Upload
university-of-regina
View
261
Download
0
Embed Size (px)
Citation preview
CONSTRUCTION OF GSM BASE STATION & TOWER FOR REGTel , CANADA
PROJECT MANAGERSULEMAN MUHAMMED BASHIRU
PROJECT TEAM MEMBERS OGUNYALE DAYO STEPHEN ABOABA AKINTUNDE ALMOTHANA DAWOUD
1
Overview2
The Need
Map Of Regina, SK, Canada Source: Google Earth
3
JUSTIFICATION
OPPORTUNITY• Number of
Students and Staff on Campus are in excess of 12,000
• About 7000 REGTel customers currently reside within the campus
PROBLEM • Experiencing
congestion at REG-03 & REGTel -08 between 10 am – 4 pm (peak utilisation)
• 18% Reduction in Number Customers since January, 2015
REVENUE• Upon Completion, the
project can generate $384,000 monthly ($40 x 9600 customers).
• Considering running cost and administrative expenses, the payback period is expected to be two (2) years
4
Project Objectives
● Provide competitive quality of services for existing and potential customers within the university and its environs.
● To decongest REGTel-03 site located west of University of Regina and REGTel-08 located north of University of Regina by 40% and 30% respectively.
5
Project Objectives Contd.
● Provide opportunity to justify REGTel sales drive. Sales can be increased by at least 19 percent within the university community.
● To serve as a hub site and back up site for REGTel-03 and REGTel-08.
6
Constraints
Bulk of the tools used will be rented
Storage of Materials
Scheduling the arrival of materials to maximise storage space
Training of Adhoc staff
7
Assumptions
Acquire licenses to build from Authorities
The project was planned & should be tracked at an activity level
Duration estimation was done based on availability of resources
It is the responsibility of the project manager to ensure that progress is made per established plans
8
Acceptance Criteria
All cables from tower top to the shelter will be channelled through cable tray
Earthing value of the site must not exceed 4.7 Ohms
Steel Reinforcement must be grade 50 deformed bars and shall be covered with concrete overlay of minimum thickness of 75mm
The Intensity of the Aviation warning light should not be below 10 Candela
9
Acceptance Criteria Contd.
Earth/Soil compaction ratio should be maintained during backfilling
The Shelter should have proper anti-static flooring and straps
All edges of slabs and tower base must be bevelled at 45 degrees
10
Project Organization Chart
Executive Director{James Peters}
Engineering Management & Administration
Lawyers
Human Resource
Officer
Supply & Procurement
Procurement Officers
Project Coordinator
Project Manager
11
EngineeringElectrical Engineer Civil Engineer
Laborers
CAD Technicians
Riggers
Rebar Workers
Carpenters
RF Engineer Microwave Engineer
Project Organization Chart Contd.
12
Project Scope
Scope
Planning
Design
Supply of Materials
Project Implementation & Control
Site Testing & Commissi
oning
Procurement
13
High Level Requirements Site Selection
Site Survey
Site Purchase
Soil Test
Civil Works Mobilisation
to site Excavation Reinforcement Formwork Casting Tower Rigging
Installation Electrical
Installation Microwave
Installation RF Installation Access Control Base Station
Commissioning
14
WBS SUMMARY1.0 Construction 1.1 Site survey & Designs
1.1.1 Site Survey & Selection 1.1.2 Soil Test 1.1.3 Design Drawings
1.2 Civil works1.2.1 Marking Out & Measurement1.2.2 Excavating1.2.3 Foundation for Tower1.2.4 Erecting Tower
1.3 Site preparations1.3.1 Supply of Temporary Water, Shelter, Power
2.0 Installation and Testing 2.1 Electrical Installation
2.1.1 Earthing of site2.1.2 Aviation Warning Light
15
WBS SUMMARY Contd. 2.2 RF/ Microwave Installation
2.2.1 RF Installation2.2.2 Microwave Instation
2.3 Acceptance Testing and Commissioning2.3.1 Base Station Commissioning & Testing2.3.2 Site on Air
3.0 Procurement/Supply of Materials 3.1 Procurement 3.2 Supply and Transportation of Materials4.0 Management and Administration 4.1 Project Management 4.2 Permits
4.2.1 Building Permit4.2.2 Frequency Reuse Permit4.2.3 Public Safety Permit
4.3 Adhoc Staff recruitment
16
Project Stakeholders
Project Sponsor, Executive Management
Project Team City of Regina Government Agencies University of Regina Authorities Canada Transport Civil Aviation
Authority
17
Risk Categories
Technical Nature of Soil
Human Resource Absenteeism & Sick calls
Workplace accident/hazards
Resignation
External Land litigation
Delay in Licensing, Permit Approvals
Unfavorable Weather condition.
