training materials: Information Sheets,
Flip charts, Flip chart pens; cards, pens
Evaluation: Confirm all are clear on topics
discussed
Q&A
5.1.3 Training Aids
Information Sheets 1-7, Module 1 – Session1.
Training for Regional Beach Management Unit Network (RBN) in East Africa
72 Project Funded by the European Union A project implemented by (Harewelle International Limited)
MODULE 1 - SESSION 1: INFORMATION SHEET 1
STRATEGIC PLANS AND PLANNING
What is the purpose of a written plan?
A written plan will:
• Ensure that the purpose, aims, objectives and proposed activities are accessible to the team
and others with whom the RBN works.
• Form the basis for decisions on allocation of funds and work load of people.
• Form a basis to measure progress.
• Help continuity by providing new members with a reference point and all members with a
reminder of what they should be doing.
REMEMBER: ―If you don’t know where you are going, that’s probably where you’ll end
up—nowhere!‖
What is strategic planning?
Strategic planning is a disciplined process for making key decisions and agreeing on actions
that will shape and guide what the RBN is, what it does, and why it does it. Strategic
planning is an opportunity to draw a road map for the RBN, one which lays out the steps it
must take to reach its vision. The strategic planning helps people make things happen.
What is the life span of a strategic plan and how often should it be updated?
It is advisable to plan for at least three years.
It is usual for a strategic plan to be reviewed annually. The plan can be amended and
modified to reflect developments that have taken place over the year. However, the more
detailed annual work plan will be needed once funds are obtained and will be more specific
and will probably require quite a lot of amendment at the end of each year.
Strategic vs Action Planning
Strategic Planning Action Planning
Long-term (usually 3-10 years) Short-term (1 year or less)
Done once every 3 years or more but lightly
reviewed annually
Done annually or more frequently
Focuses on future achievements and conditions Achievements or targets are annual
Weighs a series of alternatives before making
choices
Planned activities often represent choices
already made, alternatives not considered
Budget is approximate and not detailed Budget is detailed and more accurate
Activities are usually described broadly Activities defined in more detail
Resources (finances etc) not always identified
and plan includes sourcing funds
Resources (finances etc) for implementing
action are usually already identified
Training for Regional Beach Management Unit Network (RBN) in East Africa
73 Project Funded by the European Union A project implemented by (Harewelle International Limited)
STRATEGIC PLANNING: WHAT QUESTIONS DOES IT ANSWER?
Whether you are planning for a program, a department, a clinic, a region, or an organization,
the questions that you answer in the strategic planning process are the same. These questions
are simple and straightforward; they ask you and your colleagues to examine your
organization and discover what it is.
1. Why Does the RBN Exist? Your response to this question will be a mission statement
(sometimes called a statement of purpose) which describes the RBN‘s main purpose and
values. You will produce a mission statement as part of this strategic planning process.
2. What Does the RBN Want To Do? Your response to this question will be a set of results
or outputs for the future which describe the RBN‘s ideal state of being. These results or
outputs express what the RBN would be doing if it were performing at its best. You will
produce your results/outputs in this strategic planning process.
3. What Does the RBN Do Well? Your response to this question will emerge as you and
your colleagues determine what factors made the high points (successes) possible for the
RBN.
4. Where Does RBN Wish To Go? Your response to this question will be a vision
statement which briefly describes a shared picture of the RBN‘s best future—what it wishes
to create or what it hopes to be. You will produce a vision statement as part of this strategic
planning process.
5. How Will Your Organization Get There? Your response to this question will be a plan,
in our case a Strategic Plan, which outlines the specific action areas the RBN will engage in
to make each result/output happen. The Strategic Plan will include budget and identify
possible sources of funding and a schedule for completing them.
Training for Regional Beach Management Unit Network (RBN) in East Africa
74 Project Funded by the European Union A project implemented by (Harewelle International Limited)
MODULE 1 - SESSION 1: INFORMATION SHEET 2
VISION AND MISSION STATEMENTS
THE VISION STATEMENT
Strategic planning typically involves making a vision statement. A vision statement is a
concise expression of the RBN‘s best future, of what it wishes to be. This vision is the
―beating heart‖ of the RBN‘s work and its image of success. People want to be part of the
RBN because they believe in its vision. Most important of all, the vision for the RBN must be
shared by all who have an interest in what the organisation does. The vision should never be
something that is imposed on people. Rather, it should be generated, shared, understood,
accepted, and lived by everyone in the RBN responsible for making it a reality.
Characteristics of a Vision statement
An effective and useful vision statement typically has the following characteristics:
It looks into the medium- to long-term future (usually 2-5 years);
It is very short (usually a brief sentence, or two at most);
It describes a fixed stage;
It can be understood by anyone.
This vision is not something the RBN can achieve on its own. It is something that guides the
RBN members in their work and which they believe can be achieved if enough projects and
organisations share the vision and work towards it.
An example of a vision might be:
We strive to contribute to a society where every citizen has equal access to quality
healthcare and is able to live in an environment which supports quality health
through access for all to clean water, healthy food and sanitary living conditions.
The particular organisation with this vision may be an organisation that trains and supports
community health workers in rural villages. It believes that its work will contribute to this
vision.
THE MISSION STATEMENT
The mission statement is a more practical and precise description of the RBN‘s purpose or
reason for existence. Many people refer to an organisation‘s mission statement as its calling
card, or important part of its identity. It is typical for people researching an organisation to
ask first to see its mission statement because it conveys so much useful information.
The RBN‘s mission statement is a concise introduction to its work. It describes the RBN in
terms of its:
Purpose: what the RBN seeks to accomplish (WHY DOES IT EXIST?)
Target Audience: the target group or beneficiaries of the RBN‘s work (WHO DOES
IT SERVE?)
Training for Regional Beach Management Unit Network (RBN) in East Africa
75 Project Funded by the European Union A project implemented by (Harewelle International Limited)
Business: the main method or activity through which the RBN tries to fulfil this
purpose (WHAT SERVICES DOES IT PROVIDE and HOW DOES IT GO ABOUT
PROVIDING THEM?)
The most important characteristic of a mission statement is clarity. The RBN‘s ability to state
its mission clearly indicates how well it knows where it is going. The task of producing a
mission statement is an exercise in finding this clarity. Addressing the fundamental questions
above will help RBN members keep your mission statement clear and straightforward.
The RBN mission statement should be supported by all who are involved in its work.
Consider the possibility that every single member of the RBN can generate interest in its
activities by speaking comfortably and confidently about its mission. Think of the positive
impression you and your colleagues will make on others when you know exactly what to say
when people ask, ―what is your organization‘s mission?‖
The more people who know and understand the mission, the more likely it is to be achieved.
Characteristics of a Mission Statement
An effective mission statement typically has the following characteristics:
It gives direction;
It is concise and compelling;
It is easily understood and can be communicated by all members of the organization;
It provides motivation and rallies people to a common purpose;
It identifies the organization‘s central purpose;
It expresses the organization‘s values
A mission statement will have four components:
1. What the RBN is;
2. What the RBN aims to do or achieve;
3. Who the work is aimed at (the target group) and who it is done with;
4. How it does its work – in broad terms, what methods it uses.
An example of a mission statement:
We are an NGO working to ensure that all people in our country, particularly the landless
poor, have access to land for sustainable development. We do this by helping government
develop land policies that will benefit the disadvantaged.
Why is a mission statement important?
A mission statement is important because:
It is an easy way to communicate to others what you do and how you do it. It helps you to
clarify and focus your work. If any of the components change, then the mission statement
needs to change as well. That is why it is important to review the mission statement from
time to time.
In the context of a strategic planning process, it is useful to introduce the mission statement
once the vision has been clarified, but it cannot be finalised it until the goal and purpose
of the Strategic Plan have been agreed.
Training for Regional Beach Management Unit Network (RBN) in East Africa
76 Project Funded by the European Union A project implemented by (Harewelle International Limited)
MODULE 1 - SESSION 1: INFORMATION SHEET 3
VISION & MISSION STATEMENTS FROM FISHERIES SECTOR OF EAC
Uganda National Fisheries Policy 2004
Vision
The national vision for Uganda‘s fisheries sector is, ―an ensured sustainable exploitation of
the fishery resources at the highest possible levels, thereby maintaining fish availability for
both present and future generations without degrading the environment‖.
Fisheries Sector Goal
The overall fisheries sector goal is to ensure increased and sustainable fish production and
utilisation by properly managing capture fisheries, promoting aquaculture and reducing post
harvest losses.
Kenya Fisheries Policy 2008
Fisheries Sector Goal
The Primary goal of the fisheries sector is to ensure increased and sustainable fish production
and utilization by properly managing the Ocean and other Kenya Fishery waters.
The overall objective of this Policy is:- “to enhance the fisheries sector‘s contribution to wealth creation, increased employment for
youth and women, food security, and revenue generation through effective private, public and
community partnerships‖.
EAIFFPA Work Plan 2009-2011
Goal
Contribute to the fisheries sector‘s role in sustainable economic growth, poverty reduction
and improved livelihoods in Kenya, Tanzania and Uganda
Purpose
Sustainable production and marketing of high quality fish & seafood products compliant with
national and international market standards derived from effectively co-managed fisheries
and well linked to the national associations of the fish industry.
Lake Victoria Fisheries Management Plan 2009-2014
Vision Sustainable utilization of fisheries resources, managed through good governance to create
prosperous fishing communities
Goal
Contribute to the sustainable economic growth and reduction of poverty in East Africa.
Purpose Effectively co-manage fisheries resources of Lake Victoria for sustainable fish production
and socio- economic benefits.
Training for Regional Beach Management Unit Network (RBN) in East Africa
77 Project Funded by the European Union A project implemented by (Harewelle International Limited)
MODULE 1 - SESSION 1: INFORMATION SHEET 4
STRUCTURE OF STRATEGIC PLANS
Depending on what approach you are using, or development partner you are working with,
there are many different names for the different levels of goals and objectives used in
planning. Here we are using terminology used in EU programmes.
Goal
The goal is defined here as the accumulated benefits which beneficiaries will enjoy when the
broad development work is successful; this is not a target for which a project or plan is
accountable for delivering but rather makes some contribution to achieving the goal.
Purpose
The purpose of a plan, project or programme describes the specific situation which the
project or organisation hopes to bring about. The purpose is a deliverable against which
progress and performance are monitored. Whilst the goal is related to the vision, the purpose
is more closely related to the mission statement. The purpose sets the agenda of the RBN.
Results
In order to achieve the purpose, you need to achieve certain results that will, together, lead to
the positive situation you desire – successful delivery of the purpose. By now you should be
able to see that there is a vertical (up/down) logic at work here:
Goal achieved (in part by contribution made by the RBN Plan implemented
successfully)
Purpose achieved by
Achieving the planned results which, in turn are achieved by
Implementing planned activities
The Strategic Plan aims at contributing to the achievement of the goal by achieving the
purpose. The RBN assumes that by following this logic, it will make a difference to the
significant problem identified. Using this vertical logic is how you think strategically.
Activity Areas
To achieve a Result requires accurate identification of the activity areas needed to do this.
Each activity area will contain a variable number of activities within it.
Timeline
A Strategic Plan needs to have an implementation period divided into time intervals,
Normally a plan is from 3 to 5 years but it gets more and more difficult to plan well for the
future as the period gets longer. The time intervals for a strategic plan are usually in years.
Budget
A Strategic Plan needs a budget to give an idea of whether or not it is affordable. It should
also contain activities for sourcing funding where existing funds are not enough to implement
the plan. The costs estimates in a strategic plan are usually approximate.
Training for Regional Beach Management Unit Network (RBN) in East Africa
78 Project Funded by the European Union A project implemented by (Harewelle International Limited)
MODULE 1 - SESSION 1: INFORMATION SHEET 5
RBN FUNCTIONS CATEGORISED BY SUBJECT:
Financing and Operations
1. Open and operate a RBN bank account, set up a transparent financial accounting
system and may acquire assets to facilitate its operations.
2. In collaboration with other LVFO bodies, formulate proposals for regional
management and development interventions and submit to funding agencies.
3. Convene at least two meetings a year, prepare minutes of meetings and annual
budgeted plans for RBN activities and submit these to other BMU Networks and the
LVFO Secretariat.
Communication & promotion
4. Ensure information flows between the RBN, other BMU Networks and other
stakeholders in furtherance of RBN objectives.
5. Interact with international, regional and national government and non-government
agencies and organisations in the LVFO Partner States, the industrial fish processors
and export associations, research and academic institutions, the international
community and development partners and programmes for the management of Lake
Victoria aquatic resources and the furtherance of BMU interests and objectives.
Co-management
1. Collaborate closely with the LVFO and its Secretariat and provide a representative to
serve as a member of the LVFO regional technical advisory committees, the Fisheries
Management Committee and the Scientific Committee.
2. Contribute to the development, review and co-ordination of implementation of
harmonized regional fisheries plans, policies and legislation.
3. Compile and synthesise regional fisheries management priorities of BMUs and agree
on appropriate actions using available data.
4. Review and harmonize actions to reduce illegal fishing and fish trade in line with the
NPFMP, other fishery specific plans, the RPOA-IUU and the RPOA-Capacity.
5. Review outcomes of national joint Monitoring, Control and Surveillance (MCS) and
make recommendations on future actions.
6. Monitor the performance of BMU Networks at national level and recommend
supportive measures.
Advocacy
7. Lobby for completion of the demarcation and gazettement of jurisdictional areas of
BMUs and BMU Networks in each Partner State.
8. Provide a joint forum that represents and lobbies on behalf of the interests of all Lake
Victoria BMUs and raises their international profile.
9. In collaboration with other LVFO bodies, lobby for regional action from EAC for the
provision of health and social services for fisheries communities.
10. Assist government and private industry in the resolution of cross-border fisheries
conflicts.
Business development
11. Negotiate a fair system of fish and fish products pricing for BMU members.
Training for Regional Beach Management Unit Network (RBN) in East Africa
79 Project Funded by the European Union A project implemented by (Harewelle International Limited)
MODULE 1 - SESSION 1: INFORMATION SHEET 6
DRAFT STRATEGIC PLAN RESULTS AND ACTIVITIES
DRAFT STRATEGIC PLAN RESULTS DERIVED FROM RBN FUNCTIONS
1. RESULT 1 EFFECTIVE FINANCING & OPERATIONS
2. RESULT 2 EFFECTIVE COMMUNICATION & PROMOTIONAL
SYSTEMS
3. RESULT 3 RBN EFFECTIVE IN FISHERIES CO-MANAGEMENT
4. RESULT 4 EFFECTIVE RBN ADVOCACY
5. RESULT 5 BUSINESS DEVELOPMENT IMPROVED
DRAFT STRATEGIC PLAN ACTIVITY AREAS AND ACTIVITIES FOR EACH
RESULT
RESULT 1 EFFECTIVE FINANCING & OPERATIONS
1.1 Set up self-financing by BMUs
1.1.1 Develop self-financing procedures
1.1.2 Gain consensus of BMUs for procedures & rates of pay
1.1.3 Set up RBN financial management procedures
1.1.4 Open RBN bank account
1.1.5 Annual external audit of RBN accts
1.2 Obtain donor financing
1.2.1 Develop regional project proposals & submit to donors
1.2.2 Find possible donors & submit proposals
1.3 RBN meetings
1.3.1 Training for RBN members in planning, project design &advocacy
1.3.2 Hold two progress & planning meetings a year.
Training for Regional Beach Management Unit Network (RBN) in East Africa
80 Project Funded by the European Union A project implemented by (Harewelle International Limited)
1.3.3 Support NBNs in making budgeted plans
1.3.4 Support DBNs in making budgeted plans
1.4 RBN office established
1.4.1 Office location agreed, equipped & opened
1.4.2 Office operations
1.5 RBN Secretariat established
1.5.1 Job descriptions made, job adverts published
1.5.2 Candidates interviewed, recruited
1.5.3 Staff salaries
1.5.4 Staff allowances
1.5.5 Operating Procedures for Secretariat
1.5.6 Training in financial management for RBN members& secretariat
RESULT 2 EFFECTIVE COMMUNICATION & PROMOTIONAL SYSTEMS
2.1 Promotional & Information materials
2.1.1 RBN eNewsletter
2.1.2 Brochures, information sheets
2.1.3 Press articles
2.1.4 Radio & TV
2.1.5 Social enetworking e.g. Utube, Facebook etc
2.2 RBN website development
2.2.1 Develop TOR, hire TA
2.2.2 Website development & training Secretariat
2.3 International meetings & events
2.3.1 Present RBN at international shows & exhibitions.
2.4 Expand international networks
2.4.1 Gain membership of international NGOs
2.5 Information flows within BMU Networks & partners
2.5.1 Compile & transmit membership details of all BMU Networks.
2.5.2 Compile & transmit details of meetings of lower BMU Networks.
2.5.3 Transmit minutes of RBN meetings, plans etc.
2.6 Mobile telephony for information systems
2.6.1 Identify uses of telephony for RBN activities
2.6.2 Set up mobile telephony pilot initiative
RESULT 3 RBN EFFECTIVE IN FISHERIES CO-MANAGEMENT
3.1 Contribute to the development, review and co-ordination of implementation of
harmonized regional fisheries plans, policies and legislation.
3.1.1 Compile regional fisheries management priorities of BMUs and propose actions.
3.1.2 Participate as a member of the LVFO regional technical advisory committees to
represent BMU views in co-management.
Training for Regional Beach Management Unit Network (RBN) in East Africa
81 Project Funded by the European Union A project implemented by (Harewelle International Limited)
3.1.3 Participate in international technical fisheries meetings.
3.1.4 Review and harmonize actions to reduce illegal fishing and fish trade.
3.2 Self-monitoring of BMU co-management performance
3.2.1 Design an annual self-monitoring & evaluation system.
3.2.2 Compile, analyse & transmit results of annual BMU self-monitoring & evaluation.
RESULT 4 EFFECTIVE RBN ADVOCACY
4.1 Development of advocacy strategy
4.1.1 Training of RBN in making advocacy strategy
4.1.2 Develop a RBN advocacy strategy
4.2 Prioritise advocacy issues
4.2.1 Lobby for completion of the demarcation and gazettement of jurisdictional areas of
BMUs and BMU Networks in each Partner State.
4.2.2 Assist government and private industry in the resolution of cross-border fisheries
conflicts.
4.2.2 In collaboration with other LVFO bodies, lobby for regional action from EAC for the
provision of health and social services for fisheries communities.
RESULT 5 BUSINESS DEVELOPMENT IMPROVED
5.1 Improve information on fisheries businesses
5.1.1 Design self-recording system of fisheries business enterprises & labour force.
5.1.2 Coordinate implementation of self-recording of numbers and types of fisheries business
enterprises & labour force.
5.2 Improve business development skills
5.2.1 Design project for business development training.
5.2.2 Training of BMU Networks in business development.
5.2.3 Fisheries businesses in BMUs analysed & improved by BDS specialists.
5.3 Improve business development options
5.3.1 Promote increased access & transparency in fish pricing.
5.3.2 Explore and exploit new business opportunities for members.
5.3.3 Promote favourable business environment at all levels of BMUs.
Training for Regional Beach Management Unit Network (RBN) in East Africa
82 Project Funded by the European Union A project implemented by (Harewelle International Limited)
MODULE 1 - SESSION 1: INFORMATION SHEET 7
DETAILED STRUCTURE OF BUDGETED STRATEGIC PLAN
Lake Victoria Regional Beach Management Unit Network Strategic Plan, July 2012 – June 2015
Ref
No
Activities Details Annual Costs ($) Self-
Funding
by RBN
Donor
Funding
Needed
Total Cost Priority
1 =
highest 2012-
2013
201-
2014
2014-
2015
1 EFFECTIVE FINANCING &
OPERATIONS
1.1 Set up self-financing by BMUs
1.1.1 Develop self-financing procedures 1 RBN 2-day meeting to
agree & make Info Sheet
for BMUs
2,500 2,500 0 2,500 1
1.1.2 Gain consensus of BMUs for
procedures & rates of pay
DBN print Info Sheets
for BMUs
0 1
1.1.3 Set up RBN financial management
procedures
1 RBN meeting; cost in
1.1.1
0 1
1.1.4 Open & run RBN bank account Bank charges 25 25 25 15 60 75 1
1.1.5 Annual external audit of RBN accts Local auditor fee: 1
audit/yr
500 500 500 300 1,200 1,500 3
1.2 Obtain donor financing
Training for Regional Beach Management Unit Network (RBN) in East Africa
83 Project Funded by the European Union A project implemented by (Harewelle International Limited)
Explanation of Columns:
Column 1: Is a unique fixed activity and budget line number which is crucial for financial accounting by the RBN. It should not be changed
once funded.
Column 2: Is the title of the activity to be completed
Column 3: Gives more details of activity to help estimate a cost
Columns 4, 5, 6: The annual costs in USD ($) of each activity
Column 7: The share of the total 3-year cost funded by the RBN members
Column 8: The share of the total 3-year cost needing external financing by government or donors
Column 9: The total 3-year cost (sum of columns 7 & 8)
Column 10: A priority rating by the RBN of the urgency of the activity, scoring 1 to 3 with 1 being highest priority
Explanation of Rows:
Blue top row: Is for the headings of the columns
Green 2nd
row Result – this is a major output – there should be only a few in any plan – not more than 6 is usual. Delivery of each Result will
ensure delivery of the purpose of the Strategic Plan.
Purple 3rd
row Activity area – a sub-heading line with no costs in it
Yellow 4th
row Activity to be implemented with costs attached where needed
Training for Regional Beach Management Unit Network (RBN) in East Africa
84 Project Funded by the European Union A project implemented by (Harewelle International Limited)
5.1.4 Reference Material
Reference materials include:
a. RBN Operating Procedures.
b. Uganda National Fisheries Policy 2004
c. Kenya Fisheries Policy 2008
d. EAIFFPA Work Plan 2009-2011
e. Lake Victoria Fisheries Management Plan 2009-2014
Training for Regional Beach Management Unit Network (RBN) in East Africa
85 Project Funded by the European Union A project implemented by (Harewelle International Limited)
5.2 Module 1- Session 2
5.2.1 Training Session Plan
Module 1 - Session 2 Date: 30th
July 2012 Duration: 3 hr
Title: Making a RBN Strategic Plan – Result 1 RBN Financing and Operations
Objectives:
Know how to make a budgeted strategic plan
Understand the actions needed to set up a RBN self-financing system by BMUs
Reach consensus on setting up a RBN office and have actions in plan as appropriate
Reach consensus of aiming to set up a permanent RBN Secretariat and have actions in
plan as appropriate
Content: Training Points Methods Time
Introduction Overview of session 15 min
Development Introduction
Present draft Result 1 Activity 1.1
Present draft Result 1 Activity 1.2 & 3
Present draft Result 1 Activity 1.4
Present draft Result 1 Activity 1.5
Projector,
information
sheets,
Plenary
Q&A,
Trainee
review &
analyses
2h 30 min
Conclusion Recap of main points, address any queries 15 min
Training materials: Projector, Information Sheets, Flip charts, Flip chart pens,
Notebooks, pens,
Evaluation: Q & A
5.2.2 Trainers Notes
Module 1 - Session 2 p.1
Trainer Trainee
Introduction (15 min)
1. Give overview of task and training aids –
projector to present SP in Ms Excel since it
has a budget. Explain that Information Sheet
provides same information as on screen (5
min).
Receive Information Sheet
Q&A
2. Set up projector to show example of
training aid. Ask group to consider how to do
TOT planning & make plans without
projector.
Explain the need to work at a rate of about 8
activity lines/hr. (10 min)
Examine projector presentation. Consider
how to do TOT & make plans at NBNs,
Q&A
Training for Regional Beach Management Unit Network (RBN) in East Africa
86 Project Funded by the European Union A project implemented by (Harewelle International Limited)
Development (2 hr 30 min)
Present Result 1: Activity Area 1.1 with 5
activities (self-financing), details for costing
and indicative cost for 3 years; cost sharing
between RBN and external sources; total cost
and prioritisation of activity.( 50 min)
In plenary, review draft details, raise queries,
make amendments, additions & deletions to
activity areas, activities, costs, cost sharing
proportions and prioritisation of each
activity.
Present Result 1: Activity Area 1.2 with 2
activities (donor funding), and Activity Area
1.3 with 4 activities (RBN meetings), details
for costing and indicative cost for 3 years;
cost sharing between RBN and external
sources; total cost and prioritisation of
activity.
Give information on vision of fisheries sector
– an EAC fisheries administration 5 countries
with South Sudan maybe the 6th
covering
marine & inland. Private sector needs to keep
pace – an EAC BMU body with national
networks and water body networks. If this is
RBN vision, we could include activity line
e.g. TA to draft private members bill for
EALA to establish & recognise Regional
BMU Network under EAC (30 min)
In plenary, review draft details, raise queries,
make amendments, additions & deletions to
activity areas, activities, costs, cost sharing
proportions and prioritisation of each
activity.
Members to consider regionalisation issue
and opportunity & reach consensus on
whether to include in Strategic Plan.
Present Result 1: Activity Area 1.4 with 2
activities (setting up a RBN office), details
for costing and indicative cost for 3 years;
cost sharing between RBN and external
sources; total cost and prioritisation of
activity. (20 min)
In plenary, review draft details, raise queries,
make amendments, additions & deletions to
activity areas, activities, costs, cost sharing
proportions and prioritisation of each
activity.