18
Risk Categories
Cost Inflation Material Storage
Delay in Funding
Schedule Delay in Supply of Material
19
Risk Assessment Matrix
Risks Impact Degree of Impact
Probability of Occurrence
Response Plan and Risk Owner
Delay in Licensing, Permit Approval
• Delay the starting date.
• Delay the schedule.
High Medium Follow up on the licensing office to know the updates (PM & Legal)
Workplace incident and Hazards
Reduce skilled workers availability
High Medium • Acquire PPEs
• Train team on those PPEs (HSE)
Inflation Increase the project budget
High Low Purchase critical materials ASAP (Procure Finance)
Delay in material supply
Extend project schedule and budget
Medium Medium Always check inventory level(Supply Chain Officer)
20
Project Schedule Summary
Project duration is 217 days
Project Start date is 18th April 2016
Project Finish date is 14th February 2017
21
Milestones Schedule
Milestone 1Site Survey & Design • August 22, 2016Milestone 2
Permits & Licensing• September 14,
2016
Milestone 3Procurement &
Payment• October 12,
2016 Milestone 4Adhoc Staff & Recruitment
Milestone 5Supply &
Transportation of Materials
• October 21, 2016
November 3, 2016
22
Milestones Schedule Contd
Milestone 6Civil Works • January 2, 2017Milestone 7
Electrical Installation• January 13,
2017
Milestone 8RF & Microwave
Installation• January 13,
2017Milestone 9
Testing
Milestone 10Acceptance Testing &
Commissioning
January 18, 2017
January 20 2017
23
Project Summary –Cost Estimates
Work Package Labour Cost ($) Material Cost ($)
Site Survey & Design
79,160 32,105
Permit & Licensing 7,112 12,663.6Site Preparation 1,120 25,760Procurement and
Payment33,392 231,675
Adhoc Staff Recruitment
6,360 300
Supply/Transportation of
materials
15,600 13,850
Civil Work 39,760 20,960Electrical
Installation10,484 8,250
24
Project Summary – Cost Estimates Contd.
Work Package Labour Cost ($) Material Cost ($)
RF & Microwave Installation
3,144 58,400
Testing 2,032 3,500Site landscaping 2,820 -
Acceptance Testing & Commissioning Total
1,088 -
Project closing 81,680 -
Total 283,752 407,463.60
25
Project Cost Baseline
BAC = $691,215.60Cost Baseline: $793,215.60Available Budget : $950,000
Project Cost Baseline
$793,215.60 Contingency
Reserves$102,000
Labor Cost $283,752
Material Cost
$407,463.60
26
Cumulative Budgeted Cost
18-A
pr-16
29-A
pr-16
10-M
ay-1
6
21-M
ay-16
1-Jun
-16
12-Ju
n-16
23-Ju
n-16
4-Jul-
16
15-Ju
l-16
26-Ju
l-16
6-Aug
-16
17-A
ug-16
28-A
ug-16
8-Sep
-16
19-S
ep-16
30-S
ep-16
11-O
ct-16
22-O
ct-16
2-Nov
-16
13-N
ov-16
24-N
ov-16
5-Dec
-16
16-D
ec-16
27-D
ec-16
7-Jan
-170
100,000200,000300,000400,000500,000600,000700,000800,000
Cumulative Budget Cost ($)
Cumulative Budget Cost ($)
27
Change Management
Change Control Board, CCB, is chaired
by Project
Sponsor, James Peters
28
Change Management Contd.
Change request will be logged in the
change control
register
29
Change Management Contd.
If a change
is approved by the CCB, the project
manager will
update and re-
baseline project
documentation as necessar
y
30
Change Management Steps
• Any Stakeholder
• Project Manager
Evaluate the
Change
• Project Manager
• Requester• Project Team
31
Change Management Steps Contd.
• Project Manager
• CCB• Project Manager
Implement Change • Project Manager
32
Lessons Learnt
Withdrawal of Team Member
Adopt Progressive Elaboration
Delegation of Duties
Regular Engagement of Stakeholders
33
Thanks For Your Attention
35