Present Result 1: Activity Area 1.5 with 6
activities (setting up a RBN Secretariat),
details for costing and indicative cost for 3
years; cost sharing between RBN and
external sources; total cost and prioritisation
of activity.
( 50 min)
In plenary, review draft details, raise queries,
make amendments, additions & deletions to
activity areas, activities, costs, cost sharing
proportions and prioritisation of each
activity.
Conclusion (15 min)
Recap of main points, address any queries Q&A
Training materials: Projector, laptop,
Information Sheets, Flip charts, Flip chart
pens; notebooks, pens
Evaluation: Confirm all are clear on topics
discussed
Q&A
5.2.3 Training Aids
Information Sheet Nos.1-3, Module 1 Session 2.
Training for Regional Beach Management Unit Network (RBN) in East Africa
87 Project Funded by the European Union A project implemented by (Harewelle International Limited)
MODULE 1 - SESSION 2: INFORMATION SHEET 1
RBN STRATEGIC PLAN: RESULT 1 - ACTIVITY AREA 1.1
Ref
No
Activities Details Annual Costs ($) Self-
Funding
by
BMUs
External
Funding
Needed
Total
Cost
($)
Priority
1 =
highest 2012-
2013
2013-
2014
2014-
2015
1 EFFECTIVE FINANCING &
OPERATIONS
1.1 Set up self-financing by BMUs
1.1.1 Develop self-financing procedures 1 RBN 2-day
meeting to agree &
make Info Sheet for
BMUs
900 900 0 900 1
1.1.2 Gain consensus of BMUs for procedures &
rates of pay
DBN print Info
Sheets for BMUs
0 1
1.1.3 Set up RBN financial management
procedures
1 RBN meeting;
cost in 1.1.1
0 1
1.1.4 Open & run RBN bank account Bank charges 25 25 25 15 60 75 1
1.1.5 Annual external audit of RBN accts Local auditor fee: 1
audit/yr
500 500 500 300 1,200 1,500 3
Training for Regional Beach Management Unit Network (RBN) in East Africa
88 Project Funded by the European Union A project implemented by (Harewelle International Limited)
MODULE 1 - SESSION 2: INFORMATION SHEET 2
RBN STRATEGIC PLAN: RESULT 1 - ACTIVITY AREAS 1.2 & 1.3
Ref
No
Activities Details Annual Costs ($) Self-
Funding
by RBN
Donor
Funding
Needed
Total
Cost
Priority
1 =
highest
1.2 Obtain donor financing
1.2.1 Develop regional project proposals &
submit to donors
Do in FISH II
training July 2012 &
later RBN meetings
0 1
1.2.2 Find possible donors & submit proposals RBN allowances for
donor meetings
600 400 300 1,300 0 1,300 1
1.3 RBN planning meetings
1.3.1 Training for RBN members in planning,
project design &advocacy
EU ACP FISH II
programme support
(grant aid)
45,000 45,000 45,000
1.3.2 Hold two progress & planning meetings a
year address key issues e.g. Network
registration & certificates, legal identity of
Networks; review Operating Procedures;
harmonise functions -Kenya 2012
2 RBN 2-day
meetings –
allowances
5,000 5,000 5,000 15,000 0 15,000 1
1.3.3 Support NBNs in making budgeted plans RBN mentor NBN
meetings: NBN funds
own meeting
0
1.3.4 Support DBNs in making budgeted plans RBN mentor DBN
meetings: DBN funds
own meeting
0
Training for Regional Beach Management Unit Network (RBN) in East Africa
89 Project Funded by the European Union A project implemented by (Harewelle International Limited)
MODULE 1 - SESSION 2: INFORMATION SHEET 3
RBN STRATEGIC PLAN: RESULT 1 - ACTIVITY AREAS 1.4 & 1.5
Ref
No
Activities Details Annual Costs ($) Self-
Funding
by RBN
Donor
Funding
Needed
Total
Cost
Priority
1 =
highest 2012-
2013
201-
2014
2014-
2015
1.4 RBN office established
1.4.1 Office location agreed, equipped &
opened
Rent, services &
equipment
25,000 25,000 25,000 15,000 60,000 75,000 2
1.4.2 Office operations Stationary,
consumables
3,000 3,500 4,000 2,100 8,400 10,500 2
1.5 RBN Secretariat established
1.5.1 Job descriptions made, job adverts
published
Adverts in 3 national
press
1,000 200 800 1,000 2
1.5.2 Candidates interviewed, recruited 1 day meeting of RBN
for interviews
2,000 400 1,600 2,000 2
1.5.3 Staff salaries 2 staff members 18,000 37,000 38,000 18,600 74,400 93,000 2
1.5.4 Staff allowances Travel & subsistence 2,000 5,000 6,000 2,600 10,400 13,000 2
1.5.5 Operating Procedures developed for
Secretariat
RBN meetings funded
in 1.3.2
0 2
1.5.6 Develop project proposal & hire firm for
training in financial management for
RBN & its Secretariat
Local consultancy 10,000 2,000 8,000 10,000 2
Training for Regional Beach Management Unit Network (RBN) in East Africa
90 Project Funded by the European Union A project implemented by (Harewelle International Limited)
5.2.4 Reference Material
No additional reference material is needed for this session.
Training for Regional Beach Management Unit Network (RBN) in East Africa
91 Project Funded by the European Union A project implemented by (Harewelle International Limited)
5.3 End of Day Evaluation of Training
The following questionnaire was distributed to each RBN trainee at the end of each day‘s
training rather than leaving until the end of the course when members may not be able to
recall easily specific sessions. All RBN were asked to complete the form since there were
only 9 of them. It can be given to a group for them to discuss together and record their
collective views if literacy is an issue and where large numbers of trainees are involved.
END OF DAY TRAINING EVALUATION FORM
PLEASE MARK YOUR RESPONSE TO EACH QUESTION BY CIRCLING YOUR
ANSWER
1. Overall, did you find the course to be useful?
Yes No
Comments:
2. Was the course approach flexible enough to take account of your needs?
Yes No
Comments:
3. Did the course fulfil your expectations?
Yes No
Comments:
4. Was the course length:
Too short Just right Too long
Training for Regional Beach Management Unit Network (RBN) in East Africa
92 Project Funded by the European Union A project implemented by (Harewelle International Limited)
Comments:
5. Was the structure of the course logical and clear (timetable)?
Yes No
Comments:
6. Was the rate of delivery of the training course:
Too fast Just right Too slow
Comments:
7. How was the balance between practical exercises and theory?
Too much practical Good mix Too much theory
Comments:
8. How easy was it to understand the trainers?
Very easy Easy Difficult
Comments:
9. What did you think of the quality of the training aids?
Very good Good Poor
Comments:
10. How did you rate the different sections of the course?
Training for Regional Beach Management Unit Network (RBN) in East Africa
93 Project Funded by the European Union A project implemented by (Harewelle International Limited)
(Please circle the appropriate number)
Not Useful Partially
Useful
Useful More
than
Useful
Very
Useful
1. Module 1 Session 1:
Strategic Planning
1 2 3 4 5
2. Module 1 Session 2:
Strategic Plan - Result 1
1 2 3 4 5
1 2 3 4 5
1 2 3 4 5
1 2 3 4 5
(N.B. Trainer inserts session titles in this list before distributing to participants)
Comments:
11. Will the training help you to develop new working practices?
Yes No
Comments:
12. What do you feel has been the main benefit to you from this course? (Please mark only
one)
No benefit Sharing ideas with fellow trainees during training
Improved understanding of subject Receiving training materials
Improved skills in subject Change attitude towards subject
Comments:
14. Have you any other comments or suggestions about the training?
Training for Regional Beach Management Unit Network (RBN) in East Africa
94 Project Funded by the European Union A project implemented by (Harewelle International Limited)
5.4 Module 1- Session 3
5.4.1 Training Session Plan
Module 1 - Session 3 Date: 31st July 2012 Duration: 1 hr
Title: Making a RBN Strategic Plan – Result 3 RBN Effective in Fisheries Co-
Management
Objectives:
Understand how the adopted RBN functions relate to activities under fisheries co-
management
Agree that gathering key management issues from BMUs is vital and can be done using
Networks
Understand the importance of participating regularly in LFVO FMC & SC meetings
Understand the importance of self-monitoring of BMUs using most cost-effective
methods
Accept the need for a unified stand against fisheries illegalities and have agreed planned
actions
Content: Training Points Methods Time
Introduction Overview of session 10 min
Development Introduction
Present draft Result 3 Activity 3.1
Present draft Result 3 Activity 3.2
Projector,
information
sheets,
Plenary
Q&A,
Trainee
review &
analyses
45 min
Conclusion Recap of main points, address any queries Q&A 5 min
Training materials: Projector, laptop, Information Sheets, Flip charts, Flip chart
pens; notebooks, pens
Evaluation: Q & A
5.4.2 Trainers Notes
Opening Session p.1
Trainer Trainee
Introduction (10 min)
Overview of session; explain why covering
Result 3 before 2 – time available to finish.
Q&A
Development (45 min)
Present Result 3: Activity Area 3.1 with 4
activities (FMC meeting, influence policies,
In plenary, review draft details, raise queries,
make amendments, additions & deletions to
Training for Regional Beach Management Unit Network (RBN) in East Africa
95 Project Funded by the European Union A project implemented by (Harewelle International Limited)
laws; international meetings; BMU priorities,
illegalities), details for costing and indicative
cost for 3 years; cost sharing between RBN
and external sources; total cost and
prioritisation of activity.
activity areas, activities, costs, cost sharing
proportions and prioritisation of each
activity.
Present Result 3: Activity Area 3.2 with 2
activities (BMU self- monitoring), details for
costing and indicative cost for 3 years; cost
sharing between RBN and external sources;
total cost and prioritisation of activity.
In plenary, review draft details, raise queries,
make amendments, additions & deletions to
activity areas, activities, costs, cost sharing
proportions and prioritisation of each
activity.
Conclusion (5 min)
Recap of main points, address any queries Q&A
Training materials: Projector, laptop,
Information Sheets, Flip charts, Flip chart
pens; notebooks, pens
Evaluation: Confirm all are clear on topics
discussed
Q&A
5.4.3 Training Aids
Information Sheet No.1, Module 1 Session 3.
Training for Regional Beach Management Unit Network (RBN) in East Africa
96 Project Funded by the European Union A project implemented by (Harewelle International Limited)
MODULE 1 - SESSION 3: INFORMATION SHEET 1
RBN STRATEGIC PLAN: RESULT 2 - ACTIVITY AREAS 3.1 & 3.2
Ref
No
Activities Details Annual Costs ($) Self-
Funding
by RBN
Donor
Funding
Needed
Total
Cost
Priority
1 =
highest 2012-
2013
2013-
2014
2014-
2015
3 RBN EFFECTIVE IN FISHERIES
CO-MANAGEMENT
3.1 Co-ordinated & harmonized regional
fisheries policies, legislation
guidelines and plans
3.1.1 Compile regional fisheries management
priorities of BMUs and propose actions.
RBN meetings funded in
1.3.2
0
3.1.2 Participate as a member of the LVFO
regional technical advisory committees
to represent BMU views in co-
management.
Allowances & travel costs for
1 RBN member twice/yr
200 200 200 600 0 600
3.1.3 Participate in international technical
fisheries meetings.
Allowances & travel costs for
RBN members twice/yr
400 500 600 300 1,200 1,500
3.1.4 Review and harmonize actions to
reduce illegal fishing and fish trade.
Allowances & travel costs for
RBN members actions
300 400 500 240 960 1,200
3.2 Self-monitoring of BMU co-
management performance
3.2.1 Design and agree an annual self-
monitoring & evaluation system.
RBN meetings funded in
1.3.2; other Networks bear
own costs
0
3.2.2 Compile, analyse & transmit results of
annual BMU self-monitoring &
evaluation.
Printing & copying costs of
minutes, electronically
thereafter
100 0 0 100 0 100
Training for Regional Beach Management Unit Network (RBN) in East Africa
97 Project Funded by the European Union A project implemented by (Harewelle International Limited)
5.4.4 Reference Material
No additional reference material is needed for this session.
Training for Regional Beach Management Unit Network (RBN) in East Africa
98 Project Funded by the European Union A project implemented by (Harewelle International Limited)
5.5 Module 1- Session 4
5.5.1 Training Session Plan
Module 1 - Session 4 Date: 31st July 2012 Duration: 2hr 15 mins
Title: Making a RBN Strategic Plan – Result 2 Effective Communication & Promotional
Systems
Objectives:
Appreciate the need to raise profile & image of the RBN
Know how to go about raising profile & image
Appreciate the urgency of networking at international level
Acknowledge the potential value in mobile phones to facilitate information flow
Agree to be involved in information collection of BNU Networks
Content: Training Points Methods Time
Introduction Overview of session 10 min
Development Introduction
Present draft Result 2 Activity 2.1 and 2.2
Present draft Result 2 Activity 2.3 and 2.4
Present draft Result 2 Activity 2.5 and 2.6
Projector,
information
sheets,
Plenary
Q&A,
Trainee
review &
analyses
1 hr 55 min
Conclusion Recap of main points, address any queries Q&A 10 min
Training materials: Projector, laptop, Information Sheets, Flip charts, Flip chart
pens; notebooks, pens
Evaluation: Q & A
5.5.2 Trainers Notes
Opening Session p.1
Trainer Trainee
Introduction (10 min)
Overview of topic & its importance Q&A
Development (2 hr)
Present Result 2: Activity Area 2.1 and 2.2
with 5 and 2 activities respectively, details
for costing and indicative cost for 3 years;
cost sharing between RBN and external
sources; total cost and prioritisation of
activity.
In plenary, review draft details, raise queries,
make amendments, additions & deletions to
activity areas, activities, costs, cost sharing
proportions and prioritisation of each activity.
Present Result 2: Activity Area 2.3 and 2.4
with 1 activity each (BMU self- monitoring),
In plenary, review draft details, raise queries,
make amendments, additions & deletions to
Training for Regional Beach Management Unit Network (RBN) in East Africa
99 Project Funded by the European Union A project implemented by (Harewelle International Limited)
details for costing and indicative cost for 3
years; cost sharing between RBN and
external sources; total cost and prioritisation
of activity.
activity areas, activities, costs, cost sharing
proportions and prioritisation of each activity.
Present Result 3: Activity Area 2.5 with 3
activities and Activity Area 2.6 with 2
activities, details for costing and indicative
cost for 3 years; cost sharing between RBN
and external sources; total cost and
prioritisation of activity.
In plenary, review draft details, raise queries,
make amendments, additions & deletions to
activity areas, activities, costs, cost sharing
proportions and prioritisation of each activity.
Conclusion (5 min)
Recap of main points, address any queries Q&A
Training materials: Projector, laptop,
Information Sheets, Flip charts, Flip chart
pens; notebooks, pens
Evaluation: Confirm all are clear on topics
discussed
Q&A
5.5.3 Training Aids
Information Sheet Nos.1 and 2, Module 1 Session 4.
Training for Regional Beach Management Unit Network (RBN) in East Africa
100 Project Funded by the European Union A project implemented by (Harewelle International Limited)
MODULE 1 - SESSION 4: INFORMATION SHEET 1
RBN STRATEGIC PLAN: RESULT 2 - ACTIVITY AREAS 2.1 & 2.2
Ref
No
Activities Details Annual Costs ($) Self-
Funding
by RBN
Donor
Funding
Needed
Total
Cost
Priority
1 =
highest 2012-
2013
2013-
2014
2014-
2015
2 EFFECTIVE COMMUNICATION
& PROMOTIONAL SYSTEMS
2.1 Promotional & Information
materials
2.1.1 RBN electronic Newsletter RBN produce
Newsletter printed by
DBNs for each BMU
0 2
2.1.2 Brochures, information sheets Design & print costs 1,000 1,000 1,000 600 2,400 3,000 1
2.1.3 Press articles Make headlines without
costs
0 1
2.1.4 Radio & TV Make headlines without
costs
0
2.1.5 Electronic social networking e.g.
Utube, Facebook etc
0
2.2 RBN website development
2.2.1 Develop project proposal/TOR,
identify website developers, hire firm
Project proposal made
at RBN training 2012
0 1
2.2.2 Website development & training
Secretariat
RBN website design
costs & annual charges
10,000 1,000 1,000 2,400 9,600 12,000 2
Training for Regional Beach Management Unit Network (RBN) in East Africa
101 Project Funded by the European Union A project implemented by (Harewelle International Limited)
MODULE 1 - SESSION 4: INFORMATION SHEET 2
RBN STRATEGIC PLAN: RESULT 2 - ACTIVITY AREAS 2.3 - 2.6
Ref
No
Activities Details Annual Costs ($) Self-
Funding
by RBN
Donor
Funding
Needed
Total
Cost
Priority
1 =
highest 2012-
2013
2013-
2014
2014-
2015
2.3 International meetings & events
2.3.1 Promote RBN at international shows &
exhibitions.
Allowances & travel costs,
promotional materials
500 800 1,000 460 1,840 2,300 1
2.4 Expand international networks
2.4.1 Gain membership of international NGOs Membership fees 250 350 400 1,000 0 1,000 1
2.5 Information flows within BMU
Networks & partners
2.5.1 Compile & transmit membership details of
all BMU Networks.
Typing registers in 1st
year only, electronically
thereafter
50 0 0 50 0 50
2.5.2 Compile & transmit details of meetings of
lower BMU Networks.
Typing work in 1st year
only, electronically
thereafter
50 0 0 50 0 50
2.5.3 Transmit minutes of RBN meetings, plans
etc.
Printing & copying costs
of minutes, electronically
thereafter
100 0 0 100 0 100
2.6 Mobile telephony for information
systems
2.6.1 Identify uses of telephony for RBN
activities
Design TOR, hire
consultant
0 7,000 0 1,400 5,600 7,000
2.6.2 Set up mobile telephony pilot initiatives Various implementation
costs
0 5,000 10,000 3,000 12,000 15,000
Training for Regional Beach Management Unit Network (RBN) in East Africa
102 Project Funded by the European Union A project implemented by (Harewelle International Limited)
5.5.4 Reference Material
No additional reference material is needed for this session.
Training for Regional Beach Management Unit Network (RBN) in East Africa
103 Project Funded by the European Union A project implemented by (Harewelle International Limited)
5.6 Module 1- Session 5
5.6.1 Training Session Plan
Module 1 - Session 5 Date: 31st July 2012 Duration: 1hr 15 mins
Title: Making a RBN Strategic Plan – Result 4 Effective RBN Advocacy
Objectives:
Know how to go about advocacy in a systematic way
Agree priority advocacy issues for the RBN in 2012 and include in plan
Content: Training Points Methods Time
Introduction Overview of session 10 min
Development Introduction
Present draft Result 4 Activity 4.1
Present draft Result 4 Activity 4.2
Projector,
information
sheets,
Plenary
Q&A,
Trainee
review &
analyses
60 min
Conclusion Recap of main points, address any queries Q&A 5 min
Training materials: Projector, laptop, Information Sheets, Flip charts, Flip chart
pens; notebooks, pens
Evaluation: Q & A
5.6.2 Trainers Notes
Opening Session p.1
Trainer Trainee
Introduction (15 min)
Overview of session, explain that this session
will be better completed once the advocacy is
done and that the advocacy issues will be
prioritise in during the latter training and
incorporated with costs into the plan at that
stage. This gives some time-saving if needed.
Q&A, discuss and reach consensus on
suggestion to timetable.
Development (45 min)
Present Result 4: Activity Area 4.1with 2
activities, details for costing and indicative
cost for 3 years; cost sharing between RBN
and external sources; total cost and
prioritisation of activity.
In plenary, review draft details, raise queries,
make amendments, additions & deletions to
activity areas, activities, costs, cost sharing
proportions and prioritisation of each
activity.
Present Result 4: Activity Area 4.2 with 3
activities, details for costing and indicative
cost for 3 years; cost sharing between RBN
and external sources; total cost and
In plenary, review draft details, raise queries,
make amendments, additions & deletions to
activity areas, activities, costs, cost sharing
proportions and prioritisation of each
Training for Regional Beach Management Unit Network (RBN) in East Africa
104 Project Funded by the European Union A project implemented by (Harewelle International Limited)
prioritisation of activity. activity.
Conclusion (5 min)
Recap of main points, address any queries Q&A
Training materials: Projector, laptop,
Information Sheets, Flip charts, Flip chart
pens; notebooks, pens
Evaluation: Confirm all are clear on topics
discussed
Q&A
5.6.3 Training Aids
Information Sheet No.1, Module 1 Session 5.
Training for Regional Beach Management Unit Network (RBN) in East Africa
105 Project Funded by the European Union A project implemented by (Harewelle International Limited)
MODULE 1 - SESSION 5: INFORMATION SHEET 1
RBN STRATEGIC PLAN: RESULT 4 - ACTIVITY AREAS 4.1 & 4.2
Ref
No
Activities Details Annual Costs ($) Self-
Funding
by RBN
Donor
Funding
Needed
Total
Cost
Priority
1 =
highest 2012-
2013
2013-
2014
2014-
2015
4.1 Development of advocacy strategy
4.1.1 Training of RBN in making advocacy
strategy
Funded in 1.3.1 0
4.1.2 Develop a RBN advocacy strategy Funded in 1.3.1 0
4.1.3 RBN members guide their own NBNs in
making budgeted plans
RBN members mentor at
NBN meetings: NBN funds
own meeting
0
4.1.4 RBN members guide their own DBNs in
making budgeted plans
RBN members mentor at
DBN meetings: DBN funds
own meeting
0
4.2 Prioritise advocacy issues
4.2.1 Lobby for completion of the demarcation
and gazettement of jurisdictional areas of
BMUs and BMU Networks in each
Partner State.
TO BE AGREED IN
ADVOCACY
STRATEGY
0
4.2.2 Assist government and private industry in
the resolution of cross-border fisheries
conflicts.
TO BE AGREED IN
ADVOCACY
STRATEGY
0
4.2.3 In collaboration with other LVFO bodies,
lobby for regional action from EAC for
the provision of health and social services
for fisheries communities.
TO BE AGREED IN
ADVOCACY
STRATEGY
0
Training for Regional Beach Management Unit Network (RBN) in East Africa
106 Project Funded by the European Union A project implemented by (Harewelle International Limited)
5.6.4 Reference Material
No additional reference material is needed for this session.
Training for Regional Beach Management Unit Network (RBN) in East Africa
107 Project Funded by the European Union A project implemented by (Harewelle International Limited)
5.7 Module 1- Session 6
5.7.1 Training Session Plan
Module 1 - Session 6 Date: 31st July 2012 Duration: 1hr 15 mins
Title: Making a RBN Strategic Plan – Result 5 Effective Business Development
Objectives:
Appreciate the importance of emphasizing and incorporating this Result in the Strategic
Plan
Understand the importance of having baseline data on fisheries SMEs and agree to work
on compiling data
Agree that systematic and extensive business development training for fisheries SMEs
and Networks is a priority.
Content: Training Points Methods Time
Introduction Overview of session 10 min
Development Introduction
Present draft Result 5 Activity 5.1
Present draft Result 5 Activity 5.2
Present draft Result 5 Activity 5.3
Projector,
information
sheets,
Plenary
Q&A,
Trainee
review &
analyses
60 min
Conclusion Recap of main points, address any queries Q&A 5 min
Training materials: Projector, laptop, Information Sheets, Flip charts, Flip chart
pens; notebooks, pens
Evaluation: Q & A
5.7.2 Trainers Notes
Opening Session p.1
Trainer Trainee
Introduction (15 min)
Overview & background covering
importance in business development
approach to the RBN
Q&A
Development (55 min)
Present Result 5: Activity Area 5.1with 2
activities, details for costing and indicative
cost for 3 years; cost sharing between RBN
and external sources; total cost and
prioritisation of activity.
In plenary, review draft details, raise queries,
make amendments, additions & deletions to
activity areas, activities, costs, cost sharing
proportions and prioritisation of each
activity.
Present Result 5: Activity Area 5.2 with 3
activities, details for costing and indicative
cost for 3 years; cost sharing between RBN
In plenary, review draft details, raise queries,
make amendments, additions & deletions to
activity areas, activities, costs, cost sharing
Training for Regional Beach Management Unit Network (RBN) in East Africa
108 Project Funded by the European Union A project implemented by (Harewelle International Limited)
and external sources; total cost and
prioritisation of activity.
proportions and prioritisation of each
activity.
Present Result 5: Activity Area 5.3 with 3
activities, details for costing and indicative
cost for 3 years; cost sharing between RBN
and external sources; total cost and
prioritisation of activity.
In plenary, review draft details, raise queries,
make amendments, additions & deletions to
activity areas, activities, costs, cost sharing
proportions and prioritisation of each
activity.
Conclusion (5 min)
Recap of main points, address any queries Q&A
Training materials: Projector, laptop,
Information Sheets, Flip charts, Flip chart
pens; notebooks, pens
Evaluation: Confirm all are clear on topics
discussed
Q&A
5.7.3 Training Aids
Information Sheet No.1, Module 1 Session 6.
Training for Regional Beach Management Unit Network (RBN) in East Africa
109 Project Funded by the European Union A project implemented by (Harewelle International Limited)
MODULE 1 - SESSION 6: INFORMATION SHEET 1
RBN STRATEGIC PLAN: RESULT 5 - ACTIVITY AREAS 5.1 & 5.2
Ref
No
Activities Details Annual Costs ($) Self-
Funding
by RBN
Donor
Funding
Needed
Total
Cost
Priority
1 =
highest 2012-2013 2013-
2014
2014-
2015
5 BUSINESS DEVELOPMENT IMPROVED
5.1 Improve information on fisheries
businesses
5.1.1 Design self-recording system of fisheries
business enterprises & labour force.
Funded in 1.3.2 0
5.1.2 Coordinate implementation of self-recording
of numbers and types of fisheries business
enterprises & labour force.
RBN members mentor at
NBN & DBN meetings:
NBN & DBN fund own
meeting
0
5.2 Improve business development skills
5.2.1 Design project for business development
training.
Funded in 1.3.1 0
5.2.2 Training of BMU Networks in business
development.
Training services hired 0 70,000 70,000 0 140,000 140,000
5.2.3 Fisheries businesses in BMUs analysed &
improved by BDS specialists.
BDS services hired 0 30,000 30,000 0 60,000 60,000
5.3 Improve business development options
5.3.1 Promote favourable business environment for
SMEs & increased transparency and access to
fish prices at all levels in market chains.
Various implementation
costs
1,000 2,000 3,000 1,200 4,800 6,000
5.3.2 Explore and exploit new business
opportunities at all points in value chain for
members.
Various implementation
costs
1,000 2,000 3,000 1,200 4,800 6,000
Training for Regional Beach Management Unit Network (RBN) in East Africa
110 Project Funded by the European Union A project implemented by (Harewelle International Limited)
5.7.4 Reference Material
No additional reference material is needed for this session.
Training for Regional Beach Management Unit Network (RBN) in East Africa
111 Project Funded by the European Union A project implemented by (Harewelle International Limited)
5.8 End of Day Evaluation of Training
The methodology described in Section 5.3 was applied at the end of day 2 of the course (see
Section 5.3 for evaluation form template)
Training for Regional Beach Management Unit Network (RBN) in East Africa
112 Project Funded by the European Union A project implemented by (Harewelle International Limited)
5.9 Module 1- Session 7
5.9.1 Training Session Plan
Module 1 - Session 7 Date: 1st August 2012 Duration: 3hr 15 mins
Title: Making a RBN Strategic Plan Logical Framework (logframe)
Objectives:
Know what a logframe is and why it is needed
Understand the importance of monitoring performance of plan implementation
Understand why it is a ―logical‖ framework i.e. relationships between activities, result
and purpose
Understand what an OVI is and how it is used to monitor performance
Understand how information/data forming the basis of an OVI is obtained
Content: Training Points Methods Time
Introduction Overview of session 10 min
Development Introduction
Present draft Goal & Purpose in logframe
Present draft Result 1 in logframe
Present draft Result 2 in logframe
Present draft Result 3 in logframe
Present draft Result 4 in logframe
Present draft Result 5 in logframe
Projector,
information
sheets,
Plenary
Q&A,
Trainee
review &
analyses
2h 55 min
Conclusion Recap of main points, address any queries Q&A 10 min
Training materials: Projector, laptop, Information Sheets, Flip charts, Flip chart
pens; notebooks, pens
Evaluation: Q & A
5.9.2 Trainers Notes
Opening Session p.1
Trainer Trainee
Introduction (15 min)
Overview of logframe use for monitoring; its structure and linkages between different levels
Q&A
Development (2hr 50 min)
Importance of monitoring to an organisation
Training for Regional Beach Management Unit Network (RBN) in East Africa
113 Project Funded by the European Union A project implemented by (Harewelle International Limited)
Present draft Goal & Purpose in logframe.
Present and explain each objectively
verifiable indicator (OVI) and its verification
sources and assumptions. (30 min)
In plenary, review draft details, raise queries,
make amendments, additions & deletions to
OVIs, verification sources and assumptions
Present draft Result 1 in logframe.
Present and explain each objectively
verifiable indicator (OVI) and its verification
sources and assumptions. (30 min)
In plenary, review draft details, raise queries,
make amendments, additions & deletions to
OVIs, verification sources and assumptions
Present draft Result 2 in logframe.
Present and explain each objectively
verifiable indicator (OVI) and its verification
sources and assumptions. (40 min)
In plenary, review draft details, raise queries,
make amendments, additions & deletions to
OVIs, verification sources and assumptions
Present draft Result 3 in logframe.
Present and explain each objectively
verifiable indicator (OVI) and its verification
sources and assumptions. (25 min)
In plenary, review draft details, raise queries,
make amendments, additions & deletions to
OVIs, verification sources and assumptions
Present draft Result 4 in logframe.
Present and explain each objectively
verifiable indicator (OVI) and its verification
sources and assumptions. (25 min)
In plenary, review draft details, raise queries,
make amendments, additions & deletions to
OVIs, verification sources and assumptions
Present draft Result 5 in logframe.
Present and explain each objectively
verifiable indicator (OVI) and its verification
sources and assumptions. (20 min)
In plenary, review draft details, raise queries,
make amendments, additions & deletions to
OVIs, verification sources and assumptions
Conclusion (10 min)
Recap of main points, address any queries Q&A
Training materials: Projector, laptop,
Information Sheets, Flip charts, Flip chart
pens; notebooks, pens
Evaluation: Confirm all are clear on topics
discussed
Q&A
5.9.3 Training Aids
Information Sheet Nos 1-6, Module 1 Session 7.
Training for Regional Beach Management Unit Network (RBN) in East Africa
114 Project Funded by the European Union A project implemented by (Harewelle International Limited)
MODULE 1 - SESSION 7: INFORMATION SHEET 1
RBN STRATEGIC PLAN: LOGICAL FRAMEWORK - GOAL AND PURPOSE
NARRATIVE OBJECTIVELY VERIFIABLE
INDICATORS VERIFICATION SOURCES ASSUMPTIONS
GOAL Contribute to the fisheries
sector‘s role in sustainable
economic growth, poverty
reduction and improved
livelihoods in Kenya,
Tanzania and Uganda
PURPOSE
Co-ordinate, represent
and strengthen the
interests and actions of
BMU members and their
Network in the
sustainable production
and marketing of high
quality fish products
from well co-managed
fisheries compliant with
national and international
standards and laws.
P1. Percentage of BMUs scoring the RBN
level of satisfactory delivery of services to
members increases each year.
P1. BMU Network Annual Action Plans
developed and linked at all levels by end of
June each year.
P3. Nile perch stock does not decrease
during 2012 to end of June 2015.
P4. Profitability of small fisheries
businesses increase annually.
P1. NBN & RBN Self-
Monitoring Inspection
Reports; Minutes of RBN
meetings
P2. Minutes of RBN meetings
P.3 LVFO Fisheries Acoustic
Survey reports
P4. Inspection Reports;
Minutes of NBN & RBN
meetings
1. International market
influences outside the region
do not undermine sustainable
harvesting of fish resources or
the operation of fisheries
businesses.
2. Environmental influences
do not reduce or damage fish
stocks.
Training for Regional Beach Management Unit Network (RBN) in East Africa
115 Project Funded by the European Union A project implemented by (Harewelle International Limited)
MODULE 1 - SESSION 7: INFORMATION SHEET 2
RBN STRATEGIC PLAN: LOGICAL FRAMEWORK - RESULT 1
NARRATIVE OBJECTIVELY VERIFIABLE
INDICATORS
VERIFICATION SOURCES ASSUMPTIONS
RESULT 1
Effective RBN
financing & operations
1.1 At least one RBN meeting held each
year is financed by BMUs.
1.2 RBN Annual budgeted work plans
developed each year.
1.3 One RBN grant funded project proposal
financed by donors to establish RBN office
by end of June 2013.
1.4 At least 1 RBN Secretariat staff
recruited by end of June 2013.
1.1 Minutes of RBN meetings
1.2 Minutes of RBN meetings
1.3 Minutes of RBN meetings
1.4 Minutes of RBN meetings
1.1 BMUs willing to pay for
BMU Network meetings and
activities.
1.2 Donors willing to finance
RBN Secretariat office and
staff.
Training for Regional Beach Management Unit Network (RBN) in East Africa
116 Project Funded by the European Union A project implemented by (Harewelle International Limited)
MODULE 1 - SESSION 7: INFORMATION SHEET 3
RBN STRATEGIC PLAN: LOGICAL FRAMEWORK - RESULT 2
NARRATIVE OBJECTIVELY VERIFIABLE
INDICATORS
VERIFICATION SOURCES ASSUMPTIONS
RESULT 2 Effective
communication &
promotional systems
2.1 At least one example of RBN promotional
materials (brochures, information sheet;
posters, press article) produced each year.
2.2 Full BMU Networks register held by RBN
by end of 2012
2.3 RBN website developed by end of Dec
2013 and updated at least at quarterly intervals.
2.4 RBN presentation in at least 1 international
promotional event per year.
2.5 RBN obtains membership of at least one
international fisheries NGO by end of Dec
2012.
2.6 RBN Newsletter produced twice per year.
2.7 One regional telephony information system
piloted by end of June 2014.
2.1 RBN promotion material
2.2 BMU Networks Registers
2.3 RBN website
2.4 Minutes of RBN meetings
2.5 Minutes of RBN meetings
2.6 RBN Newsletter
2.7 Minutes of RBN meetings
2.1 BMU Network
members committed to
sharing information.
2.2 Donors interested in
supporting development of
RBN website.
Training for Regional Beach Management Unit Network (RBN) in East Africa
117 Project Funded by the European Union A project implemented by (Harewelle International Limited)
MODULE 1 - SESSION 7: INFORMATION SHEET 4
RBN STRATEGIC PLAN: LOGICAL FRAMEWORK - RESULT 3
NARRATIVE OBJECTIVELY VERIFIABLE
INDICATORS
VERIFICATION SOURCES ASSUMPTIONS
RESULT 3
RBN effective in
fisheries co-
management
3.1 Numbers of illegal beach seines
recorded in each of 3 National Fisheries
Frame Surveys in 2014 decrease from
previous levels.
3.2 Numbers of illegal monofilament nets
recorded in each of 3 National Fisheries
Frame Surveys in 2014 decrease from
previous levels.
3.3 RBN participates as a member in LVFO
Fisheries Management & Scientific
Committees meetings held each year from
2012 to 2015.
3.4 The % of BMUs scoring satisfactory
performance levels increases each year.
3.1 National & regional Frame
Survey Reports 2012
3.2 National & regional Frame
Survey Reports 2012
3.3 Minutes of RBN meetings
3.4 NBN & RBN Self-
Monitoring Inspection Reports
3.1 BMUs willing to comply
with fisheries regulations.
3.2 There is continued
commitment by EAIFFPA
members to comply with
fisheries regulations.
3.3 There is high level
political will and action to
reduce illegal regional &
domestic fish trading &
fishing.
3.4 LVFO holds regional
technical advisory meetings at
its statutory interval of twice
per year.
Training for Regional Beach Management Unit Network (RBN) in East Africa
118 Project Funded by the European Union A project implemented by (Harewelle International Limited)
MODULE 1 - SESSION 7: INFORMATION SHEET 5
RBN STRATEGIC PLAN: LOGICAL FRAMEWORK - RESULT 4
NARRATIVE OBJECTIVELY VERIFIABLE
INDICATORS
VERIFICATION SOURCES ASSUMPTIONS
RESULT 4
Effective RBN advocacy
4.1 RBN Advocacy Strategy developed and
accepted by all members by end of 2012.
4.2 At least one key enabling regional
fisheries policy or strategy influenced by
RBN each year.
4.3 Harmonisation of at least one fisheries
legislation influenced by RBN each year.
4.4 Harmonisation of at least one guideline
influenced by RBN each year.
4.1 RBN Minutes of meetings
4.2 RBN Minutes of meetings
4.3 RBN Minutes of meetings
4.4 RBN Minutes of meetings
6.1 Governments committed
to participatory development
of policies, legislation and
plans
6.2 RBN Members
sufficiently motivated to
lobby persistently on behalf of
their members
Training for Regional Beach Management Unit Network (RBN) in East Africa
119 Project Funded by the European Union A project implemented by (Harewelle International Limited)
MODULE 1 - SESSION 7: INFORMATION SHEET 6
RBN STRATEGIC PLAN: LOGICAL FRAMEWORK - RESULT 5
NARRATIVE OBJECTIVELY VERIFIABLE
INDICATORS
VERIFICATION SOURCES ASSUMPTIONS
RESULT 5
Business development
improved
5.1 List of all fisheries SMEs on Lake
Victoria registered by BMUs by end of June
2013.
5.2 100% of BMU Networks receive
training in business development and
operation by end of June 2014.
5.3 At least 20 fisheries SMEs in each
Partner State receive expert business
analysis and advice by end of June 2014.
5.1 BMU Registers; NBN &
RBN minutes of meetings
5.2 Consultancy reports; NBN
& RBN minutes of meetings
5.3 Consultancy reports; NBN
& RBN minutes of meetings
5.1 Donors interested in
technically supporting BMUs
and BMU Networks
Training for Regional Beach Management Unit Network (RBN) in East Africa
120 Project Funded by the European Union A project implemented by (Harewelle International Limited)
MODULE 1 - SESSION 7: INFORMATION SHEET 7
RBN STRATEGIC PLAN: LOGICAL FRAMEWORK - OVI SCORING
The approach adopted for monitoring the RBN Strategic Plan is based on a Logical
Framework (logframe). The logframe provides a summary of the overall programme design
and a framework for project planning and monitoring.
A simple method was adopted using logical framework indicators in a semi-quantitative
manner to provide a tool for continuous monitoring of progress and impacts. The method has
been successfully tried and tested for four years under the EU funded IFMP project on Lake
Victoria and in an earlier 5-year Integrated Lake Management (ILM) project in Uganda.
The method involves self-scoring of progress made on achieving each Objectively Verifiable
Indicator (OVI). The scoring system has 6 levels of:
1 = completely achieved
2 = largely achieved
3 = partially achieved
4 = achieved only to very limited extent
5 = unlikely to be realised
X = too early to judge extent of achievement
The logframe for the Strategic Plan contains OVIs and their Means of Verification (MOVs)
which identify the sources of information to measure and score each OVI. The logframe also
identifies key risks and assumptions in implementing each Result area of the plan. The
logframe will form the basis of all work planning undertaken as part of plan implementation.
The self-scoring of indicators should be used as part of routine review of progress and
planning future activities. Justification for any change in scoring of indicators will help
provide regular detailed monitoring of plan activities closely aligned to achieving the purpose
of the Strategic Plan.
5.9.4 Reference Material
No reference material included for this session.
Training for Regional Beach Management Unit Network (RBN) in East Africa
121 Project Funded by the European Union A project implemented by (Harewelle International Limited)
6. TRAINING ON ADVOCACY
6.1 Module 2- Session 1
6.1.1 Training Session Plan
Module 2 – Session 1 Date: 1st Aug 2012 Duration: 3 hr
Title: Improving RBN advocacy skills
Objectives:
Appreciate more fully that an advocacy role is one of the main reasons for having a RBN
Have a better understanding of how to take a more systematic, planned approach to
advocacy.
Training Points Methods Time
Introduction Overview of session Q&A 15 min
Development Introduction
Background
Advocacy process & tips
Advocacy analysis
Advocacy issues
Plenary
discussion,
individual
responses/views
on cards, sub-
group work;
Members
facilitate
Q&A
2h 35
min
Conclusion Recap of main points, address any queries Q&A 10 min
Training materials: Projector, Information Sheets, Flip charts, Flip chart pens,
Cards, notebooks, pens.
Evaluation: Q & A
6.1.2 Trainers Notes
Opening Session p.1
Trainer Trainee
Introduction (15min)
Overview of topics covered and how the
session will run
Receive overview, comment on proposed
running of session.
Q&A
Development (2h 35 min)
Training for Regional Beach Management Unit Network (RBN) in East Africa
122 Project Funded by the European Union A project implemented by (Harewelle International Limited)
Background
Ask members what advocacy means to them
– prompt each person to give one response
only; list on flip chart and synthesise.
Compare responses with Information Sheet 1.
Conclude on wide scope of advocacy aims.
Stress importance of focussing on advocacy
related to RBN issues.
(15 min)
Q&A
Give one example each and try to give
different answers
Examine Information Sheet 1 and compare
with members responses & comment.
Background
Ask members to give one example only of
their involvement in advocacy – preferably
fisheries related but other sectors can be
used. Don‘t give any guidance yet on a
framework to describe their advocacy
activities. Use cards to collect replies.
Summarise cards on a flip chart, synthesise
and present conclusions
– look for what isn‘t advocacy
- look out for systematic approach used
(25 min)
Think of a relevant example and summarise
key points on a card;
Read out the card of a neighbour in plenary
and summarise on pre-headed flip chart - one
member should write key points on flip chart
i.e. getting used to facilitating
Examine synthesis and Q&A
Background
Ask why the RBN identified advocacy
training as a priority need. List answers on
flip chart (member to do )
(Check how many know about training TOR
and were involved in its development)
The replies may identify general weaknesses
that need to be strengthened or may not.
(15 min)
In plenary, give reasons for asking for
training and summarise on flip chart
Advocacy process & tips
Use Information Sheets1 & 2 to present
advocacy process and give tips for good
advocacy practice. Ask members for more
tips to be added.
Look at guidelines on making a press release
& ask members to make a press release
headline and introduction to advertise this
training meeting. Use 3 sub-groups and cards
(40 min)
Receive presentation
Comment – try use own experiences
Add to the list of advocacy tips in plenary;
member facilitate.
For press split into 3 sub-groups and write
headline and introduction on card. Review in
plenary, select best & give reasons.
Q&A
Advocacy analysis
Ask members to give examples where
advocacy has failed and give reasons
Repeat process for examples and reasons for
success. (List on flip chart by volunteer
member). Compare reasons given with
Information Sheet 1.
(20 min)
Respond to request and give examples. One
member acts as facilitator.
Advocacy Issues Think about the question, try to suggest a
Training for Regional Beach Management Unit Network (RBN) in East Africa
123 Project Funded by the European Union A project implemented by (Harewelle International Limited)
Ask members what are the key immediate
issues that demand advocacy by the RBN. Do
this by show of hands & reply in plenary.
Remind members of their key function set
out in their Operating Procedures
―Provide a joint forum that represents and
lobbies on behalf of the interests of all Lake
Victoria BMUs and raises their
international profile‖.
Use flip chart to gather responses
Present Information Sheet 3 on National
BMU Network Functions in Kenya July 2012
and ask if this is an advocacy issue. Request
replies in plenary from each country.
(20 min)
priority example and respond with show of
hand in plenary; one member (different from
before) to write answers on flip chart.
Examine Information Sheet 3 and consider
issues with others identified. Reach
consensus through discussion on key issues.
Q&A
Advocacy Issues
Present Information Sheet 4 listing key issues
or recommended actions concerning the RBN
given in the latest report of the LVFO
Fisheries management Committee. Ask
members to decide if issues are still relevant
in 2012 and highlight any that are advocacy
issues. Do this by completing column on the
Information Sheet 4.
(20 min)
Examine Information Sheet 4 and complete
it. Reach consensus in deciding if any issues
in sheet are still issues for current advocacy.
Conclusion (10 min)
Recap of main points, address any queries Q&A
Training materials: Hand outs, Flip charts,
Flip chart pens; cards, pens
Evaluation: Confirm all are clear on topics
discussed
Q&A
6.1.3 Training Aids
Information Sheet No.1-4, Module 2 Session 1.
Training for Regional Beach Management Unit Network (RBN) in East Africa
124 Project Funded by the European Union A project implemented by (Harewelle International Limited)
MODULE 2 - SESSION 1: INFORMATION SHEET 1
ADVOCACY BASICS
What is Advocacy?
Advocacy is a broad, term that can be applied to a wide range of activities carried out to
influence thinking and decision-making and create political or practical change. There is no
one fixed definition of advocacy. Here are some examples to give you an idea of what it is:
―Advocacy represents the strategies devised, actions taken and solutions proposed to
influence decision-making at local, provincial, national and international levels to create
positive change for people and their environment‖.
―The deliberate process of influencing those who make policy decisions‖.
―Advocacy is a process to bring about change in the policies, laws and practices of
influential individuals, groups and institutions."
"Advocacy is an on-going process aiming at change of attitudes, actions, policies and laws by
influencing people and organisations with power, systems and structures at different levels
for the betterment of people affected by the issue."
Advocacy is not:
- extension work (encouraging households to change their fisheries management or
natural resource management strategies)
- information education and communication (such as launching a public campaign to
change practices and behaviours, social marketing or mass media campaigns)
- informing government partners about our work (informing partners about project
progress in order to raise RBN profile, visibility and credibility)
- raising awareness among the public about our work (articles in the press about the
work of the RBN. While the process used in such work may be similar to that used in
advocacy, unless it is targeted directly at delivering a policy message it cannot be
defined as advocacy)
Advocacy is often called policy advocacy because of its connection with influencing policy
and laws governing peoples‘ lives. Advocacy and lobbying are often taken to mean the same
but lobbying originated from a process to change laws. Now it‘s a term with wider use.
Effective Advocacy requires:
Organisation
Strategic and creative thinking
Information (which is well researched and factually accurate)
Strong, well-reasoned arguments in favour of your proposals
Effective communication
Mobilisation of support
The most successful advocacy campaigns are those that have strong and cohesive (united)
support as well as powerful and well-researched and well-presented arguments. The RBN
Training for Regional Beach Management Unit Network (RBN) in East Africa
125 Project Funded by the European Union A project implemented by (Harewelle International Limited)
should strive to present realistic and achievable solutions to help win any advocacy/lobbying
campaign.
There is a stepwise process shown below that describes advocacy activities in summary form.
Advocacy/Lobby Process
STEP 1: Select an issue/problem you want to address
STEP 2: Analyse and research the problem
STEP 3: develop your specific objectives
STEP 4: Identify your targets
STEP 5: Identify your resources
STEP 6: Identify allies
STEP 7: Make an action plan
STEP 8: Implement, monitoring and evaluation
Factors to be considered when selecting advocacy issues
Time it takes for success
A single advocacy process can be completed in a very short time, for example, getting a new
law passed, or it can take years of effort. This must be considered carefully by the RBN when
selecting advocacy issues and making action plans.
Ever–changing Activity
The issues requiring advocacy can appear quite suddenly and disappear equally suddenly.
The RBN needs to use a flexible approach and be ready to seize advocacy opportunities when
they suddenly arise unannounced. Also, issues will come and go. Hopefully, as the RBN
succeeds in advocacy it will constantly move on from one issue to the next. This is not easy
to plan for.
Sensitivity and confidentially
The very nature of advocacy requires a high degree of sensitivity especially with regard to
taking a confrontational or cooperative approach to addressing the issue. Each case will be
different and judgements will need to be made constantly on which approach looks most
appropriate. There two sides to confidentiality. The first is that the advocate may not wish to
known to be engaged in a lobby campaign for fear of repercussions by those in power.
Second, it is often better to allow the powerful decision-maker to be seen to have made a
change in course on his own initiative rather than having been coerced by some form of
advocacy activities.
The source of advocacy issues
Ideally, the issues identified by the RBN for advocacy action should be those coming from
the grassroots membership in BMUs. It‘s not uncommon, however, for issues to be identified
at higher, better informed, levels that have access to news of policy and legal changes which
have not reached the lakeshore communities. In these situations, it is appropriate for issues to
originate from higher levels.
The value of alliances
For an organisation like the RBN which is struggled to secure finances, it becomes even more
important to set up alliances in any advocacy campaign. In doing so, it is likely to achieve
more and at lower cost than it otherwise would.
Training for Regional Beach Management Unit Network (RBN) in East Africa
126 Project Funded by the European Union A project implemented by (Harewelle International Limited)
ADVOCACY CHECKLIST
Always have SMART objectives: Specific, Measurable, Achievable, Realistic, Timebound.
✔Clearly identify your issue and your goals in the short, medium and long-term. Prioritise
your efforts and resources.
✔Check that you have support, time, resources and finance to develop your advocacy.
✔Decide who your audience is and target your information effectively. Be considered in
your approach – how can you best achieve your goals – who are the key decision-makers on
your issue?
✔Consider how to distribute the information and ideas to greatest effect. Is it in the form of a
meeting, rally, conference, email, bulk SMS, policy brief or newsletter?
✔Ensure that the information that you are basing your campaign on is factually correct and
targeted at the appropriate audience.
✔Ensure that you monitor your progress during the course of your campaign, assess your
strengths and weaknesses and amend your strategy accordingly.
Training for Regional Beach Management Unit Network (RBN) in East Africa
127 Project Funded by the European Union A project implemented by (Harewelle International Limited)
MODULE 2 - SESSION 1: INFORMATION SHEET 2
ADVOCACY TIPS
TIP 1 Try to work with the media to convey your messages, generate concern and support.
TIP 2 If you represent an organisation or
community you must have a clear
mandate from your colleagues
empowering you to speak, write and
act on the issue on their behalf
TIP 3 You MUST ensure factual accuracy in any statements that are made, and when
there is doubt, if information is anecdotal or unsubstantiated, don’t use.
TIP 4 Effective communication of your
issue is essential – compiling and
presenting your arguments to the
right audience is critical to the
success of your advocacy.
TIP 5 Decisions may be announced at international meetings, but they are rarely made
there – make sure that you are well prepared and that you have contacted or
presented your views to civil servants and decision makers well in advance of
important meetings.
TIP 6 When considering undertaking any
of the above, cost, time and
potential benefits must be carefully
thought through before making
any decision.
TIP 7 The safety of you and all those you work with is of paramount importance. Never
take unnecessary risks in either researching or advocating your issue.
Training for Regional Beach Management Unit Network (RBN) in East Africa
128 Project Funded by the European Union A project implemented by (Harewelle International Limited)
Guide to writing an advocacy press release A press release uses the five ‗Ws‘ essential for all journalists:
What – Who - Where - When - Why
A press release should begin with the first four W‘s, as follows:
What is happening?
Who is doing it?
Where is it happening?
When is it happening?
This information should be in the first sentence or two, so that members of the press can see
immediately what the release is about.
A press release needs a headline, introduction and remainder of text.
The headline: Choose a simple headline for the press release (usually a short version of the
first sentence will do). While the newspapers sub-editors will think up fancy headlines, do
try to keep it as short and interesting as possible, as this will grab peoples attentions. The
purpose of the headline is to help the news editor to spot the interest in the story.
Introduction: Most editors do not have sufficient time to read even a short press release in
full. The first few lines of a release, can be the key to whether or not it is included in the
publication. The introduction has to capture the editor‘s attention immediately and tell him
or her the most interesting fact, together with the first four Ws. Where possible the
introduction should be a summary of the entire release in one or two sentences.
The remainder of the text: This should contain the remainder of the information you wish
to convey, including the ‗Why‘, if not already stated. Concentrate on presenting the facts
(rather than opinion), in order of importance.
Keep sentences short. Use the active voice where possible: for example, instead of ―a new
campaign to introduce hygiene education in schools was announced by Minister of
Education, David Mutisa‖, write ―Minister of Education David Mutisa announced a new
campaign to introduce hygiene education in schools‖. Use direct quotations as much as
possible, as most news stories are based on people.
Put a date on the press release. Always use double spacing: this allows the sub-editor to re-
write and insert instructions to the printer
At the end of the text of a press release, put ―Ends‖ underneath and separate from the final
sentence. Always put the name and telephone number (work or home) of the person who
issued the release.
Training for Regional Beach Management Unit Network (RBN) in East Africa
129 Project Funded by the European Union A project implemented by (Harewelle International Limited)
MODULE 2 - SESSION 1: INFORMATION SHEET 3
REGIONAL ADVOCACY ISSUES FOR RBN CONSIDERATION
From: National BMU Networks Guidelines for Kenya July 2012
Functions of BMU Networks in Kenya taken from the Kenya Guidelines and given below
are different from those in Uganda and Tanzania. Losing regional harmonisation and
planning coherence.
Mandate of the Networks
A BMU network shall be responsible to its members and to the Director for ensuring the
orderly, safe and effective use, management of the administrative area over which it has
jurisdiction, to which end it shall:
(a) Advocate on behalf of members to ensure favorable policies and programs.
(b) Develop and implement code of practice to strengthen self-policing and compliance.
(c) Participate in Fish Traceability systems, eco-labeling and generally participate in
activities and programs that promote fish products in local, regional and international
markets.
(d) Explore and exploit new business opportunities for members.
(e) Negotiate for favorable business environment at various levels of administration.
(f) At National level constitute the Trustees of the Fish Levy Trust Fund.
(g) Have any such mandate that may further the mandate of BMUs as provided for in the
Fisheries Act or its subsidiary regulations.
Responsibilities of the network committee
The duties of the executive committee shall be:
a) to supervise the general management of the beach management unit‘s under their
jurisdiction;
b) to approve the minutes of its previous meetings;
c) to supervise and Collaborate in the implementation Fishery or Species specific
management plans ;
d) to represent member beach management units in relationships with third parties;
e) to review applications for resignation from it and to make recommendations regarding the
suspension of committee members;
f) to conclude contracts in accordance with member BMUs approved budget and plans;
g) to employ and as necessary dismiss staff of the networks;
h) to maintain accounts and registers as specified in the guidelines;
i) to exchange information with other networks and other relevant agencies to promote the
fair and transparent pricing of fish and fish products;
j) to formulate funding proposals, make financial reports and present them to member
BMUs for approval;
k) to assist in supervising the financial management of the member beach management
units;
l) to undertake other tasks specified in these guidelines or network rules that are in sync
with the fisheries laws.
Training for Regional Beach Management Unit Network (RBN) in East Africa
130 Project Funded by the European Union A project implemented by (Harewelle International Limited)
MODULE 2 - SESSION 1: INFORMATION SHEET 4
POTENTIAL REGIONAL ADVOCACY ISSUES OF THE RBN FROM MARCH 2010
The list of issues needing actions are taken from the most recent report of the LVFO Fisheries
Management Committee meeting held March 2010. The RBN Chairman participated as a full
member of the FMC and the following actions listed below were adopted by the FMC for
onward submission to the LVFO Executive Committee.
Are any of the Issues/Actions relevant as RBN Issues in 2012? Complete form in plenary.
Action in FMC Report March 2010 Responsible
institution
Advocacy issue
of RBN in July
2012 Y/N
RBN & EAIFFPA membership - Actions: The EC is requested
to:
1) Urge Partner States to streamline paper work regarding fish
movement for vehicles going to fish factories and markets.
DoFs
2) Urge the Secretariat to set up a Steering Committee
composed of LVFO/Industry/RBN/and other agencies to define a
strategy and develop a prioritised action plan for OPSN.
Secretariat
3) Urge the Partner States to set up national Taskforces with
similar stakeholder composition as the Steering Committee to guide
and monitor implementation of national OPSN action plans.
DoFs
Operationalise NPFMP - Actions: The EC is requested to:
4) Urge the LVFO Secretariat to disseminate formally by hard
copy and electronic copy the agreed NPFMP to the Heads of
national fisheries management institutions, Heads of national
fisheries research institutions, RWG chairs, NWG chairs, Heads of
Regional/Provincial/District Governments, District Fisheries
Officers, EAIFFPA and its three national association members, and
the RBN and its national and district members.
Secretariat
BMU areas - Actions: The EC is requested to:
5) Urge the national Departments of Fisheries to complete the
identification of land-based jurisdictional areas of all BMUs and
gazette them.
DoFs
6) Direct the LVFO Secretariat with possible TA support to
develop a strategy for extending BMU jurisdictional areas to
inshore waters.
Secretariat
Species specific licensing - Actions: The EC is requested to:
7) Urge the Partner States to establish the harmonised systems
for species and fishery specific licensing in each Partner State in
2010.
DoFs
8) Urge the Secretariat to produce a regional LVFO
Information Sheet for BMUs on the need for species and fishery
specific licensing for sustainable fisheries.
Secretariat
BMU Networks & Suppliers Network - Actions: The EC is
requested to:
9) Urge the LVFO Secretariat to provide guidance on Secretariat
Training for Regional Beach Management Unit Network (RBN) in East Africa
131 Project Funded by the European Union A project implemented by (Harewelle International Limited)
registration of BMU Networks.
10) Urge national Departments of Fisheries to ensure
registration of BMU Networks at all levels and the LVFO
Secretariat to provide guidance on the procedures to be adopted.
DoFs
11) Urge national Departments of Fisheries to ensure that
legislation is developed to recognise and empower the BMU
Networks at all levels.
DoFs
12) Urge the Secretariat to initiate a process for the
establishment of Nile Perch Traders Networks to strengthen the
institutional co-management framework on the lake.
Secretariat
Fish Bills, Info policy, Anti-corruption policy - Actions: The EC
is requested to:
13) Urge Uganda to fully involve key stakeholders from the
industrial fish processors and exporters and the BMU Networks in
any review process of the Fisheries Bill to give their input before
submission of the Bill for Parliamentary approval.
DFR
BMU Financing - Actions: The EC is requested to :
14) Urge the RBN to use the BMU Networks to compile data on
landing site tenders and BMU bank accounts.
RBN
15) Urge the Partner States to ensure that their legislation
contains the Landing Site User Fee (LSUF) and the highest
percentage should go to BMUs.
DoFs
16) Urge the LVFO and RBN to review the LSUF for potential
use in BMU financing in Tanzania and Kenya.
DoFs & RBN
EAIFFPA & RBN collaboration - Actions: The EC is requested
to:
17) Urge the EAIFFPA and RBN to develop possible ways of
exchange programs of independent inspections.
EAIFFPA &
RBN
PR info for RBN etc – Actions: The FMC is requested to:
18) Urge the Secretariat to support the RBN together with
EAIFFPA as new members of FMC and SC to produce various
types of information materials on the activities of their
organisations.
Secretariat
19) Urge the Secretariat to assist the RBN and EAFFPA in
linking with international government organisations, international
fisheries NGOs and development partners.
Secretariat
6.1.4 Reference Material
No reference material included for this session.
6.2 End of Day Evaluation of Training
The methodology described in Section 5.3 was applied at the end of day 2 of the course (see
Section 5.3 for evaluation form template)
Training for Regional Beach Management Unit Network (RBN) in East Africa
132 Project Funded by the European Union A project implemented by (Harewelle International Limited)
6.3 Module 2- Session 2
6.3.1 Training Session Plan
Module 2 – Session 2 Date: 2nd
Aug 2012 Duration: 2hr 45 mins
Title: Improving RBN advocacy skills
Objectives:
Appreciate more fully that an advocacy role is one of the main reasons for having a RBN
Have a better understanding of how to take a more systematic, planned approach to
advocacy;
Leave the training venue with key issues identified by the RBN members that require
prioritised advocacy actions and everyone knows who will do what and when.
Content: Training Points Methods Time
Introduction Overview of session Q&A 10 min
Development Introduction
Prioritisation of advocacy issues Issue 1 incorporated in Strategic Plan
Issue 2 incorporated in Strategic Plan
Issue 3 incorporated in Strategic Plan
Projector,
information
sheets,
Plenary
Q&A,
Trainee
review &
analyses
2h 25 min
Conclusion Recap of main points, address any queries Q&A 10 min
Training materials: Hand outs, Flip charts, Flip chart pens
Evaluation: Q & A
6.3.2 Trainers Notes
Opening Session p.1
Trainer Trainee
Introduction (15 min)
Overview of session linking to last session
where advocacy issues were identified.
Explain methodology for activities in this
session which will complete the gap in the
Strategic Plan by incorporating key advocacy
issues with budgets.
Receive overview.
Q&A
Development (2h 20 min)
Prioritisation of advocacy issues
Examine identified issues and prioritise the
top 3 issues based on importance to RBN,
problem analysis, chance of success,
resources needed, alliances. Ask members to
discuss and select.
Review list of identified issues and select
based on criteria given. Do this in sub-groups
of 3 persons – one from each country, present
findings on flip chart and consensus reached
on top 3 in plenary.
Training for Regional Beach Management Unit Network (RBN) in East Africa
133 Project Funded by the European Union A project implemented by (Harewelle International Limited)
(35 min)
Issue 1 incorporated in Strategic Plan
Use Strategic Plan table and complete an
activity line for one issue. Decide on title of
activity, actions needed, resources needed,
cost and timing. (35 min)
Discuss as a group in plenary to complete the
Strategic Plan table for each of 3 priority
advocacy issues. Give comments and
conclusions for entry into laptop projecting
the table as a spread sheet.
Issue 1 incorporated in Strategic Plan
Use Strategic Plan table and complete an
activity line for one issue. Decide on title of
activity, actions needed, resources needed,
cost and timing. (35 min)
Discuss as a group in plenary to complete the
Strategic Plan table for each of 3 priority
advocacy issues. Give comments and
conclusions for entry into laptop projecting
the table as a spread sheet.
Issue 1 incorporated in Strategic Plan
Use Strategic Plan table and complete an
activity line for one issue. Decide on title of
activity, actions needed, resources needed,
cost and timing. (35 min)
Discuss as a group in plenary to complete the
Strategic Plan table for each of 3 priority
advocacy issues. Give comments and
conclusions for entry into laptop projecting
the table as a spread sheet.
Conclusion (10 min)
Recap of main points, address any queries Q&A
Training materials: Projector, Flip charts,
Flip chart pens; cards, pens
Evaluation: Confirm all are clear on topics
discussed
Q&A
6.3.3 Training Aids
Information Sheet No.1, Module 2 Session 2.
Training for Regional Beach Management Unit Network (RBN) in East Africa
134 Project Funded by the European Union A project implemented by (Harewelle International Limited)
MODULE 2 - SESSION 2: INFORMATION SHEET 1
RBN STRATEGIC PLAN: RESULT 4 - ACTIVITY AREAS 4.1 & 4.2
Ref
No
Activities Details Annual Costs ($) Self-
Funding
by RBN
Donor
Funding
Needed
Total
Cost
Priority
1 =
highest 2012-
2013
2013-
2014
2014-
2015
4.1 Development of advocacy strategy
4.1.1 Training of RBN in making advocacy
strategy
Funded in 1.3.1 0
4.1.2 Develop a RBN advocacy strategy Funded in 1.3.1 0
4.1.3 RBN members guide their own NBNs in
making budgeted plans
RBN members mentor at
NBN meetings: NBN
funds own meeting
0
4.1.4 RBN members guide their own DBNs in
making budgeted plans
RBN members mentor at
DBN meetings: DBN
funds own meeting
0
4.2 Prioritise advocacy issues
4.2.1 Lobby for completion of the demarcation
and gazettement of jurisdictional areas of
BMUs and BMU Networks in each Partner
State.
0
4.2.2 Assist government and private industry in
the resolution of cross-border fisheries
conflicts.
0
4.2.3 In collaboration with other LVFO bodies,
lobby for regional action from EAC for the
provision of health and social services for
fisheries communities.
0
Training for Regional Beach Management Unit Network (RBN) in East Africa
135 Project Funded by the European Union A project implemented by (Harewelle International Limited)
6.3.4 Reference Material
No additional reference material is needed for this session.
Training for Regional Beach Management Unit Network (RBN) in East Africa
136 Project Funded by the European Union A project implemented by (Harewelle International Limited)
7. TRAINING ON PROJECT PROPOSAL WRITING
7.1 Module 3- Session 1
7.1.1 Training Session Plan
Module 3 – Session 1 Date: 2nd
Aug 2012 Duration: 3hr
Title: Writing a project proposal: Introduction
Objectives:
Leave the training venue with at least one completed project proposal to be presented to
identified development partners;
Have a better understanding of the core structure of a project proposal and how to write
one.
Content: Training Points Methods Time
Introduction Overview of session Q&A 10 min
Development Introduction
Structure and content of a proposal
Successful proposal writing
Dealing with funders
Submitting a proposal
Information
sheets,
Plenary
Q&A,
Trainee
review &
analyses
2h 35 min
Conclusion Recap of main points, address any queries Q&A 15 min
Training materials: Projector, Information Sheets, Flip charts, Flip chart pens
Evaluation: Q & A
7.1.2 Trainers Notes
Opening Session p.1
Trainer Trainee
Introduction (10 min)
Overview of session
Note for this activity, TOR states – ―capacity
building for a grant-making
process/proposal‖. Interpreted as training in
writing a proposal. TOR specifically
mentions grant for RBN office and
Secretariat. We will explore this aim in more
detail in this session.
Receive overview and reach consensus of
interpretation meaning need help writing
proposals for grant support.
Q&A
Development (2h 35 min)
Design, Structure and Content of a proposal:
Present core structure of a grant proposal.
Explain the broad content of each section –
refer to Information Sheets 1 & 2 (40 min).
Review Information Sheets 1 & 2
Q&A
Successful proposal writing: Review Information Sheet 3
Training for Regional Beach Management Unit Network (RBN) in East Africa
137 Project Funded by the European Union A project implemented by (Harewelle International Limited)
Present a short guide/ tips on good proposal
writing - refer to Information Sheet 3
(15 min).
Q&A
Dealing with funders:
Present a guide on how to approach funders -
refer to Information Sheet 4 (25 min).
Review Information Sheet 4
Q&A
Submitting a proposal:
Present a guide on how to submit a proposal -
refer to Information Sheet 5 (25 min).
Review Information Sheet 5
Q&A
Issues for the RBN
Present challenges facing the RBN in
obtaining grant aid, and possible solutions to
the challenges - refer to Information Sheet 6
(30 min).
Review Information Sheet 6
Q&A
Conclusion (15 min)
Recap of main points, address any queries Q&A
Training materials: Hand outs, Flip charts,
Flip chart pens; cards, pens
Evaluation: Confirm all are clear on topics
discussed
Q&A
7.1.3 Training Aids
Information Sheet No.1-5, Module 3 Session 1.
Training for Regional Beach Management Unit Network (RBN) in East Africa
138 Project Funded by the European Union A project implemented by (Harewelle International Limited)
MODULE 3 - SESSION 1: INFORMATION SHEET 1 INTRODUCTION TO PROJECT DESIGN
WHAT IS AND IS NOT A PROJECT
Any series of activities that go through the project cycle ARE projects. The project cycle
consists of project phases. An organisation should already have a well-defined strategic plan
from which it can begin to assess relevant needs and opportunities in its field. Several ideas
will then come to light, from which an organisation may choose. The project phases then
follow logically through a) design, b) financing, c) implementation and d) evaluation stages.
Organisations often perform activities that do not fall into the category of projects. It is also
important to recognise that a project is not:
past activities that are repeated in exactly the same way on a periodic basis;
activities with no clearly defined goals;
activities which can be repeated or transplanted anywhere at any moment; or
on-going (regular) organisational activities (e.g. planning meetings).
WHAT IS THE PROJECT DESIGN?
The project design is one phase of the project cycle. It consists of two elements:
project planning (formulation of project elements); and
project proposal writing (converting the plan into a project
document).
Project design is a result of both project planning and the project proposal. Both steps are
essential to forming a solid project design.
PROJECT PLANNING CONSIDERATIONS
Here is a comparison of some key activities at the planning/design stage and the project
writing stage.
Issues to be considered at start of
project planning
Elements of the project proposal
■ Beneficiaries of the project
■ Project title
■ Project team and cooperative
partners
■ Goals and objectives of the project
■ Success criteria ■ Description of project activities
■ Goal and objectives ■ Description of expected project results
■ Methods chosen to achieve
project goal
■ Project implementation plan
■ Costs and expenditures ■ Beginning of operations
■ Own contribution ■ Resource allocation
■ Potential funders ■ Project personnel
■ Detailed project budget (fixed costs, equipment needed)
■ Other technical means(e.g. vehicles)
■ Financial sources (own contribution and other resources)
Training for Regional Beach Management Unit Network (RBN) in East Africa
139 Project Funded by the European Union A project implemented by (Harewelle International Limited)
PROJECT FORMAT
There are as many proposal formats as there are a number of donors and each donor as a
different format. Although the basic information requested by various donors is generally the
same, yet we often encounter snags that make the entire process confusing. It is important to
gather enough information about your donor, such as:
Aid priorities and issues of the donor
The donor‘s country strategy paper (if any)
Proposal Guidelines of the donor
Previously funded projects and programs by the donor
CORE STRUCTURE OF PROJECT PROPOSALS
Problem Statement (as part of Introduction/Background)
Project Rationale or Justification
Project Goal & Objectives
Strategies & Activities, Timing
Results: Impact, Outputs & Outcomes
Budget
Monitoring
PROJECT CONCEPT NOTE
Quite often a Project Concept Note is developed before a more detailed proposal is made. An
example of the format of a Concept Note is shown below which is from a ―call for funding
proposals‖ by the Micro Enterprise Support Programme Trust in Nairobi as part of support by
Danida in 2012.
Concepts notes shall be a maximum of 7 pages and shall include:
- A brief background of the sub-sector – 1 page maximum
- The problem statement/Project rationale – half page max
- The goals and objectives – half page max
- Target beneficiaries description – half page
- Brief implementation methodology – 2 pages
- Proposed partners (where applicable) – half page
- Time frame (not more than 3 years)
- Total budget (not more than 20Million Kenya Shillings – half page
Training for Regional Beach Management Unit Network (RBN) in East Africa
140 Project Funded by the European Union A project implemented by (Harewelle International Limited)
MODULE 3 - SESSION 1: INFORMATION SHEET 2
CORE STRUCTURE OF A PROJECT PROPOSAL
1. BACKGROUND
1.1 Overview of project area – key points relevant to project aims and activities
1.2 Overview of organisation involved in project – its profile: History, size, vision
mission plans (with goal/purpose) summary of achievements relevant to project
1.3 Problem statement – a description of the problem that the project will address
1.4 Justification for the project including target beneficiaries
2. GOAL, PURPOSE and EXPECTED RESULTS
2.1 Goal
Set out the goal of the project – this is not a project deliverable but something which the
project will contribute to attaining.
2.2 Purpose
Set out the purpose of the project – this is the main project deliverable and progress and
performance of the project are measured against whether or not the project purpose is
attained.
The purpose of this assignment is to strengthen the capacity of the Regional Beach
Management Unit Network (RBN) to effectively participate in the management of the
fisheries of Lake Victoria.
2.3 Results
Set out the expected results of the project in headings only.
3. PROJECT ACTIVITIES
Describe in detail the key activities of the project under each activity area heading. Include
What, When, How, Where, and Who to describe key activities.
Include sub-section on sustainability to demonstrate a project will be able to continue after
the initial funding ends.
Training for Regional Beach Management Unit Network (RBN) in East Africa
141 Project Funded by the European Union A project implemented by (Harewelle International Limited)
4. PROJECT TIMING AND DURATION
Set out the duration and expected start and end times of the project, Highlight any key factors
affecting both duration and timing.
Include a Project Implementation Plan – a table showing activities through time for the whole
project and any key milestones.
5. PROJECT MANAGEMENT
Define the organisation responsible for implementing the project
Describe any partnerships set up for project implementation
Define the project management structure – who takes decisions
6. BUDGET
Include a budget table with as much detail as possible in expenditure lines across agreed time
intervals.
7. MONITORING AND EVALUATION
Complete the M&E framework based on a logical framework.
Remember: The M&E section of the proposal should be consistent with the budget.
Training for Regional Beach Management Unit Network (RBN) in East Africa
142 Project Funded by the European Union A project implemented by (Harewelle International Limited)
MODULE 3 - SESSION 1: INFORMATION SHEET 3 DEALING WITH FUNDERS
HOW TO APPROACH FUNDERS
Don’t be shy. If you don‘t know the potential donor, write them a brief email or letter
introducing yourself and the programme. You can send attachments. Tell the potential donor
that you will call for an appointment. Be sure to follow up promptly.
Remember, funders are people. Funders prefer direct contact with the organizations and
projects they fund.
Set up an appointment. Face to face is always better. Never ask for a major contribution until
you at least speak to the potential donor. Make specific plans to follow up on your visit. Don't
just say ―We hope to hear from you.‖ Say: ―We'll call you the week of such and such, if that
fits with your schedule.‖
More calls mean more successes. The more calls for appointments you make, the more likely
you are to meet your funding goals. But don‘t pester a single individual – strike the right
balance.
Read the newspapers. Tender responses and calls for proposals are listed in the major
newspapers. Scan the papers regularly to find agencies that need the services you can provide
Be honest. It‘s the best policy.
Honour all partners. Failure to communicate appropriately with partners and to represent
them properly can kill deals.
Be direct. Show respect for busy people and don‘t take too much of their time. Get to the
point.
Have a budget amount in mind before you walk in the door.
Listen to suggestions. Sometimes the prospective donor has a good idea that you haven‘t
thought of. Seize it. It may lead to an innovative project.
Know your organizational goals. Know the vision and mission of your organisation and the
purpose of its Strategic Plan.
Speak to the right people. Make sure someone senior closes the deal.
Follow up. Don‘t forget to thank the donors for their commitments. Ask fellow employees to
do the same.
Training for Regional Beach Management Unit Network (RBN) in East Africa
143 Project Funded by the European Union A project implemented by (Harewelle International Limited)
RELATIONSHIP DO’S AND DON’TS
Remember that success in resource mobilization is often about the relationship. Keep in mind
these relationship do‘s and don‘ts.
Remember to always speak on equal terms with funders
Treat donors with respect and curiosity
Follow through on everything that you say you will do
Meet all donor deadlines
Listen well
Know who you are talking to.
Learn their name and position
Learn how to communicate with people from different backgrounds as you will be
meeting lots of different people
Don‘t use too much flattery
Don‘t speak in a ‗poor us‘ way
Don‘t act desperate or complain about having no money – the donor might think you
don‘t have the capacity to handle money
Don‘t call a potential resource provider too often or talk for too long
Don‘t hurry or rush the funder – but do keep in contact and follow up on requests
Some tips for the conversation:
Use questions to get started
Listen well and patiently
Don‘t deny objections but find a positive way to answer them
GOOD QUESTIONS TO ASK FUNDERS
What are your areas of interest for funding?
What other projects or organizations have you funded in the past?
What are your criteria/ requirements for supporting an organization?
When do you accept proposals?
What is your budget cycle (annual, every 3 years, 5 years)?
What is the application process?
When are your application deadlines?
Who is the correct person to contact and what are their contact details?
What are your areas of geographic interest?
What are your funding criteria/ proposal requirements?
Any there any special accountability needs?
What are the reporting requirements?
Are there any possibilities of donations in kind?
Training for Regional Beach Management Unit Network (RBN) in East Africa
144 Project Funded by the European Union A project implemented by (Harewelle International Limited)
MODULE 3 - SESSION 1: INFORMATION SHEET 4
SUCCESSFUL PROPOSAL WRITING
THINGS FUNDERS LOOK FOR IN THE PROPOSAL SENDER
Demonstrated accountability (financial and programme)
Proven track record
Well-presented cause that clearly explains the need
Clear and well-thought out vision and mission
A good strategic plan which shows how resources are used to meet objectives
SUCCESSFUL PROPOSAL WRITING
A proposal must convince the prospective donor of two things:
The problem you wish to address is of significant magnitude and,
You have the means and the imagination to solve the problem or meet the need
RULES FOR PROPOSAL WRITING
Be Concise Though not all proposals are short, a good rule of thumb is to be brief and concise but still be
clear. Place yourself in the shoes of the people that you are approaching. They will not want
to plough through page after page of material that may be unimportant or only interesting to
you. A concise proposal demonstrates your respect for the time that they have to commit to
your application and your ability to succinctly outline your request.
Be passionate and positive Write persuasively and confidently - you're selling a concept that will have a very positive
impact.
Avoid using conditional language like:
"We would like to . . ."
"We may include . . ."
"Possible results might be . .
Training for Regional Beach Management Unit Network (RBN) in East Africa
145 Project Funded by the European Union A project implemented by (Harewelle International Limited)
Instead, march boldly forward in your proposal with positive language such as:
"We will . . . "
"Programs will include . . ."
"The results will be . . ."
Write for each funder
Each funding application should match the structure and format requirements of the funder.
Funders will help you. Call them and ask questions - but be sure you've done your homework
first and that you're not asking a question already answered in their literature.
A proposal should reflect planning, research and vision. The importance of research cannot
be overemphasized, both in terms of the funders solicited and the types of funds requested. If
the funder provides a format, follow it carefully.
The most successful proposals are those which clearly and concisely state the community's
and organization's needs and are targeted to donors which fund that field, a reflection of
careful planning and research.
Don‘t use jargon! Use simple, clear, concise sentences.
Writing is about 20% of the issue in grants acquisition. There are factors all funders consider
"highly important":
Project purpose
Feasibility
Community need for the project
Applicant accountability
Competence – applicant‘s ability to manage the project successfully
Other factors also considered important include:
Probable impact
Money required
Community buy-in and support
Innovative solutions
Realistic - not too ambitious
Well-documented
Exciting
Current & relevant
Training for Regional Beach Management Unit Network (RBN) in East Africa
146 Project Funded by the European Union A project implemented by (Harewelle International Limited)
7.1.4 Reference Material
No additional reference material is needed for this session.
7.2 End of Day Evaluation of Training
The methodology described in Section 5.3 was applied at the end of day 2 of the course (see
Section 5.3 for evaluation form template)
Training for Regional Beach Management Unit Network (RBN) in East Africa
147 Project Funded by the European Union A project implemented by (Harewelle International Limited)
MODULE 3 - SESSION 1: INFORMATION SHEET 5
SUBMITTING A PROPOSAL
Submitting a Proposal
There should be a covering letter and a cover page for the proposal
Covering Letter
A covering letter should be written on your letterhead, and should:
Have the funder's name, title, and address
Be directed to the individual responsible for the funding program (not addressed "To
Whom It May Concern", "Dear Sirs", etc…)
Provide a brief overview of the organization and its purpose
Describe the need the project intends to meet (including target population, statistics,
example)
Provide a brief description of the project
Include the amount requested (if required by funder)
Be one page in length
Include the name and phone number of the contact at the organization
Include a thank you and next step to be taken (we will phone you in the next week to
follow up) Should not exceed two pages
Be signed by the person who can speak with authority on behalf of the organization
Cover Page
The cover page with your organisation‘s logo on it and including the name of the project you
wish to fund, who the proposal is being submitted to, who it was prepared by (with address
and contact details) and date.
Training for Regional Beach Management Unit Network (RBN) in East Africa
148 Project Funded by the European Union A project implemented by (Harewelle International Limited)
Final Check before sending
Things to check before sending a proposal Y/N
Did we use the required format?
Did we include a cover page with correct contact information?
Did we provide some organizational history?
Have we described our beneficiaries?
Is it obvious that there is a real need in our community?
Have we shown our previous experience and success ?
Is our project well explained with clear objectives?
Did we include realistic timeframes?
Have we shown how the community is involved and how they will benefit?
Is there a realistic budget?
Are our activities related to our budget?
Did we describe our financial management well?
Did we include the documents requested?
Have we done a spell check?
Training for Regional Beach Management Unit Network (RBN) in East Africa
149 Project Funded by the European Union A project implemented by (Harewelle International Limited)
MODULE 3 - SESSION 1: INFORMATION SHEET 6
ISSUES IN ATTRACTING GRANT SUPPORT FOR A RBN SECRETARIAT
There are some critical issues facing the RBN in applying for a grant application to set up and
operate a RBN Secretariat. These are as follows:
No permanent office or paid staff
No system/capability of managing and accounting for grant funding
No track record of implementing a grant-funded project
Unclear legal identity of the organisation
No publicity and communication materials e.g. brochure, website
In view of the above, it probably will be difficult to obtain grant aid in the usual way that
NGOs do.
An option that offers a way forward is to forge a partnership with another organisation that
can help the RBN Secretariat become established. The offer made by the LVFO appears to be
the best option on offer. The offer, as yet made informally, includes a rent-free room in the
LVFO Secretariat in Jinja for the RBN Secretariat. The grant support could be channelled
through the LVFO providing a financial management role until the Secretariat is capable and
trusted by the funder.
The RBN Secretariat is a regional body and as such, the potential funding agencies are likely
to be fewer than for bilateral grant support.
Grant support is most likely from existing programmes operating in the region. Of these, the
NEPAD PAF programme is worth exploring. This programme is funded by the UK
Department for International Development (DFID) and the German Development Agency
(GIZ). There is a pan-African Working Group covering the theme of ―Governance‖. One
member of the WG is the Executive Secretary of the LVFO and another is ex-Director of
Fisheries, Kenya now sited in the African Union, Nairobi. These appear to be the most useful
entry points for further discussion on the establishment of an RBN Secretariat.
Training for Regional Beach Management Unit Network (RBN) in East Africa
150 Project Funded by the European Union A project implemented by (Harewelle International Limited)
7.3 Module 3- Session 2
7.3.1 Training Session Plan
Module 3 – Session 2 Date: 3rd
Aug 2012 Duration: 6hr 45 mins
Title: Writing a project proposal included in the RBN Strategic Plan
Objectives:
Leave the training venue with at least one completed project proposal to be presented to
identified development partners;
Have a better understanding of the core structure of a project proposal and how to write
one.
Gained experience in writing a proposal.
Content: Training Points Methods Time
Introduction Overview of session Q&A 15 min
Development Develop structure of proposal
Develop structure of proposal
Write the proposal
Information
sheets,
Plenary
Q&A,
Trainee
review &
analyses
6h 15 min
Conclusion Recap of main points, address any queries Q&A 15 min
Training materials: Hand outs, Flip charts, Flip chart pens
Evaluation: Q & A
7.3.2 Trainers Notes
Opening Session p.1
Trainer Trainee
Introduction (15 min) Seek consensus on writing one proposal on
setting up the RBN office and Secretariat.
Overview and discussion on procedure for
writing proposal.
Receive overview and proposed logistical
procedure for running the day and making
proposals by members. Discuss and give
consensus decision on suggested method.
Q&A
Development (6h 15 min)
Develop structure of proposal
In plenary, plan the structure of the proposal
in terms of headings – refer to Session1
Information Sheet 1 (20 min).
Review Session 1 Information Sheet 1 and
use it to agree on section heading appropriate
for the selected proposal.
Q&A
Develop broad content of proposal:
In plenary, plan the overall content of the
proposal by using bullet points under each
Q&A; analyse section headings and suggest
bullet points for each section in the proposal.
Q&A
Training for Regional Beach Management Unit Network (RBN) in East Africa
151 Project Funded by the European Union A project implemented by (Harewelle International Limited)
heading (60 min).
Write the proposal:
Split into 3 groups of 3 persons, with 1
person from each country and write one
section each of the proposal. Once
completed, write the next section of the
proposal until proposal is completed.
Facilitate each group during the day in
completing the proposal.
Note – writing will be by pen except for one
group where a personal laptop may be
available. It will therefore need to be typed as
each section is finished. (4 h 55 min).
Split into 3 groups of 3 persons, with 1
person from each country and write one
section each of the proposal. Select a leader
author – agree broad narrative and begin
writing. Once finished, select another section
and repeat process.
Q&A
Conclusion (15 min)
Recap of main points, address any queries Q&A
Training materials: Hand outs, Flip charts,
Flip chart pens; cards, pens
Evaluation: Confirm all are clear on topics
discussed
Q&A
7.3.3 Training Aids
Information Sheet No.1, Module 3 Session 1.
7.3.4 Reference Material
No additional reference material is needed for this session.
7.4 End of Day Evaluation of Training
The methodology described in Section 5.3 was applied at the end of day 2 of the course (see
Section 5.3 for evaluation form template)
Training for Regional Beach Management Unit Network (RBN) in East Africa
152 Project Funded by the European Union A project implemented by (Harewelle International Limited)
ANNEX 15 EVALUATION OF RBN TRAINING
SUMMARY EVALUATION FORM 3
Training Title: Training the Regional Beach Management Unit (RBN) in East Africa
Place: WIFIP Headquarters, Kisumu, KENYA
Date and duration: 30th
July – 4th
August (6 days)
Reference project number: EA-4.1-B18
Evaluation criteria V.
Good
(%)
Good
(%)
Fair
(%)
Poor
(%)
Overall course evaluation 33 67
Definition of the course objectives 89 11
Clarity of the lectures / presentations 100
Balance presentations / discussions 38 62 Facilitation by the trainer (Dr James Scullion) 89 11
Interest generated by the sessions 33 56 11
Applicability of subject matter for your work 56 44
Have your expectations been met? 45 55
Duration of the workshop 56 33 11
General organization (enrolment, conf. room, etc.) 23 55 22
Facilities at the training centre (rooms, food, conf. room etc.) 50 50
Specific sessions evaluation
Day1 Module 1 Session 1 Strategic Planning Introduction – vision,
mission
45 55
Module 1 Session 2 Strategic Plan: Result 1 – Financing RBN;
Office & Secretariat etc.
45 55
Day 2 Module 1 Session 3 Strategic Plan: Result 3 – RBN Effective
in Fisheries Co-management
55 45
Module 1 Session 4 Strategic Plan: Result 2 – Effective
Communication & Promotion
55 45
Module 1 Session 5 Strategic Plan: Result 4 – Effective
Advocacy –Introduction
45 55
Module 1 Session 6 Strategic Plan: Result 5 – Business
Development Improved
75 25
Day 3 Module 1 Session 7 Strategic Plan Logframe – OVIs;
verification sources; assumptions
78 22
Module 2 Session 1 Advocacy: Introduction 78 22
Day 4 Module 2 Session 1 Advocacy: Prioritisation of Advocacy
Issues (incorporate into Plan)
67 33
Module 3 Session 1 Project Proposal Writing: Introduction 55 45
Day 5 Module 3 Session 1 Project Proposal Writing:
Writing a proposal from RBN Strategic Plan
33 67
Training for Regional Beach Management Unit Network (RBN) in East Africa
153 Project Funded by the European Union A project implemented by (Harewelle International Limited)
Comments and Suggestions for improvement on training course by RBN members:
There were detailed comments from 5 of the 9 RBN members with 2 evaluation forms having
no additional comments – possibly the Tanzanian members since the form was in English. An
interpreter helped in translation for completing the form for those who needed it.
The comments were all fairly general and highly complimentary about the trainer. The only
suggestion was that they should have more training like this course. They appreciated the
pace taken and personal attention given by the trainer. One trainee noted that they were given
a chance twice during training to put their advocacy into practice – once when the TV and
press arrived and again when they met the team from the Nile perch Traders Network of
Kenya.
One participant praised the efforts of WIFIP and the interpreter for making the course run
smoothly.
Training for Regional Beach Management Unit Network (RBN) in East Africa
154 Project Funded by the European Union A project implemented by (Harewelle International Limited)
ANNEX 16 PHOTOGRAPHS OF RBN TRAINING
RBN: 9 members wearing RBN T-shirts
RBN logo RBN slogan
Certificate awards by Provincial Director of Fisheries, Michael Obadha, to RBN some members
RBN members during training course
All photographs taken at WIFIP offices, Kisumu, Kenya by Dr Jim Scullion on 4
th August 2012
Training for Regional Beach Management Unit Network (RBN) in East Africa
155 Project Funded by the European Union A project implemented by (Harewelle International Limited)
ANNEX 17 RBN STRATEGIC PLAN
Training for Regional Beach Management Unit Network (RBN) in East Africa
156 Project Funded by the European Union A project implemented by (Harewelle International Limited)
LAKE VICTORIA REGIONAL BEACH
MANAGEMENT UNIT NETWORK
THREE-YEAR STRATEGIC PLAN
JULY 2012 – JUNE 2015
Training for Regional Beach Management Unit Network (RBN) in East Africa
157 Project Funded by the European Union A project implemented by (Harewelle International Limited)
TABLE OF CONTENTS
1. INTRODUCTION ............................................................................................................................. 158
2. THE STRUCTURE OF THE RBN ................................................................................................... 158
3. PROCESS FOR MAKING THE RBN STRATEGIC PLAN ........................................................... 160
4. PLANNING LINKAGES BETWEEN BMU NETWORKS ............................................................. 160
5. RBN VISION AND MISSION STATEMENTS ............................................................................... 160
6. STRUCTURE OF THE PLAN ......................................................................................................... 161
6.1 GOAL OF STRATEGIC PLAN .......................................................................................................................... 161 6.2 PURPOSE OF STRATEGIC PLAN ...................................................................................................................... 161 6.3 RESULTS OF STRATEGIC PLAN ....................................................................................................................... 162 6.4 ACTIVITIES OF STRATEGIC PLAN .................................................................................................................... 166
7. THE BUDGETED STRATEGIC PLAN .......................................................................................... 168
8. MONITORING PLAN ...................................................................................................................... 175
Training for Regional Beach Management Unit Network (RBN) in East Africa
158 Project Funded by the European Union A project implemented by (Harewelle International Limited)
1. INTRODUCTION
Community Beach Management Units (BMUs) were established throughout Lake Victoria as
the fundamental basis of adopting a fisheries co-management approach in which legally
recognised BMUs work in close partnership with government and the private industrial fish
processors and exporters. Unrealistically high expectations continue to be placed on BMUs to
resolve the century-old problem of non-compliance to fisheries regulations. BMUs acting
alone can do little to tackle lake-wide challenges. To do this they need to be linked to one
another. This was achieved through the formation of BMU Networks. These are associations
of BMUs established at levels coinciding with levels of government which have planning,
decision-making and budgeting authority. The Regional BMU Network is the apex body of
all lower the BMU Networks and 1,069 BMUs on the lake with a membership of over
215,000 people working in fisheries.
The RBN came into existence at its inauguration in February 2010 in Jinja, Uganda. Since
then, it has struggled to mobilise and become operational. Key challenges face its growth and
development, the most crucial of which is financing RBN activities. A second is the urgent
need to raise the RBN profile and image nationally and internally within Africa and beyond.
A third is the need to demonstrate to its BMU members at fish landing sites that the RBN is
capable of delivering effective services that bring benefits to them. The RBN 3-year Strategic
Plan, 2012 – 2015 is an important step along the path to meeting these challenges and
enabling the RBN to be recognized as ―the Champion of all BMUs on Lake Victoria‖. It aims
to do this by uniting BMUs across borders and by providing a single voice to articulate the
interests and concerns of grassroots fisheries communities around the lake. The RBN will
stand up and lobby forcefully wherever and whenever the need arises in the interests of its
members.
2. THE STRUCTURE OF THE RBN
The structure and functions of the RBN are founded upon a pyramidal system of lower BMU
Networks and the BMUs themselves (Figure 1). The 1,069 BMUs on the lake organised
themselves into higher level networks set up to coincide with different levels of government
planning and budgeting with the aim of integrating their plans into the broader government
development plans at each level of administration. The level immediately above the BMUs
varies between countries. In Tanzania, it is Village BMU Network (VBN) where there is
more than one BMU in Village. In 2007, 68 Village BMU Networks were formed, 32 in
Mwanza, 23 in Kagera and 13 in Mara Regions This level is not present in the Networks of
Kenya and Uganda.
The next administrative level up in Tanzania is the Ward which is broadly equivalent to the
Location in Kenya, and the Parish in Uganda. In 2007, 129 Ward BMU Networks (WBN)
were formed in Tanzania, with 64 in Mwanza, 38 in Mara and 27 in Kagera Regions. In
Kenya, 71 Location BMU Networks (LBN) were formed whilst in Uganda, Networks were
formed at the level above Parish which is Sub-county and 44 Sub-county BMU Networks
(SBN) were formed. In Kenya, networks were also formed at the next level above Location,
called the Division. Here, 25 Division BMU Networks (DivBN) were formed. At District
level, 8 District BMU Networks (DBN) were formed in Kenya, 12 in Tanzania and 11 in
Uganda. One National BMU Network (NBN) was formed in each Partner State.
Training for Regional Beach Management Unit Network (RBN) in East Africa
159 Project Funded by the European Union A project implemented by (Harewelle International Limited)
Figure 2 BMU Networks on Lake Victoria
Source: RBN Operating Procedures, February 2010
Three representatives of the National BMU Networks from each Partner State are nominated
to the regional level to serve as members of the RBN. At the first meeting of the RBN held in
February 2010, the members elected a chairperson, assistant–chairperson, secretary and
treasurer. 30% of the members of the RBN are women.
Training for Regional Beach Management Unit Network (RBN) in East Africa
160 Project Funded by the European Union A project implemented by (Harewelle International Limited)
3. PROCESS FOR MAKING THE RBN STRATEGIC PLAN
In 2011, the three NBN chairmen received training in institutional and organizational
development in their capacity as members of the RBN. The technical training support was
provided as part of the EU ACP FISH II programme coordinated through its Regional
Facilitation Unit in Kampala, Uganda. Follow-on training needs were identified by the RBN
for all its 9 members. One of these included strategic planning and how to make a 3-5 year
strategic plan. As a result, in July-August 2012, a further 5-day technical training support was
provided by the same programme to the 9 RBN members on this topic. This first RBN
Strategic Plan, July 2012 – June 2015 was prepared during training.
4. PLANNING LINKAGES BETWEEN BMU NETWORKS
The RBN Strategic Plan operates under wider plans such as the national strategic plans of
each Partner State and national fisheries sector plans. On Lake Victoria, there is the Fisheries
Management Plan, 2009 – 2014 (FMP2) which is designed to guide overall direction,
activities, investments and allocation of resources directed at fisheries on the lake. In order to
effectively implement the RBN Strategic Plan, there must be strong linkage and cohesion
between action plans at lower levels of BMU Networks down to individual grassroots BMU
plans. The RBN has a crucial role to play in ensuring close linkage between 3-year regional
strategic plan and the national, (County), district and sub-district annual actions plans of
BMU Networks. The 9 RBN members are unique in being the only individuals on Lake
Victoria who serve as members of all BMU planning committees (Networks) from the beach
to international level. The major benefit of completing a Training of Trainers (TOT) course is
that the RBN members then become trainers for 33 members in the 3 NBNS who in turn
become trainers for lower Networks. In this way, capacity building in planning cascades
downwards through the pyramidal structures to ultimately reach people in BMUs. This is
essential for the implementation of linked BMU Network plans.
The RBN budgeted strategic plan provides the umbrella framework for all lower level
budgeted annual action plans. A series of meetings of BMU Networks at each administrative
level will be held to develop their own work plans and operating costs, led by the National
BMU Network followed by the (County in Kenya), district and sub-district Networks.
5. RBN VISION AND MISSION STATEMENTS
The RBN developed its Vision and Mission Statements in Kisumu, Kenya in July 2012, as
part of training support provided by the EU ACP FISH II programme.
Vision Statement
Thriving East African fisheries bringing social and economic benefits to all members of
Beach Management Units served by their efficient and supportive associations in partnership
with industrial fisheries enterprises and government.
Mission Statement
The Regional Beach Management Unit Network is an international association that serves the
interests of a quarter of a million members on Lake Victoria by acting as their united voice,
fighting for their rights, lobbying for their livelihood and business interests based on well co-
managed fisheries.
Training for Regional Beach Management Unit Network (RBN) in East Africa
161 Project Funded by the European Union A project implemented by (Harewelle International Limited)
6. STRUCTURE OF THE PLAN
The format and terminology used for strategic planning varies between organisations and
donor agencies. In developing the RBN plan, the following headings for different planning
levels were adopted by members:
Goal:
The RBN contributes to achieving this but is not accountable for its delivery on its own – its
achievement is dependent on the activities other external programmes.
Purpose:
The RBN is accountable for delivery of the Purpose of the Plan and its performance is
evaluated against successful delivery of the Purpose.
Results:
These are also called Outputs or Objectives. They are the key sub-aims of the Plan and all
need to be achieved in order to achieve the Purpose. In the RBN Strategic Plan, there are five
Results numbered 1 to 5.
Activity Areas:
Activity areas are groups of related activities. Successful implementation of all activity areas
is needed to achieve each Result. Activity areas are numbered according to the respective
Result number e.g. 1.1, 1.2, 1.3 etc.
Activities:
These are the actions needed to achieve each Activity Area and are numbered according to
the number of the respective Activity Area e.g. 1.1.1, 1.1.2, 1.1.3 etc. Often, Strategic Plans
stop at the level of Activity Area but the RBN decided to plan down to the next level i.e.
activities to facilitate linkage of the plan to Annual Action Plans of lower level BMU
Networks.
6.1 Goal of Strategic Plan
The Goal is:
“To contribute to the fisheries sector’s role in sustainable economic growth, poverty
reduction and improved livelihoods in Kenya, Tanzania and Uganda”.
6.2 Purpose of Strategic Plan
The Purpose is:
“to co-ordinate, represent and strengthen the livelihood and business interests and actions
of BMU members and their Networks in the sustainable production, processing and
marketing of high quality fish products from well co-managed fisheries compliant with
national and international standards and laws”.
Training for Regional Beach Management Unit Network (RBN) in East Africa
162 Project Funded by the European Union A project implemented by (Harewelle International Limited)
6.3 Results of Strategic Plan
The Results from the activities carried out over a three year period covered by this plan are as
follows:
Result 1: Effective RBN Financing & Operations
Result 2: Effective Communication & Promotional Systems
Result 3: RBN Effective in Fisheries Co-Management
Result 4: Effective RBN Advocacy
Result 5: Business Development Improved
All Results need to be achieved in order to achieve the Purpose of the Plan. The key
components of each Result are summarised below.
Result 1: Effective RBN Financing & Operations
This Result is concerned with overcoming the greatest bottleneck currently facing the BMU –
the issue of sustainable financing. The RBN Operating Procedures are clear on this issue: the
RBN ultimately will be self-financed by its very many members (over 215,000) contributing
a little each for its operations.
To achieve this is a major challenge, especially when the RBN is geographically far-removed
from most landing sites. It is also a challenge to convince the average BMU member that the
RBN is bringing benefits back to him/her that are worth paying for.
There is a vicious circle here, where without funds to operate, the RBN is struggling to
deliver services to its quarter of a million BMU members at landing sites – consequently, the
BMUs are reluctant to pay for the RBN activities or even those of the nearer National BMU
Network.
To escape this strangle-hold on progress, a second option is required. This is an option which
again is outlined clearly in the RBN Operating Procedures – that is to seek temporary support
from partners in development. To achieve this requires improving the skills of RBN members
in designing and writing project proposals. This is a gap identified by the RBN in 2011 that
needed training support. The latter was delivered alongside planning training for all RBN
members in August 2012.
This Result is also concerned with setting up a permanent Secretariat of the RBN to enable
this international organization to operate efficiently and in a well-coordinated manner to
effectively implement its Strategic Plan. To achieve this aim, a RBN Secretariat needs to be
provided with a furnished and well-equipped office and complement of two staff members to
begin operations. Donor support is needed to establish this regional headquarters and support
the running costs in its first two years of operation whilst a more sustainable system of self-
financing is set up.
The Secretariat staff will require strengthening of skills in key areas to ensure smooth
delivery of Strategic Plan outputs. These include training in financial
Training for Regional Beach Management Unit Network (RBN) in East Africa
163 Project Funded by the European Union A project implemented by (Harewelle International Limited)
management/accounting, work planning, monitoring, production of progress and planning
reports and project formulation up to the point of submission of proposals for investment by
development partners.
The legal basis of the RBN remains unclear and appears weak. It is essential to have clear
legal identity and so under this Result, technical assistance will be sought by hiring a legal
expert to draft a private members bill of the East African Legislative Assembly (EALA)
giving legal identity to a Regional BMU Network as an EAC institution under which will be
sited the RBN, other international BMU Networks and National BMU Networks in each of
the Partner States. This is an aim in consonance with the growing interest in setting up an
inter-governmental East African fisheries administration covering both inland and marine
waters.
Also included in this Result is the holding of regular RBN progress and planning meetings, at
least twice per year and the mentoring by RBN trained members of lower Networks such as
the NBNs and DBNs and the newly emerging County BMU Networks in Kenya (CBNs).
Result 2: Effective Communication & Promotional Systems.
The RBN needs to raise its profile and improve its public image at national and international
levels. It needs to well-known around the lake and beyond its shores. This involves the RBN
members becoming more pro-active to engage in meaningful but low-cost activities. To do
this they need to rely on email communication wherever possible, even in the more remote
areas around the lake. The planned activities include producing different forms of
information and promotional materials at regular intervals.
One of the immediate outputs will be a simple regional email newsletter to publicise to
members and other stakeholders the latest news and current activities of the BMU Network.
It involves training in information packaging and dissemination using a variety of media
forms and channels but with special focus on developing a regional website for which
external support is needed. International networking by participation in meetings,
conferences, exhibitions and shows is an extremely important function of the RBN in order to
raise its profile and influence inside and outside Africa. Another way of doing this is by
applying for membership of international and global fisheries NGOs that serve as a voice for
small-scale fisheries around the world.
The RBN needs to know exactly who it is. It will therefore collate the details of all its BMUs
and BMU Networks. This type of data collection from grassroots to RBN is a challenge and
members see that technological developments in mobile telephony offers a potential solution
to information transfer within the BMU Network system. This will be explored as part of
activities in Result 2.
Result 3: RBN Effective In Fisheries Co-Management.
This Result concerns the greatest challenges facing commercial fisheries in the region, those
of overfishing, illegal fishing and illegal fish trading. The main focus of effort must be
directed towards addressing the very serious immediate threats to the Nile perch stock.
Extremely urgent action is required from the three national Competent Authorities to ensure
the eradication of illegal trade in undersized Nile perch to domestic and regional markets,
especially in the Democratic Republic of Congo. There is clear evidence that a sense of
Training for Regional Beach Management Unit Network (RBN) in East Africa
164 Project Funded by the European Union A project implemented by (Harewelle International Limited)
urgency is lacking in governments. The complete failure to fund and start the much-lauded
―Operation Save Nile Perch‖ (OSNP) announced at the Emergency Meeting of the LVFO
Council of Ministers in November 2009 is a prime example of government inertia to meet
challenges of the day.
The private sector must therefore act quickly to increase pressure on governments to take
necessary and strong actions. For its part, the RBN has planned to implement a series of
significant actions over the next 3 years. The first action area is to reintroduce harmonisation
of fisheries policies, laws, guidelines and plans. There have been worrying signs, especially
in the last 2 years, of individual countries going their own way without consulting and
harmonizing with their Partner States before making policies, guidelines and laws affecting
Lake Victoria fisheries. The RBN will gather fisheries management, environmental and
related priority concerns of their members from grassroots BMUs and bring them to regional
level for promotion, support and action.
It is crucial that LVFO convenes statutory meetings of its two regional technical advisory
committees, the Fisheries Management Committee (FMC) and the Scientific Committee
twice per year to enable co-management to operate efficiently and effectively on Lake
Victoria. The last meetings were held in March 2010 but not in 2011. The next meetings are
due towards the end of 2012. The RBN will lobby its government partners to hold meetings
regularly so that the voice of communities can heard and transmitted to the Ministers
meetings. The RBN will also actively participate in other relevant international technical
fisheries meetings to voice the concerns and interests of their members.
The RBN will review, harmonize, promote and coordinate actions to reduce illegal fishing
and fish trade. It has selected two issues for attention this year – the eradication of the illegal
beach seine and the eradication of illegal monofilament nets. The RBN has included
indicators in the logframe of its strategic plan monitoring progress in getting rid of these two
gears from Lake Victoria.
The satisfactory performance of BMUs in adhering to fisheries regulations is vital to
successful fisheries management. There is a harmonized method for evaluating the
performance of individual BMUs set out in the regional BMU Guidelines for Lake Victoria.
The monitoring framework was implemented once in 2007 under the IFMP project but not
since then. Governments are supposed to support and implement monitoring every year but
have not been able to do so. The RBN will therefore design its own system for self-
monitoring BMU co-management performance and co-ordinate its implementation by BMU
Networks.
Result 4: Effective RBN Advocacy.
This Result deals with advocacy strategies and skills. It encompasses a wide range of issues
whose nature will change as developments emerge and fade in importance. Advocacy is an
integral part of business operations and development, and often operates in subtle and
complex ways. This is a key area of activity for RBN members and undoubtedly is a core
function of the RBN. To guide the process, training in advocacy for RBN members is
included in the plan and has already been implemented with support from the EU ACP FISH
II programme in 2012. Further support will be needed in this area. A strategy has been
developed by the RBN, the results of which are incorporated in the plan as prioritised
Training for Regional Beach Management Unit Network (RBN) in East Africa
165 Project Funded by the European Union A project implemented by (Harewelle International Limited)
advocacy issues requiring immediate attention and setting out ways in which they will be
addressed. Three key issues for action in 2012 are:
A) The urgent need for national legislation explicitly recognising the BMU Networks
at all levels. Without this legal footing, the Networks remain vulnerable and their
credibility is open to question to those who may oppose the aims of the Strategic Plan.
B) The urgent need for increased price transparency at all points along the Nile perch
market chain from fishing boat to final foreign markets. If all stakeholders had
knowledge of the fish pricing system from the lake to supermarkets in Europe there
would be less conflict when sudden price changes arise in global markets leading to
reduced prices for the producer fishermen.
C) The urgent need to eradicate the tendering of fisheries tax collection in Tanzania
and Uganda which exploits fisheries businesses and their labour force by over-taxing
by private tenderers for their own massive profit. The RBN will lobby forcefully for
this system to be replaced by the introduction of the Landing Site User Fee (LSUF).
In Uganda, the LSUF was part of the Fisheries Bill since 2004 but the Bill has still not
reached Parliament – 8 years later. The RBN will pressurise for this to be done. In
Tanzania, the idea of the LSUF has not been raised or debated. The RBN will support
a process to do this.
From the list of three priority advocacy issues, it is clear that two (A and B) are designed to
bring direct benefits to individual fishermen and women in BMUs. Such delivery of service
by the RBN to its members is vital. It is also needed as a way of convincing BMU members
that the RBN is worth paying for by them.
The establishment of the RBN opens up new pathways for BMUs to engage at international
level and their geo-political significance is likely to expand rapidly as a result of this
engagement, including the RBN taking up the role as a ―champion‖ of BMUs on Lake
Victoria.
Result 5: Business Development Improved.
This result is concerned with revealing the significance of fisheries in terms of Small and
Medium Enterprises (SMEs) of business and in taking a business development approach to
fisheries. This is an innovative approach, rarely taken seriously in the past. Consequently, the
small-scale fisheries sector has been seriously neglected by government and development
partner business development service programmes.
The Result has 3 components; the first involves the RBN is gathering much-needed baseline
on the number of small and medium sized fisheries businesses and their labour force
operating at all the fish landing sites on the lake. It will do this by a simple questionnaire sent
for filling by all BMU Chairpersons. Once data are gathered and analysed, results will be
published and disseminated in the RBN Newsletter and Information Sheets as starting points.
The second component involves the improvement of business development skills through
training by business experts who have undergone an induction course on fisheries. They will
then provide training for BMUs and BMU Networks in business development and operation.
A set of selected Business Analysts will examine fisheries businesses in each country and
Training for Regional Beach Management Unit Network (RBN) in East Africa
166 Project Funded by the European Union A project implemented by (Harewelle International Limited)
provide expert advice on how to improve business efficiency and profits. The experts will
return to the same businesses after some months to assess uptake and impacts of the business
advice. The results will be reviewed and disseminated in a final stakeholder meeting.
The third component is phase to start later and involves the promotion of favourable business
environment for SMEs and increased transparency and access to fish prices at all levels in
market chains. It will also explore and exploit new business opportunities at all points along
the value chain for members.
6.4 Activities of Strategic Plan
Activities under Result 1: Effective Financing & Operations
1.1 Set up self-financing by BMUs
1.1.1 Develop self-financing procedures
1.1.2 Gain consensus of BMUs for procedures & rates of pay
1.1.3 Set up RBN financial management procedures
1.1.4 Open RBN bank account
1.1.5 Annual external audit of RBN accts
1.2 Obtain donor financing
1.2.1 Develop regional project proposals & submit to donors
1.2.2 Find possible donors & submit proposals
1.3 RBN meetings
1.3.1 Training for RBN members in planning, project design &advocacy
1.3.2 Hold two progress & planning meetings a year.
1.3.3 Support NBNs, CBNs & DBNs in making budgeted plans
1.4 RBN office established
1.4.1 Office location agreed, equipped & opened
1.4.2 Office operations
1.5 RBN Secretariat established
1.5.1 Job descriptions made, job adverts published
1.5.2 Candidates interviewed, recruited
1.5.3 Staff salaries
1.5.4 Staff allowances
1.5.5 Operating Procedures for Secretariat
1.5.6 Training in financial management for RBN members & Secretariat
1.5.7 Develop project proposal & hire firm for training Secretariat in planning,
monitoring, progress reporting & making project proposals
Activities under Result 2: Effective Communication & Promotional Systems
2.1 Promotional & Information materials
2.1.1 RBN electronic Newsletter
2.1.2 Brochures, information sheets
2.1.3 Press articles
2.1.4 Radio & TV
Training for Regional Beach Management Unit Network (RBN) in East Africa
167 Project Funded by the European Union A project implemented by (Harewelle International Limited)
2.1.5 Social electronic networking e.g. U-tube, Facebook etc.
2.2 RBN website development
2.2.1 Develop TOR, hire TA
2.2.2 Website development & training Secretariat
2.3 International meetings & events
2.3.1 Present RBN at international shows & exhibitions.
2.4 Expand international networks
2.4.1 Gain membership of international NGOs
2.5 Information flows within BMU Networks & partners
2.5.1 Compile & transmit membership details of all BMU Networks.
2.5.2 Compile & transmit details of meetings of lower BMU Networks.
2.5.3 Transmit minutes of RBN meetings, plans etc.
2.6 Mobile telephony for information systems
2.6.1 Identify uses of telephony for RBN activities
2.6.2 Set up mobile telephony pilot initiative
Activities under Result 3: RBN Effective In Fisheries Co-Management
3.1 Contribute to the development, review and co-ordination of implementation of
harmonized regional fisheries plans, policies and legislation.
3.1.1 Compile regional fisheries management priorities of BMUs and propose actions.
3.1.2 Participate as a member of the LVFO regional technical advisory committees to
represent BMU views in co-management.
3.1.3 Participate in international technical fisheries meetings.
3.1.4 Review and harmonize actions to reduce illegal fishing and fish trade.
3.2 Self-monitoring of BMU co-management performance
3.2.1 Design an annual self-monitoring & evaluation system.
3.2.2 Compile, analyse & transmit results of annual BMU self-monitoring &
evaluation.
Activities under Result 4: Effective RBN Advocacy
4.1 Development of advocacy strategy
4.1.1 Training of RBN in making advocacy strategy
4.1.2 Develop a RBN advocacy strategy
4.1.3 RBN members guide their own NBNs, CBNs & DBNs in prioritising advocacy
issues
4.2 Prioritise advocacy issues
4.2.1 National legislation recognising the BMU Networks at all levels.
4.2.2 Price transparency at all points along the Nile perch market chain from fishing
boat to final foreign markets.
4.2.2 Eradication of the tendering of fisheries tax collection in Tanzania and Uganda.
Training for Regional Beach Management Unit Network (RBN) in East Africa
168 Project Funded by the European Union A project implemented by (Harewelle International Limited)
Activities under Result 5: Business Development Improved
5.1 Improve information on fisheries businesses
5.1.1 Design self-recording system of fisheries business enterprises & labour force.
5.1.2 Coordinate implementation of self-recording of numbers and types of fisheries
business enterprises & labour force.
5.2 Improve business development skills
5.2.1 Design project for business development training.
5.2.2 Training of BMU Networks in business development.
5.2.3 Fisheries businesses in BMUs analysed & improved by BDS specialists.
5.3 Improve business development options
5.3.1 Promote favourable business environment for SMEs & increased transparency
and access to fish prices at all levels in market chains.
5.3.2 Explore and exploit new business opportunities at all points along the value
chain for members.
7. THE BUDGETED STRATEGIC PLAN
Training for Regional Beach Management Unit Network (RBN) in East Africa
169 Project Funded by the European Union A project implemented by (Harewelle International Limited)
Table 1 Lake Victoria Regional Beach Management Unit Network Budgeted Strategic Plan, July 2012 –June 2015
Ref No Activities Details Annual Costs ($) Self-
Fundin
g by
RBN
Donor
Fundin
g
Needed
Total
Cost
($)
Priority
1 =
highest 2012-
2013
2013-
2014
2014-
2015
1 EFFECTIVE FINANCING &
OPERATIONS
1.1 Set up self-financing by BMUs
1.1.1 Develop self-financing procedures 1 RBN 2-day meeting to
agree & make Info Sheet
for BMUs
1,800 1,800 0 1,800 1
1.1.2 Gain consensus of BMUs for procedures &
rates of pay
DBN print Info Sheets for
BMUs
0 1
1.1.3 Open & run RBN bank account Bank charges 25 25 25 75 0 75 1
1.1.4 Annual external audit of RBN accts Local auditor fee: 1
audit/year
500 500 500 300 1,200 1,500 2
1.2 Obtain donor financing
1.2.1 Develop regional project proposals &
submit to donors
Do in FISH II training July
2012 & later RBN meetings
0 1
1.2.2 Find possible donors & submit proposals RBN allowances for donor
meetings
600 400 300 1,300 0 1,300 1
1.3 RBN planning meetings 0
1.3.1 Training for RBN members in planning,
project design &advocacy
EU ACP FISH II
programme support (grant
aid)
45,000 45,000 45,000 1
1.3.2 Hold two progress & planning meetings a
year address key issues e.g. Network
registration & certificates, legal identity of
Networks; review Operating Procedures;
harmonise functions (Kenya differ in 2012)
2 RBN 2-day meetings –
allowances
1,800 1,800 3,6000 0 3,600 1
Training for Regional Beach Management Unit Network (RBN) in East Africa
170 Project Funded by the European Union A project implemented by (Harewelle International Limited)
1.3.3 Support NBNs, CBNs and DBNs in making
budgeted plans
RBN members mentor at
NBN, CBN & DBN
meetings: lower networks
fund own meetings
0 1
1.4 RBN office established 0
1.4.1 Office location agreed, equipped & opened Rent, services & equipment 8,000 1,000
1,000 10,000 10,000 1
1.4.2 Office operations Stationary, consumables 3,000 3,500 4,000 2,100 8,400 10,500 1
1.5 RBN Secretariat established 0
1.5.1 Job descriptions made, job adverts
published
Adverts in 3 national press 1,000 200 800 1,000
1
1.5.2 Candidates interviewed, recruited 1 day meeting of RBN for
interviews
2,000 400 1,600 2,000 1
1.5.3 Staff salaries 2 staff members 36,000 37,000 38,000 22,200 88,800 111,000 1
1.5.4 Staff allowances Travel & subsistence 2,000 5,000 6,000 2,600 10,400 13,000 1
1.5.5 Operating Procedures developed for
Secretariat
RBN meetings funded in
1.1.1
0 1
1.5.6 Develop project proposal & hire firm for
training in financial management for RBN
& its Secretariat
Local consultancy 10,000 2,000 8,000 10,000 1
1.5.7 Develop project proposal & hire firm for
training Secretariat in planning, monitoring,
progress reporting & making project
proposals
Local consultancy 8,000 1,600 6,400 8,000 1
1.6 Legal identity of RBN attained
1.6.1 Develop a proposal for technical support to
make an EALA private members bill to
recognise a regional BMU network as an
EAC institution
In-house task with RBN
meetings funded in 1.3.2
0 1
1.6.2 Find possible donors & submit proposals Cost of local lawyer 10,000 10,000 10,000 1
1.6.3 Collaborate with legal expert to assist
drafting the bill
3 Meetings with expert by 3
RBN members
1,800 1,800 1,800 1
Training for Regional Beach Management Unit Network (RBN) in East Africa
171 Project Funded by the European Union A project implemented by (Harewelle International Limited)
2 EFFECTIVE COMMUNICATION &
PROMOTIONAL SYSTEMS
2.1 Promotion & Information materials
2.1.1 RBN electronic Newsletter produced RBN produce Newsletter
emailed to Networks &
printed by DBNs for each
BMU
0 1
2.1.2 Brochures, information sheets Design & print costs 1,000 1,000 1,000 600 2,400 3,000 1
2.1.3 Press articles Press allowances 300 300 300 180 720 900 1
2.1.4 Radio & TV Make headlines without
costs
300 300 300 180 720 900 1
2.1.5 Electronic social networking e.g. Utube,
Facebook etc.
0 3
2.2 RBN website development
2.2.1 Develop project proposal/TOR, identify
website developers, hire firm
Project proposal made at
RBN training 2012
0 1
2.2.2 Website development & training Secretariat RBN website design costs
& annual charges
10,000 1,000 1,000 2,400 9,600 12,000 1
2.3 International meetings & events
2.3.1 Promote RBN at international meetings,
shows & exhibitions.
Allowances & travel costs,
promotional materials
500 800 1,000 460 1,840 2,300 2
2.4 Expansion of international networks
2.4.1 Gain membership of international NGOs Membership fees 250 350 400 1,000 0 1,000 1
2.5 Information flow between BMU
Networks & partners
2.5.1 Compile & transmit membership details of
all BMU Networks.
Typing registers in 1st year
only, electronically
thereafter
50 0 0 50 0 50 1
2.5.2 Compile & transmit details of meetings of
lower BMU Networks.
Typing work in 1st year
only, electronically
thereafter
50 0 0 50 0 50 1
Training for Regional Beach Management Unit Network (RBN) in East Africa
172 Project Funded by the European Union A project implemented by (Harewelle International Limited)
2.5.3 Transmit minutes of RBN meetings, plans
etc.
Printing & copying costs of
minutes, electronically
thereafter
100 0 0 100 0 100 2
2.6 Mobile telephony for information
systems
2.6.1 Identify uses of telephony for RBN
activities
Design TOR, hire
consultant
0 7,000 0 1,400 5,600 7,000 3
2.6.2 Set up mobile telephony pilot initiatives Various implementation
costs
0 5,000 10,000 3,000 12,000 15,000 3
3 RBN EFFECTIVE IN FISHERIES CO-
MANAGEMENT
3.1 Co-ordinated & harmonized regional
fisheries policies, legislation guidelines
and plans
3.1.1 Compile regional fisheries management
priorities of BMUs and propose actions.
RBN meetings funded in
1.3.2; airtime; travel
2,000 2,000 2,000 6,000 0 6,000 1
3.1.2 Participate as a member of the LVFO
regional technical advisory committees to
represent BMU views in co-management.
Allowances & travel costs
for 1 RBN member
twice/year
200 200 200 600 0 600 1
3.1.3 Participate in international technical
fisheries meetings.
Allowances & travel costs
for RBN members
twice/year
400 500 600 300 1,200 1,500 2
3.1.4 Review and harmonize actions to reduce
illegal fishing and fish trade.
Allowances & travel costs
for RBN members action
plans
300 400 500 240 960 1,200 1
3.2 Self-monitoring of BMU co-management
performance
3.2.1 Design and agree an annual self-monitoring
& evaluation system.
RBN meetings funded in
1.3.2; other Networks bear
own costs
0 1
3.2.2 Compile, analyse & transmit results of
annual BMU self-monitoring & evaluation.
Printing & copying costs of
minutes, electronically
thereafter
100 0 0 100 0 100 2
4 EFFECTIVE RBN ADVOCACY
Training for Regional Beach Management Unit Network (RBN) in East Africa
173 Project Funded by the European Union A project implemented by (Harewelle International Limited)
4.1 Development of advocacy strategy
4.1.1 Training of RBN in making advocacy
strategy
Funded in 1.3.1 0 1
4.1.2 Develop a RBN advocacy strategy Funded in 1.3.1 0 1
4.1.3 RBN members guide their own NBNs,
CBNs & DBNs in prioritising advocacy
issues
RBN members mentor at
NBN, CBN & DBN
meetings: lower networks
fund own meetings
0 1
4.2 Prioritised advocacy issues
4.2.1 National legislation recognising the BMU
Networks at all levels.
Meetings in each country
with gov, industry, BMUs;
press & TV meetings ($100
per meeting)
1,500 0 0 1,500 1,500 1
4.2.2 Price transparency at all points along the
Nile perch market chain from fishing boat
to final foreign markets.
Meetings with gov;
Network meetings;
publicity materials ($500
per country)
1,500 0 0 1,500 1,500 1
4.2.3 Eradication of the tendering of fisheries tax
collection in Tanzania and Uganda.
Meetings with gov;
Network meetings;
publicity materials ($500
per country)
1,500 1,000 0 2,500 2,500 1
5 BUSINESS DEVELOPMENT
IMPROVED
5.1 Improve information on fisheries
businesses
5.1.1 Design self-recording system of fisheries
business enterprises & labour force.
Funded in 1.3.2 0 1
5.1.2 Coordinate implementation of self-
recording of numbers and types of fisheries
business enterprises & labour force.
RBN members mentor at
NBN, CBN & DBN
meetings: NBN, CBN &
DBN fund own meetings
0 2
5.2 Improve business development skills
5.2.1 Design project for business development Funded in 1.3.1 0 3
Training for Regional Beach Management Unit Network (RBN) in East Africa
174 Project Funded by the European Union A project implemented by (Harewelle International Limited)
training.
5.2.2 Training of BMU Networks and BMUs in
business development.
Training services hired 0 70,000 70,000 0 140,000 140,000 3
5.2.3 Fisheries businesses in BMUs analysed &
improved by BDS specialists.
BDS services hired 0 30,000 30,000 0 60,000 60,000 3
5.3 Improve business development options
5.3.1 Promote favourable business environment
for SMEs & increased transparency and
access to fish prices at all levels in market
chains.
Various implementation
costs
1,000 2,000 3,000 1,200 4,800 6,000 2
5.3.2 Explore and exploit new business
opportunities at all points in the value chain
for members.
Various implementation
costs
1,000 2,000 3,000 1,200 4,800 6,000 2
TOTAL 151,775 173,075 174,925 64,355 435,420 499,775
Training for Regional Beach Management Unit Network (RBN) in East Africa
175 Project Funded by the European Union A project implemented by (Harewelle International Limited)
8. MONITORING PLAN
The approach adopted for monitoring the RBN Strategic Plan is based on a Logical
Framework (logframe). The logical framework of this programme is presented in Table 2.
The logframe provides a summary of the overall programme design and a framework for
project planning and monitoring. A simple method was adopted using logical framework
indicators in a semi-quantitative manner to provide a tool for continuous monitoring of
progress and impacts. The method has been successfully tried and tested for four years under
the EU funded IFMP project on Lake Victoria and in an earlier 5-year Integrated Lake
Management (ILM) project in Uganda. The method involves self-scoring of progress made
on achieving each Objectively Verifiable Indicator (OVI). The scoring system has 6 levels of:
1 = completely achieved
2 = largely achieved
3 = partially achieved
4 = achieved only to very limited extent
5 = unlikely to be realised
X = too early to judge extent of achievement
The logframe contains OVIs and their Means of Verification (MOVs) which identify the
sources of information to measure and score each OVI. The logframe also identifies key risks
and assumptions in implementing each Result area of the plan. The logframe will form the
basis of all work planning undertaken as part of plan implementation. The self-scoring of
indicators should be used as part of routine review of progress and planning future activities.
Justification for any change in scoring of indicators will help provide regular detailed
monitoring of plan activities closely aligned to achieving the purpose of the Strategic Plan.
Training for Regional Beach Management Unit Network (RBN) in East Africa
176 Project Funded by the European Union A project implemented by (Harewelle International Limited)
Table 2 Logical Framework of the Lake Victoria Regional Beach Management Unit Network Strategic Plan, July 2012 – June 2015
NARRATIVE OBJECTIVELY VERIFIABLE INDICATORS VERIFICATION SOURCES ASSUMPTIONS
GOAL Contribute to the fisheries
sector‘s role in sustainable
economic growth, poverty
reduction and improved
livelihoods in Kenya,
Tanzania and Uganda
PURPOSE
Co-ordinate, represent and
strengthen the interests and
actions of BMU members
and their Networks in the
sustainable production and
marketing of high quality
fish products from well co-
managed fisheries
compliant with national and
international standards and
laws.
P1. Percentage of BMUs scoring the RBN level of
satisfactory delivery of services to members increases
each year.
P1. BMU Network Annual Action Plans developed by
70% of Networks at District and County levels by end of
June each year.
P3. Nile perch stock does not decrease during 2012 to
end of June 2015.
P4. Profitability of small fisheries businesses increase
annually.
P1. NBN & RBN Self-Monitoring
Inspection Reports; Minutes of RBN
meetings
P2. Minutes of RBN meetings
P.3 LVFO Fisheries Acoustic Survey
reports
P4. Inspection Reports; Minutes of
NBN & RBN meetings
a) International market influences
outside the region do not
undermine sustainable harvesting
of fish resources or the operation of
fisheries businesses.
b) Environmental influences do not
reduce or damage fish stocks.
RESULT 1
Effective RBN financing &
operations
1.1 At least one RBN meeting held each year is financed
by BMUs.
1.2 RBN Annual budgeted work plans developed each
year.
1.3 One RBN grant funded project proposal financed by
donors to establish RBN office by end of June 2013.
1.4 At least 1 RBN Secretariat staff recruited by end of
June 2013.
1.1 Minutes of RBN meetings
1.2 Minutes of RBN meetings
1.3 Minutes of RBN meetings
1.4 Minutes of RBN meetings
a) BMUs willing to pay for BMU
Network meetings and activities.
b) Donors willing to finance RBN
Secretariat office and staff.
Training for Regional Beach Management Unit Network (RBN) in East Africa
177 Project Funded by the European Union A project implemented by (Harewelle International Limited)
NARRATIVE OBJECTIVELY VERIFIABLE INDICATORS VERIFICATION SOURCES ASSUMPTIONS
RESULT 2 Effective communication &
promotional systems
2.1 At least one example of RBN promotional materials
(brochures, information sheet; posters, press article)
produced each year.
2.2 Full BMU Networks register held by RBN by end of
2012
2.3 RBN website developed by end of Dec 2013 and
updated at least at quarterly intervals.
2.4 RBN presentation in at least 1 international
promotional event per year.
2.5 RBN obtains membership of at least one
international fisheries NGO by end of Dec 2012.
2.6 RBN Newsletter produced twice per year.
2.7 One regional telephony information system piloted
by end of June 2014.
2.1 RBN promotion material
2.2 BMU Networks Registers
2.3 RBN website
2.4 Minutes of RBN meetings
2.5 Minutes of RBN meetings
2.6 RBN Newsletter
2.7 Minutes of RBN meetings
a) BMU Network members
committed to sharing information.
b) Donors interested in supporting
development of RBN website.
RESULT 3
RBN effective in fisheries
co-management
3.1 Numbers of illegal beach seines recorded in each of 3
National Fisheries Frame Surveys in 2014 decrease from
previous levels.
3.2 Numbers of illegal monofilament nets recorded in
each of 3 National Fisheries Frame Surveys in 2014
decrease from previous levels.
3.3 RBN participates as a member in LVFO Fisheries
Management & Scientific Committees meetings held
each year from 2012 to 2015.
3.4 The % of BMUs scoring satisfactory performance
levels increases each year.
3.1 National & regional Frame
Survey Reports 2012
3.2 National & regional Frame
Survey Reports 2012
3.3 Minutes of RBN meetings
3.4 NBN & RBN Self-Monitoring
Inspection Reports
a) BMUs willing to comply with
fisheries regulations.
b) There is continued commitment
by EAIFFPA members to comply
with fisheries regulations.
c) There is high level political will
and action to reduce illegal
regional & domestic fish trading &
fishing.
d) LVFO holds regional technical
advisory meetings at its statutory
interval of twice per year.
Training for Regional Beach Management Unit Network (RBN) in East Africa
178 Project Funded by the European Union A project implemented by (Harewelle International Limited)
NARRATIVE OBJECTIVELY VERIFIABLE INDICATORS VERIFICATION SOURCES ASSUMPTIONS
RESULT 4
Effective RBN advocacy
4.1 RBN Advocacy Strategy developed and accepted by
all members by end of 2012.
4.2 At least one key enabling regional fisheries policy or
strategy influenced by RBN each year.
4.3 Harmonisation of at least one fisheries legislation
influenced by RBN each year.
4.4 Harmonisation of at least one guideline influenced by
RBN each year.
4.1 RBN Minutes of meetings
4.2 RBN Minutes of meetings
4.3 RBN Minutes of meetings
4.4 RBN Minutes of meetings
a) Governments committed to
participatory development of
policies, legislation and plans
b) RBN Members sufficiently
motivated to lobby persistently on
behalf of their members
RESULT 5
Business development
improved
5.1 List of all fisheries SMEs on Lake Victoria registered
by BMUs by end of June 2013.
5.2 100% of BMU Networks receive training in business
development and operation by end of June 2014.
5.3 At least 20 fisheries SMEs in each Partner State
receive expert business analysis and advice by end of
June 2014.
5.1 BMU Registers; NBN & RBN
minutes of meetings
5.2 Consultancy reports; NBN &
RBN minutes of meetings
5.3 Consultancy reports; NBN &
RBN minutes of meetings
a) Donors interested in technically
supporting BMUs and BMU
Networks
ACTIVITIES 1.1 Set up self-financing by
BMUs
1.2 Obtain donor financing
1.3 RBN meetings
1.4 RBN office established
1.5 RBN Secretariat
established
1.6 RBN legal identity
established
2.1 Promotional &
Information materials
Training for Regional Beach Management Unit Network (RBN) in East Africa
179 Project Funded by the European Union A project implemented by (Harewelle International Limited)
NARRATIVE OBJECTIVELY VERIFIABLE INDICATORS VERIFICATION SOURCES ASSUMPTIONS
2.2 RBN website
development
2.3 International meetings
& events
2.4 Expand international
networks
2.5 Information flows
within BMU Networks &
partners
2.6 Mobile telephony for
information systems
3.1 Contribute to the
development, review and
co-ordination of
implementation of
harmonized regional
fisheries plans, policies and
legislation.
3.2 Self-monitoring of
BMU co-management
performance
4.1 Development of
advocacy strategy
4.2 Prioritise advocacy
issues
5.1 Improve information on
fisheries businesses
5.2 Improve business
development skills
5.3 Improve business
development options
180 Project Funded by the European Union A project implemented by (Harewelle International Limited)
ANNEX 18 RBN PROJECT PROPOSAL
The Regional Beach Management Unit Network: ―Uniting BMUs Across Borders‖ Page 181
LAKE VICTORIA REGIONAL BEACH
MANAGEMENT UNIT NETWORK
PROJECT PROPOSAL
UNLEASHING THE POTENTIAL OF AN INTERNATIONAL
SMALL-SCALE FISHERIES ASSOCIATION
IN EAST AFRICA
JANUARY 2013 – DECEMBER 2014
Mr Tom Guda
Chairman
Lake Victoria Regional BMU Network
Tel: +254727371074; +254733979942
Email: [email protected]
The Regional Beach Management Unit Network: ―Uniting BMUs Across Borders‖ Page 182
Table of Contents
1. BACKGROUND .................................................................................................................................................. 184
2. GOAL, PURPOSE AND EXPECTED RESULTS ........................................................................................................ 188
3. PROJECT ACTIVITIES ......................................................................................................................................... 188
4. PROJECT TIMING AND DURATION .................................................................................................................... 190
5. PROJECT MANAGEMENT .................................................................................................................................. 194
6. BUDGET ............................................................................................................................................................ 195
5. PROJECT REPORTING ........................................................................................................................................ 198
7. MONITORING AND EVALUATION...................................................................................................................... 199
The Regional Beach Management Unit Network: ―Uniting BMUs Across Borders‖ Page 183
SUMMARY
The project will activate an international, small-scale fisheries association by bringing under the
support and guidance of its international government partner for an initial, temporary period of two
years. The project addresses three problems of high international significance using innovative
approaches implemented by the largest community fisheries association in the world operating on a
single water body. The project area is Lake Victoria, East Africa, shared by Kenya, Tanzania and
Uganda. The issues addressed are of global significance. They concern a) giving fisheries
communities a unified, influential voice in the management of resources upon which their
livelihoods depend; b) bringing a halt to the massive economic losses sustained through poor
fisheries governance, and c) bringing business development services to the multitude of small-scale
fisheries which, until this project, have been severely neglected by government and development
partner programmes. It will also forge a business development approach to fisheries resources
management. The project is undertaken through a partnership between the community-based Lake
Victoria Beach Management Unit Network and the inter-governmental Lake Victoria Fisheries
Organisation. The latter, being highly experienced in planning and implementing regional projects,
will be the lead organisation of the project. The base for the project is at the LVFO Secretariat in
Jinja, Uganda.
The Regional Beach Management Unit Network: ―Uniting BMUs Across Borders‖ Page 184
1. BACKGROUND
1.1 The Project Area
The project area is Lake Victoria – the second largest freshwater lake in the world covering 68, 000
km2 and shared by Kenya (6% of area) Tanzania (51%) and Uganda (43%). There are 195,000
fishermen operating 65,000 fishing boats from 1500 landing sites around the lake shore (Lake
Victoria Regional Fisheries Frame Survey, 2010). These fishermen are the small-scale producer
businesses in a sector based on hunting. They link to an even larger land-based workforce of fish
processors and traders, many of whom are women. It is not yet known precisely how many small and
medium business enterprises (SMEs) are supported by the lakes fish resources (this is on-going work
in hand), but a minimal estimate is over 100,000 of them. The mandate for management of fisheries
and fish stocks is held by the Lake Victoria Fisheries Organisation (LVFO), an international
institution of the East African Community (EAC).
1.2 Implementing Organisations
Lake Victoria Regional BMU Network
The Lake Victoria Regional BMU Network (RBN) has 215,000 members in BMUs around the lake
(IFMP, 2007), making it the largest community-based fisheries organisation in the world operating
on a single water body. It is the apex body of 1,069 Beach Management Units on Lake Victoria
(including 281 BMUs in Kenya, 433 BMUs in Tanzania, and 355 in Uganda). The RBN was
inaugurated in February 2010 in Jinja, Uganda and at that time, members adopted the RBN
Operating Procedures setting out the functions of the organisation. The organisation is registered
under the Lake Victoria Fisheries Organisation (LVFO), itself an institution of the East African
Community (EAC). The RBN members are constituted by democratic elections and nominations of
representatives from respective lower level BMU Networks in each of the 3 Partner States – Kenya,
Tanzania and Uganda. There are 9 RBN members, comprising 3 members (including the Chair,
Secretary and Treasurer) from each country. There are 275 lower Networks aligned to the different
levels of government administrations responsible for development planning and budgeting.
The RBN Vision is:
Thriving East African fisheries bringing social and economic benefits to all members of
Beach Management Units served by their efficient and supportive associations in partnership
with industrial fisheries enterprises and government.
The RBN Mission is:
The Regional Beach Management Unit Network is an international association that serves
the interests of a quarter of a million members on Lake Victoria by acting as their united
voice, fighting for their rights, lobbying for their livelihood and business interests based on
well co-managed fisheries.
The RBN has developed a detailed 3-year Strategic Plan, July 2012 – June 2015, the Purpose of
which is:
―to co-ordinate, represent and strengthen the livelihood and business interests and actions of
BMU members and their Networks in the sustainable production, processing and marketing
of high quality fish products from well co-managed fisheries compliant with national and
international standards and laws‖.
The Regional Beach Management Unit Network: ―Uniting BMUs Across Borders‖ Page 185
Lake Victoria Fisheries Organisation
The Lake Victoria Fisheries Organization was formed through a Convention signed in 1994 by the
East African Community Partner States of Kenya, Tanzania and Uganda as a result of the need to
manage fisheries resources of Lake Victoria in a coordinated manner. The Organisation is an
institution of the EAC whose aim is to harmonise, develop and adopt conservation and management
measures for the sustainable utilisation of living resources of Lake Victoria to optimise socio-
economic benefits from the basin for the three Partner States. The LFVO has a large new
headquarters in Jinja, Uganda which houses its Secretariat. It has managed and implemented several
regional projects including the EU-funded Implementation of a Fisheries Management Plan project
(IFMP) with a budget of €29.9 million. It has an experienced Executive and finance unit as well as
various technical officers.
1.3 Problem Statement
The problems addressed by this project are three-fold and all of very high regional significance:
a) The 1,069 BMUs on the lake are far from being united. There is little national and even less
regional coordination of their concerns, interest and actions. The BMU Networks are young
and fragile and not working efficiently or effectively especially at the higher national and
regional levels. The potential power of having a unified voice and spokesperson via the RBN
to represent the interests of nearly quarter of a million members has not yet been attained and
the RBN is struggling to establish itself as an apex body because of a bottleneck in financing
its activities. Unless there is a dramatic improvement in the governance of lake resources by
bringing the best in the private sector to the forefront of management via an efficient RBN
Secretariat, then the prognosis for successfully addressing all other problems remains bleak.
b) There is massive economic loss from lake fisheries due illegal and damaging fishing and fish
trading practices as well as over-fishing on some key commercial stocks such as Nile perch
and Nile tilapia (LVFO FMP2, 2008). A recent World Bank study on global fisheries,
―Sunken Billions‖ 2009, estimated that $50 billion are lost every year because of poor
governance systems that allow widespread Illegal Unreported and Unregulated (IUU) fishing
to continue with impunity. One of its supporting case studies done on Lake Victoria (Warui,
2008) revealed an annual economic loss of $165 million from the Nile perch fishery alone
due to stock decline caused by IUU fishing. This is a loss of $1.6 billion in the last decade
alone – the figures are staggering and shocking.
c) There is almost total lack of recognition in each of the 3 countries of small-scale fisheries
being the foundation of hundreds of thousands of small and medium business enterprises
(SMEs). Consequently, very little support is given to this sector by government or
development partner business development programmes. The problem also emanates from
within the sector itself, with little attention paid by fisheries stakeholders to the economic and
business aspects of their livelihood strategies. Many of them do not see themselves as
business operators, and consequently are missing opportunities to improve their livelihoods
through increased business efficiencies and development.
1.4 Project Rationale and Beneficiaries
The RBN is aiming to address these three core problems through the implementation of its Strategic
Plan 2012-2015. The plan provides a clear roadmap of where the organisation aims to go and how to
get there.
The Regional Beach Management Unit Network: ―Uniting BMUs Across Borders‖ Page 186
It will address the 3 problems by 3 action areas summarised respectively below:
a) UNITED BMUs TAKE RESPONSIBILITY: The RBN will set up its permanent
Secretariat (RBNS) staffed by a Chief Executive Officer and assistant housed temporarily
within the LVFO Secretariat in Uganda. The size of proposed programme warrants the need
for 2 staff, and additionally, a second also acts as insurance in case one staff member is not
present or no longer available. The skills of the RBNS and relevant RBN members will be
strengthened to ensure efficient delivery of services to members. The RBN and its Secretariat
will prioritise the establishment of a system for self-financing to be in place by the end of the
project period to ensure sustainable operations.
These activities are contained in Result 1 of the project design. The RBNS will co-ordinate
the drive forward of other activity areas of Result 1 including securing legal identity of the
Regional BMU Network. The most sustainable way of achieving this is by having it
recognised as an EAC body by the East Africa Legislature Assembly. This is also in line with
the current debate to establish an inter-governmental East African Fisheries Administration
under the EAC. It is vital that the RBN‘s legal footing is secure ahead of all the other
challenges it aims to address in this project. The RBN will also focus on developing linked
action plans within the Networks from the regional strategic to the grassroots BMU plans.
These are essential for clear steerage and co-ordination at all levels.
Turning plans into actions takes us to the next set of activities under Result 2 of the project.
In order to take co-ordinated actions by BMUs across borders, they must see themselves as
part of a single entity. The RBN must provide this by being more visible and voluble. With a
permanent RBNS, it will produce publicity and guidance materials – brochures, information
sheets, policy guides/briefs. It will be on radio and TV and in the press lobbying on behalf of
members on issues affecting their livelihoods and business. It will be seen as the ―champion‖
of BMUs on Lake Victoria and become well-known amongst fisheries communities and will
gain their respect and trust as they see the RBN fighting on their behalf. The RBN supported
by its Secretariat will reach international level within and outside Africa by networking
through its website and participating in international meetings and conferences.
b) SUNKEN BILLIONS HALTED BY ELIMINATING IUU FISHING: Since the
introduction of fisheries regulations on the lake a century ago, the laws have always been
broken by fishermen. Over the decades, successive governments have tried unsuccessfully to
persuade and coerce fishermen to comply with regulations that conserve fish stocks. After a
century of struggling, the BMUs came into existence under a new co-management approach
with the intention of government that the BMUs should find a way of reducing illegal
fisheries practices. The BMUs are very young – less than 6 years old in their modern form.
But already, there are some in government and academic institutions who say they have
already failed - when in fact they have hardly been given a real chance to start to succeed.
The project will give the BMUs an opportunity, led by a strong and focussed RBN, to begin
to succeed. The problem will be addressed from a new angle – stressing business and
economic and losses and concentrating on the 100,000 or more fisheries SMEs operating on
the lake. The activities addressing this problem cut across Result 3 and 4 of the project.
There are two core activity areas of result 3. The first involves policy advocacy, working
through a variety of mechanisms but primarily through membership of the LVFO regional
advisory technical committees, the FMC and the SC, which are scheduled to meet twice per
The Regional Beach Management Unit Network: ―Uniting BMUs Across Borders‖ Page 187
year. Internal advocacy campaigns targeting BMU members will target key illegal activities
e.g. the elimination of beach seines and the use of monofilament gill nets. These have been
identified as targets in the logical framework of the RBN Strategic Plan.
The second component involves the establishment of a BMU self-monitoring and regulation
system. The idea is taken from an extremely successful self-policing system operated by the
industrial fisheries private sector. Here, industry itself takes punitive measures against any
operator found not complying with agreed rules on the minimum size of fish entering any
factory. This programme has transformed industry making it fully compliant within 3 years of
implementation. In the same way, the RBN plans to introduce a self-policing programme for
BMU operations. The industry programme succeeded because it had full collaboration of
governments. In the same way, the RBN programme will depend on such full collaboration.
c) FISHERIES BUSINESS POTENTIAL ATTAINED: The first step in introducing a more
business-like approach to the fisheries sector on Lake Victoria is to gather baseline data on
the number, distribution and nature of small and medium fisheries businesses operating on
the lake. A wide selection of different types of small-scale fisheries businesses will be
provided with individual analysis of their business operations and expert advice on how to
overcome identified bottlenecks leading to potential increased profits. These activities are
contained in Result 4 of the project design.
The design of the project proposal is very closely aligned to that of the RBN Strategic Plan
2012-2015 to reinforce continuity and sustainability of the overall RBN direction and more
detailed mean of getting there.
The Regional Beach Management Unit Network: ―Uniting BMUs Across Borders‖ Page 188
2. GOAL, PURPOSE and EXPECTED RESULTS
2.1 Goal
Goal of the project is:
―Contribute to the fisheries sector‘s role in sustainable economic growth, poverty reduction
and improved livelihoods in Kenya, Tanzania and Uganda‖.
2.2 Purpose
The purpose of the project is:
―Delivery by the RBN of economic, environmental and governance benefits and services to
its members on Lake Victoria by effective implementation of its Strategic Plan, 2012–2015‖.
2.3 Results
The expected Results of the project are as follows:
Result 1 Effective RBN Secretariat and Operations
Result 2 Effective Communication and Promotion Systems
Result 3 Business Operational Efficiencies Improved
3. PROJECT ACTIVITIES
3.1 Project Implementation
Result 1
1.1 RBN office established: In the first month of the project, a rent-free office will be provided by
the LVFO Secretariat for the RBN Secretariat in Jinja, Uganda. Office furniture and equipment will
be procured using standard LVFO procurement procedures. Office utilities e.g. electricity, will be
offered with the rent-free arrangement. Office running costs e.g. stationary will be procured by the
project via the LVFO finance/procurement unit.
1.2 RBN Secretariat staff recruited: Job descriptions of Secretariat staff will be prepared by the RBN
and advertised in local and regional press in the first month of the project. Applicants will be short-
listed for interview by an RBN selection panel and evaluations will be made using standard LVFO
procedures. Two staff will be recruited, a Chief Executive Officer and an assistant by month 3. The
RBN will develop Operating Procedures for the RBNS learning from LVFO procedures.
1.3 Skills strengthened: of 2 Secretariat staff and 3 RBN members by training in financial
management and accounting learning from the procedures adopted by the LVFO Secretariat. This
will be done in quarters 2 and 3 by hiring a local consultant through a service contract developed by
the RBN and guided by the LVFO finance unit. The selection panel for choosing the consultant will
be made up from the RBN and LVFO.
The Regional Beach Management Unit Network: ―Uniting BMUs Across Borders‖ Page 189
1.4 Skills strengthened: of 2 Secretariat staff and 3 RBN members by training in project planning,
monitoring, reporting and project design. This will be done in quarters 2 and 3 in quarters 2 and 3 by
hiring a local consultant through a service contract developed by the RBN and guided by the LVFO
finance unit. The selection panel for choosing the consultant will be made up from the RBN and
LVFO.
1.5 RBN coordination: Quarterly RBN progress & planning meetings will be held to address key
issues e.g. Network registration & certificates, legal identity of Networks; review RBN Operating
Procedures.
1.6 RBN self-financing: Self-financing procedures will be developed by the RBN and consensus of
BMUs will be gained for procedures & rates of pay; a RBN bank account holding self-finance will
be opened & operated.
1.7 Legal identity of RBN attained: TOR and tender will be prepared for consultancy to produce an
EALA private members bill to recognise a regional BMU Network as an EAC institution; bids will
be short-listed, consultant selected and contract made and signed; RBN will collaborate with legal
expert to assist drafting the bill.
Result 2
2.1 Promotion & Information materials: RBN will produce an electronic Newsletter at regular
intervals; brochures, information sheets, policy briefs, press articles and radio and TV appearances
will be made; electronic social networking e.g. Utube and Facebook will be used to promote BMUs
and their Networks.
2.2 RBN website development: TOR and tender will be prepared for website development; bids will
be short-listed, consultant selected and contract made and signed; RBN members will collaborate
with developer to design website.
2.3 International networking: RBN members will participate in international technical meetings,
global conferences and exhibitions to represent the interests of BMU members; the RBN will acquire
membership of global fisheries NGOs and disseminate information on key issues globally.
Result 3
3.1 Advocacy strategy and campaigns: the RBN will compile regional fisheries management
priorities of BMUs and propose actions; participate as a member of the LVFO regional technical
advisory committees to represent BMU views in co-management; harmonize, coordinate and
promote community-led, lake-wide actions to reduce illegal fishing and fish trade through prioritised
advocacy campaigns to members e.g. eradication of beach seines and monofilament nets.
3.2 Self-monitoring and regulation of BMU co-management performance: RBN members will design
an annual self-monitoring and evaluation and regulation system for BMUs; compile, analyse and
transmit results of annual BMU self-monitoring and evaluation.
Result 4
4.1 Compile baseline fisheries SME data: RBN will design a self-recording system of fisheries
business enterprises and labour force; coordinate implementation of self-recording of numbers and
types of fisheries business enterprises and labour force.
The Regional Beach Management Unit Network: ―Uniting BMUs Across Borders‖ Page 190
4.2 Fisheries SMEs analysis & advice: RBN will design TOR and tender and advertise for project on
provision of business analyses and advice by BDS experts for individual fisheries SMEs; bids will be
short-listed, consultant selected, contract made and signed; consultancy implemented and monitored.
3.2 Project Sustainability
The sustainability of project activities and outcomes is planned in a number of ways. First, the RBN
is aiming to attain self-financing by the end of the project period. This will be achieved through the
design and implementation of financing system by the BMU themselves for their higher Network
activities. The BMU system is currently spreading in East Africa, from the inland shared lakes of
Tanzania and Uganda to their neighbours in the Democratic Republic of Congo, Burundi, Zambia
and Malawi. The BMU system is also spreading along the marine coast of East Africa. The first
National BMU Network has been established in Kenya and more are to follow, especially in
Tanzania and Uganda. The activities of this project proposal are embedded in the RBN Strategic
Plan, 2012 – 2015 which will be updated every three years.
4. PROJECT TIMING AND DURATION
The project will run for two years with an expected start date of 1st January 2013 until 31
st December
2014. The Project Implementation Plan is presented in Table 1.
The Regional Beach Management Unit Network: ―Uniting BMUs Across Borders‖ Page 191
Table 1 Project Implementation Plan
Activities Months
1 2 3 4 5 6 7 8 9 1
0
1
1
1
2
1
3
1
4
1
5
1
6
1
7
1
8
1
9
2
0
2
1
2
2
2
3
2
4
RESULT 1 Effective RBN Secretariat and Operations
1.1 RBN office established
1.1.1 Office opened at LVFO Secretariat, Uganda X
1.1.2 Office equipment and furniture procured and installed X X X
1.2 Office operations
1.2.1 Job descriptions made, job adverts published X X
1.2.2 Candidates interviewed, recruited X
1.2.3 Operating Procedures developed for Secretariat X
1.2.4 Staff salaries X X X X X X X X X X X X X X X X X X X X X
1.2.5 Staff allowances X X X X X X X X X X X X X X X X X X X X X
1.3 Improved Financial management skills of Secretariat & RBN treasurers
1.3.1 Develop TOR and tender for training in financial management & accounting for
Secretariat staff & RBN treasurers
X
1.3.2 Short-list bids, select consultant, make & sign contract X
1.3.3 Implement and monitor training consultancy in financial management & accounting X
1.4 Improved project planning, monitoring, reporting & project design skills of
Secretariat and RBN office holders.
1.4.1 Develop TOR and tender for training for Secretariat staff & RBN office holders X
1.4.2 Short-list bids, select consultant, make & sign contract X
1.4.3 Implement and monitor training consultancy X
1.5 RBN coordination
1.5.1 Hold quarterly progress & planning meetings to address key issues e.g. Network
registration & certificates, legal identity of Networks; review Operating Procedures
X X X X X X X X X
1.5.2 Support NBNs, CBNs and DBNs in making budgeted plans X X X X
1.6 RBN self-financing
1.6.1 Develop self-financing procedures X X X
1.6.2 Gain consensus of BMUs for procedures & rates of pay X X X X X X X X X X X X X X X
1.6.3 Open & operate RBN bank account holding self-finance X X X X X
The Regional Beach Management Unit Network: ―Uniting BMUs Across Borders‖ Page 192
Activities Months
1 2 3 4 5 6 7 8 9 1
0
1
1
1
2
1
3
1
4
1
5
1
6
1
7
1
8
1
9
2
0
2
1
2
2
2
3
2
4
1.7 Legal identity of RBN attained
1.7.1 Develop TOR & tender for consultancy to produce an EALA private members bill
to recognise a regional BMU Network as an EAC institution
X
1.7.2 Short-list bids, select consultant, make & sign contract X
1.7.3 Three RBN collaborate with legal expert to assist drafting the bill X
RESULT 2 Effective Communication and Promotion Systems
2.1 Promotion & Information materials
2.1.1 RBN electronic Newsletter produced X X X X X X X X
2.1.2 Brochures, information sheets X X X X
2.1.3 Press articles X X X X
2.1.4 Radio & TV X X X X
2.1.5 Electronic social networking e.g. Utube, Facebook etc. X X X X
2.2 RBN website development
2.2.1 Develop TOR and tender for website development X
2.2.2 Short-list bids, select consultant, make & sign contract X
2.2.3 Implement & RBN members collaborate with developer to design website X
2.3 International networking
2.3.1 Participation by RBN members at international technical meetings, global
conferences, exhibitions to represent the interests of BMU members
X X X X
2.3.2 Acquire membership of global fisheries NGOs & disseminate information on key
issues globally
X X X X X
RESULT 3 Effective fisheries governance
3.1 Advocacy campaigns
3.1.1 Compile regional fisheries management priorities of BMUs and propose
actions.
X X X X X X X X
3.1.2 Participate as a member of the LVFO regional technical advisory
committees to represent BMU views in co-management.
X X X X
3.1.3 Harmonize & coordinate & promote community-led, lake-wide actions to
reduce illegal fishing and fish trade through prioritised advocacy campaigns to
members e.g. eradication of beach seines & monofilament nets.
X X X X X X X X
3.2 Self-monitoring & regulation of BMU co-management performance
The Regional Beach Management Unit Network: ―Uniting BMUs Across Borders‖ Page 193
Activities Months
1 2 3 4 5 6 7 8 9 1
0
1
1
1
2
1
3
1
4
1
5
1
6
1
7
1
8
1
9
2
0
2
1
2
2
2
3
2
4
3.2.1 Design and agree an annual self-monitoring & evaluation and regulation
system for BMUs.
X X X
3.2.2 Compile, analyse & transmit results of annual BMU self-monitoring &
evaluation.
X X X X
RESULT 4 Business Operational Efficiencies Improved
4.1 Compile baseline fisheries SME data
4.1.1 Design self-recording system of fisheries business enterprises & labour
force.
X
4.1.2 Coordinate implementation of self-recording of numbers and types of
fisheries business enterprises & labour force.
X X X X
4.2 Fisheries SMEs analysis & advice
4.2.1 Design TOR & tender and advertise for project on provision of business
analyses & advice by BDS experts for individual fisheries SMEs.
X
4.2.2 Short-list bids, select consultant, make & sign contract X
4.2.3 Implement and monitor consultancy X X X X X X X X X X X X
The Regional Beach Management Unit Network: ―Uniting BMUs Across Borders‖ Page 194
5. PROJECT MANAGEMENT
The Regional BMU Network enters into partnership with the Lake Victoria Fisheries Organisation to
undertake this project. The partnership enables the inexperienced RBN to learn from the LVFO the
detailed procedures involved in project management. The LVFO will provide a supervisory and
guiding role to the RBN in implementation of this project. There is no conflict of interest in this
relationship. It is understood by both parties that there are advocacy issues expected to be raised by
the RBN that target governments and the LVFO, and that these will not be compromised by the
support provided to the RBN by the LVFO in this project.
The LVFO will be responsible for the project and signatory of the project contract. It has a similar
arrangement under a Letter of Understanding with the FAO in the running of a new aquaculture
organisation from the LVFO Secretariat. This is the Aquaculture Network of Africa (ANAF). The
Executive Secretary will have overall responsibility for financial management and accounting of the
RBN project. The RBN will be responsible for technical implementation of the project. The RBNS
Chief Executive Officer will report directly to the Chairperson of the RBN on all technical matters.
Financial reporting and accounting by the RBN will be done using the financial management systems
and structures of the LVFO. Technical project reporting will be the responsibility of the RBN
Chairperson to the LVFO Executive Secretary.
6. BUDGET
The detailed budget of the project is presented in Table 2. This provides estimated expenditure in
each activity line at quarterly intervals for the project period.
The Regional Beach Management Unit Network: ―Uniting BMUs Across Borders‖ Page 195
Table 2 Project Budget
Activity & Budget lines 2013 2014
Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Total
RESULT 1 Effective RBN Secretariat and Operations
1.1 RBN office established
1.1.1 Office location agreed, equipped, furnished & opened at LVFO
Secretariat, Uganda
4,000 4,000 500 500 9,000
1.1.2 Office operations 750 750 750 750 900 850 900 850 6,500
1.2 Office personnel
1.2.1 Job descriptions made, job adverts published 1,000 1,000
1.2.2 Candidates interviewed, 2 staff recruited: CEO & assistant 2,000 2,000
1.2.3 Operating Procedures developed for Secretariat
1.2.4 Staff salaries 9,000 9,000 9,000 9,250 9,250 9,250 9,250 64,000
1.2.5 Staff allowances 666 666 667 1250 1250 1250 1250 6,999
1.3 Improved Financial management skills of Secretariat & RBN
treasurers
1.3.1 Develop TOR and tender for training in financial management &
accounting for Secretariat staff & RBN treasurers
1,000 1,000
1.3.2 Short-list bids, select consultant, make & sign contract 1,000 1,000 2,000
1.3.3 Implement and monitor training consultancy in financial
management & accounting
10,000 10,000
1.4 Improved project planning, monitoring, reporting & project
design skills of Secretariat and RBN office holders.
1.4.1 Develop TOR and tender for training for Secretariat staff & RBN
office holders
2,000 2,000
1.4.2 Short-list bids, select consultant, make & sign contract 1,000 1,000 2,000
1.4.3 Implement and monitor training consultancy 8,000 8,000
1.5 RBN coordination
1.5.1 Hold quarterly progress & planning meetings to address key issues
e.g. Network registration & certificates, legal identity of Networks;
review Operating Procedures
1,800 1,800 1,800 1,800 1,800 1,800 1,800 1,800 14,400
1.5.2 Support NBNs, CBNs and DBNs in making budgeted plans 180 180 180 180 720
1.6 RBN self-financing
The Regional Beach Management Unit Network: ―Uniting BMUs Across Borders‖ Page 196
1.6.1 Develop self-financing procedures 1,800
1,800
1.6.2 Gain consensus of BMUs for procedures & rates of pay 0
1.6.3 Open & operate RBN bank account holding self-finance 50 50 100
1.7 Legal identity of RBN attained
1.7.1 Develop TOR & tender for consultancy to produce an EALA
private members bill to recognise a regional BMU Network as an EAC
institution
1,000 1,000
1.7.2 Short-list bids, select consultant, make & sign contract 1,000 1,000 2,000
1.7.3 Three RBN collaborate with legal expert to assist drafting the bill 10,000 10,000
RESULT 2 Effective Communication and Promotion Systems
2.1 Promotion & Information materials
2.1.1 RBN electronic Newsletter produced 50 50 50 50 50 50 50 50 400
2.1.2 Brochures, information sheets 500 500 500 500 2,000
2.1.3 Press articles 150 150 150 150 600
2.1.4 Radio & TV 150 150 150 150 600
2.1.5 Electronic social networking e.g. Utube, Facebook etc. 0
2.2 RBN website development
2.2.1 Develop TOR and tender for website development 1,000 1,000
2.2.2 Short-list bids, select consultant, make & sign contract 1,000 1,000 2,000
2.2.3 Implement & RBN members collaborate with developer to design
website plus training for Secretariat in website upkeep
10,000 10,000
2.3 International networking
2.3.1 Participation by RBN members at international technical meetings,
global conferences, exhibitions to represent the interests of BMU
members
250 250 400 400 1,300
2.3.2 Acquire membership of global fisheries NGOs & disseminate
information on key issues globally
250 150 100 500
RESULT 3: Effective Fisheries Governance
3.1 Advocacy strategy and campaigns
3.1.1 Compile regional fisheries management priorities of BMUs
and propose actions.
500 500 500 500 500 500 500 500 4,000
3.1.2 Participate as a member of the LVFO regional technical
advisory committees to represent BMU views in co-management.
200 200 200 200 800
The Regional Beach Management Unit Network: ―Uniting BMUs Across Borders‖ Page 197
3.1.3 Harmonize & coordinate actions to reduce illegal fishing and
fish trade through prioritised advocacy campaigns to members.
100 100 100 100 100 100 100 700
3.2 Self-monitoring & regulation of BMU co-management
performance
3.2.1 Design and agree an annual self-monitoring & evaluation
and regulation system for BMUs. 50 50 100
3.2.2 Compile, analyse & transmit results of annual BMU self-
monitoring & evaluation.
50 50 50 50 200
RESULT 4 Business Operational Efficiencies Improved
4.1 Compile baseline fisheries SME data
4.1.1 Design self-recording system of fisheries business
enterprises & labour force.
1,800 1,800
4.1.2 Coordinate implementation of self-recording of numbers and
types of fisheries business enterprises & labour force.
500 500 500 500 2,000
4.2 Fisheries SMEs analysis & advice
4.2.1 Design TOR & tender and advertise for project on provision
of business analyses & advice by BDS experts for individual
fisheries SMEs.
1,000 1,000
4.2.2 Short-list bids, select consultant, make & sign contract 1,000 1,000
4.2.3 Implement and monitor consultancy 28,000 28,000 28,000 28,000 28,000 140,000
Total 14,200 25,846 48,216 53,847 42,500 43,380 42,550 439,880 314,519
The Regional Beach Management Unit Network: ―Uniting BMUs Across Borders‖ Page 198
5. PROJECT REPORTING
The reporting outputs of the project comprise quarterly and annual technical reports and financial
reports, an end of project technical and financial report, ad hoc technical reports. The LVFO is
responsible for all project reporting. The RBN is responsible for technical reporting. It will submit
technical reports for approval of the LVFO.
6. MONITORING AND EVALUATION
The approach adopted for monitoring this project is based on a Logical Framework (logframe). The
logframe of this programme is presented in Table 3. The logframe provides a summary of the overall
programme design and a framework for project planning and monitoring.
The Regional Beach Management Unit Network: ―Uniting BMUs Across Borders‖ Page 199
Table 3 Project Logical Framework, January 2012 – December 2014
NARRATIVE OBJECTIVELY VERIFIABLE INDICATORS VERIFICATION SOURCES ASSUMPTIONS
GOAL Contribute to the fisheries
sector‘s role in sustainable
economic growth, poverty
reduction and improved
livelihoods in Kenya, Tanzania
and Uganda
PURPOSE
Delivery by the RBN of
economic, environmental and
governance benefits and services
to its members on Lake Victoria
by effective implementation of
its Strategic Plan, 2012–2015
P1. 70% of BMU District and County Network
Annual Action Plans developed and linked to RBN
by end of June each year.
P2. 10% increase in Nile perch biomass from start
to end of project using LVFO acoustic surveys.
P3. Profitability of 50% of selected small and
medium fisheries businesses increase by applying
consultancy advice for 6 months.
P1. RBN Annual BMU M&E Report;
Minutes of NBN & RBN meetings
P.2 LVFO Fisheries Acoustic Survey
reports
P43 BDS consultancy report;
Minutes of NBN & RBN meetings
1. International market influences
outside the region do not undermine
sustainable harvesting of fish
resources or the operation of
fisheries businesses.
2. Environmental influences do not
reduce or damage fish stocks.
3. Fishermen and fish traders are
willing to follow advice of RBN on
the need to eliminate illegal gears
and practices.
RESULT 1
Effective RBN Secretariat &
Operations
1.1 At least one RBN meeting held between July
& December 2014 financed by BMUs.
1.2 EALA private members bill passed giving the
RBN legal identity by end of project.
1.3 At least 1 RBN Secretariat staff recruited by
end of June 2013.
1.1 Minutes of RBN meetings
1.2 EALA Private members bill;
minutes of RBN meetings
1.3 Minutes of RBN meetings
1. BMUs willing to pay for BMU
Network meetings and activities.
RESULT 2 Effective Communication &
Promotion systems
2.1 At least three examples of RBN promotional
materials (brochures, information sheet; posters,
press article) produced each year.
2.1 RBN promotion material
1. BMU Network members
committed to sharing information.
The Regional Beach Management Unit Network: ―Uniting BMUs Across Borders‖ Page 200
2.2 RBN website developed by end of Dec 2013
and updated at least at quarterly intervals.
2.3 RBN presentation in at least 3 international
events per year.
2.4 RBN obtains membership of at least one
international fisheries NGO by end of June 2013.
2.5 RBN Newsletter produced twice per year.
2.2 RBN website
2.3 Minutes of RBN meetings
2.4 Minutes of RBN meetings
2.5 RBN Newsletter
RESULT 3
Effective Fisheries Governance
3.1 Numbers of illegal beach seines recorded in
each of 3 National Fisheries Frame Surveys in
2014 decrease from previous levels.
3.2 Numbers of illegal monofilament nets recorded
in each of 3 National Fisheries Frame Surveys in
2014 decrease from previous levels.
3.3 RBN participates as a member in LVFO
Fisheries Management & Scientific Committees
meetings held each year from 2012 to 2015.
3.4 The % of BMUs scoring satisfactory
performance levels increases each year.
3.5 At least one key enabling regional fisheries
policy or strategy influenced by RBN each year.
3.6 Harmonisation of at least one fisheries
legislation influenced by RBN each year.
3.7 Harmonisation of at least one guideline
influenced by RBN each year.
3.1 National & regional Frame
Survey Reports 2012
3.2 National & regional Frame
Survey Reports 2012
3.3 Minutes of RBN meetings
3.4 NBN & RBN Self-Monitoring
Inspection Reports
3.5 RBN Minutes of meetings
3.6 RBN Minutes of meetings
3.7 RBN Minutes of meetings
1. BMUs willing to comply with
fisheries regulations.
2. There is high level political will
and action to reduce illegal regional
& domestic fish trading & fishing.
3. LVFO holds regional technical
advisory meetings at its statutory
interval of twice per year.
4. National fisheries Frame Surveys
continue to be funded and
implemented every 2 years.
RESULT 4
Business operational efficiencies
increased
5.1 List of all fisheries SMEs on Lake Victoria
registered by BMUs by end of June 2013.
5.2 At least 50% of fisheries SMEs in each Partner
State receiving expert individual business analysis
5.1 BMU Registers; NBN & RBN
minutes of meetings
5.2 Consultancy reports; NBN &
RBN minutes of meetings
5.1 Fisheries business operators
motivated to adopt advice given for
improvement.
The Regional Beach Management Unit Network: ―Uniting BMUs Across Borders‖ Page 201
and advice report increased profits by end of
October 2014.
ACTIVITIES 1.1 RBN office established
1.2 Office personnel
1.3 Improved Financial
management skills of Secretariat
& RBN treasurers
1.4 Improved project planning,
monitoring, reporting & project
design skills of Secretariat and
RBN office holders.
1.5 RBN coordination
1.6 RBN self-financing
1.7 Legal identity of RBN
attained
2.1 Promotion & Information
materials
2.2 RBN website development
2.3 International networking
3.1 Advocacy strategy and
campaigns
3.2 Self-monitoring & regulation
of BMU co-management
performance
4.1 Compile baseline fisheries
SME data
4.2 Fisheries SMEs analysis &
advice
The Regional Beach Management Unit Network: ―Uniting BMUs Across Borders‖ Page 202
ANNEX 19 MINUTES OF RBN 2ND
REGULAR MEETING
The Regional Beach Management Unit Network: ―Uniting BMUs Across Borders‖ Page 203
LAKE VICTORIA REGIONAL BMU NETWORK
SECOND REGULAR MEMBERS MEETING
HELD AT WIFIP OFFICES- KISUMU KENYA ON THE 4TH
AUGUST 2012
ATTENDANCE LIST
(Dr James Scullion, ACP FISH II consultant present as observer)
Name Post in RBM ID No. Tel. No. Email Postal Address & Email
Address
Signatures
Niwagaba James Treasurer 0240 +256772 417093
+256 752 417093
Lambu Landing Site
Masaka, Uganda
Bakaaki Robert Member 0239 +256 782 622945
+256 752 946978
[email protected] Kigungu Landing Site,
Entebbe, Uganda
Tom Guda Chairman 11214762 +254 727 371074
+254 733 979942
P.O. Box 1-40301, Kendu-
Bay, Kenya
Bwire Benson Member 0245 +256 774 311044
[email protected] Buduma BMU,Sigulu;
Subcounty, Namayingo,
Uganda
Maziima Pius Secretary 07 +255 784 678347 [email protected]
P.O. Box 164, Magu,
Mwanza, Tanzania
Simon Rwekaza Vice
Chairman
08265138 +255 752 753522 [email protected]
P.O. Box 171, Muleba,
Tanzania
Pili Moro Member 120 +255 788 334048
+255 786 994331
P.O. Box 16861, Bukoba,
Tanzania
Caroline Juma Member 21240329 +254 720 792541 [email protected]
P.O. Box 102, Pap Onditi,
Kenya
Carolyn Oduor Member 13599778 +254 713 900861 [email protected]
P.O. Box 175, Bondo,
Kenya
The Regional Beach Management Unit Network: ―Uniting BMUs Across Borders‖ Page 204
AGENDA
1. Opening Prayers
2. Adoption of the agenda
3. Opening Remarks
4. Adoption of RBN Logo, Vision and Mission
5. Adoption of RBN Strategic plan
6. Adoption of 1st RBN proposal
7. Review and adoption of RBN membership with full details
8. Review the duration of tenure for RBN members
9. Deliberate on actions to be taken in regard to reduced Nile perch prices
10. Deliberate on Email addresses for all the RBN members
11. A.O.B
MIN 01/RBN/AUG 2012 – Opening Prayers
The opening prayers was delivered by Ms Pili MORO from the United Democratic Republic of
Tanzania.
MIN/02/RBN/AUG 2012 – Adoption of agenda
The agenda was put forth for adoption by the chairman. James Niwagaba from Republic of Uganda
proposed the inclusion of ‚‗Review of tenure for RBN Members― into the agenda. The final list was
then proposed for adoption by Carolyn Oduor from Kenya and seconded by Simon Rwekaza from
Tanzania.
MIN 03/RBN/AUG 2012 – Opening Remarks
The RBN chairman thanked all the members for honouring his invitation and turning up in time for
the training. He also thanked the members for staying in the meeting until the final day. He
observed that RBN is two years old but has has not been able to effectively serve its members since
they have not been able to meet regularly as stipulated in the operating procedures.
He said RBN is big and wide and as such urgently requires a competent secretariat to coordinate its
activities on a regular basis if service delivery to members is to be realized.
He also urged the members to improve information by use of phone calls and emails. In this regard,
he asked all the RBN members to open email addresses and ensure they visit them frequently. He
then wished the members fruitful deliberations.
MIN 04/RBN/ AUG 2012 - Adoption of RBN Logo, Vision and Mission
The secretary circulated the logo, RBN Vision and mission to the members for scrutiny. After
consultations among the members, Mr. Bwire Benson from Uganda proposed that the RBN logo,
Vision and Mission be adopted. He was seconded by Ms. Caroline Juma from Kenya and
unanimously endorsed by members.
MIN O5/RBN/AUG 2012 – Adoption of RBN Strategic Plan, July 2012 – June 2015
Having spent 3 days developing the RBN strategic plan, the Chairman sought the consent of
members to adopt the 3 year strategic plan. Mr. Robert Bakaaki of Uganda proposed the adoption of
the strategic plan as a guiding framework for the RBN for the next 3 years. He was seconded by Mr.
Pius Mazima from Tanzania.
The Regional Beach Management Unit Network: ―Uniting BMUs Across Borders‖ Page 205
MIN 06/RBN/AUG 2012 – Adoption of the First RBN proposal
The RBN during the training developed a project proposal that was meant to strengthen their
operations through establishing the secretariat and effective running of the office. The chairman
asked the members to consider adopting this proposal so as to give him the mandate to submit it to
respective partners for consideration. Members agreed with the Chairman and Mr. Simon Rwekaza
of Tanzania proposed the adoption of the proposal and immediate submission to LVFO and other
partners for consideration. He was seconded by Ms. Carolyn Oduor from Kenya.
MIN 07/RBN/AUG 2012 - Review and adoption of RBN membership with full details
The Chairman circulated the original list of the RBN to the members for review. The Chairman
informed the members that Mr. Elias Mugeta from Tanzania represented the Chairman of NBN
Tanzania in the first meeting and as such is not a member of the RBN. His place would be taken by
the Chairman NBN Tanzania Mr. Simon Rwekaza. The Chairman further explained that Kenya went
through elections in September 2011 that saw Ms. Irene Ojal and Mr.Dennis Kapila replaced by Ms.
Caroline Juma and Ms. Carollyn Oduor as Treasurer and Secretary respectively. The Chairman then
asked the members to adopt the RBN membership with their full contacts. Mr. Robert Bakaaki from
Uganda proposed for adoption the updated list with updated contacts of the RBN members. He was
seconded by Caroline Juma from Kenya.
MIN 08/RBN/AUG 2012 – Compile BMU Network membership details at all lower levels
Following on from deliberations of the RBN in making its Strategic Plan, the Chairman stressed the
urgency of compiling full membership details of all BMU Networks. It was agreed by members that
this would be completed in the 3 countries by 30 September 2012.
MIN 09/ RBN/AUG 2012 - Review the duration of tenure for RBN members
Mr. James Niwagaba Treasure of RBN from the Republic of Uganda proposed to amend the RBN
operating procedures Section 7.3 paragraph 2, first line to read: ― The duration of tenure as a RBN
member shall be Four years.“ This, Mr. James observe would give the RBN reasonable time to plan
and effectively implement the strategic plan with a view of efficient service delivery to its members.
This proposal was seconded by Ms. Carolyn Oduor from the republic of Kenya and agreed generally
by all the members. Members further asked the RBN chairman to lobby the other two partner states
Tanzania and Uganda to harmonize their guidelines with Kenya so as to have a uniform 4 year tenure
for all the lower networks.
MIN 10/RBN/AUG 2012 - Deliberate on reduced Nile perch prices
Members discussed the current drastic decline of Nile Perch prices and agreed to have the Chairman
write to the East African Industrial Fishing and Fish Processors Association (EAIFFPA) seeking to
be informed of the actual prices offered by the factories and the current market prices to enable them
effectively communicate with their members on the same. This, members observed, was urgent and
as such asked the Chairman to write immediately and brief them before they depart. The Chairman
agreed with the members and promised to act as advised.
MIN 11/RBN/AUG 2012 - Deliberate on Email addresses for all the RBN members
Given the importance of information sharing amongst the members, Mr. James Niwagaba from
Uganda proposed that all the RBN members open email addresses by the end of business today 4th
August 2012 and submit to the secretary for inclusion into the RBN list. Mr. James asked the
Chairman to agree to use his lap top facilitate this exercise. This position was seconded by Mr. Pius
Mazima from Tanzania and the RBN chairman agreed to support all the members without email
addresses acquire them before they leave for their respective work stations.
The Regional Beach Management Unit Network: ―Uniting BMUs Across Borders‖ Page 206
MIN 12/RBN/AUG 2012 - Deliberate on harmonisation of Kenya National BMU Network
functions with the RBN Operating Procedures
Following on from deliberations of the RBN in making its Strategic Plan, the Chairman urged RBN
members in Kenya to re-examine the contents of the National BMU Network Guidelines and seek a
meeting with Tim Odende (DoF) to improve coherence of the new listed functions with the existing
functions set out in the RBN Operating Procedures.
MIN 13/RBN/AUG 2012 - Deliberate on the need to review and influence the Fisheries Bills of
Kenya and Uganda in favour of empowering BMU Networks
Following on from deliberations of the RBN in making its Strategic Plan, the Chairman urged RBN
members in Kenya and Uganda to r-examine the respective National Fisheries Bills to ensure they
explicitly include and support BMUs and Networks.
MIN 14/RBN/AUG 2012 – Date and Venue of next RBN meeting
The next meeting of the RBN was agreed to be held in November 2012 just prior to the LVFO
Fisheries Management Committee and Scientific Committee meetings and leading up to the next
meeting of the LVFO Council of Ministers meeting reported informally by the LVFO Secretariat to
be held in December 2012. The Chairman informed the meeting that he would seek confirmation
from the LVFO Secretariat of dates of the LVFO meetings.
MIN 15/RBN/AUG 2012 – A.O.B
There being no any other business, the meeting ended with a word of prayers from Capt. Simon